Chief Justice Hecht. delivered the opinion of the Court.
In this case, the plaintiff and the main defendant both wanted an interest in a coalbed methane exploration prospect in Bulgaria. A jury found that the defendant obtained his interest by tortiously interfering with the owner's contract to convey an interest to the plaintiff. The defendant denies liability but argues that "the key question" is whether the evidence of the fair market value of the plaintiff's lost interest is too speculative to support the jury's award of damages.
That value depends in part on the profits the interest would have generated, which in turn depend, of course, on the associated risks. Texas law is quite clear that lost profits cannot be recovered as damages unless proven to a reasonable certainty, and the defendant argues that the rule applies equally to profits-based value determinations. We agree. But reasonable certainty must be measured in context, and when projected profits are considered in determining the value of a mineral prospect to be actually purchased or sold, the relevant metrics are supplied by the business market that values, invests in, and trades on such interests. Ultimately, the dispute here is not whether the rule applies but how; in this context and others, "the real difficulty lies not so much in the statement of the rules as it does in the application of the correct rule."
We affirm the judgment of the court of appeals
This case arises out of three relationships — between the owner of a prospect and each of two investors, and between the investors themselves.
In October 2000, the Republic of Bulgaria granted CBM Energy Limited a three-year concession to explore for coalbed methane in an unproven 450-square-kilometer field in the Dobroudja Coal Basin.
CBM could not fund the project itself and immediately inquired whether Carlton Energy Group, LLC, would be interested in partnering with it to help find investors, but Carlton, in the words of one of its principals, "didn't have time to mess with it." That indifference changed in 2003. Still not having raised the funding for the concession, CBM again contacted Carlton, and this time, Carlton expressed interest.
In April, Carlton agreed to pay CBM up to $8 million in three stages or "tranches" for up to a 48% interest in the project. The first tranche of $1.25 million was to cover the various costs for beginning the project and completing the first exploratory well, estimated at $750,000. If the well was successful, the second tranche, $1.5 million for the two additional wells, was due three months later. The $5.25 million balance of the $8 million was to be paid within a year after the second tranche and would go to further development of the prospect. For each timely paid tranche, Carlton would receive a proportionate share of a 48% interest in the project — 7.5%, then another 9%, and finally the remaining 31.5%.
But Carlton, too, needed investors to fund its share of the project, and by October, when the concession was set to expire, none had been found. CBM applied for a two-year extension, and the Bulgarian government agreed but required as one condition that CBM provide a $600,000 letter of credit to ensure completion of the first well.
To fund the first tranche, Carlton turned to Robert Assil and Kenneth Scholz, two friends of one of its principals, Thomas O'Dell. Assil provided $600,000 for the letter of credit, half of which was a loan to O'Dell, and Scholz sent CBM $300,000 cash. O'Dell, Assil, and Scholz agreed they would form a joint venture with Carlton to hold Carlton's 48% interest in the project, each owning one-fourth of the venture.
In tendering his $300,000, Scholz wrote CBM directly:
CBM responded by letter to Carlton that it would "not agree to such terms":
Carlton replied, asserting that Scholz's condition on his tender was no different from an oral amendment the parties had made to their agreement to delay funding the second tranche until 30 days after Carlton reviewed logs from the initial well:
CBM did not object to these assertions or refuse to accept Scholz's money.
Carlton and CBM continued to work toward funding the project. Carlton offered interests to numerous recognized investors, as it had before the extension. All declined.
One potential investor, D.W. Mitchell, asked an acquaintance, Dr. Henry Crichlow, to evaluate the Bulgarian project. Crichlow, a professional engineer and a former University of Oklahoma professor and department chair, is a leading expert on oil and gas reservoirs, including coalbed methane formations. From Raven Ridge Resources, a consulting firm and part owner of CBM, Crichlow obtained information on the project developed in part to help CBM market the investment opportunity. Crichlow reported in June that the project had "several highly desirable characteristics" that made it "a valuable international project." He listed, among others: "existing exploratory drilling in 142 boreholes", "known production technology for coal bed gas extraction", "extremely high demand for gas in Eastern Europe", "high price for wellhead gas at $5.25/MMBtu", "pipeline availability", and "available major oil company partners for additional development programs". Analyzing all available data, Crichlow valued the gas in the ground at $31.5 billion — a total volume of 35,000 bcf, 90% of which (31,500 bcf) was recoverable, worth $1/MMBtu (about $1/Mcf).
Mitchell gave Crichlow's report to Gene Phillips, a Dallas businessman who expressed interest in the project. Carlton
Carlton signed the agreement shortly after receiving it. Phillips denied ever receiving a copy of the fully executed agreement.
Two weeks later, Phillips and Crichlow met with O'Dell in Carlton's offices to discuss the Bulgarian project. After that meeting, Crichlow continued to study the prospect, becoming even more convinced of its value. In early October, Phillips and Crichlow spent a day at Raven Ridge's offices reviewing data. On October 11, Crichlow produced a second report referring to the project's "billion dollar profit potential". Crichlow urged Phillips to formally withdraw from his agreement with Carlton "as soon as possible" and take over Carlton's position with CBM, adding:
Within days, Phillips made known to CBM that he had no interest in dealing with Carlton and wanted to partner with CBM in Carlton's place. Belying his negotiations with CBM, Phillips wrote Carlton on December 3 that "we are unable to make a determination to participate in this venture" and therefore "decline to go forward with any proposed transaction." Carlton unsuspectingly responded: "Hopefully, it is not too late to reconsider, depending of course, on your other time and financial commitments."
Phillips moved quickly to supplant Carlton in the project. In mid-January 2005, he met with the Bulgarian Minister of Energy for assurance that the second two-year extension would be granted if CBM completed just one of the required wells. About the same time, Phillips renamed a dormant company he controlled and partly
By July, EurEnergy had demanded control of the project from CBM, and litigation between them ensued. They settled in May 2006, with EurEnergy buying CBM for $4.5 million.
The first exploratory well, the Vranino #1, was spudded in August 2005 and drilled to depth by October, barely in time to gain the second two-year extension of the concession. But final completion and testing were delayed by the litigation and other things. October 2005 and March 2006 estimates by Crichlow indicated that preliminary testing showed the well to be capable of commercial production, but EurEnergy was not able to convince the Bulgarian government that commercial production had been achieved. Drilling of the other two wells never commenced, and the concession terminated in October 2007. Crichlow's final report in November 2007, based on more extensive tests performed on the Vranino #1, showed recoverable gas reserves of 3.03 bcf per well, indicating a large reservoir, though only 65% of the recoverable volume projected in his June 2004 report. But EurEnergy and Phillips lost $13 million that they invested in the project.
In December 2006, Carlton sued Phillips, EurEnergy, and Phillips-related entities CabelTel International Corporation and Syntek West, Inc., alleging a breach of the August 2004 Carlton-Phillips Oil contract and tortious interference with the April 2004 CBM-Carlton contract. Carlton claimed damages for the loss of its 38% interest in the project. To prove the fair market value of that interest, Carlton relied on Crichlow's testimony and reports, and the testimony of Dr. Pete Huddleston, another professional engineer with extensive experience consulting in oil and gas exploration. From the two of them, Carlton offered evidence of three models for determining the fair market value of its 38% interest in the concession.
First, Huddleston testified that the value of that interest could be derived from the value of the gas in the ground, as forecast by Crichlow. As explained above, in June 2004, Crichlow estimated from the available data that the concession contained
Second, Huddleston estimated the value of the concession if wells were drilled only in the vicinity of the Vranino #1. Assuming that only eight additional wells were drilled around the Vranino #1 at a cost of $1 million per well, that a well could produce 2 bcf of gas, and that the success rate would be 80%, Huddleston determined the total net income from the wells, applied a discount factor, and estimated the value of the prospect to be about $33 million. Assuming 32 additional wells were drilled and a success rate of only 60% (less certain because they would be farther from the Vranino #1),
Third, Huddleston assumed that Phillips's agreement to pay Carlton $8.5 million for a 10% interest in the prospect showed that the value of the entire prospect was $82 million — $85 million less the $3 million cost of drilling the three required wells
Phillips and EurEnergy offered no evidence of the value of the prospect, though their counsel argued to the jury in summation that the "best evidence of fair market value" was the $900,000 — for 5.4% — that Carlton had already been repaid. Carlton's counsel in his summation did not mention either of Huddleston's first two methods and argued only that the fair market value of Carlton's lost interest should be based on its contract with Phillips — "you can write it down. It's $31,160,000. That is 38% of $82 million."
The jury returned a verdict for Carlton as follows:
The trial court refused to render judgment for the $66.5 million actual damages found by the jury and suggested a remittitur to $31.16 million, the figure Carlton's counsel argued in summation. Carlton accepted the remittitur in lieu of a retrial but reserved the right to seek the higher amount on appeal. The trial court determined that Carlton's tortious interference claim provided it the greater recovery and rendered judgment for the remitted actual damages and the exemplary damages found by the jury. The trial court refused to render judgment against Syntek West and CabelTel based on the jury's alter ego findings, but did render judgment against EurEnergy as Phillips's alter ego.
Carlton, Phillips, and EurEnergy appealed. The court of appeals reversed the trial court's judgment in part and rendered judgment on the verdict, awarding Carlton the $66.5 million actual damages found by the jury, as well as exemplary damages,
Phillips and EurEnergy petitioned this Court for review, as did CabelTel and Syntek West.
Phillips unquestionably induced CBM to terminate its agreement with Carlton, but for several reasons, he contends he is not liable for tortious interference. His arguments either confront adverse jury findings, which he must show are unsupported by the evidence, or are based on facts the jury refused to find, which he must show are conclusively established in the evidence.
Phillips argues that his negotiations with CBM occurred after Carlton had already failed to comply with its agreement with CBM, giving CBM the right to terminate. In effect, Phillips attacks the jury findings that Carlton complied with its agreement with CBM, and that they had agreed to the timing of the second tranche. Phillips argues that Carlton never funded the first tranche because Scholz's tender of $300,000 cash was improperly conditioned on review of the logs of the first well. Though CBM did complain of the condition at first, Carlton immediately responded that the condition was consistent with their oral agreement to delay funding of the second tranche until after the first well was drilled. Phillips argues that it would have been absurd for CBM to agree to delay funding of the second tranche until after uncertainties in the value of the prospect were dispelled by the drilling of a well — like conditioning payment for a lottery ticket on the results of the drawing. But CBM did not raise any objection at the time or deny Carlton's assertion that it "had fully complied" with their agreement. The jury could easily have believed that CBM thought it more important to have money in hand and continue to work with Carlton to find investors in the project. And the jury could also have believed that when CBM did eventually object, months later, it was due solely to Phillips's prodding. There was evidence to support the jury's findings that Carlton complied with the agreement's requirements for funding the first and second tranches.
Alternatively, Phillips argues that even if he tortiously interfered with the Carlton-CBM contract, Carlton suffered no injury. Carlton, the argument goes, had demonstrated no financial ability to perform the agreement without Phillips's investment, and he and Carlton never reached a binding agreement before he withdrew his offer. The jury found that Phillips and Carlton did have an agreement, which he breached, and that his attempt to terminate it was ineffectual. Phillips argues that there is no evidence to support these findings.
Phillips argues that notwithstanding O'Dell's testimony that he signed the counter-offer, the lack of evidence that a signed copy was ever delivered to Phillips precludes a finding that the parties had a binding agreement. But while signature and delivery are often evidence of the mutual assent required for a contract,
The evidence that Carlton and Phillips continued to gather and assess information regarding the project as joint venturers, Crichlow's understanding that Carlton and Phillips had an agreement, and Phillips's efforts to supplant Carlton, as Crichlow recommended, all strongly suggest that Carlton and Phillips had mutually assented to the August 23, 2004, written agreement. There is evidence to the contrary. Phillips points out that Carlton never set up the joint venture entity called for in the agreement, that the parties never had a formal closing, and that Carlton did not tender its working interest due before any payment from Phillips. Further, Phillips argues, there is evidence that O'Dell himself did not think the parties had a firm agreement. But this says no more than that the evidence was disputed; evidence tending to show the lack of an agreement was far from conclusive. The jury could have believed that any delays in performance — the formation of the joint venture, the closing, the tender of initial funding — were because the parties were otherwise occupied in gathering and assessing information, or due to Phillips's foot-dragging.
Phillips argues that Carlton waived any contractual rights it had by not asserting them immediately upon receiving Phillips's letter "declin[ing] to go forward with any proposed transaction." The jury refused to find waiver, and the evidence does not establish it. The jury could reasonably have believed that Carlton's response adopted a non-accusatory tone in hopes Phillips would follow through on his obligations.
We conclude that the evidence supports the jury's findings relating to tortious interference and fails to conclusively establish facts negating liability that the jury refused to find. Phillips's arguments that he is not liable for tortious interference fail.
We come to Phillips's principal argument: that Carlton's evidence of the fair market value of a 38% interest in the Bulgarian project under the CBM-Carlton agreement is too speculative to support an award of damages. We begin by stating the proper standard of review, then apply that standard to the evidence in this case.
A property's fair market value is what a willing buyer would pay a willing seller, neither acting under any compulsion.
With respect to the recovery of lost profits as consequential damages, the law is well-settled: lost profits can be recovered only when the amount is proved with reasonable certainty.
"It is impossible to announce with exact certainty any rule measuring the profits the loss for which recovery may be had."
But while whether to allow a recovery of lost profits is a fact-dependent inquiry, "[t]his does not mean ... that the `reasonable certainty' test lacks clear parameters."
While we have never spoken to whether this requirement of reasonable certainty of proof should apply when lost profits are not sought as damages themselves but are used to determine the market value of property for which recovery is sought, it clearly must. The purpose of the requirement is to prevent recovery based on speculation. We can think of no reason, and Carlton suggests none, why it would make sense to deny damages based on speculative evidence of lost profits but allow recovery of lost value based on the same evidence.
But when evidence of potential profits is used to prove the market value of an income-producing asset, the law should not require greater certainty in projecting those profits than the market itself would. The reasonable certainty requirement serves to align the law with reality by limiting a recovery of damages to what the claimant might have expected to realize in the real world had his rights not been violated; the requirement should not be used to deny a claimant damages equal to the value the market would have placed on lost property. The prospect of winning millions in the lottery is too small to support any award of potential proceeds for, say, theft of a ticket; still the ticket itself has some value — the price it commands on the market. The law is wisely skeptical of claims of lost profits from untested ventures or in unpredictable circumstances, which in reality are little more than wishful thinking.
Carlton argues that the jury's finding of $66.5 million is supported by Huddleston's testimony and Crichlow's reports regarding the value of the gas in the ground. Crichlow's June 2004 report projected that the concession contained 35,000 bcf, that 90% (31,500 bef) was recoverable, that the wellhead price would be more than $5/MMBtu (about $5/mcf), and that
Merely laying out the calculation, with its sweeping assumptions, demonstrates how completely conjectural it is. The evidence provides no basis for determining the reliability of Crichlow's volume predictions. Indeed, his own November 2007 report, based on the Vranino #1, indicated that total reserves were only a fraction of what he had projected in 2004. The evidence provides no basis for assessing the risks of completing the three wells necessary to hold the concession, much less the risks of actually getting the gas to market. Carlton's experts projected that the costs of bringing the gas to market would be four times the value of the gas in the ground, but the evidence does not explain why that projection was reasonable. There was no history of coalbed methane production in Bulgaria or the general area to support the risk analysis, a new transmission line would be necessary to reach an existing pipeline, and economies of scale would require not three, but hundreds, of wells in the area. In fact, the costs of completing the Vranino #1 greatly exceeded Phillips's expectations.
Most importantly, while Crichlow provided data used by Huddleston to project the value of the gas in the ground, Crichlow did not himself testify that the gas was actually worth $31.5 billion. Huddleston emphasized that he, too, was not testifying to the value of the gas in the ground, but was merely offering the jury "a range, a considerable range" of values to consider. Carlton did not argue to the jury that the value of its 38% interest was anywhere near Huddleston's projections. Nothing in the evidence supports the jury's $66.5 million finding.
Carlton argues alternatively that there is evidence that the value of its 38% interest in the concession was as much as $38 million, based on Huddleston's second damage model, projecting production around the Vranino #1. But this model rests on much of the same conjecture as the gas-in-the-ground model. Huddleston assumed drilling costs based on 2004 projections which were demonstrably unrealistic. He assumed that the drilling prerequisites to continuing the concession would be met, and that when gas was produced, there would be some way to get it to market. He assumed success rates and production volumes that he presumed to be reasonable, without supporting evidence beyond the parties' agreements. He factored in risks broadly, applied a discount factor, and suggested that the value of the concession was between $33 million and $100 million, again without attempting to arrive at a definite value. Huddleston's second model was no less speculative than the first.
Finally, Carlton argues that there is evidence to support Huddleston's determination of the value of Carlton's 38% interest in the prospect based on Phillips's agreement to pay Carlton $8.5 million for a 10% interest. Simply extrapolating, Huddleston calculated that the entire prospect
Phillips argues that his agreement with Carlton precludes use of the amount paid to indicate value. The agreement stated:
The provision curiously states that Phillips's payment was based on "a diligent review of the information available on the Project" but bore no relationship to "recognized criteria of evaluation". Whatever the meaning and intent of the provision, it cannot detract from the fact that a 38% interest in the prospect was sold by a willing seller to a willing buyer.
The trial court suggested a remittitur from the $66.5 million damages found by the jury to the $31.16 million based on
We come finally to CabelTel's and Syntek West's arguments that they are not liable as alter egos of EurEnergy. All three entities were controlled by Phillips. EurEnergy was owned 80% by Southmark Corporation, a publicly traded company Phillips controlled, and 20% by Syntek West (through two wholly owned subsidiaries), which Phillips owned.
The parties agree that because EurEnergy was incorporated in Nevada, the law of that state controls.
The alter ego doctrine was first recognized by the Nevada Supreme Court in 1957 in Frank McCleary Cattle Co. v. Sewell.
In 2001, the Nevada Legislature codified McCleary's requirements in Section 78.747 of the Nevada Revised Statutes, which states:
CabelTel and Syntek West contend that Section 78.747, by prescribing the requirements for alter ego liability of a shareholder, director, or officer for a corporate debt, preempts alter ego liability for any other person under Nevada common law. Therefore, they argue, because they were not shareholders in EurEnergy, they cannot be liable as its alter egos.
We do not read Section 78.747 to have such an effect. On its face, the statute does nothing more than confine shareholder, director, and officer liability for corporate debts to the common law alter ego doctrine established in McCleary,a case piercing the corporate veil between two corporations that were not shareholders, directors or officers of each other, and reiterated in Nevada Supreme Court decisions over three decades.
The Nevada Supreme Court has indicated that it also does not view the statute as preempting common law applications of alter ego doctrine. In 2008, the court applied the alter ego doctrine to conclude that one company was not liable for another's obligations.
Nevada common law does not limit alter ego liability to shareholders, officers, and directors. In McCleary, liability was imposed on a successor corporation. The Nevada Supreme Court has also held that alter ego liability may be imposed on a corporation for the obligations of an officer who was not a shareholder.
CabelTel was not a EurEnergy shareholder, and thus its alter ego liability for EurEnergy is determined by the common law, not Section 78.747. We need not decide whether Syntek West's alter ego liability is decided by the statute because of its indirect ownership of 20% of EurEnergy's stock. The common law and statutory requirements for alter ego liability are the same under Nevada law. The issue is whether extending EurEnergy's liability to CabelTel and Syntek West is consistent with those requirements.
But before we turn to that issue, we must consider CabelTel and Syntek West's argument that Section 78.747(3) applies to make the determination of alter ego liability a matter of law for the court rather than a matter of fact for the jury. Carlton responds that the mode of trial is a procedural rather than substantive matter and thus governed by the law of the forum.
To resolve this disagreement, we need not begin with abstract and notoriously difficult distinctions between substance and procedure.
Under Texas law, factual disputes related to the bases for alter ego liability, like factual disputes generally, are for the jury.
We come finally to the evidence.
CabelTel and Syntek West unquestionably influenced and governed EurEnergy. EurEnergy's general manager, Dave Morgan, was a CabelTel employee, and he reported to Syntek West's general manager, Neil Crouch, who was also EurEnergy's sole officer and director. Through Morgan and Crouch, EurEnergy was governed solely and completely by CabelTel and Syntek West. EurEnergy's interest was their interest. While Syntek West was only a 20% owner of EurEnergy, and CabelTel had no ownership interest in EurEnergy, Phillips owned a controlling interest in EurEnergy's other shareholder, Southmark, and in CabelTel. Phillips chose EurEnergy to contract with CBM, he chose Morgan to run EurEnergy, and he chose Crouch to be EurEnergy's sole officer and director and to oversee all EurEnergy's operations. In sum, EurEnergy, Syntek West, and CabelTel were all inseparable from Phillips, and thus, insofar as EurEnergy's operations were concerned, inseparable from each other.
This, we think, is the material evidence, and it was undisputed. There was other evidence about office-sharing, overlapping use of letterhead and email addresses, and other instances in which CabelTel and Syntek West could have been mistaken for EurEnergy. But that evidence aside, there is simply no disputing that EurEnergy's pursuit of the Bulgarian prospect was Phillips's interest that he chose to pursue using CabelTel and Syntek West.
We are mindful that under Nevada law, "[t]he corporate cloak is not lightly thrown aside."
Accordingly, we conclude that the evidence not only supports the jury's verdict but establishes CabelTel's and Syntek West's alter ego liability as a matter of law.
The judgment of the court of appeals is affirmed in part and reversed in part, and the case is remanded to that court for further proceedings consistent with this opinion.
Schonfeld v. Hilliard, 218 F.3d 164, 177 (2d Cir.2000). We are not persuaded that a recovery of lost market value based on projected profits is different from a recovery of lost profits because lost market value is measured at a single point in time. Capitalization of future lost profits is also based on a single moment in time. But we do think that in determining lost value, the requirement of reasonably certain proof should be applied — we would not say "leniently" — with the market's view in mind. See also 1 DAN B. DOBBS. LAW OF REMEDIES § 3.3(3) (2d ed. 1993) ("Using that market price instead of guessing about profits he might have earned is one very useful way of dealing with the uncertainty of the future."); 3 DOBBS § 12.2(3) (suggesting that "hybrid" damages — which are consequential insofar as they are not the loss of the very thing promised in a contract, but nonetheless a market loss rather than a profit loss — should be governed by the Reasonable Certainty Rule applied "leniently").