KEITH P. ELLISON, District Judge.
Pending before the Court are the parties' Cross Motions for Summary Judgment. After considering the relevant law and the arguments presented in briefing and at a hearing on the pending motions, the Court finds that Plaintiffs' Motion for Partial Summary Judgment, Docket No. 88, should be
Defendants' Motion, Docket No. 86, is
The Court further finds that certain bonds that were cancelled are now
This lawsuit involves a bitter dispute between Safety National Casualty Corporation (Safety National), a surety company authorized by the Department of Treasury to issue immigration delivery bonds, AAA Bonding Agency, Inc. (AAA), Safety National's authorized agent, and the Department of Homeland Security (DHS), regarding more than 1400 immigration bond breach determinations. An alien may use an immigration delivery bond to procure his release from the custody of DHS's Bureau of Immigration and Customs Enforcement (ICE) pending the outcome of deportation proceedings against him. As discussed below, an immigration delivery bond is a contract, akin to a bail bond, between Safety National—acting through its agent AAA—and DHS.
Plaintiffs contend that DHS has failed to follow the terms of the bond contract and the relevant regulations and statutes when determining that the immigration bonds at issue were breached. Specifically, Plaintiffs claim that DHS has demanded payment of bonds that were not actually breached or to which they have asserted valid defenses, and that DHS has refused to comply with valid requests for information made pursuant to the Freedom of Information Act (FOIA). Plaintiffs' Complaint sought declaratory and injunctive relief, including offsets and credits, for amounts due under the breached immigration bonds. Plaintiffs also pled a claim under the Freedom of Information Act, 5 U.S.C. § 552, demanding documents they had requested from DHS regarding the bonds at issue. Defendants counterclaimed against Plaintiffs for $9,255,750 in penal amounts plus interest, penalties and handling charges for outstanding breached bonds. Defendants also filed a motion to dismiss all counts except for those claims brought under the Administrative Procedures Act, 5 U.S.C. § 701 et seq. (APA).
Shortly after this lawsuit was filed, DHS informed Plaintiffs of its decision to unilaterally prohibit Safety National from writing any further immigration bonds. The Court subsequently enjoined DHS from refusing to accept bonds issued by Safety National, finding, inter alia, that Safety National had established a substantial likelihood of prevailing on the merits of its claim that DHS lacked inherent authority to refuse all bonds issued by a particular surety and on its due process claims.
The parties subsequently entered into an Agreed Framework for Alternative Dispute Resolution (ADR Agreement) that was approved by the Court on September 14, 2005. (Docket No. 27.) Pursuant to the ADR Agreement, which was prepared by Defendants, parties agreed to jointly review 50 bond breach determinations—25 selected by Plaintiffs, and 25 selected by Defendants. Defendants agreed to produce a copy of the full Alien file ("A-file") to Plaintiffs for each of these 50 bonds "exclusive of any privileged or otherwise protected documents." The parties also agreed to "review the 50 files produced and identify any and all potential defenses to payment found in the selected files" and
The Court also agreed to the Parties' joint request that it refrain from deciding Defendants' pending Motion to Dismiss until the conclusion of the ADR proceedings. The Motion to Dismiss was denied without prejudice to refiling "at the conclusion of those proceedings." (Doc. No. 37.)
Any hope that the ADR Agreement might substantially assist the parties in resolving their differences was dampened when parties later became engaged in a protracted battle over Defendants' refusal to release more than 2,000 pages of documents related to the 50 bonds based on claims of privilege.
The ADR process had some limited success. Defendants agreed to cancel six of the bond breach determinations,
As agreed, Parties have provided the JSOF and the Joint Appendix to the Court, subject to the parties'"right to object to the relevance or admissibility of
The Bureau of Immigration and Customs Enforcement (ICE) is responsible for the apprehension and detention of inadmissible and deportable aliens. 8 U.S.C. § 1103(a); 8 C.F.R. Part 236. An alien detained by ICE may be released from custody during removal proceedings under certain circumstances. 8 C.F.R. § 236.1(c). The Secretary of Homeland Security is authorized to "prescribe such forms of bond" as he deems necessary to carry out his authority. 8 U.S.C. § 1103(a)(3).
An alien may post a cash or surety bond for his release from custody on form I-352 (the Bond Contract). 8 C.F.R. § 103.6. Given the exceptionally poor draftsmanship reflected in this document, it is perhaps unsurprising that its requirements and conditions are subject to dispute. The delivery bond is issued to guarantee the appearance of an alien for deportation and at hearings in exclusion proceedings. According to the Bond Contract, "[a] delivery bond is breached when in response to a timely demand, the obligor either [sic] fails to produce the alien at the location specified in that demand." I-352, General Terms and Conditions. The Bond Contract further specifies that the bond obligation is terminated if the obligor produces or causes the alien to be produced as specified in the appearance notice "upon each and every written request until exclusion/deportation/removal proceedings" are terminated, if the alien is accepted by ICE for detention or deportation/removal, or if the bond is "otherwise cancelled." 352(G)(1). The General Terms and Conditions section of the I-352 lists a number of specific events that lead to automatic cancellation of a bond if they occur prior to the date of the breach. "[O]ther circumstances as provided by statute or regulation" are also listed as a reason for cancellation of a bond. Id. If the obligor "fails to surrender the alien in response to a timely demand while the bond remains in effect, the full amount of the bond . . . becomes due and payable." I-352(G)(1).
The relevant regulations clarify that a bond is breached "when there has been a substantial violation of the stipulated conditions." 8 C.F.R. § 103.6(e). "Substantial performance of all conditions imposed by the terms of a bond shall release the obligor from liability." 8 C.F.R. § 103.6(c)(3).
Notice of a demand to surrender an alien is sent to the bonding company on an I-340 "Notice to Deliver Alien" form, which sets forth the date, time and place the alien needs to appear. (See, e.g., Jt. Appx. 0003.) If the alien fails to appear, and the ICE Field Office Director finds a substantial violation of the terms of the bond has occurred, the bond is deemed breached. DHS must send notice of the breach and the reasons for the breach to the surety, which is usually done on a Form I-323. 8 C.F.R. § 103.6(e) ("The district director having custody of the file . . . shall determine whether the bond shall be declared breached or cancelled and shall notify the obligor on Form I-323 or Form I-391 of the decision, and, if declared breached, of the reasons therefor, and of the right to appeal. . . ."); I-352, General Terms and Conditions.
The surety has 30 days to file an administrative appeal or motion for reconsideration of the breach. I-352, General Terms and Conditions; 8 C.F.R. § 103.5, 8 C.F.R. § 103.3(a)(2)(i). The parties agree that the surety is not required by statute or
"A final determination that a bond has been breached creates a claim in favor of the United States . . . ." 8 C.F.R. § 103.6(e). "If payment is not made within 30 days of demand for payment, "interest, penalty, and handling charges" accrue from the date of the first demand, and will be payable as damages. . . ." I-352, General Terms and Conditions.
Before it can consider the parties' arguments about the contested bond breaches, the Court must clarify the basis for its jurisdiction and the applicable standard of review. As explained above, the Court is currently reviewing Defendants' decision to breach 41 bonds that were identified as part of the ADR Agreement in this case. The Court agrees with Defendants that it has jurisdiction to consider Plaintiffs' request for a declaratory judgment regarding Defendants' decision to breach these bonds under 28 U.S.C. § 1331 and pursuant to the Administrative Procedures Act, 5 U.S.C. § 704(APA) ("Agency action made reviewable by statute and final agency action for which there is no adequate remedy in a court are subject to judicial review."). Section 702 of the APA provides a clear waiver of sovereign immunity. 5 U.S.C. § 702; see also Stockman v. Federal Election Com'n, 138 F.3d 144. 151 n. 3 (5th Cir.1998).
The Court also has jurisdiction to consider Defendants' counterclaim under 28 U.S.C. § 1345. By bringing this counterclaim, Defendants have waived sovereign immunity as to certain claims by Plaintiffs, see Frederick v. United States, 386 F.2d 481, 488 (5th Cir.1967) (noting that when the sovereign sues, it waives immunity as to certain claims, but not to "claims of a different form or nature than that sought by it as plaintiff"), and Plaintiffs must be allowed to present defenses to the counterclaim. The Court believes that Defendant's counterclaim confers jurisdiction on the Court to entertain Plaintiffs' argument that certain bonds were settled. See discussion infra Part VI(G). The Court is otherwise convinced, however, that the proper defense to Defendants' claim to enforce the Agency's breach decision is that the Agency's breach decision is unenforceable because it was arbitrary and capricious. This is precisely the defense that Plaintiffs asserted in their Answer. (Doc. No. 28.)
A motion for summary judgment under Federal Rule of Civil Procedure 56 requires the Court to determine whether the moving party is entitled to judgment as a matter of law based on the evidence thus far presented. FED. R. CIV. P. 56(c). Summary judgment is proper "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment
The Court will review the disputed bond breach determinations under the arbitrary and capricious standard set forth in Section 706 of the APA. 5 U.S.C. § 706(2)(A). The Court will limit its review to the administrative record, but finds that Plaintiffs did not waive arguments they did not raise during their administrative appeals.
Plaintiffs maintain that the parties stipulated in the ADR Agreement that the Court would review the contested bond breach determinations de novo. Plaintiffs point out that, pursuant to the ADR Agreement, Defendants produced to the Court a copy of the full A-file and a joint statement of facts for each purported defense, not just the record before the Agency at the time of the bond breach determination. Defendants, on the other hand, argue that they did not intend to stipulate to de novo review in the ADR Agreement. Defendants further contend that any such stipulation would be a nullity because parties may not stipulate to a legal standard.
It is not clear whether an agency can stipulate to de novo review of its own decisions in an APA case. Defendants are correct that parties generally may not stipulate to the legal effect of admitted facts, see, e.g., Humble Oil & Refining Co. v. Sun Oil Co., 191 F.2d 705, 714 (5th Cir. 1951) (citing Swift & Co. v. Hocking Valley Ry. Co., 243 U.S. 281, 37 S.Ct. 287, 61 L.Ed. 722 (1917)). Courts have reached different conclusions, however, as to whether an agency may allow a court to review its own action de novo. See Asarco, Inc. v. EPA, 616 F.2d 1153, 1156 (9th Cir.1980) ("Courts have apparently split over the issue whether an agency can waive the requirement that a district court must not conduct a de novo review of agency adjudicatory action.") (comparing Cooperative Services, Inc. v. HUD, 562 F.2d 1292, 1295 (D.C.Cir.1977) with Independent Meat Packers Ass'n v. Butz, 526 F.2d 228 (8th Cir.1975)).
Even if an agency could stipulate to a less deferential standard of review, however, it is not clear that Defendants intended to do so in this case. The ADR Agreement does not explicitly state that the parties stipulated to de novo review. Defendants did agree to provide full copies of the A-files related to each of the 50 breach determinations to the Court, and those files admittedly contain information that was not part of the administrative
Transcripts of hearings leading up to the ADR Agreement do not provide further clarity. Defendants initially told the Court that they had proposed the ADR framework to "save both the plaintiff and the government enormous amounts of time and money" and to avoid "full blown discovery" in 1400 separate cases. (Sept. 6, 2005 Tr. at 22). Defendants also explained:
(Id. at 29-30.) Defendant also stated that most "if not all" of the information "that relates to whether or not the breach was proper . . . are all a part of the record of proceedings." (Id. at 34.) After the ADR Agreement was signed, Defendants (through different counsel) repeatedly emphasized that the Court would be reviewing only the administrative record when deciding the bonds that the parties could not agree on under the ADR framework. (Tr. Mar. 9, 2006 at 14 ("[The administrative record is] the basis for the administrative action. That's what the Court would be reviewing.").) Plaintiffs disagreed with Defendants' assessment at times, (see, e.g., Tr., May 1, 2006, at 16 ("I thought we had an admission from the government that wasn't all that was before the court from the past.")), but have not pointed the Court to any specific admission from Defendants in the transcripts.
The Court recognized at the hearing on the pending motions that it thought the purpose of the ADR Agreement was to give a full ventilation to all issues and all relevant documents. However, based on the record before it, the Court cannot find that Defendant clearly agreed to allow de novo review of the bond breach determinations.
Plaintiffs maintain that the Court should consider the bond breach determinations de novo because Defendants' fact-finding procedures were inadequate. In Citizens to Preserve Overton Park, Inc. v. Volpe, the Supreme Court held that de novo review "is authorized when the action is adjudicatory in nature and the agency factfinding procedures are inadequate." 401 U.S. 402, 415, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971); see also Camp v. Pitts, 411 U.S. 138, 141-42, 93 S.Ct. 1241, 36 L.Ed.2d 106 (1973) (noting that "de novo review is appropriate only where there are inadequate factfinding procedures in an adjudicatory proceeding, or where judicial proceedings are brought to enforce certain administrative actions."). After Overton Park, "de novo review of agency adjudications has virtually ceased to exist. In its stead, the arbitrary and capricious' standard of review of 5 U.S.C. § 706(2)(A) is now applied to review of agency determinations in the adjudicatory setting." Sierra Club v. Peterson, 185 F.3d 349, 368 n. 29 (5th Cir.1999). De novo review is only available "in special circumstances where [an] agency does not possess adequate factfinding procedure, not just that it failed to employ adequate procedures." 33 CHARLES ALAN WRIGHT AND CHARLES H. KOCH, JR., FEDERAL PRACTICE AND PROCEDURE § 8332. Furthermore, "[w]here a court finds that the agency factfinding is inadequate but that the agency has the procedural authority to correct the inadequacy then the court's proper function is to return the matter to the agency with instructions as to how to correct the inadequacy." Id. § 8372.
The Fifth Circuit has applied de novo review in at least one case based on inadequate factfinding procedures. See Porter v. Califano, 592 F.2d 770, 782 (5th Cir. 1979) ("[W]e find the process inadequate in the instant case because the biased or otherwise inadequate initial fact-finding process was not cured by a subsequent impartial and full review in the agency."). In Porter, two officials accused of corruption were themselves involved in the fact-finding process. 592 F.2d at 782 ("The chief inadequacy in the agency fact-finding procedures used in this case was the pervasive role played by . . . the officials Porter explicitly accused of corruption."). In addition, the investigation surrounding Porter's appeal "did not entail an adequate inquiry into the central issues in the case," and "to the extent questions about these matters were asked, they were asked, without benefit of cross-examination, only of persons accused of wrong-doing by Porter." Id. In addition, Porter was "denied an opportunity to confront her accusers even in the most rudimentary sense." Id.
Plaintiffs argue that DHS' factfinding procedures are similarly inadequate. Plaintiffs claim that DHS wrongfully withheld relevant documents that Plaintiffs sought through FOIA, thus depriving Plaintiffs of any meaningful opportunity to submit comments, provide information to the record, or present oral argument. Plaintiffs also note that Defendants have conceded that they wrongly declared nine of the 50 bonds breached, and argue that this provides further evidence of the agency's inadequate procedures. Defendants counter that no relevant documents were actually omitted from the agency's proceedings and convincingly argue that Plaintiffs could have obtained much of the
The Court will apply arbitrary and capricious review to the agency's bond breach determinations. 5 U.S.C. § 706(2)(A) (a court "shall hold unlawful and set aside agency action, findings, and conclusions found to be arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.") "Although Overton Park truncated the use of de novo review, it vastly expanded the range of arbitrary and capricious review under § 706(2)(A)." Sierra Club v. Peterson, 185 F.3d 349, 368 (5th Cir.1999). "[W]hile the arbitrary and capricious standard of review is highly deferential, it is by no means a rubber stamp." Pension Benefit Guar. Corp. v. Wilson N. Jones Mem'l Hosp., 374 F.3d 362, 366 (5th Cir.2004). Agency action is entitled to a presumption of regularity, but "that presumption is not to shield [its] action from a thorough, probing, in-depth review." Overton Park, 401 U.S. at 402, 91 S.Ct. 814. The Supreme Court further explained in Overton Park:
401 U.S. at 416, 91 S.Ct. 814. The Court must therefore uphold the agency's decision if it "examine[d] the relevant data and articulate[d] a satisfactory explanation for its actions including a `rational connection between the facts found and the choice made'" Motor Vehicle Mfrs. Ass'n of the United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168, 83 S.Ct. 239, 9 L.Ed.2d 207 (1962)). The Court should not, however, "weigh the evidence in the record pro and con." Harris v. United States, 19 F.3d 1090, 1096 (5th Cir.1994).
Arbitrary and capricious review is usually limited to review of the record that was before the agency at the time its decision was made. See Overton Park, 401 U.S. at 420, 91 S.Ct. 814; Camp, 411 U.S. at 142, 93 S.Ct. 1241 ("The focal point for judicial review should be the administrative record already in existence, not some new record made initially in the reviewing court."); State of La., ex rel. Guste v. Verity, 853 F.2d 322, 327 n. 8 (5th Cir. 1988) ("Nor are the courts permitted to
Although Plaintiffs have raised legitimate concerns about some of DHS' practices, this is not a case involving an entirely absent record or a record that is so incomplete that it is not susceptible to judicial review. The Court will generally limit its review to the administrative record. If, in the case of any particular bond breach determination, the Court finds that the agency developed an inadequate record or that there are serious questions as to whether the agency considered all relevant factors in reaching their determinations, the Court will remand those bond breach determinations to the Agency for further review.
Defendants argue that the Court should not consider any defenses that Plaintiffs did not raise before the agency on appeal.
The bond breach appeal process does not appear to be the kind of adversarial proceeding contemplated in Sims. It is not a formal adjudication between two parties. In fact, though the proceedings are far from identical, there are some similarities between the bond breach appeals process and the Social Security appeals process. As the Fifth Circuit recognized in Delta
Issue exhaustion may also be required by regulation. In Sims, the Court noted that issue exhaustion was required by a regulation that obliged a party to "lis[t] the specific issues to be considered on appeal." 530 U.S. at 108, 120 S.Ct. 2080 (citing 20 CFR § 802.211(a) (1999)). By contrast, the regulation governing bond appeals simply states that an appeal may be summarily dismissed if the party states no reason for the appeal. 8 C.F.R. § 103.3(a)(1)(v). ("An officer . . . shall summarily dismiss any appeal when the party concerned fails to identify specifically any erroneous conclusion of law or statement of fact for the appeal." (emphasis added)). The regulations governing motions to reopen and motions to reconsider are more specific, however. See 8 C.F.R. § 103.5(a)(2) ("A motion to reopen must state the new facts to be provided in the reopened proceeding and be supported by affidavits or other documentary evidence."); 8 C.F.R. § 103.5(a)(3) ("A motion to reconsider must state the reasons for reconsideration and be supported by any pertinent precedent decisions to establish that the decision was based on an incorrect application of law or Service policy.").
To the extent that Plaintiffs are appealing the Agency's decision on a Motion for Reconsideration or a Motion to Reopen, issue exhaustion does appear to be required by regulation. However, it
Before the Court can examine the merits of each purported defense, it must first consider the relevance of a 1995 and 1997 Settlement Agreement in the case Amwest Surety Insurance Co., et al. v. Reno, et al., C.D. Cal., No. 93-3256 JSL(SHx) and an agency memorandum explaining the application of the settlement provisions to other sureties.
On June 22, 1995, INS entered into a Settlement Agreement with Amwest Surety Insurance Company, Far West Surety Insurance Company, and Gonzales and Gonzales Bonds and Insurance Agency (Amwest I Settlement). (Jt. Appx. 672.) In the underlying lawsuit, Amwest Surety Insurance Co., et al. v. Reno, et al., No. 93-3256 JSL(SHx) (C.D.Cal.), Plaintiffs sought a declaration that INS's "interpretation of its Bond Contract (Form I-352) was contrary to case law, statute, and INS policy." (Jt. Appx. 673.) While continuing to deny those claims, the Agency agreed in the settlement agreement to distribute several policy statements "to all regional and district offices . . . with instructions that the policies stated shall be implemented immediately.'" (Jt. Appx. 674-75 para. 2.) Although the nine policy statements attached to the settlement appear to generally clarify the agency's position on certain statutory and regulatory provisions and agency policies governing immigration bonds, the agreement, by its terms, only applied to the actual parties to the settlement. (Jt. Appx. 675 ("The attached policy statements are binding on the parties in their contractual relationship formed through the execution of any immigration bond contract. . . .").) The Agency also agreed to certain practices and policies in the text of the Settlement Agreement itself.
On September 10, 1997, the parties to the Amwest I Settlement entered into a second settlement agreement (Amwest II
At some point thereafter, a substantially similar draft memorandum ("Amwest Memorandum") was authored by the Agency.
Like the Field Memorandum, the Amwest Memorandum explains that in the Amwest I Settlement, the Agency had "agreed to implement specified modifications to its immigration bond program" and again states: "By its terms the Settlement Agreement applies only to immigration bonds underwritten by Amwest and Far West. . . . As a matter of policy and fairness, however, INS has decided to apply its terms to such contracts with all other companies who underwrite immigration
There is great dispute over what became of the Amwest Memorandum. This case appears to be unique in that the Agency maintains that it never actually adopted the policies or interpretations in the Amwest Memorandum in the first place, not just that it should not be bound by those policies or interpretations.
Plaintiffs claim that the Amwest Memorandum was "widely circulated in the bond industry." (Mendoza Aff. ¶ 5.) Plaintiffs have not clarified who circulated the memo, and Defendants claim that it was circulated by members of the bond industry itself. Plaintiffs do not argue that the Agency consistently applied the policies set forth in the Amwest I Settlement or Amwest Memorandum, and instead complain that the Agency has regularly failed to do so. Plaintiffs do, however, provide evidence indicating that at least some DHS employees, including, but not limited to Field Office personnel, acted on the belief that the provisions of the Amwest Settlement had been extended to all sureties and/or that some parts of the Amwest Settlement were enforceable as policy. The Court will briefly summarize that evidence.
Secondly, when responding to Plaintiffs' FOIA requests, the agency has on some occasions stated that the request "will be processed pursuant to the settlement in Amwest v. Reno ... rather than the Freedom of Information Act."
Third, the Administrative Appeals Office has frequently cited one provision of the Settlement Agreement. See, e.g. In re Obligor, 2005 WL 2271462 (INS May 3, 2005) ("The present record contains evidence that a properly completed questionnaire.. . was forwarded to the obligor . . . pursuant to the Amwest/Reno Settlement Agreement."); see also Jt. Appx. 0355; Jt. Appx. 0580; Jt. Appx. 0609.
Fourth, the I-352 Bond Contract itself seems to recognize that the Agency considered itself bound to take certain actions pursuant to the Amwest Settlement. I-352, General Terms and Conditions ("Paragraph seven of the settlement in AMWEST SURETY v. RENO . . . requires that INS send a copy of any new or amended Notice to Appear or amended order to Show Cause to the obligor."). Interestingly, most of the provisions set forth in the text of the Amwest I Settlement also appear to be reflected in the language of the current I-352 Bond Contract, even though these provisions do not reference the settlement explicitly. For example, the I-352 includes: a provision
Finally, in a notice of proposed rulemaking published in the Federal Register, the Agency stated on May 9, 2002 that "While the [Amwest I] settlement agreement applied only to bonds underwritten by the plaintiffs, the Service as a matter of policy and fairness decided to apply the terms of the settlement agreement to all other companies underwriting immigration bonds." Requiring Aliens Removed from the United States to Surrender to the Immigration and Naturalization Service for Removal, 67 Fed.Reg. 31157, 31160 (May 9, 2002); see also 44 U.S.C. § 1507. The Agency went on to state in the Notice that it had considered the effects of that policy with respect to the proposed rule and had determined that it "should be modified for all bonds posted after the effective date of this rule." Id.
Plaintiffs have provided some evidence that the Agency did, in fact, have a policy of extending provisions of the Amwest I Settlement to other sureties. Based on the evidence in the summary judgment record, however, the Court cannot conclude that the Agency actually adopted the specific draft Amwest Memorandum included in the summary judgment record as a general agency policy or interpretation. Plaintiffs have not provided evidence that directly contradicts the Agency's sworn statement that this exact document was never formally circulated to Field Offices or the implication that the Agency never intended the document to be distributed. As such, the Court cannot conclude that this draft, undated memorandum constituted an agency statement of policy or interpretive rule. See also Wilderness Society v. Norton, 434 F.3d 584, 596 (D.C.Cir.2006) (noting that the APA requires general statements of policy to be published).
Even if the Agency in some other manner adopted an informal policy to apply the provisions of the Amwest Settlement to all sureties,
In the case of two defenses, however— Alien Granted Voluntary Departure and Failure to Provide a Questionnaire—the Bond Contract is silent.
The heart of the dispute before the Court revolves around Defendants' unwillingness to acknowledge certain defenses that Plaintiffs claim should either cancel a bond or excuse a bond breach. The Court will examine the parties' arguments about each purported defense.
The General Terms and Conditions of the I-352 Bond Contract state that "INS shall notify the obligor of a demand to produce the alien, the breach or cancellation of a bond, and any demand for payment of a bond." (I-352.) INS provides notice of a demand to produce the alien by sending an I-340 "Notice to Deliver Alien" form setting forth the time, date, and place to deliver the alien. The relevant regulations do not explicitly mention the Bond Contract provisions requiring notice of a demand to produce the alien, stating only that "A bond is breached when there has been a substantial violation of the stipulated conditions." See 8 C.F.R. 103.6(e). Surely, however, the Agency may not ignore the relevant provisions of the Bond Contract when determining whether a bond has been breached. The Bond Contract clearly states that "[a] delivery bond is breached when in response to a timely demand, the obligor either [sic] fails to produce the alien at the location specified in that demand." I-352, General Terms and Conditions. The I-352 reiterates in section G(1) that the bond becomes due and payable "if the obligor fails to surrender the alien in response to a timely demand while the bond remains in effect." (Id.) The I-352 form also allows both the obligor and agent or co-obligor to provide an address and includes and to check one of the following boxes: "Address to use for notice purposes: [] Obligor [] Agent [] Both."
The express language of the Bond Contract makes clear that a bond is breached only if Defendants make a timely demand to produce the alien. A timely demand to produce the alien is, therefore, a condition precedent to Plaintiffs' performance. Defendants argue that they can fulfill this requirement by sending notice to the obligor alone, even if the agent (in this case, AAA) provides an address and checks the box indicating that the address for both the obligor and the agent are to be used for notice purposes.
The I-352 is a contract, and the instructions on the form have been "incorporated into the section of the regulations requiring its submission."
The terms of the I-352 Bond Contract are somewhat contradictory. Although the Terms and Conditions state that INS must send notice of a breach to "the obligor," the form also includes a box that, if checked, directs the agency to use the address of both the obligor and the agent "for notice purposes." If the court were to read the contract, drafted by the agency, to require notice only to the obligor, it would render the "address to be used for notice purposes" language entirely superfluous.
Based on general principles of contract interpretation, the Court finds that the Bond Contract requires the Agency to provide notice of a demand for delivery to both the obligor and the agent if an address is provided for both on the bond form and if the I-352 form indicates that both addresses should be used for notice purposes by a checked box.
Defendants seem to argue that even where notice is a condition precedent to
The Agency argues that even if the Bond Contract requires notice to both parties, a bond breach cannot be excused unless Plaintiffs demonstrate that the failure to notify both parties prevented them from substantially complying with the terms of the bond. Specifically, Defendants maintain that the bond breaches should stand unless Plaintiffs can show that, but for the Agency's failure to notify both parties, Plaintiffs would have produced the alien. This argument is unavailing given the Court's finding that notice to both parties is a condition precedent to Plaintiffs' performance. Defendants reliance on International Fidelity Ins. Co. v. Crosland, 516 F.Supp. 1249 (S.D.N.Y.1981), is misplaced because the court in Crosland was considering the Agency's interpretation of a regulation that did not require advance notice to the surety.
Parties also quarrel over who had the burden to prove that notice was mailed. The briefing on this issue does not appear to fully take into account the nature of the Agency's process for breaching a bond and
In sum, Defendants are required to send notice of a demand to deliver the alien to both the obligor and the co-obligor if the I-352 Bond Contract indicates that notice should be addressed to both.
Plaintiffs also contend that DHS' failure to provide notice of an alleged breach within 180 days renders the bond breach ineffective. The Agency is required to "send notice of a breach of the bond to the obligor on Form I-323, Notice-Immigration Bond Breached, at the address of record." I-352 General Terms and Conditions; see also 8 C.F.R. § 103.6 (a district director "shall notify the obligor on Form I-323" of a declaration of a bond breach). Any notice of a breach "sent more than 180 days after the date of the breach shall be unenforceable." The bond contract clarifies, however, that failure to send the I-323 form within 180 days:
(I-352, General Terms and Conditions.)
Defendants do not contest that notice sent more than 180 days after the date of the breach is unenforceable, but they do argue that the bond contract does not require them to send such notice to both Safety National and AAA. Defendants' arguments that Plaintiffs cannot use failure to give notice as a defense against recovery without showing prejudice or damage are somewhat more persuasive in the context of notice of a bond breach, which is more similar to a notice of default, than in the context of notice of a demand to deliver the alien. See, e.g., Conesco Industries, Ltd., 627 F.2d 312, 317, n. 6; New Amsterdam Cas. Co., 16 F.2d at 851-52. Nonetheless, the language of the Bond Contract clearly provides that notice of a breach sent more than 180 days after the breach is unenforceable and requires that notice to be sent to the "address of record." Where a surety has indicated that notice is to be sent to "both" the obligor and the co-obligor, the checked box clarifies the meaning of notice and the term "address of record." Thus, the Agency can only comply with its clearly expressed obligation to provide notice within 180 days by sending that notice to both the obligor and the co-obligor if the "both" box is checked.
Plaintiffs allege that failure to deliver an alien is excused where DHS did not demand delivery of the alien within 90 days of a final removal order pursuant to 8 U.S.C. § 1231. According to Plaintiffs, because this statute and related regulations are implied into the terms of the bond contract, and because the I-352 General Terms and Conditions contemplate that the bond will be canceled based on "other circumstances as provided by statute and regulation," if the Agency does not comply with § 1231, the bond is cancelled. Defendants argue that § 1231, at most, only limits the Agency's detention authority and contend that the statute and relevant regulations contemplate supervision of an alien by bond beyond the 90-day period.
Section 1231 allows DHS to detain an alien for up to 90 days pending deportation after an order of removal becomes administratively final. 8 U.S.C. § 1231(a)(1)(A)
Plaintiffs argue that, if the Agency fails to remove an alien within the 90-day removal period, the immigration bond automatically cancels because the Agency no longer has the power to detain the alien. Plaintiffs' argument fails for several reasons. First, the Supreme Court itself has recognized that DHS has presumptive detention authority for at least six months. Second, the Agency may have detention authority beyond the 90-day removal period if the alien acts to prevent his own removal, § 1231(a)(1)(C), or if the alien has been "determined by the Attorney General to be a risk to the community or unlikely to comply with the order of removal, may be detained beyond the removal period," § 1231(a)(6). Plaintiffs maintain that Defendants must send a Notice of Failure to Comply before extending the removal period, but the relevant regulations indicate that the Agency must do so only where an alien is in detention. See 8 C.F.R. § 241.4(g)(1)(ii), (g)(5). Finally, the statute has been interpreted to allow the Agency to condition a post-removal-order immigrant's release from detention upon the posting of a bond. See Shokeh v. Thompson, 369 F.3d 865, 870-71 (5th Cir. 2004), vacated as moot, 375 F.3d 351 (5th Cir.2004) ("Although the statute authorizing terms of supervision, 8 U.S.C. § 1231(a)(3) and (6), does not expressly authorize a bond, it does not exclude such a condition."); see also Doan v. INS, 311 F.3d 1160, 1161 (9th Cir.2002). This finding distinguishes the Eighth Circuit's interpretation of an earlier version of the statute, 8 U.S.C. § 156, and that Circuit's conclusion that the Agency could not require an alien to post bond after the Agency's detention authority expired. Shrode v. Rowoldt, 213 F.2d 810, 812-14 (8th Cir. 1954) ("When a party is required to post bail his sureties in effect become his jailers and the power to require bail connotes the power to imprison in the absence of such bail."). Thus, the Agency may have detention authority beyond the 90-day removal period, and even if it does not, it may still be able to supervise or demand delivery of an alien after that period has expired. Section 1231 does not, therefore, require a bond to be automatically cancelled after the 90-day removal period has expired.
The Bond Contract explains that "the [e]xecution of a voluntary departure bond for an alien cancels any existing delivery bond posted on behalf of the same alien." I-352, General Terms and Conditions. Thus, a bond is cancelled if an alien is granted voluntary departure with the requirement to post a voluntary departure bond and that bond is executed. The Bond Contract makes no mention of what happens when an alien is granted voluntary departure in a removal proceeding without the requirement of a voluntary departure bond. Plaintiffs contend that under such circumstances, the bond is cancelled.
An alien may be granted voluntary departure at two different moments in the removal process. First, voluntary departure may be granted "in lieu of being subject to" removal proceedings or "prior to the completion of such proceedings." 8 U.S.C. § 1229c(a)(1). In such a case, the immigration judge "may require an alien.. . to post a voluntary departure bond, to be surrendered upon proof that the alien has departed the United States within the time specified." 8 U.S.C. § 1229c(a)(3) (emphasis added). Second, an alien may be allowed to voluntarily depart the United States at the conclusion of removal proceedings. 8 U.S.C. § 1229c(a)(3). In the second case, the alien "shall be required to post a voluntary departure bond, in an amount necessary to ensure that the alien will depart, to be surrendered upon proof that the alien has departed the United States within the time specified." 8 U.S.C. § 1229c(b)(3) (emphasis added). In either situation, the immigration judge must also enter an alternate order of removal. 8 C.F.R. § 241.5(d). Unless an extension of time to depart is granted or voluntary departure is reinstated, 8 C.F.R. § 241.5(f),(h), an alien who fails to voluntarily depart in the time granted becomes automatically removable. 8 C.F.R. § 241.5(d), 8 C.F.R. § 1240.26(b). It seems that the agency could, at that point, again demand delivery of the alien and possibly detain the alien.
The I-352 sets forth a specific list of events that result in cancellation of the bond, including issuance of a voluntary departure bond, and that list does not include a grant of voluntary departure, standing alone. The reference to the bond being "otherwise cancelled" in section G(1) would seem most likely to refer back to the list of reasons for cancellation set forth in the Terms and Conditions of the bond.
The Court has already explained why Plaintiffs may not rely on the guidance set forth in the Amwest Memorandum.
The Court therefore agrees that Defendants could reasonably determine that a delivery bond did not cancel when an alien was granted voluntary departure without the issuance of a new voluntary departure bond.
A delivery bond is cancelled upon "valid proof of the bonded alien's voluntary departure" I-352, General Terms and Conditions. The Board of Immigration Appeals persuasively clarified in Matter of Peerless Ins. Co.:
15 I. & N. Dec. 133, 134 (B.I.A.1974). Thus, if the administrative record reflects valid proof of the alien's departure, the agency's declaration that a bond was breached would be arbitrary and capricious. If, however, the record does not contain valid proof that the alien departed prior to the date that the alien failed to appear, the Agency is entitled to find the bond breached.
Plaintiffs maintain that compliance with the Freedom of Information Act is a material term of the bond contract and that DHS's failure to comply with FOIA therefore excuses Plaintiffs' performance. An agency's relevant regulations are an implied part of a bond contract, see, e.g., Bodek v. Dept. of Treasury, 532 F.2d 277, 279 n. 7 (2d Cir.1976); Wolak v. United States, 366 F.Supp. 1106, 1112 (D.Conn. 1973), and "[t]he laws existing at the time a contract is made becomes a part of the contract and governs the transaction." Texas Nat'l Bank v. Sandia Mortgage Corp., 872 F.2d 692, 698 (5th Cir.1989). Plaintiffs point to no authority, however, compelling the conclusion that failure to comply with an unrelated statute can be considered a material breach of a government contract and thus excuse another party's failure to perform on that contract.
The Court agrees that Defendants are required by law to comply with FOIA and Plaintiffs may have an independent cause of action if Defendants fail to meet their statutory obligations. Furthermore, under certain circumstances, a court may enjoin agency action pending the resolution of a FOIA claim. See Renegotiation Board v. Bannercraft Clothing Co., Inc., 415 U.S. 1, 19-20, 94 S.Ct. 1028, 39 L.Ed.2d 123 (1974); Lewis v. Reagan, 660 F.2d 124, 128 (5th Cir.1981) (finding that "a district court has jurisdiction to enjoin agency action for violation of an [sic] FOIA claim" but noting that "such intervention requires a clear showing of irreparable injury."). In the case of the bond breach determinations
The Court recognizes that the Agency's failure to comply with FOIA requests has made it more difficult for Plaintiffs to ascertain whether bonds were properly breached and to support their defenses before the Agency. Plaintiffs have not convinced the Court, however, that no alternative forms of proof were available for most defenses.
Plaintiffs contend that they are entitled to mitigation on four bonds because the aliens were surrendered into DHS custody shortly after the delivery date. The Bond Contract provides:
I-352, Mitigation. If the obligor elects to mitigate damages, it "must give the appropriate INS office written notice of delivery not less than 72 hours prior to delivering the bonded alien." Id. Written notice "may be waived by the District Director or the District Director's designee in the appropriate circumstance." Id. The Bond Contract is crystal clear on mitigation, and thus the only question about mitigation arises in the application of this provision to the facts of the four bonds at issue. The Court will discuss each of those bonds in turn.
Plaintiffs claim that they are entitled to summary judgment on three of the bonds at issue because they were cancelled pursuant to a 2004 Settlement Agreement between the parties. Defendants argue that the Court does not have jurisdiction to entertain this defense because the settlement is not final agency action for purposes of the APA and because the Court has no independent jurisdiction to enforce the terms of the settlement agreement.
"The federal government is immune from suit unless it consents to be sued." First Nat. Bank v. Genina Marine Services, Inc., 136 F.3d 391, 394 (5th Cir. 1998). "The United States can consent to be sued either by specific statutory consent or by instituting a suit as to which a defendant may plead matters in recoupment." Id. (internal quotation marks and citation omitted); see also AM.JUR.2D Counterclaim § 71 ("By instituting a civil action, the United States subjects itself to a setoff or recoupment claim that arises out of the same transaction or occurrence as the original claim and seeks to reduce or defeat the government's recovery."). In Frederick v. United States, the Fifth Circuit explained:
386 F.2d 481, 488 (5th Cir.1967); see also Pennsylvania R. Co. v. Miller, 124 F.2d 160, 162 (5th Cir.1941) (noting that the defense of recoupment "is a doctrine of an intrinsically defensive nature founded upon an equitable reason, inhering [in] the same transaction, why the plaintiff's claim in equity and good conscience should be reduced."). The definition of recoupment includes "[t]he withholding, for equitable reasons, of all or part of something that is due." BLACK'S LAW DICTIONARY (8th ed.2004). The Fifth Circuit has emphasized that "there can be no recoupment if the damages claimed by the defendant arise from the breach of an independent contract or from an independent wrong unconnected with the plaintiffs cause of action. . . ." Equal Employment Opportunity Commission v. First Nat'l Bank of Jackson, 614 F.2d 1004, 1008 (5th Cir. 1980) (refusing to allow Plaintiffs counterclaim because its connection to the EEOC's suit was "too tenuous and indirect to warrant the innovation of the doctrine of recoupment." (internal citation omitted)).
Defendants have counterclaimed against Plaintiffs, asking the Court to enter judgment in the amount of $9,255,750.00 plus interest, penalties, and handling charges, an amount that Defendants allege is owed on the breached bonds. (Defs' Countercl. 16.) Although Defendants seek to enforce DHS' administrative determinations and have not sued on the Settlement Agreement, it appears that Plaintiffs would be entitled to assert as a defense to this claim that Plaintiffs do not owe said amount because certain bond breaches that Defendant now seeks to enforce were subsequently settled. To the extent such a defense might be construed as a claim for recoupment, it certainly would seem to arise out of the same "occurrence which is the subject matter of the government's suit."
Unfortunately, the question of which bonds were actually settled as part of the 2004 Settlement Agreement is hotly disputed. The Agreement first notes that "the unpaid penal amount of the Subject Invoices set forth on Exhibit `A,' excluding penalties and interest, totals $3,652,250. (Settlement Agreement ¶ 1, Jt. Appx. 0629-0630.) Pursuant to the Settlement Agreement, Plaintiffs agreed to pay "$525,000 down as a good faith deposit on this compromise, and . . . the balance of $2,214.187.50." (Settlement Agreement ¶ 2, Jt. Appx. 0630.) The Agreement clarifies:
(Settlement Agreement ¶¶ 2, 3, Jt. Appx. 0630.) The Settlement Agreement also includes a clause providing that the Agreement "embodies the complete understanding of the Parties with respect to the matters addressed in this Agreement" and that with respect to such matters there "are no other promises, terms, conditions, communications, representations, or obligations, either oral or in writing, which are completely subsumed by the terms of this Agreement." (Id. § 6.)
Three of the disputed bonds before the Court are listed in Exhibit A. (JSOF 4, 8, 19.) The "penal due" and "current due" amounts for these three bonds in the same exhibit is listed as "$0." Defendants argue vigorously that the Agreement only settled "invoices" and that the anything with a $0 amount cannot be considered an "invoice." Unfortunately, the terms of the Agreement seem clear: Plaintiffs were released from claims as to all invoices set forth in Exhibit A. Though it does admittedly seem unusual, the Court is not aware of any reason why an "invoice" could not be issued in the amount of $0.
Defendants present several affidavits and other documents to demonstrate that the parties did not, in fact, intend to settle these three bonds and to show that the Agency does not issue invoices for $0. The Court may not look to this parol evidence, however, because the terms of the contract are unambiguous. See United States v. Waterman S.S. Corp., 397 F.2d 577, 579 (5th Cir.1968) ("Where the terms of the contract are unambiguous the determination of its meaning is a question of law and should be decided without resort to extrinsic evidence."). Defendants' further argument that this interpretation leads to the conclusion that DHS lacked authority to enter into the Settlement Agreement is similarly unavailing. Defendants maintain that DHS lacks authority to settle any bond for no consideration. Even if this were true, nothing in the Agreement itself suggests that that no consideration was paid to settle the three disputed bonds. Instead, the Settlement Agreement sets forth a global sum that Plaintiffs were to pay in consideration for release of all claims on the totality of the bonds set forth in Exhibit A.
In addition to sending an I-340 notice demanding delivery of an alien to the bonding companies, DHS also sends notice of the delivery date to the alien. According to Plaintiffs, this form is also referred to as a "run letter" because it creates a risk that the alien will leave town before the delivery or deportation date. The I-352 Bond Contract appears to acknowledge this risk, stating that "no demand to produce the bonded alien for deportation/removal shall be sent less than three days prior to sending notice to the bonded alien." I-352, General Terms and Conditions. This statement is not included in the list of events that automatically cancel a bond. The Bond Contract also clearly states, however, that a delivery bond is breached when the obligor fails to produce the alien in response to "a timely demand." I-352, General Terms and Conditions (emphasis added). The Court looks to the language of the contract as a whole
Plaintiffs argue that a bond must be cancelled if the Agency fails to send a questionnaire with the I-340 Notice to Deliver Alien. Neither the Bond Contract nor any relevant regulations mention such a questionnaire.
Plaintiffs claim that the Amwest I Settlement and Amwest Memorandum make clear that the "timely notice" required by the Bond Contract includes the attachment of a completed questionnaire to every I-340. A policy statement attached to the Amwest I Settlement provided "A questionnaire prepared by the surety with approval of INS will be completed by INS whenever a demand to produce a bonded alien is to be delivered to the surety."
The Agency admits that field offices will "sometimes prepare a questionnaire for delivery to the surety along with the Form I-340" but contends in a sworn statement that sending the questionnaire is "not required by statute, policy, or regulation." (Wells Decl. ¶ 1.) The Agency also insists
Sudden or unexplained change in a consistent Agency policy may render an agency's decision arbitrary and capricious. See Smiley v. Citibank (S.D.), 517 U.S. 735, 742, 116 S.Ct. 1730, 135 L.Ed.2d 25 (1996). However, the Court does not think that it is possible, on this record, to piece together a consistent Agency policy to cancel or rescind a bond breach if a questionnaire is not sent to a surety along with an I-340 notice. The only documents suggesting that failure to send a questionnaire is a valid grounds for appeal is the August 1997 memorandum. The Court is not at all certain that this statement by the Acting Executive Associate Commissioner of the Office of Field Operations should be construed as general Agency policy. Even if the Court were to conclude that the Agency had a policy of extending the provisions of the Amwest I Settlement to all sureties as a matter of policy and fairness, the text of the Amwest I Settlement does not make clear that failure to send a questionnaire with a demand to produce the alien necessarily renders a bond breach unenforceable. Furthermore, the Agency has provided a sworn statement, which carries the penalty of perjury, indicating that no such policy existed.
The Court concludes, therefore, that the Agency's failure to send a questionnaire with a declaration of a bond breach does not, at least on this record, constitute a valid defense to a bond breach determination.
Plaintiffs argue that they substantially complied with the conditions of one of the bonds before the Court. 8 C.F.R. § 103.6(e) ("A bond is breached when there has been a substantial violation of the stipulated conditions."). The bond at issue has been cancelled by the Agency, however, and Plaintiffs argument is therefore moot.
Because the Agency has cancelled certain bonds through the ADR process, those bonds are now moot.
Plaintiffs initially claimed that they were entitled to summary judgment on one bond the Agency claimed was due and owing because that bond was on appeal. According to Defendants, this bond (JSOF 47) is now ripe for the Court's review because the AAO dismissed Plaintiffs' appeal on May 30, 2007. The Court will consider this bond on the merits. The Court does take note of the fact, however, that the Agency had improperly attempted to invoice Plaintiffs for this bond before the appeal had been decided.
The Court has reviewed the submissions regarding each individual bond breach determination. For the reasons provided in Part VI, the Court finds, without further discussion, that Defendants are entitled to summary judgment on the following bonds because Plaintiffs' alleged defenses cannot succeed and the agency's decision was therefore not arbitrary or capricious or otherwise contrary to law:
Parties agree that the following bond was properly declared in breach, and Defendant's Motion for Summary Judgment on this bond is therefore
Defendants are also entitled to summary judgment on the following bonds, which do merit further discussion:
Plaintiffs claim that this bond should have been cancelled because Mr. Melendez-Martinez was granted voluntary departure and was required to post a voluntary departure bond.
(Jt. Appx. 006.) The Agency declared Plaintiffs' delivery bond breached after Plaintiffs failed to deliver Mr. Melendez-Martinez
The Court finds that the AAO's decision was not arbitrary and capricious or otherwise contrary to law because the AAO considered the relevant factors and because there is a rational relationship between the facts found and the decision made. See, e.g., Motor Vehicle Mfrs. Ass'n of the United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168, 83 S.Ct. 239, 9 L.Ed.2d 207 (1962)); Overton Park, 401 U.S. at 416, 91 S.Ct. 814; see also Sierra Club v. Peterson, 185 F.3d 349, 365-66 (5th Cir.1999), and because the decision was not otherwise contrary to law. The Bond Contract states that the bond is cancelled upon execution of a voluntary departure bond. There is no evidence in the record that any new voluntary departure bond was posted or executed in this case. Furthermore, based on a somewhat confusing and contradictory record from the IJ, the AAO could have reasonably found that the IJ essentially chose to keep the existing departure bond in place and did not actually require Mr. Melendez-Martinez to post a new voluntary departure bond.
Plaintiffs argue that they are entitled to summary judgment on this bond because Defendants did not provide Plaintiffs with I-340 or I-323 notice.
In the case of this bond, the address provided for the obligor (Safety National) and the agent on the I-352 form was the same. The record reflects that both an I-340 demand to deliver alien and an I-323 notice was sent to that address. The record also reflects that those forms were returned to sender as undeliverable. (Jt. Appx. 019, 023.) Plaintiffs claim in their Motion for Summary Judgment that the Agency had notice of the agent's new mailing address, (Pls.' Partial Mot. Summ. J. 22), but direct the Court to no evidence in the summary judgment record to that effect. Where the Agency attempts to provide notice to the address on the I-352 form in conformance with 8 C.F.R. § 103.5a(a)(2), an immigration bond may
Plaintiffs argue that the Agency's bond breach should be cancelled because they did not receive I-323 notice of the breach.
Plaintiffs' Motion for Partial Summary Judgment is therefore
Plaintiffs claim that they are entitled to mitigation on this bond because Ms. Morocho-Palaguachi was surrendered into custody within 30 days of the bond breach.
On appeal, the AAO noted that Plaintiffs did not provide evidence that the alien was, in fact, in ICE custody on February 11, 2004. The record before the Court includes an Agency document with a stamp indicating that Ms. Morocho-Palaguachi was surrendered on that date.
The explicit terms of the I-352 state that "if the obligor elects to deliver the bonded alien to mitigate damages, it must give the appropriate INS office written notice of delivery not less than 72 hours prior to delivering the bonded alien" unless the District Director or her designee waive such notice. Plaintiffs do not claim that they provided such notice or that the District Director waived that notice. Plaintiffs are not, therefore, entitled to mitigation on this bond. Defendants' Motion for Summary Judgment as to this bond is therefore
Plaintiffs allege that they are entitled to summary judgment on this bond because Defendants breached a material term of the bond contract by failing to respond to their FOIA request. For the reasons stated above in Part VI(E), Plaintiffs "FOIA" defense cannot succeed.
Plaintiffs also argue that they are entitled to mitigation on this bond because DHS' records reflect that the alien was in custody on March 26, 2002, 11 days after the delivery date of March 15, 2002. Plaintiffs do not allege that they themselves took Mr. Valdebenito into custody, and the record reflects that he was arrested. Plaintiffs are not, therefore, entitled to mitigation on this bond. See discussion supra Part VI(F).
Plaintiffs' Motion for Partial Summary Judgment as to this bond is therefore
Plaintiffs argue that they are entitled to mitigation on this bond because DHS has stipulated that the alien was in custody on February 26, 2002, 21 days after the delivery date of February 5, 2002. There is no evidence in the record that Plaintiffs themselves surrendered Ms. Karyna Toledo-Menocal into custody, and the record only reflects that she "currently detained by INS" on February 26, 2002. Plaintiffs are not, therefore, entitled to mitigation on this bond. See discussion supra Part VI(F). Plaintiffs' Motion for Partial Summary Judgment as to this bond is therefore
Plaintiffs contend that they are entitled to mitigation on this bond because Ms. Chacon-Alfaro was taken into custody on June 13, 2002, only seven days after her June 6, 2002 appearance date. There is nothing in the record to show that Plaintiffs themselves surrendered Mr. Chaco-Alfaro to INS, and Plaintiffs have not made that precise assertion in briefing. Plaintiffs are not, therefore, entitled to mitigation on this bond. See discussion supra Part VI(F). Plaintiffs' Motion for Partial Summary Judgment as to this bond is therefore
Based on the analysis provided in Part VI, supra, Plaintiffs' Motion for Partial Summary Judgment is
Plaintiffs are also entitled to summary judgment on the following bonds, which require some further discussion:
For the following bonds, there is no evidence in the record before the agency at the time the bond was breached that the Agency mailed a I-340 demand to deliver the alien and/or an I-323 notice of breach to both Safety National and AAA, despite the fact that such notice was requested in the I-352 Bond Contract. Nor is there any evidence in the record that the Agency believed that notice to both was required. The Court has found the Agency's determination that notice to either the obligor or the co-obligor was sufficient, despite the fact that the parties requested notice to both on the I-352 Bond Contract to be contrary to law. See discussion, supra, Part VI(A).
The Agency's argument that Plaintiffs bear the burden of proving that they did not receive notice is confusing given Defendant's simultaneous contention that the Court can review the Agency's initial breach determination and must determine whether that determination was arbitrary and capricious based on the record before the Agency at the time. Plaintiffs have no opportunity to present evidence to the Agency before a bond is declared breached. If the Court were to review an initial breach determination and were to find no evidence in the record that the Agency provided notice to Plaintiffs, it could not possibly uphold that decision even under the highly deferential arbitrary and capricious standard. Defendants have also informed the Court that Plaintiffs need not exhaust administrative remedies, and thus their argument that Plaintiffs should prove lack of notice on appeal is unconvincing. Furthermore, the Agency's arguments regarding burden of proof are presented for the first time as part of this litigation and were not provided as a reason for the Agency's decision at the time it was made.
Although parties have submitted extensive extra-record documentation and briefing on the factual issues surrounding notice for these bonds, the Court does not believe it should decide these issues. "When an administrative agency has made an error of law, the duty of the Court is to `correct the error of law committed by that body, and, after doing so to remand the case to the (agency) so as to afford it the opportunity of examining the evidence and finding the facts as required by law.'" NLRB v. Enterprise Ass'n of Steam, Hot Water, Hydraulic, 429 U.S. 507, 522 n. 9, 97 S.Ct. 891, 51 L.Ed.2d 1 (1977) (citing ICC v. Clyde S.S. Co., 181 U.S. 29, 21 S.Ct. 512, 45 L.Ed. 729 (1901)); see also Pennzoil Co. v. FERC, 789 F.2d 1128, 1136 n. 21 (5th Cir.1986). The Agency's breach determination on the following bonds is therefore
Plaintiffs argue that DHS violated the terms of the bond by failing to wait 72 hours to send Mr. Arbustine-Diaz a "Run Letter" after it sent the I-340 notice.
As explained in Part VI(H), supra, the Bond Contract requires the Agency to send the I-340 demand to surrender alien to Plaintiffs no less than three days prior to sending notice to the alien. As part of the ADR process, Plaintiffs produced a copy of a Form I-166 "Run Letter" dated May 27, 2004 and addressed to Mr. Arbustine-Diaz at the address provided for him on the Bond Contract. Plaintiffs do not clarify how they obtained this letter. The I-340 demand to deliver alien is dated the same day: May 27, 2004. (Jt. Appx. 576.) Defendants argue that the letter was not part of the administrative record and seem to suggest that it may not have been sent to Mr. Arbustine-Diaz. The Agency's own Field Manual indicates that the Record of Proceeding for Bond Breach Cases should contain a copy of the Form I-166. (Jt. Appx. 058). There is reason to believe, therefore, that the administrative record was incomplete when the AAO made its decision on this bond and that the Agency did not consider all of the relevant factors when determining that the bond had been breached. Any fact dispute regarding this document can be addressed by the Agency on remand. Defendant's Motion for Summary Judgment is therefore
Plaintiffs argue that the Agency's decision to declare this bond breached was arbitrary and capricious because neither Safety National nor AAA received I-323 Notice of the bond breach.
The record includes an I-323 Notice of Breach that has the words "certified mail" at the top. (Jt. Appx. 214.) There is no certified mail return receipt in the record. Plaintiffs allege that the presence of the Notice in the record is not sufficient to show that the Notice was mailed. Defendants contend that the presence of the I-323 letter in the file is sufficient proof of service. On at least some occasions, the Agency itself has found that the record failed to establish proper notice on an obligor where the record did not contain a domestic return receipt. See In re Obligor, 2003 WL 21000163 (INS Office of Admin. Appeals Feb. 11, 2003) ("The record fails to contain the domestic return receipt to indicate that the Notice to Deliver Alien was sent to the obligor . . . or to indicate that the obligor had received the notice to produce the bonded alien . . . . Consequently, the record fails to establish that the district director properly served notice on the obligor in compliance with 8 C.F.R. 103.5a(a)(2)(iv)."); In re Obligor,
The Agency argues that the presence of the letter in the file is sufficient to establish that it was mailed and received, relying on McCall v. Bowen, 832 F.2d 862 (5th Cir.1987). In McCall, the Fifth Circuit found that a factfinder could reasonably presume receipt of a letter sent by certified mail in the absence of a return receipt where the Agency provided a copy of the letter which was properly addressed, date stamped, and had the certified mail number written on it and submitted an affidavit that the letter had been sent to that address by certified mail. Id. at 864. Here, the Agency has not provided an affidavit that this particular notice was sent to the address by certified mail, and there is no certified mail number written on the notice. Moreover, the Fifth Circuit has held generally that there is no general presumption of delivery for certified mail when the return receipt is not received by the sender. See Mulder v. Comm'r of Internal Revenue, 855 F.2d 208 (5th Cir., 1988) ("While it is presumed that a properly-addressed piece of mail placed in the care of the Postal Service has been delivered, no such presumption of delivery exists for certified mail when the requested return receipt is not received by the sender."); see also Lundy v. United States, 2007 WL 655756, at *5 (S.D.Tex.2007) (unpublished) (finding a "broad judicial consensus on certified mail; specifically, that any presumption in favor of mailing or delivery is destroyed when the sender cannot produce the return receipt."). The Court therefore finds that the Agency's determination that Plaintiffs were given proper I-323 notice of the breach was arbitrary and capricious because there is no rational relation between the facts found and the decision made.
Of course, failure to provide such notice does not result in cancellation of the bond, but instead just requires the initial breach to be declared unenforceable. Plaintiffs' arguments that the bond must be cancelled because Ms. Hernandez was later granted voluntary departure without requirement of a bond cannot succeed. See discussion supra Part VI(C). Defendants Motion for Summary Judgment on this bond must be
The Agency has cancelled the following bonds, and those bonds are therefore moot:
The Agency has also conceded that the following two bond breach determinations are unenforceable because the I-323 as to each notice was misaddressed. The bonds are not cancelled, however, and these
Neither party's motion is granted as to these bonds.
Plaintiffs argue that the Agency's refusal to cancel this bond is arbitrary and capricious because Mr. Omar Herrada voluntarily departed the country prior to the date the Agency breached the bond. Defendants counter that Plaintiffs have not provided valid proof of Mr. Omar Herrada's departure prior to the date of the breach.
The I-352 states that "Cancellation of a bond issued as a delivery bond shall occur upon any of the following, provided they occur prior to the date of a breach: . . . valid proof of the bonded alien's voluntary departure. . . ." I-352, General Terms and Conditions. Cancellation for said reason is "automatic" and "any subsequent appearance demand, or attempt to breach the bond, is null and void." Id. "If, however, the obligor fails to surrender the alien in response to a timely demand while the bond remains in effect, the full amount of the bond . . . becomes due and payable." Id. at G(1).
The facts of this bond are complicated. Plaintiffs appealed this bond breach in May 2004 alleging, inter alia, that Mr. Omar-Herrada departed the country on April 20, 2004, the day after his April 19, 2004 delivery date. (Jt. Appx. 474-475.) The AAO considered the relevant factors and rationally found that even if Mr. Omar-Herrada had departed on April 20, that departure occurred after the date of breach and was not, therefore, a valid defense to the bond breach.
Despite the fact that the Motion to Reopen was never decided, both parties seem
For the reasons set forth above, Plaintiffs' Motion for Partial Summary Judgment is
(Jt. Appx. 667.) The Court has found that it cannot consider the Amwest Memorandum as Agency policy, however.