EWING WERLEIN, Jr., District Judge.
After approximately five days of trial, all parties rested and closed the evidence, and the Court having considered the evidence, the trial briefs, and the oral arguments and authorities of counsel, now makes the following Findings of Fact and Conclusions of Law pursuant to FED. R. CIV. P. 52.
The
1. Plaintiff Oceaneering International, Inc. ("Oceaneering") seeks to recover from Defendant Cross Logistics, Inc. ("Cross") damages for the severance of a subsea umbilical 10923 on January 9, 2009, during Defendant Cross's offshore retrieval of its barge's port stern No. 4 anchor. The subsea umbilical belonged to Enterprise Products Partners, L.P., Enterprise Field Services L.L.C. ("Enterprise Field Services"), and Flextrend Development Company L.L.C. (collectively, "Enterprise"). Enterprise subsequently sold and transferred to Oceaneering all rights of action, "whether in tort, contract or otherwise," that Enterprise had against Defendant Cross arising out of the "damage and cost of replacement" of the umbilical.
2. Enterprise is the leaseholder and/or operator of Outer Continental Shelf ("OCS") Lease No. 12631, and the owner and/or operator of wells and facilities in the Garden Banks 72 area in the Gulf of Mexico. Enterprise Field Services was in the owner group that owned the Garden Banks 72 platform with its processing facilities and, as well, was the operator of the platform itself.
3. The Garden Banks 72 platform was affixed to the sea floor in approximately 514 feet of water. Garden Banks 117 wells Nos. 1 and 2, of which Enterprise was owner and/or operator, were located approximately 3.96 miles to the southeast of the Garden Banks 72 platform, in 915 feet of water.
4. Those two wells were serviced by control umbilicals laid on the sea floor for that distance of about 3.96 miles from the Garden Banks 72 platform to subsea umbilical termination assemblies ("SUTAs") at the respective well sites.
5. The foregoing two umbilicals were identified as umbilicals 10923 (to Well No. 2) and 10929 (to Well No. 1). They were laid within a 200-feet wide right-of-way on either side of an 18" flow pipeline, and their as-laid positions were plotted and on file with the Bureau of Ocean Energy Management Regulation and Enforcement.
6. Umbilical 10923 was laid new in or about 1993 and had a design life of approximately eight years. It was composed of various materials including numbers of steel tubes that fulfilled various functions such as communications, chemical injection, and the like.
7. At least one of the tubes used for paraffin in the 10923 had failed by 2008 and could not be used, and new umbilicals had since been manufactured that were twice as strong and far more corrosion-resistant but, even after approximately 15 years of use, Enterprise still had its 10923 umbilical in service as of late August or early September, 2008, when it closed down operations in advance of Hurricanes Gustav and Ike.
8. Apache Deepwater L.L.C. (successor by merger to Mariner Energy, Inc.) ("Mariner"), a company separate from Enterprise, also had operations on the Garden Banks 72 platform in connection with is own offshore facilities producing in a separate OCS lease of which Mariner was the leaseholder and/or operator.
9. Mariner was not in the Garden Banks 72 platform owner group, but was a producer that contracted to use the owner group's processing facilities on the platform.
10. Mariner planned to install an 8" oil riser and 12" pull tube at the Garden Banks 72 platform for use in connection with production from its own wells. Mariner had in force and effect an offshore master service contract ("Main Contract") with Plaintiff Oceaneering dated July 31, 1998. In March, 2008, Oceaneering delivered to Mariner a day rate proposal for diving services to perform the installation work pursuant to the Main Contract.
11. After receiving from Mariner a purchase order for the work, Oceaneering entered into a back-to-back subcontract agreement ("Back to Back") with Defendant Cross Logistics, Inc. ("Cross") dated July 31, 2008, to procure from Cross the utilization of one of its barges to support Oceaneering's work for Mariner at the platform. The Back to Back mutually conferred upon Oceaneering and Cross all of the corresponding rights, obligations, and liabilities that Mariner and Oceaneering had with respect to each other in the Main Contract.
12. To perform its work as Oceaneering's subcontractor, Cross utilized its barge, the Crossmar 14, with a 4-point anchoring system for mooring offshore alongside the Garden Banks 72 platform. It is from the Crossmar 14 that Oceaneering's divers would conduct their subsea installation work for Mariner.
13. Cross hired Fugro Chance, Inc. ("Fugro") to perform, among other services, specialized offshore survey services to identify various subsea assemblies, structures, and equipment, including pipelines, flowlines, umbilicals, and others, to provide data to Cross to facilitate the designation of anchor drop zones for the Crossmar 14 anchors, and to generate real time GPS data in support of Crossmar 14's deployment and recovery of her anchors.
14. Fugro provided maps showing the charted subsea assets in the vicinity of Garden Banks 72, including the right-of-way where Enterprises's 10923 umbilical, 10929 umbilical, and the 18" flow line were all charted as having been laid.
15. Cross chartered an anchor handling tug, Miss Jessica, to tow the Crossmar 14 to and from the work site at the platform and to assist Crossmar 14 with anchor handling operations. The Crossmar 14 was not a self-propelled vessel and therefore was dependent on the Miss Jessica for its navigation.
16. Cross had anchoring handling procedures for the Crossmar 14, which provided for an anchor exclusion zone with respect to subsea pipelines. The policy provided for an exclusion zone of 500 feet if the vessel and its anchor were on the same side of the pipeline. If the anchor was dropped on the other side of the pipeline from the location of the vessel, however, then the exclusion zone between the anchor and the right-of-way was to be 1,000 feet.
17. Cross's policy provided that an anchor should not be permitted to enter the anchor exclusion zone after the anchor has been deployed.
18. Cross mobilized the Crossmar 14 to the designated work site at Garden Banks 72 platform on August 19, 2008. About ten days later operations were closed down as Hurricane Gustav, the second most destructive Atlantic hurricane of 2008, entered the Gulf of Mexico, and the Crossmar 14 recovered her anchors and was towed back to shore.
19. Up until the end of August and early September, when operations were closed down, there is no evidence that Enterprise's 10923 umbilical was not still functioning.
20. Hurricane Gustav made landfall near Cocodrie, Louisiana, on September 1, and already Hurricane Ike was moving across the Atlantic Ocean. A massive storm with a huge wind field, Hurricane Ike entered the Gulf of Mexico on September 9, finally making landfall near Galveston, Texas on September 13.
21. Dozens of offshore platforms suffered damages from Hurricane Ike, including the Garden Banks 72 platform. On September 17, the Crossmar 14 was returned to the Garden Banks 72 platform, but by September 23 Oceaneering concluded that the topside damages to the platform were so severe that its diving services could not be resumed. The Crossmar 14 was towed back to shore, and operations did not resume until on or about December 6.
22. Crossmar 14 was again mobilized to the Garden Banks 72 platform on December 6-7, December 16-20, December 29-January 3, 2009, and January 8-9, and thereafter as Oceaneering continued its work for Mariner.
23. On or about March 23, 2009, when Enterprise attempted to operate its 10923 umbilical, it found that it was inoperative.
24. The parties subsequently determined that Enterprise's 10923 umbilical had been severed and was, in fact, the umbilical that had been raised to the surface on the Crossmar 14 port stern anchor No. 4 on January 9, 2009, and which, at the time, all parties thought was simply trash from off the sea floor.
25. When on location at Garden Banks 72 platform on January 9, 2009, the Crossmar 14 was starboard to the south face of the platform; her bow to the west; her starboard stern No. 3 anchor was set to the northeast; her starboard bow No. 2 anchor was set to the northwest; her port bow No. 1 anchor was set to the southwest; and her port stern No. 4 anchor was set to the southeast, and on the east side of the designated 200 feet right-of-way.
26. The weather forecast for January 9 called for heavy weather from the south-southeast, which meant that diving operations would need to be suspended and the Crossmar 14 moved to shore.
27. The Crossmar 14 logs show at 0900 hours winds were out of the southeast at 15-20 knots, seas were 2-4 feet; at 1500 hours winds were out of the southeast at 15-20 knots, seas were 3-4 feet; by 1800 hours winds were out of the southeast at 20-25 knots, seas were 4-6 feet; and by 2100 hours winds were out of the southeast at 25-30 knots, seas were 5-7 feet, with occasional 9 feet.
28. Oceaneering ended its diving operations in mid-afternoon on January 9 and its diving bell was secured on the Crossmar 14 by 1746 hours. The Crossmar 14 instructed the Miss Jessica to recover in sequence the starboard stern No. 3 anchor, the starboard bow No. 2 anchor, and the port bow No. 1 anchor.
29. The Crossmar 14 at all times planned to recover the port stern No. 4 anchor by winching to the anchor on the seabed and not to use the Miss Jessica to recover the anchor.
30. The Miss Jessica recovered the starboard stern No. 3 anchor and returned it to the Crossmar 14, and then did the same with the starboard bow No. 2 anchor.
31. Close to the time that the Miss Jessica picked up the port bow No. 1 anchor, the Crossmar 14 began winching the barge in a south-southeasterly direction toward the port stern No. 4 anchor and into the prevailing seas and wind.
32. The anchor recovery plan required the Crossmar 14 to continue on that course—to back down over the port stern No. 4 anchor—and then lift the anchor from the seabed vertically, recovering the port stern anchor to the barge.
33. At approximately 2020 hours, the No. 4 anchor began to slip on the sea floor, causing the Crossmar 14, which was at that time well east of the right-of-way, to begin drifting in a northnorthwesterly direction under the influence of the prevailing winds and sea.
34. The Crossmar 14 over the next 15 minutes, more or less, drifted some 1,800 feet generally in a north-northwesterly direction and back across the right-of-way to its westerly side.
35. At approximately 2035 hours, and due to unknown forces which the parties variously argue was either the No. 4 anchor snagging the 10923 umbilical laying outside of its right-of-way, or the 10923 umbilical already snagged by the No. 4 anchor from within the right-of-way and now recoiling from the stresses imposed on it after it was fouled, or a sudden calming or reversal of winds and seas, or a combination of some such factors, the Crossmar 14's direction of drift changed and it began moving in an easterly direction for a distance of about 550 feet, crossing the right-of-way again over to its easterly side.
36. Throughout the time that the Crossmar 14 drifted to the north-northwest, and then to the east, the Crossmar 14 continued to winch in her No. 4 anchor. During this time the Crossmar 14 still was not under the effective control of the Miss Jessica.
37. At 2040 hours, the Crossmar 14 was approximately 200 feet to the east of the right-of-way when the No. 4 anchor neared the surface, enabling Cross's crew to observe that the anchor had ensnared something, and later—with the aid of a small remotely operated vehicle (ROV)—to see a "bird's nest" of cables and material tangled in the flukes and shank of the anchor.
38. Cross's personnel, as well as Oceaneering's personnel onboard the Crossmar 14, believed at the time that the "bird's nest" was trash from off the ocean floor.
39. The event was reported, and Mariner commissioned Oceaneering to survey the area and search for damage. Three days after the accident, Oceaneering set out with a new vessel, the Ocean Intervention II, and on January 13 and 14, Oceaneering made a subsea umbilical survey along the eastern side of the right-of-way—the side closest to where the No. 4 anchor had been dropped—to determine if the umbilical on the eastern side of the 18" pipeline had been disturbed or snagged by the anchor. This survey tract was about one mile along in the exact vicinity where the Crossmar 14 snagged the "bird's nest," and examined the 3" umbilical 10929, which was charted to lay on the eastern side of the 18" pipeline. The 10929 was found to be in place and undisturbed.
40. The surveyors did discover at about 600-700 feet southeast of the platform an unidentified umbilical crossing the 10929, which Oceaneering followed to the east until they reached its tattered end. Oceaneering then retraced this umbilical remnant back toward the platform until it disappeared under a new pipeline that had been laid by Mariner. The surveyor did not suspect at the time that this was the 10923 umbilical, which some months later was determined to be the fact.
41. Assuming at the time that the only umbilical that could have been fouled was Enterprise's 10929 laid to the east of the pipeline, Oceaneering did not survey the west side of the pipeline, where the 10923 was charted.
42. The same subsea survey showed some sea floor disturbance about 1,700 feet to the northwest of where the No. 4 anchor had been dropped and about 350 feet to the west-northwest of where the Crossmar 14 was located at 2020 hours when it began drifting to the north-northwest.
43. Months later, after Enterprise discovered the 10923 umbilical was not operative, it was determined that it was Enterprise's 10923 that was snagged and brought to the surface on the Crossmar 14's No. 4 anchor on the night of January 9.
44. The subsea survey made on January 14 established that the 10929 umbilical was within the right-of-way and to the east of the 18" pipeline as it had been charted, and that it was not damaged by the events of January 9.
45. There is no direct evidence that prior to the incident on January 9 the 10923 umbilical was not located where it had been laid and charted within the right-of-way.
46. When the No. 4 anchor began slipping along the ocean floor, causing the Crossmar 14 to begin an involuntary reversal of course and drift to the north-northwest under the influence of the winds and seas from the southeast, the Crossmar 14 continued to reel in the anchor.
47. The Crossmar 14 drifted under the influence of the sea and winds across and to the west of the right-of-way. At the approximate time when the anchor was about to be raised off of the ocean floor, the confluence of surface and subsea forces, including the heaves and pitch experienced by the barge while reeling in the anchor in seas with swells of up to eight feet, enabled the anchor fortuitously to pass over the 10929 umbilical and 18" pipeline but then, unfortunately, to foul the 10923 umbilical before being winched in sufficiently to remove the anchor from the sea floor.
48. As the Crossmar 14 continued to winch in the No. 4 anchor, the stresses upon the 10923 umbilical became severe. The stress and friction caused the umbilical to begin to fray and caused various cables within the umbilical to become entangled further in and between the flukes and shaft of the anchor, forming a tangled "bird's nest" out of the umbilical, but not severing the umbilical in two.
49. At 2035 hours, whether from an unexpected change in the seas and wind or from a recoil of the now severely stressed 10923 umbilical, or some combination thereof, the barge moved in an easterly direction for a distance of approximately 550 feet where, at 2040 hours, the barge winched the No. 4 anchor almost to the surface. Cross's personnel onboard the Crossmar 14 then barely saw the shank of the anchor with its ensnared "bird's nest," which was the 10923 umbilical.
50. After the Miss Jessica took control of the barge, the crew inspected the umbilical with an ROV, and attempted unsuccessfully to raise the ensnared anchor with the barge's crane. Finally, at about 2206 hours, the Miss Jessica began to tow the barge toward port in a north-northeasterly direction, which caused the 10923 umbilical to sever completely. The "bird's nest" fell from the anchor, and the Crossmar 14 was able to recover its No. 4 anchor. The Miss Jessica then returned the Crossmar 14 to harbor.
51. Subsequent surveys of the sea floor in early June located both of the two severed ends of the 10923 umbilical on the sea floor, both positioned consistent with the umbilical having been completely severed far to the east of the right-of-way and in an area consistent with where the Miss Jessica assumed control over the Crossmar 14 and began towing it in a north-northeasterly direction.
52. The subsea surveys showed that more than one mile of severed umbilical had been pulled out from the right-of-way in the direction of where the Crossmar 14 raised the 10923 umbilical to the surface. The tension on the southern portion of the 10923 umbilical was sufficient to pull the umbilical taut over its entire length, dragging and burying the SUTA, which was more than three miles away, and suspending the umbilical above a dip in the ocean floor for a span of more than 270 feet at its southern end.
53. The improbability of the anchor while being winched-in not to have snagged the 10929 umbilical and the pipeline before fouling the 10923 umbilical on the west side of the pipeline is not so great as the improbability of the 10923 umbilical somehow having been previously moved by unknown forces from out of the charted right-of-way and over to the east of both the 18" pipeline and the 10929 umbilical, especially given the absence of any reported allisions or fouling events during the several months since Enterprise had last used the 10923 umbilical in production operations at the end of August or early September, 2008.
54. Hurricane Ike, as vast as that storm was and as close as the eye came to Garden Banks 72 platform (30-50 miles), did not cause the umbilical 10923 to be moved to the other side of both the 18" pipeline and the sister umbilical 10929 at a depth of more than 500 feet of water, while at the same time leaving umbilical 10929 undisturbed in the right-of-way.
55. On January 8, when the Crossmar 14 dropped its anchors to set up at the Garden Banks 72 platform, and the next day on January 9, when it began to retrieve those anchors in the late afternoon, the 10923 umbilical was within the charted right-of-way and lay on the west side of the 18" pipeline.
56. The 10923 umbilical was in its charted position when it was fouled by the No. 4 anchor of the Crossmar 14.
57. Cross had knowledge of the location of the 10923 umbilical and has not rebutted the presumption of negligence that arose when Cross's drifting vessel allided with the stationary umbilical.
58. At the time of the accident, Mike Sampey, Jr. was Cross's barge superintendent on duty aboard the Crossmar 14, and he was responsible for ensuring the safety of the operations and of all persons onboard. Thus, as superintendent, Sampey owed a duty of care to the crew and passengers of the Crossmar 14, including the Oceaneering divers and other workers. Sampey was also responsible, in behalf of Cross, to ensure that the Crossmar 14 did not damage nearby surface or subsea assets, including the fixed platform and the related umbilicals and pipelines in the Garden Banks 72 area.
59. Robert Aucoin was Cross's deck foreman on duty aboard the Crossmar 14, but on the evening of January 9 he was in the tower, as tower operator—operating the anchor winch.
60. Alan Charlson was Oceaneering's superintendent onboard, in charge of Oceaneering's diving operations and work for Mariner on installing the 8" oil riser and 12" pull tube. Charlson was aware of 15 pipelines and seven umbilicals that came into this site at the Garden Banks 72 platform. Charlson also knew that Oceaneering's work needed to be performed from the south side of the platform, which is why the Crossmar 14 when on location was always anchored to the south face of the platform.
61. On the morning of January 9, with a forecast of heavy weather approaching, Sampey desired to retrieve anchors and return to shore, but Oceaneering's Charlson wanted to complete a dive, which is not unusual given the date rate of $70,000 per day that Oceaneering paid to Cross for use of the barge, whether it was onsite at the platform or not.
62. Sampey was in command of the vessel and the final decision-maker on when to retrieve anchors and return to shore, but desiring to accommodate Cross's customer Oceaneering, he acquiesced to Charlson's preference and Oceaneering's dive continued until about 1500 hours, when Charlson decided to cease diving operations. The "bell," which is the pressurized capsule in which the divers are lowered to the required depths, was secured back on the Crossmar 14 at about 1746 hours.
63. Mark Dean, Fugro's survey party chief who was onboard the Crossmar 14 on January 9, monitored and operated Fugro's survey equipment and received the real time GPS monitoring on the location and movement of the Crossmar 14 and the Miss Jessica. Dean was in the tower discharging that responsibility during the anchor retrieval process on January 9.
64. Cross's Aucoin was also in the tower to operate the anchor winches.
65. During anchor retrieval operations, Superintendent Sampey customarily was in the control tower to give oversight and to command retrieval operations. The Crossmar 14 was shorthanded on the evening of January 9, however, which required the deck foreman Aucoin—instead of acting as foreman on the deck—to be in the tower to operate the anchor winch. Superintendent Sampey, therefore, instead of providing command from the tower, was down on the deck substituting for Aucoin as deck foreman to monitor visually the anchor retrievals.
66. Sampey had been employed by Cross for about four years. He worked as a welder for Cross and then became a deck foreman on the Crossmar 14. After two years as a deck foreman, Cross promoted Sampey to superintendent in command of the vessel. He received anchoring training by watching others, and had had experience with numerous successful anchor drops and retrievals during the time of his employment.
67. Sampey, however, had no prior experience with an anchor slipping on the Crossmar 14, and Cross had not specifically trained him on what to do in the event that an anchor began slipping while backing down on it across valuable, charted subsea assets, as happened in this case.
68. The appropriate response—to avoid fouling subsea assets by dragging an anchor across the seabed and into subsea assets—is to "come out from under the wire," that is, to let out the anchor wire and thereby leave the anchor where it is on the seabed, rather than to imperil the subsea assets.
69. Had Superintendent Sampey known that the anchor was slipping, he testified that he would have called an all-stop and started to let out the anchor wire as just described to safeguard the subsea assets.
70. Superintendent Sampey, however, was not in the control tower to monitor the real time GPS screen displaying the Crossmar 14's location and movement, and he was therefore unaware that the anchor was slipping.
71. Robert Aucoin, Cross's winch operator in the tower, saw on the screen the GPS data showing that the barge was drifting away from the anchor drop location, which meant the anchor had slipped, but there is no evidence that Aucoin called Sampey to report that fact, and Sampey does not recall having received any such call from Aucoin.
72. When the anchor began slipping on the seabed about 2020 hours, the Miss Jessica was about a half mile distant from the Crossmar 14 and, while the Miss Jessica had lifted the port bow No. 1 anchor to the tug and secured it, the approximately half mile of No. 1 anchor wire extending from the tug to the barge gave the Miss Jessica virtually no effective control over the Crossmar 14, which was then in an anchorless drift.
73. Had Superintendent Sampey ordered Aucoin not to begin winching in the No. 4 anchor until the port bow No. 1 anchor wire was reeled in to or near the barge, the Miss Jessica then would have been in proximity to the Crossmar 14 so that if the No. 4 anchor began to slip, the Miss Jessica could control the Crossmar 14 to prevent it from drifting into and across the right-of-way while dragging the No. 4 anchor and risking an allision with the subsea assets.
74. Instead of waiting for the Miss Jessica to approach the Crossmar 14 while reeling in the anchor wire on the No. 1 anchor, however, Sampey began the process of backing down on the No. 4 anchor while the Miss Jessica was still well more than a half mile away.
75. Had Superintendent Sampey maintained his command position in the tower, he would have seen the real time GPS data showing the No. 4 anchor was slipping and, in the exercise of ordinary care, would have called an all-stop, and ordered the anchor wire let out to avoid the fouling of Enterprise's subsea assets.
76. The Crossmar 14 and its Superintendent Sampey were negligent in executing the anchoring retrievals on January 9, 2009, and Defendant's negligence was the proximate cause of the Crossmar 14's No. 4 anchor fouling the subsea umbilical 10923, and Enterprise's resulting property damages.
77. Mariner had a company man onboard, Kip Harzman, to give oversight to Oceaneering's diving work when the Crossmar 14 was anchored at the platform and installation work was in progress.
78. There is no evidence that Harzman was on deck or involved in any manner with Cross's attempted anchor retrieval of the port stern No. 4 anchor.
79. Oceaneering's superintendent onboard, Alan Charlson, was in charge of its diving operations and all installation work when the Crossmar 14 was anchored at the platform.
80. Charlson was inside his room on the Crossmar 14 and not involved in any manner with Cross's attempted anchor retrieval of the No. 4 anchor. Charlson knew of no problem until Sampey came to Charlson's room, told him that the anchor—then just below the water's surface—had fouled something, and asked if an Oceaneering diver could go in to see what had been snagged. Charlson said the sea was too rough to send his diver into the water, and suggested that Sampey use an ROV to inspect, which was done.
81. At no time did Harzman or Charlson, or any other personnel of Mariner or Oceaneering, either have or assert any control over Cross's efforts to retrieve the Crossmar 14's anchors on January 9, 2009.
82. Oceaneering, which neither had nor asserted any control over Cross's anchoring retrieval practices employed by the Crossmar 14, was not negligent with respect thereto and was not a contributing cause of the fouling of the 10923 umbilical.
83. Mariner, which neither had nor asserted any control over Cross's anchoring retrieval practices employed by the Crossmar 14, was not negligent with respect thereto and was not a contributing cause of the fouling of the 10923 umbilical.
84. Upon receiving the results of the subsea surveys of the severed 10923 umbilical, which included photographs and descriptive reports of the extreme stresses that had been inflicted upon the umbilical before it was finally severed, Enterprise soon determined not to attempt a repair of the severed umbilical but rather to replace it with a new umbilical, fabricated with better materials and much stronger, and with a much longer design life of 20 years.
85. The factors considered by Enterprise in choosing to lay a new umbilical included the reserves of oil and gas that Enterprise expected to recover in Well No. 2 in coming years; the advanced age of the 10923 umbilical, which already had far exceeded its design life and had suffered a failure of at least one paraffin tube; and the high expense of repairing the 10923 umbilical, which would not be substantially different than the expense of acquiring a new umbilical but which would entail greater risks given the extraordinary stresses to which the 10923 umbilical had been subjected and the possibility that ultimately it might prove to be incapable of being restored to serviceable condition.
86. It was reasonable for Enterprise to replace the 10923 umbilical rather than to attempt to repair it.
87. The 10923 umbilical was a distinct subsea asset used to facilitate the operation of the subsea Garden Banks 117 Well No. 2 from the Garden Banks 72 platform nearly four miles away. It was not an integral part of the platform itself nor of the wellhead, and would not have to be replaced even if (hypothetically) either the platform or the equipment at the wellhead required replacement.
88. Enterprise preferred to abandon the old umbilical in place, which would have reduced its damages, but that option was denied by the United States Mineral Management Service. Enterprise's damages therefore included the cost of removal and disposal of the severed remnants of the 10923 umbilical.
89. Enterprise contracted with Plaintiff Oceaneering to recover the damaged umbilical from the ocean floor, which it did. It disposed of the shorter segment, and rolled up and delivered to a storage yard in Florida the longer segment, but did not save the frayed, unraveled ends of either remnant where the umbilical had been severed.
90. Neither the shorter segment that was destroyed nor the longer segment that was maintained on a reel in storage has any salvage value beyond the additional cost required finally to dispose of the materials as scrap.
91. Enterprise acted reasonably to mitigate its losses.
92. Enterprise issued requests for proposals to replace the umbilical, but did not issue a uniform set of specifications upon which each of those parties submitting proposals was able to bid. The three or four proposals Enterprise received therefore had variations in scope and other details and could not be compared in the way that side-by-side bids on a common set of specifications can be compared.
93. Enterprise subjectively decided that Oceaneering's proposal was the most competitive received, and there is no evidence to the contrary.
94. Enterprise therefore chose Oceaneering to furnish and install a new umbilical from the platform to Well No. 2, which it did, and, from November 2009 through October 2010, Enterprise paid to Oceaneering a total of $3,795,340 for its work, which included removal of the damaged 10923 umbilical from the ocean floor and fabrication and installation of its replacement.
95. Oceaneering's customary profit margin for its work was approximately 15%, and Oceaneering earned a profit of approximately $569,000.00 on this replacement project.
96. In addition to the sums paid to Oceaneering, Enterprise calculated that it incurred another $884,299.00 in expenses for various consultants, engineering firms, the use of a helicopter, the ROV umbilical inspection survey done by McMoRan, and even for salaries paid to its own regular employees. When that sum was added to the amount paid separately to Oceaneering, Enterprise claimed total damages in the amount of $4,679,639.88.
97. When the work was completed and the new umbilical placed into service, Enterprise had a brand new umbilical fabricated with improved materials, which was much stronger, and with a design life of 20 years. Hence, the new replacement of the old 10923 umbilical was a betterment in that it substantially extended the expected useful life of Enterprise's subsea umbilical.
98. As a distinct subsea asset and with evidence of its age and that one tube already had failed, depreciation of the 10923 umbilical is a factor properly considered in connection with determination of Enterprise's damages caused by Cross's maritime tort.
99. The major documented cost of acquiring and installing the new umbilical in place of the severed 10923 umbilical, including the required removal of the old umbilical from the ocean floor, was $3,795,340, which Enterprise paid to Oceaneering. Enterprise's claim for additional damages of $884,299 incurred to acquire and to place in service the new umbilical was not refuted in the evidence.
100. The percentage of useful life extension—the betterment Enterprise received with its new umbilical—must therefore be applied to Enterprise's total proven calculated costs of $4,679,639.
101. According to Oceaneering's expert damages witness, whose opinion on this point is credible, the 10923 umbilical had an expected useful life of 25 years when it was installed in 1993. When it was severed as a result of Cross's negligence in January, 2009, it had been in service for 16 years. The 10923 umbilical therefore had a pre-severance remaining expected useful life of 9 years.
102. The much-improved new umbilical has a design life of 20 years, which would support an inference of a longer useful life based on the 10923 umbilical having had a longer expected useful life than its design life of only 8 years. Nonetheless, in the absence of direct evidence of a longer expected useful life for the new umbilical, its expected useful life is found to be at least equal to its design life of 20 years.
103. As a result of the replacement umbilical, the remaining expected useful life of this subsea asset was extended from 9 years to 20 years, an extension of 11 years, which was a material and the principal betterment received by Enterprise. The percentage of useful life extension is thus 11/20, or 55%, which—even in this very conservative analysis—is a very substantial betterment. (See COL Nos. 21-24, below at pp. 57, 58).
104. Applying the percentage of useful life extension (55%) to Enterprise's total replacement cost of $4,679,639 nets the sum of $2,573,801 as the value of the new umbilical's extended useful life for the benefit of Enterprise. (See COL No. 21).
105. Deducting the value of the extended useful life of the new umbilical ($2,573,801) from Enterprise's total damages of $4,679,639, establishes Enterprise's recoverable damages caused by Cross's negligent fouling and destruction of Enterprise's 16 years old umbilical: $2,105,838. (See COL Nos. 22, 28).
106. In a three-party (Enterprise, Oceaneering, and Mariner) Settlement Agreement with Grant of Subrogation and Assignment dated November 15, 2010 ("Settlement Agreement"), Enterprise did "convey, sell and transfer to Oceaneering . . . all rights, claims, causes of action and/or rights of action . . . in tort . . . that may or could be alleged . . . [against] Cross and/or the CROSSMAR 14, her appurtenances, engines, gear, and tackle, in respect of the damage and cost of replacement of the Garden Banks [10923] umbilical."
107. The Settlement Agreement recites that Oceaneering agreed to pay to Enterprise simultaneously with execution of the Settlement Agreement, "in cash, in lump sum, without discount" the total sum of $4,679,639.88 for the releases given and assignments made by Enterprise to Oceaneering.
108. Oceaneering, as the purchaser and transferee of Enterprise's maritime tort claim against Cross, alleges in its Second Cause of Action that it is entitled to recover from Cross the full sum of $4,679,639.88, plus interest, as a "result of the negligence and/or fault of Cross and the Crossmar 14 and/or unseaworthiness of the Crossmar 14 as a consequence of the improper retrieval of the port stern anchor."
109. Enterprise's recoverable maritime tort damages sustained as a proximate cause of Cross's negligence, however, are $2,105,838, plus prejudgment interest. (FOF Nos. 98-105).
110. Oceaneering, as the purchaser/transferee/assignee of Enterprise's maritime tort cause of action against Cross, is entitled to recover from Cross no greater amount of damages than Enterprise was entitled to recover from Cross.
111. Oceaneering is entitled to recover from Cross on the assigned negligence claim the sum of $2,105,838, plus prejudgment interest.
112. Cross had no contractual relationship with Enterprise, and Enterprise had no breach of contract claims against Cross to "convey, sell and transfer" to Oceaneering in the Settlement Agreement.
113. Oceaneering alleges a right to contractual indemnity from Cross, however, pursuant to the Purchase Order issued by Mariner to Oceaneering and the Back to Back between Oceaneering and Cross.
114. Oceaneering's breach of contract for indemnity claim requires examination not only of the Main Contract (between Mariner and Oceaneering and Mariner's Purchase Order with the indemnity clause issued to Oceaneering), and the Back to Back between Oceaneering and Cross, but also of the contractual arrangements between Enterprise—whose umbilical was damaged—and Mariner.
115. Enterprise and Mariner, among others, had in force and effect a Platform Processing and Limited Right of Use Agreement dated effective December 1, 2008 (hereinafter "Platform Processing Agreement"), which contractually governed their commercial relationship relevant to the Garden Banks Block 72 platform and processing facilities on the platform. Oceaneering introduced in evidence excerpts from the Platform Processing Agreement—but not the entire contract—and the Findings of Fact that follow necessarily rely on the excerpts in evidence.
116. Enterprise Field Services and other third parties, individually and collectively, are described in the Platform Processing Agreement as "Owners." Mariner was not an owner of the platform but paid Owners for certain services and processing of its production on the platform, and is identified as one of the "Producers."
117. Section 11.2(b) of the Platform Processing Agreement, inserting the names of the parties involved here, provides:
118. In the foregoing section 11.2(b), Enterprise releases Mariner, its contractors and subcontractors, and agrees to indemnify them for all property losses and damage sustained by Enterprise, arising out of or in connection with the Platform Processing Agreement, including damage to the platform located in Garden Banks Block 72, which is defined in Exhibit A of the Agreement, to include "the equipment, facilities, and fixtures. . . located on or affixed to such structure and owned by [Enterprise]." The foregoing release and indemnification clause expressly excepts from its coverage, however, the first $10 million of Enterprise's losses caused by or arising out of the fault or negligence of Mariner, its contractors and subcontractors in connection with installation activities.
119. Enterprise's 10923 umbilical terminated at the Garden Banks Block 72 platform and, necessarily, was affixed thereto, and the loss sustained by Enterprise from the severance of its umbilical arose out of or in connection with Mariner's installation activities to add an 8" oil riser and a 12" pull tube and subsea spool at the Garden Banks Block 72 platform.
120. Because it is uncontroverted that Enterprise's property damage to its 10923 umbilical was occasioned by Mariner's installation operation and the damages did not exceed the amount of $10 million, Enterprise's release and indemnification under § 11.2(b) does not apply to release Mariner, Mariner's contractor Oceaneering, or the latter's subcontractor Cross, from liability for Enterprise's property loss or damage "caused by or arising out of the fault or negligence" of Mariner, Oceaneering, or Cross.
121. Hence, Enterprise did not release Cross from liability for Enterprise's property loss caused by Cross's fault and negligence in its attempted retrieval of the Crossmar 14's No. 4 anchor on January 9, 2009, and Cross's tort liability has been found above in Findings of Fact Nos. 1 through 105.
122. There is no evidence that the fouling of Enterprise's 10923 umbilical during Mariner's installation activity was caused by or arose out of any fault or negligence on the part of Mariner or its contractor, Oceaneering.
123. Mariner did not negligently cause damage to Enterprise's umbilical or commit any maritime tort for which it was liable to Enterprise. (See also FOF Nos. 77, 78, 81, 83).
124. Oceaneering did not negligently cause damage to Enterprise's umbilical or commit any maritime tort for which it was liable to Enterprise. (See also FOF Nos. 79-82).
125. As found above (FOF No. 112), because Cross, an independent subcontractor of Oceaneering, had no contract with Enterprise and hence no contractual liability to Enterprise for having caused property damage to Enterprise's 10923 umbilical, Cross's liability to Enterprise is founded solely in tort.
126. Oceaneering had no contract with Enterprise to indemnify or hold harmless Enterprise for any property loss or damage sustained by Enterprise during installation work that was caused by the fault or negligence of an independent subcontractor, in this instance, Cross.
127. Although the $10 million exclusion under § 11.2(b) of the Platform Processing Agreement excepts Mariner from § 11.2(b)'s release and indemnity for Enterprise's property losses and damages (see FOF Nos. 117-120), Mariner in the Platform Processing Agreement assumes no liability or obligation to hold harmless or to indemnify Enterprise for Enterprise's property losses and damages arising in connection with the Platform Processing Agreement that are caused by the negligence or fault of a third party, an independent contractor, or an independent subcontractor, and without any fault or negligence on the part of Mariner.
128. Mariner had no contract with Enterprise to indemnify Enterprise for any property loss or damage sustained by Enterprise during installation work that was caused by the fault or negligence of an independent contractor or its independent subcontractor, in this instance, Cross.
129. There is no evidence that Enterprise has or had any cognizable claim against Mariner—either in contract or in tort— based upon the tortious conduct of Cross which acted at all times as an independent subcontractor.
130. Mariner had in force and effect an OFFSHORE MASTER
SERVICE CONTRACT ("Main Contract") with Oceaneering dated July 31, 1998. (See also FOF Nos. 10, 11). In March 2008, Oceaneering submitted a day rate proposal to Mariner to perform diving services pursuant to the Main Contract for Mariner's installation of an 8" oil riser and 12" pull tube and subsea spool at the Garden Banks Block 72 platform. On award of the work, Mariner issued Purchase Order No. 2113-2199 dated March 27, 2008 to Oceaneering.
131. To provide vessel support for Oceaneering to perform its obligations under the Main Contract and Purchase Order, Oceaneering entered into a Back to Back Subcontract Agreement ("Back to Back") with Cross dated July 31, 2008.
132. Pursuant to the Back to Back, Oceaneering and Cross have the same rights, obligations, and limitations with respect to each other as Mariner and Oceaneering have to each other under the Main Contract and Purchase Order.
133. Section 8 of the Main Contract states that Oceaneering "shall be an independent contractor with respect to the performance of all work provided and services rendered hereunder, and . . . Mariner shall have no direction or control over [Oceaneering] or its employees, agents, contractors, or subcontractors except in the results to be obtained."
134. Correspondingly, under the Back to Back, Cross was an independent contractor with respect to all work provided and services rendered by Cross, and Oceaneering had no direction or control over Cross except in the results to be obtained.
135. The Main Contract, as amended July 26, 1999, includes Section 13, entitled: "Release, Hold Harmless and Indemnity Obligations." Sections 13.B and 13.D, read as follows:
136. In the foregoing quoted clauses, Oceaneering releases and agrees to indemnify Mariner from any liability for claims and demands based on property damage or loss suffered by Oceaneering arising from work done under the Main Contract, even if Oceaneering's property loss or damage is caused by the negligence of Mariner itself.
137. Likewise, Mariner releases and agrees to indemnify Oceaneering and its subcontractors—in this case, Cross—from any liability for claims and demands based on property loss or damage suffered by Mariner arising from work done under the Main Contract, even if Mariner's damage or loss is caused by the negligence of Oceaneering or its subcontractors—in this case, Cross.
138. There is no evidence that Mariner suffered any property loss or damage arising from or related to any work performed by Oceaneering or its subcontractor Cross under the Main Contract.
139. Mariner sustained no property loss or damage from work performed by Oceaneering and Cross under the Main Contract in connection with installation of the 8" oil riser and 12" pull tube, and subsea spool at Garden Banks 72.
140. If Mariner had sustained any such property loss or damage caused by Oceaneering or it subcontractor Cross, Mariner released Oceaneering and Cross from all liability for such. (See FOF Nos. 135, 137).
141. The Back to Back Contract between Oceaneering and Cross states:
142. The foregoing clauses of the Back to Back adopt the identical release and indemnity concept found in the Main Contract.
143. Hence, under Section 13.D of the Main Contract—as applied in the Back to Back—Oceaneering released Cross and its subcontractors for all claims of property loss or damage suffered by Oceaneering caused by the negligence of Cross and its subcontractors related to the performance of the work under the Main Contract for installation of an 8" oil riser and 12" pull tube and subsea spool.
144. There is no evidence that Oceaneering suffered any property loss or damage arising from or related to performance of work by Cross or its subcontractors under the Back to Back and Main Contract.
145. Oceaneering sustained no property loss or damage from the work performed by Cross and its subcontractors to provide vessel support under the Back to Back and Main Contract.
146. If Oceaneering had sustained any such property loss or damage caused by Cross or its subcontractors, Oceaneering released Cross and its subcontractor from all liability for such. (See FOF Nos. 141-143).
147. The Purchase Order dated March 27, 2008, issued by Mariner to Oceaneering, included the following clause:
148. The parties are agreed that the Purchase Order was mutually accepted by Oceaneering and Cross as a part of the Back to Back Contract to which they agreed on July 31, 2008.
149. Under the Indemnity Clause of the Purchase Order, Oceaneering covenants to indemnify and save harmless Mariner against "all liability to others" for property damage arising out of the act of Oceaneering or its contractors, in this case, Cross.
150. Under the Back to Back, the Purchase Order's Indemnity Clause binds Cross to indemnify and save harmless Oceaneering against all liability to others for property damage arising out of the acts of Cross.
151. Enterprise had a cognizable maritime tort claim for $2,105,838 against Cross for the property damage it sustained as a result of Cross's negligence. (See FOF Nos. 1-105, 109).
152. Instead of lodging a claim against the tortfeasor Cross, however, Enterprise made demand upon Mariner to compensate it for the damages caused by the negligence of Cross.
153. Mariner did not negligently cause Enterprise's property damage. (See FOF Nos. 77, 78, 81, 83, 123).
154. The Platform Processing Agreement—although not releasing Mariner from liability for property damage or loss to Enterprise caused by Mariner or a subcontractor (see FOF Nos. 117-120, 127, 128)—discloses no covenant or promise by Mariner to indemnify Enterprise for maritime tort damages done to Enterprise's property by an independent subcontractor, such as occurred here.
155. Mariner had no cognizable indemnity or other contractual obligation to pay Enterprise for damages arising from Cross's negligent conduct that ruptured Enterprise's umbilical.
156. Nonetheless, over a period of months as Enterprise incurred costs related to the replacement of its umbilical, Enterprise sent to Mariner a series of invoices for reimbursement of its expenditures.
157. Mariner, in turn, made demand upon Oceaneering. By letter dated August 27, 2009, Mariner's Special Counsel advised Oceaneering that Enterprise had made a claim against Mariner for replacement of the severed umbilical 10923 and, citing Paragraph 9 of the Purchase Order, made formal demand on Oceaneering to indemnify Mariner for "all liability incident to the damaged . . . umbilical."
158. A week later, Oceaneering's General Counsel sent a letter to Cross demanding that Cross, pursuant to the Main Contract, Purchase Order, and Back to Back, indemnify Oceaneering and Mariner for the damages.
159. On July 15, 2010, according to Enterprise, a Mariner representative had told Enterprise that the accumulated invoices— which evidently included some invoices unrelated to the new umbilical—had been expedited for approval, but nearly two and a half months later—understandably—Mariner still had not paid them.
160. By letter dated September 27, 2010, Enterprise ratcheted up its demand on Mariner by stating that by October 8 it must pay invoices that then totaled $2,176,811, most of which pertained to replacement of Enterprise's 10923 umbilical, mentioned "the Owners' right to shut-in production and/or exercise of termination rights under Section 8.2(a)" of the Platform Processing Agreement when payments are 60 days past due, and stated that if payment was not received, "Enterprise shall consider Mariner to be in Default under the [Platform Processing] Agreement."
161. In the foregoing demand letter to Mariner, Enterprise cited clauses in the "Statements and Billings" and "Payments" sections of the Platform Processing Agreement, but Enterprise did not refer to any clause in the Platform Processing Agreement or any other agreement that bound Mariner to pay to Enterprise property damages resulting from a maritime tort committed by an independent subcontractor and for which Mariner was not liable.
162. After receiving Enterprise's letter threatening to shutin Mariner's production, Mariner's outside counsel by letter dated October 1, 2010, demanded that Oceaneering pay $1,276,237.90 in damages sought by Enterprise for replacement of Enterprise's umbilical, specifically relying on and quoting from paragraph 9 of the Purchase Order, as follows:
163. Mariner's October 1, 2010 demand letter to Oceaneering further asserted that "Oceaneering agreed to indemnify and save harmless Mariner from claims for property damage arising out of the acts or omissions of Oceaneering's employees, contractors, or agents." Mariner's lawyers enclosed with their demand letter a copy of Enterprise's letter dated four days earlier demanding a total sum of $2,176,811 from Mariner.
164. A month after the October 8, 2010 "Default" date specified by Enterprise, Enterprise wrote a new demand letter, dated November 9, 2010, this time addressed not only to Mariner but also to Oceaneering and, for the first time, to Cross. The November 9 letter demanded from all three parties "immediate payment of amounts previously expended by Enterprise" to repair "damages to the umbilical when an anchor of the Crossmar 14 became fouled," which damages now were claimed to be $4,679,639.88. The November 9 demand letter no longer threatened to shut-in Mariner's production or to declare Mariner in Default of the Platform Processing Agreement.
165. Similar to its September 27 demand letter to Mariner, however, Enterprise's November 9 demand letter again failed to cite any contractual covenant or legal theory as to why either Mariner or Oceaneering should be liable to Enterprise for maritime tort damages caused by the third party independent subcontractor, Cross.
166. Cross was the sole party responsible for conducting the anchor retrieval operations on January 9, 2009, and it was the negligent conduct of Cross's barge superintendent Sampey and tower winch operator Aucoin that was the sole cause of the damages to Enterprise's 10923 umbilical.
167. Cross at all times acted as an independent contractor when it conducted those anchor retrieval operations.
168. Neither Mariner nor Oceaneering exercised or asserted any control over Cross's anchor retrieval operations on January 9, 2009.
169. Neither Mariner nor Oceaneering is vicariously liable for the maritime tort damage to Enterprise's umbilical caused by Cross.
170. There is no evidence of any negligent conduct by Oceaneering that gave rise to Oceaneering having any maritime tort liability to Enterprise or to Mariner.
171. Oceaneering had no liability under contract or tort law to either Enterprise or Mariner for the damage to Enterprise's umbilical caused by the negligence of its independent subcontractor, Cross.
172. If Enterprise and Mariner had pursued their putative claims against Oceaneering, they would have been unable to prove any damages sustained by either of them from any maritime tort committed by Oceaneering.
173. The Indemnity Clause in the Purchase Order, adopted in the Back to Back Agreement, does not require Cross to hold harmless or to indemnify Oceaneering for payments made by Oceaneering to settle claims for which there is no potential basis for the indemnitee's (Mariner's) liability.
174. Nonetheless, on November 15, the fourth business day after Enterprise signed its November 9 demand letter, Enterprise, Mariner, and Oceaneering all executed a Settlement Agreement of 17 pages pursuant to which Oceaneering paid to Enterprise on the spot—even to the last 88 cents—Enterprise's full demand of $4,679,639.88.
175. The circumstances of the November 9 demand letter—no longer threatening to shut-in Mariner's production or to declare Mariner in default of the Platform Processing Agreement (see FOF No. 164) followed by an almost instantaneous 17 pages long threeparty Settlement Agreement excluding the tortfeasor Cross but paying in full the newly stated total demand of nearly $4.7 million—leads to the inevitable finding that the "settlement" was actually reached by Enterprise, Mariner, and Oceaneering before Enterprise ever served its November 9 demand letter on Cross.
176. As found below (FOF Nos. 185-192), there were compelling commercial reasons for Oceaneering's generous payment to Enterprise that evidently obviated in Oceaneering's judgment any need to conduct careful liability and maritime tort damages analyses as to whether Mariner and Oceaneering were actually liable to Enterprise and the amount of maritime tort damages for which the tortfeasor Cross was actually liable.
177. Although the Indemnity Clause requires Oceaneering to "indemnify and save harmless [Mariner] . . . from and against all claims, . . ." to discharge that covenant Oceaneering is not required to pay to or on behalf of an indemnitee an unreasonable demand made under circumstances where the claim made against Mariner was one for which Mariner had no potential liability.
178. When an indemnitor pays to or in behalf of an indemnitee an unreasonable sum to settle a claim for which the indemnitee has no potential liability, the indemnitor acts as a volunteer.
179. Likewise, under the Back to Back, to discharge its indemnity covenant to Oceaneering under paragraph 9 of the Purchase Order, Cross is not required to indemnify Oceaneering, its indemnitee, for Oceaneering's payment "in cash, in lump sum, without discount" of the full amount of Enterprise's demand made against its indemnitee, Mariner, under circumstances where Mariner had no potential liability to Enterprise for the severed umbilical.
180. Alternatively, if Oceaneering had a reasonable basis to anticipate liability to Mariner under paragraph 9 of the Purchase Order (and the evidence shows none), then for Oceaneering to recover as an indemnitee from its indemnitor, Cross, Oceaneering was required to act reasonably, that is, to settle the claim in light of the risk of exposure.
181. Oceaneering's payment to Enterprise, which had sustained maritime tort damages of approximately $2.1 million, of Enterprise's full demand of approximately $4.7 million "in cash, in lump sum, without discount," was an unreasonable payment bearing no relation to any reasonable expectation of liability exposure.
182. Oceaneering's settlement payment to Enterprise of $4,679,639.88 was unreasonable.
183. Cross has no duty under paragraph 9 of the Purchase Order to indemnify Oceaneering for an unreasonable payment made by its indemnitee, Oceaneering, to Enterprise.
184. Oceaneering has not proven itself entitled to recover any damages on its contractual indemnity claim.
185. Mariner "lawyered up" with threats of litigation against Oceaneering on October 1, 2010, after Mariner received Enterprise's threat to shut-in Mariner's offshore production and declare Mariner in default of the Platform Processing Agreement.
186. Mariner knew that it was not liable to Enterprise for maritime tort damages committed by an independent subcontractor, but Enterprise had immense commercial leverage that it brought to bear against Mariner by reason of Enterprise Field Services being not only an owner but also the operator of the Garden Banks Block 72 platform under the Platform Processing Agreement. Mariner, on the other hand, was only a producer, dependent upon the Owners' processing facilities to continue its own production.
187. Enterprise freely employed this leverage against Mariner simply by "billing" Mariner for claimed tort damages inflicted by Cross in the manner that the Platform Processing Agreement evidently authorized Enterprise to bill Mariner for processing and related services on the platform. And then, when the tort damages inflicted by the independent subcontractor Cross were not paid by Mariner, Enterprise threatened Mariner with the draconian action of shutting in its production just as if Mariner had defaulted on contractual obligations to pay for processing under the Platform Processing Agreement.
188. Mariner, in turn, was motivated to ramp up its pressure on Oceaneering, which was the beneficiary of the ten years old Main Contract with Mariner, pursuant to which Oceaneering from time to time received from Mariner profitable purchase orders. Mariner also invoked and relied upon the Indemnity Clause in paragraph 9 of the Purchase Order, asserting that Oceaneering was obligated to hold harmless Mariner from "all claims" and Enterprise had made a claim.
189. Oceaneering enjoyed highly profitable business relationships not only with Mariner but also with Enterprise. For example, Enterprise chose Oceaneering to recover from the seabed the severed two segments of the 10923 umbilical, and to provide and install the new replacement umbilical, for which work Oceaneering was paid approximately $3.8 million, with a profit margin of well more than a half million dollars—all for repairing the damage done by its own subcontractor, Cross.
190. Oceaneering's senior vice president of subsea services testified that Oceaneering annually received approximately $10 million in gross revenues from sales to Enterprise.
191. Oceaneering had compelling commercial reasons to accommodate its long-time customers, both Mariner and Enterprise, by paying "in cash, lump sum, without discount" Enterprise's full demand, notwithstanding an absence of legal basis either in contract or in tort for Enterprise to make such a demand against Mariner or against Oceaneering.
192. Thus, six days after Enterprise made its ostensible demand (see FOF Nos. 174, 175), Oceaneering wrote a check for the full $4,679,639.88, took an assignment of claims, and sued Cross in this case to recover the full sum.
193. Oceaneering claims that Cross breached the Back to Back, which adopted the Main Contract, by failing to perform its services in a safe and workmanlike manner during retrieval of its anchors on January 9, and that Oceaneering is entitled to damages in the sum of $4,679,639.88.
194. Paragraph 10 of the Main Contract, as incorporated by the Back to Back Contract, provides:
195. Pursuant to the Back to Back Contract, Cross was obligated to Oceaneering to perform its work in a safe and workmanlike manner.
196. Based upon the same Findings above with regard to Cross's negligence, Cross failed to perform its work in a safe and workmanlike manner in retrieving the Crossmar 14's port stern No. 4 anchor on January 9, 2009. (See FOF Nos. 58-76).
197. Cross at all times acted as an independent subcontractor when its unsafe and unworkmanlike anchor retrieval caused property damage to Enterprise's property.
198. Cross's failure to perform its work in a safe and workmanlike manner caused no damages to Oceaneering.
199. If Oceaneering did sustain any loss or damage to its property from Cross's unsafe and unworkmanlike anchor retrieval, Oceaneering in the Back to Back, and its incorporated Main Contract, released and agreed to hold Cross harmless from liability for such. (See FOF Nos. 135, 137, 141-146).
200. To the extent that Oceaneering contends that its November 15, 2010 payment of $4,679,639.88 to Enterprise constitutes economic damages to Oceaneering based on Cross's failure to perform in a safe and workmanlike manner, that payment—voluntarily made by Oceaneering without any showing of Oceaneering's liability for Enterprise's loss—was not a foreseeable result of Cross's breach of contract 22 months earlier. Cross's failure to perform in a safe and workmanlike manner did not proximately cause Oceaneering to pay nearly $4.7 million to Enterprise. (See also FOF Nos. 175, 176, 185-192).
201. Oceaneering is entitled to no recovery on its breach of contract claim against Cross.
202. Cross counterclaims against Oceaneering for breach of contract, alleging that the Purchase Order, incorporated into the Back to Back, requires Oceaneering to indemnify and hold harmless Cross "from and against any and all claims, losses or damages arising from uncharted debris or pipelines not located in accordance with the latest survey data during the performance of the work."
203. As previously found, the 10923 umbilical was in its charted location when it was snagged by Cross's anchor. (See FOF Nos. 55-57).
204. None of the property loss or damage proven in this case arose "from uncharted debris or pipelines."
205. Oceaneering did not breach the Back to Back or Purchase Order with respect to indemnifying or holding harmless Cross from uncharted debris or pipelines not located in accordance with the latest survey data.
1. The Court has jurisdiction of the parties and of the subject matter of this case pursuant to 28 U.S.C. § 1333.
2. As Enterprises's subrogee/transferee/assignee, and in its own right, Oceaneering alleges causes of action against Cross for negligence ("Second Cause of Action"), contractual indemnity ("FirstCause of Action"), and breach of contract ("Third Cause of Action").Cross counter-claims against Oceaneering, alleging breach of contract for failure to indemnify.
3. To establish maritime negligence, a plaintiff must demonstrate that there was a duty owed by the defendant to the plaintiff, the defendant breached that duty, the plaintiff sustained injury, and there was a causal connection between the defendant's conduct and the plaintiff's injury.
4. "Determination of the tortfeasor's duty, and its parameters, is a function of the court. That determination involves a number of factors, including most notably the foreseeability of the harm suffered by the complaining party."
5. Duty is measured by the scope of the risk that negligent conduct foreseeably entails.
6. The
7. The presumption of the
8. The
9. The common law negligence doctrine of proximate causation applies in admiralty.
10. Applying the general maritime law, the Fifth Circuit "has consistently held that a principal who hires independent contractors over which he exercises no operational control has no duty to discover and remedy hazards created by its independent contractors," and accordingly cannot be held vicariously liable for the torts of the independent contractors.
11. An exception to this general rule occurs only where the principal, despite the independent contractor arrangement, actually retains some degree of control over the manner or methods by which the contractor does his work.
12. In determining whether the principal retained control over the independent contractor's work methods,
13. Cross at all times acted as an independent subcontractor, neither Oceaneering nor Mariner assumed any operational control over Cross's anchor retrieval operations on January 9, 2009, and neither Oceaneering nor Mariner has vicarious liability to Enterprise for the damages caused to Enterprise's umbilical by Cross's negligence. (See FOF Nos. 77-83, 166-169).
14. The purpose of compensatory damages in tort cases is to place the injured person as nearly as possible in the condition he would have occupied if the wrong had not occurred.
15. The plaintiff bears the burden of proof to show the amount, as well as the fact, of damages.
16. Damages need not be proved with an exact degree of specificity.
17. When there is a tortious injury to property and the market value of that property is unknown, the amount of damages must be determined by the cost of repairs to or replacement of the property.
18. The new-for-old rule provides that a party suffering injury is entitled to recover only that which is necessary to restore his damaged property to the same condition as existed immediately before the delict.
19. Thus, where repair or replacement costs form the basis of the damage award, the Court must determine whether the repair or replacement adds new value to or extends the useful life of the property; if so, an appropriate reduction from the full repair or replacement costs should be made.
20. When the repair or replacement of the damaged property extends the useful life of the property, but to a different degree from the expected useful life of the property when it was first acquired by the plaintiff, the percentage of useful life extension is required to be determined.
21. The "percentage of useful life extension" is the portion of the total useful life of the repaired property that the useful life extension constitutes.
22. "If this allocable cost is then deducted from the total cost of repairs, the resulting damages award will precisely compensate the plaintiff for the cost of restoring his property to its precollision condition."
23. This formula applies—as in this case—when the principal or only betterment to the plaintiff's property is the extension of its useful life.
24. Depreciation under the new-for-old rule applies to the entire cost of replacement, including surveying and other incidental costs associated with replacement. See
25. Where the repairs do not extend the useful life of the property as it existed just before the collision, there should be no deduction for depreciation.
26. Repairs do not extend the useful life of an integral part of a structure if that part would have to be replaced when the entire structure is replaced. See
27. A tortfeasor bears the burden to show that the victim of its tortious conduct failed to mitigate damages. The tortfeasor must demonstrate (1) that the injured party's conduct after the accident was unreasonable and (2) that the unreasonable conduct had the consequence of aggravating the harm.
28. Applying the Fifth Circuit's rule (
29. Oceaneering brings its negligence claim as the transferee/assignee and conventional subrogee of Enterprise, pursuant to the Settlement Agreement made by them and Mariner.
30. Under the general maritime law, "the assignment of tort claims from the injured party to one tortfeasor permitting the settling defendant to proceed against a co-tortfeasor is invalid."
31. The Fifth Circuit regarded its holding in
32. The rationale of
33. On the other hand, while finding it unnecessary to determine under the facts of
34. Enterprise's sale, assignment, and transfer of its tort claim against Cross to Oceaneering, which was not a co-tortfeasor with Cross, was valid.
35. Cross's negligence in retrieving the port stern No. 4 anchor on January 9, 2009, was the sole proximate cause of Enterprise's property damage and loss. (See FOF Nos. 58-83). Cross was an independent contractor and neither Oceaneering nor Mariner was vicariously liable to Enterprise for Enterprise's damages. (See FOF Nos. 77-83, 166-169; COL Nos. 10-13). Enterprise's damages from the tort were $2,105,838. (See FOF Nos. 98-105). By reason of Enterprise's sale, assignment, and transfer of its tort claim to Oceaneering, Oceaneering is entitled to recover from Cross $2,105,838, plus prejudgment interest from the date of the injury.
36. A maritime contract containing an indemnity agreement should be read as a whole and its words given their plain meaning unless the provision is ambiguous.
37. Under federal maritime law,
38. Although the general rule requires an indemnitee to show actual liability on his part to recover against an indemnitor, "a defendant need only show potential (rather than actual) liability to recover indemnity where . . . the defendant's claim is based on a written contract of insurance or indemnification" and the settlement is reasonable.
39. A court confronted with a valid indemnification agreement "should insure that the claim was not frivolous, that the settlement was reasonable, that it was untainted by fraud or collusion, and that the indemnitee settled under a reasonable apprehension of liability."
40. "[A] settlement must be reasonable before indemnity is owed."
41. Reasonableness ordinarily is to be measured by the extent of financial exposure the settling party faces in the court where he will have to litigate if he does not settle.
42. When the parties differ sharply in their contentions about liability and damages, it may be "impossible to fix a reasonable settlement amount with anything approaching mathematical precision," such that "[t]he calculation of a reasonable settlement amount necessarily must be resolved by an exercise in judgment."
43. Once the indemnitee shows it is potentially liable, the indemnitor bears the burden to show that the amount of the settlement was unreasonable.
44. Mariner had no potential liability to Enterprise in contract or in tort for Enterprise's property damage caused by an independent subcontractor. (See FOF Nos. 77, 78, 81, 83, 127-129, 153-155, 166-169). Oceaneering knew or upon inquiry should have known that Enterprise's claim against Mariner had no basis in contract or tort, and Oceaneering knew that it had no liability to Enterprise in contract or in tort for the tort committed by its independent subcontractor Cross.
45. Oceaneering's payment to Enterprise to satisfy a claim against Mariner for which Mariner had no potential liability was not reasonable.
46. Alternatively, if Oceaneering as indemnitee of Cross had shown that it was potentially liable to Mariner—presumably to indemnify and hold harmless Mariner from Enterprise's claim, which claim against Mariner had no basis either in tort or contract—then Oceaneering's payment "in cash, in lump sum, without discount" of $4,679,639.88 to Enterprise—far more double the amount of Enterprise's $2,105,838 tort damages that it could have recovered from Cross—was a wholly unreasonable indemnity payment.
47. Oceaneering made the payment—unreasonable under an indemnity proviso—for separate commercial reasons related to its own ongoing lucrative business relationships with both Enterprise and Mariner. (See FOF Nos. 185-192).
48. Cross did not breach its contractual indemnity covenant under the Back to Back and Purchase Order by refusing to pay to Oceaneering $4,679,639.88.
49. The interpretation of both the Back to Back and the Main Contract is governed by principles of the general maritime law and the admiralty and maritime laws of the United States. In the event the laws of any state otherwise may apply, the Main Contract and the Back to Back are governed by Texas law to the extent not inconsistent with or superseded by the general maritime law.
50. The core principles of Texas contract law are consistent with the general maritime law with respect to Oceaneering's breach of contract claim. See
51. "[T]he essential elements of a breach of contract action are: (1) the existence of a valid contract; (2) performance or tendered performance by the plaintiff; (3) breach of the contract by the defendant; and (4) damages sustained by the plaintiff as a result of the breach."
52. "Where a [maritime] contract expressly refers to and incorporates another instrument in specific terms which show a clear intent to incorporate that instrument into the contract, both instruments are to be construed together."
53. Admiralty law recognizes an implied warranty of workmanlike service which arises from contractual relationships,
54. In an action for breach of contract, damages are not recoverable for loss that the party in breach did not have reason to foresee as a probable result of the breach when the contract was made. Restatement (Second) of Contracts § 351 (1981). The requirement of foreseeability in a breach of contract case "is a more severe limitation of liability than is the requirement of substantial or `proximate' cause in the case of an action in tort or for breach of warranty."
55. In admiralty, "the guilty party is liable for all foreseeable and proximately caused losses incurred by the innocent party" as a result of breach of the warranty of workmanlike performance. 1 Admiralty & Mar. Law §5-9 (5th ed.) (citing
56. Oceaneering did not sustain damages to its own property as a result of Cross not performing in a good and workmanlike manner during Cross's fateful anchor retrieval efforts on January 9, 2009. (See FOF Nos. 198, 199).
57. Cross, when it breached its contractual duty to perform its anchor retrieval work in a safe and workmanlike manner and caused $2.1 million in damages to Enterprise's umbilical, had no reason to foresee that a probable result of its breach would be for Oceaneering about two years later—driven by significant business and commercial reasons of its own—to purchase for nearly $4.7 million Enterprise's maritime tort claim and seek to recover that sum from Cross as breach of contract damages. (See FOF Nos. 185-192, 200).
58. Oceaneering is entitled to no recovery from Cross for breach of contract because Oceaneering did not sustain damages as a result of Cross's failure to perform its work in a safe and workmanlike manner.
59. It is a "bedrock premise" in maritime tort actions under the general maritime law that an award for prejudgment interest is the rule rather than the exception; prejudgment interest must be awarded unless unusual circumstances make an award inequitable.
60. Admiralty courts have broad discretion in setting the prejudgment interest rate.
61. The years since the subject maritime tort occurred on January 9, 2009, have been an unprecedented prolonged period of low interest rates. No evidence was presented at trial by either party as to a reasonable rate of prejudgment interest, and the Court therefore has taken judicial notice of several published benchmarks. The Texas post-judgment interest statute—which also applies to prejudgment interest—is premised on a benchmark rate of interest that a money judgment creditor might have to pay to borrow the unpaid amount of the judgment. See TEX. FINANCE CODE, §§ 304.003, 304.103 (Vernon 2006). The Texas statute adopts as its standard the prime rate as published by the Board of Governors of the Federal Reserve System, but with a floor of 5%.
62. Having considered a range of interest data and, as well, the circumstances of this case, the Court finds that a simple rate of interest of 2% per annum from the date of injury to the date of judgment is fair and just.
63. On Enterprise's maritime tort damages of $2,105,838.00, Plaintiff as purchaser and assignee of Enterprise's claim is entitled to recover prejudgment interest in the amount of $227,199.73, which results in a total judgment of $2,333,037.73.
64. If any of the foregoing Findings of Fact constitute Conclusions of Law, they are adopted as such; and if any of the foregoing Conclusions of Law constitute Findings of Fact, they are adopted as such.
65. Based on the foregoing Findings of Fact and Conclusions of Law, it is ORDERED that Plaintiff Oceaneering International, Inc. shall have and recover from Defendant Cross Logistics, Inc. the total sum of TWO MILLION THREE HUNDRED THIRTY-THREE THOUSAND THIRTY-SEVEN and 73/100 DOLLARS ($2,333,037.73). A separate Final Judgment will be entered.
The Clerk shall notify all parties and provide them with a true copy of these Findings of Fact and Conclusions of Law.