OPINION1
EMILY Y. HEWITT, Chief Judge.
This is an action for just compensation filed by owners of property along the eastern shore of Lake Michigan. Plaintiffs' properties are located along an area of the shoreline that erodes naturally, but allege that the government's construction and maintenance of a pair of jetties effected a taking by speeding the erosion of their properties.
This Opinion addresses a jurisdictional issue that arose after the second trial held by the court to address the merits of plaintiffs' claims. The court holds that, because plaintiffs' claims accrued earlier than 1952, plaintiffs filed this action outside of the limitations period. The court therefore dismisses plaintiffs' claims for lack of jurisdiction.
"`Without jurisdiction the court cannot proceed at all in any cause. Jurisdiction is power to declare the law, and when it ceases to exist, the only function remaining to the court is that of announcing the fact and dismissing the cause.'" Steel Co. v. Citizens for a Better Env't, 523 U.S. 83, 94 (1998) (quoting Ex parte McCardle, 74 U.S. (7 Wall) 506, 514 (1868)). For purposes of judicial efficiency, if the reviewing court in any appeal should disagree with the court's view of its jurisdiction, and to avoid the possibility of a trial opinion being drafted months or years after the trial, and the possibility of a repetitive trial, the court also presents here its findings from the trial. These findings are presented in the alternative and, in the absence of jurisdiction, do not entitle plaintiffs to just compensation in the amounts determined by the court.
Before the court are Plaintiffs' Post-Trial Brief (Pls.' Br.), Docket Number (Dkt. No.) 495, filed June 21, 2011; United States' Post-Trial Memorandum (Def.'s Br.), Dkt. No. 496, filed June 21, 2011; Plaintiffs' Response to the United States' Post-Trial Brief (Pls.' Resp.), Dkt. No. 497, filed July 12, 2011; and United States' Post-Trial Response Memorandum (Def.'s Resp.), Dkt. No. 498, filed July 12, 2011.
Also before the court is the following briefing on the topic of jurisdiction, filed pursuant to the court's August 9, 2011 Order, Dkt. No. 499: Plaintiffs' Post-Trial Brief on Jurisdiction (Pls.' Jur. Br.), Dkt. No. 501, filed September 7, 2011; United States' Supplemental Post-Trial Memorandum (Def.'s Jur. Br.), Dkt. No. 502, filed September 7, 2011; United States' Supplemental Post-Trial Response Memorandum (Def.'s Jur. Resp.), Dkt. No. 503, filed September 21, 2011; and Plaintiffs' Post-Trial Reply Brief on Jurisdiction (Pls.' Jur. Resp.), Dkt. No. 504, filed September 21, 2011.
Also before the court is the transcript of the trial of damages (Tr.), held from April 18 through April 21, 2011 and from April 25 through April 28, 2011.
I. Procedural Background and the Law of the Case
"Plaintiffs2are the owners of property along approximately four and a half miles of the eastern shore of Lake Michigan south of St. Joseph Harbor." Sept. 28, 2007 Op., Banks v. United States (Liability Op.), Dkt. No. 245, 78 Fed. Cl. 603, 604 (2007). Beginning in the 1830s, the United States government, acting through the United States Army Corps of Engineers (defendant or the Corps) re-constructed the mouth of the St. Joseph River and began constructing harbor jetties that jutted into Lake Michigan in order to accommodate commercial shipping vessels exiting the St. Joseph River into Lake Michigan. Id. Over time, the Corps lengthened the jetties and then encased them in steel. Id. Plaintiffs claim that the Corps' construction and maintenance of the jetties caused erosion of their shoreline property. Id. Specifically, plaintiffs allege that the encasement of the jetties in "sand-tight" steel sheet piling during the period from 1950 to 1989 interrupted the natural littoral3 drift of sand to their properties, resulting in erosion. See Aug. 9, 2011 Order, Banks v. United States (Order to Brief Jursisdiction), Dkt. No. 499, 99 Fed. Cl. 622, 624 (2011).
Several factors obscure the effect of the jetties on plaintiffs' properties. Plaintiffs' properties are located along a shoreline that is eroding naturally, see Tr. 2594:24-25 (Nairn); Tr. 710:22-23 (Mackey), making it necessary to distinguish the baseline of natural erosion from erosion caused by defendant. The comparatively slow process of long-term erosion is also masked by far larger swings in the width of the beaches next to plaintiffs' properties caused by cross-shore sand transport, a cyclical process by which sand is moved offshore during times of high lake levels and returned to the shore during times of low lake levels. See Tr. 2593:3-19, 2594:2-2595:2 (Nairn) ("So, I mean, you've got swings of hundreds of feet related to the cross or reversible process and then you've got a very [s]low retreat, we believe to be around .62 [feet] per year on the south end, going on in the background of all those very large swings back and forth."); cf. Tr. 1624:9-12 (Shabica) (stating that "predicting lake levels is like predicting the weather, but if we look in the past, high lake levels from one high lake level to the next have ranged anywhere between 11 years and 22 years"). Furthermore, the composition of a shoreline, a characteristic that impacts how the shoreline erodes and how it reacts to efforts to mitigate erosion, can be hidden by surface sediments, and may be complex and difficult to characterize into one of the two categories—sandy and cohesive—used by coastal engineers and geologists. See infra Part III.B.
Defendant filed a motion to dismiss on the ground that plaintiffs' claims are time-barred. July 31, 2001 Op. and Order, Banks v. United States (Accrual Op. I), Dkt. No. 3, 49 Fed. Cl. 806, 809 (2001), rev'd, 314 F.3d 1304 (Fed. Cir. 2003) (Accrual Op. II). The court granted defendant's motion to dismiss, finding that plaintiffs' claims accrued no later than 1989, more than six years before plaintiffs filed suit. See id. at 825. For reasons discussed below, see infra Part III.A.1, the United States Court of Appeals for the Federal Circuit (Federal Circuit) reversed and remanded for further proceedings, Accrual Op. II, 314 F.3d at 1310.
On remand, this case has been bifurcated for trial of liability and damages. In 2007 the court held a one-week trial of liability and issued the court's Liability Opinion.4 See generally Liability Op., 78 Fed. Cl. 603. The Liability Opinion summarizes the procedural history of the first eight years of this case, makes extensive findings of fact and describes many of the scientific concepts at issue in this case. See id. passim. In order to minimize repetition, this Opinion assumes substantial familiarity with the Liability Opinion.
After the court issued its Liability Opinion, the court directed the parties to "file a joint status report or, if they cannot agree, separate status reports, proposing additional proceedings necessary to resolve the remaining issues in this matter." Dec. 14, 2007 Order, Dkt. No. 250, at 1-2. Defendant filed a status report, stating that the parties had met in person "in an effort to discuss issues and share thoughts on how to calculate damages." Def.'s Status Report, Dkt. No. 252, at 2. Defendant described several factual and legal issues that remained outstanding in regard to the measure of damages owed by defendant. See id. at 2-5. Defendant stated that, while defendant believed that the court had ruled on the issue of shoreline composition, plaintiffs believed that they would be able to introduce additional evidence on the topic. See id. at 4. Defendant noted that the "array of factors" that must be considered by the court in order to calculate damages is complicated by the fact that "plaintiffs present a variety of different circumstances: for example, some plaintiffs claim to have lost all of their property, some plaintiffs have sold their property since the onset of litigation, and some also claim loss and damage to structures and loss of rental income." Id. at 2. Defendant suggested that appraisals of plaintiffs' properties would be necessary to establish the amount of damage caused by the government's actions. See id. at 2-3. Defendant proposed a schedule for briefing on the remaining legal issues, limited additional discovery and a trial of damages. See id. at 4-5.
Plaintiffs submitted a status report that proposed no further proceedings or discovery. Pls.' Status Report, Dkt. No 251, passim. Plaintiffs' status report proposed that the court order defendant to pay plaintiffs $124,918,219, an amount that plaintiffs argued was equal to the cost of the shore protection installed by plaintiffs, the loss of real property and structures to erosion, the loss of rent, the loss of beach access, "prospective damages" and interest. Id. at 1-3, 5. Plaintiffs did not attach adequate documentation or detailed calculations to their status report to support the amount of their alleged damages. See id. passim. Plaintiffs stated that "[p]laintiffs have reviewed numerous available appraisals and find them to be unhelpful in that they use comparables, i.e., other sold properties, which likewise lack unhindered (i.e., no need for shore protection) lake access." Id. at 6. Without explanation, plaintiffs attached to their status report a newspaper article titled "River dredging faces obstacles"; a list—largely typed but partly written by hand—of the plaintiffs and the sums alleged to be due to each; a copy of two filings in this case related to interrogatories; and a list—largely written by hand but typed in part—entitled "Properties Sold or Destroyed[,] Reasonably Foreseeable Loss." Id. at Exs. 1-4.
Plaintiffs then filed Plaintiffs' Motion for Leave to Supplement Status Report, Dkt. No. 253, attached to which was a status report with the subtitle "taking is spoliation," id. at 1. In their status report, plaintiffs stated that "defendant/spoliator, who has been found liable for taking private property landward of the high water mark (OHWM), now wants to foist upon the judicial process a tediously cumbersome effort to measure that very property which it has destroyed or disposed of by its own continuing activity." Id. at 1-2. Plaintiffs argued that "[t]he best evidence of sand loss to each plaintiff is based on his or her own recollection, photographs, appraisals, etc. listed in plaintiffs' answers to defendant's 2nd set of interrogatories." Id. at 2 (capitalization omitted). Plaintiffs further argued that "[a]n appropriate sanction for the defendant/spoliator would be for the [c]ourt to accept the calculations which have been available to defendant since July 16, 2001—over six years." Id. at 2. Plaintiffs argued that "defendant/spoliator has acted intentionally, in an anti-constitutional, anti-environmental, anti-due process, and unnecessary manner." Id. at 3.
The court conducted two telephonic status conferences with the parties, see Jan. 22, 2008 Order, Dkt. No. 258, at 1-2, and scheduled briefing on the issue of whether plaintiffs would be permitted to present additional evidence of shoreline composition at the trial of damages, see Feb. 19, 2008 Order, Dkt. No. 260, passim. Plaintiffs filed a memorandum that the court treated as a motion for reconsideration on the issue of shoreline composition. Oct. 15, 2008 Op. and Order, Banks v. United States (Order Granting Recons.), Dkt. No. 276, 84 Fed. Cl. 288, 290 (2008). Plaintiffs argued that they should be permitted at the trial of damages to present additional evidence that the shoreline in plaintiffs' zone5 is cohesive.6 Id. The court concluded that "[c]ontrary to plaintiffs' contention, the court explicitly and conclusively determined the issue of the nearshore lakebed composition in plaintiffs' zone." Id. The court stated that "[p]laintiffs did not carry their burden of proof regarding the composition of the nearshore lakebed during the liability trial." Id. at 293.7 The court further stated that "[p]laintiffs' arguments fail to demonstrate any of the three circumstances which would support reconsideration: the occurrence of an intervening change in the controlling law, the availability of previously unavailable evidence, or the necessity of allowing the motion to prevent manifest injustice." Id. at 292 (citing Matthews v. United States, 73 Fed. Cl. 524, 526 (2006)). However, notwithstanding that "[p]laintiffs had the opportunity during trial to present evidence regarding the composition of the nearshore lakebed of plaintiffs' zone," id. at 297, the court held that "in order to avoid possible inefficiency and delay in resolving plaintiffs' claims, the court will accept additional evidence regarding the composition of the nearshore lakebed in plaintiffs' zone," id. at 298; see also infra Parts III.B.2-3 (discussing additional evidence of shoreline composition). The court directed the parties to suggest a schedule for further proceedings. See Order Granting Recons., 84 Fed. Cl. at 298.
After receiving separate status reports from the parties, the court set a schedule providing for discovery and the resolution of remaining legal issues. Nov. 12, 2008 Order, Dkt. No. 282, at 2-4; see also Aug. 11, 2009 Op. and Order, Banks v. United States (Law of Damages Op.), Dkt. No. 324, 88 Fed. Cl. 665, 669-70 (2009) (listing the motions and memoranda filed by the parties). The court then issued its Law of Damages Opinion, in which it stated that "[t]he court's legal rulings contained within this Opinion and Order clarify the law that will govern the damages phase of the case." 88 Fed. Cl. at 669 n.1.
The damages available to plaintiffs are calculated in accordance with the court's finding in the Liability Opinion that defendant is liable for the portion of 30% of the total erosion damages to each plaintiff's property not mitigated by defendant. 78 Fed. Cl. at 656-57. Plaintiffs' damages are to be divided into three time periods. See id. During each time period, defendant is liable for any portion of 30% the erosion damage to plaintiffs' properties not mitigated by defendant. See id. During the first time period, which runs from 1950 to 1970, defendant undertook no mitigation activity and is liable for damages for 30% of the erosion of each plaintiff's property.8 See id. at 656. During the second time period, which begins in 1970—when the Corps began its efforts to mitigate erosion caused by the jetties—defendant is liable "for any portion of 30% of each plaintiff's total erosion above the high water mark . . . that was not effectively mitigated by the Corps' nourishment." See id. During the third time period, from January 2000 forward, defendant is liable for damages for any portion of 30% "of all reasonably foreseeable future loss" not mitigated by defendant. Id.
Plaintiffs who have installed shore protection may recover the government's share of the cost to install and maintain the shore protection, Law of Damages Op., 88 Fed. Cl. at 685 & n.16, that is, 30% of any costs incurred from 1950-1970, and a portion of the costs incurred from and after 1970 equal to the portion of the erosion caused by the jetties and not mitigated by defendant, cf. Liability Op., 78 Fed. Cl. at 656.
Regarding defendant's liability for "all reasonably foreseeable future loss," id., the court stated that if further erosion of plaintiffs' properties is "`in fact preventable by prudent measures, the cost of that prevention is a proper basis for determining the damage,'" Law of Damages Op., 88 Fed. Cl. at 683 (quoting United States v. Dickinson, 331 U.S. 745, 751 (1947)). Relevant to whether the installation and maintenance of shore protection to prevent future erosion is a "prudent measure" is whether the shore protection costs more than the reasonably foreseeable erosion damage that would occur without it. See id. ("`If revetments are less expensive than the value of the land forecast to be lost, then the [g]overment may discharge its liability by bearing the cost of bank protection.'") (quoting Boling v. United States (Boling I), 41 Fed. Cl. 674, 694 (1998), vacated on other grounds (Boling II), 220 F.3d 1365 (Fed. Cir. 2000)).
"Although the general rule in takings cases is to award plaintiff the form of just compensation that will be least expensive for the government," the court, in its Law of Damages Opinion, found this general rule "inapplicable in the particular circumstances of the present case," in which the government is not the sole source of erosion to plaintiffs' properties. Id. The court stated that "[p]laintiffs may not be financially able to pay 70% of the cost to construct shore protection measures out of their own pockets, resulting in continued erosion of their property." Id. The court held that "as an alternative to seeking 30% of the cost of shore protection measures, plaintiffs may instead seek 30% of the cost of `reasonably foreseeable future loss' to their property, although this amount may result in greater cost to the government." Id. at 684.
The court held a trial of damages from April 18 through April 21, 2011 and from April 25 through April 28, 2011 in Niles, Michigan.9 See Tr. passim.10
After the court received the parties' post-trial briefing, the court directed the parties to file additional briefing addressing whether, in light of certain evidence presented at the trial of liability and certain findings of fact made in the court's Liability Opinion, the court has jurisdiction to hear plaintiffs' claims. See Order to Brief Jurisdiction, 99 Fed. Cl. at 625-26.
II. Legal Standards
A. Jurisdiction
Subject matter jurisdiction is a threshold matter that a court must determine at the outset of a case. See Steel Co., 523 U.S. at 94-95; PODS, Inc. v. Porta Stor, Inc., 484 F.3d 1359, 1365 (Fed. Cir. 2007). "Plaintiff[s] bear[] the burden of showing jurisdiction by a preponderance of the evidence." Taylor v. United States, 303 F.3d 1357, 1359 (Fed. Cir. 2002) (citing Thomson v. Gaskill, 315 U.S. 442, 446 (1942)). The court must consider jurisdictional issues at any point in a case that they arise. Steel Co., 523 U.S. at 93. The court is obligated to raise the issue of its own jurisdiction sua sponte "if a question thereto exists." Liberty Mut. Ins. Co. v. Wetzel, 424 U.S. 737, 740 (1976) (citing Mansfield, C. & L.M. Ry. Co. v. Swan, 111 U.S. 379 (1884)).
The court must accept as true all undisputed allegations of fact made by the non-moving party and draw all reasonable inferences from those facts in the non-moving party's favor. See Henke v. United States, 60 F.3d 795, 797 (Fed. Cir. 1995) (citing Scheuer v. Rhodes, 416 U.S. 232, 236-37 (1974), abrogated on other grounds by Harlow v. Fitzgerald, 457 U.S. 800 (1982)). However, "[w]hen a party challenges the jurisdictional facts alleged in the complaint, the court may consider relevant evidence outside the pleadings to resolve the factual dispute." Arakaki v. United States, 62 Fed. Cl. 244, 247 (2004) (citing Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed. Cir. 1988) and Indium Corp. of Am. v. Semi-Alloys, Inc., 781 F.2d 879, 884 (Fed. Cir. 1985)); 2 James Wm. Moore et al., Moore's Federal Practice § 12.30[3] (3d ed. 2004) ("[U]nlike a Rule 12(b)(6) dismissal, the court need not confine its evaluation to the face of the pleadings. . . ."). If a court determines that it does not have jurisdiction, it must dismiss the claim. See Rules of the United States Court of Federal Claims (RCFC) 12(h)(3).
"Every claim of which the United States Court of Federal Claims [Court of Federal Claims] has jurisdiction shall be barred unless the petition thereon is filed within six years after such claim first accrues." 28 U.S.C. § 2501 (2006). "It is well established that statutes of limitations for causes of action against the United States, being conditions on the waiver of sovereign immunity, are jurisdictional in nature." Martinez v. United States, 333 F.3d 1295, 1316 (Fed. Cir. 2003) (en banc) (citing, inter alia, Block v. North Dakota, 461 U.S. 273, 287 (1983)). Because the statute of limitations in this court is jurisdictional, id., plaintiffs have the burden of showing by a preponderance of the evidence that their claims were timely filed, see Taylor, 303 F.3d at 1359.
B. Accrual of Takings Claims
A takings claim must be filed "within six years after such claim first accrues." See 28 U.S.C. § 2501. Pursuant to the "stabilization doctrine," "The accrual of a takings claim where the government leaves the taking of property to a gradual physical process occurs when the situation has `stabilized.'" Accrual Op. II, 314 F.3d at 1308 (quoting Boling II, 220 F.3d at 1370). The stabilization doctrine was first stated in a case involving a taking of property by a gradual process of flooding, as follows:
[A]s there is nothing in reason, so there is nothing in legal doctrine, to preclude the law from meeting such a process by postponing suit until the situation becomes stabilized. An owner of land flooded by the Government would not unnaturally postpone bringing a suit against the Government for the flooding until the consequences of inundation have so manifested themselves that a final account may be struck.
Dickinson, 331 U.S. at 749. Ten years after Dickinson was decided, the United States Supreme Court (Supreme Court) clarified its holding, stating: "The expressly limited holding in Dickinson was that the statute of limitations did not bar an action under the Tucker Act for a taking by flooding when it was uncertain at what stage in the flooding operation the land had become appropriated to public use." United States v. Dow, 357 U.S. 17, 27 (1958).
Courts have recognized that interpreting the holding of Dickinson broadly would put it in "unending conflict with the statute of limitations." Gustine Land & Cattle Co. v. United States, 174 Ct. Cl. 556, 656 (1966)); see also Del. State Coll. v. Ricks, 449 U.S. 250, 258 (1980); Boling II, 220 F.3d at 1371 (stating the holding of Ricks to be that "the proper focus in a claim accrual analysis `is upon the time of the [defendant's] acts, not upon the time at which the consequences of the acts become most painful'" (internal quotation marks omitted) (alteration in original)); Columbia Basin Orchard v. United States, 116 Ct. Cl. 348, 357, 88 F.Supp. 738, 739 (1950) ("[W]e do not think the Supreme Court, in the Dickinson case, meant to hold that plaintiff was entitled to wait until any possibility of further damage had been removed.").
Stabilization of a claim for a taking by erosion occurs "when the erosion ha[s] substantially encroached the parcels at issue and the damages [are] reasonably foreseeable." Boling II, 220 F.3d at 1373. "`[S]tabilization occurs when it becomes clear that the gradual process set into motion by the government has effected a permanent taking, not when the process has ceased or when the entire extent of the damage is determined.'" Accrual Op. II, 314 F.3d at 1308 (quoting Boling II, 220 F.3d at 1370-71). The extent of the taking must be "reasonably foreseeable," Boling II, 220 F.3d at 1371, but the damage need not be "complete and fully calculable before the cause of action accrues," Fallini v. United States, 56 F.3d 1378, 1382 (Fed. Cir. 1995).
C. Damages in Partial Takings Cases
The Fifth Amendment of the United States Constitution provides that private property shall not "be taken for public use, without just compensation." U.S. Const. amend. V. Erosion of property due to government action is one type of physical injury that rises to the level of a taking. See, e.g., Boling II, 220 F.3d at 1370. "When the government fails properly to compensate private property owners for a taking, this court has jurisdiction to enforce the owners' right to just compensation." Liability Op., 78 Fed. Cl. at 614 (citing 28 U.S.C. § 1491; Applegate v. United States, 25 F.3d 1579, 1581 (Fed. Cir. 1994)). Such a claim is often referred to as a "inverse condemnation claim," see, e.g., Owen v. United States, 851 F.2d 1404, 1418 (Fed. Cir. 1988) (en banc), or as a "taking claim," see, e.g., id. at 1406.
"If only a portion of a single tract is taken the owner's compensation for that taking includes any element of value arising out of the relation of the part taken to the entire tract. Such damage is often, though somewhat loosely, spoken of as severance damage." United States v. Miller, 317 U.S. 369, 376 (1943) (footnote omitted); see also Hendler v. United States, 175 F.3d 1374, 1383 (Fed. Cir. 1999) ("In cases of a partial physical taking, as that here, just compensation under the takings clause of the Constitution includes `not only the market value of that part of the tract appropriated, but the damage to the remainder resulting from that taking, embracing . . . injury due to the use to which the part appropriated is to be devoted.'" (alteration in original) (quoting United States v. Grizzard, 219 U.S. 180, 183 (1911))).
Plaintiffs carry the burden of proving "that a taking has occurred justifying the payment of just compensation." Loesch v. United States, 227 Ct. Cl. 34, 44, 645 F.2d 905, 914 (1981). Plaintiffs also carry the burden of proving the amount of just compensation to which they are entitled for severance damage. Ga.-Pac. Corp. v. United States, 226 Ct. Cl. 95, 107, 640 F.2d 328, 336-37 (1980); Miller v. United States, 223 Ct. Cl. 352, 383-84, 620 F.2d 812, 828-29 (1980).
Plaintiffs' properties, being adjacent to the navigable waters of Lake Michigan, are subject to the navigational servitude held by the federal government, which servitude extends to the ordinary high water mark. See United States v. Cherokee Nation of Okla. (Cherokee), 480 U.S. 700, 704 (1987); United States v. Chicago, M., St. P. & P.R. Co., 312 U.S. 592, 595-97 (1941); Owen, 851 F.2d at 1408-10. When the government properly exercises its right to improve navigation in a manner that affects property within the boundaries of this servitude, "`the damage sustained does not result from taking property from riparian owners within the meaning of the Fifth Amendment but from the lawful exercise of a power to which the interests of riparian owners have always been subject.'" Cherokee, 480 U.S. at 704 (quoting United States v. Rands, 389 U.S. 121, 123 (1967)).
Accordingly, plaintiffs are not entitled to just compensation for materials removed from the littoral zone, see Owen, 851 F.2d at 1413, or eroded below and within the ordinary high water mark, see id. at 1412 (holding that the federal navigational servitude does not extend "to land located above or outside the bed of the stream as delineated by the . . . high-water mark at the time of construction"); see generally May 26, 2006 Op., Banks v. United States (OHWM Op.), Dkt. No. 141, 71 Fed. Cl. 501 (2006) (discussing the definition of the term "ordinary high water mark"); June 23, 2005 Op. and Order, Banks v. United States, Dkt. No. 87, 68 Fed. Cl. 524 (2005) (discussing the federal navigational servitude and the date on which the ordinary high water mark is to be measured).
D. The Law of the Case Doctrine and the Mandate Rule
The law of the case doctrine "posits that when a court decides upon a rule of law, that decision should continue to govern the same issues in subsequent stages in the same case. This rule of practice promotes the finality and efficiency of the judicial process by protecting against the agitation of settled issues." Christianson v. Colt Indus. Operating Corp., 486 U.S. 800, 815-816 (1988) (citations and internal quotation marks omitted); see also Gould, Inc. v. United States, 67 F.3d 925, 930 (Fed. Cir. 1995) ("The law of the case is a judicially created doctrine, the purposes of which are to prevent the relitigation of issues that have been decided and to ensure that trial courts follow the decisions of appellate courts." (internal quotation marks omitted)). The law of the case doctrine is applicable both to issues decided explicitly and to issues decided "by necessary implication." Laitram Corp. v. NEC Corp., 115 F.3d 947, 951 (Fed. Cir. 1997).
The Federal Circuit has explained, regarding its adherence to prior appellate decisions:
[T]he law of the case doctrine is a policy not a command even respecting a prior appellate decision in the case, and should be applied "as a matter of sound judicial practice, under which a court generally adheres to a decision in a prior appeal in the case unless one of three `exceptional circumstances' exists: the evidence on a subsequent trial was substantially different, controlling authority has since made a contrary decision of the law applicable to such issues, or the decision was clearly erroneous and would work a manifest injustice."
Mendenhall v. Barber-Greene Co., 26 F.3d 1573, 1582 (Fed. Cir. 1994) (quoting Cent. Soya Co. v. Geo. A. Hormel & Co., 723 F.2d 1573, 1580 (Fed. Cir. 1983)).
"`[T]he law of the case doctrine is not applicable to issues neither presented nor decided in a former proceeding in the case.'" Halpern v. Principi, 384 F.3d 1297, 1301 (Fed. Cir. 2004) (quoting Stearns v. Beckman Instruments, Inc., 737 F.2d 1565, 1568 (Fed. Cir. 1984)).
"The mandate rule requires that the [trial] court follow an appellate decree as the law of the case." Cardiac Pacemakers, Inc. v. St. Jude Med., Inc., 576 F.3d 1348, 1356 (Fed. Cir. 2009) (citing Sibbald v. United States, 37 U.S. (12 Pet.) 488, 492 (1838)); accord In re Sanford Fork & Tool Co., 160 U.S. 247, 255 (1895). "The mandate rule provides that `issues actually decided [on appeal]—those within the scope of the judgment appealed from, minus those explicitly reserved or remanded by the court—are foreclosed from further consideration.'" Amado v. Microsoft Corp., 517 F.3d 1353, 1360 (Fed. Cir. 2008) (quoting Engel Indus., Inc. v. Lockformer Co., 166 F.3d 1379, 1383 (Fed. Cir. 1999)). "Unless remanded by [the appellate] court, all issues within the scope of the appealed judgment are deemed incorporated within the mandate and thus are precluded from further adjudication." Engel Indus., 166 F.3d at 1383.
Much like the law of the case doctrine, which "is not applicable to issues neither presented nor decided in a former proceeding," Halpern, 384 F.3d at 1301, the mandate rule provides that the trial court "may act on matters left open by the mandate," Laitram, 115 F.3d at 951 (internal quotation marks omitted); see, e.g., Exxon Chem. Patents, Inc. v. Lubrizol Corp. (Exxon), 137 F.3d 1475, 1484 (Fed. Cir. 1998) (holding that the scope of the judgment appealed from, limited to literal infringement, did not preclude adjudication of infringement by the doctrine of equivalents). "Interpretation of an appellate mandate entails more than examining the language of the court's judgment in a vacuum." Exxon, 137 F.3d at 1484. "The scope of the issues presented . . . on appeal must be measured by the scope of the judgment appealed from, not by the arguments advanced by the appellant." Engel Indus., 166 F.3d at 1382 (citations omitted). The Federal Circuit has cautioned that, "both the letter and the spirit of the mandate must be considered." Id. at 1383.
III. Discussion
A. Jurisdiction
In their original complaint,11 plaintiffs alleged "that defendant effected a gradual taking of their shorefront property through the construction and maintenance of `a series of 15 jetties along 200 miles of the eastern coast of Lake Michigan for over 100 years.'" Accrual Op. I, 49 Fed. Cl. at 810 (quoting Compl. ¶ 26, Banks v. United States, No. 99-445 L (Fed. Cl. filed July 9, 1999), Dkt. No. 1). Plaintiffs narrowed their claims in the individual complaints they filed after the court denied class certification, focusing on the effect of the jetties at St. Joseph Harbor. Compl. ¶¶ 4-7. The jetties at St. Joseph Harbor were originally built in the 1830s, and were lengthened several times, reaching their current length in 1903. Liability Op., 78 Fed. Cl. at 604 (citations omitted).
Although the jetties had been in place at their current length for nearly a century—a period of time longer than the six-year limitations period applicable takings claims, see 28 U.S.C. § 2501—plaintiffs' complaints alleged that the accelerated erosion of their properties was caused not by construction of the jetties, but by a maintenance activity that took place more recently. Specifically, plaintiffs alleged that the jetties "continued to exist without harmful interference to the natural littoral flow of sand and river sediment until the [Corps] gradually installed sand-tight steel sheet piling during the period of 1950 to 1989," which installation has "alter[ed] the supply of sand to the lake bed and subaerial visible beach in front of the plaintiffs' property." Compl. ¶¶ 6-7. After plaintiffs filed their individual complaints, defendant filed a motion to dismiss on jurisdictional grounds, arguing that "the takings causes of action accrued, at the latest, in 1989," when the government completed its encasement of the jetties in the steel sheet piling. Accrual Op. I, 49 Fed. Cl. at 811.
The briefing filed by defendant in support of its motion to dismiss and the opinions filed by the court and by the Federal Circuit make it clear that defendant, the court and the Federal Circuit presumed the truth of plaintiffs' allegation that encasing the jetties in steel sheet piling made them impermeable to sand, interfering with the littoral flow of sand and damaging plaintiffs' properties. Defendant stated in its motion that it "[a]ccepted as true for the sake of defendant's motion" that the steel sheet piling "prevents the drift of sand from passing through the jetties and proceeding south along the eastern shore toward plaintiffs' lands." Mot. to Dismiss at 6, Banks v. United States, 49 Fed. Cl. 806 (2001) (No. 99-445 L), Dkt. No. 64 (Mot. to Dismiss).
In its opinion addressing defendant's motion to dismiss, the court noted that "[w]hen considering a motion to dismiss, the court must presume that well pleaded factual allegations in the complaint are true." Accrual Op. I, 49 Fed. Cl. at 808 (citing, inter alia, Miree v. DeKalb Cnty., 43 U.S. 25, 27 n.2 (1977)). Quoting the allegations in the Banks plaintiffs' complaint, the court stated, "Plaintiffs claim that the jetties did not cause `harmful interference to the natural littoral flow of sand and river sediment until the Corps gradually installed sand-tight steel sheet piling during the period of 1950 to 1989.'" Id. at 808 (quoting Compl. ¶ 6); see also id. at 824 ("Plaintiffs allege in their complaints, which the court construes in favor of the complainants, see Scheuer, 416 U.S. at 236, that the Corps completed the installation of `sand-tight steel sheet piling' in 1989." (quoting Compl. ¶ 6)).
Applying Applegate, the court considered and rejected plaintiffs' argument that, after the installation of the steel sheet piling was completed in 1989, the government delayed the accrual of plaintiffs' claims by promising to mitigate the erosion caused by the jetties. Accrual Op. I, 49 Fed. Cl. at 812-13, 822-23. In Applegate, the Federal Circuit held that the plaintiffs' claims for a taking by erosion did not accrue while promises by the government to mitigate the damage made the plaintiffs "justifiably uncertain" whether a permanent taking had occurred. Applegate, 25 F.3d at 1583-84; see also infra Part III.A.1 (applying Applegate to the facts of this case).
Examining the evidence cited by the parties, the court found that "the evidence here does not show that the Corps' sand transfer program constituted a promise on which plaintiffs could rely to postpone the filing of their suits, as contemplated by the Applegate case." Accrual Op. I, 49 Fed. Cl. at 823. The court therefore found that "the time for filing suit expired in 1995," six years after installation of the steel sheet piling was completed. Id. at 825. Because plaintiffs did not file suit until 1999, the court granted defendant's motion to dismiss. Id. at 825-26.
The Federal Circuit reversed, finding that after the steel sheet piling was installed, mitigation efforts that the government had begun in 1970 created uncertainty as to whether any erosion damage caused by the jetties was "permanent and irreversible." Accrual Op. II, 314 F.3d at 1309-10. The Federal Circuit found that plaintiffs' claims accrued with the publication of three Corps reports that concluded that the mitigation efforts were ineffective. See id. On remand, the court determined that, because the last of these reports was published no earlier than January of 2000, plaintiffs' claims accrued in January of 2000. May 3, 2007 Op., Banks v. United States, Dkt. No. 200, 76 Fed. Cl. 686, 696 (2007).
After conducting a trial of liability, the court found that, contrary to the allegations in plaintiffs' complaints—allegations that the court had presumed to be true when considering defendant's motion to dismiss, see Accrual Op. I, 49 Fed. Cl. at 808—the jetties were impermeable to sand before they were encased in steel sheet piling, Liability Op., 78 Fed. Cl. at 636 (stating that "plaintiffs' own expert witness testified that the piers were impermeable even prior to their encasement in steel"). The court further found that "plaintiffs have failed to prove that the piers were ever permeable." Liability Op., 78 Fed. Cl. at 635.
The implication of the court's finding is that the installation of steel sheet piling had not altered the supply of littoral sand to plaintiffs' properties as plaintiffs had alleged, see Compl. ¶¶ 6-7, thereby exacerbating the erosion of plaintiffs' properties. The most recent government action that could have effected a taking by increasing the erosion of plaintiffs' properties was not the installation of steel sheet piling, a process that ended in 1989, but rather the extension of the jetties, a process that ended in 1903. See Liability Op., 78 Fed. Cl. at 604.
At the time of the court's Liability Opinion, neither the court nor the parties addressed the impact of the court's finding on the timeliness of plaintiffs' claims. See Liability Op., 78 Fed. Cl. passim. However, after the trial of damages, the court directed the parties to file briefing on the issue. See Order to Brief Jurisdiction, 99 Fed. Cl. at 626. The court now considers, in light of the extensive factual record developed at two trials, whether plaintiffs' claims were timely filed, given that the jetties were impermeable to sand before they were encased in steel sheet piling. See Steel Co., 523 U.S. at 93 (noting that the court must consider jurisdictional issues at any point in a case that they arise).
To determine whether plaintiffs' claims are timely, the court must address four questions. First, working backward from the date of filing, the court must determine the period of time during which plaintiffs' claims could not have accrued, under Applegate, because the government's promises and efforts to mitigate erosion caused by the jetties created justifiable uncertainty about the permanence of any erosion damage. Second, working forward from 1903, the year that the jetties reached their final length, the court must determine whether the situation stabilized sufficiently for plaintiffs' claims to accrue and for the statute of limitations to run before the government's promises and efforts to mitigate erosion made the permanence of any damage uncertain. Third, the court must consider plaintiffs' argument that their claims did not accrue until certain adverse precedent was overruled by the Federal Circuit, sitting en banc. Finally, the court must consider plaintiffs' argument that the law of the case doctrine prohibits the court from finding that it lacks jurisdiction over plaintiffs' claims.
1. Justifiable Uncertainty Caused by the Corps' Promises of Mitigation
The court first considers the period of time during which plaintiffs' claims could not have accrued because of the government's promises and efforts to mitigate erosion caused by the jetties. The Federal Circuit in Applegate "analyzed the stabilization doctrine set forth in Dickinson as it applied to situations in which the government was attempting to mitigate actions that would otherwise constitute a permanent taking." Accrual Op. II, 314 F.3d at 1308. In Applegate, the government repeatedly promised to build a sand transfer plant to mitigate erosion of the plaintiffs' properties caused by the government's construction and maintenance of a deep water harbor. See Applegate, 25 F.3d at 1580. The Federal Circuit determined that "[t]he gradual character of the natural erosion process set in motion by the Corps, compounded by the Government's promises of a sand transfer plant, have indeed made accrual of the landowner's claim uncertain." Id. at 1582.
When this court addressed defendant's motion to dismiss, the court found Applegate inapplicable, Accrual Op. I, 49 Fed. Cl. at 818-23; but the Federal Circuit disagreed and held that this court had "misread Applegate as requiring the presence of a legally binding promise or duty or a matter requiring a congressional appropriation," Accrual Op. II, 314 F.3d at 1309. This court noted that, according to the rate of erosion alleged in plaintiffs' complaints to be caused by the jetties, plaintiffs lost almost eighty feet of shoreline to erosion between 1950 and 1989, an amount "sufficient to put plaintiffs on inquiry notice of their potential takings claims." Accrual Op. I, 49 Fed. Cl. at 825. The court granted defendant's motion, finding that "plaintiffs' takings claims accrued no later than 1989 and the time for filing suit expired in 1995." Id. at 825-26.
The Federal Circuit reversed, stating:
In Applegate, the mere promises of a sand transfer plant, held out by the Corps and repeatedly renewed but never implemented, indicated that "the landowners did not know when or if their land would be permanently destroyed." Here, even greater uncertainty was created by the Corps' mitigation plan. While the Corps in Applegate made promises of a mitigating sand transfer plant, the Corps in this case actually performed its mitigation activities for several years before the filing of this action.
Accrual Op. II, 314 F.3d at 1309-10 (quoting Applegate, 25 F.3d at 1582). The Federal Circuit noted that the government's mitigation activities began in 1970, delaying accrual of plaintiffs' claims until the publication of three reports by the Corps, which determined that the mitigation program had not been effective and "collectively indicated that erosion was permanent and irreversible." Id. at 1310.
The Federal Circuit did not discuss whether the government's promises to mitigate erosion created justifiable uncertainty before the Corps began mitigation efforts in 1970. See id. passim. However, beginning in 1958, "[t]he Corps released a series of reports . . . over several decades describing the erosion caused south of St. Joseph Harbor by the jetties, outlining a plan to mitigate the erosion attributable to the jetties, and evaluating the effectiveness of the mitigation program that was eventually implemented." Liability Op., 78 Fed. Cl. at 612.
The first of these reports, a study released in 1958 (1958 Study), was published before mitigation efforts began. See id. at 604, 612. Plaintiffs contend that the 1958 Study delayed the accrual of their claims, pursuant to Applegate, because the 1958 Study "promises that the government will attempt to mitigate the loss." Pls.' Jur. Br. 16-18. The 1958 Study is a "beach erosion control study," transmitted by the Corps to the Speaker of the United States House of Representatives. Pls.' Ex. (PX) 132 (1958 Study) v. It assessed erosion in a "study area" including plaintiffs' zone that is "about 32 miles in length from the north city limit of Benton Harbor to the Michigan-Indiana State line." Id. at 3. The study recommended building a sand berm to protect a portion of the shoreline north of plaintiffs' zone. See id. at 24-25. It calculated the economic benefits of extending the sand berm south to the southern limit of the village of Shoreham, id. at 44, which is in plaintiffs' zone. The 1958 Study determined, however, that "[t]his downcoast reach is entirely privately owned, would have no public benefits to make it eligible for Federal aid," and would cost more to protect than the value of extending the sand berm. Id. The study noted, however, that even without including this area in the project, "this reach and adjacent shores to the south would receive substantial benefits of shore stabilization due to restoration of normal littoral drift." Id.
Plaintiffs' argument is that the 1958 Study created justifiable uncertainty about the permanence and extent of the taking of their property, when viewed in the light of Applegate. See Pls.' Jur. Br. 16-18. The 1958 Study proposes a shore protection project that, while not intended to protect plaintiffs' properties directly, was expected to benefit them by "restor[ing] normal littoral drift." PX 132 (1958 Study) 44. The sand transfer plant promised by the Corps in Applegate, unlike the sand berm proposed here, was intended directly to address the erosion of the plaintiffs' properties. See Applegate, 25 F.3d at 1580. However, it was uncertainty about the permanence of the taking, rather than the government's intentions in undertaking shore protection efforts, that delayed accrual of the plaintiffs' claims in Applegate. See id. at 1582 ("With plans for a sand transfer plant pending, the landowners had no way to determine the extent, if any, of the permanent physical occupation."); Boling II, 220 F.3d at 1372 ("[T]he critical element that delayed stabilization in Applegate [is] the justifiable uncertainty about the permanency of the taking.").
Even accepting plaintiffs' contention that the justifiable uncertainty created by the Corps began, not with the commencement of mitigation efforts in 1970, but with publication of the 1958 Study,12 for plaintiffs' claims to be timely, the situation must not have stabilized, Accrual Op. II, 314 F.3d at 1308, before 1952, six years before the possible creation of justifiable uncertainty by the publication of the 1958 Study.13
2. Claim Accrual and Stabilization: the Impermeability of the Jetties is the Law of the Case
"The accrual of a takings claim where the government leaves the taking of property to a gradual physical process occurs when the situation has `stabilized.'" Id. (quoting Boling II, 220 F.3d at 1370). Stabilization of claims for a taking by erosion occurs "when the erosion ha[s] substantially encroached the parcels at issue and the damages [are] reasonably foreseeable." Boling II, 220 F.3d at 1373. "`[S]tabilization occurs when it becomes clear that the gradual process set into motion by the government has effected a permanent taking, not when the process has ceased or when the entire extent of the damage is determined.'" Accrual Op. II, 314 F.3d at 1308 (alteration in original) (quoting Boling II, 220 F.3d at 1370-71).
Defendant contends that plaintiffs' claims stabilized with the Corps' publication of the 1958 Study, which "acknowledged that the construction and maintenance of the St. Joseph Harbor was interfering with the littoral flow to properties south of the jetties and advised that the United States did not intend to take action to protect that shoreline." Def.'s Jur. Br. 12.
The court, in its Liability Opinion, found the 1958 Study to be highly persuasive evidence that plaintiffs' properties are, and were understood to be, within the zone of influence of the jetties. Liability Op., 78 Fed. Cl. at 621 ("Although not specifically pointed out by plaintiffs, the court views the most persuasive evidence to be contained in the 1958 Study, an admission by defendant."). Although a number of Corps reports were introduced as exhibits and were before the court, id. at 612, the court found the 1958 Study to be "the most persuasive evidence" of whether and for how long plaintiffs' properties have been considered to be within the jetties' zone of influence, id. at 621. The court concluded that "plaintiffs' properties have been considered in the zone of influence of the jetties at least as far back as the 1950s, even if the specific impact of the jetties was not quantified until later." Id.
It is therefore the law of this case that plaintiffs' properties were considered to be within the zone of influence of the jetties at least as far back as the 1950s. It is also the law of the case that the jetties have caused 30% of the erosion in plaintiffs' zone since 1950. See id. at 654-57. In its Liability Opinion, the court agreed with plaintiffs' argument that "[u]ntil this litigation, the Army Corps had repeatedly endorsed the fact that the structures at St. Joseph had interrupted, dredged or diverted" a volume of sand equal to "30% of the total annual loss to the littoral zone," id. at 636 (quoting Pls.' Opening Post Trial Br., Dkt. No. 241, at 30-31), finding that the Corps had maintained, "as an admission, that the piers caused approximately 30% of the erosion to the south of the harbor," id. The court therefore found, based on plaintiffs' argument that the Corps had admitted the percentage of the erosion in plaintiffs' zone caused by the jetties,14 see id., that the government is liable for the portion of 30% of the erosion in plaintiffs' zone since 1950 not mitigated by the government, see id. at 654-57.
Plaintiffs do not argue that any exception to the law of the case doctrine applies here. See Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim. Plaintiffs do not argue that the jetties did not begin to impact their properties until later than 1950. See Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim. Plaintiffs, in fact, argue that the jetties caused significantly more than 30% of the erosion in plaintiffs' zone since 1950. See infra Part III.C.1 (discussing plaintiffs' arguments that the jetties have caused 60-70% of the erosion in plaintiffs' zone since 1950).
It therefore remains the law of the case—based on an argument made by plaintiffs and found persuasive by the court, see Liability Op., 78 Fed. Cl. at 636—that the zone of influence of the jetties reached plaintiffs no later than 1950, causing 30% of the erosion of plaintiffs' properties for no fewer than two years before 1952. Moreover, for the reasons stated below, it is the view of the court that, based upon the documentation of erosion in plaintiffs' zone contained in the 1958 Study and upon the conclusions reached by defendant's expert, Dr. Nairn, the jetties began to increase the erosion of plaintiffs' properties before 1950 and that stabilization occurred significantly earlier than 1952, more than six years before plaintiffs argue, see Pls.' Jur. Br. 16-18, that the government began to create justifiable uncertainty by publishing the 1958 Study.15
Defendant is correct that the Corps acknowledged in the 1958 Study that the jetties had long caused erosion in plaintiffs' zone.16 The 1958 Study notes that "[t]he navigation channel at St. Joseph Harbor is dredged annually to maintain project depth, and for this reason little or no beach building material is believed to pass the harbor entrance and reach the downdrift shore." PX 132 (1958 Study) 4; see also id. at 20-21 (describing the quantity of sand blocked by the jetties since 1907 and the amount of sediment dredged from the navigation channel).
The 1958 Study concluded that, if the shore protection recommended in the study were constructed, an area continuing south "to the south limit of the village of Shoreham" and the "adjacent shores to the south would receive substantial benefits of shore stabilization due to restoration of normal littoral drift." PX 132 (1958 Study) 44. Implicit in the statement that the project would restore "normal littoral drift," id., is the understanding that normal littoral drift had been disrupted. Plaintiffs acknowledge that this statement in the 1958 Study refers to a segment of shoreline that includes their properties. See Pls.' Br. 18 (stating that "the 1958 [Study] indicates that the properties in the [p]laintiffs' zone would benefit from the mitigation program").
The 1958 Study also documented the greater rate of erosion south of the jetties since their construction:17
The shores for about a mile north of the harbor structures and 1,200 feet south thereof have been advancing lakeward since the entrance structures were built. South of the latter accreting area, however, erosion of the bluffs has been severe, causing the loss of, or necessitating the movement of, a number of valuable residences and threatening a railroad and public highway. Numerous protective structures have been erected but have exhibited only moderate effectiveness.18
PX 132 (1958 Study) 3. The 1958 Study observed that, in the area up to 500 feet north of the jetties, "the shoreline has been accreting at a rate of approximately 4 feet per year since 1830," id. at 10, a rate of growth that, in the court's view, would have been apparent to landowners.
In addition to the disruption of normal littoral drift in plaintiffs' zone and the increase in erosion, the 1958 Study also documented the proliferation of shore protection structures south of the jetties after their construction, a trend that is consistent with— although it does not independently establish—an increased rate of erosion south of the jetties after their construction and lengthening. See id. at 18, 20. Describing the area northward from the jetties to the northernmost edge of Benton Harbor, the 1958 Study states:
Beach erosion in this reach of shoreline has been limited to the extreme northern end near the Benton Harbor city limits. No extensive beach protective structures have been built in this reach with protective efforts limited to the placement of an occasional steel barrel filled with sand. The remaining portion of this shoreline has been accreting.
Id. at 18. In contrast, in the area extending southward from the edge of the shore protection adjacent to a highway to the southern edge of the village of Shoreham, shore protection was very common: "Approximately 22 individual structures built by property owners are in existence and range from typical groin construction to steel sheet-pile seawalls and revetments. The protection provided by a large portion of this work is limited, and erosion is continuing in those intermediate areas not protected." Id. at 20. Further to the south, where the southernmost properties owned by plaintiffs are located, there were few shore protection structures, but the land was largely undeveloped, see id., making them less necessary.
The disruption of normal littoral drift and the increased erosion south of the jetties documented in the 1958 Study are consistent with the conclusion reached by Dr. Nairn in his 2006 expert report that the jetties have long contributed to erosion south of the harbor. See Def.'s Ex. (DX) 1 (Nairn Report) 4-151 to 4-152. Dr. Nairn, using a sediment budget19 and several types of numerical modeling, quantified the impact of the jetties on erosion in the an area of shoreline beginning at the jetties and continuing for ten miles to the south. See infra Parts III.B-C (explaining and finding persuasive Dr. Nairn's use of sediment budgets and numerical modeling to predict rates of erosion and the effectiveness of mitigation). Dr. Nairn determined that, during the period from 1836 to 1875, when the jetties were shorter, erosion in the study area continued to fall "within the range of pre-harbor erosion estimates."20 DX 1 (Nairn Report) 4-151. Between 1876 and 1903, as the Corps continued to lengthen the jetties, the rate of erosion in the study area did not increase and, in fact, decreased slightly from pre-harbor levels. See id. at 4-152.
The impact of the jetties began to be felt when they reached their final length. In terms of volume, Dr. Nairn calculates that between 1904 and 1969, the year before the Corps began its mitigation efforts, the jetties were responsible for 25% of all erosion in the study area. See id. at 4-158. This impact would have been greatest in the northern part of the study area and would not be the same for each property.21 See id. at 4-159.
In their post-trial briefing addressing the measure of their damages, plaintiffs argue that Dr. Nairn's approach significantly underestimates the impact of the jetties on their properties since 1950.22 See infra Part III.C.1. Plaintiffs contend that:
the United States has (1) substantially undercounted the volume of sand being blocked by the jetties, as well as the jetties['] percentage contribution to the erosion in the [p]laintiffs' zone; and (2) substantially overcounted the volume of sand block[ed] by the C&O and MDOT revetments, so that the jetties['] percentage contribution to the erosion in the [p]laintiffs' zone is well in excess of 30% and is fairly calculated as being between 60% and 70%.
Pls.' Br. 23; see also Tr. 19:7-24 (plaintiffs' counsel) (stating, in his opening argument, that Dr. Mackey's testimony about the flaws in Dr. Nairn's methods will demonstrate that the jetties have caused 60 to 70 percent of the erosion in plaintiffs' zone since 1950). As described below, the court finds plaintiffs' criticisms of Dr. Nairn's erosion analysis unpersuasive. See infra Parts III.B-C. However, the court finds plaintiffs' argument that the jetties caused 60-70% of the erosion in plaintiffs' zone after 1950 inconsistent—absent evidence cited by plaintiffs to explain the sudden change—with a finding that the jetties did not cause significant and noticeable erosion in plaintiffs' zone prior to 1950.
Because of the interruption of littoral drift and the erosion documented in the 1958 Study and because of Dr. Nairn's calculations of the jetties' impact on erosion, which plaintiffs fail persuasively to contradict (suggesting instead that Dr. Nairn has underestimated the amount of erosion caused by the jetties), the court finds that the erosion caused by the jetties in plaintiffs' zone was a longstanding problem by 1952, beginning as early as 1903.23
To determine the point at which plaintiffs' claims stabilized, the court must determine the point at which this additional erosion "substantially encroached the parcels at issue and the damages were reasonably foreseeable." Boling II, 220 F.3d at 1373. The Federal Circuit has advised that, in making this determination, a court must "take into account the uncertainties of the terrain, the difficulty in determining the location of the government's easement, and the irregular progress of erosion." Id. Plaintiffs are correct that, to some extent, the exact rate of erosion—and therefore changes in the rate of erosion—would have been obscured by natural variations, such as changes in lake level, barometric pressure, and wind direction, as well as "the dynamic nature of the [p]laintiffs' shoreline." Pls.' Jur. Br. 13; see also supra Part I (describing variations in beach width caused by cross-shore sand transport and changes in lake levels). Plaintiffs contend that fluctuations in lake levels of up to 1.8 feet occur with annual frequency and that, as numerous plaintiffs testified at trial, beaches "`come and go' as lake levels changed and storms occurred." Pls.' Jur. Br. 13.
However, the erosion relevant to plaintiffs' claims, that is, the erosion of property above the ordinary high water mark, can be gauged more clearly because the erosion of such property does not vary as widely as does the profile of beaches below the ordinary high water mark with changes in lake depth, barometric pressure, and wind direction. As described below in Part III.D.1, the court finds persuasive a delineation of the high water mark that lies, on properties characterized by bluffs, at the toe of the bluff, and, on properties characterized by dunes, at the edge of permanent vegetation. Although the evidence presented in this case establishes that beaches are somewhat ephemeral, see infra Part III.D.3.b.i, the ordinary high water mark is defined by these, more permanent, features, see infra Part III.D.1; Tr. 2343:18-22 (Nairn) (defining the ordinary high water mark for bluff properties as the toe of the bluff and distinguishing permanent vegetation from "ephemeral vegetation," such as marine grass and dune grass); Tr. 2363:11-13 (Nairn) (stating that the ordinary high water mark, when defined by bluffs, normally moves only in one direction). Plaintiffs cite no evidence that bluffs and permanent vegetation "come and go" as rapidly as beaches do. See Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim. The rate of erosion above the ordinary high water mark, therefore, can be determined with some confidence.
The location of the ordinary high water mark, because it is characterized by observable features, can be identified by landowners such as plaintiffs. See Loesch, 227 Ct. Cl. at 61, 645 F.2d at 925 (stating that "the OHWM on a riverbank is a physical fact, subject to determination by inspection of the riverbank" (citation omitted) (citing Kelley's Creek & Nw. R.R. Co. v. United States, 100 Ct. Cl. 396, 406 (1943) ("The high watermark is not to be determined by arithmetical calculation; it is a physical fact to be determined by inspection of the river bank. It is the line where the water stands sufficiently long to destroy vegetation below it.")). "It is not unreasonable to expect that plaintiffs, as riparian landowners, were familiar to some degree with their [shoreline]." Id. at 61, 645 F.2d at 925. It is therefore not unreasonable to expect that plaintiffs, as well as the prior owners of their properties, would have observed where the ordinary high water mark lay on their properties and would have observed its changing location over time.
Any uncertainty would have been further reduced by the significant span of time— forty-nine years—between the year 1903, when the jetties reached their final length, and 1952, the date after which plaintiffs' claims must have accrued, under plaintiffs' reading of Applegate, see supra Part III.A.1, for the uncertainty created by the 1958 Study to render plaintiffs' claims timely. Although bluffs and permanent vegetation would not be expected to "come and go" as beaches do, erosion is often an irregular process, accelerating at times of high lake levels and during storms. See infra Part III.D.4.b. The rate of erosion, and therefore the effect of the jetties, would have become clearer with the passage of time.24
During the forty-nine years between 1903, when the jetties reached their final length, and 1952, the jetties were responsible for 25% of the material eroded from Dr. Nairn's study area, the ten mile segment of shoreline south of the jetties. See DX 1 (Nairn Report) 4-158. Neither party cites—and the court does not find in the record—estimates of how many additional feet of erosion occurred in plaintiffs' zone during this period as a result of the jetties. See supra note 19 (discussing Dr. Nairn's analysis of bluff recession rates). However, a study published in 1976 determined the rate of bluff recession, averaged across all of Berrien County over 120 years to be .6 meters, or two feet, per year. See DX 40 (1997 Report) 3. Given this rate of erosion and the passage of forty-nine years between 1903 an 1952, the court concludes that the additional erosion caused by the jetties was not limited to "mere inches." Boling II, 220 F.3d at 1372.
The well-documented additional erosion caused by the lengthened jetties would have made it clear to a reasonable landowner well before 1952 that the government had effected a permanent taking. See PX 132 (1958 Study) 3-4, 10-12, 17-18, 20-21; DX 1 (Nairn Report) 4-152, 4-158. This is particularly true given the lower rates of erosion (and the accretion of sand) occurring further north since construction of the jetties, and given the diminishing impact of the jetties on properties further south from the jetties. At this time, the extent of the damage would have been reasonably foreseeable from the increased rate at which erosion had occurred for forty-nine years.
Plaintiffs assert that "[e]ven if, for the sake of argument, the 1958 [Study] placed [p]laintiffs on inquiry notice that the harbor jetties caused some degree of erosion, they were clearly not on notice that the jetties had caused erosion to their specific properties, much less a permanent loss." Pls.' Jur. Br. 14-15. Plaintiffs are correct that the 1958 Study did not discuss their properties individually. See PX 132 (1958 Study) passim. Because the 1958 Study was not prepared for purposes of this litigation, it would not be expected to discuss plaintiffs' properties individually, or to measure separately the amount of erosion caused by the jetties in plaintiffs' zone.
However, "plaintiff[s] bear[] the burden of showing jurisdiction by a preponderance of the evidence." Taylor, 303 F.3d at 1359 (citing Thomson, 315 U.S. at 446). It is not enough for plaintiffs to argue in briefing that the general pattern of erosion that followed the lengthening of the jetties in 1903 might not have affected certain of their individual properties. Because plaintiffs have the burden of showing the court's jurisdiction, they must cite evidence that erosion caused by the jetties had not reached their properties when the 1958 Study, PX 132 (1958 Study) 3-4, 10-12, 17-18, 20-21, and Dr. Nairn's analysis, see DX 1 (Nairn Report) 4-152, 4-158, indicate that it reached the rest of the area. Apart from their interpretation of the 1958 Study, plaintiffs have cited no such evidence, see Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim, and have failed to carry their burden of proof.
Plaintiffs argue that "the effect of the harbor jetties on the lakebed and adjoining shoreline to the south was a very gradual process that occurred over decades of time." Pls.' Jur. Br. 14. Citing a single page of a report published by the Corps in 1997, co-authored by defendant's expert witness, Dr. Nairn (1997 Report), plaintiffs argue that as late as 1997 it was not understood that the harbor jetties caused increased erosion in plaintiffs' zone.25 Id. The implication of plaintiffs' argument is that their claims stabilized no earlier than 1997 because it was not understood at that time26 that the jetties were causing erosion in plaintiffs' zone.27
The only relevant sentence on the page of the 1997 Report cited by plaintiffs describes an area approximately 8.2 kilometers south of the jetties, which, "up until recently, may not have been significantly influenced by the harbor jetties." DX 40 (1997 Report) 58.28 The page of the 1997 Report cited by plaintiffs does not explain why the report's authors believed that the area may not have been significantly influenced by the jetties or what they meant by "until recently." See id. Neither does the referenced page of the 1997 Report explain the term "significantly influenced."29 See id. Other portions of the 1997 Report suggest that its authors assumed that the area was not affected by the jetties. See, e.g., id. at 25, 27 (listing among the authors' "assumptions about the nearshore conditions and profile evolution prior to the comparison of the data" that this area was "not influenced by reduced sediment supply from the north—[and is] representative of natural conditions or background erosion rate"); id. at 79 (assuming that, because the rate of erosion in this area was similar to the rate of erosion north of the jetties, this area is not affected by the jetties). Plaintiffs cite no page of the 1997 Report on which the authors state that they made a detailed study of the effect of the jetties on this portion of plaintiffs' zone. See Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim. Rather, the court has found that the 1997 Report was largely based on data collected north of plaintiffs' zone. Liability Op., 78 Fed. Cl. at 624-25.
The court does not view an assumption in the single sentence cited by plaintiffs of a report published in 1997 as establishing that it was not known that the jetties caused erosion in plaintiffs' zone until at least 1997. Because there was evidence apparent to an ordinary landowner that the jetties accelerated erosion, plaintiffs were not entitled to postpone the filing of their claims until they received scientific confirmation or a technical explanation of the subsurface processes causing the harm. See Accrual Op. I, 49 Fed. Cl. at 820 (quoting Fallini, 56 F.3d at 1380).
The court therefore finds that, significantly earlier than 1952, the erosion caused by the jetties "had substantially encroached the parcels at issue and the damages were reasonably foreseeable." Boling II, 220 F.3d at 1373. Because the situation stabilized prior to 1952, the court finds that plaintiffs' claims accrued prior to 1952, see id., and that, by waiting to file a complaint until 1999, plaintiffs failed to file their claims within the six-year limitations period set out in 28 U.S.C. § 2501.
3. The Accrual Suspension Rule
In their opening brief on jurisdiction, plaintiffs argue that their claims "could not have accrued, as a matter of law, prior to the issuance of the Owen decision" because "[p]rior to Owen[,] it was settled federal law that a property owner could not recover for a taking of its fast land absent a physical invasion."30 Pls.' Jur. Br. 21. According to plaintiffs, "[p]rior to Owen[], federal cases uniformly held that erosion damage was not a taking where the damage from the federal project was caused, not by a rise in water levels, but as a consequence of some other interference with the natural water flow." Id. Plaintiffs contend that "to argue that [p]laintiffs['] takings claim was barred before they even had a recognized claim would be patently unfair." Id. at 22.
Defendant, interpreting plaintiffs' argument as an argument for the application of equitable tolling, correctly notes that equitable tolling is not available in actions brought under the Tucker Act. Def.'s Jur. Resp. 13-14 (citations omitted); see John R. Sand & Gravel Co. v. United States, 552 U.S. 130, 133-34 (2008); Young v. United States, 529 F.3d 1380, 1384 (Fed. Cir. 2008) (stating the holding of John R. Sand & Gravel to be that "the statute of limitations applicable to Tucker Act claims, 28 U.S.C. § 2501, is jurisdictional and not susceptible to equitable tolling"). Equitable tolling extends the statute of limitations "`where the claimant has actively pursued his judicial remedies by filing a defective pleading during the statutory period, or where the complainant has been induced or tricked by his adversary's misconduct into allowing the filing deadline to pass.'" Young v. United States, 535 U.S. 43, 50 (2002) (quoting Irwin v. Dep't of Veterans Affairs, 498 U.S. 89, 96 (1990)).
Plaintiffs, in their jurisdictional response brief, do not argue for equitable tolling or repeat their previous argument that it would be "patently unfair" to find that the limitations period ended before the Federal Circuit's decision in Owen. See Pls.' Resp. passim. Plaintiffs instead raise the new argument that their claims are timely under the "accrual suspension rule," which, plaintiffs assert, directs that "`[n]o cause of action generally accrues until the plaintiff has a right to enforce his cause.'" Pls.' Jur. Resp. 12 (alteration in original) (quoting United States v. One Red Chevrolet Impala Sedan (Red Chevrolet), 457 F.2d 1353, 1358 (5th Cir. 1972)).
Accrual suspension is an exception to the general rule "that a claim `first accrues' when all the events have occurred which fix the alleged liability of the defendant and entitle the plaintiff to institute an action." Hopland Band of Pomo Indians v. United States, 855 F.2d 1573, 1577 (Fed. Cir. 1988) (citing Japanese War Notes Claimants Ass'n of the Phil., Inc. v. United States, 178 Ct. Cl. 630, 632, 373 F.2d 356, 358 (1967)). It directs "that the accrual of a claim against the United States is suspended, for purposes of 28 U.S.C. § 2501, until the claimant knew or should have known that the claim existed." Martinez, 333 F.3d at 1319; see also Ingrum v. United States, 560 F.3d 1311, 1315 n.1 (Fed. Cir. 2009) (stating that it "is both more common and more precise" to describe the rule as suspending accrual while a claim is "concealed or inherently unknowable" (internal quotation marks omitted) (citing Martinez, 333 F.3d at 1319)).
"The `accrual suspension' rule is `strictly and narrowly applied: . . . [The plaintiff] must either show that defendant has concealed its acts with the result that plaintiff was unaware of their existence or it must show that its injury was `inherently unknowable' at the accrual date.'" Martinez, 333 F.3d at 1319 (alteration in original) (quoting Welcker v. United States, 752 F.2d 1577, 1580 (Fed. Cir. 1985)). "Mindful that the `accrual suspension rule' is to be `strictly and narrowly applied,' courts have concluded that a misunderstanding of the meaning of the law or one's legal rights does not trigger this rule." Petro-Hunt, L.L.C. v. United States, 90 Fed. Cl. 51, 62 (2009) (citation omitted); see also Catawba Indian Tribe v. United States, 982 F.2d 1564, 1572 (Fed. Cir. 1993) ("[A]ll the relevant facts were known. It was the meaning of the law that was misunderstood."). The accrual suspension rule "is based on a construction of the term `accrues' in section 2501," and "is distinct from the question whether equitable tolling is available under that statute, although the term `tolling' is sometimes used in describing the rule." Martinez, 333 F.3d at 1319.
Because plaintiffs did not raise their accrual suspension argument in their opening brief, see Pls.' Jur. Br. passim, defendant did not have an opportunity to respond to it, and the court finds the argument to be waived, see Cross Med. Prods., Inc. v. Medtronic Sofamor Danek, Inc., 424 F.3d 1293, 1320 n.3 (Fed. Cir. 2005) (finding an issue not properly raised in an opening brief to be waived); Becton Dickinson & Co. v. C.R. Bard, Inc., 922 F.2d 792, 800 (Fed. Cir. 1990) ("[W]e see no reason to depart from the sound practice that an issue not raised by an appellant in its opening brief . . . is waived.").
Even if the accrual suspension rule had been properly raised, it is inapplicable to plaintiffs' claims. Plaintiffs' argument is that, before Owen was decided in 1988, plaintiffs "had no cause of action" because "federal cases uniformly held that erosion damage was not a taking where the damage from the federal project was caused, not by a rise in water levels, but as a consequence of some other interference with the natural water flow."31 Pls.' Jur. Br. 21. Plaintiffs are therefore arguing that the legal basis—rather than the factual basis—of their claims was "inherently unknowable," Ingrum, 560 F.3d at 1315 n.1 (citing Martinez, 333 F.3d at 1319), until Owen was decided.
The accrual suspension rule is generally applied in situations where the factual basis, rather than the legal basis, of a plaintiff's claim is concealed or inherently unknowable.32 See, e.g., Young, 529 F.3d at 1385 (finding that the trial court had properly declined to suspend accrual because "[i]t is a plaintiff's knowledge of the facts of the claim that determines the accrual date" (citing, inter alia, United States v. Kubrick, 444 U.S. 111, 122 (1979)); Martinez, 333 F.3d at 1319 (finding that the accrual suspension rule was not applicable because "Mr. Martinez was not unaware of the existence of his injury and the acts giving rise to his claim"); Welcker, 752 F.2d at 1580 (finding that the plaintiff's claims accrued in 1949 or in 1950 because "[c]learly, appellant was aware in 1949-1950 that he had been dismissed from the federal service on grounds that he himself considered to be wrong and improper"). Plaintiffs do not cite—and the court's research has not found—any decision in which the Court of Federal Claims or the Federal Circuit has found that adverse precedent tolled a plaintiff's claims under the Tucker Act, rendering them timely.33 See Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim.
The Federal Circuit has repeatedly stated that plaintiffs must file their claims within the statute of limitations, notwithstanding the presence of adverse precedent or the futility of filing. See, e.g., Aectra Ref. & Mktg., Inc. v. United States, 565 F.3d 1364, 1373-74 (Fed. Cir. 2009) (finding, in the internal revenue context, that "futility does not excuse the failure to file a proper claim for limitations purposes" (citing, inter alia, United States v. Clintwood Elkhorn Mining Co., 553 U.S. 1, 5-6 (2008)); Frazer v. United States, 288 F.3d 1347, 1354-55 (Fed. Cir. 2002) (finding that "it is, of course, irrelevant" to the timeliness of the plaintiffs' claims whether similar claims had been unsuccessful in the past (citing Boling II, 220 F.3d at 1374)); Boling II, 220 F.3d at 1374 (stating that the difficulty of pursuing a takings claim due to adverse precedent "does not justify tolling the statute of limitations"); Welcker, 752 F.2d at 1583 (rejecting the plaintiff's argument that any attempt to pursue his claims would have been "an exercise in futility" because of the "tenor of the times" and noting that "the statute of limitations is not tolled by litigative timidity"); see also Venture Coal Sales Co. v. United States (Venture Coal), 57 Fed. Cl. 52, 54-55 (2003) (finding that accrual of plaintiffs' claims for a tax refund was not suspended until a decision finding the tax unconstitutional), aff'd, 370 F.3d 1102 (Fed. Cir. 2004).
Plaintiffs rely upon two related cases not binding on this court for the proposition that, although the factual circumstances of a plaintiff's claim are not concealed or inherently unknowable, "`[n]o cause of action generally accrues until the plaintiff has a right to enforce his cause.'" Pls.' Jur. Resp. 12 (alteration in original) (quoting Red Chevrolet, 457 F.2d at 1358); id. at 13 (citing Neely v. United States, 546 F.2d 1059, 1068 (3d Cir. 1976)). The plaintiffs in Red Chevrolet sued for the return of property forfeited to the United States government on the ground that it "had been used in conducting a gambling business without payment of the taxes required" by the Internal Revenue Code. Red Chevrolet, 457 F.2d at 1355. The plaintiffs in Neely sued for annulment of their convictions under the federal wagering statutes and the return of the fines they had paid. Neely, 546 F.2d at 1061. In both cases, the courts determined that the plaintiffs' claims were timely, notwithstanding that they were filed more than six years after the fines and forfeitures that gave rise to them.34 See Red Chevrolet, 457 F.2d at 1358; Neely, 546 F.2d at 1068.
However, both Red Chevrolet and Neely "involve[ed] claims that were filed to obtain the benefit of a new constitutional rule that the Supreme Court expressly held to have retroactive application."35 Venture Coal, 57 Fed. Cl. at 55 (citing United States v. United States Coin & Currency (U.S. Coin), 401 U.S. 715, 723-24 (1971)). The statutory provisions at issue in Red Chevrolet and Neely "commanded that gamblers submit special registration statements and tax returns that contained information which could well incriminate them in many circumstances." U.S. Coin, 401 U.S. at 717. In a pair of cases decided on the same day, the Supreme Court held that, "[b]ecause the risk of self-incrimination was substantial, . . . a Fifth Amendment privilege could be raised as a defense to a criminal prosecution charging failure to file the required forms." Id. (construing Marchetti v. United States, 390 U.S. 39 (1968) and Grosso v. United States, 390 U.S. 62 (1968)). The Supreme Court determined that the rule announced in Marchetti and Grosso applied retroactively, stating that, because "the conduct being penalized is constitutionally immune from punishment, . . . [n]o circumstances call more for the invocation of a rule of complete retroactivity." Id. at 724.
The courts in Red Chevrolet and Neely both noted the Supreme Court's holding in U.S. Coin that the rule protecting the plaintiffs from self incrimination should be applied retroactively. Red Chevrolet, 457 F.2d at 1355; Neely, 546 F.2d at 1061. In contrast, the Federal Circuit did not hold in Owen that its ruling was to be applied retroactively. See Owen, 851 F.2d passim. Plaintiffs cite no decision in which the holding of Owen was applied retroactively to extend the statute of limitations for a claim that was otherwise untimely. See Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim.
To the contrary, the Federal Circuit has expressly determined that the overruling of adverse precedent in Owen did not extend the limitations period within which erosion claims could timely be filed. The plaintiffs in Boling II argued that the "Ballam decision, which effectively barred the cause of action they intended to assert, and its subsequent reversal in Owen, form another basis for equitable tolling." Boling II, 220 F.3d at 1374. The Boling II plaintiffs further argued that "after the Ballam decision was rendered, any attempt to assert their rights to compensation under the Fifth Amendment would have been futile, because the identical claim had been previously rejected." Id. The Federal Circuit observed that "the plaintiffs point to no authority which would suggest that the presence of adverse precedent automatically leads to equitable tolling." Id. The Federal Circuit concluded: "It is true that during the period between the decision in Ballam and its subsequent reversal in Owen, any claim by the plaintiffs for compensation would have been difficult. However, this difficulty does not justify tolling the statute of limitations." Id.
Although the Federal Circuit used the term "equitable tolling" rather than "accrual suspension," the Boling II plaintiffs' argument is sufficiently analogous to the argument raised by plaintiffs in this case that the court views the Federal Circuit's decision as binding upon the court. See Martinez, 333 F.3d at 1319 (stating that the accrual suspension rule is distinct from equitable tolling, "although the term `tolling' is sometimes used in describing the rule."). The court therefore holds that the accrual suspension rule did not delay the accrual of plaintiffs' claims until the Owen decision was entered in 1988.
4. The Law of the Case and the Mandate Rule
Because the Federal Circuit has previously ruled on the timeliness of plaintiffs' claims, the court directed the parties to address in their briefing whether the law of the case doctrine prohibits the court from holding, in light of its finding that the jetties were impermeable to sand before installation of steel sheet piling, that plaintiffs did not timely file their claims. See Order to Brief Jurisdiction, 99 Fed. Cl. at 626.
Plaintiffs, in their briefing, argue that the law of the case doctrine bars the court from considering whether plaintiffs' claims are timely. Plaintiffs argue that, in its decision reversing the dismissal of plaintiffs' claims on statute of limitations grounds, the Federal Circuit "held that [p]laintiffs' claims did not accrue until January 2000, and were not time barred." Pls.' Jur. Br. 5 (citing Accrual Op. II, 314 F.3d at 1310). Plaintiffs contend that "[s]pecifically, the Federal Circuit held: `We are satisfied that the plaintiffs met their jurisdictional burden before the Court of Federal Claims.'" Id. (quoting Accrual Op. II, 314 F.3d at 1310). Plaintiffs therefore believe that, because they have met their jurisdictional burden, the court may not reexamine any aspect of the timeliness of plaintiffs' claims.
Defendant argues that "[b]ecause the Federal Circuit's decision . . . incorporated [p]laintiffs' legal theory—a theory premised on facts substantially different from those facts subsequently proven at trial—the law of the case doctrine does not preclude this [c]ourt from dismissing [p]laintiffs' action at this time." Def.'s Jur. Br. 12. Defendant further argues that "[p]laintiffs initially alleged that the installation of steel sheet-piling was the government action that began the erosion process; but the evidence presented at trial established that the construction and maintenance of St. Joseph Harbor initiated the erosion process many years before the sheet-piling installation began." Id. at 14. Defendant therefore contends that the Federal Circuit's decision "is inapposite" to the question currently before the court. Id. at 15.
Defendant's argument is best understood as two distinct arguments. First, defendant argues that the law of the case doctrine is inapplicable because the law of the case does not address the aspect of the court's jurisdiction currently at issue, which was "`neither presented nor decided in a former proceeding in the case.'" Def.'s Jur. Resp. 11 (quoting Halpern, 384 F.3d at 1301). Second, defendant argues that, even if the law of the case addresses the aspect of the court's jurisdiction currently at issue, a change in circumstances—specifically, a change in the evidence available to the court—after the Federal Circuit's decision warrants application of one of the exceptions to the law of the case doctrine. Id. at 10-12 (citation omitted). For the reasons stated below, the court agrees with defendant that the law of the case doctrine or, more specifically, the mandate rule, is inapplicable because the aspect of the court's jurisdiction currently at issue was not decided by the Federal Circuit on appeal. Rather than addressing the aspect of the court's jurisdiction currently at issue, the Federal Circuit presumed the truth of the allegations in plaintiffs' complaints related to steel sheet piling and addressed only the jurisdictional facts relevant to the judgment from which plaintiffs appealed.
"The mandate rule provides that `issues actually decided [on appeal]—those within the scope of the judgment appealed from, minus those explicitly reserved or remanded by the court—are foreclosed from further consideration.'" Amado, 517 F.3d at 1360 (alteration in original). "The scope of the issues presented . . . on appeal must be measured by the scope of the judgment appealed from, not by the arguments advanced by the appellant." Engel Indus., 166 F.3d at 1382 (citations omitted). The court must therefore determine whether the scope of the judgment that was appealed to the Federal Circuit encompassed the effect of the steel sheet piling on the erosion of plaintiffs' property.
As discussed above in Parts III.A-A.1, the question addressed by the court in its order granting defendant's motion to dismiss was whether plaintiffs' claims accrued when the government finished the installation of steel sheet piling in 1989 or whether, under Applegate, the government's promises to mitigate erosion damage created justifiable uncertainty as to the permanence of erosion caused by the jetties, delaying accrual of plaintiffs' claims. The court stated that "[w]hen considering a motion to dismiss, the court must presume that well[-]pleaded factual allegations in the complaint are true." Accrual Op I., 49 Fed. Cl. at 808.
Plaintiffs had alleged that the installation of steel sheet piling increased the rate of erosion of their properties. See id. at 810 (stating that plaintiffs allege "that it was the Corps' installation of `sand-tight steel sheet piling during the period of 1950 to 1989' that has `alter[ed] the supply of sand to the lake bed and subaerial visible beach in front of the plaintiffs' property'" (alteration in original)); id. ("Referring to the installation of the steel sheet piling, plaintiffs state that as a `direct result of [d]efendant's actions,' they `have suffered a gradual and continued taking of their property'. . . .").
The court presumed this allegation to be true, analyzing when, after installation of the piling, plaintiffs' claims for erosion damage caused by the steel-clad jetties accrued. See id. passim. Plaintiffs cite no portion of the court's opinion in which the court examined, either expressly or by necessary implication, see Laitram, 115 F.3d at 951, whether the steel sheet piling does, in fact, exacerbate erosion of plaintiffs' properties, see Pls.' Jur. Br. passim; Pls.' Jur. Resp. passim.
Plaintiffs correctly note that the exhibits that the parties intended to present at trial were before the court when it ruled on defendant's motion to dismiss. Pls.' Jur. Br. 3; see also Accrual Op. I., 49 Fed. Cl. at 809 n.4 (stating that the parties' trial exhibits had been filed in accordance with the court's pretrial order). Plaintiffs are also correct, see Pls.' Jur. Resp. 5, that some of the evidence before the court suggested that the jetties had increased erosion in plaintiffs' zone to some extent before the installation of steel sheet piling, see, e.g., Accrual Op I., 49 Fed. Cl. at 820-21 (quoting a newspaper interview in which a Corps official stated that "we have 80, 90, or 100 years of non-mitigation to make up for"). Plaintiffs correctly note, see Pls.' Jur. Resp. 2-3, that defendant argued in its motion to dismiss that the erosion caused by the jetties did not begin only with the installation of steel sheet piling,36 see Mot. to Dismiss at 10 (stating that a non-governmental report "indicate[d] that erosive processes preceded plaintiffs' theory that such erosion only began after the commencement of sheet piling maintenance by the Corps in 1950"); id. at 8 (stating that many of the exhibits submitted by plaintiffs with an earlier filing "reiterate the conditions of erosion plaintiffs complain of as having existed for decades or even more than a century").
The court, however, reviewed the evidence submitted by the parties only to resolve the dispute upon which the court decided defendant's motion: whether plaintiffs' claims had accrued, at the latest, in 1989, when the Corps finished installation of steel sheet piling, or whether the government's promises to mitigate erosion delayed accrual. The court stated that "[i]f the jurisdictional facts in the complaint are disputed, . . . the court may consider relevant evidence beyond the pleadings to decide the jurisdictional question." Accrual Op. I, 49 Fed. Cl. at 809 (emphasis added) (footnote omitted) (citing, inter alia, Land v. Dollar, 330 U.S. 731, 735 n.4 (1947)). The court therefore considered the evidence submitted by the parties as it pertained to when, after installation of steel sheet piling, plaintiffs' claims would have accrued. The court did not weigh the evidence of whether the jetties caused erosion in plaintiffs' zone or whether the steel sheet piling, in fact, exacerbated the erosion caused by the jetties. See id. passim. The court made no findings of fact regarding whether the jetties caused erosion in plaintiffs' zone or whether the steel sheet piling did, in fact, exacerbate erosion caused by the jetties. See id. passim. The court resolved these fact-intensive questions, with the assistance of extensive expert testimony and the parties' post-trial briefing, only after the trial of liability. See Liability Op., 78 Fed. Cl. passim.
On appeal of the court's dismissal of plaintiffs' claims, the Federal Circuit addressed the proper application of accrual principles rather than the factual issues of whether the jetties actually caused erosion in plaintiffs' zone or whether the steel sheet piling exacerbated this erosion. The Federal Circuit stated that "the question is whether the `predictability [and permanence] of the extent of damage to the [plaintiffs'] land' was made justifiably uncertain by the Corps' mitigation efforts." Accrual Op. II., 314 F.3d at 1309 (alterations in original) (quoting Applegate, 25 F.3d at 1583). The Federal Circuit determined that "the Court of Federal Claims and defendant misread Applegate as requiring the presence of a legally binding promise or duty or a matter requiring a congressional appropriation." Id. The Federal Circuit reversed the dismissal of plaintiffs' claims "[b]ecause the Court of Federal Claims misapplied the standard for claim accrual under Applegate, and because plaintiffs remained uncertain as to the permanent nature of the taking until the Corps reported that the erosion was permanent and irreversible." Id. at 1310. The Federal Circuit did not address whether the installation of steel sheet piling increased erosion in plaintiffs' zone. See id. passim.
In addition to the text of the Federal Circuit's decision and the judgment from which plaintiffs appealed, the court is mindful of the Federal Circuit's admonition that "both the letter and the spirit of the mandate must be considered." Engel Indus., 166 F.3d at 1383. Whether the jetties, with or without the steel sheet piling, cause erosion in plaintiffs' zone goes to the merits of plaintiffs' claims. As the Federal Circuit has explained, an appellate court reviewing the disposition of a motion to dismiss does not examine the ultimate merits of the case: "That is what the trial judge will do on remand. Appellate courts do not do that, even if we had a record on which to do it." Henke, 60 F.3d at 801 n.5; see also Cordis Corp. v. Boston Scientific Corp., 658 F.3d 1347, 1360 (Fed. Cir. 2011) ("It would be illogical for this court to remand for findings on unresolved outcome determinative issues, while simultaneously foreclosing reconsideration of the outcome after the district court considered those issues for the first time."). The court therefore concludes that the Federal Circuit did not intend to address the merits of whether the jetties cause erosion in plaintiffs' zone before the issue was taken up, and before trial was held on the issue, by the trial court.37
A trial court may act on matters left open by the mandate. Laitram, 115 F.3d at 951. The issue "actually decided on appeal," Amado, 517 F.3d at 1360 (brackets omitted), was whether, under Applegate, plaintiffs' claims could have accrued between 1989 and 1999 despite promises and efforts by the government during that period of time to mitigate erosion damage caused by the jetties. Since the decision of the Federal Circuit, the court has found, based on evidence presented at trial rather than allegations made in plaintiffs' complaints, that the most recent government act that increased the rate of erosion of plaintiffs' properties took place, not in 1989, but in 1903, more than fifty years before the government first proposed to mitigate erosion in plaintiffs' zone. See supra Parts III.A.1-2. Because the Federal Circuit addressed only the delay of accrual resulting from promises and efforts to mitigate erosion, the court finds that whether plaintiffs' claims accrued before the government made its first promises of mitigation is an issue left open by the mandate. The mandate rule therefore does not bar the court's holding that plaintiffs' claims were filed after the end of the limitations period.
B. Composition of the Shoreline
1. The Court's Previous Findings on Shoreline Composition
In its Liability Opinion, the court addressed the evidence presented at trial as to the composition of the shoreline adjacent to plaintiffs' properties. See Liability Op., 78 Fed. Cl. at 621-28. "The composition of the lake bed is relevant because the composition affects erosion and mitigation processes. If the shore is composed of sand, the quantity of sand that is depleted is directly proportional to the quantity of sand that needs to be replaced." Id. at 622 (footnote omitted). Therefore, "`[F]or a predominantly sandy shore . . . as long as the sand supply south of the harbor is restored to the pre-harbor levels, then we can assume directly that the erosion will remain the same as the pre-harbor levels, all other things aside. . . .'" Id. (alteration and omissions in original) (quoting transcript of the trial of liability (Liability Tr.) 1215:11-16, 1296:4-10 (Nairn)). As Dr. Nairn explained at the trial of liability, "`it's a simple sediment budget' and a `simpler assessment.'" Id. (quoting Liability Tr. 1215:12, 1215:8 (Nairn)).
Assessing the erosion of cohesive38 shores is "much more complicated. We know the sand acts to abrade, sort of like sandpaper, the till. And it also acts to protect it. . . ." Id. (omission in original). Once cohesive material is eroded, "it cannot reconstitute itself, and the cohesive form is lost forever." Id. (citation and quotation marks omitted). However, it is possible for sand cover to increase to the point that a cohesive section of shoreline would be categorized as sandy. See PX 178 (Coastal Engineering Manual (CEM)) III-5-939 ("[O]nly when the sand cover is sufficient to protect the cohesive substratum at all times will the shore revert to a sandy classification (i.e., truly a `thick pile of sand')."); Tr. 512:11-513:15 (colloquy between Dr. Mackey and plaintiffs' counsel) (quoting same with approval); cf. PX 178 (CEM) III-5-13 ( "Investigations of Great Lakes sites have shown that approximately 200 m3/m of sand cover (measured from the top of the beach out to the 4-m contour) is required to halt the downcutting process. . . ."). Short of providing such large quantities of sand, however, "it is unclear whether mitigation is ever possible. There no longer is a direct correlation between replacing material and effective mitigation because nourishment can act as an abrasive agent that exacerbates erosion, and the erosion of the lake bottom is considered permanent." Liability Op., 78 Fed. Cl. at 624 (citation omitted).
Determining shoreline composition can be difficult for two reasons. First, "cohesive shores are often difficult to identify owing to the presence of a sand beach at the shore," PX 178 (CEM) III-5-3, which can mask the underlying substrates, see generally infra Part III.B.2.b (discussing the CEM and its role in the parties' arguments). Cohesive shores often are covered by a thin "veneer of sand and gravel" that the CEM states "is usually in the range of a few centimeters to 2 or 3 [meters]."40 PX 178 (CEM) III-5-3. Second, a shoreline may contain both sandy and cohesive material as a result of its geological history. See, e.g., DX 3 (Larson Report) 34, Fig. 9 (geological map and cross section of plaintiffs' zone) (showing layers, pockets, and lenses of cohesive material embedded between layers of sand); Tr. 2035:3-2036:12 (colloquy between Dr. Mickelson and defendant's counsel) (describing DX 293 (Mickelson Report) 8, Fig. 341). For instance, Dr. Mickelson and Dr. Larson described a thin layer, rich in organic material, that formed approximately 6,000 years ago, which is sandwiched between thick deposits of sand in the southern portion of plaintiffs' zone. See infra Part III.B.3.a (describing the formation of the thin, organic-rich layer between thick layers of sand).
The composition of the shoreline is significant in this case because it indicates how the shoreline will erode, whether any erosion is permanent and whether it is possible to mitigate any ongoing erosion. Liability Op., 78 Fed. Cl. at 622. After analyzing the evidence of shoreline composition presented at the trial of liability, the court concluded that "plaintiffs failed to prove by a preponderance of the credible evidence that plaintiffs' properties are located on a cohesive lake bottom." Id. at 628. The court found persuasive the testimony of defendant's expert witness in geology, Dr. Larson, see id. at 628, who testified in detail about the geological history of the area and described the stratigraphy42 he had prepared by interpreting well logs and engineering borings and by traveling every path through the area to observe exposures of sediment,43 see id. at 625. The process of using well logs collected nearby to assemble a stratigraphy of the shoreline has been found persuasive in the past—by this court, by the Federal Circuit and by the United States Court of Claims—when direct evidence as to actual subsurface conditions is unavailable.44 Order Granting Recons., 84 Fed. Cl. at 296-97 (discussing Renda Marine, Inc. v. United States, 509 F.3d 1372, 1378 (Fed. Cir. 2007), aff'g Renda Marine, Inc. v. United States, 66 Fed. Cl. 639 (2005)); id. at 297 n.6 (discussing Arundel Corp. v. United States, 207 Ct. Cl. 84, 98, 515 F.2d 1116, 1124 (1975)).
Based on his stratigraphy and the geological history of the area, Dr. Larson concluded that "the shoreline for some of the northern-most plaintiffs' properties is a cohesive shore that then transitions to a sandy shore for the remaining larger group of plaintiffs' properties." Liability Op., 78 Fed. Cl. at 625 (internal quotation marks omitted). He further testified that south of the harbor, the exposed layer of till gives way to an area that is "mainly raw sand." Id. (quotation marks omitted). Dr. Nairn, defendant's expert witness in coastal engineering, reviewed Dr. Larson's stratigraphy and conducted measurements and numerical modeling, also concluding that "the properties belonging to a majority of the plaintiffs are located on a sandy, not a cohesive, shoreline." Id.
At the trial of liability, plaintiffs presented "no expert evidence . . . to counter defendant's expert's studies and explanations, and no expert review of Dr. Nairn's—and particularly Dr. Larson's—research conclusions regarding the lake bottom composition." Id. at 628. Plaintiffs' expert, Dr. Chrzastowski, testified that he had not reviewed Dr. Nairn's report, and plaintiffs provided no evidence that Dr. Chrzastowski had reviewed Dr. Larson's report or testimony. Id. Dr. Chrzastowski instead "opined that the lake bottom was cohesive, bas[ing] his evaluation on existing literature, aerial photography, historical maps, and ground photography," documentary evidence that the court found had been "credibly refuted" by Dr. Larson. Id. Dr. Chrzastowski did not take any measurements in connection with his formulation of his expert opinion. See id.
The court noted that "[t]here is no dispute that, prior to this litigation, defendant consistently held the position that the shore in the area south of St. Joseph Harbor was cohesive." Id. However, defendant had previously held this position as a result of studies conducted prior to this litigation that the court found less probative than the evidence presented at trial. Two of the earlier studies, which the court referred to in its Liability Opinion as the "1996 Report" and the "1997 Report," had focused on a broader area of shoreline with little data from plaintiffs' zone. See id. at 625, 627. A study that the court referred to in its Liability Opinion as the "1992 Pilot Study" stated on its title page that it was a preliminary study, failed to discuss the geological history of the area and, in Dr. Larson's opinion, made "no geological sense." See id. at 627 (quotation marks omitted).
The court also found the use of sidescan sonar in the 1992 Pilot Study problematic.45 Sidescan sonar, the court stated, "scans only the surface of the lake bed and does not penetrate it." Id. at 626. Sidescan sonar "doesn't [actually] tell you what's there, it simply produces a picture of what the surface of the lake bed looks like, that is, it provides information on whether it is bumpy or flat." Id. (alteration in original) (internal quotation marks omitted). The radar used to supplement sidescan sonar in the 1992 Pilot Study penetrates the ground but "can't penetrate very far . . . because the energy is consumed very rapidly." Id. at 626 (internal quotation marks omitted). Dr. Larson testified that sidescan sonar and the other techniques used in the 1992 Pilot Study were "good science" but explained that it "should not stand alone; it has to be verified," for example with well logs. Id. (citation and internal quotation marks omitted). Instead of using well logs to verify their conclusions about the composition of the lakebed, the authors of the 1992 Pilot Study performed "periodic sampling of the surface" of the lakebed by collecting sediment samples. Id. (citation and quotation marks omitted). The court found these superficial sediment samples less persuasive than "Dr. Larson's extensive use of well logs, which obtains samples of materials in strata that are at the same depth as the subsurface of the adjacent shore." Id. at 626-27.
The court, having found Dr. Larson's and Dr. Nairn's testimony persuasive, stated that "[t]he inference of this conclusion is that for any given plaintiff it is more likely than not that his or her property is located in a sandy zone." Id. However, "The evidence at trial did not permit the court to determine (by, for example, an overlay of plaintiffs' property lines onto the lakebed composition data presented by defendant) exactly which of plaintiffs' properties in the northernmost portion of plaintiffs' zone were adjacent to the cohesive nearshore lakebed shown on defendant's exhibits." Order Granting Recons., 84 Fed. Cl. at 291. The court stated that the issue of which specific properties are located along the small section of cohesive shoreline would be determined in future proceedings. Liability Op., 78 Fed. Cl. at 628.
2. Additional Evidence of Shoreline Composition Presented by Plaintiffs at the Trial of Damages
a. Observation of the Surface of the Lakebed by Sidescan Sonar, Underwater Video and Sediment Grab Sampling
At the trial of damages, plaintiffs presented additional evidence addressed to the composition of their section of shoreline.46 However, plaintiffs did not provide an interpretation of the geological history of the area or present a stratigraphy of the area to challenge the geological history and stratigraphy developed by Dr. Larson, see Tr. passim, and found persuasive by the court at the trial of liability, see Liability Op., 78 Fed. Cl. at 628. Plaintiffs' expert witness on the topic of shoreline composition, Dr. Mackey, testified at the trial of damages that he had not reviewed the well logs that Dr. Larson used to develop his stratigraphy. See Tr. 710:5 (Mackey). Plaintiffs did not present evidence that the properties of individual plaintiffs had sandy or cohesive shorelines, see Tr. passim, but instead argued that the entirety of plaintiffs' zone is located along a cohesive shoreline, see Pls.' Br. 15.
Plaintiffs retained Dr. Mackey to perform a sidescan sonar survey of the nearshore lakebed adjacent to their properties, to map the distribution of surface sediments and to determine whether the shoreline along which their properties are located is cohesive. Tr. 488:7-13 (Mackey). To aid in the interpretation of the sidescan sonar data, Dr. Mackey recorded underwater video of plaintiffs' zone. Tr. 507:17-24 (colloquy between Dr. Mackey and plaintiffs' counsel). As Dr. Mackey explains in his report, "In many respects, sidescan sonar data is similar to aerial photographs taken of the earth's surface. The only difference is that the images are produced with sound instead of light." PX 136 (Mackey Report) 3. A device called a towfish is pulled behind a boat, id. at 2, 3; the towfish emits acoustic pulses and records the acoustic energy reflected by the lakebed, id. at 2. To survey the nearshore lakebed adjacent to plaintiffs' properties, Dr. Mackey piloted a boat along five survey lines parallel to the shore, see id. at 5-6, and used specialized software to merge the data from the five survey lines "into a seamless image of the lakebed," id. at 7.
Sidescan sonar can be used to determine whether materials at the surface of the lakebed are sandy or cohesive. See id. at 2 ("Generally, harder materials (bedrock, sand, metal) will give a stronger acoustic return than softer materials (silt, clay, or mud)."); DX 136 (McNinch Report) 2 (stating that "different surfaces often generate characteristic and distinguishable changes to the reflected sound"). Dr. Mackey explained that "[i]n general, harder materials . . . will show up as `bright' patterns on the sidescan sonar. Softer materials . . . will show up as `dark' patterns on the sidescan sonar." PX 136 (Mackey Report) 10; see, e.g., id. at 11, Fig. 11.
Because sidescan sonar maps the surface of the lakebed, it is of limited value to researchers attempting to determine the composition of substrates located below the surface. Dr. Mackey testified that the sidescan sonar penetrated the lake bottom to a depth of "a couple of inches, at most." Tr. 728:16 (Mackey). Under the correct conditions, sidescan sonar can be used to detect subsurface materials located very near the surface, but it does not indicate the depth at which the subsurface materials are located.47 Tr. 727:9-11 (Mackey). Accordingly, Dr. Mackey agreed that the "mapped image usually does not provide a cross section of or insight into the depth of a substrate that appears on the surface of a lake bed." Tr. 721:2-6 (colloquy between Dr. Mackey and defendant's counsel).
In his trial testimony, Dr. Mackey agreed that he is aware of acoustic devices, including "sparkers," "boomers" and "chirper[s]," which "produce fairly high energy that allow[s] the sound of the side scan sonar to penetrate into the earth's crust and then reflect off different areas of different density in the earth's crust at varying depths." Tr. 721:7-20 (colloquy between Dr. Mackey and defendant's counsel). Dr. Mackey did not suggest to plaintiffs that they employ any of these devices, id. at 722:5-7, because he "didn't think it was [his] place to suggest the use of those sort of tools because [he does not] own that type of equipment and [he] typically [does not] do that kind of work," id. at 725:9-22. Dr. Mackey also testified that he was "not directly aware" that the question of what substrates lie below the surface of the lakebed and at what depth was an issue in this case. Id. 722:8-13.
Interpreting the results of his sidescan sonar, Dr. Mackey concludes that approximately 5% of the lakebed surface consists of cohesive material, rather than boulder cobble, bedrock, gravel or sand.48 See PX 136 (Mackey Report) 13, Table 1. Dr. Mackey infers, without explanation, that an additional 5.7% of the lake bottom is covered by "[t]hin deposits of fine-med-sand overlying cohesive clay/silt deposits." Id. at 13. Dr. Mackey states that his observations "fit the typical cohesive profile." Id. at 15.49 However, Dr. McNinch, reviewing Dr. Mackey's results, argues persuasively that far less of the lakebed surface is composed of cohesive materials. Dr. McNinch "found it very difficult to duplicate or even identify many of the same surface expressions of the cohesive clay substrate" identified by Dr. Mackey. DX 294 (McNinch Report) 4; but see PX 139 (Mackey Response to McNinch) 6 (stating that Dr. Mackey has more experience than Dr. McNinch in interpreting sidescan sonar data collected in the Great Lakes). Regarding Dr. Mackey's inference that five percent of the lake bottom is composed of a thin layer of sand overlying cohesive material, Dr. McNinch stated that "[i]nterpreting thickness based solely on the patchiness of exposed substrates . . . is highly speculative" and noted that none of Dr. Mackey's sediment samples revealed "a non-sandy, underlying layer."50 DX 294 (McNinch Report) 3.
Dr. McNinch also argues that, although "[t]he data acquisition and processing methodologies used by Dr. Mackey . . . were quite good and met conventional standards," id. at 2, Dr. Mackey failed properly to corroborate the results of his sidescan sonar, see Tr. 1799:25-1800:6 (colloquy between Dr. McNinch and defendant's counsel); DX 294 (McNinch Report) 2-5 (describing several respects in which Dr. Mackey's measurements could have been improved). Dr. Mackey acknowledges in his report that "it is always necessary (and appropriate) to validate the acoustic responses in the sidescan data either by sampling or direct observation."51 PX 136 (Mackey Report) 7.
One reason that it is necessary to validate sidescan sonar data with other measurements is that even sandy lakebeds contain a measure of finer material, which will often become separated from the sand and settle on the surface. Dr. McNinch explained that "waves and currents typically winnow and sort unconsolidated sediment on the lakebed. These processes often result in what appears as a complex, patchwork pattern of different substrates at the surface but which, in fact, could simply originate from an underlying layer that is composed of a mixture of these sediment types." DX 294 (McNinch Report) 3.
However, the sampling and direct observation undertaken by Dr. Mackey were quite limited and provide little corroboration of Dr. Mackey's conclusion that his observations "fit the typical cohesive profile." See PX 136 (Mackey Report) 15. Dr. Mackey recorded underwater videos and collected sediment samples from the surface of the lakebed. Id. at 6. After studying Dr. Mackey's underwater videos, which total fifty-five minutes in length, Dr. McNinch determined that cohesive material was visible for thirty-seven seconds, or slightly more than 1% of the time.52 Tr. 1835:3-7 (McNinch); DX 294 (McNinch Report) 5. Several of Dr. Mackey's underwater videos document no cohesive sediment at all. DX 293 (Mickelson Report) 27. Dr. Mackey does not argue that Dr. McNinch has incorrectly measured the amount of cohesive material visible in the underwater videos. See PX 139 (Mackey Response to McNinch) 3-4.
None of the sediment grab samples53 collected by Dr. Mackey verified the existence of exposed cohesive material. See PX 136 (Mackey Report) App. A (sample descriptions) (describing every sediment sample as consisting of sand or "[v]ery coarse sand/[g]ravel"); Tr. 1799:22-24 (McNinch) ("I believe from his table at the back of his report, all the samples from his petite ponar were sandy, sandy material").54 Most significantly, Dr. Mackey failed to verify his observations with subsurface investigation. See PX 136 (Mackey Report) passim (offering no discussion of subsurface investigation). Dr. McNinch stated that, when studying lakebed composition, "[w]e often take cores, and we often take sub-bottom profiles55 so that we know what the strat[um] is like just below." Tr. 1798:13-15 (McNinch). Sub-bottom profiles also allow an observer to "see where the base of the sand is, and where other layers of different geology might be present."56 Tr. 1804:24-1805:5 (McNinch). Dr. Mackey did not ground truth his results with cores or sub-bottom profiles.57 See PX 136 (Mackey Report) passim.
Dr. Mackey's observations of the surface of the lakebed are simply insufficient to establish that the shoreline is cohesive. The court discussed the limited value of sidescan sonar coupled with surface sampling in its Liability Opinion—in which it found Dr. Larson's stratigraphy more persuasive than the results of a 1992 study that relied on sidescan sonar and sampling of the lakebed surface, Liability Op., 78 Fed. Cl. at 626-28—and again pointed out the limited value of sidescan sonar and other surface evidence in its Order Granting Reconsideration, 84 Fed. Cl. at 295. Plaintiffs do not explain why they presented again at the trial of damages the results of sidescan sonar uncorroborated by subsurface investigation, such as cores or sub-bottom profiles. See Pls.' Br. passim; Pls.' Resp. passim; cf. Tr. 1798:13-15 (McNinch) (stating that, when studying lakebed composition, "[w]e often take cores, and we often take sub-bottom profiles so that we know what the strat[um] is like just below"). Neither do plaintiffs attempt to distinguish the techniques used by Dr. Mackey from the techniques used in the 1992 study, presented at the trial of liability, and found unpersuasive by the court. See Pls.' Br. passim; Pls.' Resp. passim.
The court agrees with Dr. McNinch that "sediment thickness and the character of underlying substrates cannot be directly measured from sidescan sonar, underwater video, and surface sediment samples. No corroborating evidence, such as sediment cores or sub-bottom seismic58 profiles, that explicitly measure the thickness and nature of buried substrates[,] are provided to support these interpretations." DX 294 (McNinch Report) 1. The court therefore finds that Dr. Mackey's observations of the lakebed surface, without supplementation by subsurface sampling or sub-bottom profiles, are insufficient to establish that plaintiffs' zone is cohesive.
b. CEM Techniques to Identify Cohesive Shorelines
Plaintiffs offer two arguments that supplement Dr. Mackey's observations of the surface of the lakebed with analysis drawn from the CEM. The CEM is an engineering manual drafted by the Corps to describe "the basic principles of coastal processes . . . and [to provide] guidance on how to formulate and conduct studies in support of coastal flooding, shore protection, and navigation projects." PX 316 (Guide for Preparation of the CEM) 5. Part III, Chapter 5 of the CEM, entitled "Erosion, Transport, and Deposition of Cohesive Sediments," has been admitted into evidence as PX 178 and addresses, among other things, the identification of cohesive shores. PX 178 (CEM) III-5-2 to III-5-8.
Plaintiffs' first argument concerns six visual features that the CEM states may help in the identification of a cohesive shoreline. See Pls.' Br. 9-12. Plaintiffs argue that four of the six visual features set out by the CEM are present in plaintiffs' zone. Tr. 17:5-8 (plaintiffs' counsel). Plaintiffs' second argument purports to summarize with a two-part analysis the CEM's discussion of cohesive shorelines and how they are identified. Pls.' Br. 8. Because neither argument employs the detailed analysis of shoreline composition described in the CEM, the court does not find either argument persuasive.
i. Six Visual Features that May Indicate a Cohesive Shore
Although the CEM notes that "cohesive shores are often difficult to identify owing to the presence of a sand beach at the shore," the CEM states that "[t]here are at least six ways of visually identifying the presence of underlying consolidated cohesive sediment."59 PX 178 (CEM) III-5-3. Drawing from Dr. Mackey's initial expert report,60 plaintiffs contend that "the six factors set forth in the CEM provide strong visual clues to the presence of a cohesive shore." Pls.' Br. 12; see also Tr. 17:5-8 (plaintiffs' counsel) ("There are six ways, in the [CEM], to identify whether a [cohesive]61 lakebed exists. We have four out of six."); PX 136 (Mackey Report) 17-25 (discussing the presence of four of the six factors in plaintiffs' zone).
The six visual features listed by the CEM are (1) "the presence of exposed cohesive sediment on the beach"; (2) pieces of clay or peat that have washed onto the beach; (3) "[s]prings or surface runoff across a beach"; (4) "[d]iscoloration of water in the nearshore zone"; (5) "[p]ermanent undulations in the shoreline platform"; and (6) exposed cohesive sediments in troughs between offshore bars. PX 178 (CEM) III-5-3 to III-5-6. In addition to the six visual indicators, the CEM describes the "[u]se of more detailed subsurface investigations to confirm visual observations and provide more detailed information." Id. at III-5-6. Plaintiffs claim that four of the six CEM factors are present on their properties: exposed cohesive material on the beach, pieces of cohesive material washed up on the beach, discoloration of the water in the nearshore zone and exposed cohesive sediments in the troughs between offshore bars. Pls.' Br. 10-11; see also PX 136 (Mackey Report) 17-25 (discussing the presence of four of the six visual features in plaintiffs' zone); PX 141 (Shires Report) 6-7 (discussing Dr. Mackey's analysis of the six visual features).
The CEM contemplates that the six visual indicators would be used in conjunction with "more detailed subsurface investigations." PX 178 (CEM) III-5-6; see DX 155 (Nairn Composition Report) 17 (stating that the six visual factors are "clues"). The CEM describes a shoreline in Ghana where "initial visual observations" were followed by "a series of subsurface investigations" including "augers, boreholes, vibracores and sub-bottom profiling." PX 178 (CEM) III-5-6. A section of the CEM describes "a variety of techniques for characterizing the surface and subsurface conditions, with particular focus on the sand cover thickness," including the use of steel probes, jet probes and sub-bottom profiling. Id. at III-5-20.
Plaintiffs' expert witness, Mr. Shires, examined samples obtained by divers and determined them to be cohesive. Pls.' Br. 12-13. These samples, however, are not "subsurface investigations" as claimed by plaintiffs. Id. at 12. The fact that the samples were collected below the surface of the water does not make them "subsurface investigations" as contemplated by the CEM. Compare PX 178 (CEM) III-5-6 (describing the use of the visual features in conjunction with techniques that sampled material below the surface of the lakebed), with Pls.' Br. 12-13 (characterizing as "subsurface investigations" Mr. Shires' analysis of samples collected at "various depths (between 10 and 20 feet)" below the surface of the water).
Mr. Shires testified that the samples were taken from the surface of the lakebed. Tr. 789:24-790:1 (Shires) ("So these are right on the bottom, they're exposed on the bottom."). Mr. Shires' expert report, the permits obtained before the samples were collected and the photographs taken by the divers similarly indicate that the samples were collected from the surface of the lakebed and that the divers were, in fact, prohibited from collecting samples more than four inches below the surface. See PX 141 (Shires Report) App. A., Attachment B (letter from the Corps) (authorizing collection of samples two inches thick), App. A, Attachment B (letter from Michigan Department of Natural Resources & Environment) (authorizing the collection of samples two to four inches thick), App. A, Attachment C (photographs taken by divers) (showing exposed samples of cohesive material lying on the surface of the lakebed). The letter from Prism Environmental Services (Prism), the company retained to collect the samples, states that "[t]he primary purpose of this investigation was to locate in-place exposures of cohesive bottom sediments." Id. at App. A (letter from Prism) 1 (emphasis added).
The first and second CEM features relate to the presence of cohesive materials on the beach, either as a result of intact cohesive units becoming exposed or as a result of cohesive materials washing up on the beach. PX 178 (CEM) III-5-3. Plaintiffs argue that both features are present on the beaches adjacent to their properties. Pls.' Br. 10. However, the evidence cited by plaintiffs to document the existence of exposed, intact cohesive units on the beach is limited and unpersuasive. Plaintiffs cite the trial testimony and expert report of Dr. Mackey, who, they argue, observed "exposed cohesive material and eroding cohesive scarps in the lakebed adjacent to [p]laintiffs' properties." Pls.' Br. 10 (emphasis added) (citing Tr. 538:19-539:7 (colloquy between Dr. Mackey and plaintiffs' counsel); PX 136 (Mackey Report) 20). But the CEM refers to exposed cohesive sediment "on the beach," PX 178 (CEM) III-5-3, not the lakebed. As Dr. Nairn explained, "A `beach' is defined as the above water or `subaerial' part of the nearshore profile." DX 155 (Nairn Composition Report) 12; see also The American Heritage Dictionary of the English Language (American Heritage Dictionary) 155 (4th ed. 2000) (including in its definition of a beach: "[t]he zone above the water line at a shore of a body of water"); Coastal Engineering Manual, App. A (Glossary) A-6 (2003) (defining a beach as "[t]he zone of unconsolidated material that extends landward from the low water line"), available at http://140.194.76.129/publications/eng-manuals/em 1110-2-1100/AppA/a-a.pdf.
Plaintiffs also rely on the trial testimony of Mr. Shires, Pls.' Br. 10, who identified cohesive materials in two pictures of bluffs above beaches in plaintiffs' zone by observing that "there appear[s] to be some vertically standing materials in the beach environment just upslope of the beach," Tr. 817:16-18 (Shires) (discussing PX 161 (unidentified photos of beaches) 1).62 Mr. Shires explained that "in order for it to stand vertically[,] it's got to have some consolidation, some consolidated cohesive properties to it." Tr. 817:25-818:2 (Shires).
Mr. Shires did not testify, however, that he had collected or tested samples of the material in the photos or even examined the materials in person. See Tr. 816:4-818:6 (colloquy between Mr. Shires and plaintiffs' counsel). The court finds Mr. Shires' characterization of the exposed materials as cohesive, which is based on photographs, to be less reliable evidence of their composition than the more sophisticated laboratory tests Mr. Shires ordered performed on the samples collected from the lake bottom. See Tr. 796:19-810:19 (colloquy between Mr. Shires and plaintiffs' counsel) (discussing the laboratory tests conducted on soil samples—including tests of shear strength, dry unit weight, moisture content, loss on ignition, plasticity and grain size). Furthermore, the materials Mr. Shires identified in photographs are not "on the beach" as contemplated by the CEM, see PX 178 (CEM) III-5-3, but are bluffs, see PX 161 (unidentified photos of beaches) 1, located, in Mr. Shires' words, "upslope of the beach," Tr. 817:17-18 (Shires).
Nor are the pieces of sediment that wash up on beaches in the southern reach of plaintiffs' properties, see Pls.' Br. 10 (describing this sediment as "pieces of exposed cohesive clay and consolidated peat," "chunks of grayish brown clay material" and "pieces of peat"), evidence of a cohesive shoreline. Defendant points out that the presence of rafts of organic-rich sediments washing onto the beach is consistent with defendant's explanation of the geological history and the stratigraphy of the area. See Def.'s Br. 22-23. Dr. Mickelson and Dr. Larson testified that changing lake levels deposited a thin layer of organic-rich material in the southern reach of plaintiffs' properties about seven feet below mean lake level approximately 6,600 years ago. See infra Part III.B.3.a (describing the formation of the thin, organic-rich layer); DX 293 (Mickelson Report) 3-6 (discussing the formation of a layer of "marshy soil" approximately 6,600 years ago that has become exposed in areas and creates "rafts of peaty sand that occasionally wash up on the beach").63 Dr. Larson states that radiocarbon testing of one of the rafts of material that washed up on shore determined its organic material to be approximately 6,980 years old. DX 3 (Larson Report) 17. The court is persuaded by Dr. Mickelson's conclusion that "it all fits together that the cohesive material that's showing up out here . . . is this organic-rich sand and silt." Tr. 2100:4-6 (Mickelson). The presence of rafts of "organic-rich sand and silt," id., is not evidence that the shoreline as a whole is cohesive.
The two other visual features drawn from the CEM and relied upon by plaintiffs—exposed sediment in the troughs between offshore bars and discoloration of water in the nearshore zone—are similarly unpersuasive as evidence of a cohesive shoreline. Plaintiffs argue that Dr. Mackey observed exposed cohesive sediment in the troughs between offshore sand bars. Pls.' Br. 11 (citing Tr. 542:10-543:10 (colloquy between Dr. Mackey and plaintiffs' counsel); PX 136 (Mackey Report) at 22-23). However, as Dr. McNinch explained, "waves and currents typically winnow and sort unconsolidated sediment on the lakebed. These processes often result in what appears as a complex, patchwork pattern of different substrates at the surface but which, in fact, could simply originate from an underlying layer that is composed of a mixture of these sediment types." DX 294 (McNinch Report) 3. Plaintiffs have not rebutted Dr. McNinch's account of the source and composition of the sediment and have not, therefore, carried their burden of proof.
Plaintiffs contend that "[ae]rial photographs taken of the Plaintiffs' nearshore zone document discoloration in the nearshore zone." Pls.' Br. 10. However, Dr. Nairn determined that the plumes of discoloration actually travel downstream to plaintiffs' properties from areas that defendant describes as cohesive. See DX 155 (Nairn Composition Report) 12-13; see also id. at 2-26 (describing a section of cohesive shoreline approximately 1.9 miles long and located south of the jetties). Dr. McNinch notes that "many sandy beaches worldwide exhibit . . . plumes of discoloration in the surf." DX 294 (McNinch Report) 7. Plaintiffs failed to rebut defendant's evidence on the source of the discoloration and similarly failed to carry their burden of proof on this issue.
The court finds the explanation by defendant's expert witnesses of the presence of the four visual features in plaintiffs' zone to be both credible and persuasive. Because plaintiffs failed either to rebut defendant's evidence or to supplement its evidence of the visual features on which they rely with "more detailed subsurface investigations" such as "augers, boreholes, vibracores and sub-bottom profiling," as contemplated by the CEM, PX 178 (CEM) III-5-6, the court finds unpersuasive plaintiffs' argument that the claimed existence of four of the six CEM visual features establishes that plaintiffs are located along a cohesive shoreline.
ii. Plaintiffs' Two-Part "Test" of Composition
Plaintiffs' second argument purports to summarize the CEM's discussion of cohesive shorelines as a two-part "test":
In short, if (1) cohesive materials are exposed on the lakebed or covered with less than 9 feet of sand and (2) those materials are subject to irreversible lakebed erosion, a shoreline is cohesive.
Pls.' Br. 8.64 For the following reasons, the court finds that plaintiffs' proposed two-part "test" does not accurately represent the analysis recommended by the CEM to use in identifying cohesive shorelines. Nor do the facts adduced at trial support plaintiffs' proposed analysis.
Nowhere does the CEM reduce the detailed analysis it describes to a two-part "test." See PX 178 (CEM) passim. Instead, the CEM recommends a detailed analysis. The CEM contains a non-exhaustive list of six visual factors to consider, see id. at III-5-3 to III-5-6, and describes "a variety of techniques for characterizing the surface and subsurface conditions," id. at III-5-20, which are to be used to verify the visual indicators, see id. at III-5-6 (stating that, at the shoreline used as an example, such techniques included "augers, boreholes, vibracores and sub-bottom profiling").
Not only has plaintiffs' proposed two-part "test" oversimplified the detailed analysis suggested by the CEM, but plaintiffs have also reduced the analysis described in the CEM to a "test" that is more easily satisfied. With regard to the first part of the "test," that cohesive materials are exposed on the lakebed or covered with less than nine feet of sand, Pls.' Br. 8, Dr. Mackey testified that even a very small amount of exposed cohesive material would be sufficient under plaintiffs' analysis:
Q: [S]o the presence of those two substrates, that fulfills that part of the definition for you . . .?
A: Yeah.
. . . .
Q: Sir, would that still be your opinion if the percentage of those two substrates were say 5 percent?
A: Yes.
Q: 1 percent?
A: Yes.
Tr. 715:17-716:10 (colloquy between Dr. Mackey and defendant's counsel); but see DX 294 (McNinch Report) 3 ("[W]aves and currents typically winnow and sort unconsolidated sediment on the lakebed. These processes often result in what appears as a complex, patchwork pattern of different substrates at the surface but which, in fact, could simply originate from an underlying layer that is composed of a mixture of these sediment types.").
To demonstrate the existence of cohesive materials, plaintiffs presented the testimony of Mr. Shires, who reviewed the results of laboratory tests run on samples taken from the surface of the lakebed. See PX 141 (Shires Report) 2. Rather than sampling at regular or pre-determined intervals, divers hired by plaintiffs searched the lakebed for "in-place exposures of cohesive bottom sediments" and provided samples to Mr. Shires. Id. at App. A (Letter from Prism) 1. Mr. Shires states that, although some of the samples contained as much as 87% sand, id. at 9, they could be considered cohesive, because they contain organic material that "provides binding properties (i.e., apparent cohesion) not accounted for by simply considering grain size," id. at 5; see id. at 9. Mr. Shires opined that the samples he tested are of near-shore lake bottom that is composed of "glacial till that was consolidated in the geologic past by glaciers." Id. at 7; see also id. at 1, 5.
The theory that the samples were taken from a thick layer of till formed and consolidated by glaciers, however, is inconsistent with the geological history of the area. More persuasive is the explanation that Dr. Shires' samples were collected from outcroppings of a thin layer of organic-rich soil. See infra Part III.B.3.a (describing the formation of the thin, organic-rich layer). Plaintiffs acknowledge that radiocarbon dating indicates that a layer of "peat and logs" is present seven feet below the mean lake level in the southern portion of plaintiffs' zone and contains organic material approximately 6,600 years old. Pls.' Br. 13. As Dr. Mickelson explained, the organic materials were deposited too recently to be glacial till: "the glacier was gone by 10,000 years ago . . . [T]hat layer is dated as just under 6,000 years old. . . . So, it's much later, much younger." Tr. 2096:10-21 (Mickelson); see DX 293 (Mickelson Report) 3-6 (discussing the formation of a layer of "marshy soil" approximately 6,600 years ago), 34-36 (discussing radiocarbon dating of the peat layer penetrated by engineering borings). The fact that "rafts of peaty sand," DX 293 (Mickelson Report) 3, which have been determined by radiocarbon dating to be approximately 6,600 years old, Pls.' Br. 13 (citing Tr. 2099:1-2101:4 (colloquy between Dr. Mickelson and plaintiffs' counsel)), wash up on the beach indicates that this thin, peaty layer has become exposed in some areas of the nearshore adjacent to plaintiffs' properties, see DX 293 (Mickelson Report) 3; cf. PX 136 (Mackey Report) (stating that pieces of cohesive material Dr. Mackey observed on the beach had been "eroded from exposed cohesive deposits on the lakebed located immediately adjacent to[,] and offshore from," the areas where they were found); Tr. 532:1-533:3 (colloquy between Dr. Mackey and court) (describing a scarp of material he interpreted as cohesive, visible in his sidescan sonar survey).
In addition to the age of the materials, their content is also inconsistent with their being composed of glacial till. The existence of a large proportion of organic material in the samples analyzed by Mr. Shires is consistent with defendant's explanation that the samples were collected from a thin layer, rich in peat and other organic material, formed after the retreat of the glaciers, see Def.'s Br. 22-23, and is inconsistent with Mr. Shires' contention that the material was deposited by glaciers, see PX 141 (Shires Report) 1, 5, 7. Dr. Mickelson testified that glacial till "has a mix of grain sizes and typically isn't organic. This has organic materials, fine sand grains that look like wind[-]blown sand and no pebbles, no stones. They're certainly not till." Tr. 2096:3-9 (Mickelson); see also DX 293 (Mickelson Report) 2 (stating that glacial till is "characterized by containing a wide range of grain sizes compared to sediment deposited in streams or lakes"). The court is persuaded by Dr. Mickelson's report and related testimony that the samples analyzed by Mr. Shires are pieces of the thin layer rich in organic materials located between thick deposits of sand. See Tr. 2096:10-21, 2096:3-9 (Mickelson); DX 293 (Mickelson Report) 27, 33-34 (describing the formation of the thin, organic-rich layer); cf. DX 3 (Larson Report) 16 (describing same); see infra Part III.B.3.a (describing how the thin, organic-rich layer formed and is eroding, forming rafts that wash up on the beach).65
Plaintiffs do not reconcile their "test" for the presence of a consolidated shoreline—which is satisfied by even the very small amount of cohesive material on the surface of the lakebed found by plaintiffs' experts, see Tr. 715:17-716:10 (colloquy between Dr. Mackey and defendant's counsel)—with the geological history of the area, which resulted in the incorporation of small amounts of cohesive material into otherwise sandy areas of shoreline, see infra Part III.B.3.a (describing the geological history and stratigraphy of plaintiffs' zone).
The second part of plaintiffs' "test" merely restates the fact—well established in this case—that the erosion of cohesive materials is irreversible. See Pls.' Br. 8; Liability Op., 78 Fed. Cl. at 628 (finding that the erosion of cohesive material is permanent and irreversible). The CEM provides:
A shore is defined as consolidated cohesive when the erosion process is directly related to the irreversible removal of a cohesive sediment substratum. . . . This differs fundamentally from sandy shores where erosion (or deposition) is directly related to the net loss (or gain) of noncohesive sediment from a given surface area. Erosion on a sandy shore is a potentially reversible process (i.e., due to natural processes), while erosion on a consolidated cohesive shore is irreversible.
PX 178 (CEM) III-5-2 to III-5-3. It is the nature of cohesive materials that any erosion they undergo is irreversible. See id. The second part of plaintiffs' "test" merely restates this fact.
The "test" plaintiffs propose reduces the analysis of whether a shoreline is cohesive to the narrow inquiry of (1) whether there are any "exposed cohesive materials on the lakebed in [p]laintiffs' zone which [(2)] are subject to irreversible downcutting." Pls.' Resp. 18 n.6; see also Pls.' Br. 8 (stating same). Because this approach is inconsistent with the thorough analysis of shoreline composition recommended by the CEM, see PX 178 (CEM) III-5-3 to III-5-6 (describing six visual features of cohesive shorelines); id. at III-5-20 (describing "a variety of techniques for characterizing the surface and subsurface conditions"), from which plaintiffs purport to draw their two-part "test," see Pls.' Br. 8 (citing, inter alia, PX 178 (CEM)); Tr. 716:25-717:3 (colloquy between Dr. Mackey and defendant's counsel) (agreeing that Dr. Mackey limited his analysis of shoreline composition to "what is set forth in Chapter 5 [of the CEM]"), the court declines to adopt plaintiffs' approach.
3. Additional Evidence of Shoreline Composition Presented by Defendant at the Trial of Damages
In addition to the evidence of shoreline composition submitted by defendant at the trial of liability, which the court found persuasive, see Liability Op., 78 Fed. Cl. at 621-28, defendant submitted additional evidence of shoreline composition at the trial of damages. Defendant states that assessing the composition of the shoreline "requires locating the shoreline at a point on a spectrum encompassing `two ends of a limiting system, one of which is almost all cohesive, and the other which is . . . all sand.'" Def.'s Br. 5 (omission in original) (quoting Tr. 2781:1-3 (Nairn)). Defendant, therefore, "supplemented its understanding of shoreline composition with geological and physical evidence related to the shoreline's material composition, as well as computer modeling and a sediment budget that assesses the shoreline's behavior." Id.
Specifically, defendant presented the testimony of Dr. Mickelson, a geologist, and Dr. Nairn, a coastal engineer. See supra note 9. Dr. Mickelson reviewed the stratigraphy and geological history presented by Dr. Larson at the trial of liability66 and supplemented both with his own analysis of the history and grain size distribution of the northern and southern areas of plaintiffs' zone. See Tr. 2011:7-2154:14 (testimony of Dr. Mickelson). Dr. Nairn used the stratigraphy developed by Dr. Mickelson and Dr. Larson to determine, on a property-by-property basis, whether each plaintiff's property has a sandy or a cohesive shoreline. See DX 155 (Nairn Composition Report) 27-32. Dr. Nairn also discussed the erosion and accretion of different areas in plaintiffs' zone over time, concluding that most of plaintiffs' properties were located in areas that behaved as a sandy shoreline would be expected to behave. See Tr. 2748:2-5 (Nairn) (stating that the shoreline in plaintiffs' zone behaves as a sandy shoreline).
The record indicates that the shoreline in plaintiffs' zone is neither pure sand nor pure cohesive material. Certain areas contain layers of both cohesive and sandy material. See infra Part III.B.3.a (describing the formation of a thin band of sediment rich in cohesive organic material between thick layers of sand); DX 293 (Mickelson Report) 2-3 (describing the complex stratigraphy formed in the northerly portion of plaintiffs' properties by the retreat and advance of glaciers, as well as deposition and erosion by lake and stream environments). Certain sediments sampled in plaintiffs' zone are difficult to classify as sandy or cohesive. See, e.g., PX 141 (Shires Report) 5 (discussing sediment samples with both high sand content and cohesive characteristics). Because the shoreline composition is more complex than pure sand or pure cohesive material, the court finds the approach used by defendant—an approach that employs several metrics to evaluate shoreline composition—to be useful in determining where on the spectrum of composition plaintiffs' zone is located.
a. Additional Evidence Regarding Geological History and Stratigraphy
Dr. Mickelson provided additional detail to supplement the geological history and stratigraphy presented by Dr. Larson at the trial of liability. See generally DX 293 (Mickelson Report). Regarding the stratigraphy, Dr. Mickelson reviewed all of the well logs Dr. Larson had used to assemble his stratigraphy and concluded that "for the most part I agreed with the stratigraphy that he had put together."67 Tr. 2027:5-9 (Mickelson). Dr. Mickelson states that, because of the dearth of subsurface samples, "the best information available about what is below the surface in the nearshore is extrapolation of well log data from onshore." DX 293 (Mickelson Report) 20.
Based on the geological history and stratigraphy of plaintiffs' zone, Dr. Mickelson concludes that there are "two distinctly different regions" in plaintiffs' zone, which he "treat[s] . . . separately." Tr. 2027:12-15 (Mickelson). The dividing line between Dr. Mickelson's regions, or "reaches," is West Glenlord Road, which intersects Lake Michigan in approximately the same location as the Inner Lake Border moraine, a ridge built by glaciers. Tr. 2029:7-12 (Mickelson); see also DX 293 (Mickelson Report) 4, Fig. 1 (map of plaintiffs' zone). Dr. Mickelson concludes that the compositions of the northern reach and the southern reach are very different: "The northern reach is made up of glacial till and sand and gravel. The southern reach is made up of sand dunes and some organic material." Tr. 2030:19-22 (Mickelson). The northern reach is characterized by "bluff shoreline. And south of that[,] it's dominated by dunes." Tr. 2023:11-13 (Mickelson). The twelve northernmost properties are located in the northern reach, and the twenty-eight remaining properties are located in the southern reach. DX 293 (Mickelson Report) 2.68
Dr. Mickelson explained that the differing composition of the northern and southern reaches results from their differing geological histories.69 All of the sediment underlying plaintiffs' properties was deposited since the last glaciation of the area—25,000 years ago. Id. "The glacier lobe scoured much of the Lake Michigan basin, enlarging it and removing most of the older glacial deposits down to the bedrock surface." Id. Starting approximately 20,000 years ago, the glacier began to retreat, depositing glacial till, "which is sediment deposited directly by glacier ice and which is characterized by containing a wide range of grain sizes compared to sediment deposited in lakes or streams." Id. Dr. Mickelson described how the retreat of the glaciers formed the layers that underlie the northern reach of plaintiffs' properties:
The retreat of the glacier was interrupted by numerous re-advances of the glacier as [the] climate fluctuated. Each re-advance of the glacier deposited a layer of till with a distinct composition. The two till layers present along this shoreline are the younger Saugatuck till and the somewhat older Ganges till. Gravel, sand, silt, and clay were deposited in shallow lake and stream environments near the front of the retreating glacier. These deposits lie between the Saugatuck and Ganges till units as well as beneath the Ganges till where it is present.
Id. at 2-3. The resulting stratigraphy is complex, consisting of two layers of glacial till, with deposits of gravel, sand, silt and clay between the layers of till and—in certain locations—beneath both layers of till. See DX 3 (Larson Report) 34, Fig. 9 (geological map and cross section of plaintiffs' zone). Certain of the layers of sediment are located above the surface of the lake and therefore outside of the lakebed. See id.; DX 293 (Mickelson Report) 11 (describing cohesive material located in onshore bluffs). Other layers of sediment are located below the depth to which the nearshore lakebed is eroding. See DX 155 (Nairn Composition Report) 30 (stating that, for this reason, Dr. Nairn would examine sediments to a depth of eight meters); DX 293 (Mickelson Report) 20, 34 (stating that, in characterizing the composition of plaintiffs' shoreline, Dr. Mickelson would focus on sediments up to twenty feet below the surface of the lake).
At this point, the geological histories of the northern reach and the southern reach diverge because the southern reach underwent further change. When the glacier that formed the moraine retreated, lake levels rose and the edge of the lake reached the edge of the moraine, submerging the southern reach under water.70 Tr. 2029:19-2030:7 (colloquy between Dr. Mickelson and defendant's counsel). As a result, the surface was "cleaned off by waves" and covered in sand. Tr. 2029:25-2030:12 (colloquy between Dr. Mickelson and defendant's counsel); Tr. 2032:3-4 (Mickelson) (stating that "sand would have been delivered to the area at the time the lake level was high").
Approximately 9,000 years ago, the lake level dropped, creating a land surface with shallow ponded areas, on which organic material began to collect. Tr. 2032:4-10 (Mickelson). This organic material accumulated into a layer of peat and logs approximately ten centimeters thick and located approximately seven feet below the current surface of the lake. DX 3 (Larson Report) 16. This material is cohesive, but because of its thinness, constitutes a small fraction of the sediment in the shoreline. DX 293 (Mickelson Report) 36. Approximately 6,000 years ago, lake levels again rose, submerging this layer and depositing sand above it. See Tr. 2032:22-2033:8 (Mickelson). The thin layer of organic-rich materials was penetrated by two of the well logs, as well as the two engineering borings conducted by the United States Geological Service (USGS). See DX 293 (Mickelson Report) 3.71
This thin, organic-rich layer has become exposed offshore in some areas in the southern reach of plaintiffs' properties. See id. at 36. As it erodes, it creates rafts of organic-rich material that wash up on the beach. See id. at 3. Radiocarbon testing of one of the rafts of material determined its organic material to be approximately 6,980 years old, DX 3 (Larson Report) 17, roughly the same age as the organic material in the thin, organic-rich layer, see id. at 16-17 (stating that radiocarbon dating of this layer revealed the presence of organic materials approximately 6,630 to 6,675 years old).
The geologic history described by Dr. Mickelson strongly suggests that the southern reach of plaintiffs' zone is composed primarily of sand, with a thin layer of organic-rich material deposited approximately 6,600 years ago. Tr. 2029:19-2033:8 (colloquy between Dr. Mickelson and defendant's counsel); see also DX 293 (Mickelson Report) 3-6 (describing the geological history of the southern reach). The geologic history is less probative of the shoreline composition in the northern reach. The stratigraphy of the northern reach is more complex, containing two layers of till layered with other sediments. See DX 3 (Larson Report) 34, Fig. 9 (geological map and cross section of plaintiffs' zone).
b. Grain Size Distribution in the Northern and Southern Reaches
In addition to describing the geological history of the area, Dr. Mickelson calculated the sand content of the nearshore lakebed as a percentage of its overall composition.72 DX 293 (Mickelson Report) 10, 20. Dr. Mickelson restricted his analysis to sediments located between the level of the lake surface and a level twenty feet below the lake surface.73 Id. at 20, 34. Dr. Mickelson states that whether a sediment is cohesive depends in part on grain size:
Gravel and sand are not cohesive. Coarse silt, if well sorted[,] is usually not cohesive. Medium and fine silt and clay typically have cohesion. A mix of sizes, such as occurs in till, can be cohesive depending on the amount of clay and silt it contains. Both till units (Saugatuck and Ganges) have cohesion. Most of the lake sediment between the till is not cohesive.
Id. at 10.74 Plaintiffs do not argue otherwise.75 See Pls.' Br. passim; Pls.' Resp. passim. As sources of data, Dr. Mickelson relied upon well logs, his own observations, sediment samples that Dr. Mickelson and a graduate student under Dr. Mickelson's supervision collected and analyzed, Dr. Larson's observations and "various reports and papers including USGS reports and journal articles." DX 293 (Mickelson Report) 6-7.76
To calculate the sand content of the lakebed in the southern reach and the northern reach, Dr. Mickelson employed a two-step method.77 Dr. Mickelson's first step entailed calculating the number of feet of each sediment type that each driller encountered, as recorded in the well logs, and determining the percentage of the total described as sand. See, e.g., id. at 22, Table 11 (tabulation of sediment types and thicknesses for the northern reach) (stating that, at the depths Dr. Mickelson observed, drillers in one section encountered forty-four feet of sand, zero feet of clay, thirteen feet of interbedded sand and silt, and 25 feet of Ganges till). Dr. Mickelson calculated that the well logs described 42% of the sediment in the northern reach between the level of the lake surface and a level twenty feet below the lake surface as sand and 18% as interbedded sand and silt. See id.; Tr. 2062:9-15 (colloquy between Dr. Mickelson and defendant's counsel). Dr. Mickelson calculated that the well logs described 89% of the sediment located at the same range of depths in the southern reach as sand. DX 293 (Mickelson Report) 35, Table 13 (tabulation of sediment types and thicknesses for the southern reach); see Tr. 2087:10-11 (Mickelson).
Dr. Mickelson's second step accounts for the fact that the individual sediment layers contain not a single grain size of material, such as sand or silt, but a distribution of grain sizes. See Tr. 2088:6-8 (Mickelson) (stating that "what I've tried to do then is adjust these numbers . . . for the realistic sand content in those sediment types"). Dr. Mickelson explained that "when a driller—when somebody describes something as sand[,] it isn't necessarily 100 percent sand[,] and so what I tried to do here is not count sand as being 100 percent sand. . . . There's going to be some silt [and] clay in it probably." Tr. 2087:25-2088:6 (Mickelson). Using his own observations and reviewing the measurements made by other researchers, Dr. Mickelson examined the sand content of the various types of sediment present in plaintiffs' zone. See DX 293 (Mickelson Report) 11 (discussing sources of data).78 Dr. Mickelson determined that the Saugatuck till contains 29.7% sand, the Ganges till contains 31% sand and the unit of interbedded sand and silt between the till layers contains 81.5% sand. Id. at 13-14. Dr. Mickelson treated sediments described by the well drillers as "sand" as containing only 90% sand and treated any layers described as "clay" as containing no sand. See id. at 20. Applying the sand content of each sediment type to the amount of each sediment type present, Dr. Mickelson calculated that that the material between the lake surface and a level twenty feet below the lake surface—and therefore, the material in the nearshore lakebed—consists of 65% sand in the northern reach, id. at 20, and consists of 80% sand in the southern reach, id. at 38.
Dr. Mickelson's calculations indicate that plaintiffs' zone has significant sand content. The well logs described 60% of the sediment at the depth of the lakebed in the northern reach as either sand or interbedded sand and silt. See id. at 22, Table 11 (tabulation of sediment types and thicknesses for the northern reach). The well logs described 89% of the sediment at the depth of the lakebed in the southern reach as sand. Id. at 35, Table 13 (tabulation of sediment types and thicknesses for the southern reach). Applying the sand content of each sediment type to the observations documented in well logs, Dr. Mickelson determined that the sand content of the lakebed in the northern reach is 65%, id. at 20, and that the sand content of the lakebed in the southern reach is 80%, id. at 38.
c. Grain Size Distribution on a Property-by-Property Basis
Dr. Nairn analyzed the sand content of the shoreline to determine, on a property-by-property basis, which of plaintiffs' properties are located along a sandy shoreline. Recognizing that there is a "spectrum of shore types between purely cohesive shores and fully sandy shores," DX 155 (Nairn Composition Report) 5, Dr. Nairn argues that, for three reasons, the sand content of the shoreline is "the over-riding factor" in determining whether the shoreline should be considered sandy or cohesive for purposes of erosion:
1. the definition in the literature of a limit of 10% to 30% [sand] for a cohesive shore;
2. the fact that the rate of removal of sand is limited by the available wave energy whereas the rate of removal of cohesive [material] (silt and clay) . . . offshore is not; and
3. the fact that without removal of the sand the erosion of any underlying exposures of cohesive and sandy sediment could not continue,
id. at 17.
Dr. Nairn undertook an extensive literature review to determine the maximum sand content of cohesive shorelines described in other research. See id. at 5-15. Dr. Nairn states that "[a] large body of scientific understanding of cohesive shores on the Great Lakes emerged from the Port Burwell Litigation in the early 1980's," which involved erosion caused by harbor structures. Id. at 5. Beginning with the scholarly papers that emerged from the Port Burwell litigation in 1983, Dr. Nairn examined a number of papers and articles—including several of his own that were published before this litigation, id. at 5-15—and concluded that "[t]he literature unanimously puts the upper limit for sand content of a cohesive shore no higher than 30% (although for one part of one cohesive shore bluff in the Toronto area[,] the sand content was found to be 36%)," id. at 16-17.
Using the stratigraphic map developed by Dr. Mickelson, Dr. Nairn calculated the sand content at a number of "representative locations" along the shoreline to a depth of eight meters below chart datum.79 Id. at 30. Dr. Nairn selected the eight-meter cutoff because he determined—in the analysis of historic shoreline erosion contained in the report he prepared for the trial of liability—that the nearshore profile is eroding to a depth of approximately eight meters.80 Id. For each representative location and for each of plaintiffs' properties, Dr. Nairn calculated the sand content using the Wentworth scale applied by Dr. Mickelson and most geologists, on which sand is defined as sediment larger than .0625 millimeters. See id. at 28; see supra note 74 (discussing the Wentworth scale). Dr. Nairn also calculated the sand content using a cutoff of .1 millimeters, which, although larger than the grain size cutoff normally utilized by geologists and engineers,81 is "more consistent with the grain size of sand that might be expected to exist in the littoral zone (i.e.[,] whereas finer sediment would move offshore outside the littoral zone)." DX 155 (Nairn Composition Report) 28. Of course, the .1 millimeter cutoff results in findings of lower sand content, which is favorable to plaintiffs' argument that the shoreline is cohesive.
Regardless of the grain-size cutoff Dr. Nairn used, he determined that all but one of plaintiffs' properties82 were adjacent to areas of lakebed with sand content that is consistent with a sandy shoreline. See id. at 35, Fig. 4.3b (chart of lakebed sand content) (showing one property with lakebed sand content equal to or less than 30%). The northernmost property,83 belonging to plaintiffs Gregory and Candice Bovee, has "a sand content between 61.5% and 67.5% (using the minimum sand size of 0.0625 mm and 0.10 mm, respectively)." Id. at 31. The next property, belonging to plaintiff Marcia Wineberg, has a sand content between 66% and 72%. Id. The third property, belonging to plaintiffs Kent and Margaret Werger, has a sand content between 41% and 48%, the lowest sand content of the plaintiffs' properties. Id. Dr. Nairn concludes that, although the sand content of the Werger property "is above the sand content limit for cohesive shores derived from the available literature (i.e., 30% with one instance of 36%), it is close enough to the limit[] that in this expert's opinion, it is classified as a cohesive shore." Id.
Continuing to the south, "The properties between Okonski and Nueser all fall in a range where sand content of the lakebed sediment is always greater than 59% and usually greater than 70%[,] with averages across this zone of 67.5% to 73%." Id. The properties in this area are owned by plaintiffs Okonski, Bodnar, Wilschke, Jyung, Varga, Jackson, Greenbriar, Marzke and Neuser. Id. The sand content of the lakebed adjacent to the next property, which belongs to the Del Mariani plaintiffs, is "just above 75%." Id. The lakebed adjacent to the remaining properties has a sand content of 82% to 85%. Id. at 32. These southernmost properties are owned by plaintiffs Miller, Ragins, Morvis, Chapman, Errant (Saphir), Notre Dame Path Association, Country LLC, Concklin Trust, Anderson, Melcher, Smith, Lahr, Pancoast, Renner, Carter, McKay, Kane, Cosgrove, Frett (Horvath Trust), Banks, Ehret, Cunat and Bunker.84 See id.
Plaintiffs do not present competing sand-content calculations for their properties. See Pls.' Br. passim; Pls.' Resp. passim. In fact, plaintiffs do not present any property-by-property analysis of shoreline composition, see Pls.' Br. passim; Pls.' Resp. passim, despite multiple statements by the court that such evidence would be useful, see Jan. 22, 2008 Telephonic Status Conference Tr. 13:13-22 (court) ("[W]e don't have evidence explained to the [c]ourt [about] whose properties were at the northerly end of the [p]laintiff[s'] properties, who could have fallen into the area that it shows as cohesive on Dr. Larson's study."); Order Granting Recons., 84 Fed. Cl. at 297 (quoting same in parenthetical) (quoting Jan. 22, 2008 Telephonic Status Conference Tr. 13:13-22 (court)); Liability Op., 78 Fed. Cl. at 628 ("If, in further proceedings, some or all of a plaintiff's property is determined to lie in the northernmost zone characterized by Dr. Nairn and Dr. Larson in their expert reports as not predominantly sandy, the erosion damage to such property will be analyzed as damage to a cohesive shore.").
Plaintiffs argue that, by considering the sand content of the lakebed, Dr. Nairn is "literally run[ning] from the established definition of a cohesive shoreline set forth in the CEM—a document drafted by Dr. Nairn and described by the Corps—to this day . . . as a state-of-the-art technical manual for coastal engineers." Pls.' Br. 15. Plaintiffs further contend that "the United States and Dr. Nairn attempt to create a new shoreline definition called `predominantly sandy.' This definition is found nowhere i[n] coastal engineering literature and was created out of whole cloth by Dr. Nairn for purposes of this litigation."85 Id. at 15-16. Plaintiffs argue that the CEM defines cohesive shorelines "by how the shore behaves and not by some arbitrary sand percentage." Id. at 17. "Most importantly," plaintiffs argue, "Dr. Nairn's new category of `predominantly sandy' shores fails to meet the basic requirements set forth in Daubert v. Merrell Dow Pharm[aceuticals]," because the term "predominantly sandy . . . is not recognized" in the scientific community or literature. Id. at 18; see also Daubert v. Merrell Dow Pharms., Inc., 509 U.S. 579, 592-93 (1993) (stating that, before admitting expert testimony, a trial court must make "a preliminary assessment of whether the reasoning or methodology underlying the testimony is scientifically valid").
Defendant is correct that this assertion "constitutes a straw man argument on which the United States has not relied." Def.'s Resp. 9. In pre-trial motions practice before the trial of damages, the court declined to exclude Dr. Nairn's testimony under Daubert for its use of the term "predominantly sandy." Banks v. United States, Dkt. No. 403, 93 Fed. Cl. 41, 56-57 (2010). The court stated that "[p]laintiffs present[ed] no legal basis upon which the court is required to strike Dr. Nairn's use of the term `predominantly sandy' and the court declines to do so." Id. at 57; see also id. at 56-57 (discussing plaintiffs' argument). It is the view of the court that Dr. Nairn's use of the term "predominantly sandy" in his report is similar to the court's use of the term in its Liability Opinion, 78 Fed. Cl. at 628, as a descriptive term to capture the complex composition of some of plaintiffs' shoreline, rather than as a term of art that displaces the sandy and cohesive categories of shoreline composition. Dr. Nairn, in addressing whether plaintiffs' shoreline should be characterized as sandy or cohesive, observes that there is a "spectrum of shore types between purely cohesive shores and fully sandy shores." DX 155 (Nairn Composition Report) 5. The court finds helpful Dr. Nairn's acknowledgement that shoreline composition can be complex and the clarity of his focus on the two factors he considers most significant to the court's analysis of shoreline erosion—grain size distribution and erosional behavior.86
Plaintiffs are incorrect in their view that the sand content of a lakebed is irrelevant to the determination of whether it is sandy or cohesive. See Pls.' Br. 17. The court has considered a number of metrics to determine the composition of the shoreline of plaintiffs' properties, including the sand content of the sediments it contains, its geological history, stratigraphy derived from well logs and engineering borings, the composition of the surface of the lakebed as determined by sidescan sonar, underwater video and sediment sampling, the visual features identified by the CEM, previous assessments made in the scientific literature and discussed by the parties' expert witnesses, and erosional behavior—both as predicted by numerical modeling and as measured over the span of more than a century. Although the sand content of the lakebed is not dispositive of whether the shoreline is cohesive, the court agrees with Dr. Nairn that it is useful to consider whether the lakebed has a higher sand content than cohesive shorelines identified in other research. See id. (arguing that sand content is "the overriding factor" regarding whether a shoreline should be considered sandy or cohesive).
Furthermore, Dr. Nairn's analysis of sand content is consistent with the analysis of shoreline composition described by the CEM. Plaintiffs contend that the CEM defines the composition of a shoreline "by how the shore behaves and not by some arbitrary percentage." Id. Plaintiffs oversimplify the analysis recommended by the CEM. The CEM recommends the use of "subsurface investigations" including "augers, boreholes, vibracores and sub-bottom profiling." PX 178 (CEM) III-5-6. Plaintiffs do not contend that it would be inappropriate to measure the sand content of any samples collected using these techniques. See Pls.' Br. passim; Pls.' Resp. passim. Plaintiffs' own expert witness, Mr. Shires, measured the sand content of the sediment samples collected in plaintiffs' zone as part of his investigation into whether the samples were cohesive or sandy, see PX 141 (Shires Report) 7-9, implicitly assuming that sand content is relevant to cohesion in his statement that the samples had greater cohesion than their sand content would indicate because of a high organic content, see id. at 5 ("It is my opinion that organic content . . . provides binding properties (i.e., apparent cohesion) not accounted for by simply considering grain size.").
Neither must Dr. Nairn's analysis fit within the four corners of the CEM to be "scientifically valid." See Daubert, 509 U.S. at 592-93. The Corps' goal in drafting the CEM was "to develop an engineering manual which includes the basic principles of coastal processes . . . and guidance on how to formulate and conduct studies in support of coastal flooding, shore protection, and navigation projects." PX 316 (Guide for Preparation of the CEM) 5. The CEM was to be written "at a level suitable for the USACE District, BS-level graduate civil/hydraulic engineer who has no advanced academic training in coastal engineering and its related subjects." Id.; see also Dep. of Joan Pope (Pope Dep.), Dkt. No. 493-2, 85:21-87:4 (Pope) (stating that the Corps hired Dr. Nairn to draft a portion of the CEM in part because of his ability to "explain very complex concepts so they're clearly understood by non-engineers"). The CEM was intended to be "a living document and continually revised to reflect improvements as they are developed." PX 316 (Guide for Preparation of the CEM) 5. Such improvements in the understanding of cohesive shorelines can be expected to develop in the primary literature cited by Dr. Nairn. See Tr. 1802:24-1803:4 (McNinch) (stating that the CEM "is certainly nothing that I would cite in our peer[-]reviewed publications as a cornerstone to our methodology, and we are developing new methodologies. So, I would use primary literature and try to advance the field in that manner.").
Ms. Pope, who oversaw the drafting of most of the CEM, Pope Dep. 19:15-20 (colloquy between Ms. Pope and plaintiffs' counsel), is currently the Assistant Director for Civil Works in the Research and Development Directorate of the Corps, "which means [she] coordinate[s] the overall civil works research and development activities," id. at 8:14-19. Ms. Pope testified that the study of cohesive shorelines "is probably one of the more immature areas of coastal engineering and coastal geology in terms of understanding[] the processes and being able to . . . quantify those processes," Pope Dep. 86:7-13 (Pope). Ms. Pope further testified that the Corps hired Dr. Nairn to co-author the chapter of the CEM on cohesive shorelines in part because Dr. Nairn is "the foremost English[-]speaking authority on" cohesive shorelines. Pope Dep. 86:14-16 (Pope). The chapter of the CEM on cohesive shorelines was released nearly a decade ago. See Pope Dep., Dkt. No. 493-1, 34:11-16 (colloquy between Ms. Pope and plaintiffs' counsel) (stating that the chapter authored by Dr. Nairn was released in early 2000). It appears reasonable to the court that Dr. Nairn's analysis of shoreline composition in connection with his expert report and testimony in this case would examine more than the "basic principles of coastal processes" described some years ago in the CEM, PX 316 (Guide for Preparation of the CEM) 5, and would address matters discussed in current scholarly research on cohesive shorelines—particularly given that he is working in "one of the more immature areas of coastal engineering," Pope Dep. 86:9-10 (Pope).
Dr. Nairn's testimony indicates that plaintiffs' properties, with the exception of the Werger property, are located along areas of lakebed with greater sand content than those in the cohesive shorelines described in the scholarly literature. See DX 155 (Nairn Composition Report) 31-32.
d. Shoreline Behavior
Dr. Nairn also created a sediment budget to determine whether the shoreline in plaintiffs' zone behaves as a sandy shoreline or a cohesive shoreline. See id. at 25, Table 3.2 (revised sediment budget). A sediment budget is "`an accounting procedure to keep track along the shoreline of sediment inputs and sediment losses.'" Liability Op., 78 Fed. Cl. at 613 (quoting Liability Tr. 112:25-113:3 (Meadows)). Dr. Nairn first presented his sediment budget at the trial of liability, concluding that, because the sediment budget "is able to describe the erosion of [p]laintiffs' shores and the fact that it does, necessarily means that the shore is behaving as a [sandy] shore." Tr. 2568:11-17 (Nairn); see also Liability Op., 78 Fed. Cl. passim; DX 1 (Nairn Report) 4-147 to 4-148. The court discussed Dr. Nairn's sediment budget in its Liability Opinion. See Liability Op., 78 Fed. Cl. passim. However, at the trial of liability, plaintiffs presented "no expert evidence . . . to counter defendant's expert's studies and explanations, and no expert review of Dr. Nairn's . . . research conclusions regarding the lake bottom composition." Id. at 628. Because plaintiffs now contend that Dr. Nairn's sediment budget is unreliable, Pls.' Br. 18-20, the court here describes how Dr. Nairn compiled his sediment budget and addresses plaintiffs' arguments.
One way to distinguish between sandy and cohesive shores is "[h]ow the shore erodes—in other words, the behavior of the shore when it is exposed to waves and currents." DX 155 (Nairn Composition Report) 16; see also Pls.' Br. 17 (stating that the CEM defines cohesive shorelines "by how the shore behaves"). "If the shore is composed of sand, the quantity of sand that is depleted is directly proportional to the quantity of sand that needs to be replaced." Liability Op., 78 Fed. Cl. at 622 (footnote omitted). The amount of wave energy impacts the amount of sand being carried along the shoreline at any particular location. In areas where the amount of energy decreases, the sand transport rate decreases; sand "drop[s] out," and is deposited. Tr. 2588:4-13 (Nairn); see also DX 1 (Nairn Report) 2-26 ("Sand is deposited along sections of shore where the net rate of Longshore Sand Transport (LST) diminishes spatially along the shore, i.e.[,] the capacity for the waves and wave-generated currents to carry sand is reduced and thus sand drops out of the river of sand."). In areas where the amount of wave energy increases, the water picks up additional sand. See Tr. 2589:10-17 (Nairn); DX 1 (Nairn Report) 2-26. Erosion can be therefore be expected to take place along a sandy shoreline when "there is an increase in the rate (or a gradient in the rate) of longshore sand transport from one end of an area of interest to another." DX 155 (Nairn Composition Report) 2. Accordingly, "sandy shore erosion can be defined through a sand budget approach and the rate of loss of sand from a given area of interest is directly related to, and limited by, the available wave energy." Id. at 8.
Dr. Nairn described plaintiffs' properties as being located in a "hot spot," where a decrease in water depth focuses wave energy, increasing erosion.87 See Tr. 2584:10-2585:6 (Nairn); DX 1 (Nairn Report) 2-27 to 2-29 (presenting and discussing modeling results that show the wave focusing effect). He also described areas with lower wave heights, located to the south of plaintiffs' zone, that are characterized by lower rates of erosion. Tr. 2583:5-2584:6 (Nairn). To some extent, Dr. Nairn testified, this analysis can also be applied to specific sections of plaintiffs' zone; sand can be expected to accumulate in areas where wave energy decreases and to erode in areas where wave energy increases. See, e.g., Tr. 2586:11-22 (describing several "depositional zone[s]" and "eroding zone[s]").
Dr. Nairn explained why sandy shorelines behave in a manner that can be modeled with a sediment budget while cohesive shorelines do not. Summarizing an academic paper he published in 1992, Dr. Nairn explained that "the definition of a cohesive shore is primarily related to the root cause of erosion of these shores." DX 155 (Nairn Composition Report) 8. Erosion "occurs in two steps: a) the pickup of the sediment from the beach or lakebed, where individual grains of clay, silt and sand are put into suspension; and b) the removal of these suspended grains from the area of interest." Id. at 2. The first step is the same for sandy shorelines and for cohesive shorelines with "extensive sand cover." Id. For sandy shorelines, however, the second step relates to the available wave energy:
[R]emoval of sand from a given area of interest occurs in a longshore direction within the littoral zone. This only occurs where more sand can be transported by waves and wave-generated currents out of an area of interest than is supplied to that area—in other words, there is an increase in the rate (or a gradient in the rate) of longshore sand transport from one end of an area of interest to another.
Id. Dr. Nairn explains that "[t]his is the key differentiating factor between predominantly sandy and cohesive shores: the rate of removal of the heavier sand grains is limited by the available wave energy; whereas the offshore loss of the easily suspended and smaller clay and silt grains occurs at low energy levels and the loss rate is not limited by the available wave energy." Id.
Dr. Nairn explained that, if plaintiffs' zone is a sandy shoreline, the erosion he predicts should match the historical rate of erosion. Tr. 2570:16-21 (Nairn) ("[I]f I'm able to predict the rate at which the shoreline and lake bed erode using the sediment budget when I'm considering sand only, it effectively is a validation of the approach, that taking a sand budget approach, based on a sandy shore concept, is a correct one."). Citing the study he authored in 1992, Dr. Nairn described why studying shoreline behavior is particularly useful when analyzing an area of shoreline that contains some amount of both sandy and cohesive materials:
[A] distinction is made that eroding sandy shores may feature cohesive material, but that its presence does not alter the primary mechanism of erosion[,] which is the net balance in sand supply as determined by the sediment budget. In contrast, cohesive shore erosion is distinguished by the primary importance of the irreversible loss of cohesive sediment from the nearshore zone—and the lack of a relationship between the erosion rate and the sand budget.
DX 155 (Nairn Composition Report) 8.
In calculating his sediment budget, Dr. Nairn considered the sources that provide sediment to plaintiffs' zone and the "sinks" that remove it: "[T]he difference between what's coming [in] and what goes out should match what is supplied from the bluffs and the lake bed, in terms of sand. If it does, then effectively this is behaving [as] a predominant[ly] sandy shore." Tr. 2572:25-2573:4 (Nairn). In addition to the erosion of bluffs and the lakebed, sources of sand include the littoral flow of sand around the jetties from the north and sand that is supplied by the St. Joseph River. Tr. 2573:5-20 (Nairn). Dr. Nairn testified that "[a] lot of this work, the sediment budget, then goes to evaluating . . . how much sand gets [past] the harbor effectively." Tr. 2573:5-9 (Nairn).
One factor that Dr. Nairn examined when determining how much sand flows around the harbor jetties and into plaintiffs' zone is the role of bypassing shoals. As sand travels south along the shoreline and arrives at the harbor, it is deflected offshore by the jetties and their fillet beaches.88 Tr. 2601:3-7 (Nairn). "And then as it gets into this deep water—remember, that used to be just deep water before[—]but it sort of builds a natural sort of sand bridge or attempts to build a sand bridge across and through the channel. . . ." Tr. 2601:7-11 (Nairn). The sand bridges—or bypassing shoals—act as a sink, absorbing sand as they form and as they re-form after the shipping channel is dredged. Tr. 2601:11-19, 2600:1-2601:21 (Nairn).
To determine how much sand the river supplies, Dr. Nairn examined the St. Joseph watershed at different points in time, considering—among other factors—the effect of agriculture and deforestation on the amount of sand entering the river, the effect of river dredging on the amount of sand accumulating in the river, and the effect of dams, river flows and water levels on the amount of sand carried by the river. See Tr. 2575:2-2576:5 (Nairn). Dr. Nairn's numerical modeling of the sediment delivered to plaintiffs' zone by the St. Joseph River also considered potential variations under different weather conditions, including the effect of storms and floods. See Tr. 2603:4-2607:11 (colloquy between Dr. Nairn and defendant's counsel).
The sediment sinks that Dr. Nairn examined included dredging of the harbor, accumulation of sand in fillet beaches and sand deposited in bypassing shoals. Tr. 2574:3-17 (Nairn). Using a numerical model of hydrodynamics89—which weighs, among other factors, longshore currents, water flows driven by the waves and the level of river flow—Dr. Nairn also modeled the amount of sediment lost offshore under different conditions. See Tr. 2602:22-2604:10 (colloquy between Dr. Nairn and defendant's counsel).
Dr. Nairn testified that sediment budgets are one of the "usual types of investigations we do" when working on engineering projects. Tr. 2174:1-4 (Nairn); cf. Tr. 2169:21-22 (Nairn) (stating that Dr. Nairn's work focuses on river and coastline engineering). Plaintiffs' expert witness, Mr. Shires, agreed that "a sediment budget can be used for understanding how a coastal shoreline behaves[,] which then itself . . . can be used for understanding the composition of the shoreline." Tr. 853:11-16 (colloquy between Mr. Shires and defendant's counsel). Mr. Shires further agreed that "the Coastal Engineering Manual speaks . . . about considering the quantity and mobility of sand cover," which "relates to the idea of considering the behavior of the sediment." Tr. 853:19-25 (colloquy between Mr. Shires and defendant's counsel).90
Summarizing the findings he presented at the trial of liability, Dr. Nairn writes that "a sand budget approach, relying on longshore sand transport gradients (i.e.[,] defining the deficit in sand supply) was able to predict the observed historical erosion. . . . Therefore, . . . the [p]laintiffs' shore is indeed a predominantly sandy shore."91 DX 155 (Nairn Composition Report) 16; see also Liability Op. 78 Fed. Cl. passim (discussing Dr. Nairn's sediment budget).
Plaintiffs do not propose an alternate sediment budget, see Pls.' Br. passim; Pls.' Resp. passim, but argue that "Dr. Nairn's opinions are based on manipulated and inaccurate data," Pls.' Br. 18. Specifically, plaintiffs argue that Dr. Nairn has incorrectly modeled the flow of river sediment into plaintiffs' zone, that only under rare conditions would littoral sand bypassing the jetties return to shore and that certain large areas of shore protection considered in Dr. Nairn's analysis were installed at a later date than Dr. Nairn believed. See id. at 18-20. Defendant responds that "[p]laintiffs misrepresent the record before the court." Def.'s Resp. 10.
In regard to the flow of river sand into plaintiffs' zone, plaintiffs question Dr. Nairn's testimony "that all river sand that gets to the end of the jetties[] turns left, makes it[s] way around the jetties and directly into the littoral drift aimed at [p]laintiffs' shores." Pls.' Br. 18. Plaintiffs cite to no evidence, however, to support their implicit suggestion that the river sand would not turn left at the mouth of the jetties as it encounters the prevailing water currents. See id. Plaintiffs instead argue that "sand samples taken in 1997 from lake bottom sand deposits just lakeward of the jetties and beyond the depth of closure92 were consistent with sand that came from the St. Joseph River." Id. (footnote added). Plaintiffs contend that "[t]o reconcile the data to his opinion, Dr. Nairn implausibly testified—without a shred of corroborative evidence—that the sampled sand was not river sand but sand dredged from the St. Joseph Harbor and dumped there 27 years earlier." Id.
Defendant is correct, however, that Dr. Nairn identified several bases for his conclusion that the river sand near the end of the jetties had been dredged from the harbor and placed there. Def.'s Resp. 10-11 (citing DX 1 (Nairn Report) at 3-53). At trial, Dr. Nairn testified that "the amount of dredge from the inner harbor and the outer harbor matches very closely the amount of growth or deposition in that zone . . . for each of the periods we consider." Tr. 2602:16-19 (Nairn). Dr. Nairn further testified that the coarse grain size in the samples discussed by plaintiffs is consistent with the grain size of sand in the river rather than sand that has been deposited by the river in deeper water. Tr. 2602:10-15 (Nairn).
Plaintiffs' argument that Dr. Nairn has incorrectly modeled the flow of littoral sediment into plaintiffs' zone is similarly unsupported by the evidence. Plaintiffs contend that "in conflicting testimony, Dr. Nairn embarrassingly admitted that the projected wave action required to move littoral material beyond and to the shore south of the St. Joseph jetties occurs on only 2.4 days per year . . ., which is hardly sufficient to bring that sand into the littoral drift on any regular basis." Pls.' Br. 19 (footnote omitted) (citing Tr. 2925:12-2931:21 (colloquy between Dr. Nairn and plaintiffs' counsel)); DX 1 (Nairn Report) App. A, Fig. A-20 (offshore wave rose); see also DX 1 (Nairn Report) App. A (Wave Distribution Table). Plaintiffs further argue that "[i]n contrast, Dr. Meadows testified the majority of waves do not move material close to the jetties to the [p]laintiffs' properties." Pls.' Br. 19.
Plaintiffs misinterpret Dr. Nairn's testimony. The waves described by plaintiffs as occurring only on 2.4 days per year are those projected to be traveling due south with a wave period93 of eight to ten seconds. See DX 1 (Nairn Report) App. A (Wave Distribution Table). Dr. Nairn did not testify that waves traveling south can be expected to occur on only 2.4 days per year but, instead, that "for .652 percent of the time, you get waves of eight to ten seconds from a direction of zero degrees," Tr. 2931:2-4 (Nairn); cf. Tr. 377:24 (Meadows) (stating that "zero is out of the true north"), which Dr. Nairn compared, metaphorically, to that particular type of wave occurring all day for 2.4 days per year, Tr. 2931:16-19 (Nairn). Plaintiffs appear to confuse the prediction Dr. Nairn generated by numerical modeling with the metaphor that he used to describe that prediction.
Plaintiffs also overlook waves approaching from the north but characterized by different wave periods. The chart Dr. Nairn was describing, see Tr. 2928:20-2929:1 (colloquy between Dr. Nairn and plaintiffs' counsel), is titled "Wave Distribution by Period and Direction," DX 1 (Nairn Report) App. A (Wave Distribution Table).94 Each row represents waves approaching from a different direction. See id. The columns divide the waves into wave periods ranging from two to four seconds, four to six seconds, six to eight seconds, eight to ten seconds, ten to twelve seconds and more than twelve seconds. See id. Plaintiffs are describing waves that approach from the north with a wave period between eight and ten seconds. See id. When waves characterized by wave periods of two to four seconds, four to six seconds, six to eight seconds, ten to twelve seconds and more than twelve seconds are included in the total, waves traveling south (from a direction of zero degrees) occur not .652% of the time but 6.93% of the time, a more than tenfold increase. See id.
Furthermore, plaintiffs cite no evidence indicating that waves traveling due south are the only type of "wave action required to move littoral material beyond and to the shore south of the St. Joseph jetties"95 and no evidence explaining why the percentage of waves traveling south is insufficient to carry littoral material from the end of the jetties to plaintiffs' zone. See Pls.' Br. 19 (stating, without citation to evidence, that the frequency of waves traveling south is "hardly sufficient to bring that sand into the littoral drift on any regular basis"). Instead, plaintiffs state, without further explanation, "In contrast, Dr. Meadows testified the majority of waves do not move material close to the jetties to the [p]laintiffs' properties." Id. (citing Pls.' Br. 28-29). The referenced portion of plaintiffs' Brief cites two pages of Dr. Meadows' trial testimony and—without explanation or page citation—Dr. Meadows' expert report. See id. at 29 (citing, inter alia, Tr. 377:5-378:27 (colloquy between Dr. Meadows and plaintiffs' counsel); PX 142 (Meadows Wave Condition Report)). In the two pages of Dr. Meadows' testimony cited by plaintiffs, Dr. Meadows discusses only the capacity of waves to carry nourishment material to plaintiffs' zone if the material is placed directly south of the jetties in an area that he calls a "shadow zone." Tr. 377:5-378:17 (colloquy between Dr. Meadows and plaintiffs' counsel). Dr. Meadows does not testify in that portion of his testimony that the existing wave conditions would prevent littoral material from bypassing the jetties or describe the wave conditions necessary to carry littoral sediment from the end of the jetties to plaintiffs' zone. See id.; see also infra Part III.C.2.b (discussing the limitations of Dr. Meadows' analysis of wave conditions).
Plaintiffs' final argument regarding Dr. Nairn's analysis of shoreline behavior involves the role of large installations of shore protection constructed by the C&O Railroad (C&O) and the Michigan Department of Transportation (MDOT). See Pls.' Br. 19-20. Dr. Nairn explained in his initial expert report why shore protection must be taken into account when creating a sediment budget and assessing shoreline behavior:
On an eroding shore, shore-based, shore-parallel shore protection (i.e.[,] constructed on or very near to the shore) only prevents erosion inshore and above the structure. Erosion of the lakebed will continue, whether it is sandy or cohesive. Therefore, when placed along an eroding shore, shore protection prevents sand that is inshore and above the protection from naturally entering the littoral system. The effect of this is to transfer that part of the natural erosion that was prevented by the shore protection, in addition to any harbor[-]influenced erosion . . . to the unprotected shores to the south.
DX 1 (Nairn Report) 4-138; see also id. at 4-120, Table 4.2 (listing bluff erosion rates during four time periods). Dr. Nairn therefore included in his calculations the effect of .7 miles of shore protection installed by C&O and one mile of shore protection installed by MDOT. Id. at 4-138. Plaintiffs allege that "Dr. Nairn assumed that the C&O and MDOT revetments affected the rate of bluff erosion (and the amount of sand entering the littoral system through bluff erosion) for the time period between 1871 and 1938." Pls.' Br. 19. Plaintiffs argue that "Dr. Nairn's assumption is fundamentally misconceived because C&O did not install its shore protection until 1929, which is 58 years after the start of Dr. Nairn's study period and only 9 years before that period ended." Id. (emphasis omitted). Plaintiffs further argue that "MDOT did not install any revetments until 1969, well after Dr. Nairn's study period." Id. at 19-20.
However, Dr. Nairn's report indicates that he was aware of when the MDOT and C&O shore protection measures began to affect the sediment supply to plaintiffs' zone. Dr. Nairn stated in his report that C&O completed the installation of its shore protection in 1929. See DX 1 (Nairn Report) 4-138 ("Upon completion of the full 0.7 mile (1.1 km) of shore protection for the railway line in 1929, approximately 10,000 cy/yr (7,600m3/yr) was effectively trapped or prevented from entering the littoral system. . . ."). Although the details are not in Dr. Nairn's report, he stated, both in his report and at trial, that C&O installed some of its shore protection prior to finishing the .7-mile stretch in 1929. Id. ("Some time between 1871 and 1938 the railway was moved inshore, apparently in response to the erosion. . . . Its new position was also terraced into the eroding bluff, and therefore, once again, the shoreline below the railway would have had to be protected. . . ."); Tr. 2908:7-9 (Nairn) ("I think if we check the report, we'll see that there was some earlier protection before 1929.").
Nor is there any indication in Dr. Nairn's discussion of shore protection in his report that he assumed that the MDOT shore protection began to influence the sediment budget before the shore protection was, in fact, constructed. See DX 1 (Nairn Report) 4-138 to 4-140. Rather than assuming that the MDOT shore protection currently in place affected his sediment budget during the 1871 to 1938 time period, as plaintiffs suggest, Pls.' Br. 19-20, Dr. Nairn determined that "[t]his protection was constructed in the late 1960[s] to replace a groin system that was constructed after damages caused by storms in the 1940[s]," DX 1 (Nairn Report) 4-138 to 4-139. Applying his experience in coastal engineering, however, Dr. Nairn inferred that some of the MDOT revetments were likely installed at an earlier date. See id. at 4-138 (noting that, given the slope of the bluffs and the proximity of the highway to the edge of the bluff, that "at least the northerly half of the MDOT revetment would have had to be constructed almost immediately"). Accordingly, Dr. Nairn concluded that the "reduction in recession rate is mostly due to the implementation of shore protection along the railway and part of the highway shoreline toward the end of this period." Id. at 4-118.
Without explanation, plaintiffs cite the declaration of Mr. John Konik for the proposition that "MDOT did not install any revetments until 1969." Pls.' Br. 19-20 (citing, inter alia, PX 126 (Konik Aff.)).96 Mr. Konik states in his affidavit that he is "the Chief of the Regulatory Office, U.S. Army Corps of Engineers . . ., Detroit District." PX 126 (Konik Aff.) ¶ 1. Mr. Konik states that "[t]he responsibilities of the Detroit District Regulatory Office include the processing of permit applications submitted under . . . Section 10 of the Rivers and Harbors Act of 1999." Id. ¶ 2. The construction of certain shore protection structures, including revetments, requires the permission of the Corps. Id. ¶ 5. Mr. Konick lists the permits that the Corps has granted to MDOT. Id. ¶ 18. The first permit for the construction of "a stone sea wall" was granted in 1969. Id. However, Mr. Konik also states that "there are alternate forms of authorization used in certain prescribed situations." Id. ¶ 9. One alternate form of authorization is the "[l]etter[] of permission," which "may be used where, in the opinion of the district engineer, the proposed work would be minor, not have significant individual or cumulative impact on environmental values, and should encounter no appreciable opposition." Id. Another form of authorization is the "general permit," which is not issued to individual applicants, but rather allows specific activities in a particular geographical area. Id. ¶ 10. Additionally, before the enactment of the National Environmental Policy Act in 1969 and the Federal Water Pollution Control Act of 1972 in 1974, id. ¶ 12, "if it was decided that the proposed work would have no impact on navigation, a Department of the Army permit would not have been required," id. ¶ 11. Plaintiffs cite no evidence that indicates that MDOT did not install revetments prior to 1969 pursuant to a letter of permission, a general permit or a determination that the revetments would have no impact on navigation. See Pls.' Br. 19-20.
The court finds plaintiffs' criticisms of Dr. Nairn's sediment budget unpersuasive, particularly in light of plaintiffs' failure to introduce a competing sediment budget, numerical model of erosion, hydrodynamic model of wave conditions or any other comprehensive assessment of the erosional behavior of the shoreline in plaintiffs' zone. See Pls.' Br. passim; Pls.' Resp. passim. Dr. Nairn's study of the erosional behavior of plaintiffs' shoreline provides highly persuasive evidence that the shoreline in plaintiffs' zone should be categorized as a sandy shoreline.
Plaintiffs bear the burden of demonstrating "that a taking has occurred justifying the payment of just compensation." Loesch, 227 Ct. Cl. at 44, 645 F.2d at 914. The additional evidence of shoreline composition presented by plaintiffs is unpersuasive and, at times, repetitive of evidence rejected by the court in the past. See supra Part III.B.2. In contrast, the government has presented additional evidence of shoreline composition that the court finds persuasive. Based on credible and persuasive evidence, the court finds that plaintiffs' properties are located in an area of sandy shoreline, with the exception of the Werger property, which defendant's expert witness, Dr. Nairn, locates along a section of cohesive shoreline. See DX 155 (Nairn Composition Report) 31.
C. Mitigation
1. The Proportion of the Erosion Caused by the Jetties
This case has been bifurcated to allow the issues of liability and damages to be treated separately. Following the trial of liability, the court found that, if unmitigated, the jetties are responsible for 30% of the erosion taking place in plaintiffs' zone. Liability Op., 78 Fed. Cl. at 654-57. Notwithstanding the court's finding, plaintiffs now argue that "the United States is responsible for between 60% and 70% of the erosion to [p]laintiffs' properties." Pls.' Br. 23. Plaintiffs have not filed a motion for reconsideration on the scope of the government's liability. See Pls.' Damages Trial Mem., Dkt. No. 264, passim (requesting reconsideration on the issue of shoreline composition but not requesting reconsideration of the scope of the government's liability). It therefore remains the law of this case that, if unmitigated, the jetties are responsible for 30% of the erosion taking place in plaintiffs' zone.
Plaintiffs do not acknowledge that it is the law of the case that, if unmitigated, the jetties are responsible for 30% of the erosion taking place in plaintiffs' zone. See Pls.' Br. passim; Pls.' Resp. passim. Neither do plaintiffs list the three "exceptional circumstances," Mendenhall, 26 F.3d at 1582 (internal quotation marks omitted), that may warrant departure from the law of the case or argue that any of the three is present, see Pls.' Br. passim; Pls.' Resp. passim.
Plaintiffs do cite one line of evidence that plaintiffs allege was not available at the trial of liability, arguing that dredging records "obtained in the damages phase of this matter demonstrate that the United States is responsible for between 60% and 70% of the erosion to Plaintiffs' properties." Pls.' Br. 23; cf. DX 34a (updated dredging data). However, Dr. Nairn's initial expert report contained a thorough analysis of the sediments dredged from the St. Joseph Harbor since the 1860s. See DX 1 (Nairn Report) 3-47 to 3-49, 3-85 to 3-86. Plaintiffs do not argue that the dredging data analyzed by Dr. Nairn were unavailable to them before the trial of liability. See Pls.' Br. passim; Pls.' Resp. passim; cf. DX 34 (dredging data presented at the trial of liability). Nor do plaintiffs explain how the dredging data now available differ from the data available to plaintiffs at the trial of liability. See Pls.' Br. passim; Pls.' Resp. passim.
Plaintiffs' expert witness, Dr. Mackey, examined the percentage of the dredged material dumped at a confined disposal facility against the percentage used for mitigation, concluding that the dredged material contains more sandy material appropriate for beach nourishment than Dr. Nairn calculated. PX 140 (Mackey Response to Nairn) 8-10.97 However, plaintiffs do not state that records of where dredged material was dumped were unavailable before the previous trial. See Pls.' Br. passim; Pls.' Resp. passim. Dr. Mackey also concludes, on the basis of the dredging records, that Dr. Nairn's estimate of the quantity of sediment delivered to the inner harbor by the St. Joseph River is 15% too low.98 See PX 140 (Mackey Response to Nairn) 8-10. Plaintiffs do not state, however, how this figure differs from the figure that could have been derived from dredging records available to them at the trial of liability had they retained Dr. Mackey at that time to make such a calculation. See Pls.' Br. passim; Pls.' Resp. passim. Plaintiffs therefore provide the court no basis on which to conclude that the dredging data they cite contains new information that warrants a departure from the law of the case.
The balance of the evidence relied upon by plaintiffs for their contention that the jetties cause 60 to 70% of the erosion to plaintiffs' properties consists of expert opinions that also could have been presented at the trial of liability. See Pls.' Br. 21-25. Dr. Mackey, observing the types of soil at the surface in the watershed that feeds the St. Joseph River and its tributary, the Paw Paw River, concludes that the sediment carried by the St. Joseph River contains a larger sand component than Dr. Nairn determined. See PX 140 (Mackey Response to Nairn) 3 (stating that Dr. Nairn "significantly underestimated by 35 to 40%" the amount of sand the St. Joseph River contributes to the littoral zone). Dr. Mackey buttresses this conclusion by estimating that the dams along the St. Joseph and Paw Paw Rivers trap less sand than Dr. Nairn determined, see id., and by stating that higher water flows during storms and snow melt would cause the rivers to carry more sediment than Dr. Nairn determined,99 see id. at 8 (describing the role of "episodic events" and "flood pulses"); Tr. 2957:2-2958:8 (Mackey) (describing the role of "pulses" caused by major storms and snow melt). Plaintiffs could have presented this type of evidence at the trial of liability; defendant, in fact, did so. See, e.g., DX 1 (Nairn Report) 3-67 to 3-108 (describing Dr. Nairn's analysis of sediment delivered to the littoral zone by the St. Joseph River).
The court is not compelled by "the discovery of new and material evidence," Toro Co., 383 F.3d at 1336, or by a determination that its previous finding is "is clearly incorrect and its preservation would work a manifest injustice," id. (quotation marks omitted), to depart from its conclusion that, if unmitigated, the jetties are responsible for 30% of the erosion in plaintiffs' zone.
2. The Effectiveness of Defendant's Mitigation Efforts
In its Liability Opinion, the court found that the Corps began to place dredged material in the littoral zone south of the jetties in 1970. Liability Op., 78 Fed. Cl. at 654-55. In 1972, the Corps began "sidecasting" dredged material into the littoral zone by extending a pipe over the south jetty and pumping dredged material through it. Id. at 654. In 1976, the Corps began a formal mitigation program to place beach nourishment materials in the littoral zone, replacing the sand blocked by the jetties. Id. at 655. Noting that "the Corps' effect on erosion is at issue and not the purpose of measures that could [a]ffect mitigation; mitigation incidental to another activity carries no less weight than purposeful mitigation," the court found that mitigation of the erosion caused by the jetties began in 1970. Id. The question now before the court is the effectiveness of defendant's mitigation efforts in preventing the erosion that would have been caused by the jetties.
Defendant argues that the sediment budget developed by Dr. Nairn "demonstrates that, since 1970, the Corps of Engineers' beach nourishment program has fully compensated for the impact of any erosion the jetties at the St. Joseph Harbor have caused." Def.'s Br. 14. In fact, Dr. Nairn determined that the volume of beach nourishment material placed by the Corps has more than compensated for the volume of material removed by the jetties since 1970. See Tr. 2746:25-2747:1 (stating that the sediment budget "shows that there was no impact since 1970"); Tr. 2831:2-24 (Nairn) (stating that, omitting the coarse fraction of the nourishment materials trucked in by the Corps, "there is still an overall surplus"); DX 155 (Nairn Composition Report) 25, Table 3.2 (revised sediment budget), columns xxi(a), xxi(b) (reflecting that the net result of the sand removed from the littoral system by the jetties and the sand added to the littoral system by the Corps' placement of beach nourishment materials is a net gain in sand in Dr. Nairn's study area).100 Although not argued by defendant, see Def.'s Br. passim; Def.'s Resp. passim, Dr. Nairn also determined that the rate of lakebed downcutting in much of plaintiffs' zone was lower in the time period after mitigation began, confirming Dr. Nairn's view of the effectiveness of the mitigation program, see DX 155 (Nairn Composition Report) 4-131.
Notwithstanding the evidence presented by defendant that the mitigation program has been successful, plaintiffs argue that the mitigation program cannot have been effective because the Corps failed properly to administer it and because local wave conditions prevent nourishment materials from reaching the shoreline. Pls.' Br. 26-31. Summarizing the alleged flaws in defendant's mitigation program, plaintiffs conclude that "there is no actual nourishment program. Rather, there is a dredging program, and not one of the key factors for an effective beach nourishment program . . . are taken into account." Id. at 30.
a. Administration of the Mitigation Program
Plaintiffs have not created their own sediment budget or modified Dr. Nairn's sediment budget to reflect the deficiencies that plaintiffs allege exist in the Corps' mitigation program. See Pls. Br. passim; Pls.' Resp. passim. Nor have plaintiffs developed a comprehensive study of the effectiveness of the Corps' mitigation program. See Pls. Br. passim; Pls.' Resp. passim. Instead, plaintiffs simply assert that, because of flaws in the implementation of the Corps' mitigation program, "the United States' mitigation efforts have been unsuccessful." Pls.' Br. 26 (capitalization omitted). However, the only comprehensive examination of the results of the Corps' mitigation efforts, created by Dr. Nairn, indicates that defendant has successfully mitigated all of the erosion damage caused by the jetties to properties located along sandy sections of shoreline since 1970. See DX 155 (Nairn Composition Report) 25, Table 3.2 (revised sediment budget). Dr. Nairn reached this conclusion based both on the erosion rates he projected by creating a sediment budget and the erosion rates directly observed in plaintiffs' zone. See id., columns xxi(a), xxi(b) (showing projected and historical erosion rates from 1836 to 2005).
Plaintiffs' criticisms of the Corps' mitigation program are unpersuasive. Plaintiffs argue that "beach nourishment requires, at a minimum, yearly monitoring of beach conditions at the nourished site."101 Pls.' Br. 27. Plaintiffs allege that there were gaps of up to 18 months in placement of nourishment materials and that a portion of the dredged material was placed at a disposal facility or used for construction purposes rather than being placed in the littoral zone. Id. at 28. Plaintiffs also contend that, "[a]s established in the liability phase of the trial, beach nourishment material must have the same physical properties as the natural material on the beach and nearshore." Id. at 27 (citing, inter alia, Liability Op. 78 Fed. Cl. at 630). Plaintiffs assert that "a substantial portion of the beach nourishment placed by the United Stated did not have the same physical properties at the natural material." Id.
However, because "the Corps' effect on erosion is at issue," Liability Op., 78 Fed. Cl. at 655, rather than the techniques used by the Corps to mitigate erosion, the ultimate issue is whether the Corps' mitigation efforts have been successful. Plaintiffs have developed no comprehensive study of the effect of the mitigation program to dispute the sediment budget developed by Dr. Nairn.102 See Pls.' Br. passim; Pls.' Resp. passim. Dr. Nairn's sediment budget indicates that, regardless of any potential flaws in the Corps' program, it has been effective.103 See DX 155 (Nairn Composition Report) 25, Table 3.2 (revised sediment budget). Furthermore, the court finds plaintiffs' criticisms of the Corps' mitigation program unpersuasive.
In its Liability Opinion, the court found that "the nourishment program needs to provide sediment that has the same physical characteristics as the shore that is to be nourished." Liability Op., 78 Fed. Cl. at 630 (internal quotation marks omitted). Plaintiffs are correct that some of the nourishment material placed by the Corps was transported from elsewhere and was, on average, more coarse than the natural material on which it is placed. Id. at 629. The court found that the coarse sediment is "at best ineffective and will not be considered part of mitigation as to plaintiffs' properties." Id. at 630. In light of the court's finding, Dr. Nairn revised his sediment budget, examining the grain size distribution of the sediment brought from elsewhere to determine how much of it was too coarse to be effective nourishment material.104 DX 155 (Nairn Composition Report) 19-23. After determining that 50% of the sediment was too coarse to serve as effective nourishment material under the court's ruling, id. at 23, Dr. Nairn concluded that, regardless, the Corps had completely mitigated the erosion caused by the jetties, see id. at 26 (stating that "from 1970 to 2005[,] more sand was supplied than necessary to compensate for the impact of the harbor and operations"); cf. id. at 25, Table 3.2 (revised sediment budget). Plaintiffs do not contend that Dr. Nairn has inaccurately calculated the portion of trucked sediment that the court found ineffective as nourishment material at the trial of liability. See Pls.' Br. 26-30.
Plaintiffs argue that gaps in the beach nourishment program "exacerbated the already sand[-]starved condition of [p]laintiff[s'] zone, which contributed to further lakebed downcutting." Id. at 28 (citing Tr. 616:3-15 (colloquy between Dr. Mackey and plaintiffs' counsel)). However, plaintiffs do not attempt to quantify the effect of the gaps in beach nourishment and do not state how often they occurred. See Pls.' Br. 26-30; cf. Tr. 616:7-10 (Mackey) (stating that "if you put a pile of sand in the littoral zone[,] it will gradually erode away, but if you do it on a fairly regular basis[,] you will maintain a fairly continuous sediment supply," but not stating whether the gaps in nourishment were sufficiently long for the piles of nourishment material to fully "erode away"). Furthermore, plaintiffs' theory that gaps in the nourishment program made the program ineffective appears to be premised on the lakebed adjacent to their properties being cohesive, which the court has found, with one exception, to be incorrect. See supra Part III.B. (discussing shoreline composition). In the testimony cited by plaintiffs, Pls.' Br. 28, Dr. Mackey testified that "if you have gaps in the beach nourishment program[,] you're going to have gaps in the sediment supply[,] which will cause thinning of the near shore sands and exposure of the underlying cohesive materials and actually accelerate the lake bed downcutting process," Tr. 616:11-15 (Mackey). Sandy shorelines erode differently than cohesive shorelines and can reconstitute themselves over time. See supra Part III.B.3.d (discussing shoreline behavior). Plaintiffs do not analyze the effect of gaps in the placement of beach nourishment materials on a sandy shoreline.105 See Pls.' Br. passim; Pls.' Resp. passim.
b. Wave Conditions and Placement of Nourishment Material
Plaintiffs also argue that "the effectiveness of beach nourishment also depends on the orientation of waves." Pls.' Br. 29. Plaintiffs state that the jetties diminish the energy of waves approaching from the north and northwest, creating a "shadowing effect." Id. Plaintiffs state that "[t]hese waves are prevalent and, therefore, placing beach nourishment close to the jetties diminishes its effectiveness." Id. Plaintiffs conclude that, "[c]onsistent with this principle, the Corps (and Dr. Nairn) recommended that beach nourishment be placed at Shoreham, much further south from the St. Joseph jetties than the current placement site." Id. Defendant responds that "[p]laintiffs' experts concede that their analysis did not constitute an effort to precisely locate each wave in the shadow zone, but was merely illustrative of the problem of a shadow zone generally." Def.'s Br. 14. Relying on hydrodynamic modeling performed by Dr. Nairn, defendant argues that nourishment material is, in fact, carried south to plaintiffs' zone notwithstanding the shadow zone south of the jetties. See id. at 14-15.
In his report, plaintiffs' expert witness, Dr. Meadows, writes that "[a]reas of coastline that are artificially sheltered from incident wave action (shadow zones) become traps of sediment, receiving insufficient energy to move nearshore materials along the beach." PX 142 (Meadows Wave Condition Report) 1. Based on a wave rose106 in the expert report that Dr. Nairn drafted for the trial of liability, Dr. Meadows calculated the frequency of waves approaching the shore from different directions. See id. at 3, 4, Fig. 2 (wave frequency chart). Eliminating waves that he believed would be blocked by the jetties, Dr. Meadows concluded that the nourishment material placed by the Corps "is exposed to direct wave attack and corresponding [southward transport] less than 19.65% of the time." Id. at 5. In contrast, "material placed in this same location is transported north [(]back toward the harbor structures) approximately 39.39% of the time." Id. at 6. As a result, "a good portion of the material that is placed there ends up causing this southern fillet to grow." Tr. 380:15-17 (Meadows).
However, Dr. Meadows' analysis "was intended to be demonstrative of the problem" created by shadow zones. Tr. 378:20-21 (Meadows). Dr. Meadows did not "determine the details of that transport." Tr. 407:15-19 (colloquy between Dr. Meadows and defendant's counsel). Dr. Meadows did not perform hydrodynamic modeling or conduct measurements of the actual wave conditions. See PX 142 (Meadows Wave Condition Report) passim. Dr. Meadows agreed that "all [he was] trying to show was if you put nourishment anywhere near a shadow zone, you can run into problems with the wave action." Tr. 410:12-15 (colloquy between Dr. Meadows and plaintiffs' counsel). Dr. Meadows further agreed that his "only opinion today is that the nourishment . . . should be placed well away from a shadow zone." Tr. 410:18-20 (colloquy between Dr. Meadows and plaintiffs' counsel).
In contrast, Dr. Nairn did perform hydrodynamic and sediment transport modeling, which Dr. Meadows agreed would allow Dr. Nairn to "determine the details of that transport." Tr. 407:10-408:4 (colloquy between Dr. Meadows and defendant's counsel). Dr. Nairn characterized Dr. Meadows' shadow zone analysis, which only considered the percentage of deepwater waves approaching from each direction, see PX 142 (Meadows Wave Condition Report) 4, Fig. 2 (wave frequency chart), as "very simplistic," Tr. 2609:19 (Nairn). Dr. Nairn employed his engineering firm's "in-house numerical model," called HYDROSED, which Dr. Nairn states "has been verified through laboratory experiments as well as field measurements and has been applied extensively to several projects by Baird & Associates in the past few years." DX 1 (Nairn Report) 3-50. Dr. Nairn explains that "[f]or a given wave condition, HYDROSED can provide a full spatial description of nearshore currents and sand transport around the harbor." Id.
Describing the results of his numerical modeling, Dr. Nairn disagreed with the hypothesis "that somehow if you place the sand in the wrong place and it goes to the north instead of the south, it's lost." Tr. 2611:16-21 (Nairn). Dr. Nairn explained that, because the angle at which the waves approach the shore changes as they encounter shallower water, northerly currents—those that approach from the north—strike the shore further north than Dr. Meadows determined.107 See Tr. 2609:18-2610:2 (Nairn). Although these northerly waves do split when they reach the shore, carrying some nourishment material to the north, this sediment is largely caught in an eddy, which carries the sediment north to the jetty, west along the jetty until the sediment rejoins currents traveling south, and then back to shore, Tr. 2608:17-2609: 17 (Nairn); see also DX 1 (Nairn Report) 3-59, Fig. 3.16(a), 3-60, Fig. 3.16(b) (maps showing nearshore currents and sand transport vectors during a storm from the northwest).
Dr. Nairn testified that southerly conditions—those in which currents approach from the south—occur "quite often," Tr. 2612:3-4 (Nairn), and also play a role in carrying nourishment material to plaintiffs' zone. As currents approach from the south, they move north toward the jetties, are deflected offshore by the jetties and slow as they move away from shore. Tr. 2612:2-14 (Nairn); see also DX 1 (Nairn Report) 3-61, Fig. 3.17(a), 3-62, Fig. 3.17(b) (maps showing nearshore currents and sand transport vectors during a storm from the southwest). As the currents slow, they deposit sand in a large bypassing shoal, Tr. 2612:11-14 (Nairn), where it accumulates, "waiting for northerly waves to then take it back into the system to the south," Tr. 2611:13-15; see also DX 1 (Nairn Report) 3-61, Fig. 3.17(a), 3-62, Fig. 3.17(b) (maps showing nearshore currents and sand transport vectors during a storm from the southwest).108 Therefore, even when the currents reaching the dredging material are approaching from the south, "almost all of the dredged sand that may be carried in this direction will eventually return to the shore to the south via the southward-directed current and bypassing pathway." DX 1 (Nairn Report) 3-67.
Dr. Nairn confirmed his modeling by verifying that nourishment material that was carried north has not built up on the fillet beach south of the jetties. See Tr. 2613:11-22 (Nairn). Summarizing his findings, Dr. Nairn stated that, under southerly conditions, sand is directed toward the fillet beach south of the jetties:
We know it's not growing. [The sand gets] forced off into this . . . shoal. We know it's not growing. We're tracking its growth. So, there's nowhere else that the nourishment sand can go but [south] during the northerly waves [and] come back, as I've shown, to reach the shoreline and continue to the south. Tr. 2613:17-22 (Nairn). Plaintiffs offer no hydrodynamic modeling to contest Dr. Nairn's analysis. See Pls.' Br. passim; Pls.' Resp. passim.
Plaintiffs argue that, consistent with the practice of not placing nourishment material in a shadow zone, "the Corps (and Dr. Nairn) recommended that beach nourishment be placed at Shoreham, much further south from the St. Joseph jetties than the current placement site." Pls.' Br. 29 (citing, inter alia, PX 24 (1997 Report) 88). Plaintiffs are correct that the 1997 Report, authored by Dr. Nairn with others, see DX 40 (1997 Report) i, concluded that "[i]t would be much more effective to place the entire annual allotment of beach nourishment (or at least the trucked coarse sediment) [further south,] where it would be 100 percent effective in supplying the downdrift shores," id. at 88. The 1997 Report theorized that a large lakebed depression "has been a sink, possibly for up to 50 percent of the coarse sediment placed in the feeder beach area." Id. at 87. The 1997 Report also theorized that "perhaps as much as 50 percent of the sand placed in the feeder beach area (particularly dredged finer sediment) ends up back in the navigation channel from where it was originally removed (and will be removed again)." Id. The 1997 Report proposes that both of these problems could be avoided by placing nourishment material further south. See id. at 87-88.
Dr. Nairn has since determined that the findings of the 1997 Report are inaccurate. With respect to the nourishment material that the 1997 Report predicted would be carried into the navigation channel, Dr. Nairn noted that this conclusion was made "without the benefit of [two-dimensional] numerical modeling at the harbor mouth (of waves, currents and sediment transport) and sediment budget analysis performed in support of this report." DX 1 (Nairn Report) 3-66. This numerical modeling indicates that "when sand is transported towards the north . . . it will eventually encounter a stronger southward-directed current that extends off the end of the jetties." Id. at 3-66 to 3-67. Dr. Nairn further stated that "[i]f sand was being re-deposited in the navigation channel (i.e.[,] after it was dredged and placed on the south side of the jetties), then it would be expected that the dredging quantity for the outer channel would be accelerating rapidly." Id. at 3-67. However, "There is no indication of this kind of increase in the dredging record data." Id.
Regarding the coarse material that the 1997 Report concluded is lost to an offshore depression in the lakebed, Dr. Nairn testified at the trial of liability that "this was based on an `incorrect assumption,' because a sand bar forms at the depression that `provides the pathway or bridge for sediment to get through that . . . area.'" Liability Op., 78 Fed. Cl. at 640 (citations omitted). The "very prominent long shore bar" described by Dr. Nairn, Tr. 2626:13 (Nairn), is clearly visible on the bathymetric map contained in Dr. Nairn's report, see DX 1 (Nairn Report) 3-69, Fig. 3.19 (1999 bathymetric map). Dr. Nairn testified that the sand bar serves as "the delivery path for sand past the C&O railway revetment, past the end dock, towards the south of the [p]laintiffs' property. So[,] that's sort of like the bridge or highway along which most of the sand runs now because there isn't a beach there." Tr. 2616:16-21 (Nairn).
Again, as at the trial of liability, plaintiffs "offer no expert critique countering Dr. Nairn's more recent conclusions about the [deposition of nourishment materials in the] depression," Liability Op., 78 Fed. Cl. at 640, or in the navigation channel, see Pls.' Br. passim; Pls.' Resp. passim. Apart from Dr. Meadows' description of the concept of shadow zones, plaintiffs do not offer any analysis of the local hydrodynamics that indicates that nourishment material is not carried south to their properties. See Pls.' Br. passim; Pls.' Resp. passim. Plaintiffs do not demonstrate where nourishment material is accreting over time if shadowing by the jetties prevents it from being carried south. See Pls.' Br. passim; Pls.' Resp. passim. Nor do plaintiffs dispute Dr. Nairn's conclusion, see DX 1 (Nairn Report) 3-67, that the dredging totals do not reflect a growing quantity of nourishment materials carried north into the navigation channel, see Pls.' Br. passim; Pls.' Resp. passim. Plaintiffs' argument that Dr. Nairn's testimony is "not credible" because he has reached different conclusions in prior research, Pls.' Br. 30 (capitalization omitted), is insufficient—without evidence contradicting his conclusions—to persuade the court that Dr. Nairn has doctored his conclusions for the purposes of this litigation, see supra note 85 (addressing plaintiffs' argument that Dr. Nairn's opinions are "bought and paid for" (quoting Liability Op., 78 Fed. Cl. at 618)).
In light of the evidence presented at trial, the court finds that, with regard to every property but the Werger property, which is located along a cohesive section of shoreline, see supra Part III.B, the Corps has successfully mitigated all of the erosion damage caused by the jetties between 1970 and the publication of Dr. Nairn's revised sediment budget in 2009.
D. Damages
1. The Ordinary High Water Mark
Because plaintiffs' properties are encumbered by the government's navigational servitude, no just compensation must be paid for erosion below and within the ordinary high water mark when the government acts to improve navigation. Liability Op., 78 Fed. Cl. at 655-57; see generally OHWM Op., 71 Fed. Cl. 501 (discussing the definition of the term "ordinary high water mark"). It is therefore necessary to determine what property has eroded above and outside of the ordinary high water mark.
To delineate the ordinary high water mark for plaintiffs' properties and the comparable properties considered by defendant's appraiser, Mr. Burgoyne, Dr. Nairn interpreted "historic aerial photography and satellite imagery."109 DX 172 (Nairn OHWM Report) 1. Dr. Nairn delineated the ordinary high water marks as they stood in "1950, 1970, 2000, 2009, the purchase date of the property, and sometimes the sale date of the property."110 Tr. 2339:21-23 (Nairn).
Dr. Nairn explained at trial that the properties fell into three different types, which required him to use three different techniques to delineate the ordinary high water mark. See Tr. 2341:4-23 (Nairn); see also DX 172 (Nairn OHWM Report) 12-15 (describing the three techniques). When a property had shore protection, Dr. Nairn "delineated the ordinary high water mark along the shore protection."111 Tr. 2343:4-6 (Nairn). When a property's nearshore was characterized by bluffs, Dr. Nairn "delineated the ordinary high water mark at the toe of the bluff. . . . Tr. 2343:8-10 (Nairn). Dr. Nairn noted that "often there's a different color in soil, [or a] change in vegetation. . . ." Tr. 2343:8-12 (Nairn). When a property's nearshore area was characterized by sand dunes, which, in some cases, covered shore protection structures, the "[o]rdinary high water mark is defined as the edge of the vegetation. It's not just ephemeral vegetation, like young marine grass or dune grass, but it's the—it's the more permanent vegetation. . . ." Tr. 2343:16-22 (Nairn).112
Dr. Nairn plotted the ordinary high water mark "using GIS, geographic information systems, which is essentially a tool that allows you to work on screen with a digital map." Tr. 2344:3-5 (Nairn). When no aerial or satellite photograph was available for a particular year, Dr. Nairn interpolated the line position using "an interpolation technique within the GIS tools." Tr. 2350:2-3 (Nairn); see also Tr. 2350:12-14 (Nairn) (stating that, in contrast, Dr. Meadows "took the two paper maps from my [report presented at the trial of liability] and eyeballed the position between those two lines"). To calculate the size of a property at a particular date, Dr. Nairn used the ordinary high water mark and the property boundaries listed on the property records maintained by Berrien County. Tr. 2351:22-2352:3 (Nairn).
Between 1950 and 2000, the ordinary high water mark on eighteen of the forty parcels moved lakeward, meaning that eighteen properties were larger in 2000 than they were in 1950. DX 172 (Nairn OHWM Report) 54, Table 6.6 (table of property lost and gained); Tr. 76:18 (Burgoyne) ("Half the properties gained land."); Def.'s Br. 32 n.9. Dr. Nairn observed that the ordinary high water mark moved lakeward on two types of properties: those with shore protection built, not at the ordinary high water mark, but "out in the lake," and certain of the properties with sandy beaches. Tr. 2362:16-2363:10 (Nairn). Regarding the properties with beaches, Dr. Nairn explained that as lake levels rise and fall over time, "the ordinary high water mark is moving back and forth, not just inland as it would in a bluff case." Tr. 2363:11-13 (Nairn). Accordingly, "the 2000 and 2009 positions happen to be further lakeward in a lot of the sand properties to the south because the beach was bigger in 2000 than it was in 1950 in those cases." Tr. 2363:13-16 (Nairn).
2. Plaintiffs' Evidence of Damages Between 1950 and 2000: Econometric Analysis Performed by Dr. Moore
a. Dr. Moore's Analysis and Conclusions
Because plaintiffs bear the burden of proving the amount of just compensation to which they are entitled for severance damage, Miller, 223 Ct. Cl. at 383-84, 620 F.2d at 828, the court first considers the evidence of damages presented by plaintiffs.
"The concept of just compensation . . . cannot be reduced to a formula. . . ." Ga.-Pac., 226 Ct. Cl. at 106, 640 F.2d at 336 (citing Miller, 317 U.S. at 375). Nor can just compensation "be confined to inexorable rules." Id. (citing United States v. Toronto, Hamilton & Buffalo Navigation Co., 338 U.S. 396, 402 (1949)). However, the "standard" method of proving severance damages is to determine the value of a property before and after a taking occurs. Id.; see United States v. Va. Elec. & Power Co., 365 U.S. 624, 632 (1961) (stating that comparing the value of a property before and after a taking is "indeed the conventional method"). "This is generally the simplest and perhaps the most widely used approach in severance damage determinations." Ga.-Pac., 226 Ct. Cl. at 106, 640 F.2d at 336.
Plaintiffs did not present evidence of the value of their properties before or after the erosion caused by the government occurred. See Pls.' Br. passim; Pls.' Resp. passim. Plaintiffs instead adopt the hypothetical appraisals presented by defendant's expert witness, Mr. Burgoyne, of the values of plaintiffs' properties in January 2000 with their 1950 dimensions and January 2000 improvements. See, e.g., Pls.' Br. 36. Rather than presenting evidence of the value of their properties after the erosion took place, plaintiffs presented the testimony of Dr. Moore, an economist, who determined that, although sale prices of properties affected by the jetties rose in the time period after the publication of the 1999 Report, they may have risen less than did sale prices in areas not affected by the jetties.113 Tr. 149:18-19 (Moore). Plaintiffs determine the amount of damage to their properties by calculating how much their properties' pre-erosion values, as determined by Mr. Burgoyne, failed to increase. See Pls.' Br. 38; PX 275 (table showing plaintiffs' estimates of the erosion damage to each property); see also Tr. 154:4 (Moore) (stating that he did not prepare PX 275).
Dr. Moore "employed a hedonic regression model to determine the effect of the United States'[ ] [a]nnouncement on the value of the [p]laintiff[s'] properties." Pls.' Br. 37. Hedonic regression "looks at the price of a good and tries to determine how much of that price is due to each of the attributes that enter into the market pricing." Id. (citing Tr. 132:6-133:3 (colloquy between Dr. Moore and court)). For example, a hedonic model for the price of a house may include variables for the "number of bedrooms, square footage, [and] the lot size." Tr. 133:1-2 (Moore).
Dr. Moore states that the hedonic pricing model "is directly applicable to computing the economic effects of discrete `events' as seemingly disparate as environmental contamination, an attempt to fix prices, a violation of the securities laws, or beach erosion due to a taking." PX 149 (Moore Report) 5. In a case involving securities fraud, for example, "[t]he price change around the time of the event would give a market-based estimate of the perceived fraud." Id. at 6. Dr. Moore testified that this type of analysis is called an "event study." Id. at 5; Tr. 176:25-177:1 (Moore).
To create his dataset, which contained 107 observations, PX 149 (Moore Report) Ex. 5, Dr. Moore used data on sales of properties up to three years before and three years after the publication of the report, Tr. 204:21-24 (colloquy between Dr. Moore and defendant's counsel), a time period that "equates to the years 1997 through 2003,"114 Tr. 206:16-19 (colloquy between Dr. Moore and defendant's counsel). Dr. Moore described in his report how he coded his data. Dr. Moore "created the dependent variable `price per lakefront foot [(LFF)]," by dividing selling price by reported lake frontage." PX 149 (Moore Report) 15. He created indicator variables for whether each property was located inside the affected area (treatment) and whether it was sold after the announcement (post), as well as a variable for the interaction of these two indicator variables (treatpost). Id. Because of "data limitations," Dr. Moore used three control variables: "a measure of square footage of the structure and dummy indicators of LFF between 100 and 150 feet, and LFF greater than 150 feet—to control for differences in price due to differences in the size of the house and for potential nonlinearities in the effects of LFF on price."115 Id. at 16 (footnote omitted).116 Dr. Moore noted that "[t]o the extent square footage is correlated with other characteristics (number of rooms, number of bathrooms), controlling for square footage will capture price variation due to these features too." Id.
Dr. Moore described his regression analysis as a "difference-in-differences" approach. PX 149 (Moore Report) 8. At trial, Dr. Moore summarized his analysis as follows:
I took the prices before 2000 for houses in the non-erosion zone, I took the prices before 2000 for houses in the erosion zone. I looked at the difference, the average difference in prices there. That established a baseline difference in prices that would reflect different characteristics in the neighborhoods and the properties . . . in the erosion zone, and outside the erosion zone. . . . And then I . . . made the same comparison of prices . . . after January of 2000, again comparing the non-erosion zone to the erosion zone. I observed the average difference in prices there. And then I compared the pre-announcement difference to the post-announcement difference, and the difference in those differences is what's interpreted as the treatment effect . . ., [that is,] the effect of the announcement on residential real estate prices in the erosion zone relative to a control group.
Tr. 146:5-25 (Moore).
Dr. Moore first conducted "a simple comparison of mean differences in selling prices pre- and post-announcement [to give] an unconditional estimate of the change in relative values after the announcement." PX 149 (Moore Report) 15-16. This first comparison considered only the change in price per lakefront foot of property, and did not control for lakefront footage or for the square footage of any structure built on the property. See id. at 16, Ex. 3. In his report, Dr. Moore writes that, using this approach, the changes in property values were "roughly identical" in the affected area and in the control group. Id. at 17. On cross-examination, Dr. Moore agreed that, considering only the price of property per lakefront foot, listed in Exhibit 3 of Dr. Moore's report, property values actually increased more in the affected area (142%) than in the control group (115%). Tr. 221:19-223:7 (colloquy between Dr. Moore and defendant's counsel).
Dr. Moore then controlled for differences in the square footage of the structures on each property, finding that, when the square footage of structures on the property is controlled for, property values increased more in the control group than in the affected area. See PX 149 (Moore Report) 18. Controlling for the square footage of the structure, Dr. Moore calculated that the effect of the 1999 Report on the market value of a house in the treatment group—that is, a house located within the affected area—was either 13% or 27%, depending on whether Dr. Moore used or omitted dummy indicators that describe whether the property is between 100 and 150 lakefront feet in width or greater than 150 feet.117 Id. Dr. Moore states in his report that "[n]either the 13% or 27% estimates are significantly different from zero. Given the small number of observations in the relevant cells, this is not surprising." Id.
In his final regression specification, Dr. Moore found that removing the five properties that he considered outliers increased the size of the difference-in-differences estimator. Id. Excluding outliers, Dr. Moore's model "indicates prices are about 42% lower in the erosion zone after the disclosure, [a difference] greater than its standard error, albeit statistically insignificant." Id.
Regardless of whether Dr. Moore controlled for the square footage of structures on each property and eliminated sales that he considered to be outliers, Dr. Moore concluded in his report that the effect of the 1999 Report on sale prices in the affected area was statistically insignificant. See id. at 16-18.
Citing Dr. Moore's testimony, plaintiffs argue that "the market adjusted after January 2000 to account for the United States'[ ] [a]nnouncement that the erosion to [p]laintiffs' properties was permanent and the land lost was not coming back." Pls.' Br. 37. Plaintiffs interpret Dr. Moore's conclusion to be that "there was a 42% diminution in value to the [p]laintiff[s'] properties as a result of the [a]nnouncement."118 Id. (citations omitted); see also Pls.' Resp. 5 (stating that "the market value of [p]laintiffs' properties substantially declined after January 2000"). Applying Dr. Moore's estimated coefficient of -42% to the appraised value of the plaintiffs' properties in January 2000 with their 1950 dimensions and January 2000 improvements, as determined by defendant's expert witness, Mr. Burgoyne, plaintiffs calculate that the "value of the land taken as a result of the [a]nnouncement is collectively $19,113,621." Pls.' Br. 38.
b. The Limitations of Dr. Moore's Analysis
Defendant argues that Dr. Moore's event study is inapplicable to the question of just compensation because "Unlike Mr. Burgoyne's appraisals—which attempt to capture the value of different properties at the same point in time—Dr. Moore's analysis attempts to track movement in the prices of the same properties across different times." Def.'s Br. 30. Defendant further argues that "[e]ven if Dr. Moore's analysis was applicable to the question before the [c]ourt, [p]laintiffs' reliance on Dr. Moore's report does not account for the flaws that Dr. Moore himself acknowledges in his work." Id. at 30-31. Defendant lists three such flaws. "First, Dr. Moore acknowledges that the quantity of data he was provided is less than ideal for performing a regression analysis." Id. at 31 (citation omitted). "Second, rather than show a loss in value, Dr. Moore acknowledges that property values within the erosion zone increased generally after January 2000." Id. "Third, Dr. Moore did not control for any preexisting differences in the rates of increases in the prices before January 2000." Id.
Defendant is correct that Dr. Moore's analysis is unpersuasive. Although Dr. Moore's analysis of the data provided to him is credible, the limited dataset, the fact that Dr. Moore's estimates reflect unrealized appreciation rather than a loss in value, and Dr. Moore's failure to examine and—if necessary—control for preexisting trends in price increase for the treatment group and the control group, together with plaintiffs' application of Dr. Moore's analysis—which generalizes across plaintiffs' zone—to each individual property regardless of the actual erosion damage it suffered or did not suffer leave the court unconvinced that plaintiffs have carried their burden, see Miller, 223 Ct. Cl. at 383-84, 620 F.2d at 828, to prove their severance damages.
i. Insufficient Data
Defendant argues that "Dr. Moore acknowledges that the quantity of data he was provided is less than ideal for performing a regression analysis." Def.'s Br. 31. Plaintiffs respond that "[a]lthough Dr. Moore testified under cross-examination that he would `ideally' like more data, more importantly[,] he also testified that he performed a series of sensitivity tests to ensure that the results he obtained with the data he used were accurate and reliable." Pls.' Resp. 8 (citing Tr. 204:21-206:15 (colloquy between Dr. Moore and defendant's counsel)).119
Plaintiffs appear to conflate reliability—the ability to get the same results—with accuracy—the closeness of an estimate to its true value. Compare American Heritage Dictionary 13 (stating, as one definition of "accuracy," "[t]he ability of a measurement to match the actual value of the quantity being measured"), with id. at 1474 (stating, as one definition of "reliable," "[y]ielding the same or compatible results in different clinical experiments or statistical trials"). Dr. Moore's description of the sensitivity tests he performed appears to indicate that the sensitivity tests were a minor part of his analysis, see PX 149 (Moore Report) passim (not mentioning sensitivity tests), and that he was testing the reliability of his estimates by changing the parameters underlying his model, such as "varying the event window," Tr. 205:12-13 (Moore), which did not result in "a qualitative change in the results," Tr. 205:14-15 (Moore). Although both accuracy and reliability are important, Dr. Moore does not claim, and plaintiffs have not demonstrated, that Dr. Moore's sensitivity tests would also reflect the accuracy of his estimate.
Dr. Moore's discussion of confidence intervals120 and statistical significance concerns the accuracy of his estimates.121 Dr. Moore described his use of confidence intervals as follows: "once you establish a confidence interval, and you look at your data, and you see if your test statistic lies outside your confidence interval, then you can reject your [null] hypothesis. . . ."122 Tr. 237:18-21 (Moore). Notwithstanding that Dr. Moore calculated the difference-in-differences in four different ways, revealing a range of results, see supra Part III.D.2.a, Dr. Moore writes in his report that, using a 95% confidence interval, none of the results was significantly different than zero. See PX 149 (Moore Report) 16-18. At trial, Dr. Moore indicated that, with more data, he might have been better able to determine whether the effect of the publication of the 1999 Report on housing prices in the affected area was statistically significant: "[T]here are a number of. . . interpretations you could put on this. One would be that you just don't have enough observations to estimate it precisely." Tr. 231:23-232:1 (Moore); see also PX 149 (Moore Report) 18 ("Neither the 13% nor the 27% estimates are significantly different from zero. Given the small numbers of observations in the relevant cells, this is not surprising.").
Dr. Moore used a 95% confidence interval in his report, see Tr. 230:17-19 (colloquy between Dr. Moore and defendant's counsel), a threshold that, he states, is "standard in academic research," Tr. 244:2 (Moore); see also Tr. 230:19 (Moore) (stating that he used a 95% confidence interval "as a matter of course"). Plaintiffs cite two cases in which, plaintiffs argue in explanatory parentheticals, courts found that the use of confidence intervals lower than 95% satisfied a party's "burden of proof of the preponderance of the evidence." Pls.' Br. 37; cf. Tr. 238:16-17 (Moore) (stating that the confidence interval a researcher might employ "depends on the application"); Tr. 232:12-14 (Moore) ("I can't tell you what the burden of proof is that we have here.").
Regarding the statistical significance of his 42% difference-in-differences estimate, Dr. Moore remarked for the first time at trial that if the court adopted a "one-tailed" test (or a "directional hypothesis" test), that estimate would be statistically significant. Tr. 242:11-243:19 (Moore). Dr. Moore performed a series of calculations at trial, concluding that, using a 90% confidence interval and a one-sided hypothesis test, a finding of a 42% difference-in-differences estimate between the affected area and the control group would be significantly less than zero. Tr. 242:11-243:19 (colloquy between Dr. Moore and defendant's counsel). Plaintiffs contend that the court should adopt the lower threshold of a 90% confidence interval and find that their properties diminished in value by 42%. See Pls.' Br. 37. However, this is not the analysis recommended by Dr. Moore in his report. See PX 149 (Moore Report) 17-18.
It is unnecessary to determine whether use of a confidence interval lower than 95% would be sufficient to satisfy plaintiffs' burden. As explained below, see infra Parts III.D.2.b.ii-iii, and in light of the data limitations described previously, the court is persuaded by defendant's argument that other flaws in Dr. Moore's analysis make it less reliable than the appraisals conducted by Mr. Burgoyne. See Def.'s Br. 31. Whether, in Dr. Moore's model, his difference-in-differences estimate of the effect of the publication of the 1999 Report on sale prices in the affected area is statistically significant using a confidence interval lower than 95% does not change the court's analysis.
ii. Increase in Values
Defendant contends that, "rather than show a loss in value, Dr. Moore acknowledges that property values within the erosion zone increased generally after January 2000." Id. Defendant is correct that, according to Dr. Moore's analysis, in the three years after January 2000, prices in the affected area rose significantly from their levels during the three years before January 2000. See PX 149 (Moore Report) Ex. 3 (table of mean prices per lakefront foot of property); Tr. 149:2 (Moore) ("So prices are rising in both areas."). Dr. Moore agreed that, using the mean prices calculated in his Exhibit 3, prices in the affected area more than doubled, rising 142% per lakefront foot. See Tr. 221:19-223:24 (colloquy between Dr. Moore and defendant's counsel).
Accordingly, plaintiffs' assertion that "there was a 42% diminution in value to the [p]laintiff[s'] properties as a result of the [a]nnouncement," Pls.' Br. 37, is misleading. Dr. Moore's analysis, to the extent it shows anything of statistical significance, see supra Part III.D.2.b.i, does not show that plaintiffs' properties lost value because of the publication of the 1999 Report, but rather that they may have failed to appreciate in value as rapidly as certain other properties between 1997 and 2003 when controlling for lakefront footage and for the square footage of the homes built on the properties.123 See PX 149 (Moore Report) 16-18; Tr. 221:19-223:24 (colloquy between Dr. Moore and defendant's counsel) (agreeing that, when the square footage of the structures on the properties is not controlled for, mean prices increased more in the affected area than in the control group).
Plaintiffs have failed to demonstrate that their properties diminished in value as a result of erosion caused by the jetties. Plaintiffs cite no authority for the proposition that damages in a partial takings claim are better measured by unrealized appreciation rather than lost value. See Pls.' Br. passim; Pls.' Resp. passim. Neither do plaintiffs offer a methodology to translate the claimed unrealized appreciation into a loss of value compensable as a taking. See Pls.' Br. passim; Pls.' Resp. passim. Instead, plaintiffs simply treat the claimed amount of unrealized appreciation as lost value.124 See Pls.' Br. 37 (stating that "there was a 42% diminution in value of the [p]laintiff[s'] properties as a result of the [a]nnouncement").
The court does not consider whether, in the absence of the appraisals presented by defendant, or with the assistance of a more robust economic analysis, it would be possible to discern a loss of value from the unrealized appreciation of plaintiffs' properties. Plaintiffs bear the burden of establishing the just compensation to which they are entitled for severance damages by a preponderance of the evidence. See Miller, 223 Ct. Cl. at 383-84, 620 F.2d at 828. In light of the appraisals presented by defendant, which persuasively and directly establish the extent of the erosion damage to plaintiffs' properties between 1950 and 2000, see infra Part III.D.3, plaintiffs have not met their burden.
iii. Failure to Control for Differences in Preexisting Rates of Increase in Market Values
As Dr. Moore emphasized, "[I]n the differences-in-differences test, average differences between the affected and unaffected properties at baseline must remain constant over time, so that change in the relative values of the two groups of properties can be attributed to the erosion." PX 149 (Moore Report) 8.
Defendant contends that "Dr. Moore did not control for any preexisting differences in the rates of increases in the prices before January 2000." Def.'s Br. 31. Plaintiffs respond that "the United States omits critical testimony on this issue; namely, that Dr. Moore also testified that the differences in the rates of increase before the [a]nnouncement would be reflected in the higher mean [price per lakefront foot] and would therefore be properly controlled for." Pls.' Resp. 8. As his trial testimony and expert report indicate, however, Dr. Moore did not explore whether it was necessary to control for differences in preexisting price trends and—if necessary—control for them.125
Asked at trial if he had controlled "for any preexisting differences in the rates of increases in the prices in your regression," Tr. 216:12-14 (defendant's counsel), Dr. Moore responded, "I did not," Tr. 216:15 (Moore). Asked whether, in light of his decision not to control for different preexisting trends, he "really can't be sure" that the observed difference in prices is a result of the 1999 Report rather than preexisting differences in the rate of price increases between the properties, Tr. 216:18-25 (defendant's counsel), Dr. Moore responded, "I didn't do that, so I don't know what . . . the implications would be." Tr. 217:1-3 (Moore). Dr. Moore and defendant's counsel then engaged in the following colloquy:
Q . . . So at bottom, though, that leaves open, does it not, the possibility that the changes in prices that you see post-2000 may be, to some extent, influenced or caused by the rates of increases, preexisting differences in the rate increases, before January 2000?
A I'll grant you that. I think [that] if there are differences in the rates of increase before . . . the announcement, those would be reflected in the higher mean in one group more than the other. To a certain extent[,] they will be controlled for in the differences.
Tr. 217:14-25 (colloquy between Dr. Moore and defendant's counsel). Beyond his general statement that "[p]rice changes will reflect market participants' views of . . . all known factors that affect price," PX 149 (Moore Report) 4, Dr. Moore did not quantify—and the court declines to guess—the extent to which differences in mean prices could control for variation in preexisting trends, see id. passim; Tr. 117:1-251:19 (testimony of Dr. Moore).
Because Dr. Moore failed to control for differences in preexisting rates of price increase for properties in the affected area and in the control group, or to explain why it is unnecessary to do so, the court finds his conclusions unpersuasive.
iv. Plaintiffs' Application of Dr. Moore's Conclusions to Each Property Regardless of Actual Erosion
A final drawback to Dr. Moore's model is that—because he focuses on the publication of the 1999 Report as the event of interest, rather than the amount of actual erosion—it is difficult for the court, in a takings case, where the amount of actual erosion caused by the government is the issue, to apply Dr. Moore's results in a reasoned manner. Plaintiffs suggest that the court award the same proportion of damages to all plaintiffs. See Pls.' Br. 36-39.
Plaintiffs' approach to calculating damages is inappropriate because the extent of the erosion damage has been greater for some properties than for others. The property of one plaintiff "went from being a buildable lot to being an unbuildable remnant because [a] substantial portion is down in the lake." Tr. 79:11-13 (Burgoyne). The properties of other plaintiffs eroded, but are deep enough that most of the property remains and is buildable. See, e.g., DX 297 (Bodnar Appraisal) 11, Fig. A-6 (photograph of property showing variation of ordinary high water mark over time). Nearly half of the properties owned by plaintiffs grew in size between 1950 and 2000, owing to the deposition of sand or the placement of shore protection lakeward of the ordinary high water mark. See supra Part III.D.1; see, e.g., DX 295 (Anderson Appraisal) 11, Fig. A-6 (photograph of property showing variation of ordinary high water mark over time). To treat plaintiffs' damages as though each plaintiff were similarly situated would not accurately reflect the erosion damage that each has suffered.126
3. Defendant's Evidence of Damages Between 1950 and 2000: Appraisals Performed by Mr. Burgoyne
a. Mr. Burgoyne's Analysis and Conclusions
To quantify the extent to which the jetties have harmed plaintiffs' property values, defendant presented property appraisals proposed by Mr. Burgoyne. See Def.'s Br. 26-30 (discussing Mr. Burgoyne's appraisals). For each property, Mr. Burgoyne created three appraisals, two of which are relevant under the law of this case.127 See id. at 27-28. Both appraisals were prepared with a valuation date of January 2000, "`one reflecting the conditions of the land that existed in 2000 [(2000 appraisal)], [and] one reflecting the conditions of the land that existed in 1950 [(1950 appraisal)].'"128 Id. at 27 (quoting Tr. 98:20-25 (Burgoyne)). Both appraisals included the improvements that were present on the parcel in January 2000.129 Id. at 28 (citing Tr. 99:5-7 (Burgoyne)). Using a before-and-after analysis, defendant subtracts the second appraised value from the first to determine the amount of plaintiffs' damages. See id. at 31-33.
Mr. Burgoyne used a "direct sales comparison approach" in his appraisals, researching arm's length sales of like properties and adjusting for any differences. Tr. 2473:11-16 (Burgoyne). After examining a large number of sales, Mr. Burgoyne identified a set of comparable vacant and improved properties. Tr. 2476:8-20 (Burgoyne); see also DX 295 (Anderson Appraisal) 39 (list of comparable vacant properties). Mr. Burgoyne explained that "one attempts to choose comparables which are as similar as possible, which can mean they're physically similar in terms of size, zoning, highest and best use in terms of land." Tr. 103:16-19 (Burgoyne). For improved properties, the characteristics of the improvements should also be similar: "[W]hen selecting improved comparables, you would select homes of a similar size, of similar style, like ranch versus two-story. Similar vintage. One wouldn't want to appraise a brand new house with homes built in 1930, perhaps." Tr. 103:19-24 (Burgoyne). "[O]ne tries to limit the need to adjust for those [characteristics] by selecting properties that are as similar as possible." Tr. 104:2-4 (Burgoyne).
Mr. Burgoyne considered both the attributes of the local market generally and of each property specifically. Tr. 2474:9-14 (colloquy between Mr. Burgoyne and defendant's counsel). As to the market generally, Mr. Burgoyne considered multiple factors. He studied historical population changes, noting that "Berrien County experienced a boom then bust in population between 1970 and 1990 and has since had a relatively stable population since 1990."130 DX 295 (Anderson Appraisal) 29. He considered the balance of seasonal residents to full-time residents and noted that the balance is shifting toward full-time residents over time. Id. He considered the volatility of the local real estate market, concluding that "the subject market, being properties located on Lake Michigan in the northern part of the [c]ounty, is somewhat isolated from the general fluctuations in the local market." Id. at 27. He considered access to a highway and rail service, as well as the location of hospitals, the Whirlpool corporate headquarters and other employers. Id. He studied the local amenities available to property owners, noting that "St. Joseph, just north of the subject area, contains numerous activities to pursue, services, restaurants, and cultural amenities." Id. He noted that "[c]ertain areas north of the jetties enjoy amenities such as golf course frontage or proximity to the Yacht Club that impact their sales prices." Id. at 21. Mr. Burgoyne concluded that plaintiffs' properties are "well located in a highly desirable area." Id. at 29.
To determine the physical characteristics of plaintiffs' properties, Mr. Burgoyne relied upon personal observations and discussions with the property owners, supplemented by aerial photos and public records, including assessment records containing old property descriptions. Tr. 2487:11-2488:6 (Burgoyne). Mr. Burgoyne relied upon Dr. Nairn's delineation of the "physical dimensions and geographic characteristics for each scenario." Tr. 99:14-17 (colloquy between Mr. Burgoyne and defendant's counsel). Where Dr. Nairn's measurements conflicted with information listed on plaintiffs' deeds, Mr. Burgoyne resolved the conflict in favor of plaintiffs, using the higher of the numbers contained in plaintiffs' deeds and Dr. Nairn's measurements.131 Tr. 2489:10-16 (Burgoyne).
Mr. Burgoyne's appraisals addressed any anticipated erosion damage and the cost, where necessary, to install or repair shore protection to prevent the anticipated erosion. Mr. Burgoyne incorporated Dr. Nairn's analysis of the shore protection present on the properties. Tr. 83:18-20 (Burgoyne). Dr. Nairn determined what shore protection was present on the properties and how long it would last before new shore protection would be required. See Tr. 2511:2-13 (Burgoyne); DX 205 (Nairn Shore Protection Report) 75-111 (analyzing existing shore protection, its remaining lifespan, and the cost of upgrades and maintenance where necessary). Mr. Burgoyne described shore protection as "relatively ubiquitous" in the area around plaintiffs' properties. Tr. 2516:12 (Burgoyne). Analogizing his examination of shore protection to how he would appraise a house with a leaking roof, Mr. Burgoyne stated that if "the roof was actually leaking, one would subtract the cost to put a new roof on the house right then when you did your appraisal. . . . Conversely, if . . . it had 30 years left on the roof, they wouldn't put a cost in there for putting the roof on it." Tr. 2511:23-2512:8 (Burgoyne).
For vacant lots, Mr. Burgoyne calculated the price of each property based on a price per lakefront foot of property. Tr. 64:15-16 (Burgoyne). For improved properties, Mr. Burgoyne calculated the price of each property based on a price per square foot of the residence. Tr. 64:17-19 (Burgoyne). Mr. Burgoyne "appraised all the properties both as improved and vacant," because properties with modest residences may be worth more as vacant lots. Tr. 2485:19-23 (Burgoyne); but see Tr. 2486:19-25 (Burgoyne) (stating that Mr. Burgoyne appraised the Lahr property only as vacant, despite the presence of a residence, "because we knew the highest and best use was to tear the house down"). The market value that Mr. Burgoyne listed for each property treats the property as vacant if the "highest and best use was to knock down the older improvements." Tr. 2477:4-6 (Burgoyne); see also Tr. 2486:6-7 (Burgoyne) (stating that the property owned by the Smith plaintiffs had a higher market value when appraised as vacant).
In contrast to plaintiffs' interpretation of Dr. Moore's estimates, Mr. Burgoyne, when describing the impact of the 1999 Report on the market as a whole, stated that "there didn't appear to be any adverse reaction in the marketplace." Tr. 2494:17-19 (Burgoyne). Mr. Burgoyne stated that "lakefront property continued to increase [in value], peaking in late 2007, which is similar [when] compared to the overall nationwide market." Tr. 2494:20-23 (Burgoyne); see also Tr. 2535:4-5 (Burgoyne) (stating that Mr. Burgoyne also considered statewide real estate trends); DX 295 (Anderson Appraisal) 116 (stating that "[r]eview of the actual sales comparables gives no indication that an adjustment is warranted because a purchase was made before or after the date of taking as a result of the taking"); DX 295 (Anderson Appraisal ) 116 (noting the ongoing construction of new and expensive lakefront properties in the area and concluding that "[i]f there was any significant market impact from erosion . . ., one would also expect a market reluctance to make significant investments in new construction along the lake"). Mr. Burgoyne did not speculate as to why publication of the 1999 Report did not have an adverse effect on real estate prices, but did testify that "it's a lake that's subject to erosion and people know that." Tr. 2516:14-15 (Burgoyne). Mr. Burgoyne further testified that "shore protection is relatively ubiquitous." Tr. 2516:11-12 (Burgoyne).
Mr. Burgoyne concluded that 36 of the 41 parcels he appraised had the same market value with their 2000 characteristics as with their hypothetical 1950 characteristics. See DX 336 (Summary of Appraisals) 1-2.132 The five properties that Mr. Burgoyne determined had a lower market value in their 2000 condition belong to plaintiffs Jackson, Neuser, Chapman, Notre Dame Path Association and Renner. See id. According to Mr. Burgoyne, the total loss of market value of these five properties is $465,000. See id. at 2.
Mr. Burgoyne determined that the value of the property owned by the Notre Dame Path Association diminished by $65,000, DX 333 (Notre Dame Path Association Appraisal) 9, the sum that a potential buyer would be compelled to spend immediately to replace a crumbling revetment protecting homes located on the edge of a bluff, Tr. 2512:21-2513:20 (Burgoyne). Mr. Burgoyne stated that, although other properties lack shore protection or have shore protection that will fail in the near future, none of the other properties have structures that will be imminently threatened by erosion. Tr. 2513:21-2514:4 (Burgoyne). As an example, Mr. Burgoyne described portions of the property owned by plaintiff Greenbriar Development that lack shore protection but are located "hundreds of feet from any improvements, so that the erosion wouldn't impact anything for many, many years." Tr. 2513:25-2514:4 (Burgoyne).
According to Mr. Burgoyne, the value of the Neuser property diminished by $305,000. DX 315 (Neuser Appraisal) 10. In 1950, the area of the Neuser property was 1.25 acres. Id. In 2000, the area of the Neuser property was .69 acres. Id. Between 1950 and 2000, the property lost a significant portion of its depth. Id. at 12 (map of ordinary high water marks). Mr. Burgoyne stated that, because of zoning regulations and the setback required for high risk erosion areas, the parcel was no longer deep enough to support new construction. Id. at 100. The property, which was vacant in January 2000, id., "went from being a buildable lot to being an unbuildable remnant." Tr. 79:11-12 (Burgoyne).
Mr. Burgoyne concluded that the properties owned by the Chapman, Jackson and Renner plaintiffs diminished in value by $35,000, $30,000 and $30,000, respectively. DX 336 (Summary of Appraisals) 1. Mr. Burgoyne testified that these three properties declined in value because "[t]he indication was they had a beach in 1950; and that because of the acts of erosion, they did not have a beach in 2000." Tr. 79:24-80:1 (Burgoyne).
Mr. Burgoyne found that, with regard to the rest of plaintiffs' properties, the value of the property in his 1950 appraisal was the same as in his 2000 appraisal. See DX 336 (Summary of Appraisals) 1-2.
b. Plaintiffs' Criticisms of Mr. Burgoyne's Analysis
Plaintiffs argue that, for a number of reasons, "Mr. Burgoyne's opinions regarding the diminution in the value of [p]laintiff[s'] properties caused by erosion lack any recognize[d,] reasonable methodology and are entitled to no weight." Pls.' Br. 41.
However, plaintiffs' criticisms of Mr. Burgoyne's methods are undermined by plaintiffs' reliance on Mr. Burgoyne's valuation of their properties in their own damage calculations. Plaintiffs determine the amount of their damages in part by multiplying the hypothetical value of their properties in Mr. Burgoyne's 1950 appraisals by the largest additional percentage of their value by which their properties may have appreciated, according to Dr. Moore, in the absence of the publication of the 1999 Report. See Pls.' Br. 37-38; PX 275 (table showing plaintiffs' estimates of the erosion damage to each property). Mr. Burgoyne explained that he applied the same techniques to both his pre-taking and post-taking appraisals: "The methodology doesn't differ; only the relevant characteristics of the properties differ." Tr. 104:15-16 (Burgoyne).
Plaintiffs do not explain why Mr. Burgoyne's hypothetical 1950 appraisals are sufficiently reliable for plaintiffs to incorporate them into plaintiffs' damage calculations, but Mr. Burgoyne's January 2000 appraisals, which apply the same techniques, "lack any recognize[d,] reasonable methodology and are entitled to no weight." Pls.' Br. 41; see id. passim; Pls.' Resp. passim. If, as plaintiffs' critiques of both sets of Mr. Burgoyne's appraisals claim, both sets of appraisals "lack any recognize[d,] reasonable methodology and are entitled to no weight," Pls.' Br. 41, plaintiffs do not explain why plaintiffs' damages calculations, which are based on Mr. Burgoyne's hypothetical 1950 appraisals, see id. at 38, are not similarly unreliable, see id. passim; Pls.' Resp. passim.
i. Loss of Value Absent Complete Loss of a Feature
Plaintiffs first argue that "Mr. Burgoyne's analysis is fundamentally flawed because the physical units that he uses to measure value, either price per front foot or price per square foot, does not vary with erosion." Pls.' Br. 39. Plaintiffs contend that "Mr. Burgoyne's methodology does not account for a loss of value absent a complete failure of certain characteristics of the property, such as a complete loss of beach or the loss of so much lot depth that the property is no longer buildable." Id.133
Plaintiffs are incorrect that Mr. Burgoyne failed to account for the potential loss of value due to changes in the property features he identified as significant determinants of value. Rather, Mr. Burgoyne determined that changes in those features were often insufficient to change the market value of plaintiffs' properties. Regarding changes in property depth that were insufficient to change the value per lakefront foot of the property, Mr. Burgoyne testified, "My investigation revealed that depth was not an issue. Unless the depth was such that the property was rendered unbuildable. . . ." Tr. 75:13-15 (Burgoyne). Mr. Burgoyne further testified, "I did not ignore [lot] depth. I carefully considered and came to the conclusion that [lot] depth was not relevant, not significant." Tr. 107:22-24 (Burgoyne).
Mr. Burgoyne stated that, in reaching this conclusion, he relied upon his 26 years of experience appraising property in Michigan, as well as upon market research and interviews with brokers and others in the area. Tr. 2480:7-22 (Burgoyne). Mr. Burgoyne testified that "lakefront property is special; it's different" than property located inland. Tr. 2478:3-12 (Burgoyne). The valuation of vacant lakefront property is "special" because "[i]t sells on the basis of width or lake frontage, not on the basis of land area." Tr. 2479:14-19 (Burgoyne). "[T]he amount of land area, as long as there's enough area to build, is almost irrelevant." Tr. 2480:20-22 (Burgoyne). Mr. Burgoyne testified that the valuation of lakefront property based on its lake frontage rather than the depth of the lot is "definitely borne out by the market data." Tr. 2556:2 (Burgoyne).
To illustrate that the value of vacant lakefront property is determined largely by the amount of lake frontage it has, Mr. Burgoyne described a sixteen-acre property that sold for approximately the same amount as the adjacent four-acre properties with similar amounts of lake frontage. Tr. 2482:8-23 (Burgoyne); DX 295 (Anderson Appraisal) 41-42. Mr. Burgoyne also described three parcels that were ninety, ninety-five and eighty-nine feet wide and less than an acre in size, all of which sold for "considerably more" than a sixteen-acre parcel and a four-acre parcel, both of which had less lake frontage.134 Tr. 2482:23-2483:5 (Burgoyne). Above approximately 100 or 120 feet, additional lake frontage provides a diminishing marginal return unless the property becomes wide enough that it could be divided. Tr. 2483:9-15 (Burgoyne). Plaintiffs presented no evidence to contradict Mr. Burgoyne's testimony that the value of vacant lakefront property is determined largely by the amount of lake frontage, or to quantify the effect that changes in property depth that do not affect the buildability of a parcel have on its market value.135 See Pls.' Br. passim; Pls.' Resp. passim.
Regarding the narrowing or loss of their beaches, plaintiffs are similarly incorrect that "Mr. Burgoyne's methodology does not account for a loss of value absent . . . complete loss of beach." Pls.' Br. 39. Plaintiffs argue that "Mr. Burgoyne testified that any reduction in the depth of a beach, no matter how great, had no effect on the property values of [the] Banks Plaintiffs' properties, as if a 60[-]foot beach and a 4[-]foot beach were identical." Id. at 41; see also Pls.' Resp. 6 (stating that Mr. Burgoyne equated "an expansive 100[-]foot beach with a mere 4[-]foot beach."). Plaintiffs misunderstand Mr. Burgoyne's testimony regarding the narrowing and loss of beaches. Mr. Burgoyne testified that he considered the "beach conditions" and the depth of the beaches in front of plaintiffs' properties, Tr. 2500:19-21 (colloquy between Mr. Burgoyne and defendant's counsel), and the comparable properties, Tr. 2501:4-7 (colloquy between Mr. Burgoyne and defendant's counsel); see also, e.g., DX 295 (Anderson Appraisal) 45 (stating the depth of the beach in front of a comparable property). Mr. Burgoyne testified that the presence of a beach is "a positive feature," Tr. 107:14 (Burgoyne), but concluded that the partial loss of beach does not cause damage, but full loss does, Tr. 81:22-82:10 (colloquy between Mr. Burgoyne and plaintiffs' counsel).
Plaintiffs misconstrue Mr. Burgoyne's statements regarding the effect of beach size on property values. In a colloquy between Mr. Burgoyne and plaintiffs' counsel at trial, Mr. Burgoyne stated that reductions in the size of the beach in front of a property have no effect on the value of the property so long as the remaining amount of beach can properly be called a beach:
Q: So, as long as the property had just one foot of beach, in your opinion, there is absolutely no diminution of value to that property?
A: Well, I don't know if you would call one foot a beach. Nineteen feet certainly [is] a beach; maybe one foot, you wouldn't call it a beach.
Tr. 2554:22-2555:2 (colloquy between Mr. Burgoyne and plaintiffs' counsel). Mr. Burgoyne further stated that "[t]here's a couple that are 19 and 14 and 13[,] and those are beaches." Tr. 2555:7-9 (Burgoyne). Mr. Burgoyne did not state or imply that a beach that is four feet wide can properly be called a beach; in fact, Mr. Burgoyne noted that the Lahr property, which currently has a beach that is seven feet wide, "potentially could be perceived as not having a beach." Tr. 2555:6-7 (Burgoyne).
Mr. Burgoyne pointed out that beach width plays less of a role in the valuation of plaintiffs' property because beaches in the area are "very dynamic. They come and go, widen [and] narrow. . . ." Tr. 2501:20-21 (Burgoyne). A number of plaintiffs testified that their beaches come and go over time. See, e.g., Tr. 1272:25 (Concklin) (stating that the presence of the beach "ebbs[s] and flows"); Tr. 1303:10-14 (Kane) ("We never knew what it was going to look like when we came up. . . . [O]ne year there would be some beach, the next year there would be absolutely nothing."); see also Def.'s Br. 29 n.7 (summarizing the testimony of ten plaintiffs that the beaches adjacent to their properties come and go over time).
The fact that beaches are—and are well known to be—dynamic moderates the effect of beaches and beach width on the value of lakefront properties. See Tr. 2502:18-20 (Burgoyne). When beaches are not present, many of the features that make lakefront property desirable to buyers continue to exist, including "access to the water . . . breezes; views; sunsets or sunrises . . .; [and] the moderating [e]ffect of the lake on temperature." Tr. 2503:16-2504:4 (Burgoyne). Plaintiffs presented no evidence that contradicts Mr. Burgoyne's conclusion that variations in beach width do not affect property values as long as the beach remains wide enough properly to be called a beach. See Pls.' Br. passim; Pls.' Resp. passim. Nor have plaintiffs presented evidence that indicates the amount by which Mr. Burgoyne's appraisals should be adjusted to account for the loss of beach width. See Pls.' Br. passim; Pls.' Resp. passim.
ii. Loss of Beaches
Mr. Burgoyne testified that the presence of a beach is "a positive feature." Tr. 107:14 (Burgoyne). Mr. Burgoyne further testified that, although a partial loss of beach does not damage the market value of a property, a complete loss of a beach does. Tr. 81:22-82:10 (colloquy between Mr. Burgoyne and plaintiffs' counsel). Mr. Burgoyne concluded that the Chapman, Jackson and Renner properties diminished in value by $35,000, $30,000 and $30,000, respectively, DX 336 (Summary of Appraisals) 1-2, because "[t]he indication was they had a beach in 1950;136 and that because of the acts of erosion, they did not have a beach in 2000,"137 Tr. 79:24-80:1 (Burgoyne).
While Mr. Burgoyne determined that loss of the beaches decreased the market value of certain of plaintiffs' properties, see DX 336 (Summary of Appraisals) 1, he did not determine, which, if any, of the beaches that were lost to erosion extended above the ordinary high water mark and therefore beyond the reach of the federal navigational servitude, see, e.g., DX 302 (Chapman Appraisal) passim. Neither does the table of beach widths assembled by Dr. Nairn indicate whether any portion of any beach listed in the table is located above the ordinary high water mark. See DX 188 (Nairn Beach Width and Comparables Report) 26, Table 4.1 (table of beach widths for plaintiffs' properties).
Rather, Dr. Nairn stated that he measured beach width "from the approximate water's edge to the delineated OHWM or landward extent of sand." See id. at 13. Although Dr. Nairn used the word "or," id., the court infers, in light of the techniques Dr. Nairn used to delineate the ordinary high water mark, that Dr. Nairn measured beaches from the water's edge to the ordinary high water mark in every case. Dr. Nairn delineated the ordinary high water mark differently depending on the characteristics of plaintiffs' properties. For properties with vertical shore protection or characterized by bluffs, he delineated the ordinary high water mark at the toe of the bluff or shore protection. See supra Part III.D.1. For properties with sloping shore protection, Dr. Nairn delineated the ordinary high water mark at the still water line along the shore protection. See id. For properties characterized by sand dunes, he delineated the ordinary high water mark at the edge of the more permanent vegetation. See id.
Accordingly, on properties with vertical shore protection and on properties characterized by bluffs, any beach would lie between the water's edge and the landward extent of sand, see DX 188 (Nairn Beach Width and Comparables Report) 13, which lies at the toe of the shore protection or bluff, a point that is also the ordinary high water mark for such properties. On properties with sloping shore protection, on which the ordinary high water mark is the still water line along the shore protection, no beach would be present between the water's edge and the shore protection. On properties characterized by sand dunes, any beach would lie between the water's edge and the edge of the permanent vegetation, see id., a point that is also the ordinary high water mark.
Plaintiffs do not acknowledge the possibility that their beaches may be located entirely below and within the ordinary high water mark. See Pls.' Br. passim; Pls.' Resp. passim. This oversight by plaintiffs is significant because not every government action that causes plaintiffs' properties to diminish in value is a taking for which just compensation must be paid. See generally OHWM Op., 71 Fed. Cl. 501 (discussing the role of the federal navigational servitude in this case). Plaintiffs' properties, being adjacent to the navigable waters of Lake Michigan, are subject to the navigational servitude held by the federal government, which servitude extends to the ordinary high water mark. See Cherokee, 480 U.S. at 704; see generally OHWM Op., 71 Fed. Cl. 501. When the government exercises its right to improve navigation in a manner that affects property within the boundaries of this servitude, "`the damage sustained does not result from taking property from riparian owners within the meaning of the Fifth Amendment but from the lawful exercise of a power to which the interests of riparian owners have always been subject.'" Cherokee, 480 U.S. at 704 (quoting Rands, 389 U.S. at 123).
Plaintiffs cite no evidence, specifically pointed out at trial, that would allow the court to determine whether the beaches that were lost ended at the ordinary high water mark, or whether, on any property, the "landward extent of sand," DX 155 (Nairn Beach Width and Comparables Report) 13, extended inland beyond the ordinary high water mark as it stood in 1950, see Pls.' Br. passim; Pls.' Resp. passim; see also Mar. 2, 2011 Order, Dkt. No. 439, at 2, (stating that the court may disregard any exhibit or portion of an exhibit not "[s]pecifically pointed out" at trial "with an indication of how the evidence supports or disproves a fact in issue"). Plaintiffs have not carried their burden to prove that they are owed just compensation for the loss of beaches in front of their properties.138
iii. Selection and Treatment of Comparable Properties
Plaintiffs contend that there are several flaws in Mr. Burgoyne's selection and treatment of comparable properties. See Pls.' Br. 40. Plaintiffs argue that Mr. Burgoyne, "in attempting to determine the `before taking' value of [p]laintiffs' properties, used market data from after the [a]nnouncement, despite his admission that post-announcement data would already reflect the impact of the [a]nnouncement." Id. Plaintiffs also argue that "even though Mr. Burgoyne used comparable sales that spanned a period of fourteen years, he failed to control for the effects of time on sale prices, including the effects of falling interest rates or increased demand. Id. Finally, plaintiffs contend that "although he had comparable sales from properties north of the St. Joseph jetties, Mr. Burgoyne elected not to use those comparables." Id. Plaintiffs argue that Mr. Burgoyne's selection and treatment of comparable properties "demonstrat[e] his flawed methodology." Id.
Plaintiffs are incorrect. Mr. Burgoyne's selection and treatment of comparable properties reflect a series of reasoned and well-documented decisions. It was appropriate for Mr. Burgoyne to use comparable sales data from dates after publication of the 1999 Report because Mr. Burgoyne had first determined that upon publication of the 1999 Report, "there didn't appear to be any adverse reaction in the marketplace." Tr. 2494:17-19 (Burgoyne); see also supra Part III.D.3.a (discussing the bases of Mr. Burgoyne's conclusion that the publication of the 1999 Report had no adverse reaction in the marketplace).
Contrary to plaintiffs' assertions, Mr. Burgoyne testified that he "definitely adjusted for and considered the fact that market conditions change," Tr. 2531:15-16 (Burgoyne). Mr. Burgoyne testified that "market conditions were generally increasing, so that older sales were adjusted upwards and later sales adjusted downward." Tr. 2531:16-19 (Burgoyne); see also DX 295 (Anderson Appraisal) 40 (describing the adjustments made to certain sale prices based on when the sales were made). Mr. Burgoyne's decision not to use comparable sales from north of the jetties similarly reflects Mr. Burgoyne's observations about the local real estate market. Mr. Burgoyne concluded that:
[w]hile sales that are more distant geographically to the north and south of the subject, including those north of the jetties in St. Joseph and Benton Township, were considered and researched, the sales in the immediate vicinity of the subject (occurring both before and after the January 2000 date of taking) are considered the best and most applicable comparable[] sales for appraising the subject property.
DX 295 (Anderson Appraisal) 37. Mr. Burgoyne also stated, based on his market research, that "market comparables from north of the jetties are entirely consistent with the market data from the subject area." Id. Apart from the econometric analysis created by Dr. Moore, which did not control for different preexisting trends in the affected area and the control group, see supra Part III.D.2.b.iii, plaintiffs did not present evidence that contradicts Mr. Burgoyne's testimony and have failed to persuade the court that Mr. Burgoyne's selection and treatment of comparable sales were improper.
iv. Loss of Improvements
Plaintiffs argue that "Mr. Burgoyne testified that his appraisals do not account for damages from the loss of improvements [p]laintiffs[] suffered as a result of erosion between 1950 and 2000, despite the fact that many of these improvements would increase the [p]laintiffs' property values." Pls.' Br. 41. Plaintiffs contend that "Mr. Burgoyne testified that `he was told' that damages for past improvements would be dealt with separately. In other words, he wanted to conduct a better study but was told not to." Id. (citation omitted).
The reason that Mr. Burgoyne's appraisals did not account for damage to improvements, Tr. 2520:15-21 (colloquy between Mr. Burgoyne and plaintiffs' counsel), is that he was told that "those claims would be separate and independent" of his analysis, Tr. 2525:3-4 (Burgoyne).
Plaintiffs' criticism is unconvincing given the fact that plaintiffs take the same approach to proving their damages. Plaintiffs presented the expert testimony of Dr. Moore, who attempted to determine, as a general matter, the damage done to plaintiffs' property values without considering any improvements that had been lost to erosion. See Tr. 117:1-251:19 (testimony of Dr. Moore). Plaintiffs presented separately evidence of the improvements lost by individual plaintiffs. See Pls.' Br. 31-33 (summarizing, inter alia, the improvements lost by each plaintiff).
v. Market Study
To study the effect of the increased risk of coastal erosion on property values, Mr. Burgoyne included in his appraisals a market study he conducted in Mason County, Michigan, which, like plaintiffs' zone, is located on the eastern shore of Lake Michigan. See DX 295 (Anderson Appraisal) 106-14. The market study compared a group of properties sold subject to an erosion easement absolving the adjacent power plant from any liability for erosion caused by the plant's operations to the sale of other properties not encumbered by an erosion easement. See id. at 106-07. Mr. Burgoyne concluded that the market study he conducted "clearly indicates the lack of impact from the announced risk of erosion and the erosion easement. . . ." Id. at 114. Plaintiffs argue that Mr. Burgoyne's market study is flawed. Pls.' Br. 40.
Plaintiffs contend that "Mr. Burgoyne admits that he never analyzed the properties in his `[test] group' without an erosion easement."139 Id. (citing Tr. 2544:3-12). Plaintiffs also argue that "Mr. Burgoyne failed to control for time[,] as the `auction group' properties were all sold in a single day while the `control group' properties were sold over a period of six years," id. at 40-41 (citing Tr. 173:10-174:25), and that Mr. Burgoyne "did not conduct an impact study with properties north of the St. Joseph jetties and properties south of the St. Joseph jetties," id. at 41.
The court finds it unnecessary to evaluate the validity of Mr. Burgoyne's market study because the court finds Mr. Burgoyne's appraisals persuasive without any support the market study might add. Mr. Burgoyne used a variety of methods in addition to the market study to determine whether publication of the 1999 Report impacted the local real estate market south of the jetties. See supra Part III.D.3.a (discussing the bases of Mr. Burgoyne's conclusion that the publication of the 1999 Report resulted in no adverse reaction in the marketplace). The court finds Mr. Burgoyne's conclusion that "there didn't appear to be any adverse reaction in the marketplace," Tr. 2494:17-19 (Burgoyne), well-supported and reasonable.
4. Shore Protection Expenses Incurred by Plaintiffs and Improvements Lost by Plaintiffs
a. Improvements Lost to Erosion
Several plaintiffs testified at trial that they lost improvements on their properties to erosion. See, e.g. Tr. 1305:1-3 (Kane) (stating that a set of stairs and a patio located on her property eroded into the lake). Plaintiffs include in their briefing a list of property lost to erosion that includes, among other things, improvements lost to erosion. See Pls.' Br. 31-33. Plaintiffs criticize Mr. Burgoyne for not considering the loss of improvements in his appraisals. See supra Part III.D.3.b.iv. However, the measure of just compensation to which plaintiffs claim they are entitled does not include the value of any improvements.
Plaintiffs calculate the amount of just compensation to which they claim entitlement by adding three figures: (1) the amount that plaintiffs claim, based on the analysis of Dr. Moore, that each property failed to appreciate in value as a result of the publication of the 1999 Report; (2) the cost of any shore protection already installed by each plaintiff; and (3) the cost to construct headland beaches, plaintiffs' preferred form of shore protection, at each property. See Pls.' Br. 35-51. For instance, plaintiffs calculate that the Bovee plaintiffs are entitled to just compensation of $1,261,009, id. at 50, a sum equal to the amount by which, according to plaintiffs, the value of the Bovee property failed to appreciate ($311,379), id. at 38, plus the cost of constructing a headland beach ($937,867), id. at 48, plus the costs already incurred to install shore protection ($11,763), id. at 50.140
None of the three bases of the amount of plaintiffs' claims for just compensation includes loss of improvements. Even though plaintiffs suggest that Dr. Moore's analysis includes a loss of the value of improvements, see Pls.' Br. 39 ("[P]rices act as a summary statistic for the interplay of all things that affect value."), Dr. Moore did not consider the value of any lost improvements in his analysis of the harm done to the property values of plaintiffs' properties, see PX 149 (Moore Report) passim.
The trial transcript contains references to the sums of money that plaintiffs expended to replace improvements lost to erosion. See, e.g., Tr. 1308:3-12 (colloquy between plaintiff Patricia Kane and plaintiffs' counsel) (stating that Ms. Kane spent $20,000 to replace a patio that eroded into the lake with a larger and more secure deck). However, plaintiffs do not cite, and the court has not found in the record, evidence that would allow the court to determine the value of any structures lost to erosion as of the date that they were lost. See Tr. passim; Pls.' Br. passim; Pls.' Resp. passim. Plaintiffs do not cite, nor does the record contain, evidence that would allow the court to determine which structures were lost before 1970, the date that the court has found, see supra Part III.C, that the government began to mitigate all of the erosion caused by the jetties to every property but one141 owned by plaintiffs, see Tr. passim; Pls.' Br. passim; Pls.' Resp. passim.
Because plaintiffs do not claim that they are entitled to separate compensation for improvements lost to erosion and because the evidence in the trial record does not allow the court to determine the value of the improvements lost, if any, by plaintiffs and their predecessors in interest before 1970, the court finds that plaintiffs are not entitled to compensation for any improvements lost to erosion.
b. Shore Protection Expenses
At the trial of damages, twenty-seven plaintiffs testified that they had installed shore protection to slow the erosion of their properties. See Pls.' Br. 50 (compiling, from the trial testimony of twenty-seven plaintiffs and the stipulations filed by the parties, the costs incurred by plaintiffs to install shore protection). When a taking results from erosion that is "in fact preventable by prudent measures, the cost of that prevention is a proper basis for determining the damage." Dickinson, 331 U.S. at 751; see also Law of Damages Op., 88 Fed. Cl. at 683 (quoting same). "Substantial encroachment of the parcel also puts a duty on the landowner to take reasonable steps to protect the property from further erosion damage, such as by the construction of revetments." Boling II, 220 F.3d at 1373 n.5. Reasonable expenditures to prevent erosion are those as to which "it `would have been sound economy, in view of the character and nature of the property, to have made the expenditure[s].'" Vaizburd v. United States, 384 F.3d 1278, 1286 (Fed. Cir. 2004) (alterations in original) (quoting United States v. Dickinson, 152 F.2d 865, 870 (4th Cir. 1946), aff'd, Dickinson, 331 U.S. 745).
The court must therefore determine whether it was "sound economy" for plaintiffs to construct the shore protection they installed. See id. If installing shore protection was sound economy, plaintiffs who have installed shore protection may recover the government's share of the cost to install and maintain shore protection, Law of Damages Op., 88 Fed. Cl. at 685 n.16, that is, 30% of any costs incurred from 1950 to 1970, and a portion of the costs incurred from 1970 to the present equal to the portion of the erosion caused by the jetties and not mitigated by defendant during that time period, cf. Liability Op., 78 Fed. Cl. at 656-57.
Defendant argues that "it is not enough that Plaintiffs have incurred expenses to construct or maintain shore protection on their properties." Def.'s Br. 36. Because the government is responsible for only a portion of the erosion to plaintiffs' properties, defendant argues that the plaintiffs' expenses for the construction of shore protection are only recoverable if plaintiffs establish a causal link between the Corps' activities and the construction of shore protection by plaintiffs. Id. Defendant is correct that "causation is an independent element of a takings claim." Id. (citing Cary v. United States, 552 F.3d 1373, 1379-80 (Fed. Cir. 2009)). In order to recover in an inverse condemnation action, a plaintiff must satisfy a two-part test "that can be characterized as causation and appropriation." Cary, 552 F.3d at 1376-77 (citing Ridge Line, Inc. v. United States, 346 F.3d 1346 (Fed. Cir. 2003)). "In the causation prong, it must be shown that `the government intend[ed] to invade a protected property interest or [that] the asserted invasion [was] the direct, natural, or probable result of an authorized activity and not the incidental or consequential injury inflicted by the action.'" Id. at 1377 (alterations in original) (quoting Ridge Line, 346 F.3d at 1355).
Defendant argues that "[a]s a matter of law, the evidence [p]laintiffs have proffered is insufficient to establish that the United States' activities are the proximate cause of the shore protection expenses various [p]laintiffs incurred." Def.'s Br. 37. Defendant notes that "it is undisputed that [p]laintiffs' shoreline is a naturally eroding shore." Id. Citing the trial testimony of a number of plaintiffs, defendant contends that "the overwhelming evidence in the record establishes that [p]laintiffs' shore protection efforts were taken in response to natural conditions" such as rising lake levels and storm events. Id. at 37-39.
However, the fact that erosion is associated with particular events does not mean that the jetties had no impact. The evidence presented at trial indicated that erosion is often discontinuous, with portions of plaintiffs' properties—particularly the edges of bluffs, where present—falling into the lake during storms or at times of high lake levels. See, e.g., Tr. 957:22-959:2 (colloquy between plaintiff Marcia Wineberg and plaintiffs' counsel). Additionally, Dr. Nairn testified that, especially on the southernmost properties, which are characterized by sand dunes rather than bluffs, the long-term retreat rate of a sandy shoreline can be overshadowed by the dramatic swings in beach width caused by cross-shore sand transport during storms and periods of high lake levels. See Tr. 2591:15-2595:2 (Nairn) (discussing the slow, but irreversible, erosion caused by longshore sand transport and the rapid, but reversible, erosion caused by cross-shore sand transport). Although the loss of beaches below and within the ordinary high water mark is not compensable as a taking, see supra Part III.D.3.b.ii, a landowner could be expected to install shore protection in response to the narrowing or disappearance of a beach. Plaintiffs' testimony that they installed shore protection in reaction to storms and high lake levels reflects the fact that the long-term process of erosion is often most apparent to the lay observer under such conditions. Accordingly, the "`direct, natural, or probable result,'" Cary, 552 F.3d at 1377 (quoting Ridge Line, 346 F.3d at 1355), of the erosion caused by the government would be periods of more pronounced erosion and attempts by property owners to prevent erosion following storms and during periods of high lake levels.
Defendant argues that, owing to natural erosion, plaintiffs "would have had to install shore protection, irrespective of the presence of the harbor." Def.'s Br. 37 (citation omitted). Plaintiffs respond that "[i]n essence[,] the United States is arguing that it is allowed, through accelerated erosion, to take property from private property owners without just compensation so long as there is another concurrent cause of the erosion." Pls.' Resp. 9. The Federal Circuit addressed a similar issue in Ridge Line. The plaintiff in Ridge Line claimed "that it was forced to construct . . . water detention facilities much earlier and on a larger scale than would have been required without the increased runoff caused by [a] government development." Ridge Line, 346 F.3d at 1351. The Ridge Line plaintiff's claim, analogous to plaintiffs' claim in this case, was that the government exacerbated an existing storm water runoff problem on the plaintiff's property which required remediation notwithstanding the government's actions. See id. at 1350-51. Remanding the Ridge Line case for additional proceedings, the Federal Circuit opined that "[a] share of the costs of building and maintaining storm water control facilities, proportionate to the government's quantitative contributions of storm water volumes, erosion, and sedimentation, is an entirely acceptable method of calculating damages." Id. at 1359. The court therefore finds that the government is liable for a share of plaintiffs' shore protection expenses equal to the portion of the erosion caused by the government at the time the expenses were incurred.
Defendant does not argue that the shore protection measures heretofore undertaken by plaintiffs were unduly expensive or wasteful in relation to the amount of erosion or to the harm to the market value of plaintiffs' properties that they prevented. See Def.'s Br. passim; Def.'s Resp. passim; cf. Tr. 1684:20-21 (Shabica) (describing the structures built by all but two of the plaintiffs with shore protection as "amateur shore protection"). Plaintiffs claim that their full cost of installing and maintaining shore protection was approximately $2.2 million. See Pls.' Br. 50. Defendant's expert witness, Mr. Burgoyne, calculated the market value of plaintiffs' properties in January 2000 to be approximately $25 million. See DX 336 (Summary of Appraisals) 2. The cost of building and maintaining shore protection since 1950, as calculated by plaintiffs, although not adjusted for inflation, is approximately 10% of the value of plaintiffs' properties in 2000.
Because the shore protection efforts undertaken by plaintiffs are relatively inexpensive compared to the value of plaintiffs' properties, and because defendant's expert witness, Mr. Burgoyne, testified that shore protection similar to the shore protection installed by plaintiffs is "relatively ubiquitous," Tr. 2516:11-15 (Burgoyne), reflecting a judgment by the adjacent property owners that shore protection is sound economy, plaintiffs have met their burden of demonstrating that the shore protection efforts that they have undertaken in the past are "sound economy," Vaizburd, 384 F.3d at 1286. This is so notwithstanding that plaintiffs have not presented evidence of the effect that erosion would have had on the market value of their properties in the absence of shore protection. See Ridge Line, 346 F.3d at 1354-55 (finding that, where the plaintiff prevented storm water runoff from the government's property from causing further erosion damage by taking measures that constituted sound economy, the trial court erred in holding that plaintiff had not demonstrated damages simply because it had not produced appraisals of its property showing a loss in value).
Plaintiffs do not state in their briefing, see Pls.' Br. passim; Pls.' Resp. passim, or in the stipulation filed by the parties regarding shore protection costs, see Trial Stipulations of Fact, Dkt. No. 456, passim, when plaintiffs incurred their shore protection expenses. There are references in plaintiffs' trial testimony, see, e.g., Tr. 1217:15-23 (colloquy between plaintiff Kay Varga-Smith and plaintiffs' counsel), and in the documentation of shore protection expenses presented by plaintiffs, see, e.g., PX 261 (receipts for shore protection expenses), to when certain shore protection measures were undertaken. Because these references are scattered across several thousand pages of trial testimony and documentary evidence, the court will not, in the absence of briefing or a stipulation by the parties, undertake to determine which of plaintiffs' shore protection expenses were incurred between 1950 and 1970, the period of time during which the government was responsible for 30% of the erosion taking place in plaintiffs' zone, see Liability Op., 78 Fed. Cl. at 656, and with respect to which, plaintiffs are entitled to 30% of their shore protection expenses incurred, see supra Part I. Neither will the court undertake to determine which of plaintiffs' expenses were incurred after 1970, the period of time during which the government has completely mitigated the erosion caused by the jetties. See supra Part III.C.2. If the reviewing court does not agree with the court's determination that it lacks jurisdiction to address plaintiffs' claims, the court will direct the parties to file a stipulation—or briefing, if the parties do not agree—to enable the court to determine which of plaintiffs' shore protection expenses were incurred prior to 1970 and which were incurred subsequent to 1970. Because plaintiffs had sufficient opportunity to prove the amount of their damages at trial, the court will not accept additional evidence regarding the amount of their expenses.
5. Reasonably Foreseeable Future Damages
The court previously determined that defendant is liable for damages for any portion of 30% "of all reasonably foreseeable future loss" not mitigated by defendant. Liability Op., 78 Fed. Cl. at 656.
If further erosion of plaintiffs' properties is "in fact preventable by prudent measures, the cost of that prevention is a proper basis for determining the damage." Law of Damages Op., 88 Fed. Cl. at 683 (quoting Dickinson, 331 U.S. at 751); see also Vaizburd, 384 F.3d at 1286 (stating that expenditures to cure the effects of a taking were recoverable if they were reasonable, meaning that "`it would have been sound economy, in view of the character and nature of the property, to have made the expenditure[s]'" (alteration in original) (quoting Dickinson, 152 F.2d at 870)).
If the installation of shore protection would be sound economy, it is not necessary for plaintiffs to provide appraisals to prove the exact amount of the damage their properties will suffer in the future without shore protection. See Ridge Line, 346 F.3d at 1354-55. However, to determine whether the installation of shore protection to prevent future erosion would be sound economy, the court must consider whether the government's share of the cost of shore protection would be greater than the government's share of the amount by which plaintiffs' property values would decline in the reasonably foreseeable future absent shore protection.142 See Law of Damages Op., 88 Fed. Cl. at 683 ("`If revetments are less expensive than the value of the land forecast to be lost, then the [g]overment may discharge its liability by bearing the cost of bank protection.'" (alteration in original) (quoting Boling I, 41 Fed. Cl. at 694)). If the government's share of the cost of shore protection is greater than the government's share of the amount by which plaintiffs' property values would decline in the reasonably foreseeable future absent shore protection, constructing shore protection would not be sound economy. See Boling I, 41 Fed. Cl. at 694 (stating that "if the value of land to be lost is less than the cost of revetments, however, plaintiffs cannot force the Government to pay the higher amount").
"Although the general rule in takings cases is to award plaintiff the form of just compensation that will be least expensive for the government," the court, in its Law of Damages Opinion, found this general rule "inapplicable in the particular circumstances of the present case," in which the government is not the only source of erosion to plaintiffs' properties. Law of Damages Op., 88 Fed. Cl. at 683. The court stated that "[p]laintiffs may not be financially able to pay 70% of the cost to construct shore protection measures out of their own pockets, resulting in continued erosion of their property." Id. The court held that "as an alternative to seeking 30% of the cost of shore protection measures, plaintiffs may instead seek 30% of the cost of `reasonably foreseeable future loss' to their property, although this amount may result in greater cost to the government." Id. at 684. Plaintiffs have elected to pursue just compensation equal to the government's share of shore protection rather than the government's share of future erosion damage. See Pls.' Br. 42-50 (discussing the cost of shore protection but not the dollar amount of reasonably foreseeable loss to plaintiffs' properties).
The court has determined that defendant is completely mitigating the erosion caused by the jetties to every property owned by plaintiffs but one, and has done so since 1970. See supra Part III.C.2. Therefore, for every property but one, no "reasonably foreseeable future loss," Liability Op., 78 Fed. Cl. at 656, will result from the government's actions. Plaintiffs argue that "what little dredging nourishment there is is in serious jeopardy of being cut off completely." Pls.' Br. 29. Plaintiffs further argue that "the unrebutted testimony at trial was that there is no funding available in 2012 for dredging of the St. Joseph Harbor." Id. at 29-30. Plaintiffs' argument that funding for the mitigation program "is in serious jeopardy" of lapsing in the future is speculative and dependent upon future actions by the government. At present, the mitigation program continues to provide nourishment material to plaintiffs' shoreline, as it has for more than forty years. Liability Op., 78 Fed. Cl. at 655 (finding that mitigation began in 1970). The court therefore concludes that, with the exception of one property, plaintiffs have not proven that they will suffer any reasonably foreseeable future loss as a result of the government's actions.
Furthermore, to determine whether it would be sound economy to install shore protection to prevent any reasonably foreseeable future loss, the court must compare the cost of shore protection to the damage to plaintiffs' properties expected to occur in the absence of shore protection. See Law of Damages Op., 88 Fed. Cl. at 683. For almost every plaintiff, it would not be possible for the future loss in market value to be greater than the cost of installing shore protection because the cost of the form of shore protection that plaintiffs argue is most appropriate, see Pls.' Br. 48, as estimated by plaintiffs, is greater than the full value of almost every plaintiff's property, compare, e.g., id. 48 (stating that the cost to install a headland beach143 at the Bovee property in 2010 dollars is $937,867), with id. at 36 (stating that the value of the Bovee property after publication of the 1999 Report in January 2000 was $430,000). Even if the appropriate form of shore protection is quarrystone revetments, which plaintiffs argue is not the case, see id. at 48, the cost of shore protection is nearly as much, or greater, than the full value of most of plaintiffs' properties, compare, e.g., id. at 49 (stating that the cost to install a quarrystone revetment at the Bovee property would be $429,438), with id. at 36 (stating that the value of the Bovee property after publication of the 1999 Report in January 2000 was $430,000).
The installation of shore protection measures costing more than the value of the properties they are installed to protect is not sound economy. Determining whether it is sound economy to construct shore protection measures that cost nearly as much as the properties that they are installed to protect would require persuasive evidence of when and to what extent the market value of the properties will diminish in the absence of the shore protection. Such evidence was not provided by plaintiffs. See Tr. passim.
The court has reviewed the trial record for evidence of the loss in market value that plaintiffs' properties will suffer as a result of erosion caused by the jetties in the absence of shore protection, but has found none.144 Plaintiffs' expert witness on the topic of damages, Dr. Moore, considered the effect of the government's publication of the 1999 Report, see Pls.' Br. 35-37, but did not examine the effect that ongoing erosion would have on the market value of plaintiffs' properties in the future, see PX 149 (Moore Report) passim. Defendant's expert witness on the topic of damages, Mr. Burgoyne, appraised plaintiffs' properties with their dimensions in 1950 and 2000, but did not appraise them with dimensions that they will have in the future. See, e.g., DX 295 (Anderson Appraisal) passim. Accordingly, even if the court had determined that the government's mitigation program had been ineffective as to all of plaintiffs' properties, the court would be unable to award plaintiffs the amount of just compensation to which plaintiffs claim they are entitled for the prevention of reasonably foreseeable erosion damage.
Plaintiffs have not carried their burden of proof, cf. Miller, 223 Ct. Cl. at 383-84, 620 F.2d at 828 (stating that plaintiffs bear the burden of proving the amount of just compensation to which they are entitled for severance damage), to establish that they are entitled to additional just compensation for the reasonably foreseeable erosion of their properties. Since 1970, the Corps' mitigation efforts have prevented the jetties from causing erosion to plaintiffs' properties, with one exception. Further, plaintiffs have failed to prove, with regard to any of plaintiffs' properties—whether by comparing the cost of shore protection to the dollar amount of their reasonably foreseeable damages or by some other means—that the installation of shore protection would be sound economy.
IV. Conclusion
For the reasons stated above, see supra Part III.A, the court finds that it lacks jurisdiction to hear plaintiffs' claims. The findings of fact and conclusions of law presented in Parts III.B-D of this Opinion are presented for purposes of judicial efficiency if the reviewing court in any appeal should disagree with the court's view of its jurisdiction, and to avoid the possibility of a trial opinion being drafted months or years after the trial, and the possibility of a repetitive trial. These findings are presented in the alternative and, in the absence of jurisdiction, do not entitle plaintiffs to just compensation in the amounts determined by the court.
The Clerk of Court shall ENTER JUDGMENT for defendant in each of the above-captioned cases DISMISSING each of plaintiffs' complaints.
IT IS SO ORDERED.