Summary: In the United States Court of Federal Claims No. 07-754C (Filed: July 26, 2013) * ******************** * THE RAVENS GROUP, INC., * * Plaintiff, * Breach of Contract for Negligent, Bad Faith, * or Misleading Estimates; Jury Verdict v. * Method; Demonstrating Injury as Part of * Breach Claim THE UNITED STATES, * * Defendant. * * * ******************** * Daryle A. Jordon, Fairfax, VA, for plaintiff. Joseph A. Pixley, Civil Division, U.S. Department of Justice, Washington, DC, with whom were Stuart
More
        In the United States Court of Federal Claims
                                       No. 07-754C
                                  (Filed: July 26, 2013)

* ********************
                        *
THE RAVENS GROUP, INC., *
                        *
         Plaintiff,     *                       Breach of Contract for Negligent, Bad Faith,
                        *                       or Misleading Estimates; Jury Verdict
v.                      *                       Method; Demonstrating Injury as Part of
                        *                       Breach Claim
THE UNITED STATES,      *
                        *
         Defendant.     *
                        *
* ******************** *

Daryle A. Jordon, Fairfax, VA, for plaintiff.

Joseph A. Pixley, Civil Division, U.S. Department of Justice, Washington, DC, with
whom were Stuart F. Delery, Principal Assistant Deputy Attorney General, and Jeanne
E. Davidson, Director, and Kirk T. Manhardt, Assistant Director, Commercial Litigation
Branch, for defendant. Major Nathan J. Bankson, U.S. Army, Litigation Division,
Arlington, VA, of counsel.

                                      OPINION

FIRESTONE, Judge

       Pending before the court is the United States’ (“the government” or “the

defendant”) motion for summary judgment in this action brought by The Ravens Group,

Inc. (“the plaintiff” or “TRG”), for breach of contract in connection with a contract

between TRG and the U.S. Army (“Army”) to provide housing maintenance services at

Fort Myer, Virginia and Fort McNair, Washington, D.C. The contract, which was

awarded to TRG on August 16, 2004, is identified as a “combined Fixed Price Indefinite
Delivery Indefinite Quantity Contract.” TRG filed a six-count complaint under the

Contract Disputes Act (“CDA”), 41 U.S.C. § 7103 et seq., and the Tucker Act, 28 U.S.C.

§ 1491(a)(2), in 2007, alleging various claims for payment of additional work. TRG has

agreed to dismiss two of the counts. 1 Three of the remaining four counts—Counts I, II,

and III—relate primarily to the plaintiff’s contention that the government breached the

contract by failing to provide historical workload data and for providing misleading

estimates of the number of monthly service calls TRG could expect under the contract.

See Compl. 9-11. Specifically, TRG claims that, prior to contract formation, the Army

told TRG that it could expect to receive 50 routine service calls per month and one to two

non-routine calls per year, and that the plaintiff reasonably relied on these estimates in

preparing its bid of $15,000 per month for service calls under the firm fixed price

(“FFP”) portion of the contract. Moreover, TRG claims that in addition to requiring it to

respond to more calls than it was told to expect, the government also required TRG to

provide services to three more units than the 49 units identified in the contract.

       The undisputed facts show that that estimate of the number of calls was not correct

and that TRG began responding to over 90 service calls per month shortly after the

contract was awarded. 2 In Count III, the plaintiff alleges that these facts give rise to a



1
 The plaintiff has agreed to dismiss its claims for unlawful assignment of work to third party
contractors (Count IV) and for wrongful termination (Count V). Pl.’s Resp. 4. Those claims are
hereby DISMISSED.
2
 It is not disputed that over the life of its contract, TRG exceeded the 50 calls per month
estimate by at least a total of 388 calls between August 2004 and March 2005. DCAA Report 5,
Pl.’s Appx. 3138.

                                               2
claim for breach of the implied duty of good faith and fair dealing. In Count VI the

plaintiff alleges, in the alternative, that the government constructively changed the

contract without payment.

       The government seeks summary judgment as to all of plaintiff’s claims. The

government argues that the undisputed facts establish that the Army did not provide

negligent or misleading estimates to TRG and that the plaintiff’s claim for additional

payment associated with responding to more than 50 service calls per month must be

rejected on the grounds that TRG failed to keep proper labor hour records to support a

claim for additional payment under the terms of the contract. The government also

argues that it did not breach the contract by requiring TRG to perform work at certain

units not listed in the contract on the grounds that TRG in fact never provided services to

more than 49 units as required by the contract. 3

       In the alternative, the government seeks summary judgment on the plaintiff’s

methodology for establishing damages. Assuming TRG can establish that the

government breached the contract regarding its estimate in the first instance, the


3
  The plaintiff has not responded to the government’s arguments for summary judgment
associated with certain miscellaneous claims asserted by the plaintiff. Def.’s Mot. 42-43.
Specifically, TRG does not address the government’s arguments regarding TRG’s claims for
compensation for an answering service, administrator’s salary, equipment loan loss, and for the
deletion of a contract line item number (“CLIN”) for custodial services. Under Rule 56 of the
Rules of the United States Court of Federal Claims (“RCFC”), the court may consider a fact
undisputed and grant summary judgment where the opposing party fails to respond or to properly
address the moving party’s assertion of fact if that fact is supported by the record. RCFC
56(e)(2)-(3); see also Anaheim Gardens v. United States, 
109 Fed. Cl. 33
, 37-38 (2013). Since
the court finds that the government’s argument that TRG bore the risk of additional costs
associated with the first three miscellaneous claims and further agreed to resolve the fourth with
a contract modification is supported by the factual record, the government’s motion for summary
judgment is GRANTED with regard to these claims.
                                                3
government argues, the plaintiff has nonetheless wrongly assumed it was injured solely

for having had to respond to additional calls. Rather, the government argues, where the

contract required TRG to maintain records of its service call labor hours, damages may

only be established with evidence of excess hours worked.

       For the reasons set forth below, the court finds that disputed issues of fact preclude

summary judgment with regard to the plaintiff’s claim that the government breached the

contract by providing negligent or misleading estimates. The court finds that the

government is entitled to summary judgment with regard to the plaintiff’s claim for

breach of contract based on having to provide services at more than 49 units. The court

also finds that the government is entitled to summary judgment regarding plaintiff’s

improper reliance on the jury verdict method in this case.

I.     Factual Background 4

       A.      Maintenance of the GFOQ prior to contract award

       General and Flag Officers Quarters (“GFOQ”) is military housing specifically

designated for senior officers of the United States military and their families. The GFOQ

Executive Management Office (“EMO”) was established to provide program

management for the maintenance and repair of GFOQ housing. The GFOQ units at Fort

Myer and Fort McNair, which are the subject of this litigation, were each built roughly a

century ago. Prior to August 2004 and the establishment of the EMO, they used “in-

house” personnel to respond to the majority of the maintenance and repair service calls at


4
 The facts are taken from the parties’ briefing and associated exhibits and are not in dispute
unless otherwise noted.
                                                 4
GFOQ housing. Spellman Dep. 16, Def.’s Appx. 239. The housing office at the time

also used private contractors to provide certain maintenance and repair services in cases

where the in-house government personnel were unavailable or unable to perform the

required services. TRG, a service disabled, veteran owned small business, was one of the

private vendors that serviced GFOQ housing at Fort Myer and Fort McNair prior to the

contract award at issue in this litigation. TRG was founded by Lieutenant General

(Retired) Joe Ballard, who previously served as Commander of the United States Army

Corps of Engineers and had lived in GFOQ housing at Fort McNair.

       The EMO was established in response to criticism by senior officers and their

families regarding the failings of this patchwork of private vendors and government

personnel. Spellman Dep. 16, Def.’s Appx. 239. Specifically, there were complaints

related to the “lag time” between placing service call requests and the completion of

maintenance. Clark-Evans Dep. 8, Pl.’s Appx. 2729. In addition, despite their age,

GFOQ housing units did not receive “much maintenance” prior to the contract award.

Spellman Dep. 29, Pl.’s Appx. 3441-42.

       B.     The decision to contract out the GFOQ maintenance work and pre-
              contract communications with TRG

       In response to the poor reviews and housing conditions at Fort Myer and Fort

McNair, Ms. Dee Spellman, who previously served as the GFOQ policy manager at

Army headquarters, was hired to start the EMO and to serve as its first director. In her

previous position as the GFOQ policy manager at Army Headquarters for housing, Ms.

Spellman “worked very closely with all the general and flag officer managers throughout


                                             5
Army-wide.” Spellman Dep. 14-15, Pl.’s Appx. 3435-36. Once created, the EMO tasked

Ms. Lenora Clark-Evans, the director of contracting at the United States Army

Contracting Agency at the Capital District Contracting Center (“CDCC”), 5 with drafting

a contract for housing maintenance work at the Fort Myer and Fort McNair GFOQ

facilities. Ms. Clark-Evans previously worked as a contract specialist at Hickam Air

Force Base, where she gained experience with GFOQ housing maintenance and repair.

Clark-Evans Dep. 9-10, Pl.’s Appx. 2730-31.

         Because this contract was a new initiative, the CDCC sought the assistance of

TRG to help draft the performance work statement (“PWS”) in the early summer of 2004.

The plaintiff’s work on the GFOQ PWS was performed under purchase request No.

WT3RTQ-4182-0602. Beginning with only a “generic” statement of work, TRG worked

with the government to develop a more robust and specific scope for the contract work.

Clark-Evans Dep. 12, Pl.’s Appx. 2733. TRG prepared the PWS along with the CDCC

and provided the CDCC and the EMO with a “master document.” Ballard Dep. 129, Pl.’s

Appx. 2880.

         Early in developing the PWS, TRG specifically asked Mr. William Campbell, a

division chief for contract administration at the CDCC, for access to the military service

call records for GFOQ housing at both bases. TRG wanted historical service data to

prepare the PWS as well as its own bid proposal. Mr. Campbell requested the

information through Ms. Spellman, who in turn relayed the request to the Army’s

Department of Public Works (“DPW”).

5
    The CDCC has since been renamed the Missions and Installation Contracting Command.
                                              6
       According to Mr. Campbell and Ms. Spellman, the DPW had little or no historical

data. 6 Ms. Spellman requested “the previous housing office to supply [the EMO] all the

past, any records, historical data, whatever.” Spellman Dep. 28, Pl.’s Appx. 3441. Ms.

Spellman noted that “they had very little historical data, at least that was provided to us.”

Id. Ms. Clark-Evans of
the CDCC recalled that there was “no historical data on what was

necessary” for performance of the contract. Clark-Evans Dep. 8, Pl.’s Appx. 2729; see

also 
id. 11-12, Pl.’s Appx.
2732-33 (stating that TRG was engaged to create the statement

of work because “the customer didn’t have historical data to come up with the specific

statement of work”). Ms. Clark-Evans recalled, however, that the help desk responsible

for service calls prior to the establishment of the EMO “used to get calls all the time.”

Clark-Evans Dep. 16, Pl.’s Appx. 2737. Nonetheless, Ms. Spellman considered the lack

of historical data to be “irrelevant” to developing the solicitation and contract

requirements:

       But, in reality, [the lack of historical data] didn’t really make any difference
       because what they had done up to that point was irrelevant in some degree
       because we knew that we had to just take it from that day forward and
       improve on anything that they may have already done or attempted to do.
       And, from the comments from the residents that there really had not been
       that much maintenance anyway, it just made better sense not to worry about
       past history, and just do [our] own assessments from this date forward, as
       we continued to do.




6
  The plaintiff contests the government’s assertion that “service call” and other “historical” data
for the Fort Myer and Fort McNair GFOQ was unavailable or did not exist. During fact
discovery, the government contacted the agency’s DPW, which should have had the data if they
existed and “confirmed . . . that no such records exist.” Def.’s First Suppl. Resp. Pl.’s First
Request for Prod. of Docs., Def.’s Appx. 233.
                                                 7
Spellman Dep. 28, Pl.’s Appx. 3441. In contrast to Ms. Spellman’s views, Gen. Ballard,

on behalf of TRG, stated that he believed that the historical record was not only relevant

but also essential to preparing the scope of work and preparing a bid. Ballard Dep. 218,

Pl.’s Appx. 2928. Without available data, TRG requested access to the GFOQ units to

run inspections and to get a better sense of their condition. Gen. Ballard stated that the

EMO denied TRG’s request to enter the housing units to conduct inspections. Ms.

Spellman maintains, however, that the EMO never denied TRG access. Spellman Dep.

41, Pl.’s Appx. 3452.

          In recognition of the need for some number to use in preparing the PWS, the EMO

and CDCC decided that they “would come up with a number as far as service calls to be

performed.” Campbell Dep. 25, Pl.’s Appx. 3012. Although Ms. Spellman knew that

“the number of service calls was unknown to either [the EMO or TRG],” Spellman Dep.

43, Pl.’s Appx. 3454, she orally informed TRG during pre-contract discussions that the

contractor could expect 50 monthly service calls and one to two emergency calls per

year. 7 Mr. Campbell recalled that the estimate of 50 calls was not based on any particular

data or that there was any “rhyme or reason” to the estimate. Campbell Dep. 25, Pl.’s

Appx. 3012. Mr. Campbell recalled that Ms. Spellman “just picked a number.” 
Id. Neither Mr. Campbell
nor anyone else at either the CDCC or the EMO investigated

whether Ms. Spellman’s estimate was accurate or what—if any—information was used to

determine the estimate. The estimate was not included in any written communication to

TRG. Similarly, the estimates were not incorporated into the statement of work prepared

7
    The difference among the classification of calls will be discussed more fully in the next section.
                                                   8
by TRG. Ballard Dep. 128, Pl.’s Appx. 2879. Gen. Ballard further indicated his belief

that the estimates were based on some modicum of data and represented something other

than a mere guess. 
Id. 22, Pl.’s Appx.
2811-12. The government does not dispute, for

purposes of this motion, that TRG was given the estimate of 50 routine service calls per

month. Def.’s Reply 11-12.

          C.     The contract award to TRG

          TRG submitted the PWS to the EMO in July 2004. The plaintiff included in the

PWS a line item for “service calls” which provided for a unit price of $15,000 per month

for a twelve month period, totaling $180,000. According to plaintiff, this number was

computed by assuming 50 service calls per month, at an average of $300 per call. 8 As

noted above, the CDCC awarded contract No. W91QV1-04-D-0013 (“GFOQ contract”)

to the plaintiff with an estimated value of $1,585,210.00. The contract was subsequently

modified on September 30, 2004 to reflect an adjusted total estimated amount of

$1,181,610.08. The contract period performance was for one year with four option years.

          The contract work was expressly split into two sections—an FFP component and a

separate indefinite delivery/indefinite quantity (“IDIQ”) component. The IDIQ portion

of the contract provided for a range of specific work including change of occupancy

maintenance (C.6.2) and spot painting (C.6.2.3). In regard to specific work performed

under the IDIQ portion, the contract provided:

          Specific work is defined as maintenance repair, demolition, installation of
          equipment and miscellaneous items; relocation of equipment, materials, and
          devices; alteration; minor construction work requirements; and

8
    The plaintiff has not submitted evidence indicating how it arrived at the rate of $300 per call.
                                                    9
       miscellaneous services which are not included in the Firm Fixed Price
       portion of the contract or identified as fixed-unit price work. Housing work
       may also be accomplished by other means including self-help by occupants,
       impact card purchases, and the use of other prime contractors.

GFOQ contract C.7.1. The contract further included a “maximum quantities” clause,

which provided:

       As referred to in 5252.216-9319, “COMBINATION FIRM FIXED-
       PRICE/INDEFINITE-QUANTITY CONTRACT” clause, the minimum
       guarantee of work is the firm-fixed-price portion of the contract. The
       maximum dollar value of the contract is the total dollar value of the fixed-
       price and indefinite quantity items. The maximum shall not be exceeded
       except as may be provided for by formal modification to the contract.

GFOQ contract C.9.6.

       With regard to the FFP component of the contract, TRG was responsible for a

preventative maintenance and inspection program (C.5.2), pest control services (C.5),

grounds maintenance service (C.5.4), annual inspection of facilities, grounds, and

pavements (C.5.5), custodial services (C.5.6), and warehouse operation (C.5.7). The FFP

component of the contract also included the contract’s service call management

provisions.

              1.     Classification of GFOQ service calls

       With regard to service calls, as noted above, TRG agreed to a monthly FFP of

$15,000 for all service calls. Under the terms of the contract, the plaintiff was required to

“[r]eceive, classify and respond to service calls for military family housing units and

related support facilities.” GFOQ contract ¶ C.5.1. TRG or the government could

classify each service call into one of three categories: “emergency,” “urgent,” or

“routine.” The Army reserved the right to reclassify service calls. 
Id. 10 “Emergency” calls
involved “the correction of conditions that constitute an

immediate danger to personnel, threaten property, or require action to restore essential

services.” 9 GFOQ contract ¶ C.5.1.1. Among the requirements, TRG had to arrive at the

site within an hour after the receipt of an emergency call and work continuously until the

issue was addressed. 
Id. If TRG could
not complete the work upon its first visit to the

GFOQ unit, then it had to work until the emergency condition was arrested and then

reschedule the work for completion. 
Id. “Urgent” calls were
those that “will not

immediately endanger personnel or threaten property” but “could lead to more serious

adverse effects.” 10 
Id. ¶ C.5.1.2. The
response time for urgent calls did not require the

immediacy as that for emergency calls but generally required a response on the same or

next day and did not require continuous work until completion. 
Id. The contract defined



9
    The contract provided further detail with regard to emergency service calls:

          Typical Emergency Service Calls include overflowing drains, roof leaks, broken
          water and/or frozen water pipes, electrical power outages, electrical defects which
          may cause fire or shock, gas leaks, loss of heat when the exterior temperature falls
          below 40° F, loss of air conditioning when the exterior temperature rises above
          90° F, or loss of heat or air conditioning in quarters of occupants that have a
          documented medical requirement for maintaining stable temperature levels.

GFOQ contract ¶ C.5.1.1.
10
     The contract provided further detail with regard to urgent service calls:

          Typical Urgent Service Calls included clogged tubs and toilets, inoperable water
          heaters, ranges, ovens, refrigerators, broken windows during cold weather, loss of
          heat when the exterior temperature falls between 40° F and 50° F[, or] loss of air
          conditioning when the exterior temperature rises between 85° F and 90° F.

GFOQ contract ¶ C.5.1.2.
                                                   11
“routine” calls as those involving work not otherwise classified as emergency or urgent.

Id. ¶ C.5.1.3. The
response and completion time for routine calls was five days. 
Id. The contract provided
that routine and urgent service calls were those calls where

the work, as estimated by the government, would cost $2,000 or less. 
Id. ¶ C.5.1.6. The
contract provided that payment for those calls would be based on the government’s

estimated cost. 
Id. ¶ C.5.1.6. Specifically,
the contract provided that:

       the Government’s estimated cost will be calculated using the current R.S.
       Means, or other commercially available estimating systems to determine
       labor hours required, the Contractor’s marked up hourly rate (determined
       from the offered price for this line item divided by the workload cumulative
       labor-hour estimate, including the agreed variance) and the lowest available
       material prices.

       
Id. The contract required
TRG to respond to all service calls “regardless of

whether the cumulative labor-hours or materials exceed the estimated workload.” 
Id. ¶¶ C.5.1.8.1, C.5.1.9.2.
Under the contract, TRG would be entitled to payment beyond

$15,000 per month if the cumulative hours for 3 months exceeded workload estimates.

The same principle applied to emergency calls, which were not limited to a $2,000

threshold. GFOQ contract ¶ C.5.1.9. The contract provided that the Army would

compensate TRG for those portions of each emergency call exceeding the $2,000

threshold by issuing an additional, discrete work order for the excess. 
Id. The estimated cost,
including labor hours, for emergency calls was determined in the same fashion as

for urgent and routine calls using R.S. Means estimates or estimates from another

commercially available estimating system. 
Id. 12 2. Data
collection and maintenance requirements

       The contract contained several provisions relating to developing, maintaining and

providing records related to the contract work. For instance, the contract provided that

the “historical number and scope of service calls and [sic] by month of the year are

maintained within the GFOQ office and shall be made available to Contractor for review

upon request.” GFOQ contract ¶ C.5.1.8. It is not disputed that despite requests from

TRG, the GFOQ never provided these data. The contract also required TRG to document

all work including time started and completed. C.5.1.7. and C.5.1.9.1.

              3.     The contract’s variance and adjustment provisions for work
                     exceeding estimated workload

       As noted, the contract provided a mechanism by which TRG could seek

adjustments to compensation beyond the monthly $15,000 FFP for service calls.

Specifically, the Army and TRG “agreed that the Contractor will be compensated for that

portion of actual Routine and Urgent service call workload which exceeds the cumulative

figures for the three (3) month period.” GFOQ contract ¶ C.5.1.8.1. TRG was to

measure charged labor hours in 15 minute increments. 
Id. ¶¶ C.5.1.8.1; C.5.1.9.2.
The

parties included a formula by which the additional compensation would be determined

during contract performance:

       Labor-hours—Exceeding the 5% Variation Limitation. These hours
       will be determined from the completed work authorization data submitted
       by the Contractor as described by paragraph C.5.1.7 herein. . . . Once the
       adjusted actual cumulative labor-hours are determined, the estimated
       cumulative labor hours above will be adjusted upward by five (5%) percent.
       This result will be subtracted from the adjusted actual cumulative labor
       hours and the remaining hours will be the basis for additional
       compensation. The remaining hours will be multiplied by the Contractor’s

                                            13
      marked up hourly rate, as described in the example below to determine the
      compensation to be provided [to] the Contractor for the increased
      workload.

Id. ¶ C.5.1.8.2. The
contract provided the following example to guide the parties in

determining possible overage compensation for routine and urgent service calls:

       Example. The adjustment and calculations will be done as follows:


      The workload estimated for 3 months.         535.5 labor hours


      (Average number of calls per month x average labor hours per call x number
      of months x 1.05) = (85 x 2.0 x 3 x 1.05) = 535.5 labor hours

      Actual hours after adjustments by the
                                                   672.5 labor hours
      Government:
      Excess hours (Actual labor hours –
                                                   137.0
      estimated labor hours)
      The Contractor offered $15,000 per month to perform service Calls.

      The Contractor’s marked up labor costs (which includes all [d]irect costs,
      indirect costs, G&A and profit)
      (Contractor’s offered price – cost of
      materials) ($15,000 - $2,295)                $12,705

      Marked up hourly labor rate:
      (12,705) / (85 x 2)                          $74.74
      (Marked up labor cost) / (Ave. no. of calls per month x Average labor hours
      per call)
      The 137 excess hours are multiplied by $74.74 to yield $10,239.38
      compensation for all costs (except materials) and profits for the excess
      workload.
      The 5% variance is not used in calculating either the materials Portion of the
      offered price or the marked up labor portion of the Offered price in order to
      yield higher hourly rates and thus higher compensation for the contractor.



                                              14

Id. ¶ C.5.1.8.2 (emphasis
added to provide clarity). Adjustments to compensation for

emergency calls would be calculated in the same manner as for urgent and routine calls

described above with the exception that all work above the $2,000 threshold for which

TRG would be compensated with indefinite quantity orders would be excluded from the

computation. 
Id. ¶ C.5.1.9.2. Finally,
the contract provided that “compensation for

service calls would be consolidated” and provided the following formula to calculate

billable overage:

       Total Routine Hours + Total Urgent Hours + Total Emergency Hours + 5%
       = Contract Hours.

       Total Hours Worked – Contract Hours = Billable Overage.

       Refer to Paragraphs C.5.1.8.2 and C.5.1.8.3 for calculation of labor hours
       and material costs.

Id. ¶ C.5.1.9.3. D.
    Service call overage and renegotiation meetings

       Soon after the contract was awarded, TRG began to experience a service call

volume greater than what it had anticipated based on the oral estimate of 50 service calls

a month provided by the Army. Further, TRG noted that it was being asked to take on

the responsibility of maintaining four additional units that were not on the initial list of 49

units provided to it when the contract was awarded.

       TRG arranged for a meeting with the CDCC and the EMO on February 9, 2005 to

discuss, among other items, the call volume it was experiencing. At the meeting, TRG

noted that it was losing money on the service calls and that it remained unaware of the

“historical data for GFOQ during the development of the contract.” GFOQ contract

                                              15
Renegotiation Meeting Minutes 1, Feb. 9, 2005 (“Feb. 9 Minutes”), Def.’s Appx. 141. It

also noted that since the beginning of the contract period, TRG only received one “true”

emergency call and that while most of the calls had been routine, TRG responded as if

they were urgent. 
Id. TRG’s meeting minutes
noted that “[T]RG would need to keep a

close account of all firm-fixed dollars spent to include all salaries, vehicles, and other

overages so that when it hits the $15,000, any amount over will have a claim processed to

recoup the money.” Feb. 9 Minutes 3, Def.’s Appx. 144.

       Following the February 9, 2005 meeting, TRG submitted a revised CLIN pricing

proposal to Mr. Campbell proposing a service call price increase for the FFP unit price

from $15,000 monthly to $102,675 monthly for a total CLIN price of $1,269,063. TRG

Line Item Proposal, Def.’s Appx. 148. TRG noted that the government’s inability to

provide estimates, coupled with its “best guess” for the number of service calls, caused

TRG to provide “a rather severe under estimation in the workload and material

requirements for this particular CLIN.” 
Id. There is no
evidence that the Army officially

reviewed or came to a formal decision on TRG’s proposal but Mr. Campbell, CDCC’s

division chief of contract administration, later called the plaintiff’s proposed pricing for

service calls “astronomical.” Campbell Dep. 60, Pl.’s Appx. 3043.

       TRG and the Army held a second contract negotiation meeting on April 19, 2005.

TRG’s notes from the meeting indicate, under a heading titled “CDCC Change Answers,”

that the Army would “control the service desk so the service calls do not exceed the

contract requirements established when estimating $15,000.” GFOQ contract

Renegotiation Meeting Minutes 1, Apr. 19, 2005 (“Apr. 19 Minutes”), Def.’s Appx. 156

                                              16
The notes further indicated an agreement to remedy the service call overage: “Although

triage of service calls will be done by EMO, there will be fair dealing with The Ravens

Group as it concerns types of service calls received and use of outside vendors when the

service calls exceed the 50 calls for the month.” 
Id. On May 2,
2005, several weeks after

the April 19, 2005 meeting, TRG and the CDCC executed bilateral modification P00003

to the contract, which removed funding for custodial service for contractor-occupied

office spaces. The contract modification did not reflect the changes to the service call

requirement discussed at the meeting.

       On June 15, 2005, the Army sent TRG a letter notifying it that the GFOQ contract

was scheduled to expire on August 15, 2005. Notification Letter, Def.’s Appx. 159.

Subsequent to the notification letter, on August 12, 2005, TRG and the Army executed a

bilateral modification, P00004, extending the contract for six months to February 14,

2006. Contract Modification P0004 1, Def.’s Appx. 98. The contract provided the

following release:

       In consideration of the modification (s) agreed to herein as complete
       equitable adjustments for the Contractor’s acceptance of six month
       extension of services required for GFOQ proposal (s) for adjustment, the
       Contractor hereby releases the Government from any and all liability under
       this contract for further equitable adjustments attributable to such facts or
       circumstances giving rise to the proposal (s) for adjustment.

Id. 2, Def.’s Appx.
99.

       E.     TRG’s claim before the contracting officer and final decision

       On September 29, 2006, TRG submitted a claim and request for a contracting

officer’s (“CO”) final decision, seeking $1,488,616.80 plus interest in connection to a


                                            17
range of issues associated with the GFOQ contract. GFOQ Contracting Officer Claim 1,

Def.’s Appx. 170. TRG stated that it answered an average of 93 service calls per

month—far more than the 50 it was quoted prior to contract formation. Moreover, the

claim stated that TRG was told it could expect to respond to one or two emergency calls

per year but actually responded to 10 per month in addition to 13 urgent service calls on a

monthly basis. 
Id. at 6, Def.’s
Appx. 175. TRG stated that it had relied on the estimates

when it had submitted its bid and had been harmed by the increased workload.

Additionally, TRG claimed that the government required it to perform work on more than

49 housing units as provided for in the initial maintenance list.

       In its claim, TRG noted that it had previously submitted a request for equitable

adjustment on May 10, 2006 but had received no response from the Army. Among its

claims, TRG alleged that the Army provided it misleading estimates and breached the

implied duty of good faith and fair dealing by failing to provide historical workload data

after contract formation. It further alleged that the Army constructively changed the

contract by requiring TRG to respond to more service calls, forcing it to purchase more

supplies and equipment while doubling its workforce.

       By letter dated December 21, 2006, the CO, Mr. Campbell, issued his final

decision, agreeing to pay $53,966.77 to TRG for claims relating to garbage disposal,

mulching, and snow removal. December 2006 Final Decision Letter, Def.’s Appx. 183.

The CDCC agreed to pay an additional $5,718.09 for a separate claim. 
Id. Mr. Campbell rejected
the rest of TRG’s claims. He noted that there was no mention of the 50 service

call estimate in the contract. Mr. Campbell further pointed out that the claim was

                                             18
“lacking of documentation in accordance with (IAW) C.5.1.7 in support to [sic] alleged

overage on Service Call Overage and Service Call Response Overage.” December 2006

Final Decision Letter, Def.’s Appx. 183. The letter also stated that TRG was not entitled

to compensation for purchases of additional equipment or any increases in workforce

because it was an FFP contract. TRG filed the instant case on October 29, 2007.

       F.     Defense Contract Audit Agency audit and TRG’s expert damages
              calculations

       At the request of the Army, the Defense Contract Audit Agency (“DCAA”) in a

report, dated May 9, 2011, audited TRG’s claim. The report noted that during its

examination of TRG’s claims, “the contractor was unable to provide adequate, verifiable

supporting documentation for the claimed costs.” DCAA Report 2, Def.’s Appx. 189.

TRG calculated its claims for additional service calls over the 50 calls per month by

assigning a value of $300 per routine call. TRG claimed this amount by dividing the

value of the monthly CLIN ($15,000) by the number of calls provided in the oral estimate

(50). TRG did not provide the auditors with the number of hours associated with each

service call. TRG did not maintain any labor hour records, so it instead used the $300 per

call estimate. TRG then marked up the value of the routine calls by 25% and 50% to

calculate the cost of each urgent and emergency call over the one to two call threshold at

$375 and $450 respectively. Because TRG did not have any evidence of the exact hours

spent on each call, the DCAA questioned TRG’s claims in their entirety.

       With regard to the service call overage, the audit found that TRG did not provide

“adequate supporting documentation” for the overage as required by paragraph C.5.1.7 of


                                            19
the contract. DCAA Report 4, Def.’s Appx. 191. The audit further concluded that no

adjustments could be made under paragraph C.5.1.8.1 since the contractor did not

maintain adequate data necessary to determine overages. 
Id. Specifically, the audit
noted

that the service logs kept by TRG did not include a start/stop time, actual hours

expended, or the name of TRG’s employees who performed the work. 
Id. 6. The audit
also took exception to the basis of calculation for call overages, concluding that the 50

call estimate was not included in the contract itself and that there was no basis for the

markup calculations for urgent and emergency calls. 
Id. 7. TRG responded
to the audit in February 2012 with its own expert, Kenneth

Bricker, who in his affidavit concluded that TRG’s calculations regarding excess service

calls and for increased personnel costs associated with meeting the service call increase

were reasonable and supported. Specifically, Mr. Bricker supported TRG’s claim that

regardless of hours spent on each call, it was reasonable to assume an average cost of

$300 a call used to establish the $15,000 price and to multiply that number by the alleged

388 additional calls for an unpaid amount for routine calls at $116,400. Mr. Bricker then

applied a modified formula with a 25% per call markup to calculate the amount owed for

126 urgent calls in the amount of $47,250 and a 50% per call markup to calculate the

amount for 44 emergency calls in the amount of $19,800. In addition, Mr. Bricker

calculated costs of $354,896 for increased personnel relating to TRG having to hire

additional employees and subcontractors to respond to the increased service calls.

       This motion for summary judgment followed.



                                             20
II.    Standard of Review

       In considering a motion for summary judgment, the court’s role is to determine

whether there exists a genuine issue of material fact for trial, and not “to weigh the

evidence and determine the truth of the matter.” Anderson v. Liberty Lobby, Inc., 
477 U.S. 242
, 249 (1986). Summary judgment is appropriate “if the movant shows that there

is no genuine dispute as to any material fact and the movant is entitled to judgment as a

matter of law.” RCFC 56(a); see also DIRECTV Gr., Inc. v. United States, 
670 F.3d 1370
, 1374-75 (Fed. Cir. 2012). A material fact is one that “might affect the outcome of

the suit,” and a dispute is genuine “if the evidence is such that a reasonable jury could

return a verdict for the nonmoving party.” 
Anderson, 477 U.S. at 248
. In reviewing the

facts, “all justifiable inferences are to be drawn” in favor of the party opposing summary

judgment. 
Id. at 255. Once
the movant has shown that no genuine issue of material fact exists, the party

opposing summary judgment must demonstrate that such an issue does, in fact, exist.

Celotex Corp. v. Catrett, 
477 U.S. 317
, 324 (1986). To establish a genuine issue of

material fact, a party “must point to an evidentiary conflict created on the record; mere

denials or conclusory statements are insufficient.” Radar Indus., Inc. v. Cleveland Die &

Mfg. Co., 424 F. App’x 931, 936 (Fed. Cir. 2011) (quoting SRI Int’l v. Matsushita Elec.

Corp. of Am., 
775 F.2d 1107
, 1116 (Fed. Cir. 1985)) (internal quotation omitted). Where

there is doubt as to the existence of a genuine issue of material fact, that doubt must be

resolved in favor of the nonmovant. Unigene Labs., Inc. v. Apotex, Inc., 
655 F.3d 1352
,



                                             21
1360 (Fed. Cir. 2011) (citing Ortho-McNeil Pharm., Inc. v. Mylan Labs., Inc., 
520 F.3d 1358
, 1360-61 (Fed. Cir. 2008)).

III.      Discussion

          A.     Claims associated with negligent or misleading estimates

          The primary focus of the government’s motion for summary judgment revolves

around whether the Army breached the contract by providing TRG with an estimate of 50

calls per month before TRG prepared its bid. It is recognized in this court that while

government estimates are not guaranteed, bidders are ordinarily entitled to rely on

estimates as representing honest and informed conclusions when preparing their bids.

Hi-Shear Tech. Corp. v. United States, 
53 Fed. Cl. 420
, 429 (2002) (citing Medart, Inc. v.

Austin, 
967 F.2d 579
, 581 (Fed. Cir. 1992)). 11 In this regard, the Court of Claims has

stated:

          Intrinsically, the estimate made in such circumstances must be the product
          of such relevant underlying information as is available to the author of the
          invitation. If the bidder were not entitled to so regard it, its inclusion in the
          invitation would be surplusage at best or deception at worst. Assuming that
          the bidder acts reasonably, he is entitled to rely on Government estimates as
          representing honest and informed conclusions.

Womack v. United States, 
389 F.2d 793
, 801 (Ct. Cl. 1968) (footnote and citation

omitted). Accordingly, the government “is not free to carelessly guess at its needs.”
11
   While the parties also disagree as to whether the GFOQ contract can properly be classified as a
requirements contract or an IDIQ contract, that issue as well as any others related to contract
interpretation are left for resolution later in this litigation. For now, it is enough that the parties
agree that the service call portion represents firm fixed pricing, Def.’s Suppl. Brief 2, and that the
government might be liable for a breach of contract if the government gave misleading or
negligent estimates to the contractor. See Engineered Demolition, Inc. v. United States, 70 Fed.
Cl. 580, 591-93 (2006) (holding that the government can be liable for breach for providing
negligent estimates on a non-requirements FFP contract). Nonetheless, the government does not
concede that that the 50 call estimate was actually part of or incorporated into the contract.
                                                  22

Medart, 967 F.2d at 581
. While the risk of variance generally rests with the contractor,

the government may nevertheless be liable for breach where the contractor can show by a

preponderance of evidence that the government (1) failed to prepare an estimate in good

faith, (2) prepared an estimate negligently, or (3) failed to use reasonable care. Rumsfeld

v. Applied Cos., 
325 F.3d 1328
, 1335 (Fed. Cir. 2003); Clearwater Forest Indus. v.

United States, 
650 F.2d 233
, 239 (Ct. Cl. 1981).

       The three standards tend to overlap and generally involve an inquiry into what

efforts the government took in locating and integrating relevant information into the

estimate formulation. The good faith standard, for instance, “requires [the government]

to seek the most current information available, and either reformulate its estimate when

warranted by the information available, or to notify offerors of situations or factors likely

to affect the estimate.” Datalect Computer Servs., Ltd. v. United States, 
40 Fed. Cl. 28
,

35 (1997) (citations omitted) rev’d in part on other grounds 
215 F.3d 1344
(Fed. Cir.

1999). Similarly, to prove negligence or that the government failed to use reasonable

care in preparing the estimates, the contractor must show that there was information that

the government “could have, or should have” considered in determining its estimate.

Educators Assocs., Inc. v. United States, 
41 Fed. Cl. 811
, 818 (1998). A failure to

consider such information could rise to the level of negligence regardless of the extent of

impact of the information on the estimate. Hi-Shear 
Tech., 53 Fed. Cl. at 430
. Whether

information is “reasonably available” depends on the particular facts and circumstances

surrounding the preparation of the estimate. 
Id. The government is
generally not obliged

to search for or create additional information in formulating an estimate. Medart, 
967 23 F.2d at 582
. Nonetheless, merely disclosing to the bidders everything known—or not

known—at the time the estimate is made does not insulate the government from potential

liability where it fails to inquire about potentially relevant and readily available

information. 
Womack, 389 F.2d at 800
. In this regard, one of the “common threads in

the cases where courts have found estimates to be unreasonable” is when the agency

“fail[s] to take reasonable efforts to confirm doubtful estimates.” Fed. Gr., Inc. v. United

States, 
67 Fed. Cl. 87
, 98 (2005).

              1. Disputed issues of fact preclude summary judgment on whether the
                 estimates were negligent or misleading

       Tested by these standards, the court finds that disputed issues of fact preclude

summary judgment as to whether the Army provided a negligent or misleading estimate

to TRG when it told TRG that it could expect 50 service calls each month. The

government argues that its estimates were not negligently prepared or misleading because

the undisputed evidence shows that no data were available to make accurate estimates

and TRG was aware of their general unavailability. The plaintiff argues that the

government’s claims that TRG knew that 50 calls per month constituted nothing more

than an uninformed guess and that historical service call data or other data did not exist

are not “credible.” Pl.’s Opp. 27. TRG points first to a provision in the contract that

states: “The historical number and scope of service calls and [sic] by month of the year

are maintained within the GFOQ office and shall be made available to Contractor for

review upon request.” GFOQ contract ¶ C.5.1.8. TRG next argues, based on the

testimony of Ms. Spellman, that the EMO should have had these data because, as she


                                              24
explained, the EMO closely watched “every penny” spent on GFOQ housing and

generally tracks expenditures on associated housing maintenance. Pl.’s Resp. 5 (citing

Spellman Dep. 47-48, Pl.’s Appx. 3458-59). Similarly, Gen. Ballard recalls from his

time as a resident living in GFOQ at Fort McNair that records were kept for all

maintenance calls.

       The plaintiff further asserts that even if it were true that the government no longer

had historical data for service calls at Fort McNair and Fort Meyer, the Army was still

negligent by providing the 50 call estimate without endeavoring to confirm the estimate

with alternative sources of information. TRG argues that data from Fort Belvoir and Fort

Meade—two other forts in the National Capital Region—were potential sources of

relevant information that should have been consulted or at least considered to calculate an

estimate. TRG notes that Mr. Campbell testified that he did not attempt to conduct any

further investigation to determine whether the 50 call per month estimate provided by

Ms. Spellman was accurate even though he knew it was not supported by any data.

Finally, TRG asserts that it had no reason to believe that the provided estimate was not

rooted in some sort of data and represented nothing more than mere guesswork.

       The government argues that these facts do not give rise to a material dispute

because, it contends, the plaintiff has not produced any relevant evidence to show that

data regarding service calls were reasonably available at any other military installation.

The government further argues that TRG helped prepare the PWS and thus “knew” that

the Army did not have any data. In such circumstances, the government argues, TRG

could not have been misled and assumed the risk of variance in calls by relying on the

                                             25
information. Finally, the government argues that the contract provisions providing for

modifications for variances of 5% above the estimated workload demonstrate that TRG

could not rely on the 50 call estimate. In essence, the government argues, TRG cannot

pursue a claim for breach where the contract provided for an acceptable variance and

adjustments beyond that variance.

       The court finds that TRG has provided sufficient evidence to defeat the

government’s motion for summary judgment regarding the oral estimates provided to

TRG during the bid process. In particular, the court finds that the plaintiff has presented

evidence to show that it had no reason to know that the 50 call number was wholly

fabricated. See Ballard Dep. 22-26, 34, Pl.’s Appx. 2811-15, 2933 (indicating TRG’s

belief that the government based its estimate of service calls on something other than an

uninformed guess and that some set of data was utilized). In addition, there is disputed

evidence regarding the availability of potentially relevant historical records from other

installations. Ms. Clark-Evans testified that almost every military installation maintains a

separate office or branch to service GFOQ housing, suggesting a wide availability of

potentially relevant service call records. Clark-Evans Dep. 10, Pl.’s Appx. 2731. Ms.

Clark-Evans’s and Ms. Spellman’s extensive experience working with GFOQ housing

further suggests that the Army could have, at the very least, sought the records with

reasonable effort. In such circumstances, the government is not entitled to summary

judgment as to the reasonableness of its estimates.




                                             26
               2.     The contract’s variance and equitable adjustment provisions do
                      not foreclose TRG’s claim for breach based on misleading or
                      negligent estimates

       The court also rejects the government’s argument that TRG is barred from

recovering any damages based on the contract’s variance and equitable adjustment

clause. The court finds that the contract’s variance and equitable adjustment clause

served only to protect the government from unforeseen circumstances at the time of

contract formation. 
Womack, 389 F.2d at 801
. It did not, however, excuse the

government if it provided a misleading or negligent estimate to plaintiff. Id.; see also

Chem. Tech., Inc. v. United States, 
645 F.2d 934
, 948 (Ct. Cl. 1981) (“[T]he Government

cannot provide inaccurate data in this manner and then be allowed to bar an equitable

recovery by arguing that the resulting damages . . . fall within the Volume Variation

clause.”). The Federal Circuit has made plain, moreover, that such provisions for

equitable adjustments do not necessarily bar other measures of damages in cases where

the court finds a breach. Hi-Shear Tech. Corp. v. United States, 
356 F.3d 1372
, 1381-82

(Fed. Cir. 2004). Instead, the issues of injury and damages remain. 
Id. The court holds,
therefore, that the government cannot successfully use the contract’s variance and

equitable adjustment provision to preclude the plaintiff from the opportunity to present

the merits of its breach of contract case. 12




12
  This is not to say that the plaintiff is absolved from proving injury and damages, but only that
the contract’s variance clause does not apply if TRG can establish a breach.

                                                27
       B.      The government is entitled to summary judgment on TRG’s claim
               regarding its service of 49 units

       TRG also claims that the government breached the contract by requiring it to

perform work on four housing units that were not included on the list provided at the time

of contract formation. TRG contends that it “remained responsible for maintenance for

the 49 units on the original list as well as [4] additional units” without receiving

additional compensation. Pl.’s Resp. 8.

       The government argues that there is no evidence to support TRG’s contention that

TRG performed work on any more than 49 GFOQ units. The government asserts that

TRG’s own daily status reports establish that TRG performed work on no more than 49

units. The government concedes that the daily status reports include three units that were

not identified on the government’s original list: MY24AU, 13 MY25B, and MY26B. The

reports further demonstrate, however, that TRG did not perform work on three housing

units that were on the original list: MY22A, MY22B, and MN09. As a result, the

undisputed facts demonstrate that TRG did not perform work on more units than agreed

upon by the parties in the contract’s scope of work.

       In view of the foregoing undisputed facts, the court agrees with the government

that TRG has failed to show that there is a genuine issue of fact as to whether it

performed work on more than 49 housing units. To the contrary, as noted above, TRG’s

own daily housing reports indicate that TRG serviced only 49 units. In such


13
  The list refers to individual housing units located at Fort Myer with an “MY” prefix and units
located at Fort McNair with an “MN” prefix.

                                               28
circumstances, the government is entitled to summary judgment on TRG’s claim that is

entitled to additional compensation for performing services for more than 49 units.

       C.     TRG cannot rely on the jury verdict method to establish damages

       The government also seeks summary judgment barring TRG from using the “jury

verdict” method for calculating damages in the event that the plaintiff establishes a

breach of contract. The jury verdict method is an approach to approximating damages

based on the entire record. Grumman Aerospace Corp. v. Wynne, 
497 F.3d 1350
, 1358

(Fed. Cir. 2007) (citing Raytheon Co. v. White, 
305 F.3d 1354
, 1367 (Fed. Cir. 2002)). It

is disfavored, however, and serves as a method for determining damages only when more

exact methods are inapplicable—particularly where quantitative data are unavailable.

Grumman, 497 F.3d at 1358
; see also Dawco Constr., Inc. v. United States, 
930 F.2d 872
,

881 (Fed. Cir. 1991) (“[T]he contractor bears the burden of establishing that no more

reliable method is available than the ‘guesstimate’ of the ‘jury verdict method,’ i.e., a

method that would more precisely calculate the cost for the extra work.”) (emphasis in

original) (citation omitted). In order to adopt the jury verdict method for determining

damages, the court must find that (1) clear proof of injury exists, (2) there is no more

reliable method for computing damages, and (3) the evidence is sufficient for a court to

make a fair and reasonable approximation of the damages. 
Grumman, 497 F.3d at 1358
(citing 
Dawco, 930 F.2d at 880
).

       The government’s motion requires the court to resolve (1) whether TRG has

demonstrated the clear proof of injury necessary to use the jury verdict method and (2)

whether there is a more reliable method for computing damages. The government argues

                                             29
that the plaintiff’s reliance on the jury verdict approach is fundamentally flawed because

it ignores the import of the $15,000 monthly payment guaranteed under the contract and

the contract’s provisions on overage compensation. The government argues that even if

the $15,000 was estimated based on 50 service calls per month, the plaintiff fails to

recognize that the number of calls estimated served merely as a proxy for calculating the

number of labor hours to be spent on service calls. Therefore, according to the

government, the plaintiff can only show an injury if it can demonstrate that it incurred

labor costs over and above the $15,000 a month threshold provided for under the contract

based upon expended labor hours. Because the plaintiff did not keep records, the

government continues, TRG cannot show that it incurred more than $15,000 worth of

labor hours in any given month—or on average over any given three-month period—and

thus it cannot establish an injury in connection with any breach. The government asserts,

moreover, that the court cannot simply rest a finding of “clear proof of injury” by

assuming that each and every service call resulted in $300 or more of labor charges. For

this same reason, the government argues that the plaintiff’s reliance on the jury verdict

method is not a reliable approach for calculating damages.

       TRG contends, in response, that the alleged misleading estimate and the resulting

number of calls beyond that estimate are inherently “clear proof of injury” because TRG

was not contractually required to keep labor hour records and that to the extent it was

required to keep labor hours, the government waived such requirements through its

course of dealing. Pl.’s Resp. 35-36. TRG asserts that without records noting the labor



                                            30
hour spent per call, the jury method presented by its expert, Mr. Bricker, is a reliable

basis for both finding and awarding damages.

              1.     TRG does not show clear proof of injury justifying use of the
                     jury verdict method

       The court agrees with the government that TRG cannot rely on the jury verdict

method to establish damages in this case. It is elemental that in order to recover for

breach of contract, a party must allege and establish (1) a valid contact between the

parties, (2) an obligation or duty arising out of the contract, (3) a breach of that duty, and

(4) damages caused by the breach. Cent. Exploration New Orleans, LLC v. United

States, 
110 Fed. Cl. 148
, 163 (2013) (quotations removed) (citing San Carlos Irr. and

Drainage Dist. v. United States, 
877 F.2d 957
, 959 (Fed. Cir. 1989)). That is, even if

breach is established, the plaintiff is limited only to nominal damages and may not

recover more without separately establishing that it has actually in fact been injured by

the breach. 24 Williston on Contracts § 64:8 (4th ed.). Before the court may determine

the proper quantum of damages to which the plaintiff may be entitled, the plaintiff must

first demonstrate that the breach caused an economic injury. See 
id. § 64:9 (“[I]t
is now

well established that the uncertainty that prevents recovery is uncertainty as to the fact of

damage and not as to its amount.”); see also D’Andrea Bros. LLC v. United States, 
109 Fed. Cl. 243
, 264 (2013); Mega Constr. Co. v. United States, 
29 Fed. Cl. 396
, 424 n.15

(1993).

       The court agrees with the government that TRG’s response to service calls above

the 50 call oral estimate does not alone establish economic injury. TRG improperly


                                              31
assumes that any service call beyond the oral estimate of 50 calls necessarily resulted in

an economic injury compensable by an award of damages. Rather, to establish an injury

in this case, the plaintiff must show that it incurred labor hours as a result of those calls

above the 50 call monthly estimate requiring compensation in excess of the monthly

$15,000 FFP payment. This approach corrects the central fallacy of the plaintiff’s

argument that “routine service calls were priced at $300 each.” Pl.’s Reply Suppl. Brief

9. The plaintiff’s assumption that the government agreed to a fee of $300 per service call

by simply dividing $15,000 by 50 calls is wholly unsupported by the contract.

       Specifically, the contract measured overage costs beyond the agreed upon $15,000

FFP primarily as a function of labor hours expended, and not the number of service calls

performed. See, e.g., GFOQ contract ¶¶ C.5.1.8.1, C.5.1.8.2 (determining overage

compensation in reference to overage hours and not by number of service calls). The

contract provided that TRG could claim compensation for excess hours above the

government estimate if the amount of remuneration based upon hours worked exceeded

the $15,000 FFP monthly payment taking into account the 5% variation clause over a

three-month period. 
Id. ¶¶ C.5.1.8.1, C.5.1.8.2,
C.5.1.9.2, C.5.1.9.3. The contract

required TRG to demonstrate that those additional hours were justified when compared to

the government estimate of hours based on R.S. Means or other commercially available

estimating systems. 
Id. ¶¶ C.5.1.9.1, C.5.1.9.3.
       The court holds that under the terms of this contract, the plaintiff must show that it

incurred labor hours above the $15,000 guaranteed each month in order to demonstrate



                                              32
injury. 14 Under the plaintiff’s theory of the case, the plaintiff would be injured and

entitled to damages for each marginal service call beyond the 50 call estimate without

any regard to the $15,000 monthly FFP. The number of service calls, however, was not

the basis for compensation under the contract and injury would only exist, therefore, to

the extent that the extra calls resulted in labor hours compensable beyond $15,000. 15

GFOQ contract, Def.’s Appx. 14 (listing the FFP unit price for service calls as months

rather than calls). Under its theory of recovery, TRG would eschew all burden of risk

associated with FFP contracts and conceivably be entitled to compensation—without

regard to actual costs incurred—even if it answered only 51 calls in a month and even if

all of those calls resulted in less than $15,000 in total labor costs for that month. Dalton

v. Cessna Aircraft Co., 
98 F.3d 1298
, 1305 (Fed. Cir. 1996) (noting that contractors in

FFP contracts typically carry the burden of risk that cost of performance will be higher

than the price of the contract). This view is not supportable. Unless the additional 388

14
   In this connection, the court recognizes that there could be great variability of the average
labor required among the various types of service calls performed by TRG. For instance, if R.S.
Means or other commercially available estimating system were to determine that the average
labor hours required for all calls was only 15 minutes, TRG may not have been injured as the
total cost of compensation would likely not have exceed the $15,000 paid by the Army each
month. Conversely, if R.S. Means or other commercially available estimating system
demonstrates that the average call required many labor hours, it is conceivable that compensation
frequently exceeded the $15,000 threshold.
15
  TRG explicitly recognizes, despite its argument, that the number of service calls does not form
the basis for compensation under the contract. Pl.’s Reply to Suppl. Brief 6 n.3 (“The Ravens
Group does not contend that the estimates provided by the Army were contractual in nature.”).
Rather, the plaintiff acknowledges that the service calls estimate merely served as a basis for
estimating the monthly FFP of $15,000. 
Id. As stated, it
is undisputed that the parties agreed
that the FFP CLIN unit cost for service calls was measured in months and not on a per call basis.
GFOQ contract, Def.’s Appx. 14. On these facts, there is no foundation for the plaintiff’s
contention that “routine calls were priced at $300 each.” Pl.’s Reply to Suppl. Brief 9.

                                               33
calls identified by TRG gave rise to a sum of labor hours requiring compensation beyond

the FFP $15,000 paid by the government each month, TRG cannot establish an injury as

a basis for awarding damages. 16 The plaintiff, therefore, must establish some means of

demonstrating that the number of excess calls resulted in labor hours requiring

compensation beyond the $15,000 provided for under the contract.

               2.     Sufficient records exist to reasonably compute damages
                      precluding use of the jury verdict method

       The court further holds that, assuming TRG can show that the government

breached the contract and that the breach resulted in economic injury, it cannot rely on

the jury verdict method to calculate damages because there appears to be sufficient

information to adequately reconstruct the labor hours TRG spent on service calls. The

evidence presented to the court and highlighted by TRG, Pl.’s Resp. 37, consists of daily

work sheets recording the number of service calls, the type of service call, and the type of

work performed by TRG for each call during the period of the contract. Pl.’s Appx. 10-

50. Also before the court are TRG’s financial statements and general ledgers for the

entire period of contract performance. 
Id. 51-701, 718-1711, 1715-2704.
Given these

records and the contract’s provisions cited above, the court finds that the plaintiff fails to


16
  The court does not find, as the government argues, that injury, assuming proof of breach, can
only be established by reference to plaintiff’s actual labor hours—hours that the parties do not
dispute were not recorded on a per call basis. Under the approach discussed above, TRG might
be able to establish injury by demonstrating that the number of monthly labor hours spent on
service calls—as calculated by R.S. Means or other commercially available estimating systems
and based upon the daily work sheets—required compensation above and beyond the monthly
$15,000 FFP without regard to the 5% variance clause. Additionally, the court recognizes that
TRG may have incurred other additional costs, such as material costs for example, as a result of
the increased workload.

                                               34
demonstrate that there is not a more reliable method for establishing damages. See

Dawco, 930 F.2d at 880
(holding that “reasonable computation” of damages from “actual

figures” is favored over the jury verdict method). The court therefore agrees with the

government that TRG cannot ignore the available data and rely on Mr. Bricker’s report,

which is based on an assumed $300 per routine service call charge with percentages

added for their non-routine calls as proof of damages.

IV.   Conclusion

      For the foregoing reasons, the government’s motion for summary judgment is

GRANTED-in-PART and DENIED-in-PART. Counts IV and V of the plaintiff’s

complaint are DISMISSED. The parties shall file a joint status report detailing proposed

next steps in the litigation by September 9, 2013.

      IT IS SO ORDERED.



                                                         s/Nancy B. Firestone
                                                         NANCY B. FIRESTONE
                                                         Judge