Elawyers Elawyers
Washington| Change

Eco Tour Adventures, Inc. v. United States, 13-532C (2013)

Court: United States Court of Federal Claims Number: 13-532C Visitors: 52
Judges: Bush
Filed: Dec. 12, 2013
Latest Update: Mar. 02, 2020
Summary: In the United States Court of Federal Claims No. 13-532 C (Filed December 12, 2013)1 ********************* Pre-Award Bid Protest; National ECO TOUR ADVENTURES, INC., * Park Service Concessions * Management Improvement Act Plaintiff, * of 1998, 16 U.S.C. §§ 5951-5966 * (2012); Right of Preference for v. * Preferred Offerors; Procurement * Integrity Act, 41 U.S.C. §§ 2101- THE UNITED STATES, * 2107 (Supp. V 2011); Implied * Contract to Consider Bids Fairly Defendant. * and Honestly. **************
More
              In the United States Court of Federal Claims
                                         No. 13-532 C

                                 (Filed December 12, 2013)1

*********************                                  Pre-Award Bid Protest; National
ECO TOUR ADVENTURES, INC., *                           Park Service Concessions
                           *                           Management Improvement Act
              Plaintiff,   *                           of 1998, 16 U.S.C. §§ 5951-5966
                           *                           (2012); Right of Preference for
         v.                *                           Preferred Offerors; Procurement
                           *                           Integrity Act, 41 U.S.C. §§ 2101-
THE UNITED STATES,         *                           2107 (Supp. V 2011); Implied
                           *                           Contract to Consider Bids Fairly
              Defendant.   *                           and Honestly.
*********************

       Kevin R. Garden, Alexandria, VA, for plaintiff.

      Joshua A. Mandlebaum, United States Department of Justice, with whom
were Stuart F. Delery, Assistant Attorney General, Jeanne E. Davidson, Director,
and Reginald T. Blades, Jr., Assistant Director, Washington, DC, for defendant.
                         _________________________

                                 OPINION AND ORDER
                               _________________________

BUSH, Senior Judge.

      Now pending before the court are the parties’ cross-motions for judgment on
the administrative record. Plaintiff Eco Tour Adventures, Inc. (Eco Tour) filed a
pre-award bid protest complaint on August 1, 2013, and filed an amended

       1
         / This opinion was issued under seal on November 26, 2013. Pursuant to ¶ 6 of the
ordering language, the parties were invited to identify proprietary or confidential material subject
to deletion on the basis that the material was protected/privileged. The parties submitted their
proposed redactions on December 11, 2013. Brackets ([ ]) identify the redacted portions of this
opinion.
complaint on August 8, 2013.2 In this protest, Eco Tour objects to the anticipated
award by the United States Department of the Interior, National Park Service (the
Park Service or NPS) of two concession contracts to provide guided cross-country
ski tours, including associated transportation and food services, in Grand Teton
National Park. Eco Tour alleges that certain actions taken by NPS in connection
with its selection of cross-country ski touring concessioners were arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law. Eco
Tour seeks a permanent injunction, declaratory relief, and bid preparation costs, as
well as attorney fees and costs incurred in pursuing this bid protest.

       The administrative record (AR) was originally filed on August 12, 2013, and
supplements to the AR were filed on September 6, 2013, and October 1, 2013.3
Briefing was filed according to an expedited schedule and oral argument was held
on November 8, 2013. As discussed below, the NPS violated applicable law, acted
arbitrarily and capriciously, and abused its discretion in concluding that incumbent
concessioners Jackson Hole Mountain Resort Corporation and The Hole Hiking
Experience, Inc. submitted proposals that were “responsive” to the requirements of
the prospectus and in allowing them to match the better terms of Eco Tour’s
proposals for the disputed contracts. Accordingly, plaintiff’s motion for judgment
on the administrative record is granted, and defendant’s motion for judgment on
the administrative record is denied.4




       2
         / The court notes that plaintiff’s name appears as “EcoTour” in several portions of the
administrative record, including in plaintiff’s proposals for the disputed contracts. See, e.g., AR
Tabs 21-22. However, the court will refer to plaintiff as “Eco Tour,” as that is the spelling of
plaintiff’s name used in the complaint and amended complaint.
       3
        / On September 6, 2013, the government filed a supplement to the AR with
documentation of the source-selection authority’s final decisions. AR Tabs 42-45. On October
1, 2013, the court granted the government’s unopposed motion to further supplement the AR to
include a copy of the signed transmittal letter accompanying Jackson Hole Mountain Resort
Corporation’s proposal. AR Tab 46.
       4
         / Although the court concludes that Eco Tour has prevailed on the merits of its bid
protest, the court does not grant all of plaintiff’s requested relief for the reasons discussed infra.


                                                   2
                                 BACKGROUND

I.    Statutory and Regulatory Framework for NPS Concession Contracts

       Congress first created the NPS in 1916, authorizing the Secretary of the
Interior to “grant privileges, leases, and permits for the use of land for the
accommodation of visitors in the various parks, monuments, or other reservations”
under the Secretary’s authority. Act of Aug. 25, 1916, ch. 408, Pub. L. No. 64-
235, § 3, 39 Stat. 535, 535; Circle Line-Statue of Liberty Ferry, Inc. v. United
States, 
76 Fed. Cl. 490
, 491 (2007) (Circle Line). From its inception, the NPS
offered financial incentives to attract concessioners to provide services in National
Park locations and to induce substantial capital investments on those lands. See
Circle 
Line, 76 Fed. Cl. at 491
; S. Rep. No. 89-765, at 7 (1965), reprinted in 1965
U.S.C.C.A.N. 3489, 3495. These incentives included a preferential right of
renewal, allowing an incumbent concessioner to renew its contract by matching the
best offer of any competing bidder so long as it had performed its present contract
satisfactorily. See Circle 
Line, 76 Fed. Cl. at 491
(citation omitted); S. Rep. No.
89-765, at 7, 10-11.

      For almost fifty years, the NPS recognized the preferential right of renewal
as a matter of policy, although it did not generally write such a term within its
concession contracts. Circle 
Line, 76 Fed. Cl. at 491
-92. In 1965, however,
Congress enacted the National Park Service Concession Policies Act, Pub. L. No.
89-249, 79 Stat. 969 (the 1965 Act), in order to “put into statutory form policies
which, with certain exceptions, have heretofore been followed by the National Park
Service in administering concessions.” S. Rep. No. 89-765, at 1.

      In November 1998, Congress revisited the issue of renewal preferences in
the National Park Service Concessions Management Improvement Act of 1998,
Pub. L. No. 105-391, tit. IV, 112 Stat. 3497, 3503 (the 1998 Act) (codified at 16
U.S.C. §§ 5951-5966 (2012)), which repealed the 1965 Act and “establish[ed] a
new and comprehensive concession management program for national parks.”
Nat’l Park Hospitality Ass’n v. Dep’t of the Interior, 
538 U.S. 803
, 806 (2003)
(National Park Hospitality); see also Circle 
Line, 76 Fed. Cl. at 492
. Having
found that “[t]rue competition simply did not exist” in the award of concession
contracts, Concession Contracts, 65 Fed. Reg. 20630, 20630 (Apr. 17, 2000),
Congress restricted the right of preference set forth in the 1965 Act to apply only to

                                          3
(1) “outfitting and guide” concessioners and (2) concessioners holding contracts
with annual gross receipts under $500,000, 16 U.S.C. § 5952(7)-(8); Circle 
Line, 76 Fed. Cl. at 492
; 65 Fed. Reg. at 20630-31. 5

      Under the 1998 Act, an outfitting and guide concessioner is entitled to
exercise a right of preference if each of the following requirements is satisfied:

                 (i) the contract with the outfitting and guide
                 concessioner does not grant the concessioner any interest
                 . . . in capital improvements on lands owned by the
                 United States within a unit of the National Park System
                 [with certain exceptions not relevant here] . . .

                 (ii) the Secretary determines that the concessioner has
                 operated satisfactorily during the term of the contract
                 (including any extension thereof); and

                 (iii) the concessioner has submitted a responsive
                 proposal for a proposed new contract which satisfies the
                 minimum requirements established by the Secretary
                 pursuant to [16 U.S.C. § 5952(4)].



       5
           / The 1998 Act defines the term “outfitting and guide concessions contract” as follows:

                 [A] concessions contract which solely authorizes the provision of
                 specialized backcountry outdoor recreation guide services which
                 require the employment of specially trained and experienced
                 guides to accompany park visitors in the backcountry so as to
                 provide a safe and enjoyable experience for visitors who otherwise
                 may not have the skills and equipment to engage in such activity.
                 Outfitting and guide concessioners, where otherwise qualified,
                 include concessioners which provide guided river running,
                 hunting, fishing, horseback, camping, and mountaineering
                 experiences.

16 U.S.C. § 5952(8)(B).


                                                  4
16 U.S.C. § 5952(8)(B). In contrast, a concessioner holding a concession contract
with annual gross receipts under $500,000 is entitled to exercise a right of
preference if requirements (ii) and (iii) above are satisfied. 
Id. § 5952(8)(C).
       The 1998 Act directed the Secretary of the Interior to promulgate regulations
“appropriate” for the implementation of the 1998 Act. 
Id. § 5965.
Pursuant to this
statutory grant of authority, the NPS promulgated implementing regulations in
April 2000. 65 Fed. Reg. 20630 (codified at 36 C.F.R. §§ 51.1-51.104 (2013)).

       Under the regulations, an incumbent concessioner that is eligible to exercise
a right of preference is referred to as a “preferred offeror.” 36 C.F.R. § 51.27(a).
A concessioner is a preferred offeror if each of the following conditions is met:

               (a) The concessioner was a satisfactory concessioner
               during the term of its concession contract . . . ;

               (b) The applicable new contract is a qualified concession
               contract . . . ; 6 and



       6
        / For purposes of 36 C.F.R. § 51.36(b), a new contract is a “qualified concession
contract” if the NPS Director determines that:

               (a) The new concession contract provides for the continuation of
               the visitor services authorized under a previous concession contract
               . . . ; and either

               (b) The new concession contract . . . is estimated to result in . . .
               annual gross receipts of less than $500,000 . . . ; or

               (c) The new concession contract is an outfitter and guide
               concession contract . . . .

Id. § 51.37.
“Visitor services” are defined as “accommodations, facilities and services
determined by the Director as necessary and appropriate for public use and enjoyment of a park
area provided to park area visitors for a fee or charge by a person other than the Director.” 
Id. § 51.3.
Such services “may include, but are not limited to, lodging, campgrounds, food service,
merchandising, tours, recreational activities, guiding, transportation, and equipment rental.” 
Id. 5 (c)
If applicable, the concessioner’s previous concession
               contract was an outfitter and guide concession contract . .
               ..

Id. § 51.36.
        Preferred offeror status does not guarantee a right of preference, however.
Under the regulations, in order to exercise a right of preference and match the best
offer of any competing bidder, a preferred offeror must first submit a “responsive”
proposal. 
Id. § 51.27(b)
(“A right of preference is the right of a preferred offeror,
if it submits a responsive proposal for a qualified concession contract, to match in
accordance with the requirements of this part the terms and conditions of a
competing proposal that the [NPS] Director has determined to be the best
responsive proposal.”) (emphasis added); 
id. § 51.30
(“A preferred offeror must
submit a responsive proposal . . . if the preferred offeror wishes to exercise a right
of preference.”); 
id. § 51.31.
A “responsive” proposal is “a timely submitted
proposal that is determined by the Director as agreeing to all of the minimum
requirements of the proposed concession contract and prospectus and as having
provided the information required by the prospectus.” 
Id. § 51.3.
        If a preferred offeror fails to submit a responsive proposal, the preferred
offeror “may not exercise a right of preference” and the contract “will be awarded
to the offeror submitting the best responsive proposal.” 
Id. § 51.31.
If, however,
the preferror offeror submits a responsive proposal, the NPS “must advise the
preferred offeror of the better terms and conditions of the best proposal and permit
the preferred offeror to amend its proposal to match them.” 
Id. § 51.32.
If a
preferred offeror amends its proposal within the time period allowed by the NPS,
and the NPS determines that the amended proposal matches the better terms and
conditions of the best proposal, then the NPS “must select the preferred offeror for
award of the contract upon the amended terms and conditions.” 
Id. Conversely, “[i]f
a preferred offeror does not amend its proposal to meet the terms and
conditions of the best proposal within the time period allowed by the Director, the
Director will select for award of the contract the offeror that submitted the best
responsive proposal.” 
Id. § 51.33.



                                            6
II.   The Disputed Contracts and Eco Tour’s Bid Protest

      On December 20, 2012, NPS issued a prospectus, titled “A Concession
Business Opportunity for Guided Ski Touring Services within Grand Teton
National Park,” soliciting proposals for three concession contracts – GRTE024-13,
GRTE025-13, and GRTE032-13 – for the provision of guided cross-country ski
touring services, including associated transportation and food services, in Grand
Teton National Park. AR Tabs 4-17 (prospectus and appendices). Proposals for
the contracts were to be submitted no later than March 20, 2013. AR Tab 4 at 9,
27.

      The concession services solicited by the prospectus are currently being
provided by incumbent concessioners Jackson Hole Mountain Resort Corporation
(Jackson Hole), under contract GRTE024-03; Powder Hounds, Inc., doing business
as Rendezvous Ski Tours, under contract GRTE025-03; and The Hole Hiking
Experience, Inc. (Hole Hiking), under contract GRTE032-03. The NPS has
“determined [that] the three existing Concessioners are qualified contracts and,
therefore the existing Concessioners are Preferred Offerors for the New Contracts.”
AR Tab 4 at 24; see also Tab 2 at 4 (concluding that “[a]ll three Winter Ski Tour
Contracts will be released as having preferred offeror status”). The agency’s
determination in that regard is not in dispute.

       The prospectus included detailed instructions setting forth the protocol for
submitting proposals and the selection factors to be used by the NPS to evaluate
proposals. See AR Tab 4 at 25-31. Of particular relevance to this bid protest, the
instructions state that “[o]nly an Offeror submitting a responsive proposal is
eligible to be awarded the new concession contract.” 
Id. at 27.
The instructions
define a “responsive proposal” as a “timely submitted proposal that is determined
by the Service as agreeing to all of the minimum requirements of the draft
concession contract and Prospectus and as having provided the information
required by the Prospectus.” 
Id. In addition,
paragraph 1(d) of the instructions
defines “information required by the prospectus” as “information expressly
required by the Prospectus and that is material, as determined by the Service, to an
effective evaluation of the proposal under the applicable selection factor.” 
Id. at 27
(emphasis added).




                                         7
       The instructions further provide that NPS, when evaluating proposals, “will
apply the principal selection factors and secondary factors as set forth in 36 C.F.R.
Part 51 by assessing each timely proposal under each of the selection factors on the
basis of a narrative explanation discussing any subfactors when applicable and
other supporting information.” 
Id. at 28.7
The principal and secondary selection
factors set forth in the instructions are:

               Principal Selection Factor 1. The responsiveness of the
               proposal to the objectives, as described in the prospectus,
               of protecting, conserving, and preserving resources of the
               park area;

               Principal Selection Factor 2. The responsiveness of the
               proposal to the objectives, as described in the prospectus,
               of providing necessary and appropriate visitor services at
               reasonable rates;

               Principal Selection Factor 3. The experience and
               related background of the Offeror, including the past
               performance and expertise of the Offeror in providing the
               same or similar visitor services as those to be provided
               under the new concession contract;

               Principal Selection Factor 4. The financial capability
               of the Offeror to carry out its proposal;

               Principal Selection Factor 5. The amount of the
               proposed minimum franchise fee, if any, and/or other
               forms of financial consideration to the Service.
               Consideration of revenue to the United States will be
               subordinate to the objectives of protecting, conserving,
               and preserving resources of the park area and of
               providing necessary and appropriate visitor services to
               the public at reasonable rates; and
       7
        / The selection factors set forth in the prospectus are consistent with those set forth in
the 1998 Act, see 16 U.S.C. § 5952(5), and the regulations, see 36 C.F.R. § 51.17.


                                                 8
             ....

             Secondary Selection Factor 1. The quality of the
             Offeror’s proposal to conduct its operations in a manner
             that furthers the protection, conservation, and
             preservation of the park area and other resources through
             environmental management programs and activities,
             including, without limitation, energy conservation, waste
             reduction, and recycling.

Id. at 29.
Each proposal was to receive a “score that reflects the determined merits
of the proposal under the applicable selection factor and in comparison to the other
proposals received.” AR Tab 4 at 28. The first four principal selection factors
were to be scored from zero to five; the fifth principal selection factor was to be
scored from zero to four; and the secondary selection factor was to receive a score
from zero to three. 
Id. The NPS
would then “assign a cumulative point score to
each proposal based on the assigned score for each selection factor.” 
Id. at 29.
       The prospectus also included a proposal package explaining the minimum
requirements of the disputed contracts as well as the information required by the
prospectus. Part A of the proposal package sets forth the minimum requirements
of the disputed contracts. 
Id. at 27
, 41. Although Part A states that principal
selection factors 3 and 4 “do not have specific requirements,” it also states that
certain information “is required for principal selection factors 3 and 4” and that
“[f]ailure to provide material information required thereunder may result in an
offeror being deemed non-responsive.” 
Id. at 41.
       Part B of the proposal package provides explanations for each of the
selection factors, and also sets forth various subfactors to be considered by the
NPS in evaluating proposals. Of particular relevance here, the subfactors under
principal selection factor 4 list the specific information “required” by Part A of the
proposal package:

             Subfactor 4(a). Demonstrate that you have a credible,
             proven track record of meeting your financial
             obligations by providing the following:

                                          9
     (1) The completed Business History Information
     Form provided on the next page. . . .
     (2) Financial statements for the two most recent
     fiscal years in one of the following formats:

        o NPS Concessioner Annual Financial Reports
          (AFR), including a current balance sheet if a
          balance sheet was not submitted as part of the
          AFR. . . .

     (3) A CURRENT credit report (within the last six
     months) in the name of the Offeror from a major
     credit reporting company such as Equifax,
     Experian, TRW or Dun & Bradstreet. . . .

Subfactor 4(b). Demonstrate that your proposal is
financially viable and that you understand the
financial obligations of the Draft Contract by
providing the following:

     (1) Please list . . . the personal property
     (equipment) . . . with monetary value over $500
     that you will be using for this operation. Please
     note whether you currently own this equipment or
     not. . . .

     (2) Please estimate the amount of money that you
     will need to begin operating the business in the
     format of the table below. Only provide estimates
     for the Personal Property items (Equipment) that
     you need to acquire in order to begin operating.
     Do not include items that you already own. . . .

     (3) Please demonstrate that your proposal is
     financially feasible (that you will have a
     reasonable opportunity to make a profit from your

                         10
                      business while carrying out the terms and
                      conditions of the Draft Contract) by completing
                      the Proforma Income Statement and Operating
                      Assumptions. . . .

                         o Please fully explain the assumptions on which you
                           base your projections and detail them sufficiently
                           so the Service can determine whether the
                           projections are realistic. . . .

                Subfactor 4(c). Demonstrate your ability to obtain
                the required funds for start-up costs under the Draft
                Contract by providing credible, compelling
                documentation, particularly evidence from
                independent sources, such as bank statements,
                financial statements, and signed loan commitment
                letters. Fully explain the financial arrangements you
                propose, using the following guidelines:

                      ....

                      (4) Current bank statements must be provided,
                      regardless of the funding source . . . . Current
                      bank statements must be provided even if you do
                      not anticipate significant start-up costs.

Id. at 49-54.
      For contract GRTE024-13, the NPS received timely proposals from Eco
Tour, Jackson Hole (the preferred offeror), and two other offerors. AR Tabs 20-
21. For contract GRTE032-13, the NPS received timely proposals from Eco Tour,
Hole Hiking (the preferred offeror), and two other offerors. AR Tabs 19, 22. Eco
Tour did not compete for contract GRTE025-13; therefore, the only contracts in
dispute are contract GRTE024-13 and contract GRTE032-13.

       An evaluation panel reviewed each proposal against the five principal
selection factors and one secondary selection factor, and assigned cumulative

                                          11
scores to each proposal. AR Tabs 23-24. Eco Tour’s proposals received the
highest cumulative scores for both contract GRTE024-13 and contract GRTE032-
13. AR Tab 23 at 1094, Tab 24 at 1120. The evaluation panel therefore
determined that Eco Tour submitted the best proposals for both contracts. AR
Tabs 28-29, Tab 42 at 1272-75, 1304-07, Tab 43 at 1312-15, 1344-47.

       In its evaluation of Jackson Hole’s and Hole Hiking’s proposals, the panel
found that each offeror had omitted certain financial information specified by
principal selection factor 4. AR Tab 23 at 1112-16, Tab 24 at 1138-42, Tab 42 at
1273, Tab 43 at 1313. Despite these omissions, the panel nevertheless found
Jackson Hole’s and Hole Hiking’s proposals to be “responsive to the minimum
requirements of the Prospectus.” AR Tab 30 at 1190, Tab 31 at 1193; see also AR
Tab 42 at 1273-74, 1304-06, Tab 43 at 1313-14, 1344-46. Accordingly, in letters
dated June 20, 2013, the NPS advised Jackson Hole and Hole Hiking that they
could exercise a right of preference by agreeing to match twelve terms of Eco
Tour’s proposals that the evaluation panel “determined were elements of a better
offer”:

            1.   Principal Selection Factor 1 Subfactor (a). The
                 best proposal committed to an Idle Free Policy to
                 protect the air that surrounds the park as well as
                 minimize any disturbance to wildlife from the sound
                 of a running vehicle. . . .

            2.   Principal Selection Factor 1 Subfactor (a). The
                 best proposal committed to requiring guides to carry
                 a minimum of one pair of binoculars on each tour to
                 share with guests. . . .

            3.   Principal Selection Factor 1 Subfactor (b). The
                 best proposal committed to carrying a vehicle spill
                 kit to contain fluid spills in case of leaks or
                 accidents. The best proposal committed to scanning
                 the parking area and cleaning up any leaks from the
                 vehicle. . . . An example of a spill kit is the Pig Spill
                 Kit in Spill Pack.



                                         12
4.   Principal Selection Factor 1 Subfactor (b). The
     best proposal committed to removing all solid
     human waste with human waste removal bags. The
     best proposal committed to carrying one human
     waste removal bag per person, in addition to extra
     bags in case they are needed. The best proposal
     committed to removing all toilet paper and hygiene
     products. . . . An example of the human waste
     removal bags are the Cleanwaste WagBag products.

5.   Principal Selection Factor 1 Subfactor (b). The
     best proposal committed to removing all trash
     created while on tours and disposing of the waste
     outside of the Park, in order to limit the frequency of
     trash trucks traveling in the park. . . .

6.   Principal Selection Factor 2 Subfactor (b). The
     best proposal committed to requiring Wilderness
     First Responder certification for all guides. . . .

7.   Principal Selection Factor 2 Subfactor (b). The
     best proposal committed to requiring all driving
     guides to complete a winter driving program. . . .

8.   Principal Selection Factor 5 . . . . The best
     proposal committed to a franchise fee of 4.25% of
     annual gross receipts or a flat fee of $500, whichever
     is greater. . . .

9.   Secondary Selection Factor 1 Subfactor (a). The
     best proposal committed to using reusable plates,
     reusable silverware, cloth napkins and reusable mugs
     on the tour in order to reduce the amount of trash
     produced on each tour. . . .

10. Secondary Selection Factor 1 Subfactor (a). The
    best proposal committed to providing each guest

                             13
                  with a high quality, Made in America, reusable water
                  bottle for guest use on the tour. Guests are given the
                  bottle to take home with them. The goal of the water
                  bottle is to limit plastic petroleum disposable bottles
                  and encourage visitors to reuse their new water
                  bottle while in the area. . . .

             11. Secondary Selection Factor 1 Subfactor (a). The
                 best proposal described how it will train its guides
                 about the Wilderness Act using, among other
                 methods, an online training course called “The
                 Wilderness Act of 1964” produced by the Eppley
                 Institute for Parks and Public Lands. . . .

             12. Secondary Selection Factor 1 Subfactor (a). The
                 best proposal described how it will monitor the
                 accuracy of the information guides provide on tours
                 by having the owner or manager shadow each guide
                 unannounced at least once per season. . . .

AR Tab 30 at 1190-91, Tab 31 at 1193-94.

        The NPS also asked both Jackson Hole and Hole Hiking to “expand on your
initial response . . . in order to bring the quality of your response up to the level of
the best proposal” by providing the financial information that had been omitted
from Jackson Hole’s and Hole Hiking’s proposals. AR Tab 30 at 1192, Tab 31 at
1195. In that regard, the NPS requested the following financial information that
had been omitted from Jackson Hole’s proposal:

             1.   Principal Selection Factor 4 Subfactor (a). The
                  best proposal provided a complete set of financial
                  statements. Although you submitted an Annual
                  Financial Report (AFR), it did not contain a balance
                  sheet. Please submit a current balance sheet or a
                  balance sheet as of the year ending date of the AFR.




                                           14
            2.   Principal Selection Factor 4 Subfactor (a). The
                 best proposal provided a current credit report.
                 Although you provided your Dun & Bradstreet
                 Company ID, the National Park Service (Service) is
                 unable to run the report. Please submit a current
                 credit report for each Offeror-Guarantor.

            3.   Principal Selection Factor 4 Subfactor (c). The
                 best proposal provided a current bank statement as
                 requested in Principal Selection Factor 4 Subfactor c,
                 question 4. Please submit a current bank statement.

AR Tab 30 at 1192. Additionally, the NPS requested the following financial
information that had been omitted from Hole Hiking’s proposal:

            1.   Principal Selection Factor 4 Subfactor (a). The
                 best proposal provided a complete set of financial
                 statements. Although you submitted an Annual
                 Financial Report (AFR) it did not appear to be
                 complete. Please submit the complete AFR for 2011
                 and 2012.

            2.   Principal Selection Factor 4 Subfactor (b). The
                 best proposal provided clear revenue and expense
                 projection assumptions. Please submit additional
                 assumptions for your revenue and expense
                 projections. The panel is interested in understanding
                 why revenue projections are so much higher than
                 historical projections and why some of the expense
                 assumptions appear low.

            3.   Principal Selection Factor 4 Subfactor (b). The
                 best proposal provided a clear Pro forma. Please
                 correct the mathematical errors on the Pro forma and
                 resubmit.




                                        15
             4.   Principal Selection Factor 4 Subfactor (c). The
                  best proposal provided substantial documentation
                  related to its financial position. Although you
                  provided a balance sheet and bank statement, the
                  reporting period of the balance sheet did not
                  correspond with the bank statement. The panel is
                  interested in understanding your financial position,
                  specifically, if you have a cash position to respond to
                  any unanticipated expenses as you indicated you do
                  not need any financing in Subfactor 4c. Please
                  submit a current bank statement with a list of current
                  liabilities.

AR Tab 31 at 1195.

      Both Jackson Hole and Hole Hiking timely exercised a right of preference
by agreeing to match the twelve terms set forth in NPS’s June 20, 2013 letters and
by providing the requested additional financial information. AR Tabs 25-26, Tabs
32-35, Tab 38, Tab 44 at 1368-83, Tab 45 at 1400-20.

        Eco Tour filed its bid protest complaint in this court on August 1, 2013, and
filed an amended complaint on August 8, 2013. Eco Tour’s amended complaint
contains three counts. In Count I, Eco Tour alleges that the NPS violated
applicable law, acted arbitrarily and capriciously, and abused its discretion by
finding that Jackson Hole’s and Hole Hiking’s proposals were “responsive” to the
requirements of the prospectus and by allowing them to match the better terms of
Eco Tour’s proposals for contracts GRTE024-13 and GRTE032-13. In Count II,
Eco Tour alleges that the NPS violated the Procurement Integrity Act, as amended,
41 U.S.C. §§ 2101-2107 (Supp. V 2011), by disclosing to Jackson Hole and Hole
Hiking information that Eco Tour had allegedly marked in its proposal as
confidential. Finally, in Count III, Eco Tour alleges that the NPS violated
applicable law, acted arbitrarily and capriciously, and abused its discretion when it
found that Jackson Hole and Hole Hiking had matched all of the better terms of
Eco Tour’s proposals for contracts GRTE024-13 and GRTE032-13. With respect
to all three counts, Eco Tour further asserts that the NPS’s actions breached an
implied contractual obligation of the government to consider bids fairly and
honestly.

                                         16
       On August 19, 2013, the court amended the briefing schedule to allow time
for the government to obtain final decisions from the source-selection authority. 8
The source-selection authority subsequently determined that Eco Tour, Jackson
Hole, and Hole Hiking had submitted responsive proposals for the contracts at
issue, that Eco Tour’s proposals were the best, and that Jackson Hole and Hole
Hiking had amended their proposals to match the terms of Eco Tour’s best
proposals. AR Tabs 42-45. On September 4, 2013, the source-selection authority
determined that contracts GRTE024-13 and GRTE032-13 should be awarded to
Jackson Hole and Hole Hiking, respectively. AR Tab 44 at 1352-53, Tab 45 at
1384-85.

                                      DISCUSSION

I.     Jurisdiction

       Before proceeding to the merits of Eco Tour’s bid protest, the court must
address the threshold issue of jurisdiction. Steel Co. v. Citizens for a Better Env’t,
523 U.S. 83
, 94-95 (1998) (“The requirement that jurisdiction be established as a
threshold matter . . . is ‘inflexible and without exception.’” (quoting Mansfield, C.
& L. M. Ry. Co. v. Swan, 
111 U.S. 379
, 382 (1884))); Hambsch v. United States,
857 F.2d 763
, 765 (Fed. Cir. 1988) (“When a court is without jurisdiction to hear a
case, it is correspondingly without authority to decide the merits of that case.”)
(citations omitted).

      Although the government does not question the court’s jurisdiction to
consider Eco Tour’s claims, the parties dispute the source of that jurisdiction and,
       8
        / On August 15, 2013, the government filed a motion to dismiss the amended complaint
on ripeness grounds based on the government’s assertion that the source-selection authority had
not rendered final decisions with respect to the award of the disputed contracts. On August 19,
2013, the court deferred ruling and suspended briefing on defendant’s motion to allow the
source-selection authority to render final decisions and to allow defendant to supplement the
administrative record accordingly. The government filed a supplement to the AR with
documentation of the source-selection authority’s final decisions on September 6, 2013, AR Tabs
42-45, and the government did not renew its motion to dismiss in connection with its motion for
judgment on the administrative record. Accordingly, the court denies defendant’s motion to
dismiss as moot.


                                              17
correspondingly, the nature of the relief the court is authorized to grant. Eco Tour
seeks injunctive and declaratory relief, as well as bid preparation costs, and asserts
that the court possesses jurisdiction to grant such relief pursuant to 28 U.S.C. §
1491(a)(1) (2006) and 28 U.S.C. § 1491(b)(1) (2006). See Am. Compl. ¶ 1; Pl.’s
Mot. at 43-48. Defendant contends that “[r]elief under 28 U.S.C. § 1491(b) is
unavailable because the contracts at issue are not procurements.” Def.’s Mot. at
28. For the reasons specified below, the court agrees with the government that
section 1491(a)(1) – not section 1491(b)(1) – provides the jurisdictional basis for
Eco Tour’s claims.

       Section 1491(b)(1), which Congress added to the Tucker Act by enacting the
Administrative Dispute Resolution Act of 1996 (ADRA), Pub. L. No. 104-320,
sec. 12, § 1491, 110 Stat. 3870, 3874, grants the court “jurisdiction to render
judgment on an action by an interested party objecting to a solicitation by a Federal
agency for bids or proposals for a proposed contract or to a proposed award or the
award of a contract or any alleged violation of statute or regulation in connection
with a procurement or a proposed procurement.” 28 U.S.C. § 1491(b)(1)
(emphasis added). As the United States Court of Appeals for the Federal Circuit
has held, “relief under [section] 1491(b)(1) is unavailable outside the procurement
context.” Res. Conservation Grp., LLC v. United States, 
597 F.3d 1238
, 1245
(Fed. Cir. 2010) (Resource Conservation). Thus, whether the court has jurisdiction
under section 1491(b)(1) depends upon whether the disputed solicitation for
concessions contracts involved a “procurement.”

      Section 1491(b) does not define the term “procurement.” However, for
purposes of determining the scope of section 1491(b), the Federal Circuit has
adopted the definition of “procurement” contained in 41 U.S.C. § 403(2), which
has been reorganized into 41 U.S.C. § 111 (Supp. V 2011). Resource
Conservation, 597 F.3d at 1244
(citing Distributed Solutions, Inc. v. United States,
539 F.3d 1340
, 1345-46 (Fed. Cir. 2008)). Section 111 provides that “the term
‘procurement’ includes all stages of the process of acquiring property or services,
beginning with the process for determining a need for property or services and
ending with contract completion and closeout.” 41 U.S.C. § 111.

      The court has previously noted the existence of “conflicting authority as to
whether a solicitation for concession contracts is a ‘procurement.’” Frazier v.
United States, 
79 Fed. Cl. 148
, 160 & n.5 (2007), aff’d, 301 F. App’x 974 (Fed.

                                          18
Cir. 2008). This court has thrice ruled that concession contracts are not
procurement contracts, albeit not in the specific context of a bid protest
jurisdictional challenge. Terry v. United States, 
98 Fed. Cl. 736
, 737 (2011)
(holding that a concession contract for the operation of a t-shirt kiosk at Fort
Benning was not a procurement contract subject to the Contract Disputes Act
(CDA), 41 U.S.C. §§ 7101-7109 (Supp. V 2011), because it did not involve the
procurement of property or services by the government); Frazier v. United States,
67 Fed. Cl. 56
, 59 (2005) (same with respect to a concession lease for the operation
of a marina on a federal reservoir), aff’d, 186 F. App’x 990 (Fed. Cir. 2006); YRT
Servs. Corp. v. United States, 
28 Fed. Cl. 366
, 392 n.23 (1993) (YRT Services)
(concluding that an NPS concession contract for the provision of “lodging, food
and gift services” in Yosemite National Park “does not constitute a procurement,
but is a grant of a permit to operate a business and the government is not
committing to pay out government funds or incur any monetary liability”). 9

       In contrast to YRT Services and related decisions of this court, the Interior
Board of Contract Appeals has consistently held that NPS concession contracts are
procurement contracts subject to the CDA, see, e.g., Watch Hill Concessions, Inc.,
IBCA No. 4284-2000, 
2001 WL 170911
(Feb. 16, 2001) (holding that “at least in
any concession contract where the concessioner is required to perform specific
services or to make specific improvements to the land it occupies, as is the case
here, the contract is a procurement contract, subject to the Contract Disputes Act”),
and the Government Accountability Office (GAO) has consistently held that
concession contracts which involve the delivery of more than de minimis services
to a federal agency are procurement contracts, see, e.g., Great South Bay Marina,

       9
          / In Blue & Gold Fleet, LP v. United States, 
70 Fed. Cl. 487
(2006), aff’d, 
492 F.3d 1308
(Fed. Cir. 2007) (Blue & Gold Fleet), this court assumed, without deciding, that it had
jurisdiction under section 1491(b) over a pre-award bid protest involving an NPS concession
solicitation. 70 Fed. Cl. at 492
. Jurisdiction was not challenged on appeal, and the Federal
Circuit likewise assumed, without deciding, that the Court of Federal Claims had jurisdiction
under section 
1491(b). 492 F.3d at 1313
, 1315. The Federal Circuit in Blue & Gold Fleet did
not address the issue of whether NPS concession contracts are procurement contracts subject to
section 1491(b). This is unsurprising, given that Blue & Gold Fleet was decided before
Resource Conservation, which clarified that section 1491(b)(1) bid protest jurisdiction is limited
to the procurement 
context. 597 F.3d at 1245
. Because Blue & Gold Fleet did not address the
issue of the jurisdictional basis for bid protests involving NPS concession contracts, it is not
dispositive of that issue here.


                                               19
Inc., B-296335, 2005 CPD ¶ 135, 
2005 WL 1650829
, at *1 (Comp. Gen. July 13,
2005) (“It has consistently been our Office’s view that a mixed transaction that
includes the delivery of goods or services of more than de minimis value to the
government is a contract for the procurement of property or services within the
meaning of [the Competition in Contracting Act, 31 U.S.C. §§ 3551-3556
(2006)].” (citing Starfleet Marine Transp., Inc., B-290181, 2002 CPD ¶ 113, 
2002 WL 1461877
(Comp. Gen. July 5, 2002))).

       The court, cognizant of the somewhat conflicting authority on this issue,
concludes that the greater weight of authority is to the effect that NPS concession
contracts, such as those in dispute in this bid protest, are not contracts for the
procurement of goods and services, and thus are not subject to the court’s section
1491(b) jurisdiction. As an initial matter, the court notes that the prospectus at
issue here “is issued under the authority of” the regulations set forth at 36 C.F.R.
§§ 51.1-51.104, which are incorporated by reference into the prospectus and
control in the event of any inconsistency between the terms of the prospectus and
the regulations. See AR Tab 4 at 27. In the regulations, the NPS has taken the
position that NPS concession contracts “are not contracts within the meaning of
[the CDA] and are not service or procurement contracts within the meaning of
statutes, regulations or policies that apply only to federal service contracts or other
types of federal procurement actions.” 36 C.F.R. § 51.3; see also National Park
Hospitality, 538 U.S. at 806
(quoting 36 C.F.R. § 51.3); 65 Fed. Reg. at 20635
(“NPS concession contracts [under the 1998 Act] do not procure services for the
government; rather, they authorize third parties to provide services to park area
visitors.”).

        Although the court is not bound to accept the agency’s views regarding NPS
concession contracts, the agency’s reasoning finds support in the language of the
1998 Act, which indicates in several places that NPS concession contracts are for
the provision of goods and services to the public, not to the government. See, e.g.,
16 U.S.C. § 5952 (directing the Park Service to enter into concession contracts “to
authorize a person, corporation or other entity to provide accommodations,
facilities and services to visitors to units of the National Park System”) (emphasis
added); 
id. § 5955
(requiring that “[e]ach concessions contract shall permit the
concessioner to set reasonable and appropriate rates and charges for facilities,
goods, and services provided to the public”) (emphasis added). The 1998 Act also
requires that “[a] concessions contract shall provide for payment to the government

                                          20
of a franchise fee or such other monetary consideration as determined by the
Secretary.” 16 U.S.C. § 5956; see also AR Tab 4 at 24, 41, 55, 64 (prospectus
stating that concessioners will be charged a “franchise fee” equal to at least three
percent of the concessioner’s gross receipts or a flat fee of $500, whichever is
greater). Thus, according to the language of the 1998 Act itself, NPS concession
contracts appear to be unlike traditional government procurement contracts insofar
as the government does not make payments to the contractor in exchange for the
provision of goods or services to the government; instead, concessioners pay the
government a fee for the privilege of charging the public for services provided to
the public. See YRT 
Services, 28 Fed. Cl. at 392
n.23. The essence of NPS
concession contracts is not the acquisition of goods or services by the government,
but the grant, for a fee, of certain rights to private contractors.

      The agency’s reasoning also finds support in the legislative history of the
1998 Act. The committee reports accompanying the 1998 Act concluded that Park
Service concession contracts “do not constitute contracts for the procurement of
goods and services for the benefit of the government or otherwise.” S. Rep. No.
105-202, at 39 (1998); H.R. Rep. No. 105-767, at 43 (1998).

       Additionally, it is worth noting that the United States Court of Appeals for
the District of Columbia Circuit has concluded, in the context of a challenge to 36
C.F.R. § 51.3, that NPS concession contracts are not procurement contracts subject
to the CDA. See Amfac Resorts, L.L.C. v. Dep’t of the Interior, 
282 F.3d 818
, 835
(D.C. Cir. 2002) (“A procurement contract . . . is a contract for which the
government bargains for, and pays for, and receives goods and services.
Concession contracts are not of that sort.”) (citation and internal quotation marks
omitted), vacated on other grounds sub nom National Park Hospitality, 
538 U.S. 803
. Although the D.C. Circuit’s opinion in Amfac Resorts was later vacated by
the United States Supreme Court on ripeness grounds, see National Park
Hospitality, 538 U.S. at 808-12
, its analysis nevertheless provides further support
for the conclusion that NPS concession contracts are not procurement contracts
because they do not involve the payment of money or conferral of a benefit by the
government in exchange for goods and services.

      The court has considered Eco Tour’s arguments in support of section
1491(b) jurisdiction and finds them unpersuasive. In its reply brief, Eco Tour
argues that “the contracts at issue qualify as procurements by NPS of services,

                                         21
through contractors, that meet NPS’s statutory obligations” under the 1998 Act.
Pl.’s Reply at 22. This ipse dixit argument carries no authoritative weight, and
avails Eco Tour nothing. Accordingly, the court concludes that the concession
contracts in dispute are not procurement contracts and, consequently, the court
lacks jurisdiction under section 1491(b).

       As noted, Eco Tour also alleges that defendant’s actions breached an implied
contractual obligation to treat offerors fairly. See Am. Compl. ¶¶ 105, 115, 122;
Pl.’s Mot. at 40-42. This court has long had jurisdiction, under 28 U.S.C. §
1491(a), to hear cases and grant relief premised on the theory that when the
government invites bids or solicits proposals from the public, it enters into an
“implied-in-fact” contract to consider those bids or proposals fairly. See e.g.,
Resource 
Conservation, 597 F.3d at 1242
; Impresa Construzioni Geom. Domenico
Garufi v. United States, 
238 F.3d 1324
, 1331 (Fed. Cir. 2001); Southfork Sys., Inc.
v. United States, 
141 F.3d 1124
, 1132 (Fed. Cir. 1998); CACI, Inc.-Federal v.
United States, 
719 F.2d 1567
, 1573 (Fed. Cir. 1983). The Federal Circuit recently
held, in Resource Conservation, that this court’s implied-in-fact contract
jurisdiction under section 1491(a) survives, post-ADRA, for bid protests in which
section 1491(b) may not provide a 
remedy. 597 F.3d at 1245-47
. Based on this
binding precedent, the court concludes that it has jurisdiction over Eco Tour’s
implied contract claims under section 1491(a).

II.   Standards of Review

      A.    Judgment on the Administrative Record

       Rule 52.1(c) of the Rules of the United States Court of Federal Claims
(RCFC) provides for judgment on the administrative record. To review a motion
or cross-motions under RCFC 52.1(c), the court asks whether, given all the
disputed and undisputed facts, a party has met its burden of proof based on the
evidence in the record. Bannum, Inc. v. United States, 
404 F.3d 1346
, 1356-57
(Fed. Cir. 2005). The court must make factual findings where necessary. 
Id. The resolution
of RCFC 52.1(c) cross-motions is akin to an expedited trial on the paper
record. 
Id. 22 B.
    Bid Protest Review

       The court first examines whether the plaintiff in a bid protest has standing to
bring the suit. Info. Tech. & Applications Corp. v. United States, 
316 F.3d 1312
,
1319 (Fed. Cir. 2003) (ITAC). Bid protest standing is limited to those plaintiffs
who are actual or prospective bidders and whose direct economic interest would be
affected by the award of the contract or by the failure to award the contract. Orion
Tech., Inc. v. United States, 
704 F.3d 1344
, 1348 (Fed. Cir. 2013) (citation
omitted). In the circumstances of a pre-award protest where, as here, an award
decision has been made but not finalized, a protester possessing a “substantial
chance” of winning the disputed contract has a “direct economic interest” and has
standing before this court. 
Id. at 1348-49.
       Upon determining that a plaintiff has standing to sue, the court next
considers the merits of the bid protest. A bid protest proceeds in two steps, with
the trial court first determining whether the government acted without a rational
basis or contrary to law, and then determining as a factual matter whether the
plaintiff was prejudiced by the arbitrary or unlawful conduct. 
Bannum, 404 F.3d at 1351
.

       The standard of review for the typical bid protest brought pursuant to section
1491(b) is whether the agency action was arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law (the APA standard). 28 U.S.C.
§ 1491(b)(4) (incorporating the APA standard set forth in 5 U.S.C. § 706 (2012));
Banknote Corp. of Am. v. United States, 
365 F.3d 1345
, 1350-51 (Fed. Cir. 2004)
(citing Advanced Data Concepts, Inc. v. United States, 
216 F.3d 1054
, 1057-58
(Fed. Cir. 2000)). Under the APA standard, a procurement decision may be set
aside if it lacks a rational basis or if the agency’s decision-making involved a clear
and prejudicial violation of statute or regulation. 
Banknote, 365 F.3d at 1351
;
Emery Worldwide Airlines, Inc. v. United States, 
264 F.3d 1071
, 1085-86 (Fed.
Cir. 2001) (citing 
Impresa, 238 F.3d at 1332-33
).

       The APA standard is “highly deferential.” Advanced Data 
Concepts, 216 F.3d at 1058
. Under this standard, de minimis errors in the procurement process do
not justify relief. Grumman Data Sys. Corp. v. Dalton, 
88 F.3d 990
, 1000 (Fed.
Cir. 1996) (citing Andersen Consulting v. United States, 
959 F.2d 929
, 932-33, 935
(Fed. Cir. 1992)). A bid protest plaintiff bears the burden of proving that a

                                         23
significant error marred the procurement in question. 
Id. (citing CACI
Field
Servs., Inc. v. United States, 
854 F.2d 464
, 466 (Fed. Cir. 1988)). Examples of
arbitrary and capricious agency action include “when the agency ‘entirely failed to
consider an important aspect of the problem, offered an explanation for its decision
that runs counter to the evidence before the agency, or [the decision] is so
implausible that it could not be ascribed to a difference in view or the product of
agency expertise.’” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 
586 F.3d 1372
, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm
Mut. Auto. Ins. Co., 
463 U.S. 29
, 43 (1983)) (alteration in original). The court will,
however, “uphold a decision of less than ideal clarity if the agency’s path may
reasonably be discerned.” Bowman Transp., Inc. v. Arkansas-Best Freight Sys.,
Inc., 
419 U.S. 281
, 286 (1974) (citation omitted).

       Similarly, to recover under the implied contract for bids to be fairly and
honestly considered in a protest brought pursuant to section 1491(a), a plaintiff
must establish that the agency acted arbitrarily or capriciously, or abused its
discretion. 
Southfork, 141 F.3d at 1132
(citing Keco Indus., Inc. v. United States,
492 F.2d 1200
, 1203 (Ct. Cl. 1974) (Keco II)); Distributed Solutions, Inc. v. United
States, 
106 Fed. Cl. 1
, 25 (2012) (citations omitted), aff’d, 500 F. App’x 955 (Fed.
Cir. 2013); FAS Support Servs., LLC v. United States, 
93 Fed. Cl. 687
, 694 (2010)
(citing Keco II, 
492 F.2d 1200
). The standard of review for a bid protest alleging a
breach of the implied contract under section 1491(a) is, therefore, “essentially the
same” as the APA standard applicable to protests pursued under section 1491(b).
FAS 
Support, 93 Fed. Cl. at 694
.

       “‘If the court finds a reasonable basis for the agency’s action, the court
should stay its hand even though it might, as an original proposition, have reached
a different conclusion as to the proper administration and application of the
procurement regulations.’” Honeywell, Inc. v. United States, 
870 F.2d 644
, 648
(Fed. Cir. 1989) (quoting M. Steinthal & Co. v. Seamans, 
455 F.2d 1289
, 1301
(D.C. Cir. 1971)). If, on the other hand, the protester has shown a significant error
in the procurement process, the court must determine as a factual matter whether
that error prejudiced the protester, because both error and prejudice are required for
the protester to prevail. Statistica, Inc. v. Christopher, 
102 F.3d 1577
, 1581 (Fed.
Cir. 1996) (citing Data Gen. Corp. v. Johnson, 
78 F.3d 1556
, 1562 (Fed. Cir.
1996)).



                                         24
       A bid protest plaintiff bears the burden of establishing prejudice. 
Bannum, 404 F.3d at 1358
. To meets its burden, a protester must show that there was a
“substantial chance” it would have received the contract, but for the agency’s
alleged error. 
Bannum, 404 F.3d at 1353
; Alfa Laval Separation, Inc. v. United
States, 
175 F.3d 1365
, 1367 (Fed. Cir. 1999); Data Gen. 
Corp., 78 F.3d at 1562
.
This “substantial chance” inquiry is the same as that applied to determine a
protester’s standing. Thus, in this bid protest, the “substantial chance” standard
must be applied twice: first, to determine EcoTour’s standing to bring its suit; and,
second, to determine whether EcoTour suffered prejudice as a result of any
adjudged errors in the procurement process. See, e.g., Linc Gov’t Servs., LLC v.
United States, 
96 Fed. Cl. 672
, 695-96 (2010) (differentiating between
“allegational prejudice” and “APA prejudice,” both of which apply the “substantial
chance” test).

III.   Standing

       Although the government has not challenged Eco Tour’s standing in either
its motion for judgment on the administrative record or its reply brief, standing is a
threshold inquiry that the court must address before considering the merits. 
ITAC, 316 F.3d at 1319
. As 
stated supra
, bid protest standing is limited to those plaintiffs
with a substantial chance of winning the contracts at issue in the protest. 
Orion, 704 F.3d at 1348-49
. The record demonstrates that Eco Tour submitted responsive
proposals that received the highest cumulative scores of any of the proposals
received by the NPS for the disputed contracts. AR Tab 23 at 1094, Tab 24 at
1120, Tabs 28-29, Tab 42 at 1272-74, Tab 43 at 1312-14. Thus, under the
regulations, there is a substantial chance that Eco Tour would have been awarded
the disputed contracts if not for the errors alleged in the amended complaint. See
36 C.F.R. §§ 51.31, 51.33. Accordingly, the court concludes that Eco Tour has
standing to bring its bid protest.

IV.    Analysis of the Merits

      Eco Tour challenges three determinations by the NPS as arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law. First,
Eco Tour challenges the agency’s determination that Jackson Hole and Hole
Hiking submitted “responsive” proposals despite their failure to include certain
financial information required by the prospectus. Second, Eco Tour alleges that

                                         25
the Park Service violated applicable law – including the Procurement Integrity Act
and the implied contract to consider bids fairly and honestly – by disclosing to
Jackson Hole and Hole Hiking information that Eco Tour had allegedly marked in
its proposal as confidential. Third, Eco Tour alleges that the NPS improperly
failed to require Hole Hiking to match one of the better terms of Eco Tour’s
proposal for contract GRTE032-13, and therefore improperly determined that Hole
Hiking had matched all of the better terms of Eco Tour’s proposal for that contract.

       A.      The Agency’s “Responsiveness” Determination (Count I) 10

      With respect to Count I, Eco Tour asserts that Jackson Hole and Hole Hiking
omitted from their proposals certain financial information required by the
prospectus, and that the NPS therefore erred in determining that these preferred
offerors’ proposals were “responsive.” 11 Pl.’s Mot. at 19-37. In this regard, Eco

       10
          / The court is mindful that, in procurements subject to the Federal Acquisition
Regulation (FAR), the concept of responsiveness is generally confined to sealed bidding. See
Excel Mfg., Ltd. v. United States, 
111 Fed. Cl. 800
, 806 & n.3 (2013); Dyonyx, L.P. v. United
States, 
83 Fed. Cl. 460
, 468 (2008) (citations omitted). By contrast, “[i]n negotiated
procurements, a proposal that fails to conform to the material terms and conditions of the
solicitation should be considered unacceptable and a contract award based on such an
unacceptable proposal violates the procurement statutes and regulations.” E.W. Bliss Co. v.
United States, 
77 F.3d 445
, 448 (Fed. Cir. 1996) (citations and internal quotation marks omitted).
As 
explained supra
, solicitations for NPS concession contracts are not “procurements” subject to
the FAR. Moreover, as the government correctly noted at oral argument, the NPS’s
determination of the “responsiveness” of proposals for the disputed contracts is mandated by the
particular regulations governing NPS concession contracts. Tr. at 53-54; see also 36 C.F.R. §§
51.27, 51.30-51.31. Accordingly, the aforementioned authorities confining the concept of
responsiveness to sealed bidding are inapplicable in the unique context of NPS concession
contracts.
       11
          / Eco Tour also argues that Jackson Hole’s proposal was non-responsive because
Jackson Hole did not submit a signed transmittal letter with its proposal as required by the
prospectus. Pl.’s Mot. at 14-15, 22-23; see AR Tab 4 at 27 (prospectus instructions stating that
“[f]ailure to submit a signed Offeror’s Transmittal Letter . . . will make your proposal non-
responsive”), 35 (proposal package stating that the transmittal letter “indicates your acceptance
of the terms and conditions of the concession opportunity as set forth in this Prospectus” and
“must bear original signatures”), Tab 20 at 638-40 (Jackson Hole’s unsigned transmittal letter).
However, after the filing of Eco Tour’s motion, the government supplemented the AR to include
a copy of the signed transmittal letter accompanying Jackson Hole’s proposal. See AR Tab 46.
                                                                                     (continued . . .)

                                                 26
Tour relies upon the regulations implementing the 1998 Act, which define a
“responsive” proposal as “a timely submitted proposal that is determined by the
Director as agreeing to all of the minimum requirements of the proposed
concession contract and prospectus and as having provided the information
required by the prospectus.” 36 C.F.R. § 51.3 (emphasis added).

       The court agrees with Eco Tour that the prospectus required each offeror to
submit with its proposal certain financial information to allow the NPS to evaluate
the financial capability of the offeror to carry out its proposal. As noted, Part A of
the proposal package stated that certain information “is required for principal
selection factors 3 and 4,” and that “[f]ailure to provide material information
required thereunder may result in an offeror being deemed non-responsive.” AR
Tab 4 at 41. Part B of the proposal package listed the specific financial
information “required” by Part A. 
Id. at 49-54.
       The court also agrees with Eco Tour that neither Jackson Hole nor Hole
Hiking submitted with their proposals all of the financial information required by
the prospectus. With its proposal for contract GRTE024-13, Jackson Hole
provided: (1) a business history form; (2) Annual Financial Reports (AFRs) for
two previous years; (3) a chart of the equipment to be used and its value; (4) a pro
forma income statement; and, (5) a chart of financial “operating assumptions.” AR
Tab 20 at 705-23. However, Jackson Hole’s proposal did not include the balance
sheet or credit report required under principal selection subfactor 4(a) or bank
statements required under principal selection subfactor 4(c). AR Tab 23 at 1112,
Tab 30 at 1192, Tab 42 at 1305-06.

       With its proposal for contract GRTE032-13, Hole Hiking provided: (1) a
business history form; (2) AFRs for two previous years; (3) a balance sheet; (4) a
credit report; (5) a chart of the equipment to be used and its value; (6) a pro forma
income statement; (7) a chart of financial “operating assumptions”; and, (8) bank
statements from January and February 2013. AR Tab 19 at 588-613, 615-18, 620-
26. However, the Park Service found that the AFRs submitted by Hole Hiking
were incomplete, AR Tab 24 at 1139, Tab 31 at 1195, Tab 43 at 1345-46, and

Therefore, Eco Tour’s additional responsiveness argument is unsupported by the record. Indeed,
Eco Tour did not continue to advance that particular argument in either its reply brief or at oral
argument.


                                               27
noted that Hole Hiking failed to completely explain its revenue and expense
projections, AR Tab 24 at 1140, Tab 31 at 1195. The Park Service also determined
that the pro forma income statement submitted by Hole Hiking contained
“numerous mistakes,” AR Tab 24 at 1140, including “mathematical errors,” AR
Tab 31 at 1195. Additionally, the Park Service concluded that the January and
February 2013 bank statements submitted by Hole Hiking did not correspond to
the reporting period of Hole Hiking’s balance sheet, and therefore the Park Service
was unable to ascertain whether Hole Hiking’s cash position was sufficient “to
respond to any unanticipated expenses” in light of Hole Hiking’s assertion that it
did not require any financing for start-up costs. AR Tab 31 at 1195. Finally, the
NPS determined that Hole Hiking’s balance sheet contained certain unspecified
“anomalies,” AR Tab 43 at 1346, and noted that “without notes to explain the
balance sheet, the panel was concerned with the financial position of the Offeror,”
AR Tab 24 at 1139.

       Despite these omissions, the NPS found that Jackson Hole’s and Hole
Hiking’s proposals were “responsive to the minimum requirements of the
Prospectus” because the agency determined that the omitted financial information
was not material to an effective evaluation of the proposals. AR Tab 37 at 1244
(“The lack of quality and omissions [in the preferred offerors’ proposals] were
reflected in lower scores for the preferred offerors; however, the omissions were
not significant enough to hamper an effective evaluation of the proposals.”), Tab
40 at 1268 (same), Tab 42 at 1305-06 (responsiveness determination for Jackson
Hole), Tab 43 at 1345-46 (responsiveness determination for Hole Hiking). In that
regard, the NPS relied upon paragraph 1(d) of the prospectus instructions, which
limits the meaning of the term “information required by the prospectus” to only
such information as is “material, as determined by the Service, to an effective
evaluation of the proposal under the applicable selection factor.” AR Tab 4 at 27
(emphasis added).

       Eco Tour first contends that paragraph 1(d) of the prospectus instructions is
contrary to the regulations insofar as it limits the definition of “information
required by the prospectus” to information that is expressly required by the
prospectus and is deemed “material” by the NPS. Pl.’s Mot. at 27-32; Pl.’s Reply
at 4-5. Next, Eco Tour contends that, even if the NPS were allowed to impose
such a “materiality” limitation, the agency acted arbitrarily and capriciously, and
abused its discretion, in determining that the financial information omitted from

                                         28
Jackson Hole’s and Hole Hiking’s proposals was not material to an effective
evaluation of those proposals. Pl.’s Mot. at 32-37; Pl.’s Reply at 6-10. Therefore,
to resolve Eco Tour’s claims with respect to Count I, the court must determine
whether the NPS violated applicable law, acted arbitrarily and capriciously, or
abused its discretion in determining that the financial information omitted from
Jackson Hole’s and Hole Hiking’s proposals was not material.

             1.    Eco Tour’s Objection to the Materiality Limitation Set
                   Forth in Paragraph 1(d) of the Prospectus Instructions

       Eco Tour first contends that the NPS acted contrary to law and abused its
discretion by limiting the definition of “information required by the prospectus” to
only such information that the NPS deems “material . . . to an effective evaluation
of the proposal under the applicable selection factor.” Pl.’s Mot. at 30. In that
regard, Eco Tour relies upon the definition of “responsive” set forth in 36 C.F.R. §
51.3, and contends that paragraph 1(d) of the prospectus instructions is “directly
contrary to the plain language of” 36 C.F.R. § 51.3 insofar as the regulation “does
not include a provision that allows NPS to limit the term ‘required’ to information
which NPS, in its discretion, determines is ‘material to an effective evaluation of
the proposal.’” 
Id. Eco Tour
also argues that paragraph 1(d) constitutes an
improper “expan[sion] [of] the very limited exception set by Congress for when a
concessioner can exercise a right of preference and evade true competition.” 
Id. at 31.
For the reasons specified below, the court concludes that the NPS neither acted
contrary to law nor abused its discretion in imposing a materiality limitation.

                   a.     Eco Tour Waived Any Objection to Paragraph 1(d)

       Defendant argues that Eco Tour’s contention that “materiality” cannot be a
factor in evaluating responsiveness is a challenge to paragraph 1(d) of the
prospectus instructions, and, as such, is waived because Eco Tour failed to object
to paragraph 1(d) before the deadline for the submission of proposals. See Def.’s
Mot. at 11-12 (citing Blue & Gold Fleet, LP v. United States, 
492 F.3d 1308
, 1313-
14 (Fed. Cir. 2007)). The court agrees.

       It is axiomatic that “a party who has the opportunity to object to the terms of
a government solicitation containing a patent error and fails to do so prior to the
close of the bidding process waives it ability to raise the same objection

                                         29
subsequently in a bid protest action in the Court of Federal Claims.” Blue & Gold
Fleet, 492 F.3d at 1313
. Citing the desire to prevent contractors “from taking
advantage of the government and other bidders” and to “avoid[] costly after-the-
fact litigation,” the Federal Circuit, in Blue & Gold Fleet, stated that “‘[v]endors
cannot sit on their rights to challenge what they believe is an unfair solicitation,
roll the dice and see if they receive the award.’” 
Id. at 1314
(quoting Argencord
Mach. & Equip., Inc. v. United States, 
68 Fed. Cl. 167
, 175 n.14 (2005)); see also
Weeks Marine, Inc. v. United States, 
575 F.3d 1352
, 1362-63 (Fed. Cir. 2009).
Blue and Gold Fleet thus prevents a protester from raising post hoc objections to
the terms of a solicitation. That is precisely what Eco Tour seeks to do here. Eco
Tour’s argument that the materiality limitation in paragraph 1(d) of the prospectus
instructions conflicts with 36 C.F.R. § 51.3 is, essentially, an allegation of patent
error in the prospectus. Having failed to object to the materiality limitation before
the deadline for the submission of proposals, Eco Tour has waived its right to do so
before this court. See Blue & Gold 
Fleet, 492 F.3d at 1313
.

       In an attempt to avoid the waiver rule announced in Blue & Gold Fleet, Eco
Tour asserts that it is not challenging the terms of the prospectus, but rather
invoking the prospectus’s own mechanism for resolving conflict between the terms
of the prospectus and the regulations, which are incorporated by reference into the
prospectus and control in the event of any inconsistency. See Pl.’s Mot. at 30 n.8
(“[B]ecause the terms of the Prospectus were not defective, Eco Tour was not
required to challenge those terms prior to the submission of its proposal.”); Pl.’s
Reply at 13. Eco Tour’s argument in this regard is unpersuasive and unsupported.
A patent ambiguity is “present when the contract contains facially inconsistent
provisions that would place a reasonable contractor on notice and prompt the
contractor to rectify the inconsistency by inquiring of the appropriate parties.”
Stratos Mobile Networks USA, LLC v. United States, 
213 F.3d 1375
, 1381 (Fed.
Cir. 2000). To the extent that there is any conflict between the prospectus
instructions and the regulations incorporated by reference into the contract –
insofar as the former impose a materiality limitation on the definition of
“information required by the prospectus” – any such conflict is a patent ambiguity
regarding which Eco Tour “‘had a duty to seek clarification from the government’”
before the close of bidding. Blue & Gold 
Fleet, 492 F.3d at 1314
(quoting Stratos




                                         30
Mobile 
Networks, 213 F.3d at 1381
). Accordingly, Eco Tour’s challenge to the
materiality limitation in paragraph 1(d) is waived.12

                       b.      The Materiality Requirement in Paragraph 1(d) Is
                               Consistent with 36 C.F.R. § 51.3

       Even assuming, arguendo, that Eco Tour did not waive its right to challenge
the materiality limitation in paragraph 1(d), its challenge fails for the additional
reason that such a limitation is not contrary to law. As 
noted supra
, 36 C.F.R. §
51.3 defines a “responsive” proposal as “a timely submitted proposal that is
determined by the Director as agreeing to all of the minimum requirements of the
proposed concession contract and prospectus and as having provided the
information required by the prospectus.” Although section 51.3 does not expressly
provide for a materiality limitation, it also does not preclude such a limitation.
Indeed, by including the phrase “determined by the Director,” section 51.3 confers
discretion upon the NPS to determine whether a proposal has provided the
information required by the prospectus. Contrary to Eco Tour’s argument, this
conferral of discretion is sufficiently broad to allow the NPS to place limits on the
definition of “information required by the prospectus.”

       Neither is paragraph 1(d) in conflict with the 1998 Act. Eco Tour argues
that by imposing a materiality limitation the NPS “is improperly trying to expand
the very limited exception set by Congress for when a concessioner can exercise a
right of preference and evade true competition.” Pl.’s Mot. at 31. Yet, the 1998
Act provides that outfitting and guide concessioners such as Jackson Hole and
Hole Hiking are entitled to exercise a preferential right of renewal if, inter alia, the
concessioner “has submitted a responsive proposal for a proposed new contract
which satisfies the minimum requirements established by the Secretary pursuant to
[16 U.S.C. § 5952(4)].” 16 U.S.C. § 5952(8)(B)(iii).
       12
           / The only authority Eco Tour cites in support of its argument that it was not required
to challenge paragraph 1(d) before the close of bidding is BayFirst Solutions, LLC v. United
States, 
102 Fed. Cl. 677
, 681-82 (2012). See Pl.’s Mot. at 30 n.8. That case is inapposite
because it did not involve a challenge to the terms of a solicitation, but rather a challenge to the
agency’s evaluation of proposals. Eco Tour’s reliance upon the court’s passing statement that a
chart contained in the solicitation “could, with effort, be harmonized with the weighting scheme
presented on the previous page of the solicitation,” 
BayFirst, 102 Fed. Cl. at 681
, is therefore
fruitless.


                                                 31
        Moreover, the materiality limitation in paragraph 1(d) is consistent with
analogous precedent applying provisions of the FAR in the context of negotiated
procurements. Under such precedent, “‘a proposal that fails to conform to the
material terms and conditions of the solicitation should be considered unacceptable
and a contract award based on such an unacceptable proposal violates the
procurement statutes and regulations.’” Allied Tech. Grp., Inc. v. United States,
649 F.3d 1320
, 1329 (Fed. Cir. 2011) (emphasis added) (quoting E.W. 
Bliss, 77 F.3d at 448
); Furniture by Thurston v. United States, 
103 Fed. Cl. 505
, 518 (2012)
(“It is blackletter law that a procuring agency may only accept an offer that
conforms to the material terms of the solicitation.” (emphasis added) (citing
Centech Grp., Inc. v. United States, 
554 F.3d 1029
, 1037 (Fed. Cir. 2009))).
Although such FAR-based cases are not directly applicable to the concession
contracts at issue in this bid protest, they further undermine Eco Tour’s contention
that a materiality component to responsiveness is contrary to law. See YRT
Services, 28 Fed. Cl. at 414
n.33 (“[T]he language and experience represented by
the FAR is helpful for reference purposes.”).

            2.     Was the Agency’s Materiality Determination a
                   Responsibility Determination?

       The government argues that because the information omitted from Jackson
Hole’s and Hole Hiking’s proposals related to their financial ability to carry out
their proposals, the NPS’s determination that these omissions were immaterial was
a responsibility determination, not a responsiveness determination. Def.’s Mot. at
14; Def.’s Reply at 4-6. As such, defendant contends that the agency’s materiality
determination is “effectively unreviewable absent a claim of fraud or bad faith.”
Def.’s Mot. at 14; Def.’s Reply at 5. Inasmuch as Eco Tour has not formally
alleged fraud or bad faith on the part of the NPS, the government argues that Eco
Tour’s challenge to the agency’s responsiveness determination “need not be
considered further by the Court.” Def.’s Mot. at 15; see also Def.’s Reply at 6.

       In response, Eco Tour asserts that the deference typically afforded to an
affirmative determination of responsibility is inappropriate here because the NPS
“was not making a threshold ‘responsibility’ determination with regard to this
information, but in fact was evaluating, comparing and scoring proposals on a 0-5
point scale pursuant to Principal Selection Factor 4 and as required by the

                                        32
regulations.” Pl.’s Reply at 11; see also 
id. (“This information
was not part of a
‘yes/no’ responsibility determination, it was sought as part of an effort to evaluate
and score each offeror’s capabilities by comparing them to the other offerors.”).
Eco Tour also argues that “in making ‘responsibility’ determinations under the
FAR, government agencies do not identify specific information that must be
provided as NPS did here, but instead they allow bidders to provide whatever
information they believe would show their ‘responsibility’ after bids are opened.”
Pl.’s Reply at 12 (citing John C. Grimberg Co. v. United States, 
185 F.3d 1297
,
1299 (Fed. Cir. 1999), and Blount, Inc. v. United States, 
22 Cl. Ct. 221
, 226
(1990)). Here, by contrast, the prospectus requires specific financial information
and the regulations governing NPS concession contracts provide very limited
circumstances in which proposals may be amended or supplemented after the
deadline for submitting proposals has passed. Pl.’s Reply at 12 (citing 36 C.F.R. §
51.15(a) (allowing offerors to amend or supplement proposals after submission
only if “requested by the Director to do so and the Director provides all offerors
that submitted proposals a similar opportunity to amend or supplement their
proposals”)).

       The court agrees with Eco Tour that the NPS’s materiality determination
was not a responsibility determination. Although a determination of an offeror’s
financial capability is traditionally considered to pertain to the offeror’s
responsibility, e.g., Supreme Foodservice GmbH v. United States, 
112 Fed. Cl. 402
, 413 (Fed. Cl. 2013) (“A responsibility evaluation includes consideration of
financial backing as well as the ability to meet the operational requirements of the
contract . . . .”) (citations omitted); 
Blount, 22 Cl. Ct. at 227
; see also 48 C.F.R. §
9.104-1 (2012) (setting forth “general standards” for responsibility in the
procurement context, including “adequate financial resources to perform the
contract, or the ability to obtain them”), here the offerors’ financial capability is
one of several evaluation factors considered under a comparative assessment of the
various proposals. By contrast, a determination of responsibility is a “pass/fail
inquiry.” PlanetSpace, Inc. v. United States, 
92 Fed. Cl. 520
, 527 (2010) (citing 48
C.F.R. § 9.103); see also Frontier Sys. Integrators, LLC, B-298872.3, 2007 CPD ¶
46, 
2007 WL 776887
, at *5 (Comp. Gen. Feb. 28, 2007) (“Our Office has long
held that pass/fail evaluations of capability issues, such as past performance, are
tantamount to responsibility determinations, with the result that a rating of
‘unacceptable’ in these areas is the same as a determination of nonresponsibility.”
(citing Phil Howry Co., B-291402.4, 2003 CPD ¶ 33, 
2003 WL 282206
(Comp.

                                          33
Gen. Feb. 6, 2003))). A consideration of responsibility-related factors, such as
financial capability, in the context of a comparative assessment of proposals does
not constitute a responsibility determination. See, e.g., 
PlanetSpace, 92 Fed. Cl. at 546
(“Standing apart from the responsibility determination, however, procuring
agencies may, in the context of a comparative evaluation of proposals, use
traditional responsibility criteria, such as considering an offeror’s financial
resources and past performance.” (citing Delta Data Sys. Corp. v. Webster, 
744 F.2d 197
, 203 (D.C. Cir. 1984), and YRT 
Services, 28 Fed. Cl. at 394-95
)); YRT
Services, 28 Fed. Cl. at 394-95
(“‘Agencies commonly use responsibility related
factors in the evaluation process, notwithstanding the fact that a responsibility
determination must ultimately be made. . . . This process does not constitute a
responsibility determination . . . .’” (quoting John Cibinic, Jr. and Ralph C. Nash,
Jr., Formation of Government Contracts 547 (2d ed. 1986))).

       The court has considered the government’s arguments to the contrary and
finds them unpersuasive. Defendant cites several cases in support of its argument
that the NPS’s materiality determination was a responsibility determination that is
“effectively unreviewable absent a claim of fraud or bad faith.” Def.’s Mot. at 14-
15; Def.’s Reply at 4-6 (citing John C. 
Grimberg, 185 F.3d at 1303
, Trilon Educ.
Corp. v. United States, 
578 F.2d 1356
, 1358 (Ct. Cl. 1978), News Printing Co., Inc.
v. United States, 
46 Fed. Cl. 740
, 746 (2000), and 
Blount, 22 Cl. Ct. at 227
).
However, none of these cases involved an assessment of responsibility-related
factors, such as financial capability, in the context of a comparative assessment of
proposals. Rather, each involved a “pass/fail” determination of responsibility (i.e.,
was the offeror responsible or not?). Accordingly, defendant’s case law is
inapposite.13


       13
          / Additionally, even if defendant’s case law were applicable, the government
overreaches when it suggests that responsibility determinations are “effectively unreviewable”
absent allegations of fraud or bad faith. Indeed, the government conceded so at oral argument by
pointing the court to Impresa Construzioni Geom. Domenico Garufi v. United States, 
238 F.3d 1324
(Fed. Cir. 2001), in which the Federal Circuit rejected an argument, virtually identical to
that made by the government here, that “absent allegations of fraud or bad faith,” a responsibility
determination is “immune from judicial 
review.” 238 F.3d at 1333
; see Tr. at 55. In disposing
of that argument, the Federal Circuit concluded that the government had “seriously misread” the
Court of Claims’ decisions in Keco Indus., Inc. v. United States, 
492 F.2d 1200
(Ct. Cl. 1974)
(Keco II), and Trilon Educ. Corp. v. United States, 
578 F.2d 1356
(Ct. Cl. 1978), which the
                                                                                   (continued . . .)

                                                34
       Additionally, in its reply brief, defendant appears to argue that the NPS’s
materiality determination constitutes a responsibility determination because it was
a “yes/no” determination (i.e., were the omissions material or not?). Def.’s Reply
at 6 (“What Eco Tour does contest is NPS’s separate ‘yes/no’ determination that
the responses to [principal selection factor] 4 were ‘material,’ and therefore
responsive. . . . These are responsibility determinations.”). But both
responsiveness and responsibility are “yes/no” inquiries. Thus, the “yes/no”
character of the agency’s materiality determination does nothing to transform it
from a responsiveness determination to a responsibility determination.

       For these reasons, the court rejects defendant’s attempt to characterize the
NPS’s materiality determination as one of responsibility, which the court would
normally afford heightened deference. Accordingly, the court will address whether
the agency’s materiality determination was arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law.

              3.      Was the NPS’s Materiality Determination Arbitrary,
                      Capricious, an Abuse of Discretion, or Otherwise Not in
                      Accordance with Law?

                      a.     Jackson Hole’s and Hole Hiking’s Failure to Provide
                             Current Bank Statements (Principal Selection
                             Subfactor 4(c))

       The NPS determined that neither Jackson Hole nor Hole Hiking submitted
current bank statements demonstrating their ability to obtain funds for start-up
costs as required under principal selection subfactor 4(c). AR Tab 23 at 1115, Tab
30 at 1192, Tab 31 at 1195, Tab 42 at 1305-06. The NPS nevertheless found these
omissions to be immaterial because both Jackson Hole and Hole Hiking indicated
in their proposals that, as incumbent concessioners, they had no start-up costs.
With respect to Jackson Hole, the agency stated as follows:



Federal Circuit determined “impose no such limits” on judicial review of responsibility
determinations. 
Impresa, 238 F.3d at 1333
.


                                               35
             [Principal selection subfactor 4(c)] requests that the
             Offeror demonstrate its ability to obtain the required
             funds for any start-up costs under the new Contract. It
             also requests the Offeror to provide a bank statement.
             Jackson Hole responded that [principal selection
             subfactor 4(c)] is not applicable because Jackson Hole is
             already operating as the current concessioner. Jackson
             Hole did not provide a bank statement. The Panel
             concluded that Jackson Hole’s status as the incumbent
             concessioner supported Jackson Hole’s assertion that it
             had no start-up costs. Thus, Jackson Hole did not need to
             demonstrate funding to support such costs, and provided
             a material response.

AR Tab 42 at 1306; see also AR Tab 20 at 664-65 (Jackson Hole’s proposal stating
that the requirements in the prospectus to identify property to be acquired and the
source of funding for start-up costs were “not applicable”). Similarly, with respect
to Hole Hiking, the NPS stated that “Hole Hiking responded in [principal selection
subfactor 4(b)] that it would not have any start-up expenses and the response in
[principal selection subfactor 4(c)] supported this assertion.” AR Tab 43 at 1346;
see also AR Tab 19 at 614, 619 (Hole Hiking’s proposal stating that it would have
no start-up costs).

       Eco Tour argues that the NPS erroneously accepted Jackson Hole’s and Hole
Hiking’s representations that they had no start-up costs. Pl.’s Mot. at 24-25, 36-37;
Pl.’s Reply at 7-8. In that regard, Eco Tour notes that Jackson Hole stated, on a
chart listing the equipment to be used by Jackson Hole in carrying out contract
GRTE024-13, that it “anticipated” purchasing a [ ] and [ ] “for Season 2014.” AR
Tab 20 at 720. Eco Tour further notes that Hole Hiking stated, in the portion of its
proposal related to principal selection subfactor 2(a), that “[a]t the beginning of the
year, we order new [ ] and [ ].” AR Tab 19 at 581. In light of these anticipated
purchases, Eco Tour asserts that Jackson Hole and Hole Hiking did, in fact, have
start-up costs, and therefore the NPS acted arbitrarily and capriciously in accepting
Jackson Hole’s and Hole Hiking’s contrary representations. Pl.’s Mot. at 24-25,
36-37; Pl.’s Reply at 7-8.




                                          36
        The court agrees with Eco Tour that the NPS arbitrarily and capriciously
determined that Jackson Hole and Hole Hiking had no start-up costs and that their
failure to provide bank statements was immaterial. Although the evaluation panel,
in its evaluation of Jackson Hole’s proposal, acknowledged Jackson Hole’s
anticipated purchase of a [ ] and [ ], AR Tab 23 at 1114, the panel subsequently
ignored this information in its responsiveness evaluation, in which it concluded
that “Jackson Hole’s status as the incumbent concessioner supported Jackson
Hole’s assertion that it had no start-up costs,” AR Tab 42 at 1306. Similarly, in
concluding that Hole Hiking had no start-up costs, see AR Tab 43 at 1346, the
panel completely ignored Hole Hiking’s anticipated purchase of [ ] and [ ] “[a]t the
beginning of the year,” AR Tab 19 at 581.

       To the extent that the panel mentioned this information at all in its
responsiveness determinations, it merely noted that “Jackson Hole’s anticipated
purchases were not firm commitments” and that Jackson Hole’s failure to identify
these as start-up costs “is immaterial because these purchases are not required by
the terms of the Prospectus, including the Draft Contract.” AR Tab 42 at 1306.
Defendant relies upon this statement to argue that Jackson Hole’s failure to provide
bank statements to prove its financial ability to make its anticipated purchases was
immaterial because such purchases were not required by the terms of the
prospectus. Def.’s Mot. at 18; Def.’s Reply at 9-10 (citing AR Tab 42 at 1306).
This argument fails for the simple reason that nothing in principal selection
subfactors 4(b) or 4(c) limits the requirement to identify start-up costs (and to
demonstrate financial ability to pay for such costs by providing bank statements) to
only those start-up costs specifically required by the prospectus. To the contrary,
principal selection subfactor 4(b)(2) directed offerors to “provide estimates for the
Personal Property items (Equipment) that you need to acquire in order to begin
operating,” AR Tab 4 at 51, and principal selection subfactor 4(c) directed offerors
to demonstrate their “ability to obtain the required funds” for such start-up costs,
AR Tab 4 at 54.

      Defendant’s additional arguments fare no better. For instance, defendant
argues that Hole Hiking’s failure to report [ ] and [ ] as start-up costs, and to
provide bank statements demonstrating its ability to obtain funds for such costs, is
immaterial because the total cost of the [ ] and [ ] is low and “will likely not
prevent Hole Hiking from performing the contract.” Def.’s Mot. at 19; see also
Def.’s Reply at 10. However, nothing in principal selection subfactors 4(b) or 4(c)

                                         37
limits the requirement to identify start-up costs (and to demonstrate financial
ability to pay for such costs) to only those start-up costs above a certain dollar
amount. To the contrary, principal selection subfactor 4(c) expressly states that
“[c]urrent bank statements must be provided even if you do not anticipate
significant start-up costs.” AR Tab 4 at 54 (emphasis added).

       Finally, defendant argues that, even assuming that Jackson Hole and Hole
Hiking failed to demonstrate their ability to obtain the required funds for start-up
costs, Eco Tour’s proposal suffered from the same defect, and should likewise be
rejected as non-responsive, because Eco Tour failed to explain the cost of and to
demonstrate funding for its anticipated conversion to natural gas. Def.’s Mot. at
18-19 (citing AR Tab 21 at 901 (describing Eco Tour’s plan to convert one-half of
its vehicles to natural gas “in the first year after a compressed natural gas filling
station comes to . . . Jackson, Wyoming,” and to convert the other half the
following year, with unspecified “viable grant sources”), and Tab 22 at 1086
(same)). This argument is similarly unpersuasive because, unlike Jackson Hole
and Hole Hiking, both of whom anticipated making purchases of equipment at the
beginning of the 2014 winter season, Eco Tour anticipated converting one-half of
its vehicles to natural gas “in the first year after a compressed natural gas filling
station comes to . . . Jackson, Wyoming,” and the other half “during the second
year that [a natural gas] fuel source is available in Jackson.” AR Tab 21 at 901,
Tab 22 at 1086. Although Eco Tour “estimate[d]” that a compressed natural gas
filling station would arrive in Jackson “in early 2014,” this was merely an estimate
and, ultimately, outside of Eco Tour’s control. 
Id. Thus, Eco
Tour’s anticipated
conversion to natural gas cannot reasonably be deemed to constitute a start-up cost.

                   b.     Jackson Hole’s Failure to Provide a Balance Sheet
                          and Credit Report (Principal Selection Subfactor
                          4(a))

       The NPS also determined that Jackson Hole failed to provide a balance sheet
and credit report as required under principal selection subfactor 4(a). AR Tab 23 at
1112, Tab 30 at 1192, Tab 42 at 1305-06. The NPS nevertheless concluded that
these omissions were immaterial because the NPS was able to obtain the missing
information by reviewing Jackson Hole’s business history form, AFRs, and
financial projections and assumptions:



                                         38
             [Principal selection subfactor 4(a)] requests the Offeror
             to demonstrate that it has a credible, proven track record
             of meeting financial obligations by submitting (1) a
             business history form; (2) a balance sheet; (3) Annual
             Financial Report (AFRs) (for current concessioners) OR
             financial statements (for interested parties who are not
             current concessioners); and (4) a credit report. Jackson
             Hole submitted a complete business history form and two
             years of AFRs. However, Jackson Hole did not submit a
             balance sheet, and provided a Dun & Bradstreet
             Company ID instead of a physical copy of the credit
             report. The Service does not have access to credit
             reporting services.

             By analyzing the business history form and the AFRs in
             combination with the projections and assumptions
             supplied in [principal selection subfactor 4(b)], the panel
             determined that Jackson Hole had a credible proven track
             record of meeting its financial obligations and would
             have the operating income to satisfy its liabilities. All of
             the information supplied on the business history form
             was positive, and both of Jackson Hole’s AFRs revealed
             a positive net income. A balance sheet and physical
             credit report might have provided further corroboration,
             but the Panel did not view these omissions as material.

AR Tab 42 at 1305-06.

       Eco Tour argues that the NPS could not effectively evaluate Jackson Hole’s
financial ability to carry out its proposal without the balance sheet and credit
report, and, therefore, the NPS arbitrarily and capriciously determined that Jackson
Hole’s failure to provide these documents was immaterial. Pl.’s Mot. at 34-35;
Pl.’s Reply at 6-7. In that regard, Eco Tour first asserts that Jackson Hole’s
business history form consists solely of uncorroborated “one-word responses” to
general questions regarding Jackson Hole’s recent history of default, bankruptcy,
foreclosure, receivership, or litigation related to unmet financial obligations. Pl.’s
Mot. at 35 (citing AR Tab 20 at 719). Next, Eco Tour argues that the AFRs

                                         39
submitted by Jackson Hole “merely pertain to [Jackson Hole’s] revenues and
expenses under the prior contract,” and do not demonstrate anything about Jackson
Hole’s “track record of meeting its financial obligations.” Pl.’s Mot. at 35 (citing
AR Tab 20 at 705-18); see also Pl.’s Reply at 7 (“Nowhere in those documents
does [Jackson Hole] state its current credit status, amount of assets, funding or
available cash.”). As a result, Eco Tour contends, the NPS “was totally unaware of
the status of [Jackson Hole’s] current cash assets, its corporate balance sheet health
and its credit rating.” Pl.’s Reply at 7.

       The court agrees with Eco Tour that the NPS acted arbitrarily and
capriciously in concluding that Jackson Hole’s failure to provide a balance sheet
and credit report was immaterial to an effective evaluation of Jackson Hole’s
history of meeting its financial obligations. Principal selection subfactor 4(a)
required Jackson Hole to “[d]emonstrate . . . a credible, proven track record of
meeting [its] financial obligations.” AR Tab 4 at 49 (emphasis added). The
financial information Jackson Hole supplied did not demonstrate such a track
record. While the AFRs submitted by Jackson Hole indicate its gross receipts and
expenses under its current contract, they provide no information regarding the
extent of Jackson Hole’s liabilities or its credit history. See AR Tab 20 at 705-18.
At most, the AFRs demonstrate that Jackson Hole has achieved a positive net
income under its current contract. A positive net income, however, cannot allay
potential concerns regarding the extent of Jackson Hole’s liabilities as compared to
its assets, nor can it demonstrate that Jackson Hole has a history of paying its
debts. Additionally, although the pro forma income statement and operating
assumptions submitted by Jackson Hole under principal selection subfactor 4(b)
demonstrate Jackson Hole’s projections and assumptions regarding its future
performance and profitability, they provide no information regarding Jackson
Hole’s prior “track record” of meeting its financial obligations. See AR Tab 20 at
721-23. Therefore, the NPS’s conclusion that Jackson Hole’s AFRs, pro forma
income statement, and operating assumptions were sufficient to demonstrate
Jackson Hole’s “track record of meeting its financial obligations” was arbitrary and
capricious.

      Defendant posits that Jackson Hole’s business history form – on which
Jackson Hole indicated, inter alia, that it had never defaulted on a concession
contract, had no recent bankruptcies or foreclosures, and had been the subject of no
recent lawsuits or administrative proceedings – adequately demonstrated Jackson

                                         40
Hole’s history of meeting its financial obligations. Def.’s Mot. at 18 (citing AR
Tab 20 at 719). Defendant argues that the NPS was entitled to “accept Jackson
Hole’s responses without confirming their accuracy.” 
Id. at 17.
In support of this
argument, defendant quotes from L-3 Global Communications Solutions, Inc. v.
United States, 
82 Fed. Cl. 604
, 609 (2008), for the proposition that “the test for
noncompliance is generally a test of facial noncompliance, not a test as to whether
the subjective, undisclosed intent of an offeror is noncompliant with the
solicitation’s requirements,” and Akal Sec., Inc. v. United States, 
103 Fed. Cl. 310
,
326 (2011), for the proposition that “[c]ontracting officers generally are entitled to
rely on information available to them at the time of a responsibility determination,
absent any indication that the information is defective, unsupported, or suspect.”
Def.’s Mot. at 17. Yet, in making this argument, defendant ignores the plain
language of principal selection subfactor 4(a), which required Jackson Hole to
demonstrate a “credible” and “proven” record of meeting its financial obligations
by presenting documentary proof in the form of a balance sheet and credit report.
AR Tab 4 at 49. Defendant also relies upon inapposite case law. Unlike L-3
Global, in which “all three bids were facially compliant with the solicitation’s
requirements,” 82 Fed. Cl. at 612
, Jackson Hole’s proposal omits required financial
information and, thus, is noncompliant on its face. Defendant’s citation to Akal is
likewise off the mark because Akal involved a determination of whether the
prevailing bidder was a “responsible offeror,” not whether it had submitted a
proposal that was responsive to the material terms and conditions of the
solicitation. 
See 103 Fed. Cl. at 324-26
.

                   c.     Deficiencies in Hole Hiking’s Financial Records
                          (Principal Selection Subfactors 4(a) and 4(b))

       Finally, as noted, the NPS determined that Hole Hiking’s financial
documents omitted information and contained errors. AR Tab 24 at 1139-40, Tab
31 at 1195, Tab 43 at 1345-46. Specifically, the NPS concluded that: (1) the
AFRs submitted by Hole Hiking were each missing a page, AR Tab 24 at 1139,
Tab 31 at 1195, Tab 43 at 1345-46; (2) Hole Hiking’s pro forma income statement
and operating assumptions failed to explain “why [Hole Hiking’s] revenue
projections are so much higher than historical projections and why some of the
expense assumptions appear low,” Tab 31 at 1195; see also AR Tab 24 at 1140; (3)
Hole Hiking’s pro forma income statement contained “numerous mistakes,” AR
Tab 24 at 1140, including “mathematical errors,” Tab 31 at 1195; and, (4) Hole

                                         41
Hiking’s balance sheet contained certain unspecified “anomalies,” AR Tab 43 at
1346, which raised “concern[s]” regarding Hole Hiking’s financial position, AR
Tab 24 at 1139.

        The NPS nevertheless concluded that these deficiencies were immaterial,
and that “[t]he Panel was able to evaluate the proposal and conclude [that] Hole
Hiking had the financial ability to carry out the terms and conditions of the
contract.” AR Tab 43 at 1346. With respect to principal selection subfactor 4(a),
the Park Service determined that “[a]lthough each AFR was missing a page, the
panel was able to use the information provided [on the business history form and
credit report] to estimate a positive net income.” AR Tab 43 at 1345.
Additionally, the NPS concluded that “[a]lthough the current liability information
supplied on the balance sheet was somewhat ambiguous, Hole Hiking’s credit
report demonstrated that it had satisfied its liabilities in the past,” and, “[t]herefore,
the panel concluded [that] Hole Hiking would have the operating income to satisfy
its liabilities.” AR Tab 43 at 1345. With respect to principal selection subfactor
4(b), the NPS simply noted that “Hole Hiking submitted the requested forms.” AR
Tab 43 at 1346.

       Eco Tour argues that “Hole Hiking did not fully explain its assumptions that
future revenues would be much higher than past levels and expenses would be very
low,” and, therefore, the NPS arbitrarily and capriciously determined that the
deficiencies in Hole Hiking’s financial documentation were immaterial. Pl.’s Mot.
at 36. Eco Tour also asserts that Hole Hiking’s financial projections are “further
suspect given that Hole Hiking reported total gross revenues in 2010/2011 of
$21,835 based on 569 total tours,” resulting in approximately $38 of revenue per
tour – which Eco Tour contends is “well below the approved rates” under Hole
Hiking’s current contract (contract GRTE032-03). 
Id. at 36
n.9 (citing AR Tab 4
at 23-24 (listing annual gross revenue for the last three seasons under contracts
GRTE024-03 and GRTE032-03), and Tab 8 at 186 (listing approved rates under
Hole Hiking’s current contract)); see also Tab 19 at 618 (listing Hole Hiking’s
projected revenue per tour under contract GRTE032-13). Defendant offers no
rebuttal other than to assert that Eco Tour “misreads the charts” on the prospectus,
which show that Hole Hiking led only 294 tours during the 2010/2011 season
resulting in approximately $74 of revenue per tour – which defendant implies is
much closer to the approved rates under Hole Hiking’s current contract. Def.’s
Mot. at 19 (citing AR Tab 4 at 23-24).

                                           42
       Here again, the court must agree with Eco Tour that the NPS failed to
provide a rational basis for its determination that the errors and omissions in Hole
Hiking’s financial information were immaterial. Although the NPS rationally
determined that Hole Hiking’s omissions under principal selection subfactor 4(a)
were immaterial (i.e., missing pages in the AFRs and ambiguous current liability
information on the balance sheet) because the NPS could determine from the
business history form and credit report that Hole Hiking had “satisfied its liabilities
in the past,” AR Tab 43 at 1345, the NPS failed to even address the mathematical
errors on Hole Hiking’s pro forma income statement and Hole Hiking’s
unexplained revenue and expense projections. AR Tab 43 at 1346. Rather, the
NPS merely stated, without explanation, that “Hole Hiking submitted the requested
forms.” AR Tab 43 at 1346. The NPS’s failure to provide any explanation with
respect to its materiality determination as to the pro forma income statement and
operating assumptions is wholly arbitrary.

      For the aforementioned reasons, the court concludes that each of the NPS’s
materiality determinations, as well as its resulting responsiveness determinations,
was arbitrary, capricious, and an abuse of discretion. Therefore, the court must
proceed to determine, as a factual matter, whether Eco Tour was prejudiced by the
NPS’s arbitrary and unlawful conduct. See 
Bannum, 404 F.3d at 1351
.

             4.     Prejudice Resulting from the NPS’s Responsiveness
                    Determinations

       As noted, to demonstrate prejudice, Eco Tour must show a “substantial
chance” that it would have received the disputed contracts if not for the NPS’s
arbitrary and capricious responsiveness determinations. See 
id. at 1353.
The court
concludes that Eco Tour has made such a showing because it submitted responsive
proposals that received the highest cumulative scores of any of the proposals
received by the NPS for the disputed contracts. AR Tab 23 at 1094, Tab 24 at
1120, Tabs 28-29. Thus, in accordance with the regulations, there is a substantial
chance that Eco Tour would have been awarded the disputed contracts if not for
the errors alleged in the amended complaint. See 36 C.F.R. §§ 51.31, 51.33.

      B.     The Agency’s Disclosure of the Better Terms of Eco Tour’s
             Proposals (Count II)

                                          43
       With respect to Count II, presented as an alternative to Count I, Eco Tour
argues that the NPS improperly disclosed to Jackson Hole and Hole Hiking the
better terms of Eco Tour’s proposals in contravention of paragraph 4 of the
prospectus instructions. Pl.’s Mot. at 8-15, 40-42; Pl.’s Reply at 20-21. That
paragraph, titled “Proposals Considered Public Documents,” provides as follows:

            (a) All proposals submitted in response to this
            Prospectus may be disclosed by the Service to any
            person, upon request, to the extent required or authorized
            by the Freedom of Information Act (5 U.S.C. § 552).

            (b) If you believe that your proposal contains trade
            secrets or confidential commercial or financial
            information exempt from disclosure under the Freedom
            of Information Act, mark the cover page of each copy of
            the proposal with the following legend:

                   The information specifically identified on pages of this
                   proposal constitutes trade secrets or confidential
                   commercial or financial information that the Offeror
                   believes to be exempt from disclosure under the Freedom
                   of Information Act. The Offeror requests that this
                   information not be disclosed to the public, except as may
                   be required by law.

            You must specifically identify what you consider to be trade
            secret information or confidential commercial or financial
            information on the page of the proposal on which it appears,
            and you must mark each such page with the following legend:

                   This page contains trade secrets or confidential
                   commercial and financial information that the Offeror
                   believes to be exempt from disclosure under the Freedom
                   of Information Act, and which is subject to the legend
                   contained on the cover page of this proposal.



                                        44
             (c) Information so identified will not be made public by
             the Service except in accordance with law.

AR Tab 4 at 28. Eco Tour asserts that the NPS, in paragraph 4, “promised offerors
. . . that it would not disclose confidential information included in the proposals.”
Pl.’s Mot. at 40. Eco Tour further asserts that its “reasonable assumption . . . in
light of [the] NPS’s unqualified agreement to not disclose confidential information
was that [Eco Tour] would be provided with the opportunity to agree to have its
confidential information disclosed to its competitor, but that it did not have to
agree.” 
Id. at 40-41.
“If [Eco Tour] did not want this disclosure to occur, it would
have the option of withdrawing its proposal.” 
Id. at 41.
       Eco Tour argues that the NPS improperly disclosed Eco Tour’s confidential
information – in contravention of paragraph 4 of the prospectus instructions, and in
violation of the Procurement Integrity Act as well as the implied contract to
consider bids fairly and honestly – by identifying the better terms and conditions of
Eco Tour’s proposals in the NPS’s June 20, 2013 letters to Jackson Hole and Hole
Hiking. 
Id. at 15,
40-41. The allegedly confidential information disclosed to
Jackson Hole and Hole Hiking

             related to Eco Tour’s policies as to minimizing idling
             time of its vehicles, ensuring it had maximized visitors’
             experiences through the use of binoculars, preventing or
             remedying spills of fluids from its vehicles, ensuring
             removal of human waste and other related waste,
             ensuring its guides had certifications and training to
             ensure the safety of all guests, the use of reusable
             products to minimize waste and quality control measures
             to ensure its guides were performing in an optimal
             manner.

Id. at 41
(citing AR Tabs 30-31, Tab 37); see also 
id. at 15.
Eco Tour contends
that it marked this information as confidential in accordance with paragraph 4 of
the prospectus instructions, and therefore was entitled to prevent the disclosure of
such information. 
Id. at 9
(citing AR Tabs 21-22)); Pl.’s Reply at 20.




                                         45
             1.    Eco Tour Has Not Waived Its Unlawful Disclosure Claim

       Defendant argues, unpersuasively, that Eco Tour has waived its objection to
the NPS’s disclosure of the better terms of Eco Tour’s proposals. Def.’s Mot. at
23; Def.’s Reply at 14. The government’s waiver theory is premised upon its
characterization of Count II as a challenge to the terms of the prospectus, which
notified potential offerors that “[i]f an existing Concessioner submits a responsive
proposal and that proposal is not selected as the best proposal, the Preferred
Offeror designation allows it to match the terms of the best offer and be awarded
the Contract.” AR Tab 4 at 24. Defendant contends that pursuant to this language
in the prospectus, “Eco Tour . . . was on notice that ‘terms of the best offer’ could
be disclosed” and, therefore, waived its right to object to this language by not
objecting before the close of bidding. Def.’s Mot. at 23 (citing Blue & Gold 
Fleet, 492 F.3d at 1313
). However, in Count II, Eco Tour does not object to any terms of
the prospectus, but rather invokes the confidentiality provisions in paragraph 4 of
the prospectus instructions. See Pl.’s Mot. at 8-15, 40-42; Pl.’s Reply at 20-21.
Thus, defendant’s waiver theory with respect to Count II is without merit.

             2.    No Violation of the Procurement Integrity Act

       The government asserts that Count II fails to the extent that it arises under
the Procurement Integrity Act because NPS concession contracts are not
“procurement” contracts, as that term is defined by the Procurement Integrity Act.
Def.’s Mot. at 23-24; Def.’s Reply at 14. The court agrees. The Procurement
Integrity Act generally prohibits, “[e]xcept as provided by law,” the disclosure of
“contractor bid or proposal information or source selection information before the
award of a Federal agency procurement contract to which the information relates.”
41 U.S.C. § 2102(a)(1). “Federal agency procurement” is defined under the statute
as “the acquisition (by using competitive procedures and awarding a contract) of
goods or services (including construction) from non-Federal sources by a Federal
agency using appropriated funds.” 
Id. § 2101(4).
The disputed concession
contracts do not satisfy that definition. First, as 
explained supra
, the court
concludes that NPS concession contracts, such as those in dispute in this bid
protest, are not contracts for the procurement of goods and services. Second, even
if NPS concession contracts did involve the acquisition of goods or services for the
benefit of the government, they do not involve the expenditure of appropriated
funds by the NPS. Rather, such contracts “provide for payment to the government

                                         46
of a franchise fee or such other monetary consideration as determined by the
Secretary.” 16 U.S.C. § 5956(a) (emphasis added); see also 36 C.F.R. § 51.78
(“Concession contracts will provide for payment to the government of a franchise
fee or other monetary consideration as determined by the Director upon
consideration of the probable value to the concessioner of the privileges granted by
the contract involved.”) (emphasis added). Therefore, the Procurement Integrity
Act does not apply to Eco Tour’s bid protest.

       Additionally, defendant contends that even if the Procurement Integrity Act
were applicable to the instant lawsuit, it has not been violated because the
allegedly confidential information disclosed to Jackson Hole and Hole Hiking was
already public knowledge. Def.’s Mot. at 24-26; Def.’s Reply at 14-15. Again, the
court agrees with defendant. As noted, the Procurement Integrity Act applies only
to the disclosure of “contractor bid or proposal information.” 41 U.S.C. §
2102(a)(1). The term “contractor bid or proposal information” is defined as certain
types of information submitted to a federal agency in connection with a proposal to
enter into a procurement contract “if that information previously has not been
made available to the public or disclosed publicly.” 
Id. § 2101(2).
The NPS’s
letters to Jackson Hole and Hole Hiking did not mention Eco Tour by name, nor
did they disclose any information about the better terms of Eco Tour’s proposals
that was not otherwise publicly known. See AR Tabs 30-31. The twelve better
terms of Eco Tour’s proposals included: minimizing the idling of vehicles; using
binoculars, spill kits, human waste removal bags, and reusable plates, utensils,
mugs, and water bottles; disposing of waste outside the park; requiring guides to
receive Wilderness First Responder certification and training in winter driving and
the Wilderness Act; and, unannounced monitoring of guides. See AR Tab 30 at
1190-91, Tab 31 at 1193-94. The availability of such practices, none of which
involve the use of Eco Tour’s proprietary information or trade secrets, is within the
realm of public knowledge. Indeed, as defendant notes, four of the twelve
disclosed terms – the use of binoculars, spill kits, solid human waste removal bags,
and disposal of trash outside the park – were already in use by one or both of the
preferred offerors by the time the NPS sent its June 20, 2013 letters. See AR Tab
19 at 578 (Hole Hiking’s proposal stating that “[w]e carry plastic bags and offer to
guest[s] if needed for any refuse. . . . [and] then dispose[] of [such bags] in
appropriate container[s],” and that “[w]e purchase environmentally approved
products such as recyclable napkins and containers”), Tab 20 at 642 (Jackson
Hole’s proposal stating that “[c]lients are educated on ‘Leave-No-Trace’ principles

                                         47
and guides sweep all rest/break areas for waste before departing,” and that Jackson
Hole “commits to including a set of binoculars in every guide pack”), Tab 20 at
645 (Jackson Hole’s proposal stating that “[a]ll guides carry one emergency
‘wagbag’”), AR Tab 34 at 1204-05 (Jackson Hole’s response to the NPS’s June 20,
2013 letter stating that Jackson Hole “currently supplies spill kits for all vehicles
and commits to continuing to do so,” and that Jackson Hole “currently use[s] the
Wag Bag Wastekit [human waste disposal] product” and “[a]ll guide packs are, and
will continue to be, supplied with this product”), Tab 45 at 1405 (Hole Hiking’s
response to the NPS’s June 20, 2013 letter stating that “[Hole Hiking] guides
always carry a minimum of one pair of binoculars on each tour”).

        Eco Tour counters, unpersuasively, that the twelve better terms of Eco
Tour’s proposals that were disclosed by the NPS were not publicly known because,
if they were, Jackson Hole and Hole Hiking “would have included those policies in
their proposals.” Pl.’s Mot. at 41; see also Pl.’s Reply at 21. Yet, of course, the
fact that the preferred offerors did not include particular terms in their proposals
does not prove that such terms were not publicly known. Next, Eco Tour asserts
that, even if the twelve better terms of its proposals constitute public information
when considered in isolation, its particular combination of such terms is a
“confidential and strategic business decision.” Pl.’s Reply at 20. According to
Eco Tour, “[s]imply because the public knows that some of those items exist does
not mean that a company’s strategic decision to include them in its proposal is also
public knowledge.” 
Id. at 20-21.
This argument, too, is unpersuasive. Under Eco
Tour’s argument, any business practice undertaken by a concessioner, no matter
how commonly employed in the industry, would qualify as confidential so long as
it is combined with other similarly common practices. This view is not in
accordance with law. Although the court recognizes that a particular combination
of individual pieces of information in the public domain may qualify as a trade
secret if the combination is itself not generally known or not easily duplicated,14
the combination of Eco Tour’s twelve better terms does not meet that standard. As
noted above, none of these twelve better terms involved proprietary information or
trade secrets, and four of the terms were already in use by Jackson Hole and Hole

       14
          / See, e.g., Comprehensive Techs. Int’l, Inc. v. Software Artisans, Inc., 
3 F.3d 730
, 736-
37 (4th Cir. 1993) (“[A]lthough a trade secret cannot subsist in information in the public domain,
it can subsist in a combination of such information as long as the combination is itself a secret.”)
(citations omitted), vacated pursuant to settlement and appeal dismissed, Sept. 30, 1993.


                                                48
Hiking. Eco Tour has offered no evidence to support its view that the combination
of the twelve better terms of its proposals was not generally known or not easily
duplicated.

       For the foregoing reasons, the court concludes that even if the Procurement
Integrity Act were applicable to Eco Tour’s bid protest, it was not violated in this
instance because none of the information disclosed to Jackson Hole and Hole
Hiking constitutes “contractor bid or proposal information” as defined by the Act.
Therefore, Count II fails to the extent that it is based upon an alleged violation of
the Procurement Integrity Act.

             3.     No Breach of the Implied Contract to Consider Bids Fairly
                    and Honestly

       The government also argues that Eco Tour has failed to prove that the NPS’s
disclosure of the better terms of Eco Tour’s proposals breached the implied-in-fact
contract to consider bids fairly and honestly. Def.’s Mot. at 27; Def.’s Reply at 16.
Again, the court agrees with defendant. As noted, to recover under the implied
contract for bids to be fairly and honestly considered, Eco Tour must establish that
the NPS acted arbitrarily or capriciously, or abused its discretion. E.g., 
Southfork, 141 F.3d at 1132
(citing Keco 
II, 492 F.2d at 1203-04
). Four factors are generally
relevant to a determination of whether the government has breached the implied
contract to consider bids fairly: (1) subjective bad faith on the part of the
government; (2) the absence of a reasonable basis for the administrative decision;
(3) the amount of discretion afforded to the procurement officials by applicable
statutes and regulations; and (4) proven violations of pertinent statutes or
regulations. 
Id. Eco Tour
has not demonstrated that the agency’s disclosure of the better
terms of Eco Tour’s proposals was motivated by bad faith, lacked a reasonable
basis, or violated any statute or regulation. To the contrary, under the regulations,
the NPS was required to “advise the preferred offeror of the better terms and
conditions of the best proposal and permit the preferred offeror to amend its
proposal to match them.” 36 C.F.R. § 51.32. The NPS’s June 20, 2013 letters to
the preferred offerors complied with this regulatory provision.




                                          49
       Additionally, while paragraph 4 of the prospectus instructions provided that
the NPS would not make public any information specifically marked in Eco Tour’s
proposal as a trade secret or as “confidential commercial and financial
information,” see AR Tab 4 at 28, Eco Tour failed to mark its proposals in
accordance with paragraph 4. Specifically, Eco Tour failed to mark the cover
pages of its proposals with the legend specified in paragraph 4(b), and also failed
to specifically identify the allegedly confidential information in its proposals as
required by paragraph 4(b). Compare AR Tab 4 at 28 (requiring the offeror to
“mark the cover page of each copy of the proposal with the following legend” and
to “specifically identify what you consider to be trade secret information or
confidential commercial or financial information on the page of the proposal on
which it appears”), with AR Tabs 21-22 (showing that Eco Tour’s proposals lack
legends on cover pages and specific identification of confidential information).
Although Eco Tour marked most pages of its proposals with the general disclaimer
set forth in paragraph 4(b), it failed to satisfy the second requirement of paragraph
4(b), which was to “specifically identify” the allegedly confidential information.
See AR Tab 4 at 28 (“You must specifically identify what you consider to be trade
secret information or confidential commercial or financial information on the page
of the proposal on which it appears, and you must mark each such page with the
following legend . . . .”) (emphasis added). Therefore, even if paragraph 4 would
otherwise prohibit the NPS from disclosing Eco Tour’s properly identified
confidential information, Eco Tour cannot take advantage of such protection after
having failed to comply with the requirements of paragraph 4.

             4.    Eco Tour Has Not Demonstrated Prejudice Resulting from
                   the Alleged Improper Disclosure

       Finally, the government contends that, even assuming that the NPS’s
disclosure of the better terms of Eco Tour’s proposals violated the Procurement
Integrity Act or breached the implied contract to consider bids fairly and honestly,
Eco Tour has failed to demonstrate prejudice. The court must again agree with
defendant. In its motion, Eco Tour asserts, without explanation, that the NPS’s
disclosure caused Eco Tour unspecified “substantial harm.” Pl.’s Mot. at 41. Eco
Tour reiterates this unsupported assertion in its reply brief and asserts that
prejudice is “obvious.” Pl.’s Reply at 21 (“[B]y unilaterally disclosing these
products and services to Eco Tour’s direct competitors and explicitly informing
those competitors that their competitor offered a better proposal because of these

                                         50
specific terms, NPS has now totally eliminated Eco Tour’s competitive advantage.
That is obvious prejudice.”). These unsupported allegations of “substantial harm”
and elimination of competitive advantage cannot satisfy Eco Tour’s burden to
demonstrate that the government’s disclosure of the better terms of Eco Tour’s
proposals deprived Eco Tour of a “substantial chance” of being awarded the
disputed contracts. See 
Bannum, 404 F.3d at 1353
.

       Eco Tour’s only specific allegation of prejudice is that the NPS deprived
Eco Tour of the opportunity to “weigh the risks of having its confidential
information handed over to its competitors” and to choose between “agree[ing] to
have its confidential information disclosed to its competitor” or “withdrawing its
proposal.” Pl.’s Mot. at 41. This allegation is likewise insufficient to demonstrate
prejudice. As defendant correctly notes, “[a]n opportunity to withdraw from the
competition would not have given Eco Tour a substantial chance of winning the
competition.” Def.’s Mot. at 28.

       C.      The Agency’s Failure to Require Hole Hiking to Use Biodiesel
               Fuel (Count III)

       With respect to Count III, also presented as an alternative to Count I, Eco
Tour argues that the NPS violated applicable law, acted arbitrarily and
capriciously, and abused its discretion when it found that Hole Hiking had matched
the better terms of Eco Tour’s proposal for contract GRTE032-13. Pl.’s Mot. at
15-16, 39; Pl.’s Reply at 14-19. In its proposal, Eco Tour stated that it has used
biodiesel fuel in all of its vehicles since 2008, AR Tab 22 at 937, and that, “[u]nder
the new concession contract, [it] will use biodiesel in over 60 percent of [its]
vehicles until 100 percent of the vehicles have been converted [to] compressed
natural gas,” 
id. at 1086.
Eco Tour contends that the NPS, by not requiring Hole
Hiking to match this term of Eco Tour’s proposal, violated 36 C.F.R. § 51.32,
which requires the NPS to “advise the preferred offeror of the better terms and
conditions of the best proposal and permit the preferred offeror to amend its
proposal to match them.” Pl.’s Mot. at 39.15


       15
           / In contrast to Jackson Hole, which indicated in its proposal for contract GRTE024-13
that it uses biodiesel [ ], see AR Tab 20 at 645, 668, Hole Hiking did not state in its proposal for
contract GRTE032-13 that it uses any sort of alternative fuels [ ], see AR Tab 19 at 630.


                                                51
       In response, the government first argues that the NPS is not obligated to
require Hole Hiking to use biodiesel in its vehicles in order to exercise a right of
preference because doing so would violate 36 C.F.R. § 51.19, which prohibits the
agency from awarding a concession contract which “materially amends” the terms
and conditions of the draft concession contract set forth in the prospectus “[e]xcept
for incorporating into the concession contract appropriate elements of the best
proposal.” Def.’s Mot. at 21; Def.’s Reply at 11. In that regard, the government
asserts that the utilization of alternative fuels in vehicles is not “appropriate” for
the disputed contracts because such contracts are for cross-country ski tours, not
vehicle-based tours. Def.’s Mot. at 21; Def.’s Reply at 11.

       Eco Tour argues, in rebuttal, that “the use of alternative fuel vehicles was
appropriate and a better term in Eco Tour’s proposal” because it “result[s] in
greatly reduced emissions, thus protecting the environment in and around Grand
Teton National Park” in furtherance of the goals articulated under principal
selection subfactor 1(a) and secondary selection factor 1. Pl.’s Reply at 14. The
government responds that the only environmental practices required under
principal selection subfactor 1(a) and secondary selection factor 1 are “those that
protect the park from contamination,” and that the use of alternative fuels is but
one of “numerous environmental practices in [Eco Tour’s] proposal” which “have
nothing to do with protecting the park environment during a ski tour.” Def.’s
Reply at 12-13.

       By way of background, principal selection subfactor 1(a) directs offerors to
“describe how you will conduct your operations in a manner that will minimize
disturbance to Park wildlife by addressing . . . [t]he measures you will take to
minimize disruption of wildlife while conducting tours.” AR Tab 4 at 43.
Secondary selection factor 1 is the “quality of the offeror’s proposal to conduct its
operations in a manner that furthers the protection, conservation, and preservation
of the park and other resources through environmental management programs and
activities, including, without limitation, energy conservation, waste reduction, and
recycling.” AR Tab 4 at 57 (emphasis added).

      Eco Tour’s argument regarding biodiesel is not without support in the
record. In rating Eco Tour’s proposal for contract GRTE032-13 as “excellent”
under principal selection subfactor 1(a), the evaluation panel noted that Eco Tour’s
commitment to an “idle free policy” with its tour vehicles helped to “minimize

                                         52
disruption of wildlife while conducting tours.” AR Tab 24 at 1122. The NPS also
required Hole Hiking to match Eco Tour’s “idle free policy” because such a policy
“minimize[s] any disturbance to wildlife from the sound of a running vehicle.” AR
Tab 31 at 1193. In its proposal for contract GRTE032-13, Eco Tour stated that
using biodiesel not only reduces total vehicle emissions, but also produces “less
offensive” vehicle exhaust than petroleum-based fuel. AR Tab 22 at 937
(“Biodiesel is a fuel made in this country that has safer emissions than regular fuel.
Life cycle analysis completed by the National Renewable Energy Laboratory, and
later by Argonne National Laboratory, found that greenhouse gas emissions for
biodiesel could be more than 52 percent lower than those from other petroleum
products. In addition, the smell of exhaust is less offensive than petroleum
exhaust.”), 1086 (“The biodiesel fuel we have used since 2008 is produced in
Colorado and is made from used vegetable oil or soybean oil. The fuel releases
carbon dioxide into the air in smaller quantities than does petroleum-based fuel.”).
Thus, the record suggests that Eco Tour’s use of biodiesel fuel, like its “idle free
policy,” may reduce the disturbance of wildlife in furtherance of the goals
articulated under principal selection subfactor 1(a).

       Additionally, in rating Eco Tour’s proposal for contract GRTE032-13 as
“very good” under secondary selection factor 1, the evaluation panel took into
account Eco Tour’s “multiple company-wide policies and practices related to
environmental stewardship, such as using biofuel, using ‘green’ cleaning products,
and contributing to a carbon-offset fund.” AR Tab 24 at 1144 (emphasis added).
Therefore, at least one of the goals articulated in the prospectus is the conservation
of energy, and the NPS expressly recognized that Eco Tour’s use of biodiesel fuel
furthered that goal.

       However, despite the foregoing, the court is unable to conclude that the NPS
violated applicable law, acted arbitrarily or capriciously, or abused its discretion in
not requiring Hole Hiking to use biodiesel or similar alternative fuels in its tour
vehicles. First, in requiring the preferred offerors to adopt an “idle free policy”
under principal selection subfactor 1(a), the NPS appears to have been primarily
concerned with the disturbance caused by “the sound of a running vehicle.” AR
Tab 31 at 1193. Even if biodiesel fuel produces “less offensive” vehicle exhaust
than petroleum-based fuel, see AR Tab 22 at 937, the record contains no evidence
that vehicles using biodiesel fuel produce less noise than vehicles using petroleum-



                                          53
based fuel. Thus, the record does not establish that the use of biodiesel fuel
achieves precisely the same environmental benefits as an “idle free policy.”

       Second, Eco Tour’s use of biodiesel fuel was but one of several “company-
wide policies and practices related to environmental stewardship” that the NPS
considered in its evaluation of Eco Tour’s proposal under secondary selection
factor 1. AR Tab 24 at 1144. Other such policies and practices included utilizing
“green” cleaning products and contributing to a carbon-offset fund. 
Id. Under Eco
Tour’s theory, the NPS should have required Hole Hiking to match each of these
terms. That the NPS did not do so provides support for the government’s argument
that the use of biodiesel fuel, like the use of “green” cleaning products and
contributing to a carbon-offset fund, is outside the scope of the disputed contracts
for guided cross-country ski tour concessions.

       Therefore, although Eco Tour’s use of biodiesel fuel could reasonably be
viewed as furthering the goals articulated under principal selection subfactor 1(a)
and secondary selection factor 1, Eco Tour has not shown that the NPS acted
irrationally or arbitrarily in declining to require Hole Hiking to match this term,
and the court will not second guess the agency’s technical determination in that
regard. See, e.g., E.W. 
Bliss, 77 F.3d at 449
(“[T]echnical ratings . . . involve
discretionary determinations of procurement officials that a court will not second
guess.”) (citations omitted); Omega World Travel, Inc. v. United States, 
54 Fed. Cl. 570
, 578 (2002) (“It is well settled that contracting officers are given broad
discretion with respect to evaluation of technical proposals.” (citing E.W. 
Bliss, 77 F.3d at 449
)); Electro-Methods, Inc. v. United States, 
7 Cl. Ct. 755
, 762 (1985)
(“[W]here an agency’s decisions are highly technical in nature, . . . judicial
restraint is appropriate and proper.” (citing Isometrics v. United States, 
5 Cl. Ct. 420
, 423 (1984))).16

       16
         / In reaching this conclusion, the court declines to consider Eco Tour’s citations to
various extra-record evidence purportedly demonstrating that the use of alternative fuel was
within the scope of the disputed contracts. Pl.’s Reply at 16-19 (citing a “Fact Sheet” available
on the NPS website and two articles available on the Department of Energy website). As Eco
Tour’s extra-record evidence is not necessary for effective judicial review, and would not alter
the court’s analysis with respect to Count III even if the court were to consider it, the court grants
defendant’s motion to strike such evidence. See, e.g., Axiom Res. Mgm’t, Inc. v. United States,
564 F.3d 1374
, 1379 (Fed. Cir. 2009).


                                                 54
IV.   Eco Tour is Limited to a Recovery of Bid Preparation Costs

        Having determined that the NPS acted arbitrarily and capriciously in
concluding that Jackson Hole’s and Hole Hiking’s proposals were responsive, and
that Eco Tour was prejudiced as a result, the court now turns to the issue of the
relief to be granted. The government argues that the court lacks authority to grant
Eco Tour’s requested injunctive and declaratory relief “because 28 U.S.C. §
1491(b) does not apply to concession contracts, and 28 U.S.C. § 1491(a) provides
for only monetary relief.” Def.’s Mot. at 28; see also Def.’s Reply at 17-20. For
the reasons specified below, the court agrees that it lacks the authority to award
injunctive or declaratory relief to Eco Tour. Therefore, Eco Tour is limited to an
award of damages in the form of bid preparation costs.

       Except in narrow statutorily defined circumstances, the Court of Federal
Claims lacks jurisdiction to award injunctive or declaratory relief. United
Keetoowah Band of Cherokee Indians of Okla. v. United States, 
480 F.3d 1318
,
1326 n.5 (Fed. Cir. 2007) (citation omitted); Kanemoto v. Reno, 
41 F.3d 641
, 644-
45 (Fed. Cir. 1994) (“The remedies available in [the Court of Federal Claims]
extend only to those affording monetary relief; the court cannot entertain claims
for injunctive relief or specific performance, except in narrowly defined, statutorily
provided circumstances . . . .”); Terry v. United States, 
103 Fed. Cl. 645
, 656
(2012); Leitner v. United States, 
92 Fed. Cl. 220
, 223 (2010) (“This Court may
issue declaratory judgments or offer equitable relief only under an express grant of
such jurisdiction in a federal statute.” (citing United States v. Testan, 
424 U.S. 392
,
398 (1976), and United States v. King, 
395 U.S. 1
, 4 (1969))). This court has
statutory authority to award equitable relief in certain types of tax cases, see 28
U.S.C. § 1507 (2006); in “nonmonetary disputes” arising under the CDA, see 28
U.S.C. § 1491(a)(2); and, in procurement bid protests, see 28 U.S.C. § 1491(b)(2).
Additionally, in cases where the equitable relief is “‘tied and subordinate to a
money judgment,’” James v. Caldera, 
159 F.3d 573
, 580 (Fed. Cir. 1998) (quoting
Austin v. United States, 
206 Ct. Cl. 719
, 723 (1975)), the court may “issue orders
directing restoration to office or position, placement in appropriate duty or
retirement status, and correction of applicable records,” 28 U.S.C. § 1491(a)(2).

       The court concludes that none of these statutory provisions authorize the
injunctive and declaratory relief requested by Eco Tour. As an initial matter, this
case is not a tax case, nor does it invoke the CDA. Therefore, the first and second

                                          55
statutory bases for equitable relief are inapplicable. Additionally, as set 
forth supra
, the court finds that the disputed concession contracts are not procurement
contracts, and thus section 1491(b) is inapplicable.

       Nor is Eco Tour entitled to injunctive or declaratory relief under section
1491(a). In its reply brief, Eco Tour suggests that the court may grant equitable
relief under section 1491(a)(2) because such relief would be “‘incident of and
collateral’ to a monetary judgment.” Pl.’s Reply at 22-23 (quoting Voisin v. United
States, 
80 Fed. Cl. 164
, 177-78 (2008)). Yet Eco Tour has not cited any case in
which equitable relief was granted under section 1491(a)(2) in the context of a
claim for breach of the implied contract to consider bids fairly and honestly.

       Additionally, the court concludes that Congress, by enacting ADRA in 1996,
divested this court of authority to award equitable relief in bid protests pursued
under an implied contract theory. Before the enactment of ADRA in 1996, this
court’s jurisdiction over bid protests was predicated on an implied contract
between the government and prospective bidders to treat bidders’ proposals fairly
and honestly. See, e.g., Resource 
Conservation, 597 F.3d at 1242
; Emery
Worldwide 
Airlines, 264 F.3d at 1078-80
(explaining the “long and complicated”
history of judicial review of government procurement decisions); 
Impresa, 238 F.3d at 1331-32
(same); 
Southfork, 141 F.3d at 1132
; CACI, 
Inc.-Federal, 719 F.2d at 1573
; United States v. John C. Grimberg Co., 
702 F.2d 1362
, 1367 (Fed. Cir.
1983); Keco Indus., Inc. v. United States, 
428 F.2d 1233
, 1237 (Ct. Cl. 1970)
(Keco I).

       Until 1982, an aggrieved bidder asserting an implied contract claim “was
typically limited to monetary relief such as bid preparation costs.” 
Impresa, 238 F.3d at 1331
(citing Keco 
II, 492 F.2d at 1203
, and Finley v. United States, 31 Fed.
Cl. 704, 708 (1994)); see also Keco 
I, 428 F.2d at 1240
(“[I]f it should be
determined subsequently by the commissioner that plaintiff’s bid was not treated
honestly and fairly by the Government, then plaintiff should be allowed to recover
only those costs incurred in preparing its technical proposals and bid.”). In 1982,
the court was first given authority to grant declaratory and injunctive relief in pre-
award bid protests pursued under an implied contract theory. Federal Courts
Improvement Act of 1982, Pub. L. No. 97-164, sec. 133(a), § 1491(a)(3), 96 Stat.
25, 39-40. Such authority was formerly codified at 28 U.S.C. § 1491(a)(3), which
provided, in pertinent part: “‘To afford complete relief on any contract claim

                                         56
brought before the contract is awarded, the court shall have exclusive jurisdiction
to grant declaratory judgments and such equitable and extraordinary relief as it
deems proper, including but not limited to injunctive relief.’” Resource
Conservation, 597 F.3d at 1244
n.10 (quoting former section 1491(a)(3)).

        In 1996, however, Congress enacted ADRA, which “repealed former section
1491(a)(3), and enacted its substance as section 1491(b)(2).” 
Id. In so
doing,
Congress removed bid protest remedies from section 1491(a) and provided this
court with a new, and independent, basis for bid protest jurisdiction in section
1491(b), under which the Court of Federal Claims is authorized to award “any
relief that the court considers proper, including declaratory and injunctive relief.”
28 U.S.C. § 1491(b)(2); see also Lion Raisins, Inc. v. United States, 
52 Fed. Cl. 115
, 118 (2002) (citations omitted).

         Although the Federal Circuit has not had occasion to rule on the issue of
whether the Court of Federal Claims has authority, post-ADRA, to grant equitable
relief in implied contract bid protests pursued under section 1491(a), this court has
consistently answered that question in the negative. See Terry v. United States, 
96 Fed. Cl. 131
, 153 (2010) (citations omitted) (“Under section 1491(a)(1), plaintiff is
precluded from obtaining equitable relief, which is only available for a section
1491(b)(1) protest, and is limited to a recovery of monetary damages that comprise
the costs she incurred while preparing her proposal.”), vacated in part on other
grounds, 
98 Fed. Cl. 736
(2011); FAS 
Support, 93 Fed. Cl. at 694
(“The major
difference between a protest brought under 28 U.S.C. § 1491(b)(1) and one
brought pursuant to an implied contract under 28 U.S.C. § 1491(a)(1) is the
equitable relief which is available for the section 1491(b)(1) protest, but not for
breach of the implied contract. Only monetary relief is available for breach of the
implied contract, comprising the costs incurred in preparing the proposal and bid.”
(citing Keco 
I, 428 F.2d at 1240
)); Overstreet Elec. Co. v. United States, 47 Fed.
Cl. 728, 731 n.5 (2000) (noting that a claim for breach of an implied-in-fact
contractual obligation to consider and treat all bids fairly “no longer is the trigger
for injunctive relief in this court”); W & D Ships Deck Works, Inc. v. United States,
39 Fed. Cl. 638
, 641 (1997) (“The repeal by [ADRA] . . . of § 1491(a)(3)
eliminated this court’s statutory authority to grant equitable relief on the basis of
the old implied contract theory.”); cf. L-3 Commc’ns Integrated Sys., L.P. v. United
States, 
94 Fed. Cl. 394
, 397 (2010) (“Section 1491(a)(1) continues to allow any
plaintiff, including a disappointed bidder, to invoke this Court’s general contract

                                         57
jurisdiction to recover money damages, including bid preparation and proposal
costs.”).

      While the court is not bound to follow its prior decisions concerning the
availability of equitable relief in bid protests pursued under an implied contract
theory, it finds the reasoning of those decisions to be persuasive. Simply put, if
equitable relief was unavailable in implied contract bid protests pursued under
section 1491(a) until the enactment of section 1491(a)(3) in 1982, and section
1491(a)(3) was repealed with the enactment of ADRA in 1996, then it follows that
equitable relief is again unavailable in implied contract bid protests pursued under
section 1491(a). Accordingly, the court concludes that Eco Tour is precluded from
obtaining injunctive and declaratory relief.

       In its reply brief, Eco Tour argues that “this Court has the explicit authority
from Congress [under section 1491(a)(2)] to issue as declaratory relief an order
remanding this matter to NPS with directions as to what this Court deems proper
and just.” Pl.’s Reply at 23. Specifically, Eco Tour asks the court to “remand with
a direction for NPS to review its decision that the preferred offerors’ proposals
were responsive and, even if NPS continues to find such proposals responsive, to
provide direction that Hole Hiking needs to match Eco Tour’s better terms.” 
Id. at 24.
The court rejects Eco Tour’s request for a remand.

       Even if the court were authorized to grant a remand under section 1491(a)(2)
in connection with a bid protest pursued under an implied contract theory (an issue
which is far from certain 17), Eco Tour’s requested remand is beyond the scope of
any such authority. Eco Tour would shoehorn into the court’s ability to remand
with “proper and just” directions unfettered authority for the court to issue
essentially unlimited orders to the agency, such as requiring Hole Hiking to “match
Eco Tour’s better terms.” Pl.’s Reply at 24. This treads beyond the proper scope
of remand into the realm of injunctive relief. The power to remand with “proper
and just” instructions cannot trump the unavailability of injunctive and declaratory
relief under section 1491(a). See, e.g., Todd Const., L.P. v. United States, 88 Fed.
Cl. 235, 245 (2009).

       17
         / Eco Tour cites no authority supporting the grant of a section 1491(a)(2) remand in the
context of a bid protest pursued under an implied contract theory, and the court has found none.


                                               58
      For all of the foregoing reasons, the court concludes that Eco Tour is
precluded from obtaining injunctive or declaratory relief and is limited to a
recovery of monetary damages that comprise the costs Eco Tour incurred while
preparing its proposal. Accordingly, the court need not consider the parties’
remaining arguments concerning the particular equitable relief requested by Eco
Tour.

                                 CONCLUSION

       The Park Service acted arbitrarily and capriciously in concluding that the
financial information omitted from Jackson Hole’s and Hole Hiking’s proposals
for the disputed contracts was immaterial, and therefore that Jackson Hole’s and
Hole Hiking’s proposals were responsive to the requirements of the prospectus.
Accordingly, in allowing Jackson Hole and Hole Hiking to match the better terms
of Eco Tour’s proposals for the disputed contracts, the Park Service breached the
implied contract for bids to be fairly and honestly considered. As Eco Tour
submitted responsive proposals for the disputed contracts that received the highest
cumulative scores of any of the proposals received by the Park Service, Eco Tour
has demonstrated a “substantial chance” that it would have received the disputed
contracts if not for the Park Service’s arbitrary and capricious responsiveness
determination with regard to the proposals of Jackson Hole and Hole Hiking.
Having established prejudice resulting from the Park Service’s arbitrary and
capricious action, Eco Tour is entitled to judgment on the administrative record.

       The court encourages the parties to resolve the bid preparation costs issue
amicably, preferably by stipulation as to an amount due Eco Tour. If such a
resolution is not achieved, Eco Tour must file a motion and accompanying brief in
support of its request for bid preparation costs. The parties are directed to confer
to determine how they wish to proceed with respect to determining the amount of
bid preparation costs Eco Tour is entitled to receive in light of the court’s
resolution of this protest. The court also encourages the parties to explore and
address the issue of attorney fees and costs in advance of any necessity to litigate
that issue. Defendant shall file a status report as to the results of the parties’
negotiations in that regard on or before January 6, 2014.




                                         59
       Accordingly, it is hereby ORDERED that 18

       (1)    Plaintiff’s Motion for Judgment on the Administrative Record, filed
              September 20, 2013, is GRANTED;

       (2)    Defendant’s Motion for Judgment on the Administrative Record, filed
              October 22, 2013, is DENIED;

       (3)    Defendant’s Motion to Dismiss for Lack of Jurisdiction, filed August
              15, 2013, is DENIED as moot;

       (4)    Defendant’s Motion to Strike References to Documents Outside of the
              Administrative Record Made Within Plaintiff’s Opposition to
              Defendant’s Motion for Judgment on the Administrative Record, filed
              November 1, 2013, is GRANTED;

       (5)    On or before December 20, 2013, counsel for the parties shall
              CONFER and FILE with the Clerk’s Office a redacted copy of this
              opinion, with any material deemed proprietary or confidential marked
              out and enclosed in brackets, so that a copy of the opinion can then be
              prepared and made available in the public record of this matter;

       (6)    On or before December 20, 2013, defendant shall FILE, as a separate
              UNSEALED document on CD-ROM, a redacted version of the
              administrative record filed August 12, 2013, as well as redacted
              versions of the supplements to the administrative record filed on
              September 6, 2013 and October 1, 2013, so as to establish a proper
              public record of this protest;

       (7)    The parties shall CONFER and attempt a resolution of plaintiff’s
              requests for bid preparation costs and attorney fees and costs; and

       18
         / In ¶ 5 of the ordering language in the sealed version of this opinion issued on
November 26, 2013, the court directed the entry of final judgment in favor of plaintiff.
However, because the quantum of Eco Tour’s bid preparation costs has yet to be determined, the
court defers entry of final judgment pending the court’s final disposition regarding Eco Tour’s
bid preparation costs.


                                              60
(8)   On or before January 6, 2014, defendant shall FILE a Status Report
      as to the results of the parties’ negotiations regarding plaintiff’s
      requests for bid preparation costs and attorney fees and costs.


                                     /s/Lynn J. Bush
                                     LYNN J. BUSH
                                     Senior Judge




                                61

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer