Space Exploration Technologies Corp. v. United States, 14-354 (2015)

Court: United States Court of Federal Claims Number: 14-354 Visitors: 3
Judges: Susan G. Braden
Filed: Jan. 13, 2015
Latest Update: Mar. 02, 2020
Summary: In the United States Court of Federal Claims No. 14-354 C Filed: January 13, 2015 *************************************** * SPACE EXPLORATION TECHNOLOGIES * CORP., * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant, * * and * * UNITED LAUNCH SERVICES, LLC, * * Defendant-Intervenor. * * *************************************** Hamish Hume, Boies Schiller & Flexner LLP, Washington, D.C., Counsel for the Plaintiff. Alexander V. Sverdlov, United States Department of Justice, Civil Division, W
More
 In the United States Court of Federal Claims
                                         No. 14-354 C
                                    Filed: January 13, 2015

***************************************
                                      *
SPACE EXPLORATION TECHNOLOGIES *
CORP.,                                *
                                      *
      Plaintiff,                      *
                                      *
v.                                    *
                                      *
THE UNITED STATES,                    *
                                      *
      Defendant,                      *
                                      *
and                                   *
                                      *
UNITED LAUNCH SERVICES, LLC,          *
                                      *
      Defendant-Intervenor.           *
                                      *
***************************************

Hamish Hume, Boies Schiller & Flexner LLP, Washington, D.C., Counsel for the Plaintiff.

Alexander V. Sverdlov, United States Department of Justice, Civil Division, Washington, D.C.,
Counsel for the Government.

Charles J. Cooper, Cooper & Kirk, PLLC, Washington, D.C., Counsel for the Defendant-
Intervenor.

MEMORANDUM OPINION AND ORDER DENYING DEFENDANT-INTERVENOR’S
              JANUARY 7, 2015 MOTION TO DISMISS

BRADEN, Judge.

       On January 7, 2015, United Launch Services, LLC (“ULA”) filed a Motion To Dismiss
Space Exploration Technologies Corp. v. United States, Case No. 14-354 (Fed. Cl. 2014), pursuant
to RCFC 12(b)(1) and 12(b)(6), arguing that the National Defense Authorization Act for Fiscal
Year 2015, Pub. L. No. 113-291, §§ 1601 et seq. (2014) (“NDAA”) 1 ratified Contract No. FA8811-

       On December 19, 2014, the President signed H.R. 3979, the Carl Levin and Howard P.
       1

“Buck” McKeon National Defense Authorization Act for Fiscal Year 2015. See Press Release,
Department of Defense, President Signs National Defense Authorization Act (Dec. 19, 2014),
13-C-0002 (the “002 Contract”) and Contract No. FA8811-13-C-0003 (the “003 Contract”),
precluding judicial review. Dkt. No. 176; see also Dkt. No. 176-1, at 2–13. In the alternative,
ULA asserts that this case is moot, because the NDAA requires that the Secretary of Defense
(“SecDef”) increase competition in the Evolved Expendable Launch Vehicle (“EELV”) program
only if he can do so and “remain in compliance” with the 003 Contract. Dkt. No. 176-1, at 13–14.

       On December 16, 2014, the President signed the Consolidated and Further Continuing
Appropriations Act, 2015, Pub. L. No. 113-655 (2014) (“Appropriations Act”) 2 that funds the
Department of Defense (“DoD”) for fiscal year 2015. Two Sections of that Act are relevant to this
case. First, Section 8084 states that $125 million shall be available for the acceleration of a
competitively awarded EELV mission only if competitions are “open to all certified providers of
[EELVs],” “consider bids from two or more certified providers,” and permit EELV providers to
“compete any certified launch vehicle in their inventory.” Appropriations Act § 8084. Section
8118 prohibits DoD from “enter[ing] into a contract, memorandum of understanding, or
cooperative agreement with, or make a grant to, or provide a loan or loan guarantee to
Rosoboronexport or any subsidiary,” without a waiver by the SecDef, that is subject to review by
the DoD’s Inspector General. Appropriations Act § 8118(a); see also Appropriations Act
§ 8118(b), (c).

         On December 19, 2014, the President signed the NDAA that, in part, imposes certain
restrictions and reporting requirements on how DoD uses the funds made available for FY′15 by
the Appropriations Act. Several of these provisions concern the EELV program.

       First, the NDAA requires that the Secretary of the Air Force provide appropriate
congressional committees with “notice of each change to the [EELV] acquisition plan and
schedule . . . included in the budget submitted by the President . . . for [FY′15].” NDAA § 1602(a).

        Second, the NDAA prohibits the SecDef from awarding or renewing “a contract for the
procurement of property or services for space launch activities under the [EELV] program, if such
contract carries out space launch activities using rocket engines designed or manufactured in the
Russian Federation.” NDAA § 1608(a). The SecDef, however, may certify that such a contract
is required “for the national security interests of the United States” and that “space launch services
and capabilities covered by the contract could not be obtained at a fair and reasonable price without
the use of rocket engines designed or manufactured in the Russian Federation.” NDAA § 1608(a),
(b). There are two exceptions to the prohibition in Section 1608(a): the “placement of orders or
the exercise of options under Contract numbered FA8811-13-C-003, awarded on December 18,
2013”; and “rocket engines designed or manufactured in the Russian Federation that prior to
February 1, 2014, were either fully paid for by the contractor or covered by a legally binding
commitment of the contractor to fully pay for such rocket engines.” NDAA § 1608(c)(1). In


available at http://www.defense.gov/news/newsarticle.aspx?id=123866 (last visited Jan. 13,
2015).
        2
          See Press Release, The White House, Statement by the Press Secretary on H.R. 83 (Dec.
16, 2014), available at http://www.whitehouse.gov/the-press-office/2014/12/16/statement-press-
secretary-hr-83 (last visited Jan. 13, 2015) (stating that the President signed H.R. 83, the
Consolidated and Further Continuing Appropriations Act, 2015).


                                                  2
addition, Section 1608(c)(2) sets forth the certification procedure that the SecDef must follow in
awarding or renewing a contract that includes the use of rocket engines designed or manufactured
in the Russian Federation. See NDAA § 1608(c)(2).

       Third, no later than June 1, 2015, the Comptroller General is required to submit a report to
the congressional defense committees on the EELV program that includes “an assessment of the
advisability of the [SecDef] requiring . . . that new entrant launch providers or incumbent launch
providers establish or maintain business systems that comply with the data requirements and cost
accounting standards of the [DoD], including certified cost or price data.” NDAA § 1609.

        Fourth, the NDAA requires that the SecDef increase the number of cores to be purchased
on a competitive basis in FY′15 by one. See NDAA § 1611(a)(1). For FY′15–′17, one additional
core is also to be purchased on a competitive basis, unless the SecDef certifies to the congressional
defense committees that there is “no practicable way” to purchase this core for FY′15–′17 and
“remain in compliance with the requirements of the firm fixed price contract for [thirty-five] rocket
engine cores during the five fiscal years beginning with [FY′13].” NDAA § 1611(a)(2)(A).

        ULA insists that enactment of the NDAA and specific reference to DoD’s payment
obligations under the 002 and 003 Contracts “ratify” or render them lawful. Dkt. No. 176-1, at 2–
13. Congress, however, directed DoD to procure one mission competitively in 2015, without
regard to its obligations under the 002 and 003 Contracts. As for FY′15–′17, Congress directed
DoD to procure one more additional core, but if “there is no practicable way” to do so and comply
with the “firm fixed price contract for [thirty-five] rocket engine cores,” the SecDef is required to
submit a certification to that effect to congressional defense committees. NDAA § 1611(a)(2).
Upon receipt of this certification, Congress may elect to authorize funds for that launch or not—
or to require DoD to reprogram or transfer other authorized funds for this purpose. See, e.g.,
Appropriations Act § 8075 (transferring funds). In other words, Section 1611(a)(2)(A) simply
recognizes the status quo, i.e., the fact that DoD has a pre-existing contractual relationship with
ULA, nothing more. In addition, there is no text in the NDAA exhibiting “full congressional
knowledge or awareness” of the allegations in the November 18, 2014 Second Amended
Complaint in this case, or information contained in the Administrative Record, the Court’s Record,
or the myriad exhibits proffered by the parties. Indeed, all of these documents and the parties
motions and briefs have been placed under seal. Without such “knowledge,” Congress was in no
position to “ratify” the conduct of the Air Force at issue in this case. See generally United States
v. Beebe, 
180 U.S. 343
(1901) (holding that Congress can ratify unlawful agency action only if it
had knowledge of the unauthorized activity); see also Schism v. United States, 
316 F.3d 1259
,
1289–94 (Fed. Cir. 2002) (en banc) (discussing cases). As such, the NDAA does not affect the
court’s Tucker Act 3 jurisdiction or exempt the Air Force from compliance with federal
procurement laws or regulations in awarding the 002 Contract and the 003 Contract.


       3
         The Tucker Act authorizes the United States Court of Federal Claims “to render judgment
on an action by an interested party objecting to a solicitation by a Federal agency for bids or
proposals for a proposed contract or to a proposed award or the award of contract or any alleged
violation of statute or regulation in connection with a Federal procurement or proposed a
procurement.” 28 U.S.C. § 1491(b)(1).


                                                 3
        Likewise, the NDAA does not render this case moot. As a matter of law, a claim becomes
moot when “the issues presented are no longer ‘live’ or the parties lack a legally cognizable interest
in the outcome.” Powell v. McCormack, 
395 U.S. 486
, 496 (1969). In addition, “actual
controversy must remain at all stages, not merely at the time the complaint is filed.” Gerdau
Ameristeel Corp. v. United States, 
519 F.3d 1336
, 1340 (Fed. Cir. 2008) (citing Steffel v.
Thompson, 
415 U.S. 452
, 460 n.10 (1974)). To determine whether a case is moot, the court
examines whether: “(1) it can be said with assurance that ‘there is no reasonable expectation . . .’
that the alleged violation will recur, and (2) interim relief or events have completely and
irrevocably eradicated the effects of the alleged violation.” Cnty. of L.A. v. Davis, 
440 U.S. 625
,
631 (1979) (internal citations omitted). Space Exploration Technologies Corp. (“SpaceX”) had
and retains a “cognizable interest” in the outcome of the case, as the court may determine that the
award of the 002 Contract and/or the 003 Contract violated federal procurement laws or regulations
or was arbitrary and capricious. Compare 
Powell, 395 U.S. at 496
, with Pl. 11/18/14 2nd Am.
Compl. ¶¶ 182–206 (alleging violations of the Competition In Contracting Act, 10 U.S.C. § 2304
and Part 6 of the Federal Acquisition Regulations); Pl. 11/18/14 2nd Am. Compl. ¶¶ 207–212
(alleging violations of the Defense Acquisition Regulations System Subpart 217.1); Pl. 11/18/14
2nd Am. Compl. ¶¶ 213–217 (alleging that the Air Force’s awards of the 002 and the 003 Contracts
were “arbitrary and capricious” under 5 U.S.C. § 706(2)(A)). Moreover, SpaceX’s potential
opportunity to compete for the missions identified in Section 8084 of the Appropriations Act or
the two missions identified in Sections 1611(a)(1)–(2) of the NDAA may not necessarily
“completely and irrevocably eradicte[] the effects” of the allegedly improper award of the 002 and
003 Contracts to ULA. See Cnty. of 
L.A., 440 U.S. at 631
. Therefore, SpaceX’s claims are not
moot.

        On June 30, 2014 and November 25, 2014, the Government filed Motions To Dismiss.
Dkt. Nos. 75, 162. On December 19, 2014, SpaceX filed a Motion For Judgment On The
Administrative Record under RCFC 52.1(c). Dkt. No. 171. Briefing is now complete on all of
these motions. The court has advised the parties that it will not rule on pending motions for
jurisdictional discovery or on the merits until the mediation, scheduled to commence this month,
is concluded. In turn, the Air Force has advised the court that it will not make a final decision
about the [REDACTED] missions until [REDACTED], 2015. Dkt. No. 166, at 3, 11. In addition,
the [REDACTED] has been scheduled as a competitive mission to be awarded in the near future.
AR SMC 54196.

        Finally, on January 6, 2015, the Air Force issued a Notice Of Press Announcement stating
that, while no new entrants were able to be certified by December 2014, a “new entrant is close”
and that the Air Force “will continue to invest significant resources in a close collaborative effort
on the certification process in 2015.” Dkt. No. 175 Att. A (statement by Lt Gen Samuel Greaves,
Commander of the Space and Missile Systems Centers).

       For these reasons, ULA’s January 7, 2015 Motion To Dismiss is denied.

IT IS SO ORDERED.
                                                      s/ Susan G. Braden
                                                      SUSAN G. BRADEN
                                                      Judge



                                                  4

Source:  CourtListener