NANCY B. FIRESTONE, Judge.
This lawsuit is one of a number of cases arising out of the failure of the defendant, the Department of Energy ("DOE" or "government") to perform its contractual obligations to remove spent nuclear fuel ("SNF") from nuclear power plants, including plaintiff Entergy Nuclear Palisades, LLC ("Entergy"), which operates the Palisades nuclear power plant located in Covert, Michigan. The Nuclear Waste Policy Act ("NWPA") of 1982, codified as amended at 42 U.S.C. §§ 10101-10270, called for DOE to enter into agreements under which nuclear power plants would pay the government to take SNF from the plants and put the SNF in a long-term storage facility in Yucca Mountain, Nevada. Though the NWPA and Entergy's contract, DE-CR01-83NE44374 for Disposal of Spent Nuclear Fuel and/or High Level Radioactive Waste (the "Standard Contract") required the government to begin accepting SNF on January 31, 1998, to date, the DOE has not accepted any SNF from Palisades or any other plant, and has no immediate plans to do so. Over the life of the contract, Entergy and its predecessor in ownership, Consumers Power Company ("Consumers"), have paid approximately $279 million in fees to the DOE.
This is the second case that has been filed concerning the government's breach of the Standard Contract with respect to the Palisades plant. Consumers entered into the Standard Contract in 1983. When the government failed to abide by its obligations under the Standard Contract, Consumers sued the DOE to recover the costs of its efforts to mitigate the damages caused by the government's failure to accept any SNF, including constructing and maintaining two long-term SNF storage facilities, known as independent spent fuel storage installations ("ISFSI"), at the Palisades plant. In 2005, this court held that the government had breached the Standard Contract when it failed to begin accepting SNF in 1998.
In this lawsuit, Entergy is seeking to recover costs it incurred to mitigate the government's breach between the time it acquired Palisades on April 11, 2007 through June 30, 2013 (the "claims period"). The government agreed that it was liable to Entergy for approximately $20.6 million of the $36.1 million Entergy sought in this litigation. On May 18, 2015, the court entered partial judgment against the government in that amount. Order of Judgment, ECF No. 65.
Thereafter, the court held a seven-day trial in December 2015, at which thirteen witnesses testified, with regard to the amount of damages still in dispute. After the trial had concluded, the government conceded that, following the Federal Circuit's decision in
Prior to trial, the parties entered into stipulations of fact in which the government agreed that, while it did contest that Entergy was entitled to recover certain costs, it did not contest that Entergy actually incurred the amounts claimed, other than the amount claimed for security at the second ISFSI. The government also stipulated that, with respect to any payroll loaders associated with Entergy's claims, the government would not challenge the calculation of the payroll loader rates and agreed that if a claimed damage category is recoverable, the associated payroll loaders are also recoverable.
At trial, Entergy presented evidence with respect to three broad categories of damages, discussed below. The government, in turn, presented evidence in support of its argument that Entergy would have incurred many of these costs even if the government had not breached the Standard Contract.
During the claims period, Entergy expended $10,359,120 to replace deteriorating racks, located in the spent fuel pool at Palisades, which hold SNF immediately after the fuel is removed from the reactor.
The court finds that Entergy would not have undertaken the re-rack project had the government not breached the contract. However, the court finds that the plaintiff did not meet its burden with respect to the cost of removing stuck fuel assemblies from the spent fuel pool during the rack replacement project because Entergy would have had to remove the stuck assemblies even if the government had performed under the contract.
Entergy initially claimed that it is entitled to recover $24,436,531 for costs related to loading the SNF into dry storage canisters and constructing the second ISFSI for long-term dry storage of SNF at Palisades. The government has already paid $19,957,483 in this case for this category of damages. The bulk of the remaining $4,480,048 of damages related to the labor costs associated with loading the SNF into dry fuel storage casks for long-term storage, and the corresponding payroll loaders. At trial, the government claimed that Entergy had not met its burden of showing that the government's breach caused these damages. However, following the Federal Circuit's decision in
The government still disputes that Entergy is entitled to $387,301 in welding contractor standby costs associated with cask closure activities and $558,030 Entergy paid to lease equipment for several weeks while the loading campaign was delayed. The court finds that the government is not liable for the delay costs associated with Entergy's dry fuel storage efforts because the additional expenses came as a result of Entergy's errors and thus Entergy broke the chain of causation between the government's breach and Entergy's mitigation efforts.
In addition, the government disputes Entergy's claim for $12,496 associated with structural analysis of part of the Palisades plant known as the "track alley." Entergy presented testimony that the structural review was part of the transition to a new dry cask storage system and is thus attributable to the government's breach. The government counters that Entergy would have had to perform the structural analysis as part of Entergy's routine maintenance, and therefore this cost was not caused by the government's breach. The court finds that the analysis was performed as part of the plant's dry fuel storage campaign and thus Entergy is entitled to recover this cost.
Finally, Entergy presented evidence to show that it was providing full time security at the second ISFSI, which would not have been constructed had the government performed. Entergy's witnesses testified that there were two posts dedicated to the second ISFSI and both posts were staffed around the clock, as required under Nuclear Regulatory Commission ("NRC") regulations. Entergy claims that it incurred $1,306,316 staffing the two posts around the clock during the claims period.
At the partial summary judgment phase, the government agreed to pay $676,713 in additional security costs, representing its calculation of the cost of staffing one of the two posts at the second ISFSI. Entergy claims it is entitled to an additional $629,603 for the cost of staffing the second post. The government contends that Entergy has not provided sufficient evidence to show that Entergy actually staffed both posts at all times. Further, the government argues that Entergy has failed to prove these damages because Entergy's total security costs did not increase by the amount that Entergy calculated that it cost to staff the two posts during the claims period. The court finds that Entergy established its right to recover $677,399 in security costs associated with guarding a facility for storing spent nuclear fuel.
The plaintiff's burden for establishing damages in a SNF case, where, as here, the government's liability for breach is established, is well settled. In order to recover the costs of mitigating the government's breach, a plaintiff must prove that the cost incurred was caused by the government's breach of the Standard Contract and that the cost would not have been incurred in a "but-for" world in which the government did not breach the contract.
As noted, the bulk of Entergy's damages claim is $10,359,120 it incurred during the claim period in connection with the spent fuel pool re-rack project, which includes both the replacement of the Carborundum racks and the liberation of assemblies that had become stuck in the racks. The parties largely agree on the sequence of events.
The reactor at the Palisades plant uses uranium fuel pellets that are stacked into long metal tubes called "fuel rods." Joint Supp. Stips. at ¶ 1. The fuel rods are placed into an array called an "assembly." The reactor core at Palisades holds 204 fuel assemblies.
The spent fuel pool at Palisades contains racks designed in a grid formation creating individual "cells." Each cell is intended to hold one fuel assembly, keeping all assemblies a set distance from each other. The racks at issue in this litigation were installed in 1977 and increased the pool's capacity from 272 cells to 798 cells which could theoretically each contain one assembly.
Though the Carborundum panels inside the cell walls of the Region I racks were intended to help control radioactive criticality of the spent fuel pool, the Carborundum degraded over time generating a gas that damaged the racks.
Under Entergy's amended license, which went into effect on February 6, 2009, Entergy no longer took credit for Carborundum as a neutron absorber in the spent fuel pool for the purposes of the pool's criticality analysis.
In 2011, Entergy entered into a contract with Holtec International to replace the Region I Carborundum racks with racks using a neutron absorbing material called "Metamic," instead of Carborundum. Joint Supp. Stips. at ¶ 12. The re-rack of Region I of the Palisades spent fuel pool was completed in 2013.
Though Entergy acknowledges that the racks were problematic even before the government breached the Standard Contract, Entergy asserts that the plant would not have replaced the Carborundum racks had the DOE begun accepting SNF in 1998. Entergy presented evidence, which the government did not dispute, that there would have been fewer fuel assemblies in the spent fuel pool if the government had not breached the Standard Contract than there were in the actual world at the time that Entergy decided to replace the racks, and the number of assemblies in the pool would have continued to decrease over time. By contrast, in the actual world, the number of assemblies in the pool will continue to increase. Entergy's witnesses testified, and the court agrees, that if there had been fewer assemblies in the spent fuel pool, Entergy could and would have worked around the problems with the existing Carborundum racks in accordance with its amended NRC license until the plant was decommissioned.
Guy "Tom" Wiggins, a reactor engineer at Palisades, testified that primary reason Entergy decided to re-rack the spent fuel pool was because the space restrictions in the spent fuel pool made it so that Entergy did not have enough available cells to perform a full-core offload. Tr. 257:9-12 (Wiggins).
Mr. Wiggins explained that in preparation for the scheduled full-core offload, Entergy underwent a Kepner-Tregoe ("KT") analysis, in which various potential options for addressing a problem are given a score reflecting their positive and negative attributes, to determine how to best address the lack of space in the spent fuel pool. Tr. 252:3-10 (Wiggins); PX 594 (KT Decision Analysis). The objectives of the analysis, from most weighted to least weighted, included: maximizing fuel storage capacity; minimizing adverse impact on outage schedule; minimizing O&M cost; minimizing personnel exposure; minimizing complications to technical specifications; minimizing capital cost; minimizing rack damage during stuck assembly removal; minimizing licensing change requirements; and minimizing radioactive waste. PX 594 at 2. In the KT analysis, Entergy considered re-racking Region I; re-racking the entire spent fuel pool; increasing dry fuel storage; or doing nothing, and determined that re-racking Region I was the best solution.
Though increasing Entergy's dry fuel storage efforts to increase room in the spent fuel pool was considered, the KT team rejected that option for several reasons. According to Entergy's findings, Entergy would have had to load four to five additional casks as part of the 2011 loading campaign on top of the six casks it intended to load during that campaign in order to remove enough fuel to restore full-core offload capability for the 2014 inspection. PDX 3 (Wiggins) at Slide 32; PX 597 (Spent Fuel Storage at Palisades Power Point) at 4-5. That would bring the total number of assemblies that Entergy would have to identify as qualifying for dry fuel storage up to approximately 224. PX 597 at 5. The KT team found that identifying 224 qualifying assemblies would require a major ultrasonic testing campaign, and even with such a campaign, it might not have been possible to qualify 224 assemblies as being sufficiently burned off and cooled to be placed in dry fuel storage.
Further, Entergy concluded that even if it increased its dry storage campaign to restore full-core offload ability for the required 2014 inspection, Entergy would likely lose full-core offload ability again in the near future as newer, hotter fuel was added to the pool. PX 597 at 5 Though Entergy was not required to be able to fully offload its core at all times, having that ability is preferable because, as Entergy project manager William Harper explained, "no nuclear station in the country ever wants to be in a position that they can't offload their core completely if they needed [to] perform any kind of emergent maintenance or emergent repair during [a] refueling outage." Tr. 454:11-455:16 (Harper). For these reasons, Entergy decided that replacing the racks was the best option.
Mr. Wiggins further explained that if the DOE had performed, re-racking would not have been necessary because there would have been fewer assemblies in the pool at the critical juncture leading up to the 2014 full-core offload, and that Entergy would have expected the number of assemblies in the pool to continue to decline in the future.
The government's expert, Gregory A. Maret, did not contradict Entergy's calculations of how many assemblies would have remained in the spent fuel pool at Palisades in the non-breach world compared to how many assemblies were in the pool in the actual world.
Mr. Maret testified that Entergy would have decided to replace the Carborundum racks regardless of the breach because the Carborundum racks were highly undesirable in that they had stopped absorbing neutrons and would continue to degrade further, and, as a result, the pool required continued monitoring to maintain desirable criticality levels. Tr. 983:2-987:1; 996:2-18 (Maret). In addition, the government argues that additional cell wall swelling would continue to be an unpredictable problem and asserted that it was "highly unlikely that [Entergy] would have continued to operate with the unpredictable cell wall swelling caused by the defective Carborundum racks." Def.'s Resp. 5-6.
The court does not find Mr. Maret's opinion persuasive because, in the real world, Entergy had been working around the problems with the Carborundum racks without replacing them until Entergy ran out of space in the pool to perform a full-core offload. As discussed, Entergy had been operating the pool without taking credit for any of the Carborundum's neutron absorbing capability through spacing out assemblies across more cells. Therefore, the court agrees with Entergy that Carborundum degradation, or the potential for additional Carborundum degradation, was not a sufficient reason in and of itself for Entergy to undertake a capital project of this magnitude.
The court is also not persuaded that additional dry fuel storage would have been a more reasonable mitigation response than re-racking the spent fuel pool. Mr. Maret testified that the 55 "stranded" or damaged assemblies could in fact have been loaded into dry fuel storage had Entergy used a different type of cask. Tr. 1007:11-1008:12 (Maret). According to the government, in order to regain full-core offload capability for the 2014 inspection, Entergy would have had to load two additional casks, which, based on the amount it cost Entergy to load and procure casks during the 2011 loading campaign, would have increased the cost of that campaign by $4,308,588. Def.'s Reply 6 (citing Tr. 109:24-110:7, 120:2-11, 133:17-134:11, 156:19-158:21 (VanWagner); DX 59 at KRG-PAL011706-37; DX 95; J. Mot. to Amend Damages Chart (ECF No. 118-1) at 1). The government argues that because this expense is significantly lower than the approximately $18.4 million total cost of the project (approximately $10 million of which was incurred during the claims period), the re-rack was not a reasonable mitigation choice.
The court is not persuaded that the fact that Entergy could have, at least in the short term, regained full-core offload capability through additional dry fuel storage makes Entergy's decision to re-rack the pool an unreasonable choice. First, the government's comparison of approximately $18.4 million for the re-rack compared to $4.3 million to load additional casks is misleading. The $18.4 figure includes approximately $4.7 million ($677,399 of which accrued during the claims period) attributable to liberation of the fuel assemblies that had become trapped in the swollen cells. DX 233 at 5; Tr. 439:21-441:4 (Harper). As discussed below, the court has found that Entergy cannot recover those costs. Further, even assuming that Mr. Maret is correct and only two additional casks would have been required to regain full-core offload capability, as opposed to the four or five additional casks estimated by Entergy, the court cannot assume that it would cost the same amount to procure and load dry storage casks for the "stranded" or damaged assemblies as it did to procure and load other casks during the 2011 dry fuel storage campaign. Mr. Wiggins testified that the stranded assemblies were damaged and would have had to have been placed in special damaged fuel canisters. Tr. 250:14-21, 251:2-5, 274:25-275:7. Accordingly, the court cannot assume that it would cost the same amount to procure and load dry storage casks for the "stranded" or damaged assemblies as it did to procure and load other casks during the 2011 dry fuel storage campaign.
Second, the court finds that it was reasonable and proper for Entergy to take other factors, in addition to cost into account when deciding to re-rack the pool. As the KT team found, re-racking the pool "provide[d] a permanent solution to the problem where as several of the other options provided only temporary solutions." PX 599 at 11. William Harper, Entergy project manager, Suzanne Leblang, former Entergy project manager, and Tom Woody, former Entergy reactor engineer, testified that, by re-racking, and replacing the Carborundum racks with racks containing Metamic as the neutron absorber, Entergy was able to regain flexibility and predictability in its spent fuel pool and increase storage capacity. Tr. 453:9-16 (Harper); Tr. 882:18-885:5 (Leblang); Tr. 931:19-934:23 (Woody). In addition, the court finds that Entergy was correct to conclude that if it increased its dry fuel storage efforts to regain full offload capacity, the plant would likely lose that capacity soon after as more spent assemblies were added to the pool.
Accordingly, the court finds that if the government had performed, there wo
In addition to the costs of installing new racks, Entergy is also claiming $677,399 for the cost of liberating 11 fuel assemblies that had become stuck in the pool's Carborundum racks because of swelling in the cell walls. The government argues that even if Entergy is entitled to the costs of replacing the Carborundum racks, Entergy should not be able to recover the costs of liberating the stuck assemblies because under the Standard Contract, Entergy was required to prepare the assemblies before DOE removed the SNF from Palisades. Accordingly, the government argues that its breach was not the but-for cause of this expense because Entergy would have had to liberate the stuck assemblies if the government had performed under the contract.
Entergy argues that had the government performed, there would have been enough space in the spent fuel pool to leave the stuck assemblies in place until the plant decommissioned. Tr. 269:5-271:10 (Wiggins). Therefore, had the government performed Entergy would not have incurred the cost of removing the stuck assemblies during this claims period. However, Entergy did not dispute the government's assertion that Entergy would have had to liberate the assemblies from the racks at some point at its expense if the government had performed.
Following the
Though the government is no longer contesting that Entergy is entitled to recover the above-noted amount of damages in connection with the SNF loading campaigns, the government still disputes that Entergy is entitled to $945,331 of the costs Entergy incurred during the 2011 loading campaign as a result of that campaign being delayed for approximately six weeks beyond Entergy's initial estimate. The costs of the delay include $387,301 in welding contractor standby costs paid to the contractor PCI Energy and $558,030 in standby costs for equipment that Entergy had leased from the contractor Transnuclear. The government states that these additional costs were either caused by Entergy's errors or unexplained, and therefore not proximately caused by the government's breach. Entergy counters that the delays and associated costs were reasonable and foreseeable consequences of the government's breach.
The Federal Circuit has held that a plaintiff may not recover damages that "could have been avoided by reasonable efforts."
At trial, Bob VanWagner, senior project manager at Entergy in charge of the 2011 loading campaign, testified that Entergy planned to begin the 2011 cask loading campaign on September 26, 2011, and anticipated that the campaign would be completed on November 4, 2011. Tr. 145:6-17 (VanWagner),
In addition to the delay in beginning the loading campaign, Mr. VanWagner testified the campaign was further delayed because of "incorrect programming of a fuel handling machine." Tr. 122:11-14 (VanWagner). Mr. VanWagner testified that Entergy loaded SNF into canisters provided by Transnuclear in both its 2008 and 2011 loading campaigns. Tr. 185:21-188:1 (VanWagner). However, between the 2008 and the 2011 campaigns, there was a change in the measurements of an element of the canister known as a "fuel spacer," which is designed to keep the assemblies at the correct height within the canister. Tr. 187:12-18 (VanWagner). Mr. VanWagner explained that the fuel spacer is approximately two feet long, and the difference between the 2008 and 2011 measurements was approximately 3/16 of an inch. Tr. 188:2-17 (VanWagner). However, given the "very tight parameters" for handling SNF, the difference in the fuel spacer's measurement was significant enough that Entergy's fuel handling machine had to be reprogrammed. Tr. 188:18-24 (VanWagner). According to Mr. VanWagner, Transnuclear did not bring the change in the canister design to Entergy's attention and no one at Entergy realized the fuel spacer length had changed. Tr. 186:23-188:22 (VamWagner). These delays pushed the campaign into the Thanksgiving and Christmas holidays, which further delayed the campaign. Tr. 153:12-20 (VanWagner). The campaign ultimately ended on December 15, 2011, Tr. 155:1-3 (VanWagner), six weeks after the scheduled end date of November 4, 2011. At trial, Mr. VanWagner testified that in his opinion, the delay was not abnormal and could have been anticipated:
Tr. 122:19-123:2 (VanWagner).
The government contends that it is not liable for the costs attributable to the delays in the 2011 loading campaign because the delays were caused by Entergy's own errors and therefore were not a reasonably foreseeable result of the government's breach. In this connection, the government relies on the testimony of Mr. Van Wagner who did not recall the reason for the start delay and conceded on cross-examination that the delay resulting from the program error was an "Entergy-caused delay," Tr. 160:9-12 (VanWagner). Further, the government notes that had Entergy followed the guidelines in its own dry fuel storage management manual, Entergy could have established that there had been a change in the measurements of Transnuclear's fuel spacer. The manual, dated October 14, 2010, states:
5.3 Spent Fuel/Dry Cask Loading Preparation Phase
PX 948 at 12, 15. Entergy's manual therefore anticipated that a vendor such as Transnuclear may have modified the design of a cask system and specifically instructed the project manager to discuss and review design changes with the vendor during the preparation phase of the spent fuel loading campaign. Further, the government notes that the same manual states that "[c]onsideration should be given to performing a Dry Run at the beginning of every campaign in an effort to minimize [radiation] dose and gain operational efficiency prior to the commencement of the loading campaign."
With respect to the two-week delay in the beginning of the campaign, the court must conclude that the delay was not reasonable when Entergy's witness could not give an explanation as to why delay occurred.
Further, the court finds that the government has met its burden of showing that the delay costs caused by Entergy's failure to note the change in the fuel spacer measurements were not reasonably foreseeable because, had Entergy followed its own protocols, the delay could have been avoided. At the time of the 2011 loading campaign, Mr. VanWagner was the Senior Manager for dry fuel storage and the person ultimately responsible for understanding the cask design specifications. PDX 2, Slides 3-5 (VanWagner); Tr. 149:5-12 (VanWagner). However, Mr. VanWagner stated that he did not review the documentation detailing the cask specifications provided by Transnuclear, which Mr. VanWagner acknowledged contained the correct measurements for the fuel spacer. Tr. 149:1-18 (VanWagner). Instead, the documents were reviewed by the fabrications engineer, who did not discover the change. Tr. 149:16, 188:25-189:13 (VanWagner). Though the change in measurements may have been small, it was evidently very significant when applied to the handling of nuclear material, which is precisely why Entergy's manual instructed the program manager to review design changes with the vendor.
In this regard, the court rejects plaintiff's contention that this case is similar to another SNF case,
The court therefore finds that the costs attributable to loading delays either were not adequately explained could have been avoided by reasonable efforts and thus are not recoverable.
The final category of damages associated with Entergy's 2011 dry fuel storage campaign concerns the $12,496 Entergy incurred in undertaking a structural review of the "track alley," a large room within the Palisades original auxiliary building that was designed to bring heavy equipment into the building. Tr. 805:18-24 (Lyon).
The court finds that the evidence Entergy presented at trial is sufficient to show that the track alley review was necessitated by the government's breach and would not have occurred if the government had not breached the Standard Contract. At trial, Alan Lyon, a senior engineer in the design engineering group within the civil/structural/mechanical section at Palisades, testified that the work that CTL performed would not have been performed but for the transition from the NUHOMS system to the Holtec system. Tr. 815:6-11 (Lyon). In addition, Mr. Lyons testified that Entergy did not avoid any routine monitoring or maintenance, because the Palisades plant already conducted structures monitoring of the same structures that CTL was hired to analyze. Tr. 817:23-818:2-17 (Lyon).
The government states that Entergy's own testimony confirms that the outside review of the track alley would have had to have been performed regardless of the government's breach because the concrete degradation was a safety concern. Def.'s PTB 32. However, as Mr. Lyon testified, Entergy was already aware of the general safety problems through their own internal monitoring system, and is not seeking compensation for repairs of the track alley. Mr. Lyon testified that CTL was hired to resolve a "relatively specialized analytical problem" by evaluating "the structure for any potential degradation that's occurred; also, to verify that the—the work that was being done analytically matched the design of the plant" in association with the transition from NUHOMS to Holtec casks, 809:1-810:12 (Lyon), and therefore did not abrogate the need for the Palisades internal structures monitoring program, which was also conducted. The government has not presented any evidence to contradict Entergy's assertion that CTL's analysis was performed in addition to, not instead of, any routine monitoring or maintenance at Palisades. Consequently, the court finds that these costs are recoverable.
Entergy's claims for additional security arise from the need to guard the second ISFSI at the Palisades plant. The government agrees that the second ISFSI was constructed to store SNF at Palisades as a result of the government's breach, and has agreed to pay the cost of its design and construction. Joint Stips. at ¶ 11. Pursuant to an agreement with the NRC, Entergy is required to staff two security posts dedicated to the second ISFSI 24 hours a day every day.
With respect to the government's first argument, the court finds that Entergy has met its burden of proof to show that the security posts were consistently staffed. At trial, the security manager at the Palisades during the claims period, David Berkenpas, testified that since April of 2011, Entergy has staffed two posts dedicated to the second ISFSI around the clock every day. Tr. 515:20-2 (Berkenpas). Mr. Berkenpas testified that security personnel at Palisades rotated through security posts approximately every two hours to combat fatigue, and that every security officer would have rotated through the two ISFSI posts. Tr. 522:2-24 (Berkenpas); PDX 4 Slide 20. Mr. Berkenpas stated that while Entergy creates shift rotation schedules which assign security officers to each of the posts for specific blocks of time during each shift, the schedules cannot be used to identify which security officer staffed a given post at all times during the claims period because the schedules are subject to change and are retained for only a few months.
The government argues that Entergy's evidence is insufficient to show that the posts were consistently staffed because Entergy was unable to demonstrate which employees were staffing each post at any given time. The government notes that on cross-examination, Mr. Berkenpas acknowledged that it would have been possible for officers to charge time spent monitoring the new ISFSI to a second work order, but that Entergy chose not to segregate time spent on the ISFSI from time spent on other security posts at Palisades.
The court finds that the uncontroverted sworn testimony of Entergy's security manager that Entergy complied with its obligations to the NRC and did in fact staff the two posts at the second ISFSI 24 hours a day, 365 days a year is sufficient proof that the posts were indeed staffed. Further, the court finds that Entergy was not required to produce evidence showing which security officer staffed each security post at all times during the two years the ISFSI was operational during the claims period. While collecting that data would have been possible, the court finds that it would have been costly and would not have had an effect on the security of the plant. Peter Sabo, the site finance manager at Palisades, estimated that he believed that changing the system to allow security officers to bill time specifically to the posts at the second ISFSI could cost as much as "three-quarters of a million dollars" and would not add value to the security system. Tr. 503:20-504:8 (Sabo). Therefore, it was reasonable for Entergy to treat staffing records for the two new security posts just as it had treated the records for previously-existing posts.
The government also argues that Entergy's trial evidence did not establish that the commitment of two new security posts resulted in an increase in total security costs to the extent claimed by Entergy. The government's expert calculated that there was a slight increase in hours worked after the addition of the two new security posts, but not enough to account for the amount that Entergy claims in costs associated with the two security posts. At trial, Mr. Berkenpas calculated that staffing the two posts 24 hours a day every day beginning in April of 2011 required 17,520 on-post hours during the claims period. Tr. 520:2-19 (Berkenpas). Because each security officer rotated through the two posts, Entergy calculated the cost of those hours using an average labor rate for security officers, and concluded that required 9.3 full time equivalent employees ("FTEs") to staff the two posts during the claims period. Tr. 520:14-18, 522:14-22 (Berkenpas). Mr. Berkenpas explained that the total number of security personnel did not immediately increase at the time the two posts were dedicated because Entergy initially did not hire additional personnel to staff the posts at the second ISFSI, but instead relied on overtime, which stressed personnel resources. Tr. 517:18-23 (Berkenpas); PDX 4 Slide 13. Mr. Berkenpas testified that had the second ISFSI not been built, the "total security cost at Palisades would be lower by 9.3 FTE." Tr. 517:9-15 (Berkenpas).
The court finds that Entergy has sufficiently proved its labor costs. The Federal Circuit has found that "to recover internal labor costs incurred in mitigation of the Government's breach, [a plaintiff] must prove that it did in fact use its own employees in its mitigation efforts, and the number of hours those employees spent on mitigation related projects."
In this case, the court has found that the evidence establishes that Entergy used its resources to staff two security posts at the new ISFSI all day every day and that Entergy would not have needed to secure the ISFSI but for the government's breach.
Further, with respect to the amount that Entergy is claiming in damages for the cost of staffing each post, the fact that the government's calculation of the cost of staffing one post ($630,217) was so close to the plaintiff's calculation ($629,603) demonstrates that Entergy has fulfilled its obligation to show with "reasonable certainty that the awarded costs were actually caused by the breach."
For the reasons stated above, the court finds in favor of the plaintiff with respect to its claims for costs related to the replacing the rack in the spent fuel pool at Palisades; the dry fuel storage loading costs the government now agrees it owes Entergy; the review of the track alley; and the additional security costs. The court finds in favor of the government with respect to Entergy's claims for costs associated with the liberation of spent fuel assemblies and the standby costs associated with delays in Entergy's dry fuel storage campaigns. Judgment shall be entered in favor of Entergy in the amount of $13,828.676.00.