THOMAS C. WHEELER, Judge.
This case is before the Court on remand from the United States Court of Appeals for the Federal Circuit to determine the proper amount of damages due Plaintiff Agility Defense & Government Services, Inc. ("Agility"). The Federal Circuit instructed this Court to calculate Agility's equitable adjustment arising from damages Agility incurred from performing in excess of its contract with Defense Reutilization Management Services ("DRMS") to dispose of surplus property received from the military services as troops were departing from areas of operation in Iraq, Afghanistan and Kuwait.
For the reasons explained below, the Court finds that Agility is entitled to a total equitable adjustment of $6,906,339.20, plus interest. The Court bases this conclusion on a finding that this calculation accurately captures the cost of additional, unanticipated work Agility had to perform on the contract as a result of DRMS' negligent estimates.
A detailed factual history of this case can be found in the Court's previous opinion in this matter.
The Defense Logistics Agency ("DLA") provides supplies to the military services and supports Department of Defense acquisition activities. Stip. ¶ 1. DRMS is a primary field activity of DLA.
Prior to 2007, the Government performed in-house all of the work relating to the receipt and processing of surplus property. Stip. ¶ 4. In December 2006, the Director of DRMS determined that the agency could not adequately support the surplus property functions in the future. Washington, Tr. 416-17. Agency management was concerned that the "planned movement of U.S. Military forces" would create more work than the agency could handle. JX 20 at 2. At that point, the agency decided to solicit and award an outside contract for this work. Stip. ¶ 4; Washington, Tr. 416-17.
On January 18, 2007, DRMS issued Solicitation No. SP4410-07-R-007 seeking a contractor to perform all surplus property disposition services at six locations in Southwest and Central Asia. Stip. ¶ 5; JX 2. The six locations were at Bagram, Afghanistan; Camp Arifjan, Kuwait; and Camps Anaconda, Victory, Al Asad, and Speicher, Iraq. JX 2. In Block 7 of the coversheet to the Solicitation, the Government explained:
Amendment 004 to the Solicitation contained a listing of the questions and answers between the agency and the offerors prior to the Preproposal Conference.
The agency's website contained historical workload information for each of the six DRMO locations covered by the contract. Washington, Tr. 421-22; Baker, Tr. 43. The agency updated the website's workload data on a regular basis. Washington, Tr. 422. The workload was measured by the weight of scrap processed and by the number of line items. Baker, Tr. 43, 47, 48. The website also showed the number of direct and contract staff members employed by DRMS at each location. Baker, Tr. 48; JX 50 at 3; JX 59 at 4; JX 66 at 4; JX 73 at 3; JX 76 at 4; JX 80 at 4. DRMS used the workload data for August 4, 2007 as the baseline when issuing delivery orders under the contract. JX 80 at 4.
Prior to 2007, Agility acquired Taos Industries, Inc., a small firm based in Huntsville, Alabama. Taos specialized in performing logistics contracts for the U.S. Government, but it had not previously operated a DRMO. Baker, Tr. 38. Agility hired three former DLA employees to provide expertise in preparing its proposal in response to the Solicitation, including the development of a Performance Work Statement ("PWS"). Baker, Tr. 39.
Agility was one of three offerors to submit a proposal in response to the Solicitation. Stip. ¶ 14. The agency's Source Selection Authority determined that Agility's proposal provided the best overall value to the Government. Agility's final price was $45,233,914.92. Baker, Tr. 68; JX 16 at 8. The final price reflected a $20,342,608.00 offset for revenues expected from scrap. JX 10 at 17. Agility's proposal was based upon a staffing plan of 174 persons. Baker, Tr. 40; JX 10 at 35-38.
DRMS notified Agility on November 29, 2007 that its proposal had been accepted for award. Stip. ¶ 16. The parties executed Contract No. SP4410-08-D-2000 ("the Contract") on the same day. JX 21. The Contract contained six line items, one for each of the DRMO locations, and each line item had a firm-fixed-price to be paid on a monthly basis.
The agency ordered work under the Contract by placing Delivery Orders for each DRMO site. Washington, Tr. 453. The initial Delivery Orders were issued in January and February 2008. The Delivery Orders incorporated the "workload baseline" for each DRMO site as reflected by the historical data in the website update for August 4, 2007. The agency calculated the monthly baseline from the August 4, 2007 website update by adding together the two figures for "Received Line Items," each for a one-week period, and then doubling the total to obtain the monthly line items. The baselines were as follows:
JX 50 at 3; JX 59 at 4; JX 66 at 4; JX 73 at 3; JX 76 at 4; JX 80 at 4; PX 114 at 2. The annualized baselines are derived simply by multiplying the monthly baseline by twelve.
From the beginning of performance, the actual workload experienced at each of the six DRMO locations, with the exception of Camp Speicher, Iraq, was much greater than the workload baselines established in the August 4, 2007 Historical Data. Mohr, Tr. 172; PX 114 at 1-3, JX 186 at 1-2. The actual annual workloads experienced from March 2008 to March 2009, by number of line items, were as follows:
In total, the pre-March 2009 workload for all six locations was 217.2 percent of the annualized workload derived from the single-month baseline provided in the Delivery Orders.
Agility began contract performance at Camp Arifjan, Kuwait, where more than 60 percent of the contract work would be performed. At Arifjan, Agility inherited a backlog of approximately 70,000 line items. Mohr, Tr. 168, 271; Burns, Tr. 556-57. In addition to the backlog, the volume of property received at Arifjan was greater than anticipated from the very beginning. Mohr, Tr. 172. Agility did not have the necessary staff in place to process both the backlog work and the higher than expected level of new work. Baker, Tr. 82-83; Mohr, Tr. 167.
In May 2008, Agility began performance at the other five DRMO locations. JX 166. Agility encountered backlogs at these locations as well, but not to the same extent as the Arifjan backlog. Burns, Tr. 559-60. To help with the additional workload, Agility hired 105 extra personnel, 66 of which were assigned to Camp Arifjan. Mohr, Tr. 180-81; JX 167. Agility also dispatched fifteen additional employees from its headquarters to improve Agility's performance. Mohr, Tr. 182. Agility understood that the initial number of staff assigned to the Contract was insufficient and that more employees would be needed. Mohr, Tr. 167, 224. Agility also noted that these increases in staffing would come "at no additional cost to the [G]overnment." JX 167 (email transmission).
Despite Agility's assertion that there would be no additional cost to the Government, Agility attempted to obtain the Government's consent to fund its additional personnel. Mohr, Tr. 174-75, 186, 314-17. The Government was aware that Agility had added extra staff and was processing work in excess of the Delivery Order baselines, but insisted that the requirements of clause H.19 had not been met. Mohr, Tr. 314-17. In order to warrant a funding adjustment, clause H.19 required an increase above 150 percent of the workload for the previous three months. Since the workload from the beginning of performance was high, there never was a time that the increase was above 150 percent. Agility did not submit a formal proposal to increase staff under clause H.19. Mohr, Tr. 296.
On November 13, 2008, the Government exercised the first option year. JX 31. In March 2009, after months of dialogue, the parties entered into a bilateral modification amending clause H.19 so it would apply whenever the workload was more than 25 percent above the fiscal year 2008 average for a given DRMO location. JX 35 at 2-3.
In the fall of 2009, Public Warehouse Company ("PWC"), the parent company of Agility, was accused of fraud against the United States, and PWC and its affiliates, including Agility, were barred from contracting with the Government. On June 30, 2010, the Government terminated the Contract for convenience. Stip. ¶ 23. On June 29, 2011, Agility submitted a claim for termination settlement costs in the amount of $2,194,509.56. JX 48 at 2. On December 20, 2012, the parties negotiated a settlement of this claim for $757,972.63.
Agility submitted two certified claims to the contracting officer, the first on January 31, 2012 for $4,359,071.79 covering the period April 1, 2008 through March 26, 2009, PX 114 at 1, and the second on February 6, 2012 for $1,602,148.67 covering the period March 27, 2009 through June 30, 2010, for the additional costs it incurred as a result of DRMS' negligent estimates. Dkt. No. 1, at Ex. 1 (13-97C). In addressing Agility's certified claims, the contracting officer issued two final decisions on June 14, 2012, finding that Agility was entitled to $236,363.93 on the first claim, but zero on the second claim. Agility timely appealed these final decisions to this Court on January 23, 2013 and February 5, 2013 respectively, and they were docketed as case numbers 13-55C and 13-97C. By order dated April 2, 2013, the Court consolidated these two actions for all purposes.
After conducting a three-day trial and hearing closing arguments, this Court held that DRMS' estimates were not negligent because they were based on accurate historical data and thus, Agility was not entitled to any damages.
Cases before this Court on remand are governed by the mandate rule.
Here, the Federal Circuit's mandate instructs this Court to calculate Agility's equitable adjustment resulting from damages it incurred from performing in excess of DRMS' negligent estimates.
As a preliminary matter, the Court will address the Government's argument that Agility is not entitled to an equitable adjustment. The Government primarily argues that Agility cannot prove it incurred compensable damages because Agility has failed to show that it relied on the information DRMS provided, Def.'s Br. at 13-14, and has failed to show that DRMS' negligence was the cause of its damages.
The Government also argues that the Federal Circuit's interpretation of clause H.19 limits any of Agility's damages to the first month of performance.
When the Government provides a negligent estimate and a contractor reasonably relies on that estimate to its financial detriment, an equitable adjustment is the proper remedy.
To prove damages under the actual cost method, the contractor must provide the court with specific, segregated documentation of the expenses caused by the Government's change.
Here, Agility has furnished the Court with ample evidence to satisfy the actual cost method. For its pre-March 2009 claim, Agility provides the Court with the following breakdown of costs for the additional labor needed to complete performance of the Contract:
Pl.'s Br. at 9. Agility likewise provides the Court with a similar breakdown for its post-March 2009 claim, after both parties bilaterally agreed to modify the Contract:
These additional costs accurately reflect the excess work Agility performed on the Contract as a result of DRMS' negligent estimates. As such, the Court finds that Agility has met its burden of proving reasonable damages using the actual cost method and is therefore entitled to a total equitable adjustment of $6,906,339.20, plus interest.
For the foregoing reasons, the Court finds that Agility is entitled to an equitable adjustment of $4,932,118.89 for its pre-March 2009 claim and $1,974,220.31 for its post-March 2009 claim, for a total damages award of $6,906,339.20, plus interest. The Court awards Agility interest from January 31, 2012 for its pre-March 2009 claim and from February 6, 2012 for its post-March 2009 claim.
IT IS SO ORDERED.