THOMAS C. WHEELER, Judge.
On May 25, 2018, the Court issued an Order granting the Government's motion to dismiss this consolidated bid protest, lifting the February 26, 2018 Preliminary Injunction ("PI"), denying Plaintiffs' motions for leave to file supplemental pleadings, and denying as moot Defendant-Intervenor Performant Recovery, Inc.'s motion for partial dismissal.
In this post-award bid protest, twenty plaintiffs challenge the Department of Education's ("ED" or "the Agency") decision to award debt collection contracts for defaulted student loans to awardees Performant Recovery, Inc. ("Performant") and Windham Professionals, Inc. ("Windham"). Each consolidated Plaintiff alleges that ED acted arbitrarily, capriciously, and without a rational basis in evaluating Plaintiffs' proposals and making its final award decision. This is the second round of bid protests related to the solicitation at issue, with the first round of protests dismissed by this Court on February 14, 2018, roughly a month after the Agency completed corrective action.
Between February 2, 2018 and February 16, 2018, Plaintiffs FMS Investment Corp., Account Control Technology, Inc., GC Services Limited Partnership, and Continental Service Group, Inc. filed motions for Preliminary Injunctions to enjoin ED from (1) proceeding with new contract awards under Solicitation No. ED-FSA-16-R-0009; and (2) recalling borrower accounts that the above-mentioned Plaintiffs are currently servicing under 2015 Award Term Extensions ("2015 ATE") to the July 2009 Private Collection Agency ("PCA") task orders as part of ED's contract transition to the new awards. The Government made multiple representations to the Court that ED had voluntarily agreed to stay its contract awards to Performant and Windham during the pendency of this bid protest, excluding appeal, and the Court granted part two of the preliminary injunction motions on February 26, 2018.
On March 2, 2018, Performant filed a motion to disqualify Pillsbury Winthrop Shaw Pittman LLP ("Pillsbury") as counsel for Plaintiff Continental Service Group, Inc. ("ConServe"), citing a concurrent conflict of interest because Performant is also a current client of Pillsbury—although not in this particular matter—and is directly adverse to ConServe in this litigation. Dkt. No. 110. The Court granted Performant's motion on March 23, 2018, Dkt. No. 160, and issued a more substantive Opinion on the disqualification issue on March 29, 2018. Dkt. No. 163.
On March 9, 2018, the Government produced the Administrative Record ("AR") in this case.
On May 7, 2018, the Government filed a motion to dismiss this bid protest and to lift the February 26, 2018 PI, arguing that ED's decision to cancel the solicitation rendered Plaintiffs' claims moot. Dkt. No. 189, at 1. Shortly thereafter, the following twelve Plaintiffs moved for leave to file supplemental pleadings under RCFC 15(d) to add claims that ED's decision to cancel the solicitation was arbitrary, capricious, and contrary to law: FMS Investment Corp. (Dkt. No. 214); Account Control Technology, Inc. (Dkt. No. 215); Texas Guaranteed Student Loan Corp. (Dkt. No. 221); Transworld Systems, Inc. (Dkt. No. 223); Gatestone and Co. International, Inc. (Dkt. No. 226);
On May 18, 2018, 17 parties, including Defendant-Intervenors Performant and Windham, filed formal responses to the Government's motion to dismiss.
On March 15, 2018, Defendant-Intervenor Performant filed a motion for partial dismissal of all counts in Plaintiffs' complaints that allege ED extended preferential treatment to Performant during the evaluation process because of Education Secretary Betsy DeVos' former financial ties to Performant. Dkt. No. 140. The parties concluded briefing Performant's motion on April 26, 2018, and the Court likewise deems oral argument unnecessary.
The Tucker Act grants this Court subject matter jurisdiction over bid protests. 28 U.S.C. § 1491(b)(1) (2012). In a bid protest, the Court reviews an agency's decision pursuant to the standards set out in the Administrative Procedure Act ("APA"). 28 U.S.C. § 1491(b)(4) (2012); 5 U.S.C. § 706 (2012). Under the APA, this Court shall set aside an agency action if it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. § 706(2)(A) (2012);
Even if the agency acted without a rational basis, the Court cannot grant relief unless the agency's action prejudiced the protestor.
In its motion to dismiss, the Government argues that ED's decision to cancel the solicitation at issue in this case has mooted Plaintiffs' protests. Courts have no subject matter jurisdiction over moot claims.
Although mootness is part of the "case or controversy" requirement in Article III of the United States Constitution,
For example, bid protest actions brought pursuant to this Court's jurisdiction under 28 U.S.C. § 1491(b)(1) may become moot if the government cancels the challenged procurement.
Here, ED has cancelled the solicitation at issue in this bid protest and terminated for convenience its contract awards to Performant and Windham. As such, Plaintiffs' complaints challenging ED's evaluation of proposals and award decisions are now moot. To the extent Plaintiffs argue that other counts in their complaints remain live, the Court has evaluated these arguments and find them to be without merit. Accordingly, the Court GRANTS the Government's motion to dismiss.
In its motion to dismiss, the Government also requests that the Court lift the February 26, 2018 PI entered in this case, which enjoined the Government from recalling in-repayment borrower accounts that Plaintiffs FMS Investment Corp., Account Control Technology, Inc., GC Services Limited Partnership, and Continental Service Group, Inc. are currently servicing under their 2015 ATEs to the July 2009 PCA task orders that were part of ED's contract transition to the now non-existent new awards.
The Court agrees with the Government that it can no longer maintain the February 26, 2018 PI, as the facts upon which the PI was predicated—mainly facts related the Court's concerns over ED's evaluation of proposals in this procurement—are no longer operative. Even if the Court were to allow the Moving Plaintiffs to file their supplemental claims protesting ED's cancellation decision, the Court would still have to conduct a new factual analysis under the PI factors to determine whether it could justify entering another PI in this case since the facts of this case have significantly changed. Moreover, the Government has indicated to the Court that ED will voluntarily stay any recall of these accounts until June 30, 2018, which allows Plaintiffs enough time to file new motions for TROs or PIs along with their new bid protests, should they decide to take this course of action.
In an attempt to cure the Court's jurisdictional deficiency over Plaintiffs' now moot claims, the Moving Plaintiffs argue that they should be allowed to file supplemental complaints asserting new counts that challenge ED's decision to cancel the solicitation at issue in this bid protest. To support their arguments, the Moving Plaintiffs rely primarily on
First, the four bid protest cases the Moving Plaintiffs rely on contained only one protestor, whereas this bid protest contains twenty. While it may be judicially efficient to allow a single protestor to supplement its pleadings instead of filing a new complaint, the same cannot be said in this case, which has already seen its fair share of complexity and entanglement. It would be highly inefficient for the Court to go back and individually dismiss the counts in each Plaintiff's complaint that do not relate to ED's cancellation of the solicitation; instead, it would be more efficient for the Court and the parties to start on a fresh slate of protests with clean, narrowly focused complaints centered on the cancellation issue alone.
Second, the very process the Moving Plaintiffs complain of that would result from having to file new complaints would still result even if this Court allowed the supplemental complaints to move forward: the Government would still have to produce an AR related to its cancellation decision, and the parties would still have to proceed with an MJAR briefing schedule. Instead of "complicating an already complicated" AR and docket, the Court again finds it more efficient for each party to file new bid protests, which will trigger the production of a clean, narrowly focused AR that does not contain information no longer relevant to the prospective protests.
Third, there will now be a significant realignment of parties in this bid protest, as former Defendant-Intervenors Performant and Windham will likely become protestors. What's more, it is unclear whether all Plaintiffs in this action will even file new protests or, alternatively, seek to intervene in support of a particular party. The Court sees little value in attempting to reshuffle the parties on the current docket when it can instead start on a clean slate to ensure certainty and to minimize confusion.
Finally, Plaintiff Automated Collection Services, Inc. has already notified the Court and the Clerk's Office that it intends to file a separate bid protest challenging ED's decision to cancel the solicitation.
For all these reasons, the Court DENIES the Moving Parties' motions for leave to file supplemental pleadings.
As the Court has explained above, ED's decision to cancel the solicitation has mooted all of Plaintiffs' claims and allegations in this case. Thus, Performant's motion for partial dismissal is likewise moot and DENIED accordingly.
For the reasons stated above, the Court GRANTS the Government's motion to dismiss, LIFTS the February 26, 2018 PI, DENIES Plaintiffs' motions for leave to file supplemental pleadings, and DENIES Performant's motion for partial dismissal as MOOT. As directed by the Court in its May 25, 2018 Order, the Clerk has dismissed Plaintiffs' complaints without prejudice.
IT IS SO ORDERED.