Elawyers Elawyers
Ohio| Change

New England Specialty Services, Inc. v. United States, 19-643 (2020)

Court: United States Court of Federal Claims Number: 19-643 Visitors: 2
Filed: May 26, 2020
Latest Update: May 26, 2020
Summary: In the United States Court of Federal Claims No. 19-643C (Filed: May 26, 2020) ) NEW ENGLAND SPECIALTY ) Contract claim; motion for summary SERVICES, INC., ) judgment; genuine issues of material fact ) Plaintiff, ) ) v. ) ) UNITED STATES, ) ) Defendant. ) ) Scott K. DeMello, Lepizzera & Laprocina Counsellors at Law, Warwick, RI, for plaintiff. Robert R. Kiepura, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant. Wit
More
             In the United States Court of Federal Claims
                                           No. 19-643C

                                      (Filed: May 26, 2020)

                                               )
 NEW ENGLAND SPECIALTY                         )      Contract claim; motion for summary
 SERVICES, INC.,                               )      judgment; genuine issues of material fact
                                               )
                        Plaintiff,             )
                                               )
        v.                                     )
                                               )
 UNITED STATES,                                )
                                               )
                        Defendant.             )
                                               )

       Scott K. DeMello, Lepizzera & Laprocina Counsellors at Law, Warwick, RI, for plaintiff.

        Robert R. Kiepura, Trial Attorney, Commercial Litigation Branch, Civil Division,
United States Department of Justice, Washington, D.C., for defendant. With him on the briefs
were Joseph H. Hunt, Assistant Attorney General, Civil Division, and Robert E. Kirschman, Jr.,
Director, and Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil
Division, United States Department of Justice, Washington, D.C. Of counsel was Theresa
Negron, Deputy District Counsel, New England District, United States Army Corps of
Engineers.

                                        OPINION AND ORDER

LETTOW, Senior Judge.

        This case presents a dispute over a design-build contract for the construction of a pre-
engineered metal building and related site work in Natick, Massachusetts for the United States
Army Corps of Engineers. Plaintiff, New England Specialty Services, Inc. (“NESS”), has
brought suit against the United States (“the government”), alleging, inter alia, breach of contract
and unreasonable delay. Pending before the court is defendant’s motion for summary judgment
(“Def.’s Mot.”), ECF No. 13. Plaintiff opposes this motion. See Pl.’s Resp. to Def.’s Mot.
(“Pl.’s Resp.”), ECF No. 14. Following the conclusion of briefing, see Def.’s Reply, ECF No.
15, a hearing was held on May 7, 2020, and the parties filed supplemental briefs on May 18,
2020, see ECF Nos. 20, 22.
                                        BACKGROUND 1

        On September 26, 2015, New England Specialty Services, Inc., was awarded a firm-fixed
price contract, Contract No. W912WJ-15-C-0032, to construct a storage warehouse located at the
U.S. Army Soldier Systems Center in Natick, Massachusetts. See Def.’s App. at 1-2. 2 The
project consisted mainly of two tasks: (1) constructing a pre-engineered metal building and (2)
site work which included installation of an electrical duct bank, concrete masonry units, grout,
and air curtains. See
id. at 3;
Compl. ¶ 11, ECF No 1. The contract provided for 425 calendar
days within which to complete the project following issuance of the notice of proceed, see Def.’s
App. at 1, making the required contract completion date December 3, 2016.

        NESS’s first project baseline schedule, including a critical path layout and narrative,
projected the completion date of the project to be August 3, 2016. See Pl.’s App. at 342. As the
project moved forward, however, numerous issues arose that caused the completion date to be
delayed. See, e.g.,
id. at 344
(noting an initial delay due to a flawed contract specification). The
project was not completed until February 16, 2017, 75 days later than the original contract
completion date, see Def.’s App. at 874, and 134 working days later than the original NESS
schedule completion date of August 3, 2016,
id. at 898.
At the heart of this dispute is whether it
is the government or NESS who is responsible for the delays and who, then, should bear the
associated costs.

        Relevant to plaintiff’s claims are six bilateral modifications that were issued while project
work was ongoing, which adjusted the scope of work under the contract. See Def.’s App. at 836-
68. Notably, the required contract completion date was not changed by these modifications.
Id. Most relevant
to the claims here are Modifications 3, 4, 5, and 6. Modification 3 related to
“various structural changes,”
id. at 844;
Modification 4 related to “electrical ductbank changes,”
id. at 847;
Modification 5 related to more “electrical changes,”
id. at 851;
and Modification 6
related to small structural and mechanical changes, see
id. at 863-64.
Each of these
modifications included release language noting that “the contract time is not affected,” “the
contract price is increased as stated . . . which reflects all credits due the Government and all
debits due the Contractor,” and “this adjustment constitutes compensation in full on behalf of the
Contractor and its Subcontractors and Suppliers for all costs and markups directly or indirectly
attributable [to] the change ordered [and] for all delays related thereto . . .” See
id. at 846,
849,
854, 865.



       1
         The following recitations do not constitute findings of fact by the court. Instead, the
recited factual elements are taken from the complaint and the parties’ briefs and attached
appendices.
       2
        Both plaintiff and defendant attached appendices to their briefs. Both appendices were
consecutively paginated. Defendant’s appendix will be cited as “Def.’s App. at [page number]”
and plaintiff’s appendix will be cited as “Pl.’s App. at [page number].”

                                                 2
        NESS submitted a certified claim to the contracting officer on April 25, 2018. See
id. at 869-900.
In its claim, NESS sought costs for schedule delays, costs for alleged changes in the
contract terms, including structural changes to the air curtain, painting of structural beams, an
additional support for an overhead door, additional as-built drawings, and preparation of claim
costs, as well as a rejection of liquidated damages threatened by the contracting officer’s
representative. See
id. at 874.
The contracting officer issued the final decision on these claims,
granting them only in part, on December 21, 2018. See Pl.’s App. at 338-52. 3 Subsequently,
NESS filed its complaint in this court seeking $542,105.86 in damages, inclusive of delay costs
and direct costs, and the release of its final payment as previously sought in the certified claim.
See Compl. at 15.

                                STANDARDS FOR DECISION

        The court shall grant summary judgment “if the movant shows that there is no genuine
dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Rule
56(a) of the Rules of the Court of Federal Claims (“RCFC”). A material fact is one that “might
affect the outcome of the suit.” Anderson v. Liberty Lobby, Inc., 
477 U.S. 242
, 248 (1986)
(interpreting Fed. R. Civ. P. 56). 4 A genuine dispute exists when the finder of fact may
reasonably resolve the dispute in favor of either party.
Id. at 250.
         The movant bears the burden of demonstrating the absence of any genuine disputes of
material fact, see Celotex Corp. v. Catrett, 
477 U.S. 317
, 322 (1986), and shall “cite[] to
particular parts of materials in the record, including depositions, documents, electronically stored
information, affidavits or declarations, stipulations . . . , admissions, interrogatory answers, or
other materials,” RCFC 56(c)(1)(A). The court may consider other materials in the record even
if not cited by the parties. RCFC 56(c)(3). “[T]he inferences to be drawn . . . must be viewed in
the light most favorable to the party opposing the motion.” Matsushita Elec. Indus. Co. v. Zenith
Radio Corp., 
475 U.S. 574
, 587 (1986) (quoting United States v. Diebold, Inc., 
369 U.S. 654
,
655 (1962)). If the record taken as a whole “could not lead a rational trier of fact to find for the
non-moving party, there is no ‘genuine issue for trial’” and summary judgment is appropriate.
Matsushita, 475 U.S. at 587
(quoting First Nat’l Bank of Ariz. v. Cities Serv. Co., 
391 U.S. 253
,
289 (1968)).




       3
        NESS was awarded $58,263.94 by the contracting officer. See Contracting Officer’s
Decision (Dec. 21, 2018) at 14-15, ECF No. 19. This amount has not been paid. Hr’g Tr. 8:17-
20 (May 7, 2020).
       4
        Because RCFC 56 mirrors Fed. R. Civ. P. 56, the rules should be interpreted in pari
materia.

                                                 3
                                           ANALYSIS

        In its motion for summary judgment, the government seeks summary judgment on all of
plaintiff’s claims, dividing them into four categories: (1) delay claimed before December 3,
2016; (2) delay claimed between December 3, 2016 and February 16, 2017; (3) direct costs
claimed for constructive changes to the contract; and (4) the liquidated damages claim. Def.’s
Mot. at 1. In its response, plaintiff argues mainly that “[t]here remain genuine issues of material
fact concerning [its] claims,” and therefore, “the [g]overnment’s [m]otion for [s]ummary
[j]udgment must be denied.” Pl.’s Resp. at 23 (heading). The court concurs that genuine issues
of material fact exist that prevent a grant of summary judgment.

         The government argues that NESS cannot recover for delay claimed before December 3,
2016 because “the maximum number of delay days that a contractor may recover is the number
of days that work continued on the project after the contract completion date.” Def.’s Mot. at 11
(emphasis in original) (citing Mega Constr. Co., Inc. v. United States, 
29 Fed. Cl. 396
, 426
(1993)). This argument, however, fails to account for the precept that “[a] contractor may
recover damages for government-caused delay to the contractor’s early completion of
performance if the contractor establishes that it could realistically complete the project early.”
Weaver-Bailey Contractors, Inc. v. United States, 
24 Cl. Ct. 576
, 578 (1991) (citation omitted).
This issue thus presents two factual questions—whether delay was caused by the government
and, if so, whether NESS can show that it could have completed the project early. These are
genuine disputes that cannot be resolved on summary judgment, particularly when viewing the
facts most favorably to plaintiff. By way of example, plaintiff’s initially proposed schedule, see
Pl.’s App. at 342, serves as “contemporaneous documentation of its planned early completion,”
Jackson Constr. Co., Inc. v. United States, 
62 Fed. Cl. 84
, 98 (2004) (citation omitted), that
suffices to show that plaintiff could potentially be entitled to delay costs prior to December 3,
2016.

         Similarly, genuine issues of material fact remain with regard to delay costs claimed by
plaintiff for the time period between December 3, 2016 and February 16, 2017. The government
makes two main arguments as to why it is entitled to summary judgment, but these are
unpersuasive. Citing no precedent, the government first argues that because NESS signed
Modification 6, agreeing to maintain December 3, 2016 as the contract completion date, on
November 17, 2016, any alleged causes of delay prior to this date may not form the basis for a
claim. See Def.’s Mot. at 13. But merely because NESS agreed in Modification 6 not to alter
the contract completion date does not supersede its claims for earlier delay. NESS may have
logically believed, when it agreed to the terms of Modification 6, that only the changes within
the scope of modification 6 did not alter the construction timeline—that is not the same as a
blanket agreement that no issues before that modification altered the expected completion date.
What NESS accepted in Modification 6 is a question of fact that has not been resolved, and that
is just the point. There is a material dispute as to the scope of the several cited modifications,
that is, their proper subject matter, and the intent of the parties in agreeing to them, that is,
whether there was a meeting of the minds regarding the releases. See generally Meridian Eng’g
Co. v. United States, 
144 Fed. Cl. 667
(2019). These factual questions would not be
appropriately resolved on summary judgment. See Meridian Eng’g Co. v. United States, 885
                                                 
4 F.3d 1351
, 1356 (Fed. Cir. 2018) (remanding to the trial court to make factual findings about an
accord and satisfaction defense).

        The government’s second argument as to the delay claims is that even though the air
curtains were completed following Modification 6, NESS cannot claim delay from this work
because this delay was not on the critical path. However, plaintiff’s claims relating to the air
curtain work are not limited to that part of the work which was completed after February 2017
when the government occupied the building, as the government claims, see Def.’s Mot. at 14, but
instead allege that the government’s indecisiveness about the air curtains throughout the project
and dating back at least as early as November 2016 led to the delay, see Pl.’s Resp. at 7. Thus,
there is some evidence to suggest that the air curtain work could have been on the critical path
for the project. This is a question of material fact that is disputed by the parties, see Def.’s Mot.
at 14-15; Pl.’s Resp. at 7, and like the others, is not properly resolved on summary judgment.

        With regard to defendant’s argument that plaintiff cannot recover damages for direct
costs or constructive changes, factual issues are also present. Defendant argues that “NESS’s
claims for change costs are barred by the doctrine of accord and satisfaction via either the
contract or the [release language in the] modifications.” Def.’s Mot. at 15. As with the delay
claims, the court must resolve the material factual disputes about the scope of the contract and of
the modifications and whether there was a meeting of the minds before a ruling can be made.
Therefore, summary judgment would be inappropriate.

        Lastly, defendant seeks summary judgment on plaintiff’s claims for liquated damages
because “liquidated damages were never assessed.” Def.’s Mot. at 19. The government is
correct that the contracting officer never assessed liquidated damages, and, correspondingly,
none have ever been assessed against NESS. Defendant, however, represented to the court that it
does not believe it is “bound by the decision of the contracting officer.” Hr’g Tr. 9:3-4 (May 7,
2020). Despite the fact that the decision of the contracting officer includes the conclusion that
“no liquidated damages will be withheld or assessed,” Contracting Officer’s Decision at 15, ECF
No. 19, the court cannot accept that this issue has been factually resolved. As such, a material
factual dispute remains.

                                          CONCLUSION

        For the reasons stated, defendant’s motion for summary judgment is DENIED. Genuine
disputes of material fact exist regarding all of plaintiff’s claims, and are not limited merely to
those identified in this opinion. 5 The court requests that the parties file a joint status report by
June 19, 2020, with a proposed schedule for further proceedings in this case.



       5
         The motion by NESS for discovery to support its opposition to defendant’s motion for
summary judgment, ECF No. 21 (filed May 18, 2020), is DENIED as moot. Defendant filed an
answer on August 29, 2019, and, with the denial of defendant’s motion for summary judgment,
the parties may engage in further discovery as a matter of course.
                                                 5
It is so ORDERED.

                        s/Charles F. Lettow
                        Charles F. Lettow
                        Senior Judge




                    6

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer