TENA CAMPBELL, District Judge.
On June 11, 2010, in the foothills of Salt Lake City, Utah, approximately 800 barrels of crude oil leaked from a pipeline owned by Chevron Pipe Line Company (CPL) into Red Butte Creek and migrated into the Liberty Park pond. The Pipeline and Hazardous Materials Safety Administration (PHMSA) investigated and concluded that an electrical arc from an electrical transition station owned by Rocky Mountain Power (RMP) created a hole in the pipeline which caused the oil to leak. PHMSA imposed penalties on CPL. CPL paid the fines and conducted a costly cleanup.
Approximately sixty homeowners along the path of the spill sued CPL and RMP for damages. CPL and RMP filed claims against each other. Now that the original plaintiffs have settled, CPL seeks payment from RMP on the theory that RMP's negligence caused all or part of the costs that CPL incurred responding to the spill.
Trial is not on the horizon. But RMP has moved
The investigative reports and orders were created in connection with PHMSA's investigation of the oil spill. CPL, the subject of the investigation, opposes admission of the evidence on the basis that the documents do not satisfy the elements of Rule 803(8) and, under Federal Rule of Evidence 403, any probative value the documents may have is outweighed by the danger of unfair prejudice, confusion of the issues, and misleading the jury.
For the reasons set forth below, the court holds that the PHMSA Documents are admissible under Rule 803(8) with the caveat that redactions within those documents may be necessary to avoid other potential evidentiary problems. Possible curative measures may be addressed shortly before trial begins.
The Executive Summary of the PHMSA investigative report states that "[a] large electrical charge was introduced to a fence directly over Chevron's pipeline. The charge jumped from a metal fence post to Chevron's pipeline causing an ~1" hold in the fence post and an ~1/2" hold near the 12:00 position on the pipe. The leak occurred near a small creek that runs through a high density populated area. The crude followed the creek to a pond where most of it was captured." (Apr. 14, 2011 PHMSA Failure Investigation Report at 2, Ex. E to RMP's Rule 104 Mot., Docket No. 123.)
The day after the spill, PHMSA, as part of its regulatory responsibilities, began investigating the cause of the spill and whether CPL had violated regulations that govern pipelines. As part of the United States Department of Transportation, PHMSA is authorized by statute to regulate gas pipeline facilities. It does not regulate electrical facilities such as the one from which the electrical arc originated.
Over the course of PHMSA's investigation and subsequent enforcement action against CPL, it created four documents that RMP now asks the court to admit into evidence. Those documents (the "PHMSA Documents" or "Documents") were created between October 2010 and April 2011:
(
The following is a summary of the documents. Significantly, PHMSA's findings and conclusions about CPL's conduct did not substantively change from the initial report to the final report, as is evident from the document descriptions below.
PHMSA drafted this report (the Violation Report) soon after it completed its investigation. The Violation Report summarizes facts gathered during that investigation (both from on-site investigation and review of CPL documents, such as internal policies and procedures). It lists four violations, the regulations that were violated, the evidence supporting each finding of a violation, the action that resulted in the violation, and the proposed action for each violation.
PHMSA concluded that CPL violated 49 C.F.R. § 195.402, titled "Procedural manual for operations, maintenance, and emergencies," which reads as follows:
According to PHMSA, CPL violated the regulation because it did not follow the procedure for patrolling its pipeline right-of-way. PHMSA proposed a civil penalty and issuance of compliance order.
PHMSA maintained that CPL violated 49 C.F.R. § 195.575, titled "Which facilities must I electrically isolate and what inspections, tests, and safeguards are required?" That regulation requires that:
According to PHMSA, CPL violated the regulation because it "did not install any devices to protect the pipeline against damage from fault currents." (Violation Rep. at 10.) PHMSA proposed a civil penalty and compliance order.
PHMSA contended that CPL violated 49 C.F.R. § 195.452, titled "Pipeline integrity management in high consequence areas," which includes the following language:
According to PHMSA, CPL violated the regulation because
(
PHMSA contended that CPL violated 49 C.F.R. § 195.250, titled "Clearance between pipe and underground structures." That regulation reads:
According to PHMSA, CPL violated the regulation because "Chevron's Crude Oil #2 pipeline had a fencepost installed within 3 inches of it." (
In this document, PHMSA noted that Chevron did not challenge the contents of the Violation Report. Based on that lack of opposition, PHMSA issued the final order, and the proposed penalties became final.
This document is a wrap-up, or summary, of the investigation.
After PHMSA issued its Final Order, CPL paid the penalties. CPL also cleaned up the contaminated site. After CPL settled with private litigants, it pursued its action against RMP, alleging negligence and seeking reimbursement for some, if not all, of the cleanup costs. RMP made a similar claim against CPL, arguing that CPL's negligence caused the damage. Now RMP asks the court to adjudicate the admissibility of the four documents described above.
The key issues in this case are whether CPL was negligent, whether RMP was negligent, and, if so, the relative fault of CPL and RMP. This case is not nearing trial (in fact, no trial date has been set). But RMP has raised a preliminary question about the admissibility of the four PHMSA Documents. Under Rule 104 of the Federal Rules of Evidence, "[t]he court must decide any preliminary question about whether . . . evidence is admissible." Fed. R. Evid. 104(a). According to RMP, "[a] determination on admissibility will clarify issues for discovery and expert preparation, make trial preparation more focused, and inform potential settlement discussions." (Rule 104 Mot. at ii.) To that end, RMP asks the court to hold that the PHMSA Documents are admissible under Federal Rule of Evidence 803(8), "Public Records.
RMP asserts that the documents are admissible under Rule 803(8) of the Federal Rules of Evidence, also known as the "Public Records" exception to the rule against the admissibility of hearsay evidence. Under that exception, a "record or statement of a public office" is admissible in a civil case if "it sets out . . .
Under the first element of Rule 803(8), the party offering the document into evidence must show that the document was issued by a public office or agency and contains factual findings resulting from a legally authorized investigation.
The parties do not dispute that PHMSA is a public agency that conducted a legally authorized investigation. The Pipeline Safety Act grants the Department of Transportation (DOT) authority to prepare and issue evaluative reports, like the PHMSA Documents.
49 C.F.R. § 190.203(a) (emphasis added). Accordingly, federal law authorizes PHMSA to inspect pipeline accidents and issue documents—like the PHMSA Documents—in response to these accidents.
CPL asserts that the Documents are inadmissible because they contain opinions and conclusions. Although the Documents do contain conclusions and opinions, the United States Supreme Court holds that because such conclusions are based on facts that were established as part of an investigation, they are "factual findings" under Rule 803(8). In
The Tenth Circuit has also "admitted conclusions and opinions found in evaluative reports of public agencies" under Rule 803(8). In
Here, PHMSA's Documents are based on facts gathered during PHMSA's investigation of the oil spill. Under
Courts consider a non-exclusive list of factors to determine whether a document is trustworthy. The Advisory Committee for the Federal Rules of Evidence suggests four criteria: "the timeliness of the investigation; the special skill or experience of the investigator; whether a hearing was held and the level at which it was conducted; and any possible motivation problems in the preparation of the report."
CPL, as the opponent of the evidence, has the burden of showing "that the source of information or other circumstances indicate a lack of trustworthiness." Fed. R. Civ. P. 803(8)(B);
Looking at the first factor, the court finds that the timeliness of the investigation does not pose a problem here. And the parties do not dispute that. The PHMSA issued its initial report (the Violation Report) approximately four months after the oil spill. It is clear from that report that PHMSA inspectors were on site one day after the spill. (
As for the second factor, it is not disputed that PHMSA is the federal agency charged with overseeing pipeline safety issues, including CPL's pipeline. But CPL contends that "there is no evidence that the PHMSA employees involved in the investigation are qualified to opine" on what CPL identifies as the "key issue in this case": the "relative fault of CPL and RMP." (CPL Mem. Opp'n to Rule 104 Mot. at 13, Docket No. 133.) CPL's argument misses the mark because the factual findings and conclusions in the Documents do not address issues of negligence or relative fault. They address whether the facts within the scope of the agency's jurisdiction show a violation of DOT regulations. This factor does not weigh in CPL's favor either.
Pointing to the third factor—the availability of a hearing—CPL contends that the lack of a formal hearing is reason for the court to find the Documents untrustworthy. CPL also asserts that even if a hearing had been held before the PHMSA, such a hearing would not have been sufficient to establish trustworthiness of the Documents because CPL would not have been able to cross-examine authors of the reports or apply formal rules of evidence. CPL's argument is not persuasive.
Lack of a hearing is not necessarily dispositive of a report's trustworthiness.
Even if CPL had followed through with an administrative hearing without the full host of procedural safeguards typically present in a court setting, the lack of cross-examination would not render the Documents untrustworthy. The court in
Along similar lines, CPL contends that, even if the Documents are admissible under Rule 803(8), the written opinions and conclusions of PHMSA employees are inadmissible. According to CPL, the Documents are "`only admissible to the extent that the maker of [the] document could testify to that evidence were he present in court.'" (CPL's Opp'n Mem. at 11 (quoting
CPL's argument is foreclosed because Rule 803(8) does not require the declarant to testify about the contents of the document. Section 9.9(c) has no bearing on the court's determination of admissibility. The court also notes that the regulation was issued before the statute allowing the PHMSA documents to be used in private litigation (
Another factor courts consider is whether the motivation for issuing the documents is questionable. Neither party raises bias as an issue, so the court will only briefly address this factor. Bias can indicate lack of trustworthiness. "By bias the courts and the Advisory Committee [of the Federal Rules of Evidence] refer principally to reports compiled in anticipation of litigation."
Finally, CPL asserts that two of the PHMSA Documents—the Violation Report and the Probable Violation Notice—are preliminary and so are not trustworthy. The only language in the Violation report that is tentative is the term "Proposed Action." But that does not mean the information in the report is unsettled. The facts were settled and there was nothing left to investigate. In the Probable Violation Notice, PHMSA told CPL that PHMSA had determined that CPL had violated four different regulations. Because PHMSA allowed CPL an opportunity to contest the factual findings and conclusions, PHMSA could not officially conclude at that point that the violations had occurred. But CPL's waiver of its opportunity to contest essentially finalized PHMSA's tentative conclusion that CPL violated four regulations.
Numerous courts have held that a report is trustworthy even though it is called a preliminary or interim report.
CPL cites to an unreported decision,
For all of the reasons set forth above, the court finds that the PHMSA Documents are trustworthy. CPL has not satisfied its burden to provide affirmative evidence of untrustworthiness. Accordingly, the PHMSA Documents are admissible under Rule 803(8).
CPL argues that even if the documents are admissible under Rule 803(8), they should be excluded under Federal Rule of Evidence 403. "The court may exclude relevant evidence if its probative value is substantially outweighed by a danger of one or more of the following: unfair prejudice, confusing the issues, misleading the jury, undue delay, wasting time, or needlessly presenting cumulative evidence." Fed. R. Evid. 403.
CPL says the probative value of the Documents is negligible because they do not evaluate the relative fault of CPL and RMP, PHMSA did not investigate or make any findings about RMP's role in the incident, and evidence contained in the Documents can be presented to the jury in another form. "For example, RMP may offer copies of CPL's right of way inspection procedures into evidence to show their existence and terms. And it may call CPL's representatives to testify at trial on whether or how CPL complied with those procedures." (CPL Opp'n Mem. at 7.) But, as RMP points out,
(RMP Reply Mem. at 11-12, Docket No. 148.)
CPL maintains that any probative value the Documents may have is outweighed by the danger of unfair prejudice. According to CPL, the Documents will "mislead the jury into believing that a government agency found CPL solely liable for the spill," (CPL Opp'n Mem. at 6), and would suggest to the jury that it should reach the same conclusion reached by PHMSA's experts. But RMP persuasively counters CPL's concern: "the PHMSA Documents contain no analysis of relative fault or of RMP's conduct, nor would a jury draw such a conclusion from them. The PHMSA Documents contain factual findings relating to CPL's conduct. CPL can and will present evidence of its claims of negligence on the part of RMP and argue relative fault, and there is little risk of jury confusion." (RMP Reply Mem. at 15.)
CPL expresses concern that PHMSA was charged with focusing exclusively on CPL's conduct, so the Documents are an incomplete picture of the situation:
(CPL Opp'n Mem. at 8.) But the limitations identified by CPL can be countered sufficiently to avoid any unfair prejudice. Nothing in the PHMSA Documents forecloses's CPL's right to present admissible evidence that rebuts findings in the PHMSA documents. CPL can also argue to the jury that the PHMSA Documents tell only one side of the story and that RMP's actions led to the oil spill.
In short, the probative value of the PHMSA Documents is not outweighed by any prejudice they may pose. Nevertheless, the court will allow the parties to submit proposed redactions right before trial to address other evidentiary concerns—such as double hearsay—as well as a proposed cautionary instruction to the jury,
For the reasons set forth above, the court holds that the following documents are admissible at trial, with the caveat that redactions and a jury instruction may be necessary to reduce other evidentiary concerns: (1) PHMSA Pipeline Safety Violation Report, dated October 20, 2010; (2) PHMSA Notice of Probable Violation, dated November 1, 2010; (3) PHMSA Final Order, dated February 17, 2011; and (4) PHMSA Failure Investigation Report, dated April 14, 2011.
Where investigators rely on hearsay and non-hearsay in compiling a report, the court may review and edit certain portions of the report, rather than excluding the entire exhibit. Edited portions of the report remain admissable [sic] because Rule 803(8) attaches an assumption of trustworthiness to the government investigation as a whole. Courts have admitted exhibits to accident investigation reports on this basis."