Filed: Oct. 26, 2018
Latest Update: Oct. 26, 2018
Summary: ORDER CURTIS V. G MEZ , District Judge . On October 24, 2018, the Court held an evidentiary hearing in this matter. At the conclusion of that hearing, the Court held a post-hearing conference in chambers. At that conference, the parties agreed that there was a need to provide meaningful and complete information regarding: (1) the Tier 2 Analysis that is to be performed at the Anguilla and Bovoni landfills; (2) whether approval from the U.S. Army Corps of Engineers is required prior to comp
Summary: ORDER CURTIS V. G MEZ , District Judge . On October 24, 2018, the Court held an evidentiary hearing in this matter. At the conclusion of that hearing, the Court held a post-hearing conference in chambers. At that conference, the parties agreed that there was a need to provide meaningful and complete information regarding: (1) the Tier 2 Analysis that is to be performed at the Anguilla and Bovoni landfills; (2) whether approval from the U.S. Army Corps of Engineers is required prior to compl..
More
ORDER
CURTIS V. GÓMEZ, District Judge.
On October 24, 2018, the Court held an evidentiary hearing in this matter. At the conclusion of that hearing, the Court held a post-hearing conference in chambers. At that conference, the parties agreed that there was a need to provide meaningful and complete information regarding: (1) the Tier 2 Analysis that is to be performed at the Anguilla and Bovoni landfills; (2) whether approval from the U.S. Army Corps of Engineers is required prior to completion of the Bovoni road reconstruction project; and (3) the status of Federal Aviation Administration ("FAA") concurrence on the Anguilla landfill expansion.
The premises considered, it is hereby
ORDERED that an evidentiary hearing in this matter is SCHEDULED to begin promptly at 9:00 A.M. on November 27, 2018; it is further
ORDERED that the parties' shall SUBMIT briefs addressing: (1) the Tier 2 Analysis that is to be performed at the Anguilla and Bovoni landfills; (2) whether approval from the U.S. Army Corps of Engineers is required prior to completion of the Bovoni road reconstruction project; and (3) the status of FAA concurrence on the Anguilla landfill expansion no later than 3:00 P.M. on November 14, 2018; it is further
ORDERED that the Government of the Virgin Islands shall, through such process as is necessary, procure the attendance at the evidentiary hearing scheduled for November 27, 2018, of such FAA and Port Authority officials that can testify regarding the status of FAA concurrence regarding the Anguilla expansion project.