Filed: Dec. 16, 2008
Latest Update: Mar. 03, 2020
Summary: STATE OF VERMONT ENVIRONMENTAL COURT } In re: Three Church Street } Docket No. 22-2-06 Vtec In re: Three Church Street Act 250 Permit } Docket No. 174-7-06 Vtec (Appeals of Hummel) } } Decision and Order on Pending Motions In Docket No 22-2-06 Vtec, Appellants Kermit and Barbara Hummel appealed from a January 2006 decision of the Development Review Board (DRB) of the Village of Woodstock, approving an application by Applicant The Lauren Group, LLC relating to an inn at Three Church Street in Woo
Summary: STATE OF VERMONT ENVIRONMENTAL COURT } In re: Three Church Street } Docket No. 22-2-06 Vtec In re: Three Church Street Act 250 Permit } Docket No. 174-7-06 Vtec (Appeals of Hummel) } } Decision and Order on Pending Motions In Docket No 22-2-06 Vtec, Appellants Kermit and Barbara Hummel appealed from a January 2006 decision of the Development Review Board (DRB) of the Village of Woodstock, approving an application by Applicant The Lauren Group, LLC relating to an inn at Three Church Street in Wood..
More
STATE OF VERMONT
ENVIRONMENTAL COURT
}
In re: Three Church Street } Docket No. 22-2-06 Vtec
In re: Three Church Street Act 250 Permit } Docket No. 174-7-06 Vtec
(Appeals of Hummel) }
}
Decision and Order on Pending Motions
In Docket No 22-2-06 Vtec, Appellants Kermit and Barbara Hummel appealed
from a January 2006 decision of the Development Review Board (DRB) of the Village of
Woodstock, approving an application by Applicant The Lauren Group, LLC relating to
an inn at Three Church Street in Woodstock. In Docket No. 174-7-06 Vtec, Appellants
appealed from a decision of the District #3 Environmental Commission granting Act 250
Land Use Permit #3W0956 to The Lauren Group, LLC relating to the same property,
and denying Appellants’ motion to alter that decision. Both matters were disposed of by
a consent order entered on July 25, 2007 (the 2007 Settlement Order).
Appellants are represented by J. Christopher Callahan, Esq.; Appellee-Applicants
The Lauren Group, LLC and its manager Jack Maiden are represented by Thomas
Hayes, Esq.; and the Village of Woodstock is represented by Todd C. Steadman, Esq.
In the Act 250 appeal only, the Agency of Natural Resources is represented by
Catherine Gjessing, Esq.
The Lauren Group, LLC, has moved under V.R.C.P. 60(b) for relief from one
requirement of the 2007 Settlement Order. Appellants have moved for Contempt or for
Sanctions to enforce the entirety of the same order. Neither the Village nor ANR have
submitted memoranda on the pending motions. In a third case, on inactive status
pending the resolution of the present motions, Docket No. 111-6-08 Vtec, the Village
brought an enforcement action against The Lauren Group, LLC.
1
The 2007 Settlement Order contained conditions in paragraphs numbered 2, 3,
and 4, requiring Applicant to move an existing kitchen exhaust vent to a specified
location by May 1, 2008; allowing Applicant to hold no more than four events per
calendar year in excess of 33 people, conditioned as provided in an attached schedule;
and incorporating all conditions, not inconsistent with the settlement, imposed by the
two municipal permits at issue in Docket No. 22-2-06 Vtec, and the Act 250 Land Use
Permit at issue in Docket No. 174-7-06 Vtec.
In its present motions, Applicant has moved under V.R.C.P. 60(b) for relief from
paragraph 2 of the Order, which contains the conditions concerning the relocation of the
exhaust vent, and has also requested “relief to locate the vent either where it is now
located or at the same location, but elevated.” Appellants have moved for contempt
and sanctions based on Applicant’s failure to move the exhaust vent to the specified
location by May 1, 2008.
A motion under Rule 60(b) is the appropriate method for a party to seek relief
from a stipulated settlement agreement that is incorporated into a final judgment.
Johnston v. Wilkins,
2003 VT 56, ¶ 8,
175 Vt. 567 (mem.). V.R.C.P. 60(b) allows a Court
to grant relief from a final judgment or order, upon motion and “upon such terms as are
just,” for reasons of:
(1) mistake, inadvertence, surprise, or excusable neglect; (2) newly
discovered evidence . . . ; (3) fraud . . . , misrepresentation, or other
misconduct of an adverse party; (4) the judgment is void; (5) the judgment
has been satisfied, released, or discharged, . . . or it is no longer equitable
that the judgment should have prospective application; or (6) any other
reason justifying relief from the operation of the judgment.
In the present motion, Applicant has moved for relief under V.R.C.P. 60(b)(6).
Rule 60(b)(6) is “intended to ‘prevent hardship or injustice and thus [is] to be liberally
construed and applied.’” Sandgate Sch. Dist. v. Cate,
2005 VT 88, ¶ 7,
178 Vt. 625
(mem.) (quoting Estate of Emilo,
146 Vt. 421, 423–24 (1985)).
2
Despite this liberal construction, there are circumstances in which the “interests
of finality limit when relief is available” under Rule 60(b)(6). Riehle v. Tudhope,
171 Vt.
626, 627 (2000) (mem.) (citing Tudhope v. Riehle,
167 Vt. 174, 178 (1997)). Rule 60(b)(6)
should not be used to relieve a party from “an ill-advised tactical decision or from some
other free, calculated, and deliberate choice of a party.”
Id. (citing Richwagen v.
Richwagen,
153 Vt. 1, 3–4 (1989)). Nor is Rule 60(b)(6) relief appropriate when the
movant is at fault or has failed to prevent the circumstances which allegedly justify the
relief sought. McCleery v. Wally’s World, Inc.,
2007 VT 140, ¶ 12 (mem.) (citing 12 J.
Moore, et al., Moore’s Federal Practice § 60.48(3)(b), at 60-188).
Unlike motions for relief under subsections (1)–(3) of V.R.C.P. 60(b), which must
be filed within one year after judgment, Rule 60(b)(6) motions have no time limit, as
long as they are filed “within a reasonable time” after judgment. See Kellner v. Kellner,
2004 VT 1, ¶ 12,
176 Vt. 571 (mem.). Rule 60(b)(6) cannot be used to avoid the time
limitation imposed on motions filed for the reasons set forth in subsections (1) through
(3) of the Rule. See Juster v. Juster,
2007 VT 111, ¶ 4,
182 Vt. 622 (mem.) (citing
Alexander v. Dupuis,
140 Vt. 122, 124 (1981)).
Applicant’s motion was filed on July 29, 2008, one business day after the
expiration of one year from the entry of the 2007 Settlement Order. However, it does
not fall within the other listed subsections of Rule 60(b) and is therefore not barred by
the one-year limitation.
Applicant argues that relief from judgment is justified because the action
required by paragraph 2 of the Settlement Order is “not physically possible.”1
Paragraph 2 requires the exhaust vent to be relocated “behind an existing chimney on
1
A stipulated agreement is an “’independent contract’” over which the Court has
jurisdiction, see Lussier v. Lussier,
174 Vt. 454, 456 (2002) (mem.) (quoting Manosh v.
Manosh,
160 Vt. 634, 634 (1993) (mem.)), making a request for relief analogous to the
defense of ‘impossibility of performance’ in contract law. See generally 17A Am. Jur. 2d
Contracts §§ 655–683.
3
the main roof.” However, Applicant has not, or has not yet, made a showing that
relocation of the vent is not physically possible. Rather, in discussions with the vent
contractor, Applicant became aware that the stipulated location does not conform to fire
code regulations, which require a through-roof vent (such as the exhaust vent at issue
here) to be located at least ten feet from any existing chimney. Applicant argues that
locating it at the required distance would eliminate a second-floor guest room and
“impinge on the viability of a third-floor room,” which it describes as “not an option”
due to other considerations.2 Applicant argues that its possible alternatives are to keep
the vent at its current location, to raise it higher at its current location, or to run the vent
where the chimney is now located,3 which would require design review approval.
Applicant requests to be allowed to keep the vent in its current location or to raise it
higher in its current location.
Relief from the requirement that the vent be placed in the agreed location is
justified by the conflicting fire code requirement; however, such relief does not warrant
approval of any alternative location or approval of the original location. Rather, as this
court explained in In re Appeal of Cumberland Farms, No. 196-9-02 Vtec, slip op. at 5
(Vt. Envtl. Ct. Apr. 18, 2008) (Wright, J.):
Relief from one aspect of a stipulation . . . without vacating the
remainder of the stipulation . . . is particularly disfavored because “the
granting of partial relief alters the parties’ original agreement and
generally causes one of the parties to bear the burdens of the agreement
while foregoing its benefits.” Hood v. Hood,
146 Vt. 195, 197 (1985).
2 The number of seats approved for the restaurant is related to the number of rooms at
the inn, under the applicable zoning regulations.
3
Applicant does not indicate whether it is proposing as an alternative that the vent be
run inside the existing chimney, or whether it is proposing that a new brick chimney be
constructed around the vent pipe, or whether it is proposing that a metal vent pipe
replace the chimney in its location.
4
In this case, it would not be equitable to allow Appellants to leave the vent in the
location that was the primary basis for Appellants’ appeal, without allowing Appellants
to proceed with their appeal of that issue. Accordingly, Applicant’s motion seeking
relief from judgment “to locate the vent either where it is now located[,] or at the same
location[] but elevated,” is DENIED. However, any party may move under V.R.C.P.
60(b) to vacate the 2007 Settlement Order, at least as to the issues relating to the kitchen
vent location, so that those issues may be litigated and so that the various alternatives
proposed by either party may be considered by the Court. Appellants’ Motion for
Contempt Sanctions is therefore DENIED as MOOT at this time, subject to renewal if
appropriate.
A telephone conference has been scheduled (see enclosed notice) to discuss
whether any party anticipates filing any further motions in these cases and to set a
schedule for proceeding with Docket No. 111-6-08 Vtec.
Done at Berlin, Vermont, this 16th day of December, 2008.
_________________________________________________
Merideth Wright
Environmental Judge
5