Rose, J.
Appeal from an order of the Supreme Court (Platkin, J.), entered March 17, 2015 in Albany County, which denied petitioner's application pursuant to CPLR 7503 to permanently stay arbitration between the parties.
Petitioner, a contractor, entered into a construction contract (hereinafter the subcontract) with respondent subcontractor. When a dispute arose and petitioner withheld certain payments from respondent, respondent sought expedited arbitration pursuant to General Business Law article 35-E, also known as the Prompt Payment Act (hereinafter PPA). Petitioner then commenced this proceeding, seeking to permanently stay the arbitration on the ground that section 6.2 of the subcontract expressly states that litigation, not arbitration, is the parties' chosen method of dispute resolution. Supreme Court denied petitioner's application, interpreting the PPA to render the subcontract's dispute resolution provision void and unenforceable because it denies respondent the option to arbitrate the payment dispute. Petitioner appeals.
Here, petitioner contends that the PPA expressly provides that the subcontract's dispute resolution provision supersedes the PPA's requirement that expedited arbitration be available to an aggrieved party, and that it is unaffected by the "[e]xcept as otherwise provided" language of General Business Law § 756-a. Petitioner argues that the only exception to the PPA's general policy of giving primacy to the terms of a construction contract is found in General Business Law § 756-b (1), which provides for the accrual of interest on overdue payments "[n]otwithstanding any contrary agreement." Petitioner's reading of the PPA, however, ignores the existence of General Business Law § 757 (3), which, as we have stated, unambiguously voids and renders unenforceable any contractual provision that makes expedited arbitration unavailable to one or both parties. Contrary to petitioner's argument, the obvious function of section 6.2 of the subcontract is to establish litigation as the sole legal option for the resolution of disputes under the subcontract, which, in turn, denies both parties the opportunity to arbitrate such claims. Inasmuch as General Business Law § 757 (3) clearly operates to void and render unenforceable the subcontract's
Although petitioner also argues that Supreme Court's reading of the PPA violates its own constitutional right to a jury trial, petitioner admittedly raised this issue for the first time on appeal and, thus, it is unpreserved for our review (see People v Haskell, 68 A.D.3d 1358, 1361 [2009]; Matter of County of Sullivan [ABC Pac. Realty, LLC], 55 A.D.3d 1029, 1031 [2008], lv denied 12 N.Y.3d 713 [2009]). Moreover, even if we were to consider this issue (see State of New York v Butti, 304 A.D.2d 917, 918 [2003]; Matter of Woodin v Lane, 119 A.D.2d 969, 970 [1986]), petitioner's argument — though styled as a challenge to the application of the PPA to the facts of this case — is, in reality, a facial challenge to the constitutionality of its provisions requiring expedited arbitration. Accordingly, petitioner was required to serve notice upon the Attorney General, who must be permitted to intervene in support of the constitutionality of the statute (see Executive Law § 71; CPLR 1012 [b]). As there is no evidence that petitioner did so at any stage of this proceeding, we decline to pass upon the constitutional issue at this time (see People v Parker, 290 A.D.2d 650, 652 [2002], lv denied 97 N.Y.2d 759 [2002]).
Ordered that the order is affirmed, with costs.