WORSWICK, J.
¶ 1 Flor Avellaneda was seriously injured when two cars crossed the median on state route (SR) 512 and one of them struck her car. Flor
¶ 2 On July 23, 2006, Flor was driving eastbound on SR 512 when two cars going the opposite direction crossed the median and one of them struck her car. Although the WSDOT had planned to install a cable barrier on that median, no barrier was in place at the time of the accident.
¶ 3 In 2001, the Highway Safety Executive Group amended the WSDOT's design manual to recommend installing median barriers on medians less than 50 feet wide. Under RCW 47.05.010, the WSDOT is required to rationally allocate funding based on the relative priority of projects, which the WSDOT implements by formulating a "priority array" of projects for which it seeks funding. CP at 386. To implement the design manual amendment pursuant to this priority programming mandate, the WSDOT distributed guidelines to its regional offices instructing them how to calculate benefit/cost ratios
¶ 4 The WSDOT's proposed budget for the 2003-05 biennium did not include a funding request for the SR 512 project because all the projects the WSDOT requested funding for had a benefit/cost ratio of one or greater and the SR 512 project had a benefit/cost ratio of zero. The Transportation Commission reviewed and modified the budget before sending it to the legislature.
¶ 5 In August 2003, the portion of SR 512 where Flor's accident would occur was combined with another stretch of SR 512, giving the combined project a much higher benefit/cost ratio, making it 13th priority on the list of proposed median barrier projects. In April 2004, the WSDOT adjusted the benefit/cost calculations to include collision data from 2001 and 2002, as well as updated cost factors. The new calculation further adjusted the SR 512 project to 9th highest priority.
¶ 7 For efficiency, the WSDOT combined the SR 512 project with a median barrier project on United States route (US) 101. The design process for this project began December 5, 2005, after necessary project approvals were granted. The project was given an "advertisement date," the date it was to be submitted to the public for bids, of May 15, 2006. CP at 85 But an unforeseen sloping issue required additional design time, causing the WSDOT to push the project's advertisement date to July 17.
¶ 8 Bids were due by August 16, and the WSDOT had 45 days to review the bid documents and award the contract. The WSDOT awarded the winning bid on August 21, and the winning bidder had up to 20 days to execute the contract. The winning bidder executed the contract on September 8. The winning bidder then had 90 days to acquire the materials necessary for the project. The winning bidder commenced construction of the U.S. 101 portion of the project on December 11. Work commenced on the SR 512 barrier in February 2007 and was substantially completed by March 30.
¶ 9 The Avellanedas sued the State, alleging that the WSDOT negligently delayed constructing a cable barrier on SR 512, which would have prevented the crash. The State moved for summary judgment on the Avellanedas' claims. The trial court ruled that there were genuine issues of material fact whether the accident would have occurred with the cable barrier in place. But the trial court further ruled that the State was entitled to discretionary immunity for its timing of the project. The Avellanedas appeal.
¶ 10 We review a grant of summary judgment de novo. Briggs v. Nova Servs., 166 Wn.2d 794, 801, 213 P.3d 910 (2009). Summary judgment is appropriate where, viewing all facts and resulting inferences most favorably to the nonmoving party, the court finds no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Briggs, 166 Wash.2d at 801, 213 P.3d 910. "A genuine issue of material fact exists where reasonable minds could differ on the facts controlling the outcome of the litigation." Ranger Ins. Co. v. Pierce County, 164 Wn.2d 545, 552, 192 P.3d 886 (2008).
¶ 11 The Avellanedas first argue that the trial court erred by granting summary judgment to the State under the doctrine of discretionary immunity. This argument presents two questions. First, was the decision whether to include the SR 512 project in the WSDOT's priority array entitled to discretionary immunity? And second, are there genuine issues of fact whether the WSDOT negligently delayed the implementation of the SR 512 project once it was funded? We hold that the decision to exclude SR 512 from the priority array was entitled to discretionary immunity and that there is no genuine issue whether the WSDOT negligently delayed the project's implementation.
¶ 12 Our Supreme Court set forth the test for discretionary immunity in Evangelical United Brethren Church of Adna v. State, 67 Wn.2d 246, 407 P.2d 440 (1965). The Evangelical court noted that "in any organized society there must be room for basic governmental policy decision and the implementation thereof, unhampered by the threat or fear of sovereign tort liability." 67 Wash.2d at 254, 407 P.2d 440. In other words, "`it is not a tort for government to govern.'" 67 Wash.2d at 253, 407 P.2d 440 (quoting Dalehite v. United States, 346 U.S. 15, 57, 73 S.Ct. 956, 97 L.Ed. 1427 (1953) (Jackson, J., dissenting)).
¶ 13 Holding that it is necessary to draw the line between "truly discretionary and other executive and administrative processes," the Evangelical court announced a four-factor test to determine when discretionary immunity applies:
67 Wash.2d at 255, 407 P.2d 440. The court held, "If these preliminary questions can be clearly and unequivocally answered in the affirmative, then the challenged act, omission, or decision can, with a reasonable degree of assurance, be classified as a discretionary governmental process and nontortious, regardless of its unwisdom." 67 Wash.2d at 255, 407 P.2d 440. The court further held that the question of discretionary immunity "should present a question of law, although in some instances it may well give rise to a mixed question of law and fact." 67 Wash.2d at 253, 407 P.2d 440.
¶ 14 Our Supreme Court has also held that discretionary immunity is a narrow doctrine, limited to "discretionary" acts, not "ministerial" or "operational" ones. Taggart v. State, 118 Wn.2d 195, 214-15, 822 P.2d 243 (1992). In order for a decision to qualify as discretionary, the State must show that the decision was the outcome of a conscious balancing of risks and advantages. Taggart, 118 Wash.2d at 214-15, 822 P.2d 243. And the decision must be a basic policy decision by a high-level executive. Taggart, 118 Wash.2d at 215, 822 P.2d 243.
¶ 15 The first question we must answer is whether the decision to exclude SR 512 from the budgetary priority array was entitled to discretionary immunity. Washington courts have not directly addressed whether a decision to include or exclude a project from the priority array constitutes a discretionary decision. We hold that the decision here was, because the decision satisfied the tests set forth in Evangelical and its progeny and because applying discretionary immunity to this type of decision safeguards the separation of powers.
¶ 16 RCW 47.05.010 recognizes that limited revenues prevent the State from satisfying all transportation needs and that "[d]ifficult investment trade-offs will be required." The statute mandates a "priority programming" system based on "the rational selection of projects and services according to factual need and an evaluation of life cycle costs and benefits that are systematically scheduled to carry out defined objectives within available revenue." RCW 47.05.010. The WSDOT complies with this priority programming mandate by generating a priority array of projects for which it requests funding. To formulate the priority array at issue here, each WSDOT region developed a list of proposed
¶ 17 Our Supreme Court addressed the Evangelical factors in Stewart v. State, 92 Wn.2d 285, 597 P.2d 101 (1979). There, the court addressed the claim that the State had negligently designed a section of freeway and the accompanying lighting system where an accident occurred. 92 Wash.2d at 292, 294, 597 P.2d 101. The court acknowledged that decisions such as those to build the freeway, to decide its location, and to decide the number of lanes, are essential to a basic government policy, program, or objective, satisfying the first and second Evangelical factors. 92 Wash.2d at 294, 597 P.2d 101. But the court held that negligently designing the freeway and its lighting system was not essential to such a basic policy, program, or objective. 92 Wash.2d at 294, 597 P.2d 101. In other words, while a decision may be protected by discretionary immunity, its negligent implementation will not be, as negligent implementation is never essential to a basic policy, program, or objective. See also Riley v. Burlington Northern, Inc., 27 Wn.App. 11, 17-18, 615 P.2d 516 (1980) (failing to place adequate signs at railroad crossing was analogous to negligent freeway design in Stewart and not protected by discretionary immunity).
¶ 18 The first Evangelical factor, that the decision necessarily involves a basic governmental policy, program, or objective, is unequivocally satisfied here. RCW 47.05.010 expresses the basic policy that highway funding decisions should be based on the rational selection of projects, evaluating the costs and benefits, leading to difficult trade offs. The decision determining the SR 512 project's priority was at least as basic as the decision to build a single freeway, recognized in Stewart as satisfying the first Evangelical factor. 92 Wash.2d at 294, 597 P.2d 101.
¶ 19 The second factor, that the decision is essential to the realization or accomplishment of that policy, program, or objective, is satisfied as well. The priority array embodies the basic policy underlying RCW 47.05.010 and is essential to its realization. The record reflects that the WSDOT promulgated and followed guidelines for systematically ranking median barrier projects according to their benefit/cost ratios. Such systematic ranking was indispensible for the State to comply with RCW 47.05.010.
¶ 20 The third factor, that the decision requires the exercise of basic policy evaluation, judgment, and expertise, is also satisfied. Here, the WSDOT was required to collect data about accident history and the cost of possible median barrier projects, and to devise a system to analyze the data and rank potential projects. This required a great deal of basic policy evaluation, judgment, and expertise.
¶ 21 Finally, the fourth factor, that the WSDOT possess the requisite constitutional, statutory, or lawful authority and duty to do or make the challenged act, omission, or decision, is satisfied. It is undisputed that the WSDOT had the requisite authority and duty to formulate the priority array as it did here.
¶ 22 As such, formulating the priority array here unequivocally satisfied all four Evangelical factors. Moreover, the Transportation Commission reviewed, modified, and finalized the prioritized median barrier projects as part of the final WSDOT budget. The ultimate decision regarding the funding of projects in the priority array thus rested with a high-level executive body; it was not an operational-level decision.
¶ 23 Furthermore, the WSDOT showed that its decision here was the outcome of a conscious balancing of risks and advantages. The record contains the guidelines WSDOT used to calculate the priority of projects, as well as declarations by WSDOT employees that higher priority projects were selected first. The Avellanedas submitted no evidence to the contrary. Accordingly, there is no genuine issue of material fact whether the WSDOT consciously balanced the risks and advantages of selecting the projects to fund. Because the priority programming decision excluding the SR 512 project satisfied the tests set forth in Evangelical and its progeny,
¶ 24 The Avellanedas argue to the contrary that the WSDOT's decision to assign the SR 512 project an initial benefit/cost ratio of zero was ministerial and thus not subject to discretionary immunity. But accepting this characterization would contravene past precedent of this court.
¶ 25 We rejected a similar theory in Jenson v. Scribner, 57 Wn.App. 478, 482-83, 789 P.2d 306 (1990). There, we considered the Jensons' claim that the State had negligently failed to install a median barrier on SR 3. 57 Wash.App. at 479, 789 P.2d 306. The Jensons argued that the State was liable for calculating the project's priority based on crash data collected every two years. 57 Wash.App. at 482-83, 789 P.2d 306. They argued that if the State had collected data annually, the project would have had a higher priority. 57 Wash.App. at 483, 789 P.2d 306. We held that data collection was part of the decision-making process, not part of implementation, making it a discretionary act entitled to immunity. 57 Wash.App. at 483, 789 P.2d 306.
¶ 26 So too here, the calculation of the SR 512 project's benefit/cost ratio was part of the decision-making process going into formulating the priority array. Like the decision as to how often to collect crash data, the WSDOT's benefit/cost calculations here involved the application of "basic policy evaluation, judgment, and expertise." Evangelical, 67 Wash.2d at 255, 407 P.2d 440. We hold that just as the ultimate decision not to include SR 512 on the priority array, the particular benefit/cost calculation that gave SR 512 a ratio of zero was protected by discretionary immunity.
¶ 27 The doctrine of separation of powers further supports this conclusion. In McCluskey v. Handorff-Sherman, 125 Wn.2d 1, 12-13, 882 P.2d 157 (1994), our Supreme Court "outline[d] the analysis" for whether discretionary immunity applies to priority programming decisions by citing several out-of-state cases relevant to the issue. But the court declined to actually decide the issue because the State abandoned it at trial. McCluskey, 125 Wash.2d at 13, 882 P.2d 157.
¶ 28 McCluskey cited Julius Rothschild & Co. v. State, 66 Haw. 76, 655 P.2d 877 (Haw. 1982). 125 Wash.2d at 13, 882 P.2d 157. There, the Supreme Court of Hawaii addressed whether the state could be held liable for failing to reconstruct or replace a bridge to comply with modern building standards that were more rigorous than those in place when the bridge was built. 655 P.2d at 879-80. The court applied a rule similar to Washington's, noting that Hawaii holds discretionary government decisions immune from tort liability, but not operational level decisions. 655 P.2d at 880-81. The court had "no difficulty" in holding that the decision whether to reconstruct or replace the bridge involved the evaluation of "broad policy factors," immunizing the decision from judicial review. 655 P.2d at 881. The court found it important to "`[recognize] the separate powers and functions of the legislative and executive branches of state government and [protect] them from any attempted disturbance through the courts.'" 655 P.2d at 881 (quoting Breed v. Shaner, 57 Haw. 656, 562 P.2d 436, 442 (Haw.1977)).
¶ 29 McCluskey also cited Industrial Indemnity Co. v. State, 669 P.2d 561 (Alaska 1983). 125 Wash.2d at 13, 882 P.2d 157. There, the Supreme Court of Alaska addressed whether the state could be held liable for failing to install a highway guardrail.
¶ 30 Both Julius Rothschild and Industrial Indemnity are convincing. As both of those cases noted, judicial intrusion into the difficult balancing of planning, policy, and budget trenches on the authority of both the executive and legislative branches. And as noted in Industrial Indemnity, it is poor public policy for the courts to extend their influence into matters beyond their institutional competence. We are not equipped with the resources or expertise to second-guess the legislature's funding decisions or the minutiae of the WSDOT's planning decisions and we decline to do so.
¶ 31 Moreover, the separation of powers concerns reflected in Julius Rothschild and Industrial Indemnity are consistent with those expressed by the Washington Supreme Court under other circumstances. In general, Washington courts hold that the separation of powers doctrine is violated when the activity of one branch threatens the independence or integrity or invades the prerogative of another. Waples v. Yi, 169 Wn.2d 152, 158, 234 P.3d 187 (2010) (quoting Putman v. Wenatchee Valley Med. Ctr., 166 Wn.2d 974, 980, 216 P.3d 374 (2009)). And in SEIU Healthcare 775NW v. Gregoire, the Supreme Court held that "[d]eciding the allocation of limited state funds" in drafting a budget proposal is an essential policy decision that is political by nature and within the prerogative of the executive. 168 Wn.2d 593, 600, 229 P.3d 774 (2010) (quoting Marbury v. Madison, 5 U.S. (1 Cranch) 137, 170, 2 L.Ed. 60 (1803)). The court moreover recognized that "the recent severe economic difficulties faced by our state present circumstances dictating. . . judicial restraint" on budgetary matters. 168 Wash.2d at 601, 229 P.3d 774.
¶ 32 The Avellanedas ask us to invade the executive prerogative by permitting them to recover in tort based on the WSDOT's decisions in drafting the budget proposal that excluded funding for the SR 512 project. Such a result would violate the separation of powers by injecting our court into the budget process after the fact. We decline to commit such judicial overreach by assigning potential liability to a budgetary decision properly within the WSDOT's purview.
¶ 33 The Avellanedas also argue that there are genuine issues of material fact whether the WSDOT negligently implemented the SR 512 project by unreasonably delaying it. We disagree because there is no evidence of an unreasonable delay.
¶ 34 While the decision whether to include a project on the priority array is entitled to discretionary immunity, negligent implementation of that decision may still be the basis for tort liability. In Jenson, the plaintiffs conceded that the State's decision whether to include a median barrier project on the priority array was a discretionary decision but they argued that the State could be held liable for negligently implementing that decision after funding became available. 57 Wash.App. at 481, 789 P.2d 306. We agreed, noting that discretionary immunity does not apply to the negligent implementation of discretionary decisions. 57 Wash.App. at 481, 789 P.2d 306 (citing Stewart, 92 Wash.2d at 294-95, 597 P.2d 101).
¶ 35 However, in Jenson we did not find any genuine issue of material fact on the issue of negligent implementation. 57 Wash. App. at 482, 789 P.2d 306. We noted that funds were authorized for planning the SR 3 barrier project in the 1981-83 biennium, funds for the project itself were authorized in
¶ 36 So too here, the record reflects no unreasonable delay in the construction of the SR 512 median barrier project. As we set out above, the WSDOT sought funding for, designed, advertised, and built the project. The record does not show any unexplained periods of inactivity on the project.
¶ 37 To the contrary, the Avellanedas argue that the project was first ranked 13th on the priority array, but it was then reassigned a benefit/cost ratio of zero and removed from the array, leading to a two-year delay. But the record reflects that the portion of SR 512 where Flor's accident occurred was initially given a benefit/cost ratio of zero. This benefit/cost ratio was only adjusted after the State combined the project with another stretch of SR 512 that had a higher benefit/cost ratio. Moreover, as we noted above, the calculation of benefit/cost ratios is part of the decision-making process and is subject to discretionary immunity. By analogy to Jenson, a genuine issue of fact on the calculation of the benefit/cost ratio would not be material to the State's liability and thus would not preclude summary judgment.
¶ 38 The Avellanedas further argue that the SR 512 project was negligently delayed because the WSDOT failed to request funding for it in a series of supplemental funding requests made during the 2001-03 biennium. But the decision whether to request supplemental funding is yet another part of the discretionary process involved in prioritizing highway projects and is again subject to discretionary immunity.
¶ 39 The Avellanedas finally argue that the WSDOT negligently failed to start the SR 512 project as soon as funding became available and negligently delayed the project during its construction. However, there are no facts in the record to suggest that the WSDOT's timing of the project was negligent. The Avellanedas argue that other, lower-ranked projects were completed before the SR 512 project, showing a negligent delay. But the Avellanedas fail to cite the record on this point, and our review of the record reveals no support for their assertion. Based on the record before us, reasonable minds could conclude only that there was no unreasonable delay in the implementation of the SR 512 project. Accordingly, there is no genuine issue of fact on this point and the Avellanedas' arguments fail.
¶ 40 Affirmed.
We concur: PENOYAR, C.J., and VAN DEREN, J.