THOMAS O. RICE, District Judge.
BEFORE THE COURT are Plaintiffs' Motion for Summary Judgment (ECF No. 61), Defendant John Janney's Motion for Summary Judgment (ECF No. 82), and Defendant Chelan County Public Utility Dist. No. 1's Motion for Summary Judgment (ECF No. 91). These motions were heard with oral argument on June 20, 2012. Steven C. Lacy appeared on behalf of the Plaintiffs. Portia R. Moore and Jeffrey B. Youmans appeared on behalf of the Defendants. The Court has reviewed the motions, the responses, the replies, and the record herein and is fully informed.
This is a wrongful termination lawsuit filed by two former employees of Chelan County Public Utility District No. 1. Plaintiffs have sued Defendants for violating their rights to substantive and procedural due process under 42 U.S.C. § 1983, and for the tort of breach of a promise of specific treatment in a specific circumstance under Washington common law.
Chelan County Public Utility District No. 1 ("the PUD") provides utility services to residents of Chelan County, Washington. Beginning in approximately the year 2000, the PUD began an ambitious campaign to build a county-wide fiber-optic data network for use by its business and residential customers. From the beginning, the PUD planned to extend this network to as many areas of Chelan County as possible — including its more rural areas.
Recognizing that the project would require an extensive amount of planning, the PUD assigned several of its employees to a so-called "fiber group" tasked with designing the network and budgeting for its construction. This group was led by Plaintiffs Joe Jarvis ("Jarvis") and John Smith ("Smith"). In their capacities as Executive Manager of Operations, and Managing Director of Engineering and Technology, respectively, Jarvis and Smith were the two highest-level managers directly assigned to the build-out project. Jarvis and Smith both reported to Defendant John Janney ("Janney"), the PUD's General Manager and highest appointed official.
By 2009, the PUD had invested more than $100 million in the fiber project. Despite this sizeable investment, however, the network had only been extended to about 75% of the private residences in Chelan County. The PUD estimated that extending the network to the remaining 25% of residences — many of which were located in rural areas — would cost an additional $60 million. Knowing that it could not afford this additional cost without raising utility rates, the PUD sought input from its customers about whether the network should be extended to the remaining 25% of the county. Those surveyed overwhelmingly rejected a rate increase to finance the $60 million build-out. ECF No. 85 at 344.
In September of 2009, the PUD learned of a federal grant program created by the American Recovery and Reinvestment Act of 2009 known as the Rural Utilities Service Broadband Initiatives Program ("RUS"). In early 2010, the PUD decided to pursue an RUS grant as an alternative means of financing the build-out to the county's more rural areas. The PUD assigned Jarvis and Smith to oversee the application process.
On March 27, 2010, the PUD submitted a formal application for an RUS grant. In its application, the PUD explained,
ECF No. 85 at 321-23.
On August 4, 2010, the PUD was informed that it would be awarded an RUS grant — provided that it agreed to contribute $8 million of its own funds toward the $33 million overall cost. Shortly thereafter, the PUD surveyed its customers once again to determine whether they were willing to fund the $8 million contribution through rate increases. In this survey, the PUD asked,
ECF No. 85 at 358. Sixty-one percent of respondents answered that they were in favor of increasing rates to fund the PUD's share of the build-out cost. ECF No. 85 at 358.
On August 24, 2010, the PUD hosted a public meeting to discuss whether the RUS grant should be accepted. At this meeting, the PUD gave a presentation outlining the terms of the grant and discussing the advantages and disadvantages to accepting the funding. This presentation informed the public, inter alia, that (1) the "[t]otal amount to complete build-out is $33 [million];" (2) that the PUD would be responsible for contributing $8 million to the project; (3) approximately 6,800 premises would be reached by the build-out; and (3) approximately 64% of customers surveyed were in favor of increasing rates to fund the PUD's $8 million contribution. ECF No. 85 at 367-68, 375. At the conclusion of the meeting, the PUD invited members of the public to comment on whether the grant funds should be accepted. The PUD's Board of Commissioners voted to accept the RUS grant and to increase utility rates 2-3% the following day.
On January 18, 2011, the PUD held a meeting of the "Fiber Strategic Planning Subcommittee" to discuss the status of the fiber build-out. At this meeting, Jarvis and Smith presented the following information concerning the network-access status of the private residences in Chelan County (in substantially the following format):
Networks Premises Status as of 1/14/2011 Pending Premises Orders Lit Premises 31,029 69% 864 12% RUS Premises 7,468 17% 545 8% Infill — Not yet lit 6,523 14%Total Premises: 45,020 100%
ECF No. 85 at 405. Those attending the meeting, including two members of the PUD's Board of Commissioners, were surprised to learn that the fiber group was distinguishing between "lit" premises (i.e., premises that could be readily connected to the fiber network) and "infill" premises
On Friday, February 4, 2011, Janney met with Jarvis and Smith individually to discuss the apparent discrepancy between the 98% coverage figure and the numbers presented at the January 18, 2011 subcommittee meeting. During these meetings, Janney focused on the fact that the PUD's representations to the federal government, its Board of Commissioners, and the general public about the RUS grant extending coverage to 98% of the county could be misleading in light of the additional investment required to provide access to the "infill" premises. Jarvis and Smith replied that the representations could be construed as misleading when read out of context, but maintained that they were generally accurate based upon the manner in which the fiber group had classified premises throughout the project.
On Monday, February 7, 2011, Janney again met with Jarvis and Smith individually to inform them that their employment was being terminated. The PUD's General Counsel, Carol Wardell ("Wardell"), and Director of Human Resources, LaDawn Ostmann ("Ostmann"), were also present. During this meeting, Janney read from a script that had been prepared by Ostmann at Janney's request. The script read as follows:
ECF No. 85 at 411.
Later that same day, Janney sent an email to all PUD employees to inform them that Jarvis and Smith had been terminated and to advise them of new temporary management assignments. ECF No. 85 at 418. This email read, in pertinent part:
ECF No. 85 at 418.
Also on February 7, 2011, Janney issued a press release announcing Jarvis's and Smith's firings. The press release read, in relevant part:
ECF No. 85 at 421.
Janney met with Smith once again the following morning at Smith's request. During this meeting, Smith told Janney that he did not fully understand the reasons why he had been fired. Specifically, Smith stated that he did not perceive any differences in "philosophical alignment" between himself and Janney and that, in his mind, both had been dutifully carrying out the wishes of the PUD's Board of Commissioners. ECF No. 85 at 416. Smith also lamented that Janney had not given him any advance warning that his job was in jeopardy and that, had he been advised of this fact, he would have made efforts to "correct things." ECF No. 85 at 416. Finally, Smith advised Janney that he "never felt [that his] job was in jeopardy[,] so [he] went out and bought a new car." ECF No. 85 at 416. Janney ultimately declined to reconsider his decision to terminate Smith.
Approximately two months after Jarvis and Smith were terminated, the PUD's Board of Commissioners voted to withdraw
Six months after Jarvis and Smith were terminated, the PUD offered each of them a post-termination hearing. ECF No. 85, Exhibits NN and OO, pages 446-51. Neither accepted the offer.
Summary judgment is appropriate when a moving party demonstrates "that there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a matter of law." Fed. R.Civ.P. 56(a). The party moving for summary judgment bears the initial burden of informing the court of the basis for its motion and of identifying the portions of the affidavits, pleadings, and discovery that demonstrate an absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). For purposes of a summary judgment motion, a fact is "material" if it might affect the outcome of the suit under the governing law. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). A dispute is "genuine" as to a material fact if there is sufficient evidence for a reasonable jury to return a verdict for the non-moving party. Id. at 248, 106 S.Ct. 2505. In determining whether there is a genuine issue of material fact sufficient to preclude summary judgment, a court must construe the facts, as well as all rational inferences therefrom, in the light most favorable to the non-moving party. Scott v. Harris, 550 U.S. 372, 378, 127 S.Ct. 1769, 167 L.Ed.2d 686 (2007).
Plaintiffs allege that Janney and the PUD violated their Fourteenth Amendment right to procedural due process by failing to provide them with an adequate pre-termination hearing. It is well-settled that a public employee with a constitutionally-protected interest in his or her continued employment is entitled to due process prior to being terminated. Cleveland Bd. of Educ. v. Loudermill, 470 U.S. 532, 538, 105 S.Ct. 1487, 84 L.Ed.2d 494 (1985). Generally speaking, due process requires that an employee facing termination receive "oral or written notice of the charges against him, an explanation of the employer's evidence, and an opportunity to present his side of the story." Id. at 546, 105 S.Ct. 1487. Although an employer need not provide a full evidentiary hearing, it must, at a minimum, allow an employee facing termination "to present reasons, either in person or in writing, why [the] proposed action should not be taken." Id. at 545-46, 105 S.Ct. 1487. As the Supreme Court emphasized in Loudermill, an employee's opportunity to be heard must occur before the employee is terminated. Id. at 546, 105 S.Ct. 1487 ("[T]he root requirement of the Due Process Clause [is] that an individual be given an opportunity for a hearing before he is deprived of any significant property interest.") Id. at 546, 105 S.Ct. 1487 (emphasis added) (internal quotations and citations omitted).
As an initial matter, the court finds that Jarvis and Smith had a protected
Turning to Jarvis's and Smith's terminations, the court finds that the pre-termination procedures followed by the PUD were deficient for two reasons. First, Janney did not advise Jarvis and Smith that they were facing potential termination before they were formally terminated on February 7, 2011.
Id. (emphasis added).
Here, Defendants concede that Jarvis and Smith were never advised that the PUD was considering terminating their employment prior to their meetings with Janney on February 7, 2011. Although Janney expressed his frustrations with Jarvis and Smith on February 4, 2011, he failed to mention that he was considering terminating their employment (or any other form of disciplinary action) on that occasion. ECF No. 63 at ¶ 82; ECF No. 102 at ¶ 82. Thus, Jarvis and Smith did not learn that the allegations against them were serious enough to warrant potential termination until Janney informed them that they had been terminated on February 7, 2011. In the absence of any prior notice that termination was imminent — or even being considered — Jarvis and Smith were deprived of a "fundamental" due process requirement — the right to "present
To whatever extent Jarvis and Smith received notice on February 4th, that there was a dispute about the fiber group's figures, the court finds that the notice was not specific enough to comport with due process. Unlike an employee who is confronted by his employer about specific instances of misconduct, Jarvis and Smith were never advised of the precise nature of the "charges" against them. Rather, they were simply informed that they had failed to fulfill their responsibility to ensure that the information provided by the fiber group was accurate. Notably, Jarvis and Smith were never advised how their alleged shortcomings as managers might amount to cause for termination.
Second, the court finds that the claimed pre-termination hearings on February 7, 2011, did not afford Jarvis and Smith a meaningful opportunity to be heard. As the PUD readily admits, these "hearings" began with Janney reading from a prepared script informing Jarvis and Smith that they had been terminated. ECF No. 85 at 179. The unmistakable tenor of this script is that Janney had already made his decision to terminate Jarvis and Smith — and that his decision was final.
Although Janney nominally advised Jarvis and Smith that they "ha[d] the right to be heard on my reasons," the record reflects that Janney was not open to a meaningful dialogue. Indeed, when Smith attempted to further explain the reasons for the discrepancies in the fiber group's figures, Janney rejected his explanations out-of-hand, explaining that "this is all a continuation of our discussion on Friday [February, 4, 2011]." ECF No. 71 at Exhibit 67. Accordingly, the February 7, 2011 meetings did not afford Jarvis and Smith a meaningful opportunity to "present [their] side of the story" before being terminated. Loudermill, 470 U.S. at 546, 105 S.Ct. 1487; see also Matthews 819 F.2d at 893 (holding that teacher's right to due process was violated by school board's vote to terminate her employment before holding a pre-termination hearing). Loudermill clearly counseled, "[e]ven where the facts are clear, the appropriateness or necessity of the discharge may not be; in such cases, the only meaningful opportunity to invoke the discretion of the decisionmaker is likely to be before the termination takes effect." Loudermill, 470 U.S. at 543, 105 S.Ct. 1487.
Here, the court finds that Jarvis's and Smith's terminations were, for all intents and purposes, "effective" on February 7, 2011. As evidenced by Janney's termination script, Jarvis and Smith were forbidden from accessing their computers, told to collect their personal belongings (with the assistance of a security officer) and ordered to leave the premises within two hours of being informed that they had been terminated. Shortly thereafter, Janney announced the firings — as well as Javis's and Smith's replacements — to the entire PUD employee roster. He also announced the firings to the general public in a press release later that same day. These facts lead to one inescapable conclusion: that Jarvis and Smith were formally terminated on February 7, 2011. As of that date, Jarvis and Smith were not in a position to "challenge and forestall" their terminations while "still employed at the same job." Bignall, 538 F.2d at 246. Accordingly, the fact that Jarvis and Smith were ultimately paid for two additional workdays is irrelevant to the pre-termination procedural due process analysis.
Finally, to the extent that Defendants believe that the February 4, 2011 meetings satisfied Jarvis's and Smith's right to be heard, such a belief is entirely misplaced. As discussed above, Jarvis and Smith had no reason to believe that their jobs were in jeopardy when they met with Janney to discuss the variations in the fiber group's reported figures. By all accounts, Janney's purpose in conducting these meetings was to convince Jarvis and Smith to acknowledge that the figures reported in August of 2010 could have been either misinterpreted or construed as misleading. While Janney apparently believed that any such acknowledgement amounted to grounds for termination, Jarvis and Smith believed that they were simply being asked to acknowledge that Janney had presented a valid concern. At bottom, Jarvis and Smith had no reason to believe that they were being asked to defend themselves against allegations of misconduct during their February 4, 2011 meetings
Plaintiffs are entitled to summary judgment on these claims that they were denied a proper pre-termination due process hearing.
Plaintiffs contend that they were not only denied pre-termination due process, but also they were denied a timely post-termination due process hearing. ECF No. 62 at 6-11; ECF No. 114 at 12. Defendants contend that each were told by Janney that they "have a right to be heard on my reasons", each was given a copy of Policy 101, and each was offered a post-termination hearing by letter dated August 3, 2011.
It may seem unnecessary to determine whether post-termination procedures were adequate given the court's ruling above. However, inadequate post-termination procedures can be a distinct due process violation and ultimately, "the existence of post-termination procedures is relevant to the necessary scope of pretermination procedures." Loudermill, 470 U.S. at 547 n. 12, 105 S.Ct. 1487. Accordingly, the court is also required to consider this alleged due process violation.
First, it must be observed that in the context of process due a terminated public employee, a full post-deprivation hearing does not substitute for the required pre-termination hearing. Loudermill itself reveals that post-termination administrative hearings, even if followed by judicial review, are ordinarily insufficient standing alone to satisfy procedural due process in the public employee context. Although the nature of subsequent proceedings may lessen the amount of process that the state must provide pre-termination, subsequent proceedings cannot serve to eliminate the essential requirement of a pre-termination notice and opportunity to respond. See Clements v. Airport Authority of Washoe County, 69 F.3d 321, 332 (9th Cir.1995). The "absolute" right to adequate procedures stands independent from the ultimate outcome of the hearing. Id.; see also Knudson v. City of Ellensburg, 832 F.2d 1142, 1148-49 (9th Cir.1987) (denial of a required pre-termination hearing is always actionable, even where an adequate post-deprivation hearing was provided and even where the deprivation itself was justified). Where the procedures are constitutionally inadequate, but the property deprivation was justified, a plaintiff could recover nominal damages. Where the deprivation was unjustified, the plaintiff is entitled to full compensatory damages. Id.
At minimum, one must be given notice and an opportunity to be heard at a meaningful time and in a meaningful manner by an impartial decision maker, have an opportunity to confront all the evidence adduced against him and present his own evidence. See generally, Vanelli v. Reynolds School Dist. No. 7, 667 F.2d 773 (9th Cir.1982).
In this case, the court finds that Janney's statement contained in his script that "[y]ou have a right to be heard on my reasons," does not constitute a post-deprivation hearing. Indeed, it is not a hearing at all, but rather an offer to repeat the reasons for the termination that has already occurred.
Second, the court finds that handing each terminated employee a copy of Policy 101 is not an offer of a valid post-termination hearing. Defendants' have taken two inherently contradictory positions: First, Defendants contend that Policy
The court finds that Policy 101 does not provide, on the undisputed facts of this case, a valid post-termination hearing process. The first contemplated hearing is plainly only applicable "[p]rior to discharge...." That did not occur in this case. The second hearing contemplated by Policy 101 is specifically limited to "address the reasons for the employee's discharge, but not the decision to discharge." With those stated limitations, a valid post-termination hearing was not offered.
Finally, the Defendants contend that the August 3, 2011 letters sent to each plaintiff six months after they were terminated and their subsequent declination of the offered hearing, constituted a waiver of their right to a due process hearing. The court finds otherwise. Post-termination hearings must be given at a meaningful time and in a meaningful manner. See e.g., Bignall v. North Idaho College, 538 F.2d 243 (9th Cir.1976). Neither of those prerequisites is present in an offer six months post-termination.
Plaintiffs are entitled to summary judgment on these claims that they were denied a timely and proper post-termination due process hearing.
The court finds that genuine issues of material fact remain concerning whether Defendants had adequate cause to terminate Jarvis and Smith. As an initial matter, the parties have offered conflicting and internally inconsistent evidence concerning the precise reason or reasons why Jarvis and Smith were terminated. The script read by Janney during the February 7, 2011 termination meetings suggests that Plaintiffs were terminated for (1) acknowledging that the figures reported by the fiber group were misleading; (2) demonstrating "carelessness and inattention" during the reporting process; (3) damaging the PUD's reputation; and (4) Janney's lack of confidence in their abilities as managers. ECF No. 85 at 411. Janney's subsequent internal and external announcements of the firings state that Janney wanted to be more "philosophically aligned with [his] management team," and that he terminated Jarvis and Smith "[t]o restore full confidence in his management team." ECF No. 85 at 418, 421. Janney later testified that the "primary focus" of his decision to terminate Jarvis and Smith was the misleading nature of the figures reported by the fiber group and their alleged admission to knowing that the figures were misleading when they were reported. Janney Dep., ECF No. 73, at 390.
Counsel for Defendants contended at oral argument that Jarvis and Smith were terminated specifically only for violation of Policy 101, examples 4 and 5:
Plaintiffs, for their part, have presented facially credible evidence that Janney knew — or should have known — that the reported figures were not as clear-cut as he claimed to believe. They have also presented
Moreover, questions of material fact abound concerning the discrepancies in the fiber group's reported figures. While there is no question that the differences between the figures were substantial, lingering questions remain about whether the August 2010 and November 2010 estimates presented (or were even intended to present) a true "apples to apples" comparison. Stated differently, there is conflicting evidence about whether the discrepancies were caused by mistakes on the part of the fiber group or whether those interpreting the figures at the highest levels of management simply misunderstood what they were intended to convey. The court concludes that this crucial issue of fact must be resolved by a jury. Accordingly, Plaintiffs' motion for summary judgment on the cause for termination issue is denied.
The termination of a public employee which includes publication of stigmatizing charges triggers due process protections. A liberty interest is implicated in the employment termination context if the charge impairs a reputation for honesty or morality. However, Plaintiffs each obtained alternative employment and have agreed to the dismissal of their liberty interest claims. ECF No. 98 at 14.
Defendant Janney argues that he is immune from suit under the doctrine of qualified immunity.
As discussed above, Janney violated Plaintiffs' right to procedural due process by failing to provide them with advance notice of their terminations and a meaningful opportunity to be heard before the terminations became effective. Accordingly, the dispositive question for purposes of the qualified immunity analysis is whether the Plaintiffs' rights to (1) advance notice of the terminations; and (2) a meaningful opportunity to be heard was clearly established at the time of the violation. See Brewster v. Bd. of Educ. of Lynwood Unified Sch. Dist., 149 F.3d 971, 977 (9th Cir.1998) (emphasizing that courts "should focus the qualified immunity inquiry at the level of implementation" rather than the more general nature of the constitutional right at issue). The court finds that these rights have been clearly established
470 U.S. at 542, 105 S.Ct. 1487 (emphasis in original) (internal quotations and citations omitted).
In light of Loudermill and its progeny, a reasonable official in Janney's position should have known that the procedures followed in this case violated Jarvis's and Smith's right to procedural due process. The very essence of the Loudermill decision is that an employee must be given a fair opportunity to oppose his termination before it occurs. This necessarily requires "oral or written notice of the charges against him" and a subsequent opportunity "to present reasons, either in person or in writing, why [the] proposed action should not be taken." Loudermill, 470 U.S. at 546, 105 S.Ct. 1487. A simple discussion of conduct which the employer subjectively believes amounts to cause for termination — without notice to the employee that disciplinary action is being considered — like that which occurred at the February 4th meeting, does not satisfy this standard. Neither does terminating an employee, locking him out, announcing it to every employee in the organization and the press, and then claiming the employee had two days to discuss the matter before being taken off the payroll. Finally, irrespective of the pre-termination violation, no post-termination due process hearing was provided. Post termination due process has been required since at least the time Loudermill was decided in 1985.
Janney has made some reference to the advice of counsel he received when he took his actions, as well as his consultation with the human resources department. However, his subjective good faith is not the issue. Qualified immunity is the legal question of whether Janney's actions were objectively reasonable in light of prevailing law at the time. See Harlow v. Fitzgerald, 457 U.S. 800, 815-19, 102 S.Ct. 2727, 73 L.Ed.2d 396 (1982).
Accordingly, Janney is not entitled to qualified immunity.
Defendant Janney seeks summary judgment on Plaintiffs' allegations that punitive damages are available on this record.
The PUD has moved for summary judgment on Plaintiffs' state law claims for breach of promise of specific treatment in specific circumstances. According to the PUD, these state-law claims are based upon the theory that it violated Policy 101 by terminating Plaintiffs' employment without adequate cause.
The parties agree that the terms of Plaintiffs' employment with the PUD were governed by a document entitled "Nature of Employment — Non-Bargaining Unit Employees — Policy # 101". This policy provides, in relevant part:
ECF No. 85 at 413-14.
As an initial matter, the court finds that Policy 101 contains an express and unambiguous promise that non-bargaining unit employees will not be terminated except for cause. Accordingly, the first element of Plaintiffs' claims is easily satisfied.
With regard to the second element of Plaintiffs' claims, there is little doubt that Plaintiffs relied upon the PUD's promise that they would not be terminated except for cause. Contrary to Defendants' assertions, the fact that Jarvis and Smith both applied for other jobs while employed by the PUD does not preclude them from establishing reliance. Indeed, the argument that a tenured employee is effectively precluded from seeking career advancement outside his or her current organization is patently absurd. In any event, the record reflects that (1) Jarvis would not have considered abandoning his tenured employment with the PUD unless he was offered similar job security with a different employer (Jarvis Decl., ECF No. 107, at ¶ 6): and (2) Smith did not apply for any positions outside the PUD after his employment was changed from at-will to for cause in 2004 (Smith Decl., ECF No. 108, at ¶ 6). Smith also testified that he purchased a new car in express reliance upon his continued employment. Thus, on the record presently before the court, Jarvis and Smith have established adequate reliance.
Further, the court finds that Policy 101's disclaimer language does not preclude
ECF No. 85 at 414. Defendants claim that this language effectively precludes Plaintiffs from relying on the District's promise that they would not be terminated except for cause. This argument fails for two reasons. First, Policy 101 was amended in 2004 for the express purpose of changing the employment status of non-bargaining unit employees from terminable at-will to terminable only for cause. For employees like Jarvis and Smith — who had previously been terminable at will — this amendment represented a major concession by their employer. Any reasonable employee in Jarvis's and Smith's position would have understood this concession to be binding upon the PUD unless and until it was expressly revoked.
Second, the cases relied upon by Defendants in support of their disclaimer arguments are distinguishable. Critically, each of these cases involve promises allegedly made by an employer in the context of an at will employment relationship. See Swanson v. Liquid Air Corp., 118 Wn.2d 512, 515, 826 P.2d 664, 665 (1992); Thompson v. St. Regis Paper Co., 102 Wn.2d 219, 221, 685 P.2d 1081, 1083 (1984); Birge v. Fred Meyer, Inc., 73 Wn.App. 895, 900, 872 P.2d 49, 52 (1994); Nelson v. Southland Corp., 78 Wn.App. 25, 28, 894 P.2d 1385, 1386 (1995); Quedado v. Boeing Co., 168 Wn.App. 363, 276 P.3d 365, 372 (2012); Kinne v. Othello Cmty. Hosp., 2010 WL 457361 at *1 (E.D.Wash.2010) (unpublished). The fundamental question presented in each of these cases was whether the employer's alleged promise of specific treatment was sufficiently definite to "contractually modify the terminable at will relationship." Swanson, 118 Wash.2d at 520, 826 P.2d 664. Where, as here, the promise at issue is that an employee will no longer be terminable at will, there is no need to determine whether the promise "create[s] an implied contract modifying the at-will relationship." Quedado, 168 Wn.App. 363, 276 P.3d at 368-69. In this circumstance, the at-will employment relationship has been expressly modified. Defendants conceded at oral argument that Plaintiffs were terminable only for cause.
Finally, as discussed above, Plaintiffs have established a triable issue of fact regarding whether the PUD had adequate cause to terminate their employment. Accordingly, the PUD is not entitled to summary judgment on the third element of Plaintiffs' state law breach of promise claims. The PUD's motion for summary judgment on these claims is denied.
The District Court Executive is hereby directed to enter this Order and provide copies to counsel.