Northwest Environmental Advocates v. United States Environmental Protection Agency, 2:14-cv-0196-RSM. (2017)

Court: District Court, D. Washington Number: infdco20170705i19 Visitors: 5
Filed: Jun. 29, 2017
Latest Update: Jun. 29, 2017
Summary: ORDER GRANTING JOINT AND UNOPPOSED MOTION TO AMEND SCHEDULING ORDER RICARDO S. MARTINEZ , Chief District Judge . The Court, having considered the Joint and Unopposed Motion to Amend the Scheduling Order, and for good cause shown, hereby GRANTS the Motion. Accordingly, IT IS HEREBY ORDERED: 1. The Scheduling Order previously entered by this Court (ECF Nos. 77 and 79) is hereby replaced with the following Amended Scheduling Order: ACTION REQUIRED DATE E
More

ORDER GRANTING JOINT AND UNOPPOSED MOTION TO AMEND SCHEDULING ORDER

The Court, having considered the Joint and Unopposed Motion to Amend the Scheduling Order, and for good cause shown, hereby GRANTS the Motion.

Accordingly, IT IS HEREBY ORDERED:

1. The Scheduling Order previously entered by this Court (ECF Nos. 77 and 79) is hereby replaced with the following Amended Scheduling Order:

ACTION REQUIRED DATE EPA shall file its final administrative November 3, 2017 record(s). NWEA shall file its motion for summary December 11, 2018 judgment. EPA shall file its memorandum in opposition February 5, 2018 and separate dispositive cross-motion. Intervenor-Defendants State, Washington February 19, 2018 Cattlemen's Association, and the Northwest Pulp and Paper Association et al. shall file separate memorandums in opposition and separate dispositive cross-motions. NWEA shall file oppositions to the cross-motions March 26, 2018 and its reply brief. EPA shall file a reply on its cross-motion. April 26, 2018 Intervenor-Defendants shall file replies on May 10, 2018 their cross-motions.