Summary: STIPULATED MOTION AND [PROPOSED] ORDER TO MODIFY CLAIM CONSTRUCTION SCHEDULE JAMES L. ROBART , District Judge . Plaintiffs SRC Labs, LLC & Saint Regis Mohawk Tribe (collectively, "Plaintiffs") and Defendant Microsoft Corporation ("Microsoft") submit this stipulation to request the following modification to the Court's Minute Order Setting Trial Dates and Related Dates entered on May 22, 2018 (Dkt. No. 94) (the "Minute Order"). Event Current Deadline Mod
More

STIPULATED MOTION AND [PROPOSED] ORDER TO MODIFY CLAIM CONSTRUCTION SCHEDULE

Plaintiffs SRC Labs, LLC & Saint Regis Mohawk Tribe (collectively, "Plaintiffs") and Defendant Microsoft Corporation ("Microsoft") submit this stipulation to request the following modification to the Court's Minute Order Setting Trial Dates and Related Dates entered on May 22, 2018 (Dkt. No. 94) (the "Minute Order").

Event Current Deadline Modified Deadline Reports from expert witnesses 9/7/18 9/21/08 regarding Markman issues Rebuttal expert reports 9/21/18 10/5/18 regarding Markman issues Joint claim chart and 9/28/18 10/24/18 Prehearing Statement Opening claim construction briefs 10/26/18 11/2/18 Responsive claim constructive briefs 11/9/18 11/16/18 Markman Hearing 12/20/18 12/20/18

Good cause exists for this extension because the parties are currently engaging in ongoing discussions to narrow the number of claim terms in dispute. The proposed modifications do not change the date of the Markman hearing and will not require modifying any other deadlines set forth in the Court's Minute Order.

[PROPOSED] ORDER

This matter is before the Court on the parties' Stipulated Motion to Modify Claim Construction Schedule. The Court, having considered this matter and the record in this case, ORDERS as follows:

The Stipulated Motion is GRANTED in its entirety.

IT IS HEREBY ORDERED THAT the claim construction deadlines are modified as follows.

Event Current Deadline Modified Deadline Reports from expert witnesses 9/7/18 9/21/08 regarding Markman issues Rebuttal expert reports 9/21/18 10/5/18 regarding Markman issues Joint claim chart and 9/28/18 10/24/18 Prehearing Statement Opening claim construction briefs 10/26/18 11/2/18 Responsive claim constructive briefs 11/9/18 11/16/18 Markman Hearing 12/20/18 12/20/18

SO ORDERED.