JOHN C. COUGHENOUR, District Judge.
This matter comes before the Court on Puget Soundkeeper Alliance, Sierra Club, and Idaho Conservation League's (collectively, the "proposed intervenors") motion to intervene (Dkt. No. 24) and motion for leave to file a brief in opposition to Plaintiff's pending motion for a preliminary injunction (Dkt. No. 27). Having thoroughly considered the parties' briefing and the relevant record, the Court finds oral argument unnecessary and hereby GRANTS the motions for the reasons explained herein.
Plaintiff is a nonprofit trade organization operating in Washington on behalf of the beef industry. (See Dkt. No. 1 at 3.) In 2015, Defendants U.S. Environmental Protection Agency (the "EPA") and Army Corps of Engineers (the "Corps") promulgated new regulations that changed the definition of the term "navigable waters" in the Clean Water Act ("CWA"), 33 U.S.C. §§ 1362(7), 1363(12) (the "2015 Rule"). (See id. at 8-10.) On April 16, 2019, Plaintiff filed a complaint challenging the 2015 Rule. (See generally id.) Plaintiff argues that the EPA and Corps exceeded their regulatory authority in promulgating the 2015 Rule and denied Plaintiff its right to notice and comment, and raises various constitutional challenges to the 2015 Rule. (See id. at 15-21.) Plaintiff seeks declaratory relief finding the 2015 Rule invalid and an injunction barring Defendants from enforcing the 2015 Rule. (See id. at 21-22.) On June 14, 2019, Plaintiff moved for a preliminary injunction, which is noted for the Court's consideration on July 19, 2019. (Dkt. No. 15.)
Puget Soundkeeper Alliance is a nonprofit corporation organized in Washington with members situated throughout the Puget Sound watershed, with the stated goal of protecting and preserving the waters of Puget Sound. (Id. at 4.) The Sierra Club is a nonprofit corporation organized in California, with local chapters in various states. (Id. at 5.) The Idaho Conservation League is a nonprofit corporation organized in Idaho with members dedicated to protecting Idaho's natural resources. (Id. at 5-6.) All three proposed intervenors participated in the public comment process for the 2015 Rule. (Id. at 4-6.)
On June 25, 2019, the proposed intervenors moved to intervene in this action. (Dkt. No. 24.)
The Court, in its discretion, may grant permissive intervention where the applicant "has a claim or defense that shares with the main action a common question of law or fact" and where intervention would not "unduly delay or prejudice the adjudication of the original parties' rights." Fed. R. Civ. P. 24(b)(1)(B), (b)(3). The Court may consider factors including (1) "the nature and extent of the intervenors' interest," (2) whether existing parties adequately represent those interests, (3) "the legal position [intervenors] seek to advance," and (4) "whether parties seeking intervention will significantly contribute to full development of the underlying factual issues in the suit and to the just and equitable adjudication of the legal questions presented." Spangler v. Pasadena City Bd. of Ed., 552 F.2d 1326, 1329 (9th Cir. 1977). "Rule 24 traditionally receives liberal construction in favor of applicants for intervention." Arakaki v. Cayetano, 324 F.3d 1078, 1083 (9th Cir. 2003).
Plaintiff does not oppose Puget Soundkeeper Alliance's permissive intervention into this lawsuit. (Dkt. No. 28 at 2-3.)
Further, the permissive intervention of the proposed intervenors into this case will not unduly delay or prejudice the adjudication of Plaintiff's rights. See Fed. R. Civ. P. 24(b)(3). The lawsuit was filed in April 2019, and Plaintiff moved for a preliminary injunction in June 2019. (Dkt. Nos. 1, 15.) Thus, the permissive intervention of the proposed intervenors at this early stage in the lawsuit will not unduly delay or prejudice the proceedings as a whole. See Fed. R. Civ. P. 24(b)(3). Granting the proposed intervenors sufficient time to respond to Plaintiff's pending motion for a preliminary injunction will necessarily delay the Court's consideration of the motion, as Defendants' response was due on July 15, 2019 and the motion is noted for the Court's consideration on July 19, 2019. (See Dkt. Nos. 15, 32.) But such delay is not undue in light of the interests at stake in the litigation and the history of the lawsuit, and Plaintiff has not identified any prejudice that it will suffer as a result. (See Dkt. No. 28 at 3-4.) Further, Plaintiff will be granted additional time to fully respond to the proposed intervenors' arguments, as discussed below, which further alleviates any prejudice Plaintiff would otherwise suffer. (See id. at 4; Dkt. No. 29 at 3.)
Therefore, the Court finds that permissive intervention of the Puget Soundkeeper Alliance, Sierra Club, and the Idaho Conservation League is appropriate, and the proposed intervenors' motion to intervene (Dkt. No. 24) is GRANTED.
The proposed intervenors move for leave to file a brief in opposition to Plaintiff's pending motion for a preliminary injunction. (Dkt. No. 27.) Plaintiff filed its motion for a preliminary injunction on June 14, 2019. (Dkt. No. 15.) Defendants filed their response to the motion on July 15, 2019. (Dkt. No. 32.) Plaintiff's reply is presently due on July 19, 2019. (See Dkt. No. 15.)
As discussed above, permissive intervention of the proposed intervenors is appropriate in this case, and allowing them time to respond to Plaintiff's pending motion for a preliminary injunction will not unduly delay or prejudice an adjudication of Plaintiff's rights. See supra Section II.A. Therefore, the proposed intervenors' motion to file a brief in opposition to Plaintiff's pending motion for a preliminary injunction (Dkt. No. 27) is GRANTED. The briefing schedule for Plaintiff's pending motion for a preliminary injunction is hereby modified as set forth below.
For the foregoing reasons, the proposed intervenors' motion to intervene (Dkt. No. 24) and motion to file a brief in opposition to Plaintiff's pending motion for a preliminary injunction (Dkt. No. 27) are GRANTED. The proposed intervenors' opposition brief shall be filed no later than August 2, 2019. Plaintiff's combined reply to Defendants' response and the proposed intervenors' response shall be filed no later than August 9, 2016 and shall not exceed 24 pages in length. (See Dkt. No. 29 at 3.) The Clerk is DIRECTED to re-note Plaintiff's pending motion for a preliminary injunction (Dkt. No. 15) to August 9, 2019.