ROBERT D. MARTIN, UNITED STATES BANKRUPCY JUDGE.
Debtor, CS Estate, Inc. (CS), filed an objection to the claim of creditor Houlihan Lokey Capital, Inc. (Houlihan). After a preliminary hearing, the parties filed a stipulation requesting a ruling as a matter of law on three issues: (1) the choice of law to be applied in interpreting the contract; (2) whether the Consent Provision is a condition precedent to the formation and enforceability of the Contract, such that the stipulated failure to obtain the executed Consent rendered the contract null and void; (3) whether Houlihan could unilaterally waive the Consent Provision.
CS's predecessor, Cardiac Science Corporation (Cardiac), negotiated with Houlihan regarding Cardiac's engagement of Houlihan as Cardiac's investment banker.
The crux of the parties' disagreement centers on Paragraph 5 of the Contract (Consent Provision). Paragraph 5 provides:
Letter, ¶ 5. DBS Bank Ltd. (DBS) never provided the requested consent. CS argues that because the condition was never satisfied, no enforceable contract was formed.
Two other provisions are implicated. First, the Contract includes a choice of law provision. Paragraph 20 provides (in relevant part):
Letter, ¶ 20.
Second, the Contract includes a section that is explicitly subject to unilateral waiver. Paragraph 16, dealing with "Bankruptcy Court Approval," states: The terms of this Section are solely for the benefit of Houlihan Lokey, and may be waived, in whole or in part, only by Houlihan Lokey. Letter, ¶ 16.
CS argues that the contract's choice-of-law provision should be ignored and that a significant contacts test compels the application of Wisconsin law. Further, CS argues that the Consent Provision is a condition precedent to contract formation, and because the contract is for Houlihan's services, a condition precedent to those services is a condition precedent to the existence of the contract.
Finally, CS argues that Houlihan cannot unilaterally waive the Consent Provision because the Consent Provision is not exclusively for Houlihan's benefit. Both parties had an interest in ensuring "that the Debtor was authorized to engage and pay an investment banker for the purpose of securing additional financing and selling its assets." CS points to Paragraph 16 of the Letter which includes a provision explicitly stating that "the terms of this Section are solely for the benefit of Houlihan Lokey, and may be waived, in whole or in part, only by Houlihan Lokey." From that, it infers that, when the Contract is silent, the parties intend to preclude the unilateral waiver of the Consent Provision.
Houlihan argues that the Contract's choice-of-law provision should be enforced and that the court should not presume the invalidity of the contract. Furthermore, Houlihan argues that courts enforce contractual choice-of-law provisions that do
Houlihan also argues that the plain language of the Contract states that Paragraph 5 expressly conditions Houlihan's performance. And, because the Contract includes an engagement date, the Consent Provision should not be interpreted as a condition on the entire engagement.
Finally, Houlihan argues that the Consent Provision was solely for its own benefit. Thus, it claims the right to unilaterally waive such provision. Houlihan also argues that the unilateral waiver provision in Paragraph 16 of the Contract is inapposite because the nature of that paragraph is entirely different.
The Seventh Circuit has stated: "A contract's choice-of-law provision may not apply if the contract's legality is fairly in doubt, for example, if the contract is unconscionable, or if there is some other issue as to the validity of the very formation of the contract." Life Plans, Inc. v. Sec. Life of Denver Ins. Co., 800 F.3d 343, 357 (7th Cir.2015). In the absence of a contractual choice-of-law provision, Sybron Transition Corp. v. Security Ins. Co. of Hartford, 107 F.3d 1250 (7th Cir.1997) describes Wisconsin's approach:
Sybron Transition Corp., 107 F.3d at 1255 (quoting Hystro Prods., Inc. v. MNP Corp., 18 F.3d 1384, 1387 (7th Cir.1994) (footnote omitted)). The federal approach has been stated by Vanston Bondholders Protective Comm. v. Green, 329 U.S. 156, 161-62, 67 S.Ct. 237, 91 L.Ed. 162 (1946). To wit:
Vanston Bondholders Protective Comm., 329 U.S. at 161-62, 67 S.Ct. 237.
Here, the parties dispute whether the Consent Provision was a condition precedent to contract formation or only to Houlihan's performance under the Contract. Under the Life Plans standard, this is an issue as to the validity of the very formation of the contract. Under either of the choice-of-law approaches,
In Wisconsin: "There is a distinction (often blurred) between a condition
Parkview Gen. Hosp., Inc. v. Eppes, 447 S.W.2d 487, 489 (Tex.Civ.App.1969). Parkview Gen. Hosp. has been approvingly quoted multiple times in Wisconsin, including by the Wisconsin Supreme Court. See Fox v. Catholic Knights Ins. Soc., 263 Wis.2d 207, 665 N.W.2d 181, 189 (2003) (quoting 447 S.W.2d at 490-91) ("Where the parties to the proposed contract have agreed that the contract is not to be effective or binding until certain conditions are performed or occur, no binding contract will arise until the conditions specified have occurred or been performed.").
Regarding, when a court will interpret an ambiguous condition as precedent to formation, the Seventh Circuit has stated:
Nat. Dairymen Ass'n v. Dean Milk Co., 183 F.2d 349, 352-53 (7th Cir.1950).
In Nat. Dairymen Ass'n, the condition read as follows: "This offer is subject to the government's acceptance for export and if a permit is issued for us to ship on above basis, we will try to get you additional quantities at that time." Id. at 350. The offer explicitly asked for an "early reply;" it did not ask for action. Id. The court concluded that the condition as issue was precedent to rights and obligations, not effectiveness of the contract.
The issue has been generally stated as follows:
M. West, Inc. v. Oak Park Mall, L.L.C., 44 Kan.App.2d 35, 234 P.3d 833, 843 (2010) (citations omitted).
In this case the plain language of the Contract imposes a condition precedent to the formation of the contract. The only purpose of the Contract was to gain the performance of Houlihan, so conditioning all that performance on consent of DBS, conditioned the existence of the contract on that consent.
It has long been established that a party can waive a condition precedent that is for its own benefit: "Conditions precedent may doubtless be waived by the party in whose favor they are made." Jones v. United States, 96 U.S. 24, 28, 24 L.Ed. 644 (1877).
In Williston on Contracts:
13 Williston on Contracts § 39.24 (4th ed.)
Under Wisconsin law: "Such a waiver may not be made, however, where the waiver would deprive the non-waiving party of a benefit under the provision in question." Goebel v. First Fed. Sav. and Loan Ass'n of Racine, 83 Wis.2d 668, 266 N.W.2d 352 (1978). When considering whether a provision is for the benefit of both parties, the Wisconsin Supreme Court court stated:
Id. at 497.
The Godfrey court also stated:
Godfrey Co. v. Crawford, 23 Wis.2d 44, 126 N.W.2d 495, 498 (1964).
Here, a unilateral right to waive the condition would be equivalent to creating an indefinite option contract. Like in Godfrey, CS would be indefinitely subject to the initiation of the contract by Houlihan, extending its liability and constraining its ability to pursue alternative options. In short, if a condition is precedent to performance by both parties (because it is precedent to formation), it is difficult to see how that provision could be considered for the benefit of only one party. Therefore, it appears that because the Consent Provision is a condition precedent to formation, Houlihan does not have the right to unilaterally waive the condition.