DAVIS, Justice:
The petitioner herein and defendant/third-party plaintiff below, J.A. Street & Associates, Inc. (hereinafter "Street"), appeals from an order entered September 24, 2010, by the Circuit Court of Cabell County. By that order, the circuit court affirmed its previous order of July 20, 2010, and certified it as a final order pursuant to Rule 54(b) of the West Virginia Rules of Civil Procedure. The July 20, 2010, order granted the partial motion for summary judgment requested by the respondent herein and defendant/third-party plaintiff below, S&ME, Inc. (hereinafter "S&ME"), and dismissed Street's amended cross-claims against S&ME that sought recovery of remediation costs incurred by Street in 2003. The lower court granted partial summary judgment based on its determination that some of Street's cross-claims were time-barred by the applicable statute of limitations
Briefly, this case involves a dispute regarding developed property known as the Merritt Creek Farms Development (hereinafter "Merritt Creek") in Cabell County, West Virginia. The interested parties before this Court are Street, the project's general contractor, and S&ME, a geotechnical engineering firm. While there are only two parties involved in this appeal, a clear understanding of the facts requires a basic knowledge of the other entities who appeared before the circuit court. Thundering Herd Development, LLC., and THD Investors 7, LLC., (hereinafter "THD," collectively) own the development. Bizzack, Inc. (hereinafter "Bizzack"), is a grading contractor, and CTL Engineering of West Virginia, Inc. (hereinafter "CTL"), is an engineering firm. Finally, SITE, Inc. (hereinafter "SITE"), was the civil engineer for the project.
S&ME and Street disagree on several factual assertions, as well as the impact of these disputes on this case. These discrepancies will be discussed, when relevant, in the Discussion section of this Opinion. See generally § IV, infra. A summary of the undisputed facts is as follows.
In 2000, THD began exploring developing ideas for the future Merritt Creek project. THD contracted with S&ME in 2001 for a preliminary geotechnical evaluation of the site, which provided recommendations regarding site preparation.
After receipt of S&ME's report, Street, by letter dated April 22, 2003, wrote to Bizzack, the "land mover" contractor. Street's correspondence informed Bizzack that "S&ME... feels that the placement of the fill was not in accordance with the original recommendation and was the cause of the settlement." The letter further requests Bizzack's opinion regarding placement of fill. Bizzack responded in writing on May 8, 2003, and disputed the assertion that there was any problem with fill placement. Bizzack's letter to Street explained that all fill placement was monitored by CTL, who did not object to any placements or fill materials during site preparation. Bizzack stated that it "believe[s] that the problems that you [Street] are experiencing are not related to the placement of the fill." Street responded to Bizzack on June 2, 2003. The letter detailed some of the repair work and costs that Street had absorbed as a result of the "settlement of Shop `A' which ... has been attributed to filling not in accordance with specifications." Street expressed concern that Bizzack had not followed all soil specifications at construction. Further, Street wrote that "[t]he problem with Shop `A' settlement is coming to a head and we feel a meeting with all parties in the near future will give us direction and determine who is responsible for this failure and the ultimate cost." Subsequently, THD contracted with an engineer, George Cross, who prepared a report in May 2007. Mr. Cross's report noted the presence of groundwater
THD filed its initial complaint in the Circuit Court of Cabell County on June 9, 2003, naming S&ME as the sole defendant. The complaint alleged that S&ME had negligently provided recommendations with respect to site preparation for the Target store area, as well as the remainder of the planned Merritt Creek site. On December 11, 2007, THD amended its complaint to name petitioner, Street, as well as several other defendant entities who are not parties to this appeal. S&ME then cross-claimed against Street and filed third-party claims against CTL and Bizzack. Bizzack then counterclaimed against S&ME. Street filed its answer and counterclaim against THD; and, on January 14, 2008, filed cross-claims against S&ME; and filed third-party claims against CTL and Bizzack.
On December 8, 2009, Street filed a motion for leave to amend its cross-claims, which amendments form the underlying basis of this appeal.
The circuit court granted S&ME's motion for partial dismissal of Street's amended cross-claims,
In so ruling, the lower court determined that Street had knowledge of an independent action against S&ME in 2003;
The appeal before this Court stems from the circuit court's order granting summary judgment in favor of S&ME on its partial motion to dismiss
Syl. pt. 1, Alden v. Harpers Ferry Police Civil Serv. Comm'n, 209 W.Va. 83, 543 S.E.2d 364 (2001).
In undertaking our de novo review, we apply the same standard for granting summary judgment that is applied by the circuit court:
Syl. pt. 2, Painter, 192 W.Va. 189, 451 S.E.2d 755. Moreover,
Syl. pt. 4, Painter, id. We also are cognizant that "[t]he circuit court's function at the summary judgment stage is not to weigh the evidence and determine the truth of the matter, but is to determine whether there is a genuine issue for trial." Syl. pt. 3, Painter, id.
Additionally, resolution of this matter requires the application of a statute:
Syl. pt. 1, State v. Brandon B., 218 W.Va. 324, 624 S.E.2d 761 (2005). To fully dispose of this case, this Court also must analyze Rule 13(g) of the West Virginia Rules of Civil Procedure. In cases where we are called upon to construe a rule, we are guided by the proposition that "[a]n interpretation of the West Virginia Rules of Civil Procedure presents a question of law subject to a de novo review." Syl. pt. 4, Keesecker v. Bird, 200 W.Va. 667, 490 S.E.2d 754 (1997). Mindful of these applicable standards, we proceed to consider the parties' arguments.
On appeal to this Court, Street assigns error to the circuit court's ruling that W. Va.Code § 55-2-21 does not apply to toll the statute of limitations. The circuit court's determination relied on its decision that Street's cross-claims were truly independent causes of action. Alternatively, Street argues that the circuit court incorrectly denied application of the discovery rule to toll the statute of limitations. We will address each of these issues in turn.
Street first argues that the circuit court erred in its finding that its cross-claims were truly independent claims, such that the tolling provision for cross-claims in W. Va.Code § 55-2-21 did not apply. In support of its argument, Street advocates that W. Va.Code § 55-2-21 specifically denotes a cross-claim as an included claim and states that it shall be deemed to toll the running of any statute of limitations with respect to any claim. Thus, Street contends that, as a matter of law, § 55-2-21 tolls the running of the statute of limitations on its cross-claims against S&ME.
S&ME rejects Street's assertion that its claims are properly styled as cross-claims. Rather, S&ME contends that Street's claims are independent claims; therefore, according to S&ME, W. Va.Code § 55-2-21 does not apply to this case. S&ME supports the circuit court's ruling, which stated that
At issue in this case is the construction of W. Va.Code § 55-2-21, which states as follows:
In our analysis of statutes, we have explained that the first step is to identify the intent expressed by the Legislature in promulgating the provision at issue. "The primary object in construing a statute is to ascertain and give effect to the intent of the Legislature." Syl. pt. 1, Smith v. State Workmen's Comp. Comm'r, 159 W.Va. 108, 219 S.E.2d 361 (1975). Then, we study the particular language used by the Legislature. "Where the language of a statute is clear and without ambiguity the plain meaning is to be accepted without resorting to the rules of interpretation." Syl. pt. 2, State v. Elder, 152 W.Va. 571, 165 S.E.2d 108 (1968). Accord Syl. pt. 5, State v. Gen. Daniel Morgan Post No. 548, Veterans of Foreign Wars, 144 W.Va. 137, 107 S.E.2d 353 (1959) ("When a statute is clear and unambiguous and the legislative intent is plain, the statute should not be interpreted by the courts, and in such case it is the duty of the courts not to construe but to apply the statute."); Syl. pt. 2, State v. Epperly, 135 W.Va. 877, 65 S.E.2d 488 (1951) ("A statutory provision which is clear and unambiguous and plainly expresses the legislative intent will not be interpreted by the courts but will be given full force and effect.").
Applying these principles to the current statute under review, we find that the wording is clear: "After a civil action is commenced, the running of any statute of limitation shall be tolled for ... the pendency of that civil action as to any claim
Accordingly, based on the nondiscretionary, mandatory language of the statute, we hold that, pursuant to W. Va.Code § 55-2-21 (1981) (Repl.Vol.2008), during the pendency of a civil action, the statute of limitation shall be tolled as to any cross-claim that has been or may be asserted therein.
This clear language illustrates the fallacy in the circuit court's reasoning that "[Street] cannot use W. Va.Code § 55-2-21 to excuse its own lack of diligence over the course of five years in pursuing a claim that it knew or should have known of as far back as 2003." The circuit court's rationale adds an element to the statute that simply does not exist: the statute does not require a showing of due diligence in bringing a cross-claim. It simply states that the statute of limitation is tolled as to any cross-claims that may be filed while the civil action is pending.
To be clear, the parties do not offer different interpretations of the statute. Instead, they disagree as to whether the statute applies in the first instance, which application is based on the classification of Street's claims against S&ME as either a cross-claim or as an independent cause of action. While W. Va.Code § 55-2-21 speaks to the filing of a cross-claim, it is silent as to the definition of a cross-claim. The trial court determined that Street's claims are not properly classified as cross-claims; however, the trial court's order is devoid of any analysis of the definition of a cross-claim within the meaning of Rule 13(g) of the West Virginia Rules of Civil Procedure. Rule 13(g) provides:
W. Va. R. Civ. P. 13(g).
The key language in this Rule defining "cross-claims" is the phrase "arising out of the transaction or occurrence." While we have discussed this expression in regard to other rules, it does not appear that this Court has ever addressed this language under the specific rule, Rule 13(g), at issue herein. It has been noted, with reliance on the case of Maritime Ventures International, Inc. v. Caribbean Trading & Fidelity Ltd., 689 F.Supp. 1340 (S.D.N.Y.1988), that
Franklin D. Cleckley, Robin J. Davis, & Louis J. Palmer, Jr., Litigation Handbook on the West Virginia Rules of Civil Procedure, § 13(g), at 392 (3d ed.2008). It has been recognized that the common requirement in Rules 13(a) and 13(g) that claims arise from the same transaction or occurrence results in the Rule 13(a) definition being instructional to the definition of the same terms used in Rule 13(g). See generally Painter v. Harvey, 863 F.2d 329 (4th Cir.1988). Factors to consider, as pointed out in Painter, are as follows: (1) Are the issues of fact and law largely the same? (2) Will substantially the same evidence support or refute the complaint as well as the cross-claim? (3) Is there any logical relationship between the complaint and the cross-claim?
Returning to the case sub judice, we find that the circuit court prematurely found that W. Va.Code § 55-2-21 did not apply. Prior to such a determination, a proper analysis of Street's claims is required. If the claims arose out of the same transaction or occurrence as the original action, then they are properly classified as cross-claims such that the statute of limitations would be tolled pursuant to W. Va.Code § 55-2-21. The lower court stated that Street's claims were not cross-claims, but, rather, were independent causes of action. In light of the lower court's failure to analyze whether the claims arose from the same transaction or occurrence and, thus, constituted cross-claims or independent causes of action, this issue is reversed and remanded to provide the circuit court an opportunity to apply the test set forth in this Opinion.
Street argues, alternatively, that the circuit court incorrectly denominated its claims against S&ME as an independent cause of action and applied the discovery rule to bar the same. In support of its argument, Street sets forth that it was injured when it incurred significant expenses and costs in an effort to repair the Shops A area. Street, as well as THD, had contacted S&ME to investigate and determine a resolution for the problem and Street had followed the recommendations contained in S&ME's report. The opinion of S&ME was that the damage had been caused by problems with the fill. As a general contractor, Street asserts that it could not have known that groundwater was the significant contributing cause of the settlement until the 2007 engineering report, which was the earliest date upon which the statute of limitations could begin to run.
In response, S&ME states that whether an entity knows of, or should know of, a cause of action is an objective test. Regardless of the actual problem causing ground settlement, S&ME urges that Street was aware that a problem existed as far back as 2003. According to S&ME, Street had a duty to investigate at the time that the problem was known; however, Street failed to perform its own investigation. Thus, S&ME contends that there is no material question of fact as to when Street knew there was a problem, and the summary judgment should be upheld.
In Syllabus point 5 of Dunn v. Rockwell, 225 W.Va. 43, 689 S.E.2d 255 (2009), we held as follows:
We need not analyze all of the Dunn factors because there are clearly material issues of fact such that summary judgment was improper in the alleged independent cause of action. In so finding, we are mindful that "`[t]he circuit court's function at the summary judgment stage is not to weigh the evidence and determine the truth of the matter, but is to determine whether there is a genuine issue for trial.' Syllabus point 3, Painter v. Peavy, 192 W.Va. 189, 451 S.E.2d 755 (1994)." Syl. pt. 3, Toth v. Bd. of Parks & Recreation Comm'rs, 215 W.Va. 51, 593 S.E.2d 576 (2003). Further,
Syl. pt. 5, Toth, 215 W.Va. 51, 593 S.E.2d 576.
While the circuit court specifically found in its order that Street knew or should have known of the presence of groundwater and should have sought out answers starting in 2003, Street asserts that it had no way of knowing of the groundwater presence until 2007. Significantly, Street points out that it did take steps in 2003 to determine the cause of the problem. Those steps led Street to rely on the expertise of S&ME, who opined that the problem was related to fill placement. Street had no reason to doubt the accuracy of S&ME's conclusions until 2007. The engineer who issued the report in May 2007 testified that groundwater could have been addressed in the site construction method if it had been detected or known; that the groundwater contributed to the settlement and continued deterioration under Shops A; that the groundwater placed pressure upon and influenced the building movement; and that he could not find any prior soil borings or monitoring in the lower end of the development where Shops A is located.
Street disagrees with the circuit court's finding that Street received two reports in 2003 that should have alerted it to the groundwater issue. The reports received by Street may have observed the presence of groundwater; however, as asserted by Street, those reports indicated the settlement damage was caused by improper fill placement and never attributed such problems to the presence of groundwater. Street continues its argument by delineating that the connection between the groundwater and the settlement damage was not evident until the 2007 report by Mr. Cross. Further, there is a disagreement as to when the Shops A area became a part of the original action, as well as when it became a part of the purported cross-claims filed by Street against S&ME. These disputed facts are merely examples of the factual issues that should have been resolved by the trier of fact.
In summary, we agree with Street's argument that genuine issues of material fact exist so as to preclude summary judgment if its claim is an independent cause of action. This issue is reversed and remanded to the circuit court.
On remand, if the circuit court determines that Street's claims meet the test to be cross-claims, then W. Va. § 55-2-21 applies to toll the running of the statute of limitations. Should the circuit court determine that Street's claims were independent causes of actions rather than cross-claims, genuine issues of material fact exist such that a trier of fact should determine if and when the discovery rule should be applied.
For the foregoing reasons, the orders of the Circuit Court of Cabell County are hereby
Reversed and Remanded.
Chief Justice WORKMAN and Justice KETCHUM concur in part, and dissent in part, and reserve the right to file separate opinions.
WORKMAN, Chief Justice, concurring, in part, and dissenting, in part:
I concur with the majority's holding that W. Va.Code § 55-2-21 (1981) (Repl.Vol.2008) tolls the statute of limitation during a pending civil action as to any cross-claim that has been or may be asserted therein. I also concur with the new syllabus point created by the majority in this case which sets forth the factors to be considered in determining whether a cross-claim arises out of the same transaction or occurrence as the original action. I dissent, however, to the majority's decision to remand this case to the circuit court to determine whether the claims asserted by J.A. Street & Associates, Inc., ("Street") in December 2009 constitute cross-claims or independent causes of action. I would have applied the new test created by the majority in Syllabus Point 9 and concluded that as a matter of law, the claims asserted by Street in December 2009 are in fact cross-claims.
Upon review of the record, it is clear that the amended cross-claims asserted by Street on December 8, 2009, arise out of the same transaction as the original action. The allegations in both the original action and the amended cross-claims stem from the construction of the Merritt Creek Farms Development and, in particular, from the preliminary geotechnical evaluation of the site that was prepared by S & ME, Inc. ("S & ME"). In that regard, the original action filed by Thundering Herd Development, L.L.C., ("THD") alleged that S & ME had negligently provided recommendations with respect to the site preparation for the Target store location as well as the remainder of the development resulting in unanticipated settling of the fill material on certain portions of the property. Likewise, Street's amended cross-claims alleged that S & ME negligently failed to perform a thorough, complete and competent geotechnical exploration and investigation of the construction site and that it negligently failed to discover the presence or effect of ground water resulting in the settling of the fill material at the Shops A site and causing Street to incur costs to repair the settlement damage.
Although this litigation was initiated in 2003, the plaintiff, THD, did not amend its complaint to assert a cause of action against Street until 2007. Until then, Street had no need or reason to initiate litigation of its own against S & ME. Given all the above, resolution of both the original action and the cross-claims will require consideration of the same facts and law. The same evidence will support or refute both the complaint and the cross-claims. Also, without question, there is a logical relationship between the original claim and the cross-claims.
Because the cross-claims asserted by Street clearly arise out the same transaction as the original action, there was no need for this Court to remand this case to the circuit court to make a determination on this issue. The circuit court's order granting S & ME's motion for partial summary judgment should have been reversed, and this case should have been remanded for further proceedings with a finding that the claims asserted by Street in December 2009 clearly are proper cross-claims that are not barred by the applicable statute of limitation pursuant to W. Va.Code § 55-2-21.
For the reasons set forth above, I concur, in part, and dissent, in part, to the majority's decision in this case. I am authorized to state that Justice Ketchum joins me in this separate opinion.