FREDERICK P. STAMP, Jr., District Judge.
The plaintiff has filed a motion to withdraw its jury demand and to strike the jury demand contained in the amended intervenor-complaint. The defendant and the intervenor-plaintiff oppose the plaintiff's request to withdraw its jury demand, and the intervenor-plaintiff opposes the plaintiff's request to strike the intervenor-plaintiff's jury demand. This memorandum opinion and order sets forth in detail this Court's prior oral ruling made at the telephonic status and scheduling conference held on October 31, 2016. For the following reasons, the plaintiff's motion is denied.
The plaintiff, Turner Construction Co. ("Turner"), entered into a contract with the Federal Bureau of Investigation ("FBI") to build facilities in Clarksburg, West Virginia. After initially engaging Institutional Products, Inc. in a subcontract to provide millwork, Turner entered into a subcontract with Designer's Specialty Cabinet Company doing business as Designer's Specialty Millwork ("DSM") to replace Institutional Products, Inc. The original defendant, American Safety Casualty Insurance Company ("ASCIC"), issued a performance bond guaranteeing DSM's performance of the subcontract. The performance bond incorporated by reference the subcontract's terms, including a provision indemnifying Turner against any increased costs due to a slow-down or breach of the subcontract. Turner alleges that DSM defaulted on the subcontract by improperly staffing the project, by providing late supplies deliveries, and by ignoring directions from Turner and the FBI. Turner then exercised the subcontract's alternative completion clause and engaged another subcontractor to complete the project.
Turner filed this civil action against ASCIC to collect under the indemnification clause of the subcontract as incorporated into the performance bond. Turner's complaint "DEMANDS A JURY ON ALL ISSUES SO TRIABLE." ECF No. 1 at 10. TIG Insurance Company ("TIG") has since replaced ASCIC as the defendant as ASCIC's successor by merger. DSM has been permitted to join the action as an intervenor-plaintiff, with Turner and the Miller Act sureties named as intervenor-defendants.
In its amended intervenor-complaint, DSM alleges that it is entitled to payment of the Miller Act bonds by the sureties and asserts claims against Turner for breach of contract, fraudulent inducement, common law fraud, and cardinal change. Turner filed a counterclaim against DSM for breach of contract. DSM's original intervenor-complaint did not include a jury demand, but its amended intervenor-complaint does include a jury demand.
Federal Rule of Civil Procedure 38(b) provides that a party may demand a jury trial "[o]n any issue triable of right by a jury." Fed. R. Civ. P. 38(b). A party may withdraw its jury demand "only if the parties consent." Fed. R. Civ. P. 38(d). Under Rule 39(a), a court may strike a party's jury demand if the court "finds that . . . there is no federal right to a jury trial" on the issues for which a jury trial was demanded. Fed. R. Civ. P. 39(a)(2).
Turner's complaint "DEMANDS A JURY ON ALL ISSUES SO TRIABLE." ECF No. 1 at 10. ASCIC's original answer and TIG's amended answer do not include a jury demand. DSM's original intervenor-complaint did not include a jury demand, but its amended intervenor-complaint does include a jury demand. Neither TIG nor DSM consent to Turner's motion to withdraw its jury demand. Turner argues that TIG and DSM's consent is not required to withdraw its jury demand because neither party relied on Turner's jury demand.
First, Turner argues that ASCIC and TIG waived their rights to a jury trial by not relying on Turner's jury demand because "there is no evidence that ASCIC, the party against whom the jury demand was made, had any intention of relying on Turner's jury demand or that it failed to make its own jury demand in reliance on Turner's jury demand." ECF No. 109 at 4. However, the right to a jury trial is a fundamental right; thus, waivers of that right are heavily scrutinized and "courts indulge every reasonable presumption against" such waivers.
Second, Turner argues that DSM's consent is irrelevant because DSM contractually waived its right to a jury trial. While it is true that consent is not required from a party that does not have a right to a jury trial,
Turner argues that DSM's jury demand should be stricken because DSM contractually waived its right to a jury trial and, alternatively, because its jury demand is untimely. For the following reasons, this Court finds that DSM's claims are embraced by Turner's jury demand, that DSM did not contractually waive its right to a jury trial, and that DSM's jury demand should not be stricken.
As a preliminary matter, DSM's claims against Turner are embraced by Turner's jury demand and DSM's demand is superfluous, regardless of whether DSM waived its right to a jury trial.
Rule 38(d)'s consent-to-withdrawal requirement means that "once one party files . . . a [jury] demand other parties are entitled to rely on that demand for the issues it covers, and need not file their own demands."
Turner made a general jury demand in its complaint, embracing all issues raised in the complaint. This demand necessarily "extends even to issues raised by the opposing party"; originally ASCIC, now TIG.
Because ASCIC and now TIG are DSM's sureties, they are entitled to raise any defenses that DSM could raise. To that end, ASCIC's original answer and TIG's amended answer each incorporate by reference all DSM's affirmative defenses to Turner's counterclaim against DSM. ECF Nos. 98 at 7, 234 at 8. Those affirmative defenses include: (1) that DSM's performance was excused due to Turner's material breaches of the subcontract, ECF No. 91 at 3-5, 8; (2) that Turner fraudulently misled DSM and its surety in the course of performance,
In its amended intervenor-complaint, DSM alleges that Turner breached the subcontract, that DSM is entitled to payment of the Miller Act bonds by the sureties because of Turner's breach, that Turner fraudulently induced DSM to enter into the subcontract, that Turner committed common law fraud in the course of performance, and that Turner affected a cardinal change to the subcontract. Each of these claims is co-extensive with ASCIC and TIG's affirmative defenses. Because DSM's claims are identical to TIG's affirmative defenses, DSM's claims do not raise new issues. Thus, Turner's jury demand embraces DSM's claims regardless of whether DSM has a right to a jury trial on those claims.
Turner argues that Article XXXIII of the subcontract between it and DSM constitutes a waiver of DSM's right to a jury trial. "The Seventh Amendment right is of course a fundamental one, but it is one that can be knowingly and intentionally waived by contract."
Article XXXIII of the subcontract, with the header "Dispute Resolution," provides in full:
ECF No. 109-2 at 11-12 (emphasis added).
This Court finds the jury waiver's scope to be ambiguous. It is unclear whether the waiver applies to disputes between Turner and the FBI implicating DSM's work, to disputes between Turner and DSM, or to both. The final paragraph of Article XXXIII deals both with disputes between DSM and Turner and with disputes between Turner and the FBI relating to DSM's work. The jury waiver clause uses "the dispute" as an unqualified term, making it unclear to which type of dispute it refers. Further, the preceding paragraphs of Article XXXIII all deal with how the results of disputes between Turner and the FBI affect DSM. The term "the dispute" may reasonably be interpreted to apply to either disputes between DSM and Turner, disputes between Turner and the FBI involving DSM's work, or both.
Turner also argues that DSM waived its right to a jury trial by failing to make a timely jury demand. A jury demand is timely if it has been served on all other parties "no later than 14 days after the last pleading directed to the issue is served." Fed. R. Civ. P. 38(b)(1). Where an amended pleading raises new issues not contained in the original pleadings, the amended pleading is the "last pleading" for the purpose of the new issues.
Although this Court finds that DSM's claims are embraced by Turner's jury demand, if they are not, then they would constitute new issues for which DSM was permitted to demand a jury trial. Thus, DSM's jury demand would be timely as to the new claims raised in the amended intervenor-complaint because the amended-intervenor complaint would be the "last pleading" as to those issues.
For the foregoing reasons, Turner Construction Co.'s motion to withdraw its jury demand and to strike DSM's jury demand (ECF No. 109) is DENIED. Turner's jury demand, contained in the complaint, embraces all issues raised in this civil action.
IT IS SO ORDERED.
The Clerk is DIRECTED to transmit a copy of this memorandum opinion and order to counsel of record herein.