FREDERICK P. STAMP, Jr., District Judge.
This is a Miller Act, 40 U.S.C. §§ 3131-3133, case arising out of an alleged breach of a subcontract on a government construction project. Turner Construction Company ("Turner"), entered into a contract with the Federal Bureau of Investigation ("FBI") to build the Biometric Technology Center at the FBI CJIS Division Complex in Clarksburg, West Virginia. Turner entered into a subcontract with Modern Mosaic, Ltd. ("Modern Mosaic") to fabricate and install concrete panels for two structures as part of the FBI project, one of which was a preexisting parking garage. During the course of Modern Mosaic's performance, Modern Mosaic was required to provide additional labor, materials, and equipment totaling $1,264,131.31. Modern Mosaic filed this civil action under the Miller Act against Turner and its sureties for breach of contract, to collect outstanding payments, and to enforce the Miller Act bonds. The defendants filed a motion for partial summary judgment regarding additional work and increased costs on the parking garage, totaling $975,072.31. For the following reasons, that motion is granted.
Turner and Modern Mosaic entered into the Subcontract on May 22, 2011, providing that Modern Mosaic would fabricate and install precast concrete panels for two structures.
As part of the approval process, the dimensions of the parking garage were to be "field verified" to ensure that they matched the parking garage's plans and specifications.
Modern Mosaic submitted a total of four shop drawings for the parking garage panels. These included designs for two broad sets of panels, those designed to fit between columns on the parking garage in a straight line ("the flat-wall panels") and those designed to be installed on the corners of the structure ("the corner panels"). ECF No. 45-2 at 11. Modern Mosaic's first set of shop drawings was returned stamped "Revise & Resubmit" on August 23, 2011. ECF No. 39-7 at 1. The second set was returned stamped "Revise & Resubmit" on October 11, 2011. ECF No. 39-8 at 1. On January 5, 2012, Modern Mosaic began fabricating the flat-wall panels, continuing fabrication through February 1, 2012. ECF Nos. 39-13 at 6, 20; 45-1 at 5; 45-2 at 11. Modern Mosaic's third set of shop drawings was returned stamped "Revise & Resubmit" on February 3, 2012. ECF No. 39-15.
At Modern Mosaic's request, on March 1, 2012, Thrasher surveyed the entire parking garage to verify its dimensions and discovered discrepancies between the parking garage's plans and specifications and its as-built conditions. ECF No. 39-19. On March 21, 2012, Modern Mosaic sent a letter to Turner notifying it of dimensional discrepancies. ECF No. 39-19. After receiving this letter, Turner forwarded the notice of discrepancies to the FBI and requested that it expedite resolution of the discrepancies. ECF No. 39-22 at 2. Later that month, Modern Mosaic sent Turner another letter suggesting certain changes to the dimensions of four different panels. ECF No. 39-20.
On April 4, 2012, Modern Mosaic submitted its fourth set of shop drawings. These were returned on April 16, 2012 stamped "Approved as Noted" with notations from the architect stating that the location of the embeds needed to be field verified. ECF No. 39-18. Modern Mosaic then began fabricating panels for the corner portions of the parking garage ("the corner panels"). ECF No. 45-2 at 11.
On May 4, 2012, Modern Mosaic sent Turner a letter noting that the parking garage was not square and plumb, causing a "dimensional bust." ECF No. 39-23. Then, on June 3, 2012, Modern Mosaic sent Turner a letter stating that it must redesign a number of panels because of the dimensional discrepancies. ECF No. 39-24. Modern Mosaic claims that the dimensional discrepancies caused the corner panels to not fit properly but that the flat-wall panels were not affected. ECF Nos. 45-1 at 5; 45-2 at 11. Modern Mosaic then had to refabricate the affected corner panels to fit the structure and pay for storage for the unaffected flat-wall panels for later installation. ECF No. 45-1 at 5, 45-2 at 11. Turner did not pay Modern Mosaic for the costs of refabrication and storage resulting from the discrepancies and delays. Modern Mosaic claims that it is entitled to payments of those as damages totaling $975,072.31.
Under Federal Rule of Civil Procedure 56, this Court must grant a party's motion for summary judgment if "there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). A fact is "material" if it might affect the outcome of the case.
The party seeking summary judgment bears the initial burden of showing the absence of any genuine issues of material fact.
Turner argues that it is entitled to summary judgment as to the parking garage claims because Modern Mosaic is responsible for its own damages. Turner's argument turns on two key issues. First, whether Modern Mosaic was obligated to conduct field verification of the parking garage before fabricating and installing the panels. Second, whether Modern Mosaic breached the Subcontract and must bear its own damages.
Turner argues that the Subcontract unambiguously obligated Modern Mosaic to field verify the dimensions of the parking garage before fabrication. Modern Mosaic argues that the Subcontract is ambiguous regarding who was obligated to field verify the structure, creating a genuine issue of material fact. Contract interpretation is a legal issue to be determined by the Court.
A "valid written instrument which expresses the intent of the parties in plain and unambiguous language is not subject to judicial construction or interpretation but will be applied and enforced according to such intent."
"The mere fact that parties do not agree to the construction of a contract does not render it ambiguous."
Article XI of the Subcontract provides that "[n]otwithstanding the dimensions of the Plans, Specifications and other Contract Documents it shall be the obligation and responsibility of the
ECF No. 39-2 at 4. Attachment AP-1 to the Subcontract defines the scope of Modern Mosaic's work and provides that Modern Mosaic "shall verify and accept existing conditions
ECF No. 39-2 at 13 (emphasis added). It further provides that each of Modern Mosaic's shop drawing submissions "must be formally certified . . . stating they have carefully reviewed the submittal, verified against field conditions
The Subcontract makes clear that Modern Mosaic was obligated to field verify the dimensions of the parking garage before submitting its shop drawings for approval and before fabricating the panels. Further, Modern Mosaic was obligated to report any discrepancies or defects it found in the structure to Turner with sufficient time for Turner and the FBI to remedy the defects. Because the Subcontract unambiguously obligated Modern Mosaic to field verify the parking garage's dimensions, this Court rejects Modern Mosaic's appeals to prior and contemporaneous documents not incorporated by reference into the Subcontract and the parties' communications and stated understandings after the Subcontract was executed.
Nevertheless, Modern Mosaic proffers two arguments against this interpretation. First, Modern Mosaic argues that the prime contract obligated Turner to verify all existing conditions, remedy any "conditions detrimental to the proper and timely completion of the Work," and to "not proceed until unsatisfactory conditions have been corrected." ECF No. 39-3 at 2. However, Article II of the Subcontract contains what is commonly referred to as a "flow down" clause, and provides:
ECF No. 39-2 at 1 (emphasis added). Thus, while Modern Mosaic is correct that the General Contract obligated Turner to conduct all necessary field verification, the Subcontract's flow down provision along with the specific provisions discussed above obligated Modern Mosaic to conduct field verification as it pertained to the work in the Subcontract. Thus, this Court finds that the Subcontract unambiguously obligated Modern Mosaic to field verify the dimensions of the parking garage before fabricating the panels.
Second, Modern Mosaic argues that Attachment AP-3 to the Subcontract includes "alternate" terms for the Subcontract that Turner could exercise by issuing a change order. AP-3 indicates that "Option #1" was "Not Exercised." ECF No. 45-3 at 46. Option #1 is not defined in the document. ECF No. 45-3 at 46. Modern Mosaic argues that its bid included an optional addition entitled "Add for survey of Structure and embeds at precast locations only," ECF No. 45-5 at 2, which it argues is "Option #1" in AP-3. Modern Mosaic argues that Turner did not exercise that option and, thus, retained its obligation to field verify the structure. It argues that this is in conflict with other portions of the Subcontract, making the it ambiguous as to who was obligated to field verify the parking garage.
However, Modern Mosaic's argument is flatly contradicted by the clear terms of the Subcontract. Option #1 is undefined in the Subcontract and the parties offer competing definitions. However, this disagreement does not create a latent ambiguity because the Subcontract unambiguously obligated Modern Mosaic to field verify the parking garage's dimensions.
Further, Article XXXVII of the Subcontract provides that the document "constitutes the entire agreement" between the parties and that "[n]o oral representations or other agreements have been made. . . except as stated in the [Subcontract]." ECF No. 39-2 at 5. The parties have offered no evidence to the contrary, and this Court finds the Subcontract to be a fully integrated written contract. Thus, Modern Mosaic's reliance on its bid is irrelevant because the bid was not incorporated by reference into the subcontract. The Subcontract's clear, unambiguous language obligated Modern Mosaic to field verify the parking garage's dimensions before fabricating any panels.
Having found that Modern Mosaic was obligated to field verify the dimensions of the parking garage before fabricating the panels, this Court must now determine whether Modern Mosaic defaulted on that obligation. Turner argues that Modern Mosaic fabricated the flat-wall panels before its shop drawings were approved and that Modern Mosaic fabricated the corner panels before field verifying the parking garage's dimensions. Modern Mosaic argues that it received approval for all panels before fabrication.
First, Modern Mosaic breached the Subcontract by fabricating the flat-wall panels before receiving proper approval of its shop drawings and before field verifying the parking garage's dimensions. Modern Mosaic argues that its second set of shop drawings, which were returned on October 11, 2011 stamped "Revise & Resubmit," specifically noted that the flat-wall panels were "accepted as noted." ECF No. 45-11. Modern Mosaic began fabricating the flat-wall panels in January 2012, after this alleged approval. However, under § 013000 of the General Contract, revise and resubmit "means that a portion of the submittal does not comply with the design intent of the Contract Documents and that
Second, Modern Mosaic breached the Subcontract by fabricating the corner panels in the face of known dimensional discrepancies. Modern Mosaic field verified the parking garage's dimensions on March 1, 2012 and informed Turner of the dimensional discrepancies it found on March 21, 2012. ECF No. 39-19. Turner then forwarded those discrepancies to the FBI and asked the FBI to expedite its review and resolution of the discrepancies so Modern Mosaic's work could proceed. ECF No. 39-22 at 2. Modern Mosaic continued to inform Turner of additional discrepancies as Thrasher discovered them through continued analysis of its survey data. ECF Nos. 39-19 at 1; 39-20; 39-21 at 2; 39-23. Although Modern Mosaic's fourth set of shop drawings was returned "Approved as Noted" on April 16, 2012, Modern Mosaic's letters to Turner from April to June 2012 indicate that Modern Mosaic was aware of dimensional discrepancies affecting its now approved corner panels and that those discrepancies had not yet been resolved by Turner, the architect, or the FBI.
Article XII of the Subcontract provides that "[a]pproval of such shop drawings . . . shall not relieve [Modern Mosaic] . . . of its responsibility for the proper matching and fitting of the [panels] with contiguous work." ECF No. 39-2 at 4. Further, attachment AP-5 to the Subcontract provides that: "Each submittal must be formally certified . . . and approved by the Subcontractor prior to submission, stating they have carefully reviewed the submittal [and] verified against field conditions
Nevertheless, Modern Mosaic argues that it was unable to field verify the parking garage before fabrication because Turner failed to provide Modern Mosaic with the "Building Control Lines" so that it could field verify the garage. Attachment
ECF No. 45-3 at 51 (emphasis added). The term "Flatwork Contractor" is not defined in the Subcontract. However, the Subcontract, and specifically AP-5, uses the proper nouns "Contractor" to refer to Turner and "Subcontractor" to refer to Modern Mosaic. These proper nouns make clear that "Flatwork Contractor" references some third party. Thus, the Subcontract provides that the Flatwork Contractor was obligated to provide initial building control points and benchmarks, and that Modern Mosaic was "responsible for providing [its] own layout and control." ECF No. 45-3 at 51. Turner was not obligated to provide building controls for Modern Mosaic, and Modern Mosaic's obligation to fabricate panels for the as-build structure was not absolved because the initial building controls. Modern Mosaic fabricated the flat-wall panels before its shop drawings were approved and fabricated the corner panels in the face of known dimensional discrepancies. Thus, Modern Mosaic's damages were the result of its own breach of the Subcontract.
This Court finds that there is not genuine issue of material fact regarding the parties' contractual obligations and performance of the Subcontract regarding the parking garage. Turner Construction Company is entitled to judgment as a matter of law as to Modern Mosaic, Ltd.'s parking garage claims. Accordingly, the defendants' motion for partial summary judgment (ECF No. 39) is GRANTED.
IT IS SO ORDERED.
The Clerk is DIRECTED to transmit a copy of this memorandum opinion and order to counsel of record herein.