Recommendation Based upon the above findings of fact and conclusions of law it is recommended that the permit requested be issued in accordance with the recommendations and special provisions set forth in the staff report (attached thereto). Respectfully submitted this 3rd day of November, 1975, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of November, 1975. COPIES FURNISHED: Thomas C. Garwood, Jr., Esquire Post Office Box 231 Orlando, Florida 32802 John Wheeler, Esquire Post Office Box V West Palm Beach, Florida
The Issue Whether the applicants own the property in question? Whether the project would comply with the criteria of the South Florida Water Management District contained in Basis of Review for Surface Water Management Systems, specifically Sections 3.1.3 and 3.2? Whether flood protection would be inadequate or septic tanks unsuitable or whether the public health and safety would be compromised or the ultimate purchasers be deprived of usage of the property due to inundation in violation of Chapter 373, Florida Statutes (1981), or Rule 40E-4.301(1), Florida Administrative Code?
Findings Of Fact Ms. Williamson and Messrs. Leggett and Collins hold in fee simple a triangular 117.24-acre parcel in Okeechobee County as tenants in common under a warranty deed executed in their favor by one W. C. Sherman. They propose to develop the property as a trailer park (complete with airstrip) large enough to accommodate 109 trailers. To this end, soil would be dug up from the center of the property and used to raise the elevation of the surrounding land above the 100-year floodplain. (T. 47) The applicants have a dredging permit from the Department of Environmental Regulation authorizing them to excavate 629,889 cubic yards. They are proposing to dig to a depth of 76 feet below ground. This would create an 18-acre body of water ("Poe's Lake") which would overflow a V-notched weir into a county canal. The county canal would take the water to C- 38, one of the large canals to which the Kissimmee River has been relegated, at a point about 18 miles upstream from Lake Okeechobee. Runoff would wash over residential lots and roadways; the site would be graded to assure drainage into Poe's Lake. The minimum road crest elevation would be 30 feet NGVD ("[a]round twenty-nine feet" T.52), as compared to the control elevation for surface waters of 28.5 feet NGVD. WATER QUALITY The developers plan septic tanks for wastewater treatment. At the close of all the evidence, counsel for the applicants stated that sanitary sewers could be installed instead. Respondents' Proposed Recommended Order, p. With all the housing units in use, at least 10,900 gallons of effluent would seep into the ground from the tanks daily. There would be some evapotranspiration, but all the chemicals dissolved in the effluent would eventually end up in the groundwater. During the dry season, septic tank effluent would cause mounding of the groundwater and some groundwater movement toward, and eventual seepage into, Poe's Lake. The eventual result would be eutrophication and the growth of algae or macrophytes on the surface of Poe's Lake. This would cause dissolved oxygen violations in Poe's Lake. Discharges from the lake would inevitably occur, aggravating the situation in C-38, which already experiences dissolved oxygen levels below 5.0 milligrams per liter in the rainy summer months. Some fraction of the nutrients in the effluent from the septic tanks would ultimately reach Lake Okeechobee itself. The sheer depth of the excavation would create another water quality problem. Under the anaerobic conditions that would obtain at the bottom of Poe's Lake, bacteria acting on naturally occurring sulfates would produce hydrogen sulfide, ammonia and various other reduced organic nitrogen compounds. These substances are toxic to human beings and would, in some indeterminate quantity, enter the groundwater from Poe's Lake. This would affect the taste and perhaps the potability of water from any well nearby. It would be "possible to design a better system where there would be nutrient removal and a greatly reduced probability of violation of the dissolved oxygen criterion and obviation of the potential for ground water contamination." (T. 200) Installation of a baffle on the weir would serve to prevent buoyant debris from entering surface waters of the state. BASIS OF REVIEW Official recognition was taken of the "Basis of Review for Surface Water Management Permit Applications Within the South Florid Water Management District," parts of which all parties agree pertain in the present proceedings. Among the criteria stated in this document are: 3.1.3 Waste and Wastewater Service - Potable water and wastewater facilities must be identified. The Applicant for a Surface Water Management Permit must provide information on how these services are to be provided. If wastewater disposal is accomplished on-site, additional information will normally be requested regarding separation of waste and storm systems. 3.2.1.4 Flood protection - Building floors shall be above the 100 year flood elevations, as determined from the most appropriate information, including Federal Flood Insurance Rate Maps. Both tidal flooding and the 100 year, 3 day storm event shall be considered in determining elevations. b. Commercial and industrial projects to be subdivided for sale are required to have installed by the permittee, as a minimum, the required water quality system for one inch of runoff detention or one half inch of runoff retention from the total developed site. State standards - Projects shall be designed so that discharges will meet State water quality standards, as set forth in Chapter 17-3, Retention/detention criteria - Retention and/or detention in the overall system, including swales, lakes, canals, greenways, etc., shall be provided for one of the three following criteria or equivalent combinations thereof . . . Wet detention volume shall be provided for the first inch of runoff from the developed project, or the total runoff from a 3-year, 1-hour rainfall event, whichever is greater. Dry detention volume shall be provided equal to 75 percent of the above amounts computed for wet detention. Retention volume shall be provided equal to 50 percent of the above amounts computed for wet detention. 3.2.4.1 Discharge structures should include gratings for safety and maintenance purposes. The use of trash collection screens is desirable. Discharge structures shall include a "baffle" system to encourage discharge from the center of the water column rather than the top or bottom. 3.2.4.4.2 b. Control elevations should be no higher than 2 feet below the minimum road centerline elevation in the area served by the control device in order to protect the road subgrade. Simply detaining runoff before discharging it offsite will not insure that the water quality standards set forth in Chapter 17-3 will be met. Whether the standards are met depends on, among other things, the composition of the runoff. FWF'S INTEREST Among the purposes of the FWF, as stated in its charter, Shall be to further advance the cause of conservation in environmental protection, to perpetuate and conserve fish and wildlife, oil, water, clean air, other resources of the State and so manage the use of all natural resources, that this generation and posterity will receive the maximum benefit from the same. (T. 248-9) Four or five thousand Floridians belong to FWF. FWF members "make use" (T. 250) of the waters of Lake Okeechobee, the Kissimmee River and specifically of the waters in C-38. PROPOSED FINDINGS CONSIDERED The applicants and FWF filed post hearing memoranda and proposed recommended orders including proposed findings of fact which have been considered in preparation of the foregoing findings of fact. They have been adopted, in substance, for the most part. To the extent they have been rejected, they have been deemed unsupported by the weight of the evidence, immaterial, cumulative or subordinate.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That SFWMD deny the pending application for surface water management permit. DONE and ENTERED this 29th day of November, 1983, in Tallahassee, Florida. ROBERT T. BENTON II, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of November, 1983. COPIES FURNISHED: Dennis J. Powers, Esquire Gunster, Yoakley, Criser & Stewart 400 South County Road Palm Beach 33480 Terrell K. Arline, Esquire 325-C Clematis Street West Palm Beach, Florida 33401 Irene Kennedy Quincey, Esquire 3301 Gun Club Road West Palm Beach, Florida 33406 Charles P. Houston, Esquire 324 Datura Street, Suite 106 West Palm Beach, Florida 33401
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Respondent owns real property located in Township 2 North, Range 7 East, Section 32, in Madison County, Florida, that has surface water flowing through it and is encompassed within what is defined as "wetlands." Respondent is in control and possession of the property in question and all work on the property that is material to this proceeding is under the control or direction of the Respondent. There were access roads on the property as early as 1973 as reflected by Respondent's exhibit 2, a 1973 aerial photograph, but the width of the roads or the existence of ditches or culverts cannot be determined from the photograph. Petitioner's exhibit 2, a 1981 aerial photograph, shows the roads still in existence in 1981 but the width of the roads or existence of ditches or culverts cannot be determined from the photograph. Sometime before the Respondent purchased the property and began construction to expand the roads, ditches and culverts were in place; however, there was no evidence as to when the ditches and culverts came to be in place. A 1976 survey of the property reflects 60 foot roads which were to provide access to platted but unrecorded lots. These roads had not been constructed when Respondent purchased the property or began construction to expand the roads. The newly constructed portions of the road indicates an attempt to build the roads in accordance with the 1976 survey. The previously existing roads attempted to follow the natural contour of the land and as a result were not always straight, and only had a negligible effect on the flow or storage of surface water in regard to the property. Sometime around October 1987, Respondent began to rebuild and construct roads on the property by straightening existing curves, removing fill material from adjacent wetlands to widen and heighten the existing roadbed or construct a new roadbed, and to increase the depth and width of existing ditches or dig new ditches. The initial portion of the existing road providing access to the property from the county graded road has been substantially rebuilt with portion of the roadbed being 40 to 43 feet wide. Ditches along this portion of the roadbed have had their width increased up to 14 feet and their depth increased up to 6 and 8 feet. Other portions of the road has been expanded beyond the previously existing roadbed by increasing the width and height of the roadbed. The increased size of the ditches and the expanded roadbed has increased the interception of surface water above that already being intercepted by the previous roadbed and ditches and, as a result, there is an increased amount of surface water impounded or obstructed. The effect is that surface water is removed from Respondent's property at a faster rate than before road construction began and, as a result, sheet flow of surface water is decreased which diminishes the storage of surface water on the property. Although new culverts were installed during road construction, there was insufficient evidence to show that these new culverts were in addition to the culverts already in place or if they replaced old culverts. There was insufficient evidence to show that the new culverts allowed water to flow in a different direction or be removed from the property at a faster rate than before or if they impounded or obstructed surface water more so than before. The previously existing roads had sufficiently served an earlier timber harvest on the property and, by Respondent's own testimony, were sufficient for his ongoing hog and goat operation. The extensive rebuilding and constructing of roads in this case was neither necessary nor a customary practice for construction of farm access roads in this area. Respondent is engaged in the occupation of agriculture in that he has a bona fide hog and goat operation. However, Respondent's silviculture occupation is somewhat limited in that he is presently harvesting the timber but shows no indication of replanting or continuing the forestry operation upon completing the present harvesting operation. The extensive rebuilding and constructing of roads in this case goes beyond what is necessary or is the customary practice in the area for a hog or goat operation or forestry operation such as Respondent's and is inconsistent with this type of agriculture or silviculture occupation. Respondent has never applied for nor received a surface water management permit from the Petitioner even though the Petitioner has informed Respondent that a permit was required for the work being done on his property. The present alteration of the topography of the land by Respondent has obstructed and impounded surface water in such a fashion that the interruption of the sheet flow of surface water has been increased, causing the storage of surface water on the property to be diminished. At the present time, Respondent has been enjoined by the Circuit Court of Madison County, Florida, from any further activity on this project. However, should Respondent be allowed to complete this project, it is evident that the sole and predominant purpose would be to impound and obstruct the sheet flow of surface water and diminish the storage of surface water on the property in question.
Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore, RECOMMENDED that the Petitioner, Suwannee River Management District, enter a Final Order requiring Respondent, Norman Leonard, to: (a) remove all unauthorized fill material placed within jurisdictional wetlands and return those areas to predevelopment grades and revegetate with naturally occurring local wetlands species to prevent erosion; (b) back fill excavated swale ditches, return road beds and excavated ditches to predevelopment condition and grades and seed disturbed non-wetland areas with a 50:50 mix of bahia and rye grass and; (c) refrain from any other development until and unless a required permit is obtained for such development. Respectfully submitted and entered this 13th day of February, 1989, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of February, 1989. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 88-1445 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner 1. Adopted in Finding of Fact 1. 2.-3. Adopted in Finding of Fact 2. 4.-7. Are unnecessary findings for this Recommended Order. Adopted in Finding of Fact 18. Adopted in Finding of Fact 19. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Subordinate to the facts actually found in this Recommended Order. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12. Rejected as conclusions of law. Adopted in Findings of Fact 3 and 4. Adopted in Finding of Fact 8. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 8. Adopted in Finding of Fact 6. Adopted in Finding of Fact 7. Adopted in Finding of Fact 6. Adopted in Finding of Fact 10. Adopted in Findings of Fact 15 and 17. 26.-29. Adopted in Finding of Fact 12. 30. Adopted in Finding of Fact 13. 31.-32. Subordinate to facts actually found in this Recommended Order. Adopted in Finding of Fact 12. Adopted in Finding of Fact 16. 35.-38. Subordinate to facts actually found in this Recommended Order. 39.-42. Rejected as not being relevant or material. Specific Rulings on Proposed Findings of Fact Submitted by Respondent 1. The first paragraph adopted in Finding of Fact 16. The balance is rejected as a conclusion of law. 2.-3. Rejected as not being relevant or material. Not a finding of fact but a statement of testimony. However, it is subordinate to facts actually found in this Recommended Order. Rejected as not supported by substantial competent evidence in the record. The more credible evidence is contrary to this finding. COPIES FURNISHED: Janice F. Baker, Esquire Post Office Box 1029 Lake City, Florida 32056-1029 Norman Leonard, Pro Se Route 2, Box 172-D Live Oak, Florida 32060 Donald O. Morgan Executive Director Suwannee River Water Management District Route 3, Box 64 Live Oak, Florida Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Findings Of Fact This application is a request for a consumptive use permit for two wells located in Pasco County, Florida, within the Pithlachascotee Basin. The subject wells are also located in that area wherein the Board of Governors of the Southwest Florida Water Management District declared a water shortage in Order No. 76-3D, Southwest Florida Water Management District. The application seeks an average daily withdrawal of 95,000 gallons with a maximum daily withdrawal of 360,000 gallons. The use of this water is for public supply involving effluent disposal by on-site percolation and ponding. This-use was existing prior to January 1, 1975 with am average daily withdrawal for 1974 of 74,000 gallons. The testimony presented by staff members of the Southwest Florida Water Management District establishes that the consumptive use for which a permit is sought will not violate any of the criteria set forth in Subsections 163- 2.11(2)(3) or (4), Florida Administrative Code, except that the use may significantly induce salt water encroachment. No evidence was presented showing that the sought for consumptive use will, in fact, significantly induce salt water encroachment. In the twelve month period ending October, 1975, applicant's highest average daily withdrawal was 81,000 gallons. This time frame corresponds to that time frame referred to in paragraph 1 of Water Shortage Order No. 76-3D, Southwest Florida Water Management District. In view of Water Shortage Order No. 76-3D, Southwest Florida Water Management District, the staff recommends granting of the permit for an average daily withdrawal of 81,000 gallons and a maximum daily withdrawal of four times that figure or 234,000 gallons. The staff further recommends imposition of the following conditions: That the permittee shall install totalizer flow meters of the propeller driven type on all withdrawal points covered by the permit with the exception of those wells which are currently ganged together using a single meter. That the permittee shall submit to the District a record of his pumpage for each meter, said pumpage to be read on a monthly basis and submitted quarterly to the District on April 15, July 15, October 15, and January 15 for each preceding calendar quarter. That all individual connections to the system be metered. That the permittee have water samples from all wells permitted analyzed for chloride on a monthly basis and results submitted to the District by April 15, July 15, October 15, and January 15 for each preceding calendar year.
Findings Of Fact This application is to provide irrigation necessary to develop 11,520 acres zoned agricultural into improved grazing land. The land to be so developed is Sections 1, 2, 3, 10, 11, 12, 13, 14, 15, 23, 24, & 25, Township 47 South, Range 34 East, a portion of Sections 4, 9, 16, 21, 22, 26, 27, 35 & 36, Township 47 South, Range 34 East, a portion of Section 1, Township 48 South, Range 34 East, and a portion of Section 6, Township 48 South, Range 35, East. It is bounded on the west and southwest by the L-3 canal, and on the east by the Rotenberger tract which has been purchased by the State of Florida as a Wildlife Management Area. Details of the proposed water management system are contained in Exhibit 4, C&SFCD Staff Report. The tract here involved is basically flat with the elevation going from +14 feet in the northwest portion to +13 feet in the southeast portion. Although the Addendum to the Staff Report (Exhibit 5) states that the application calls for the conversion of several thousand acres of original sawgrass Everglades into improved pasture, expert witnesses testified without contradiction that the tract involved is more on the edge of the Everglades and only a small portion in the southeastern part thereof is truly swamp and marsh land typical of the Everglades. The western portion of the area is comprised of sandy soil rather than the muck characteristic of Everglades land. Although the Intervenors contended that the development of the tract would be environmentally counterproductive, no evidence was submitted to support this position. Conversion of the land to pasture may prove more useful to wildlife than leaving it in its present state which primarily supports deer. As improved pasture the land would still support a substantial deer population. Wading birds in particular will benefit if the wild land is converted to pasture. The annual water allocation recommended by the C&SFCD staff and concurred in by applicant, should be 15,360 acre-feet (16.0 inches/acre/year) which is the basin yield for the area. Therefore the irrigation use should have no adverse impact on the water resource or affect other users.
Findings Of Fact Application No. 76-00450 is for a consumptive use permit from 10 wells located in Hillsborough County, to be used for public water supply for the City of Temple Terrace. The permit seeks to withdraw 2.028 million gallons a day average annual withdrawal and 4.564 million gallons per day maximum daily withdrawal. The sought for withdrawal may affect other wells by drawdown of an average of 1" in a surrounding well. Such a drawdown will not seriously and adversely affect the surrounding wells. The Southwest Florida Water Management District's staff recommends issuance of the permit with the following conditions: That the applicant shall install totalizing flowmeters of a type acceptable to the district on all withdrawal points covered by the permit. That the applicant shall record the pumpage on a weekly basis and shall submit a record of that pumpage to the district quarterly beginning January 15, 1977. All individual connections supplied by withdrawals permitted will be metered. Records of meter readings will be made available to the district upon request. That the permit shall expire on December 31, 1980.
Findings Of Fact By application number 21312, the applicant seeks a ten year water use permit for a total annual diversion of 3,831 million gallons to provide water and sewer services to an area containing approximately 7,300 acres. In September of 1969, the Florida Public Service Commission granted the applicant certificates of convenience and necessity. The existing facilities of the applicant include nine wells and an average capacity of 700 gallons per minute each. Based upon historical data and taking into accourt the reduction of construction in the service area, the projected 1984 water demand is 375 gallons per day per unit. This is equivalent to an average of 150 gallons per day per person, using a figure of 2.5 persons per living unit. The ultimate estimated population is to be 70,000 to 80,000 people with 28,000 to 32,000 living units. Based upon the average capacities of the wells, in order to meet the projected demand a total number of 22 or 23 wells will be required. This includes the nine existing wells, eleven proposed wells with the same 700 gallon per minute average and a fifteen percent standby capability of two or three additional wells. Rather than the total number of wells utilized -- 22 or 23, -- what is important is the total gallon per minute capacity of 15,400. An allocation based on this data would be equal to the applicant's requested annual maximum diversion of 3,831 million gallons and a daily maximum diversion of 18.37 million gallons. The requested diversion presents no threat of salt water intrusion. The proposed well sites will create no adverse impact upon the Fort Lauderdale well fields. While there is evidence of recharge to the aquifer from runoff waters, there is insufficient data to determine the exact amount which will be returned. For this reason, the staff report's water budget calculations are conservative.
Recommendation Based upon the above findings of fact and conclusions of law, it is recommended that a ten year permit be issued to the applicant for a maximum annual diversion of 3,831 million gallons; a maximum daily diversion of 18.37 million gallons and a maximum installed field capacity of 15,400 gallons per minute, utilizing 22 or 23 wells with a capacity of 700 gallons per minute each. It is further recommended that the applicant be subject to the conditions set forth on page 5 of the staff report (Exhibit 8) concerning the submission of monthly reports of daily pumpage and actual connections or population served, conformance with health department standards of the water quality of all wells, and the installation and maintenance of an observation well and monthly reports of the data obtained therefrom. Respectively submitted and entered this 10th day of May, 1976, in Tallahassee, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 COPIES FURNISHED: Mr. John R. Maloy Executive Director Central and Southern Florida Flood Control District P.O. Box V West Palm Beach, Florida 33402 Mr. Edward B. Deutsch 350 Southern Federal Building 400 North State Road 7 Margate, Florida 33063 Mr. John Wheeler P.O. Box V West Palm Beach, Florida 33402 Attorney for the Central and Southern Florida Flood Control District
Findings Of Fact Application No. 76-00254 seeks a consumptive use water permit for 1.08 million gallons per day average daily withdrawal and 2.16 million gallons per day maximum daily withdrawal from one well. This is a new use. The purpose of the consumptive use is a semi-enclosed irrigation system for the irrigation of tomatoes in south Hillsborough County. The water is to be taken from the Floridan Aquifer with some discharge off site. According to Barbara Boatwright, hydrologist for the district, there is some possibility that salt water intrusion may occur, but the district has never documented it in the subject area. The consumptive use will exceed the water crop as defined by the district because 25 percent of the water used will run off site and thus be lost. Except as otherwise stated above, none of the conditions set forth in Subsection 16J-2.11(2),(3) or (4), F.A.C., will be violated. The Southwest Florida Water Management District's staff recommends issuance of the subject permit in the amounts requested with the following conditions: By January 1, 1978, applicant shall reduce runoff to 8.6 percent of the amount pumped, which reduction will bring the amount pumped within the water crop as defined by the district. That the applicant analyze the quality of the water at the beginning and end of each production season and that these analyses be submitted to the district. That the district be allowed to install flowmeters on any discharge canal and on the pump with proper notification of applicant and to enter on property to read the meters.
Recommendation Noting that, with the conditions requested by the Southwest Florida Water Management District's staff, issuance of the sought for permit appears consistent with the public interest, it is RECOMMENDED that a consumptive use permit be issued pursuant to Application No. 75-00254 with the conditions set forth in paragraph 4. CHRIS H. BENTLEY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Terry Elsberry Staff Attorney Elsberry Brothers, Inc. Southwest Florida Water Route 2, Box 70 Management District Ruskin, Florida 33570 Post Office Box 457 Brooksville, Florida 33512
Findings Of Fact In approximately 1987, the Petitioner purchased land in Pinellas County, of which approximately 85 percent lies within jurisdictional wetlands. (The jurisdictional wetlands approximate the surface water mean high water line.) Some of the wetlands will have to be filled in order to construct a residential dwelling on the property. The nearest public sewer connection is over a mile away from the Petitioner's property. The only reasonable alternative for the treatment of residential sewerage is an onsite sewage treatment and disposal system. The only reasonable alternative for construction of an onsite sewage treatment and disposal system on the property would require a drainfield to be located well within 75 feet of the jurisdictional wetlands, which are surface waters of the State. In fact, the proposed drainfield would have to be as close as six to twelve feet from the jurisdictional wetlands in most places. In addition, there is a drainage ditch along the road on the western boundary of the Petitioner's property. The drainage ditch contains water for extended periods of time in the rainy summer months. The drainfield for the Petitioner's proposed onsite sewage treatment and disposal system would be approximately 21 feet from the drainage ditch. In other words, a 75 foot setback from the drainage ditch would overlap the 75 foot setback from the jurisdictional wetlands. Although the Petitioner's proposed onsite sewage treatment and disposal system is designed to function without failing during such conditions, parts of the drainfield can be expected to be inundated during the rainy season. In effect, as a result of rainfall and runoff during rainy weather, the water from the wetlands and the drainage ditch would be expected to overflow the jurisdictional line and the ditch banks and inundate parts of the drainfield. There would be a direct connection between the waters inundating the drainfield and the surface waters of the wetland and of the drainage ditch. The Petitioner proposes to have, and several neighbors have, potable water wells to supply drinking water. There are sinkholes all over the area of the Petitioner's property. It is not known whether there is a sinkhole on the Petitioner's property, but it is well known that sinkholes are common in cypress head swamps like the wetlands on the Petitioner's property. If there is a sinkhole, or if one develops, it could act as a direct conduit from the surface water to the aquifer from which the private drinking water wells in the area draw water. Contamination from the Petitioner's drainfield then would be able to contaminate the drinking water. Potential fecal coliform contamination of the surface waters adjacent to the Petitioner's proposed drainfield (both the wetlands and the drainage ditch) also could pose a public health threat. The County recently has disposed of digested sludge in the vicinity of the Petitioner's site (i.e., within approximately a mile away). (It is not clear from the evidence whether this still is taking place.) However, under applicable Department of Environmental Protection rules, the sludge was being applied to pasture at least 300 feet from cypress heads, and the County also was required to meet other environmental controls and regulations for that kind of disposal. The Petitioner's evidence did not prove that discharge from his proposed onsite sewage treatment and disposal system will not adversely affect the health of the Petitioner or the public or that it will not significantly degrade the groundwater or surface waters.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Health and Rehabilitative Services (HRS) enter a final order denying the Petitioner's application for a variance. RECOMMENDED this 14th day of March, 1994, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of March, 1994. COPIES FURNISHED: R. Patrick Mirk, Esquire Post Office Box 10598 Tampa, Florida 33679-0598 David Jon Fischer, Esquire Assistant District Legal Counsel Department of Health and Rehabilitative Services 11351 Ulmerton Road Largo, Florida 34648 Robert L. Powell Agency Clerk Department of Health and Rehabiltiative Services 1323 Winewood Blvd. Tallahssee, Florida 32399-0700 Kim Tucker, Esquire General Counsel Department of Health and Rehabiltiative Services 1323 Winewood Blvd. Tallahssee, Florida 32399-0700
The Issue The issue is whether Respondent's water use permit should be revoked for nonuse of the permit for a period of two years or more.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background The District is a state agency charged with the responsibility of issuing water use permits under Chapter 373, Florida Statutes, and Florida Administrative Code Chapter 40B- 2 for the geographic area under its statutory jurisdiction. Alachua County is within that geographic jurisdiction. Respondent is a Florida corporation with offices at 700 Northwest Cheeota Avenue, High Springs, in northern Alachua County. It owns approximately 700 acres in High Springs (west of Interstate Highway 75) on which it operates a church retreat and summer camping and recreational facility known as Camp Kulaqua. The property surrounds, and is contiguous to, Hornsby Spring, a first-order magnitude spring (having a flow rate of 100 CFS or greater) which, under normal conditions, discharges into the nearby Santa Fe River. Hornsby Spring is one of 296 documented springs within the District's jurisdiction. After receiving an overture from a representative of a private water bottling company, on September 28, 1999, Respondent filed an application for a General Water Use Permit in Township 7 South, Range 17 East, Section 26, in High Springs. In its application, Respondent represented that it desired a daily allocation of 2,000,000 gallons; that it intended to install two 12-inch wells, each having a capacity of 1,400 gallons per minute, just east of, and upgradient from, Hornsby Spring; and that all water withdrawals would be used in conjunction with a privately-owned commercial spring water bottling facility to be located on its property. The application also represented that the facility would employ 36 persons and operate 168 hours per week. The application was reviewed by a former District hydrogeologist, William H. Kirk. During the review process, and in response to Mr. Kirk's request for more information, Respondent provided a comparison of the requested allocation with the overall flow of Hornsby Spring. This was because Mr. Kirk was concerned that the requested allocation was "a bit high," and he wanted to ensure that the issuance of the permit would not cause harm to, or adversely affect, the water resources. Under a professional guideline that Mr. Kirk used, if the applicant could show that the cumulative amount being withdrawn was to be less than ten percent of what the available data showed to be the mean spring flow, the District would consider it to be "an acceptable impact." Notwithstanding Mr. Kirk's use of this guideline, the District points out that there is no District rule or policy sanctioning the ten percent rule, and at hearing it denied that this standard is used by the District in assessing water use applications. Further, the Permit itself does not refer to a relationship between spring flow and the size of the allocation. Even so, this analysis was considered by Mr. Kirk in determining whether Respondent had given reasonable assurance that the spring would not be impacted. In its response to the request for additional information, Respondent reduced its requested allocation to 750,000 gallons per day and indicated that if a bottling plant were to be constructed on its property, approximately 700,000 gallons of the total allocation would be consumed in "bulk transfer and bottling," with the remainder for camp use. More specifically, Respondent indicated that it would allocate 490,000 gallons per day for bulk transport, 210,000 gallons per day for spring bottling water, and 50,000 gallons per day for incidental uses at its property. By reducing the allocation from 2,000,000 gallons per day to 750,000 gallons per day, Respondent's requested average daily allocation represented only 0.4 percent of the average daily spring flow as measured over the last 28 years. The reduced allocation satisfied Mr. Kirk's concern that Respondent demonstrate a reasonable demand and a reasonable need for that allocation, and he recommended approval of the application.2 On February 25, 2000, the District approved the application and issued Water Use Permit No. 2-99-00130 (Permit).3 The Permit authorizes an average daily withdrawal of 0.7500 million gallons per day (750,000 gallons per day) or a maximum daily withdrawal and use of 0.7500 million gallons per day with an annual allocation not to exceed 273.750 million gallons (273,750,000 gallons) per calendar year in conjunction with the operation of a privately-owned water bottling plant. The Permit expires on February 25, 2020. After the Permit was issued, under the regulatory process in place, Respondent was required first to obtain a permit for a temporary test well which would be used to collect information concerning the site of the proposed activity, and to then file an application for permits authorizing the construction and operation of the two 12-inch production wells. The Permit contains a number of conditions, two of which require a brief comment. First, Condition No. 2 provides that "[t]his permit is classified as unconfined [F]loridan aquifer for privately owned bottled water plant." This means that all water withdrawals must be made from the unconfined Floridan aquifer, as opposed to the spring head of Hornsby Spring. (Respondent's proposed siting of its two production wells 660 yards east of the spring is consistent with this provision.) Second, Condition No. 4 provides that "[t]he permittee shall submit daily pumpage records on a monthly basis to the [District]." Pumpage reports are filed by permittees so that the District can determine whether the permit is actually being used, and if so, to ensure that the amount of water being withdrawn under the permit does not exceed the authorized allocation. As it turned out, pumpage reports were never filed by Respondent. (However, the record shows that the District has never strictly enforced this requirement for any permittee.) In late 2002, the District staff undertook a review of the nine water bottling permit holders within its jurisdiction, including Respondent. That category of permit holders was selected for review because of the small number of permits and the limited resources of the District staff. (In all, the District has probably issued several thousand permits to other types of users.) On February 4, 2003, the District served its Complaint under the authority of Sections 120.60 and 373.243, Florida Statutes, and Florida Administrative Code Rule 40B-2.341. As grounds for revoking the permit, the District alleged that there was "non-use of the water supply allowed by the permit for a period of two (2) years or more." Although Respondent contends that it should have been given an opportunity to correct the nonuse allegation before the Complaint was issued, nothing in the Administrative Procedure Act or District rules requires that this be done. Until the issuance of the Complaint against Respondent in early 2003, and similar Complaints against eight other permit holders at the same time, the District had never invoked this statutory provision.4 There is no evidence to support Respondent's contention that the Complaints were issued for "purely political reasons." On March 4, 2003, Respondent requested a formal hearing challenging the District's proposed action. In the parties' Pre-Hearing Stipulation, the issues have been broadly described as follows: whether Section 373.243(4), Florida Statutes, is to be strictly or liberally construed; whether Respondent's nonuse is based upon extreme hardship for reasons beyond its control; and whether the District is equitably estopped from permit revocation. (According to the District, even if the Permit is revoked, such revocation is without prejudice to Respondent reapplying for, and receiving, another permit so long as it meets all applicable requirements.) Equitable Estoppel Respondent first contends that the District is estopped from revoking its Permit on the theory that, under the circumstances here, the doctrine of equitable estoppel applies. For that doctrine to apply, however, Respondent must show that the District made a representation as to a material fact that is contrary to a later asserted position; that Respondent relied upon that representation; and that the District then changed its position in a manner that was detrimental to Respondent. See, e.g., Salz v. Dep't of Admin., Div. of Retirement, 432 So. 2d 1376, 1378 (Fla. 3d DCA 1983). The District issued Respondent's Permit on the condition that Respondent operate in conformity with all pertinent statutes and regulations. This finding is consistent with language on the face of the Permit, which states that the Permit "may be permanently or temporarily revoked, in whole or in part, for the violation of the conditions of the permit or for the violation of any provision of the Water Resources Act and regulations thereunder." Respondent relied on the District's representation that it could use the Permit so long as it complied with all statutes and regulations. In reliance on that representation, in addition to staff time, after its Permit was issued, Respondent expended "somewhere around" $70,000.00 to $74,000.00 for conducting water quality testing; sending cave divers underground to ascertain the correct location of the portion of the aquifer on which to place its production wells; drilling a 6-inch test well in August 2000; obtaining the City of High Springs' approval in March 2000 for industrial zoning on a 10-acre tract of land on which to site a "water plant"; and engaging the services of a professional who assisted Respondent in "seeking out businesses and getting the right qualifications of the spring water to make sure that it was a marketable water." The District has never asserted anything different from its original position: that if Petitioner complied with all statutes and rules, it could continue to lawfully make water withdrawals under its Permit. The issuance of the Complaint did not represent a change in the District's position. Because a change in position in a manner that was detrimental to Respondent did not occur, the necessary elements to invoke the doctrine of equitable estoppel are not present. Was the Permit Used? A preliminary review by District staff indicated that Respondent had never filed the daily pumpage reports on a monthly basis and had never requested permits authorizing the construction of the two 12-inch production wells. These preliminary observations were confirmed at final hearing, along with the fact that Respondent has never entered into an agreement with a water bottling company (although draft agreements were once prepared); that Respondent has never constructed a water bottling facility; and that no operations were ever conducted under the Permit. Therefore, the evidence supports a finding that Respondent did not use its Permit for the two-year period after it was issued, as alleged in the Complaint. Respondent's contention that the evidence fails to support this finding belies the evidence of record. In an effort to show that it actually used the Permit, Respondent points out that in August 2000 it applied for, and received a permit to construct, an unmetered 6-inch test well in association with its General Water Use Permit. (Respondent sometimes erroneously refers to the test well as a test production well. This is incorrect as the well is a test well, and not a production well.) After the test well was installed, at some point Respondent says it began withdrawing approximately 50,000 gallons per day of water from that well for incidental uses associated with the operation of Camp Kulaqua.5 These withdrawals were made on the assumption that the test well permit fell under the broad umbrella of the General Water Use Permit. (Respondent also has a permitted 6- inch diameter well and an unregulated 4-inch well on its premises, both of which are used for water supply needs at Camp Kulaqua.) It is true, as Respondent asserts, that its Permit authorized incidental withdrawals of up to 50,000 gallons per day for unspecified uses at Camp Kulaqua. However, these withdrawals are authorized under the General Water Use Permit and not the test well permit. The two permits are separate and distinct. On the one hand, a test well is intended to be temporary in nature and used only for the purpose of test well development and collecting information regarding the height of the aquifer and water quality at the site of the proposed activity. Conversely, withdrawals for any other purpose, even incidental, must be made from the production wells, which are only authorized by the General Water Use Permit. Before a test well can be used for normal consumptive purposes, the permit holder must seek a modification of the permit to include it as a part of its general water use permit. Here, no such modification was sought by Respondent, and no authorization was given by the District. Therefore, Respondent's incidental water uses associated with its test well cannot be counted as "uses" for the purpose of complying with the use requirement in Section 373.243(4), Florida Statutes. In light of the District's credible assertion to the contrary, Respondent's contention that it is common practice to lawfully withdraw water from a test well for incidental consumptive purposes has been rejected. (It is noted, however, that the District has not charged Respondent with violating the terms of its test well permit.) Extreme Hardship Under Section 373.243, Florida Statutes (which was enacted in 1972), the District is authorized to revoke a water use permit "for nonuse of the water supply allowed by the permit for a period of 2 years." However, if the user "can prove that his or her nonuse was due to extreme hardship caused by factors beyond the user's control," revocation of the permit is not warranted. The phrase "extreme hardship caused by factors beyond the user's control" is not defined by statute or rule. In the context of this case, however, the District considers an extreme hardship to occur under two scenarios. First, if the aquifer level has dropped so low due to drought conditions that a permit holder cannot access the water through its well, its nonuse is excusable. Alternatively, if an emergency order has been issued by the District directing permit holders (including Respondent) to stop pumping due to certain conditions, an extreme hardship has occurred. (Presumably, a severe water shortage would precipitate such an order.) In this case, the District issued a water shortage advisory, but not an emergency order, due to a "severe drought," indicating that users could still pump water, but were encouraged to voluntarily reduce their usage. This advisory remained in effect from the summer of 1998 until the spring of 2003, when a severe drought ended. However, no emergency order was ever issued by the District. Respondent contends that its nonuse was due to an extreme hardship caused by factors beyond its control. More specifically, it argues that a severe drought occurred in Alachua County during the years 1998-2003, and that under these conditions, federal regulations prevented it from withdrawing water for bottling purposes, which was the primary purpose for securing a permit. Further, even if it had withdrawn water during these drought conditions, such withdrawals could have adversely impacted Hornsby Spring and constituted a violation of a District requirement that water resources not be adversely impacted. Because an investment of several hundred thousand dollars was required to drill and install the two production wells, Respondent contends it was not financially prudent to make that type of investment and begin operations until normal spring conditions returned. These contentions are discussed in greater detail below. Around September 7, 1999, a representative of a water bottling company first approached Respondent about the possibility of the two jointly operating a water bottling plant and/or transporting water in bulk from Respondent's property. Prompted by this interest, less than three weeks later Respondent filed its application for a water use permit (although at that time it did not mention on the application that off-site bulk transfers would occur), and a permit was eventually issued in February 2000. Later, and through a professional firm it employed, Respondent had discussions with representatives of several bottling companies, including Great Springs Waters of America (Great Springs) and Perrier Group of America. Apparently, these more serious discussions with a potential suitor did not take place until either late 2000 or the spring of 2001. Periodic measurements taken by District staff at Hornsby Spring reflected natural drought conditions from April 2000 to April 2003. As noted earlier, this was the product of a "severe drought" which took place between the summer of 1998 and the spring of 2003; the drought was one of a magnitude that occurs only once in every 50 to 100 years. During the years 2000 through 2002, the spring had zero flow or was barely flowing much of the time.6 Had Respondent pumped water during 20 out of the 24 months after the Permit was issued, it could have potentially violated the requirement that it not harm Hornsby Spring. This fact is acknowleged by a District witness who agreed that if the "spring is not flowing, . . . [pumping] would have an [adverse] impact." Even as late as October 2003, the spring had tannic discoloration caused by the lengthy drought conditions. The parties agree, however, that there is no water shortage in the District at the present time. To illustrate the difficulty that it experienced in obtaining a joint venture partner for water bottling purposes, Respondent established that in the spring of 2001, a Great Springs representative visited the site when the spring was "barely flowing." For obvious reasons, Respondent could not "bring a party there who would want to enter into a business [agreement]" under those conditions. These same conditions remained in effect during most of the two year period. The District points out, however, that even though the spring was low or barely flowing, so long as the aquifer itself was not too low, Respondent could still withdraw water from the aquifer, since Condition 2 of the Permit authorizes withdrawals from the aquifer, and not the spring. The reason for this apparent anomaly is that when a spring ceases to flow, the aquifer has simply dropped below the level of the spring vent; even under these circumstances, however, there may still be a substantial quantity of water in the aquifer available for pumping. Assuming that it could still lawfully pump water when the spring was dry or barely flowing without causing adverse impacts to the spring, Respondent was still subject to federal regulations which govern the bottling of spring water. See Title 21, Part 165, C.F.R. For spring water to be marketed as bottled "spring water," 21 C.F.R. § 165.119(2)(vi) requires that the water "be collected only at the spring or through a bore hole tapping the underground formation feeding the spring." This means that the bore hole had to be physically connected with the cave system feeding Hornsby Spring or produce water of the same quality as that discharging from the spring. The regulation goes on to provide that "[i]f spring water is collected with the use of an external force [such as by a pump], water must continue to flow naturally to the surface of the earth through the spring's natural orifice." While this regulation obviously does not prohibit Respondent from pumping water, since that authority lies within the District's exclusive jurisdiction, it does provide that in order to use spring water for bottling purposes, the water must continue to flow naturally from the aquifer to the spring. If it does not, the water cannot be used for this purpose. Because Hornsby Spring had zero flow for parts of 2001 and 2002, and severely reduced flows during most of the other time during the two-year period ending February 2002, Respondent was effectively prevented by the foregoing regulation from using the water for bottling purposes. Therefore, Respondent's nonuse was due to extreme hardship caused by factors beyond its control -- a severe drought lasting throughout the two-year period after the Permit was issued, and federal regulations which prevented it from using water for the purpose for which the Permit was issued. Thus, the nonuse is excusable.