WILLIAM DEPKIN vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-001309 (1989)
Division of Administrative Hearings, Florida Number: 89-001309 Latest Update: Aug. 08, 1989

Findings Of Fact Based upon the record evidence, the Hearing Officer makes the following Findings of Fact: Petitioner and his wife own residential property on the northwest side of Key Thargo in Monroe County, Florida. The property is situated on Florida Bay, a Class III Outstanding Florida Water. The area surrounding the Depkins' property is predominately residential, but there is some nearby commercial development, including a motel which is located on an adjoining parcel. A seawall runs the entire length of the shoreline of the Depkins' property. An L-shaped dock and a covered dock extend out into the water from opposite ends of the seawall forming a cove. The Depkins, who live in Key Thargo only a portion of the year, have a boat which they currently moor alongside the L-shaped dock in that area of the cove where the depth of the water is the greatest. The operation of the boat in this area of the cove has not caused any obvious damage to the bay bottom. Two of the Depkins' boats have sunk in stormy weather while moored alongside the L-shaped dock. Therefore, they now dock their boat at a marina when they are away from Key Largo. The Depkins propose to dredge a relatively small 600 square foot area of bay bottom, which they own, in the cove immediately waterward of the seawall. The depth of the water in this area of the cove now ranges from six inches to a foot and a half. The proposed dredging project would increase the depth of the water by two feet and thereby enable the Depkins to dock their boat alongside the seawall, a location they consider safer than the one they presently use for this purpose. The bay bottom which the Depkins propose to dredge consists primarily of bedrock which is irregularly shaped. Most of the bedrock is exposed, however, some of the depressions in the bedrock are filled with sediment. The remaining portion of the bay bottom is covered with sand which is inhabited by various living organisms. Approximately 50% to 75% of the proposed dredging site is covered with vegetation. The dominant vegetation is live algae attached to the exposed bedrock. Various species of algae are present, including red algae, which is the preferred habitat for juvenile lobster. A small portion of the site is covered by live turtlegrass. These few patches of turtlegrass are found in the depressions in the bedrock that are filled with sediment. Without sediment turtlegrass cannot grow. Algae and turtlegrass play significant roles in the production and sustenance of marine life. They have considerable value as a habitat and as a source of food for other living organisms. In addition, they help reduce turbidity and water pollution. If the Depkins dredged the proposed project site, all existing biota within the boundaries of the site would be eliminated and it is unlikely that the area would experience a complete or significant recovery. About twelve to fourteen years ago the Depkins dredged sand from the bay bottom near their L-shaped dock. Almost 30 years ago the owners of the motel situated on the parcel of land adjoining the Depkins' property undertook a similar sand dredging project in the bay. Neither of these prior dredging projects resulted in the long-term loss of any vegetation. If anything, the vegetation in these areas has increased. Unlike these previous projects, the project which the Depkins now propose to undertake involves the dredging of primarily bedrock, not sand. 1/ Revegetation typically does not occur following such dredging activity. It is the exception rather than the rule. Therefore, more likely than not, the Depkins' proposed dredging project, if permitted, will result in the permanent loss of vegetation and consequently will have a long-term adverse effect on ambient water quality, the conservation of fish and other aquatic wildlife, and marine productivity. Furthermore, if the project was completed and the Depkins were to begin docking their boat alongside the seawall, there would be an increase in conflict turbidity attributable to the movement of the boat in and out of this area of shallow water. 2/ No measures to mitigate these adverse consequences have been proposed or suggested. 3/ There are many other owners of bayfront property in the Florida Keys who, like the Depkins, are desirous of dredging an access channel to the landward extent of their property. The Department's current practice is to deny these property owners permission to engage in such dredging activity. Although in the past year the Department has processed only about a half dozen permit applications for dredging projects similar in size and scope to that proposed by the Depkins, there would likely be a substantial increase in the number of permit applications were the Department to announce, through its disposition of the Depkins' permit application, that it was henceforth allowing such projects. If the Depkins and these other property owners were permitted to undertake such projects, the resulting damage to the marine environment would be widespread. The impact would extend far beyond the relatively small area of bay bottom that the Depkins propose to dredge. The Department has proposed the following reasonable alternative to the proposed dredging project which would also provide the Depkins with improved access to their residence by boat: Extend the existing [L-shaped] dock offshore to a terminal platform located at a water depth of at least four (4) feet MLW and elevate the intermediate portion of the dock to at least five (5) feet above MHW to prevent boat mooring in shallower areas.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Environmental Regulation issue a final order denying the Depkins' permit application. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 8th day of August, 1989. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division f Administrative Hearings this of 8th day of August, 1989.

Florida Laws (2) 267.061380.06
# 1
CRYSTAL RIVER PROTECTIVE ASSOCIATION, INC., ET AL. vs. CENTRAL DEVELOPMENT COMPANY AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 76-001102 (1976)
Division of Administrative Hearings, Florida Number: 76-001102 Latest Update: Nov. 04, 1977

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, as well as the Hearing Officer's personal view of the subject premises, the following relevant facts are found: In April or May of 1974, William M. Lyons, as president of Central Development Company, submitted an application for a permit to construct a 20 foot wide, 172 foot long concrete bridge across sovereign land connecting Parker Island in King's Bay with a mainland lot. Both the mainland lot, known as Lot 20, Parker Haven, and Parker Island are owned by Central Development Company. The application contains specific plans for run-off control. In 1975, various studies were performed by representatives of different environmental agencies concerning the proposed project. Representatives from the respondent Department of Environmental Regulation concluded that the bridge should cause no significant direct degradation of or adverse effect upon the water quality of King's Bay. The Director of the Division of Environmental Permitting therefore recommended the issuance of a permit and water quality certification following public notice of the project. In February of 1975, the Chief of Survey and Management of the Department of Natural Resources conducted a biological and hydrographic assessment and found that "the proposed bridge construction would eliminate a limited area of vegetated bottoms but would not, in itself, significantly affect aquatic biological resources," and that "it is improbable that the proposed bridge construction . . . would have significantly adverse hydrographic effects." The Game and Fresh Water Fish Commission had no objection to the bridge itself, but did express concern over the future development of Parker Island. The petitioners herein are citizens and property owners in the area and have requested a hearing on the permit application. The Department of Environmental Regulation forwarded the petition to the Division of Administrative Hearings, and the undersigned Hearing Officer was duly designated to conduct the hearing. Upon the agreement of all parties, the hearing was consolidated with other cases involving permits for projects in the King's Bay area of Crystal River. The prime issue upon which testimony was adduced at the hearing was the effect of the proposed bridge upon navigation. The waters of King's Bay are affected by the ebb and flow of the tide. The bridge is to be approximately four and one-half feet above the mean high water level. The pass between Parker Island and the mainland Lot 20 is approximately 250 feet wide and is relatively shallow, ranging from a low of one foot to a high of approximately four and one- half feet deep, depending upon the tide. Net fishing and gigging in that area are prohibited. Power boats, air boats and small sailboats presently utilize the pass, but large sailboats would not prudently use this pass for safety reasons. Small power boats with windshields and/or covered tops would probably not be able to use the pass during high tide if the proposed bridge at a height of four and one-half feet is constructed. A mean high water survey, per se, was not conducted by or on behalf of the applicant. Rather, the applicant relied upon a bulkhead map which establishes a bulkhead line around Parker Island (Exhibit 9). This document describes mean high water as +1.2 elevation and the metes and bounds description of the bulkhead line is followed by the words "all being along the mean high water line." The King's Bay area and the springs located therein provide a winter home for manatee, an endangered species. During high tides, manatees have occasionally been observed in the pass between Parker Island and Lot 20 on the mainland. While further development and degradation of the area could affect the manatee population, the placement of the bridge itself would not affect the navigation of the manatee travelling in that area, though some would balk or be hesitant around the bridge. One of the greatest hazards to the manatee is injury or even fatality from boat propellers and collisions with fast moving power boats. A boat travelling at five miles per hour should present no problem to the manatee. Several residents owning waterfront lots on King's Bay testified that their view of the open water would be obstructed by the existence of the proposed bridge. The purpose of constructing the bridge is obviously to provide a means of access from the mainland to Parker Island. Parker Island is about five and one-half acres in size and is owned by Central Development Company. Preliminary land use plans have been developed for an environmentally oriented low density subdivision on Parker Island. The conceptual plans include the sale of eleven lots, one-third acre each, for residential purposes. Each lot owner would only be permitted to develop 5,000 square feet of the lot, with the remainder of the lot to be retained in an undisturbed state. The preliminary plans call for underground utilities, no seawalls and a centralized dock. It must be emphasized that these are preliminary or conceptual plans for development of the Island, and Central is in no way bound by said plans. On or about April 5, 1977, the Board of County Commissioners of Citrus County passed a resolution declaring that the area known as King's Bay and the islands located therein was an area of critical habitat, and that any man-made changes in the area be subject to public hearings and comply with all Citrus County ordinances, resolutions and regulations. Lot 20 on the mainland is zoned R-1AA which permits single family dwellings, municipally owned or operated parks and playgrounds, golf courses, certain temporary signs and certain conditioned accessory uses. Central Development Company has not appeared before the zoning board to seek a zoning change or exception for Lot 20. Central Development Company has submitted to the Department of Natural Resources an application for an easement for its bridge construction. This is the subject matter of Case No. 77-960, for which a separate recommended order is being entered.

Recommendation Based upon the findings of fact and conclusions of law recited above, it is recommended that the Department of Environmental Regulation issue to Central Development Corporation a permit to construct a concrete bridge between Lot 20, Parkers Haven, and Parker Island subject to the following conditions: The height of the structure above mean high water level be increased from four and one-half (4 1/2) feet to six and one-half (6 1/2) feet; and Receipt by the applicant and exhibition to the Department of Environmental Regulation of the required easement or other form of consent from the Board of Trustees of the Internal Improvement Trust Fund authorizing the proposed use of sovereignty lands, as required by Florida Statutes 253.77 (1976). Respectfully submitted and entered this 16th day of September, 1977, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Kenneth F. Hoffman, Esquire Post Office Box 1872 Tallahassee, Florida 32302 Alfred W. Clark, Esquire Assistant General Counsel Department of Environmental Regulation 2562 Executive Center Circle, E. Montgomery Building Tallahassee, Florida 32301 Baya M. Harrison, III, Esquire Post Office Box 391 Tallahassee, Florida 32302 David Gluckman, Esquire 3348 Mahan Drive Tallahassee, Florida 32303 Mr. H. A. Evertz, III Florida Power Corporation Post Office Box 14042 St. Petersburg, Florida 33733 Kent A. Zaiser, Esquire Assistant Department Attorney Department of Natural Resources Crown Building 202 Blount Street Tallahassee, Florida

Florida Laws (3) 253.12253.77403.087
# 2
TRUMP PLAZA OF THE PALM BEACHES CONDOMINIUM ASSOCIATION, INC. vs PALM BEACH COUNTY AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 08-004752 (2008)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 23, 2008 Number: 08-004752 Latest Update: Nov. 09, 2009

The Issue The issue is whether an Environmental Resource Permit (ERP) and a Letter of Consent to Use Sovereignty Submerged Lands (Letter of Consent) should be issued to Respondent, Palm Beach County (County), authorizing it to fill 7.97 acres of submerged lands for a restoration project in Lake Worth Lagoon.

Findings Of Fact Based upon all of the evidence, the following findings are determined: The Parties Trump is the owner association for a two-towered residential and commercial condominium building located at 525 South Flagler Drive in downtown West Palm Beach, upland and west of the project site in the Lagoon. Each tower rises thirty floors and together they have of two hundred twenty units. The first five floors are common areas including a lobby on the first floor, while a pool and patio are located on the fifth floor of the north tower. The property is separated from the Lagoon by Flagler Drive, a four-lane divided road with landscaping and sidewalks which runs adjacent to, and on the western side of, the Lagoon. There is no dispute that Trump has standing to initiate this action. Flagler owns, manages, and leases two multi-story office buildings located at 501 Flagler Drive on the upland real property directly west of the project location. Like the Trump property, the Flagler property is separated from the Lagoon by Flagler Drive. There is no dispute that Flagler has standing to participate in this matter. The County is a political subdivision of the State and is the applicant in this proceeding. The Department is the state agency with the authority under Part IV, Chapter 373, Florida Statutes,2 to issue to the County an ERP for the project, as well as authority as staff to the Board of Trustees of the Internal Improvement Trust Fund (Board of Trustees) to authorize activities on sovereign submerged lands pursuant to Chapter 253, Florida Statutes, and Chapter 18-21. Background On October 29, 2007, the County submitted to the Department its Joint Application for an ERP and Letter of Consent to use sovereignty submerged lands in the Lagoon owned by the Board of Trustees. The application was assigned File No. 50- 0283929-00. After an extensive review process, including three requests for additional information, on August 12, 2008, the Department issued its Notice of Intent authorizing the County to fill 7.97 acres of submerged lands in the Lagoon with approximately 172,931 cubic yards of sand and rock material to create the following: (a) approximately 1.75 acres of red mangrove habitat including 1.52 acres of mangrove islands and 0.23 acres of red mangrove planters; (b) approximately 0.22 acres of cordgrass habitat; (c) approximately 0.90 acres of oyster habitat; (d) approximately 3.44 acres of submerged aquatic vegetation habitat; and (e) a 10-foot by 556-foot (5,560 square feet) public boardwalk with two 3-foot by 16-foot (48 square feet) educational kiosk areas and a 16-foot by 16-foot (256 square feet) observation deck for a total square footage of approximately 5,912 square feet. The Notice of Intent also included a number of general and specific conditions particular to this project. Trump (by timely Petition) and Flagler (by intervention) then challenged the Notice of Intent. They contend generally that the project unreasonably infringes upon or restricts their riparian rights and fails to meet the permitting and consent to use criteria set forth in Chapters 18-21 and 40E-4, as well as Chapter 373, Florida Statutes, and Section 253.141, Florida Statutes. Conflicting evidence on these issues was presented at the hearing. The conflicts have been resolved in favor of the County and the Department, who presented the more persuasive evidence. The Project The project area is a cove in the Lagoon, a Class III water body which extends within the County from North Palm Beach to Manalapan. The western side of the water body in the project area is lined with a vertical concrete seawall approximately 6.64 feet above the mean low water line. The waters immediately adjacent to the Trump and Flagler upland property are generally two to five feet deep along the seawall. To the east lies the island of Palm Beach, to the south is the Royal Park Bridge, which connects West Palm Beach and the Town of Palm Beach, while to the north is the Flagler Memorial drawbridge. The Lagoon is approximately 2,000 feet from shore to shore. The Intracoastal Waterway (ICW) runs roughly through the middle of the Lagoon in a north-south direction. Currently, there is an artificial dredge hole in the project area around four hundred feet from the western seawall. The dredge hole, which descends to approximately twenty feet at its deepest location, is filled with muck, which can be re- suspended by wave energy into the water, blocking the sunlight necessary for the support of biotic life. The muck covers the natural hard bottom, consumes oxygen, and presents an unsuitable environment for benthic organisms. The dredge hole is too deep to support seagrasses. The project calls for filling the dredge hole to intertidal elevations, i.e., between the high and low tide elevations, for mangroves and elevations suitable for seagrass. In all, approximately 173,000 cubic yards of fill will be placed in and around the hole to build up three separate islands within the project footprint, on which the County will plant 10,000 red mangroves, which naturally grow between fifteen and twenty-five feet in height. (The County estimates that eighty to ninety percent of the mangroves will survive and grow to a height of at least fifteen feet.) The top of the islands, not including mangroves, will be just below the mean high water mark. The County also proposes locating planters along the seawall and oyster reefs along the southern end of the project. The planters are designed to extend out approximately twenty feet from the seawall and will be placed on sovereign submerged lands. The last five feet will consist of limestone rock. Mangrove, spartina, and seagrass habitats will provide a biodiverse source of food and habitat for other species, and occurs naturally within the Lagoon but has been lost over time. Oyster habitat is proposed for additional bio-diversity and to provide a natural water filtration function. From the County's perspective, the restoration project would be incomplete without all the habitats proposed. The planters will be at an intertidal elevation, planted with red mangroves and spartina, and faced with rock to reduce wave energy in the area. The oyster reefs are rock structures designed to rise one foot above mean high water line for visibility to boaters. The project also includes a boardwalk and attached educational kiosks on the south side of the project to bring the public in contact with the habitats. The County will maintain the boardwalk, empty the trash daily, and open/close the gates at sunrise/sunset. The County proposes a minimum ten-foot buffer between seagrass beds and the fill area. The project is part of the County's Lagoon Management Plan, which outlines the County's restoration goals within the Lagoon. The County has performed numerous other restoration projects within the Lagoon to re-introduce mangrove and seagrass habitat, such as Snook Island, which consisted of filling a 100- acre dredge hole, installing mangrove islands, seagrass flats, and oyster reefs. The Snook Island project restored mangrove habitat and recruited fish and bird species, including endangered and threatened species. Snook Island has remained stable, with no sediment deposition or erosion. The County intends to fill the dredge hole with native lagoon bottom sediment. A clam-shell machine will deposit the sediment below the water line to reduce turbidity. Sediment will be placed around the edges of the dredge hole, reducing the velocity of the fill as it settles to the bottom and encapsulates the muck, as required by Draft Permit Special Condition No. 19. The County will use turbidity curtains, monitor conditions hourly, and stop work if turbidity levels rise beyond acceptable standards. These precautions are included in Draft Permit Conditions 12, 13, and 14. The County will use construction barges with a four- foot draft to avoid propeller dredge or rutting and will place buoys along the project boundary to guide the construction barges, precautions integrated into the Draft Permit conditions. The County's vendor contracts require maintenance of construction equipment to prevent leakage. A similar condition is found in the Draft Permit. Both the intertidal and seagrass flats elevations at the top of the islands will be built at a 4:1 slope; elevations subject to wind and wave energy will be reinforced with a rock revetment constructed of filter cloth and rock boulders. Seagrass elevations will have no reinforcing rock because they are deep enough to avoid significant currents. Proposed drawings were signed and sealed by a professional engineer. The ERP Criteria To secure regulatory approval for an ERP, an applicant must satisfy the conditions in current Rules 40E-4.301 and 40E- 4.302. The first rule focuses primarily on water quantity, environmental impacts, and water quality. The latter rule requires that a public interest balancing test be made, and that cumulative impacts, if any, be considered. Also, the BOR, which implements the rule criteria, must be taken into account. a. Rule 40E-4.301 21. Paragraphs (1)(a), (1)(b), (1)(c), (1)(g), (1)(h), and (1)(k) and subsections (2) and (3) of the rule do not apply. Although Trump and Flagler have focused primarily on paragraphs (1)(d), (f), and (i) in their joint Proposed Recommended Order, all remaining criteria will be addressed. Paragraph (1)(d) requires that an applicant give reasonable assurance that the proposed activity "will not adversely affect the value of the functions provided to fish and wildlife and listed species by wetlands and other surface waters." Based on the project design, the filling of the dredge hole and capping of muck, the restoration of seagrass habitat, and the creation of mangrove habitat, the project will have no adverse impacts but rather will be beneficial to the value of functions for fish and wildlife. Paragraph (1)(e) requires that an applicant give reasonable assurance that the proposed activity will not adversely affect the quality of receiving waters. The County will be required to manage turbidity that may be generated from the project. In part, the turbidity will be contained by the proposed construction method for filling the dredge hole. As noted earlier, the native sand will be deposited using a clamshell-type arm to dump the sand under the water around the periphery of the edge of the downward slope of the dredge hole. This will continue around the periphery of the hole, building up a lip and letting it slide down towards the bottom of the hole, squeezing the muck into the center of the hole and beginning to encapsulate it. Once there are several feet of native sand over the muck to encapsulate it, the County will resume the filling at the target rate. Subsection 4.2.4.1 of the BOR requires that the County address stabilizing newly created slopes of surfaces. To satisfy this requirement, the County will place the fill at a 4:1 slope. The outer edge of the mangrove islands slope back to a 4:1 slope and use rock rip-rap to stabilize that slope. Also, filter cloth, bedding stones, and boulders will be used. Because water currents slow near the bottom, the 4:1 slope for the seagrass elevations on the bottom will not de-stabilize. There will be turbidity curtains around the project area. Those are floating tops and weighted bottoms that reach to the bottom and are intended to contain any turbidity that may be generated by the project. Specific Conditions 12, 13, and 14 require extensive monitoring of turbidity. The County proposes to use a barge with a draft no greater than four feet. This aspect of the project will require a pre-construction meeting and extensive monitoring throughout the project. As a part of the application review, the County performed a hydrographic analysis which was coordinated with and reviewed by the Department staff. There are no expected debris or siltation concerns as a result of the project. The more persuasive evidence supports a finding that over the long term, the project is expected to have a beneficial effect on water quality. By filling the dredge hole and providing habitat for seagrass, mangroves, and oysters, the project will provide net improvement to water quality. The requirements of the rule have been met. Paragraph (1)(f) requires that the applicant provide reasonable assurance that the activities will not "cause secondary impacts to the water resources." More detailed criteria for consideration are found in BOR Subsection 4.2.7. The County has provided reasonable assurance that through best management practices, it will control turbidity. Also, Specific Conditions in the proposed permit require that water quality monitoring be conducted throughout the process. There will be no impacts to upland habitat for aquatic or wetland dependent species. This is because a vertical seawall is located upland of the project site, and no surrounding uplands are available for nesting or denning by aquatic or wetland dependent listed species. A secondary impact evaluation also includes an evaluation of any related activities that might impact historical and archaeological resources. There are, however, no historical or archaeological resources in the area. If resources are uncovered during the project, Draft Permit conditions require notification to the Department of State. Finally, there are no anticipated future activities or future phases on the project to be considered. Rule 40E-4.301(1)(i) requires that the applicant provide reasonable assurance that the project "will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed." Trump and Flagler contend that the project cannot be constructed and successfully operated as proposed. Trump's expert witness, Joseph Pike, testified that there were ambiguities and conflicts within the plan drawings that would require changes upon build-out; either fill will be placed outside of the fill area, or the mangrove islands will be smaller than depicted. Mr. Pike also voiced concerns that a 4:1 slope would not be stable and might cause fill to migrate to existing seagrass beds. He further stated that the Snook Island project included 18:1 slopes, and he thought providing rock revetment only at the intertidal zone was insufficient. Mr. Pike acknowledged that he had used 4:1 slopes in lake projects; however, in a tidal project involving fill placement, he opined that a 4:1 slope was likely to "relax." He did not do calculations about what slope might hold and admitted that prior experience using similar slopes with the same type of fill might change his opinion. Finally, Mr. Pike noted that a portion of the dredge hole would not be filled and concluded that the project would not fully cap the muck. Trump's biologist, James Goldasitch, speculated that the water flow changes would cause sediment deposition on existing seagrass beds, possibly causing the seagrasses to die. He admitted, however, that the County's plans called for the creation of 3.44 acres of seagrass and did not know the amount of habitat created compared to the amount of habitat he anticipated being affected. The Department's engineer, Jack Wu, approved the hydrologic aspects of the County's plan, but Mr. Goldasitch speculated that Mr. Wu was more focused on shoreline stability than on depositional forces. Mr. Goldasitch never actually spoke to Mr. Wu regarding his analysis, and Mr. Wu's memorandum refers not only to engineering and construction aspects of the proposal but also to the criteria in Rules 40E-4.301 and 40E-4.302. Mr. Goldasitch believed the County's boardwalk will impact the seagrass beds by blocking sunlight, but acknowledged that the Draft Permit required the boardwalk to be elevated and portions to be grated. Both the Florida Fish and Wildlife Conservation Commission and the Department's expert witness concluded that the permit conditions for constructing the boardwalk, which are common, eliminated impacts to seagrass. Mr. Goldasitch further opined that the 4:1 slope might slump, but then deferred to the opinion of a registered engineer on this type of engineering matter. The County presented its professional engineer, Clint Thomas, who worked on the project design. Mr. Thomas explained that permit drawings are not intended to be construction-level in detail, but are merely intended to provide sufficient detail for the regulator to understand the project within the 8 and 1/2 by 11-inch paper format required by the Department. The County will ultimately prepare permit-level, construction-level, and as-built drawings. Permit conditions also require a pre-construction meeting. No fill will be placed outside the area designated for fill, and the 4:1 slope will start at the outer boundary of the designated fill area until it reaches the specified elevation. Mr. Thomas acknowledged that the plan view drawings depict a mangrove island too close to the western project boundary, but stated that the mangrove island would simply be placed farther to the east during the construction-level plan process. Islands will become smaller islands, but will not be relocated, and in no event will the fill area expand; the fill boundary is a very strict limit. There is no evidence that the County has ever violated a fill boundary established in a permit. The 4:1 slope was based on the type of fill proposed for the project and to maximize project features. Mr. Thomas has successfully used 4:1 slopes with non-compacted fill in the Lagoon, both at Snook Island in its as-built state and at other projects. The islands at Snook Island are similar to those proposed. Other areas in the Lagoon have held slopes steeper than 4:1 with the same type of fill. Therefore, Mr. Thomas opined the 4:1 slope would hold. In rendering this opinion, he explained that the currents in the project vicinity are only around 1.2 knots. Because currents slow near the bottom, the 4:1 slope for the seagrass elevations on the bottom will not de- stabilize. Mr. Thomas addressed the contention that a change in water flow velocity would cause sediment to deposit on existing seagrass. The oyster reefs are rubble structures that allow the water to flow through. If any sediment flows through, it will deposit on the north side of the oyster bar, rather than on the seagrass beds. Given these considerations, the evidence supports a finding that the project will function as proposed. Finally, paragraph (1)(j) requires that the County provide reasonable assurance that it has the financial, legal, and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit. The evidence supports a finding that the County has complied with this requirement. In summary, the evidence supports a finding that the County has given reasonable assurance that the project satisfies the criteria in Rule 40E-4.301. b. Rule 40E-4.302 In addition to the conditions of Rule 40E-4.301, the County must provide reasonable assurance that the construction of the proposed project will not be contrary to the public interest. See Fla. Admin. Code R. 40E-4.302(1)(a)1.-7. Rule 40E-4.302(1)(a)1. requires that the Department consider whether the activity will adversely affect the public health, safety, or welfare or the property of others. Trump first contends that the project will increase the mosquito population. The evidence shows, however, that the mangroves will be placed below the mean high water mark and therefore no increase in mosquitoes should occur. Also, the design of the project, coupled with the local mosquito control program, should ensure that there will be no increase in mosquito population or a risk to the public health. Trump also raised the issue of an increase in trash along the boardwalk area or in the newly-created mangrove islands. The County presented evidence that there will be appropriate trash receptacles in the area as well as regular garbage collection. In terms of safety, navigation markers are included as a part of the project for safe boating by the public. The County consulted with the United States Coast Guard regarding navigation issues. Further, the project will not cause flooding on the property of others or cause an environmental impact on other property. Although a number of Trump residents expressed sincere and well-intended concerns about the project impacting the value of their condominiums (mainly due to a loss of view), BOR Subsection 4.2.3.1(d) provides that the "[Department] will not consider impacts to property values or taxes." Rule 40E-4.302(1)(a)2. requires that the Department consider whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. Subparagraph 4. of the same rule requires that the Department consider whether the activity will adversely affect the fishing or recreational value or marine productivity in the vicinity of the activity. The proposed activity is a restoration project for the creation of seagrass and mangrove habitats. As such, it is beneficial to the conservation of fish and wildlife and is expected to increase the biotic life in the project area. Besides providing additional habitat for fish and wildlife, the project will add to the marine productivity in the area. In terms of recreational opportunities, the project is expected to be a destination for boating, kayaking, fishing, and birdwatching. The Florida Fish and Wildlife Conservation Commission has also recommended issuance of the permit with the standard manatee condition for in-water work. This recommendation has been incorporated as Specific Conditions 23 through 25 Rule 40E-4.301(1)(a)3. requires that the Department consider whether the activity will adversely affect navigation and the flow of water, or cause harmful erosion or shoaling. The nearest navigation channel is the ICW. The project is located outside of that area. Subsection 4.2.3.3 of the BOR provides additional guidance on the evaluation of impacts of this nature. Paragraph (a) of that subsection provides that, in evaluating a proposed activity, the Department "will consider the current navigational uses of the surface waters and will not speculate on uses which may occur in the future." Trump residents indicated that in the project area persons are now picked up off the seawall and then travel to the ICW. Access to the seawall is possible from the east and south, although existing shoals currently limit the approach from the south. Large boats do not use the area because of shoals. In general, "[t]here's not a whole lot of boating activity in the project area." The parties agree that if the project is constructed as designed, boats will not be able to travel directly out from the seawall in front on Trump or Flagler to the ICW, as they now do. However, navigation in the area will still be available, although not as convenient as before. As to water flow, shoaling, and erosion, the more persuasive evidence supports a finding that the 4:1 slope will be stable and will not cause fill to migrate outside of the boundaries of the project into existing seagrass beds. The tidal flow will continue through the area after construction without sediment deposition into existing seagrass beds or destabilizing the 4:1 slope. There will be no shoaling or erosion. Finally, the project will be permanent and there are no significant historical and archaeological resources in the area. See Fla. Admin. Code R. 40E-4.302(1)(a)5. and 6. In summary, the evidence supports a finding that the County's proposal is neutral as to whether the activity will adversely affect the public health, safety, welfare, or the property of others; that the County's proposal is neutral with respect to navigation, erosion and shoaling, and water flow, as well as to historical and archaeological concerns; and that the County's proposal is positive with respect to the conservation of fish and wildlife, recreational values and marine productivity, permanency, and current values and functions. When these factors are weighed and balanced, the project is not contrary to the public interest and qualifies for an ERP. D. Proprietary Authorization Chapter 18-21 applies to requests for authorization to use sovereign submerged lands. The management policies, standards, and criteria used to determine whether to approve or deny a request are found in Rule 18-21.004. In making its review, the Department reviews the rule in its entirety; it also looks at the forms of authorization (e.g., letters of consent, leases, deeds, or easement) to determine the most appropriate form of authorization for an activity. Trump and Flagler have raised contentions regarding the proprietary authorization, including whether the application should have been treated as one of heightened public concern, whether the proper form of authorization has been used, and whether their riparian rights are unreasonably infringed upon by the project. Heightened Public Concern Rule 18-21.0051 provides for the delegation of review and decision-making authority to the Department for the use of sovereign submerged lands, with the following exception found in subsection (4) of the rule: (4) The delegations set forth in subsection (2) are not applicable to a specific application for a request to use sovereign submerged lands under Chapter 253 or 258, F.S., where one or more members of the Board, the Department, or the appropriate water management district determines that such application is reasonably expected to result in a heightened public concern, because of its potential effect on the environment, natural resources, or controversial nature or location. On March 13, 2008, the Department's West Palm Beach District Office sent a "heightened public concern [HPC]) memo" to the Department's review panel in Tallahassee,3 seeking guidance as to whether the project required review by the Board of Trustees under the above-cited rule. The Department emailed the County on March 14, 2008, stating that the project would be elevated to the Board of Trustees for review to approve the entire Lagoon Management Plan. The County asked for reconsideration, concerned over timing restraints on grant opportunities. This concern is based on the fact that the County will receive grant monies to assist in the construction of the project and must have regulatory approval by a date certain in order to secure those funds. A second HPC memorandum was sent to the review panel on April 22, 2008. Part of the interim decision to elevate the application to the Board of Trustees concerned the boardwalk connection to the City of West Palm Beach's existing seawall. The City of West Palm Beach is the upland owner of the seawall, sidewalk, and Flagler Drive. On June 9, 2008, the Mayor of West Palm Beach sent a letter to the Department stating that the City "fully supports" the proposed activity, and that the County and the City collaborated on the design of the project, held joint public meetings, and produced a project video. See Department Exhibit Trump and Flagler argue that under the City Charter, the Mayor cannot unilaterally bind the local government to allow structures to be built on City property. Assuming this is true, one of the remaining conditions for the County to initiate the project is to obtain a "letter of concurrence" from the City of West Palm Beach authorizing the County to connect the boardwalk to the seawall. Therefore, the review panel ultimately concluded that the application could be reviewed at the staff level and did not require Board of Trustees review. The evidence at hearing did not establish that the application was one of heightened public concern, given the limited size of the project, its location, and the net benefit to both environmental and natural resources. Compare Brown, et al. v. South Fla. Water Mgmt. Dist., et al., DOAH Case No. 04-0476, 2004 Fla. ENV LEXIS 112 (DOAH Aug. 2, 2004, SFWMD Sept. 8, 2004). Therefore, review by the Board of Trustees was not required. Form of Authorization Trump and Flagler contend that an easement is required by the County, rather than a consent of use. The standard for obtaining an easement is more stringent than a consent of use, and an easement offers a greater interest in sovereign lands. Rule 18-21.005(1) provides the general policy direction for determining the appropriate form of authorization and reads in relevant part as follows: It is the intent of the Board that the form of authorization shall grant the least amount of interest in the sovereignty submerged lands necessary for the activity. For activities not specifically listed, the Board will consider the extent of interest needed and the nature of the proposed activity to determine which form of authorization is appropriate. This rule requires that the Department should apply the lowest and least restrictive form of authorization. Trump and Flagler argue that the County's project constitutes a spoil disposal site under Rule 18-21.005(1)(f)8., a public water management project other than public channels under Rule 18-21.005(1)(f)10., or a management activity which includes "permanent preemption by structures or exclusion of the general public," as described in Rule 18-21.005(1)(f)11. Each of these activities requires an easement rather than a letter of consent in order to use sovereign submerged lands. The evidence shows that the County's project is not a spoil disposal site. Also, it is not primarily a public water management project as there is no evidence that the project relates in any way to flood control, water storage or supply, or conservation of water. Likewise, there is no evidence indicating that the activities will prevent access by the public by exclusion. Even though many of the features (structures) of the project will be permanent, the project is intended to generally increase public access to water resources, as well as the islands, boardwalk, and kiosks. Besides raising the issue of heightened public concern, the second HPC Memorandum dated April 22, 2008, sought guidance as to whether the project required a consent of use or an easement. The review panel concluded that the project qualified for a consent of use, rather than an easement under Rule 18- 21.005(1)(f), because the County's project most closely fits the definition in Rule 18-21.005(1)(c)15. That rule provides that if the proposed activity involves "[h]abitat restoration, enhancement, or permitted mitigation activities without permanent preemption by structures or exclusion of the general public," an applicant may use sovereign submerged lands with a consent of use. Because the County's project increases public access not only to water resources in the Lagoon but also to the permanent structures being built, it more closely falls within the type of activity described in Rule 18-21.005(1)(c)15. Notably, all of the County's restoration projects in the Lagoon have been previously authorized through a consent of use. Finally, the review panel concluded that the project did not fall under Rule 18-21.005(1)(f)16., which requires an easement for environmental management activities that include "permanent preemption by structures or exclusion of the general public" because of the rule's focus on the exclusion of the general public. Riparian Rights The parties have stipulated, for the purpose of this proceeding, that Trump and Flagler have riparian rights, including view, ingress/egress, fishing, boating, swimming, and the qualified right to apply for a dock, that should be considered. Trump and Flagler contend that their right to wharf out (build a dock) from the seawall, ingress/egress from navigable water, and view will be unreasonably infringed upon if the application is approved. See Fla. Admin. Code R. 18- 21.004(3)(a)("[n]one of the provisions of this rule shall be implemented in a manner that would unreasonably infringe upon the traditional, common law riparian rights, as defined in Section 253.141, F.S., of upland property owners adjacent to sovereignty submerged lands"). For the reasons given below, the greater weight of evidence establishes that none of these riparian rights will be unreasonably infringed upon. Currently, while access is possible from the east and the southern approaches, existing shoals limit the southern approach. The boardwalk will further limit boat traffic on the south end, and boats would not be able to cross over the islands. Boat traffic will still be able to access the cove from the north end, and the restoration project will create a boating destination. Trump witness Pike opined that the County's project would negatively affect navigation between the upland parcels and the ICW because the project would eliminate the eastern and southern approaches and leave only the northern approach, which could not be used by both parcels fully. The County's expert, Dr. Nicholas De Gennarro, testified that, during his site visits, he observed boat traffic waiting for the drawbridges using the east side of the ICW away from the project site. Dr. De Gennarro noted that several existing structures are closer to the ICW than the proposed County project, which lies 220 feet away from the ICW. Thus, Dr. De Gennarro concluded that the project would not impact navigation in the ICW. With respect to ingress/egress, Dr. De Gennarro acknowledged that access to the Trump and Flagler properties would not be available from the southern and eastern approaches, but concluded that the restriction represented nothing more than an inconvenience. He noted that the southern approach was already a less preferable approach due to existing shoals. At present, there is very little boating in the area outside of special events. While the project would limit the use of boats directly over the one and one-half acres of mangrove islands, the project will provide a boating destination. Further, both the City docks to the north of the site and the temporary docks in front of Flagler's property –- both used for special events –- will still be available under the County's proposal. There is no swimming and very little fishing in the area because of the degraded conditions caused by the dredge hole. Accordingly, while the project will fill a small portion of water currently available, but not used, for swimming, it will greatly enhance swimming by providing a destination for swimmers. The mangroves planned for the intertidal islands are likely to reach a height of fifteen feet and will be interspersed with spartina. The seawall is located six feet above the water line, making a person's view at eye level already several feet above the water. Trump and Flagler's buildings are built at even higher elevations. Therefore, the mangroves will not substantially obscure the view from either property, even at street level where the view is already partially obscured by existing landscaping. The Lagoon is approximately 2,000 feet across. From north to south around one hundred acres of water can now be viewed from the vicinity. Since the intertidal islands only comprise one and one-half acres, the overall impact to the view of the water body is very small. The mangroves in the planters extending out from the seawall will be trimmed to one foot above the seawall; the County requested the condition and committed at hearing to trimming the mangroves if the City of West Palm Beach does not. County photographs show Trump and Flagler's present view of the water body and demonstrate the comparatively small percentage of the view affected by the one and one-half acres of mangrove islands. See County Exhibits 133a-e and 134a-d. The photographs also demonstrated that sizeable palm trees are already part of the existing view. Additionally, the County photographs depicted the small impact that trimmed mangrove planters would have on the view. The area obstructed by the mangrove islands and seagrass is negligible compared to the expanse of the existing view. Trump and Flagler offered no evidence to contradict the County's analysis regarding the scope of the impact on the view. Trump residents Dale McNulty, Dean Goodman, and Charles Lemoine testified that they personally would not want to view mangrove islands regardless of tree size or the size of the islands. Understandably, after years of unfettered view and an open expanse of water, they are opposed to any type of project in this area of the Lagoon. However, Mr. Goodman acknowledged that he would still be able to see the Town of Palm Beach from his unit. The evidence supports a finding that while the project will undoubtedly alter the view of the water from both Trump and Flagler's property, the impact on view is not so significant as to constitute an unreasonable infringement of their riparian rights. Mr. Lemoine stated that he had a forty-foot trawler that he would like to dock in front of his property. He currently docks the boat at a marina twenty miles north of the Trump property. He prefers to bring his boat in stern first and enter slips oriented north to south. He indicated that he can drive his boat in five feet of water, but prefers six feet; however, he also testified that he has brought his boat directly up to the bulkhead in front of Trump, which is approximately a two- or three-foot depth. The witness has seen sailboats and other boats moored near the bulkhead over extended timeframes. Mr. Lemoine speculated that Trump might seek a dock, either alone or in conjunction with Flagler, but admitted that Trump has never applied for a dock permit. He stated that Trump has had discussions about the possibility of a dock over the last fifteen years and speculated that a dock plan might include anything from the purchase/lease of the City docks to a lease of Trump's riparian interests to a third party. By contrast, Trump resident and former Board member Dean Goodman indicated "the idea was to provide an amenity [for] a number of people that are in the building that are boaters." Mr. Goodman stated that he hoped to be able to have a boat in front of the building someday, but did not own a boat in Florida. Association president Dale McNulty explained that, while informal discussions have occurred regarding the possibility of a dock, no official action had been taken. Mr. McNulty characterized the dock plans as being "sort of in the land of wishful thinking." Mr. Pike, while acknowledging that both parcels would still be able to design a dock for their property, opined that the County's project unreasonably limited the size and configuration of the docks possible. Mr. Pike initially admitted that a safe navigation depth for a forty-foot boat, or even a sailboat, was four feet below mean low water (MLW), but stated that he would prefer to design a dock with an additional two-to- three feet of water below the four-foot draft to avoid propeller damage. However, Mr. Pike conceded that he has designed docks for boats in four feet below MLW and ultimately based his own calculations on an assumption of a four-foot draft and one-foot cushion, or five feet below MLW. Mr. Pike also opined that a north-south alignment for boat slips was a preferred slip orientation. Given the bathymetry in the area and the documented seagrasses, Mr. Pike estimated that twenty slips could be designed for the Flagler property, rather than the thirty-four slips provided for by the County Manatee Protection Plan. He thought that a design might accommodate thirty to thirty-two slips for Trump, rather than the forty-slips provided for by the County Manatee Protection Plan. Based on the limitation on number of slips and configurations, the witness opined that the County's project would unreasonably interfere with Trump and Flagler's ability to design a dock. He admitted, though, that the numbers derived from the County Manatee Protection Plan represent a maximum number, rather than a specified or guaranteed number. He further admitted that other agency limitations may further restrict Trump and Flagler's right to dockage. Without a permit application or plan from Trump or Flagler, County witness Robbins concluded that the most reasonable assumption was an owner-oriented facility designed for the building owners/tenants. The County introduced a graphic illustrating areas available for dock construction, with sufficient depth for 35- to 40-foot boats (-6 feet NGVD) and with no seagrasses present. Rule 18-21.004(4)(b)2. limits ownership-oriented facilities generally to forty square feet for each foot of riparian shoreline, giving Trump the ability to apply for a dock that preempted a maximum of 16,000 square feet, and Flagler a maximum of 14,000 square feet. Under the County Manatee Protection Plan, Trump would be limited to forty slips; Flagler would have the potential for thirty-four slips. Mr. Robbins testified that, in his experience, a minus five MLW is a common depth for docks, but that elevations as shallow as a minus four MLW could be used depending on the type of boats and the dock configuration. Mr. Robbins explained that, even with the County's project in place and factoring in the other limitations, Trump would still have 61,842 square feet of potential space within which to design a dock. Flagler would still have 41,481 square feet of potential space, even considering the need to retain a path for ingress and egress from the Trump parcel. A more detailed analysis of the seagrasses might make more square footage available for dock construction. Dr. De Gennarro also evaluated whether a dock could be designed to serve Trump and Flagler's parcels. The vessel owner statistics for the County indicate that at least ninety-five percent of the boats registered in the County are thirty-nine feet or less; consequently, Dr. De Gennarro focused on boats forty feet or less. Dr. De Gennarro considered the water depths and the existence of subaquatic vegetations and concluded that the graphic presented by Mr. Robbins was conservative, but still provided adequate space for both Trump and Flagler to construct appropriate dockage, allowing thirty-eight boats for Trump and thirty-two for Flagler of varying size. However, Dr. De Gennarro concluded that a dock design of forty slips for each would also be possible, depending on the size of the boats. Dr. De Gennarro proposed that a single, double-loaded parallel dock design would be a good layout for a potential docking facility in front of both Trump and Flagler's property that would be protected by the County's proposed islands, provide sufficient water depths, and provide an attractive facility. He specified, however, that the single, double-loaded parallel dock design was simply one of "many" that might work in the given space. Dr. De Gennarro explained that the existing dredge hole would not be a preferable location for either a mooring field or a dock because the deep muck-bottom would drive up the costs for either type of facility. Accordingly, Dr. De Gennarro concluded that the County's project would not foreclose or even substantially restrict the ability to locate a dock in front of Trump and Flagler’s property. The more persuasive evidence supports a finding that neither the right of ingress/egress nor the right to boat in the vicinity is unreasonably infringed upon by the County's project. Trump and Flagler will continue to have reasonable access to navigation. The northerly approach preserved by the County's project will allow for boat traffic to safely navigate in the area. While the southerly and easterly approaches are eliminated by the County's plan, the evidence indicates that the two approaches were less preferable than the northerly approach because of the presence of shoals. Based on the above considerations, the County's project will not unreasonably infringe upon Trump or Flagler's qualified right to a dock. The fact that the project might preclude the design and permitting of a dock that would host very large vessels does not mean that Trump and Flagler's rights regarding docking have been unreasonably infringed. The evidence shows that substantial docking facilities of multiple configurations are still possible even if the County's project is approved. In summary, the County's application for proprietary authorization should be approved. Other Contentions All other contentions raised by Trump and Flagler have been considered and are found to be without merit.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department enter a final order approving the County's application for a consolidated ERP and consent to use sovereignty submerged lands. DONE AND ENTERED this 24th day of September, 2009, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September, 2009.

Florida Laws (6) 120.52120.569120.57120.68253.1417.64 Florida Administrative Code (5) 18-21.00418-21.00518-21.005140E-4.30140E-4.302
# 3
FRANK J. FABRE AND LARRY M. JACOBS (GARCON POINT) vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 85-000365 (1985)
Division of Administrative Hearings, Florida Number: 85-000365 Latest Update: Mar. 28, 1986

The Issue Whether Petitioners are entitled to validation of an alleged determination by Respondent of the landward extent of its dredge and fill jurisdiction over a portion of Petitioners' Property?

Findings Of Fact Under former DER rules, those using the vegetative index adopted June 10, 1975, as amended March 11, 1981, DER's dredge and fill jurisdiction upland of the mean high water line depended exclusively on the landward extent of waters of the state, as evidenced by the dominance of certain species of plants that thrive under wet conditions. Only if these indicator species, in the aggregate, were not dominant along the edge of a water body would DER's jurisdiction end at the shoreline. In 1977, Petitioners Fabre and Jacobs acquired more than 43 acres of unimproved land on Garcon Point, fronting Blackwater Bay in Santa Rosa County. By the time of the hearing, their original development plans had changed, but Petitioners still held the property in the hope of subdividing part of it for resale. At Petitioners' request, somebody from the Pensacola office of the Department of Environmental Regulation (DER) inspected the site in the fall of 1979, probably Michael C. Applegate on October 3, 1979. Petitioners wanted to know what DER permits, if any, would be required in order for a road to be built on the property. In connection with their inquiry, they furnished DER a legal description of the parcel and an aerial photograph of the area. Whether DER also received a site plan at that time depicting the proposed road is not shown by the record. DER's pre-application file on the parcel has probably been destroyed. At least in the minds of some DER employees, there is a clear difference between advising whether a particular project falls within DER's permitting jurisdiction, based on a site visit; and making a jurisdictional determination, which may involved planting flags that are then surveyed or photographed from the air. Petitioner Fabre received a letter from Michael C. Applegate, at the time DER's dredge and fill supervisor in Pensacola, which stated: RE: Approximate 43.48 acre parcel located between State Road 191 and Blackwater Bay, Garcon, Section 14, Township I s, Range 28 w, Santa Rosa County, Florida Dear Mr. Fabre: The above referenced land parcel (legal description enclosed) was inspected by a member of this Department to determine the necessity of obtaining dredge and fill permits for future construction activities on the site. It is the opinion of the staff that since the site is dominated by upland vegetation (oaks, pines, etc.) and has no water bodies connecting to the adjacent B1ackwater Bay that dredge and fill permits will not be required for construction activities within the interior of the property; however, any construction along the shoreline or any attempt to connect artificial lakes or canals to Blackwater Bay will require prior permit authorization from this Department in accordance with the provisions of Section 403.087, Florida Statutes, 253.123 and 253.124, F.S. and Section 17-4.28, Florida Administrative Code. Further, should your development of the property result in and [sic] increased stormwater discharge, a stormwater permit may also be required. Joint Exhibit No. 4 In the opinion of DER's expert witness, "along the shoreline" usually means to the edge of open water. In surveying, "shoreline" is a term of art meaning mean high water line. As a practical matter, mean high water line surveys are seldom undertaken because they are complex, expensive and time- consuming. Because Mr. Applegatets letter was undated, Mr. Fabre later asked for a dated reiteration, which DER furnished by copy of a memorandum to the file from DER's William H. Daughdri11, stating: SUBJECT: Review of Undated Correspondence to Frank Fabre [sic] (Baskerville Donovan Engineers) Regarding Proposed Construction on a 43.48 Acre Parcel of Property on Blackwater Bay. On June 23, 1980, I received a call from Mr. Prank Fabre, [sic] during which he requested clarification of a letter written by Mike Applegate in October, 1979. I advised Mr. Fabre that my recollection of the proposed project and subsequent letter was that the excavation was on the interior of the property and not subject to Department of Environmental Regulation's permitting jurisdiction. I cautioned Mr. Fabre [sic] to read the letter carefully and proceed accordingly. On June 24, 1980, I reviewed Mile's letter to Mr. Fabre [ sic] (copy) attached). Mike's letter indicated that no permit would be required for construction activities in the interior of the property; however, construction along the shoreline or any attempt to connect artificial lakes or canals to Blackwater Bay would require a valid Department permit. I called Mr. Fabre and advised him of same. Finally, in reviewing Mr. Applegate's letter to Mr. Fabre, I discovered it to be undated. The photograph attached to the letter referenced a date of October 3, 1979. I assume that the letter to Mr. Fabre went out within a week of the inspection and would therefore be properly dated between October 5 and October 10, 1979. Joint Exhibit No. 3. Having received this memorandum, Petitioners filled out a form Army Corp of Engineers/DER joint application for activities in the waters of the State of Florida. They attached an aerial photograph on which a proposed road is shown, lying more than 200 feet inland; and a drawing representing a proposed community building elevated on piling, approximately 50 feet inland of the mean high water line. Joint Exhibit No. 5. On September 24, 1984, copies of the joint form application with attachments were mailed to DER, along with a cover letter stating, "As we discussed, an application fee is not included since D.E.R. does not have jurisdiction based on enclosed letters from Michael Applegate and William Draughdrill [sic]." Joint Exhibit No. 5. In response, W. Richard Fancher, DER's dredge and fill supervisor, wrote Petitioners, on October 9, 1984: I have reviewed your permit application for a fill road leading to Blackwater Bay, along with the accompanying jurisdictional determinations. However, the Department's dredge and fill jurisdiction has changed significantly since Mr. Applegate's and Mr. Daughdrill's determinations, specifically, since October 1, 1984. Unless you have had the old pre- October 1 jurisdiction verified by our Bureau of Permitting in Tallahassee ("grandfathered"), the Department must consider the project under the post-October 1 jurisdiction and permitting standards. Joint Exhibit No. 7 (emphasis supplied.) A DER "completeness summary" also dated October 9, 1984, was included indicating that Petitioners' application was incomplete for failure to pay the application fee, because, "approximate MHW's" had not been labeled, a claim at least partially belied by attachments to the application, and because certain water quality information allegedly had been omitted. Joint Exhibit No. 7. On October 15, 1984, DER received Petitioners' request for validation with supporting papers. Joint Exhibit No. 9.

Florida Laws (1) 403.087
# 4
STORMY SANDQUIST, MARION C. SNIDER, ET AL. vs. RONALD JANSON AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-001309 (1983)
Division of Administrative Hearings, Florida Number: 83-001309 Latest Update: Feb. 28, 1984

Findings Of Fact On November 1, 1982, Respondent Janson filed a Joint Application for a dredge and fill permit from Respondent, Department of Environmental Regulation, and from the Department of the Army Corps of Engineers. The project described in that application involved the construction of an approximately 1,000-square- foot, pile-supported residence, landward of the mean high water line but within the landward extent of Robinson Creek in St. Johns County, Florida. The proposed project also involved the placement of approximately 35 cubic yards of fill and a 30-foot culvert within a small (approximately 4-foot), tidally- influenced roadside ditch for driveway access and parking. The original application sought permission to place part of a concrete driveway and tool shed within the landward extent of Robinson Creek. The project is to be constructed on Lot 47, J.A. Lew Subdivision. Respondent Janson owns Lot 47, as well as Lots 45 and 46, which lots are north of and adjoining Lot 47 and also adjoining Robinson Creek. The next adjoining property owner to the north is the City of St. Augustine, Florida, which presumably owns the street. The adjoining property owner to the south of Lot 47 is Virginia P. Melichar. Neither Melichar nor the City objected to the Department's approval of the dredge and fill permit application. In support of his application, Janson retained the services of a registered surveyor and civil engineer, who performed a survey on Lot 47 to determine the location of the mean high water line with reference to the proposed project. That expert determined the location of the mean high water line to be at elevation 2.4 feet. Accordingly, all work contemplated by the dredge and fill permit is upland from the mean high water line. T.J. Deuerling, an environmental specialist for Respondent, Department of Environmental Regulation, visited the project site on December 13, 1982 and on December 30, 1982 in order to prepare the Department's Biological and Water Quality Assessment. As a result of those site visits, Deuerling recommended to Respondent Janson that he modify his permit application by moving the concrete slab and tool shed from the marsh area onto the uplands. Janson did so revise his application. In spite of the name of the permit being sought by Respondent Janson, the project involves no dredging. However, the culvert and its attendant fill would be placed in the man-made roadside ditch. That ditch constitutes a very weak transitional marsh. Although the culvert will eliminate some vegetation within that ditch, the effect of the elimination will be insignificant on water quality. The pilings for the pile-supported residence will also eliminate a small area of marsh. The anticipated shading caused by the pile-supported residence may impact somewhat on the vegetation in a small area below the residence; however, due to the fact that the floor of the house will be eight feet above the ground, light will still be able to penetrate. Therefore, the vegetation below the pile-supported residence will continue to act as a filter for pollutants. Janson has mitigated the small loss in wetlands by modifying his project so as to remove the concrete slab and tool shed from the marsh area to the uplands. Due to the project's small size, no storm water impact can be expected. Additionally, no evidence was introduced to show a violation of any water quality standard as a result of the proposed project. On March 16, 1983, Respondent, Department of Environmental Regulation, executed its Intent to Issue the dredge and fill permit in accordance with the revised application and subject to the conditions that: (1) turbidity curtains be employed in the ditch during the placement of fill over the culvert to contain any turbidity generated, and (2) construction on the uplands be confined to periods of normal water level conditions. On July 5, 1983, the Department of the Army Corps of Engineers issued its Permit and Notice of Authorization. The essence of the testimony presented by the Petitioners, including that of the employees of the St. Johns River Water Management District, who testified in opposition to the proposed project, is that even though Janson's proposed project would not impact water quality in a way that was either significant or measurable (although no one even suggested any specific water quality standard that might be violated), approval of Janson's permit might set a precedent for other projects which might then have a cumulative impact in some unspecified way at some unspecified location. No evidence was offered to show that Respondent, Department of Environmental Regulation's review of permit applications is other than site specific. Further, no evidence was introduced to show any proposed project anywhere having any impact with which Janson's project could be cumulative. Petitioners Sandquist and Shuler live in the neighborhood of the proposed project, perhaps as close as two blocks away.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered dismissing with prejudice the petition filed herein as to each individual Petitioner and issuing a dredge and fill permit to Respondent Janson in accordance with his revised application. DONE and RECOMMENDED this 13th day of January, 1984, in Tallahassee, Leon County, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of January, 1984. COPIES FURNISHED: Stormy Sandquist 3 Aviles Street St. Augustine, FL 32084 Marion C. Snider Volla F. Snider 79 Fullerwood Drive St. Augustine, FL 32084 Carmen Ashton 51 East Park Avenue St. Augustine, FL 32084 Reuben D. Sitton Gail P.Sitton 35 Seminole Drive St. Augustine, FL 32084 Sandra N. Shuler 22 East Park Avenue St. Augustine, FL 32084 Patty Severt Greg Severt 1 Fern Street St. Augustine, FL 32084 Nancy Moore Paul Moore, Jr. 6 Fern Street St. Augustine, FL 32084 John D. Bailey, Jr., Esq. P.O. Box 170 St. Augustine, FL 32085-0170 Charles G. Stephens, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301

Florida Laws (2) 120.57120.66
# 5
KATHRYN HAUGHNEY vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 90-007215 (1990)
Division of Administrative Hearings, Florida Filed:Ormond Beach, Florida Nov. 14, 1990 Number: 90-007215 Latest Update: Apr. 25, 1991

The Issue Whether or not Petitioner is entitled to a dredge and fill permit to construct a dock and seawall by provision of reasonable assurances that the project is in the public interest.

Findings Of Fact On May 8, 1989, the Petitioner, Kathryn Haughney, applied to DER for a permit to construct a dock and seawall on the shore of the Halifax River in Volusia County. The portion of the Haughney property where the dock and seawall would be constructed is separated from the Haughney home by John Anderson Drive, which parallels the river's edge and is separated from the river by a ribbon of undeveloped property at that location and to the south. A house is located at water's edge on the lot to the north of the proposed construction site. The Haughney home itself is set well back from John Anderson drive on the side of the street away from the river. The Halifax River is classified as a Class III water body under DER rules. The particular part of the Halifax River where the Haughney property is located and where the dock and seawall are proposed is also within the Tomoka Marsh Aquatic Preserve, which is an Outstanding Florida Water under DER rules. The dock as proposed by Petitioner will be 320 square feet. DER denied the permit application on July 19, 1990, but in so doing did not deny the application on the basis of the proposed dock, which, because of its dimensions, is exempt from DER permitting requirements. The seawall as proposed is to be 137 feet long. Petitioner applied to extend it 16 feet out into waters of the state at the northern end, gradually increasing to 34 feet into waters of the state at the south end. Additionally, 5 feet of riprap would also extend out into waters of the state along the seawall's entire length. The waters of the state that would be filled by the proposed seawall contain lush wetland vegetation that provides habitat for a number of macroinvertebrate species which are part of the food chain feeding fish and wading birds such as egrets and herons. Fiddler crabs and colonies of mussels have been observed on the site. The area to be filled provides a valuable habitat for fish and wildlife. There was no mitigation offered by Petitioner to make up for the loss of habitat to be occasioned by the proposed construction. Although Petitioner asserted DER had named no "endangered species" and that the Environmental Protection Administration had not designated this area as "endangered," those federal concerns were not at issue. If such federally designated species or location designation existed in the locale, it might militate against granting this application for permit, but in the negative, it is irrelevant. A vertical seawall exists immediately north of Petitioner's shoreline. The shoreline to the south remains undeveloped. (See Finding of Fact 2). Construction of seawalls, especially those that extend out from the existing shoreline, typically causes erosion on adjacent shorelines, and additional seawalls exaggerate wave energy and can have a cumulative erosive effect. The foregoing fact is found in reliance upon the testimony of Don Medellin, an Environmental Specialist II for DER, and Barbara Bess, an Environmental Manager for DER, both accepted as experts in environmental aspects of dredge and fill permits. The assertion that actual erosion on the property to the south has already occurred was contained in a letter from Petitioner's southern neighbor (DER Exhibit 6). Petitioner's representatives objected to consideration of this exhibit as "hearsay." They are correct and current erosion to the south is not found as a fact. Nonetheless, actual erosion in a pocket on the north end of Petitioner's shoreline has been shown by the direct testimony of Emmett and Martha Haughney, who assert that their property is eroding due to the existing seawall and that Petitioner wants a permit for a seawall to alleviate this erosion. Their evidence is confirmed by the personal observations and testimony of Mr. Medellin and Ms. Bess. Further, upon their testimony, it is accepted that this minimal pocket of erosion is most likely due to the existing seawall to the north and that if the Petitioner builds a seawall to the specifications now set out in the permit application, there is potential for similar and perhaps cumulative erosion to the shoreline to the south of Petitioner's lot. Neither the city nor county involved has land use restrictions which would prohibit Petitioner's proposed seawall except that Volusia County advocates riprap requirements if this permit application were granted. In its Notice of Permit Denial, DER advised Petitioner as follows: The Department has determined that the follow- ing changes to the project may make the project permittable: The vertical seawall should be eliminated and replaced with coquina rock riprap revet- ment. The riprap should be located further landward and conform to the slope of the existing embankment. Backfilling on the north property line is acceptable provided the fill area does not extend more than 10 feet westward in the most eroded area. Accordingly, the riprap could extend to the adjacent seawall and gradually extend in a more landward direc- tion to prevent excessive elimination of the littoral zone vegetation. Whatever alternative the applicant elects to choose, the removal or elimination of littoral zone vegetation must be offset in the form of mitigation if the impacts can not be reduced any further. Finally, the agent should eliminate the use of generic drawings which must be continually revised. All drawings should reflect the existing and proposed conditions and the impacts associated with the project. Petitioner's contractor, Andy Harris, testified to other alternatives that could be used by Petitioner in constructing her seawall, but the evidence of Mr. Medellin and Ms. Bess is persuasive that the alternative measures proposed by Mr. Harris would not provide the reasonable assurances the law requires DER to obtain from Petitioner.

Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Regulation enter a Final Order affirming its July 19, 1990 Notice of Permit Denial. RECOMMENDED this 25th day of April, 1991, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of April, 1991. APPENDIX TO RECOMMENDED ORDER, CASE NO. 90-7215 The following constitute specific rulings pursuant to Section 120.59(2) F.S. upon the parties' respective proposed findings of fact (PFOF): Petitioner's letter to Hearing Officer (filed March 22, 1991) The first paragraph complains that a VCR was unavailable in the hearing room so that Petitioner's videotape could not be shown. Petitioner should have made arrangements for showing the tape and did not. Likewise, Petitioner never offered the tape in evidence (for viewing by the Hearing Officer afterwards in preparation of this Recommended Order). Therefore, it very properly was not considered. The next 3 paragraphs refer to the Casden letter (DER Exhibit 6), which is covered in FOF 8-9. The remaining paragraphs are rhetoric and legal argument upon which no ruling need to made under Section 120.59(2) F.S.; however, they are alluded to in the Conclusions of Law. Petitioner's letter to DER Counsel (filed March 25, 1991 by DER, suggesting it was Petitioner's proposed findings of fact) 1-3 For the reasons set out above, the Petitioner's videotape was not considered. The subject of erosion to the degree proved at the hearing is covered in the Recommended Order. 4-5, PS 1-3 Mere rhetoric and legal argument upon which no ruling need be made under Section 120.59(2) F.S.; covered in the Conclusions of Law to the degree appropriate. Respondent's PFOF: 1-11 Accepted as modified to reflect the greater weight of the credible and probative record evidence as a whole. That which is rejected is rejected as not proven or not persuasive. Unnecessary or irrelevant material has likewise been excluded. COPIES FURNISHED: Douglas MacLaughlin Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Kathryn Haughney 2301 John Anderson Drive Ormond Beach, FL 32074 Emmett and Martha Haughney 2301 John Anderson Drive Ormond Beach, FL 32074 Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (2) 120.57403.813
# 6
CLARK VARGAS, ET AL. vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 84-003528 (1984)
Division of Administrative Hearings, Florida Number: 84-003528 Latest Update: Nov. 01, 1991

Findings Of Fact In June 1984, Clark Vargas applied for a permit with the Department of Environmental Regulation for activities in the waters of the state. The application stated that the proposed activity was to construct a soil road 700 feet long and constructed of 2,000 cubic yards of fill to be deposited landward of the mean high water line. The roadway proposed was to have Geotextile Fabric placed over it, and would have fifteen inch culverts for cross flow. The purpose of the road was to allow 8 property owners to have automobile access to their lots. Attached to the application was a copy of a larger engineering drawing of the project, reduced to letter size paper. The larger drawing C in evidence as Responder's Exhibit 1, and the original application is in evidence as Respondent's Exhibit 2. The drawing depicts the construction that is proposed, and in the notes states that the mean high water line is 1.1 feet above mean sea level. The drawing (Respondent's Exhibit 2) shows a number of elevation readings along the road. The elevation readings on the land upon which approximately one half of the road is to be located, the southerly portion closest to Julington Creek, and adjacent to lots 19 through 26, are all below the elevation of mean high water. The data as to the mean high water elevation for the note on the drawing was obtained by Mr. Vargas from the Corps of Engineers. The elevations on the road were the elevations measured by a survey caused to be conducted by Mr. Vargas starting from a U.S.G.S. benchmark three quarters of a mile away. The survey was conducted by a registered land surveyor. Mr. Vargas stated that the survey was not meant to be a survey to establish mean high water, and that it was intended to determine a price and plan for construction. In Mr. Vargas's professional opinion, the survey was not adequate to establish the mean high water line. Timothy J. Deuerling, an Environmental Supervisor I for the Northeast District, visited the site of the project in the summer of 1984. He saw water throughout the area. He developed the initial opinion that the project was landward of the mean high water line. When he returned to the office, he looked at the small attached drawing and decided that the project appeared to be mostly landward of the mean high water line. The elevations are very unclear on the reduced size version attached to the application. Mr. Deuerling's statement as to the mean high water line is contained in Respondent's Exhibit 4. It is the finding of the Hearing Officer that the drawing was so small and the elevations so unclear that Mr. Deuerling's opinion as to the mean high water line in Exhibit 4 is not reliable, and is rejected. Jeremy G. Tyler, Environmental Supervisor of the Dredge and Fill Section, North East District, said that the conclusions contained in the Intent to Deny and Final Order of Denial, Respondent's Exhibits 7 and 6, that one-third of the fill was to be placed waterward of the mean high water line, was based upon the data provided to DER by Mr. Vargas, Respondent's Exhibit 2. Mr. Tyler said that it is very hard to determine mean high water line by site inspection, and that he credited the survey as better evidence. It is she finding of the Hearing Officer that the location of the mean high water line has not been established by the evidence. This finding is not based upon the testimony of Mr. Vargas, however. Mr. Vargas did not present any evidence that the standard for mean high water, which was obtained from the Corps of Engineers, was inaccurate, and he did not present any evidence that the survey elevations on the drawing were inaccurate. There is good reason to believe that the proposed road in this case may be, at least with respect to the one half from lots 19 through 26, waterward of the mean high water line. The evidence shows there is an elevated ridge along the edge of the canal, that this ridge was caused by deposit of dredged material when the canal was dredged in the 1950's or 1960's, and that the ridge has eroded in places, and the water from the canal and Julington Creek floods much of the area from time to time through low places in the ridge. The engineering drawing, however, runs a series of elevation readings across only two places on the ridge, and in both cases there is at least one reading above mean high water level. Further, the only reading at a spot directly on the open water is at the southerly end of the proposed road, and it also is above mean high water. It is possible, therefore, that although portions of the road are below mean high water elevation, these portions may be completely surrounded by higher ground. It is also possible that the several low spots on the canal ridge bring the mean high water line to the road itself. On this record, it is not possible to conclude where the mean high water line is. The site of the proposed road and surrounding lots are located in a hardwood swamp associated with Julington Creek in Duval County. The land upon which the road would be built is heavily wooded. Julington Creek is Class III waters of the state. The land upon which the road is to be built is the landward extent of the waters of the state. All of the Petitioners stipulated at the hearing that the Department of Environmental Regulation has jurisdiction to require a permit for fill pursuant to Chapter 403, Florida Statutes. The proposed project would result in the placement of silica fill upon a strip of wetlands described above measuring 25' by 702.5', which is 17,562.5 square feet, plus four driveway pads to lots measuring 25' by 30', for an additional 3900 square feet, for a total of 20,562.5 square feet, which is 0.47 of an acre. (An acre is 43,560 square feet.) The sand of the roadway and driveway pads will not pollute the waters of the state. The sand of the road will not increase biological oxygen demand or nutrients. During construction, turbidity could be increased if high waters are experienced and the area is not properly stabilized, but turbidity could be monitored and controlled. The materials of the roadway further will not depress the oxygen levels in Julington Creek. The project originally proposed that seed and fertilizer be used to stabilize the banks of the road, and fertilizer would contribute to nutrients in the waters of the state, but Petitioners at the hearing gave reasonable assurances that seeding could be accomplished without fertilizer by using burlap and seed. The roadway itself will also not generate unlawful bacteria that could make its way to the waters of the state. The road will disturb the biological integrity of the organisms living in the soil beneath the roadway and driveway pads. The proposed project will permanently destroy 0.47 of an acre of the wetlands associated with Julington Creek. These and adjacent wetlands function as a natural kidney, cleansing the water of pollutants, in a continuous cycle. Wetlands contain soil and living organisms that, in balance, filter out pollutants, assimilate nutrients, and provide habitat for organisms. The silica road proposed by Petitioners will not perform these functions. Petitioners presented no evidence to rebut these findings, except to argue that the loss of wetland was insignificant and to argue that wetlands, at times, will also cause pollution. Petitioners gave no other reasonable assurances that the long-term effects of the road would not degrade water quality. The exchange of water, which results in the natural filtration and cleansing described above, occurs from waters coming from the uplands, from the wetlands, and from open waters such as Julington Creek. Julington Creek is tidal, and the testimony indicated that with significant regularity the wetlands associated with this proposed road were inundated with water. In a natural state, wetlands will experience dry conditions. During such periods, which are natural and cyclical, water will drain from the swamp and there can be a natural depression of oxygen levels in the open waters, increasing suspended solids. While these facts are true, Petitioners did not present evidence to show with particularity whether this had occurred or to what extent this had occurred with respect to the wetland area where the road is to be located, and did not show with particularity how removal of these wetlands by constructing this road would prevent natural degradation of the water in the future. Moreover, whether or not the natural filtration system of a wetland becomes less efficient due to natural cycles is not relevant in this case. Petitioners here do not propose to replace nature's cyclical inefficiencies with a better, manmade system, but propose, rather, to remove a significant portion of the only filter now operating, without replacement. The entire Julington Creek drainage basis is 30 or 40 square miles. The relevance of this figure was not established, since from the map which is Respondent's Exhibit 9 it is clear that the drainage basis of Julington Creek, with its associated wetlands, serves to filter pollutants from an equally large, if not larger, upland area. Petitioners argue that removal of 0.47 acre is insignificant if the entire area is 30 to 40 square miles, but from Respondent's Exhibit 9 it is evident that much of that other part of the wetland is not available to function as a filter for the waters currently filtered by the wetlands in the vicinity of the pro- posed roadway. The proposed road is near the conjunction of Julington and Durbin Creeks, and near the place where the open waters enlarge. The wetlands of the proposed road would be expected to serve the filtration function for those open waters and the uplands immediately above the wetlands, and not some other part of the 30 or 40 square miles. The land at the headwaters of Julington Creek is now being developed for multifamily housing and industrial uses, and the whole watershed of the Creek is being developed. The waters of Julington Creek have already been stressed in a general way by this development. Petitioners Vargas, Mrs. M. E McCullough, Dr. Robert L. Barksdale, and Mr. Steve Scecere, all testified at the hearing, and own, respectively, lots 22, 21, 19, and 24. All testified that they intend to build houses on their lots, but have not yet applied for permits. Since 1977, the Department of Environmental Regulation has consistently taken the position that deposit of fill on the wetlands which are the landward extent of Julington Creek will degrade the quality of the waters of the state, and have consistently acted to prohibit such fill. See Respondent's Exhibits 8, 10, and 11. The Department further has consistently told prospective buyers of this position with regard to these wetlands. Of particular relevance to this application, in 1977 the Respondent denied a fill permit to place 2,500 cubic yards of fill on lot 20 as depicted on Respondent's Exhibit 1. This lot is now owned by Debra H. Prevatt, and is contiguous to lot 19 owned by Petitioner, Dr. Robert L. Barksdale. The fill proposed in 1977 would have eliminated 20,000 square feet of wetlands, approximately the same as the proposed project in this case. Petitioner proposes the finding that the Corps of Engineers stands ready to issue their permit pending resolution of their application by the Department of Environmental Regulation. This finding is based solely upon the testimony of Mr. Vargas as to the intentions of unnamed officials in the Corps of Engineers, and as such, is hearsay. Therefore, absent direct evidence on the point, the proposed finding is rejected. Petitioners propose a finding that the permitting process progressed "without negative feedback" until objections were raised by adjacent property owners. This finding was not supported by any evidence other than the opinion of Mr. Vargas, and will be rejected as unsupported and possibly hearsay. It is also rejected as irrelevant since there was no evidence that the Respondent denied the permit for reasons other than those provided by statute and regulation. The Petitioners have paid taxes on their property, are of the opinion that they cannot build on their land if the permit is denied, and would be willing to sell their land to the state for a reasonable amount if the permit is denied. Respondent has not placed a monetary value on the wetlands which Petitioners propose to fill. If Petitioners proposed to build the road on pilings, elevated above the wetlands so that most of the wetlands would continue to function, the application would be approved.

Recommendation It is therefore recommended that the application for a dredge and fill permit to construct the road and driveway pads as proposed by Petitioners be DENIED. DONE and ORDERED this 1st day of March, 1985, in Tallahassee, Florida. WILLIAM C. SHERRILL, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of March, 1985. COPIES FURNISHED: Clark Vargas, P.E. President C. Vargas & Associates 8596 Arlington Expressway Jacksonville, Florida 32211 M. E McCullough 9139 Warwickshire Jacksonville, Florida 32217 Steve Scecere 9058 Kentism Court Jacksonville, Florida 32217 Dr. Robert L. Barksdale 2423 Acadie Jacksonville, Florida 32205 Ross Burnaman, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinke, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (2) 120.57403.087
# 7
A. WAYNE LUJAN vs DEPARTMENT OF ECONOMIC OPPORTUNITY AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 20-000663 (2020)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 06, 2020 Number: 20-000663 Latest Update: Mar. 06, 2025

The Issue The issue to be decided in these cases is whether Petitioner, A. Wayne Lujan (Petitioner), was entitled to issuance of five environmental resource permits (ERPs) that Respondent, Department of Environmental Protection (DEP), intended to deny as stated in notices of denial dated October 25, 2019.

Findings Of Fact The following Findings of Fact are based on the stipulations of the parties and the evidence adduced at the final hearing. Parties and Background Petitioner Lujan is the president and a director of Kay Haven Associated Enterprises, Inc. (Key Haven), that owns the five parcels, which are the subject matter of this hearing. Although Key Haven owns numerous lots, it chose to submit ERP applications for the Subject Lots within the Key Haven Tenth Addition plat dated September 1966 (Plat). See Joint Exhibit 84. Joint Exhibit 84 The Subject Lots are located in an unincorporated part of the County on the northwestern edge of a body of land lying north of State Road A1A, identified on the Plat as Raccoon Key. The Subject Lots are approximately half a mile east of the city limits of Key West, Florida. The Subject Lots are all characterized by a small upland portion adjacent to Floral Avenue. The majority of the Subject Lots transition into a mangrove fringe of varying depth and submerged lands containing marine seagrasses and sponges. See Joint Exhibits 81 and 82. Joint Exhibit 81 Joint Exhibit 82 DEP is the administrative agency of the state having the power and duty to protect Florida's air and water resources, and to administer and enforce the provisions of part II of chapter 380, part IV of chapter 373, and chapter 403, Florida Statutes. DEP also administers the provisions of Florida Administrative Code chapters 62-312 and 62-330 regarding activities in wetlands and other surface waters of the state. DEO is the state land planning agency and reviews certain permit applications for consistency with its statutory responsibilities under the Florida Coastal Management Program (FCMP), which includes part II of chapter 163, and part I of chapter 380, Florida Statutes. Relevant to this proceeding, DEO exercises authority over the ACSC program. See § 380.05, Fla. Stat. On July 26, 2018, Petitioner filed five applications for ERPs with DEP. Although certain details within each application differed, the applications all sought to authorize construction of a seawall in the waters of the Gulf of Mexico and in unnamed wetlands within the landward extent of the Gulf of Mexico, a Class III OFW, to remove the entirety of the existing mangrove fringe, and to place fill within wetlands and other surface waters for the construction of single-family residences (Project). The minor differences in each application relate to the length of the seawall and the amount of fill necessary for each lot. Although some testimony was provided concerning the differences, no party argued that the differences were material to the determinations necessary in this proceeding. Accordingly, the factual and legal analysis for the Subject Lots and ERP applications were addressed without distinction herein. DEP forwarded a copy of the applications to DEO for its recommendation. On August 24, 2018, DEO issued objections to approval of the permits citing inconsistency with the Florida Keys ACSC Principles for Guiding Development (PGDs) in section 380.0552(7). DEO also objected based on inconsistencies between the Project and the Monroe County Comprehensive Plan (Comp Plan) and Land Development Code (LDC), which implement the PGDs. DEP's first RAI dated August 24, 2018, included DEO's objections. The first RAI notified Petitioner that DEP had concerns with the Project that included: (1) installation of the vertical seawall; (2) placement of fill within an OFW; (3) direct impacts to marine seagrass bed community without adequate mitigation; and (4) failure to provide stormwater management plans since the Project was a common plan of development. The first RAI contained 19 specific requests for additional information. On October 23, 2018, Petitioner responded to DEP's first RAI by submitting slightly revised plans. The revised Project proposed less of a vertical seawall footprint by adding rip-rap to the side seawalls as a means of containing fill. Petitioner's responses to the 19 specific requests for information can generally be categorized as follows: (1) elimination of some vertical seawalls, but not the ones on the waterward edge of the Subject Lots; (2) no change in the placement of fill; (3) Petitioner would attempt to find appropriate compensatory mitigation for the seagrass impacts; and (4) Petitioner did not consider the Project to be a common plan of development. Regarding DEO's objections, Petitioner stated that "[w]e acknowledge that the project has been forwarded to FWC [Florida Fish and Wildlife Conservation Commission] and DEO and that additional comments and information may be requested by those agencies in order to fully evaluate the application." Petitioner did not substantively address DEO's objections. DEP issued a second RAI on November 21, 2018. DEO again objected in a letter dated November 26, 2018. DEP's second RAI raised the same concerns as the first RAI and acknowledged that four of the 19 specific items were adequately addressed. On January 11, 2019, Petitioner responded to DEP's second RAI by again submitting slightly revised site plans. However, the Project remained generally unchanged, with a proposed vertical seawall on the waterward edge of the lots, rip-rap along the sides, removal of the entire mangrove fringe, and fill of the entire lots eliminating the existing marine seagrasses. DEP issued a third RAI to Petitioner on February 8, 2019. DEO reiterated its objections by letter dated February 8, 2019. The third RAI raised the same concerns as the first and second RAIs, although DEP acknowledged that six of the 19 specific items were adequately addressed. By letter dated April 8, 2019, Petitioner responded to DEP's third RAI. The response again proposed slightly altered site plans from the January 2019 submissions. Petitioner essentially stated that mitigation opportunities were scarce, but had contacted the County and was looking into derelict vessel removal. However, the proposed Project remained generally unchanged, with a proposed vertical seawall on the waterward edge of the lots, rip-rap along the sides, removal of the entire mangrove fringe, and fill of the entire lots eliminating the existing marine seagrasses. As it relates to DEO's objections, Petitioner responded that "[a]fter review of the comments outlined in the [DEO] revised letter, it seems that the DEO objections are related to compliance with the provision[s] of the [Monroe] County [Comp Plan]. We will deal with those issues at the time of local permitting." Petitioner again failed to substantively address DEO's objections. DEP issued its final RAI on May 8, 2019. DEO again objected by letter dated May 6, 2019. This final RAI raised the same concerns as the first, second, and third RAIs. DEP stated that seven of the 19 specific items were not addressed by Petitioner, and that failure to provide a complete response to the prior RAI may result in denial of the ERP applications. On August 29, 2019, Petitioner responded to DEP's final RAI by once again submitting slightly revised plans, and additional information concerning mitigation proposals. However, the Project did not change and Petitioner again failed to substantively address DEO's objections. DEO’s objection letter identified that the ERP applications were inconsistent with the Florida Keys ACSC PGDs, seven Comp Plan policies, and six regulatory provisions of the County's LDC. DEP denied the ERP applications on October 25, 2019. The grounds for denial reiterated the issues not addressed by Petitioner's RAI responses. Specifically: (1) the failure of the Project to provide reasonable assurances concerning direct, secondary, and cumulative impacts to the marine seagrass bed community; (2) continued reliance upon construction of a vertical seawall; (3) failure to provide stormwater management information necessary given the determination that the Project constituted a common plan of development; (4) inconsistency with the FCMP as identified by DEO in its objection letters; and (5) failure to provide reasonable assurances that the Project was clearly in the public interest. Direct Impacts The Project proposed to entirely fill the Subject Lots, contain the fill with vertical seawalls and rip-rap, and construct pile-supported single-family residences. The Project would remove the entire mangrove fringe that aerials and site inspections show is a healthy mix of red, black, and white mangroves along with some green buttonwood. The shallow, open surface waters are dominated by marine seagrasses that vary in density. Petitioner did not make any design modifications to the Project that sought to reduce or eliminate direct impacts to the mangrove fringe and marine seagrasses. Petitioner's resource inventory was done using GIS aerial photography so that the aerial benthic resource surveys submitted to DEP were not ground- truthed. DEP staff conducted physical site inspections and ground-truthing inspections that included swimming in the open surface waters. DEP staff found significant marine seagrasses and sponges that were not mentioned in Petitioner's resource surveys. Depending on the lot, the Project would fill approximately 6,000 square feet of wetlands and other surface waters, i.e., 900 to 2,500 square feet of mangrove habitat and 4,000 to 4,800 square feet of marine seagrass bed habitat. The seawalls depicted in the final version of Petitioner's site plans were "vertical seawalls" because the rip-rap would not face the seawalls to the mean high water line (MHWL). The rip-rap would be placed on submerged resources inside the property lines of the Subject Lots. Also, Petitioner's final plans did not include the mooring of vessels. Vertical seawalls are prohibited in the OFW of the County. Petitioner did not affirmatively demonstrate that fill or shoreline stabilization could be accomplished by using native vegetation instead of vertical seawalls. Secondary Impacts DEP's expert witness, Ms. Mills, testified that Petitioner's ERP applications did not identify any potential secondary impacts. Ms. Mills testified that the expected secondary impacts from the Project included stormwater runoff, shading, and erosion or shoaling. Although the Project plans showed that stormwater would be collected and directed to Floral Avenue, DEP's investigation established that there is no stormwater management system on the side of Floral Avenue abutting the Subject Lots. Thus, the collected and directed stormwater would end up flowing back into the mangrove fringe and surface waters at the lot locations that were not proposed for development, e.g., Lots 36 and 38. The proposed single-family homes are piling-supported structures. Ms. Mills testified that the piling-supported structure would cause shading of the immediate adjacent resources on either side. She identified potential shading impacts to the resources of the undeveloped Lots 36 and 38. In addition, Ms. Mills identified potential erosion or shoaling impacts to the undeveloped Lots 36, 38, and unnamed lots to the left of Lot 40 since they would be surrounded by developed fill on either side. Although Mr. Swakon testified that tidal velocity is low in this area, other aspects, such as effects from wind-driven circulation, were not adequately addressed. Mitigation Petitioner was required to propose mitigation to offset remaining direct and secondary impacts after going through a reduction and elimination exercise. However, Petitioner did not propose any revisions to the Project to reduce or eliminate the direct and secondary impacts identified above. Ms. Mills explained that appropriate mitigation usually provides benefits to the same type of ecological community as the one being impacted. Petitioner's ultimate mitigation proposal was to purchase saltwater credit at a mitigation bank, the Florida Power and Light Everglades Mitigation Bank (FPL EMB). The FPL EMB is located on the mainland of Florida approximately a hundred miles away from the Subject Lots. Ms. Mills testified that saltwater credit would be appropriate to offset and replace the same ecological function of mangroves, but not to offset the submerged benthic communities that would be impacted by the Project. Mr. Swakon testified that calculation of the amount of mitigation credits included a multiplier to address secondary and cumulative impacts, the out-of-kind mitigation, and the dissimilarities in the communities. However, Ms. Mills persuasively testified that the proposed multiplier was not sufficient to justify the three aspects of impact that needed to be offset. Whether to justify dissimilarities between the ecological communities, secondary and cumulative impacts, or the distance of the mitigation site from the Project, the multiplier was not sufficient. Cumulative Impacts The Project is not within a recognized cumulative impact basin of the South Florida Water Management District (SFWMD) for mitigation of impacts purposes. Accordingly, Ms. Mills testified that the plain language of a cumulative impacts analysis is considered. Contiguous lots to the Subject Lots owned by Petitioner could be developed through similar requests in the future. Also, each ERP application's cumulative impact analysis would consider the other four ERP applications as in-house examples of potential future projects. Common Plan of Development Petitioner contested DEP's conclusion that the Project was a common plan of development subject to section 2.0 of the Applicant's Handbook Volume 1 and associated stormwater management requirements. The Project would facilitate the advancement of land uses such as multiple residences, a residential subdivision, or phased site development. The Project comprised a total land area divided into multiple lots or parcels that are under common ownership or control. In total, Petitioner owns 648 lots under common ownership within the Key Haven Tenth and Eleventh Addition. The Subject Lots are all part of a residential subdivision. Thus, the preponderance of the evidence demonstrated that the Project was a common plan of development. For this common plan of development, Petitioner's proposed stormwater management consisted of a cap on the proposed seawalls directing stormwater to swales on each lot. The swales would then direct stormwater to Floral Avenue with no additional treatment or management. During site inspections, DEP staff did not find any evidence of stormwater management along Floral Avenue. Seawalls and Rip-rap The seawalls depicted in the final version of Petitioner's ERP applications would be vertical seawalls because the rip-rap facing the seawall did not come above the MHWL. In addition, the final plans did not include the mooring of vessels. As found above, the Project would place fill, seawalls, and rip-rap on marine seagrasses and sponges. Petitioner failed to affirmatively demonstrate that native vegetation was not sufficient to prevent erosion. The evidence established that Petitioner did not apply for any waiver or variance of applicable ERP rule criteria. FCMP Consistency The evidence demonstrated that Petitioner refused to address DEO's objections based on a mistaken view of the criteria governing ERP applications in the County and the Florida Keys ACSC. Relevant to this proceeding, DEO exercises authority over the ACSC program. See § 380.05, Fla. Stat.; see also § 380.23(6), Fla. Stat. (Each agency charged with implementing statutes and rules that are part of the FCMP, shall be afforded an opportunity to provide DEP with its comments and determination regarding consistency of the activity with those statutes and rules.). Section 380.05(16) prohibits persons from undertaking any development within the Florida Keys ACSC, except in accordance with the PGDs. Thus DEO, as the administrator of the ACSC program, reviewed the ERP applications for consistency with applicable regulatory requirements. DEO issued objections to approval of the permits citing inconsistency with the Florida Keys ACSC PGDs; and inconsistencies between the Project and the County's Comp Plan and LDC which implement the PGDs. DEO identified that the Project would be inconsistent with four PGDs. DEO's expert witness, Ms. Powell, testified that the Project was inconsistent with the PGD, which provides for strengthening local government capabilities for managing land use and development so that the local government is able to achieve these objectives without continuing the ACSC designation. See § 380.0552(7)(a), Fla. Stat. Ms. Powell persuasively testified that the ERP applications were inconsistent with this PGD because the Project would impair the local government's ability to have the ACSC designation removed. Allowing development inconsistent with its regulations would hurt the local government's ability to pursue de-designation. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The second PGD cited by DEO provides for protecting shoreline and marine resources, including mangroves, coral reef formations, seagrass beds, wetlands, fish and wildlife, and their habitat. See § 380.0552(7)(b), Fla. Stat. It was undisputed that the Project would result in total removal of the mangrove and buttonwood fringe on each lot and 100% destruction of existing submerged marine resources. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The third PGD cited by DEO provides for limiting the adverse impacts of development on the quality of water throughout the Florida Keys. See § 380.0552(7)(e), Fla. Stat. Ms. Powell testified that degradation to nearshore water quality from prior dredge and fill activity was one of the reasons for the designation of the Florida Keys as an ACSC. Additionally, as further discussed below, the Project would be inconsistent with the County's Comp Plan policies and LDC regulations that further the goal of protecting the quality of water throughout the Florida Keys ACSC. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The fourth PGD cited by DEO provides for protecting the public health, safety, and welfare of the citizens of the Florida Keys, and maintaining the Florida Keys as a unique Florida resource. See § 380.0552(7)(n), Fla. Stat. As further discussed below, the Project would be inconsistent with the County's Comp Plan and LDC regulations that prohibit the use of structural fill within velocity zones. No evidence was presented by Petitioner that the Project would be consistent with this PGD. Ms. Powell testified that DEO considered the remaining statutory PGDs, and determined they were not particularly applicable to these ERP applications. In accordance with its duties, DEO had also reviewed and approved the County's Comp Plan and LDC as consistent with the statutory PGDs. DEO identified that the Project would be inconsistent with seven Comp Plan policies. They are Policies 102.1.1, 101.5.25, 203.1.1, 204.2.2, 204.2.3, 204.2.4, and 212.5.3. Policy 102.1.1 provides: The County shall protect submerged lands and wetlands. The open space requirement shall be one hundred (100) percent of the following types of wetlands: submerged lands mangroves salt ponds fresh water wetlands fresh water ponds undisturbed salt marsh and buttonwood wetlands Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetlands only for use as transferable development rights (TDRs) away from these habitats. Submerged lands, salt ponds, freshwater ponds, and mangroves shall not be assigned any density or intensity. Policy 101.5.25 provides that "[t]he allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available." Policy 203.1.1 provides that "[t]he open space requirement for mangrove wetlands shall be one hundred (100) percent. No fill or structures shall be permitted in mangrove wetlands except for elevated, pile-supported walkways, docks, piers and utility pilings." Policy 204.2.2 provides: To protect submerged lands and wetlands, the open space requirement shall be 100 percent of the following types of wetlands: submerged lands; mangroves; salt ponds; freshwater wetlands; freshwater ponds; and undisturbed salt marsh and buttonwood wetlands. Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetland only for use as transferable development rights away from these habitats. Submerged lands, salt ponds, freshwater ponds and mangroves shall not be assigned any density or intensity. Within one (1) year after the adoption of the 2030 Comprehensive Plan, the County shall revise the LDC to include a prohibition of development in salt ponds. Policy 204.2.3 provides: No structures shall be permitted in submerged lands, mangroves, salt ponds, or wetlands, except for elevated, pile-supported walkways, docks, piers, and utility pilings. No fill shall be permitted in submerged lands, mangroves, salt ponds, or wetlands except: as specifically allowed by Objective 212.5 and subsequent Policies; to fill a manmade excavated water body, such as a canal, boat ramp, or swimming pool if the Director of Environmental Resources determines that such filling will not have a significant adverse impact on marine or wetland communities; or as needed for shoreline stabilization or beach renourishment projects with a valid public purpose that furthers the goals of the Monroe County Comprehensive Plan, as determined by the County. Policy 204.2.4 provides: No fill or structures shall be permitted in mangroves or wetlands except as allowed by Policy 204.2.3 (as amended) and for bridges extending over mangroves or wetlands that are required to provide automobile or pedestrian access to dwelling units located on upland areas within the same property for which there is no alternative means of access. Such bridges shall be elevated on pilings such that the natural movement of water, including volume, rate, and direction of flow shall not be disrupted or altered. Upland areas shall include disturbed wetlands that have been lawfully converted into uplands through filling. Policy 212.5.3 provides: Bulkheads, seawalls or other hardened vertical shoreline structures shall be permitted on residential canals and altered shorelines only in the following situations: to replace an existing deteriorated bulkhead or seawall; or to stabilize a severely eroding shoreline area. DEO's expert witness, Ms. Powell, persuasively testified that the Project was inconsistent with all seven policies, because it did not protect the submerged lands and wetlands, did not provide for 100% open space within the submerged lands and wetlands, and provided for the construction of a seawall not excepted from the general prohibition. Petitioner did not present any evidence that the Project was consistent with the cited policies. Instead, Petitioner's witness, Mr. Nelson, testified that he felt certain County regulations would militate in favor of allowing the development. The main factor cited by Mr. Nelson was that the Subject Lots were designated as Tier III parcels under the County's LDC. However, designation of a parcel as Tier III did not conflict with the policies cited by DEO. The more credible and persuasive evidence concerning the Project's compliance with the Comp Plan policies was provided by Ms. Powell, who concluded that the Project was not consistent with those policies. DEO identified that the Project would be inconsistent with six sections of the County's LDC regulations. Those are sections 118-4, 118-10(e), 118-12(k)(2), 122-4(b)(5), 130-157, and 130-162. The LDC regulations are more specific methods for implementing the Comp Plan policies outlined above. Section 118-4 provides: No development activities, except as provided for in this chapter, are permitted in submerged lands, mangroves, salt ponds, freshwater wetlands, freshwater ponds, or in undisturbed salt marsh and buttonwood wetlands; the open space requirement is 100 percent. Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetlands only for use as transferable development rights away from these habitats. Submerged lands, salt ponds, freshwater ponds and mangroves shall not be assigned any density or intensity. Section 118-10(e), in relevant part, provides: Mangroves, wetlands, and submerged lands. All structures developed, used or occupied on land classified as mangroves, wetlands or submerged lands (all types and all levels of quality) shall be designed, located and constructed such that: Generally. Only docks and docking facilities, boat ramps, walkways, water access walkways, water observation platforms, boat shelters, nonenclosed gazebos, riprap, seawalls, bulkheads, and utility pilings shall be permitted on or over mangroves, wetlands, and submerged lands, subject to the specific restrictions of this subsection. Trimming and/or removal of mangroves shall meet Florida Department of Environmental Protection requirements. * * * (4) Placement of fill. No fill shall be permitted in any mangroves, wetlands, or submerged lands except: As specifically allowed by this Section or by Section 118- 12(k) (Bulkheads, Seawalls, Riprap) and 118-12(l) (Boat Ramps); To fill a manmade, excavated water body such as a canal, boat ramp, boat slip, boat basin or swimming pool if the County Biologist determines that such filling will not have a significant adverse impact on marine or wetland communities; As needed for shoreline stabilization or beach renourishment projects with a valid public purpose that furthers the goals of the Monroe County Comprehensive Plan, as determined by the County Biologist; For bridges extending over salt marsh and/or buttonwood association wetlands that are required to provide automobile or pedestrian access to lawfully established dwelling units located on upland areas within the same property for which there is no alternate means of access. Such bridges shall be elevated on pilings so that the natural movement of water, including volume, rate and direction of flow shall not be disrupted or altered; or As approved for Disturbed Salt Marsh and Buttonwood Association Wetlands with appropriate mitigation as defined by the wetland regulations of subsection (e)(6) of this Section. Section 118-12(k)(2) provides: (2) Vertical type seawalls or bulkheads shall be permitted only to stabilize severely eroding shorelines and only on manmade canals, channels, or basins. Such seawalls or bulkheads shall be permitted only if native vegetation and/or riprap and filter cloth is not a feasible means to control erosion. No new seawalls, bulkheads, or other hardened vertical structures shall be permitted on open water. Section 122-4(b)(5), in relevant part, provides: Coastal high-hazard areas (V zones). Within the areas of special flood hazard are areas designated as coastal high- hazard areas, which have special flood hazards associated with wave wash. The following provisions shall apply in these areas: * * * e. There shall be no fill used as structural support. Section 130-157, Maximum Permanent Residential Density and Minimum Required Open Space, provides at note (a): (a) The allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available. Section 130-162, Maximum Densities for Hotel/Motel, Campground, Recreational Vehicle, Seasonal and Institutional Residential Uses, and Minimum Open Space, proves at note (a): (a) The allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available. Ms. Powell persuasively testified that the Project was not consistent with the County's LDC regulations in sections 118-4, 118-10(e), 118-12(k)(2), 122- 4(b)(5), 130-157, and 130-162. The Project was inconsistent with the cited LDC regulations because it sought to construct seawall in submerged land, fill portions of the lots subject to a 100% open space requirement, remove the entirety of the existing mangrove fringe, impair 100% of the marine seagrass resources within the Subject Lots, and utilize structural fill within a Federal Emergency Management Agency (FEMA) designated Velocity Zone. The preponderance of the evidence demonstrated that the Project did not meet the criteria of part IV of chapter 62-312 and section 380.0552. The testimony also demonstrated that Petitioner did not apply for a variance or waiver of the County's LDC regulations. Conditions for Issuance Petitioner generally argued that the five applications provided reasonable assurance for issuance of individual ERPs. However, the persuasive and credible evidence established that the Project did not satisfy a majority of the conditions for issuance under rule 62-330.301. Petitioner failed to provide adequate information regarding stormwater management, the impacts of runoff to Floral Avenue, and runoff flowing back into the Gulf of Mexico OFW. This failure resulted in a lack of reasonable assurance that the Project would not cause adverse flooding to on-site or off-site property; would not cause adverse water quantity impacts to receiving waters and adjacent lands; and would not adversely affect the quality of receiving waters. The preponderance of the evidence demonstrated that the Project would adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. Those functions would be 100% impacted and the impacts would not be adequately offset by appropriate mitigation. As found above, the Project would cause adverse secondary impacts to the water resources, adverse impacts to surface water conveyance, and the adverse impacts would not be adequately offset by appropriate mitigation. Additional Conditions for Issuance Petitioner generally contended that the five applications provided reasonable assurance that the Project was clearly in the public interest under rule 62-330.302. However, the persuasive and credible evidence established that the Project did not satisfy a majority of the applicable additional conditions for issuance. The Project would adversely affect the public health, safety, or welfare or the property of others because Petitioner failed to provide adequate information regarding stormwater management. DEP's site inspection found no stormwater management or treatment system on the side of Floral Avenue adjacent to the Subject Lots. Thus, the collected and directed stormwater would end up flowing back into the mangrove fringe and the OFW. The preponderance of the evidence demonstrated that the Project would adversely affect the conservation of fish and wildlife, or their habitat, as a result of the 100% impact to benthic communities, which would not be adequately offset by appropriate mitigation. The preponderance of the evidence demonstrated that the Project would adversely affect marine productivity, the current condition, and the relative value of functions being performed by the impacted areas. Also, the Project would be permanent in nature. The preponderance of the evidence demonstrated that Petitioner failed to provide reasonable assurance that there would not be harmful erosion or shoaling. The Project would not adversely affect or enhance any significant historical and archaeological resources. The Project would not be within a recognized cumulative impact basin of the SFWMD for mitigation of impacts purposes. Contiguous lots to the Subject Lots owned by Petitioner could be developed through similar requests in the future. Each ERP application's cumulative impact analysis would consider the other four ERP applications as in-house examples of potential future projects. Thus, Petitioner did not provide reasonable assurance that each ERP application would not cause unacceptable cumulative impacts upon wetlands and other surface waters.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that DEP enter a final order denying Petitioner's five ERP applications. DONE AND ENTERED this 14th day of April, 2021, in Tallahassee, Leon County, Florida. S FRANCINE M. FFOLKES Administrative Law Judge 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of April, 2021. COPIES FURNISHED: Kathryn E.D. Lewis, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Jay Patrick Reynolds, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 William Moore, Esquire Moore Bowman & Reese, P.A. Suite 100 551 North Cattlemen Road Sarasota, Florida 34232 Justin G. Wolfe, General Counsel Department of Environmental Protection Legal Department, Suite 1051-J Mail Station 35 Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Jon F. Morris, Esquire Brandon W. White, Esquire Department of Economic Opportunity 107 East Madison Street, Mail Station 110 Tallahassee, Florida 32399 Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Noah Valenstein, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Valerie A. Wright, Esquire Department of Economic Opportunity 107 East Madison Street Tallahassee, Florida 32399

Florida Laws (14) 120.52120.569120.57120.68267.061373.042373.086373.413373.414373.428380.05380.0552380.23403.813 Florida Administrative Code (8) 62-302.30062-312.40062-312.41062-312.44062-312.45062-330.30162-330.30262-4.242 DOAH Case (5) 20-065920-066020-066120-066220-0663
# 8
FREDERICK B. SPIEGEL vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-000233 (1978)
Division of Administrative Hearings, Florida Number: 78-000233 Latest Update: Apr. 06, 1979

Findings Of Fact Collier Development Corporation, Naples, Florida, owns a triangular tract of land consisting of approximately 16 acres in Naples, Florida. In 1958, the Trustees of the Internal Improvement Fund conveyed by quitclaim deed to Collier Development Corporation all its interests in the property. A 1958 affidavit of Collier's surveyor who prepared the legal description of the land was filed in the Collier County public records and states that the land conveyed by the quitclaim deed was "high land" erroneously shown as bay bottom land according to the original government survey, and that the deed was executed in exchange for the conveyance of certain parcels of bay bottom land in Naples Bay to the Trustees. (Exhibits 1-2) In 1976, Petitioner executed an option agreement with Collier Development Corporation to purchase the land in question, contingent upon certain conditions including a requirement to obtain any required fill permits. On December 27, 1976, Petitioner assigned the option agreement to Michael S. Spiegel and himself as joint tenants. On March 14, 1977, a "short form" application was filed by Petitioner, as authorized by Collier Development Corporation, with Respondent to fill the land above the mean high water line to building grade for future residential, multi-family, or commercial uses. The application reflected that 400 cubic yards of rock riprap would be placed at least five feet upland of the designated mean high water line along the boundary of the property that faced the Gordon River and Rock Creek. The riprap revetment is designed to provide a method of containing upland fill material. The application contemplates that a fabric-like material "Mirafi" will be placed on the ground and wrapped over the riprap barrier. The application further provides that approximately 90,000 pounds of fill material will be trucked into the site and placed behind the riprap material to fill the land to a minimum elevation of four feet. It is also proposed to slope the fill material behind the riprap and plant grass seed thereon. In October, 1977, Petitioner filed a "long form" application which merely amplified the original application. The mean high water line was established by a survey performed under standard procedures and which utilized the existing bulkhead line as a point of reference. The survey was conducted in 1977 and 1978, and the procedures used were approved by and the survey filed in the Department of Natural Resources on June 26, 1978. (Testimony of Park, Lawson, Exhibits 4, 6, 8, 11) By letter dated January 26, 1978, Respondent provided notice of its intent to deny the permit application pursuant to Chapters 253 and 403, Florida Statutes, and Public Law 92-500. The reasons stated for the proposed denial generally were that filling the land would destroy mangrove vegetation which provides a major input of organic material to estuarine tropic webs, and filters and assimilates pollutants from upland runoff. It was stated that the proposed project would eliminate approximately 15 acres of submerged lands and transition zones, as defined in Chapter 17-4, Florida Administrative Code, which would reduce the quality and quantity of the state's marine resources adjacent to Class II waters and "tend to cause degradation of water quality conditions." Thereafter, on January 25, 1978, Petitioner submitted a petition for hearing wherein the jurisdiction of the Respondent in the matter and its grounds for the proposed denial were challenged. (Exhibit 5) The land in question is located south and adjacent to the confluence of the Gordon River and Rock Creek along the north side of U.S. Highway 41. The Gordon River and Rock Creek are tributaries of Naples Bay and all are Class II waters. The area is vegetated by red mangroves with a lesser number of white and black mangroves. A pond of about one-half acre surrounded by red mangroves is located in the southern section of the tract which occasionally overflows into a ditch running parallel to U.S. 41 located within the highway right-of- way. There is a berm alongside the ditch designed to prevent highway runoff from flowing onto Petitioner's land. During high tides, most of the land is inundated to varied depths ranging from two to eight inches. Certain marine vegetational species are present on portions of the land, such as sea grape, sea purslane, sea daisy, and button wood. Certain marine animal life is present in the mangrove area, including coffee bean snails, ribbed mussels, marsh clams, mangrove crabs, fiddler crabs, and mosquito fish. Other marine species, such as common oysters, scorched mussels, and barnacles inhabit the Rock Creek shore line. There is sparse bird population on Petitioner's land that may in part be due to the proximity of Naples Airport. (Testimony of Lawson, Park, Carroll, Fields, M. Spiegel, Exhibits 3, 7, 10) The quality of water in the Gordon River and Rock Creek is adversely effected to some degree by receipt of sewage plant effluent, discharge from nearby canals and runoff from residential and commercial areas. As a result of high bacterial count in these waters, shell fishing and swimming is not permitted. The mangrove forest on Petitioner's property is in a stressed condition as evidenced by the thinness of the canopy. It is probable that this condition was caused primarily by the introduction of fresh water from canals into the surrounding waters. (Testimony of Carroll, Fields, Erwin, Yokel) Mangrove wetlands are an important component of the estuarine ecosystem which provide nutrient stabilization and transformation in the supply of an organic base to the estuarine food chain, filtration of upland runoff, and storage of storm waters. They are a nursery for fish and invertebrate species, and a fish and wildlife habitat. The mangrove system on Petitioner's property is productive and contributing to the needs of marine life in the Naples Bay area. In this respect, most of the detritus produced by the mangrove system occurs below the mean high water line. However, the tidal flow during storm conditions at certain times of the year can release accumulated organic matter from the higher areas. This generally occurs in late summer and early fall when feeding demands of organisms are high. (Testimony of Erwin, Yokel) Although no system for containing surface water runoff was set forth in Petitioner's permit application, it is planned that such runoff will be retained on the site by a site drainage plan that would be accomplished by grading and the use of the existing pond or other means of retention, in addition to the natural percolation into the sandy fill material. (Testimony of Park) The application did not specify the precise distance from the mean high water line at which fill would be placed, but Petitioner clarified this point at the hearing. Fill material will not be placed closer than 100 feet upland of the mean high water line. The mangrove area left intact below that point will enable the ecological system to survive. However, due to the fact that the Naples Bay area does not produce sufficient organic matter to fully support animal life in the area, the loss of a substantial portion of mangroves will impact on the detrital food chain to some extent. (Testimony of Carroll, Yokel)

Recommendation That Respondent issue the requested permit to Petitioner, subject to the modification thereto made at the hearing with regard to the 100' setback as set forth in paragraph 8 of the foregoing Findings of Fact. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 20th day of February, 1979. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 1979. COPIES FURNISHED: H. Ray Allen, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Howard Horowitz, Esquire 3550 Biscayne Boulevard Suite 402 Miami, Florida 33137 William Blackwell, Esquire 3003 North Miami Trail Naples, Florida

# 9
A. WAYNE LUJAN vs DEPARTMENT OF ECONOMIC OPPORTUNITY AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 20-000659 (2020)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 06, 2020 Number: 20-000659 Latest Update: Mar. 06, 2025

The Issue The issue to be decided in these cases is whether Petitioner, A. Wayne Lujan (Petitioner), was entitled to issuance of five environmental resource permits (ERPs) that Respondent, Department of Environmental Protection (DEP), intended to deny as stated in notices of denial dated October 25, 2019.

Findings Of Fact The following Findings of Fact are based on the stipulations of the parties and the evidence adduced at the final hearing. Parties and Background Petitioner Lujan is the president and a director of Kay Haven Associated Enterprises, Inc. (Key Haven), that owns the five parcels, which are the subject matter of this hearing. Although Key Haven owns numerous lots, it chose to submit ERP applications for the Subject Lots within the Key Haven Tenth Addition plat dated September 1966 (Plat). See Joint Exhibit 84. Joint Exhibit 84 The Subject Lots are located in an unincorporated part of the County on the northwestern edge of a body of land lying north of State Road A1A, identified on the Plat as Raccoon Key. The Subject Lots are approximately half a mile east of the city limits of Key West, Florida. The Subject Lots are all characterized by a small upland portion adjacent to Floral Avenue. The majority of the Subject Lots transition into a mangrove fringe of varying depth and submerged lands containing marine seagrasses and sponges. See Joint Exhibits 81 and 82. Joint Exhibit 81 Joint Exhibit 82 DEP is the administrative agency of the state having the power and duty to protect Florida's air and water resources, and to administer and enforce the provisions of part II of chapter 380, part IV of chapter 373, and chapter 403, Florida Statutes. DEP also administers the provisions of Florida Administrative Code chapters 62-312 and 62-330 regarding activities in wetlands and other surface waters of the state. DEO is the state land planning agency and reviews certain permit applications for consistency with its statutory responsibilities under the Florida Coastal Management Program (FCMP), which includes part II of chapter 163, and part I of chapter 380, Florida Statutes. Relevant to this proceeding, DEO exercises authority over the ACSC program. See § 380.05, Fla. Stat. On July 26, 2018, Petitioner filed five applications for ERPs with DEP. Although certain details within each application differed, the applications all sought to authorize construction of a seawall in the waters of the Gulf of Mexico and in unnamed wetlands within the landward extent of the Gulf of Mexico, a Class III OFW, to remove the entirety of the existing mangrove fringe, and to place fill within wetlands and other surface waters for the construction of single-family residences (Project). The minor differences in each application relate to the length of the seawall and the amount of fill necessary for each lot. Although some testimony was provided concerning the differences, no party argued that the differences were material to the determinations necessary in this proceeding. Accordingly, the factual and legal analysis for the Subject Lots and ERP applications were addressed without distinction herein. DEP forwarded a copy of the applications to DEO for its recommendation. On August 24, 2018, DEO issued objections to approval of the permits citing inconsistency with the Florida Keys ACSC Principles for Guiding Development (PGDs) in section 380.0552(7). DEO also objected based on inconsistencies between the Project and the Monroe County Comprehensive Plan (Comp Plan) and Land Development Code (LDC), which implement the PGDs. DEP's first RAI dated August 24, 2018, included DEO's objections. The first RAI notified Petitioner that DEP had concerns with the Project that included: (1) installation of the vertical seawall; (2) placement of fill within an OFW; (3) direct impacts to marine seagrass bed community without adequate mitigation; and (4) failure to provide stormwater management plans since the Project was a common plan of development. The first RAI contained 19 specific requests for additional information. On October 23, 2018, Petitioner responded to DEP's first RAI by submitting slightly revised plans. The revised Project proposed less of a vertical seawall footprint by adding rip-rap to the side seawalls as a means of containing fill. Petitioner's responses to the 19 specific requests for information can generally be categorized as follows: (1) elimination of some vertical seawalls, but not the ones on the waterward edge of the Subject Lots; (2) no change in the placement of fill; (3) Petitioner would attempt to find appropriate compensatory mitigation for the seagrass impacts; and (4) Petitioner did not consider the Project to be a common plan of development. Regarding DEO's objections, Petitioner stated that "[w]e acknowledge that the project has been forwarded to FWC [Florida Fish and Wildlife Conservation Commission] and DEO and that additional comments and information may be requested by those agencies in order to fully evaluate the application." Petitioner did not substantively address DEO's objections. DEP issued a second RAI on November 21, 2018. DEO again objected in a letter dated November 26, 2018. DEP's second RAI raised the same concerns as the first RAI and acknowledged that four of the 19 specific items were adequately addressed. On January 11, 2019, Petitioner responded to DEP's second RAI by again submitting slightly revised site plans. However, the Project remained generally unchanged, with a proposed vertical seawall on the waterward edge of the lots, rip-rap along the sides, removal of the entire mangrove fringe, and fill of the entire lots eliminating the existing marine seagrasses. DEP issued a third RAI to Petitioner on February 8, 2019. DEO reiterated its objections by letter dated February 8, 2019. The third RAI raised the same concerns as the first and second RAIs, although DEP acknowledged that six of the 19 specific items were adequately addressed. By letter dated April 8, 2019, Petitioner responded to DEP's third RAI. The response again proposed slightly altered site plans from the January 2019 submissions. Petitioner essentially stated that mitigation opportunities were scarce, but had contacted the County and was looking into derelict vessel removal. However, the proposed Project remained generally unchanged, with a proposed vertical seawall on the waterward edge of the lots, rip-rap along the sides, removal of the entire mangrove fringe, and fill of the entire lots eliminating the existing marine seagrasses. As it relates to DEO's objections, Petitioner responded that "[a]fter review of the comments outlined in the [DEO] revised letter, it seems that the DEO objections are related to compliance with the provision[s] of the [Monroe] County [Comp Plan]. We will deal with those issues at the time of local permitting." Petitioner again failed to substantively address DEO's objections. DEP issued its final RAI on May 8, 2019. DEO again objected by letter dated May 6, 2019. This final RAI raised the same concerns as the first, second, and third RAIs. DEP stated that seven of the 19 specific items were not addressed by Petitioner, and that failure to provide a complete response to the prior RAI may result in denial of the ERP applications. On August 29, 2019, Petitioner responded to DEP's final RAI by once again submitting slightly revised plans, and additional information concerning mitigation proposals. However, the Project did not change and Petitioner again failed to substantively address DEO's objections. DEO’s objection letter identified that the ERP applications were inconsistent with the Florida Keys ACSC PGDs, seven Comp Plan policies, and six regulatory provisions of the County's LDC. DEP denied the ERP applications on October 25, 2019. The grounds for denial reiterated the issues not addressed by Petitioner's RAI responses. Specifically: (1) the failure of the Project to provide reasonable assurances concerning direct, secondary, and cumulative impacts to the marine seagrass bed community; (2) continued reliance upon construction of a vertical seawall; (3) failure to provide stormwater management information necessary given the determination that the Project constituted a common plan of development; (4) inconsistency with the FCMP as identified by DEO in its objection letters; and (5) failure to provide reasonable assurances that the Project was clearly in the public interest. Direct Impacts The Project proposed to entirely fill the Subject Lots, contain the fill with vertical seawalls and rip-rap, and construct pile-supported single-family residences. The Project would remove the entire mangrove fringe that aerials and site inspections show is a healthy mix of red, black, and white mangroves along with some green buttonwood. The shallow, open surface waters are dominated by marine seagrasses that vary in density. Petitioner did not make any design modifications to the Project that sought to reduce or eliminate direct impacts to the mangrove fringe and marine seagrasses. Petitioner's resource inventory was done using GIS aerial photography so that the aerial benthic resource surveys submitted to DEP were not ground- truthed. DEP staff conducted physical site inspections and ground-truthing inspections that included swimming in the open surface waters. DEP staff found significant marine seagrasses and sponges that were not mentioned in Petitioner's resource surveys. Depending on the lot, the Project would fill approximately 6,000 square feet of wetlands and other surface waters, i.e., 900 to 2,500 square feet of mangrove habitat and 4,000 to 4,800 square feet of marine seagrass bed habitat. The seawalls depicted in the final version of Petitioner's site plans were "vertical seawalls" because the rip-rap would not face the seawalls to the mean high water line (MHWL). The rip-rap would be placed on submerged resources inside the property lines of the Subject Lots. Also, Petitioner's final plans did not include the mooring of vessels. Vertical seawalls are prohibited in the OFW of the County. Petitioner did not affirmatively demonstrate that fill or shoreline stabilization could be accomplished by using native vegetation instead of vertical seawalls. Secondary Impacts DEP's expert witness, Ms. Mills, testified that Petitioner's ERP applications did not identify any potential secondary impacts. Ms. Mills testified that the expected secondary impacts from the Project included stormwater runoff, shading, and erosion or shoaling. Although the Project plans showed that stormwater would be collected and directed to Floral Avenue, DEP's investigation established that there is no stormwater management system on the side of Floral Avenue abutting the Subject Lots. Thus, the collected and directed stormwater would end up flowing back into the mangrove fringe and surface waters at the lot locations that were not proposed for development, e.g., Lots 36 and 38. The proposed single-family homes are piling-supported structures. Ms. Mills testified that the piling-supported structure would cause shading of the immediate adjacent resources on either side. She identified potential shading impacts to the resources of the undeveloped Lots 36 and 38. In addition, Ms. Mills identified potential erosion or shoaling impacts to the undeveloped Lots 36, 38, and unnamed lots to the left of Lot 40 since they would be surrounded by developed fill on either side. Although Mr. Swakon testified that tidal velocity is low in this area, other aspects, such as effects from wind-driven circulation, were not adequately addressed. Mitigation Petitioner was required to propose mitigation to offset remaining direct and secondary impacts after going through a reduction and elimination exercise. However, Petitioner did not propose any revisions to the Project to reduce or eliminate the direct and secondary impacts identified above. Ms. Mills explained that appropriate mitigation usually provides benefits to the same type of ecological community as the one being impacted. Petitioner's ultimate mitigation proposal was to purchase saltwater credit at a mitigation bank, the Florida Power and Light Everglades Mitigation Bank (FPL EMB). The FPL EMB is located on the mainland of Florida approximately a hundred miles away from the Subject Lots. Ms. Mills testified that saltwater credit would be appropriate to offset and replace the same ecological function of mangroves, but not to offset the submerged benthic communities that would be impacted by the Project. Mr. Swakon testified that calculation of the amount of mitigation credits included a multiplier to address secondary and cumulative impacts, the out-of-kind mitigation, and the dissimilarities in the communities. However, Ms. Mills persuasively testified that the proposed multiplier was not sufficient to justify the three aspects of impact that needed to be offset. Whether to justify dissimilarities between the ecological communities, secondary and cumulative impacts, or the distance of the mitigation site from the Project, the multiplier was not sufficient. Cumulative Impacts The Project is not within a recognized cumulative impact basin of the South Florida Water Management District (SFWMD) for mitigation of impacts purposes. Accordingly, Ms. Mills testified that the plain language of a cumulative impacts analysis is considered. Contiguous lots to the Subject Lots owned by Petitioner could be developed through similar requests in the future. Also, each ERP application's cumulative impact analysis would consider the other four ERP applications as in-house examples of potential future projects. Common Plan of Development Petitioner contested DEP's conclusion that the Project was a common plan of development subject to section 2.0 of the Applicant's Handbook Volume 1 and associated stormwater management requirements. The Project would facilitate the advancement of land uses such as multiple residences, a residential subdivision, or phased site development. The Project comprised a total land area divided into multiple lots or parcels that are under common ownership or control. In total, Petitioner owns 648 lots under common ownership within the Key Haven Tenth and Eleventh Addition. The Subject Lots are all part of a residential subdivision. Thus, the preponderance of the evidence demonstrated that the Project was a common plan of development. For this common plan of development, Petitioner's proposed stormwater management consisted of a cap on the proposed seawalls directing stormwater to swales on each lot. The swales would then direct stormwater to Floral Avenue with no additional treatment or management. During site inspections, DEP staff did not find any evidence of stormwater management along Floral Avenue. Seawalls and Rip-rap The seawalls depicted in the final version of Petitioner's ERP applications would be vertical seawalls because the rip-rap facing the seawall did not come above the MHWL. In addition, the final plans did not include the mooring of vessels. As found above, the Project would place fill, seawalls, and rip-rap on marine seagrasses and sponges. Petitioner failed to affirmatively demonstrate that native vegetation was not sufficient to prevent erosion. The evidence established that Petitioner did not apply for any waiver or variance of applicable ERP rule criteria. FCMP Consistency The evidence demonstrated that Petitioner refused to address DEO's objections based on a mistaken view of the criteria governing ERP applications in the County and the Florida Keys ACSC. Relevant to this proceeding, DEO exercises authority over the ACSC program. See § 380.05, Fla. Stat.; see also § 380.23(6), Fla. Stat. (Each agency charged with implementing statutes and rules that are part of the FCMP, shall be afforded an opportunity to provide DEP with its comments and determination regarding consistency of the activity with those statutes and rules.). Section 380.05(16) prohibits persons from undertaking any development within the Florida Keys ACSC, except in accordance with the PGDs. Thus DEO, as the administrator of the ACSC program, reviewed the ERP applications for consistency with applicable regulatory requirements. DEO issued objections to approval of the permits citing inconsistency with the Florida Keys ACSC PGDs; and inconsistencies between the Project and the County's Comp Plan and LDC which implement the PGDs. DEO identified that the Project would be inconsistent with four PGDs. DEO's expert witness, Ms. Powell, testified that the Project was inconsistent with the PGD, which provides for strengthening local government capabilities for managing land use and development so that the local government is able to achieve these objectives without continuing the ACSC designation. See § 380.0552(7)(a), Fla. Stat. Ms. Powell persuasively testified that the ERP applications were inconsistent with this PGD because the Project would impair the local government's ability to have the ACSC designation removed. Allowing development inconsistent with its regulations would hurt the local government's ability to pursue de-designation. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The second PGD cited by DEO provides for protecting shoreline and marine resources, including mangroves, coral reef formations, seagrass beds, wetlands, fish and wildlife, and their habitat. See § 380.0552(7)(b), Fla. Stat. It was undisputed that the Project would result in total removal of the mangrove and buttonwood fringe on each lot and 100% destruction of existing submerged marine resources. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The third PGD cited by DEO provides for limiting the adverse impacts of development on the quality of water throughout the Florida Keys. See § 380.0552(7)(e), Fla. Stat. Ms. Powell testified that degradation to nearshore water quality from prior dredge and fill activity was one of the reasons for the designation of the Florida Keys as an ACSC. Additionally, as further discussed below, the Project would be inconsistent with the County's Comp Plan policies and LDC regulations that further the goal of protecting the quality of water throughout the Florida Keys ACSC. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The fourth PGD cited by DEO provides for protecting the public health, safety, and welfare of the citizens of the Florida Keys, and maintaining the Florida Keys as a unique Florida resource. See § 380.0552(7)(n), Fla. Stat. As further discussed below, the Project would be inconsistent with the County's Comp Plan and LDC regulations that prohibit the use of structural fill within velocity zones. No evidence was presented by Petitioner that the Project would be consistent with this PGD. Ms. Powell testified that DEO considered the remaining statutory PGDs, and determined they were not particularly applicable to these ERP applications. In accordance with its duties, DEO had also reviewed and approved the County's Comp Plan and LDC as consistent with the statutory PGDs. DEO identified that the Project would be inconsistent with seven Comp Plan policies. They are Policies 102.1.1, 101.5.25, 203.1.1, 204.2.2, 204.2.3, 204.2.4, and 212.5.3. Policy 102.1.1 provides: The County shall protect submerged lands and wetlands. The open space requirement shall be one hundred (100) percent of the following types of wetlands: submerged lands mangroves salt ponds fresh water wetlands fresh water ponds undisturbed salt marsh and buttonwood wetlands Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetlands only for use as transferable development rights (TDRs) away from these habitats. Submerged lands, salt ponds, freshwater ponds, and mangroves shall not be assigned any density or intensity. Policy 101.5.25 provides that "[t]he allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available." Policy 203.1.1 provides that "[t]he open space requirement for mangrove wetlands shall be one hundred (100) percent. No fill or structures shall be permitted in mangrove wetlands except for elevated, pile-supported walkways, docks, piers and utility pilings." Policy 204.2.2 provides: To protect submerged lands and wetlands, the open space requirement shall be 100 percent of the following types of wetlands: submerged lands; mangroves; salt ponds; freshwater wetlands; freshwater ponds; and undisturbed salt marsh and buttonwood wetlands. Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetland only for use as transferable development rights away from these habitats. Submerged lands, salt ponds, freshwater ponds and mangroves shall not be assigned any density or intensity. Within one (1) year after the adoption of the 2030 Comprehensive Plan, the County shall revise the LDC to include a prohibition of development in salt ponds. Policy 204.2.3 provides: No structures shall be permitted in submerged lands, mangroves, salt ponds, or wetlands, except for elevated, pile-supported walkways, docks, piers, and utility pilings. No fill shall be permitted in submerged lands, mangroves, salt ponds, or wetlands except: as specifically allowed by Objective 212.5 and subsequent Policies; to fill a manmade excavated water body, such as a canal, boat ramp, or swimming pool if the Director of Environmental Resources determines that such filling will not have a significant adverse impact on marine or wetland communities; or as needed for shoreline stabilization or beach renourishment projects with a valid public purpose that furthers the goals of the Monroe County Comprehensive Plan, as determined by the County. Policy 204.2.4 provides: No fill or structures shall be permitted in mangroves or wetlands except as allowed by Policy 204.2.3 (as amended) and for bridges extending over mangroves or wetlands that are required to provide automobile or pedestrian access to dwelling units located on upland areas within the same property for which there is no alternative means of access. Such bridges shall be elevated on pilings such that the natural movement of water, including volume, rate, and direction of flow shall not be disrupted or altered. Upland areas shall include disturbed wetlands that have been lawfully converted into uplands through filling. Policy 212.5.3 provides: Bulkheads, seawalls or other hardened vertical shoreline structures shall be permitted on residential canals and altered shorelines only in the following situations: to replace an existing deteriorated bulkhead or seawall; or to stabilize a severely eroding shoreline area. DEO's expert witness, Ms. Powell, persuasively testified that the Project was inconsistent with all seven policies, because it did not protect the submerged lands and wetlands, did not provide for 100% open space within the submerged lands and wetlands, and provided for the construction of a seawall not excepted from the general prohibition. Petitioner did not present any evidence that the Project was consistent with the cited policies. Instead, Petitioner's witness, Mr. Nelson, testified that he felt certain County regulations would militate in favor of allowing the development. The main factor cited by Mr. Nelson was that the Subject Lots were designated as Tier III parcels under the County's LDC. However, designation of a parcel as Tier III did not conflict with the policies cited by DEO. The more credible and persuasive evidence concerning the Project's compliance with the Comp Plan policies was provided by Ms. Powell, who concluded that the Project was not consistent with those policies. DEO identified that the Project would be inconsistent with six sections of the County's LDC regulations. Those are sections 118-4, 118-10(e), 118-12(k)(2), 122-4(b)(5), 130-157, and 130-162. The LDC regulations are more specific methods for implementing the Comp Plan policies outlined above. Section 118-4 provides: No development activities, except as provided for in this chapter, are permitted in submerged lands, mangroves, salt ponds, freshwater wetlands, freshwater ponds, or in undisturbed salt marsh and buttonwood wetlands; the open space requirement is 100 percent. Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetlands only for use as transferable development rights away from these habitats. Submerged lands, salt ponds, freshwater ponds and mangroves shall not be assigned any density or intensity. Section 118-10(e), in relevant part, provides: Mangroves, wetlands, and submerged lands. All structures developed, used or occupied on land classified as mangroves, wetlands or submerged lands (all types and all levels of quality) shall be designed, located and constructed such that: Generally. Only docks and docking facilities, boat ramps, walkways, water access walkways, water observation platforms, boat shelters, nonenclosed gazebos, riprap, seawalls, bulkheads, and utility pilings shall be permitted on or over mangroves, wetlands, and submerged lands, subject to the specific restrictions of this subsection. Trimming and/or removal of mangroves shall meet Florida Department of Environmental Protection requirements. * * * (4) Placement of fill. No fill shall be permitted in any mangroves, wetlands, or submerged lands except: As specifically allowed by this Section or by Section 118- 12(k) (Bulkheads, Seawalls, Riprap) and 118-12(l) (Boat Ramps); To fill a manmade, excavated water body such as a canal, boat ramp, boat slip, boat basin or swimming pool if the County Biologist determines that such filling will not have a significant adverse impact on marine or wetland communities; As needed for shoreline stabilization or beach renourishment projects with a valid public purpose that furthers the goals of the Monroe County Comprehensive Plan, as determined by the County Biologist; For bridges extending over salt marsh and/or buttonwood association wetlands that are required to provide automobile or pedestrian access to lawfully established dwelling units located on upland areas within the same property for which there is no alternate means of access. Such bridges shall be elevated on pilings so that the natural movement of water, including volume, rate and direction of flow shall not be disrupted or altered; or As approved for Disturbed Salt Marsh and Buttonwood Association Wetlands with appropriate mitigation as defined by the wetland regulations of subsection (e)(6) of this Section. Section 118-12(k)(2) provides: (2) Vertical type seawalls or bulkheads shall be permitted only to stabilize severely eroding shorelines and only on manmade canals, channels, or basins. Such seawalls or bulkheads shall be permitted only if native vegetation and/or riprap and filter cloth is not a feasible means to control erosion. No new seawalls, bulkheads, or other hardened vertical structures shall be permitted on open water. Section 122-4(b)(5), in relevant part, provides: Coastal high-hazard areas (V zones). Within the areas of special flood hazard are areas designated as coastal high- hazard areas, which have special flood hazards associated with wave wash. The following provisions shall apply in these areas: * * * e. There shall be no fill used as structural support. Section 130-157, Maximum Permanent Residential Density and Minimum Required Open Space, provides at note (a): (a) The allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available. Section 130-162, Maximum Densities for Hotel/Motel, Campground, Recreational Vehicle, Seasonal and Institutional Residential Uses, and Minimum Open Space, proves at note (a): (a) The allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available. Ms. Powell persuasively testified that the Project was not consistent with the County's LDC regulations in sections 118-4, 118-10(e), 118-12(k)(2), 122- 4(b)(5), 130-157, and 130-162. The Project was inconsistent with the cited LDC regulations because it sought to construct seawall in submerged land, fill portions of the lots subject to a 100% open space requirement, remove the entirety of the existing mangrove fringe, impair 100% of the marine seagrass resources within the Subject Lots, and utilize structural fill within a Federal Emergency Management Agency (FEMA) designated Velocity Zone. The preponderance of the evidence demonstrated that the Project did not meet the criteria of part IV of chapter 62-312 and section 380.0552. The testimony also demonstrated that Petitioner did not apply for a variance or waiver of the County's LDC regulations. Conditions for Issuance Petitioner generally argued that the five applications provided reasonable assurance for issuance of individual ERPs. However, the persuasive and credible evidence established that the Project did not satisfy a majority of the conditions for issuance under rule 62-330.301. Petitioner failed to provide adequate information regarding stormwater management, the impacts of runoff to Floral Avenue, and runoff flowing back into the Gulf of Mexico OFW. This failure resulted in a lack of reasonable assurance that the Project would not cause adverse flooding to on-site or off-site property; would not cause adverse water quantity impacts to receiving waters and adjacent lands; and would not adversely affect the quality of receiving waters. The preponderance of the evidence demonstrated that the Project would adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. Those functions would be 100% impacted and the impacts would not be adequately offset by appropriate mitigation. As found above, the Project would cause adverse secondary impacts to the water resources, adverse impacts to surface water conveyance, and the adverse impacts would not be adequately offset by appropriate mitigation. Additional Conditions for Issuance Petitioner generally contended that the five applications provided reasonable assurance that the Project was clearly in the public interest under rule 62-330.302. However, the persuasive and credible evidence established that the Project did not satisfy a majority of the applicable additional conditions for issuance. The Project would adversely affect the public health, safety, or welfare or the property of others because Petitioner failed to provide adequate information regarding stormwater management. DEP's site inspection found no stormwater management or treatment system on the side of Floral Avenue adjacent to the Subject Lots. Thus, the collected and directed stormwater would end up flowing back into the mangrove fringe and the OFW. The preponderance of the evidence demonstrated that the Project would adversely affect the conservation of fish and wildlife, or their habitat, as a result of the 100% impact to benthic communities, which would not be adequately offset by appropriate mitigation. The preponderance of the evidence demonstrated that the Project would adversely affect marine productivity, the current condition, and the relative value of functions being performed by the impacted areas. Also, the Project would be permanent in nature. The preponderance of the evidence demonstrated that Petitioner failed to provide reasonable assurance that there would not be harmful erosion or shoaling. The Project would not adversely affect or enhance any significant historical and archaeological resources. The Project would not be within a recognized cumulative impact basin of the SFWMD for mitigation of impacts purposes. Contiguous lots to the Subject Lots owned by Petitioner could be developed through similar requests in the future. Each ERP application's cumulative impact analysis would consider the other four ERP applications as in-house examples of potential future projects. Thus, Petitioner did not provide reasonable assurance that each ERP application would not cause unacceptable cumulative impacts upon wetlands and other surface waters.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that DEP enter a final order denying Petitioner's five ERP applications. DONE AND ENTERED this 14th day of April, 2021, in Tallahassee, Leon County, Florida. S FRANCINE M. FFOLKES Administrative Law Judge 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of April, 2021. COPIES FURNISHED: Kathryn E.D. Lewis, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Jay Patrick Reynolds, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 William Moore, Esquire Moore Bowman & Reese, P.A. Suite 100 551 North Cattlemen Road Sarasota, Florida 34232 Justin G. Wolfe, General Counsel Department of Environmental Protection Legal Department, Suite 1051-J Mail Station 35 Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Jon F. Morris, Esquire Brandon W. White, Esquire Department of Economic Opportunity 107 East Madison Street, Mail Station 110 Tallahassee, Florida 32399 Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Noah Valenstein, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Valerie A. Wright, Esquire Department of Economic Opportunity 107 East Madison Street Tallahassee, Florida 32399

Florida Laws (14) 120.52120.569120.57120.68267.061373.042373.086373.413373.414373.428380.05380.0552380.23403.813 Florida Administrative Code (8) 62-302.30062-312.40062-312.41062-312.44062-312.45062-330.30162-330.30262-4.242 DOAH Case (5) 20-065920-066020-066120-066220-0663