Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs RALPH N. BATTAGLIA, INTERCONTINENTAL CONSTRUCTION CORPORATION, INC., 07-000052PL (2007)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Jan. 04, 2007 Number: 07-000052PL Latest Update: May 08, 2007

The Issue Whether Respondent committed the violations alleged in the Amended Administrative Complaint issued against him and, if so, what disciplinary action should be taken.

Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made to supplement and clarify the facts to which the parties stipulated at the outset of the final hearing (Parties' Stipulations)2: The contract referenced in the Parties' Stipulations (Building Contract) was signed by Mr. Stasinos (on behalf of ICC) and Mr. Skiera (on behalf of himself and his wife) on June 29, 2000. The home that ICC agreed to build for the Skieras (Skiera Residence) was described in the Building Contract as a "[c]ustom two-story residence with detached garage and riding cor[r]al for a total of 5,370 square feet." It was to be constructed on a tract of land owned by the Skieras in Boynton, Beach, Florida. The Building Contract provided for the following allowances: $20,000.00 for "electrical"; $17,000.00 for "plumbing"; $15,000 for "HVAC"; a "door hardware allowance" of "$50.00 per [interior] door"; $6,000.00 for a "stacked stone veneer" exterior; an "entry door hardware allowance" of "$100.00 per door"; $15,000.00 for "kitchen cabinetry and vanity"; $8,000.00 for "counter tops and vanity tops"; $9,000.00 for "landscaping," including "trees, shrubs, sod, automatic time clock, [and an] operated irrigation system with rain sensor"; and $7,000 for "driveways, walkways, [and] flatwork." There was no written statement in the Building Contract explaining a consumer's rights under the Construction Industries Recovery Fund, as then required by Section 489.1425, Florida Statutes. The Building Contract contained a "[p]ayment [d]raw [s]chedule," which provided as follows: Upon execution of contract: 10%- $36,608.00 Thereafter, progress payments based on schedule of values. This "schedule of values" (referred to in the "[p]ayment [d]raw [s]chedule") contained the following "scheduled values" (excluding change orders): 1. Permits $21,600.00 2. Clearing/Grading/Fill $10,800.00 3. Foot'gs. Undgr Plumb, Soil Treatmt $23,000.00 4. Foundation/Slab poured $32,760.00 5. Exterior Walls/Tie Beam $26,600.00 6. Roof Trusses $26,600.00 7. Roof Sheathing/Felt $19,400.00 8. Interior Framing Complete $14,000.00 9. Windows/Exterior Door Frames Set $14,400.00 10. 2nd Plumbing/Tub Set $7,200.00 11. Wiring Rough-In $14,400.00 12. HVAC Ducts Installed $7,200.00 13. Roof Shingles/Tiles Installed $14,400.00 14. Insulation (wall & ceiling) $4,200.00 15. Exterior Trim/Soffits $11,800.00 16. Drywall Hung $14,400.00 17. Drywall Finish $10,800.00 18. Interior Trim/Interior Doors Installed $13,400.00 19. Interior Paint $8,800.00 20. Siding/Stucco $14,400.00 21. Exterior Paint Complete $8,800.00 22. Exterior Doors & Garage Door Install $6,200.00 23. Cabinets/Countertops Installed $10,000.00 24. Plumbing Finish $3,600.00 25. Electrical Finish $5,600.00 26. HVAC-Compressor/A.H. Installed $10,920.00 27. Driveway/Walks Installed $3,600.00 28. Landscaping/Irrigation $7,200.00 There were six separate change orders. They were dated August 20, 2000 (Change Order No. 001), August 29, 2000 (Change Order No. 002), September 26, 2000 (Change Order No. 003), October 15, 2000 (Change Order No. 004), October 15, 2000 (Change Order No. 005), and November 10, 2000 (Change Order No. 006). As of December 21, 2000, ICC had been paid in full for all six change orders, as well as for items 1 through 8 on the "schedule of values." As of February 27, 2001, ICC had received additional monies from the Skieras: payment in full for items 9 through 12 and 15 on the "schedule of values" and partial (50 percent) payment for items 13 and 20 on the "schedule of values." As of April 10, 2001, ICC had been paid a total of $287,966.20 (all from the proceeds of a mortgage loan the Skieras had obtained from Admiralty Bank) for work done on the Skiera Residence. On May 1, 2001, the Skieras paid ICC an additional $16,800.00 for drywall work, bringing the total amount of payments that ICC had received from (or on behalf of) the Skieras, as of that date, to $304,766.20. The Skieras made no further payments to ICC. The "eight valid claims of lien" referenced in the Parties' Stipulations were filed by eight different subcontractors, all of whom had been hired by ICC to work on the Skiera Residence: Boca Concrete Pumping, Inc.; Gulf Stream Lumber Company; L & W Supply Corp., d/b/a Seacoast Supply; Waste Management of Palm Beach; B.T. Glass & Mirror, Inc.; Boca Raton Decorating Center Company; American Stairs; and Broten Garage Door Sales Inc.3 Boca Concrete Pumping was the "very first" subcontractor to work on the construction of the Skiera Residence. It did the "slab work, the foundation" (referenced in item 4 of "schedule of values"). Its lien was recorded on December 6, 2000. The lien was in the amount of $1,001.25, and it indicated, on its face, that it was for unpaid "concrete pumping" that had been furnished between September 8, 2000, and September 22, 2000. A satisfaction of this lien, dated March 8, 2001, was filed March 24, 2001. Gulf Stream Lumber's original lien was recorded February 15, 2001. It was in the amount of $67,872.59, and it indicated, on its face, that it was for unpaid "building material" that had been furnished between August 15, 2000, and January 24, 2001. An amended claim of lien was recorded May 3, 2001, in the amount of $36,530.59 for unpaid "building material" that, according to the lien, had been furnished between August 25, 2000, and March 27, 2001. A satisfaction of the original lien and amended claim of lien, dated November 30, 2001, was filed December 5, 2001. The liens were satisfied, pursuant to the terms of a Settlement Stipulation, upon the Skieras' payment of $39,579.28 to Gulf Stream Lumber. L & W Supply's lien was recorded April 30, 2001. It was in the amount of $4,536.98, and it indicated, on its face, that it was for unpaid "building materials [and] related items" that had been furnished between December 16, 2000, and January 30, 2001. A satisfaction of this lien, dated October 11, 2001, was filed November 7, 2001. The lien was satisfied by the payment of $10.00 "and other good and valuable consideration" (which was the payment of an additional $2,850.00 by check dated October 11, 2001). Waste Management of Palm Beach's lien was recorded May 31, 2001. It was in the amount of $1,665.89, and it indicated, on its face, that it was for unpaid "[w]aste [r]emoval [s]ervices" that had been furnished between August 30, 2000, and April 5, 2001. A satisfaction of this lien, dated October 19, 2001, was filed November 13, 2001. B.T. Glass & Mirror's lien was recorded June 29, 2001. It was in the amount of $3,560.00, and it indicated, on its face, that it was for an unpaid "glass/mirror package" that had been furnished between May 3, 2001, and May 31, 2001. A satisfaction of this lien, dated October 19, 2001, was filed November 13, 2001. The lien was satisfied by the payment of $1,600.00 (by check dated November 10, 2001), plus an agreement to provide "$2,000.00 in gazebo or arbor products from the Hitching Post," the Skieras' family business. Boca Raton Decorating Center's lien was recorded May 19, 2001. It was in the amount of $1,218.79, and it indicated, on its face, that it was for unpaid "paint, sealers [and] sundries" that had been furnished between May 1, 2001, to May 2, 2001. A satisfaction of this lien, dated October 11, 2001, was filed November 7, 2001. American Stairs' lien was recorded August 16, 2001. It was in the amount of $4,188.00, and it indicated, on its face, that it was for unpaid "[s]tairs and [r]ailings" that had been furnished between June 8, 2001, and June 15, 2001. A satisfaction of this lien was executed on October 15, 2001. Broten Garage Door Sales' lien was recorded September 5, 2001. It was in the amount of $3,214.00, and it indicated, on its face, that it was for the unpaid "sale and installation of garage doors and openers," which took place between June 25, 2001, and July 17, 2001. A satisfaction of this lien, dated January 31, 2002, was filed on February 5, 2002. At a meeting "in the early part of August [2001]" attended by Respondent, Mr. Stasinos, the Skieras, and the president of the bank from which the Skieras had borrowed the money to pay for the construction of their residence, Respondent announced that, on behalf of ICC, "he was filing [for] bankruptcy."4 ICC stopped working on the Skiera Residence after this meeting. At the time, the Skiera Residence was approximately 70 to 80 percent completed (and the Skieras had paid ICC a total of $304,766.20, or approximately 80 percent of the total contract price (including change orders) of $378,286.205). In addition to paying $57,316.62 to satisfy the "eight valid claims of lien" referenced in the Parties' Stipulations, the Skieras paid approximately an additional $57,000.00 to other subcontractors who provided goods and/or services "needed to complete the house." The $10,000.00 check referred to in the Parties' Stipulation 14 (that the Skieras received from Andover Construction, Inc.) did not "represent any kind of final settlement" between the Skieras and ICC. The October 4, 2001, Certificate of Occupancy for the Skiera Residence referred to in the Parties' Stipulations indicated, on its face, that ICC was the contractor, notwithstanding that ICC had abandoned the project "in the early part of August [2001]." Respondent has been a Florida-licensed general contractor since July 29, 1987. In his capacity as ICC's licensed qualifier, he has previously (by Final Order filed in DBPR Case Nos. 2001-03283 and 2001-03284 on December 23, 2003) been found guilty of, and disciplined for, violating (in connection with two residential construction projects undertaken by ICC for A. Richard Nernberg) the same subsections of Section 489.129(1), Florida Statutes (Subsections (1)(g), (i), and (m)) that he is accused of violating in the instant case. In these prior disciplinary proceedings, Respondent's license was suspended for two years, and he was fined $6,000.00 and required to pay $958.30 in investigative costs. Administrative complaints were also filed against Respondent in DBPR Case Nos. 94-15958 and 97-17352. Both of these cases were resolved by settlement stipulations in which Respondent "neither admit[ted] [nor] denie[d] the allegations of fact contained in the [a]dministrative [c]omplaint[s]."

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board issue a Final Order: finding Respondent guilty of violating Section 489.1425(1), Florida Statutes, as alleged in Count I of the Amended Administrative Complaint, and fining him $1,000.00 for this violation; (2) finding Respondent guilty of the violation of Section 489.129(1)(g)1., Florida Statutes, relating to Boca Concrete Pumping's December 6, 2000, $1,001.25 lien, alleged in Count II of the Amended Administrative Complaint, and taking the following disciplinary action against him for this violation: suspending his license for four years (with such suspension to run consecutively with his current suspension); (b) fining him $5,000.00; (c) requiring him to pay restitution in the amount of $1,001.25 to the Skieras; and (c) ordering him to reimburse the Department for all reasonable investigative and prosecutorial costs (excluding costs related to attorney time) incurred by the Department; and (3) dismissing all other charges in the Amended Administrative Complaint. DONE AND ENTERED this 8th day of May, 2007, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of May, 2007.

Florida Laws (16) 1.01120.569120.5717.001206.20218.79455.2273458.331489.115489.119489.1195489.129489.140489.1425627.8405810.02
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs MICHAEL W. BALLANS, 89-005192 (1989)
Division of Administrative Hearings, Florida Filed:St. Cloud, Florida Sep. 22, 1989 Number: 89-005192 Latest Update: Apr. 16, 1990

The Issue The issue for disposition is whether, as alleged in the Administrative Complaint, Respondent committed various violations of Chapter 489, F.S., regulating the practice of contracting, by failing to complete a roofing job which he had agreed to perform.

Findings Of Fact At all times relevant, Michael W. Ballans was licensed by the State of Florida as a certified building contractor, holding License Number CB C036542. He qualified as an individual doing business at 1107 Oregon Avenue, St. Cloud, Florida 32769. On April 6, 1988, H. Earl Fisher signed his acceptance of a written proposal by Michael Ballans for Ballans to install a new roof on Fisher's double-wide trailer at 7650 E. Irlo Bronson Memorial Highway, in St. Cloud, Florida. The price for the job was $1,575.00, for supplies and labor. Fisher made an initial payment of $1,018.00 on June 6, 1988. Materials were delivered to the job site, but Ballans never commenced work. Fisher contacted Ballans four or five times to try to get him to do the job or to get someone else to do it. Ballans never returned the funds and at one point told Fisher that he could not do the work because he lost his insurance. Fisher did not agree to do the work himself and told Ballans he wanted the money back and the materials removed from his property. Stanton Alexander was qualified as an expert in construction industry contracting, including roofing. He has practiced in the profession for approximately thirty years. He served two terms on the construction industry licensing board, including a term as chairman. He has testified in the past as an expert in construction industry practices. A contractor terminates his responsibility under a contract after payment and final inspection and a certificate of occupancy has been issued. Until then, he is responsible for completion of the job. Proper procedure when a contractor becomes unable, to complete a job is to refund the money and remove the materials or to get permission from the building department and owner to bring in another contractor to complete the work. Michael Ballans did neither, and simply abandoned the job. This deviation from the standards of construction industry practice constitutes incompetency or misconduct.

Recommendation Based on the foregoing, it is hereby, RECOMMENDED That a Final Order be entered finding Michael W. Ballans guilty of violations alleged in Counts I, II and IV of the Administrative Complaint, and imposing a fine of $500.00. DONE AND RECOMMENDED this 16th day of April, 1990, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of April, 1990. COPIES FURNISHED: Jack L. McRay, Esquire Dept. of Professional Regulation 1940 N. Monroe St., Suite 60 Tallahassee, FL 32399-0792 Michael W. Ballans 2314 Knob Hill Drive, Apt. #12 Okemos, Michigan 48864 Kenneth D. Easley, General Counsel Dept. of Professional Regulation 1940 N. Monroe St., Suite 60 Tallahassee, FL 32399-0792 Fred Seely, Executive Director DPR-Construction Industry Licensing Board P.O. Box 2 Jacksonville, FL 32202

Florida Laws (5) 120.57455.225455.227489.1195489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs ROBERT E. POINDEXTER, D/B/A ACCURATE DEVELOPMENT, INC., 97-001956 (1997)
Division of Administrative Hearings, Florida Filed:Melbourne, Florida Apr. 24, 1997 Number: 97-001956 Latest Update: Mar. 20, 1998

The Issue Whether disciplinary action should be taken against Respondent's license to practice contracting under license number CR C056639, based on violations of subsections 489.129(1)(h)(2), (m), (n), and (k), Florida Statutes, as charged in the Administrative Complaint.

Findings Of Fact Based on the evidence and the testimony of the witnesses presented and the entire record in this proceeding, the following facts are found. At all times pertinent to this proceeding, Respondent was a contractor, having been issued license number CR C056639, by the Florida Construction Industry Licensing Board on January 22, 1993. Respondent is the licensed qualifier for Accurate Development Inc., a Florida corporation. On or about December 23, 1994, the Respondent contracted with Joseph and Kathleen Hauser to construct a 2,000 square foot house on lot 15 of the Iroquois South Subdivision, (606) Jillotus Street in Merritt Island, Florida. The contract between Respondent and the Hausers was for the construction of a house only. The real estate upon which a house was to be built was already owned by the Hausers. The construction contract between the Hausers and Accurate Development was executed on December 23, 1994. Respondent presented the contract to the Hausers, who affixed their signatures to the contract first. They then gave the contract back to Respondent for his signature, whereupon he signed it and then he inserted the six percent commission provision in favor of Castle Real Estate. The contracted price for the construction was $147,800.00. The Hausers paid the Respondent $6,940.00 by check as a deposit when they signed the contract on December 23, 1994. The check was payable to Accurate Development. At no time during the transaction between Accurate Development and the Hausers did the Hausers meet a representative of Castle Real Estate in any capacity, nor were the Hausers ever represented by a real estate agent of their own choosing or one furnished by Accurate Development or Castle Real Estate. The Hausers did not discuss a six percent commission for the benefit of Castle Real Estate with the Respondent at any time prior to signing the contract, and they did not initial the six percent provision to approve it. But the Hausers did not object to the insertion of the commission at the time of the signing of the contract or at a later time. The check was endorsed and deposited by Accurate Development on December 23, 1994. On or about February 2, 1995, the construction contract was amended to increase the size of the house. Mr. And Mrs. Hauser applied for a construction loan in the amount of $150,750.00 from the Space Coast Credit Union in Melbourne, Florida. Upon approval of said loan, they paid Accurate Development an additional deposit of $6,940.00 on March 3, 1995. On or about March 3, 1995, the construction contract was revised to separate the construction contract from the spa contract with Aqua-Blue Pools to build a pool. On the date the construction loan was closed, a payment was made by Space Coast Credit Union directly to Castle Real Estate in the amount of $9,045.00 as a six percent commission on the construction contract between Accurate Development and the Hausers. This amount was shown on the closing statement, and no objection was raised by the Hausers. The Respondent was at all material times a director of and closely affiliated with Castle Real Estate. Respondent's spouse was the owner/broker of the real estate company. All of Accurate Development's sales went through Castle Real Estate who provided sales personnel at the Respondent's company's model homes. Respondent did not pull the permit to construct the Hauser's home. During several meetings between the Respondent and the Hausers in May and June 1995, Respondent informed the Hausers that he was having financial difficulties and cash flow problems. At that time, he asked the Hausers if they would pull the permit for the construction of their home or if they would become an owner/builder. Respondent stated that he did not have the money to pull the permit and begin construction. On May 26, 1995, at a meeting between Respondent and the Hausers, Respondent suggested that the Hausers become owner/builder or that they have their home built by Andy Barber, a general contractor and friend of the Respondent or that they take a second or third mortgage on other property that Respondent owned for the amount of the deposit. On or about June 10, 1995, the Hausers contacted Andy Barber about building their home, but he informed them that he was too busy and would not be able to build their house. The Hausers contracted with another builder (Gary Shaul) to build their house, and Mr. Shaul pulled the permit and constructed the house. On June 7, 1995, the Hausers asked the Respondent for an itemized list of what had been done with their up-front money. Respondent informed the Hausers that he had paid general bills. Respondent did not provide an itemized list of his expenses. On August 7, 1995, Mr. Hauser informed the Brevard County Building Department that Respondent was no longer their contractor. Respondent did not object to the Hausers' notice to the Brevard County Building Department that Gary Shaul of Shaul Builders would be constructing the Hausers' home. Respondent has not refunded any portion of the monies paid to him by the Hausers as deposits or the six percent commission paid to Castle Real Estate. Respondent is defending the disciplinary action against him by relying on paragraph 16 of the contract, a liquidated damages clause, to justify retaining the Hausers' deposit money. Paragraph 16 of the contract upon which the Respondent relies, provides in part that "In the event of Purchaser's default hereunder, contractor shall have the option to terminate this contract and retain all monies previously paid by purchaser as its liquidated damages upon five (5) days written notice to purchaser, or contractor may sue for damages or pursue any other legal remedy it may have." Respondent never notified the Hausers in writing that he considered them to be in breach of their contract with him and that he therefore intended to retain the $13,880 deposit they had paid. The Hausers were ready, willing and able to live up to their contract responsibilities. Respondent abandoned the Hausers' job without just cause causing them financial harm.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violating subsections 489.129(1)(h)(2), (k), (m) and (n), Florida Statutes; it is FURTHER RECOMMENDED that the Board impose an administrative fine in the amount of $6,500, require Respondent to make restitution to the Hausers in the amount of $13,880, require Respondent to pay the costs incurred in the investigation and prosecution of this case, and that Respondent's license be SUSPENDED for five years. RECOMMENDED this 16th day of October, 1997, at Tallahassee, Leon County, Florida. COPIES FURNISHED: John L. Chaves, Esquire Department of Business and Professional Regulation Northwood Centre 1940 N. Monroe Street Suite 60 DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 16th day of October, 1997. Tallahassee, Florida 32399-0792 Robert E. Poindexter 2545 Burns Avenue Melbourne, Florida 32935 Lynda L. Goodgame General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Rodney Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467

Florida Laws (4) 120.57455.227489.1195489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PAUL MCALLISTER, D/B/A GARNETT-MCALLISTER, 78-001552 (1978)
Division of Administrative Hearings, Florida Number: 78-001552 Latest Update: Jun. 29, 1979

Findings Of Fact Respondent Paul McAllister is a certified general contractor and was the qualifying individual for the firm of Garnett-McAllister Associates, Inc., Fort Lauderdale, Florida, in 1977 and until July, 1978. (Stipulation) On April 8, 1977, Respondent's firm entered into a contract with Ray Borchardt, Westchester, Illinois, for the construction of a four-unit apartment building at Lighthouse Point, Florida. The contract provided for a total price of $139,110.00, payable in five payments or "draws" in various percentages of the contract price at specified stages of construction. However, the contract did not specify a time for performance or completion of the building. It contained a clause stating "Any alteration or deviation from above specifications involving extra costs - will be executed only upon written orders, and will become an extra charge over and above the estimate." Respondent obtained a building permit for the construction of the building from the building official, City of Lighthouse Point, Florida, on May 8, 1977. (Petitioner's Exhibits 1, 2) Prior to the commencement of construction, it was determined that foundation pilings for the building were required and therefore Borchardt sent Respondent the sum of $13,519.65 on June 9, 1977, as an additional sum over and above the contract price. At this time, he also sent the first draw in the amount of $20,866.00 even though such payment was not called for until completion of the foundation and "rough in" of plumbing and electric connections. On August 1, 1977, Borchardt paid the second draw of $20,866.00 although the roof was not on, nor had the beam been poured at the time as called for under the contract. Respondent was delayed approximately three weeks by failure of a supplier to provide the second floor concrete planking. On October 24, 1977, Borchardt paid the third draw in the amount of $34,777.00 although construction was not at the stage called for under the contract. On November 22, 1977, Borchardt paid $18,000.00 of the fourth draw and on January 23, 1978, paid the remaining portion of $16,777.00. At that time, the roof was not completed, tile work had not been started, woodwork was incomplete, and kitchen cabinets and vanities had not been installed pursuant to the terms of the contract. Borchardt had made a number of trips from Illinois to Florida during the construction period and was aware that his various partial payments were made in advance of completion of the several construction phases. He had dealt primarily with Edward J. Garnett, president of Garnett-McAllister Associates, Inc., as to the financial aspects of the project. Respondent primarily was a "field" man in charge of supervising construction. Also, Borchardt's son-in- law, Vincent A. Svegel, had moved to Florida in September, 1977, and acted as Borchardt's contact with Respondent's firm after that time. Both Respondent and Garnett informed Svegel in the fall of 1977 that the building would be completed by December 15. (Testimony of Borchardt, Svegel, Petitioner's Exhibit 1) Although during the early part of 1978, five subcontractor liens were filed against the property for work and materials supplied on the project, three of these liens were eventually paid by Garnett-McAllister and the remaining two totaling over $7,000.00 were eventually paid by Borchardt. One of the latter liens was filed by Pompano Roofing Company, Inc. That firm refused to install the roofing tile until paid and the tile therefore "sat on the roof" for approximately five months. On March 13, 1978, Borchardt filed a complaint with Petitioner based on the fact that the work had not been performed according to the draw schedule and liens had been placed on the property. Borchardt also complained to James P. Simmons, the building official of Lighthouse Point about the project delays and claims of lien. As a result, on March 14, 1978, Simmons referred the complaint to Petitioner because Respondent was certified by the state. Petitioner's local inspector, Wallace Norman, issued a Notice of Violation of Section 468.112(2)(e), F.S., to Respondent on March 15, 1978, for diversion of funds based on the filing of liens by suppliers. In a meeting with Respondent and Garnett, Norman asked for an explanation of the situation. They told him that they had been building a house in Davies, Florida, and had used some of the money that Borchardt had paid them to pay suppliers on that house and they had expected to be able to put the money back into the Borchardt project when they sold and realized a profit on the other house. (Testimony of Borchardt, Svegel, Simmons, Norman, Petitioner's Exhibits 7, 9, 10; Respondent's Exhibit 3) During the period between January and March, 1978, some progress was made toward completing the building, including the rough in of the plumbing and electrical systems, installation of inside lath work, installation of tub and shower stalls, and extension of a kitchen area. As late as April 19, 1978, Respondent accompanied Borchardt to a supplier to purchase windows for the building. (Testimony of Svegel, Respondent, Pet. Ex. 3) On May 29, 1978, Svegel, in behalf of Borchardt, notified building official Simmons that Garnett-McAllister Associates, Inc. had been terminated from any further work on the building due to the fact that the building permit had expired and would not be reissued, and requested authorization to finish the building. Simmons thereafter issued a building permit to complete the building to Borchardt on June 21, 1978. He also instructed his staff not to issue any more permits to Respondent due to his "poor track record" and liens which had been filed against the building under construction. Simmons issued the completion permit under the authority of Section 304.3 of the South Florida Building Code, Broward County Edition, which provided that a building permit expires and becomes null and void if work is abandoned at any time for a period of ninety days. Although Simmons considered that the time limit had elapsed because an inspection had not been called for by the builder for ninety days, he erroneously believed that the last inspection had been on January 4, 1978, when, in fact, the city's inspection records show that the plumbing department had made an inspection of rough plumbing on March 27, 1978. Simmons did not notify Respondent of the issuance of the second permit. He considered that he had inherent authority in his position to prohibit issuance of additional permits to Respondent, but didn't consider his action in this regard to be disciplinary in nature because the City of Lighthouse point does not issue contractor's licenses. Therefore, the matter was referred to Petitioner for any action against Respondent's state certification. (Testimony of Simmons, Svegel, Petitioner's Exhibit 3, 4, 11, Respondent's Exhibit 1) At some time prior to obtaining the permit to complete the building, Borchardt had refused to pay the final draw of $27,824.00 to Garnett-McAllister Associates, Inc. because the firm was so far behind on the job. Garnett had told Borchardt that be was selling another home for $80,000.00 and was going to put some of the money he realized from that sale into the Borchardt project. He wanted Borchardt to loan him $20,000.00 and take back a lien on a boat in order to have money in the interim to work on the building. When Borchardt declined to do so, Garnett told him that he could not complete the job. Borchardt also received a call from Respondent to the effect that he would finish the job on his own for $150.00 a week if Borchardt would pay the remaining costs. Borchardt informed him that he would pay nothing further until the job was completed. Garnett had also told Svegel that he had used some $25,000 to $30,000 of the Borchardt funds to construct the house in Davies and that he would put that money back into the firm's business account to use for the Borchardt building when the house was sold. (Testimony of Borchardt, Svegel, Respondent) At the time Borchardt took over completion of construction, the building was approximately 70-75 percent completed. Borchardt paid an additional sum of about $82,000.00 to complete the building which was some $54,000.00 more than the original contract price. However, about $12,000.00 of this sum constituted changes to the original specifications that had been agreed to by Borchardt during the course of construction. Some of these involved changes due to building code requirements, such as the addition of a ramp for the handicapped. Other changes were made on the recommendation of subcontractors or resulted from requests by Borchardt's daughter and son-in-law who were intending to occupy one of the apartments in the building. None of these changes was reflected in a written change order or supplemental agreement to the contract because Borchardt had agreed to the changes and neither party to the contract apparently considered it necessary to formalize these matters. Additional changes in the sum of some $12,000 were made to the building after Borchardt took over construction. These primarily dealt with carpeting, appliances and the like. (Testimony of Borchardt, Svegel, Simmons, Respondent, Stipulation, Petitioner's Exhibits 5, 8) Respondent testified at the hearing and disclaimed knowledge of the financial affairs of the corporation which he claimed were handled exclusively by Garnett. He denied ever abandoning the project and stated that he was unaware, until June 7, 1978, that Borchardt was taking over the construction project to complete. He acknowledged that funds became a problem about mid- January, 1978, and that he then recognized that the contract price had been set at too low a figure because cost overruns were being experienced. He denied diversion of Borchardt's funds to the Davies house, and claimed that his firm did not purchase supplies for that project. He conceded, however, that the firm had one corporate business account from which suppliers on all jobs were paid. Respondent further testified that when funds for the Borchardt building became scarce, profits from other jobs were used in meeting construction costs on the building. He acknowledged receiving a salary of $8,420.00 during the course of construction and said that Garnett had also drawn a sum of approximately $11,000.00 for himself. (Testimony of Respondent) A review of the books of Garnett-McAllister Associates, Inc. by a certified public accountant indicated that they were not well kept and were frequently in error. The auditor's report reflected that the firm had expended at least $80,675.00 in direct construction costs on the project. Certain cost items could not be verified due to the failure of suppliers to respond to the auditor's inquiry. These accounts were reflected on the books of the firm at a total of approximately $1,000.00. (Testimony of Webb, Respondent's Exhibit 4)

Recommendation That Respondent's certification as a general contractor be suspended for a period of 90 days, but that he be permitted to complete any contracts which are uncompleted at the time suspension is effected. DONE and ENTERED this 25th day of April, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32302 Alan C. Brandt, Jr., Esquire 1040 Bayview Drive Fort Lauderdale, Florida 33304 J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 4
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs FRED T. GARRETT, 01-003480PL (2001)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Aug. 31, 2001 Number: 01-003480PL Latest Update: Jul. 03, 2002

The Issue The issues are whether Respondent committed the several violations of Sections 489.129(1)(h)2.,(h)3.,(j),(k), and (n), Florida Statutes (1997), for the reasons stated in the respective Administrative Complaints and, if so, what, if any, penalties should be imposed. (All chapter and section references are to Florida Statutes (1997) unless otherwise stated.)

Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a certified general contractor pursuant to license number CG C059414. At all relevant times, Respondent was the qualifying agent for Fred T. Garrett Construction, Inc. ("FTG"). As the qualifying agent, Respondent was responsible for all of FTG's contracting activities in accordance with Section 489.1195, Florida Statutes. Respondent failed to obtain a certificate of authority for Fred T. Garrett Construction, Inc., as required by Section 489.119(2), Florida Statutes. The St. Cyr Case On or about August 21, 1998, Respondent entered into a contract with Louis L. St. Cyr to construct an addition to the residence located at 201 South Bel Air Drive, Plantation, Florida. The contract price was $50,000. Although Mr. St. Cyr paid $2,500 to Respondent, Respondent failed to commence work and canceled the project, thereby abandoning it without just cause and without proper notification to Mr. St. Cyr. The contract did not permit Respondent to keep the $2,500 paid by Mr. St. Cyr, and Respondent failed to refund the payment within 30 days after abandonment. Out of the $2,500 he received from Mr. St. Cyr, however, Respondent paid $1,600.00 to the architect before abandoning the project. Thus, the net amount that Respondent owes to Mr. St. Cyr is $900. Petitioner incurred a total of $1,092.28 in investigative costs relating to the St. Cyr case. The Forney Case On May 22, 1998, Respondent, who was doing business as FTG, entered into a contract with Mr. Warren Forney for the construction of a two-bedroom, one-bath addition to the residence located at 1698 Northeast 33rd Street, Oakland Park, Florida. The contract price was $32,500. The contract with Mr. Forney did not contain a written statement explaining the customer’s rights under the Construction Industries Recovery Fund, as required by Section 489.1425(1), Florida Statutes. On July 7, 1998, Respondent obtained permit number 98-050297 from the Oakland Park Building Department. Construction commenced on or about July 7, 1998, and continued sporadically until October 29, 1998, when Mr. Forney dismissed Respondent for failure to timely complete the project. The Oakland Park Building Department issued notices of violation against the project on August 3, September 11, and October 14, 1998, for various building code violations. Mr. Forney was forced to obtain a homeowner’s permit and subsequently hired a subcontractor to complete the work. Mr. Forney paid Respondent approximately $29,250 before relieving Respondent of his duties. To complete the project, Mr. Forney paid a total of $48,746.52, which was $15,396.52 over and above the original contract price. Petitioner incurred a total of $2,190.78 in investigative costs relating to the Forney case. The Kong Case In or around January 1998, a contractor named Lakeview Concepts hired Respondent to perform demolition work for the Kong dry cleaning store project on the property located at 5171 South University Drive, Davie, Florida. On or about June 17, 1998, permit 98-00002349 was issued to Respondent to perform alterations on commercial property located at 5171 South University Drive, Davie, Florida. Respondent, however, did not yet have a contract with the owner for this work. The next month, on or about July 30, 1998, Respondent, who was doing business as FTG, entered into a contract with Shek Kong to complete the dry cleaning store project at 5171 South University Drive, Davie, Florida, for the contract price of $22,300. Shek Kong made payments to Respondent totaling $16,000. Respondent’s work was of poor quality, however, and on or about November 6, 1998, he ceased work, though the project had not been completed. On or about November 14, 1998, Douglas Frankow, license number CB C052960, gave Mr. Kong an estimate of $20,562 to complete the project. Thereafter, on or about June 30, 1999, Mr. Kong contracted with George Settergren, another licensed contractor, to complete the project for a contract price of $27,956. On December 9, 1999, in Case No. 98-020065 08, the Circuit Court, Seventeenth Judicial Circuit, Broward County, Florida, rendered a Final Judgment against Respondent and in favor of Mr. Kong. This judgment awarded Mr. Kong the total amount of $28,693.30, plus 10 percent interest per annum. Petitioner incurred a total of $2,502.78 in investigative costs relating to the Kong case.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Florida Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violating Sections 489.129(1)(h)2., (h)3., (j), (k), and (n), Florida Statutes, imposing administrative fines in the aggregate amount of $3,700, assessing investigative costs in the aggregate amount of $5,785.84, placing Respondent's license on probation for a period of four years from the date the Final Order is entered by the Board, and awarding payment of restitution to each customer as follows: (1) to Warren Forney, the amount of $15,396.52; (2) to Shek Kong, satisfaction of the unpaid civil judgment in the amount $28,693.30, plus 10 percent interest accrued thereon; and (3) to Louis L. St. Cyr, the amount of $900. DONE AND ENTERED this 15th day of February, 2002, in Tallahassee, Leon County, Florida. _________________________________ JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 2002.

Florida Laws (7) 17.00117.002489.119489.1195489.127489.129489.1425
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILLIAM B. GARRISON, 83-002289 (1983)
Division of Administrative Hearings, Florida Number: 83-002289 Latest Update: Dec. 04, 1990

The Issue The issues in this matter are as promoted by an administrative complaint brought by the State of Florida, Department of Professional Regulation against William B. Garrison. In particular, the respondent is charged with having diverted funds or property received for the completion of a specific project in violation of Section 489.129(1)(h), Florida Statutes (1979). In addition, the respondent is charged with signing a statement falsely indicating that payment had been made for all subcontracting work, in violation of Section 489.129(1)(1), Florida Statutes (1979), and of making misleading, deceptive, untrue or fraudulent representations in the practice of his profession in violation of Section 455.227(1)(a), Florida Statutes (1979). It is the respondent's denial of these accusations and request for formal hearing which eventuated in this recommended order.

Findings Of Fact Respondent is a holder of a registered building contractor's license issued by the Florida Construction Industry Licensing Board. That license number is RB0029142, first issued in 1975. Respondent has been associated with the construction business on a full time basis since 1970. From 1975 through 1981 respondent operated as Garrison Builders of Tallahassee, Inc. At all times relevant to the administrative complaint, respondent was the qualifier of Garrison Builders of Tallahassee, Inc., pursuant to Section 489.119, Florida Statutes. On August 6, 1980, Garrison Builders of Tallahassee, Inc., contracted with TBW, Inc., to build eight townhouses at Larette Drive, in Tallahassee, Florida, for a contract price of $269,424.00. That base contract price was subject to change orders, the first of which decreased the contract price by $8,000 and the second which increased the contract price by $864.00. As a consequence, the final contract price was $262,388.00. Garrison Builders of Tallahassee, Inc., was paid a total of $257,598.38 under the terms of the contract. Garrison Builders paid out, related to the account for this project, $257,890.01. As of March 31, 1981, respondent had failed to pay the following subcontractors and materialmen in the amounts designated: Butterfield's Floor Covering, Inc. $ 277.10* Barineau & Sons Heating and Air Conditioning 2,420.00 Big Bend Rental Center, Store #1 596.96 Sam Crowder Co. 61.39 Discount Lumber, Inc. 445.33* Ken Driggers, Inc. 32.14 Deep South Insulation Co. 600.00 John T. Daniel Cabinet Co. 3,400.00 Miller Sheet Metal 1,292.00 Melco Wood fixtures 1,502.59 Maples Concrete Products Co., Inc. 1,571.31 Quality Plumbing, Inc. 5,864.00* Tallahassee Glass & Screen 690.56 Tallahassee Rug Co. 1,486.51 Yarbrough Paint & Decorating Center 1,589.15 City Building Department-Systems Charges 1,790.10 Wallpaper Installation-50 rolls @ $7.00/roll 350.00* Total $23,969.14 *Billing not complete The contract between Garrison Builders and TBW was to be performed in 150 days after August 6, 1980, subject to allowances for rain days, etc. Garrison Builders was responsible for satisfying the claims of the materialmen and subcontractors as reflected above, in keeping with the terms of the contract. Respondent, as president of Garrison Builders, was responsible for the overall project. In keeping with the contract terms, respondent and the job foreman for the subject project made application and certification for payment. These applications and certifications may be found as part of the petitioner's composite Exhibit Number 2, admitted into evidence. The last of those applications was made by the respondent on February 17, 1984. Prior to that payment, Garrison Builders had been paid $247,136.70. On that occasion, as on other occasions, respondent certified, "that all amounts have been paid by him for work for which previous certificates for payment were issued and payments received from the owner. . . ." in signing the certification for an additional $10,461.68 draw. At that point in time approximately 98 percent of the job had been completed. Nonetheless, contrary to the certification statement, materialmen and suppliers had not been paid as demonstrated in the accounting set forth above showing that as of March 31, 1981, $23,969.14 was still owed, which amount far exceeds the difference between the contract price of $262,388.00, and the amount Garrison Builders had been paid prior to the last draw, i.e., $247,136.70. That differential is $15,251.30. In a meeting in March 1981 at which respondent attended and was represented by counsel, respondent admitted to a representative of TBW that materialmen and suppliers had not been satisfied in terms of payment. By affidavit of April 3, 1981, a copy of which is petitioner's Exhibit Number 5 admitted into evidence, he acknowledged the $23,969.14 of outstanding claims effective March 31, 1981. Moreover, in a court appearance involving TBW and some of the materialmen and suppliers in which the question of possible liens by those latter entities was litigated, respondent admitted that he had lied in his statement of certification in the contractor's application and certificate for payment, wherein he stated that all materialmen and suppliers had been satisfied before obtaining payments under the contract. This admission, taken in the context of the other facts found, indicates that the respondent appreciated that materialmen and suppliers had not been paid when he made application for the February 17, 1981, draw and swore that they had. This oath as to that circumstance was not one of mistake or inadvertence. It was a comment made with the knowledge of the implications of the oath. Thus, the effect was to be false, misleading, deceptive, untrue and fraudulent, contributing to a loss of $277.10 which the owner paid Butterfield Floor Covering without reimbursement. Respondent was not paid the balance of the contract price, the owner having claimed that the contract was 90 days beyond the contract date for completion, and upon the assertion by the owner that additional funds had to be expended to complete the contract over and above the contract amount. Respondent claims that the reason for late completion concerned a problem with a subcontractor who was providing cabinets, one John Daniel. In addition, respondent alludes to the fact that he was in the hospital from November 10, 1980, through November 20, 1980, and again from December 2 through 19, 1980, and as a consequence was unable to supervise the job in a manner which he preferred. Daniel was a subcontractor chosen by the owner and accepted by the respondent. From a review of the evidence, it is unclear whether Daniel was the responsible agency for the project being approximately 90 days over the contract period. It is also uncertain whether the essentially 90 day delay was in view of respondent's failures as responsible agent for Garrison Builders. Had Garrison Builders been responsible the owner would have been entitled to deduct essentially $20 a day for late penalties. Finally, the owner's claim of expenditures in excess of $10,000 to complete the job was not satisfactorily proven. In summary, the job was late for reasons unestablished. Certificates of occupancy were issued for the eight units in March 1983 signaling the completion of the job. On the subject of whether respondent diverted funds and property from this project into other projects thereby affecting the outcome of the project, the proof on balance demonstrates that Garrison Builders, under the aegis of the respondent, made a bad bargain by underbidding this project as opposed to diverting funds and property to other pursuits.

Recommendation Upon consideration of the findings of facts and conclusions of law, it is RECOMMENDED that a final order be entered which finds the respondent guilty of a violation of Section 489.129(1)(1), Florida Statutes, and Section 455.227(1)(a), Florida Statutes, and dismisses the allegation of a violation of Section 489.129(1)(h), Florida Statutes. For the violations established, a penalty of a 60 day suspension should be imposed against the respondent. DONE AND ENTERED this 11th day of September 1984 in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of September 1984. COPIES FURNISHED: Michael Egan, Esquire ROBERTS, EGAN & ROUTA, P.A. 217 South Adams Street Tallahassee, Florida 32302 Jeffrey H. Savlov, Esquire Post Office Box 10082 Tallahassee, Florida 32302 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 James Linnan, Executive Director Board of Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (6) 120.57455.227489.119489.129589.15790.10
# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer