Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
WEST VOLUSIA CONSERVANCY vs. ARBORETUM DEVELOPMENT GROUP AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 86-002463 (1986)
Division of Administrative Hearings, Florida Number: 86-002463 Latest Update: Sep. 16, 1987

The Issue The issue is whether Bayou Arbors, Inc. (Arbors), is entitled to a dredge and fill permit to construct docks in DeBary Bayou, Volusia County, Florida.

Findings Of Fact On January 8, 1986, DER received an application from Arboretum, a predecessor in interest of Arbors, to construct 12,758 square feet of docks in DeBary Bayou to provide ninety eight (98) boat slips, and to dredge 2,509 cubic yards of shoreline material from DeBary Bayou in areas within DER's jurisdiction under the proposed boat docks, and to place approximately 800 linear feet of concrete riprap along the shoreline after it was dredged. Following the initial application review process, which included on- site evaluations by several DER biologists, on April 14, 1986, DER prepared a Biological and Water Quality Assessment in which DER's staff recommended that the project be modified to delete the dredging, allowing the littoral zone to remain intact. On April 24, 1986, DER forwarded its Biological and Water Quality Assessment to Mr. Charles Gray, the property owner. In response to DER's recommendations, the Applicant submitted, and on April 30, 1986, DER received, a revised Application which deleted the originally-proposed shoreline dredging of 2,509 cubic yards of material as well as the placing of 800 linear feet of concrete riprap. This Application was submitted by Mr. Duy Dao, a Professional Engineer registered in the State of Florida. This Application proposed constructing approximately 17,000 square feet of docking facilities, providing ninety-eight boat slips, along approximately 2,580 linear feet of shoreline adjacent to twenty-four acres of uplands owned by the Applicant. The original and the revised drawings omitted a vertical scale from the cross-section drawings of the project. This omission gave the impression that the shoreline bank of DeBary Bayou was steeper than it actually is and that the water depths in DeBary Bayou adjacent to the north shoreline are deeper than they actually are. However, DER's biologists were on-site four times between February 25, 1986, and May 19, 1986. They observed the existing slope of the DeBary Bayou shoreline and the existing depths in DeBary Bayou, and the on-site observations negated the effect of the omission in the drawings. The omission in the drawings did not affect DER's evaluation of the project. On May 23, 1986, DER issued its Intent to Issue and Draft Permit No. 64-114399-4 to Arboretum. The Intent to Issue and the Draft Permit include the following Specific Conditions: Further construction on the Applicant's property along the DeBary Bayou shall be limited to uplands; Issuance of this permit does not infer the issuance of a permit for dredging in the Bayou at a future date, should an application for dredging be submitted; A deed restriction shall be placed on the condominium limiting boats moored at the facility to seventeen feet or less. A copy of the deed restriction shall be submitted to the Department within sixty days of issuance of this permit; There shall be no "wet" (on-board) repair of boats or motors at this facility; All boats moored at the dock shall be for the use of residents of the condominium only. Public use of the dock or rental or sale of mooring slips to non-residents of the condominium is prohibited; Manatee warning signs shall be placed at 100 foot intervals along the length of the dock(s); Turbidity shall be controlled during construction (by the use of siltation barriers) to prevent violations of Rule 17-3.061(2)(r), Florida Administrative Code. On June 29, 1987, Volusia County, DER and Arboretum entered into a "Joint Stipulation for Settlement" wherein Arboretum agreed not to construct more than twenty-six docks accommodating more than fifty-two boat slips along Arboretum's DeBary Bayou frontage of 2,580 feet. Furthermore, Arboretum agreed that it would modify the configuration and the design of the boat slips and the location of the boat docks; that it would post Slow Speed, No Wake zone signs and manatee education signs along DeBary Bayou from the 1-4 bridge west to a point 100 feet west of the western boundary of Arboretum's boat docks; and that as mitigation for the removal of vegetation from the littoral zone where the boat slips would be constructed, Arboretum would plant wetland hardwood trees. In addition to the Joint Stipulation for Settlement, on June 14, 1987, the property owners, Charles Gray and Sandra Gray, as part of their agreement with Volusia County, executed a "Declaration of Covenants, Conditions, and Restrictions" to which the Joint Stipulation for Settlement was attached as an exhibit. Said Declaration of Covenants, Conditions, and Restrictions, reiterated the Joint Stipulation's limitation of construction of boat docks in DeBary Bayou and further provided that said boat docks would not be constructed at the Arboretum project site in DeBary Bayou unless and until certain maintenance dredging set forth in Article II of the Declaration of Covenants, Conditions, and Restrictions occurred. Furthermore, Article III of said Declaration of Covenants, Conditions and Restrictions set forth certain prohibitions regarding constructing boat ramps on the Arboretum property and docking or storing boats along the DeBary Bayou shoreline except at the site of the proposed docks. In 1969, an artificial channel was excavated in DeBary Bayou adjacent to the north shoreline of DeBary Bayou by a dragline operating along the shoreline. At present, said channel has been partially filled by organic sediments originating in DeBary Bayou. There exists in Section 403.813(2)(f), Florida Statutes, an exemption from the DER's permitting requirements for the performance of maintenance dredging of existing man-made channels where the maintenance dredging complies with the statutory provisions and with the regulatory provisions found in Florida Administrative Code Rule 17-4.040(9)(d). The dragline excavation work performed in DeBary Bayou in 1969 created a structure which conforms to the definition of "channel" provided in Section 403.803(3), Florida Statutes. The maintenance dredging required by the Declaration of Covenants, Conditions, and Restrictions is to be performed by suction vacuuming of the silt sediment, from the 1969 channel and that dredged material is to be placed on Arbors' upland property at the project site. This maintenance dredging differs from the dredging originally proposed by the applicant in its application submitted in January 1986. The dredging originally proposed, which DER recommended against, was to be performed by back hoes and drag-lines which would have cut into the north shoreline of DeBary Bayou and would have affected the littoral zone along the project shoreline. The average water level in Lake Monroe and DeBary Bayou is approximately 1.8 feet above mean sea level. On April 18, 1987, transact studies in DeBary Bayou showed water levels at 3.2 feet above mean sea level and that water depths in DeBary Bayou to a hard sand/fragmented shell bottom ranged from approximately one foot along the south shoreline to approximately nine feet in deep areas in the former channel. The average depth of the channel is five feet below mean sea level. The water depth in DeBary Bayou ranges from approximately one to three feet. At times of average water levels, one to three feet of silt or unconsolidated sediment overburden covers the natural hard sand/shell bottom of DeBary Bayou. This silt and sediment overburden is composed of organic material and is easily disturbed. When it is disturbed, it raises levels of turbidity, although there was no evidence presented that the turbidity would violate state water quality standards. This silt and sediment overburden has been deposited at a faster rate than it would normally be deposited under natural conditions because of the Army Corps of Engineers' herbicidal spraying of floating plants in DeBary Bayou. As this silt and sediment overburden decomposes, it takes oxygen from the water. The presence of a strong odor of hydrogen sulfide indicates that the oxygen demand created by the sediment is greater than the available supply of oxygen at the sediment-water interface. This unconsolidated silt and sediment overburden does not appear to harbor either submerged vegetation or significant macroinvertebrate populations. The Shannon/Weaver diversity index of benthic macroinvertebrates at four locations in DeBary Bayou indicated lowest diversity at the project site and highest diversity at the 1-4 overpass, where a small patch of eel grass is growing. Removal of this silt and sediment overburden from the 1969 channel will enhance the system, enabling a hard bottom to be established, with a probability of subsequent establishment of a diversity of submerged macrophytes. Removal of the silt and sediment overburden from the 1969 channel will restore the natural hard sand/fragmented shell bottom in that area of DeBary Bayou. It is unlikely that boat traffic in the restored channel will cause turbidity which will violate state water quality standards. Removal of this silt and sediment overburden will improve water quality in DeBary Bayou by removing a source of oxygen demand. Removal of this silt and sediment overburden will create a better fish habitat by exposing some of the natural bottom of DeBary Bayou. Fish are unable to spawn in the unstable silt and sediment. Removal of this silt and sediment overburden will increase the depth of water in DeBary Bayou channel to between four to six feet. The maintenance dredging, required by the Declaration of Covenants, Conditions, and Restrictions, is limited by statute to the channel which was excavated in 1969. Therefore, a continuous channel will not be maintained from the project site eastward to Lake Monroe. At present, a sandbar exists at the confluence of DeBary Bayou and Lake Monroe. During low water, this sandbar restricts navigation into and out of DeBary Bayou to small craft. At present, boats can and do travel on DeBary Bayou for fishing and for other water-related recreational activities. However, due to water level fluctuations, boating on DeBary Bayou is easier during higher water periods. During lower water periods, navigation into and out of DeBary Bayou is still possible, but boaters must proceed using common sense and caution. The United States Fish and Wildlife Service (FWS) has no evidence that manatees presently use or have ever used DeBary Bayou. Adult manatees have an average girth of approximately three (3) feet. Without a continuous channel open to Lake Monroe, manatees are not likely to go up DeBary Bayou. Since the water at the sandbar at the mouth of DeBary Bayou at its confluence with Lake Monroe is generally less than three feet deep throughout the year, it is likely that these shallow waters will deter manatees from entering DeBary Bayou. DeBary Bayou is a spring-fed run from a spring a substantial distance upstream. The sheetflow of the spring water follows a circuitous route through marsh areas prior to reaching the area of this project. The proposed site is just west of the 1-4 overpass and Lake Monroe. The FWS's data show that the St. Johns River in Volusia County has an extremely low documented manatee mortality rate resulting from boat/barge collisions. Generally, boats greater than 23 feet long are more likely to kill manatees outright than smaller boats are. In marinas, manatees are very rarely killed by collisions with boats. Manatees and marinas are highly compatible. On August 1, 1986, the FWS issued a "no-jeopardy" opinion regarding Arbors' project. In this letter, the FWS stated that Arbors' project was not likely to jeopardize the continued existence of the manatee or to adversely modify the manatee's critical habitat. In the year since the FWS issued its no-jeopardy opinion, no manatee mortalities resulting from boat-barge collisions have been documented in the St. Johns River in Volusia County. The FWS recommended one boat slip per one hundred linear feet of waterfront, or twenty-six boat slips for the project. A single-family residence which would be entitled to one pier could berth an unlimited number of boats at that single pier. The FWS would have no control over the number of boats using that single pier. Arbors' project calls for twenty-six piers. The FWS's evaluation of Arbors' project is exactly the same as that agency's evaluation of any other marina project anywhere in areas designated as critical manatee habitat. All of the St. Johns River in Volusia County, Florida, is designated as critical manatee habitat. On July 16, 1986, after issuance of its Intent to Issue, DER received comments from the Florida Department of Natural Resources regarding Arbors' project and its potential impact on manatees. DER considered the possibility of boat/manatee collisions and had specifically considered this issue. DER did not agree with the broad and general concerns expressed by the Department of Natural Resources, and DER's rules have not adopted a specific requirement regarding a ratio between the length of a project's shoreline and the number of permittable boat slips. On July 16, 1986, the Department received a letter from the FWS concerning fisheries issues and navigation. This FWS letter was received after issuance of DER's Intent to Issue. Although DER considered these comments, DER disagreed with the FWS's recommendations regarding these issues. Water quality sampling and analysis showed that at present, there are no violations of DER's Class III water quality standard in DeBary Bayou, except for the dissolved oxygen criterion on some occasions during early-morning hours, and that result is to be expected. It is further not expected that there will be any water quality violations after the project is completed. If the work areas affected by driving piles to build floating docks and the work area around the maintenance dredging of the DeBary Bayou channel are contained within turbidity barriers, as required by general and specific conditions of the DER's proposed Draft Permit, it is anticipated that no violations of the Class III turbidity criterion will occur during construction of Arbors' project. By maintenance dredging the former DeBary Bayou channel, Arbors will remove the silt and sediment overburden from the channel and restore a deep (four to five feet below mean sea level) channel having a hard sand/fragmented shell bottom. Arbors' dock will be restricted to small boats whose operation in the deep channel will be unlikely to re-suspend silt and sediment and cause violations of the Class III turbidity criterion. Additionally, it is unlikely that any turbidity which is created by turbulence from boat propellers in a designated "No Wake, Slow Speed" zone will violate the Class III turbidity criterion. Although the entire project will be enhanced by the proposed maintenance dredging, such dredging is not a part of the permit application. From the evidence it appears that the project is permittable without the dredging. Although Arbors' project will result in the addition of some oils and greases associated with outboard motors to DeBary Bayou, the addition is not expected to result in violations of the Class III water quality standards. Additionally, release of heavy metals from anti-fouling paints should be minimal, and that release can be further controlled by specifically prohibiting over-water repair of boats and motors. Some addition of phosphorous to the waters of DeBary Bayou is anticipated due to use of phosphate-based detergents for washing boats. Additionally, minimal amounts of phosphorous may be added to DeBary Bayou from re-suspension of organic silts by turbulence from boat propellers. However, DER has no standards for phosphorous in fresh waters, and the minimal additional amounts of phosphorous expected from these sources are not anticipated to violate DER's general nutrient rule. Operation of boats at Arbors' proposed boat docks will cause no water quality problems which would not be caused by operation of boats at any other marina anywhere in Lake Monroe or anywhere else in the State of Florida. While WVC's expert, Robert Bullard, testified that Arbors' proposed boat docks could potentially cause violation of DER's Class III water quality criteria for turbidity, oils and greases, heavy metals and phosphorous, he was unable to testify that Arbors' project actually would cause such violation. His testimony in this regard was speculative and is not given great weight. No other WVC expert testified that Arbors' project was likely to cause violation of any criteria of DER's Class III water quality standards. It is anticipated that the shade cast by the boat docks will not have an adverse affect on water quality. Additionally, DeBary Bayou is a clear, spring-fed water body open to direct sunlight. The boat docks will cast shade which will enhance fish habitat. The proposed docks will not threaten any production of fish or invertebrate organisms. The mitigation plan proposed by the applicant and accepted by Volusia County and DER requires planting wetland hardwood tree species. These trees will certainly assist in stabilizing the bank of DeBary Bayou and minimizing erosion of the shoreline. Additionally, these trees will absorb nutrients from the water and will perpetuate the wooded wetland habitat along the DeBary Bayou shoreline. Arbors' own expert, Carla Palmer, also suggested the sprigging of eel grass in the dredged portion of DeBary Bayou. Such planting should be included as part of the mitigation plan. DER considered the cumulative impact of this docking facility. Four marinas are presently permitted on Lake Monroe and in the St. Johns River between Lake Monroe and Deland. DER considered these facilities' existence when it reviewed Arbors' application, and was satisfied that Arbors' boat dock facility would not have an adverse cumulative impact. There are no specific guidelines for a cumulative impact evaluation; accordingly, DER must apply its cumulative impact evaluation on a case-by-case basis. In the present case, there is no showing of adverse cumulative impacts from this project. Arbors' project will not adversely affect significant historical or archaeological resources recognized pursuant to applicable Florida or Federal Law. WVC was organized in March 1985, to oppose development in West Volusia County. WVC did not meet regularly and did not keep regular minutes of its meetings in the interim between organizing and filing the Petition in June 1986, for an administrative hearing on the Intent to Issue a permit for Arbors' project. When the Petition was filed, WVC did not have a membership roll, and was unsure how many members it had. Further, it is unclear as to how many members may have attended an "emergency" meeting to authorize filing said Petition. Approximately five months after said Petition was filed, WVC was incorporated and approximately nine months after the Petition was filed, WVC compiled a list of the people who were WVC members in June 1986. The emergency meeting WVC held in June 1986, to authorize filing said Petition was the first and the only such "emergency" meeting WVC ever held. The minutes of the emergency meeting have been lost. In June 1986, WVC may have had written rules authorizing emergency meetings and authorizing it to file suit, but its Chairman is unsure of this. Six of WVC's approximately 20 members may have lived within one mile of Arbors' project site in June 1986. Two of these members lived on waterfront property on Lake Monroe east of the 1-4 bridge. Some of these WVC members have never taken a boat west of 1-4 onto DeBary Bayou. WVC, as an organization, never sponsored outings or boat trips onto DeBary Bayou before filing the Petition. WVC's officers at the time of filing the Petition did not use DeBary Bayou for boating, fishing or swimming. No WVC members have ever seen manatees in DeBary Bayou. As with any other similar project on Lake Monroe, the boats which might be berthed at Arbors' project might add additional trash to the waters of Lake Monroe, might disturb the wildlife which WVC members might see on their property, and might cause wakes which might erode waterfront property. One of WVC's founders, who was an officer in June 1986, when WVC filed the Petition, stated that she would not be adversely affected in kind or degree any more than any other taxpayer in Florida. Friends timely intervened and its intervention was authorized by its membership at a regularly noticed meeting.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Regulation enter a Final Order granting Permit Number 64-114399-4, subject to those specific conditions set forth in paragraph 6 hereof and as modified by the stipulation entered into between Arboretum, Volusia County, and Department of Environmental Regulation, as more particularly described in paragraphs 7 and 8 hereof, and to include within the mitigation plan the sprigging of eel grass in areas of the dredged portion of DeBary Bayou. DONE AND ENTERED this 16th day of September 1987, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 16th day of September 1987. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 86-2463 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner and Intervenor, West Volusia Conservancy, Inc., and Friends of the St. Johns, Inc. 1. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(3); 2(5); 8(24); 13(8); 46(57); and 47(57). 2. Proposed findings of fact 3, 4, 7, 10, 11, 12, 28, 29, 32, 34, 35, 36, 40, 42, 43, 44, and 45 are rejected as being subordinate to the facts actually found in this Recommended Order. 3. Proposed findings of fact 5, 14, 15, 16, 17, 20, 23, 24, 25, 26, 27, 30, 31, 33, 39, and 41 are rejected as being unsupported by the competent, substantial evidence. 4. Proposed findings of fact 6, 9, 18, 19, 21, 22, 37, and 38 are rejected as irrelevant. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Bayou Arbors, Inc. 1. Each of proposed findings of fact 1-56 are adopted in substance as modified in the Recommended Order, in Findings of Fact 1-56. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Department of Environmental Regulation Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-11(1-11); 13-28(12-27); 29-38(29-38); 39(38); and 40-48(39-47). Proposed finding of fact 12 is rejected as unnecessary. COPIES FURNISHED: Dale Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Richard S. Jackson, Esquire 1145 West Rich Ave. Deland, Florida 32720 Dennis Bayer, Esquire P. O. Box 1505 Flagler Beach, Florida 32036 Philip H. Trees, Esquire P. O. Box 3068 Orlando, Florida 32802 Vivian F. Garfein, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301-8241

Florida Laws (4) 120.57403.412403.803403.813
# 1
ERICH SCHLACHTA AND ESTER SCHLACHTA vs. CITY OF CAPE CORAL, PARKS AND RECREATION DEPARTMENT, 80-002258 (1980)
Division of Administrative Hearings, Florida Number: 80-002258 Latest Update: Jul. 16, 1981

Findings Of Fact The Petitioners are, and at all times material hereto were, owners of residential real property adjoining the site of the proposed construction to the northwest. The City of Cape Coral is, and at all times material hereto was, the applicant for the permit from the Department of Environmental Regulation for the construction of the proposed project, which is a public boat ramp. This boat ramp is located within the corporate limits of the City of Cape Coral. The Department of Environmental Regulation is, and at all times material hereto was, the agency of the State of Florida which has the authority to issue permits for dredging, filling or other activities of a similar nature to include construction of boat ramps on the shores or banks of navigable waterways of the state. The Caloosahatchee River is a navigable, Class III waterway of the State of Florida. Lands covered by the waters of the Caloosahatchee River at the location of the proposed project are submerged lands of the State of Florida. The City applied to the Department on March 27, 1980, for a permit to construct a boat ramp on the Caloosahatchee River at the Cape Coral Yacht Club. A boat ramp currently is located at the site of the proposed project. The existing ramp was initially partially constructed in 1964, and subsequently a seawall was removed and the two existing seawalls projecting into the water were constructed in 1969. The City's application was initially incomplete, lacking evidence of approval by the City Council. At the request of the Department, the City submitted additional information. The application as originally proposed contemplated dredging waterward of the mean high water line at the proposed project site. The dredged material was to be placed along a beach area adjacent to the proposed boat ramp, and the spoil would have projected waterward of the mean high water line. The proposed project was revised in September, 1980, to delete placing the dredged material on the adjacent beach. The revised project would retain the dredged material landward on the mean high water line until it had dried, at which time it would be removed from the site. After the dredging described above has been completed, the revised project calls for the construction of a concrete boat ramp 42 feet wide and 58 feet long extending approximately 28 feet waterward of the mean high water line of the Caloosahatchee River. In addition, three timber poling walkways at the sides of and in the middle of the boat ramp will be constructed extending waterward of the mean high water line. On May 10, 1980, Dan Garlick, an employee of the Department, conducted a Permit Application Appraisal and concluded the project would have an insignificant impact on biological resources or water quality, and would comply with Chapters 17-3 and 17-4, Florida Administrative Code. Garlick recommended approval of the project. David Key, another employee of the Department, conducted an on-site investigation and expressed concurrence with the findings contained in Garlick's report. Key also noted that no adverse impact on navigation was anticipated as a result of the project. On July 1, 1980, the National Marine Fisheries Service and US Fish and Wildlife Service investigated the proposed project. These federal agencies had no objection to the proposed boat ramp or the dredging aspects of the proposed project. These agencies had no objection to the proposed spoil basis located in the upland area of the site required to dry the dredged material. These agencies objected only to placement of the dredged material on the adjoining beach, which proposal was deleted in the City's revised plan. Petitioners introduced no expert testimony relating to the effects of the proposed project on water quality, marine resources or navigation. Lay testimony was received regarding conditions around the site of the existing boat ramp. Garbage, dead fish and flotsam accumulate at or near the site in the water and on the land. The existing seawalls extending perpendicular from the shore prevent matter in the water from being flushed by the current and tides. In the proposed project the seawall to the right of the existing boat ramp would not be removed. Prior to January, 1981, the existing ramp site was not regularly cleaned by the City. Since that date the area has been cleaned regularly; however, after weekends when the facility is most heavily used there are large quantities of refuse and garbage around the site. The City has requested and received permission from and payment has been made to the Department of Natural Resources for use of sovereignty submerged lands and the removal of 215 cubic yards of fill. After a review of the revised application, the Department gave notice of its intent to issue a permit for the proposed project by letter dated November 10, 1980. The Department based its intent to issue on a determination that the project would not adversely affect navigation, marine resources or water quality, provided the conditions set in the letter were met. The Department's Exhibit 2 is the only documentation presented by the City reflecting the City Council's action on the application. Exhibit 2 contains no findings by the local government that the proposed project would not violate any statute, zoning or ordinances; makes no findings that the project would present no harmful or increased erosion, shoaling of channels or stagnation of waters; and contains no findings that no material injury or monetary damage will result to adjoining land. The Petitioner's Exhibit 1, Minutes of the City Council for the City of Cape Coral Meeting of June 18, 1980, does not reflect that the final reports on the ecological effects of the proposed project were read into the record, and does not reflect that those reports were duly considered by the Council. It was at this meeting that final action on the application for permitting of the proposed project was presumably taken. However, the motion approved at that meeting did not authorize approval of the proposed project nor issuance of the permit. The motion empowered the Mayor to write a letter expressing approval. This motion presumable resulted in the letter of June 17, 1980, the Department's Exhibit 2, which was signed by the City Manager and not the Mayor.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law the Hearing Officer recommends that the agency head withhold final action on the application for a reasonable period of time to permit the applicant to cure the procedural defects. Upon curing the procedural defects, the Hearing Officer would recommend issuance of the permits originally requested. DONE and ORDERED this 12th day of June, 1981, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of June, 1981. COPIES FURNISHED: Daniel Sasso, Esquire Post Office Box 1422 1413 Cape Coral Parkway Cape Coral, Florida 33904 Richard Roosa, Esquire 1714 Cape Coral Parkway Post Office Box 535 Cape Coral, Florida 33904 Paul R. Ezatoff, Jr., Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION ERICH SCHLACHTA and ESTER SCHLACHTA, husband and wife, Petitioner, vs. CASE NO. 80-2258 CITY OF CAPE CORAL, PARKS AND RECREATION DEPARTMENT and STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION, Respondent. /

Florida Laws (4) 120.52120.57403.087403.813
# 2
WILLIAM J. HELWIG AND A. W. ROWE vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 79-001570 (1979)
Division of Administrative Hearings, Florida Number: 79-001570 Latest Update: Dec. 10, 1979

Findings Of Fact Seago Group, Inc., the Applicant/Intervenor, owns a tract of land in Lee County Florida, which is completely surrounded by creeks and canals, including Indian Creek on the north. The Intervenor intends to develop the parcel and is seeking a permit from the Department to construct a bridge over Indian Creek to provide access. There is presently a cul-de-sac at the end of Indian Creek Drive on the north side of the creek. The bridge would extend Indian Creek Drive over the creek onto the applicant's property. The Intervenor held an option to purchase land for the right-of-way on the north side of the creek. The Petitioners own property adjacent to Indian Creek Drive. The Petitioner Helwig owns property upon which be resides, and which adjoins the proposed bridge site. The Petitioner Rowe owns property upon which he resides several lets up Indian Creek Drive from the proposed bridge site. The Intervenor originally made application to construct a road over Indian Creek at a different, but nearby location using a culvert rather than a bridge. The Department's staff appraised the application and recommended that it be denied because deposits of fill around the culverts would have eliminated productive submerged creek bottoms, interfered with the ability of the aquatic habitat to support fish and wildlife populations, and eliminated shoreline vegetation which serves to filter runoff which enters the creek, thus helping to preserve good water quality in the creek. The application was withdrawn by the Intervenor before final action was taken on the Department's staff recommendations. The Intervenor thereafter filed the instant application. The application was to construct: ... A 26 ft. wide by 50 ft. long vehicular bridge constructed with 21" prestressed slabs on pile bent abutments over Indian Creek in Lee County, Florida. The application further provided: All work will be conducted on upland with no need for any equipment or material required to be in the water. All equip- ment and material will be delivered by upland access. The application did not reflect that Intervenor had previously sought a permit for the culvert constructions, but the Department was clearly aware of the previous applications and its appraisal of the bridge application was treated as a supplement to the appraisal of the culvert application. In its Notice of Intent to Issue the Permit, the Department erroneously designated the bridge as a "two-span" bridge. The application is actually for a one-span bridge. In its notice the Department added the following specific conditions: Turbidity screens shall be used during construction. Drainage at bridges approaches shall be by swale and no ditches shall be constructed. Drainage shall meet county specifications. No dredging or filling in Indian Creek. No bridge construction shall take place until ownership or easement is obtained through Mr. David Ruch's property pursuant to letters on file with the Department. The Intervenor has acceded to the specific conditions and agreed to comply with them in the event the permit is ultimately issued. All of the pilings for the proposed bridge would be constructed at or above the mean high water line of Indian Creek. Some turbidity could be expected during construction, however, the use of turbidity screens would eliminate any significant impact upon the water quality, fish and other wildlife resources of Indian Creek during construction. The only potential source of pollution from the bridge after construction would be from runoff entering Indian Creek from the bridge. The amount of runoff that would result from a 50 ft. long by 26 ft. wide bridge is negligible. The limited impact that such runoff could have upon the creek can be eliminated by having drainage flow through a swale system. Since the Intervenor has agreed to utilize a swale system, it does not appear that the bridge would have any adverse impact upon the water quality of Indian Creek or any other water body. Neither does it appear that the bridge would adversely affect fish and wildlife resources. Since all bridge pilings would be constructed at or above the mean high water line, transitional zone vegetation can continue to flourish along the shoreline. The planned clearance between the creek elevation at mean high water and the bridge is seven feet. The bridge would thus impede traffic by any boats that protrude more than seven feet above the water line. This presents no significant navigational impact in Indian Creek. There are two avenues for navigating from the bridge site on Indian Creek to the Caloosahatchee River. One of these avenues is presently obstructed by a bridge with an elevation less than that proposed by the Intervenor. The other avenue is obstructed by a very shallow area that will not permit navigation by other than very small vessels. The Department in the past has denied applications to dredge that shallow area. The Intervenor and the Department have submitted Proposed Findings of Fact. To the extent that these proposed findings have not been included in the foregoing Findings of Fact, they are hereby adopted as fully as if set forth herein.

Florida Laws (1) 120.57
# 4
LARRY J. SAULS AND HARRIETT TINSLEY SAULS vs. FELO MCALLISTER AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 79-002030 (1979)
Division of Administrative Hearings, Florida Number: 79-002030 Latest Update: Mar. 13, 1980

Findings Of Fact Respondent Felo McAllister and his wife Dorothy own a home and dock on Texar Bayou off Escambia Bay in Pensacola, Florida. A storm sewer with a diameter of 15 to 18 inches empties into the Bayou near the dock. The silt- laden outflow from the storm sewer has resulted in a sand bar or berm two or three feet wide paralleling the shoreline from the McAllisters' property line to the dock. This sand bar separates a ditch caused by the outflow from Texar Bayou. Over the years, silt has accumulated underneath the dock. The McAllisters originally applied for a permit to dredge boat slips at the dock. Andrew Feinstein, an environmental specialist II in respondent Department's employ, evaluated the original application and recommended denial, because he felt extending the dock was preferable to dredging. The McAllisters then modified their application so as to seek a permit for dredging at the mouth of the storm sewer in order that the silt already deposited there would not wash underneath the dock. Mr. Feinstein and Michael Clark Applegate, an environmental specialist III and dredge and field supervisor employed by the Department, testified without contradiction that the Department has reasonable assurances that the proposed project will not violate any applicable rules. The permit DER proposes to issue contemplates that the berm will not be breached. The bottom on which the dredging is proposed to take place belongs to the City of Pensacola. Although under water, it is a part of a dedicated roadway. The City itself does maintenance dredging to ensure the efficiency of storm sewers, but is glad for assistance from private citizens in this regard. J. Felix, City Engineer for Pensacola, is authorized allow dredging on this road right of way, and has done so. See also respondent's exhibit No. 2. The site proposed for placement of the spoil is a low area affected by flooding. Fill there would affect drainage onto neighbors' property.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That respondent DER issue respondent McAllister the permit it proposed to issue in its letter of September 14, 1979, upon condition that the spoil be placed at least 100 feet from the water's edge. DONE and ENTERED this 12th day of February, 1980, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: William L. Hyde, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Mr. Larry Jay Sauls and Ms. Harriett Tinsley Sauls 14 West Jordan Street Pensacola, Florida 32501 Felo McAllister 2706 Blackshear Pensacola, Florida 32503

# 5
BOARD OF PILOT COMMISSIONERS vs. HOWARD P. KRUEGER, 82-001972 (1982)
Division of Administrative Hearings, Florida Number: 82-001972 Latest Update: Jan. 06, 1983

Findings Of Fact Howard P. Krueger is a licensed deputy pilot for the Port of Tampa and was so licensed at all times here relevant. Shortly after 8:00 p.m. on 28 February 1982 the M. V. SNOWDRIFT piloted by Respondent Krueger left her berth at the northeast end of Garrison Channel near Davis Island in upper Tampa Bay, and, with the assistance of two tugs, moved to the center of the turning basin headed south to exit Tampa through Sparkman Channel. When in this position, the two tugs were let go and the M. V. SNOWDRIFT started down Sparkman Channel at slow speed. At 6:10 p.m. on 28 February 1982 the tank barge OCEAN 135 commenced discharging gasoline to Cities Service Company at the Tampa Electric Company dock, which is located at the northeast side of Sparkman Channel. The pumping from the OCEAN 135 was in progress as the M. V. SNOWDRIFT passed the moored OCEAN 135. The only evidence presented by the Petitioner was Exhibit 1, a copy of the log of the tank barge OCEAN 135, for February 28, 1982. All entries contained therein are as follows: CITCO Tampa, Florida Voyage 505 1650 Arrival 1710 Secure 1730 Gauged 1745 Hose on regular 1800 Hose on no lead 1810 Start regular 1810 Start no lead At app 2030 while the OCEAN 135 was moored to the dock at T.E.C.O., Hookers Point discharging gaso- line to Cities Service Co. the vessel "Snowdrift" got underway on the opposite side of the turning basin - when she got on a sourtherly heading in mid-channel she let go her tugs & struck out for sea at an extreme engine order & when she was abeam of the OCEAN 135 she was throwing a wake & did part two of my mooring lines &forced me to shut down. /s/ Stevens No time was entered in the log when the pumping was shut down as the log entry states; nor was the log entered when pumping recommenced, if that occurred on February 28. The captain of the tug, Evon St. Phillip, who assisted the M. V. SNOWDRIFT away from the dock and positioned her in the turning basin on February 28, 1982, testified that when he let go he proceeded south through Sparkman Channel alongside the M.V. SNOWDRIFT, that the speed of the SNOWDRIFT as they passed the OCEAN 135 was between one and 1.5 knots, and that he saw no wake of the M. V. SNOWDRIFT hit the OCEAN 135. Captain Krueger testified that he saw the OCEAN 135, knew she was discharging dangerous cargo (by the red lights shown) and that when the M.V. SNOWDRIFT passed the OCEAN 135 she was making between 1.5 and 2.0 knots. Because the log of the OCEAN 135 is incomplete in not logging the time when the Dumping operations were shut down, because I do not believe the "extreme engine order" logged could be heard (or observed by Stevens) the 250 to 300 yards he was distant from the M. V. SNOWDRIFT when the SNOWDRIFT's engines were ordered ahead, and because ships do not accelerate rapidly from a stopped position, the live testimony, that the M. V. SNOWDRIFT was proceeding at 1.5 to 2.0 knots when she passed the OCEAN 135, is deemed more credible than the inference that could be drawn from Exhibit 1, that the M. V. SNOWDRIFT was making excess speed as she passed the OCEAN 135. The speed limit in Sparkman Channel as established by the code of she City of Tampa is 4.0 knots. The M. V. SNOWDRIFT was light when she departed Tampa on 28 February 1982 with a draft of about 12 feet forward and 22.5 feet aft. This vessel is 570 feet in length and is over 11,000 gross registered tons.

Florida Laws (1) 310.101
# 6
C. W. PARDEE, JR. vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 90-005734 (1990)
Division of Administrative Hearings, Florida Filed:Ocala, Florida Sep. 11, 1990 Number: 90-005734 Latest Update: Feb. 21, 1991

The Issue The issues concern the request by Petitioner for a permit(s) to dredge in a man-made canal and to construct two boat houses and six boat slips.

Findings Of Fact Petitioner owns property in Marion County, Florida, from which he has legal access to a man-made canal that intersects the Oklawaha River. This river is an Outstanding Florida Water body. The canal and river are in Marion County, Florida. In November 3, 1989, Respondent received a permit application from Petitioner. This application sought approval to dredge in the man-made canal which is approximately 800 feet long. That canal is owned by the Canal Authority of Florida. The dredging activity would include removal of material at the mouth of the canal as it intersects the Oklawaha River. The applicant intends to expand by dredging the length in the landward extent of the canal from 60 feet to 120 feet and the width from 50 feet to 170 feet. In the landward extent of the dead-end canal, what is described as the boat basin, the applicant seeks approval for the construction of six boat slips and two boat houses. The relative design of the these activities and the placement of the spoil materials removed in the dredging are shown in the application to include responses to the omissions request. That application is found as the Respondent's Composite Exhibits No. 1. At present the applicant has a 30 foot pontoon boat in the dead-end canal. He has a 17 foot bass boat and his neighbor has a 24 foot pontoon boat that use the canal. With the advent of as many as six boats available for the six slips contemplated by this application, the boats would vary in length from 16 feet to 30 feet. In carrying out the dredging activities Petitioner states that he would use anchored turbidity curtains at the intersection of the canal and the Oklawaha River while dredging activities transpired. The exact location of the proposed project is the south shore of the Oklawaha River in Marion County, Florida, in Section 35, Township 14 South, Range 23 East. On June 1, 1990, Respondent noticed its intent to deny the permit. Following that denial Petitioner timely requested a formal hearing to consider his entitlement to the permit(s). The history of the dead-end canal in question is not clear from the record. Its present condition does suggest that it has existed for a considerable number of years. Its appearance does not reflect that routine maintenance has been performed to preserve its original configuration to include maintaining its original depths throughout its course. At the location where the canal intersects the Oklawaha River, the river runs in an easterly direction for a short stretch. Its flow regime at that point is quite swift. This intersection is in a bend of the river. The high energy flow at that juncture has created an undercut at the mouth of the canal and for some distance on either side. The landward extent of the canal or area of the proposed boat basin is an area which was dredged from uplands. The canal extends in an northerly direction to the river through a wetlands swamp. Spoil material from the original dredging had been placed on the east and west side of the canal. There was sufficient deposition on the west side to allow vehicular traffic. That bank of the canal provides physical access to the river. In the Petitioner's experience, at around the time of the application process the water levels in the river and canal were as low as they had been during his three years of observation. At other times during that three year period the water levels had been approximately two feet higher than the low levels described. It is, however, unclear from the record what the normal high and low ranges of water levels in the river would be at this location. Petitioner has observed that the water levels in the canal during the time in question is three feet in most of the canal except at the mouth as it intersects the river where the water level is shallower. As seen in the photographs a great deal of vegetation is present in the water in the canal causing it to be in a marsh like condition. Emergent vegetation exists in certain portions of the canal which indicates a generally permanent shallow water condition. The low water level in the mouth of the canal which has been described is only a few inches deep. The bottom of the canal where it enters the river is more substantial in compaction as compared to the rest of the canal. It is not clear when this compaction occurred, in particular whether it occurred following the original construction of the canal. Navigation is a problem for most boats in the condition of the canal as it was described at the time of hearing. Petitioner describes that he and other fishermen have navigated in the canal when the water levels were high enough to allow that navigation. The canal in its present condition serves as a habitat for wildlife. The wildlife includes blue winged teal, little blue heron, large mouth bass, bream and alligators. In order to mitigate the effects of this project Petitioner has offered to place a recycling water fall in or near the proposed boat basin to allow oxygen to be placed in that basin. This is described in the application documents. Petitioner proposes to landscape the slopes of the basin with boulders and natural vegetation. He proposes to place "no wake" signs along the canal. Notwithstanding the intent to use a turdibity curtain to protect against violations of turdibity standards in the waters in the canal and the adjacent Oklawaha River while dredging, problems of violation of Respondent's turbidity standards are expected to occur. This occurrence is probable given the relatively fast current in the river which precludes the efficient use of turbidity screens or curtains. Dead-end canals such as that envisioned in this project have water quality problems. Enlargement of the dead-end canal does not assist in addressing the problems, even taking into account the intention by Petitioner to recycle water in the proposed boat basin. The water quality standards that are likely to be violated concern dissolved oxygen and BOD (biological oxygen demand). The assurances Petitioner has given about these standards in terms of protections against violations are not reasonable assurances. The addition of six boat slips and the potential for greater use of the canal by boats other than those that presently exist creates an opportunity for other water quality violations. Those possibilities pertain to turbidity problems through the stirring of bottom sediments and a violation of standards for turbidity and nutrients through that process. Oils and greases are associated with the placement of boats in the dead-end canal and a violation of Respondent's water quality standards for oils and greases is possible. During high water events and other flushing events when water from the canal enters the river, the poor quality of that water from the canal will reduce the water quality in the receiving body of water, the Oklawaha River, potentially causing water quality violations in the river. More specifically related to the artificial water fall proposed by Petitioner, such a device is not generally found to be an acceptable solution in addressing any potential water quality problems created by the expansion of the dead-end canal system. In any event, that system of aeration only would address the dissolved oxygen water quality parameter and not other regulatory parameters. The dredging of the canal has adverse affects on the fish and wildlife presently using the waters in the canal through the adverse affect on their habitat. When the water quality is degraded as described it adversely affects public health, safety and welfare for those who use these waters. Petitioner has observed logs jamming in the curve of the river and the accumulation of sand around that area further closing the mouth of the canal. In order to keep the logs free from the canal entrance they have to be moved on a weekly or monthly basis. Petitioner would attempt to save as many trees as possible when dredging in the mouth of the canal. Petitioner intends to sod slopes where dredging occurs and to place berms to keep water from running off into the canal and to prohibit erosion in the area of the boat basin. Petitioner has in mind making it convenient for boats to turn around in the landward end of the dead-end canal and hiding those boats from the sight of persons on the river by keeping them in that area. However, Petitioner acknowledges that when boats negotiate inside the landward extent of the dead- end canal they churn up the bottom sediments and cause problems with water quality. More specifically, Petitioner's right of access to the mouth of the canal is an easement across the property of the Canal Authority of Florida. Petitioner owns the area of the boat basin which is at the far end of the canal. Activities by Petitioner in that portion of the canal about which he does not have ownership rights which violate Respondent's environmental regulations would be adverse to the interest of the Canal Authority of Florida. Petitioner intends to improve the road access along the bank of the canal as it offers access to the river. Two hundred fifty to three hundred feet of the canal length moving away from the river is through a swamp which is marshy with weeded vegetation on its slopes. The rest of the length of the canal is through an uplands. As you move up the slopes in the canal it goes from submerged to transitional to upland species of plants. It is a shallow water system where plants can live inundated or exposed. These are types of plants seen along edges of rivers or lakes where water flows slow. At the mouth of the canal, the compacted substrate has the appearance of what you would find on the edge of a deep creek or river channel. This material is compacted clay or rock with a sand overlay. The area is stabilized. The long term impact of this project is the elimination of vegetation within a marshy system thereby removing habitat for aquatic and semi-aquatic invertebrates and vertebrates and their breeding and feeding areas. In the dead-end canal systems the dissolved oxygen problems are presented by a slow moving regime of water and the suspension of nutrients and materials from the banks of the canal. The bottom materials that are stirred up by boats are transported to the river. Ordinarily canals are too deep to support the form of emergent vegetation found in some portions of the canal. The deeper the canal the more difficult the water problems, and the flushing times take longer. This is especially true with long canals such as the one at issue. This contributes to problems with violation of standards related to DO and BOD. While the canal itself is not an Outstanding Florida Water, the Oklawaha River's ambient water quality is at risk with the dredging activities contemplated by this project.

Recommendation Based upon the consideration of the facts found and conclusions of law reached, it is recommended that a Final Order be entered which denies the permit(s) for dredging and construction of boat slips and docks. RECOMMENDED this 21st day of February, 1991, in Tallahassee, Florida. CHARLES C. ADAMS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of February, 1991. APPENDIX TO RECOMMENDED ORDER, CASE NO. 90-5734 Having considered the proposed facts of the Respondent they are subordinate to facts found. COPIES FURNISHED: Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 C. W. Pardee, Jr. 2769 Northeast 32nd Place Ocala, FL 32670 Douglas H. MacLaughlin, Esquire State of Florida, Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.57403.087403.813
# 7
KAY E. GILMOUR AND LOIS O. GRAY vs JOHNNY P. HIRES AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 90-003690 (1990)
Division of Administrative Hearings, Florida Filed:Jacksonville, Florida Jun. 14, 1990 Number: 90-003690 Latest Update: Oct. 18, 1990

The Issue Whether or not the applicant has provided reasonable assurances that the proposed project meets the requirements of Chapter 403 F.S. and Chapter 17 for issuance of a dredge and fill permit, and if so, how those assurances may be incorporated into the permit as finally issued. BACKGROUND AND PROCEDURE On May 3, 1989, the applicant, Johnny P. Hires, applied to the Department of Environmental Regulation (DER) for an "after the fact" dredge and fill permit to authorize the existence of a dock and associated structures which had already been constructed on Miller's Creek in Duval County, Florida. On July 28, 1989 DER executed its Notice of Permit Denial for the project. On May 29, 1990, negotiations between Hires and DER resulted in a Notice of Permit Issuance which approved the project subject to a specific condition (Specific Condition No. 7) to which Mr. Hires had already agreed. On June 8, 1990, DER received Gilmour and Gray's petition challenging DER's approval of the permit. On June 13, 1990, the petition was referred to the Division of Administrative Hearings for formal hearing pursuant to Section 120.57(1) F.S. and was assigned DOAH Case No. 90-3690. Prior to formal hearing, DER personnel reassessed the agency position once again with the result that at formal hearing DER asserted that Specific Condition No. 7 of the proposed permit was not stringent enough and sought to present evidence that Specific Condition No. 7 should be modified if the permit is to be issued at all. Neither Petitioners nor Hires objected to this procedure, so the parties' positions at hearing were, by agreement, as follows: Mr. Hires wanted the proposed permit finalized as drafted; the Department wanted the proposed permit issued, with a modified Specific Condition No. 7; and Petitioners wanted the proposed permit denied.

Findings Of Fact Mr. Hires constructed a dock, boathouse, and three catwalks in February or March of 1989, without a permit, within the landward extent of Miller's Creek. The dock is 40 feet by 5 feet with a 24-foot "L" at the waterward end. The catwalks form two boat slips, which are 16 feet by 32 feet and 8 feet by 24 feet. These slips are more or less covered by a roof 32 feet by 24 feet. The boathouse is as yet incomplete. Miller's Creek flows into the St. Johns River near the base of the Hart Bridge in Jacksonville, Florida. This location subjects the project to DER's jurisdiction of Class III (recreational use) waters. It is also near Atlantic and Beach Boulevards. Mr. Hires' property is on the west side of the Creek. At low tide, the creek bottom is exposed, except for a channel which is located near the eastern edge of the creek. The channel is approximately 110 feet from the boat slips. DER's original permit denial stated: Use of the slips by boats would result in continuous bottom scour by prop dredging of the area within the slips and between the slips and the channel. This area is approximately 110 feet in length. Prop dredging creates turbidity and moves bottom material into other areas of the creek which can alter the physical, chemical and biological nature of the water body. The movement of bottom material into the existing channel will cause shoaling within adjacent sections of the creek, altering habitat and affecting flows of water and navigation. Increased turbidity in the water column results in reduced light penetration and photosynthetic oxygen production which together with the resuspension of organic bottom material can increase oxygen demand and release pesticides, heavy metals and hydrogen sulphide into the water column. Therefore the project can be expected to have a long-term detrimental impact on water quality and biological resources of the river. Specific Condition No. 7 of the proposed permit issuance document requires that: At no time shall any motorized vessel utilizing the dock disturb the bottom sediments causing prop dredging or generating turbidity which exceeds the State Water Quality Standard. Mr. Hires has indicated his intent to comply with Specific Condition No. 7 and sincerely believes that he will be able to do so. DER has adopted water quality standards within Ch. 17 F.A.C. These may apply to primary turbidity, that is, turbidity due to actual construction of the project, or secondary turbidity, that is, turbidity resulting from subsequent use of the completed project. Turbidity is the resuspension of bottom material into the water column. Prop dredging from motorboats causes turbidity and changes the bottom contours of a waterway. The amount of turbidity which is generated depends, among other things, upon the kind of sediment which comprises the bottom of a waterway. The bottoms of water bodies in Florida range from fine particles, called mud or silt, to larger particles, known as sand. The creek bottom of Miller's Creek is composed of mud and silt. Because of the lighter weight of mud and silt particles, they are more easily resuspended and stay resuspended longer than the larger, sand particles. The environmental impacts of turbidity depend, among other things, upon pollutants, such as heavy metals, which may become mixed with the natural sediments. Pollutants are more likely to be trapped in fine sediments, such as mud and silt, than they are likely to be trapped in coarser, sandy sediments. Runoff from Beach and Atlantic Boulevards and possible past contamination from a nearby shipyard make sediment contamination in Miller's Creek a distinct possibility. Neither DER nor Mr. Hires has performed a sediment study to determine whether pollutants were present. In approximately May of 1989, a small "access trough" was prop dredged over the 110 foot distance between the channel and Mr. Hires' dock. No permit was issued by DER for this dredging and, if a permit application for such prop dredging were submitted, no permit would be issued. The tidal range of Miller's Creek is approximately 1.5 feet. Thus, at high tide, the water is reasonably expected to be 1.5 feet above the creek bottom that is exposed at low tide. No study of the depth of the water in the access trough was presented to DER, although Mr. Hires estimated its depth at high tide to be 4 feet. Mr. Hires represented, and there is no evidence to refute his statement, that the maximum use of his own boat in this area over the last year preceding formal hearing (September 1989-September 1990) has been twelve times. Despite the credible evidence that the access trough was created by prop dredging, Mr. Hires maintained that it was not possible for his boat, which is equipped with a tunnel hull design, to further dredge the area because he can only operate his boat on idle speed on high tide in this area. Because the props on Mr. Hires' boat are recessed upward from the bottom of the boat, Mr. Hires maintained his boat would not further dredge the access trough or the remainder of Miller's Creek. However, without accurate information as to natural water depth and only vague information as to what might occur if the tide changed while Mr. Hires was out in his boat, what might occur if Mr. Hires used another boat, or what might occur if other types of boats docked at the Hires dock, Mr. Hires' information about his current boat does not constitute a reasonable assurance that no further prop dredging of Miller's Creek will occur. Mr. Tyler submitted that Hires could pole or row his boats from his dock to the channel when there is sufficient water so as to avoid prop dredging. Mr. Hires volunteered to post a bond to ensure that there would be no scouring from his use of motorized boats from his dock to the channel, but there was insufficient expert evidence to establish how high a bond would be reasonable or that DER would regard such bonding as any more substantial assurance than the applicant's policing himself under Specific Condition No. 7 as now drafted. There also was no evidence that bonding has been a successful inhibitor of prop dredging in the past, that any insurer is available to issue such a bond, or that Mr. Hires could post a sufficient cash bond. Upon the expert testimony of Jeremy Tyler and the keen observations of the lay witnesses, it is found that, through natural processes, the access trough may be reasonably expected to, with time, silt in and return to a depth consistent with the existing creek bottom. It is further found that prop dredging may be reasonably expected to cause adverse environmental impacts at this location. Upon Mr. Tyler's expert testimony, it is further found that Hires' dock and the dock's associated structures which have already been installed are not reasonably expected to cause any adverse environmental consequences. Contrary to DER's initial permit denial document, there is no vegetation in the area which might be adversely affected by shade from the dock and associated structures. If the pilings were driven into place at low tide, some temporary turbidity would have been generated by the dock and boathouse construction. However, no evidence of such turbidity can be seen at the present time. The only habitat effects of the constructed items and those planned but not completed would be the loss of the habitat which is displaced by the pilings themselves, an effect which, at this location, is inconsequential. The non-expert testimony of Petitioners with regard to endangered species was without appropriate predicate and is not probative with regard to habitat. No competent evidence was offered by Petitioners to suggest that the dock and associated structures themselves would adversely affect water quality or the public interest test criteria.

Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED the Department of Environmental Regulation enter a Final Order establishing the Department's proposed permit issuance action as final, provided, however, Specific Condition No. 7 of the draft permit should read: "At no time shall any motorized vessel utilize the dock." DONE and ENTERED this 18th day of October, 1990, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of October, 1990. APPENDIX TO RECOMMENDED ORDER The following constitute specific rulings pursuant to Section 120.59(2) F.S. upon the parties' respective proposed findings of fact (PFOF): Petitioners' PFOF: Covered in preliminary material. Accepted. Subordinate. Accepted in part; remainder rejected as mere argument. Respondent Hires' PFOF: Covered in preliminary material. First sentence rejected as not proved. Second sentence accepted in part and rejected in part as set out in the Recommended Order. Third sentence accepted so far as it goes but is rejected as a whole for the reasons set forth in FOF 12. Accepted that the offer was made; rejected that it provides reasonable assurances. Respondent DER's PFOF: 1-11 Accepted as modified to more accurately reflect the record evidence as a whole. Copies furnished to: COPIES FURNISHED: Kay E. Gilmour Lois O. Gray 1347 Morier Street Jacksonville, Florida 32207 Johnny P. Hires 1321 Morier Street Jacksonville, Florida 32207 William H. Congdon Assistant General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Florida Laws (2) 120.57267.061
# 8
HENRY ROSS vs CITY OF TARPON SPRINGS AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 00-002100 (2000)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Mar. 12, 2004 Number: 00-002100 Latest Update: Oct. 19, 2004

The Issue The issue in this matter is whether the Joint Application for Environmental Resource Permit and Authorization to Use State-Owned Submerged Lands and Federal Dredge and Fill Permit to dredge sediments from specified areas in the Anclote River and surrounding bayous and lagoons should be granted.

Findings Of Fact Petitioner Henry Ross resides at 1005 South Florida Avenue, Tarpon Springs, Florida. The City of Tarpon Springs (City of Tarpon Springs or City) is located on the Gulf of Mexico and is a coastal community with 56 miles of shoreline. The City of Tarpon Springs is known as the "sponge capital of the world" and has a sponging industry that dates back to the early 1900s. Other activities within the City are recreational boating and shrimp and other commercial fishing operations. The Department of Environmental Protection (Department) is the agency of the State of Florida charged with the responsibility of regulating activities in, on, or over surface waters and wetlands of the state pursuant to Chapter 373 and the rules promulgated thereunder. Pursuant to these responsibilities, the Department is responsible for reviewing and taking final agency action on all environmental resource permit or dredge and fill permit applications. The City's Application, filed with the Department in December 1998 and at issue in this proceeding, is an environmental resource permit application for authorization to use state-submerged lands. The Application initially sought authorization for new dredging and maintenance dredging of approximately 16,888 cubic yards of sediment from 11 locations in or adjacent to the Anclote River and surrounding bayous and lagoons. These areas are Outstanding Florida Waters and are identified as follows: Area 1, Tarpon Bayou; Area 2, Kreamer Bayou (Upper Tarpon Bayou); Area 3, Kreamer Bayou (West Chesapeake Point); Area 4, Kreamer (Bayshore Access); Area 5, Sunset Lagoon; Area 6, Anclote River; Area 7, South Tarpon to Spring Bayou; Area 8, Minetta Bayou; Area 9, Innes Bayou; Area 10, Spring Bayou; and Area 11, Lake Lutea. Consistent with its procedures, the Department sent copies of the Application to all the appropriate agencies for comments and then initiated its own review of the Application. Copies of the Application were sent to Protected Species Management, formerly within the Department, but currently under the Florida Wildlife Conservation Commission; the Army Corps of Engineers; the Department of Community Affairs; and State Lands, an office in the Department responsible for determining how much of the project occurs on state submerged lands. These various offices responded by sending comments to the Department. Based on the agency comments, as well as the Department staff person’s own knowledge and experience, the Department requested additional information from Blasland, Bouck and Lee, Inc. (B.B.L.), the engineering firm that prepared the application on behalf of the City. Also of importance to the Department was the issue of whether the project proposed in the Application was new dredging or maintenance dredging. In order to make this determination, the Department requested additional information from B.B.L. and/or the City about past dredging in the area. This determination was necessary in order to ensure that the statutory criteria for issuing the permit was satisfied. If the City's proposed project were "new" dredging, there was a likelihood of increased boating traffic in the area. On the other hand, if the proposed project were maintenance dredging, there would likely be no increased boating traffic. B.B.L. and/or the City responded to the Department's request, indicating that there was not adequate evidence or information of past dredging. In the absence of such evidence or information, the Department relied on other information to determine if the proposed project was maintenance dredging or new dredging. Specifically, the Department reviewed the Application and other information submitted by the City and/or B.B.L., and aerial photos of the area from 1989, provided by the Army Corp of Engineers. The Department staff also considered observations made and information obtained as a result of their field inspections of the areas. Based on its review of all pertinent information, the Department found that, with the exception of Area 6, the areas designated for the proposed dredging activities were existing navigational channels and were currently functioning as such. Ultimately, the Department determined that the proposed project was a maintenance dredging project and that the purpose of the project was to have the City maintain these existing navigational channels, regardless of their origin. During the Department's 1999 field inspection, the Department staff looked at the depth and width of all existing channels. With regard to depth, the Department believed that the City should not dredge any deeper than the present channels. The Department's decision regarding the width and length of the channels was based on the existing depth of the channels; existing habitat values; the Department's site inspection; current site conditions; the current bathymetry provided by the City, which the Department confirmed; and consideration of what is necessary for safe and common navigation. With respect to Area 6, the Department found that there had been some degree of boating traffic in that area in the past. However, the Department concluded, based on its field inspection, that area had not been maintained adequately to consider it a functioning navigational channel. Therefore, dredging in Area 6 would be considered new dredging. After the Department staff conducted the 1999 field inspection, the Department sent a letter to the City, which recommended how the project could be modified and how some of the potential impacts could be minimized or avoided. Some of the Department's concerns involved the proposed dredging depths and widths of the channels discussed in paragraph 12, and the sensitive habitats in the areas to be dredged. The City addressed the concerns raised by the Department in a June 1999 letter and, in September 1999, the City modified its Application to address those concerns. The City's Application, as modified, significantly changed the whole concept of the project. In light of the modifications, the project changed from one that would increase boating traffic to one that would maintain current boating traffic. Because the Department concluded that the maintenance dredging proposed in the modified Application would not increase the frequency or size of boats using the areas or channels, there will be no secondary impacts associated with new or increased boating traffic. In response to the Department's concerns and requests, the City modified its Application to reduce the initially proposed dredging depths of the channels. For example, in some instances, the City had initially proposed that the depth of the channels be five feet, but subsequently, reduced the depth to three feet. Based on these modifications related to depths and widths, at this time, the City will not dredge Areas 1, 7, 8, and 10 because no dredging is necessary to maintain current depths of the channels. However, if there is accretion or accumulation of sediment at some of those locations, the City will have the right under the permit proposed to be issued, to dredge those areas during the term of the permit. Any dredging, however, would have to be consistent with the terms of the permit. At this time, only three areas have evidence of accreted sediments (accumulated silt) and will be dredged: Area 5, Sunset Lagoon; Area 9, Innes Bayou; and Area 11, Lake Lutea. The City's Application, as modified, reduces or minimizes the impact on the environment in the areas to be dredged, as well as the impact on sea grasses and manatees in those areas. Moreover, the proposed maintenance dredging project will reduce the risks for manatees associated with shallow water by increasing the water depths to safer levels. The Save the Manatee Club (STMC) opposes the proposed dredging project. The STMC considers the proposed project as new dredging and its typical response to such projects is that new dredging may affect manatees or manatee habitats in a negative manner. In this case, the STMC recommended that the Department deny new dredging because the cumulative effect from increased boat traffic will be adverse to manatees and will have more than a negligible effect on the species. Notwithstanding its opposition to the project, the STMC recommended measures to protect manatees should the project be approved. Most of these measures were included in the conditions incorporated in the Notice of Intent to Issue Environmental Resource Permit. In reviewing the City's modified Application, the Department considered the cumulative impact of the proposed project. Contrary to the opinion of the STMC, the Department reasonably determined that because this proposed project involves maintenance of existing navigational channels, there is little potential for cumulative impacts to be an issue. The Florida Wildlife Conservation Commission (Commission) is required to review and comment on all environmental resource applications relative to how the projects will impact manatees. After carefully reviewing and considering the modified Application, the Commission determined that the project, as proposed in the modified Application, varied significantly from the original Application and concluded that "the areas to be dredged are limited to those considered maintenance dredging," and that sea grasses have been avoided. The Commission also concluded that the conditions in the Notice of Intent to Issue regarding manatees' protection are adequate to offset the expected impacts to manatees from the proposed activity. The Notice of Intent to Issue includes the following conditions which minimize the impact to manatees: (1) a manatee observer must be designated and this observer must be in the water when the proposed work is being done; (2) if a manatee is sighted within 50 feet of the dredging activity, the activity will stop until the manatee is out of the area; (3) a log which details the sighting of manatees will be maintained; (4) work will not be performed after sunset because manatees cannot be seen during that time; (5) in-water work will be performed from March to November when manatees are less likely to be in the area; (6) when possible, work will be performed using a hydraulic dredge; and (7) boat traffic within the area will operate at a slow speed during the dredging activity. To ensure that conditions regarding sea grass had not changed since the Department's field inspection more than two years prior to this proceeding, Department staff conducted another field inspection of the area on April 11, 2003, four days prior to this hearing. That field inspection focused on Area 6 because it was conducive to some presence of sea grass. The findings of the April 11, 2003, field inspection were consistent with past reports and field inspections, which revealed that the quantity and density of sea grass were extremely low. During the April 1999 inspection, only a few sprigs of sea grass were observed within or adjacent to the potential dredge area. Due to the continued low density of sea grass, the planned dredging activities do not pose any direct negative impacts to the environmentally-protected aquatic vegetation, including sea grasses. The Department has reasonable assurances that the State water quality standards will not be violated by the proposed permit. Initially, the Department had to establish whether sediments at the proposed areas to be dredged contain pollutants. To make this determination, the Department first used a tiered approach established by the Army Corps of Engineers and the Environmental Protection Agency. This tiered approach requires looking at the location of the proposed areas to be dredged and then looking at the consistency of the sediments in that area. Depending on the result of these reviews, additional testing might be required. In this case, the three sites where the proposed dredging was to be done were identified and grain-size analyses of sediments from each of the areas were completed. These analyses provided information regarding the percentage of fine sediments in the areas proposed to be dredged. The higher the percentage of finer sediments, the greater the potential that the sediments contain pollutants. Based on the grain-size analyses, the sediments from the three areas proposed to be dredged--Area 5, Sunset Lagoon; Area 9, Innes Bayou; and Area 11, Lake Lutea--were coarse enough that they did not have much potential to contain pollutants. Therefore, additional testing of those sites was not necessary. The Department then considered the City's modified Application in terms of how the water quality and quantity will be maintained during the dredging process. For the dredging project, the City proposed using "closed bucket" clamshell dredging and utilizing double floating silt barriers as the containment method. Upon review, the Department authorized the "closed bucket" clamshell dredging for this project. This method is an intermediate method of protecting against pollutants that may be generated by the dredging project. Although hydraulic dredging is a cleaner process, the "closed bucket" clamshell method is more appropriate for this dredging project because it involves "spot" dredging to remove high spots and to maintain the currently existing navigational depths. Pursuant to conditions included in the Notice of Intent to Issue, the City must meet State water quality standards during the dredging events. If the State water quality standards are exceeded, the State has the power to enforce the water quality standards and to shut down any dredging operation that clearly exceeds that criteria. Mark Peterson is currently, and has been for the past two years, the environmental manager of the Department's Environmental Resource Permitting Section. Prior to this, Mr. Peterson was an environmental specialist with the Department. Mr. Peterson has a bachelor of science degree in biology from University of South Florida and a bachelor of science degree in horticulture from Florida Southern College. During his employment with the Department, Mr. Peterson has reviewed thousands of applications for environmental resources permits, exemptions, or authorizations to use State submerged lands. Mr. Peterson has made site visits to locations involved in instances where permits have been issued, with the exception of about two of the 500 approved applications, exemptions, or authorizations. About 50 of the projects were similar to the project at issue in this case. Mr. Peterson has been the Department's primary reviewer of the City's Application and modified Application for this proposed dredging project since its inception. Based upon Mr. Peterson's review of all relevant documents and analyses, the comments of appropriate agencies, and his field inspections of the site, the project, as proposed in the modified Application and the Notice of Intent to Issue Environmental Resource Permit, meets the public interest test set forth in Section 373.414(1). It is specifically found that: The activity will not adversely affect the public health, safety, and welfare or the property of others; The activity will not adversely affect the conservation of fish and wildlife, including endangered or threatened species or their habitat; The activity will not adversely affect navigation or the flow of water or cause harmful erosion or shoaling; The activity will not adversely affect the fishing or recreational values on marine productivity in the vicinity of the activity; The activity will be of a temporary nature because the channels tend to silt over time (over months, sometimes over many, many years; The activity will not adversely affect in any manner any significant historical and archaeological resources under the provisions of Section 267.061; and The activity will not affect the current condition and relative value of functions being performed by areas. In order to begin this dredging project, the City also needed to get approval from the United States Corps of Engineers and the Pinellas Water and Navigation Control Authority. These agencies have approved permitting the project.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that Respondent Department of Environmental Protection enter a final order granting the Application of the City of Tarpon Springs, as amended, and issuing Environmental Resources Permit No. 52-01481903-001. DONE AND ENTERED this 7th day of October, 2003, in Tallahassee, Leon County, Florida. S CAROLYN S. HOLIFIELD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of October, 2003. COPIES FURNISHED: Doreen Jane Irwin, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Henry Ross 1005 South Florida Avenue Tarpon Springs, Florida 34689 Thomas J. Trask, Esquire John G. Hubbard, Esquire Frazer, Hubbard, Brandt & Trask, LLP 595 Main Street Dunedin, Florida 34698 Kathy C. Carter, Agency Clerk Office of the General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

Florida Laws (18) 120.569120.57163.3161253.002253.03253.12258.37258.39258.40258.42258.43267.061373.413373.414373.421373.427403.031403.814
# 9
JAMES E. SLATER, AS TRUSTEE, AND ALICIA O`MEARA vs ORANGE COUNTY PARKS AND RECREATION DEPARTMENT AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 97-000437 (1997)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Jan. 30, 1997 Number: 97-000437 Latest Update: Feb. 12, 1999

The Issue The issue presented for decision in this case is whether Orange County should be granted Environmental Resource Permit (“ERP”) No. 940519-1 for the Keene’s Park and Boat Ramp project (also referred to herein as the "R.D. Keene boat ramp") to be located on Lake Isleworth, part of the Butler Chain of Lakes, an Outstanding Florida Water (“OFW”), pursuant to the permitting criteria of Chapter 373, Part IV, Florida Statutes, Chapter 40E- 4, Florida Administrative Code, and the Basis of Review for Environmental Resource Permit Applications of the South Florida Water Management District (the “District”).

Findings Of Fact Based on the oral and documentary evidence adduced at the final hearing, and the entire record in this proceeding, the following findings of fact are made: THE PARTIES Petitioner Alicia O’Meara and Intervenor Regina Gibbs are the owners of waterfront property on Lake Isleworth. Petitioner James E. Slater is the trustee and legal owner of waterfront property on Lake Isleworth. Orange County is the owner of waterfront property on Lake Isleworth. The Orange County Parks and Recreation Department, which prepared and submitted the ERP application, administers a budget in excess of $36 million and employs more than 425 persons. The District is a public corporation initially established under Chapter 25270, Laws of Florida, 1949, and currently operating pursuant to Chapter 373, Florida Statutes, and Chapter 40E, Florida Administrative Code. The District is statutorily responsible for issuance of ERP permits. THE CURRENT SITUATION The Butler Chain of Lakes is a series of interconnected lakes in Orange County, covering in excess of 5,000 acres, and including Lake Down (the northernmost lake in the Butler Chain), Lake Butler, Wauseon Bay, Lake Louise, Lake Isleworth (also known as Lake Palmer), Lake Chase, Lake Blanche, Lake Tibet-Butler, Lake Sheen, Pocket Lake, Little Fish Lake, and their connecting canals. The Butler Chain drains south into the Upper Kissimmee River Basin. The Butler Chain of Lakes is a Class III water body, and has been designated as an OFW since 1984. The Butler Chain of Lakes is surrounded by exclusive residential communities. There are approximately 1,400 docks on the Butler Chain of Lakes, providing private access to at least that many motorized watercraft. At all relevant times, there has been one boat ramp open to the general public on the Butler Chain. That public ramp is located in the southeastern portion of Lake Down, and is immediately adjacent to vehicular traffic on Conroy-Windermere Road. The ramp was deeded to Orange County by a private owner in the 1950s. The Lake Down ramp is an inclined cement or concrete slab that leads down into the shallow water and allows boat trailers to be backed to water’s edge and boats to be unloaded into Lake Down. The ramp has no dock, floating dock, buoys, or any other structure that would provide ease of access to handicapped or disabled persons. The ramp has no mooring facility in its vicinity. Should there be a need to moor a boat, the operator must do so in the shoreline vegetation. The Lake Down ramp has no adjacent parking lot. Orange County leases a vacant lot on the other side of Conroy-Windermere Road for boat ramp parking. This lot is approximately 1,900 feet from the boat ramp. Boaters must unload their boats at the ramp, moor the boats, drive to the lot to park their vehicles and trailers, then walk the 1,900 feet along Conroy-Windermere Road back to the place where they left their boats. The sidewalk along Conroy-Windermere Road does not extend the full 1,900 feet between the Lake Down ramp and the vacant lot. For about 300 feet of the trek to and from the ramp, people must walk on the roadside grass. Orange County leases the vacant lot from Windermere Property Holdings. The term of the lease expires on January 15, 2001. The lease also provides that either party may terminate it by providing 60 days written notice. Absent this lease, Orange County would have no provision for parking vehicles and boat trailers anywhere remotely near the Lake Down ramp. A further problem with the public ramp at Lake Down is that the only access channel from Lake Down to the remainder of the Butler Chain is through Wauseon Bay. The Wauseon Bay channel runs under a low vehicular overpass, which prevents access for all but the smallest boats from Lake Down to the other lakes in the chain when the water level is too high or too low. Thus, there are times when the general public has boating access only to Lake Down, the northernmost lake in the Butler Chain. There are other boat ramps on the Butler Chain, but none of these is available to the general public of Orange County. The Orlando Utility Company owns a private ramp on Lake Down. The Town of Windermere owns a public ramp, but allows its use only by residents of the Town of Windermere. The Sportsman’s Club owns a ramp on Lake Sheen, but access is limited to club members. There is a private ramp on Lake Tibet-Butler at the Bay Hill Lodge, with a fueling system, a marina, and a mooring facility. The Isleworth Country Club owns a recently permitted ramp on Lake Tibet-Butler. THE KEENE'S PARK AND BOAT RAMP SITE The limited public access to the Butler Chain led the Orange County Board of County Commissioners to pursue a policy of obtaining multiple access sites on the Butler Chain. The Keene's Park site, on approximately 52 acres of property owned by Orange County, was the Board’s first choice. The site of the proposed R.D. Keene boat ramp is located within an abandoned citrus grove. While the site was being used as a citrus grove, a canal was constructed from Lake Isleworth to the adjacent uplands to provide a source of water for irrigation. The proposed ramp would be located within this previously excavated canal, which is deep enough to permit navigation out into the lake without running over shallow areas and with minimal potential for turbidity. Also on the site was a pump house for a diesel powered pump that was used for irrigating the citrus grove. A site inspection indicated that there was soil contamination caused by a fuel leak from the pump house. At the request of the Florida Department of Environmental Protection (“DEP”), Orange County removed the pump house and performed environmental remediation on the site, including the removal, incineration and replacement of 21 tons of soil. DEP issued a Site Rehabilitation Completion Order on February 15, 1995, indicating that Orange County had fully remediated the on-site contamination. On May 19, 1994, Orange County submitted to the District a Joint Application for Works in the Waters of Florida. The Surface Water Application was numbered 940519-1, and the Dredge and Fill Application was numbered 940519-1-D. The District sent Requests for Additional Information as to both permits to Orange County on August 24, 1994, and Orange County submitted its responses to December 6, 1995. The District sent further Requests for Additional Information to Orange County as to both permits on January 12, 1996, and Orange County responded to both requests on November 6, 1996. On or about November 7, 1996, Orange County converted its Surface Water and Dredge and Fill Permit Applications to an ERP Application. The District issued an ERP Staff Review Summary on December 26, 1996; an Amended ERP Staff Review Summary on October 30, 1997; and a Second Amended ERP Staff Review Summary on February 13, 1998. In each of the Staff Review summaries, District staff recommended that the proposed permit be issued, subject to attached general and special conditions. THE PROPOSED BOAT RAMP The proposed R. D. Keene boat ramp consists of a 30-foot wide boat ramp, two 6-foot wide concrete walks, one floating dock designed to accommodate the handicapped or anyone else who has difficulty getting in or out of a boat, and a mooring system allowing boats to queue for use of the ramp. No boat slips or fueling facilities are proposed for the boat ramp. The installation of the boat ramp will utilize the Tedder Boat Ramp System, which minimizes the amount of dredging and filling required during construction by placing a factory precast concrete slab directly onto the lake bottom, eliminating the need for dewatering during installation. The ramp will be a double ramp, allowing two boats to load or unload simultaneously. The Tedder System is the latest technology in boat ramps. The ramp will be beneath the boats as they get on and off the trailer, minimizing turbidity even if boats “power load,” i.e., use their engines to push the boats on and off the trailer, as opposed to manually cranking the boat on or off the trailer. In any event, power loading will be prohibited at the R.D. Keene boat ramp. This proposal contrasts with the public ramp at Lake Down, where there is no prohibition on power loading and where the boats load and unload directly over the lake bottom, creating the potential for turbidity. During construction of the R.D. Keene ramp, hay bales and a silt fence will be used to protect against erosion, and two turbidity barriers will be used to isolate turbidity caused by the construction. The erosion control devices will be placed landward of an average 25-foot upland buffer zone. The queuing system will be approximately 230-feet long to prevent shoreline mooring and to provide temporary facilities for waiting boats if the ramp is in use. A post and cabling system will be run along the line of vegetation on the northeast side of the proposed ramp, allowing boats to moor in the vicinity of the ramp. Petitioners correctly state that this queuing system, located on the west side of the ramp, will not prevent shoreline mooring on the east side of the ramp. However, Orange County more credibly contends that there is no reason for boaters to moor in the vegetation on the east side. The queuing system will permit 20 to 30 boats conveniently to moor in the vicinity of the ramp. The queuing system is on the west side of the ramp, as is the parking lot. Dale Mudrak of Orange County credibly testified that the queuing system is sufficient for the anticipated use of the ramp, and there will be no need for boaters to moor in vegetation, as they are forced to do at the Lake Down ramp. Boaters have been forced to improvise at the Lake Down ramp due to the paucity of amenities. Petitioners are wrong to assume that boaters will continue these improvised behaviors at the R.D. Keene ramp, a facility that will provide such basics as a place to moor and to park boat trailers. Pursuant to the special conditions of the District’s Staff Review, absorbent booms will be installed on each side of the boat ramp to absorb oils, greases, and petroleum-based byproducts. Each section of the boom is 10 feet long, five inches in diameter, and, according to the manufacturer’s specification, capable of absorbing six to nine gallons of petroleum-based liquid. Between six and eight booms will be in place at any given time, enough to contain small oil spills at the boat ramp. Randall Armstrong of Phoenix Environmental opined that these booms will be inadequate because they will absorb only those pollutants, particularly hydrocarbons, which they come in contact with on the surface of the water. Mr. Armstrong testified that pollutants farther down in the water column will not be absorbed by the booms, rendering the booms ineffective. Mr. Armstrong’s opinion is not credited, because it assumes that Orange County must guarantee that the booms will absorb all water-borne pollutants in the vicinity of the proposed boat ramp. Having the booms in place will obviously be preferable to not having them in place. If the booms work well, as Orange County has credibly testified they will, it is unreasonable to criticize them because they will not work perfectly. Pursuant to the special conditions of the District's Staff Review, an oil-spill emergency response kit will be maintained at the ramp site at all times. Park staff will be trained in proper use of the emergency kit. Contact numbers will be posted at the site for use by the public, should a spill occur when park personnel are not present. In case of a fuel or oil spill, park personnel are required to take immediate measures to notify the appropriate emergency response agency. The construction of the proposed boat ramp utilizes suitable technology for all stationary installations, including those created for drainage, flood control, or by dredging or filling. The parties agree that the storm water management system and the surface water management system for the project meet all applicable criteria for issuance of the ERP, and that the facility will have no adverse wetland impact. Deed restrictions between Orange County and the predecessor title holder of the property limit the number of boat trailer parking spaces to fifty (50) or fewer at all times for the entire 52-acre site. A total of 50 parking spaces are proposed for construction: 47 regular vehicle trailer spaces, two (2) handicapped spaces, and one space for staff. Posts with cabling will be constructed along the entrance roadway and parking areas to prevent parking of boat trailers in undesignated areas. Signage will also indicate that parking along the driveway and main access road is prohibited. Access to the proposed ramp will be limited to daylight hours. The R.D. Keene Park will be locked at night to prevent public access. Petitioners assert that Orange County has not and cannot guarantee that only 49 boats will enter Lake Isleworth from the ramp at any one time, citing the fact that Orange County does not control access to the ramp by way of Chase Road, which is the access road to the R.D. Keene Park. Petitioners speculate that boaters may park their trailers along Chase Road, causing an excess of 49 users of the ramp at a given time. Absent more than speculation, Petitioners’ assertions cannot be credited nor can Orange County be held at fault for failure to anticipate these remote possibilities. Petitioners are once more observing the improvised behaviors at the Lake Down ramp and assuming they will carry over to the R.D. Keene ramp, even though the latter will have adequate parking adjacent to the ramp. Petitioners also cite the fact that Orange County’s construction plans do not include fencing on the south side of the park to prevent pedestrian access from the Keene’s Pointe subdivision. Petitioners speculate that boaters will put their boats in at the R.D. Keene ramp, park their trailers somewhere in that subdivision, then walk back to the ramp to take their boats out on the lake. Again, Petitioners contend this operates to negate Orange County’s assurances there will be only 49 users of the ramp at a given time. Again, these speculations cannot be credited as facts nor can Orange County be found at fault for failure to anticipate these remote possibilities. Petitioners provided no evidence that this ramp will be so overwhelmed with boaters that the overflow will pour out into the nearby neighborhoods. The boat ramp will be staffed by personnel from the Orange County Parks and Recreation Department. Orange County staff will not be present at all times the boat ramp is open. Orange County has made no commitment to have staff present during all hours of weekend operation. Christi Flood, Manager of the Orange County Parks and Recreation Department, testified that full-time staff will be present on predictably busy weekends. Petitioners contend that the lack of staff present at the ramp during all hours of operation means that Orange County cannot prevent: power loading or unloading; draining, cleaning or washing; discharging of bilge pumps or popping of drain plugs into the water; shoreline mooring or disturbance of shoreline vegetation; fueling at the ramp; watercraft over 27 feet; boats with antifouling paint; or use of the facility by watercraft without permits. However, Petitioners failed to offer hard evidence that the patrols proposed by Orange County will not reasonably enforce the park rules, or support for their assumption that users of the boat ramp will ignore the park rules when staff is absent. Orange County could not guarantee perfect compliance with every rule, even with the full-time staff that Petitioners seek. Orange County staff will be empowered to enforce the park rules with citations, which would include fines or revocation of the privilege to use the boat ramp. Parking restrictions will be enforced by the Orange County Sheriff’s Department. The Butler Chain of Lakes is patrolled by other agencies, including the Florida Game and Fresh Water Fish Commission, Orange County’s Environmental Protection Department, the Windermere Navigational Board, and the Marine Patrol. The special conditions of the District’s Staff Review require Orange County to implement an Operational Plan, the terms of which have been specifically set forth by Orange County in its submissions to the District. To use the ramp, a boater must fill out a Day Use Permit stating that the boater will abide by the park’s rules, and pay a fee. All conditions of the Operational Plan are included in the Day Use Permit. Permitting will be done on the honor system when Orange County staff persons are not actually present. Blank permit forms will be left at the ramp. Boaters will fill out the forms, place their money in an envelope to be deposited in a secure tube provided at the site, then display the permits on their car dashboards while parked at the ramp. Ms. Flood testified that no more than 49 permits will be issued at a given time. A trailer carrying multiple watercraft will be required to obtain a permit for each watercraft. Ms. Flood conceded that more than 49 permits could be issued over the course of a day, as boats come and go from the ramp. As stated in the Operational Plan and the Day Use Permit, the following rules will apply to all watercraft launching at proposed boat ramp: No power loading or unloading. No draining, cleaning or washing at the ramp. No discharging of bilge pumps and opping of drain plugs at the ramp or in the water. No anchoring or parking along shoreline and no disturbance of shoreline vegetation. Use designated queuing system while waiting for ramp availability. No littering. All "No wake" areas must be obeyed (including the No Wake Zone within 100 feet of shoreline, as mandated by Orange County ordinance). No fueling allowed at the ramp for any watercraft. No watercraft over 27 feet will be permitted. No boats with antifouling paint will be permitted. No overnight mooring. The R.D. Keene Park will be closed if the water level falls below 97-feet. Dale Mudrak, the Program Development Supervisor in the Planning and Design section of the Orange County Parks and Recreation Department, testified that 97 feet was chosen to ensure that boats would not use the ramp when the water is too low. Mr. Mudrak stated that when the water elevation is at 97 feet, there is 5-feet of water at the ramp, but only 3-feet of water in the shallow canals leaving Lake Isleworth. He testified that the Windermere Navigational Board recommended closing the ramp when the level reaches 96 feet, but that Orange County conservatively decided to add 1-foot to the recommendation. WETLAND IMPACTS AND MITIGATION The project is expected to result in 0.07 acres of secondary wetland impacts (removal of littoral zone vegetation) above that required for construction. A total of 0.14 acres of wetland impacts will occur from direct construction and secondary wetland impacts. Mitigation for the 0.14 acres of wetland impact includes 0.56 acres of wetland creation. The wetland creation areas are divided into three separate zones (A, B, and D). Both forested and herbaceous species will be planted in each area. The forested species include cypress, red maple, sweet bay, water oak, swamp bay and dahoom. The herbaceous species include soft rush, maidencane, cordgrass, sawgrass, duck-potato, pickerel-weed, and buttonbush. Approximately 1.61 acres of wetland preservation is also provided as mitigation. Pursuant to the special conditions of the District's Staff Review, Orange County will provide a conservation easement. The conservation easement will be placed over the preserved wetlands, mitigation area, and upland buffer zones and deeded to the District. A total of 2.90 acres will be placed under this conservation easement. Elimination and reduction of wetland impacts has been demonstrated. Adverse impacts to aquatic dependent species from wetland impacts are not expected, because the values and functions provided by the proposed mitigation outweigh the wetland loss. AMBIENT WATER QUALITY Orange County has an extensive water quality monitoring program, and has accumulated historic water quality data for over thirty years, including a broad range of physical, chemical and biological parameters, for the Butler Chain of Lakes. In its application, Orange County provided site- specific water quality, sediment, and macroinvertebrate samples. The water quality parameters sampled include four categories: physical properties, inorganics, organics, and microbiology. Orange County also provided historic water quality data for a period of ten years (1984-1994) for Lake Isleworth, Lake Louise (the immediate upstream waterbody), and Lake Tibet-Butler (the immediate downstream waterbody). This data included the year Lake Isleworth was designated as an OFW in 1984 and the year prior to submission of the ERP application. Linda Jennings, the Laboratory Supervisor for the Orange County EPD, testified that the historical data demonstrated that the water quality in the Butler Chain of Lakes has been excellent since at least 1983 and remains so today, even with development and boating steadily increasing over that period. The historical data show some small variances attributable to seasonal and cyclical fluctuations, but no long- term deterioration of water quality in the Butler Chain, despite the heavy recreational use of those lakes during the period in question. The historical water quality data provided by Orange County in this case is far better than is usually submitted to an agency during the application process, even for those projects located in OFWs. This historical data allowed the District to make a more informed decision than usual regarding the long term status of the water quality of the Butler Chain. Orange County provided water quality data for those parameters showing the general water quality, and for those parameters specifically related to boat ramp activity, such as Polynuclear Aromatic Compounds, discussed in more detail below. The historic water quality data demonstrates there have been no major changes in water quality over the ten-year period of record and that, if there is any trend at all, it is a trend toward improved water quality. The water quality of Lake Isleworth and the Butler Chain of Lakes is excellent and has maintained its superior quality since 1983. ORANGE COUNTY’S PAH DATA Orange County provided water quality data from October 1997 and January 1998 for Lake Sheen, Lake Isleworth and Lake Down. Orange County collected and analyzed numerous water and sediment samples for Polycyclic Aromatic Hydrocarbons (“PAHs”), also called Polynuclear Aromatic Compounds, which are compounds found in gasoline and other petroleum products. The presence of PAHs in the water indicates the presence of petroleum products in the water. Starting on October 14, 1997 and continuing through October 20, 1997, Orange County EPD took 84 water samples on seven consecutive days at twelve stations: at the ramp, east edge, and center of Lake Down; at the west edge, center, and east edge of Lake Isleworth; at the ramp, center, and west edge of Lake Sheen; and at the ramp, center, and east edge of Lake Conway, a heavily used Orange County lake outside of the Butler Chain. Orange County EPD also took 28 sediment samples, representing a total of 84 sediment samples, at each of the twelve stations for seven consecutive days, taking composites of the three sites in each of the four lakes: Lake Down, Lake Isleworth, Lake Sheen and Lake Conway. An independent laboratory, Bottorf Associates, Inc., analyzed each of the 84 water samples and the 28 composite sediment samples for 16 different PAH parameters, including naphthalene. This represents a total of 112 samples and a total of 1,792 different PAH tests. Environmental testing laboratories are required by the Florida Department of Environmental Protection to file a comprehensive quality assurance plan (“QAP”) for all field and lab procedures they perform. Among the data included in the filed QAP is a statement of the method detection limit ("MDL"), the lowest level of a particular compound that the laboratory can report on a continuing basis using a particular form of test and a particular piece of equipment, with 99 percent confidence that the value is above zero. The MDL is arrived at by assessing the U.S. Environmental Protection Agency (“EPA”) testing method being used, in conjunction with the particular instrument and the abilities of the analyst, with the goal of stating an MDL that can be achieved on a daily basis in the ordinary operations of the laboratory. The MDL can also be described as that level below which the laboratory cannot be certain whether it is reporting accurate values or whether it is reporting background noise in the sample. The laboratory results reported by Bottorf Associates, using EPA Test Method 610 for PAHs, indicated that every reading for every parameter tested was below the MDL for the following array of PAHs (MDLs are stated in micrograms/liter): Acenaphthene 1.4 Acenaphylene 3.4 Anthracene 4.2 Benzo(a)anthracene 4.0 Benzo(a)pyrene 0.2 Benzo(b)fluoranthene 3.9 Benzo(ghi)prylene 10.0 Benzo(k)fluoranthene 4.0 Chrysene 4.0 Dibenzo(a,h)anthracene 6.8 Fluoranthene 1.7 Fluorene 3.0 Indeno(1,2,3-cd)pyrene 7.5 Naphthalene 1.4 Phenanthrene 1.2 Pyrene 2.4 Orange County’s test results indicated that, as a practical matter, there were no PAHs at any of these locations on the days of testing. In January 1998, Orange County EPD took additional water samples at the following 10 sites: the ramp, east edge, and center of Lake Down; the west edge, center, east edge, and future ramp site on Lake Isleworth; and the ramp, center, and west edge of Lake Sheen. The 10 water samples were tested for 13 different PAH constituents, including naphthalene. All of the constituents tested in January 1998, were below the MDL, confirming the testing done in October 1997. Orange County EPD’s result sheets from the January 1998, sampling included qualifier identifier codes to show that the data was being reported at a level below the MDL. Essentially, the codes indicate that no PAHs could be detected even at a level of one-half the MDL on file with DEP. Orange County’s data indicates that neither the water nor the sediments at Lake Down, which has had a public boat ramp for decades, show any reliably detectable levels of PAHs. Orange County’s data indicates that neither the water nor the sediments from Lake Sheen, which has a boat ramp for a membership club with a fueling facility and dock, show any reliably detectable levels of PAHs. Orange County’s data indicates that neither the water nor the sediments from Lake Conway, which has a heavily used boat ramp, show any reliably detectable levels of PAHs. PETITIONERS’ PAH DATA Petitioners introduced a study performed by Mote Marine, a state certified research laboratory, assessing the levels of hydrocarbon contamination associated with boat launching and loading activities at the Lake Down and Lake Sheen boat ramps. Specifically, Mote Marine sampled for naphthalene, one of the PAHs that is an indicator of petroleum discharges into the water body. Mote Marine collected water samples at the boat ramp, the opposite shoreline, and the center of Lake Down and Lake Sheen. Mote Marine also collected water samples at the site of the proposed boat ramp and near a canal on Lake Isleworth. All of these samples were taken during Labor Day weekend, between August 31 and September 4, 1995. Mote Marine’s QAP indicates that its MDL for naphthalene under either EPA Method 625 for Base/Neutrals and Acids or EPA Method 610 is two micrograms per liter. Mote Marine employed EPA Method 625. Orange County used EPA Method 610. The values for naphthalene reported by Mote Marine were expressed not in terms of micrograms, but in terms of nanograms. A nanogram is one-thousandth of a microgram. Of the 72 individual water samples collected by Mote Marine at Lake Down, Lake Sheen, and Lake Isleworth over the 1995 Labor Day weekend, only one registered a naphthalene concentration above the two micrograms per liter MDL in Mote Marine’s QAP. The majority of the measurements were reported as less than 10 nanograms per liter. Dr. Richard Pierce, the Director of Research at Mote Marine, testified that the QAP on file at DEP is a broad based plan encompassing all the various analyses performed by the laboratory, in effect a “worst case scenario” setting a high MDL that is easy to meet in all cases. Dr. Pierce also testified that DEP and the U.S. EPA allow a laboratory to vary from its filed MDL on specific projects, and that his laboratory was able to establish an MDL of six nanograms per liter for this particular project. Dr. Pierce testified that three major factors are involved in establishing a project specific MDL. The first factor is how “clean” the sample is, i.e., how many interfering compounds are present that may elicit a response from the detector being used. The second factor is the quality of the instrumentation, and the third is the skill of the analytical chemist performing the analysis. Dr. Pierce’s factors coincide with the factors listed by Ms. Jennings of Orange County as to the considerations involved in establishing a comprehensive MDL. Mote Marine did not file a Quality Assurance Project Plan for this project. Dr. Pierce testified that such a filing was not required in order to apply a lower MDL for this project. Orange County contended that such a filing was necessary, but offered no specific reference to a rule that would have required Mote Marine to file a Quality Assurance Project Plan under these circumstances. The undersigned could discover no DEP rule that unequivocally would require the filing of a Quality Assurance Project Plan for the activities conducted by Mote Marine. Thus, Dr. Pierce’s expertise as Director of Research is credited and it is accepted that Mote Marine could establish a project specific MDL in this instance, and properly did so. A chart in the Mote Marine report, purporting to show the average naphthalene concentrations in the subsurface water as determined by Mote Marine’s sampling, contained several inaccuracies. The chart stated that the measurements were being reported in terms of micrograms, when in fact the numbers represented nanograms. In two places, the average concentrations were miscalculated, either because the correct factors were not included or due to simple mathematical error. The Mote Marine report also provided no information on the actual locations of the testing sites in terms of latitude and longitude, thus making it difficult if not impossible to check or repeat the sampling. The problems with methodology and with simple calculations make it difficult confidently to rely on the Mote Marine report as regards naphthalene. However, even if the Mote Marine report had been impeccably accomplished, its results would not establish a definite correlation between naphthalene contamination and boating activities. Petitioners assume that the concentrations of naphthalene that Mote Marine found in the vicinity of the Lake Down and Lake Sheen boat ramps are attributable to boating activity, ignoring the fact that neither of these boat ramps has a storm water management system. Both the Lake Down and Lake Sheen ramps directly adjoin roads, and have no buffering system whatever for storm water runoff from those roads. There was rain on the Butler Chain during the Labor Day weekend of 1995, when Mote Marine took its samples. In fact, a tropical depression had only recently passed through the Orlando area. Dr. Pierce could not determine the relative input of contaminants from automobiles and from boats. Dr. Pierce had no opinion on whether the amount of naphthalene found by his laboratory is environmentally or ecologically significant. Dr. Pierce had no opinion as to whether hydrocarbon contamination is degrading the water quality of Lake Down. Randall Armstrong, a consultant with Phoenix Environmental, opined that the reported naphthalene levels would degrade the water quality, but admitted that he was not an expert in chemistry and was ignorant of Mote’s methodology. Even accepting all of Petitioners' assertions as accurate, it cannot be found that the proposed R.D. Keene ramp and its surface water management system would lead to the introduction of petroleum products into the water column in amounts sufficient to degrade the water quality. Dr. Douglas Durbin, a Senior Ecologist with Biological Research Associates and an expert in lake ecology, defined degradation of water quality as a negative and permanent change in the ecological or recreational status of a water body. Dr. Durbin testified that, even if the Mote Marine data were accurate and reliable, those levels of naphthalene were lower by at least two orders of magnitude than levels that could potentially affect even the most sensitive organisms, as those affective levels have been established by the United States EPA. This is not necessarily the standard for determining degradation, but is indicative that the levels of naphthalene under discussion are infinitesimal. Mr. Armstrong of Phoenix Environmental contended that the impact to water quality by an activity need not be permanent in nature or even ecologically significant in order to violate the water quality standards of the District. Mr. Armstrong's rationale is that any "measurable" lowering of the water quality of the OFW violates the rules, even if that measurement must be accomplished in nanograms and cannot be shown to have any effect whatever on any of the biota of the water system. This rationale would essentially shut down all new activities on OFWs, and is at odds not only with the District's interpretation but with the views expressed by Mr. Armstrong himself on other projects. Dr. Durbin's opinion regarding the nature of degradation is credited over that of Mr. Armstrong. WATER QUALITY MODELING AND IMPACT OF THE PROJECT After establishing the ambient water quality, Orange County performed water quality modeling to determine if the ambient water quality would be lowered by the construction and operation of the boat ramp. The number of boat ramp users will vary based on various factors including temperature and day of the week. The ramp is sized for 144 launch events per day, meaning that a maximum of 72 boats could use the ramp on a given day. Mr. Mudrak testified that the ramp was sized so that parking, not the size of the ramp, will be the limiting factor in ramp usage. The ramp will have 50 parking spaces, one of which will be reserved for Orange County staff use and two of which will be designated for handicapped use. Robert Robbins, the District’s permitting expert, testified that the District’s analysis generally concerns a determination of the amount or rate of input of pollutants that a lake can assimilate without exceeding its assimilation threshold, i.e., lowering the ambient water quality. Mr. Robbins further testified that this determination was unnecessary here because the District found a negative answer to a threshold question: would a boat ramp and 50 boat parking area under any circumstances exceed the assimilation threshold? As part of a grant project that involved a water quality model and water management study, Parsons Engineering Science, Inc., collected data on the geometric characteristics of the lakes, the topographic and ecological characteristics of the basins, and the existing land uses to develop a hydrodynamic and water quality model of the Butler Chain of Lakes, hereafter referred to as the “BCL model.” The BCL model provided a conservative hydrodynamic analysis of the rate of input and dilution of pollutants, and indicated that there is no potential for the accumulation of pollutants in the Butler Chain of Lakes as a result of the project. Parsons Engineering considered the chemical and physical properties of the gasoline constituents and ran the BCL model using the pertinent chemical and physical parameters. The BCL model took into consideration volatilization and adsorption of hydrocarbons from the water. In an effort to reach a conservative result, the BCL model did not include the loss of gasoline constituents through biodegradation or photolysis, processes in which the hydrocarbons dissipate over a longer period of time. The BCL model predicted that no accumulation of gasoline constituents, including naphthalene, would occur in Lake Isleworth at a level equivalent to the expected daily usage of the proposed boat ramp, an average of 25 boats per day. The BCL model predicted that no accumulation of gasoline constituents, including naphthalene, would occur at a constant level of 77 boats using the proposed ramp every day, triple the expected daily usage and five boats more than the capacity of the proposed ramp. At a level equivalent to the expected daily usage, the BCL model predicted that the daily concentration of the PAHs benzene, toluene and naphthalene, would be below the laboratory detection limits. At a level that is triple the expected daily usage, the BCL model predicted that the daily concentration of the PAHs benzene, toluene and naphthalene would be below the laboratory detection limits. In summary, the BCL model predicts that even if the proposed ramp had a capacity of 77 boats per day rather than 72, and if 77 boats were served by the ramp every day of the year, rather than the actual anticipated average of 25 boats, there would be no degradation of water quality caused by introduction of hydrocarbons into the water of Lake Isleworth. Dr. Kenneth Echternacht, a consultant engineer with Phoenix Environmental, also performed a hydrographic study to determine flushing patterns for Lake Isleworth in the vicinity of the proposed boat ramp. Dr. Echternacht testified that, without good flushing, continuous loads of pollutants will build in the water body, lowering water quality. “Flushing” is the time required to reduce the concentration of a “conservative” pollutant to ten percent of its original concentration. A conservative pollutant is one that does not erode, decay, or go through any biological update process. Dr. Echternacht testified that standard engineering practice in Florida is to assume that a flushing time in excess of four days will result in the accumulation of materials. Section 4.2.4.3 of the Basis of Review states that a four day flushing time is “desirable” for docking facilities. The project at issue is not a "docking facility" as that term is used in Section 4.2.4.3, hence there is no requirement or preference in law for a four-day flushing period. Dr. Echternacht’s study concluded that the minimum flushing time for the proposed boat ramp on Lake Isleworth will be 26 days. Dr. Echternacht’s study was limited to a strict one- dimensional appraisal of the physics of Lake Isleworth. Dr. Echternacht professed no expertise in chemistry, and he did not take into account the chemical properties of the pollutants at issue in this proceeding. He assumed that the pollutants would be “conservative,” when in fact petroleum constituents are volatile, and will disappear through volatilization, adsorption, biodegradation, and photolysis. Petitioners failed to establish any connection between Dr. Echternacht’s flushing analysis and the Mote Marine study on PAHs. Dr. Echternacht’s analysis is thus of little practical significance, because no evidence was adduced to show that a 26-day flushing time will result in the accumulation of PAHs and a degradation of water quality, when the PAHs are introduced in the nanogram amounts reported by Mote Marine. The Lake Down ramp has been heavily used by the public for many years, directly adjacent to a reasonably busy road and without any surface water management system, and still the only traces of naphthalene found by any laboratory were measured in nanograms, with no indication that these pollutants will accumulate when introduced in those trace amounts. In summary, the evidence regarding naphthalene concentrations is insufficient to establish that the proposed R.D. Keene ramp will have any adverse effect on the water quality of Lake Isleworth specifically or the Butler Chain generally as regards petroleum contamination. TURBIDITY At the same time they collected water samples regarding PAHs, both Orange County and Petitioners collected turbidity samples. Turbidity is a means of quantifying particular matter in water that absorbs light or otherwise keeps light from passing through the water. It may have natural causes, such as phytoplankton cells or erosion after a storm, or it may be caused by human activity in or adjacent to water bodies. Turbidity is measured in nephelmetric turbidity units, or “NTUs.” The historical water quality data shows a turbidity range of 0.3 NTUs to 2.2 NTUs for Lake Isleworth. These are low levels of turbidity, indicating very clear water in Lake Isleworth. Dr. Durbin testified that natural turbidities can run into the hundreds or even thousands of NTUs, depending on what is happening in the watershed, and that turbidity is not considered a problem until it reaches levels at which there is some effect on the organisms that live in the system. Both Dr. Durbin and Ms. Jennings testified that, in assessing measurements in NTUs, the numbers to the right of the decimal are unreliable; in other words, a measurement of 2.0 NTUs should be considered as virtually identical to a measurement of 2.40 or 2.80 NTUs. In the period from October 14 through October 20, 1997, Orange County took turbidity samples from Lake Down (east edge, center, and boat ramp area), Lake Isleworth (west edge, east edge, and center), Lake Sheen (west edge, center, and boat ramp area), and Lake Conway (east edge, center, and boat ramp area). Seven samples were taken at each location, making a total of 84 turbidity samples. The highest individual measurement was 5.40 NTUs, measured at the Lake Down boat ramp on October 15. This is itself a low level. Dr. Durbin testified that no concerns are raised until turbidity measurements reach 30 NTUs, and that short-term measurements in the hundreds or even thousands of NTUs may cause no harm to the biota of a system. Further, in fewer than 24 hours this measurement of 5.40 NTUs had settled out to a measurement of 1.60 NTUs. None of the other 83 measurements even reached the level of 2.0 NTUs, all within the historical background turbidity range for the Butler Chain of Lakes. No increase in turbidity can be traced to boating activity in the October 1997 sampling. The samplers’ field notes indicate whether and how much boating activity was occurring as the samples were being taken, and no causal connection can be drawn between boating activity and turbidity. Orange County EPD took further turbidity samples on January 23, 1998. These samples were taken in the Wauseon Bay canal, and were an effort by Orange County to deliberately follow in the wake of boats and obtain the maximum possible amount of turbidity. None of the 8 measurements taken in this sampling showed turbidity in excess of the background turbidity, considering Ms. Jennings undisputed testimony that NTUs may be reliably measured only in whole numbers. The measurements taken in the wake of boats ranged from 1.18 NTUs to 1.71 NTUs, as compared with background measurements ranging from 1.05 NTUs to 1.13 NTUs. Phoenix Environmental, in conjunction with Mote Marine, took turbidity samples at the Lake Down boat ramp during the Labor Day weekend of 1995. These samples indicated background turbidity from 1.2 NTUs to 2.5 NTUs, and showed turbidity spiking to levels as high as 29.0 NTUs during extensive launching activity, particularly when the boat operators used the “power loading” technique discussed above. “Power loading” will be prohibited at the proposed R.D. Keene ramp. Further, the Tedder system would minimize turbidity even if boat operators violated the prohibition, because it would eliminate prop dredging directly on the lake bottom. As notable as the turbidity spikes in the Phoenix/Mote samples is the rapidity with which the turbidity diminished. The aforementioned measurement of 29.0 NTUs had diminished to 2.8 NTUs within eight minutes. This is consistent with the testimony of Ms. Jennings that the nature of the sediments in the Butler Chain is such that turbidity settles out very quickly. Michael Henry, a senior chemist at Mote Marine, concurred that three minutes is enough time for boat ramp sediments to clear on Lake Down. The turbidity sampling by Phoenix/Mote over the Labor Day weekend of 1995 was not conducted with an approved quality assurance and control plan. Mr. Armstrong thus made the decision that further turbidity sampling should be done, using the proper protocols. The second turbidity sampling by Mote Marine, performed on October 26, 1997, and corrected on February 13, 1998, showed values much closer to those found in the Orange County sampling. The highest properly recorded value was a reading of 6.54 NTUs at the Lake Down boat ramp, and this value settled to 1.5 NTUs within eight minutes. As to this second Mote Marine study, Orange County contends that Mote Marine used bottles for taking samples that were not laboratory cleaned, did not properly calibrate the equipment, used a blank test sample which their records indicated had expired, and improperly influenced the results of the sampling by wading out to the sample area. None of these contentions is supported by the evidence. Mote Marine ran out of laboratory cleaned bottles before it had completed sampling, and thus was required to field clean and reuse 15 bottles. The weight of the evidence is that Mote Marine properly field cleaned those bottles in accordance with the section of its filed QAP dealing with cleaning procedures for equipment not being used for trace analyses. Orange County’s criticisms might have been well taken had Mote Marine been collecting samples for naphthalene testing, but not for collection of turbidity samples. Mote Marine’s turbidity meter was bench calibrated by a senior chemist at Mote Marine about four days prior to the actual testing. Continuing calibration verification (“CCV”) was performed in the field. Mr. Henry testified that the meter was performing perfectly, and that it is acceptable practice to use a meter over several days without a bench calibration, provided it has not malfunctioned during a CCV. The weight of the evidence supports a finding that Mote Marine properly calibrated its turbidity meter. In calibrating the meter, the senior chemist employs a formazin standard, which is diluted to a specific concentration, placed in the meter and read, generating a calibration curve to which the rest of the unknown samples are calibrated. The calibration was performed on October 23, 1997, but the report prepared by the chemist indicates that two of the formazin standard dilutions used had expiration dates of April 23, 1997. Orange County contends that the use of these apparently expired formazin standards compromised the calibration and rendered unreliable the turbidity sampling conducted by Mote Marine. Mr. Henry testified that the formazin standard in question was purchased and received via express delivery on October 23, 1997, the day the calibration was conducted. The chemist performed the dilutions, which at the levels in question had a six month expiration date. Thus, these dilutions would have had an expiration date of April 23, 1998. Mr. Henry testified that the chemist simply made an error in writing down “4/23/97” rather than the correct date of “4/23/98.” Mr. Henry’s explanation is plausible and is accepted. Mote Marine did not use expired calibration blanks. Mr. Henry testified that the sampling was accomplished by wading into the water to about shin height, opening the lid to the sample bottle, stepping forward, rinsing the bottle, stepping forward again, then collecting the sample. Mr. Henry stated that this was an acceptable procedure. His presence in the water did not itself cause turbidity because sediments do not kick straight up from the bottom, and his reaching out to collect the sample eliminated any potential for collecting samples influenced by his presence. Ms. Jennings correctly pointed out that the better sampling method would involve standing on shore or in a boat and using an extension pole to take the sample, eliminating any remote possibility of taking a sample tainted by sampler-caused turbidity. However, the weight of the evidence, including the essential similarity of results for all the reliably conducted turbidity samplings introduced in this case, is that the method used by Mr. Henry did not influence the results of the October 1997 sampling conducted by Mote Marine. However, Petitioners failed to establish that the minor and very short-term elevations in turbidity found around the Lake Down boat ramp constituted a degradation of water quality, or would be repeated at the proposed R.D. Keene boat ramp. There are many distinctions between the existing Lake Down ramp and the proposed R.D. Keene ramp. The Lake Down ramp has no surface water management system. The storm water runoff from the adjacent Conway- Windermere Road and from the boat ramp itself flows directly into Lake Down in the vicinity of the boat ramp. In contrast, the proposed R.D. Keene boat ramp will provide dry retention for up to a 25-year, 24-hour storm event, so that unfiltered storm water will not reach the lake system. The Lake Down ramp has no accessory dock, which can reduce turbidity caused by boaters stirring up the bottom when climbing into the boat. The proposed R.D. Keene facility will have such a dock. The Lake Down ramp does not have a concrete ramp extending beneath the launching point to minimize dredging the bottom. The proposed R.D. Keene facility will have such an extended concrete ramp. At the Lake Down ramp, boaters must moor their boats along the shoreline while taking their vehicles and trailers to the parking lot. The proposed R.D. Keene facility will have a queuing system to prevent the erosion and turbidity caused by shoreline mooring, which will be prohibited. There is no prohibition on power loading at the Lake Down ramp, which also is not deep enough to allow boats to float easily on and off their trailers. Power loading will be prohibited at the proposed R.D. Keene ramp, and in any event will not be necessary because the depth of the water and the design of the ramp will enable boats to float on and off their trailers. In conclusion, it is found that none of the samplings taken by any of the parties in this proceeding establishes that the water quality of Lake Isleworth specifically or of the Butler Chain generally will be degraded or lessened by turbidity caused by boating activity around the proposed R.D. Keene boat ramp. SECONDARY AND CUMULATIVE IMPACTS Based on the Operational Plan, the design, the water quality sampling and modeling, the District determined that there will be no adverse secondary impacts from the proposed boat ramp or associated activity. After considering all existing boat ramps, marinas and other projects on the Butler Chain of Lakes, the District concluded that the proposed R.D. Keene boat ramp will not have an accumulation of impacts and pollutants in its home lake system and does not have the potential to contribute any cumulative impacts throughout the Butler Chain of Lakes. At the R.D. Keene Park, Orange County owns 1,780 feet of shoreline. Existing rules provide an exemption that would allow one boat dock for every 65 feet of shoreline, meaning that up to 27 exempt docks could be placed along this 1,780 feet of shoreline if it were in private hands and not subject to the conservation easement that is being granted by Orange County. 166. The water quality sampling performed in this case demonstrated that existing projects and activities have not resulted in an accumulation of impacts to the Butler Chain of Lakes. The historic water quality data demonstrate there have been no major changes in water quality over the 10-year period of record and that the trend is, if anything, toward improved water quality. The water quality is excellent and has maintained its superior quality since 1983, even though residential development and boat usage on the Butler Chain of Lakes has steadily increased over the last ten years. There is no boat ramp currently located at the property owned by Orange County on Lake Sheen. The Lake Sheen site has three homes and two docks on it at present. The District has no applications pending for similar projects that would be considered as part of the cumulative impact review. No applications for a boat ramp at Lake Sheen have been submitted by Orange County nor is there a boat ramp currently under construction at that site. No applications for a public boat ramp, other than the one at issue in this proceeding, have been submitted to the District by Orange County. The east side of the Butler Chain of Lakes is fully developed. There is no evidence of any Development of Regional Impact that would include a boat ramp for the west portion of the Chain. The zoning and land use designations of the property owned by Orange County on Lake Sheen are rural country estate on part of the property and low density residential on the other part of the property. There is no evidence that the Lake Sheen site is under review, vested or approved as a Development of Regional Impact. PUBLIC INTEREST TEST As further described in the Conclusions of Law below, an applicant for a project located in an OFW must provide reasonable assurances that the project is clearly in the public interest. The public interest test weighs and balances seven factors, as listed in the subheadings below. Extensive testimony was elicited from several expert witnesses who offered their applications of the public interest test. Anna Hacha-Long, Manager of Orange County EPD, and Pamela Thomas, Senior Environmental Specialist of Orange County EPD, both concluded that the proposed project was clearly in the public interest. Dale Mudrak, Orange County’s construction, design and project management expert, concluded that the proposed project is clearly in the public interest. Dr. Douglas Durbin, Orange County’s expert in limnology, ecology, water quality and permitting, concluded that the proposed project is clearly in the public interest. Robert Robbins, Director of the Natural Resource Management Division of the District, concluded on the District’s behalf that the proposed project is clearly in the public interest. The only expert who concluded that the project is not in the public interest was Randall Armstrong of Phoenix Environmental. PUBLIC HEALTH, SAFETY, WELFARE OR PROPERTY OF OTHERS The parties stipulated that the proposed boat ramp facility will not adversely affect the public health. The proposed ramp will improve public safety as follows: The proposed ramp, centrally located in the Butler Chain, will provide quicker access for emergency rescue in the case of injuries to boaters or skiers. The proposed ramp should somewhat alleviate the traffic concern at the Lake Down ramp by shifting some traffic away from the Lake Down ramp. The proposed ramp will enhance public welfare by: increasing the recreational opportunities to the Butler Chain of Lakes; allowing access to the Butler Chain of Lakes by handicapped and disabled individuals; and the clean up of diesel fuel contamination that Orange County has already performed on the site. Orange County EPD performs extensive aquatic plant management activities on the Butler Chain, including spraying for harmful exotic plants. If Orange County were to lose access to the Butler Chain -- a real possibility should the proposed project not be built and the lease for parking at the Lake Down ramp expire -- it could also lose public grant money for aquatic plant management. The proposed project will not impact the property of others because: Orange County owns the land on which the ramp will be built, and the State of Florida owns the water into which the boats will be launched. Orange County EPD has received no complaints from property owners related to the existing use of the Butler Chain of Lakes by boaters. No-wake zone regulations prohibit high speed boating activities within 100 feet of the shoreline, protecting boaters and the property of adjacent landowners. The area is extensively regulated by both the Butler Patrol and full-time Orange County EPD staff. The canals connecting the lakes are wide enough that there will be no safety problems related to boating through the canals. CONSERVATION OF FISH AND WILDLIFE, INCLUDING ENDANGERED OR THREATENED SPECIES, OR THEIR HABITATS Orange County is providing 0.56 acres of mitigation by way of wetland creation, which offsets not only the 0.07 acres of direct wetland impact from construction and 0.07 acres of secondary impacts caused by removal of littoral zone vegetation, but also the District’s doubling of the usual two-to-one mitigation ratio for wetlands impacts. The District doubled the usual mitigation ratio as a conservative measure to account for the slight possibility of boats disturbing the area in the vicinity of the boat ramp. The parties have stipulated that the proposed boat ramp facility will not adversely affect the conservation of endangered species or their habitats, will not affect the conservation of threatened species or their habitats, and will not adversely impact gopher tortoises. The proposed project benefits the conservation of fish and wildlife or their habitats. Some habitat will be impacted by the construction of the boat ramp, but Orange County is providing mitigation many times larger than the area being developed, and is placing 1.61 acres of wetlands under a conservation easement to ensure that the land cannot be altered from its natural state. A total of 2.90 acres of wetland preservation, wetland creation, and upland buffer areas will be placed under conservation easement. Thus, habitat will enjoy a net enhancement from the project. Multiple evaluations of plant and animal parameters in the ecosystem led the District reasonably to conclude that the increase in habitat and habitat diversity due to the mitigation and conservation easements will provide net benefits to wildlife. The proposed boat ramp and associated activity will not cause any negative impacts on fish and wildlife and their habitats, except for the unavoidable immediate impacts caused by the footprint of the ramp itself. As described above, these impacts are addressed in Orange County’s mitigation plan. Orange County EPD has not seen a decline in fish populations, nor any fish kills, nor any type of damage due to increased turbidity from natural or man-made causes in the Butler Chain of Lakes. It is reasonable to find that this project is unlikely to lead to such impacts. NAVIGATION OR FLOW OF WATER OR HARMFUL EROSION OR SHOALING The parties have stipulated that the proposed boat ramp and associated activities will not adversely affect the flow of water. There is no evidence of harmful erosion or shoaling from the existing boat traffic, even though the traffic has steadily increased over the years. Orange County EPD has not seen sand bar formation or erosion at first hand, nor has it received complaints about erosion. Orange County has not been required to dredge the canals interconnecting the lakes since the 1980s. The proposed project will not cause harmful erosion or shoaling because the dimensions of the canals are sufficient for boats to pass, and the edges of the canals are well vegetated. Mr. Armstrong's contrary testimony, based on a single visit to the Butler Chain over the past ten years, is not credited. It is reasonable to believe that the ramp will reduce traffic through the canals by providing a public point of access that is more centrally located than the current one at Lake Down. Boaters will be able to enter the Butler Chain at a point nearer their intended destination. At the very least, the flow of boating traffic should be more evenly distributed, as all boats entering the Butler Chain will no longer be forced to proceed through the canals connected to Lake Down. The main cause of harmful erosion on the Butler Chain is residents’ failure to use turbidity or erosion barriers when they pull up aquatic or semi-aquatic plants along the shoreline. This project is thus unrelated to the true causes of turbidity in the Butler Chain. The proposed project is designed and will be managed to minimize the potential for dredging or erosion from boat propellers, as follows: The boat ramp itself is designed to accommodate two boats launching simultaneously. The boat ramp has adjacent docks and structures so that boats can raft to these structures during launching and loading, rather than running into the shoreline or tying to vegetation. The proposed project will also have a 230-foot long queuing system for mooring boats on the west side of the ramp. The queuing system will also act as a barrier to prevent boaters from using the shoreline to access their vehicles. The Operational Plan prohibits power loading and unloading, minimizing the potential for erosion at the ramp. Officer Jeffrey Hudson of the Florida Game and Fresh Water Fish Commission and the Windermere Water and Navigational Control District, regularly patrols the Butler Chain of Lakes. He foresees no navigational problems arising from the placement of the boat ramp, because of the no-wake zones and because people will be launching from a cove that gives them a good view of traffic in the lake before they enter. Because of the size of the Butler Chain of Lakes, there is a natural timing factor that will regulate the sequence of boaters returning to the proposed ramp. Even if a large storm arose suddenly, all the boats in the water would not arrive at the proposed R.D. Keene ramp at once because of the differing amounts of time it would take boats to arrive from their dispersed positions on the Butler Chain. The only expert witness who testified that the third factor weighed negatively against the public interest was Mr. Armstrong of Phoenix Environmental. Mr. Armstrong’s testimony that the connecting canals are too narrow for boats to comfortably pass each other is rejected as unsupported by the weight of the documentary and other testimonial evidence. Mr. Armstrong’s characterization of the potential for increased boating traffic in the southern portion of the Butler Chain as a negative factor is likewise rejected. Providing increased recreational access for the general public is one of the chief positive aspects of this project. Mr. Armstrong also expressed concern that the ramp’s location on a small, pass-through lake, and its placement therein, would mean that boats coming into or away from the ramp would be crossing directly into the path of boats passing through. Officer Hudson’s contrary testimony that the placement of the new ramp will not cause navigational or safety problems is accepted as based on superior knowledge of the Butler Chain of Lakes and greater expertise in boating and navigational safety. Mr. Armstrong testified that boat wakes would cause erosion. He testified that on his visit to the Butler Chain, he saw banks in canals undercut and roots exposed in areas where the vegetation was not heavy. As noted above, Mr. Armstrong has been on the Butler Chain once in the past ten years. Pamela Thomas of Orange County EPD, who has spent hundreds of hours studying the Butler Chain and regularly boats on the lakes in connection with her job, testified that the main cause of erosion is the clearing of vegetation by residents who wish to have beaches. Boat wakes cause few problems, particularly in the canals, because of the no-wake zones and their strict enforcement. Ms. Thomas’ testimony is accepted as based on superior knowledge and expertise regarding erosion in the Butler Chain of Lakes. FISHING OR RECREATIONAL VALUES OR MARINE PRODUCTIVITY The January 1984 DEP report recommending designation of the Butler Chain of Lakes as an OFW cited the need for increased public access to the Butler Chain. The report specifically noted the fact that there was only one public boat ramp on the Butler Chain and that this ramp had limited parking. This situation has remained unchanged in the intervening 14 years. The Lake Down ramp remains the only point of access for the general public to the Butler Chain of Lakes, and provides only limited access to the entire chain during the periods when Lake Down is waterlocked by the low bridge over the Wauseon Bay canal. The proposed boat ramp will enhance the fishing and recreational value by providing increased and easier public access to the Butler Chain of Lakes for fishing and recreational purposes. Even though "marine” productivity is typically applied to saltwater rather than freshwater systems, the proposed project will actually enhance productivity due to the amount of mitigation. Mr. Armstrong of Phoenix Environmental contended that this factor should be viewed negatively because there will be less opportunity for fishing in the cove immediately adjacent to the proposed boat ramp, due to the launching and loading activity. It may be true that providing greater public access will inconvenience those who already have access to the Butler Chain by other means, but it is implausible to suggest that improved public access be considered a negative aspect of the proposed project. TEMPORARY OR PERMANENT The proposed boat ramp facility will be permanent. The increased mitigation, conservation easement and public access are also permanent. HISTORICAL AND ARCHAEOLOGICAL RESOURCES The proposed boat ramp facility will neither adversely affect nor enhance significant historical and archaeological resources. CURRENT CONDITION AND RELATIVE VALUE OF FUNCTIONS BEING PERFORMED BY AREAS AFFECTED BY THE PROPOSED ACTIVITY The proposed ramp will be placed in a section of the lake shoreline that was previously dredged out as a canal. Thus, Orange County has chosen an area already impacted by development rather than an environmentally pristine location for the boat ramp. The site was originally used as a citrus grove and will be enhanced by the wetlands creation. When Orange County acquired the site, it had a pump house with a leaking diesel fuel pump that was contaminating both the soil and Lake Isleworth. Orange County performed environmental remediation on the site preparatory to installing the proposed boat ramp. The removal of 21 tons of contaminated soil is a positive factor in terms of fish and wildlife. Petitioners attempted to minimize this aspect by arguing that Orange County, as the owner of the contaminated property, would have been required by law to perform the remediation regardless of whether the boat ramp is ever built. This argument is rejected, because the weight of the evidence is that Orange County purchased this property for the express purpose of placing a park and boat ramp on it. Orange County’s ownership of the property, and the consequent duty to remediate the contamination, are inextricably linked with Orange County’s plans to build a boat ramp on the site. The mitigation associated with the proposed ramp will increase wetland habitat and thus improve the ecological value of the site, another positive factor under this heading. In summary, every judgmental factor in the public interest test weighs in favor of a finding that this project is clearly in the public interest. ALTERNATIVE SITES Subject to the relevance objections of the District and Orange County, on which a ruling was withheld at the time of hearing, Petitioners offered evidence regarding Orange County’s consideration of boat ramp sites other than the R.D. Keene site. Orange County owns property on Lake Sheen, a large lake on the southern end of the Butler Chain of Lakes. Orange County intends to construct a boat ramp on this property, as part of its strategy to enhance public access to the Butler Chain by way of offering public ramps in the northern, central, and southern portions of the lake system. The District is and has been aware that Orange County eventually plans to build a boat ramp on Lake Sheen, though the formal permitting process has yet to commence. Orange County EPD has estimated the cost of developing the R.D. Keene boat ramp at $1,068,000, and the cost of developing the Lake Sheen ramp at $560,000. Orange County has prepared a scope of services for the design of the proposed Lake Sheen ramp, selected a design firm, issued a notice to proceed with design. The design firm is currently designing the Lake Sheen ramp. Petitioners assert, and the District admits, that the District did not consider the planned Lake Sheen ramp as an alternative to the R.D. Keene site. For reasons explained in the Conclusions of Law below, the District was not required to consider alternatives to the proposed R.D. Keene ramp. The evidence presented by Petitioners regarding the planned Lake Sheen ramp is irrelevant insofar as Petitioners seek to establish an obligation on the part of the District to review alternative project sites to the one proposed by Orange County and/or to require Orange County to modify its ERP application to propose a different site.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Governing Board of the South Florida Water Management District enter a Final Order issuing Environmental Resource Permit No. 940519-1 to Orange County, subject to the general and special conditions set forth in the District's Staff Review Summaries. DONE AND ENTERED this 29th day of June, 1998, in Tallahassee, Leon County, Florida. COPIES FURNISHED: R. Duke Woodson, Esquire Mary A. Doty, Esquire Foley & Lardner Post Office Box 2193 Orlando, Florida 32802-2193 Linda Brehmer Lanosa, Esquire Assistant County Attorney LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1998. Orange County Attorney’s Office 315 East Robinson Street, Suite 650 Orlando, Florida 32801 William Palmer, Esquire Palmer & Palmer, P.A. 3117-B Edgewater Drive Orlando, Florida 32804 Julie Kendig-Schrader, Esquire John Fumero, Esquire Douglas MacLaughlin, Esquire Office of Counsel, South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33406

Florida Laws (8) 120.569120.57267.061373.042373.086373.414373.421380.06 Florida Administrative Code (9) 40E-4.09140E-4.30140E-4.30262-302.20062-302.30062-302.40062-302.53062-302.70062-4.242
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer