Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
FLORIDA POWER AND LIGHT COMPANY vs. DIVISION OF STATE PLANNING, 77-002044 (1977)
Division of Administrative Hearings, Florida Number: 77-002044 Latest Update: Mar. 17, 1978

Findings Of Fact Based on the testimony of the witnesses adduced at the hearing and the entire record compiled herein, I make the following: The Beker-Manatee transmission line was planned and given budget approval by Petitioner in 1974. This action was taken by Petitioner as a result of a documented request by Beker Phosphate Corporation to provide high-voltage service to the proposed Beker Phosphate Corporation mine in Manatee County, Florida. Right-of-way acquisition was begun in June, 1975, and more than one- half of the right-of-way has now been acquired by Petitioner. The original projected in-service date for the transmission line was July 1, 1976, however, completion was delayed due to, inter alia, alleged environmental problems encountered by Beker Phosphate Corporation in bringing its phosphate mine into production. Presently, Petitioner plans to complete construction and have the Beker-Manatee transmission line energized by the Spring of 1980. Additionally, Petitioner plans to construct an electrical transmission line between the proposed Keentown substation in Manatee County, and a proposed substation in DeSoto County near Arcadia, Florida, which is called the Whidden Substation. (Herein, sometimes called the Keentown-Whidden transmission line). The Keentown-Whidden transmission line was planned and budgeted by Petitioner during late 1975 as the most appropriate means of satisfying Petitioner's needs including providing reliable and adequate service to the Arcadia area; to provide service for specific customers (future) near the Keentown-Whidden transmission line and utilization of its existing facilities including existing transmission lines; to provide bulk power transfer capacity from Manatee into other parts of Petitioner's service area and to improve all transfer capacity between Tampa Bay and the lower west coast of Florida for mutual load supporting generation for emergency and economic reasons. According to its present plans, Petitioner plans to complete construction and have the Keentown-Whidden transmission energized by the summer of 1981, that is more than one year after the Beker-Manatee line is built and energized. On October 14, 1977, Respondent issued a binding letter of interpretation concluding that the Beker-Manatee transmission line is a development of regional impact within the guides of Chapter 380, Florida Statutes, and pertinent regulations since it formed a part of the Keentown-Whidden transmission line. However, in support of this position, Respondent introduced testimony and statements during the hearing indicating that its decision that the subject line is a development of regional inpact is based on five factors as follows: The Beker-Manatee transmission line is a 240 KV line, That the Beker-Manatee Line connects to the Keentown-Whidden transmission line, One of the functions of the Keentown-Whidden transmission line is to transfer bulk power, That the subject line is "the" source of power to energize the Keentown-Whidden transmission line and The Beker-Manatee and Keentown-Whidden lines are inseparable because without the Beker-Manatee transmission line the Keentown-Whidden transmission come not be energized. An examination of these factors revealed that the first three factors are applicable to all 240 KV lines of Petitioner as well as all other power companies. Specifically, testimony was introduced without rebuttal that all other 240 KV transmission lines connect with the subject line as well as the Keentown-Whidden line and form a statewide transmission system in what is commonly referred to as the "Grid". And of course, a primary function of all 240 KV transmission lines is to transmit bulk power. The remaining two factors, when examined, indicate that the Respondent relied on erroneous factors and/or conclusions in reaching its determination that the subject line is a development of regional impact. In this regard, testimony was introduced to the effect that the Beker-Manatee transmission line could be energized through any transmission line within the electrical grid provided the right switching devices were activated. It was also noted that the Keentown-Whidden transmission line could be energized without the Beker-Manatee transmission line provided again that the appropriate switching devices were activated. Throughout the engineering profession, transmission lines are customarily defined by the electric utility industry and by federal and state governmental agencies involved in the regulation of transmission lines, as a line extending from an electric generating power plant to the nearest substation or from a substation to the nearest substation. For example, the Federal Power Commission and the Institute of Electrical and Electronic Engineers' Standard Dictionary of Electrical Terms (1971) define transmission lines in this manner. With this in mind, it was noted that the Beker-Manatee transmission line is a line which extends from a substation to the nearest substation and it does not cross a county line. Respondent failed to demonstrate why the subject transmission line should not be reviewed as similar lines have been throughout the electric utility industry. Consideration was given to Respondent's argument that the subject line must be viewed as an integral electrical transmission line which when completed will connect and cross portions of DeSoto, Hardee and Manatee counties. However, evidence was introduced that when the subject line is completed, it like all other 240 KV lines form a contiguous segment of the entire electrical grid throughout the United States, and in that respect, such a consideration is not a distinguishing factor for this or any other 240 KV transmission line.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that the Division of State Planning issue a binding letter of interpretation to Florida Power and Light Company holding that the proposed Beker-Manatee line does not meet the criteria of Chapter 380, Florida Statutes, and Section 22F-2.03, Florida Administrative Code and therefore is not a development of regional impact. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 14th day of February, 1978. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675

Florida Laws (5) 120.57366.015366.04380.04380.06
# 1
FLORIDA POWER CORPORATION (TIGER BAY COGENERATION FACILITY) vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 97-004488EPP (1997)
Division of Administrative Hearings, Florida Filed:Fort Meade, Florida Sep. 26, 1997 Number: 97-004488EPP Latest Update: Jun. 26, 1998

The Issue The principal issue to be resolved in this proceeding concerns whether certification should be issued to Florida Power Corporation (FPC) for approval to operate a nominal 269 megawatt (MW) combined-cycle generating unit located at FPC's Tiger Bay Cogeneration Facility west of Ft. Meade, Florida, in accordance with the provisions of Section 403.501(2), Florida Statutes. The second issue to be resolved in this consolidated proceeding is whether the site of the Tiger Bay Cogeneration Facility is in compliance and consistent with the applicable land use plans and zoning ordinances of Polk County, pursuant to Section 403.508(2), Florida Statutes.

Findings Of Fact Florida Power Corporation is an investor-owned utility that provides electric service to more than 1.2 million customers in its Florida service area. Tiger Bay Limited Partnership completed the construction of the Tiger Bay Cogeneration Facility in late 1994. FPC entered into a power purchase agreement to purchase the power provided by the Tiger Bay Facility. On January 20, 1997, FPC agreed to purchase the Tiger Bay Facility from the Tiger Bay Limited Partnership. FPC now operates the Tiger Bay Plant as one of its electric generating facilities. The Tiger Bay Cogeneration Facility is an existing combined-cycle electrical generating plant which has been in operation since January 1995. The Facility consists of a combustion turbine (CT) and a steam turbine generator, that is currently limited to generating no more than 74.9 megawatts (MW) of electricity. The steam turbine has been specifically operated to produce no more than 74.9 MW. Therefore, the Plant was not subject to the Power Plant Siting Act. However, FPC has determined that the generating capacity of the steam turbine is nominally 10-15 MW greater than the capacity currently being used at the Plant. The Tiger Bay Facility is currently operating under separate environmental and other permits and approvals issued by FDEP, the Southwest Florida Water Management District (SWFWMD), Polk County and other agencies. The Tiger Bay Facility has been operated in compliance with those permits and approval, and no violations of those permits have occurred since the Plant began operation. By this certification application, FPC is seeking to consolidate the current permits and approvals for the Tiger Bay Facility into a single PPSA certification to authorize the use of the Plant's incremental steam-electric generating capacity. FPC proposes to utilize the additional steam-electric generating capacity in the steam turbine which would increase the generating capacity above the 75 MW threshold of the Power Plant Siting Act. Therefore, certification under the PPSA is required before FPC can obtain the additional electricity from the Plant. No physical changes to the facility or new construction are required to obtain the additional electricity. Only a minor operational change in the steam turbine controls is required to produce the incremental electricity through more efficient utilization of the steam. The Tiger Bay Facility is located on a 6.2 acre tract of land that is leased from the U. S. Agri-Chemical (USAC), Ft. Meade Chemical Complex. The lease extends until 2025 and may be renewed for an additional 25 years. The project's site boundaries will not be expanded to obtain the additional electrical generation. The site is located in southwest Polk County, Florida, approximately 3 miles west of Ft. Meade. The site is bounded on the north by S. R. 630. The project site is in the unincorporated area of Polk County. Ft. Meade is the only local government within a 5-mile radius of the Facility. The area surrounding the Tiger Bay Facility has been dominated by phosphate mining operations. Most of the land within a 5-mile radius of the Plant consists of active phosphate mining, reclaimed mine land, and lands in various stages of reclamation. Other land uses in the area include pasture land and citrus groves, along with limited residential, commercial and industrial uses. The nearest residence is over one mile from the project site. Land use in this area of Polk County is in transition as the phosphate industry completes mining phosphate deposits in the County. The Tiger Bay Plant site contains no significant environmental features. No wetlands, trees, shrubs or listed species or habitats exist within the site. Site vegetation consisted of ruderal and grassy communities prior to development for this project. No jurisdictional natural wetlands exist on the project site. No archaeological or historical sites were found on the project site when developed for this facility. The Tiger Bay Cogeneration Facility consists of one combustion turbine and electric generating unit, and one heat recovery steam generator (HRSG) and one steam turbine generator. In the CT, compressed air and fuel are ignited to provide energy to the air as it passes through the expansion section of the CT. The CT drives an electrical generator which has a nominal electrical output of 184 MS. Exhaust gases from the combustion turbine are then routed to the HRSG where water is boiled into steam. The steam from the HRSG powers a steam turbine which drives a second electrical generator, which will now generate 85.5 MW (nominal) of electricity. As a Cogeneration facility, the Tiger Bay Plant also exports up to 75,000 pounds per hour of low-pressure steam to the adjacent USAC Plant for use in its processes. This steam is extracted from the steam turbine part way through the steam electric generation process. The combined cycle facility is fired primarily with natural gas, with fuel oil as a backup fuel. Natural gas is supplied by a pipeline connected to the Florida Gas Transmission System. Oil will be stored in an onsite tank. The increase in steam generating capacity will be obtained by more efficient use of the steam that is already being produced in the HRSG. Currently, the steam is not fully utilized because its pressure is throttled by an internal control valve. To obtain the additional steam-generated electricity, the controls on this valve will be adjusted to increase the volume and pressure of the steam passing through the steam turbine. This increased steam pressure will generate additional electricity in the steam turbine generator. However, no physical modifications to the Tiger Bay Facility are required to obtain this additional steam generating capacity. Further, no increase in fuel use is required to obtain this additional capacity, and no increase in air emissions will result. All of the air emissions form the Facility are associated with the operation of the combustion turbine, which operates independently from the heat recovery steam generator. The main plant cooling-system begins with a steam condenser which cools the steam exhausted from the steam turbine. Heated cooling water is circulated to the on-site cooling tower where it is sprayed within the cooling tower to release the heat to the atmosphere. Fans at the top of the tower pull air into the tower in the opposite direction to the falling water. Cooled water collects in the bottom of the cooling tower and its returned back to the steam condenser. Approximately five percent of the cooling-water is lost in the cooling tower through evaporation and through drift, or water entrained in the air flowing through the tower. Two deep wells on site supply the makeup water for the cooling-water system. The other on-site water use is the potable water system, permitted for up to 1,000 gallons per day. Water is piped from an on-site well, filtered, and treated in a chlorinator before being distributed for use in the Plant. Wastewaters from the Plant consist of blowdown, or water withdrawn from the cooling tower and the heat recovery steam generator. This blowdown is necessary to prevent a buildup of dissolved solids in the waters from scaling in the circulating water system. Process wastewater and stormwater that contacts industrial processes are collected and recycled or routed to the adjacent USAC Plant where the wastewater is used in the phosphate production process. The Tiger Bay Facility has no off-site discharges of wastewater to either surface water or groundwater. The Facility also includes a back-up zero liquid discharge unit, which treats cooling-tower blowdown and process waters to remove the solids. The recovered high-quality water is recycled back into the Plant's process water stream. Domestic wastewater is treated and disposed on site through a septic tank system. Solid wastes that are generated at the Plant are typical of those associated with a light industrial facility. These wastes are re-cycled or re-used as much as possible. Solid wastes not re-cycled are picked up and disposed of in the Polk County landfill. The back-up zero liquid discharge system, when operational, produces a filter cake as result of drying the wastewater discharge. The non-hazardous material is also sent to the Polk County landfill for disposal. Electricity generated at the Plant is distributed from an on-site switchyard into the Florida Power Corporation transmission system. No changes to this transmission system are required for the additional electricity to be produced. Project Impacts: The Tiger Bay site is located in an area classified by FDEP as in "attainment" of all criteria air pollutants. The area is designated as Class II from a "prevention of significant deterioration" standpoint. The nearest Class I air-quality area is over 100 km to the northwest of the project site. The Tiger Bay Cogeneration Facility operates under an existing FDEP-issued Prevention of Significant Deterioration (PSD) permit. Nitrogen oxide (NOX) emissions are controlled with the use of low NOX burners when using natural gas, and with steam or water injection when firing oil. Particulate matter (PM) emissions are controlled through the use of clean fuels and combustion controls. Carbon monoxide and volatile organic compound emissions are also controlled through good combustion practices. Emissions of sulfur dioxide and metals, such as lead, mercury, beryllium and arsenic, are controlled through the use of clean fuels. PSD increments and ambient air-quality standards will be protected when the facility is being operated. The operation of the Plant at its increased steam generating capacity of 85.5 MW will not require any changes or additions to the facility. No increase in environmental impacts will result from the 10-15 MW (nominal) increase in steam generating capacity. The Plant will continue to operate within the currently permitted quantities of water for the facility, under the existing SWFWMD consumptive use permit. The project will not result in an increase in project- related traffic. The project also will not result in an increase in noise levels at the Plant site. The benefits of the project are that additional electricity is obtained without increasing either fuel use or environmental impacts from the Tiger Bay Plant. These "free megawatts" result from enhancing the efficiency of the Tiger Bay Plant, resulting in savings to FPC's customers. The project also conserves energy by using the additional existing generating capacity without increasing fuel use in the Plant. Consistency with Local Land-Use Plans and Zoning Ordinances: The Tiger Bay Cogeneration Facility is located in a future land-use classification of "PM" or phosphate mining on the Polk County future land-use map. Electrical power plants like the Tiger Bay Cogeneration Facility are permitted in that land- use category. The project site is zoned by Polk County as "RC" or rural conservation, which allows electric power generating facilities as a conditional use in that zoning district. Polk County issued a conditional use permit and site approval for the Tiger Bay Cogeneration Facility on November 20, 1992. The continued operation of the Tiger Bay Plant with its increased electrical output under site certification will be consistent with the land-use and zoning designations for the project site as well as the conditional use permit since there will be no physical changes made to the facility. The Polk County development approvals for the Tiger Bay Facility were consistent with the Comprehensive Plan in effect at the time the approvals were granted. Further amendments to the Polk County Comprehensive Plan are not retroactively applied to projects once they have received necessary development approvals. Agency Positions and Stipulations: The DEP, the Florida Department of Community Affairs (DCA), the Florida Game and Freshwater Fish Commission (FG&FWFC), the Southwest Florida Water Management District (SWFWMD), the Florida Department of Transportation (FDOT), and Polk County each prepared written reports on the Project, and all recommended approval of the Tiger Bay Cogeneration Project. The DCA determined the project, if certified, would be consistent and on balance with the state comprehensive plan. In its report, Polk County indicated that no changes to zoning at the project site were required as a result of certification of the project. Polk County also determined that the Facility would still meet the conditions of the County's original conditional use permit for the project and no further actions would be required by the Applicant. The Central Florida Regional Planning Council did not submit a report to the Department of Environmental Protection as part of its review of the project. No state, regional or local agency has recommended denial of certification. The recommended Conditions of Certification incorporate the existing permits for the Facility.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the Evidence of Record, and the pleadings and argument of the parties, it is, RECOMMENDED that: Florida Power Corporation be granted final certification, pursuant to Chapter 403, Part II, Florida Statutes, for the location and continued operation of the existing Tiger Bay Cogeneration Facility and its increased steam- electric generation capacity, as proposed in the Site Certification Application, and subject to the Conditions of Certification attached hereto; and The Siting Board find that the site of the Tiger Bay Cogeneration Facility, as described in the Site Certification Application, is consistent and in compliance with the existing land-use plans and zoning ordinances of Polk County, as they apply to the site, pursuant to Section 403.508(2), Florida Statutes. DONE AND ENTERED this 30th day of April, 1998, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1998. COPIES FURNISHED: Scott A. Goorland, Esquire Department of Environmental Protection Twin Tower Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Doug Roberts, Esquire Hopping, Green, Sams and Smith, P.A. Post Office Box 6526 Tallahassee, Florida 32314-6526 Charles T. Collette, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Station 35 Tallahassee, Florida 32399-3000 Robert V. Elias, Esquire Division of Legal Services Florida Public Service Commission 2540 Shumard Oak Boulevard Tallahassee, Florida 32399-0850 James V. Antista, Esquire Game and Fresh Water Fish Commission Bryant Building 620 South Meridian Street Tallahassee, Florida 32399-1600 Andrew S. Grayson, Esquire Department of Community Affairs 2555 Shumard Oak Boulevard Suite 315 Tallahassee, Florida 32399-2100 Earl Peterson, Director Division of Forestry Department of Agriculture and Consumer Services 3125 Conner Boulevard, C-19 Tallahassee, Florida 32399-1650 Hamilton Oven, Administrator Office of Siting Coordination Department of Environmental Protection 2600 Blair Stone Boulevard Mail Station 48 Tallahassee, Florida 32399-2400 Brian Sodt Central Florida Regional Planning Council 555 East Church Street Bartow, Florida 33830 Mary Miller, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458 George W. Perry, Director Director of Historical Resources Archives and History R. A. Gray Building 500 South Bronough Street Tallahassee, Florida 32399 Pepe Menendez, P.E. Department of Health Environmental Health Services 1317 Winewood Boulevard Tallahassee, Florida 32399-0070 Rich Tshantz, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Merle Bishop Polk County Florida Post Office Box 60 Bartow, Florida 33830 W. Jeffrey Pardue Florida Power Corporation Post Office Box 14042 MAC H2G St. Petersburg, Florida 33733 Doug Roberts, Esquire Hopping, Green, Sams and Smith, P.A. Post Office Box 6526 Tallahassee, Florida 32314-6526

Florida Laws (5) 120.68403.501403.502403.507403.508
# 2
LISA LANDER vs DEPARTMENT OF ENVIRONMENTAL PROTECTION AND PALM BEACH COUNTY WATER UTILITIES DEPARTMENT, 05-002983 (2005)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 18, 2005 Number: 05-002983 Latest Update: Nov. 02, 2005

The Issue The issue is whether Palm Beach County's application for a permit to construct a domestic wastewater collection/transmission system in Palm Beach County should be approved.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Parties The County is a political subdivision of the State of Florida and is the permittee in this matter. The County Water Utilities Department currently serves approximately 425,000 persons, making it the largest utility provider in Palm Beach County and the third largest in the State of Florida. ITID is an independent water control special district created by special act of the legislature in 1957 and whose boundaries lie within the County. Portions of the transmission line to be constructed by the County will cross easements and roads, and pass under canals, owned by ITID. Petitioners Joseph Acqualotta, Michael D'Ordine, Ann Hawkins, and Lisa Lander all live in areas in close proximity to the proposed transmission line. Lander lives adjacent to the proposed route of the line along 40th Street North, while Acqualotta, D'Ordine, and Hawkins live adjacent to the proposed route along 140th Avenue North. Acqualotta, Hawkins (but not D'Ordine, who resides with Hawkins), and Lander own the property where they reside. Petitioners Troy and Tracey Lee (Case No. 05-2979), Lisa Gabler (Case No. 05- 2980), and Anthony and Veronica Daly (Case No. 05-2982) did not appear at the final hearing. The Department is an agency of the State of Florida authorized to administer the provisions of Part I of Chapter 403, Florida Statutes, and is the state agency charged with the responsibility of issuing domestic wastewater collection/ transmission permits under Section 403.087, Florida Statutes (2004).1 Background On December 15, 2004, the County filed its application with the Department for an individual permit to construct a domestic wastewater collection/transmission system (Transmission Line). The Transmission Line is one element of the County's Northern Region Utilities Improvement Project (Project) and will be approximately 41,050 feet long and comprised of approximately 32,350 linear feet of 20-inch force main and 18,700 linear feet of 30-inch force main (or nearly ten miles in length). A primary purpose of the Project is to provide water and wastewater service to the Village, a 1,900 acre parcel located in the unincorporated part of the County several miles west of the Florida Turnpike, south of State Road 710, and north of the Villages of Wellington and Royal Palm Beach. The Village will be the home of the Scripps Project and Campus. The Transmission Line will run from the southeastern corner of the Village south to Northlake Boulevard, then east to 140th Avenue North, then south along that roadway to 40th Street North, where it turns east until it interconnects with existing facilities. The wastewater will be collected in a regional pump station on the Scripps Project site, where it will be pumped through the Transmission Line to the East Central Plant, which will be the primary treatment facility. The East Central Plant is owned and operated by the City of West Palm Beach (City), but the County owns between forty and forty-five percent of the treatment capacity. Because the wastewater system is interconnected, the wastewater could also be treated at the County's Southern Regional Plant. Ultimately, the flow from the Scripps Project will be one or two million gallons per day. The Transmission Line is the only way that wastewater can be handled at the Scripps Project. A preliminary analysis by the Department and the South Florida Water Management District determined that on-site treatment was not feasible because of the environmentally sensitive nature of the area. The Scripps Project will include residential units, commercial entities, and institutional uses, such as medical clinics. Besides serving these customers, the Transmission Line will also serve other customers in the area. The County has already signed agreements with the Beeline Community Development District (which lies a few miles northwest of the Village) and the Village of Royal Palm Beach (which lies several miles south-southeast of the Village). At the time of the hearing, the County anticipated that it would also sign an agreement with Seacoast Utility Authority (whose service area is located just southeast of the Village) to transport wastewater through the Transmission Line. All of the treatment facilities have sufficient existing capacity to treat the estimated amount of domestic wastewater that will be generated by the Scripps Project and the other users that will discharge to the Line. The County commenced construction of the Transmission Line in May 2005 when the Department issued the Permit. On August 2, 2005, the County published the Department's Notice to issue the Permit, and once the Petitions were filed, the County stopped construction pending the outcome of this hearing. Approximately seventy percent of the Transmission Line is now completed. The Permit does not allow the Transmission Line to be used until it is pressure tested and certified complete. Upon completion, the County must receive an Approval to Place a Domestic Wastewater Collection/Transmission System into Operation from the Department. Such approval is given only after the County has given reasonable assurance that adequate transmission, treatment, and disposal is available in accordance with Department standards. See Fla. Admin. Code R. 62-604.700. On August 15, 2005, Petitions challenging the issuance of the Permit were filed by ITID and the individual Petitioners. ITID contends that the Transmission Line will convey not only domestic wastewater, but also industrial waste; that the County did not comply with all applicable technical standards and criteria required under the Department's rules; that the Project will be located on ITID's right-of-way, on which the County has no right to occupy; that the Project will be located within seventy-five feet from private drinking wells and does not provide an equivalent level of reliability and public health protection; and that the pipe material and pressure design is inappropriate for the Transmission Line's requirements. The individual Petitioners (who filed identical Petitions) are mainly concerned about the location of the Transmission Line in relation to their private drinking wells and property, the possibility of the pipe bursting or leaking once it becomes operational, and the restoration of their property to its original condition after construction is completed. As to the property claims by all Petitioners, the County plans to place the Transmission Line in property that it either owns or has an easement, in property that it is in the process of condemning, or in a public right of way. While the County acknowledges that it has already placed, and intends to place other portions of, the Transmission Line in easements that ITID says it has the exclusive right to use and for which a permit from ITID is required, the County alleges that it also has the right to use those easements without an ITID permit. The dispute between the County and ITID is the subject of a circuit court proceeding in Palm Beach County, and neither the Department nor DOAH has the authority to decide property interests. Petitioners' Objections Domestic wastewater and pretreatment The wastewater that will be generated by the Scripps Project is considered domestic wastewater; it will not include industrial wastewater. Waste that is industrial or non- domestic must be pretreated to protect the wastewater plant, collection system, and the health of system workers and the general public. The Department administers a pretreatment program through which it requires a public wastewater utility to police the entities that discharge to their wastewater plants. A central part of the pretreatment program is the local ordinance that gives legal authority to the utility to permit, inspect, and take enforcement action against industrial users who are part of the pretreatment program. The utility files an annual report with an industrial user survey, and the Department periodically inspects and audits local pretreatment programs to ensure they are being operated as intended. The system is not failsafe but is designed to ensure that potentially harmful wastes are rendered harmless before discharge. For example, the utility has the authority to immediately shut water off if a harmful discharge is occurring. Both the County and the City have pretreatment programs approved by the Department. The City has an ordinance that allows it to enforce the pretreatment standards for all entities that discharge to its wastewater system. The County Water Utilities Department has a written pretreatment manual, and the County has zoning restrictions on the discharge of harmful material to the wastewater system. It has also entered into an interlocal agreement under which it agrees to enforce the City ordinance. The County provides wastewater treatment to industrial, educational, and medical facilities, and it has never experienced a discharge from any of these facilities that has caused adverse health or environmental impacts. The County pretreatment program for the Southern Regional Facility was approved in 1997. The City pretreatment program for the East Central Regional Facility was approved in 1980. The Scripps Project must apply for a permit from the County and provide a baseline monitoring report, data on its flow, and information on the flow frequency and raw materials. Medical waste from the Scripps Project will be pretreated to render it safe before it is discharged into the Transmission Line. Transmission Line Design The Transmission Line was designed in accordance with the technical standards and criteria for wastewater transmission lines in Florida Administrative Code Rule 62- 604.300(5). That rule incorporates by reference a set of standards commonly known as the Ten State Standards, which contain several of the standards used in the design of this project. These standards are recommended, but are not mandatory, and a professional engineer should exercise his or her professional judgment in applying them in any particular case. The Transmission Line also meets the design standards promulgated by the America Water Works Association (AWWA). Specifically, the County used the AWWA C-905 design standard for sizing the polyvinyl chloride, or PVC, pipe used in the project. The County has received written certification from the manufacturer that the PVC pipe meets the standards in AWWA C-905. The Transmission Line is designed with stub-outs, which will allow for future connections without an interruption of service, and inline isolation valves, which allow the line to be shut down for maintenance. The Use of PVC Pipe There is no standard regulating the selection of PVC pipe material in the Department's rules. Instead, the Department relies on the certification of the applicant and the engineer's seal that the force main will be constructed to accepted engineering standards. The only specification applicable to the Transmission Line is the Ten State Standard, adopted and incorporated by reference in Florida Administrative Code Rule 62-604.300(5)(g). That document contains a general requirement that the material selected have a pressure rating sufficient to handle anticipated pressures in wastewater transmission lines. The Transmission Line will be constructed with PVC piping with a thickness of Dimension Ratio (DR) 32.5, which is the ratio of the outside diameter of the pipe to its thickness. Higher ratios mean thinner-walled pipes. This is not the first time the County has used 32.5 PVC piping for one of its projects, and other local governments in the State have used 32.5 or thinner pipe. The County is typically conservative in requiring thicker-walled pipe, because most transmission lines are built by developers, and the County is unable to design the entire line or control or inspect its installation. The specifications for wastewater transmission lines built in the County call for the use of DR 25 pipe. On this project, however, the County determined that thicker- walled pipe would have been an over-design of the system because the County controls the pump stations and oversees the installation; therefore, the Director of the Water Utilities Department has waived that requirement. The County considers the use of DR 32.5 PVC to be conservative. Although this pipe will be thinner than what is typically used in the County, it satisfies the Department's requirements. The Department has permitted many miles of similar PVC force mains in South Florida, and none have failed. PVC has benefits over other transmission line material, such as ductile iron. For example, PVC is more corrosion resistant. Wastewater generates hydrogen sulfide as it decomposes, which can form highly corrosive sulfuric acid. Some of the older transmission lines in the County that were made of ductile iron have corroded. PVC also has a superior ability to absorb surges, such as cyclical surges, than ductile iron. It is easier to install, and its interior flow characteristics are smoother than ductile iron or pre-stressed concrete pipe. Mr. Farabee, a professional engineer who testified on behalf of ITID, recommended a DR 14 pipe, which is thicker- walled than the DR 32.5 pipe used by the County. While he opined that the DR 32.5 pipe was too thin for the project, he could not definitively state that it would not pass the 150 per square inch (psi) pressure test. He also opined that the pipe is undersized because it will be unable to withstand the surge pressures during cleaning. The witness further testified that the pipe would be subject to much higher pressures than 150 psi, and therefore it was impossible to know whether the pipe would fail. In his opinion, this means the Department did not have reasonable assurance for the project. The County consulted with the Unibell PVC Pipe Association (Unibell) in the planning of this project. Unibell is a trade association that provides technical support for PVC pipe manufacturers. Robert Walker, a registered professional engineer and Unibell's executive director who testified on behalf of the County, disagreed with Mr. Farabee's conclusions concerning the adequacy of the PVC pipe in this project. The AWWA C-905 standard uses a safety factor of two, which means the pipes are tested at pressures that are at least twice their stated design strength. Mr. Walker explained the different standards that apply to PVC pipe. DR 32.5 pipe, which is used in this project, has a minimum interior pressure rating of 125 pounds per square psi. Each pipe section is tested before it is shipped at 250 psi, and the minimum burst pressure for the material is in excess of 400 psi. The pipe also meets a 1000- hour test at 270 psi. In light of these standards and testing, the pipe will pass the two-hour 150 psi test required by the Department. Mr. Farabee expressed some concern that the PVC pipe would be more prone to breakage than ductile iron or thicker PVC. However, the PVC pipe standards provide that the pipe can be flattened at sixty percent without splitting, cracking, or breaking. At shallow depths on dirt roads, ovalation, which occurs when PVC is flattened through pressure, will initially occur, but over time the soil around the pipe will become compacted and result in re-rounding of the pipe. The joints are three times stiffer than the body of the pipe, which will protect the joint from excessive ovalation and leaking, and the use of mechanical restrained joints will further strengthen the joints. There has been no joint leakage in Florida due to deflection of the joints. Finally, there have been no failures of PVC pipe caused by three-feet of fill, which is the depth to which the Transmission Line pipe will be buried. To further protect the pipe, the County optimized its pumping system to avoid cyclical surges by using variable frequency drive pumps that gradually increase and decrease speed rather than just turning on or off. In addition, the pump stations are fed by two power lines that come from different directions and emergency generators, which should lessen the chances of harmful surging. Testing the Installation The anticipated pressures in the Transmission Line will likely be about 50 psi. After installation, the Line will be pressure tested at 150 psi for two hours, which is sufficient to provide the Department with reasonable assurance that the Line will hold pressure and will not leak. Also, the County contract inspectors are on the construction site daily. If problems with the installation arise later, the County has committed to promptly fix the problem, even if it means digging up the line. During the hearing, ITID asserted that the Uniform Policies and Procedure Manual standards, which the County has adopted for use by developers when constructing wastewater transmission lines, should be applied to the County as well. This standard, which requires pressure testing to 200 psi for PVC pipes larger than 24 inches, has not been adopted by the Department and is not an applicable Department permitting standard. Even if it did apply, the Transmission Line would meet this criterion because it is designed to withstand 270 psi for at least 1,000 hours. Mr. Farabee believed that the entire Transmission Line would be pressure tested after the construction was complete, which would require digging up sections of the pipe to install bulkheads. However, this assessment of the County's testing program is incorrect. Leisha Pica, Deputy Director of the Water Utilities Department, developed the schedule for the project, helped develop the phasing of the work and budget, and oversaw the technical aspects. She stated that the County has successfully tested approximately fifty percent of the line that was already installed at 150 psi for two hours and not a single section of the line failed the test. Compaction The County has stringent backfilling and compaction requirements, which are sufficient to ensure the pipe will be properly installed and that there will be adequate compaction of the fill material. The County plans and specifications provide that compaction must be to ninety-five percent of the American Association of State Highway and Transportation Officials (AASHTO) standards for non-paved surfaces and one hundred percent of AASHTO standards for paved surfaces. Even ITID's expert agreed that the compaction specifications are sufficient. Mr. Farabee contended, however, that even though the standards are stringent, the County cannot properly test the installation for compliance with the standards. Mr. Farabee believed that testing of the backfill would be done after all of the construction was complete. In that case, he did not see how the testing could be done without digging many holes to check for the density of the backfill. These assumptions, however, are incorrect. The evidence shows that a total of two hundred sixty-four compaction tests have already been done on the portion of the Transmission Line that was completed. No part of the installation failed the tests. The County has an inspector who observes the installation and pressure tests. The compaction was tested at every driveway and major roadway, as well as every five hundred feet along the route. While Lander and D'Ordine pointed out at hearing that no compaction tests have been performed on the dirt roads which run adjacent to their property and on which construction has taken place, the Department requires that, before the work is certified as complete, non-paved roads must be compacted in accordance with AASHTO standards in order to assure that there is adequate compaction of the fill material. The Sufficiency of the Application When an application for an individual transmission/ collection line permit is filed with the Department, the applicant certifies that the design of the pipeline complies with the Department's standards. However, not all of the details of the construction will be included in the permit application. The Department relies on the design engineer to certify that the materials used are appropriate. The application form is also signed and sealed by a professional engineer registered in the State of Florida. All plans submitted by the County, including the original, modifications, and final version, were certified by professional engineers registered in the State of Florida. After receiving the application, the Department requested additional information before issuing the permit, and the County provided all requested information. The original construction plans that were submitted with the application were changed in response to the Department's requests for additional information. The Permit issued by the Department indicates the Transmission Line would be constructed with ductile iron pipe, but this was a typographical error. ITID maintains that all of the technical specifications for the project must be included in the application, and because no separate engineering report was prepared by the County with the application, the County did not meet that standard. While the County did not submit an engineering report, it did submit sufficient data to provide reasonable assurance that the project will comply will all applicable rules of the Department. As a part of its application package, the County submitted construction plans, which contain the specifications required by the Department. Also, the general notes included in the construction drawings specify the use of restrained joints where appropriate, the selection of pipe material, the pressure testing of the Transmission Line, and other engineering requirements. In addition, the plans contain numerous other conditions, which are also specifications sufficient to fulfill the Department's requirements. Finally, further explanation and clarification of the technical aspects of the application was given by the County at the final hearing. At the same time, the Department engineer who oversaw the permitting of this project, testified that a detailed engineering report was not necessary. This engineer has extensive experience in permitting transmission lines for the Department and has worked on over five hundred permits for wastewater transmission and collection systems. The undersigned has accepted his testimony that in a relatively straightforward permit such as this, the application and attachments themselves can function as a sufficient engineering evaluation. This is especially true here since the County is seeking only approval of a pipeline project, which would not authorize the receipt of wastewater flow unless other wastewater facilities are permitted. Impacts on Public and Private Drinking Water Wells As part of the design of the Transmission Line, the County located public and private drinking water wells in the area of the line. County personnel walked the route of the Transmission Line and looked for private wells and researched the site plans for all of the properties along the route. No public wells were found within one-hundred feet of the Transmission Line route, but they did find seventeen private wells that are within seventy-five feet of the line. None of the Petitioners have private wells that are within seventy- five feet of the line. While Petitioners D'Ordine and Hawkins initially contended that the well on Hawkins' property was within seventy-five feet of the Transmission Line, at hearing Mr. D'Ordine admitted that he "misread the plans and referred to the wrong property." In order to protect the private drinking water wells, Florida Administrative Code Rule 62-604.400(1)(b) requires that the County provide an extra level of protection for the wells that are within seventy-five feet of the Transmission Line. The County will provide that extra level of protection by installing restrained joints that will restrain the joints between the pipe sections. The restrained joints are epoxy-coated mechanical devices that reduce the tendency for the pipes to separate under pressure. The County has used these restrained joints on its potable water and wastewater lines in other areas of the County and has never experienced problems with the devices. The restrained joints will provide reliable protection of the private wells within seventy-five feet of the Transmission Line. The Department is unaware of any instances where restrained joints have failed in South Florida. If more wells are discovered that are within seventy-five feet of the Transmission Line, then the County will excavate the Line and install restrained joints. Minimum Separation Distances The County has complied with all applicable pipe separation requirements in the installation of the Transmission Line. More specifically, it is not closer than six feet horizontally from any water main and does not intersect or cross any reclaimed water lines. See Fla. Admin. Code R. 62-555.314(1)(a). It will be at least twelve inches below any water main or culvert that it crosses. See Fla. Admin. Code R. 62-555.314(2)(a). Finally, it will be a minimum of twelve inches below any culverts that it crosses. (However, the Department has no separation requirement for culverts crossed by the Transmission Line.) h. The M-Canal Crossing The Transmission Line must cross the M-canal, which runs in an east-west direction approximately midway between 40th Street North and Northlake Boulevard. The original design called for the Transmission Line to cross above the water, but the City and the Department suggested that it be located below the canal to eliminate the chance that the pipe could leak wastewater into the canal. In response to that suggestion, the County redesigned the crossing so that a 24- inch high density polyethylene pipe in a 48-inch casing will be installed fifteen feet below the design bottom of the canal. The polyethylene is fusion-welded, which eliminates joints, and is isolated with a valve on either side of the canal. Appropriate warning signs will be installed. See Fla. Admin. Code R. 62-604.400(2)(k)2.-5. The depth of the subaqueous line and the use of the slip line, or casing, exceeds the Department's minimum standards. See Fla. Admin. Code R. 62-604.400(2)(k)1. i. Flushing Protocol Section 48.1 of the Ten State Standard recommends that wastewater transmission lines maintain a velocity of two feet per second. When the Transmission Line becomes operational, it will not have sufficient flow to flush (or clean) accumulated solids from the lines at the recommended two feet per second velocities. (Sufficient flow will not occur until other customers connect to the Transmission Line during the first one to three years of operation.) Accumulated solids produce gases and odors that could create a problem at the treatment plant and might leak out of the manhole covers. To address this potential problem, Specific Condition 9 of the Permit requires the County to flush the lines periodically. Pursuant to that Condition, the County plans to flush the Transmission Line with additional water which will raise the velocity to three or four feet per second, so that the accumulated solids will be flushed. The water will be supplied by large portable tanks that will be temporarily set up at several locations along the Line. During the purging of the Line, sewage will collect in the pump stations until the purge is finished. There is sufficient capacity in the pump stations to contain the wastewater. In addition, the County will use a cleansing tool known as a pig, which is like a foam bullet that scrapes the sides of the pipe as it is pushed through the line. This protocol will be sufficient to keep the Line clean. ITID asserts that the County's plan for flushing is inadequate, because it does not provide enough water for long enough to flush both the 20-inch and 30-inch lines. Mr. Farabee calculated that the County would need almost twice the proposed volume, or almost six million gallons, to adequately flush the lines. ITID's analysis of the flushing protocol is flawed, however, because it assumes a constant flow in all segments of the pipe, which is not practical. In order to maintain the flushing velocity of three feet per second, the County will introduce water into the Transmission Line at three separate locations, resulting in a more constant flow velocity throughout the Transmission Line. In this way, it can maintain the proper velocity as the lines transition from a 20-inch to 30-inch to 36-inch pipe. The County has flushed other lines in the past using this protocol and has had no problems. This flushing protocol would only be in effect from one to three years. The County estimates that the necessary volumes to maintain a two-feet-per-second velocity in the 20- inch line would be reached in about one year. The 30-inch line should have sufficient flows sometime in 2008. These estimates are based on the signed agreements the County has with other utilities in the area to take their flows into the Transmission Line. Because of these safeguards, the Transmission Line will not accumulate solids that will cause undesirable impacts while flow is less than two feet per second. Other Requirements The construction and operation of the Transmission Line will not result in the release or disposal of sewage or residuals without providing proper treatment. It will not violate the odor prohibition in Florida Administrative Code Rule 62-600.400(2)(a). It will not result in a cross- connection as defined in Florida Administrative Code Rule 62- 550.200. The construction or operation of the Transmission Line will not result in the introduction of stormwater into the Line, and its operation will not result in the acceptance of non-domestic wastewater that has not been properly pretreated. If constructed and permitted, the Transmission Line will be operated so as to provide uninterrupted service and will be maintained so as to function as intended. The record drawings will be available at the Department's district office and to the County operation and maintenance personnel. Finally, concerns by the individual Petitioners that the County may not restore their property to its original condition after construction is completed are beyond the scope of this proceeding. At the hearing, however, the Deputy Director of the Water Utilities Department represented that the County would cooperate with the individual property owners to assure that these concerns are fully addressed. Reasonable Assurance The County has provided the Department with reasonable assurance, based on plans, test results, installation of equipment, and other information that the construction and installation of the Transmission Line will not discharge, emit, or cause pollution in contravention of the Department's standards.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order denying all Petitions and issuing Permit No. 0048923-017-DWC. DONE AND ENTERED this 18th day of October, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of October, 2005.

Florida Laws (4) 120.569120.57403.087403.973
# 3
IN RE: NEW HOPE POWER PARTNERSHIP OKEELANTA COGENERATION FACILITIES POWER PLANT SITING APPLICATION NO. PA 04-46 vs *, 04-003209EPP (2004)
Division of Administrative Hearings, Florida Filed:South Bay, Florida Sep. 10, 2004 Number: 04-003209EPP Latest Update: May 31, 2005

The Issue The issue to be determined in this case is whether the Governor and Cabinet, sitting as the Siting Board, should grant certification to New Hope for the expansion of the Okeelanta cogeneration facility to a total net steam electrical generating capacity of 140 megawatts (”MW”).

Findings Of Fact The Applicant The Applicant, New Hope Power Partnership, is a Florida partnership that owns the existing Okeelanta cogeneration Facility. Ex. 1 at 1-1, 3-1. New Hope will also own the Project. See id. The Site The Facility is located in an unincorporated area in western Palm Beach County, Florida. Ex. 1 at 2-1; Ex. 4 at 6; T It is approximately six miles south of South Bay and two miles west of U.S. Highway 27. Id. The Facility is located on a site (the ”Site”) that is approximately 82.1 acres in size. Ex. 1 at 2-1; Ex. 4 at 8; T 19. The Site is adjacent to Okeelanta Corporation’s existing sugar mill, sugar refinery, and sugarcane fields. Ex. 1 at 2-1; Ex. 4 at 6; T 17, 20. The Surrounding Area There are large buffer areas around the Site. See Ex. 1 at 2-1, 2-2, 2-4; Ex. 4 at 6; T 17-18. Almost all of the land within five miles of the Site is used for agricultural purposes (sugarcane farming). Id. The community nearest the Site is South Bay. Ex. 1 at 2-2; Ex. 4 at 6; T 17. The nearest home is more than 3.5 miles northeast of the Site. Ex. 1 at 2-4; Ex. 5 at 9; T 17-18. The Facility is adjacent to an existing electrical substation (Florida Power & Light Company’s Okeelanta Substation). See Ex. 1 at 1-2. An existing electrical transmission line connects the Facility to the substation. Ex. 1 at 3-1. The Existing Facility The Facility uses biomass fuels (e.g., bagasse from the sugar mill; clean wood waste) to generate steam and up to 74.9 MW of electricity (net). Ex. 1 at 1-1, 3-1; Ex. 4 at 6-7; T 18. The Facility supplies steam to the sugar mill during the sugarcane harvest (October through March) and it supplies steam to the refinery throughout the year. Ex. 1 at 1-2, 3-1; Ex. 4 at 7; see T 18. Excess steam from the Facility is used to generate electricity, which is sold to utility companies, including Florida Power & Light Company. Ex. 1-3; Ex. 4 at 7; See T 50-51. The existing Facility includes three steam boilers, one steam turbine/electrical generator, a cooling tower, an electrical switchyard, materials handling and storage facilities for biomass fuels, and ancillary equipment. Ex. 1 at 2-1, 3-1; Ex. 4 at 7; T 20-21. The Expansion Project The Expansion Project will increase the Facility’s electrical generating capacity by 65 MW (net), creating a total generating capacity of 140 MW (net). Ex. 1 at 1-1, 1-3, 2-1; Ex. 4 at 7; T 18. The Expansion Project will involve the installation of a new turbine/electrical generator, a cooling tower, and related equipment at the Site. Ex. 1 at 1-3, 2-1; Ex. 4 at 8; T 19. Construction of the Expansion Project Approximately 0.5 acres of the Site will be occupied by the new equipment that will be installed for the Expansion Project. Ex. 1 at 2-1; Ex. 4 at 8; T 19. The construction of the Project will occur in disturbed upland areas that already are used for industrial operations. Ex. 1 at 3-2, 4-1; Ex. 4 at 9; T 20. No construction will take place in any wetland, wildlife habitat, environmentally sensitive area, or 100-year flood plain. Ex. 1 at 2-2, 2-18, 4-1; Ex. 4 at 9; T 20. No new electrical transmission lines will need to be built to accommodate the additional electrical power generated by the Expansion Project. See Ex. 1 at 3-1, 6-1. During construction, there will be a temporary increase in sound levels due to the heavy equipment associated with the construction process. Ex. 1 at 4-9 through 4-10; Ex. 5 at 9; T 42-43. Given the remote location of the Site, the sounds generated by the construction of the Expansion Project will not interfere with human activities or otherwise cause a nuisance at any residential locations. Id. The construction of the Expansion Project will result in a temporary increase in traffic on some roads near the Site, but these roads will continue to operate at acceptable traffic levels. Ex. 1 at 4-8 through 4-9; Ex. 5 at 9; T 42. Operation of the Expansion Project The Facility currently operates at its full capacity during the sugarcane harvest. See Ex. 30, Technical Evaluation at 2. The Expansion Project will enable the Facility to operate at its full capacity year-round. See Ex. 1 at 3-1 through 3-2; Ex. 30, Technical Evaluation at 2. Although the Facility will generate more electricity after the Expansion Project is completed, the basic operation of the Facility will not change. Ex. 4 at 10; Ex. 5 at 6; T 22. The Facility has a water use permit issued by the South Florida Water Management District, which authorizes the Facility to use water from the Miami/North New River Canal System, the surficial aquifer, and the Floridan aquifer. Ex. 1 at 3-11; Ex. 5 at 7; T 40-41. The Okeelanta Corporation also may provide water to the Facility, in accordance with the SFWMD water use permit for the Okeelanta Corporation’s sugar mill. Ex. 5 at 7; T 41. After the Expansion Project is completed, the amount of water used by the Facility will increase, commensurate with the increased use of the Facility. Ex. 5 at 7; DEP Ex. 2, Staff Analysis Report at 3; T 41. The additional water will be obtained from the cooling pond/rock pit located at the adjacent sugar mill. Id. In March 2005, the SFWMD issued a water use permit that allows the Okeelanta Corporation to increase the amount of water provided to the Facility from 0.4 mgd to 2.0 mgd. Ex. 37; see T 41. The Facility’s stormwater and process water are routed to a 600-acre area that is divided into four percolation basins. Ex. 1 at 3-16; Ex. 5 at 8; T 41. Each basin is used on a rotating basis--i.e., the basin is used for percolation for one year and then it is used for growing sugarcane for three years. Ex. 5 at 8; T 41. Each percolation basin is designed to hold all of the Facility’s process water, plus all of the contact and non-contact stormwater runoff from a 100-year, three-day storm event. Id. The Facility does not discharge any stormwater or process water to any surface water. Ex. 1 at 5-9; Ex. 5 at 8; T 41-42. The Facility’s use of the percolation ponds has not caused and is not expected to cause any violations of any ground water quality standards. Ex. 5 at 8. The Facility generates fly ash and bottom ash from the combustion of biomass fuels. Ex. 1 at 3-16, 5-10; Ex. 5 at 9; T 42. These materials are taken to a landfill for disposal. Id. The operation of the Expansion Project will not have any significant impacts on traffic. Ex. 1 at 5-17; Ex. 5 at 9; T 42. The local roads will continue to operate at an acceptable level of service. Id. Air Quality Regulations The Facility must comply with New Source Performance Standards (”NSPS”) and Best Available Control Technology (”BACT”) requirements, both of which impose strict limits on the Facility’s airborne emissions. See Ex. 1 at 3-5; Ex. 30, Technical Evaluation at 3. The Facility also must comply with Ambient Air Quality Standards (”AAQS”) and Prevention of Significant Deterioration (”PSD”) standards, which establish criteria for the protection of ambient air quality. Id. The Facility previously was reviewed and approved under the PSD program. Ex. 1 at 3-5; Ex. 5 at 6; Ex. 30, Technical Evaluation at 2; T 39-40. The DEP has determined that the Expansion Project is not subject to PSD pre-construction review. Ex. 5 at 6; Ex. 30, Technical Evaluation at 5; T 38. The cooling towers will be the only new source of air pollution associated with the Expansion Project. Ex. 1 at 3-5; Ex. 5 at 6; T 38. The water droplets leaving the cooling tower will evaporate, causing small amounts of particulate matter to enter the atmosphere near the Site. Ex. 5 at 6; T 38. However, the emissions from the cooling tower are so small that the cooling tower is exempt from the permitting requirements established by the DEP. Id. Best Available Control Technology A BACT determination is required for each pollutant for which PSD review is required. Ex. 1 at 3-5; Ex. 5 at 7; DEP Ex. 2, Staff Analysis Report at 15. BACT is a pollutant- specific emission limit that provides the maximum degree of emission reduction, after taking into account the energy, environmental, and economic impacts and other costs. Ex. 1 at 3-5; Fla. Admin. Code R. 62-210.200(38). As part of its BACT analyses for the Facility, DEP determined that mechanical cyclone dust collectors and an electrostatic precipitator (”ESP”) will control the Facility’s emissions of particulate matter, a selective non-catalytic reduction system (”SNCR”) will control oxides of nitrogen (”NOx”), use of low-sulfur fuels will control sulfur dioxide emissions, and proper facility design and operating methods will control other pollutants. Ex. 1 at 3-6 through 3-8; Ex. 30, Draft Permit at D-1; T 40. Accordingly, these air pollution control systems and techniques are utilized at the Facility. Id. The Facility also uses an array of continuous emissions monitors to ensure that the Facility is continuously in compliance with the BACT emission limits. Ex. 1 at 5-14; Ex. 30, Draft Permit at E-1 through E-2. Protection of Ambient Air Quality The EPA has adopted ”primary” and ”secondary” National Ambient Air Quality Standards (”NAAQS”). See Ex. 1 at 2-21. The primary NAAQS were promulgated to protect the health of the general public with an adequate margin of safety. See Ex. 1 at 2-21; see also 42 U.S.C.A. § 7409(b) (1997). The secondary NAAQS were promulgated to protect the public welfare, including vegetation, soils, visibility and other factors, from any known or anticipated adverse effects associated with the presence of pollutants in the ambient air. Id. Florida has adopted EPA’s primary and secondary NAAQS, and has adopted some Florida AAQS (”FAAQS”) that are more stringent than EPA’s NAAQS. See id. The Facility’s potential impacts on ambient air quality were evaluated by DEP, based on the continuous operation of the Facility at full load, following completion of the Project. Ex. 30, Technical Evaluation at 4. DEP concluded that the maximum impacts from the Facility will not cause or contribute to any violations of AAQS. Ex. 1 at 5-10 through 5- 14; Ex. 5 at 6-7; Ex. 30, Technical Evaluation at 4; Ex. 5 at 6; T 39. Other PSD Analyses The PSD program provides protection for those areas that have good air quality. See Ex. 1 at 2-22; Ex. 30, Technical Evaluation at 3-4. Different areas of Florida have been designated as PSD ”Class I” or ”Class II” areas, depending upon the level of protection that is to be provided under the PSD program. Id. In this case, the Project is located in a PSD Class II area. Id. The nearest PSD Class I area is the Everglades National Park (”Everglades”), which is approximately 92 kilometers (”km”) south of the Site. Ex. 1 at 2-22. The DEP’s analyses demonstrate that the Facility’s impacts on ambient air quality will not violate any applicable PSD requirement for the Class I and Class II areas. Ex. 1 at 5- 14; Ex. 5 at 6; Ex. 30, Technical Evaluation at 4; DEP Ex. 2, Staff Analysis Report at 16-17; T 39. Compliance With Air Standards New Hope has provided reasonable assurance that the Expansion Project and the Facility will comply with all of the applicable air quality standards and requirements. Ex. 5 at 7; Ex. 30; DEP Ex. 2, Staff Analysis Report at 17; T 38-40. Environmental Benefits of the Project The Expansion Project will provide environmental benefits. Ex. 1 at 7-3 through 7-4; Ex. 5 at 10; T 43-44. For example, the Project will be capable of producing approximately 65 MW (net) of electricity in Southeast Florida, which needs new electrical generating capacity. Ex. 1 at 7-3 through 7-4; Ex. 5 at 10; T 43-44. The Expansion Project will also enhance fuel diversity by using renewable biomass fuels to generate electricity. Id. Over 20 years, the Project may displace the use of approximately 5,600,000 barrels of oil worth nearly $170,000,000 (assuming oil prices of $30 per barrel). Id. In addition, the Expansion Project will beneficially reuse clean wood waste, which otherwise would likely be placed in a landfill for disposal. Ex. 1 at 7-4; Ex. 5 at 10; T 44. The Facility receives wood waste and biomass materials from Miami-Dade County, the Palm Beach County Solid Waste Authority, and approximately 25 private recycling companies, thus assisting them with their solid waste management programs. Ex. 5 at 10; T 44. The Facility also burns melaleuca trees that have been removed pursuant to land clearing programs for the eradication of this nuisance species. Ex. 5 at 10. Socioeconomic Benefits of the Project The Expansion Project will provide jobs for an average of 70 construction workers during the 12-month construction phase of the Project. Ex. 1 at 7-1 through 7-2; Ex. 5 at 10; T 43. Approximately $3.5 million will be paid in wages for construction employees working on the Expansion Project. Id. Consistency with Land Use Plans and Zoning Ordinances The proposed use of the Site is consistent and in compliance with Palm Beach County’s comprehensive land use plan and zoning ordinances. Ex. 1 at 2-2 through 2-4; Ex. 4 at 16; Ex. 23; Ex. 24; Ex. 38; Ex. 39; T 28-29. The Facility and Project have both been reviewed and approved by the Palm Beach County Board of County Commissioners. Ex. 4 at 11-12; Ex. 23; Ex. 24; T 23-25. Compliance with Environmental Standards New Hope has provided reasonable assurance that the Facility and Project will comply with all of the nonprocedural land use and environmental statutes, rules, policies, and requirements that apply to the Project, including but not limited to those requirements governing the Project’s impacts on air quality, water consumption, stormwater, and wetlands. Prehearing Stipulation at 24, paragraph 5.B.3.; Ex. 5 at 11; DEP Ex. 2, Staff Analysis Report at 22; T 44-45, 60. The location, construction and operation of the Facility and Project will have minimal adverse effects on human health, the environment, the ecology of the State’s lands and wildlife, and the ecology of the State’s waters and aquatic life. Ex. 5 at 12; DEP Ex. 2, Staff Analysis Report at 20; T 45-46, 61-62. The Facility and Project will not unduly conflict with any of the goals or other provisions of any applicable local, regional or state comprehensive plan. Ex. 4 at 16; Ex. 23; Ex. 24; Ex. 38; Ex. 39; T 28-29. The Conditions of Certification establish operational safeguards for the Facility and Project that are technically sufficient for the protection of the public health and welfare. Ex. 5 at 13; T 46-47, 61. Agency Positions and Conditions of Certification On November 18, 2004, the PSC issued an Order (No. PSC-04-1105A-FOF-EI) granting New Hope’s petition for determination of need for the Expansion Project. Ex. 22; DEP Ex. 2, Staff Analysis Report at 4-6, 12-13. The PSC determined, consistent with the criteria of Section 403.519, Florida Statutes, that the Expansion Project is needed. Id. The DEP, DOT, DCA, and SFWMD all recommend certification of the Expansion Project, subject to the Conditions of Certification. Prehearing Stipulation at 10-11, 13-16. New Hope has accepted, and has provided reasonable assurance that it will comply with, the Conditions of Certification. Prehearing Stipulation at 24-25, paragraph V.B.4; Ex. 5 at 11-12; T 45, 61-62. Public Notice of the Certification Use Hearing On September 29, 2004, New Hope published a ”Notice of Filing of Application for Electrical Power Plant Site Certification” in the Palm Beach Post, which is a newspaper of general circulation published in Palm Beach County, Florida. Ex. 31; see also Ex. 5 at 16; T 49. On October 1, 2004, the Department published ”Notice of Receipt of Application for Power Plant Certification” in the Florida Administrative Weekly. Ex. 35; see also Ex. 5 at 16; T 49. On February 2, 2005, New Hope published notice of the Certification Hearing in the Palm Beach Post. Ex. 33; see also Ex. 5 at 16; T 49. On February 4 and 11, 2005, the Department published notice of the Certification Hearing in the Florida Administrative Weekly. Ex. 36; see also Ex. 5 at 16; T 49. The public notices for the Certification Hearing satisfy the informational and other requirements set forth in Section 403.5115, Florida Statutes, and Florida Administrative Code Rules 62-17.280 and 62-17.281(4). Prehearing Stipulation at 24, paragraph V.B.2,3; Ex. 5 at 17; T 49, 63-64.

Conclusions For Petitioner New Hope Power Partnership (”New Hope”): David S. Dee, Esquire Landers & Parsons 310 West College Avenue Tallahassee, Florida 32301 For the Florida Department of Environmental Protection: Scott A. Goorland, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that the Governor and Cabinet, sitting as the Siting Board, enter a Final Order granting certification for the expansion of the Okeelanta Cogeneration Facility to a total capacity of 140 MW (net), in accordance with the Conditions of Certification, DEP Exhibit 3. DONE AND ENTERED this 31st day of March, 2005, in Tallahassee, Leon County, Florida. S CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of March, 2005. COPIES FURNISHED: David S. Dee, Esquire Landers & Parsons 310 West College Avenue Tallahassee, Florida 32301 Scott Goorland, Esquire Office of General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 James V. Antista, General Counsel Florida Fish and Wildlife Conservation Commission 620 South Meridian Street Tallahassee, Florida 32399-1600 Roger Saberson, General Counsel Treasure Coast Regional Planning Council 70 Southeast 4th Avenue Delray Beach, Florida 33483 Jennifer Brubaker, Esquire Public Service Commission Division of Legal Services 2540 Shumard Oak Boulevard Tallahassee, Florida 32399-0863 Leslie Bryson, Esquire Department of Community Affairs 2555 Shumard Oak Boulevard Tallahassee, Florida 32399 Sheauching Yu, Esquire Department of Transportation 605 Suwannee Street Mail Station 58 Tallahassee, Florida 32399-0458 Sarah Nall, Esquire 9341 Southeast Mystic Cove Terrace Hobe Sound, Florida 33455 Denise M. Nieman, Esquire Palm Beach County Attorney's Office 302 North Olive Avenue, Suite 601 West Palm Beach, Florida 33401-4705 Raquel A. Rodriguez, General Counsel Office of the Governor The Capitol, Suite 209 Tallahassee, Florida 32399-1001 Kathy C. Carter, Agency Clerk Department of Environmental Protection Office of General Counsel Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

Florida Laws (6) 120.569403.501403.502403.508403.5115403.519
# 4
MICHAEL D`ORDINE AND ANN E. HAWKINS vs DEPARTMENT OF ENVIRONMENTAL PROTECTION AND PALM BEACH COUNTY WATER UTILITIES DEPARTMENT, 05-002982 (2005)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 18, 2005 Number: 05-002982 Latest Update: Nov. 02, 2005

The Issue The issue is whether Palm Beach County's application for a permit to construct a domestic wastewater collection/transmission system in Palm Beach County should be approved.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Parties The County is a political subdivision of the State of Florida and is the permittee in this matter. The County Water Utilities Department currently serves approximately 425,000 persons, making it the largest utility provider in Palm Beach County and the third largest in the State of Florida. ITID is an independent water control special district created by special act of the legislature in 1957 and whose boundaries lie within the County. Portions of the transmission line to be constructed by the County will cross easements and roads, and pass under canals, owned by ITID. Petitioners Joseph Acqualotta, Michael D'Ordine, Ann Hawkins, and Lisa Lander all live in areas in close proximity to the proposed transmission line. Lander lives adjacent to the proposed route of the line along 40th Street North, while Acqualotta, D'Ordine, and Hawkins live adjacent to the proposed route along 140th Avenue North. Acqualotta, Hawkins (but not D'Ordine, who resides with Hawkins), and Lander own the property where they reside. Petitioners Troy and Tracey Lee (Case No. 05-2979), Lisa Gabler (Case No. 05- 2980), and Anthony and Veronica Daly (Case No. 05-2982) did not appear at the final hearing. The Department is an agency of the State of Florida authorized to administer the provisions of Part I of Chapter 403, Florida Statutes, and is the state agency charged with the responsibility of issuing domestic wastewater collection/ transmission permits under Section 403.087, Florida Statutes (2004).1 Background On December 15, 2004, the County filed its application with the Department for an individual permit to construct a domestic wastewater collection/transmission system (Transmission Line). The Transmission Line is one element of the County's Northern Region Utilities Improvement Project (Project) and will be approximately 41,050 feet long and comprised of approximately 32,350 linear feet of 20-inch force main and 18,700 linear feet of 30-inch force main (or nearly ten miles in length). A primary purpose of the Project is to provide water and wastewater service to the Village, a 1,900 acre parcel located in the unincorporated part of the County several miles west of the Florida Turnpike, south of State Road 710, and north of the Villages of Wellington and Royal Palm Beach. The Village will be the home of the Scripps Project and Campus. The Transmission Line will run from the southeastern corner of the Village south to Northlake Boulevard, then east to 140th Avenue North, then south along that roadway to 40th Street North, where it turns east until it interconnects with existing facilities. The wastewater will be collected in a regional pump station on the Scripps Project site, where it will be pumped through the Transmission Line to the East Central Plant, which will be the primary treatment facility. The East Central Plant is owned and operated by the City of West Palm Beach (City), but the County owns between forty and forty-five percent of the treatment capacity. Because the wastewater system is interconnected, the wastewater could also be treated at the County's Southern Regional Plant. Ultimately, the flow from the Scripps Project will be one or two million gallons per day. The Transmission Line is the only way that wastewater can be handled at the Scripps Project. A preliminary analysis by the Department and the South Florida Water Management District determined that on-site treatment was not feasible because of the environmentally sensitive nature of the area. The Scripps Project will include residential units, commercial entities, and institutional uses, such as medical clinics. Besides serving these customers, the Transmission Line will also serve other customers in the area. The County has already signed agreements with the Beeline Community Development District (which lies a few miles northwest of the Village) and the Village of Royal Palm Beach (which lies several miles south-southeast of the Village). At the time of the hearing, the County anticipated that it would also sign an agreement with Seacoast Utility Authority (whose service area is located just southeast of the Village) to transport wastewater through the Transmission Line. All of the treatment facilities have sufficient existing capacity to treat the estimated amount of domestic wastewater that will be generated by the Scripps Project and the other users that will discharge to the Line. The County commenced construction of the Transmission Line in May 2005 when the Department issued the Permit. On August 2, 2005, the County published the Department's Notice to issue the Permit, and once the Petitions were filed, the County stopped construction pending the outcome of this hearing. Approximately seventy percent of the Transmission Line is now completed. The Permit does not allow the Transmission Line to be used until it is pressure tested and certified complete. Upon completion, the County must receive an Approval to Place a Domestic Wastewater Collection/Transmission System into Operation from the Department. Such approval is given only after the County has given reasonable assurance that adequate transmission, treatment, and disposal is available in accordance with Department standards. See Fla. Admin. Code R. 62-604.700. On August 15, 2005, Petitions challenging the issuance of the Permit were filed by ITID and the individual Petitioners. ITID contends that the Transmission Line will convey not only domestic wastewater, but also industrial waste; that the County did not comply with all applicable technical standards and criteria required under the Department's rules; that the Project will be located on ITID's right-of-way, on which the County has no right to occupy; that the Project will be located within seventy-five feet from private drinking wells and does not provide an equivalent level of reliability and public health protection; and that the pipe material and pressure design is inappropriate for the Transmission Line's requirements. The individual Petitioners (who filed identical Petitions) are mainly concerned about the location of the Transmission Line in relation to their private drinking wells and property, the possibility of the pipe bursting or leaking once it becomes operational, and the restoration of their property to its original condition after construction is completed. As to the property claims by all Petitioners, the County plans to place the Transmission Line in property that it either owns or has an easement, in property that it is in the process of condemning, or in a public right of way. While the County acknowledges that it has already placed, and intends to place other portions of, the Transmission Line in easements that ITID says it has the exclusive right to use and for which a permit from ITID is required, the County alleges that it also has the right to use those easements without an ITID permit. The dispute between the County and ITID is the subject of a circuit court proceeding in Palm Beach County, and neither the Department nor DOAH has the authority to decide property interests. Petitioners' Objections Domestic wastewater and pretreatment The wastewater that will be generated by the Scripps Project is considered domestic wastewater; it will not include industrial wastewater. Waste that is industrial or non- domestic must be pretreated to protect the wastewater plant, collection system, and the health of system workers and the general public. The Department administers a pretreatment program through which it requires a public wastewater utility to police the entities that discharge to their wastewater plants. A central part of the pretreatment program is the local ordinance that gives legal authority to the utility to permit, inspect, and take enforcement action against industrial users who are part of the pretreatment program. The utility files an annual report with an industrial user survey, and the Department periodically inspects and audits local pretreatment programs to ensure they are being operated as intended. The system is not failsafe but is designed to ensure that potentially harmful wastes are rendered harmless before discharge. For example, the utility has the authority to immediately shut water off if a harmful discharge is occurring. Both the County and the City have pretreatment programs approved by the Department. The City has an ordinance that allows it to enforce the pretreatment standards for all entities that discharge to its wastewater system. The County Water Utilities Department has a written pretreatment manual, and the County has zoning restrictions on the discharge of harmful material to the wastewater system. It has also entered into an interlocal agreement under which it agrees to enforce the City ordinance. The County provides wastewater treatment to industrial, educational, and medical facilities, and it has never experienced a discharge from any of these facilities that has caused adverse health or environmental impacts. The County pretreatment program for the Southern Regional Facility was approved in 1997. The City pretreatment program for the East Central Regional Facility was approved in 1980. The Scripps Project must apply for a permit from the County and provide a baseline monitoring report, data on its flow, and information on the flow frequency and raw materials. Medical waste from the Scripps Project will be pretreated to render it safe before it is discharged into the Transmission Line. Transmission Line Design The Transmission Line was designed in accordance with the technical standards and criteria for wastewater transmission lines in Florida Administrative Code Rule 62- 604.300(5). That rule incorporates by reference a set of standards commonly known as the Ten State Standards, which contain several of the standards used in the design of this project. These standards are recommended, but are not mandatory, and a professional engineer should exercise his or her professional judgment in applying them in any particular case. The Transmission Line also meets the design standards promulgated by the America Water Works Association (AWWA). Specifically, the County used the AWWA C-905 design standard for sizing the polyvinyl chloride, or PVC, pipe used in the project. The County has received written certification from the manufacturer that the PVC pipe meets the standards in AWWA C-905. The Transmission Line is designed with stub-outs, which will allow for future connections without an interruption of service, and inline isolation valves, which allow the line to be shut down for maintenance. The Use of PVC Pipe There is no standard regulating the selection of PVC pipe material in the Department's rules. Instead, the Department relies on the certification of the applicant and the engineer's seal that the force main will be constructed to accepted engineering standards. The only specification applicable to the Transmission Line is the Ten State Standard, adopted and incorporated by reference in Florida Administrative Code Rule 62-604.300(5)(g). That document contains a general requirement that the material selected have a pressure rating sufficient to handle anticipated pressures in wastewater transmission lines. The Transmission Line will be constructed with PVC piping with a thickness of Dimension Ratio (DR) 32.5, which is the ratio of the outside diameter of the pipe to its thickness. Higher ratios mean thinner-walled pipes. This is not the first time the County has used 32.5 PVC piping for one of its projects, and other local governments in the State have used 32.5 or thinner pipe. The County is typically conservative in requiring thicker-walled pipe, because most transmission lines are built by developers, and the County is unable to design the entire line or control or inspect its installation. The specifications for wastewater transmission lines built in the County call for the use of DR 25 pipe. On this project, however, the County determined that thicker- walled pipe would have been an over-design of the system because the County controls the pump stations and oversees the installation; therefore, the Director of the Water Utilities Department has waived that requirement. The County considers the use of DR 32.5 PVC to be conservative. Although this pipe will be thinner than what is typically used in the County, it satisfies the Department's requirements. The Department has permitted many miles of similar PVC force mains in South Florida, and none have failed. PVC has benefits over other transmission line material, such as ductile iron. For example, PVC is more corrosion resistant. Wastewater generates hydrogen sulfide as it decomposes, which can form highly corrosive sulfuric acid. Some of the older transmission lines in the County that were made of ductile iron have corroded. PVC also has a superior ability to absorb surges, such as cyclical surges, than ductile iron. It is easier to install, and its interior flow characteristics are smoother than ductile iron or pre-stressed concrete pipe. Mr. Farabee, a professional engineer who testified on behalf of ITID, recommended a DR 14 pipe, which is thicker- walled than the DR 32.5 pipe used by the County. While he opined that the DR 32.5 pipe was too thin for the project, he could not definitively state that it would not pass the 150 per square inch (psi) pressure test. He also opined that the pipe is undersized because it will be unable to withstand the surge pressures during cleaning. The witness further testified that the pipe would be subject to much higher pressures than 150 psi, and therefore it was impossible to know whether the pipe would fail. In his opinion, this means the Department did not have reasonable assurance for the project. The County consulted with the Unibell PVC Pipe Association (Unibell) in the planning of this project. Unibell is a trade association that provides technical support for PVC pipe manufacturers. Robert Walker, a registered professional engineer and Unibell's executive director who testified on behalf of the County, disagreed with Mr. Farabee's conclusions concerning the adequacy of the PVC pipe in this project. The AWWA C-905 standard uses a safety factor of two, which means the pipes are tested at pressures that are at least twice their stated design strength. Mr. Walker explained the different standards that apply to PVC pipe. DR 32.5 pipe, which is used in this project, has a minimum interior pressure rating of 125 pounds per square psi. Each pipe section is tested before it is shipped at 250 psi, and the minimum burst pressure for the material is in excess of 400 psi. The pipe also meets a 1000- hour test at 270 psi. In light of these standards and testing, the pipe will pass the two-hour 150 psi test required by the Department. Mr. Farabee expressed some concern that the PVC pipe would be more prone to breakage than ductile iron or thicker PVC. However, the PVC pipe standards provide that the pipe can be flattened at sixty percent without splitting, cracking, or breaking. At shallow depths on dirt roads, ovalation, which occurs when PVC is flattened through pressure, will initially occur, but over time the soil around the pipe will become compacted and result in re-rounding of the pipe. The joints are three times stiffer than the body of the pipe, which will protect the joint from excessive ovalation and leaking, and the use of mechanical restrained joints will further strengthen the joints. There has been no joint leakage in Florida due to deflection of the joints. Finally, there have been no failures of PVC pipe caused by three-feet of fill, which is the depth to which the Transmission Line pipe will be buried. To further protect the pipe, the County optimized its pumping system to avoid cyclical surges by using variable frequency drive pumps that gradually increase and decrease speed rather than just turning on or off. In addition, the pump stations are fed by two power lines that come from different directions and emergency generators, which should lessen the chances of harmful surging. Testing the Installation The anticipated pressures in the Transmission Line will likely be about 50 psi. After installation, the Line will be pressure tested at 150 psi for two hours, which is sufficient to provide the Department with reasonable assurance that the Line will hold pressure and will not leak. Also, the County contract inspectors are on the construction site daily. If problems with the installation arise later, the County has committed to promptly fix the problem, even if it means digging up the line. During the hearing, ITID asserted that the Uniform Policies and Procedure Manual standards, which the County has adopted for use by developers when constructing wastewater transmission lines, should be applied to the County as well. This standard, which requires pressure testing to 200 psi for PVC pipes larger than 24 inches, has not been adopted by the Department and is not an applicable Department permitting standard. Even if it did apply, the Transmission Line would meet this criterion because it is designed to withstand 270 psi for at least 1,000 hours. Mr. Farabee believed that the entire Transmission Line would be pressure tested after the construction was complete, which would require digging up sections of the pipe to install bulkheads. However, this assessment of the County's testing program is incorrect. Leisha Pica, Deputy Director of the Water Utilities Department, developed the schedule for the project, helped develop the phasing of the work and budget, and oversaw the technical aspects. She stated that the County has successfully tested approximately fifty percent of the line that was already installed at 150 psi for two hours and not a single section of the line failed the test. Compaction The County has stringent backfilling and compaction requirements, which are sufficient to ensure the pipe will be properly installed and that there will be adequate compaction of the fill material. The County plans and specifications provide that compaction must be to ninety-five percent of the American Association of State Highway and Transportation Officials (AASHTO) standards for non-paved surfaces and one hundred percent of AASHTO standards for paved surfaces. Even ITID's expert agreed that the compaction specifications are sufficient. Mr. Farabee contended, however, that even though the standards are stringent, the County cannot properly test the installation for compliance with the standards. Mr. Farabee believed that testing of the backfill would be done after all of the construction was complete. In that case, he did not see how the testing could be done without digging many holes to check for the density of the backfill. These assumptions, however, are incorrect. The evidence shows that a total of two hundred sixty-four compaction tests have already been done on the portion of the Transmission Line that was completed. No part of the installation failed the tests. The County has an inspector who observes the installation and pressure tests. The compaction was tested at every driveway and major roadway, as well as every five hundred feet along the route. While Lander and D'Ordine pointed out at hearing that no compaction tests have been performed on the dirt roads which run adjacent to their property and on which construction has taken place, the Department requires that, before the work is certified as complete, non-paved roads must be compacted in accordance with AASHTO standards in order to assure that there is adequate compaction of the fill material. The Sufficiency of the Application When an application for an individual transmission/ collection line permit is filed with the Department, the applicant certifies that the design of the pipeline complies with the Department's standards. However, not all of the details of the construction will be included in the permit application. The Department relies on the design engineer to certify that the materials used are appropriate. The application form is also signed and sealed by a professional engineer registered in the State of Florida. All plans submitted by the County, including the original, modifications, and final version, were certified by professional engineers registered in the State of Florida. After receiving the application, the Department requested additional information before issuing the permit, and the County provided all requested information. The original construction plans that were submitted with the application were changed in response to the Department's requests for additional information. The Permit issued by the Department indicates the Transmission Line would be constructed with ductile iron pipe, but this was a typographical error. ITID maintains that all of the technical specifications for the project must be included in the application, and because no separate engineering report was prepared by the County with the application, the County did not meet that standard. While the County did not submit an engineering report, it did submit sufficient data to provide reasonable assurance that the project will comply will all applicable rules of the Department. As a part of its application package, the County submitted construction plans, which contain the specifications required by the Department. Also, the general notes included in the construction drawings specify the use of restrained joints where appropriate, the selection of pipe material, the pressure testing of the Transmission Line, and other engineering requirements. In addition, the plans contain numerous other conditions, which are also specifications sufficient to fulfill the Department's requirements. Finally, further explanation and clarification of the technical aspects of the application was given by the County at the final hearing. At the same time, the Department engineer who oversaw the permitting of this project, testified that a detailed engineering report was not necessary. This engineer has extensive experience in permitting transmission lines for the Department and has worked on over five hundred permits for wastewater transmission and collection systems. The undersigned has accepted his testimony that in a relatively straightforward permit such as this, the application and attachments themselves can function as a sufficient engineering evaluation. This is especially true here since the County is seeking only approval of a pipeline project, which would not authorize the receipt of wastewater flow unless other wastewater facilities are permitted. Impacts on Public and Private Drinking Water Wells As part of the design of the Transmission Line, the County located public and private drinking water wells in the area of the line. County personnel walked the route of the Transmission Line and looked for private wells and researched the site plans for all of the properties along the route. No public wells were found within one-hundred feet of the Transmission Line route, but they did find seventeen private wells that are within seventy-five feet of the line. None of the Petitioners have private wells that are within seventy- five feet of the line. While Petitioners D'Ordine and Hawkins initially contended that the well on Hawkins' property was within seventy-five feet of the Transmission Line, at hearing Mr. D'Ordine admitted that he "misread the plans and referred to the wrong property." In order to protect the private drinking water wells, Florida Administrative Code Rule 62-604.400(1)(b) requires that the County provide an extra level of protection for the wells that are within seventy-five feet of the Transmission Line. The County will provide that extra level of protection by installing restrained joints that will restrain the joints between the pipe sections. The restrained joints are epoxy-coated mechanical devices that reduce the tendency for the pipes to separate under pressure. The County has used these restrained joints on its potable water and wastewater lines in other areas of the County and has never experienced problems with the devices. The restrained joints will provide reliable protection of the private wells within seventy-five feet of the Transmission Line. The Department is unaware of any instances where restrained joints have failed in South Florida. If more wells are discovered that are within seventy-five feet of the Transmission Line, then the County will excavate the Line and install restrained joints. Minimum Separation Distances The County has complied with all applicable pipe separation requirements in the installation of the Transmission Line. More specifically, it is not closer than six feet horizontally from any water main and does not intersect or cross any reclaimed water lines. See Fla. Admin. Code R. 62-555.314(1)(a). It will be at least twelve inches below any water main or culvert that it crosses. See Fla. Admin. Code R. 62-555.314(2)(a). Finally, it will be a minimum of twelve inches below any culverts that it crosses. (However, the Department has no separation requirement for culverts crossed by the Transmission Line.) h. The M-Canal Crossing The Transmission Line must cross the M-canal, which runs in an east-west direction approximately midway between 40th Street North and Northlake Boulevard. The original design called for the Transmission Line to cross above the water, but the City and the Department suggested that it be located below the canal to eliminate the chance that the pipe could leak wastewater into the canal. In response to that suggestion, the County redesigned the crossing so that a 24- inch high density polyethylene pipe in a 48-inch casing will be installed fifteen feet below the design bottom of the canal. The polyethylene is fusion-welded, which eliminates joints, and is isolated with a valve on either side of the canal. Appropriate warning signs will be installed. See Fla. Admin. Code R. 62-604.400(2)(k)2.-5. The depth of the subaqueous line and the use of the slip line, or casing, exceeds the Department's minimum standards. See Fla. Admin. Code R. 62-604.400(2)(k)1. i. Flushing Protocol Section 48.1 of the Ten State Standard recommends that wastewater transmission lines maintain a velocity of two feet per second. When the Transmission Line becomes operational, it will not have sufficient flow to flush (or clean) accumulated solids from the lines at the recommended two feet per second velocities. (Sufficient flow will not occur until other customers connect to the Transmission Line during the first one to three years of operation.) Accumulated solids produce gases and odors that could create a problem at the treatment plant and might leak out of the manhole covers. To address this potential problem, Specific Condition 9 of the Permit requires the County to flush the lines periodically. Pursuant to that Condition, the County plans to flush the Transmission Line with additional water which will raise the velocity to three or four feet per second, so that the accumulated solids will be flushed. The water will be supplied by large portable tanks that will be temporarily set up at several locations along the Line. During the purging of the Line, sewage will collect in the pump stations until the purge is finished. There is sufficient capacity in the pump stations to contain the wastewater. In addition, the County will use a cleansing tool known as a pig, which is like a foam bullet that scrapes the sides of the pipe as it is pushed through the line. This protocol will be sufficient to keep the Line clean. ITID asserts that the County's plan for flushing is inadequate, because it does not provide enough water for long enough to flush both the 20-inch and 30-inch lines. Mr. Farabee calculated that the County would need almost twice the proposed volume, or almost six million gallons, to adequately flush the lines. ITID's analysis of the flushing protocol is flawed, however, because it assumes a constant flow in all segments of the pipe, which is not practical. In order to maintain the flushing velocity of three feet per second, the County will introduce water into the Transmission Line at three separate locations, resulting in a more constant flow velocity throughout the Transmission Line. In this way, it can maintain the proper velocity as the lines transition from a 20-inch to 30-inch to 36-inch pipe. The County has flushed other lines in the past using this protocol and has had no problems. This flushing protocol would only be in effect from one to three years. The County estimates that the necessary volumes to maintain a two-feet-per-second velocity in the 20- inch line would be reached in about one year. The 30-inch line should have sufficient flows sometime in 2008. These estimates are based on the signed agreements the County has with other utilities in the area to take their flows into the Transmission Line. Because of these safeguards, the Transmission Line will not accumulate solids that will cause undesirable impacts while flow is less than two feet per second. Other Requirements The construction and operation of the Transmission Line will not result in the release or disposal of sewage or residuals without providing proper treatment. It will not violate the odor prohibition in Florida Administrative Code Rule 62-600.400(2)(a). It will not result in a cross- connection as defined in Florida Administrative Code Rule 62- 550.200. The construction or operation of the Transmission Line will not result in the introduction of stormwater into the Line, and its operation will not result in the acceptance of non-domestic wastewater that has not been properly pretreated. If constructed and permitted, the Transmission Line will be operated so as to provide uninterrupted service and will be maintained so as to function as intended. The record drawings will be available at the Department's district office and to the County operation and maintenance personnel. Finally, concerns by the individual Petitioners that the County may not restore their property to its original condition after construction is completed are beyond the scope of this proceeding. At the hearing, however, the Deputy Director of the Water Utilities Department represented that the County would cooperate with the individual property owners to assure that these concerns are fully addressed. Reasonable Assurance The County has provided the Department with reasonable assurance, based on plans, test results, installation of equipment, and other information that the construction and installation of the Transmission Line will not discharge, emit, or cause pollution in contravention of the Department's standards.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order denying all Petitions and issuing Permit No. 0048923-017-DWC. DONE AND ENTERED this 18th day of October, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of October, 2005.

Florida Laws (4) 120.569120.57403.087403.973
# 5
# 6
FLORIDA POWER CORPORATION vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 91-002148 (1991)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 23, 1992 Number: 91-002148 Latest Update: May 10, 1993

The Issue On December 13, 1989, Florida Power Corporation (FPC) filed a wetland resource permit application with the Florida Department of Environmental Regulation (DER) for a project to construct, operate and maintain a 69 kilovolt (kV) electrical transmission line in Osceola County. The application described the placement of power line poles in jurisdictional wetlands. On September 28, 1990, DER issued its notice of permit denial, DER File No. 49-173789-4. The ultimate issue for determination is whether FPC is entitled to the permit. Ancillary issues include the scope of "cumulative impacts" to be considered; the scope of "secondary impacts"; whether alternative sites must be considered; whether FPC's clearing of the right of way constituted dredge and fill activity; and whether mitigation is required, and if so, whether the mitigation offered by the applicant is adequate.

Findings Of Fact FPC, whose headquarters are located at 3201 34th Street, South, St. Petersburg, Florida, 33733, is required by Florida Statutes and regulations promulgated by the Florida Public Service Commission (PSC) to provide electric utility service in the vicinity of the proposed transmission line. DER, 2600 Blair Stone Road, Tallahassee, Florida 32399-2900 is an executive agency directly responsible for prevention of pollution of the air and waters of this State. Pursuant to that obligation, Sections 403.91-403.929, Florida Statutes, and Chapter 17-312, F.A.C., DER regulates proposed dredging and filling activities in waters of the State. FPC, pursuant to its statutory and regulatory mandate, transmits electricity through 33 counties within the state, providing actual service to customers in 32 counties. FPC's electrical transmission lines range in voltage capacity from 69 kV (69,000 volts) to 500 kV (500,000 volts). Considering other utilities, there are approximately 7,000 miles of 69 kV electrical transmission lines within the state, over 1,855 miles of which are operated and maintained by FPC. The Project The electrical transmission line at issue in the instant proceeding will traverse approximately 10 miles. It intercepts two areas of jurisdictional wetlands; however, the main point of contention in the permitting proceeding is the six acres of wetland vegetation which have been cleared in the vicinity of where the transmission line corridor intersects the main crossing of Reedy Creek. The original application for this project was 14 miles long; however, FPC and DER agreed to modify the application by separating the northern-most four miles of the project and submitting it as a separate application. The northern segment starts at the Intercession City substation and proceeds easterly along an existing transmission line corridor in the right of way of SR 17/92 to Old Tampa Road and then turns south terminating at the Poinciana Industrial Park. The proposed transmission line which is the subject of this proceeding starts from the Poinciana Industrial Park and proceeds south, then crosses Reedy Creek in a northeast to southwest direction and continues south, ultimately terminating at the Poinciana substation. There are references in the application to a 72 kV line. 72,000 volts is the maximum operating voltage. 69,000 volts is the normal daily load. Direct dredge and fill impacts associated with the proposed construction include 301 cubic yards of fill, which includes the wooden transmission poles as well as crushed rock backfill at the base of those poles. This fill material would be placed over .00846 acres. This fill amount equates to an area analogous to a 20 foot by 20 foot room. Initial placement and continued maintenance of the poles and lines require clearing. This enables access by equipment and prevents vegetation from interfering with the lines. Clearing is essential for the safety and reliability of the electrical power distribution system. The wood electrical transmission line poles will be spaced approximately 300 foot apart in an area of vegetation clearing 60 feet wide. The major jurisdictional area north and south of the Reedy Creek crossing is approximately 4,400 feet long. The Applicant will, after construction, undertake corridor maintenance on a three to five year cycle. An area will be kept clear 50 foot square around each wooden pole structure along the proposed transmission line. Vegetation will be maintained at ground or water level for 17 feet on either side of the wooden utility poles. The outer 13 feet on each side will be allowed to regenerate except for fast growing trees and other vegetation with the potential to reach 30 feet prior to the next regularly scheduled maintenance period. Fast growing trees within the 13 foot outer area on either side of the corridor will be girdled or treated with herbicides by specific and selective application. The only herbicides to be used will be those that are EPA approved for use in the State of Florida. All exotic or nuisance target species will be removed from the entire right of way as part of FPC's maintenance program. The Application Process FPC submitted a wetland resource permit application for this project on December 6, 1989, received by the DER Central Florida District on December 13, 1989. DER requested additional information on January 12, 1990, and the Applicant submitted responses by letter dated April 20, 1990. On May 18, 1990, DER submitted a second request for additional information, which was responded to by FPC at a meeting with DER Central District staff in Orlando on June 5, 1990, and by a follow-up letter dated June 20, 1990. Neither of DER's requests for additional information required information relative to alternate routes for the proposed transmission line; however, a letter from DER to FPC dated June 20, 1990 states that mitigation would be required since an alternative route was not presented and impacts could not be reduced any further. The application was deemed complete on June 22, 1990. Subsequently, FPC proposed a preservation mitigation of 1:1 ratio by offering for preservation a 6-acre area of Reedy Creek Swamp near the Intercession City substation. FPC waived DER's 90 day statutory time clock in which it has to act on complete permit applications until October 1, 1990. The DER Central District Office issued a notice of permit denial regarding FPC's project on September 28, 1990. The maintenance plan described in paragraph 6, above, includes a departure from FPC's past practices. The plan and specifics of the 13-foot border areas were provided to DER during the hearing on December 3, 1991. Without objection by DER, the hearing proceeded on the application thus modified. Reedy Creek Swamp and the Project Context Reedy Creek Swamp is located in Orange, Osceola and Polk Counties. It is the only large mixed wetland forest system in Osceola County and is one of the largest systems in central Florida. It provides valuable forested wetland habitat for numerous plant and animal species. The proposed dredging and filling activity which is the subject of this application occurs in the South Reedy Creek basin. It is part of the Reedy Creek and its associated floodplains and uplands that drain south-southeast of Interstate-4. South Reedy Creek basin, as described in the instant proceeding, consists of over 92,000 acres of upland and wetland habitats. Approximately 31,448 acres of contiguous forested wetland are contained within that 92,000 acres. Based on the limited nature of the project's corridor, the six acre disturbance has been correctly characterized as de minimis. Since the turn of the century the South Reedy Creek basin has been the subject of extensive logging and silviculture impacts through either clearcutting or selective timbering which continues to this day. The basin is also the subject of an ongoing effort by the South Florida Water Management District for land aquisition and management. Approximately 7,000 acres of the basin have been bought or are under plans to purchase for protection. Commercial and environmental interests command the basin's resources. Clearing the Way FPC's clearing of the six acres of forested wetland was accomplished from March 12 through June 7, 1990. Clearing occurred during the processing of the dredge and fill application in order to take advantage of dry conditions and to facilitate bringing the electrical transmission line into service in accordance with FPC's established schedule. All vegetation in the wetland area was removed at ground or water level and the material was then either burned on site or removed to upland locations. Charles Duncan, FPC's chief inspector for transmission line construction, made regular spot investigations of all construction and assured that the hand clearing and low pressure rubber wheeled and tracked vehicles used by FPC did not result in significant soil disturbance. It is unrefuted that between June and November 1990, well after FPC's clearing was completed, considerable silvicultural activity occurred immediately adjacent to the corridor, both east and west. John Vogel, an expert in forestry and the effects of clearcutting, provided photographic evidence of those silvicultural entities' use of the corridor and identified the adjacent property owner as the party actually responsible for that activity. These facts, and DER employee Don Medellin's tacit admission that what he saw on his June 7, 1990, site inspection clearly could have been accomplished by parties other than FPC, leads to the specific finding that no FPC-initiated dredging and filling has occurred within the corridor. Dredging and filling will occur when the poles are placed. The evidence submitted by FPC, including rainfall and flow discharge information for the relevant time period, closely corroborate Mr. Duncan's eye witness accounts that clearing was conducted during a period when the wetland areas were extremely dry. Mr. Duncan further noted that the dry conditions precluded the burning of all of the collected and stockpiled debris beyond the week of June 7, 1990, and those conditions account for some of Mr. Medellin's observations of stockpiled material during his visit to the site on June 7, 1990. Considering the site conditions at the time of clearing and the absence of running water within Reedy Creek itself, there were effectively no water quality consequences to the creek from the clearing activity. Silt screens were constructed on the site on May 1, 1990, and according to Dr. Miles Smart, an expert in water chemistry and limnology, that precaution adequately safeguarded water quality within Reedy Creek during subsequent rain events. DER witness, Don Medellin, confirmed that the Department had no knowledge of any water quality violations having occurred during the FPC construction activity. The Public Interest Criteria Much, if not all, of the Department's opposition to the proposed project is based on the clearing of vegetation as opposed to pole placement and filling associated therewith. In this case the impacts of the clearing are already known. In the traditional dredge and fill case, the applicant provides evidence, testimony and test results predicting the impacts of the proposed construction activity, whereas in the instant case, the Applicant has the benefit of providing reasonable assurances by documenting the consequences of its acts. In the instant case, FPC provided a detailed analysis of biological and water quality ramifications from its clearing. DER presented several witnesses who contested the positive or neutral effects that the proposed transmission line corridor would have on wildlife, citing nest parasitism, predation, fragmentation, and reduction in patch size as examples of adverse impacts that the proposed line could impose on wildlife. DER witness, Dr. Francis Putz, testified that the project could cause unraveling of the forested wetland and sunscalding of newly exposed trees along the edge of the corridor. However, no DER witness presented any quantitative data or analyses that would indicate that any of the possible adverse consequences mentioned above were, in fact, occurring or reasonably likely to occur in Reedy Creek as a result of FPC's project. It is undisputed by either party that clearing of the proposed transmission line corridor resulted in a change to that specific six acre area from a forested wetland to a herbaceous/shrub wetland. Furthermore, it is undisputed that FPC's proposed maintenance practices will maintain that change over the expected 30-year operational life of the transmission line. However, different is not synonymous with adverse. The structural change to the wetland has not had, and will not have, any deleterious consequences to water quality within Reedy Creek. Dr. Miles Smart, the only expert in water chemistry and limnology to testify, presented testimony, based on samples of water quality in Reedy Creek and available historical water quality data, that water quality approximately a year and a half after initial clearing was no different than the ranges observed over the ten year period for which historical information was available. In most cases, water quality was the same or extremely close for the sampled parameters which included water temperature, pH, dissolved oxygen, alkalinity, turbidity, concentrations of nitrogen, phosphorous, total kjeldahl nitrogen and orthophosphate nitrogen. FPC's proposed maintenance practices which include the use of EPA approved herbicides for use in control of target species, will pose no problem to water quality. A study of twenty-two transmission line rights of way in the State of New York found virtually no water quality problems as a result of maintenance of those transmission lines. It was uncontroverted that FPC has never experienced water quality violations as a result of its management practices, nor has it been the focus of any enforcement or noncompliance action with respect to any previous clearing or construction activity it has undertaken. The clearing created no impediment to flow or impounding. The continuing use of silt screens and hay bales by FPC during pole installation will reduce the likelihood of erosion or shoaling. Extensive ground cover currently present in the corridor and FPC's proposed preservation of this herbaceous/shrub vegetation will further minimize any possible shoaling and erosion. Vegetative surveys conducted approximately a year and a half after the initial clearing show that the corridor has revegetated with 85 percent mean herbaceous plant cover in the corridor. Species composition of vegetation is similar in the corridor and no new species have been introduced nor have any been eliminated as a result of the clearing activity. Based on primary productivity and decomposition rate studies, FPC's clearing activity and the vegetative change that has resulted predictably should increase net primary productivity threefold over what exists in the adjacent forest, primary productivity being simply biomass accumulated over a period of time. Several DER witnesses testified to the possible introduction of nuisance or invader species as a result of FPC's clearing activity and subsequent maintenance of the corridor. However, FPC's proposed maintenance practices will eliminate those target species which inhibit the growth of other species, resulting in a wetland community having similar shrub and herb strata to that of the adjacent forest. DER admitted that any proliferation of nuisance species can be controlled with proper management techniques and has required such control as mitigation for clearing associated with an electrical transmission line project by Florida Power and Light Company in Lee County. Left to natural processes, the cleared corridor would eventually return to a forested area similar in species composition to the adjacent forest within several years. This rapid regeneration comports with experiences in other transmission line projects and in the silviculture industry. Qualitative analysis of other utility corridors in the Central Florida region confirm this natural process of succession. One of those projects, the Tampa Palms Corridor Improvement Project, constructed in a large forested wetland similar to the Reedy Creek Swamp, revealed that in 25 years after clearing, trees had regenerated to heights of 10 to 50 feet with corresponding diameters at breast height ranging from 2.7 to 30.5 centimeters. John Vogel, an expert in forestry and the effects of clearcutting, provided unrefuted testimony and photographic evidence of a clear cut site in the South Reedy Creek basin where after a period of 8 years rapid revegetation and reforestation was occurring, resulting in a fully stocked pre-commercial stand of timber. Several DER witnesses indicated that FPC's manner of cutting trees at ground or water height could have adverse effects on the ability of tree species to regenerate. However, this was refuted by the evidence of tree coppicing ( sprouting within the cut-off stumps) within the corridor with some canopy species having coppices over six feet tall in the 18 month period since FPC's initial clearing. DER employee, Donald Medellin, indicated at hearing that the clearing and proposed maintenance activity of FPC may impact a limited number of plant species listed as threatened. The Applicant's onsite analysis established that Tillandsia, a species listed in Chapter 581, Florida Statutes, as endangered, does exist in the adjacent forest in large numbers. No species referenced by Mr. Medellin appear on any federal endangered or threatened plant species list. Certain referenced plants appear on various state lists; however, none of these lists preclude the clearing of such vegetation with permission of the landowner. FPC's proposed maintenance activities for this project would not threaten the continuing existence of any of those species. The loss of some individual plants as a result of FPC's initial clearing was inconsequential, and continued maintenance of the corridor will not impact the species' continuing existence in the area. The change from forested to herbaceous wetland was demonstrated to have had no adverse effect on the conservation of fish and wildlife in the South Reedy Creek basin. An extensive quantitative analysis undertaken by J. Steven Godley established that aquatic organisms (i.e., fish, aquatic amphibians, and reptiles), invertebrates, mammals, and birds have not been negatively impacted by FPC's initial clearing of the transmission line corridor. It was uncontroverted that the project has occasioned a twofold increase in the number of aquatic organisms in the corridor as compared to the adjacent forest. Even though wildlife surveys conducted over 1,000 manhours revealed no measurable impact to any species of wildlife, Mr. Godley constructed a theoretical listing of several species of vertebrates indigenous to the Reedy Creek Swamp system which were likely to use the swamp system in an average year or at least a part of their life cycle, in order to assess the possible impact of the corridor on those species. Mr. Godley's unrefuted analysis revealed that the vast majority of all species of the various groups (fish, amphibian, reptiles, mammals, birds) are expected to be either positively affected or not affected at all by FPC's proposed project. DER witness, Dr. Herbert Kale, testified that some bird species such as red-eyed vireos, warblers, woodpeckers and thrushes could possibly be impacted due to the loss of forested canopy since they are cavity nesters, and because of nest parasitism by the brownheaded cowbird. Dr. Kale readily admitted, however, that the transmission line swath was small and was not fatal to any of those interior forest bird species. Moreover, his testimony regarding the nest parasitism was inherently contradictory, since the cowbirds breed in winter during a period when the other species are actually in Central and South America. The wetland change occasioned by FPC's project will not adversely affect endangered or threatened wildlife species. The only reptile likely to occur in the Reedy Creek Swamp that is either threatened, endangered or a species of special concern is the indigo snake, which will likely be positively impacted by the corridor, as it feeds on aquatic organisms in the swamp. No listed mammals will be impacted by the corridor. Three species of wading birds, the wood stork, little blue heron and snowy egret, will be positively affected by the transmission line corridor as they, too, will be provided excellent feeding habitat. DER's witness, Dr. Kale, agreed that the change will provide additional habitat for marsh wading birds. The only other possible endangered species that may occur in the swamp is the bald eagle. Since bald eagles prefer large water bodies, they are unlikely to occur. They would benefit, however, from the enhanced feeding habitat. Existing literature regarding the ecological impacts of clearcutting and electrical transmission line corridors on wildlife is consistent with the quantitative evidence submitted by FPC. Existing scientific literature generally reflects that transmission line rights of way cause edge effect, defined as a transition between two or more diverse communities. This edge causes an increase in species number and diversity for wildlife in the corridors, as compared to the adjacent forest. This is particularly true of bird species. For small mammals there is either a nonsignificant difference in species numbers in the corridor as compared to the adjacent forest, or there is a larger small mammal diversity within the corridor as opposed to the adjacent forest. The same applies for larger mammals and game species. The applicant's witnesses touted edge effect as essentially positive, while DER's witnesses described the phenomenon as a negative impact, since any new species are already abundant in other habitats. No finding is made generally on this issue, but rather in this case it is concluded that edge effect is not so significant as to constitute a negative consequence of the project. Based on the weight of empirical evidence and opinion testimony presented, wildlife species residing in the South Reedy Creek basin have been and will continue to be either positively affected or not affected at all by FPC's proposed project. Moreover, the overall productivity of the wetland from the standpoint of vegetation and wildlife, when balanced across all plant and animal species, has not and will not be negatively affected. Although the opportunities for recreational activities are limited in South Reedy Creek basin due to the inaccessibility of the site, those activities such as hunting, fishing, and bird watching are unchanged or have improved as a result of the small localized change to a herbaceous/shrub wetland. The need for the electrical transmission line was unrefuted. FPC must meet minimum service standards in its provision of electric power as set out by the PSC. In order to meet these service standards, FPC decided, through its internal system planning and modeling, that a new 69 kV electrical transmission line was required between its Intercession City and Poinciana substations to provide a more reliable source of power to the towns of Davenport and Haines City as well as the Parker-Poinciana 55,000 unit residential development, as these areas have experienced problems with low voltage. The demonstrated need for this facility and the public benefit which DER has admitted it will provide, when balanced with minimal changes to the forested wetland system, lead to the finding that this project is not contrary to the public interest. Cumulative Impacts DER failed to present any evidence disputing the hydrologic and biologic validity of the boundaries of the South Reedy Creek basin or the location of existing and proposed electrical transmission lines in that system. The only other projects suggested by DER for cumulative impact analysis were several projects consisting of construction of berms, roads and pipelines, as well as proposed developments of regional impact (DRI's). However, these projects were not shown to be similar in construction or amount of impact to FPC's proposed electrical transmission line, except for their linear nature. Unlike this project, roads, berms, pipelines and residential developments remove wetlands. It was not established that all the project applications considered by DER for cumulative impacts were within the South Reedy Creek basin. Instead, several DER witnesses alluded to the loss of forested wetlands allegedly occurring throughout the state. The evidence was anecdotal and unreliable. DER cited an analysis showing a three percent decline in forested wetlands, but the study combined both South Carolina and Florida acreages. Of the existing and proposed transmission lines within a 10 year planning horizon, very few (only three) will directly cross any portion of the South Reedy Creek basin. Those proposed electrical transmission lines will be co-located along existing rights of way and will have little, if any, impact on the forested component of the South Reedy Creek basin. It was undisputed that as a general proposition, the construction and operation of electrical transmission lines vital to the provision of electrical service does not stimulate subsequent development in an area but, in fact, follows development where electrical services are projected to be needed. Logging has occurred extensively in this area in the past and there is no evidence that the 60 foot corridor has induced additional logging activity, as asserted by DER. Consideration of Alternative Routes and Methods Having identified the need for a new transmission line, FPC conducted an intensive route selection analysis taking into account environmental, property (real estate), economic, and construction considerations. In this case, FPC considered two routes to address the electrical needs of this area: the recommended route, which is the subject of this proceeding, and an alternate route to the east and along an existing roadway. The alternate route would still have crossed Reedy Creek and its contiguous wetlands at some point in order to connect to the Poinciana substation. Both of the proposed corridor routes are within FPC's service territory. A consideration in choosing the recommended route was its proximity to existing and proposed substations. The alternate route would have necessitated more vegetative clearing in the future, as its location was not near proposed substations in this area. Moreover, the recommended route was aligned through the narrowest portion of the South Reedy Creek basin through what was an old tram railbed used by the logging industry. Major property owners in the area of the proposed line expressed their preference for the recommended route. The landowner for most of the proposed corridor south of the Reedy Creek crossing granted easements at no cost to FPC. FPC fully participated in the give and take of the permit application process for this project with DER. It was unrefuted that FPC employee, W. Jeffrey Pardue, met with a DER employee prior to submittal of the application during which meeting the two routes were discussed. The only concern about the project expressed by DER at that meeting was construction of access roads. In response to this concern, and prior to application submittal, FPC's transmission line was redesigned to consist of only wooden pole structures requiring shorter span construction and allowing less right-of-way clearing, since the transmission line wires would not move as much due to wind or other weather conditions. Wood pole construction will also allow for the use of low pressure, high flotation, equipment for construction and maintenance of the transmission line, thereby obviating the need for access roads. Mitigation: The policy applied In order to appease DER's demand for mitigation, FPC entered into negotiations with DER and offered the preservation of six acres of existing wetlands located east of its Intercession City substation adjacent to State Road 17/92, an area vegetatively similar to the area affected. Mitigation is the reduction or elimination of actual or anticipated adverse effects caused by a wetland project. Mitigation, as evolved in DER's permitting processes, can be the creation of new wetlands to replace those destroyed, the enhancement of an existing wetland, or preservation of an existing wetland other than that impacted by the project. Because preservation as a mitigation measure does not replace lost wetlands, DER has consistently required a preservation ratio of more than 1:1, most often 10:1, and sometimes substantially more than 10:1. The requirement is based on a case by case analysis of the quality of the wetland impacted, the extent of the impact and the quality of the wetland offered for preservation by the applicant. Clearing, without more, is not considered a dredge and fill activity and therefore has not, alone, required a DER permit. Clearing has not, therefore, been the subject of mitigation requirements in the past. Until the recent past, DER has not applied its mitigation policy to clearing associated with construction and maintenance of electrical transmission lines. Most of those lines have been placed along roadways and other existing corridors with little additional impact to jurisdictional areas. DER has required mitigation for other linear configured projects such as pipelines and the unique "Maglev" project, a high speed elevated train proposed to be constructed from the Orlando Airport to a tourist center in Orange County. DER is presently requiring power companies in three power plant or transmission line siting cases to address the secondary impact of clearing. Until the review of impacts is complete, the DER staff cannot predict what and how much mitigation will be required in those cases. Prior to the instant case, DER Chief of the Bureau of Wetland Resource Management, Janet Llewellyn, could identify only one instance of mitigation for clearing associated with an electrical transmission line: the Florida Power and Light Company line in Lee County addressed in paragraph 21, above. The "mitigation" required in that case is already proposed in FPC's maintenance plan. DER in this case has adequately justified its policy of considering secondary impacts of clearing related to the construction and maintenance of electrical transmission lines. Those impacts are legitimately assessed when the need for mitigation is being considered. The nature and extent of secondary impacts from clearing are properly part of the discourse and review of the nature and extent to which mitigation will be required. The need for mitigation, however, is not reached when no adverse impacts are found. Here, the applicant has successfully demonstrated by the substantial weight of evidence that neither the clearing already completed, (albeit precipitately) nor the planned pole and line construction and future right of way maintenance will violate water quality standards or otherwise offend the public interest criteria of Section 403.918, F.S. The application of DER's mitigation policy is unnecessary in this case.

Recommendation Based on the foregoing, it is, hereby RECOMMENDED: That the agency enter its final order granting the application for permit #49-173789-4. DONE and RECOMMENDED this 19th day of February, 1992, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1992. APPENDIX TO RECOMMENDED ORDER The following constitute specific rulings on the findings of fact proposed by the parties. Petitioner's Proposed Findings Adopted in paragraph 1. Adopted in paragraph 2. Adopted in paragraph 3. Adopted in paragraph 4. Adopted in paragraph 5. Adopted in paragraph 6. Adopted in paragraph 7. Adopted in paragraph 11. Adopted in paragraph 12. Adopted in paragraph 13. Adopted in paragraph 9 and paragraph 10. Adopted in paragraph 14. Rejected as unnecessary. Adopted in paragraph 15. Rejected as unnecessary. Adopted in paragraph 16. Adopted in paragraph 17. Adopted in paragraph 18. Adopted in paragraph 19. Adopted in substance in paragraph 20. Adopted in substance in paragraph 21. Adopted in substance in paragraph 22. Adopted in substance in paragraph 23. Adopted in substance in paragraph 24. Adopted in substance in paragraph 25. Adopted in substance in paragraph 26. Adopted in substance in paragraph 27. Adopted in paragraph 28. Adopted in paragraph 29. Adopted in paragraph 30. Adopted in paragraph 31. Adopted in paragraph 32. Adopted in paragraph 33. Adopted in part in paragraph 34, except for the proposed finding that forested wetlands are increasing, which finding is not supported by reliable, nonhearsay evidence. Adopted in paragraph 35. Adopted in paragraph 36. Adopted in paragraph 37. Adopted in paragraph 38. Adopted in paragraph 39. Rejected, except for the conclusory finding that mitigation is not necessary here because of no finding of adverse impacts. See paragraph 44. The proposed findings related to the error of the policy generally are rejected as contrary to the evidence. Respondent's Proposed Findings Adopted in paragraph 7. 2.-3. Adopted in paragraph 4. 4.-5. Adopted in part in paragraph 7. Rejected as unnecessary. Rejected as contrary to the evidence (as to any implication that dredging and filling was done by the applicant); otherwise adopted by implication in paragraph 11. Adopted in substance in paragraph 11. 9.-10. Adopted in substance in paragraph 7. Adopted in substance in paragraph 39. Adopted in substance in paragraph 7. Adopted in substance in paragraph 4. Adopted in substance in paragraphs 6 and 7. Adopted in substance in paragraph 5. Adopted in substance in paragraph 6. Adopted in substance in paragraph 5 and conclusions of law #3. Rejected as contrary to the evidence. The clearing conducted by FPC did not constitute dredge and fill activity. 19.-22. Adopted in substance in paragraph 11. 23.-24. The conclusion that logging activity is a secondary impact of the FPC is rejected as wholly unsubstantiated by competent evidence. Adopted in paragraph 8. Adopted in part in paragraph 8, otherwise rejected as contrary to the weight of evidence. Rejected as unnecessary. Adopted in substance in paragraph 24. Adopted in paragraph 10. Adopted in paragraph 16. Rejected as unsupported by competent, credible evidence. 31(a). Rejected as contrary to more substantial evidence and, as to recreation mitigation, unnecessary. 32.-33. Rejected in substance as unsubstantiated by the weight of evidence. Rejected as unnecessary. Rejected as contrary to the weight of evidence. 36.-38. Rejected as unnecessary. FPC will remove the nuisance species as part of its maintenance plan. 39.-47. Rejected as contrary to the greater weight of evidence. 48.-50. Rejected as unsubstantiated by competent evidence. 51.-52. Rejected as contrary to the weight of evidence. Adopted in paragraph 17. Rejected as unnecessary. The construction activity could have, but did not cause water quality violations. See paragraph 13. 55.-58. Rejected as unnecessary. 59. Rejected as contrary to the evidence. The logging activity was occurring long before and during the relevant period and was not caused by the FPC project. 60.-76. Rejected as irrelevant or contrary to the weight of evidence. Adopted in paragraph 32. Adopted in paragraph 36. 80.-87. Rejected as irrelevant. 88. Adopted in part in paragraph 42. That mitigation is required is rejected as contrary to the evidence. 89.-90. Adopted in paragraph 39. Rejected as unnecessary. Adopted in part in paragraph 42, otherwise rejected as an enforcement issue and irrelevant here. Adopted in paragraph 40. Adopted in substance in paragraph 40. 95.-106. Rejected as unnecessary. COPIES FURNISHED: Frank E. Matthews, Esquire Michael P. Petrovich, Esquire Hopping, Boyd, Green & Sams O. Box 6526 Tallahassee, FL 32314 Douglas MacLaughlin, Esquire Office of the General Counsel Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (6) 120.57120.68267.061380.06403.0616.01
# 7
FLORIDA POWER CORPORATION, POLK COUNTY PROJECT (PA 92-33) vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 92-005308EPP (1992)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Aug. 28, 1992 Number: 92-005308EPP Latest Update: Nov. 29, 2001

The Issue In this proceeding, Florida Power Corporation (FPC) seeks approval to construct and operate 470 MW of natural gas-fired advanced design combined cycle (NGCC) generating capacity at its proposed Polk County Site. Additionally, FPC seeks a determination that the Polk County Site has the environmental resources necessary to support an ultimate capacity of 3,000 MW of combined cycle generating capacity fueled by a combination of natural gas, coal-derived gas and distillate fuel oil. Such an ultimate site capacity certification may be granted pursuant to Section 403.517, Florida Statutes and Rule 17-17.231, Florida Administrative Code.

Findings Of Fact Project Site and Vicinity FPC's proposed Polk County Site is located on approximately 8,200 acres in southwest Polk County, Florida, in an area dominated by phosphate mining activities. The Polk County Site is approximately 40 miles east of Tampa, 3 miles south of Bartow and 3.5 miles northwest of Fort Meade. Homeland, the nearest unincorporated community, lies about one mile to the northeast of the site boundary. The Polk County Site is bounded on the north by County Road (CR) 640 and along the southeast and south by a U.S. Agri-Chemical Corporation (USAC) mine. CR 555 runs north-south through the site. The Polk County Site is comprised of land in four different phases of mining activity: mine pits, clay settling ponds associated with phosphate mining, land which has been mined and reclaimed, and land which has yet to be mined. Approximately one-half of the Polk County Site is subject to mandatory reclamation. Land uses adjacent to the Polk County Site consist almost entirely of phosphate mining activities. One mobile home is located at the intersection of CR 640 and CR 555 approximately 2 miles from the proposed location of the principal generating facilities. General Project Description The initial generating capacity at the Polk County Site will be NGCC units. Under what has been designated as the Case A' scenario, ultimate site development will consist of 1,000 MW of NGCC and 2,000 MW of CGCC generating capacity, for a total of 3,000 MW. Under the alternative Case C scenario, the ultimate site capacity would consist of 3,000 MW of all NGCC capacity. The Case C scenario was initially developed as the worst case scenario for the socioeconomic impact analysis (i.e., the one that would produce the least amount of economic benefit.) The combined cycle units which initially burn natural gas can be modified to burn coal gas if necessary to meet changes in fuel supply or pricing. However, under the proposed ultimate site capacity, CGCC generating capacity will be limited to a maximum of 2,000 MW out of the total of 3,000 MW. At ultimate buildout the major facilities at the Polk County Site will include the plant island, cooling pond, solid waste disposal areas, and brine pond. The plant island will be located on mining parcels SA-11, SA-13 and the northerly portion of SA-12. The plant island ultimately will contain the combined cycle power block, oil storage tanks, water and sewage treatment facilities, coal gasification facilities, coal pile and rail loop, and coal handling facilities. The cooling pond at ultimate buildout will be located in mining parcels N-16, N-15 and N-11B, with a channel through N-11C. Mining parcels N-11C, P-3, Phosphoria, Triangle Lakes and P-2, if not used as a solid waste disposal area, will be used as water crop areas to collect rainfall for supplying the cooling pond. The brine pond will receive wastewater reject from the reverse osmosis (RO) water treatment system and will be located on mining parcel SA-9. Two solid waste disposal areas (SWDA) are planned for ultimate development of the Polk County Site. The SWDAs will be mining parcel SA-8 initially and mining parcel P-2 in later phases, if necessary. Coal gasification slag will be the predominant solid waste to be disposed of in the SWDAs. Other areas included within the Polk County Site are mine parcels N- 11A, N-13, N-9B, Tiger Bay East, Tiger Bay, the northerly 80 acres of N-9, SA-10 and the southerly 225 acres of SA-12. Along with providing a buffer for the Polk County Site facilities, these parcels also will provide drainage to Camp Branch and McCullough Creek. Linear facilities associated with the initial 470 MW of generating capacity at the Polk County Site will include a 230 kilovolt (kV) transmission line upgrade, a reclaimed water pipeline, and a backup natural gas pipeline. Site Selection A comprehensive process was used to select the Polk County Site. The goal of that process was to identify a site which could accommodate 3,000 MW of generating capacity and offer characteristics including: (1) multi-unit and clean coal capability; (2) technology and fuel flexibility; (3) cost effectiveness; (4) compatibility with FPC's commitment to environmental protection; (5) ability to comply with all government regulations; and (6) consistency with state land use objectives. The site selection process included the entire State of Florida. Participants in the site selection process included a variety of FPC departments, environmental and engineering consultants, and an eight-member Environmental Advisory Group (EAG) composed of environmental, educational, and community leaders. In October, 1990, with the concurrence of the EAG, the Polk County Site was selected. The ultimate basis for the selection of the Polk County Site was the disturbed nature of the site as a result of extensive phosphate mining activities. The Polk County Site also is compatible with FPC's load center and transmission line network, and is accessible to rail and highway transportation systems. PSC Need Determination On February 25, 1992, the PSC issued Order No. 25805 determining the need for the first 470 MW of generating capacity at the Polk County Site. The PSC concluded in its order that the first two combined cycle units (470 MW) at the Polk County Site will contribute to FPC's electric system reliability and integrity. It also concluded that the first two units would enable FPC to meet winter reserve margin criteria and to withstand an outage of its largest unit at the time of system peak demand. The PSC stated that it was important for FPC to secure a site to meet future needs and that the first two units would contribute toward this goal. Basis for Ultimate Site Capacity The Site Certification Application (SCA), including the Sufficiency Responses, addressed the impacts associated with 3,000 to 3,200 MW of generating capacity under several scenarios. FPC eliminated or modified several of the scenarios by filing a Notice of Limitations which addressed the capacity and environmental effects of 1,000 MW of NGCC and 2,000 MW of CGCC generating capacity at the Polk County Site. Throughout the SCA, Sufficiency Responses and Notice of Limitations, the capacity constraints and environmental effects were analyzed under a worst case scenario, i.e., the maximum environmental effects that could be expected at ultimate site capacity. An ultimate site capacity determination will significantly reduce the time and expense associated with processing supplemental applications for future units at the Polk County Site under the expedited statutory procedures of the Power Plant Siting Act. This will allow FPC to respond more quickly to changes in growth and demand. An ultimate site capacity determination also provides FPC the assurance that the Polk County Site has the land, air and water resources to support future coal gas-fired generating capacity. Project Schedule and Costs Construction of the initial 470 MW of NGCC generating capacity is scheduled to begin in 1994. These units will go into operation in 1998 and 1999. Based on current load forecasts, it is expected that approximately one 250 MW unit will be added every other year to the Polk County Site. Under this schedule, ultimate site development of 3,000 MW would occur about 2018. Capital investment for the Polk County Site is expected to be approximately $3.4 billion for the 1,000 MW NGCC/2000 MW CGCC Case A' scenario and approximately $1.7 billion for the all NGCC Case C scenario. Project Design Generating units for the Polk County Site will be advanced design combined cycle units firing natural gas and/or coal gas, with low sulfur fuel oil as backup. Each combined cycle unit will consist of one or two combustion turbines (CT), a heat recovery steam generator (HRSG) for each CT and one or two steam turbines (ST). The first 470 MW of generating capacity will consist of two CTs firing natural gas, two HRSGs and one or two STs. At ultimate site capacity, the Polk County Site will consist of 12 CTs, 12 HRSGs, and 6 to 12 STs. A combined cycle unit is a generating system that consists of two sequential generating stages. In the first stage, the natural gas, coal gas or fuel oil is burned to operate the CT. Hot exhaust gas from the CT is passed through the HRSG to produce steam to operate the ST. The CT and steam from the HRSG can be arranged to drive individual generators or a single generator. In later phases of the Polk County Site, up to 2,000 MW of combined cycle generation may be fired on coal gas. The combined cycle units that were initially constructed to operate on natural gas can be modified to operate on coal gas. Under the Case A' scenario, two coal gasification plants would be built to produce coal gas for the combined cycle units. Associated with the coal gasification phase of the project will be the expansion of the plant island to accommodate the storage and handling of coal. Coal will be transported onsite by railroad. A rail loop for coal trains will be constructed on the plant island. It will be sized to accommodate a 100-car coal train. The coal storage area and limestone stockout will be located within the coal loop. Limestone is used in the coal gasification process as a fluxing agent to improve the viscosity of the coal slag, a by-product of the coal gasification process. The coal storage area, including the coal piles and emergency coal stockout system, will be lined with an impervious liner, and runoff from the coal storage area will be recycled to the coal gasification plants. The cooling pond for the Polk County Site will be located north and east of the plant island. Water from the cooling pond will be used for producing steam and condenser cooling. The cooling pond will be constructed initially in mining parcel N-16 and then in parcels N-15 and N-11B for later phases. These areas are mined-out pits which are surrounded by earthen dams. These dams will be upgraded where required to provide stability equivalent to the requirements of Chapter 17-672, Florida Administrative Code, for phosphate dams. Soil and Foundation Stability To evaluate the existing soil conditions at the Polk County Site, more than 165 test borings were made. The plant island is an existing mine pit which has been partially filled with sand tailings from phosphate mining operations. Underlying the sand is the Hawthorn formation which is often used as the base for deep load bearing foundations. Foundations for the heavier loads of power plant facilities will require pile foundations or similar types of deep foundations that will extend into the Hawthorn formation. The potential for sinkhole development at the Polk County Site was investigated by reviewing historic sinkhole records, aerial photographs, well drillers' logs, and by drilling three deep borings at the site. The investigation demonstrated that the potential for sinkhole development at the Polk County Site is low and acceptable for this type of construction. Construction Activities Construction of the Polk County Site will be phased over an approximately 25-year period beginning in 1994. The development of the Polk County Site is expected to take place in seven phases. Changes in the scope or sequence of the individual phases may occur depending on capacity needs over time. During Phase I, the initial earthwork and dewatering activities required for the construction of the plant island and cooling pond will take place. The initial cooling pond and plant island area will be dewatered and fill will be placed in SA-11 and SA-13 for the initial power plant construction. Water from the dewatering activities will be conserved by storage in mining parcels SA-8, SA-9, SA-10, N-15 and the northerly part of SA-12, except for quantities used in IMC's recirculation system. Clay consolidation will commence for other parcels, such as N-11A, N-11B, N-11C, N-13 and N-9B. Phosphate mining and related operations will still function in parcels P-2, P-3, Phosphoria, Triangle Lakes, and N-9. The initial vertical power plant construction for the first 470 MW of generating capacity will take place in Phase II. Water stored in Phase I, along with reclaimed water from the City of Bartow, will be used to fill the cooling pond in parcel N-16. Any excess reclaimed water from the City of Bartow, if necessary, will be stored in the eastern portion of N-16. Mining parcels SA-10, the southerly part of SA-12, and a portion of the offsite Estech Silver City plant site will be configured for drainage enhancement to McCullough Creek. Mining parcel SA-8 will be prepared to receive solid waste and parcel SA-9 will be prepared to receive wastewater from the RO system and neutralization basin. Wildlife habitat creation and enhancement will begin in parcels N-9B and N-13. Phase III of the Polk County Site represents the operation of the power plant from 235 MW to 1,500 MW, currently projected as NGCC capacity. The plant island, which will contain the generating units, will be located on mining parcels SA-11 and SA-13. The cooling pond will be located in N-16 and will receive reclaimed water from the City of Bartow and water crop from mining parcels P-3, Phosphoria, P-2, Triangle Lakes, N-15, N-11B, N-11C, the northerly end of SA-12 and the east end of N-16. Phase IV will encompass the development of the Polk County Site from 1,500 MW to 2,000 MW, currently projected as NGCC capacity. In conjunction with the additional generating units onsite, the cooling pond in N-16 will be enlarged to 1,219 acres. Other portions of the Polk County Site would remain the same as in Phase III. During Phase V, coal gasification is projected to be introduced to the Polk County Site. Generating capacity will be increased to 2,250 MW of which 1,000 MW are projected to be NGCC and the remaining 1,250 MW will be CGCC. To accommodate the coal gasification facilities, the northerly portion of SA-12 would be filled. The balance of the site would remain as described in Phase IV. During Phase VI, the generating capacity at the Polk County Site is projected to increase from 2,250 MW to 3,000 MW. This generating capacity will be a combination of 1,000 MW on NGCC and 2,000 MW on CGCC. During this phase, the cooling pond will be enlarged to 2,260 acres and will include parcels N-16, N-15 and N-11B, and a channel through N-11C. Earthwork will be required in N-15 and N-11B to repair and improve dams, and add slope protection on the dam inner faces and seeding on the exterior faces. Phase VII will be the final phase of the Polk County Site. During this phase, if the solid waste disposal area in mining parcel SA-8 were to become full it would be closed and mining parcel P-2 would be prepared to receive solid waste from the power plant operations. Parcels P-3 and Phosphoria will be available for mitigation, if necessary, as a result of activities in parcel P-2. This phase might not occur if coal slag is successfully recycled. Fuel Supply Fuel for the initial 470 MW of combined cycle generation will consist primarily of natural gas, with light distillate fuel oil as backup. Natural gas will be delivered by pipeline to the Polk County Site at a rate of 3.75 million cubic feet per hour. FPC currently plans to receive natural gas from the proposed Sunshine Pipeline for which certification is being sought in a separate proceeding. The Application for the Sunshine Pipeline was filed with DEP in August 1993. The other source for natural gas will be the backup natural gas pipeline which is being certified in this proceeding as an associated linear facility. Fuel oil will be delivered to the site by tanker truck, and enough fuel oil will be stored onsite for three days of operation for each combined cycle unit. At ultimate development, three 4-million gallon oil tanks will be located on the Polk County Site. All fuel handling and storage facilities, including unloading areas, pump areas, piping system, storage tanks, and tank containment areas will meet the requirements of DEP Chapter 17-762, Florida Administrative Code, and applicable National Fire Prevention Association Codes. At ultimate site development, the combined cycle units would use both natural gas and coal gas as primary fuels, and fuel oil as a backup fuel. As with the initial phase of operation, natural gas will be supplied by pipeline. At 1,000 MW of NGCC capacity, six to eight million cubic feet per hour of natural gas will be required. Coal for the coal gasification units will be delivered by railroad. For 2,000 MW of CGCC generating capacity, approximately 15,000 to 20,000 tons of coal a day will be required. Linear Facilities The initial 470 MW of NGCC generation includes three associated linear facilities: a 230-kV transmission line upgrade, a reclaimed water pipeline, and a backup natural gas pipeline. 230-kV Transmission Line The 230-kV transmission line will be routed from the existing FPC Barcola Substation within the Polk County Site to the FPC Ft. Meade Substation adjacent to CR 630. The transmission line corridor is approximately 1,000 feet wide within the Polk County Site boundary and narrows to 500 feet as the corridor leaves the site. The transmission line corridor follows several linear facilities including an existing transmission line right-of-way, CR 555 and CR 630. Land uses along the corridor are primarily phosphate mining, agricultural and industrial. Wetlands within the transmission line corridor are minimal and are associated primarily with roadside ditches. Where the transmission line crosses McCullough Creek, the creek will be spanned. The 230-kV transmission line will be constructed using single shaft tubular steel poles with a double circuit configuration for two 230-kV circuits. The transmission line structures will range in height from 110 feet to 145 feet. The conductor for the transmission line is a 1590 ACSR conductor that is approximately 1.54 inches in diameter. Conductor span lengths between structures will range from 500 to 900 feet. The transmission line will be constructed in six phases. During the first phase, the right-of-way will be cleared. Clearing in upland areas will be done using mowers and other power equipment. Clearing in wetlands, if necessary, will be accomplished by restrictive clearing techniques. After the right-of-way has been cleared, existing structures which will be replaced with new transmission line structures will be removed by unbolting them from their foundations and removing the structures with a crane. Foundations for new transmission line structures will be vibrated into the ground using a vibratory hammer or placed into an augured hole and backfilled. After the foundations are in place, new structures will be assembled on the foundations using a crane. Insulation and pole hardware will be mounted on the structures after erection. In the fifth phase of construction, conductors will be placed on a structure by pulling the conductors through a stringing block attached to the structure. During the final phase of construction, the structures will be grounded and any construction debris will be removed from the right-of-way. The construction of the 230-kV transmission line is estimated to require approximately 17 weeks. Construction of the transmission line will meet or exceed standards of the National Electrical Safety Code; FPC transmission design standards; Chapter 17- 814, Florida Administrative Code; and the Florida Department of Transportation Utility Accommodation Guide, where applicable. Electric and magnetic fields from the 230-kV transmission line will comply with the standards set forth in Chapter 17-814, Florida Administrative Code. Audible noise from the transmission line should occur only during rainy weather and will not exceed 39.1 dBA at the edge of the right-of-way. Since the transmission line is not located near many residences, interference to television and AM radio reception should be minimal. If interference does occur, it can be identified easily and corrected on an individual basis. Backup Natural Gas Pipeline The backup natural gas pipeline will originate at the Florida Gas Transmission pipeline in Hillsborough County at CR 39. The backup pipeline corridor runs generally east for 18 miles until it enters the Polk County Site at the western boundary of the plant island. The pipeline corridor is 1,000 feet wide and it generally follows linear facilities such as Jameson Road, a Tampa Electric Company transmission line, the CSX Railroad, Durrance Road, and Agricola Road. Several subalternate corridors are proposed in Polk County where the backup natural gas pipeline crosses phosphate mining land. The subalternate corridors, all of which are proposed for certification, are necessary to maintain flexibility in routing the backup natural gas pipeline around active mining operations. The uses of land crossed by the backup natural gas pipeline corridor consist primarily of phosphate mining and some agriculture. There are only two areas of residential land use along the corridor, one along Jameson Road in Hillsborough County, and the other near Bradley Junction along Old Highway 37 in Polk County. Ecological areas crossed by the natural gas pipeline corridor include a portion of Hookers Prairie in Polk County, some isolated wetlands associated with phosphate mining activities, and the South Prong Alafia River near CR 39 in Hillsborough County. The backup natural gas pipeline will consist of a metering facility, a scraper trap for pipeline cleaning, a maximum 30-inch buried pipeline made of high strength steel, a pressure regulating station, a cathodic protection system for corrosion control, and a Supervisory Control and Data Acquisition (SCADA) system to monitor and operate the pipeline. The pipe to be used for the natural gas pipeline will be manufactured in accordance with standards specified in 49 CFR 192 and the industrial standards referenced therein. Pipe thickness will vary depending on the population of the area crossed. External corrosion control for the pipe will be provided by an external coating around the pipe and a cathodic protection system designed to prevent electrochemical corrosion of the pipe. Pipeline sections will be hydrostatically tested before leaving the factory to 125 percent of the design pressure. Activities associated with the construction of the backup natural gas pipeline will include survey and staking of the right-of-way, right-of-way preparation, stringing of the pipe, bending, lineup welding and nondestructive testing, ditching, lowering in of pipeline sections, backfilling, tying in pipeline sections, testing and right-of-way restoration. Construction of the pipeline will take place typically within a 75 foot-wide right-of-way. A wider right-of-way may be required where specialized construction activities, such as jack and bore methods, are used. After construction, the natural gas pipeline will have a permanent 50-foot right-of-way. Where the pipeline crosses federal and state highways or water courses, directional drilling or jack and bore construction methods will be used to minimize disturbance. Where the pipeline crosses the South Prong Alafia River, directional drilling will be used to locate the pipeline underneath the river bed. Pipeline welding will be done by highly skilled personnel who have been qualified in accordance with 49 CFR 192. Pipeline welds will be visually inspected and a percentage of the welds will be x-rayed for analysis. Once the pipeline is constructed, buried and tie-in welds completed, the pipeline will be hydrostatically tested. Hydrostatic testing will use water with a minimum test pressure of 125 percent of maximum operating pressure. Water for hydrostatic testing will be pumped from and returned to the Polk County Site cooling pond. Construction of the pipeline will comply with Title 49 CFR Part 192, Transportation of Natural and Other Gas by Pipelines: Minimum Federal Safety Standards; Chapter 25-12, Florida Administrative Code; Safety of Gas Transportation by Pipeline; and the FDOT Utility Accommodation Guide. After construction of the backup natural gas pipeline, the right-of- way will be restored and a 50-foot-wide permanent right-of-way will be maintained. Line markers will be located along the pipeline at regular intervals and warning signs will be posted where the pipeline crosses roads, railroads, or stream crossings. The estimated cost for the pipeline construction is $611,100 per mile, or $11.2 million for the 18.2 mile pipeline route. Reclaimed Water Pipeline The reclaimed water pipeline will run from the City of Bartow to the cooling pond near the eastern side of the Polk County Site. The reclaimed water pipeline corridor follows the CSX Railroad and U.S. Highway 17/98 south from the southerly Bartow city limit turning west toward the Polk County Site just south of Homeland. Land uses along the corridor include phosphate mining, commercial sites, rural residences and recreation. The corridor does not cross any environmentally sensitive habitats. The reclaimed water pipeline consists of a buried pipe, 24 to 36 inches in diameter, butterfly valves about every mile along the pipeline, and a flow meter. Pumping of reclaimed water will be provided by the Bartow Sewage Treatment Plant. Construction of the reclaimed water pipeline is similar to that of the natural gas pipeline and includes the following activities: survey and staking of the right-of-way, right-of-way preparation, ditching or trenching construction, stringing of the pipe and pipe installation, back filling, hydrostatic testing, and right-of-way restoration. Where the pipeline crosses state or federal highways or railroads, the pipe will be installed by using jack and bore construction. Construction of the reclaimed water pipeline is estimated to cost $500,000 per mile or $5,000,000 for the total length of the pipeline. Construction of the reclaimed water pipeline will comply with the standards in Chapter 17-610, Florida Administrative Code, the Florida Department of Transportation Utility Accommodation Guide, and the EPA Guidelines for Water Reuse Manual. The pipeline will be hydrostatically tested prior to operation. Corrosion control of the pipeline will depend on the material used for the pipeline and the soil conditions. If a polyethylene or a polyvinylchloride material is used, no corrosion control will be necessary. If ductile iron is used, the soil will be tested for corrosive properties and, if necessary, the pipeline will be protected from corrosion with a poly wrap material. Solid Waste Disposal Various types of solid waste will be generated by the operation of the Polk County Site. Depending upon the type of solid waste, disposal may be made in the onsite solid waste disposal areas or it may be disposed of offsite. Waste inlet air filters from the combustion turbines and general waste, such as office waste, yard waste and circulating water system screenings, will be recycled or disposed of offsite at the Polk County North Central Landfill. Solid waste from the well water pretreatment and blowdown pretreatment will be disposed of onsite in the solid waste disposal area to be constructed in mining parcel SA-8. Sulfur, a by-product of coal gasification, will be of marketable grade and will be stored in a molten state onsite and delivered to buyers by rail car or tanker truck. Slag, a by-product of coal gasification, will be the largest volume of solid waste generated at the Polk County Site. Slag is potentially marketable and FPC will make efforts to recycle this by-product as construction aggregate. If slag is not marketable, it will be disposed of in the onsite solid waste disposal areas initially in mining parcel SA-8 and later, if necessary, in parcel P-2. Low volume spent acidic and basic solutions produced in the regeneration of demineralizer resin bed ion exchanges during operation of the facility will be treated in an elementary neutralization unit to render them non-hazardous. Other potentially hazardous waste will be tested and if determined hazardous will be disposed of in accordance with all applicable federal and state laws. Onsite disposal of slag, and well water and blowdown pretreatment solids will be made in the solid waste disposal areas to be constructed in parcels SA-8 and later, if necessary, P-2. These parcels are clay lined impoundments that have clays generally 20 to 40 feet thick. Prior to disposal of any solid waste in a clay settling area, that area will be drained and the clays consolidated. The clays will be probed and if the clay thickness is less than 10 feet it will be refurbished or patched with a synthetic liner. Additionally, a geotextile net will be installed to provide tensile strength to the upper layer of clay. Perimeter leachate collection piping will be installed. Leachate in the interior of the solid waste disposal areas will be monitored and collected by the use of well points to maintain the leachate head at no greater than 4 feet. The solid waste disposal area in parcel SA-8 will be closed by installing a two-foot thick soil cover which will be seeded and graded to provide water crop to parcel N-16. At closure, the leachate level will be pumped down to minimize the residual leachate head. The clay which lines the base of the solid waste disposal areas decreases in permeability as it consolidates and the solids content of the clay increases. In the first 20 to 50 years of consolidation, the hydraulic gradient of the clay is reversed and water will drain upward. Analysis of the clay shows that it would take 60 to 100 years for leachate to seep through the clay liner. After closure and capping of the solid waste disposal area occurs and the leachate residual head is pumped out, leachate is not expected to break through the liner. Based on the design of the solid waste disposal areas and the analysis of the clay, the solid waste disposal areas in parcels SA-8, and later P-2, should provide equivalent or superior protection to that of a Class I landfill under Chapter 17-7.01, Florida Administrative Code. Industrial Wastewater The Polk County Site is designed to be a zero discharge facility. There will be no offsite surface water discharge of contaminated stormwater or cooling pond blowdown. Cooling pond blowdown will be treated first by a lime/soda ash softening pretreatment system. A portion of the softened effluent will be routed to the cooling pond and a portion will be treated further by reverse osmosis (RO). High quality water from the RO system will be reused in the power plant as process water. The reject wastewater from the RO system will be sent to the brine pond for evaporation. In later stages of the Polk County Site operation, the RO reject wastewater will be concentrated prior to disposal in the brine pond. The brine pond will be constructed in parcel SA-9, a waste clay settling pond. Parcel SA-9 has thick waste clay deposits which will act as a liner. A synthetic liner will be placed along the interior perimeter of the brine pond out to a point where the clay is at least 10 feet thick. The synthetic liner will prevent seepage of the brine through the embankment of the brine pond and will provide added protection near the perimeter of the brine pond where the clay liner is thinner. Groundwater Impacts/Zone of Discharge The brine pond and solid waste disposal areas will be located in waste clay settling ponds with thick clay liners. They will be constructed to minimize, if not eliminate, seepage of brine and leachate to groundwater. If brine or leachate should seep through the clay liner, dispersion and dilution will reduce chemical concentrations so that neither primary nor secondary groundwater quality standards will be exceeded at the boundary of the zone of discharge. A zone of discharge has been established for the solid waste disposal area in parcel SA-8, the brine pond in parcel SA-9, and the cooling pond in parcels N-11B, N-15 and N-16. The zone of discharge will extend horizontally 100 feet out from the outside toe of the earthen dam along a consolidated boundary surrounding these facilities and vertically downward to the top of the Tampa member of the Hawthorn Group. A groundwater monitoring plan will be implemented to monitor compliance with groundwater standards at the boundary of the zone of discharge. Surficial Hydrology and Water Quality Impacts The Polk County Site is located along the divide between the Peace River Drainage Basin and the Alafia River Drainage Basin. Water bodies near the site include McCullough Creek, Camp Branch, Six Mile Creek, Barber Branch, and South Prong Alafia River. Mining has disrupted or eliminated natural drainage patterns from the Polk County Site to these water bodies. Currently the only drainage from the Polk County Site to these water bodies is through federally permitted National Pollutant Discharge Elimination System (NPDES) outfalls to McCullough Creek and Camp Branch. To assess the impact to the surficial hydrology of the Polk County Site and surrounding water bodies, the baseline condition was assumed to be the surficial hydrology which would be present under current mandatory reclamation plans for the mining parcels onsite and offsite. The baseline for non-mandatory parcels was assumed to be the minimum reclamation standards under the DEP/Bureau of Mine Reclamation (BOMR) (formerly within the Department of Natural Resources) Old Lands Program and the baseline for non-mandatory offsite parcels was considered to be the existing condition. The one water body onsite for which the baseline condition presently exists is Tiger Bay, which has been reclaimed and released. The baseline condition for the Polk County Site ultimately would include elimination of seepage from N-16 to Tiger Bay and removal of the NPDES outfall weir from Tiger Bay to Camp Branch. These conditions will result in a lowering of the water table in Tiger Bay and the drying out of wetlands in that area. Under current reclamation plans, water bodies also will be created in parcels SA-12 and SA-11. Other than the reclaimed Tiger Bay and Tiger Bay East, DEP, Southwest Florida Water Management District (SWFWMD) and Polk County have not claimed jurisdiction over any of the water bodies onsite within areas in which phosphate mining activities have been or will be conducted. The major construction activities which may impact offsite surface water bodies are the dewatering activities associated with the initial phase of construction. During this period, parcels SA-11, SA-13 and N-16 will be dewatered to allow earth-moving activities to take place. Dewatering effluent will be stored onsite, reused in IMC's recirculation system, or discharged in the event of above-average rainfall. After the earthwork is complete, the water will be returned to N-16. Based on this construction scenario, no adverse impact to offsite surface water bodies is expected from the construction activities associated with the Polk County Site. The Polk County Site has been designed to function as a "zero discharge" facility. No surface water will be withdrawn from or discharged to any offsite surface water body as a result of plant operations. Certain non- industrial areas within the Polk County Site will be designed, however, to provide offsite drainage to enhance flows to McCullough Creek and Camp Branch. Flow to McCullough Creek will be enhanced by drainage from parcel SA-10, an offsite portion of the Estech Silver City Plant Site, and the southerly portion of parcel SA-12. Drainage from parcels N-11A, N-13, N-9B, Tiger Bay East and Tiger Bay will enhance flows to Camp Branch. Additionally, FPC has agreed to explore the possibility of restoring drainage to Six Mile Creek if onsite water cropping produces more water than FPC needs for power plant operations and if such drainage can be accomplished without additional permits. The net effect of the drainage enhancement plans will be to equal or improve flows to McCullough Creek and Camp Branch over the baseline condition for the site. There are several types of surface water systems to be developed on the Polk County Site. Surface water runoff from the plant island, other than that from the coal and limestone storage areas, will be routed to the site runoff pond and then used in the cooling pond as makeup water. Surface water runoff from the coal and limestone storage areas, as well as runoff from the active solid waste disposal area, will be routed to a lined recycle basin and will be used as process makeup water for the coal gasification plant. Surface water runoff from mining parcels N-11C, Triangle Lakes, N-11B and N-15 prior to its use as part of the cooling pond, P-3, Phosphoria, P-2 prior to its use as a solid waste disposal area, and SA-8 after it has been closed as a solid waste disposal area, will be directed to the cooling pond as makeup water. All of the surface water management systems will meet the requirements of the SWFWMD Management and Storage of Surface Water rules. Subsurface Hydrology and Impacts from Water Withdrawal The Polk County Site will use a cooling pond for process water and for cooling water for the combined cycle units and the coal gasification facilities. For the initial 940 MW of generating capacity, makeup water for the cooling pond will come from onsite water cropping and reclaimed water from the City of Bartow. FPC has negotiated an agreement with the City of Bartow for 3.5 or more million gallons per day (mgd) of reclaimed water from its wastewater treatment facility. At ultimate site capacity, the Polk County Site will require up to 23.6 mgd from a combination of offsite sources and groundwater for the operation of the power plant. FPC has agreed with the SWFWMD to obtain at least 6.1 mgd from reclaimed water and other offsite non-potable water sources, including the City of Bartow, for use as makeup water for the cooling pond. The additional 17.5 mgd of water may be withdrawn from the Upper Floridan Aquifer if additional sources of reclaimed water are not available. FPC has identified substantial amounts of reclaimed water that may be available. A limited quantity of potable water from the Upper Floridan Aquifer will be needed to supply drinking water and other potable water needs for power plant employees. Well water from the Upper Floridan Aquifer will be treated, filtered and chlorinated in an onsite potable water treatment system prior to consumption. At ultimate site development, potable water consumption is estimated to average 19,000 gallons per day, with a peak consumption of 36,000 gallons per day. As an alternative, FPC may connect with the City of Bartow or the City of Fort Meade potable water system. The subsurface hydrology of the Polk County Site consists of three aquifer systems. The uppermost system is the surficial aquifer which is located in the upper 20 to 30 feet of soil. Due to mining operations, the surficial aquifer has been removed from the site except beneath highway rights-of-way and portions of some dams. Below the surficial aquifer lies the intermediate aquifer which is comprised of an upper confining layer approximately 120 feet thick, a middle water bearing unit about 60 feet thick, and a lower confining unit about 80 to 100 feet thick. This aquifer system provides potable water to some small quantity users in the area. Below the intermediate aquifer is the Floridan Aquifer, which consists of the Upper Floridan Aquifer, a discontinuous intermediate confining unit, and the Lower Floridan Aquifer. The Upper Floridan Aquifer provides a larger source of potable water for the area. The Lower Floridan Aquifer is characterized by poorer quality water and has not been used generally for water supply. The principal impact to groundwater from construction of the Polk County Site will be from the dewatering activities in parcels N-16, SA-11 and SA-13. This impact, if not mitigated, could result in the lowering of groundwater levels in the surficial aquifer in adjacent wetlands. During construction, recharge trenches will be constructed in certain locations near wetlands. Modeling analysis demonstrates that the recharge trenches will adequately mitigate any offsite groundwater impacts that otherwise would be caused by construction dewatering. The principal groundwater impact from the operation of the Polk County Site will be the withdrawal of water from the Upper Floridan Aquifer for process water and cooling pond makeup. Water from the Upper Floridan Aquifer is the lowest quality of groundwater that can be used for the Polk County Site while maintaining the cooling pond as a zero discharge facility. The withdrawal of 17.5 mgd from the Upper Floridan Aquifer at ultimate site development will not adversely impact offsite legal users of groundwater and will comply with the SWFWMD consumptive use criteria for groundwater withdrawal. Ecological Resources The baseline for the ecological resources at the Polk County Site was established as the site condition that would exist following (i) mandatory reclamation under reclamation plans approved by the DEP/BOMR, and (ii) non- mandatory reclamation normally carried out by the mining companies. In the cases of Tiger Bay, which has been reclaimed and released by DEP/BOMR, and Tiger Bay East, which has revegetated naturally without reclamation, the ecological baseline was represented by the current condition of these parcels. This baseline methodology was proposed by FPC in a Plan of Study which was accepted by DEP in a Binding Written Agreement. The predominant land cover that would occur under the baseline condition at the Polk County Site would be agriculture. Approximately 70 percent of the Polk County Site, or approximately 5,678 acres, would be developed as crop land, citrus or pasture. The remaining 30 percent of the site would be reclaimed as non-agricultural uplands, wetlands and open water bodies. Tiger Bay already has been reclaimed and released by DEP/BOMR and Tiger Bay East has revegetated naturally. These two parcels represent one-fourth (524 acres) of the natural habitat under the ecological baseline condition. The quality of the baseline land cover and vegetation was established by surveying several onsite and offsite areas which have been reclaimed and released. Baseline aquatic resources at the Polk County Site consist of Tiger Bay and the aquatic resources which would have been developed under existing reclamation plans. This baseline would include open water bodies and forested wetlands in parcels SA- 11 and SA-12, and forested and herbaceous wetlands in parcel N-16. Both Estech and IMC have exceeded their mine-wide wetlands mitigation obligations even without those wetlands. The quality of the baseline open water bodies on the Polk County Site was evaluated by surveying parcel N- 16, which currently consists of open water habitat. The quality of wetlands was determined by surveying Tiger Bay, which contains wetlands that have been reclaimed and released. The baseline aquatic resources were found to have significant fluctuations of dissolved oxygen, and were characterized by encroachment of cattail, water hyacinth and other nuisance species. All of the aquatic areas sampled as representative of baseline conditions showed significant eutrophication. No DEP or SWFWMD jurisdictional wetlands currently exist onsite, within areas in which phosphate mining activities have been or will be conducted, except in the reclaimed Tiger Bay and Tiger Bay East. Baseline evaluation of threatened and endangered species, and species of special concern (listed species) was conducted by collecting information regarding regional habitat descriptions; plant species lists and ecological reports for the area; lists and ecological reports of birds, mammals, reptiles and amphibians common to the area; species checklists; reports of sightings or abundance estimates; interspecific relationships and food chains of important species; location of rare, threatened or endangered species or critical habitat for these species in the region; and occurrence of potential preexisting stresses. Information from the Florida Natural Areas Inventory and approved mine reclamation plans was reviewed. Visits were made to nearby reclaimed sites by land and low-flying helicopters. No listed plant species were found at the site or offsite study areas. Existing reclamation plans, and consequently the ecological baseline condition, do not require the planting of such species. Listed animal species which were observed at the Polk County Site and are expected under the baseline conditions include the American alligator, woodstork, southeastern kestrel, osprey, little blue heron, snowy egret and tricolored heron. The baseline conditions would provide suitable feeding habitat for these species, but only limited areas of suitable nesting habitat. Both the current condition of the site and baseline condition provide feeding habitat for the American bald eagle, however, the nesting potential for this species will be greater after the implementation of the baseline condition. Impacts to the baseline ecological resources from the construction and operation of the Polk County Site will be more than compensated by habitat creation and enhancement programs proposed by FPC. The primary impacts to the baseline ecological resources will occur when power plant facilities, such as the plant island, cooling pond, brine pond and solid waste disposal area are constructed, eliminating these parcels from the baseline ecological resources. Without development of the Polk County Site, these parcels would represent approximately 2,268 acres of viable lakes and upland and wetland habitats. FPC has proposed a total of 3,713 acres of viable wildlife habitat as part of the ultimate development of the Polk County Site. Accordingly, the available wildlife habitat after construction of the Polk County Site represents a net increase of 1,445 acres over the baseline ecological resource conditions. This increase in habitat, particularly in the buffer area, will be a net benefit for protected species. In providing more wildlife habitat than baseline conditions, FPC has agreed to certain enhancement activities that will specifically offset any impact to baseline ecological resources. These enhancement programs include habitat and wetland creation in parcels N-9B and N-13; habitat creation and offsite drainage enhancement in parcel SA-10; implementation of a wildlife habitat management plan and exotic vegetation control in parcels SA-10, N-9B and N-13; drainage enhancement to McCullough Creek and Camp Branch; and funding the acquisition of a 425 acre offsite area to serve as part of a wildlife corridor. Air Pollution Control Polk County has been designated by the U.S. Environmental Protection Agency (EPA) and DEP as an attainment area for all six criteria air pollutants. Federal and state Prevention of Significant Deterioration (PSD) regulations provide that the project will be subject to "new source review." This review generally requires that the project comply with all applicable state and federal emission limiting standards, including New Source Performance Standards (NSPS), and that Best Available Control Technology (BACT) be applied to control emissions of PSD pollutants emitted in excess of applicable PSD significant emission rates. The project will limit emission rates to levels far below NSPS requirements. For the initial 470 MW phase of the Project, BACT must be applied for the following pollutants: sulfur dioxide (SO2), nitrogen oxides (NOx), particulates (PM and PM10), volatile organic compounds (VOCs), carbon monoxide (CO), beryllium, inorganic arsenic, and benzene. For the ultimate site capacity, BACT is required for each of these pollutants, and sulfuric acid mist (H2SO4), mercury, and lead as well. BACT is defined in DEP Rule 17-212.200(16), Florida Administrative Code, as: An emission limitation, including a visible emission standard, based on the maximum degree of reduction of each pollutant emitted which the Department, on a case-by-case basis, taking into account energy, environmental and economic impacts, and other costs, determines is achievable through application of production processes and available methods, systems and techniques (including fuel cleaning or treatment or innovative fuel combustion techniques) for control of each such pollutant. The primary purpose of a BACT analysis is to minimize the allowable increases in air pollutants and thereby increase the potential for future economic growth without significantly degrading air quality. Such an analysis is intended to insure that the air emissions control systems for the project reflect the latest control technologies used in a particular industry and is to take into consideration existing and future air quality in the vicinity of the project. The BACT analysis for the project therefore evaluated technical, economic, and environmental considerations of available control technologies and examined BACT determinations for other similar facilities across the United States. For the first 470 MW of NGCC units, BACT for SO2 emissions from the CTs is the use of natural gas as the primary fuel and the use of low sulfur oil for a limited number of hours per year. For the first 470 MW of NGCC units, BACT for CO, VOCs, PM, beryllium, arsenic, and benzene emissions from the CTs is efficient design and operation of the CTs, the inherent quality of natural gas (the primary fuel), and a limitation on the annual use of fuel oil. For the first 470 MW of combined cycle units, BACT for NOx emissions from the CTs is the use of advanced dry low NOx combustors capable of achieving emissions of 12 parts per million by volume dry (ppmvd) at 15 percent oxygen when burning natural gas, water/steam injection to achieve 42 ppmvd at 15 percent oxygen when burning fuel oil, and limited annual fuel oil use. For the first 470 MW of NGCC units, the DEP staff initially proposed BACT for NOx emissions from the CTs as 9 ppmvd at 15 percent oxygen when burning natural gas, using dry low NOx combustor technology. However, after careful consideration, it was determined that, because of the lack of proven technology to achieve such emission rate, it would be more appropriate to establish BACT at 73 lb/hour/CT (24-hour average, based on 12 ppmvd at 15 percent oxygen and 59o F) using dry low NOx combustor technology and to require FPC to make every practicable effort to achieve the lowest possible NOx emission rate with those CTs when firing natural gas. FPC also is required to conduct an engineering study to determine the lowest emission rate consistently achievable with a reasonable operating margin taking into account long-term performance expectations and assuming good operating and maintenance practices. Based on the results of that study, DEP may adjust the NOx emission limit downward, but not lower than 55 lb/hour/CT (24-hour average, based on 9 ppmvd at 15 percent oxygen and 59o F.). For the 99 MBtu/hour auxiliary boiler that is part of the initial phase of the project, BACT for NOx emissions is low NOx burners, limited annual fuel oil use, and limited hours of annual operation. BACT for NOx emissions from the 1300 kW diesel generator is combustion timing retardation with limited hours of annual operation. For the 99 MBtu/hour auxiliary boiler and the diesel generator as part of the initial phase of the project, BACT for CO, VOC, SO2, PM, benzene, beryllium, and arsenic emissions consists of good combustion controls, the inherent quality of the fuels burned, the use of low-sulfur fuel oil, and limited hours of operation. For the fuel oil storage tank as part of the initial phase of the project, BACT is submerged filling of the tank. For the coal gasification and other facilities to be built during later phases of the project, a preliminary BACT review was undertaken by FPC to support the demonstration that the Polk County Site has the ultimate capacity and resources available to support the full phased project. Air Quality Impact Analysis Air emissions from the project also must comply with Ambient Air Quality Standards for six criteria pollutants and Prevention of Significant Deterioration increments for three pollutants. Polk County and the contiguous counties are classified as Class II areas for PSD purposes; the nearest Class I area is the Chassahowitzka National Wilderness Area, located approximately 120 km. from the Site. An air quality analysis, undertaken in accordance with monitoring and computer modeling procedures approved in advance by EPA and DEP, demonstrated that the project at ultimate capacity utilizing worst-case assumptions will comply with all state and federal ambient air quality standards as well as PSD Class I and II increments. For nitrogen dioxide, sulfur dioxide and particulate matter, air quality modeling was based on conservative assumptions, including background concentrations based upon the highest long- term and second highest short-term measured values (established through an onsite one-year air quality monitoring program and regional data), existing major sources at their maximum emissions, the estimated maximum emissions from certain other proposed projects, and the impacts of the proposed FPC project at ultimate site capacity. For other pollutants, detailed analyses were not performed because offsite impacts were predicted to be insignificant. Impacts of the project's estimated emissions of certain hazardous air pollutants (antimony, arsenic, barium, beryllium, benzene, boron, cadmium, calcium, chromium, cobalt, copper, formaldehyde, magnesium, manganese, nickel, selenium, vanadium, and zinc) at ultimate capacity were compared to the DEP draft no-threat levels under DEP's draft "Air Toxics Permitting Strategy." All pollutants except arsenic were projected to be below the corresponding draft no- threat level. Because of the conservatism of DEP's draft no-threat levels, it was concluded that arsenic impacts would not pose a significant health risk to the population in the surrounding area. Impacts on vegetation, soils, and wildlife in both the site area and the vicinity of the Chassahowitzka National Wilderness Area, the nearest PSD Class I area, will be minimal. Visibility in the vicinity of the Chassahowitzka National Wilderness Area will not be impaired significantly by the project's emissions. Air quality impacts from commercial, industrial, and residential growth induced by the project are expected to be small and well-distributed throughout the area. Impacts from the initial phase of the Project (470 MW) will comply with all State and federal ambient air quality standards as well as PSD Class I and II increments. The impacts from the initial phase of the Project are also well below the draft no-threat levels. The initial phase of the Project will not significantly impair visibility in the vicinity of the Chassahowitzka National Wilderness Area, and the impact on vegetation, soils, and wildlife in both the site area and the vicinity of the Chassahowitzka National Wilderness Area will be minimal. The air quality impacts due to commercial, industrial, and residential growth from the initial phase of the Project will be small, and are not expected to impact air quality. Land Use Planning/Socioeconomic Impacts of Construction and Operation The proposed site is an appropriate location for the Polk County Site project. The Polk County Site has adequate access to highway and rail networks, including CR 555, a major collector road, and the CSX railroad. The Polk County Site is located away from major residential areas in a location already heavily disturbed by mining activity. The site is located in reasonable proximity to major metropolitan areas that can supply an adequate work force for construction. Development of the Polk County Site in a mined-out phosphate area is a beneficial use of land and will provide an economic benefit for Polk County. The Polk County Site also is close to existing facilities, such as existing transmission line corridors and reclaimed water facilities, which will benefit the operation of the site while minimizing the impact of the project. The linear facilities associated with the Polk County Site are sited in appropriate locations. The 230-kV transmission line upgrade, reclaimed water pipeline and backup natural gas pipeline corridors: (i) are located adjacent to other linear facilities, such as existing roads and transmission lines, (ii) avoid major residential areas, and (iii) minimally disrupt existing land uses. The Polk County Site is compatible with the State Comprehensive Plan, the CFRPC Regional Policy Plan, and will meet the requirements of the Polk County Conditional Use Permit. The portion of the backup natural gas pipeline located in Hillsborough County is consistent with the Hillsborough County Comprehensive Plan and the policies of the TBRPC Regional Policy Plan. Construction of the Polk County Site will occur over an approximately 25-year period beginning in 1994. If the Polk County Site is developed only for NGCC capacity, construction employment will average 153 jobs per year with a peak employment of 350. The average annual payroll for construction of the Polk County Site on all NGCC is expected to be $7.1 million per year. If 1,000 MW of NGCC and 2,000 MW of CGCC units are built at the Polk County Site, peak construction employment will be 1,000 with an average annual construction employment of 315 over the approximate 25-year period. Average annual payroll under this scenario would be $14.6 million per year. Indirect jobs created as a result of buildout of the Polk County Site will average 231 jobs for all NGCC and 477 jobs if 2,000 MW of CGCC is added to the Polk County Site. After completion of the construction of the Polk County Site at ultimate capacity, 110 permanent direct jobs will be created if the site uses all NGCC and 410 jobs will be created if coal gasification is added to the Polk County Site. The operation of the Polk County Site will have a multiplier effect on the Polk County economy. The all NGCC scenario will create 272 indirect jobs and the Case A' scenario with CGCC will create 1,013 indirect jobs. After buildout, property taxes generated by the Polk County Site are estimated to be $24.3 million per year for the all NGCC scenario and $37.4 million per year if CGCC capacity is constructed at the site. Noise Impacts The ambient noise, or baseline noise condition at the Polk County Site was measured in five locations. These measurements show that the baseline noise condition for the site ranges between 30 dBA and 65 dBA at the nearest residential location. The higher noise levels are caused by truck traffic associated with the phosphate mining industry. Noise impacts from construction will be loudest during initial site preparation and steel erection stages. Earth moving equipment will produce noise levels of 45 to 50 dBA at the nearest residence in Homeland. During final phases of construction, steam blowout activity to clean steam lines will produce short duration noise levels of 69 dBA at the nearest residence. This activity will take place only during daylight hours. Noise levels from the operation of the Polk County Site were calculated using a computer program specifically designed for assessing noise impacts associated with power plant operation. The highest predicted continuous noise level will be 41 dBA at several houses 2.9 miles south of the site and 47 dBA at the nearest church. Noise impacts from fuel delivery trucks and coal trains will not significantly increase the noise levels over existing conditions. The continuous noise level from the operation of the Polk County Site at the nearest residence or church will be below the 55 dBA level recommended by the U.S. Environmental Protection Agency. Traffic Traffic analyses were made for impacts to highway traffic which will result from the construction and operation of the Polk County Site. These analyses included impacts at rail crossings caused by the delivery of coal to the Polk County Site under the Case A' scenario. A highway traffic analysis was made to determine if the existing roadway network in the vicinity of the Polk County Site would operate at acceptable levels of service based upon increased volumes of traffic associated with the construction and operation employment at the Polk County Site. Methodologies for evaluating traffic impact complied with Polk County, FDOT and CFRPC criteria. County roads were evaluated using Polk County criteria and state roads were evaluated using both Polk County and FDOT criteria. Traffic volumes were evaluated for peak construction traffic in 2010 and full plant operations, estimated in 2018. The traffic evaluation included analysis of existing traffic conditions, increased traffic volume associated with growth in the area not associated with the Polk County Site, and increased traffic associated with construction and operation employment at the Polk County Site. During peak construction employment under the Case A' scenario, 1,000 employees are expected at the Polk County Site. Under this scenario, the expected trip generation of the Polk County Site is expected to be 1,792 trips per day, with a morning peak of 717 trips and an afternoon peak of 717 trips. Based on this analysis, all roadways are expected to operate at acceptable levels of service with currently planned improvements to the roadways. Intersection levels of service were found acceptable for 7 out of 11 intersections. FPC has recommended improvements to four intersections at U.S. 98 and SR 60A, SR 60 and CR 555, SR 37 and CR 640, and CR 555 and CR 640 at specified traffic levels. Peak operation employment under the Case A' scenario is expected to be 410 employees in 2018. Based upon this employment figure, the expected trip generation of the Polk County Site is 964 trips per day with a morning peak of 195 trips and an afternoon peak of 154 trips. At peak operation employment, all roadways evaluated were found to operate at acceptable levels of service. All intersections, except the intersection at SR 60 and CR 555, were found to operate at acceptable levels. FPC has recommended a protected/permissive westbound left turn lane at this intersection. With FPC's recommended improvements, which have been incorporated as conditions of certification, and those improvements currently planned by FDOT, the existing roadway network will meet Polk County and FDOT approved levels of service at peak employment during the construction and operation of the Polk County Site to its ultimate capacity. In addition to the highway traffic impact analysis, FPC evaluated the impact on rail/highway crossings from the transportation of coal by rail under the Case A' scenario. It was assumed that all coal for the Polk County Site will be delivered by rail over existing CSX transportation lines. It is expected that at full operation two 90-car trains per day will be required for the delivery of coal, resulting in four train trips per day. It was also assumed that trains will travel at speeds averaging 35 to 45 miles per hour. Evaluation of the impacts at rail crossings found an increase of .5 second per vehicle per day at urban rail crossings and .3 second per vehicle per day at rural rail crossings. Based on the 1985 Highway Capacity Manual, the total delay at rail crossing intersections caused by the increased train traffic to and from the Polk County Site will not cause a significant delay and the rail crossing intersections will maintain level of service A. Archaeological and Historic Sites The Florida Department of State, Division of Historical Resources, has stated that because of the location of the Polk County Site, it is unlikely that any significant archaeological or historical sites will be affected. Mandatory Reclamation of Mining Parcels The Polk County Site is comprised of phosphate mining parcels, portions of which are subject to mandatory reclamation under the jurisdiction of DEP/BOMR. The mandatory mining parcels are currently owned by Estech, IMC, and USAC. FPC has entered into stipulations with each mining company agreeing to reclamation of the mandatory mining parcels in accordance with the conditions of certification proposed by DEP/BOMR. In those conditions, DEP has proposed to incorporate the reclamation conceptual plan modifications included in Appendix 10.9 of the SCA into the certification proceeding for the Polk County Site and has redesignated those conceptual plan modifications as EST-SC-CPH and IMC-NP- FPC. The portions of the site which will be developed by FPC will be released from mandatory reclamation requirements when FPC purchases the Polk County Site. Variances FPC has requested variances from certain reclamation standards set forth in Rule 16C-16.0051, Florida Administrative Code, which will be necessary until the affected mining parcels on the Polk County Site are released from reclamation. FPC has requested a variance from Rule 16C-16.0051(5)(a), which requires artificial water bodies to have an annual zone of fluctuation, and Rule 16C-16.0051(5)(b), which requires submerged vegetation and fish bedding in artificially-created water bodies. The criteria in these rules are inappropriate for a cooling pond, because it is an industrial wastewater treatment facility which cannot be efficiently or safely operated with fluctuating water levels and aquatic vegetation zones. With regard to the construction of dams for the cooling pond, brine pond and solid waste disposal areas, FPC will need a variance from Rule 16C-16.0051(2)(a), which requires a 4:1 slope for dam embankments and Rule 16C-16.0051(9)(b) and (c), which requires vegetation of upland areas, which may include dam embankments. Dams for the cooling pond, brine pond and solid waste disposal areas will have steeper slopes and the interiors of the dams will be concrete blanket revetments, synthetic liners or solid waste consistent with the industrial purposes for which these facilities have been constructed. Access to these areas will be controlled to prevent any potential safety hazard. Finally, FPC will need a variance from Rule 16C-16.0051(11)(b)(4), which requires reclamation to be completed within two years after mining operations are completed. Construction of the Polk County Site requires extensive dewatering and earthwork which cannot be completed within this timeframe. Applications for variances from mining reclamation criteria were included in Appendix 10.9 of the SCA and have been incorporated into the certification proceeding for the Polk County Site. DEP has redesignated these variance applications as EST-SC-FPC-V and IMC-NP-FPC-V. These variances are appropriate and should be granted. Agency Positions and Stipulations The Department of Environmental Protection, Southwest Florida Water Management District, and Polk County have recommended certification for the construction and operation of the initial 470 MW of natural gas combined cycle generating capacity and have recommended the determination that the Polk County Site has the ultimate capacity for 3,000 MW of natural gas and coal gas combined cycle generating capacity, subject to appropriate conditions of certification. No other state, regional or local agency that is a party to the certification proceeding has recommended denial of the certification for the construction of the initial 470 MW of generating capacity or determination of ultimate site capacity. Several agencies which expressed initial concern regarding certification of the Polk County Site have resolved those concerns with FPC and have entered into stipulations with FPC as discussed below. The Florida Department of Transportation, the Game and Fresh Water Fish Commission, and the Department of Community Affairs have entered into stipulations with FPC recommending certification of the Polk County Site and a determination that the Polk County Site has the ultimate site capacity to support 3,000 MW of NGCC and CGCC generating capacity subject to proposed conditions of certification. Hillsborough County, the Environmental Protection Commission of Hillsborough County, and the Tampa Port Authority have entered into a stipulation and agreement with FPC recommending certification of the backup natural gas pipeline corridor subject to proposed conditions of certification. FPC and the agency parties have agreed on a set of conditions of certification for the Polk County Site. Those conditions are attached as Appendix A to this Recommended Order.

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that: Florida Power Corporation be granted certification pursuant to Chapter 403, Part II, Florida Statutes, for the location, construction and operation of 470 MW of combined cycle generating capacity as proposed in the Site Certification Application and in accordance with the attached Conditions of Certification. Florida Power Corporation's Polk County Site be certified for an ultimate site capacity of 3,000 MW fueled by coal gas, natural gas, and fuel oil subject to supplemental application review pursuant to 403.517, Florida Statutes, and Rule 17-17.231, Florida Administrative Code, and the attached Conditions of Certification. A zone of discharge be granted in accordance with the attached Conditions of Certification. The conceptual plan modifications (EST-SC-CPH and IMC-NP-FPC) for the mandatory phosphate mining reclamation plans be granted subject to the attached Conditions of Certification. The variances from reclamation standards (EST-SC-FPC-V and IMC-NP-FPC- V) as described herein be granted subject to the attached Conditions of Certification. DONE AND ENTERED this 3rd day of December, 1993, in Tallahassee, Florida. DIANE K. KIESLING, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of December, 1993. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-5308EPP RECOMMENDED CONDITIONS OF CERTIFICATION * * NOTE: 114 page Recommended Conditions of Certification plus attachments is available for review in the Division's Clerk's Office. COPIES FURNISHED: Gary P. Sams Richard W. Moore Attorneys at Law Hopping Boyd Green & Sams Post Office Box 6526 Tallahassee, Florida 32314-6526 Representing Applicant Pamela I. Smith Corporate Counsel Florida Power Corporation Post Office Box 14042 St. Petersburg, Florida 33733-4042 Richard Donelan Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road, Room 654 Tallahassee, Florida 32399-2400 Representing DER Hamilton S. Oven, Jr. Office of Siting Coordination Division of Air Resources Mgmt. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Lucky T. Osho Karen Brodeen Assistant General Counsels Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Representing DCA Michael Palecki, Chief Bureau of Electric & Gas Florida Public Service Commission 101 East Gaines Street Tallahassee, Florida 32399-0850 Representing PSC M. B. Adelson, Assistant General Counsel Department of Natural Resources 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Representing DNR Carolyn S. Holifield, Chief Chief, Administrative Law Section Department of Transportation 605 Suwanee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Representing DOT Doug Leonard, Executive Director Ralph Artigliere, Attorney at Law Central Florida Regional Planning Council 409 East Davidson Street Bartow, Florida 33830 Representing CFRPC Julia Greene, Executive Director Tampa Bay Regional Planning Council 9455 Koger Boulevard St. Petersburg, Florida 33702 Representing Tampa Bay Regional Planning Council John J. Dingfelder Assistant County Attorney Hillsborough County Post Office Box 1110 Tampa, Florida 33601-1110 Representing Hillsborough County Mark Carpanini Attorney at Law Office of County Attorney Post Office Box 60 Bartow, Florida 33830-0060 Representing Polk County Martin D. Hernandez Richard Tschantz Assistant General Counsels Southwest Florida Water Management District 2370 Broad Street Brooksville, Florida 34609-6899 Representing SWFWMD James Antista, General Counsel Florida Game and Fresh Water Fish Commission Bryant Building 620 South Meridian Street Tallahassee, Florida 32399-1600 Representing GFWFC Sara M. Fotopulos Chief Counsel Environmental Protection Commission of Hillsborough County 1900 Ninth Avenue Tampa, Florida 33605 Representing EPCHC Joseph L. Valenti, Director Tampa Port Authority Post Office Box 2192 Tampa, Florida 33601 Representing Tampa Port Authority Board of Trustees of the Internal Improvement Trust Fund Don E. Duden, Acting Executive Director Department of Natural Resources 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Representing the Trustees Honorable Lawton Chiles Governor State of Florida The Capitol Tallahassee, Florida 32399 Honorable Robert A. Butterworth Attorney General State of Florida The Capitol Tallahassee, Florida 32399-1050 Honorable Bob Crawford Commissioner of Agriculture State of Florida The Capitol Tallahassee, Florida 32399-0810 Honorable Betty Castor Commissioner of Education State of Florida The Capitol Tallahassee, Florida 32399 Honorable Jim Smith Secretary of State State of Florida The Capitol, PL-02 Tallahassee, Florida 32399-0250 Honorable Tom Gallagher Treasurer and Insurance Commissioner State of Florida The Capitol Tallahassee, Florida 32399-0300 Honorable Gerald A. Lewis Comptroller State of Florida The Capitol, Plaza Level Tallahassee, Florida 32399-0350

USC (1) 49 CFR 192 Florida Laws (3) 403.508403.517403.519
# 8
CITY OF TALLAHASSEE (HOPKINS-TO-BAINBRIDGE) vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-001022 (1981)
Division of Administrative Hearings, Florida Number: 81-001022 Latest Update: Aug. 20, 1981

Findings Of Fact The proposed transmission line corridor is for the purpose of connecting a 230 kV line from the City of Tallahassee's existing system to the Georgia Power Transmission grid. The southern terminus of the corridor is in Leon County where the City's 230 kV line running north from the Hopkins' Power Plant makes a right angle turn toward the east, following Interstate Highway 10 (Section 13, Range 1 West, Township 1 North). The northern terminus of the corridor is that point where it ties to the Georgia system in Gadsden County, Florida, just south of the Florida State line in close proximity to the intersection of U.S. Highway 27 and SR 157 (Section 90, Range 1 West, Township 3 North, north of the Watson line). The corridor generally follows a center line conjunct with the Range 1 West range line, except that approximately 2.75 miles north of its southern terminus the corridor bends approximately 25 degrees to the east for a distance of approximately one-half mile before turning north for approximately 1.4 miles at which point the corridor turns west approximately 25 degrees for a distance of approximately 1.2 miles, and then turns east approximately 35 degrees for approximately 8 miles before once again turning north. The corridor encompasses several major highways, including Interstate Highway 10 and U.S. Highway 27. It also encompasses part of the Ochlocknee River, the Gadsden County, Florida landfill, part of the Tallahassee Commercial Airport, and part of the Ochlocknee Wildlife Management Area and Lake Talquin State Recreation Area. Just north of the rest stop on Interstate Highway 10, the corridor includes an area known as Riverwood Acres, a non-platted subdivision. The center line of the corridor bisects the subdivision. From its southern origin north, for approximately the first one mile of the corridor, the width of the corridor is approximately 9/16 mile. Thereafter the width of the corridor is approximately 1/2 mile. The location of the corridor is depicted in Figures 2-3, 2-6A, 2-6B, and 2-6C of the application. There being no more definitive a description of the location of the corridor than that shown in the maps comprising figures 2-6A, B, and C of the application, it is found as a matter of fact that those figures define the parameters of the proposed corridor. The length of the corridor is approximately 15 miles. The purpose of the corridor is to provide a 100 foot right-of-way for a 230 kV transmission line constructed upon H-frame wood poles, with an approximate span of 600 feet. Pursuant to the requirements of Section 403.537, Florida Statutes (1980 Supp.), the Florida Public Service Commission, by order dated March 31, 1981, found that: The construction of the proposed transmission line will enhance electric system reliability and integrity. The proposed transmission line will improve the availability of low-cost electric energy within the State of Florida. The point at which the City of Tallahassee proposes to connect to the construction of Georgia Power Company, and the point at which it proposes to connect to its own system, are the appropriate starting and ending points of the line. The Public Service Commission then concluded that the proposed transmission line is needed. Approximately 11.0 miles of the corridor's center line traverses land that is wooded and undeveloped. The remainder of the corridor center line, 3.9 miles, crosses land that reflects some type of human development or use. That includes land that is currently agricultural, in improved pasture, or simply open, cleared land. Although no residences lie within the corridor's center line, houses do lie elsewhere within the corridor. Several houses are located near the southern end of the corridor just north of Interstate Highway 10 in the area referred to as Riverwood Acres. Several houses are located near the Gadsden County Sanitary Landfill, and scattered houses are located in the corridor to the west of the Concord and to the south of the Darsey communities. Immediately beyond the eastern corridor boundary, but not within the corridor, is a developing neighborhood located in Township 1 north, Range 1 West, Section In that area residential property boundaries abut the eastern corridor boundary. Because of the objection by homeowners in the Riverwood Acres area, the width of the corridor has been slightly extended along the western and eastern boundaries so that the right-of-way may be placed with least impact upon the homes in that area. Approximately 0.05 acres of agricultural land will be directly disturbed by placement of transmission structures. It is expected that agricultural land can continue to be farmed between transmission structures. Where possible, existing road crossings or roads adjacent to the right-of-way will be utilized for maintenance and construction purposes. Where necessary, new access roads will be developed, but only to the extent needed for construction and maintenance of the line. The only major water body crossed by the proposed corridor is the Ochlocknee River. Impacts to the river should be negligible since the line structures on each side of the river will be physically located away from the river banks, and the lines and structures spanning the river will be situated well above the ordinary high water mark as defined by the United States Corps of Engineers. The uncontradicted evidence presented indicates that other streams or small water bodies crossed by the corridor will not be adversely impacted. Similarly, the uncontradicted evidence established that the two wetland areas to be crossed by the corridor center line will not be adversely impacted. A 230 kV transmission line is not considered an extra high voltage transmission line. Lines at 345 kV or larger are considered extra high voltage lines. The uncontradicted evidence establishes that there will be no significant noise impacts from the proposed transmission line operation. Except as otherwise noticed in the Findings of Fact herein, the uncontradicted evidence established that the proposed transmission line, if constructed along a right-of-way in the proposed corridor, pursuant to the conditions of certification, would have no significant adverse effect on the environment. Its impact on the environment will be minimal. Although none of the parties to this proceeding posed any objection to the proposed transmission line corridor and the transmission line to be constructed therein, three members of the public gave testimony in opposition to the site certification at the final certification hearing. The three persons were all residents of Riverwood Acres and were generally expressing the concerns of the neighborhood. Their sincere concern is evidenced by the excellent quality of their presentation. They expressed their opinion that their land value would be diminished by the construction of a transmission line adjacent or over their property. While it is difficult to consider the construction of such a transmission line as an enhancement to the property, as established by the testimony of their property will be diminished by the construction of the transmission line. These public witnesses also expressed a concern for the aesthetic damage to their neighborhood by the construction of this transmission line. It is found as a matter of fact that should the transmission line be constructed over or adjacent to these residential owners in Riverwood Acres, the aesthetic value of their environment would be diminished by the visual impact of the transmission line. Finally, these public witnesses expressed their concern and belief that the effects of the electric and magnetic fields generated by the transmission line would effect the health and welfare of the residents of the neighborhood. However, as established by the testimony of two witnesses expert in the areas of electrical engineering, radiation biology, and biophysics, the electric and magnetic field forces encountered in the vicinity of the transmission line at ground level will have essentially no biological effect, and will be no stronger than similar forces encountered in the normal course of modern daily life. These members of the public presented a thoughtful, well conceived proposed alternative routing which would take the proposed transmission line around their residential neighborhood. However, the evidence presented in this proceeding does not establish that the existence of the alternative proposed by these members of the public by itself indicates that the corridor for which site certification has been requested, will not produce minimal adverse effects on the environment, public health, safety and welfare. The Department of Environmental Regulation, the Department of Veterans and Community Affairs, the Department of Natural Resources, the Florida Game and Fresh Water Fish Commission, and the Northwest Florida Water Management District have all recommended that the proposed transmission line corridor will have minimal, if any, adverse effects on the environment and public health, safety and welfare. Those agencies have recommended no reason why the site should not be certified subject to the conditions proposed by the Department of Environmental Regulation, which conditions are attached to this Recommended Order. Notice of the final certification hearing was published on May 13, 1981, in the Tallahassee Democrat, a daily newspaper published at Tallahassee, in Leon County, Florida.

Recommendation Having reviewed the record of this proceeding, and based upon the Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that certification, pursuant to the Transmission Lines Siting Act, Chapter 403, Florida Statutes (1980 Supp.), be GRANTED to the City of Tallahassee for the transmission line corridor and the construction of the subject transmission lines as proposed in the application as amended and the evidence admitted to the record. It is further RECOMMENDED that certification be made subject to the Conditions of Certification attached hereto and the further condition pursuant to the requirement in Section 403.531(3), Florida Statutes (1980 Supp.), that the City of Tallahassee shall be required to seek any necessary interests in state lands, the title to which is vested in the Board of Trustees of the Internal Improvement Trust Fund, from the Board prior to engaging in any activity on or affecting such lands. DONE AND ENTERED this 23rd day of July 1981 in Tallahassee, Florida. CHRIS H. BENTLEY Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July 1981. COPIES FURNISHED: Louis F. Hubener, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 C. Laurence Keesey, Esquire Department of Veteran and Community Affairs Room 204, Carlton Building Tallahassee, Florida 32301 Paul Sexton, Esquire Public Service Commission 101 East Gaines Street Tallahassee, Florida 32301 Douglas Stowell, Esquire Northwest Florida Water Management District Route 1, Box 3100 Havana, Florida 32333 Kenneth Gilleland, Esquire Game and Fresh Water Fish Commission Bryant Building 620 South Meridian Street Tallahassee, Florida 32301 John Williams, Esquire Department of Natural Resources 3300 Commonwealth Building Tallahassee, Florida Ted Steinmeyer, Esquire Leon County Attorney Leon County Courthouse, Room 203 Tallahassee, Florida 32301 John Shaw Curry, Esquire Gadsden County Attorney Post Office Box 469 Quincy, Florida 32351 Barrett Johnson, Esquire c/o Mahoney, Hadlow & Adams Post Office Box 471 Tallahassee, Florida 32302 James R. Brindell, Esquire Post Office Box 3103 Tallahassee, Florida 32303 (Representing Riverwood Acres Neighborhood Association)

Florida Laws (5) 403.52403.526403.531403.536403.537
# 9
IN RE: TECO POLK COUNTY PROJECT (PA 92-32) vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 92-004896EPP (1992)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Aug. 11, 1992 Number: 92-004896EPP Latest Update: Nov. 30, 1993

The Issue The issue is whether the proposed site is consistent and in compliance with existing land use plans and zoning ordinances.

Findings Of Fact Notice of Hearing Applicant published sufficient notices of the October 29, 1992, land use hearing in The Tampa Tribune (Hillsborough County) on September 12, 1992, and in The Ledger (Polk County) on September 13, 1992. Notice of the land use hearing was also posted at the site on September 14, 1992. On September 18, 1992, DER mailed by certified mail, return receipt requested, a copy of the public notice for the land use hearing for the proposed project to Polk County Development Services. Copies were mailed by certified mail, return receipt requested, to the Central Florida Regional Planning Council and the Tampa Bay Regional Planning Council. On October 21, 1992, DER issued a news release concerning the proposed project and the land use and zoning hearing to appropriate media selected by DER. The notice for the land use hearing published in the September 25, 1992, Florida Administrative Weekly was not published at least 45 days prior to the public hearing on the land use hearing as required by Section 17- 17.151(4)(e), Florida Administrative Code. On October 27, 1992, Applicant filed a motion for alteration of the 45-day time limit for notice of publication in the Florida Administrative Weekly. During the hearing, the Hearing Officer granted Applicant's motion and approved of the late notice in the Florida Administrative Weekly. On November 4, 1992, the Hearing Officer entered a written order confirming her prior oral order. Stipulation Applicant and Polk County entered into a stipulation concerning the proposed project's compliance with Polk County's zoning and land use regulations. This stipulation was admitted as Exhibit 4. The stipulation reflects Polk County's agreement that the proposed site of the Polk Power Station and transmission line corridors, which are subject to Conditional Use Permit number 92-05, are consistent and in compliance with the Polk County Comprehensive Plan and Polk County zoning ordinance number 83-2 and subsequent amendments (hereinafter The Polk County Zoning Ordinance). Site Identification Process In identifying the location of the Polk Power Station, Applicant received public guidance from a public power plant siting task force composed of environmentalists, educators, and business people. Over half the task force membership was composed of environmentalists. The task force selected a professional environmental consulting firm to assist in conducting the studies necessary to complete the siting project. A six county study area was initially selected for evaluation by the task force, which then commenced a multi-phase screening process. First, preliminary study areas were identified and reviewed and some areas were rejected. In phase two, the remaining preliminary areas were subjected to an environmental, engineering, and economic review which narrowed the list to fifteen candidate sites. In phase three, the task force reviewed these fifteen sites in greater detail, then narrowed the list to six "prime siting areas" and received input concerning these six areas from the public and various governmental agencies including DER and the Southwest Florida Water Management District. Upon completion of the third phase, the task force narrowed the field to three preferred sites, all of which were located in southwestern Polk County on land that had been mined for phosphate. The task force determined that each of these sites was essentially indistinguishable and left the selection of the final site to Tampa Electric Company. Project Site Description Design and Construction Applicant proposes to construct and operate a power plant and affiliated components including two transmission lines. The total generating capacity at the site will be approximately 1150 megawatts. The plant will commence operation in two stages. The first stage will be construction of a nominal 260-megawatt integrated coal gasification combined cycle (IGCC) demonstration project developed by Applicant and supported in part by the United States Department of Energy under the Clean Coal Technology Demonstration program. The IGCC facility is scheduled to be brought on-line in two phases. The first phase of the IGCC project will begin commercial operation in July, 1995, and will consist of a simple cycle combustion turbine. During this first year of operation, the combustion turbine will burn low sulfur number two fuel oil. In July, 1996, the remaining facilities consisting of the heat recovery steam generator, steam turbine, and coal gasification facilities will be added and integrated to complete the nominal 260-megawatt IGCC unit. After integration of these facilities, the IGCC unit will be fueled by coal-derived gas which is produced in the coal gasification facilities, with low sulfur number two fuel oil as the backup fuel. The second stage of the project will be the addition of two nominal 220-megawatt combined cycle facilities and six 75- megawatt nominal combustion turbines. These facilities are proposed to be fueled by natural gas as the primary fuel, with low sulfur number two fuel oil as the backup fuel. Associated with the Polk Power Station electrical generating plant will be a coal handling facility, a rail loop, water treatment and storage facilities, fuel oil storage and handling facilities, storm water management ponds, transmission lines and substations, and a cooling reservoir located southeast of the plant site. The cooling reservoir will be used to cool the steam from the heat recovery steam generator so that water can be reused in the system. Location of Site The proposed site for the Polk Power Station consists of 4,348 acres. The site is located in southwestern Polk County approximately 10.4 miles northwest of Bowling Green in Hardee County. Within Polk County, the nearest municipality is Fort Meade, approximately 10.8 miles to the east of the proposed site. Within Hillsborough County, the nearest municipality is Plant City located approximately 19.2 miles to the northwest. Within Manatee County, Bradenton is located approximately 34.8 miles to the southwest. The unincorporated community of Bradley Junction is located approximately 4.4 miles to the north of the generating facility. The Polk Power Station site is bisected by State Road 37, which divides the project into two tracts, the eastern tract and the western tract. The eastern tract will contain the proposed generating facility and cooling reservoir. The western tract will be reclaimed into a series of wetlands and uplands for a natural habitat area. Existing Land Uses The eastern tract is bordered to the north by County Road 630 and bordered to the east by the existing Hardee-Pebbledale 230 Ft. Green Road, and a CSX Railroad line. The eastern tract is bordered to the south by clay settling areas. The western tract is bordered to the south by State Road 674 and bordered to the west by the Hillsborough/Polk County line. The western tract is bordered to the north by Albritton and Bethlehem Roads. The western tract of the proposed site is currently undergoing active phosphate mining operations. Most of the western tract will be mined. The eastern tract has also been subject to phosphate mining operations. Portions of the eastern tract have not and will not be mined and will be the location for the proposed generating facility. The eastern tract contains three lakes of significant size, all created from phosphate mining activities. Adjacent land uses for the western tract include reclaimed phosphate mining lands, citrus groves, scattered residences, pasture lands, inactive clay settling ponds, undeveloped lands, an inactive phosphate chemical processing plant and cooling pond, and an active clay settling pond. Land uses adjacent to the eastern tract include pasture land, a citrus grove, one single family residence, active and inactive clay settling ponds, and an agricultural test tract operated by Polk County and the Florida Institute of Phosphate Research. Transmission Line Corridors Description Design and Construction The proposed transmission lines will transport bulk power at the 230- kV level from the Polk Power Station substation to the existing Tampa Electric Company grid system. Two types of transmission line structures are planned for the Polk Power Station. The first, the H-frame structure, consists of two vertical poles with an out-of-ground height of approximately 65 feet. The vertical poles are connected by a cross-arm assembly. The cross-arm assembly holds the porcelain insulators and the conductors for the transmission system. One overhead ground wire is attached to the top of each vertical pole. The single pole structure may be constructed in two configurations: single circuit or double circuit. These configurations are identical except that the single circuit configuration has one set of conductors, insulators, and ground wires, whereas the double circuit configuration has two sets. The typical out-of- ground height for the single pole structure is 96 feet. Location of Corridors There are two transmission line corridors associated with the proposed Polk Power Station, which are referred to as the eastern and northern corridors. The eastern corridor exits a substation located on the project site in a northeast direction to a point where the corridor meets the existing Hardee- Pebbledale 230-kV line, located along the western edge of Fort Green Road, with the point of intersection being located approximately 1400 feet south of County Road 630. The eastern corridor will be 400 feet wide and is approximately one mile long. The northern corridor commences from an onsite substation and runs in a westerly direction onsite until it meets State Road 37. This onsite portion of the northern corridor will be 400 feet wide and approximately three quarters of a mile long. At the point where the northern corridor meets State Road 37, the corridor turns northeast and continues in that direction parallel to State Road 37 to a point south of Bradley Junction, where it turns to the northwest, and then to the north, crossing Doc Durrance Road. At this point, the northern corridor meets the existing Mines Pebbledale 230-kV transmission line. The width of the northern corridor along State Road 37 is one-half mile and the width in the northwestern segment is one mile. The total offsite length of the northern corridor is approximately 5.2 miles. Existing Land Uses The eastern corridor is located exclusively on land that previously has been mined for phosphate. The onsite portion of the northern corridor also crosses only land previously mined for phosphate. The northern corridor east of State Road 37 and north of County Road 630 encounters undeveloped land, a citrus grove, an abandoned gasoline service station, phosphate mining lands, a wetland, scattered residences, and unclaimed phosphate mining lands. Land uses within the northern corridor west of State Road 37 include inactive clay settling areas, mixed forested areas and scattered citrus groves, wetland areas, phosphate mining lands, scattered residences, and a clay settling pond. Existing land uses within the northwestern segment of the northern corridor include reclaimed agricultural lands, a reclaimed lake, and a clay settling area. Consistency With Applicable Land Use Plan and Zoning Ordinance The Polk Power Station site and associated electrical transmission line corridors are located exclusively in Polk County. Therefore, the land use plan and zoning ordinances applicable to the Polk Power Station and associated components and transmission lines are those adopted by Polk County. Conditional Use Permit On January 24, 1992, Applicant filed with Polk County a conditional use permit application for the Polk Power Station. Supplemental information for that application was submitted by Applicant on February 12, 1992. The project was reviewed at an impact review meeting on March 16, 1992. The Polk County Zoning Advisory Board recommended approval of a conditional use permit for the project on May 13, 1992. On June 2, 1992, the Polk County Board of County Commissioners unanimously approved Applicant's conditional use permit application and on June 18, 1992, Conditional Use Permit number 92-05 was issued. Polk County Land Use Plan The land use plan that governs the Polk Power Station site and associated transmission line corridors is the Polk County Comprehensive Plan, as adopted by the Polk County Board of County Commissioners on April 19, 1991. The future land use element of the Polk County Comprehensive Plan allows for the development of certified electric power generation facilities (i.e., generation facilities and ancillary facilities required to be certified pursuant to the PPSA) in the phosphate mining (PM) future land use category if the proposed facility is reviewed and approved by Polk County through a conditional use permit. The Polk County Comprehensive Plan also contains specific objectives and policies which are used in determining the appropriateness of a location for a certified electric power generating facility. These include locational, environmental, development approval, and adjacent development criteria contained in the future land use element. Also, general policies and objectives relating to design and operational features for developments within Polk County are contained in the future land use, conservation, economic, traffic circulation, and infrastructure elements of the Comprehensive Plan. Electric transmission lines are permitted as specialized uses in all future land use categories in Polk County, subject to County approval. Polk County has stipulated that the site of the proposed Polk Power Station and associated transmission line corridors, which are subject to the conditions contained in Conditional Use Permit number 92-05, are in compliance and consistent with the Polk County Comprehensive Plan. The power plant site is in compliance and consistent with the Polk County Comprehensive Plan. This determination is based on the fact that the Polk Power Station, a facility required to undergo certification review pursuant to the PPSA, is a certified electric power generating facility to be located within the PM future land use category. Electric power generating facilities such as the Polk Power Station are allowed in the PM future land use category if the County grants its approval in the form of a conditional use permit. Here, Conditional Use Permit number 92-05 has been issued by the County approving the Polk Power Station site. Furthermore, the proposed Polk Power Station site complies with the locational, environmental, development approval, and adjacent development criteria of the land use element of the Comprehensive Plan applicable to certified electric power generating facilities as well as with the general policies for developments contained in the future land use, conservation, economic, infrastructure and traffic circulation elements of the Plan. With respect to the Polk Power Station transmission line corridors, the eastern transmission corridor and onsite portions of the northern corridor are located within the PM future land use category. The offsite portion of the northern corridor is located primarily within the PM future land use category with a small area in the southern portion of this corridor located in the agricultural/residential-rural category. Because transmission lines are permitted uses within all future land use categories, subject to Polk County approval, and County approval was issued for the Polk Power Station transmission line corridors in the form of Conditional Use Permit number 92-05, the Polk Power Station transmission line corridors are in compliance with the Polk County Comprehensive Plan. Polk County Zoning Ordinance Power stations are Class III Essential Services in Polk County, which are allowed conditional uses in the Rural Conservation (RC) zoning district. Electric transmission lines are Class I Essential Services under the Polk County Zoning Ordinance. Class I Essential Services are permitted uses in all zoning districts located within the transmission line corridors. Polk County has stipulated that the proposed site for the Polk Power Station and the associated transmission line corridors, which are subject to Conditional Use Permit number 92-05, are consistent and in compliance with the Polk County Zoning Ordinance. The proposed Polk Power Station site is in compliance and consistent with the Polk County Zoning Ordinance. This determination is based on the fact that Polk Power Station site is located exclusively within the RC zoning district, and Class III Essential Services, which include the Polk Power Station generating facility, are allowed conditional uses within the RC district subject to County approval in the form of a conditional use permit. Since Conditional Use Permit number 92-05 was issued to the Applicant for the Polk Power Station site, the site is consistent with the Polk County Zoning Ordinance. With respect to the Polk Power Station transmission line corridors, the entire eastern transmission line corridor and the onsite portion of the northern transmission line corridor lie within the RC zoning district. The offsite portion of the northern corridor is located predominately within the RC district with a small area within the Regional Commercial (C-3), Single Family Mixed residential (SF-1M), and Residence (R-1) zoning districts. Because transmission lines such as those associated with the proposed project are Class I Essential Services permitted in all Polk County zoning districts, it must be concluded that the Polk P ower Station transmission line corridors are consistent with the Polk County Zoning Ordinance.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Governor and Cabinet sitting as the Siting Board enter a Final Order finding that the proposed site of the Polk Power Station and associated facilities, including the site of the corridors for the directly associated transmission lines, are consistent and in compliance with existing land use plans and zoning ordinances. DONE and ENTERED this 23rd day of November, 1992, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of November, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-4896EPP The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted in this case. Specific Rulings on Proposed Findings of Fact Submitted by the Applicant and DER 1. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-27(1-27). COPIES FURNISHED: Lawrence N. Curtin Attorney at Law Holland & Knight Post Office Drawer 810 Tallahassee, FL 32302 Representing Applicant Richard Donelan Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Representing DER Hamilton S. Oven, Jr. Office of Siting Coordination Division of Air Resources Mgmt. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Lucky T. Osho Assistant General Counsel Department of Community Affairs 2740 Centerview Drive Tallahassee, FL 32399-2100 Representing DCA Michael Palecki, Chief Bureau of Electric & Gas Florida Public Service Commission 101 East Gaines Street Tallahassee, FL 32399-0850 Representing PSC M. B. Adelson, Assistant General Counsel Department of Natural Resources 3900 Commonwealth Blvd. Tallahassee, FL 32399-3000 Representing DNR Vernon Whittier Assistant General Counsel Department of Transportation 605 Suwanee Street, M.S. 58 Tallahassee, FL 32399-0491 Representing DOT James Antista, General Counsel Florida Game and Fresh Water Fish Commission Bryant Building 620 South Meridian Street Tallahassee, FL 32399-1600 Representing GFWFC Martin D. Hernandez Richard Tschantz Assistant General Counsels Southwest Florida Water Management District 2379 Broad Street Brooksville, FL 34609-6899 Representing SFWMD Julia Greene, Executive Director Tampa Bay Regional Planning Council 9455 Koger Boulevard St. Petersburg, FL 33702 Representing Tampa Bay Regional Planning Council R. Douglas Leonard, Executive Director Central Florida Regional Planning Council 490 East Davidson Post Office Box 2089 Bartow, FL 33830 Representing CFRPC John J. Dingfelder Attorney at Law Hillsborough County Post Office Box 1110 Tampa, FL 33601-1110 Representing Hillsborough County Mark Carpanini Attorney at Law Office of County Attorney Post Office Box 60 Bartow, FL 33830-0060 Representing Polk County Sara M. Fotopulos Chief Counsel Environmental Protection Commission of Hillsborough County 1900 Ninth Avenue Tampa, FL 33605 Representing EPCHC Honorable Lawton Chiles Governor State of Florida The Capitol Tallahassee, FL 32399 Honorable Robert A. Butterworth Attorney General State of Florida The Capitol Tallahassee, FL 32399-1050 Honorable Bob Crawford Commissioner of Agriculture State of Florida The Capitol Tallahassee, FL 32399-0810 Honorable Betty Castor Commissioner of Education State of Florida The Capitol Tallahassee, FL 32399 Honorable Jim Smith Secretary of State State of Florida The Capitol, PL-02 Tallahassee, FL 32399-0250 Honorable Tom Gallagher Treasurer and Insurance Commissioner State of Florida The Capitol Tallahassee, FL 32399-0300 Honorable Gerald A. Lewis Comptroller State of Florida The Capitol, Plaza Level Tallahassee, FL 32399-0350

Florida Laws (5) 120.57403.502403.508403.5095403.519
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer