Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CLIFFORD B. SMITH, 86-003698 (1986)
Division of Administrative Hearings, Florida Number: 86-003698 Latest Update: Apr. 22, 1987

Findings Of Fact Respondent has been a registered roofing contractor at all times material hereto. His license number is RC-0035594. On or about April 26, 1985 Respondent, doing business as Pinellas Roofing Service, contracted with Bausch and Lomb to reroof their plant in Manatee County, at a contract price of $31,150. Respondent admits that at no time material hereto was he licensed to engage in contracting in Manatee County. Pinellas Roofing thereafter began, and partially performed, this job for which it was paid a total of $28,035. Petitioner alleges, and Respondent denies, that Respondent diverted funds received from this job for other purposes, and was thereafter unable to fulfill the terms of the contract with Bausch and Lomb. Petitioner did not present competent substantial evidence in support of this charge. Respondent never completed this job and took no steps to inform Bausch and Lomb that he would not complete the contract or make other arrangements for its completion. He left several thousand dollars worth of material on the roof, exposed, when he walked off this job, and this resulted in these materials being substantially destroyed. During the job, he did not take precautions to assure that the roof did not leak during heavy rainstorms. In fact, on at least three occasions, leaks caused damage to the interior of the plant and Respondent could not be reached. Therefore, Bausch and Lomb had to have another roofing contractor make emergency repairs on June 25, July 15 and September 3, 1985, at a total additional cost of $4,150. Since Respondent did not complete the contract, and left the roof unfinished, Bausch and Lomb contracted on September 17, 1985 with Bernard J. Lozon, Inc., to complete the job, and make certain additional repairs, at a cost of $24,000. In the opinion of Bernard J. Lozon, who was accepted as an expert in roofing contracting, the actual work that was done by Pinellas Roofing was satisfactory. However, Respondent's actions in walking off the job and leaving the roof unattended without completing the job is an unacceptable practice in roofing contracting, and constitutes incompetence and misconduct. Respondent failed to properly supervise this job. He relied upon his son to hire the necessary crews, pay them, handle financial aspects of the job, and assure its completion. His testimony indicates he fails to understand his own responsibility for supervising and completing the work for which he contracted, and which was performed under his license. At no time material hereto did Respondent qualify Pinellas Roofing Service with Petitioner. Respondent failed to apply for and obtain a Manatee County building permit for the roofing job in question, and also failed to request the county building department to perform inspections of the work performed. The Board of County Commissioners of Manatee County has adopted and follows the 1979 edition of the Standard for Installation of Roof Coverings, Southern Building Code, as amended in 1981. This Code requires all contractors performing work in Manatee County to be registered in Manatee County, and to obtain permits for all roof replacements and repairs in excess of $200, as well as obtain inspections of all such work to insure compliance with the Code. Respondent failed to comply with these requirements of the local building code. When Respondent submitted his proposal on April 16, 1985 for the Bausch and Lomb job, he specifically acknowledged, in writing, that "all work (is) to be done according to owner specifications sheet." (Emphasis supplied). At hearing, Respondent contended that when he submitted his proposal he never saw the project specification sheet which was thereafter attached to his contract with Bausch and Lomb and made a part thereof. Rather, he testified that his proposal referred to certain specifications that appeared on project drawings which he reviewed prior to submitting his proposal. After considering the demeanor of the witnesses and all of the evidence presented, and particularly the fact that Respondent referred to the "specifications sheet" and not "drawings" in his proposal, it is specifically found that Respondent had knowledge of, and did in fact submit his proposal based upon the "specifications sheet" which ultimately became a part of his contract. As such, he was bound thereby in the performance of work under this contract. In pertinent part, the "specifications sheet" requires that the contractor obtain all necessary permits from Manatee County, that notice be given to the owner in advance of work that will produce excessive amounts of dust or tar fumes so proper precautions could be taken, that roofing materials be stored in a manner that protects them from damage or adverse weather conditions during construction, and that the contractor provide a two year written guarantee at the conclusion of the job. Respondent failed to comply with these requirements of the specifications.

Recommendation Based upon the foregoing, it is recommended that Petitioner enter a Final Order suspending Respondent's registration for a period of ninety (90) days and imposing an administrative fine in the amount of $1,500. DONE AND ENTERED this 22nd day of April, 1987 in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of April, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-3698 Rulings on Petitioner's Proposed Findings of Fact: Adopted in Finding of Fact 1. Adopted in Finding of Fact 8. 3,4 Adopted in Finding of Fact 2. 5,6 Adopted in Finding of Fact 3, but otherwise rejected as irrelevant and unnecessary. 7,8 Adopted in Finding of Fact 9. Adopted in Finding of Fact 6. Adopted in Findings of Fact 5, 6. Rulings on Respondent's Proposed Findings of Fact: Adopted in part in Findings of Fact 3, 5. Rejected as not based upon competent substantial evidence. Adopted in part in Finding of Fact 3. Adopted in part in Findings of Fact 2, 3. 5-7 Addressed in Findings of Fact 2, 3 and 5. 8,9 Rejected as irrelevant and unnecessary. 10. Adopted in part in Finding of Fact 5. 11,12 Adopted in part in Finding of Fact 6. Rejected as not based upon competent substantial evidence. Adopted in Findings of Fact 5, 6. Adopted in Finding of Fact 6. COPIES FURNISHED: W. Douglas Beason, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750 Michael Schlesinger, Esquire 655 Ulmerton Road Building 11-A Large, Fl 33541 Fred Seely Construction Industry Licensing Board Post Office Box 2 Jacksonville, Fl 32201 Van Poole Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750 Joseph A. Sole, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750

Florida Laws (4) 120.57489.117489.119489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GRACIELA ZARA, 84-002421 (1984)
Division of Administrative Hearings, Florida Number: 84-002421 Latest Update: Dec. 04, 1990

Findings Of Fact At all times pertinent to the issues herein, Graciela Zara was a registered roofing contractor in the State of Florida having license number RC 0035417. Respondent qualified Rolando Lopez Roofing Corp. at all times material to the complaint. Roofing work was done on the building located at 8413 8415 Hardin Avenue; however, the roofing work was not done by Rolando Lopez Roofing, but rather by Chungo, an employee of M. G. Construction Company, the owner of the building. Certain materials for the roofing work were delivered to 8413-8415 Harding Avenue by Tops All Roofing & Building Products, Inc., and those materials were ordered by Rolando Lopez and/or Renee Garcia. Rolando Lopez Roofing performed roofing work at the the bank at Las Americas Shopping Plaza, 8500 N.W. 85th Street; however, there was no evidence presented that Rolando Lopez Roofing failed to obtain a permit for the work it performed. Tropical Roofing entered into a contract for roofing work at the home of Mr. Sosa, 3001 S.W. 96th Avenue, Miami, Florida. 2/ The work was subcontracted to and done by Rolando Lopez Roofing. Although a permit for the work was required, respondent failed to obtain a permit. The respondent was responsible for obtaining the permit because the contractor that performs the work is responsible for obtaining the permit. Leon Gomez entered into a contract with Rene Garcia for roofing work at 309 Pinecrest Drive. Rene Garcia performed the roofing work on the house and was paid for the work by Mr. Gomez. However, the permit for the roofing work was obtained by the respondent. Roofing work was performed at the home of Felipe Acosta, 401 Flagami Boulevard, Miami, Florida. The permit for the roofing work was obtained by respondent. The contract for the work was with Rolando Lopez Roofing. The roofing work was performed by Rene Garcia and other workers that Mr. Acosta did not know. Mr. Acosta does not know Rulando Lopez. The contract negotiations and the payment for the job were handled by Mr. Acosta's brother. Mr. Acosta did not know whether Rene Garcia or Rolando Lopez received payment for she roofing work, but he knows his brother paid one of them. The roofing work was performed pursuant to the contract with Rolando Lopez Roofing. On June 1, 1983, Rolando Lopez Roofing Corp. issued a check for $11,667.86 to Tops All Roofing & Building Products. The check was returned by the bank stamped "Account Closed." On September 16, 1983, Rolando Lopez was adjudicated guilty of issuing a worthless check in violation of Section 832.05. Mr. Lopez paid $5,000 in restitution to Tops All Roofing & Building Products, but he was unable to pay the remaining amount because he has been unable to get any work. There was no evidence that Rolando Lopez Roofing Corp. failed to pay creditors for materials furnished. Although Rolando Lopez failed to make full restitution to Tops All Roofing and Building Products for the $11,667.86 check that was returned, there was no evidence that the check was for building supplies furnished to Rolando Lopez Roofing. Rolando Lopez testified that the check was written for the benefit of his nephew, Rene Garcia, to be used as collateral. Further, there was no evidence that Tops All Roofing & Building Products had furnished any building materials to Rolando Lopez Roofing prior to June 1, 1983, the date of the check. There was no evidence presented that Rene Garcia was not licensed by the State of Florida as a registered or certified roofing contractor

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that the Respondent be placed on probation for a period of six months. DONE and ORDERED this 2nd day of January, 1985, in Tallahassee, Leon County, Florida. DIANE GRUBBS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of January, 1985.

Florida Laws (4) 120.57489.119489.129832.05
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RUTH OGNE, 88-001776 (1988)
Division of Administrative Hearings, Florida Number: 88-001776 Latest Update: Apr. 20, 1989

The Issue The central issue in this case is whether Respondent is guilty of the violations alleged in the amended administrative complaints.

Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received at the hearing, I make the following findings of fact: At all times material to the allegations, Respondent, Ruth Ogen, was a licensed roofing contractor, license no. CC CO27471. A. R. Ogen Construction, Inc. was qualified by the Department as a roofing contractor. Respondent is the sole qualifier and licensee associated with the company, A. R. Ogen Construction, Inc. Respondent is married to Avraham Ogen who presents himself as the president of A. R. Ogen Construction, Inc. On or about November 9, 1986, A. R. Ogen Construction, Inc. doing business as Ogen Roofing & Waterproofing entered into a contract with Ardee Yuran to replace the entire roof of a commercial structure located at 14951 N.E. 6th Avenue, North Miami Beach (6th Avenue). The contract provided, among other things, that the top row of tiles around the parapet wall would be removed and reinstalled upon completion of the roof. In negotiating the contract described in paragraph 4, Mrs. Yuran was mindful of the work Avraham Ogen had performed at her residence. Mr. Ogen had supervised the reroofing of Mrs. Yuran's residence which had been satisfactorily performed. The residential job had required the removal of the tiles along the parapet wall and Mrs. Yuran expected the same process would be utilized in completing the commercial roof. The purpose intended to be accomplished by removing the tiles was to allow the roofers to extend the roofing materials up the sides of the parapet and over the crest. The roofing material is then sealed to the wall and the tiles replaced. This procedure results in a waterproof barrier so that when rain accumulates on the flat roof (and the water level rises) it cannot seep through the sealed perimeter. During the time Mr. Ogen was negotiating and performing the roof work for the 6th Avenue building, he was also retained to paint the structure (which was to be completed after the roof was finished). There came a time when Mrs. Yuran and Mr. Ogen disagreed regarding aspects of the roof work and the painting that was to be done. Eventually, the parties reached an impasse where neither was willing to concede: Mr. Ogen was not willing to perform the work as specified by Mrs. Yuran, Mrs. Yuran was not willing to pay Mr. Ogen any more on the contracts. At this point, Ruth Ogen, Respondent, had not been involved in the daily work progress made at the site. To make matters worse, a leak developed at the 6th Avenue property which resulted in a waterfall pouring down through the overhang of the building. As a result of the disagreement, both parties retained lawyers and, understandably, the issues escalated. Mrs. Yuran retained three individuals to review the work performed by Mr. Ogen. On March 4, 1987, Walter H. Scott, Scott Roofing & Repair, Inc., determined that water accumulating on the 6th Avenue roof was draining behind flashing which had not been properly sealed to the perimeter walls instead of running through the outlets. Mr. Scott recommended that the flashing be resealed along the wall. Had the tiles been removed and the work been performed as stated in the contract, the leak would have been avoided. A second licensed roofing contractor, Gary Carruth, Falcon Roofing Co., inspected the property on June 23, 1987, and recommended reflashing the walls along the perimeter of the 6th Avenue building. Mr. Carruth observed that the tiles had not been removed along the wall and that the roofing materials had not been properly sealed along the perimeter. James Rodgers, a consulting engineer performed a third inspection of the roof at 6th Avenue on June 25, 1987. According to Mr. Rodgers, several items of the contract work completed by Mr. Ogen were inadequately performed. Mr. Rodgers found that the pitch pans were not installed properly around the air conditioning units and that the flashing along the parapet wall was not properly completed nor performed as described in the contract. Respondent also retained a licensed roofer to review the work at 6th Avenue. Bill Mathews, Bill Mathews Roofing, completed a roof inspection report on November 21, 1988. According to Mr. Mathews, the flashing along the parapet wall required repair because it had been improperly sealed. Mr. Mathews noted that the top row of tile should have been removed so that flashing could have been taken up and over the parapet wall. Mr. Mathews also noted that the flat roof had buckles or "fish mouths" which should have been corrected as the roof was being installed. Mr. Mathews recommended that the flashing be resealed and that the buckles be cut and sealed with membrane and roofing cement. Finally, Mr. Mathews determined that the pitch pans under the air conditioning units should be filled with an asphalt cold process to prevent further cracking and potential leaks. A final inspection report was completed by Robert B. Hilson, Bob Hilson & Company, Inc., on August 18, 1988. Mr. Hilson is a consultant for the Department and made the inspection at the request of its attorney. Mr. Hilson's findings and recommendations mirrored those suggested by Mr. Mathews. The work performed by Mr. Ogen on the 6th Avenue property did not meet the terms of the contract and did not meet performance standards acceptable in the roofing industry. Mr. Ogen failed to properly seal all flashing materials along the parapet wall, failed to correct the buckles or "fish mouths," and failed to meet the contractual obligations (removing the tiles and extending the flashing over the crest). Because of the substandard work, Mrs. Yuran incurred additional expenses and inconvenience. Respondent did not view the 6th Avenue structure either before or during the time that her husband supervised the work performed. Respondent's role with the company was as secretary, bookkeeper, and office manager. Mr. Ogen supervised or performed all work at the 6th Avenue job. Respondent did not supervise Mr. Ogen or the workers under his supervision. "Ogen Roofing & Waterproofing" has not been qualified by the Department as a roofing contractor. On or about April 28, 1987, A. R. Ogen Construction, Inc. was requested to perform a roofing inspection at 1180 N.E. 204 Terrace. The subject property was under contract for sale and was ultimately purchased by Rose Zenar. According to the inspection report filed by Mr. Ogen, the roof and roof covering were in satisfactory condition with no evidence of leaks. Mr. Ogen signed the inspection report as president of A. R. Ogen Construction, Inc., state license no. CC CO27471. During the first rain after she had moved into the house, Mrs. Zenar observed water leaking through the ceiling into the kitchen. She immediately called Mr. Ogen who came out, observed the problem, but did not repair the leak. Mr. Ogen did not return Mrs. Zenar's subsequent calls. Ultimately, she contacted James Rodgers to perform a second roof inspection. As a result of Mr. Rodgers' inspection, Mrs. Zenar discovered that the leak was of long duration as it had completely rotted and decayed the roof rafters and sheathing in the area of the leak. Mr. Rodgers took pictures of the area which clearly showed the discolored wood. Evidence of the discoloration was visible from the attic entrance located in the garage adjacent to the kitchen. Mr. Ogen's failure to discover the rotted roof was due to an inadequate inspection of the crawl space between the ceiling and the roof rafters. It is the normal practice of qualified roof inspectors to examine the crawl space between the ceiling and roof supports. Respondent did not perform the roof inspection at Mrs. Zenar's home, did not supervise the inspection performed by Mr. Ogen, and did not have a checklist of items to be reviewed by him in making the inspection. The erroneous inspection performed by Mr. Ogen resulted in expenses and inconvenience to Mrs. Zenar.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Department of Professional Regulation, Construction Industry Licensing Board, enter a final order finding the Respondent guilty of the violations set forth above and, based upon the penalties recommended by rule, impose an administrative fine against the Respondent in the amount of $3000.00 DONE and RECOMMENDED this 20th day of April, 1989, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of April , 1989. APPENDIX RULINGS ON PETITIONER'S PROPOSED FINDINGS OF FACT: Paragraphs 1 through 7 are accepted. With the correction to reflect Mrs. Yuran not Mr. Yuran, paragraph 8 is accepted. Paragraphs 9 through 12 are accepted. Paragraph 13 is accepted. Paragraph 14 is accepted with the correction that the witness' name was Gary Carruth. With the deletion of the last paragraph of paragraph 15 which is rejected as argument or comment, the first five paragraphs of paragraph 15 are accepted. Petitioner is warned not to subparagraph statements of fact or to restate testimony, but to simply set forth the fact deduced from such testimony. Paragraph 16 is rejected as irrelevant or immaterial. Paragraph 17 is accepted to the extent that it finds the reroofing work performed on the 6th Avenue building was a poor quality which was not done under the supervision of a qualified, licensed roofing contractor. Further, it was gross negligence not to properly supervise the job. No conclusion is reached as to whether Respondent is able to supervise a job. Paragraph 18 is accepted. Paragraph 19 is rejected as a recitation of testimony. Paragraphs 20 through 24 are accepted. Paragraphs 25 through 31 are accepted. Paragraph 32 is accepted. Paragraph 33--none submitted. With regard to paragraph 34, the first sentence is accepted. The remainder is rejected as conclusion of law, argument, or comment. Paragraph 35 is rejected as irrelevant. Paragraphs 36-38 are accepted. Paragraph 39 is rejected as comment, irrelevant, or recitation. The first two sentences of paragraph 40 are accepted, the remainder is rejected as comment, conclusion of law, or argument. Paragraph 41 is rejected as irrelevant, conclusion of law, or argument. RULINGS ON RESPONDENT'S PROPOSED FINDINGS OF FACT: Paragraph 1 is accepted. Paragraph 2 is accepted but is irrelevant. Paragraph 3 is accepted. Paragraph 4 is rejected as irrelevant to the issue of whether a competent inspection was performed. Paragraph 5 is accepted. Paragraph 6 is rejected as irrelevant to the issue of whether a competent inspection was performed. Paragraph 7 is rejected as irrelevant or unsupported by the record. Paragraph 8 is accepted. Paragraph 9 is accepted. Paragraph 10 is rejected as contrary to the weight of the credible evidence presented. Paragraph 11 is rejected as argument, speculation, or unsupported by the record. Paragraph 12 is rejected as irrelevant. Paragraph 13 is rejected as argument, irrelevant, or unsupported by the weight of credible evidence. Paragraph 14 is rejected as argument, irrelevant, or comment. Paragraph 15 is accepted but is irrelevant. Paragraph 16 is rejected as argument. Paragraph 17 is accepted but is irrelevant. Paragraph 18 is rejected as irrelevant, argument, or unsupported by this record. Paragraph 19 is rejected as irrelevant. The following are rulings on case no. 88-1776 as submitted by Respondent: Paragraph 1 is accepted. Paragraph 2 is rejected as unsupported by the record. Paragraph 3 is rejected as irrelevant. Paragraph 4 is accepted but is irrelevant, immaterial. Paragraph 5 is rejected as unsupported by the record. Paragraph 6 is rejected as irrelevant, immaterial, or unnecessary. Paragraph 7 is rejected as unsupported by the weight of credible evidence. Paragraph 8 is rejected as irrelevant, immaterial, or unnecessary. Paragraph 9 is accepted but is irrelevant. Paragraph 10 is rejected as irrelevant, immaterial or unnecessary. Paragraph 11 is rejected as irrelevant, immaterial or unnecessary. Paragraph 12 is rejected as irrelevant. Paragraph 13 is rejected as argument or unsupported by the weight of the credible evidence. Paragraph 14 is rejected as contrary to the weight of the credible evidence. Paragraph 15 is accepted but is irrelevant. COPIES FURNISHED: Fred Seely Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 Bruce D. Lamb General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Elizabeth R. Alsobrook Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57489.105489.119489.129
# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs GREG ALAN ROACH, 07-004376PL (2007)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Sep. 20, 2007 Number: 07-004376PL Latest Update: Nov. 26, 2008

The Issue The issues in Case No. 07-4376PL are whether Respondent violated Subsections 489.129(1)(i), 489.119(2), 489.126(2)(a), and 489.129(1)(j), (m), and (o), Florida Statutes (2004),1 and, if so, what discipline should be imposed. The issues in Case No. 07-4377PL are whether Respondent violated Subsections 489.1425(1), and 489.129(1)(i) and (o), Florida Statutes, and, if so, what discipline should be imposed.

Findings Of Fact Petitioner is the state agency charged with regulating the practice of contracting pursuant to Section 20.165 and Chapters 455 and 489, Florida Statutes. Mr. Roach is, and was at all times material to this action, a certified roofing contractor in the State of Florida having been issued License No. CCC1326005. Mr. Roach's Certified Roofing Contractor License No. CCC1326005 is current and active. Mr. Roach's current addresses of record are Post Office Box 345, Orange Springs, Florida, and 22204 U.S. Highway 301, Hawthorne, Florida. At all times material to this action, Mr. Roach was a licensed qualifier for All Florida Roofing Contractors, Inc. (All Florida). There is evidence in the record sufficient to establish that Mr. Roach has been previously disciplined for a violation under Chapter 489, Florida Statutes. Notably, Mr. Roach has been previously disciplined for, among other things, violations of Subsections 489.129(1)(m) and (o), Florida Statutes. Case No. 07-4376PL Mr. Roach failed to obtain a Certificate of Authority for All Florida, as required by Subsection 489.119(2), Florida Statutes. On or about August 23, 2004, Mr. Pang contracted with Mr. Roach, to remove and replace the hurricane-damaged roof of his hotel property located at 1620 West Vine Street, Kissimmee, Florida. The contract price for the aforementioned project was $40,000.00. Mr. Pang made an initial payment of $2,250.00 on August 22, 2004, and another payment of $20,000.00 on August 23, 2004. As part of the contract, All Florida was required to pull the building permits for the project, and Mr. Roach failed to do this. Mr. Roach commenced work on the project on or about September 7, 2004. On or about late September 2004, he ceased work on the project, and the project remained unfinished. Mr. Pang paid All Florida an additional $10,000.00 on September 16, 2004. On October 1, 2004, the City of Kissimmee issued a Notice of Violation against Mr. Pang for failure to have a building permit for the work that had been performed by Mr. Roach on the roof. Mr. Roach scheduled repairs on the project, but did not return to the project. Mr. Roach did not have any inspections performed on the roof. Later, another contractor hired by Mr. Pang finished the roofing project at a cost of an additional $32,975.00. Case No. 07-4377PL On or about September 15, 2004, Ms. Perez contracted with Mr. Roach to repair roof damage to her residence at 1502 Golden Poppy Court, Orlando, Florida. The contract price for the aforementioned project was $7,268.32, of which Mr. Roach was paid $3,634.16 on September 18, 2004. The contract entered into between Ms. Perez and Mr. Roach failed to inform the homeowner of the Construction Industry Recovery Fund. On or about October 27, 2004, the Orange County Building Department issued Mr. Roach a permit for the aforementioned project (Permit No. T04018050). Mr. Roach did not have any inspections performed on the roof. On September 25, 2004, Ms. Perez paid $3,614.16 to All Florida, which was the remaining amount of the contract. Another contractor was hired by Ms Perez to correct deficient aspects of Mr. Roach's work on the roof at a cost of $900.00.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered whose outcome is the following: That in Case No. 07-4376PL Respondent violated Subsections 489.129(1)(i), (j), (m) and (o), Florida Statutes; Dismiss Count II of the Administrative Complaint in Case No. 07-4376PL; In Case No. 07-4376PL, imposing an administrative fine of $1,000.00 for the violation of Subsection 489.129(1)(i), Florida Statutes; imposing an administrative fine of $5,000.00 for the violation of Subsection 489.129(1)(j), Florida Statutes; imposing an administrative fine of $2,500 for the violation of Subsection 489.129(1)(o), Florida Statutes; no administrative fine is recommended for the violation of 489.129(1)(m), Florida Statutes, because the violation is included in the violations of Subsections 489.129(1)(j) and (o), Florida Statutes; That in Case No. 07-4377PL, Respondent violated Subsections 489.129(1)(i) and (o), Florida Statutes; In Case No. 07-4377PL, imposing an administrative fine of $1,000 for the violation of Subsection 489.129(1)(i), Florida Statutes; imposing an administrative fine of $2,500 for the violation of Subsection 489.129(1)(o), Florida Statutes; Requiring Respondent to make Restitution to Mr. and Mrs. Pang in the amount of $25,000; Requiring Respondent to make Restitution to Ms. Perez in the amount of $900; and Revoking Respondent's contractor license. DONE AND ENTERED this 31st day of March, 2008, in Tallahassee, Leon County, Florida. S SUSAN B. HARRELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of March, 2008.

Florida Laws (10) 120.569120.5717.00117.00220.165489.119489.1195489.126489.129489.1425 Florida Administrative Code (3) 61G4-17.00161G4-17.00261G4-17.003
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STEVE G. PETERS, 86-002552 (1986)
Division of Administrative Hearings, Florida Number: 86-002552 Latest Update: Jul. 02, 1987

The Issue Petitioner, the state agency charged with regulating the practice of contracting pursuant to Section 20.30 and Chapters 455 and 489, Florida Statutes, filed an administrative complaint dated May 20, 1986. Thereby, it has charged Respondent with violations of Sections 489.119, 489.129(1)(g), (j), and Florida Statutes, for which violations it seeks to impose, according to its post-hearing proposal, the requirement of $5600 restitution to Mr. Kenneth Jessell, a fine of $1500, and a one year suspension of Respondent's contractor's license. BACKGROUND AND PROCEDURE The parties' Joint Prehearing Statement was admitted as Hearing Officer Exhibit 1. Petitioner presented the oral testimony of Kenneth A. Jessell, Richard P. Scanlon, Gene O. Seymour, and Robert D. Hilson, and had admitted Petitioner's Exhibits 1, 2, 4, 5 and 6. Exhibit P-3 was marked for identification and proffered but not admitted. Respondent presented the oral testimony of Sheldon Israel and Respondent and had admitted Respondent's Exhibits 1, 2, and 4. Exhibit R-3 was marked for identification and proffered but was not admitted. At the close of hearing, Respondent moved for dismissal for failure of Petitioner to establish a prima facie case. That motion was taken under advisement and is addressed in the following conclusions of law. Upon the filing of a copy thereof as a post-hearing exhibit, judicial notice was taken of Section 3401.1(a)(3) South Florida Building Code, without objection. Petitioner filed transcript herein, and the parties' timely filed their respective post-hearing proposals within the time extensions agreed-upon and granted. The parties' respective proposed findings of fact are ruled upon pursuant to Section 120.59(2), Florida Statutes, in the appendix to this recommended order.

Findings Of Fact Respondent is, and has been at all times material hereto, a certified roofing contractor, license number CCC02955I, whose address of record is 2311 N. E. 35th Street, Lighthouse Point, Florida 33064. On or about June 6, 1985, Respondent, doing business as Great Southern Industries, contracted with Mr. Kenneth Jessell to install a roof on Jessell's house at Lighthouse Point, Florida. The contract price was $5,600. At no time relevant to the charges herein did Respondent or anyone else qualify Great Southern Industries nor did that name appear on Respondent's license. At hearing, Respondent admitted a violation of Section 489.129(1)(g), Florida Statutes, by acting in the capacity of a contractor under a name other than that appearing on his state certificate, and further admitted violation of Sections 489.129(1)(j) and 489.119, Florida Statutes, by failing to qualify a legal entity through which he was contracting. The parties stipulated those allegations of the complaint were to be considered proven. In mitigation, Respondent established that no fraud or deceit concerning who was actually performing the roofing work was perpetrated against Mr. Jessell, that Respondent's omissions were due to his misunderstanding of the legal requirements involved, and that at all times since its incorporation, August 31, 1984, Respondent has been sole shareholder, officer, and director of Great Southern Industries, Inc., a Florida corporation. Upon being made aware of his violations, he has ceased to do business as Great Southern Industries. There is no evidence of prior misconduct. Respondent, as Great Southern Industries, partially completed work on Jessell's house and Jessell partially paid for said work when a dispute arose between Respondent and Jessell relative to the work. Respondent began work on Jessell's roof on June 17, 1985. On June 18, 1985, a pitch fire broke out. The pitch fire resulted from a tar kettle which had not been appropriately handled by an employee of Respondent who had been assigned to tend it. Such fires are not uncommon in the industry. After the fire was put out, work ceased for the day, but Respondent appeared the very next day and continued with the roofing project. There is expert testimony that leaving such a pitch or tar fire unattended was negligent and that if the overly hot pitch or tar had then cooled overnight, been reheated, and used on Jessell's roof it would have been inadequate for the job. However, there is no direct credible testimony or documentary evidence that this is what actually occurred. Mr. Jessell was not present on the site the next day and approximately 60-70 percent of the base layer of the roof had been tarred over before this event occurred. Mr. Jessell is a college professor in finance and real estate. He has no expertise in contracting, roofing, or inspection of such jobs or the material used therein, but upon observation from the ground, without going onto the roof, Jessell decided the roof was not being properly constructed. On June 25, 1987, at Mr. Jessell's insistence, Gene O. Seymour, the Chief Building Inspector of the Broward County Building Department inspected the job, which he did not approve at that time. Respondent came back to conform the job to the inspector's concerns. Seymour did not approve the job at reinspection on July 1, so Jessell withheld payment. Respondent again returned and did some additional work. On July 9, the job again did not pass inspection. Respondent did further repairs on July 29. There were numerous other inspections but the job did not pass for one reason or another. On each occasion, Respondent came back to address the inspector's concerns. Seymour's testimony can be synopsized that he made an extraordinary number of inspections (at least 20) at Mr. Jessell's urging, and that the roof often failed to pass, mostly because the work was not yet fully completed. Inspector Seymour noted that sometimes the job would pass one inspection only to have Jessell call him back and show him new problems which had appeared in the interim. Seymour could not explain how this could be. He termed the job "jinxed." Respondent maintains, and Jessell denies, that Jessell frequently would go up on the roof and make suggestions to Respondent and his employees on how the roofing should be done, that Jessell pulled up on the felts, and that Jessell otherwise damaged the work done by Respondent and his crew. Having observed the respective candor and demeanor of Jessell and Respondent, and after considering and weighing the foregoing comments of Inspector Seymour and of all the witnesses' peripheral testimony on how rapid deterioration and excessive patching occurred, I find Respondent's explanation of the problems up to this point to be the more credible explanation, if a somewhat exaggerated one. Up until August 22, 1985, Respondent came and fixed anything Jessell complained of or that had been noted by an inspector. Finally, on August 22, Inspector Seymour approved the job as ready for the addition of tiles. Jessell was still dissatisfied with the roof.. By this time, he had been up on it several times with and without Seymour. Jessell took photographs and sought out Seymour in his office. Seymour rescinded his approval due to the appearance of new water blisters. Both Jessell and Seymour concur that at this point there were no leaks. On August 30, Seymour inspected again. He cut deeply into the roofing material in three places; in each place, he cut down to the base plywood sheeting and found no evidence of any water. This type of testing is considered "destructive testing." He also observed gouges, slashes, and nails working out. He proposed that Jessell get an independent consultant to resolve the problems between them. Respondent obtained a visual inspection by Sheldon Israel who wrote a letter which was signed off on by a certified architect and which confirmed that the roof as completed by Respondent thus far complied with the intent of the South Florida Building Code, which Code has been adopted in Broward County. On September 20, Seymour gave final approval for the stage the job had reached based on the letter from Israel and the fact that the waterproof membrane which Respondent had installed was intact at that time. Thereafter, Jessell hired Richard Paul Scanlon, a licensed and certified roofer, who eventually tore off what had been done by Respondent and did a complete "reroof" at a cost to Mr. Jessell of $6500. Scanlon, qualified at hearing to give expert evidence in roofing contracting, saw the roof in January 1986, approximately six months after Respondent had left the job. During those six months, the unfinished roof had been sitting exposed to the elements, without tiles, and with numerous patches, gouges, and cuts in it. He opined that Respondent's work constituted poor work and gross negligence. His opinion is based on his visual inspection without any tests whatsoever. Errors in Respondent's work which he noted included mopping the tar the wrong way, improper water lapping, and use of some rag felts and some fiberglass felts as opposed to the use of fiberglass as required by the Jessells' contract with Respondent. (However, rag felts and fiberglass felts both meet Code requirements.) Scanlon felt there was a possibility the roof would slide if tiles were added atop Respondent's work but declined to say this was a probability. In order to give a roof warranty, Scanlon felt he had to tear off Respondent's work and "reroof." Whatever he may have found when he tore the roof off later was not explored. Robert D. Hilson, a licensed and certified roofing contractor was also qualified as an expert witness. He also did not inspect the Jessell work until January 1986. He stated the number of patches over the base layer was excessive and unusual and the consistency of the tar was far too "runny," thin, and "gooey." As opposed to this thin consistency being clearly connected to the kettle fire and base coat mopping, Hilson indicated the consistency of tar he was objecting to was a last attempt at overpatching the base layer. He also testified that the roof patches had been lapped the wrong way and occasionally had been mopped inadequately or the wrong way, and he assumed the base layer was also lapped the wrong way, but he never "eyeballed" the base layer to verify this. He found water present at that time. He indicated 6 months exposure would have caused insignificant deterioration. Contrariwise, Sheldon Israel, also accepted as an expert, opined that possibly 6 months could have caused the deterioration Scanlon, Hilson and Jessell all described as existing in January 1986. The contract between the Jessells and Respondent is ambiguous. One portion provides: "5. Install Spanish Style, cement tile roof over 90 lb. roof surface." Another paragraph provides: "8. Owners to select specific colors of Gory Spanish S by 6/12/87 at 12:00 p.m." Printed instructions (specifications) for installation of Gory roofing tile require water laps on 90 pound felt. The Southern Building Code requires prepared roof coverings to be applied in accordance with manufacturers' printed instructions for the products used. Respondent used 90 lbs. rag felts and some fiberglass felts. Both meet Code. Respondent admits he also installed a waterproof membrane or tile underlayerment that was manufactured especially to go underneath Genstar cement tile. This waterproof membrane can only be exposed to the elements without covering for 6-8 months before it is too damaged for use. Respondent planned to install Gory tile on top of the membrane but according to the best expert testimony Gory tile cannot competently be installed over such a waterproof membrane and its ability to be installed over fiberglass felts is questionable. The dispute between Jessell and the Respondent was resolved and Mr. and Mrs. Jessell executed and tendered a full release dated March 20, 1986, for all work performed on their house by Respondent and Great Southern Industries, Inc.

Recommendation Upon the foregoing findings of fact and conclusions of law it is recommended that the Construction Industry Licensing Board enter a final order finding Respondent guilty of violations of Sections 489.129(1)(g), 489.129(1)(j) and 489.119, Florida Statutes, assessing a penalty of $1000 administrative fine therefor, and dismissing the charge of fraud, deceit, gross negligence, incompetency, or misconduct brought under Section 489.129(1)(m), Florida Statutes. DONE AND ORDERED this 2nd of July 1987, in Tallahassee, Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of July 1987. APPENDIX TO RECOMMENDED ORDER CASE NO. 86-2552 The following constitute rulings pursuant to Section 120.59(2), Florida Statutes, upon the parties respective proposed findings of fact (FOF). Petitioner's Proposed FOF. 1-2. Covered in FOF 1. Covered in FOF 1 and 4. Accepted but subordinate and unnecessary. Sheldon Israel was accepted as an expert witness upon other qualifications of record. Accepted but alone is not dispositive of any issue at bar. Rejected as out of context and as not constituting an ultimate material fact. The topic as a whole is covered in FOF 9-11 and the conclusions of law so as to conform to the credible record as a whole. Accepted but not dispositive of any issue at bar. Topic covered in FOF 5 and 10. Accepted but not dispositive of any issue at bar. Contrary to the parties' belief, lack of supervision was not alleged with specificity in the administrative complaint. I accept Respondent's testimony that the employee assigned to the kettle, improperly oxygenated its contents but had not abandoned it. See FOF 5 and 10. Rejected as covered in FOF 11 which conforms with the evidence of record. Rejected as covered in FOF 9 which conforms to the evidence of record. Respondents Proposed FOF. Covered in "Issues." Covered in FOF 1. Covered in FOF 2. Covered in FOF 4. Covered in FOF 12. Covered in FOF 3. Rejected as covered in FOF 11, which conforms with the evidence of record. Rejected as a conclusion of law. Accepted as modified in FOF 6-7 to conform to the evidence of record. COPIES FURNISHED: G. Vincent Soto, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Gary I. Blake, Esquire 3111 University Drive Coral Springs, Florida 33065 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Van Poole, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Joseph A. Sole, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (3) 489.105489.119489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. THOMAS G. WALKER, D/B/A INSULSHIELD ROOFING, 78-002448 (1978)
Division of Administrative Hearings, Florida Number: 78-002448 Latest Update: May 15, 1979

Findings Of Fact Based on my observation of the witnesses and their demeanor while testifying, the documentary evidence and the positions of the parties, I hereby make the following: Thomas G. Walker (herein sometimes called "Licensee" or "Respondent") is a registered residential contractor and is issued license number RR 0009839. Thomas G. Walker was initially licensed by the Board in July of 1969 as an individual and during January, 1975, he changed his registration status as an individual to qualify Insulshield Roofing as the business entity through which he would conduct his business (Petitioner's Exhibit No. 1). An examination of the official records pertaining to the Licensee reveals that he does not now nor has he ever held a roofing license in the State of Florida. On February 16, 1979, the Licensee was apprehended contracting roofing without a State roofing contractor's license by the Board's representative and was issued a Notice of Violation (Petitioner's Exhibit No. 3). On July 26, 1977, the Licensee entered into an agreement with Jan Soderstrom, 501 Orlando Avenue, Indialantic, Florida, to remove the tile from the Florida Room of her residence and hot mop the herein-described roofing area, to replace tile as needed, to clean and coat the entire roof, and to install a cap over Ms. Soderstrom's chimney. He guaranteed the work for a period of five (5) years and charged a contracted price of $800.00. The Licensee was paid the contracted price of $800.00 by check dated August 4, 1977 (Petitioner's Exhibit No. 5). During early February, 1978, Ms. Soderstrom detected a leak in her roof and summoned the Licensee back to her residence to repair same. During February, 1978, Respondent returned to Ms. Soderstrom's residence to repair the leak in her roof. Upon his return, he removed several roof tiles and since February, 1978, to the present, he has not returned to this project. Clyde Pirtle, a field investigator for the Board, investigated the Licensee based on complaints that he received from Ms. Soderstrom and from a Mr. Capitz. On or about February 16, 1977, Mr. Pirtle discussed a Notice of Violation with the Licensee and explained to him the necessity to register as a Roofing Contractor, if he was in the business of acting as a Roofing Contractor. Mr. Charles D. Franklin, a building official of Indian Harbor Beach, Florida, is the custodian of the records in Indian Harbor, Florida. Based on an examination of the records by Mr. Franklin, the Respondent/Licensee is not registered as a Roofing Contractor locally.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby, RECOMMENDED: That the registered residential contractor's license, number 0009839, of the Licensee, Thomas G. Walker, d/b/a Insulshield Roofing, be suspended for a period of one (1) year. RECOMMENDED this 4th day of April, 1979, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32202 Thomas G. Walker d/b/a Insulshield Roofing 170 5th Street South Melbourne Beach, Florida 32951 J. K. Linnan, Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL J. HITTENBERGER, 89-003002 (1989)
Division of Administrative Hearings, Florida Number: 89-003002 Latest Update: Nov. 17, 1989

The Issue Whether Respondent committed the offenses described in the Administrative Complaint? If so, what disciplinary action should be taken against him?

Findings Of Fact Respondent is a roofing contractor licensed to practice in the State of Florida. Since January, 1982, he has been the qualifying agent for Tropical Clima-Coat Inc. (Tropical). On September 21, 1983, Tropical entered into a written contract with Bertha Guerry and her husband Joseph, in which it agreed, for $2,449.10, to perform the following roofing work on the Guerrys' residence, which was located at 2185 S.W. 38th Street in Fort Lauderdale, Florida: Remove loose gravel and dirt from existing roof surface/flat deck. Apply Tropical Clima-Coat's resin- based cement to fill holes and cracks in the roof surface. Apply acrylic primer to provide maximum adhesion for acrylic waterproofing. Apply acrylic waterproofing, creating a uniform, bonded, elastomeric, watertight surface. Apply White Acrylic Roof Finish as a durable, mildew-resistant wear barrier. The contract further provided that the Guerrys were to receive a "5 year, 100% warranty against leaks." The work specified in the contract was completed on October 31, 1983, and the Guerrys thereupon paid Tropical in full. Tropical, in turn, gave the Guerrys a written warranty signed by its Vice-President, which provided, in part, as follows: If within 5 years after Tropical Clima- Coat applies its Roof System to your roof, a leak develops because of the failure of our roofing system,* we will repair it free. * Damage excluded from warranty: Tropical Clima-Coat shall not be liable for any leaks or damage caused by riots or vandalism, termites or other insects, penetration of the roof or waterproofing system by nails; nor shall Tropical Clima-Coat be liable for leaks or damage caused by acts of God, including but not limited to: lightening, gale, hurricane, tornado, hailstorm, flood, earthquake, or unusual phenomena of the elements; nor from damage to roof due to settlement, distortion, dry rot, failure or cracking of the roof deck, walls, partitions, or foundation of the structure; nor defects or failure of materials used as a roof base, over which our waterproofing system is applied; nor by biological growth, traffic upon the roof or any similar cause. The warranty also contained the following provision prescribing the time and manner in which claims under the warranty had to be made: The owner of the roof will notify Tropical Clima-Coat immediately by certified mail, at its main office (3746 N.W. 16th Street, Ft. Lauderdale, Florida 33311) of any leaks alleged to result from causes not excluded from coverage by this warranty. Such notification must be mailed within 30 days of discovery of the need for repairs, and all correspondence must include the above Certificate Number. In June, 1986, Mrs. Guerry noticed that there was a leak in her roof above the living room. She telephoned Tropical and requested that it repair the leak in accordance with the warranty she and her husband had been given. Tropical responded promptly to Mrs. Guerry's request. It sent one of its workers to the Guerry residence and he patched the leak. Arrangements were made for the worker to return to the Guerry residence and pressure clean the roof. Pursuant to these arrangements, the worker came back to the residence and pressure cleaned the roof as he had promised. It took him two hours to complete the task. Following the pressure cleaning of the roof, Mrs. Guerry discovered that there were now leaks in the roof above the kitchen. Having made this discovery, she again telephoned Tropical and requested that it repair these newly-discovered leaks. As it had done in response to her previous telephonic request, Tropical dispatched a worker to the Guerry residence, albeit not as promptly as on the prior occasion. The worker applied black ceramic granules to the surface of the roof in an attempt to alleviate the problem. The Guerrys now had a black roof instead of the white roof for which they had contracted. Mrs. Guerry again telephoned Tropical and complained about the new color of her roof. Tropical responded by having a worker go to the Guerry residence and spray paint the roof white. The paint, however, did not adhere well to the granular material on the roof. Furthermore, Mrs. Guerry observed new leaks in the roof. On September 8, 1986, she telephoned Tropical to advise it of these recent developments. Respondent visited the Guerry residence the next day. He told Mrs. Guerry that Tropical intended to remove the granules and recoat the roof with an asphalt material imbedded with a polyester fabric for greater strength to prevent against leaks. He further assured her that, upon completion of the repair work, the roof would be white. On September 15, 1986, a crew of Tropical workers were on the Guerrys' roof with approximately 80 to 100 gallons of asphalt when a sudden, unexpected heavy rainstorm interrupted their work. The rainwater mixed with the asphalt and created "black goo," some of which fell from the roof onto the sides of the house, the porch, the driveway, the sidewalks, the grass, the bushes, and the trees. Tropical had its workers endeavor to clean up the mess that the rainstorm had created. They used mineral spirits in an attempt to remove the hardened remains of the "black goo" from the porch, the driveway and the sidewalks and swept the residue onto the grass, bushes and trees. In so doing, they contaminated the soil and killed the vegetation. Respondent was responsible for the decision to use mineral spirits in the cleanup effort. He did not realize, as he should have, that the use of this substance would result in environmental damage. The cleanup progressed slowly. Frustrated by the lack of substantial progress, Mrs. Guerry telephoned Respondent and demanded that he go to her home and do something about the situation. Respondent did not believe that his presence at the home would help matters any and he told Mrs. Guerry so. Nonetheless, on September 17, 1986, he paid his final visit to the Guerry residence. During his visit, Respondent met with Mrs. Guerry for approximately an hour and a half. Mrs. Guerry expressed to Respondent her outrage concerning the situation. Respondent recognized that Mrs. Guerry had a right to be annoyed and that Tropical needed to take action to remedy her plight. He wrote down on a piece of paper the following things that Tropical would do for the Guerrys: FIX ROOF LOOSEN SOIL W/RAKE 4. REMOVE "STICKINESS" FROM DRIVEWAY AND SIDEWALK 3. REMOVE BLACK FROM CHATTAHOOCHEE (STAINS WILL REMAIN) REMOVE "STICKINESS" FROM CHATTAHOOCHEE REMOVE STICKINESS FROM DECORATIVE WALL (STAINS WILL REMAIN) REMOVE STICKINESS FROM SIDEWALKING STONES REMOVE BLACK FROM CHAT @ BACK DOOR SOD- TO BE DETERMINED LATER Respondent indicated he would sign this document and he asked Mrs. Guerry to do the same to acknowledge their understanding and agreement as to the remedial action Tropical was to take. Mrs. Guerry refused. Nonetheless, the cleanup effort continued. Mrs. Guerry, however, did not permit Tropical to continue its repair work on the roof. Concerned about the damage that had been done to the vegetation on her property, Mrs. Guerry contacted a horticultural consultant, Robert G. Haelhle. Haelhle surveyed the property on September 18, 1986. Following his survey he wrote a letter to the Guerrys advising them of the following: On September 18, 1986, I visited the Guerry property at Mrs. Guerry's request. The landscape plantings are in real trouble due to a mineral spirits spill. Mineral spirits and water were used to clean up roofing tar that washed off the roof after a heavy rainstorm. The kerosene [sic] and water mixture washed over the lawn, around the base of a West Indian Cherry tree (very rare), an arborvitae, and a 165 foot Ixora hedge on the east and west sides of the house. The Ixora hedge is over 7 feet tall and 30 years old and would not be replaceable. The mineral spirits/water mix will poison the soil and eventually could affect the water table. All affected soil will have to be removed from the area before any new planting can be accomplished. The West Indian Cherry was starting to yellow and the grass was dying at the time of my visit. Time is of the essence to preserve the remaining plantings. The kerosene [sic]/water mix poisons the root system of the plants and does not allow for normal water penetration. I am not optimistic about the remaining plantings. I contacted Jane McCarthy of the Environmental Quality Board, tel: 765- 5881. She was to send an inspector to assess the soil damage at the site. Neither Tropical nor Respondent replaced the "plantings" that had been damaged or destroyed as a result of the cleanup effort. On September 22, 1989, Mrs. Guerry telephoned Respondent. She reiterated that she did not want any work done on the roof until she had an independent expert inspect it and provide her with guidance. That same day, Edward T. Weiner, a licensed architect hired by the Guerrys, inspected their roof. Based on his observations of the condition of the roof, it was Weiner's opinion that the repair work done by Tropical was unacceptable and that a new roof needed to be installed. He so advised the Guerrys by letter dated September 29, 1986. The Guerrys also hired an attorney, Craig W. Lekach, to furnish them legal advice and representation concerning their dealings with Tropical. On September 23, 1986, Lekach telephoned Respondent and instructed him to "get busy" with the repair work that needed to be done. The following day, Respondent telephoned Mrs. Guerry and told her that he was anxious to complete the repair work on her roof. Mrs. Guerry took the opportunity to again express her displeasure with the work Tropical had done. She also indicated that she had yet to hear from Weiner regarding his assessment of the condition of the roof. That same day, September 24, 1986, Respondent received word that a Broward County Environmental Compliance Officer had inspected the Guerrys' property and determined that mineral spirits used in the cleanup effort had contaminated soil on the property. Respondent was further informed that the excavation of the contaminated soil would remedy the situation. Having received permission from the Guerrys' attorney to proceed with the repair work, Respondent sent a crew to the Guerry residence on September 25, 1986, to vent the roof. Mrs. Guerry, however, did not allow the workers to install the vents. Another telephone conversation between Mrs. Guerry and Respondent ensued. Respondent reiterated that it was his desire to finish the work that needed to be done on the roof. Mrs. Guerry, in turn, indicated that she would not let Tropical continue its work on the roof until she had Weiner's report in hand and had the opportunity to further discuss the matter with her attorney, her son and others with whom she had consulted. The conversation ended with Respondent telling Mrs. Guerry that he would be waiting to hear from her. On September 26, 1989, Respondent wrote a letter to Attorney Lekach in which he complained that Mrs. Guerry was interfering with Tropical's efforts to make her whole. The letter read, in part, as follows: We do carry casualty insurance and I feel it may be best to supply you with the name and address of our agent and allow him to coordinate with Mrs. Guerry's homeowners agent. Truly, this situation is considered an "act of God" and I do not believe that we can adequately communicate with the customer as she is in such an excited state we now find her implacable. We would be glad to install the proper roof vents and do the final painting of her roof if she will permit us. If she will not, then we must close the file and direct her to our insurance company. This is really unfortunate! Sound roofing practices were utilized; we were careful to watch the weather and, although we had a sudden cloudburst, we did stay around to try to clean up. We have not been negligent and we have spent considerable time and money to resolve the situation. Please advise at your earliest convenience. Respondent next heard from Lekach on October 9, 1986. Later that same day, pursuant to Lekach's request, Respondent met with Lekach and discussed "the problems at the Guerry residence." The following day, Lekach sent Respondent a letter memorializing the highlights of their discussion. The letter provided, in part, as follows: You will be permitted access to the Guerry property for the following purposes: Inspection of the roof, cleaning of the yard which will include replacement of sod as necessary, replacement of topsoil as necessary, and removal of tar. The performance of the above shall neither be construed as an admission of liability on your part, nor an acceptance of this work as being satisfactory or complete. I agree, however, that it is imperative that steps be taken immediately to mitigate the damage. Further we will both be doing the following: obtain information about repair methods and costs for chattahoochee surface. obtain information about repair methods for the "staining" problem on walls and patio so that the area can be painted. review proposals for correction or replacement of roof, if necessary. There is going to have to be a certain amount of good faith between you and Mrs. Guerry if this situation is to be resolved without litigation. Accordingly, we are now permitting you access to the property in the hope that you will also attend to the other matters set forth above. Mrs. Guerry has been hesitant to accept a partial resolution of this problem without your commitment to complete all of the repairs and this is the reason that the cleanup was delayed in some respects. Hopefully, we will be able to work towards resolving all aspects of the damage. On October 11, 1986, Respondent dispatched a crew to the Guerry property to perform the excavation work that was necessary to remove the soil that had been contaminated by the mineral spirits used in the cleanup effort. On this occasion, the workers were given access to the property for this purpose and they removed and replaced the contaminated soil. On October 13, 1986, Tropical sent a crew to the Guerry property to inspect their roof. Mrs. Guerry would not permit the Tropical workers to enter the premises. She indicated that she would not allow the workers on her property to inspect or repair the roof until she had heard from all those with whom she had consulted regarding the matter. Having been denied access to the property by Mrs. Guerry, the workers left without performing their inspection. At no time thereafter did the Guerrys directly contact Tropical and request that the workers return to the residence to finish the repair of the roof. In the absence of any such direct communication from the Guerrys, Tropical did not attempt to do any further repair work on the roof after October 13, 1986. On October 6, 1986, the Broward County Environmental Quality Control Board had issued a notice of violation citing Tropical with discharg[ing] a substance (mineral spirits) to ground." A hearing on the charge was held before the Board on November 7, 1986. Respondent appeared on behalf of Tropical at the hearing. He admitted that Tropical was guilty of discharging a pollutant, to wit: mineral spirits, into the soil, although he explained that the violation was a product of ignorance on his part regarding the qualities of mineral spirits. Based on this admission of guilt, the Board imposed a $500.00 fine, which was subsequently paid by Respondent. In late 1986, the Guerrys filed with the Department of Professional Regulation a complaint against Respondent. An investigation of the complaint was conducted, following which an initial determination was made that there was "presently no probable cause to find that [Respondent] violated the contractor disciplinary statutes." Respondent was notified of this determination by letter dated May 14, 1987. This determination of no probable cause was subsequently reversed. On January 11, 1989, an administrative complaint was filed by the Department charging Respondent with wrongdoing in connection with the work performed on the Guerry home. The Guerrys no longer own the home. The property was purchased by Broward County in furtherance of the County's airport expansion project. Respondent has previously been disciplined by the Construction Industry Licensing Board. In early 1987, Respondent was fined $500.00 for failing to obtain a permit as required by local law. In March, 1988, he was fined $1,500.00 for failing to call for all required inspections. In August, 1988, he was fined $500.00 for proceeding without a required permit, failing to obtain all required inspections, failing to reasonably honor a guarantee, and displaying gross negligence, incompetence or misconduct.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order (1) finding Respondent guilty of gross negligence and incompetence, in violation of Section 489.129(1)(j) and (m), Florida Statutes, in connection with his supervision of the cleanup of the Guerry residence; (2) suspending Respondent's license for six months and imposing a fine of $1500 for said violation; and (3) dismissing the remaining charges against Respondent that are set forth in the instant Administrative Complaint. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 17th day of November, 1989. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of November, 1989.

Florida Laws (5) 120.57489.105489.115489.119489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES M. MCCURLEY, 85-003254 (1985)
Division of Administrative Hearings, Florida Number: 85-003254 Latest Update: Mar. 25, 1986

The Issue Whether respondent's license should be revoked, suspended or restricted, or whether an administrative fine should be levied against him, or whether he should be reprimanded for the reasons alleged in the administrative complaint?

Findings Of Fact James M. McCurley is a registered roofing contractor, holding Florida License No. RC 0042226. Licensed in Florida since 1982, Mr. McCurley has been in the roofing business for 25 years all told. Although he holds a state license, he is registered to do roof projects in Broward County only, 82-3201-R-R. Thomas v. Shoop, a real estate broker, manages the Mayani Biscayne Condominiums in Miami at 5995 Biscayne Boulevard, (Mayan) and the Camelot South Apartments on 17th Street in Fort Lauderdale (Camelot), which consist of three buildings (A, B and C). Above Camelot B's roof, which "is not properly set up for drainage at all," (T. 183), loomed a leaking water tower, which has only recently been fixed. In the summer of 1983, all four buildings' roofs leaked; and the roofer who had given long-term guarantees on Camelot's roofs had gone bankrupt. An associate of Mr. Shoop knew one John Emig, who was a salesman for Mr. McCurley. Messrs. Shoop and Emig visited the roofs and discussed the problems. In order to "mak[e] sure that they got a reputable roofer. . . [Mr. Shoop] did great deal of research with a list . . . [of] people that [Mr. McCurley] had done work for and were satisfied." (T. 16). Through Mr. Emig, Mr. McCurley offered to replace the 8,000-square-foot roof on Camelot B for $25,000. Further conversations eventuated instead in an agreement, reduced to a separate writing with respect to each Camelot building, Petitioner's Exhibit No. 2, that called for Mr. McCurley to repair, clean and paint the root and soffits of the three Camelot buildings. The contract for Camelot A characterized the work both as restoration and as preventive maintenance. Repairs were to be effected "as needed." The contracts recited the roofing contractor's "opinion [that] the following maintenance work should put this roof and mansard in the best possible condition, and that it reasonably can be expected to have up to a five year service life." Petitioner's Exhibit No. 2. The agreements specified installation of a total of 35 vapor pressure release vents and stated that Mr. McCurley was to: Check and reseal where needed all pitch pockets, using 10-year rubberized elastomers. . . . Remove all blistering coating from the roof decks and at all such spots install a repair patch. Repair any bulges or blisters and treat all cracks as needed using elastomeric and waterproofing membrane. Petitioner's Exhibit No. 2 The contracts were typed on printed forms. When Mr. Emig and Mr. Shoop signed the roofing contracts on August 24, 1983, Mr. McCurley was not present. At the time the agreements were signed, "3 was substituted for "1" in the phrase, "The above work . . . carries with it our 1 year Pree Service Guarantee should any leak occur . . ." Petitioner's Exhibit No. 2. Unchanged was a typewritten paragraph on each contract stating: In this particular situation our warranty shall be a one year unconditional one, which is standard procedure in the industry. Petitioner's Exhibit No. 2. Although Mr. Shoop dealt primarily with Mr. Emig in negotiating the contract, Mr. Shoop and Mr. McCurley went up on a roof together at one point before the contracts were signed. On September 20, 1983, an addendum to the contracts, calling for work on the buildings other than roofing, was executed. The contract price for the roofing work was less than 40 cents per square foot. The roofs in the Camelot complex were built-up tar and gravel, coated with a cementitious fill. Ordinarily insulation lies underneath a built-up roof of this kind. The vapor pressure release vents were proposed and contracted for on the assumption that insulation underlay the tar, insulation which permitted lateral movement of water and water vapor trapped by the tar and cementitious fill. Pressure attendant on vaporization of water trapped underneath the tar and fill is the apparent cause of the cracking and blistering that led to the leaks. In installing the first vapor pressure release vent, Mr. McCurley discovered that the tar had been placed directly on the roof sheathing. He explained to Mr. Shoop that there was no good reason to go forward with installation of the other vents because the impermeability of tar and fill precluded lateral movement of moisture and, therefore, its escape in any significant quantity through the vents. Mr. Shoop insisted, however, that all the vents called for by the contract go in, and Mr. McCurley complied. The vents stood useless (T. 99) but firmly affixed to the roof as recently as five or six months before the hearing. (T. 94) Thereafter, many were dislodged by the contraction and expansion of the roof, aggravating the leakage problems. To meet the contract requirement of an "elastomeric and waterproofing membrane," Mr. McCurley employed a coating he had never used before, but one which was advertised by a company listed on the New York Stock Exchange, Rohm & Haas, as capable of withstanding ponding water. At the time he entered into the contract, Mr. McCurley did not know that this claim was false. In the fall of 1983, he applied this coating not only to places where cementitious fill had bulged, blistered, or cracked, but also to unblemished portions of the Camelot roofs, covering them entirely twice, before applying a final coat of high gloss white paint. Before he was paid, Mr. McCurley had done everything called for by the contract. On May 30, 1984, however, Mr. Shoop told Mr. Emig that old leaks had reappeared and that new leaks had sprung open. Mr. Shoop also telephoned and left word for Mr. McCurley to this effect on June 15, 18, and 19. On July 5, 1984, Mr. Shoop wrote Mr. McCurley a letter, Petitioner's Exhibit No. 4, in response to which Mr. McCurley applied another acrylic waterproofing compound and plastic cement. When he finished, "it looked from a laym[a]n's point of view that it was a good job." (T. 31). In November of 1984, the B building roof still looked good but it leaked. In response to complaints, Mr. McCurley returned several times to repair blistered areas with acrylic waterproofing and to apply plastic cement. Typically these repairs prevented leaks the next hard rain but not the one following. Camelot B needs reroofing, which involves taking out the existing roof and building up a new one with tar and gravel, the approach Mr. McCurley originally recommended.) Mr. Hilson, who has spent approximately 30 years in the roofing business, testified that the coatings that Mr. McCurley used were permeable, and inappropriate for use on horizontal surfaces on that account. Specifically, after inspecting Camelot B's roof, Mr. Hilson testified: It has continued to leak from what we was shown and told. I made a note here that it takes a zero perm rating to hold back water, and these coatings apparently have no such perm rating. These coating[s] are breathable. And because they are breathable they allow water to go through them and become trapped, underneath the cementious fill. The only type of coating that we know of that these type of coatings were normally used on vertical surfaces where water can't stand on them, showing these photographs here the water where it does pond on this coating, it deteriorates the coating. It actually eats it. The fungus attacks it. Basically that's it, except where the bottom statement that I made is that these type of coatings cannot hold back water and should not be used to try to hold back water. And anybody with any roofing knowledge should understand or know they can't hold back water. (T. 71, 72). Respondent McCurley testified that he did not know what numerical "perm rating" the material he used had been given, but that he relied on the manufacturer's representations that it would withstand ponding, when he told Mr. Shoop that he thought it would work. He did not dispute that the coating had failed. Mr. Hilson was of the opinion that not even an impermeable coating would have worked, because it would not only have prevented water's penetrating, but would also have trapped moisture already in the cementitious fill. In his view, when the trapped water vaporized, it "would have blown the system off". Petitioner's Exhibit No. 7. Mr. McCurley also contracted with Mr. Shoop to work on the roof of the Mayani apartment building in Miami. For $1200.00, he undertook, among other things, to check and reseal as needed "litch [sic] pans," repair three leaks in the deck, cover "all bald spots with gravel," and install Gravel Lok over the entire gravel roof area. The leak repairs were unconditionally guaranteed for a year. After work was completed, Mr. McCurley received full payment on September 6, 1983. Before he began work, Mr. McCurley telephoned some government office in Dade County and asked whether a permit was "required to put a cement coating over a gravel built-up roof," (T. 9) and was told that none was required. After the present proceedings were instituted he called again and got the same answer. As a practical matter, persons not licensed as roofers, including "the average painter, goes out and does a waterproof of a roof." (T. 103) Repair of the three leaks probably cost Mr. McCurley $30.00. (T. 99) When he began on the Mayani roof Mr. McCurley was aware that Dade County's code is similar to Broward County's, which incorporates the South Florida Building Code, and knew specifically that Dade County required a permit for roofing repairs "after Three Hundred dollars," (T. 98) a permit he was ineligible to obtain. Dade County does indeed require permits for the "application, construction or repair of any roof covering. . .exceeding three hundred dollars (S300.00) in value of labor and materials, . . . or for work exceeding 2 roofing squares in extent," Petitioner's Exhibit No. 6, and the requirement applied to the job Mr. McCurley did at Mayani. (T. 66). When Mr. Shoop reported the Camelot leaks to Mr. Emig on May 30, 1984, he also reported leaks at Mayani that had appeared after heavy rains in Miami. Eventually respondent repaired the Mayani roof, but problems developed again in November of 1984.

Florida Laws (2) 489.117489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN TERRANOVA, 86-004480 (1986)
Division of Administrative Hearings, Florida Number: 86-004480 Latest Update: Dec. 11, 1987

Findings Of Fact Roger A. Lollis was licensed as a registered roofing contractor at all times material hereto, having been issued license number RC-0030088. His address of record on file with Petitioner has at all times been 912 Tuskawilla Street, Clearwater, Florida, and this is the address to which notice of the hearing was sent. The hearing notice was not returned to the Division of Administrative Hearings by the post office for any reason. Lollis has been the subject of two previous Final Orders imposing disciplinary actions by the Construction Industry Licensing Board. John P. Terranova was first licensed as a registered specialty contractor in August, 1985, having been issued license number RX-0049212 as the qualifying agent for Stretch and Seal Roofing Systems, Inc. Terranova and his wife are the only shareholders of this corporation, and he is the Chairman of its Board of Directors, as well as its President. On November 15, 1984, Mrs. Judith Fugitt executed a contract with Stretch and Seal Roofing Systems, Inc., through its authorized agent, Scott St. John, for work to be performed on her residence at 1636 Bravo Drive, Clearwater, Florida, in order to correct a problem she was having with leaks. The work to be performed was specified in the contract to include: clean and mildewcide roof surface; inspect for water damage beneath tiles that are cracked or broken; replace broken and cracked tiles as necessary; flow coat to seal chimney flashing against leaks; apply 15 year Stretch and Seal coating in color to be specified by home owner; and color to be applied approximately 2 weeks after Stretch and Seal is applied. The contract further stated that the expense of any labor or materials for work not specified in the contract, such as to replace rotten wood, would be the responsibility of the homeowner. The Fugitt contract provided a 15 year warranty and guarantee and stated, "All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard practices." The contract price for the work to be done on the Fugitt's house was $2500, which was to be paid $500 at commencement of the job, $1500 upon completion of the application of Stretch and Seal, and the balance upon completion of painting of the roof tiles. Although Terranova denies meeting with the Fugitts at the time this contract was executed, Mr. Elmer Fugitt testified that Terranova was present and gave his personal guarantee that the work would be done as specified in the contract and would correct the leak problem. Terranova also represented to Elmer Fugitt that he had 30 years experience in the roofing business. It is specifically found, based upon the demeanor of the witnesses, that the testimony of Elmer Fugitt concerning Terranova's personal involvement in this transaction on or about November 15, 1984, is credible, and Terranova's denial thereof is not. Shortly after November 15, 1984, work commenced on the Fugitt roof, and some rotten wood was discovered which needed to be replaced. Tim Egner, another authorized representative of Stretch and Seal Roofing Systems, Inc., then prepared another proposal for repair and replacement of the rotten wood, which Judith Fugitt also accepted. The contract price for this work was $482.50. Both St. John and Egner worked full-time for Terranova's company, with his knowledge and under his control. Terranova referred to Egner as his "operational manager" who handled customer complaints. The Fugitts paid Terranova, through Stretch and Seal Roofing Systems, Inc., a total of $2981.00 between November 27 and December 23, 1984, for work performed on their roof. This was the full amount due under the November 15, 1984 contract and also the subsequent contract for repair and replacement of rotten wood. In late December, 1984, all tiles were in place, the Stretch and Seal coating had been applied, but the tiles had not been painted. In January, 1985, the Fugitt roof continued to leak and Elmer Fugitt therefore contacted Terranova's company. After repeated contacts, Terranova arranged for Roger Lollis to inspect the roof. On March 12, 1985, Lollis obtained a permit from the Pinellas County Department of Building Inspection for roof repair on the Fugitt residence. Lollis never discussed what he was doing with the Fugitts, but was simply assigned to the job by Terranova. Mr. Fugitt saw Lollis on his roof one time. After tearing up a section of tiles and leaving a portion of the Fugitt roof exposed, Lollis walked off the job and never returned. Thereafter, Elmer Fugitt reset the tiles himself after repeated efforts by his attorney to contact Terranova had failed. The Fugitt roof has never been painted although they contracted and paid for this to be done by Terranova's company. At the hearing, Terranova denied his company either contracted for, or performed, roofing work. It was his testimony that he was only obligated to do painting, and it was Lollis' and the Fugitts' responsibility to do the roofing work. Terranova's testimony is not credible because it is contrary to the terms of the contracts the Fugitts executed with his company, and is outweighed by the convincing testimony of Elmer Fugitt. Terranova contracted for and did perform, through his company, roofing work on the Fugitt residence at a time before he was licensed as a roofing contractor. The roofing work performed by Terranova for the Fugitts would be found to be incompetent and would constitute misconduct in the practice of contracting if he had been licensed at the time. He did not repair the leaks, he accepted full payment for a job that was not completed, he avoided or failed to return repeated calls from and on behalf of the Fugitts, and he allowed their roof to be left exposed to the elements after Lollis walked off the job. Terranova failed to honor the guarantee set forth in his contract with the Fugitts. Lollis performed work on the Fugitt roof at the request and direction of Terranova in March, 1985, at a time Terranova was not a licensed roofing contractor. He did obtain a local permit, but did not call for any inspection. In fact, he walked off the job and left the Fugitt roof exposed. Lollis' actions constitute incompetence and misconduct in the practice of contracting, but there is no evidence he knew that Terranova was not licensed at the time. Lollis was not the qualifying agent for Stretch and Seal. Pinellas County building code ordinances require a permit for any roof repair that exceeds $50 and for any general construction that exceeds $500. Terranova failed to obtain any required permits for the Fugitt job. A final inspection on any roofing job for which a permit has been issued is required, but Lollis never called for one after he obtained the permit in March, 1985.

Recommendation Based upon the foregoing, it is recommended that the Construction Industry Licensing Board enter a Final Order: Dismissing the Administrative Complaint filed against John P. Terranova since it has not been shown that the Board has jurisdiction over him under Section 489.129(1)(m), Florida Statutes, for matters occurring prior to his having been licensed. Finding that Roger A. Lollis has violated Sections 489.129(1)(d),(j) and (m), Florida Statutes, and therefore imposing a six month suspension and $1000 administrative fine against him based not only on the facts found herein concerning his actions regarding the Fugitt roof, but also the fact that this is the third disciplinary action taken against his license by the Construction Industry Licensing Board. DONE AND ENTERED this 11th day of December, 1987, in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December, 1987. COPIES FURNISHED: W. Douglas Beason, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 John P. Terranova 3 Birdie Lane Palm Harbour, Florida 33528 Roger A. Lollis 912 Tuskawilla Street Clearwater, Florida 33516 Fred Seely Executive Director Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32201 William O'Neil General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (2) 120.57489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer