THE URBAN GROUP vs DEPARTMENT OF TRANSPORTATION, 94-005967BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 25, 1994 Number: 94-005967BID Latest Update: Feb. 14, 1995

Findings Of Fact The Department issued an invitation to bid (ITB) and solicited bids for district-wide miscellaneous property management maintenance services pursuant to ITB-DOT-94-95-4004. Kemp Services, Inc. (Kemp), submitted the lowest bid for the subject ITB. Petitioner, Urban Group, Inc., submitted the second lowest bid for the subject ITB. Section 1.1 of the ITB provided: Invitation The State of Florida Department of Transport- ation requests written bids from qualified firms to MAINTAIN RIGHT-OF-WAY STRUCTURES AND VACANT LOTS BY PROVIDING CLEAN-UP SERVICES, LAWN SERVICES, LANDSCAPE SERVICES, SECURING OF BUILDINGS, AND OTHER MISCELLANEOUS HANDYMAN AND SKILLED LABOR SERVICES. ALSO PROVIDE SERVICES FOR SIGN REMOVAL FOR STRUCTURES ILLEGALLY ON THE DEPARTMENT'S RIGHT-OF-WAY OR ILLEGALLY ON PRIVATE PROPERTY IN THE FOLLOWING FIVE COUNTY AREA: BROWARD, MARTIN, PALM BEACH, ST. LUCIE AND INDIAN RIVER COUNTIES. For the purpose of this document, the term "bidder" means the prime Consultant acting for itself and those individuals, partnerships, firms, or corporations comprising the bidder's team by joint venture or subcontract. The term "bid package" means the complete response of the bidder to the Invitation To Bid, including properly completed forms and supporting documentation. [Emphasis in text.] The services were to be provided on an as-needed basis for the term of the agreement, two years. Section 1.7.1 of the ITB provided: Qualifications 1.7.1 Bidders must meet the following minimum qualifications: BIDDERS MUST HAVE AT LEAST TWO YEARS EXPERIENCE PROVIDING AT LEAST TWO (2) OF THE SIX SERVICES OUTLINED IN THE SCOPE OF SERVICES IN EXHIBIT "A". BIDDERS MUST HAVE BEEN IN CONTINUOUS BUSINESS FOR THE PAST TWO (2) YEARS AND COMPLETE FORM "F" WITH THE INFORMATION REQUESTED REGARDING WORK EXPERIENCE AND REFERENCES. ALL REFERENCES WILL BE CHECKED. FAILURE TO PROVIDE FORM "F" AND THE WORK EXPERIENCE REQUESTED WILL CONSTITUTE A NON- RESPONSIVE BID. [Emphasis in text.] Section 1.7.4 of the ITB provided: Qualifications of Key Personnel Those individuals who will be directly involved in the project must have demonstrated experience in the areas delineated in the scope of work. Individuals whose qualifications are presented will be committed to the project for its duration unless otherwise accepted by the Department's Contract Manager. Where State of Florida registration or certification is deemed appropriate, a copy of the registration or certificate should be included in the bid package. Section 1.7.5 of the ITB provided: Authorizations and Licenses The Consultant must be authorized to do business in the State of Florida. Such authorization and/or licenses should be obtained by the bid due date and time, but in any case, will be required prior to award of the contract. For corporate authorization, contact: Florida Department of State Division of Corporations The Capitol Building Tallahassee, Florida 32399 (904)487-6052 Other than the provisions above, no other licensure or authorization to do business was required by the ITB. Section 1.8.2 of the ITB provided: Responsiveness of Bids All bids must be in writing. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid. Bids found to be non-responsive shall not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons, including, but not limited to, failure to utilize or complete prescribed forms, conditional bids, incomplete bids, indefinite or ambiguous bids, improper undated or unsealed signatures (where applicable). Section 1.8.4 of the ITB provided: Other Conditions Other conditions which may cause rejection of bids include evidence of collusion among bidders, obvious lack of experience or expertise to perform the required work, or failure to perform or meet financial obligations on previous contracts, or in the event an individual, firm, partnership, or corporation is on the United States Comptroller General's List of Ineligible Contractors for Federally Financed or Assisted Projects. Bids will be rejected if not delivered or received on or before the date and time specified as the due date for submission. Section 1.8.5 of the ITB provided: Waivers The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregular- ities are defined as those that will not have an adverse effect on the Department's interest and will not affect the price of the Bids by giving a bidder an advantage or benefit not enjoyed by other bidders. Section 1.18.1 of the ITB provided: Award of the Contract The Department intends to award a contract to the responsible and responsive bidder who bids the lowest cost as identified in Form "C", Bid Blank, attached hereto and made a part hereof. The ITB did not specify a minimum number of employees, vehicles or hours of service for a bidder to be deemed responsible or responsive. At all times material to this case, Kemp has been in continuous business for the past two (2) years, and completed form "F" with the information requested regarding work experience and references. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. At all times material to this case, Kemp had at least two years experience providing at least two (2) of the six services outlined in the scope of services. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. While Mr. Gentile was authorized to check with all references listed by Kemp, the failure to do so does not discount the information obtained from the sources that were checked. Kemp had an appropriate occupational license to perform work in the tricounty area, but did not have occupational licenses with the City of Hollywood or Broward County. At all times material to this case, Kemp maintained a warehouse to secure the equipment to be used such as lawnmowers, trimmers, and cleaning supplies/equipment. After the bid protest was filed, the Department verified that Kemp had used the warehouse as it claimed. No evidence to the contrary was presented. The mailing address Kemp listed on the first page of its bid response was 8637 S. Sutton Drive, Miramar, Florida. Mr. Faluade resides at that address. He listed that address for mail purposes. The business address for Kemp listed on the bid response was 6200 Johnson Street, Miramar, Florida. This address is a store-front facility with limited office equipment and furniture. Kemp maintains an office at this location but stores its equipment elsewhere as noted above. Kemp was the lowest responsive, responsible bid for ITB-DOT-94-95- 4004.

Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department of Transportation enter a final order dismissing Petitioner's challenge to the award of ITB-DOT-94-95-4004 to Kemp Services, Inc. DONE AND RECOMMENDED this 14th day of February, 1995, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of February, 1995. APPENDIX TO RECOMMENDED ORDER, CASE NO. 94-5967 Rulings on the proposed findings of fact submitted by the Petitioner: Paragraphs 1 through 4, 6, and 8 are accepted. With regard to paragraphs 5, 7, and 16 noting that the additional emphasis is not in the text and that the citations are incomplete (and perhaps misleading), they are accepted. Paragraph 9 is rejected as contrary to the weight of credible evidence. Paragraph 10 is rejected as contrary to the weight of credible evidence. Paragraph 11 is rejected as incomplete, and therefore, misleading. Corporate documents may have been filed on that date, however, the weight of the credible evidence established that Kemp had been in business the requisite amount of time. Paragraph 12 is rejected as incomplete, and therefore, misleading. The business conducted by the Kemp personnel continued regardless of the business entity structure that was used. Paragraph 13 is rejected as contrary to the weight of credible evidence. Paragraph 14 is rejected as contrary to the weight of credible evidence or irrelevant. Paragraph 15 is rejected as contrary to the weight of credible evidence. Paragraph 16 is rejected as contrary to the weight of credible evidence. Moreover, no credible evidence was presented to establish that Kemp did not provide services as described in the ITB or that it was not in business the requisite time. Paragraph 17 is rejected as incomplete, and therefore, misleading. The mailing address listed by Kemp was a residential address. Paragraph 18 is rejected as irrelevant. Paragraph 19 is rejected as contrary to the weight of credible evidence. Paragraph 20 is rejected as irrelevant. Kemp probably does not have a Leon County occupational license either. It did have an appropriate occupational license at all times material to this case. Rulings on the proposed findings of fact submitted by the Respondent: 1. Paragraphs 1 through 29 are accepted. COPIES FURNISHED: Thomas H. Duffy Assistant General Counsel Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Mitchell B. Polay Mark H. Klein 750 S.E. Third Avenue Suite 205 Fort Lauderdale, Florida 33316 Thornton J. Williams General Counsel Department of Transportation 562 Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450

# 1
FLORIDA BLACKTOP, INC. vs DEPARTMENT OF TRANSPORTATION, 02-002187BID (2002)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida May 29, 2002 Number: 02-002187BID Latest Update: Sep. 13, 2002

The Issue The issue is whether Respondent’s proposed award of a contract to Intervenor is contrary to statutes, rules, policies, or the specifications, pursuant to Section 120.57(3)(f), Florida Statutes.

Findings Of Fact On February 15, 2002, Respondent advertised for bids for Contract E4D18 (ITB). The ITB requires bidders to submit their bids with a bid bond and power of attorney no later than 11:00 a.m. on March 8, 2002. Petitioner and Intervenor timely submitted bids at the specified location. Petitioner’s bid price was $2,094,748.99, and Intervenor’s bid price was $2,095,530.00. Petitioner and Intervenor have standing to participate in this case. In preparing its bid, Petitioner obtained a bid bond and power of attorney from Great American Insurance Company through its local bonding agent, Nielson, Alter and Associates. (All references to bid bonds shall mean the bid bond and accompanying power of attorney.) Nielson, Alter and Associates and its predecessor has provided bid bonds for Petitioner for 12 years. Pursuant to its standard business practice, Petitioner received the bid bond from Nielson, Alter and Associates the day prior to the deadline for submitting bids. The bond was in proper form, duly authorized, and validly executed, so it was enforceable upon delivery from Petitioner to Respondent. If Petitioner in fact delivered the bond with the bid on the following day, Respondent would have no basis to reject Petitioner’s bid as unresponsive. Petitioner’s employee responsible for assembling and delivering Petitioner’s bid has been so employed by Petitioner for three and one-half years. She testified that she placed the bid bond in the package with the bid itself, sealed the package, drove it to the assigned location, and submitted the sealed bid package to Respondent by 10:30 a.m. on March 8, 2002. Respondent’s employees accepted Petitioner’s sealed bid package and, without opening it, placed it in a locked filing cabinet, where they placed the three other timely submitted bids for the subject project. At 11:00 a.m.--the time specified for the opening of bids--one of Respondent’s employees removed the four sealed bid packages and took them to the conference room for the opening of the bids in response to the ITB. At the same time and place, Respondent’s employees were opening 21 other bids in response to five other invitations to bid on projects unrelated to the subject project. The conference room was small and contained a table. On one side of the table sat three of Respondent’s employees, who remained with the bid packages continuously from when they arrived in the conference room until, after they were opened, they were taken upstairs to a data processing center. On the other side of the table sat Petitioner’s employee and a representative of another bidder. The 25 bid packages were in six separate piles, divided by project. One of Respondent’s employees opened each bid and handed it to a second employee who announced the name of the bidder and the amount of the bid. The second employee then passed the bid to the third employee who recorded the bid. As was consistent with Respondent’s past practice, no one announced whether each bid was complete. At the end of the opening of the bids in response to the ITB, Respondent’s employee announced that Intervenor had submitted the lowest bid. Due to a mathematical error in Intervenor’s bid, it appeared from the cover sheets that Intervenor’s bid was the lowest. Only later, after the mathematical error was corrected, did Respondent’s employees discover that Petitioner had submitted the lowest bid. After Petitioner’s employee and the representative of the other bidder had left the conference room, Respondent’s three employees examined the bid packages more closely. They could not find the bid bond in Petitioner’s bid package, nor could they find the bid bond in the bid package of a bidder for one of the other contracts. The first of Respondent’s employees to discover that she could not find the bid bond in Petitioner’s bid package reexamined Petitioner’s bid package in search of the documents. The three employees then checked inside every envelope for the documents that were missing from the bid packages of Petitioner and the other bidder, but they could not find the missing documents. It was highly unusual for a bid bond to be missing from a bid package and probably unprecedented for bid bonds to be missing from two bids for separate jobs opened at the same time. Consistent with their practice then and now, Respondent’s employees separated the bidders’ checks from the bid packages and placed the checks in a secure location. Consistent with their practice then and now, one of Respondent’s employees then delivered the remainder of each bid package to the data processing center upstairs. Consistent with their practice then, but not now, Respondent’s employees did not document that the bid bond was missing for several days after the bid opening. Petitioner contends that Respondent’s employees did not discover that the bid bond was missing until days after the bid opening. Petitioner reasons, in part, that Respondent’s employees were not as attentive to Petitioner’s bid because they thought that it was only the second lowest bid. Petitioner contends that the discovery of the missing bid bond several days after its submittal provides Respondent’s employees with considerable opportunity to mishandle the bid package and inadvertently misplace the bid bond. In support of its contention that Respondent’s employees did not immediately discover the missing bid bond, Petitioner offered the testimony to this effect of its president and proffered similar testimony of another witness. The bases of this testimony were separate statements from the employee who supervised the three employees who opened, announced, and recorded the bids. However, this testimony, even from both witnesses, could not overcome the clear and unequivocal testimony of all three of Respondent’s employees that they discovered that Petitioner’s bid package was missing the bid bond on the day of the bid opening. Any statement to the contrary by Respondent's supervisory employee may have been based on her misrecollection or ignorance of the facts or misunderstanding of the questions posed to her, although it is also possible that both listeners separately misunderstood what she was saying. A bid bond is a crucial component of a bid. Its omission confers a competitive advantage upon a bidder, which, after bid opening, could elect not to cure the omission and thus be relieved of the obligation that it otherwise appeared to have offered to undertake by submitting its bid. Intervenor's post-hearing memorandum adds a perceptive discussion of the dullness of memory when attesting to a matter of routine, as was the testimony of Petitioner's employee who "always" attached bid bonds to bids, compared to the vividness of memory when attesting to a rare deviation from routine, as was the testimony of Respondent's three employees who were startled to find that bid bonds were missing from two bid packages, looked for the missing documents, and could not find them. On the present record, it would be slightly less troubling to find that Petitioner's bid package lacked the bid bond, but, as noted below, the burden of proof is on Petitioner, so it suffices to find that Petitioner has failed to prove that its bid package contained the bid bond.

Recommendation It is RECOMMENDED that the Department of Transportation enter a final order dismissing the bid protest of Petitioner and awarding the contract to Intervenor. DONE AND ENTERED this 6th day of August, 2002, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 6th day of August, 2002. COPIES FURNISHED: Thomas F. Barry, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 James C. Myers, Clerk of Agency Proceedings Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450 Barbara Gasper Hines Assistant General Counsel Department of Transportation 605 Suwanee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Joseph W. Lawrence, II Vezina, Lawrence & Piscitelli, P.A. 360 East Las Olas Boulevard, Suite 1130 Fort Lauderdale, Florida 33301 F. Alan Cummings Smith, Currie & Hancock LLP 1004 DeSoto Park Drive Post Office Box 589 Tallahassee, Florida 32302-0589

Florida Laws (1) 120.57
# 2
SPINELLA ENTERPRISES, INC. vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 08-003380BID (2008)
Division of Administrative Hearings, Florida Filed:Lauderdale Lakes, Florida Jul. 14, 2008 Number: 08-003380BID Latest Update: Nov. 04, 2008

The Issue The issue in this bid protest is whether Respondent acted arbitrarily when it decided to reject all of the bids it had received in response to a solicitation seeking bids on a contract for roof repairs.

Findings Of Fact On January 10, 2008, the Florida Department of Environmental Protection (the "Department" or "DEP") issued an Invitation to Bid (the "ITB"), the purpose of which was to solicit competitive bids from qualified contractors on a project whose scope of work envisioned repairs to the wind-damaged roofs of several buildings located on the grounds of the Hugh Taylor Birch State Park in Fort Lauderdale, Florida. Some of the buildings to be repaired were single-family residences. Work on these structures accordingly needed to conform to the requirements prescribed in the 2007 Manual of Hurricane Mitigation Retrofits for Existing Site-Built Single Family Residential Structures (the "Manual"), which the Florida Building Commission (the "Commission"), following an explicit legislative directive, see Section 553.844(3), Florida Statutes,1 recently had adopted, by incorporative reference, as a rule. See Fla. Admin. Code R. 9B-3.0475 (2007).2 The Rule had taken effect on November 14, 2007, giving the Manual's contents the same status and force as the Florida Building Code. Id. Just before the Department issued the ITB, the Commission had approved, at a meeting on January 8, 2008, a modified version of the Manual, which it called the 2007 Manual of Hurricane Mitigation Retrofits for Existing Site-Built Single Family Residential Structures, Version 2 (the "Revised Manual"). In consequence of the Commission's approval of the Revised Manual, the Florida Department of Community Affairs ("DCA") caused a Notice of Proposed Rule Development to be published on January 25, 2008, in the Florida Administrative Weekly. This official advertisement announced that the Commission intended to amend Rule 9B-3.0475, so that its incorporative reference would mention the Revision Manual instead of the Manual. See 34 Fla. Admin. W. 461-62 (Jan. 25, 2008).3 DCA caused a Notice of Proposed Rule respecting the intended revision of Rule 9B-3.0475 to be published on February 1, 2008, in the Florida Administrative Weekly. See 34 Fla. Admin. W. 605 (Feb. 1, 2008).4 On February 5, 2008, the Department issued Addendum No. 4 to the ITB (the "Addendum"). The Addendum provided in pertinent part as follows: Bidders shall bid the project as specified despite the recent change in Rule 9B-3.0475 relating to hurricane mitigation retrofits. Any additional water barrier will be accomplished by Change Order after award of the contract. (The foregoing provisions of the Addendum will be referred to hereinafter as the "Directive"). On February 12, 2008, the Department opened the bids it had received in response to the ITB. Ten (out of 12) of the bids submitted were deemed responsive. The bid of Petitioner Spinella Enterprises, Inc. ("Spinella") was one of the acceptable bids. On February 19, 2008, DEP posted notice of its intent to award a contract to the lowest bidder, namely Spinella, which had offered to perform the work for $94,150. The second lowest bidder was The Bookhardt Group ("Bookhardt"). Bookhardt timely protested the intended award, raising several objections, only one of which is relevant here. In its formal written protest, dated March 3, 2008, Bookhardt alleged that "[t]he new State of Florida law F.S. 553.844 was not part of the solicitation." On April 4, 2008, Rule 9B-3.0475, as amended to incorporate by reference the Revised Manual, took effect. See Fla. Admin. Code R. 9B-3.0475 (2008). On May 16, 2008, DEP posted notice of its intent to reject all bids received in response to the ITB. (Bookhardt's protest, which remained pending, had never been referred to DOAH for a formal hearing.) Spinella timely protested the Department's decision to reject all bids. In an email sent to Spinella on July 22, 2008, DEP's counsel explained the rationale behind the decision: The reason the Department rejected all bids follows. When the Department posted the notice of intent to award the contract to Spinella Enterprises, Inc., the second low bidder (Bookhardt Roofing) protested the intent to award. The second low bidder's basis for protesting the intended award was that Addendum 4 directed bidders to ignore certain rules of the Construction Industry Licensing Board [sic], which had become effective after the bid opening, which was not in accordance with the law. As a result, this may have caused confusion and the Department had no assurance that bidders were bidding the project correctly. In addition, the statement in Addendum 4 that the Department would add the required moisture barrier afterward by change order set up a situation where bidders had no idea how much the Department would be willing to pay for the change order. Further, the moisture barrier was not the only thing required by the new rules. Potential bidders may not have bid due to these uncertainties. The Department agreed with Bookhardt's assertions and rejected all bids . . . . Notwithstanding Spinella's protest, the Department issued a second invitation to bid on the project in question. As of the final hearing, the bids received in response to this second solicitation were scheduled to be opened on August 12, 2008. Ultimate Factual Determinations The Department's decision to reject all bids is premised, ultimately, on the notion that the Directive told prospective bidders to ignore an applicable rule in preparing their respective bids.5 If this were true, then the Directive could have been a source of potential confusion, as the Department argues, because a prudent bidder might reasonably hesitate to quote a price based on (possibly) legally deficient specifications. The Directive, however, did not instruct bidders to ignore an applicable, existing rule. Rather, under any reasonable interpretation, it instructed bidders to ignore a proposed rule and follow existing law. Such an instruction was neither confusing nor inappropriate. To be sure, the first sentence of the Directive——at least when read literally——misstated a fact. It did so by expressing an underlying assumption, i.e. that Rule 9B-3.0475 recently had been changed, which was incorrect. In fact, as of February 5, 2008, the Rule was exactly the same as it had always been. (It would remain that way for the next two months, until April 6, 2008).6 DEP's misstatement about the Rule might, conceivably, have confused a potential bidder, at least momentarily. But DEP did not factor the potential for such confusion into its decision to reject all bids, and no evidence of any confusion in this regard was offered at hearing.7 More important is that the unambiguous thrust of the Directive was to tell bidders to rely upon the "not recently changed" Rule 9B-3.0475, which could only have meant Florida Administrative Code Rule 9B-3.0475 (2007) as originally adopted, because that was the one and only version of the Rule which, to that point, had ever existed. Thus, even if the Department were operating under the mistaken belief, when it issued the Addendum, that Rule 9B-3.0475 recently had been amended; and even if, as a result, DEP thought it was telling prospective bidders to ignore an applicable, existing rule, DEP nevertheless made clear its intention that prospective bidders follow the original Rule 9B- 3.0475, which was in fact the operative Rule at the time, whether or not DEP knew it. Indeed, as any reasonable potential bidder knew or should have known at the time of the Addendum, (a) the Commission recently had approved the Revised Manual, but the contents thereof would not have the force and effect of law unless and until the Revised Manual were adopted as a rule, which had not yet happened; (b) the Commission had initiated rulemaking to amend Rule 9B-3.0475 so as to adopt the Revised Manual as a rule, but the process was pending, not complete; (c) Rule 9B-3.0475 had not been amended, ever; and, therefore, (d) the Manual still had the force and effect of law. See endnote 6. The Directive obviously could not alter or affect these objective facts. At bottom, then, a reasonable bidder, reviewing the Directive, would (or should) have concluded either (a) that the "recent change" which DEP had in mind was the Commission's approval of the Revised Manual (or the subsequent announcement of the proposed amendment to Rule 9B-3.0475) or (b) that DEP mistakenly believed the Rule had been changed, even though it had not been. Either way, a reasonable bidder would (or should) have known that the Department wanted bidders to prepare their respective bids based not on the Revised Manual, but the Manual. In other words, regardless of what DEP subjectively thought was the existing law, DEP clearly intended (and unambiguously expressed its intent) that bidders follow what was, in fact, existing law. This could not have confused a reasonable bidder because, absent an instruction to exceed the minimum required legal standards (which the Directive was not), a reasonable bidder would have followed existing law in preparing its bid, just as the Directive required. Once it is determined that the Directive did not, in fact, instruct bidders to ignore an applicable, existing law, but rather told them to rely upon the applicable, existing law (notwithstanding that such law might change in the foreseeable future), the logic underlying the Department's decision to reject all bids unravels. Simply put, there is no genuine basis in logic or fact for concluding that the Addendum caused confusion. The other grounds that DEP has put forward do not hold water either. Contrary to the Department's contention, the possibility that a Change Order would be necessary if an "additional water barrier" were required could not possibly have confused potential bidders or caused them to be uncertain about how much money the Department would be willing to pay for such extra work. This is because Article 27 of the Construction Contract prescribes the procedure for entering into a Change Order, and it specifies the method for determining the price of any extra work. See ITB at 102-05. The fact that the proposed amendment to Rule 9B-3.0475, if it were to be adopted and become applicable to the instant project, might require other additional work, besides a water barrier, likewise could not reasonably have caused potential bidders to refrain from bidding, for the same reason: The Construction Contract contains explicit provisions which deal with the contingency of extra work or changes in the work. Id. In sum, DEP's intended decision to reject all bids cannot be justified by any analysis that a reasonable person would use to reach a decision of similar importance. It is, therefore, arbitrary.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department enter a final order finding that its decision to reject all bids was arbitrary. Because the Department elected not to comply with the statutory directive to abate this procurement pending the outcome of Spinella's protest, with the result that the contract at issue possibly has been awarded already to another bidder; and because the choice of remedies for invalid procurement actions is ultimately within the agency's discretion, the undersigned declines to make a recommendation regarding the means by which DEP should rectify the harm to Spinella, but he urges that other appropriate relief be granted if Spinella cannot be awarded the contact. DONE AND ENTERED this 2nd day of October, 2008, in Tallahassee, Leon County, Florida. JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of October, 2008.

Florida Laws (3) 120.569120.57553.844 Florida Administrative Code (2) 9B-3.0479B-3.0475
# 3
DIVERSIFIED DESIGN ENTERPRISES vs SEMINOLE COUNTY SCHOOL BOARD, 90-002357BID (1990)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Apr. 20, 1990 Number: 90-002357BID Latest Update: May 22, 1990

The Issue The issue in this case is whether Respondent properly rejected the bid of Petitioner.

Findings Of Fact Respondent issued on February 28, 1990, an invitation to bid concerning the installation of bleachers at a high school ("ITB"). The ITB was duly advertised. Among the bidders was Interkal, Inc., which is a manufacturer of bleachers. The Interkal bid, which was timely submitted, was executed by its president. The Interkal bid contained a bid bond naming Interkal as principal and a certification from the secretary of Interkal reflecting a corporate resolution authorizing the execution of all bid documents on behalf of Interkal by its corporate officers. The Interkal bid disclosed two subcontractors. The supplier was shown as Interkal, and the erector was shown as Petitioner. Petitioner is the authorized factory representative for Interkal in Florida. As such, Petitioner solicits business and installs and removes bleachers on behalf of Interkal. As compensation, Petitioner receives commissions for such work from Interkal. However, the shareholder and chief executive officer of Petitioner is not a shareholder or officer of Interkal. In addition, Petitioner is not authorized to execute bid documents on behalf of Interkal. Petitioner is no more than a Subcontrator of Interkal. The bidder in this case was Interkal, not Petitioner, even though Petitioner handled much of the paperwork or its manufacturer. When an unrelated bidder was awarded the contract, Petitioner filed a formal written protest in its name. Interkal has not participated as a party in the subject proceeding.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that Respondent enter a Final Order dismissing the petition of Diversified Design Enterprises. ENTERED this 22nd day of May, 1990, in Tallahassee, Florida. ROBERT D. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of May, 1990. COPIES FURNISHED: Ned N. Julian Stenstrom, McIntosh, et al. P.O. Box 1330 Sanford, FL 32772-1330 William Merkel, President Diversified Design Enterprises 321 N.E. Second Avenue Delray Beach, FL 33444 Robert W. Hughes, Superintendent Seminole County School Board 1211 Mellonville Avenue Sanford, FL 32771

Florida Laws (2) 120.53120.57
# 4
COS AND PALMER CONSTRUCTION COMPANY AND OVERLAND CONSTRUCTION COMPANY vs. SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 85-002044BID (1985)
Division of Administrative Hearings, Florida Number: 85-002044BID Latest Update: Jul. 09, 1985

Findings Of Fact Based on the stipulations and admissions of the parties, on the exhibits received in evidence, and on the testimony of the witnesses at hearing, I make the following findings of fact. The South Florida Water Management District (hereinafter "District") advertised for bids on Contract No. M-0137, Bid No. B-85-91, for the construction of a structure maintenance facility. The Specifications and Contract Documents for the project required that bidders submit a "Base Bid," which related to the essential components of the project, and three "add alternates," which related to additional items that the District might contract for over and above the Base Bid. The Notice To Contractors regarding this project included the following language: The right is reserved, as the interest of the District may require, to reject any or all proposals, to waive any informality in the proposal, or to readvertise for other or future proposals. Paragraph 2 of the Instructions To Bidders includes the following language: "The intent of the Proposal Form is to secure a price, based on unit prices, for the work described in the Contract. . . ." (emphasis added) Paragraph 4 of the Instructions To Bidders reads as follows: The District reserves the right to reject any and all proposals (i) when such rejection is in the interest of the District; (ii) if such proposal is void per se; or (iii) if the proposal contains any irregularities, PROVIDED, however, that the District reserves the right to waive any irregularities and to accept the lowest responsible bidder's proposal determined by the Engineer on the basis of the gross sum for which the work will be performed, arrived at by a correct computation of the base bid plus the alternate bid item or items selected by the District. Bid items will be considered by the District on the has is of budgetary capability. (First emphasis in original; second emphasis added.) Paragraph 5 of the Instructions To Bidders reads as follows: Proposals will be considered irregular if they show omissions, unauthorized alterations of form, additions not called for, conditional or unauthorized alternate bids, or other irre- gularities of any kind; also if the unit prices are unbalanced either in excess of or below the reasonable cost analysis values, or incomplete in any manner, including failure to bid on all items on the bid form. Paragraph 8 of the Instructions To Bidders reads as follows: No proposal can be withdrawn after it is filed unless the Bidder makes his request in writing to the District prior to the time set for the opening of bids, or unless the District fails to accept it within sixty (60) days after the date fixed for opening bids. Paragraph 10 of the Instructions To Bidders reads as follows: No interpretation of the meaning of the Plans, Specifications or other Contract Documents will be made to any Bidder orally. Every request for such interpretation should be in writing addressed to the Engineering & Construction Division, South Florida Water Management District, 3301 Gun Club Road, Post Office Box V, West Palm Beach, Florida, zip code 33402, and to be given consideration must be received at least Ten (10) calendar days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written Addenda to the Specifications which, if issued, will be mailed by registered mail to all prospective bidders (at the respective addresses furnished for such purposes) not later than Five (5) calendar days prior to the date fixed for the opening of bids. Failure of any bidder to receive any such Addendum of interpretation shall not relieve any bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the Contract Documents. The bid items are described in Section 01021 of the Specifications and Contract Documents. Subsection 1.01 of that Section describes what is included in the Base Bid as follows: The Base Bid includes all work shown on the plans and called for in the specifications for: Structure Maintenance Facility, complete. Building utilities including all rough-in required for alternate bid items whether or not alternate bids are accepted. Site work including utilities. All other costs of the project not attributable to Items 1 thru 3 above or Alternate Bid Nos. 1 thru 3 below. Subsection 1.02 of Section 01021 describes what is included in Alternate Bid No. 1 as follows: In the Base Bid all structural supports to receive the monorail trolley beams and hoists are included. Alternate No. 1 includes all work shown on the plans and called for in the specifications for two 15 ton capacity monorail hoists and trolley beams complete and operational. Work includes all final utility connections to points indicated on drawings, shipping, unloading at site, installation and final check-out and instruction to owner on operation of equipment as well as all other costs not attributable to items previously mentioned. Subsection 1.03 of Section 01021 describes what is included in Alternate Bid No. 2 as follows: In the Base Bid all mechanical and electrical rough-in is to be provided for the two offices and the toilet and locker rooms above. Alternate No. 2 includes all costs over the Base Bid for completing the offices, toilets and locker rooms including all plumbing and lighting fixtures, partitions, lockers finishes, structure and metal stair as indicated and specified in the applicable sections of these specifications. Subsection 1.04 of Section 01021 describes what is included in Alternate Bid No. 3 as follows: The Base Bid includes all site grading to finish elevations indicated. Alternate No. 3 includes all costs over the Base bid for providing subsurface preparation and asphaltic concrete paving to finish elevations indicated as described in Section 02513 for all areas where asphaltic concrete paving is shown. In September of 1984 the District had received bids for a similar project. Similar contract documents and bid forms were used for the project. Cox & Palmer Construction Company, Overland Construction Company, Inc., and Booth Construction, Inc., all submitted bids on the September 1984 project. All of the bids submitted on the September 1984 project, including the Booth bid, were submitted on an add alternates" basis. All of the September 1984 bids were rejected. A total of seven bidders submitted bids on the instant project. With the exception of Booth Construction, Inc., all of the bidders on the instant project calculated their bids on an "add alternates" basis. It was the clear intent of the architecture firm that prepared the Specifications and Contract Documents that the bids should be submitted on an add alternates" basis. There were no irregularities in the bidding process regarding the instant project prior to the opening of the first bid. At the duly appointed time a representative of the District began the process of opening and announcing the amounts of the bids. The first bid to be opened was the bid submitted by Overland Construction Company, Inc. The amounts bid by Overland were as follows: Base Bid $ 378,800 Alternate No. 1 64,000 Alternate No. 2 18,000 Alternate No. 3 11,200 Immediately after the announcement of the amounts bid by Overland, Mr. York, the Director of the District's Engineering and Construction Division, asked, "Is that an add-on or deduct?" Someone in the audience answered that it was an "add-on" bid. Mr. Gerachi, on behalf of Booth, promptly stated that the alternates should have been bid as "deducts". A general discussion ensued among members of the audience regarding whether the alternates should have been bid as "add-on" or "deducts." In order to continue with the bid opening process and to restore order in the room, a representative of the District announced that the matter would be resolved when the bids were tabulated and another representative of the District began the process of opening the rest of the bids. The bid submitted by Booth Construction, Inc., was the fourth bid to be opened. The amounts written on the Booth bid were as follows: Base Bid $ 396,586 Alternate No. 1 54,072 Alternate No. 2 14,597 Alternate No. 3 9,185 Immediately after the amounts of the Booth bid were announced, Mr. Alvin Booth, president of Booth Construction, Inc. stood up and stated that the Booth bid had been calculated on the basis of "deduct" alternates. The essence of his statement was that in calculating the amount of his company's Base Bid he had added to the base bid the sum of the three alternate bids with the understanding that the amounts shown for any of the three alternates would be deducted from his Base Bid if the District decided not to award a contract for one or more of the alternates. This statement following the opening of the Booth bid was the first time that anyone on behalf of Booth had made a specific unambiguous statement to representatives of the District responsible for this bidding process regarding the manner in which the Booth bid was calculated. 1/ The bid submitted by Cox & Palmer Construction Company was opened after the Booth bid. The amounts bid by Cox & Palmer were as follows: Base Bid $ 392,225 Alternate No. 1 38,770 Alternate No. 2 19,200 Alternate No. 3 11,456 The bid submitted by Booth Construction, Inc., was prepared by both Vincent Gerachi, an estimator and project manager employed by Booth Construction, Inc., and by Alvin Booth, president of Booth Construction, Inc. Mr. Gerachi has been an estimator on construction projects for approximately 12 years. Mr. Booth has been in the construction business for approximately 30 years and has had his own construction company for about 18 years. Both Mr. Gerachi and Mr. Booth were uncertain whether the alternate bids were supposed to be bid as "add-ons" or as "deducts." Neither of them attempted to do anything to resolve their uncertainty until the morning of the very day on which bids were to be submitted. On that morning Mr. Gerachi called a representative of the District to ask whether the bid should be prepared with the alternate bids calculated as "add-ons" or as "deducts." Mr. Gerachi spoke to Mr. Brown at the District, who suggested that Mr. Gerachi call the architecture firm that had prepared the Specifications and Contract Documents. Notwithstanding the provisions of Paragraph 10 of the Instructions To Bidders (see paragraph 6 of these findings of fact, above), it is a customary practice of the trade for bidders to communicate directly with project architects to resolve any uncertainties in the Specifications and Contract Documents. Indeed, it is generally understood in the trade that it is the duty of the bidder to communicate with the project architect to seek resolution of any ambiguities. Mr. Gerachi tried to reach the project architect by telephone, but was unable to reach him because the architect had already left his office to drive to the bid opening. Mr. Gerachi did not have an opportunity to talk to the architect prior to filing the Booth Construction bid because the architect did not come into the bid opening room until about one minute after 2:00 p.m. Mr. Gerachi talked to Mr. and Mrs. Booth before turning in the Booth bid. Mr. Gerachi prepared the Booth bid with the alternate bids calculated as "deducts" from the Base Bid. In other words, the amount of the Base Bid on the Booth bid included the sum of the three alternate bids, which alternate bids were also separately stated on the Booth bid. Alvin Booth participated in the preparation of the bid and was aware of the manner in which the Booth bid was calculated before the bid was submitted to the District. Even though the Base Bid on the Booth bid is in the amount of $396,586, it was the intention of Booth Construction, Inc., to bid $318,732 for the work described as being within the scope of the Base Bid. The reason for the higher amount being entered for the booth Base Bid is that Vincent Gerachi and Alvin Booth misinterpreted the Specifications and Contract Documents and added to the Booth Base Bid the sum of the Booth bids on each of the three Alternate Bids. 2/ This misinterpretation of the Specifications and Contract Documents was caused by the culpable negligence or willful inattention of Vincent Gerachi and Alvin Booth. After all of the bids were opened a representative of the District announced that the District would consider the matter and notify all bidders of its decision at a later date. Thereafter the District, having concluded that Booth Construction, Inc., had acted in good faith and that the irregularities in the form of its bid were "minor irregularities," decided to treat the oral statements by Mr. Gerachi and Mr. Booth as amendments to the Booth bid, to treat the Booth Base Bid as being $318,732, and to award a contract to Booth Construction, Inc., for the Base Bid and Alternate No. 1 in the amount of $372,804, calculated as follows: $318,732 (Amended Booth Base Bid) 54,072 (Booth Alternate No. 1 Bid) $372,804 (Total Contract) Booth Construction, Inc., has the ability to perform the contract and can perform the contract for the proposed contract amount of $372,804. Booth Construction, Inc., is a responsible bidder. The District estimate of the cost of the work covered by the Base Bid and Alternate No. 1 was $329,000. There are no irregularities in the bid submitted by Cox & Palmer Construction Company. Cox and Palmer Construction Company is a responsible and responsive bidder. The bid submitted by Cox & Palmer is the lowest responsive bid for the combination of the Base Bid and Alternate No. 1. 3/ The foregoing findings of fact include the substance of the majority of the findings proposed by the parties, although I have rejected a number of unnecessary details and editorial comments in the parties' proposals. Any proposed findings which are not incorporated in the foregoing findings are rejected on the grounds of not being supported by competent substantial evidence or as being contrary to the weight of the persuasive evidence.

Recommendation Based on all of the foregoing, I recommend that the South Florida Water Management District enter a Final Order to the following effect: Concluding that the irregularities in the Booth Construction, Inc., bid may not be waived and that the bid will be considered, as submitted, to be a Base Bid in the amount of $396,586; Concluding that in view of the foregoing treatment of the Booth bid, the bid of Palmer & Cox Construction Company is found to be the lowest responsive bid for the Base Bid plus Alternate No. 1; Concluding that the District will accept the bid of Palmer & Cox Construction Company and enter into a contract with Palmer & Cox Construction Company consistent with the amounts bid by Palmer & Cox Construction Com- pany for the Base Bid and Alternate No. 1; and Concluding that the petition of Overland Construction Company, Inc., is dismissed for lack of standing. DONE AND ORDERED this 9th day of July, 1985, at Tallahassee, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of July, 1985.

Florida Laws (4) 1.011.021.04120.57
# 5
RECREATIONAL SURFACES, INC. vs PALM BEACH COUNTY SCHOOL BOARD, 94-006955BID (1994)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Dec. 14, 1994 Number: 94-006955BID Latest Update: Mar. 30, 1995

The Issue Whether the apparent low bid on contract No. SB 95C-66W should be disqualified on the grounds that the bidder does not meet the experience specifications contained in the Invitation to Bid.

Findings Of Fact On August 16, 1994, the School Board issued Invitation to Bid (ITB) No. SB 95C-66W, which was described as being a "term contract to provide and/or install rubberized coatings for sports surfaces." Among the bidders who responded to the ITB were the Petitioner, Papico Construction, Inc., and AAA Tennis Courts, Inc. On August 31, 1994, bids were tabulated and the School Board posted its intent to award the bid to Papico. Thereafter, the bid process was delayed as a result of a protest filed by another bidder. On December 12, 1994, Petitioner filed the formal bid protest that resulted in this proceeding. The School Board does not challenge the timeliness of Petitioner's protest. Among the special conditions of the ITB is the following pertaining the qualifications of the bidder: E. QUALIFICATIONS: The bidder shall have maintained continual work experience in coatings for running tracks for a period of three years prior to the bid date. Bidder must submit written documentation with bid or within three days upon request, substantiating experience requirement. The bidder shall have a place of business for contact by the owner during normal working days. Petitioner framed its challenge to the bid process by the following portion of its formal bid protest: . . . To award this project to Papico or AAA Tennis Courts is not only directly in contradiction to the 3 years of continuous work experience section of the specifications (Special Conditions - E), but also deprives the school system of our experience. . . . Papico timely submitted to the School Board written documentation that substantiated that it met the experience requirement contained in Special Condition - E. The evidence presented at the formal hearing established that Papico is an experienced contractor for recreational surfaces and has been involved in coatings for running tracks since 1989. Between 1989 and the time of the formal hearing, Papico had been involved as either the contractor or as a subcontractor for the surfacing or resurfacing of running tracks at Indiantown Middle School, Parkland High School, Hidden Oaks Middle School, J.D. Parker Elementary School, Florida Atlantic University, Martin County High School, South Plantation High School, and Deland High School. At the formal hearing, Petitioner asserted that Papico also did not meet the experience criteria contained in Special Condition - M. That provision is as follows: M. QUALIFICATIONS: The contractor will submit a list of five all-weather running tracks the firm has resurfaced during the past three years. The list shall contain: owner name, location, phone number, number of tracks, and year constructed or resurfaced. (The district reserves the right to contract these owners as references.) Notwithstanding the fact that this issue was not properly preserved by Petitioner, the evidence established that Papico provided this list to the School Board, thereby complying with Special Condition - M.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Palm Beach County enter a final order that adopts the findings of fact and conclusions of law contained herein, dismisses the bid protest filed by Recreational Surfaces, Inc., and awards the subject contract to Papico Construction, Inc. DONE AND ENTERED this 9th day of February, 1995, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of February, 1995. COPIES FURNISHED: James Petrucelli Recreational Surfaces, Inc. 2123 Oregon Street Orlando, Florida 32803 Robert A. Rosillo, Esquire Palm Beach County School Board 3318 Forest Hill Boulevard, Suite C-302 West Palm Beach, Florida 33406-5813 Dr. Monica Uhlhorn, Superintendent Palm Beach County School Board 3340 Forest Hill Boulevard West Palm Beach, Florida 33406-5869

Florida Laws (2) 120.57287.012
# 6
SANMAR GENERAL CONTRACTORS, INC. vs. STATE UNIVERSITY SYSTEM OF FLORIDA, 83-001919BID (1983)
Division of Administrative Hearings, Florida Number: 83-001919BID Latest Update: Dec. 15, 1983

Findings Of Fact On November 30, 1982 the Chancellor of the State University System approved Amendment 567, as revised, to the Capital Outlay Implementation Plan. This Amendment budgeted $6,350,000 for the construction and equipment of a teaching gymnasium at Florida International University on the Tamiami Campus. Included within that figure were $350,000 of planning expenses appropriated by the 1981 Florida Legislature and $6,000,000 appropriated by the Legislature in 1982 for the expenses of construction, art work and contingencies. In the early part of 1983 the State University System advertised for bids from contractors to construct the gymnasium. The bids were open on May 17, 1983 at 2:00 PM. on the Florida International University Tamiami Campus. Petitioner's base bid of $5,998,000 was the lowest of the 17 received, nevertheless it was $350,000 above the estimate in Amendment 567. The next lowest bid was for $6,045,000. The bid specifications required that six alternatives in addition to the base cost be bid on, but through an oversight Sanmar's bids on these alternatives did not conform to the bid specifications. Sanmar's alternative bids failed to indicate that the amount reflected was in addition to the base cost bid. However, because the issues in this case concern the base bid amount, Sanmar's error with respect to the alternatives is not material. At the May 17, 1983 bid opening Respondent's agent, the architectural firm of Greenleaf-Telesca, announced that it would recommend to the Board of Regents that all bids be rejected as being in excess of the funds available through legislative appropriations. Respondent intends to make design changes in the project to make it less expensive and to then rebid it. On May 18, 1983 Sanmar timely filed a protest to the rejection of its bid. Subsequent to May 17, 1983 and Respondent's decision to reject all bids, the Florida Legislature through Section 2(2)(y), Chapter 83-333, Laws of Florida (1983), appropriated an additional $500,000 for the construction of the gymnasium. This appropriation became effective on July 1, 1983. After its receipt of Sanmar's bid protest Respondent provided in a letter dated June 3, 1983 the figures on which the Respondent based its decision to reject all bids including Sanmar's. These figures follow: Architects fee including additional services $ 379,240.00 **Architects construction observation (included in architects estimate as part of the fee and contingencies) $ 90,000.00 Sanmar Base Bid $5,998,000.00 Equipment $ 200,000.00 Contingency (3 percent of construction cost) $ 179,940.00 Based on Sanmar's bid $6,847,420.00 Artwork $ 28,240.00 $6,875,420.00 **Estimated based on 18-month construction time. Petitioner has taken issue with the 3 percent contingency amount included in the above figures, however, the evidence shows that 3 percent is a reasonable amount based upon the State University System's experience with previous construction and is a fair estimate to insure that projects once begun can be adequately funded by the amount appropriated for their construction.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Board of Regents enter a Final Order rejecting all bids for the construction of a teaching gymnasium at the Tamiami Campus of the Florida International University. DONE and RECOMMENDED this 15th day of December, 1983, in Tallahassee, Florida. MICHAEL PEARCE DODSON Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of December, 1983.

Florida Laws (4) 120.53120.56120.57255.043
# 7
NATIONAL CLEANING OF FLORIDA, INC. vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 92-004311BID (1992)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 15, 1992 Number: 92-004311BID Latest Update: Sep. 14, 1992

The Issue Whether Respondent properly rejected Petitioner's bid on the grounds that the bid did not meet a fatal item requirement.

Findings Of Fact On April 24, 1992, Respondent published a Request for Proposals (RFP) for the provision of housekeeping services to South Florida State Hospital. Attached to the RFP as Appendix I was a blank copy of Respondent's "Standard Contract" which is also referred to as its "core model contract". Paragraph 1.a. of Section D of the RFP contains the following instructions to bidders: BIDDER RESPONSE a. State of Florida Request for Proposal Contractual Services Acknowledgment Form, Pur 7033 The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, Appendix II must be signed and returned ... with the proposal or submitted by itself if you choose not to submit a proposal and wish to remain on the department's active vendor list. Paragraph 1.g. of Section D of the RFP, contains the following instructions to bidders: Required Bidders Certification Contract Terms and Conditions The proposal must include a signed statement in response to the RFP indicating acceptance of the terms and conditions of provisions of service as specified in the RFP and contained in the core model contract. Bidders were provided a copy of the RFP rating sheet which contained the following under the heading of Fatal Items: The following criteria must be met in order for the proposal to be considered for evaluation, failure to receive a "Yes" response for any time [item] will result in automatic rejection of the proposal. * * * Does the proposal include a statement agreeing to terms and conditions set forth in the core model contract and the RFP? Petitioner was represented at a "Bidders' Conference" held May 15, 1992, at which the fatal items were discussed. Bidders were advised that it would be necessary for the responses to contain a statement agreeing to the terms and conditions set forth in the core model contract. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, contains the following certification: I certify that this proposal is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same contractual services, and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. In submitting a proposal to an agency for the State of Florida, the proposer offers and agrees that if the proposal is accepted, the proposer will convey, sell, assign or transfer to the State of Florida all rights, title and interest in and to all causes of action it may now or hereafter acquire under the Anti-trust laws of the United States and the State of Florida for price fixing relating to the particular commodities or services purchased or acquired by the State of Florida. At the State's discretion, such assignment shall be made and become effective at the time the purchasing agency tenders final payment to the proposer. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was signed by Richard A. Cosby on behalf of Petitioner and submitted as part of Petitioner's response to the RFP. Upon receipt of all responses, Respondent convened an evaluation committee to evaluate the responses. The evaluation committee determined that the response submitted by Petitioner did not contain the required statement agreeing to the terms and conditions set forth in the core model contract and the RFP. Consequently, the evaluation committee rejected Petitioner's proposal from further consideration. Petitioner does not challenge the specifications of the RFP, but, instead, asserts that Mr. Cosby's execution of the State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was sufficient to meet the requirement the evaluation committee found lacking. The language of the Contractual Services Acknowledgment Form, PUR 7033, that most closely approximates the certification that the bidder accepts the terms and conditions set forth in the core model contract and of the RFP is as follows: I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. The proposal submitted by Petitioner did not contain any other statement which could be construed as accepting the terms and conditions set forth in the core model contract and the RFP. The broad language of the Contractual Services Acknowledgment Form, PUR 7033, upon which Petitioner relies does not state that the bidder accepts the terms and conditions set forth in the core model contract and the RFP. The evaluation committee properly determined that Petitioner's response failed to meet this fatal item. In this proceeding, there was evidence that the Respondent routinely inserts in its Request for Proposals the fatal item requirement that the bidders agree in writing to accept the terms and conditions set forth in the core model contract and the RFP, and that Respondent has never waived that fatal item requirement. There was no evidence that Respondent was using this fatal item requirement to discriminate against or in favor of any bidder.

Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of August, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of August, 1992. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 92-4311BID The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioner. 1. The proposed findings of fact submitted by Petitioner are accepted in material part by the Recommended Order. Petitioner's conclusions based on those facts are rejected for the reasons discussed in the Recommended Order. The following rulings are made on the proposed findings of fact submitted on behalf of the Respondent. 1. The proposed findings of fact submitted by Respondent are adopted in material part by the Recommended Order. COPIES FURNISHED: Richard A. Cosby, Vice President National Cleaning of Florida, Inc. 1101 Holland Drive, #32 Boca Raton, Florida 33487 Colleen A. Donahue, Esquire District 10 Legal Office Room 513 201 West Broward Boulevard Fort Lauderdale, Florida 33301-1885 Sam Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Slye, General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700

Florida Laws (3) 120.57287.012287.057
# 8
MIDDLESEX CORPORATION AND AFFILIATES, INC. vs DEPARTMENT OF TRANSPORTATION, 92-004858BID (1992)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 10, 1992 Number: 92-004858BID Latest Update: Jan. 12, 1993

The Issue The issue in this proceeding is whether Petitioner, The Middlesex Corporation and Affiliates (Middlesex) or Intevenor, J. B. Coxwell Contracting, Inc. (J. B. Coxwell), submitted the lowest and best responsive bid for State Project No. 55040-3521 let by the Florida Department of Transportation (FDOT).

Findings Of Fact The Florida Department of Transportation issued an invitation to bid (ITB) for a contract to construct road improvements on State Road 363 in Tallahassee, Leon County, Florida; Project No. 55040-3521. The ITB incorporated the plans and specifications for the proposed highway improvements. The specifications stated in pertinent part: Article 1-3. . . . for the purpose of award, after the proposals are opened and read, the correct summation of the products of the approximate quantities shown in the proposal, by the unit prices, will be considered the bid. . . . . Until the actual award of the contract, however, the right will be reserved to reject any or all proposals and to waive technical errors as may be deemed in the best interest of the State. . . . .(emphasis supplied) Article 2-6. A proposal will be subject to being considered irregular and may be rejected if it shows omissions, alterations of form, additions not called for, conditional or unauthorized alternate bids, or irregularities of any kind; also if the unit prices are obviously unbalanced, either in excess of or below the reasonable costs analysis values. In addition to the specifications, a part of the plans for the project required the successful bidder to perform substantial excavation work on the project site. The excavation work would more likely than not yield enough fill material to complete any fill or embankments required in the project. Therefore, the plans contemplated that the soils obtained from the excavation work would be used for the construction of an estimated 44,000 cubic yards of embankment in the project. In order to achieve this goal, page seven of the plans entitled "The Summary of Quantities" indicated that embankment was to be a "no-pay item". However, the bid proposal, the form which constitutes the actual bid of the contractor, contained a line item for a price quotation for embankment/fill, Item No. 120-6. By including such a line item in the bid proposal, bidders were required to submit some figure for this item or risk their bid being declared irregular under the specifications for this project. There was no timely objection filed by any bidder indicating that the bidder would be prejudiced by treatment of the embankment/fill item as a no-pay or as a pay item. Likewise, there was no timely challenge to the apparently conflicting plans and pay item sheet or that the conflicting plans and pay item sheet created a stiutaion which prohibited a bidder from submitting a responsive bid. Seven bids for the contract were submitted and opened on May 27, 1992. The three apparent lowest bids at the opening were: Anderson-Columbia at $4,251,147.89; J. B. Coxwell at $4,964,327.81; and Middlesex at $4,977,371.48. After the bids were opened, each bid was reviewed by FDOT's Technical Review Committee (TRC) to determine whether the bid was mathematically and materially unbalanced, contained all appropriate signatures, contained all appropriate documents and otherwise met the technical requirements of the ITB. In essence, the TRC reviews each bid to determine whether it is responsive to the bid proposal and, if not responsive whether the bid's lack of responsiveness is immaterial and waivable by FDOT. After its review of all the bids, the TRC then makes a recommendation to FDOT's Contract Awards Committee on whether a bid should be rejected for material nonresponsiveness to the ITB. In this case, the TRC recommended to the Contract Awards Committee that Anderson-Columbia's bid be rejected as nonresponsive to the ITB. On June 16, 1992, FDOT's Contract Awards Committee adopted the recommendation of the Technical Review Committee and declared Anderson-Columbia's bid nonresponsive. The awards committee also voted to award the bid to J. B. Coxwell as the second responsive low bidder and on July 6, 1992, FDOT posted a notice of intent to award the contract to J. B. Coxwell. In making the award, FDOT looked at the impact of the conflict between the plans and the bid proposal sheet. FDOT's practice is to add all the unit prices listed on the bid proposal sheet to determine the total amount of the bid. FDOT has never deleted an item from the unit price list to determine the amount of a bid. Following these policies and Consistent with Article 3-1 of the specifications, FDOT determined that a bidder's price quote for the enbankment/fill item would be included as a pay item in the total bid despite the plan's indication that embankment/fill would be a no-pay item and despite the fact that the embankment item probably will not be paid as long as the fill required is less than the excavation. However, at the time of bidding, no bidder could be certain that FDOT would choose to pay or not pay item 120-6. In this case, a review of the bids demonstrates that bidders were not uniform in their application of the conflict between the plans and bid proposal sheet in developing their specific bids. Some bidder's, like J. B. Coxwell, bid very low prices for the embankment/fill in their bid. Some bidder's, like Middlesex, bid prices for the embankment/fill item closer to the average unit price for embankment/fill. In any event, no bidder received any advantage over another bidder due to the conflicting designation of the embankment/fill item and no bidder was favored or discriminated against because of the conflict. In short, all bidders received the same plans and bid proposal, reacted to them in the normal course of their businesses and prepared their bids according to those dictates. The evidence did not demonstrate that the conflict between the plans and bid proposal sheet or FDOT's handling of the conflict was so unfair or confusing that the conflict completely impeded or subverted the purpose or fairness of the competitive bidding process. J. B. Coxwell. Finally, as indicated, the TRC reviews bids to determine whether they are materially unbalanced. In general, unbalanced bids are discouraged by the Department because an unbalanced bid has the potential to allow the contractor to recoup or receive a larger portion of the contract price at the beginning of the contract term thereby making it less disadvantageous for the contractor to walk away from the contract and making agency control over the contractor more difficult. However, not all unbalanced bids will be rejected by FDOT because mathematically unbalanced bids often will have no material impact on the order of the bidders or the interests of the state in the timely and orderly performance of a given road project. Additionally, because of the nature of a given project, there may be a very good reason for a contractor to submit a mathematicallly unbalanced bid. In fact, approximately 80% of all the bids submitted to FDOT contain some form of mathematical unbalancing. Given these facts, FDOT will only reject an unbalanced bid if the unbalancing is material to the project and its award. In evaluating unbalanced bids, FDOT follows the guidance in a May, 1988, memorandum from the Federal Highway Administration (FHWA), which addresses bid analysis and unbalanced bids. The memorandum provides that where unit prices for items bid are either unusually high or low in relation to the engineer's estimate of the price (or mathematically unbalanced), the accuracy of the estimated quantities of the items are to be checked. If the quantities are reasonably accurate, the bid is to be further evaluated to determine whether the mathematical imbalance is "materially unbalanced" such that there is "reasonable doubt that award to the bidder submitting the mathematically unbalanced bid will result in the lowest ultimate cost to the Government." The analysis of a mathematically unbalanced bid to determine if it is materially unbalanced considers the effect of the unbalanced bid on the total contract amount; the increase, if any, in the contract cost when quantities are corrected; whether the low bidder will remain as the low bidder; and whether the unbalanced bid would have a potential detrimental effect upon the competitive process or cause contract administration problems later. In this case, FDOT compared the unit prices (line item prices) by each bidder on the bid proposal sheet to the average unit price for that item. The average unit price is based upon an average of the bidders' unit prices bid for a given pay item and the Department's estimated unit price for that item. If an individual bidder's unit price is significantly greater or less than the average price, FDOT's computer flags the item as mathematically unbalanced. Such a bid then receives further evaluation by FDOT to ensure the accuracy of the original estimates of the quantities of those items for which an unbalanced unit price has been submitted. FDOT also reviews the project plans for accuracy. The more in-depth review is performed to determine if there is a potential for a cost overrun or if there is an error in FDOT's estimated quantities which would result in an increased cost to the State for the project. In this case, J. B. Coxwell and Middlesex submitted bid proposals for each of the individual line item prices contained on FDOT's form. J. B. Coxwell's unit price for the embankment/fill item was $.10 per cubic yard of fill. FDOT's average price for the embankment/fill item was $3.20. The Middlesex quotation for embankment/fill was $2.25 per cubic yard of fill. FDOT's computer analysis of J. B. Coxwell's bid flagged the embankment/fill item as mathematically unbalanced. The quote by Middlesex for the embankment/fill item was not unbalanced and therefore was not flagged for furhter review by FDOT. However, the Middlesex bid was flagged as unbalanced for other line item quotations contained in its bid proposal. FDOT then made a more in-depth review of the bid of J. B. Coxwell and determined that although the bid was mathematically unbalanced, it was not materially unbalanced and did not result in a change in the bidding order. This determination was primarily based on the fact that the excavation portion of the project would yield enough fill to perform the embankment portion of the contract. Thus, a lower than average price in that item was not detrimental to the state, but, in fact, was in its best interest since a quote closer to FDOT's average would cause the state to be double billed for the fill FDOT's site would supply. There is no question that this was a reasonable analysis of the project in this case. Similarly, FDOT, utilizing the same analysis for unbalanced bids, also determined that the mathematically unbalanced unit prices submitted in the Middlesex bid were not materially unbalanced. Given the fact that Middlesex also had a mathematically unbalanced bid, which received the same analysis, Petitioner's argument that Coxwell's mathematically unbalanced bid should be rejected for such imbalance is rejected. Therefore, Middlesex has failed to demonstrate that it submitted the best responsive bid for State Project No. 55040-3521 and its protest should be dismissed.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered awarding the bid to J. B. Coxwell and dismissing Petitioner's protest. DONE AND ENTERED this 8th day of December, 1992, in Tallahassee, Leon County, Florida. DIANNE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings thes 8th day of December, 1992

Florida Laws (3) 120.53120.57337.11
# 9
BROOKS BUILDERS, INC. vs DEPARTMENT OF TRANSPORTATION, 97-001502BID (1997)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Mar. 26, 1997 Number: 97-001502BID Latest Update: Jul. 15, 1997

The Issue The issue presented is whether Petitioner Brooks Brothers, Inc., should be awarded the contract to renovate the Snapper Creek Service Plaza.

Findings Of Fact This is a bid protest arising out of an invitation to bid (hereinafter “ITB”) for state contract number 97870-3363, a construction project for renovation of the Snapper Creek Service Plaza on Florida’s Turnpike (the “contract” or “project”). The ITB included requirements relating to participation on the project by minority business enterprises (hereinafter “MBEs”). The ITB established a goal of 21% MBE participation. The 21% only could be met by utilizing MBE firms certified by the state Minority Business Advocacy and Assistance Office. According to the ITB, if the apparent low bid did not reflect that 21% of the work would be performed by certified MBE firms, the apparent low bidder would be required to submit documentation within 2 days establishing that a good faith effort had been made to meet the goal. If the low bidder could not demonstrate that it had made a good faith effort to meet the goal, the bid would be considered non-responsive and the Department would evaluate the next lowest bid for responsiveness. The process would be repeated until a responsive bid was found. Section B-27 of Exhibit 20 to the ITB specifically required the MBE participation information to be submitted with the contractor's bid and further provided, in pertinent part, as follows: Good Faith Efforts In evaluating a contractor's good faith efforts, the Owner will consider the statutory requirements and documentation submitted to demonstrate implementation undertaken by the contractor. Contractors may utilize methods in addition to those set forth below to attempt to increase participation by MBE's [sic]. Documentation of other methods will be considered. . . .Whether the contractor attended any solicitation or prebid meetings that were scheduled by the agency to inform minority business enterprises of contracting and subcontracting opportunities. * * * . . .Whether the contractor advertised in general circulation, trade association, and/or minority-focus media concerning the subcontracting opportunities. * * * . . .Whether the contractor provided written notice to a reasonable number of specific minority business enterprises that their interest in the contract was being solicited in sufficient time to allow the minority business enterprises to participate effectively. * * * . . .Whether the contractor followed up initial solicitation of interest by contacting minority business enterprises or minority persons to determine with certainty whether the minority business enterprises or minority persons were interested. * * * . . .Whether the contractor selected portions of the work to be performed by minority business enterprises in order to increase the likelihood of meeting the minority business enterprises goals, including, where appropriate, breaking down contracts into economically feasible units to facilitate minority business enterprise participation. * * * . . .Whether the contractor provided interested minority business enterprises or minority persons with adequate information about the plans, specifications, and requirements of the contract or the availability of jobs. * * * . . .Whether the contractor negotiated in good faith with interested minority business enterprises or minority persons, not rejecting minority business enterprises or minority persons as unqualified without sound reasons based on a thorough investigation of their capabilities. * * * . . .Whether the contractor effectively used the services of available minority community organizations; minority contractors' groups; local, state, and federal minority business assistance offices; and other organizations that provide assistance in the recruitment and placement of minority business enterprises or minority persons. * * * Evaluation The Owner will examine apparent low bid proposal to calculate whether the contractor has met the project MBE goal by determining whether: The MBE's [sic] listed on the Utilization Summary are certified by the Bureau of Minority Business Assistance Office. The MBE's [sic] are certified to perform the trade or service specified. The percentage of the contract amount to be paid to qualifying MBE's [sic] meets or exceeds the project goal. The Owner will notify the apparent low bidder whether the project goal has been met. If the goal has not been met, the bidder must dispatch all documentation of its good faith not later than two working days after notification effort [sic] for overnight delivery to the Owner. The documentation will be reviewed by the Evaluation Committee to determine whether a good faith effort has been made. If the apparent low bidder is determined not to have made a good faith effort, the Owner will repeat steps 1 and 2 with the next lowest bid. This process will be repeated until a responsive bid within budget is found. The bid documents included forms on which bidders were to identify any MBE firms intended to be used on the project. The title of the form is “MBE Utilization Summary.” Sixteen contractors submitted bids for the project. After bid opening, the Department reviewed the bids to determine responsiveness including compliance with the MBE requirements. Carivon Construction Company submitted the apparent low bid. On its MBE Utilization Summary, Carivon indicated it would use its own forces and one other MBE to meet the 21% goal. The Department determined that Carivon’s bid did not meet the 21% MBE goal because Carivon was not a certified MBE at the time of the bid. In accordance with the ITB, the Department informed Carivon that it had not met the goal and provided Carivon an opportunity to establish its good faith effort to do so. The Department determined that Carivon’s good faith effort was insufficient and rejected Carivon’s bid as non-responsive. The Department then reviewed the second low bid submitted by Spectrum Group Construction, Inc. Spectrum’s MBE Utilization Summary indicated that Spectrum would meet the goal by subcontracting some of the work to MBE firms and performing some of the work with its own forces. Spectrum was a certified MBE at the time its bid was submitted. The Department determined that Spectrum’s bid did not reflect that the goal was met because the other firms identified on Spectrum’s MBE Utilization Form were not certified. When the participation of those firms was excluded, Spectrum’s bid did not reflect that 21% of the work would be performed by MBE firms even though Spectrum was an MBE and had identified itself on the MBE Utilization Summary as one of the MBEs to work on the project. The Department therefore requested that Spectrum submit its good faith efforts documentation. Spectrum responded with information explaining that it would perform more than 21% of the work with its own forces, thereby performing more of the work itself than it had indicated on its MBE Utilization Summary. The Department determined that Spectrum had failed to demonstrate its good faith efforts and, in actuality, was amending its bid. It, therefore, rejected Spectrum’s bid as non- responsive. The Department then reviewed the third low bid submitted by Pino. Pino had submitted an MBE Utilization Summary indicating that 21% of the work would be subcontracted to MBE firms. Pino also was a certified MBE at the time of the bid. However, unlike Carivon and Spectrum, Pino’s MBE Utilization Summary did not include itself and did not indicate that it intended to meet the goal by using its own forces. Pino’s certification is not apparent from the face of the bid. The Department determined that the bid did not on its face meet the MBE goal because one of the minority firms Pino identified on its MBE Utilization Summary was not certified. Without that firm, Pino’s bid reflected only 11.8% MBE participation. The Department therefore sent Pino a letter advising that Pino's MBE participation totaled only 11.8% and requesting that Pino submit documentation of its good faith efforts to meet the 21% goal. The request for good faith efforts documentation specifically stated that it was made in accordance with Section B-27, C of Exhibit 20. Pino’s response to the Department's request did not attempt to document its good faith efforts to meet the goal in accordance with Section B-27, C of Exhibit 20 of the ITB. Rather, like Spectrum, Pino submitted information explaining that it was a certified MBE and would perform more than 25% of the work with its own forces. Unlike its treatment of Spectrum, the Department accepted Pino’s explanation and posted a notice of intent to award the contract to Pino. In doing so, the Department did not consider the fact that Pino's bid did not reflect that it was a certified MBE or that it intended to count its participation toward the MBE requirement. Rather, Pino's bid certified on its signed MBE Utilization Summary that it was relying on certain named subcontractors to meet the MBE requirement. Brooks submitted the fourth lowest bid. Brooks’ bid also included an MBE Utilization Summary indicating that at least 21% of the work would be performed by MBE firms. One of the MBE firms identified in Brooks’ bid was not certified. During the deposition of Brooks M. Muse, II, taken the afternoon before the final hearing in this cause and admitted in evidence at the final hearing as one of the Department's exhibits, the Department reviewed Brooks’ good faith efforts documentation. Documentation was produced as to the elements contained in the bid specifications for performing good faith efforts. The Department's representative who attended the deposition announced on the record in the deposition that she was satisfied with Brooks' documentation, and the Department's attorney who was taking the deposition announced on the record in the deposition that Brook's documentation was more thorough than she had ever seen. Brooks' representative attended the pre-bid conference. Brooks' advertised for MBEs in the Miami Herald. Brooks contacted the Hispanic Builders Association, the Black Builders Association, and Women in Construction. Brooks faxed to minority businesses and persons a solicitation letter and a follow-up letter. Brooks met with interested MBEs, gave them copies of the bid specifications, and offered them assistance. Brooks' representative contacted the Minority Business Advocacy and Assistance Office for information as to additional certified MBEs. Brooks documented these many contacts. Brooks made a good faith effort to meet the MBE goal in accordance with the specifications in the ITB. The ITB also included the following provisions regarding subcontractor participation on the project. EXHIBIT 5. LIST OF SUBCONTRACTORS FORM - Architect-Engineer shall insert only major types of subcontractors applicable to this job and removing all unused blanks. * * * LISTING OF SUBCONTRACTORS In order that the Owner may be assured that only qualified and competent subcontractors will be employed on the project, each Bidder shall submit with the proposal a list of the subcontractors who will perform the work for each Division of the Specifications utilizing the 'List of Subcontractors' form enclosed as Exhibit 5. [Emphasis added.] * * * SUBCONTRACTOR DATA Within 2 working days after bid opening, the apparent low bidder shall submit to the Owner's Project Director the following for each subcontractor. Corporate Charter Number. (If applicable). License Number. Name of record license holder. Complete name, address and phone number for listed subcontractors. * * * 2. The Contractor shall provide a certified list of all subcontractors, laborers and material suppliers to the owner within thirty (30) calendar days of his receiving his notice to proceed with the work. [Emphasis added.] The List of Subcontractors form referenced in section B-14 contained five numbered spaces for identifying the type of work to be performed and the name of the subcontractor. The directions on the form state: “The undersigned, hereinafter called 'bidder’, lists below the name of each subcontractor who will perform the phases of the work indicated. [Emphasis added.] Nevertheless, the List of Subcontractors form does not indicate any "phases of work." Further, the List of Subcontractors form does not provide that all subcontractors the bidder intends to use must be listed. Moreover, section B-15 of the ITB established that the apparent low bidder would be required to submit a complete list of all subcontractors within 2 days of notification by the Department. Certain portions of the work to be performed are considered “specialty work” which requires a specialty license. Unless the bidder possessed the specialty license, it would have to subcontract that work. Brooks' president and sole stockholder has been bidding for public contracts for over 30 years. He understands that in submitting competitive bids, bidders may not alter or amend the bid form or the bid will be considered non-responsive. Further, the ITB for this project specified in section B-13 that any proposal containing any alteration might be rejected. He determined, therefore, that he could not amend the List of Subcontractors form by adding an attachment. Based upon his experience, the language of the form, and the existence in the ITB of specifications providing for the subsequent submittal of subcontractor information to the Department, Brooks listed five subcontractors on the List of Subcontractors form although Brooks intends to utilize additional subcontractors, specifically certain specialty subcontractors. Brooks identified several subcontractors on the List of Subcontractors form that would perform various portions of the division of the work identified in the ITB as “mechanical.” Brooks also identified a subcontractor that would perform fencing and a subcontractor that would perform concrete and masonry work. Fencing is included in one of the divisions of the work. Concrete and masonry is identified as a division of work under two separate sections. The List of Subcontractors form did not specify the categories of work for which subcontractors were to be identified. The ITB did indicate that only major types of subcontractors would be required to be identified. Brooks’ understanding of the requirements for identifying subcontractors was consistent with the totality of the provisions contained in the ITB. Like Brooks, Pino did not list all the subcontractors it would utilize on the project. Specifically, Pino did not identify certain specialty subcontractors which it would require in order to perform the specialty work for which Pino does not have a specialty license. Pino only listed three of its subcontractors, leaving two lines blank. Pino did not submit a complete list of all subcontractors within 2 days of being notified that it was the apparent low bidder. By the time of the final hearing in this cause, Pino had still not identified all subcontractors. Brooks has not yet submitted to the Department a complete written list of all subcontractors. However, Brooks has not yet been notified that it is the apparent low bidder.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED THAT the Department enter a final order rejecting Pino’s bid as non-responsive and awarding the contract to Brooks if the Department is able to negotiate with Brooks a price for the project which is within the Department's budget. If the Department is unable to negotiate a price within budget, then the Department should enter a final order rejecting all bids. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 10th day of June, 1997. LINDA M. RIGOT Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of June, 1997. COPIES FURNISHED: Mary M. Piccard, Esquire Vezina, Lawrence & Piscitelli, P.A. 318 North Calhoun Street Tallahassee, Florida 32301 Mary S. Miller, Esquire Department of Transportation Haydon Burns Building, M.S. 58 605 Suwannee Street Tallahassee, Florida 32399-0458 John A. Barley, Esquire 400 North Meridian Post Office Box 10166 Tallahassee, Florida 32301 Ben G. Watts, Secretary Department of Transportation c/o Diedre Grubbs Haydon Burns Building, M.S. 58 605 Suwannee Street Tallahassee, Florida 32399-0458 Pamela Leslie, General Counsel Department of Transportation Haydon Burns Building, M.S. 58 605 Suwannee Street Tallahassee, Florida 32399-0458

Florida Laws (1) 120.57