Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
THOMAS EDWARD DALTON vs STATE OF FLORIDA BUILDING CODE ADMINISTRATORS AND INSPECTORS BOARD, 14-004188 (2014)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Sep. 10, 2014 Number: 14-004188 Latest Update: Mar. 09, 2015

The Issue The issue in the case is whether the application filed by Thomas Edwards Dalton (Petitioner) to take the examination for certification as a plumbing plans examiner should be approved.

Findings Of Fact The Petitioner is seeking to become a state-certified plumbing plans examiner. The Respondent is the state agency charged with responsibility for certification of plumbing plans inspectors. On December 12, 2013, the Petitioner submitted to the Respondent his application to take the examination for the certification sought. As required by rule, the Petitioner also submitted an “Affidavit of Work Experience” setting forth a statement of work experience presumably relevant to his application. The affidavit form requires that it be “completed by an architect, engineer, contractor or building code administrator, who has personal knowledge of the application’s experience” for the relevant period. The Petitioner wrote the narrative of his experience contained within the affidavit dated December 8, 2013. The affidavit was signed by a person identified as Anthony Applebeck, a building code administrator in Altamonte Springs, Florida. Generally, an “Application Review Committee” (ARC) comprised of three building code enforcement specialists reviews applications and affidavits submitted to the Respondent. In this case, two members of the ARC independently reviewed the Petitioner’s submission and determined that additional information related to the Petitioner’s work experience was required. In an email dated December 17, 2013, the Respondent advised the Petitioner that additional information was required. The letter stated as follows: The Affidavit of Work Experience that was submitted with your application is missing detailed hands-on plumbing experience. Please complete the enclosed Affidavit of Work Experience and submit it to the department. The person completing the work affidavit should be specific when explaining your duties and actual hands-on experience. The ARC’s determination that the Petitioner’s Affidavit of Work Experience was insufficient was correct. The affidavit lacked a detailed explanation of the Petitioner’s work experience, specifically as to “hands-on” plumbing involvement. The Petitioner failed to submit the supplemental work experience affidavit requested by the Respondent. In an email dated December 18, 2013, the Petitioner requested that the ARC reconsider his original submitted affidavit. On February 18, 2014, the Respondent issued a Notice of Intent to Deny the Petitioner’s application based on the failure to submit sufficient information to establish that the Petitioner has the experience required for the certification sought. By letter dated February 28, 2014, the Petitioner challenged the proposed denial of his application and requested an administrative hearing. The evidence presented at the hearing by the Petitioner was insufficient to establish that the Petitioner meets the requirements to take the examination for certification as a plumbing plans examiner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Petitioner's application to take the examination for certification as a plumbing plans examiner be denied. DONE AND ENTERED this 16th day of December, 2014, in Tallahassee, Leon County, Florida. S WILLIAM F. QUATTLEBAUM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 16th day of December, 2014. COPIES FURNISHED: Thomas Edward Dalton 906 Delta Court Altamonte Springs, Florida 32714 (eServed) Robert Antonie Milne, Esquire Office of The Attorney General Plaza Level 01, The Capitol Tallahassee, Florida 32399-1050 (eServed) J. Layne Smith, General Counsel Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399 (eServed) Robin Barineau, Executive Director Division of Professions Building Code Administrators and Inspectors Board Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399 (eServed)

Florida Laws (5) 120.569120.57468.606468.609633.216
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANNY E. FOX, 82-000094 (1982)
Division of Administrative Hearings, Florida Number: 82-000094 Latest Update: Jan. 26, 1984

Findings Of Fact At all times material to this action, Respondent was and presently is a registered plumbing contractor having been issued License No. RF0038438. On August 18, 1981, the Collier County Contractor's Licensing Board revoked Respondent's competency card to practice plumbing in Collier County. The revocation was based upon Respondent's violation of Sections 4.1.10 and 4.1.17, Collier County Ordinance No. 78-02. Respondent failed to appear at the public hearing held before the Collier County Contractor's Licensing Board on August 18, 1981.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's license as a registered plumbing contractor be revoked. DONE and ENTERED this 9th day of August, 1983, in Tallahassee, Florida. MARVIN E. CHAVIS Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of August, 1983. COPIES FURNISHED: Xavier J. Fernandez, Esquire Nuckolls, Johnson & Fernandez Post Office Box 729 Fort Myers, Florida 33902 Danny E. Fox Route 1, Box 54 Pleasant Shade, TN 37145 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (2) 489.117489.129
# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs JERRY ANDERSON, D/B/A MR. FIXIT, 97-002105 (1997)
Division of Administrative Hearings, Florida Filed:Panama City, Florida May 05, 1997 Number: 97-002105 Latest Update: Jan. 27, 1999

The Issue The issues to be resolved in this proceeding concern whether the Respondent violated Section 489.127(1)(f), Florida Statutes, by contracting without a license.

Findings Of Fact The Petitioner is an agency of the State of Florida charged with regulating entry into and the practice of contracting. It is also charged with discipline of licensed contractors who violate the various provisions of Chapter 489, Florida Statutes and the related rules, as well as those who practice contracting without appropriate licensure or certification. The Respondent, by his own admission and by stipulation, was not registered, certified, or otherwise licensed by the State of Florida for engaging in the practice of contracting, at pertinent times. On or about February 21, 1996, at her request, the Respondent provided Betty Thompson with a proposal to remodel and complete a new addition to her home at 110 Granger Street, Panama City Beach, Florida. The agreed-upon contract price was $26,685.00. Ms. Thompson signed the proposal, which contemplated construction of an addition in the amount of 593 square feet, at a price of $45.00 per square foot or $26,685.00. The price included all concrete, plumbing, and electrical work and installation. The terms of the contract stated that the price included the materials and the labor involved. The Respondent also obtained plans for the addition on Ms. Thompson's behalf. The plans depict the Respondent's name thereon as the contractor for the project. The Respondent then instructed Ms. Thompson to obtain the necessary building permit, which she did. The Respondent obtained several laborers to perform work on the project, including Eddie George, his son Shannon George, and Tim Polston. He introduced them to Ms. Thompson as the men who would perform most of the labor on the addition to her home. He hired these men as laborers and not Ms. Thompson. Later when he abandoned the job she hired them, or at least some of them, to finish the job. Eddie and Shannon George performed the majority of the actual labor on the project under the Respondent's supervision. Mr. Polston performed the electrical work. According to Mr. George's testimony they were supervised by the Respondent just as they would be by any contractor. They were paid by the Respondent by the hour. The Respondent stopped at the job site frequently and discussed the job's progress with Ms. Thompson. She addressed any questions and concerns to the Respondent, who conveyed any necessary information to his foreman, Eddie George. The Respondent also performed some construction work himself. The Respondent helped tear out a back wall of the house, set two (2) doors, did some painting, and did some air conditioning work on the project. He also checked the job site each day, and checked to see what materials were needed, and bought and delivered the needed materials. The Respondent received intermittent payments from Ms. Thompson, which he used to pay for the materials he purchased for the project. He also used a portion of those payments to pay his laborers. On or about May 6, 1996, the Respondent abandoned the job. This occurred shortly after he first met with Ms. Thompson's father who was paying for the job. Apparently there were some disagreement or issue raised between them and the Respondent never appeared at the job site again. After the Respondent abandoned the project, Ms. Thompson was unable to get another contractor to complete the job. She thereupon employed the laborers who had already worked on the job, the Georges and Tim Polston, to continue working there, which they agreed to do. It was only after the Respondent abandoned the job that Ms. Thompson paid the laborers directly herself. The addition that the Respondent contracted to construct has numerous construction flaws, including, but not limited to, malfunctioning air conditioning in the addition, improperly installed flooring, gaps between the old and new roofs and the old and new exterior concrete block work, as well as a leaking roof. These problems arose during the construction which occurred under the Respondent's supervision.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED: That a Final Order be entered by the Florida Construction Industry Licensing Board, finding that the Respondent violated Section 489.127(1)(f), Florida Statutes, by contracting without proper licensure or certification, and imposing a fine of $5,000.00. DONE AND ENTERED this 1st day of April, 1998, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 1st day of April, 1998. COPIES FURNISHED: John O. Williams, Esquire Boyd, Lindsey, Williams, and Branch, P.A. 1407 Piedmont Drive, East Tallahassee, Florida 32317 Sher L. Allan, Esquire 731 Oak Avenue Panama City, Florida 32402 Rodney Hurst, Executive Director Construction Industry Licensing 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Linda L. Goodgame, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-1007

Florida Laws (6) 120.5720.165455.228489.103489.105489.127
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PHILIP J. MAINS, 80-002231 (1980)
Division of Administrative Hearings, Florida Number: 80-002231 Latest Update: Jul. 08, 1981

Findings Of Fact In early September of 1979, John and Ruth E. Lockwood contracted with P & P Custom Pools, Inc. (P & P), for the construction of a swimming pool at their home, 231 El Dorado Drive, Debary, Florida. Respondent, Philip J. Mains, signed the contract on behalf of P & P and later obtained a building permit. He and his men began excavating on site in mid-September. The Lockwoods paid respondent $700.00 on September 6, 1979. As construction progressed, they paid him $1,706.25 on September 27, 1979; $1,000.00 on October 26, 1979; $1,047.50 on October 29, 1979; and $1,706.25 on November 20, 1979. At the appropriate times, a building inspector was summoned, who inspected the project, including the placement of reinforcing steel, ground wiring, and lights. Neither the "steel inspection" nor the "deck inspection" revealed any problem. The workmanship was excellent, as far as it went, but the Volusia County building inspector's office was never asked to perform a final inspection. As respondent promised there would be, there was water in the swimming pool by Christmas of 1979, but respondent did no further work after December, 1979. He never installed the pump, filter, diving board, or hand bars called for in the Lockwoods' contract. Earlier in 1979, Patrick T. Ryan, the other principal in P & P, left town and abandoned the business which was then $37,000 in debt. In November of 1979, respondent turned the company's books over to an accountant. In January of 1980 the business' financial problems became critical and, at the accountant's suggestion, respondent so advised the eight homeowners for whom he was building swimming pools, including, in January or February, Mr. Lockwood, who reacted angrily. Respondent testified that Mr. Lockwood "cussed him out." Thereafter respondent avoided the Lockwoods until April of 1980 when they found him working on another pool. There was enough money owed on the eight contracts as a group to finish all the pools, according to respondent's uncontroverted testimony, at the time the Internal Revenue Service levied on respondent's bank account and seized his tools and equipment. Even then respondent offered to finish the Lockwoods' pool if they would buy the materials. Respondent's wife asked Mrs. Lockwood to write a check to a supplier for a pump and filter so that respondent could install them and get water in the pool circulating. Instead, during the last week of April, 1980, the Lockwoods contracted with somebody else to finish the job and paid him $1,200. Respondent subcontracted with a Jacksonville cement company to pour concrete for the pool. After the concrete had been poured, the Lockwoods got a registered letter from the subcontractor threatening to place a lien on their property if he were not paid. According to Mr. Lockwood, the problem was that some check [supposedly drawn by respondent in favor of the subcontractor] had been delayed in the mail. In any event, there was no indication in the evidence that the Lockwoods heard anything further from the subcontractor.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's registration for thirty (30) days. DONE AND ENTERED this 29th day of April, 1981, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1981. COPIES FURNISHED: Charles F. Tunnicliff, Esquire 130 North Monroe Street Tallahassee, Florida 32301 Philip J. Mains c/o Sue Mains Route 2, Box 799A DeLand, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, vs. CASE NO. 80-2231 PHILIP J. MAINS, RP 0024663, Respondent. /

Florida Laws (1) 489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILLIAM R. MACKINNON, 76-000026 (1976)
Division of Administrative Hearings, Florida Number: 76-000026 Latest Update: Sep. 28, 1976

The Issue Whether Respondent's License as a residential pool contractor should be suspended for alleged violation of Section 468.112(7), Florida Statutes. The Respondent did not appear at the hearing although proper notice thereof had been furnished under date of February 11, 1976 to him by the hearing officer. Accordingly, the hearing was conducted as an uncontested proceeding.

Findings Of Fact Respondent has been licensed as a registered pool contractor by the Florida Construction Industry Licensing Board since June 20, 1974. The license was not renewed for 1975/76 (Exhibit 4). Respondent filed a Voluntary Petition in Bankruptcy in the U.S. District Court for the Northern District of Florida, Bankruptcy No. TBK 75-25, on March 13, 1975 (Exhibit 5).

Recommendation That the registration of William R. MacKinnon as a residential pool contractor be suspended until such time as he meets the qualifications and other requirements for renewal of registration and applies therefor. DONE and ENTERED this 5th day of April, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of April, 1976. COPIES FURNISHED: David Linn, Esquire 217 South Adams Street Tallahassee, Florida 32301 Mr. William R. Mackinnon Route 3, Box 584C Tallahassee, Florida 32303

# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL LOZEAU, 87-000445 (1987)
Division of Administrative Hearings, Florida Number: 87-000445 Latest Update: Sep. 17, 1987

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times material hereto, Respondent was a certified pool contractor, holding license no. CP-C033753, issued by the State of Florida, Department of Professional Regulation, Construction Industry Licensing Board. At all times material hereto, Respondent's certified pool contractor's license qualified Artistic Pools and Spas, Inc. with the Florida Construction Industry Licensing Board. On or about May 19, 1986, Respondent, d/b/a Artistic Pools and Spas, Inc. entered into a contract with Joseph and Joyce Malinoski for the construction of a swimming pool at 31 Sea Harbour Drive, Ormond Beach, Florida for a contract price of $9,737.75. The contract required a down payment of ten per cent (10 percent) of the contract amount ($973.78) which was paid by the Malinoskis on May 19, 1986. The Malinoskis resided in Massachusetts at the time they contracted for the swimming pool with Respondent and had contracted for the construction of a home in Ormond Beach, Florida to begin upon the pool shell being in place. The Malinsokis returned to Massachusetts upon execution of the contract expecting Respondent to commence work on the pool two weeks after he was notified by the builder that the survey was completed and the benchmark in place. On or before June 18, 1986, Respondent contacted the Malinoskis by phone to advise them that the pool was under construction, that Respondent was ready to start pouring concrete, and that he needed the next two (2) installments (20 percent due on day of excavation and 35 percent due on day of concrete shell installation) in the amount of $5,355.76. On or about June 18, 1986, the Malinoskis forwarded a cashier's check in the amount of $5,355.76 made payable to Respondent with the understanding from Respondent that the pool was under construction. On or about June 25, 1986, the Malinoskis were advised by their building contractor that the pool was not under construction. On or about July 5, 1986, the Malinoskis returned to Ormond Beach and found that the pool was not under construction. Although the business phone at Artistic Pools and Spas, Inc. had been disconnected, the Malinoskis ultimately located the Respondent but were unable to resolve the problem until after a complaint had been filed. In early August, 1986, an agreement was reached with the Malinoskis, Respondent and David Larsen whereby Respondent would furnish the labor to build the pool, Larsen would pay the bills and the Malinoskis would pay the balance owed on the contract to Larsen and at end of construction Larsen would give the Malinoskis release of liens. The pool was constructed without the Malinoskis having to pay any additional money on the contract. The money used by Larsen to purchase materials above the amount paid to Larsen by the Malinoskis was repaid to Larsen by Respondent. Respondent supplied all the labor to construct the pool. The testimony of Respondent, which I find credible, was that the funds received by Respondent were frozen due to an Internal Revenue Service levy on the Respondent's business account which resulted in the IRS taking all the funds in the bank account, including the money from the Malinoskis. There was insufficient evidence to show that Respondent diverted the Malinoskis' funds or that the Respondent was unable to fulfill the terms of the contract. On or about November 15, 1985 Respondent, d/b/a Artistic Pools and Spas, Inc. contracted with John and Louise McGowan for the construction of a swimming pool and spa at 1266 Robbin Drive, Port Orange, Florida for an original contract price of $11,500. These were 2 addendums to the original contract bringing the total contract price to $13,005.75. The contract provided for the spa to be 7 feet long by 5 feet wide with a depth ranging from 18 inches to 36 inches. As constructed, the spa was 5 feet long by 5 feet wide with a depth of 44 inches. The spa was also unlevel resulting in water spilling on to the deck rather than into the spillway to the pool. The therapy jets were located too deep in the spa to allow them to function properly. The spa has never been operational. Respondent was aware of the deficiencies in the construction of the spa but failed to correct them. The deck around the pool was not properly finished in that it is uneven and rough in several locations and is pitched toward the pool rather than away from the pool. The deck also has several facial cracks (not structural) which indicate a nonuniform thickness. As contracted, the pool was to have 3 return fittings of which only 2 were installed. The contract called for the installation of a heater by the Respondent. Although the heater was installed, it was improperly placed resulting in the inspector putting a "red tag" on the heater and having the gas company disconnect it. The McGowans have paid all but $575 of the contract price but refuse to pay the balance until corrections are completed. Respondent was aware of the deficiencies in the construction of the pool but failed to correct them. The evidence is clear that Respondent failed to properly supervise the construction of the McGowans' pool and spa, thereby resulting in poor workmanship in the construction of the pool and spa.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED that the Florida Construction Industry Licensing Board (Board) enter a final order finding Respondent guilty of violating Section 489.129(1)(j) and (m), Florida Statutes and for such violation it is Recommended that the Board assess the respondent with an administrative fine of $500.00 and suspend the Respondent's pool contracting license for a period of two (2) years, stay the suspension, and place Respondent on probation for a period of two (2) years, provided the Respondent pays the administrative fine of $500.00 within sixty days of the date of the Final Order. It is further Recommended that the charges of violating Section 489.129(1)(h) and (k), Florida Statutes be DISMISSED. Respectfully submitted and entered this 17th day of September, 1987, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of September, 1987.

Florida Laws (3) 120.57489.105489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STANLEY MONDS, 88-002551 (1988)
Division of Administrative Hearings, Florida Number: 88-002551 Latest Update: Jul. 18, 1989

The Issue Whether Respondent's registered plumbing contractor's license should be revoked, suspended or otherwise disciplined under the facts and circumstances of this case.

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times material to this proceeding, Respondent, Stanley Monds, held a registered plumbing contractor's license number RF 0037461 which had been placed on a delinquent status for non-renewal effective July 1, 1985 and was invalid during the 1987-89 licensing period. On June 19, 1987, Monds, doing business as Clay Well and Pump Service, contracted with Charles W. Plath to install a culvert for the sum of $341.25. The culvert was installed by Monds and Plath paid Monds in accordance with the contract. On July 10, 1987, Monds, doing business as Clay Well and Pump Service, contracted with Plath to: (a) install a 2- inch well and a 1-Horsepower Meyers pump; (b) supply fill for septic tank pad and a culvert; (c) install septic tank and culvert; (d) install a 200 amp electrical service for mobile home and pump and; (e) tie-in the water line and electricity to the mobile home and pump. The net contract price was $6,574.00 of which Plath paid $4,295.00 in advance, leaving a balance of $2,279.00. Plath's mobile home site is located in Whitehouse, Duval County, Florida. There was no written or verbal agreement between Plath and Monds concerning a completion date. However, Plath had told Monds that he needed to be in the mobile home by August, 1987. Plath understood that Monds had other jobs that he was currently working on but would get to Plath as soon as possible. Monds advised Plath that the necessary permits for the job would have to be applied for (pulled) by Plath. Plath did not object to this, and on June 19, 1987 applied for a mobile home move-on permit with the Duval County Building Department. The mobile home move-on permit was issued to Plath on July 6, 1987. An applicant for a mobile home move-on permit must show that a septic tank permit has been issued before a mobile home move-on permit will be issued. The septic tank permit is issued through the local health department. The Duval County Building Department requires the person who is issued the mobile home move-on permit to assume the responsibility for acquiring the necessary inspections, even though the work is being performed by someone other than the person to whom the permit was issued. It was Plath's responsibility to see that the necessary inspections were made, including the septic tank inspection. The well and pump were installed sometime around the last of July or the first of August, 1987. Monds subcontracted the drilling of the well. Although part of the work under the contract had been completed, such as the well and pump installation and part of the septic tank, Plath encountered difficulty in making contact with, and getting a response from, Monds concerning the progress of the job and a completion date. Therefore, in October, 1987 Plath decided to contract the work to someone else. On October 8, 1987, Plath contracted with Wilkins & Sons Electric (Wilkins) to install: (a) the 200 Amp mobile home service pole and connect to mobile home; (b) the 220 Volt, 20 Amp circuit and connect to pump and; (c) the 175 Watt mercury vapor light fixture. The total price of the contract was $850.00. However, $85.00 for a mercury vapor light fixture was not part of the original contract with Monds. Wilkins applied for and was issued the required electrical permit for the Plath job on October 6, 1987. The final electrical inspection was made on October 9, 1987. 13 On October 13, 1987, Plath contracted with AA Septic Tank Service, Inc. to finish the partially completed septic tank which Monds had failed to complete for $300.00. Although the septic tank permit was issued before the mobile home move-on permit was issued, there is no evidence that anyone made a septic tank inspection. Although Monds was hampered by the rain during the period of time Monds worked on the Plath site, there was insufficient evidence to show that Monds was prevented by the rain from completing the work under the contract before Plath decided to contract with someone else because of the delay or that Monds advised Plath of the reason for the delay. Plath did not prevent, or prohibit, Monds for completing the work under the contract. Monds failed to pay Tim Prep, Inc. for 15 loads of fill ordered and used by Monds on the Plath job. As a result of Monds failure to pay for the fill, Tim Prep, Inc. filed a Notice Of Intention To Claim A Lien in the amount $1,181.25 against Plath's property. Monds had not paid Tim Prep, Inc. for the fill at the time of the hearing. The work on the on the Plath job was completed in late October or early November, 1987. Monds was still working on the Plath job as late as September 1, 1987 when Tim Prep, Inc. delivered fill to the Plath site for Monds. Although Plath never paid Monds the $2,279.00 balance, Plath was required to pay other contractors $1,075.00 ($850.00 minus $85.00 plus $310.00) and will be required to pay $1,181.25 to Tim Prep, Inc. to remove the lien from his property which comes to a total of $2,256.25, leaving a balance of $22.75. This does not take into consideration any compensation for the delay suffered by Plath. Although probable cause was found against Monds by the Florida Construction Industry Licensing Board (Board) on January 7, 1988 and a letter of guidance issued in apparently another matter, there was no evidence concerning the violations or the charges involved.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses and Rule 21E- 17, Florida Administrative Code, it is, therefore, RECOMMENDED that the Board enter a Final Order finding Respondent, Stanley Monds guilty of violating Section 489.115(3)(a), Section 489.119(3), and Section 489.129(1)(j) and (m), Florida Statutes, and for such violation impose an administrative fine of $750.00. It is further RECOMMENDED that the charges alleged in the Administrative Complaint of violating Section 489.129(1)(d) and (k), Florida Statutes be DISMISSED. DONE AND ENTERED this 18th day of July, 1989, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of July, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-0464 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the Proposed Findings of Fact submitted by the Petitioner in this case. Specific Rulings on Proposed Findings of Fact Submitted by the Petitioner: Each of the following Proposed Findings of Fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the Proposed Finding of Fact: 1 & 2(1); 3(2- 5); 4 & 5(3); 6(6); 7(9); 8(10); 9(9); 10(11); 11(13); 12(18); 13(17); 14(6 & 12); 15(6 & 8); 16(12); 17(16); 18(2 & 3); 19(1). Specific Rulings on Proposed Findings of Fact Submitted by the Respondent: 1. Respondent did not submit and posthearing proposed findings of fact. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 Kenneth Easley, Esquire General Counsel Department of Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0750 Elizabeth R. Alsobrook, Esquire Department of Professional Regulation Northwood Centre 1940 N. Monroe St. Tallahassee, Florida 32399-0750 Stanley Monds 326 West Macclenny Avenue Macclenny, Florida 32063 =================================================================

Florida Laws (5) 120.57489.105489.115489.119489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MICHAEL ANGUELO, 84-003835 (1984)
Division of Administrative Hearings, Florida Number: 84-003835 Latest Update: Dec. 31, 1985

The Issue May Respondent's contracting license be revoked, suspended or otherwise disciplined? EVIDENCE AND PROCEDURE Petitioner presented the testimony of the following witnesses: Randall F. Patterson; Bob R. Pope; Roberta Ballenger; Joel A. Dean; and Victor F. Boucher. Petitioner's exhibits number one through fourteen were admitted into evidence. Respondent was not present, put on no evidence, and submitted no after- filed proposals. Petitioner filed the transcript of proceedings on October 17, 1985, and filed proposed findings of fact and conclusions of law styled "Petitioner's Proposed Recommended Order" on November 8, 1985. Although additional time for filing proposals was neither applied-for nor granted, these proposals have been considered, and are ruled on within the Appendix to this Recommended Order.

Findings Of Fact Respondent is, and at all times material to the Administrative Complaint, was a registered residential contractor in the State of Florida having been issued license number RR 0032683. On August 7, 1982 Respondent d/b/a Future Homes of America Construction Company, Inc. contracted with Victor Boucher for the construction of a single family residence at 822 Fairview Avenue, Altamonte Springs, Florida. Section 14.5 of the Fixed Price Construction Agreement provided: The owner will, as agreed to by the contractor, request the contractor to obtain payment and performance bonds, issued by a surety and in amounts acceptable to owner, guaranteeing the full performance of contractor's payment and performance obligations hereunder. (Pet. Exh. 1, Pet. Exh. 9). Article 14.5 of the construction contract required Respondent to obtain a payment and performance bond. Respondent failed to obtain a payment and performance bond. During the construction of the home, Boucher asked Respondent whether a payment and performance bond had been obtained. Boucher wanted to see the bond because he was concerned about Respondent actually finishing the project. In response to Boucher's request, Respondent indicated a bond had not been obtained; however, Respondent assured Boucher that a payment and performance bond would be obtained. On April 7, 1953 Respondent and Boucher obtained a construction loan in the amount of $54,400.00 from the American Savings and Loan Association of Florida, Winter Park, Florida. The construction loan was secured by a mortgage on the property located at 522 Fairview Avenue, Altamonte Springs, Florida. The proceeds of the construction loan were paid out in draws. American Savings and Loan Association of Florida paid the contract draws directly to Respondent. On August 29, 1953 Respondent executed an affidavit in support of final construction draw. American Savings and Loan Association of Florida required the affidavit as a precondition to making final disbursement to Respondent of the $4,338.50 remaining on the construction loan. The affidavit provided in pertinent part: 4. The undersigned swears that construction of the improvements to the PROPERTY has been fully completed in accordance with the plans and specifications therefore,...that all persons furnishing labor or materials, engaged as subcontractors or contracting directly with the owner of the PROPERTY in connection with said improvements, except the following, identified by name, address and amount due: [none known] have been paid in full and no person, firm or corporation has or holds any claim or lien against the PROPERTY for labor or material in connection with said improvements. Boucher was also required to sign the affidavit referred-to in Paragraph 5, above, in support of the final construction draw. Boucher's signature was required in support of the affidavit for final construction draw because Boucher had previously contacted the savings and loan association with regard to freezing the disbursement of construction funds. His request to freeze disbursements was made because Boucher was under the impression Respondent had moved to Miami and Boucher's attempts to contact Respondent had proven unsuccessful. Prior to executing the affidavit, Respondent told Boucher that certain subcontractors had not been paid. Nonetheless, Boucher, contrary to advice of legal counsel signed the affidavit knowing that certain subcontractors had not been paid and therefore knowing he was making a false affidavit. Respondent convinced Boucher that the final draw would be utilized to satisfy the remaining subcontractors and materialmen. Respondent's Answer pleads accord and satisfaction as an affirmative defense that Boucher agreed to pay off all bills of Overhead Door Co., Future Plumbing, Quality Fiberglass, and Patterson Well Drilling but Boucher's testimony that he, Boucher, insisted Respondent meet him to pay off all subcontractors out of the final draw and Respondent did not do so, overcomes any burden of proof problems raised by this affirmative defense. (See "Conclusions of Law.") On November 29, 1983 Patterson Well Drilling Company filed a claim of lien against Boucher's property. The claim of lien represented materials and labor furnished to Respondent in connection with the construction of the Boucher residence. The claim of lien was in the amount of $1,510.00. Although the claim of lien under oath of President Randall F. Patterson states that the services were provided between September 9 and September 12, 1983, Boucher testified that Patterson's services were actually provided prior to the August 29, 1983 execution of the affidavit in support of final construction draw. Randall F. Patterson's testimony tends to support this timeframe set out by Boucher, and although the difference in dates between Mr. Patterson's affidavit within the claim of lien and his oral testimony at formal hearing might otherwise present a credibility issue, his explanation at hearing coupled with Boucher's explanation of how he relates the dates persuade the undersigned that Patterson Well Drilling Company installed the well prior to August 29, 1983. Respondent failed to pay Patterson prior to executing the bank affidavit. Respondent also failed to pay Patterson from the funds received in the final construction draw. Boucher paid Patterson Well Drilling Company for the services represented by the claim of lien. A check substantiates that Boucher actually paid Patterson the amount of $1,562.40. Respondent contracted with Quality Fiberglass Industries to provide materials and services in connection with the construction of the Boucher residence. Respondent failed to fully reimburse Quality Fiberglass for the services and materials provided. On August 19, 1953 Quality Fiberglass Industries filed a claim of lien against the Boucher property for $219.00. Mr. Pope, Quality's representative, testified he was actually owed $325.00 and he has never been paid. Boucher testified he was required to pay the Quality Fiberglass lien prior to the closing on the home. There is no documentary evidence to reconcile this issue and in the absence of clear evidence that Boucher paid the fee, payment of the lien or the difference in amount is not proved. Overhead Door Company provided services to Respondent d/b/a Future Homes of America, Inc. in connection with the construction of the Boucher residence. On July 11, 1983 Overhead Door Company installed a garage door. Although contacted on several occasions, Respondent failed to pay Overhead Door Company $356.00 for the services provided. Overhead Door Company has not otherwise been reimbursed for the services provided. The construction plans for the Boucher home indicated a tar and gravel roof would be constructed over the patio. However, with the acquiescence of Mr. Boucher, Respondent placed rolled roofing rather than tar and gravel roofing on the patio. The construction plans were submitted in conjunction with the building permit application. According to Joel A. Dean, the county building department currently relies upon the construction plans in issuing the building permit. A contractor currently is required to notify the building department of any change or deviation from the submitted plans. This requirement enables the building department to control the type of building construction, the occupancy and use of the building, and ensures the buildings are constructed safe and watertight. Respondent did not notify the building department concerning the agreed roofing change as would be required by current requirements and requirements at the pertinent times under Section 114 of the Standard Building Code.

Recommendation That the Florida Construction Industry Licensing Board enter a final order suspending Respondent's contracting license for a period of two (2) years and imposing an administrative fine in the amount of $1,000.00, provided, however, if Respondent submits to the Board competent and substantial evidence of payment to Overhead Doors Co. of $356.00 and payment to Quality Fiberglass of $219.00, the period of suspension shall be reduced to one (1) year. DONE and ORDERED this 31st day of December, 1985, in Tallahassee, Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of December, 1985. APPENDIX TO RECOMMENDED ORDER, CASE NO. 84-3835 Rulings on Petitioner's Proposed Findings of Fact According To the Paragraph Number assigned by Petitioner. Accepted. Accepted. Accepted. Accepted. Accepted. Accepted. Rejected as not supported by the credible competent substantial evidence in the record as a whole as set out more fully in Finding of Fact Paragraph 9. Accepted. Accepted. Accepted. COPIES FURNISHED: W. Douglas Beason, Esquire Fred M. Roche, Secretary Department of Professional Department of Professional Regulation Regulation 130 North Monroe Street 130 North Monroe Street Tallahassee, Florida 32301 Tallahassee, Florida 32301 Michael Anguelo James Linnan 1415 West 28th Street Executive Director Apartment 4 Construction Industry Hialeah, Florida 33010 Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (3) 120.57455.227489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer