The Issue The issue in this administrative proceeding is whether the Florida Department of Transportation’s ("DOT" or "the Department") denial of Petitioner’s, Network Engineering Services, Inc. d/b/a Bolton Perez & Associates ("BPA"), 2019 application for qualification pursuant to section 337.105, Florida Statutes, and Florida Administrative Code Chapter 14-75, was for good cause due to Petitioner’s participation in the construction of the Florida International University ("FIU") City Prosperity Project ("FIU Bridge project").
Findings Of Fact DOT is the state agency responsible for coordinating the planning, construction, and maintenance of a safe, viable, and balanced state transportation system. DOT relies on qualified contractors and professional consultants to provide services for Florida’s transportation needs. Section 287.055(3), Florida Statues, requires that any firm or individual desiring to provide professional services to a governmental agency must first be certified by the agency as qualified, pursuant to law and the regulations of the agency. The agency must find that the firm or individual to be employed is fully qualified to render the required service. Among the factors to be considered in making this finding are the capabilities, adequacy of personnel, past record, and experience of the firm or individual. Each agency is also required to evaluate professional services, including capabilities, adequacy of personnel, past record, and experience of the firm or individual. Section 337.105 and Florida Administrative Code Chapter 14-75 also governs the qualifications of professional consultants and other contractual services providers to DOT. Section 337.105 authorizes DOT to deny or suspend an application for qualification based upon a determination of "good cause," which includes, but is not limited to, nine illustrative examples specified in section 337.105(1)(a)–(i). DOT may, for good cause, deny or suspend for a specified period of time a person or firm from consideration for award of a professional service contract for a particular type of work. BPA is a multidiscipline engineering firm specializing primarily in transportation related engineering services, including bridge design, roadway design, civil works, construction engineering inspection ("CEI"), and program and construction management. At the time of the hearing, BPA had approximately 38 employees. BPA was formed by Joaquin "Jake" Perez, P.E., and John Bolton, P.E., in 1997 to provide transportation-related engineering services. BPA’s CEI qualifications are independent from, and do not necessarily mirror, BPA’s design qualifications. In some instances, BPA was qualified to serve as a CEI for categories of structures that the firm was not qualified to design. This is because BPA was internally divided into two core groups: design and CEI. Since inception, BPA’s design group was and continues to be headed by Mr. Perez, and the CEI group headed by Mr. Bolton. The operations of BPA’s CEI and design groups were completely segregated within the firm. CEI personnel did not work on design projects, and design personnel did not work on CEI projects. As President, Mr. Perez was involved in pursuing contracts for CEI services, but CEI services were provided only by CEI personnel. In or about 1999 or 2000, BPA first became qualified to respond to DOT’s request for qualifications to provide professional services to DOT. Mr. Bolton qualified the firm to provide CEI services, and Mr. Perez qualified it to provide design services. BPA remained qualified with the Department on an annual basis for both CEI and design work for nearly 20 years until July 2019. At that time, DOT issued a NOID removing BPA from consideration for award of professional service contracts with DOT for 2019- 2020. DOT issued the NOID based solely upon a report issued by OSHA and the investigation of NTSB regarding the collapse of the FIU Bridge project on March 15, 2018. THE FIU PEDESTRIAN BRIDGE PROJECT In 2014, DOT entered into a Local Agency Program ("LAP") Agreement with FIU for its pedestrian bridge project, a Category II, complex bridge, that would be constructed along Southwest 109th Avenue and Southwest 8th Street in the City of Sweetwater, Florida (the "project"). As the supervising agency of the LAP program, DOT was responsible for supervising and authorizing work by the local agency. The design of a Category II structure required an independent peer review by a firm with no other involvement in the project, which was prequalified with DOT. In September 2016, FIGG Bridge Engineers, Inc. ("FIGG"), the Engineer of Record ("EOR") for the project, hired Louis Berger to review FIGG’s plans for bridge foundation, substructure (end bents and center tower), and superstructure. Those plans included construction sequencing (including construction sequence drawings), the covered main span pre-casting, transport of main span, and placement of the main span between end bent 1 (south pier) and the pylon pier. The plans also included the post-tensioning stressing and destressing sequences. As the Local Agency, FIU was in responsible charge of the day-to-day activities, including project safety issues. Alfredo Reyna, P.E., was the Department’s LAP Coordinator for the project. Mr. Reyna is a licensed professional engineer, although he is not a structural engineer. In January 2016, FIU entered into a design-build contract1 with Munilla Construction Management, LLC ("MCM"), to design the bridge and to perform all work and furnish all materials, equipment, supplies, and labor necessary to construct the project. The bridge was designed by FIGG, a member of the MCM design-build team and the EOR. FIGG is a reputable designer who has been recognized internationally for its work. FIGG has experience in designing complex bridges, such as the Sunshine Skyway Bridge near Tampa, Florida. On September 23, 2016, FIU entered into a Standard Professional Services Agreement with BPA for CEI services (the "CEI Contract"). At the 1 The interaction of the local agency, contractor, designer, EOR, DOT, and the CEI is different between a "conventional" and a "design build" bridge project. In a conventional project, the designer is hired by DOT or owner to create a new bridge. The design goes through a review process at DOT and a final set of plans goes to bid for a contractor. By the time the contractor is selected, the EOR has completed the plans. The EOR is essentially "on call" for the construction phase of the project because the design work is complete. The CEI begins its work when the contractor begins construction. If there is a question in the field, the CEI makes a request for information from the EOR. DOT supplies design and construction managers throughout the process. In contrast, for a "design build" project, the owner has a conceptual plan for the project. The designer and contractor bid for the job based on the preliminary conceptual plan. The Designer/EOR and contractor work hand in hand from the beginning of the project and are in constant communication. The CEI begins work when the contractor starts work on the project. The CEI facilitates the resolution of any issues between the EOR/designer and the contractor who continue to plan throughout the duration of the project. Like a conventional build project, DOT has construction managers and design project managers involved from the beginning of the project. If concrete cracking occurs, it is the CEI's obligation to document the cracking and speak to people in the process who can assess and address the cracking. For a conventional build bridge, if cracking is observed, the CEI documents it, copies DOT, and sends it to the EOR for assessment. The EOR provides an assessment by conducting a site visit. The EOR then prepares an Engineering Assessment Report (EAR) for the project team. In a design build bridge job, if cracks are observed, they are documented by the CEI who notifies the EOR. The EOR, who is already on the job site, assesses the cracks and works with the contractor to devise a solution. time, John Bolton was the CEI qualifier for BPA. As CEI, BPA was to act as the liaison between the project owner (FIU) and the contractor (MCM). The CEI handles quality control, materials, schedules, payments, documents the entire process, and monitors the project. Jose Morales, P.E., worked under John Bolton as the Senior Project Engineer for the project. Mr. Morales first obtained his professional engineer’s license in 2006. He had approximately 12 years of CEI experience at the time of the collapse. Although he was the Senior Project Engineer for the project, Mr. Morales had little-to-no design experience. Mr. Morales was first involved in the early stages of pursuing the CEI Contract for the project. After the project was awarded, BPA was not involved in the design phase, but was later brought back into the fold beginning in October 2016, when BPA received the Notice to Procced and fully staffed its CEI scope of services when construction was scheduled to begin in or about March of 2017. The "Scope of Services" section (Exhibit B) to the CEI Contract required BPA to be prequalified with the Department in the following work categories: Work Type 10.1--Roadway CEI; Work Type 10.4--Minor Bridge and Miscellaneous Structures CEI; and Work Type 10.5.1--Major Bridge CEI- -Concrete. For the FIU bridge project, Categories 10.1 and 10.4 were considered to be the "major" type of work while 10.5.1 was considered to be the "minor" type of work. As expressly permitted by the Standard Professional Services Agreement, BPA satisfied the 10.5.1 prequalification requirement through its sub-consultant, The Corradino Group, Inc. ("Corradino"). BPA’s scope of services for the project did not include any design responsibilities. BPA performed constructability review of the plans as part of its CEI scope of work, but it did not review the plans or drawings on a technical level. The FIU bridge was a Complex Category II structure as defined by the Department’s Design Manual. The structure had a unique, complex design that was meant to be a signature, architectural feature for the area. The relevant construction sequence for the main span (Span 1) of the FIU bridge consisted of: casting the main span superstructure in the casting yard; installing post-tension bars in the diagonal and vertical members of the structure; stressing of the main-span post-tensioning while the main span is in the casting yard; removing the temporary formwork and supports; transporting the main span from the casting yard using a self- propelled modular transporter and placing the structure in a "simply supported" condition on the south pier and pylon pier; and de-tensioning truss members 2 and 11. Generally, cracks in concrete are common and are not, in and of themselves, a cause for concern. On a design-build job, when cracks manifest themselves in a concrete element, the CEI must document the cracking and report it to the design-build team, which includes the EOR. Depending on the nature of the cracks, the CEI may request an EAR from the EOR. This process is set out in section 400, subsection 400-21, of DOT’s Standard Specifications for Road and Bridge Construction (the "Standard Specifications"). DOT's Construction Project Administration Manual ("CPAM") includes the procedures to be followed by a CEI in addressing cracks in concrete. The CPAM requires that the CEI identify and document its observations and convey the information to the EOR for a final disposition as to the potential danger of the crack or the need for further evaluation. The FIU Bridge Cracking and Inspections by BPA On or about February 6, 2018, while Span 1 of the bridge was still in the casting yard, BPA became aware of certain cracks that had developed in the structure. Mr. Morales personally inspected the structure after the tendons on truss members 2 and 11 were stressed, and he noted that cracks had developed in other locations on the bridge. The cracks observed were very small, approximately 0.004 of an inch wide. On February 13, 2018, BPA submitted Crack Report #1 to MCM, FIU, and Corradino, documenting the cracks that had developed in the concrete truss members after completing the post-tensioning operations in the casting yard. Despite the small size of the cracks, BPA requested that the EOR provide an assessment of the cracks. FIGG, the EOR, responded to BPA’s request by stating that the current condition observed was temporary in nature and that the cracks were not an issue. BPA exercised independent professional judgment when it exceeded the requirements of section 400 of the Standard Specifications and the CPAM by documenting and reporting these initial cracks. In late February 2018, before the placement of the main bridge span on the permanent pylon and south pier supports, cracks were observed in certain truss members. BPA prepared and submitted Crack Report #2 to FIU and MCM on February 28, 2018, documenting the size and location of these cracks and requested that FIGG evaluate the cracks and provide a disposition. In its report, BPA called attention to certain cracks that were significant in size. As CEI, BPA was not qualified to determine whether these larger cracks posed an imminent danger of collapse. Further, BPA’s design team was not involved in the design of the bridge and was not qualified to evaluate these cracks from a design engineering perspective due to the category and complexity of the bridge. At this point, the cracks were not "structural" as defined by Section 400 of the Standard Specifications. Cracks more than one-half inch in depth are deemed "structural" and trigger the obligation of the CEI to notify the EOR. Nevertheless, BPA, again, exercised its independent professional judgment above and beyond the requirements of the Standard Specifications and CPAM by requesting that the report be forwarded to the EOR and requesting that the EOR provide a response and disposition of the cracks. On March 7, 2018, FIGG replied to Crack Report #2, stating, in part, that the cracks appeared small, that they were not concerned about these types of cracks in the particular region shown in the report, and that MCM would need to seal the cracks in accordance with the Department’s specifications. As the EOR, FIGG did not have any structural concerns regarding the cracks in Crack Report #2. On March 7, 2018, FIGG representatives were on site and observed the cracks referenced in Crack Report #2. After observing the cracks, FIGG did not delay the bridge movement that was scheduled to take place three days later on March 10th. As of March 8, 2018, BPA had no concerns regarding the integrity of the structure or public safety because the EOR had looked at the cracks in- person and assured the project team that the cracks were not a safety issue or structurally significant. These assurances came two to three days prior to the bridge being moved over Southwest 8th Street and placed on the permanent pylon and pier supports. The bridge movement was not delayed due to the cracks observed by the EOR. On March 10, 2018, Span 1 was moved from the casting yard and placed on the permanent pylon and south pier supports. After the placement and de-tensioning of diagonal members 2 and 11, cracks began to appear at the construction joint of diagonal 11, the deck, and at the top of diaphragm II. At approximately 11:00 a.m. on March 13, 2018, two days before the collapse, BPA circulated a draft of Crack Report #3 to MCM, recommending further monitoring and documenting of the cracks to determine whether they were active or dormant, and requesting that BPA be informed of the outcome of the EOR’s EAR and course of action. At 5:18 p.m. on March 13, 2018, the EOR responded to MCM with additional recommendations and stated "[a]gain, we have evaluated this further and confirmed that this is not a safety issue." Because BPA’s design team was not involved in the project, no BPA design personnel were aware of the documented cracking on the structure until sometime after Crack Report #3 was generated. At that time, Mr. Morales provided Mr. Perez with a copy of a draft of Crack Report #3. Mr. Perez briefly reviewed the draft report and confirmed with Mr. Morales that the CEI team had elevated the issue to the EOR. At all times in the documented communication relating to the cracks, the EOR and members of the FIGG design team represented to BPA that the cracks were not a safety concern, without reservation. Starting on March 13, 2018, FIGG directed MCM to implement an initial, temporary measure to address observed cracking in the member 11/12 nodal region. At that time, BPA was not aware of this communication between the EOR and the contractor. To restore the temporary support conditions when the structure was in the casting yard, MCM placed shims between diaphragm II and the pylon on March 13, 2018. FIGG also directed re-tensioning the post-tensioning rods in truss member 11 to begin on March 15, 2018. The re-tensioning operation was made as a "rushed request" to the post-tensioning subcontractor by MCM on March 14, 2018. "FIGG recommends to stress these PT bars as soon as possible but again, this is not a safety concern." MARCH 15, 2018, AND THE BRIDGE COLLAPSE Rather than waiting for the EAR, BPA once again exercised its independent, professional judgment and went above and beyond the requirements of the Standard Specifications, CPAM, and Contract Documents when it further escalated the issue of the cracks by calling for a meeting with the EOR. On the morning of March 15, 2018, a meeting requested by BPA and coordinated by MCM, was held in Miami, Florida. Representatives of FIGG, MCM, DOT, FIU, and BPA were present. At the March 15th meeting, BPA first became aware of the EOR’s instruction to MCM to proceed with a second temporary measure. This subsequent temporary measure was to reinstate the post-tensioning compression force back in member 11 as per the previous construction phase. As explained by the EOR, both temporary measures (shims and re- tensioning) were intended to restore the temporary support conditions when the structure was in the casting yard. Prior to the start of the meeting, the EOR, other FIGG engineers, and DOT’s LAP Coordinator inspected the bridge and the cracks in the nodal region of members 11/12. Only FIGG had structural engineers at the meeting. No other engineers present at the meeting had a background in structural engineering, including those in attendance on behalf of BPA. The meeting was called for purposes of discussing the concrete cracking on Span 1, and specifically the concrete cracking in nodal connection between truss members 11 and 12 and the bridge deck. At this meeting, BPA informed FIGG that the cracks in the bridge were lengthening and growing daily. Though not formally invited, Mr. Reyna attended this meeting in his capacity as DOT’s consultant/Assistant LAP Coordinator. At the March 15th meeting, the EOR presented FIGG's assessment of the cracking after having reviewed the three BPA crack reports and having personally inspected the cracks on at least the following two occasions: (1) prior to the bridge being moved from the casting yard over Southwest 8th Street; and (2) on the morning of the March 15th meeting. The EOR’s presentation consisted of a lengthy and comprehensive PowerPoint slide presentation on the conditions of the bridge, structural analysis by calculations and 3D modeling of the loads and forces the area of member 11/12 nodal region cracks, and an evaluation of the safety of the span over Southwest 8th Street for workers and the public. Throughout the March 15th meeting, BPA exercised its independent professional judgment by actively participating in the EOR’s presentation, questioning and challenging the EOR. For example, BPA: inquired as to whether temporary shoring was needed; sought clarification regarding the mechanism being used to capture the load from the node and whether it would have to be integrated with the pylon diaphragm; requested clarification on the amount of transferred post- tensioning assumed for the nodal shear stability analysis; inquired as to whether there were any restrictions on load; inquired as to whether there would be a crack monitoring plan; requested a copy of the EOR’s presentation; inquired as to whether it had been peer reviewed and commented that it wanted more eyes on the presentation calculations; and BPA requested a copy of the stressing procedure that was being recommended by the EOR. Throughout the presentation, and during the question and answer phase of the meeting, the EOR assured BPA and the other attendees that the structure was safe. These assurances were based on statements made by the EOR as well as its calculations and modeling, which were part of its slide presentation at the meeting. In the presentation on the slide entitled "Safety," FIGG stated that "…[it] had conducted sufficient supplemental/independent computations to conclude that there is not any concern with safety of the span suspended over the road." At the end of the presentation, the EOR concluded the meeting with "[b]ased on conservative calculations, it is concluded that the design meets LRFD strength requirements for this temporary condition and therefore there is no safety concern relative to the observed cracks and minor spalls." During the meeting, the EOR stated that some cracking similar to the ones on the structure, were expected. The EOR further stated during the meeting that the top deck spalls could not be replicated, but that the spalled areas were minor and they should be repaired during the next phase of work when the pylon concrete was to be placed. No engineer at the meeting, including DOT's representative, Mr. Reyna, requested or recommended a complete road closure to protect the public safety or that the bridge be shut down. BPA had no reason to request a full road closure of Southwest 8th Street. There was no preplanned complete road closure, there was no maintenance of traffic ("MOT") deficiency, and, based on the EOR’s presentation, BPA was reasonably satisfied that no safety issues required a road closure. Towards the end of the meeting on March 15th, MCM informed BPA that a specialty contractor, Structural Technologies ("VSL"), was already onsite to conduct the re-tensioning operation. Without BPA’s knowledge, VSL had already mobilized on site to perform the remedial re-tensioning. BPA was not involved in pre-coordination for the re-tensioning operation. Therefore, BPA’s sub-consultant, Corradino, was not onsite to participate in monitoring of the re-tensioning procedure. Corradino’s role, as BPA's sub-contractor, was that of a 10.5.1 CEI (Major Bridge CEI--Concrete). Corradino was responsible for monitoring and documenting the post-tensioning operations. The post-tensioning operation after placement of the span had already occurred and therefore, Corradino was not on-site on March 15, 2018. Based on the safety assurances and conservative calculations presented by the FIGG EOR that the structure was safe, BPA, and the other professional engineers present at the meeting, including those representing FIU and DOT, followed the recommendations of the FIGG EOR to bring the main span condition back to its pre-existing state when the span was in the casting yard. BPA did not have the expertise or the contractual duty to perform its own analysis of the cracking on this complex bridge and override, or even call into question, FIGG’s unequivocal assessment that the bridge was safe. During the restressing operation of member 11, the roadway below the bridge had two westbound lanes closed as per the blanket, two-lane, closure permit issued by DOT. This blanket, two-lane, closure permit was obtained by MCM to provide workspace underneath the bridge to conduct the remedial action. MCM obtained the blanket, two-lane, closure permit from the Department the morning of March 15, 2018, before conducting the remedial action. A CEI’s authority to request a partial or complete road closure is defined by the contract plans and roadway closure permits, which is implemented using the procedures outlined by the CPAM and the CEI Scope of Services of the CEI Contract. A CEI is authorized to request the contractor to either partially or fully close a road if there is an MOT deficiency, as contemplated by CPAM Section 9.1.8--"Recommended Action to Shut Down a Project Due to MOT Deficiencies." Lastly, a CEI has authority to request a partial or full road closure if it is aware of a safety issue. None of these conditions existed on the project in the days leading up to the collapse in light of the EOR’s comprehensive presentation regarding the cracking conditions of the bridge, strength in the area of member 11/12 nodal region, safety of the span over Southwest 8th Street, and repeated, unequivocal reassurances that the structure did not pose a safety concern. Ultimately, BPA’s authority to request a partial or complete road closure on the project was a collective effort with the Department and FIU. BPA did not have the authority or ability to act on its own to close the road. The FIU Pedestrian Bridge collapsed during the re-tensioning of the truss member 11 post-tensioning rods on the afternoon of March 15, 2018. Six people died as a result of the FIU bridge collapse, including one bridge worker and five vehicle occupants. Ten people were critically injured as a result of the FIU bridge collapse, including two BPA employees, Mr. Morales and Carlos Chapman. Mr. Chapman was on the canopy of the bridge during the re- tensioning operation, observing the work being performed by VSL and communicating the progress to Mr. Morales who was on the deck of the bridge. Because of the representations made by the EOR, neither Mr. Chapman nor Mr. Morales was concerned for his own safety or well-being when they went on the bridge on the day it collapsed. BPA’s role, responsibilities, and scope of work on the FIU Bridge project as the CEI was that of a contract administrator, not as a structural engineer with the capability to analyze the structural behavior of the bridge sufficient to determine if the cracks posed any danger of collapse. BPA had no basis, ability, or contractual obligation, to perform its own analysis of this complex structure sufficient to override the FIGG EOR’s unequivocal safety assessment and recommendations. BPA performed its CEI duties and utilized its independent professional judgement when it documented and monitored the cracks and requested an immediate structural evaluation by the FIGG EOR. Ultimately, the bridge collapse was caused by a fundamental design error. THE OSHA AND NTSB INVESTIGATIONS Shortly after the collapse, both OSHA and NTSB began investigating the causes of the collapse. OHSA completed its investigation and released a written report of its findings in June 2019.2 The June 2019 OSHA report was 2 DOT failed to enter into evidence the OSHA report on which it relies. However, prior to the final hearing, DOT filed a Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse ("Motion"). The Motion was opposed by BPA on the basis that the first OSHA report was not final because a second report was issued, and is hearsay. By Order dated January 24, 2020, the undersigned officially recognized both the issued without prior review or comments from all party members who willingly cooperated with and were involved in the investigation, including NTSB and BPA. OSHA released an amended report on the collapse of the FIU Bridge project in July 2019; however, none of the amendments in the report pertained to the actions of BPA on the FIU Bridge project. NTSB completed its investigation and issued its report in October 2019. Significantly, no evidence was presented at the final hearing regarding from whom either agency conducted the investigations or drafted the reports, the qualifications or expertise of the investigators, the methodology used in the investigations, or the ability of any of the participants in the investigation to rebut the findings or conclusions. BPA willingly participated in both the OSHA and NTSB investigations, working with investigators and providing them with information, photographs, and details on the FIU Bridge project. Both OSHA and NTSB also conducted interviews of BPA personnel involved with the FIU Bridge project as part of their investigations. In its report, OSHA found that BPA failed to classify the concrete cracks, which were structural in nature, in accordance with DOT requirements. OSHA determined that BPA, as CEI, was expected to exercise its own independent professional judgment in accordance with their contract with FIU and DOT requirements. With intimate knowledge of extensive initial OSHA report and the NTSB report. Accordingly, references to the report in this Recommended Order are based upon the official recognition. As noted in the Order on the Motion, official recognition of the OSHA and NTSB reports, however, does not make the statements contained therein automatically admissible. "The distinction between noticing the contents of a record and noticing the truth of the contents resembles the distinction in the hearsay doctrine between offering an out-of-court statement simply to show it was said, and offering it for the truth of the matter asserted." C. Ehrhardt, Florida Evidence § 201.1 (2011 Edition)(quoting Wright & Graham, Federal Practice and Procedure: Evidence § 6337). Although the existence of the report and its findings were officially recognized, the greater weight of the evidence supports that the contents were not accurate as to the exercise of independent judgment of BPA. cracking on the bridge, BPA failed to recognize the bridge was in danger of collapsing, and did not recommend to FIU, MCM, or others to close the street and shore the bridge, regardless of the opinion held by the EOR. As a result, OSHA imposed a monetary fine on BPA for its conduct and failure to take appropriate action in the days leading up to the collapse of the main bridge span. In its October 2019 report (issued after the NOID to BPA in this case), NTSB found that beginning with the cracking identified on February 24, 2018, the distress in the main bridge span was active, continued to grow, and was well documented by all parties involved in the design, construction, and oversight of the bridge. Neither FIU, MCM, FIGG, nor BPA took responsibility for declaring that the cracks were beyond any level of acceptability and did not meet DOT standards. Further, NTSB concluded that under the terms and conditions of the CEI Contract, BPA had the authority to direct or authorize partial or complete road closures as necessary, acting in concert with DOT and FIU; however, none acted to close the road under the bridge, contributing to the severity of the impact of the bridge collapse. BPA POST-COLLAPSE ACTIVITIES AND 2018 APPLICATION FOR QUALIFICATION On May 3, 2018, BPA submitted its Request for Qualification for the July 1, 2018, through June 30, 2019, fiscal year ("2018 Application"). BPA’s 2018 Application was for the same Work Groups that would eventually be included in the 2019 Request for Qualification. Each work category is tied to a distinct job function. There is no relationship or similarity between CEI services (Work Group 10) and the other work groups. On June 27, 2018, DOT accepted BPA’s Request for Qualification in all work categories. In processing the application, the Department did not ask BPA any questions regarding its involvement in the project, offer any criticisms of BPA in response to the application, request to interview any BPA employees, or raise any concerns at all regarding BPA’s participation in the project. From the date of the collapse on March 15, 2018, to December 2018, DOT awarded two contracts to BPA directly for CEI and design services, respectively. During the same period, DOT allowed BPA to participate as a qualified sub-consultant on one CEI contract, three design contracts, and one traffic task work order contract. During the 2018-2019 fiscal year, before DOT attempted to suspend BPA’s qualifications, BPA was able to win several jobs in both the prime and sub-consultant role, including projects in which BPA would be providing CEI services. In October 2018, approximately seven months after the collapse, BPA applied to change its CEI qualifier from John Bolton to Jose Morales because John Bolton wanted to retire. DOT approved the request and did not object or raise any concerns with respect to Jose Morales serving as BPA’s qualifier for CEI services. On December 19, 2018, nine months after the collapse, DOT expressed concern for the first time about BPA’s role in the bridge project, staffing of current DOT projects, quality assurance/quality control ("QA/QC") plans, and professional liability insurance. DOT sent BPA a "Qualifications Letter of Concern," stating that it had "serious concerns regarding [BPA]’s involvement as the Construction Engineering Inspection consultant on the Florida International University (FIU) pedestrian bridge project[.]" DOT requested in its letter, among other things, "a detailed explanation of the firm’s actions on the FIU pedestrian bridge project and… any controls or changes in personnel, policies or practices that [BPA] has implemented subsequent to the collapse." On December 21, 2018, BPA responded to the Letter of Concern addressing each concern raised by the Department, in detail, including providing a copy of its Certificate of Liability Insurance demonstrating that there was no lapse in professional liability insurance coverage. On February 12, 2019, DOT responded to BPA’s correspondence dated December 21, 2018, requesting additional detail from BPA relative to its revised QA/QC plan and punctuated the correspondence by stating that DOT would refuse to process any further qualification requests from BPA, including ministerial prequalification name changes, until the matter was addressed to the Department’s satisfaction. Around this time, BPA submitted a request to change its name with DOT to reflect its business name with the Division of Corporations. BPA requested that DOT update this information on its website, but DOT refused to process the request due to its concerns with BPA’s qualifications. On February 20, 2019, BPA provided further detail regarding the specific policies and procedures that have been implemented to its CEI services. Specifically, BPA provided extensive detail regarding its revised QA/QC plan, which included a section dedicated to Category II type bridge structures and included a copy of the revised QA/QC program for DOT review. DOT never responded or requested any additional information in this regard. On March 15, 2019, one year to the day after the collapse, DOT issued a Notice of Intent to Suspend BPA’s existing certificate of qualifications. DOT attempted to suspend BPA’s qualifications in all Work Groups and declare BPA non-responsible for a period of one year for good cause. DOT further claimed that BPA "failed to adequately address the Department’s concerns regarding the firm’s performance of the contract, and the [BPA] staff directly involved with the FIU project who continue to work on other Department structural contracts." No further explanation was provided as to how BPA failed to address these concerns. BPA timely responded to the Notice of Intent to Suspend by way of a Notice of Contest, requesting an administrative hearing on the issues raised therein. Despite the Notice of Contest, DOT suspended BPA’s qualification, and sent written notice to its various offices stating, among other things, that BPA had been removed from DOT’s prequalification list. Ultimately, DOT reinstated BPA’s qualifications, but never formally withdrew the Notice of Intent to Suspend. However, in reinstating BPA’s qualifications, DOT neglected to reinstate BPA’s Small Business Enterprise ("SBE") designation, which negatively affected BPA’s ability to obtain points for SBE participation. The points add value in scoring competing responses to Requests for Proposals for DOT contracts. BPA repeatedly requested that this be corrected. BPA’s requests went largely ignored for nearly two months. On April 2, 2019, after BPA had an in-person meeting with Courtney Drummond, DOT's Assistant Secretary of Engineering and Operations, BPA submitted a qualifications modifications package to replace Jose Morales, P.E., with John Bolton, P.E., as the qualifier for the CEI Work Group to address Mr. Drummond's and DOT’s concerns about BPA staff involved on the FIU project working on other DOT contracts. On April 5, 2019, in response to the Notice of Intent to Suspend, BPA provided specific facts in support of BPA’s proper performance of the CEI Contract. As an accommodation to DOT, BPA further proposed a solution to DOT's concern about the staff involved in the FIU project. BPA stated that it was "willing to immediately remove the BPA staff directly involved in the FIU Bridge project from working on any Department contracts or qualifying the company for CEI services" and resubmitted its qualifications application with those changes. 2019 BPA REQUEST FOR QUALIFICATION REJECTION On May 7, 2019, BPA submitted its 2019 Request for Qualification to the Department early due to the lack of response from DOT on BPA's April 5, 2019, correspondence. BPA sought qualifications for design work and CEI services in the same work categories it was qualified in for the prior fiscal year. On June 10, 2019, BPA’s counsel met with DOT representatives in Tallahassee to discuss several outstanding issues relative to BPA’s current qualification, the upcoming renewal, and DOT’s failure to reinstate BPA’s SBE designation. DOT responded by promising to correct the "mistake" that same day. Inexplicably, it took another two weeks and several reminders from BPA for DOT to finally correct the SBE designation. BPA’s 2018-2019 qualifications expired on June 30, 2019. The next day, on July 1, 2019, DOT untimely responded to BPA’s Request for Qualification with a letter titled "Incomplete Renewal Applications for Pre- Qualification." DOT's letter raised the same concerns regarding BPA’s involvement in the bridge project and, again, requested "a detailed explanation of BPA’s actions on the FIU pedestrian bridge project and…any controls or changes in personnel, policies or practices that BPA has implemented subsequent to the collapse." This is the same request that had been previously made by DOT in its December 19, 2018, Qualifications Letter of Concern, February 12, 2019, Qualifications Letter of Concern, March 15, 2019, Notice of Intent to Suspend, and April 26, 2019, denial of BPA’s Submittal for Modification. BPA had already provided the information requested several months prior to DOT's July 1, 2019, correspondence. On July 11, 2019, DOT issued its Notice of Intent to Deny Request for Qualification directed to BPA’s 2019 Request for Qualification. In issuing its denial of BPA’s Request for Qualification, DOT relied solely on the findings and conclusions of the June 2019 OSHA Report as they relate to the CEI services provided by BPA on the project and referenced the pending NTSB investigation. The Department’s Notice of Intent to Deny was executed by William Watts, the Department’s Chief Engineer. Mr. Watts admitted at final hearing that he does not have the training or experience necessary to evaluate a CEI’s performance on a CEI contract. Moreover, neither Mr. Watts nor DOT retained or consulted with any individuals with CEI expertise prior to issuing the Notice of Intent to Deny. When he issued the Notice of Intent to Deny, Mr. Watts was completely unfamiliar with the following: the terms of BPA’s CEI Contract; BPA’s Request for Qualification; BPA’s past performance on CEI or any other Department contract; and BPA’s professional reputation. Mr. Watts did not evaluate BPA under the criteria required by Florida Statutes and the Florida Administrative Code prior to denying BPA’s Request for Qualification for good cause. Mr. Watts did not receive any analysis from the Department’s prequalification staff regarding their evaluation of BPA’s application under the statutory criteria. Mr. Watts admitted that he was aware that BPA documented the cracking on the bridge, reported the cracking to the design-build firm, and requested an EAR from the EOR--actions which were all in accordance with BPA's obligations as CEI pursuant to the CPAM and its contractual obligations with FIU. Mr. Watts’ only reason for issuing the Notice of Intent to Deny, as Chief Engineer for DOT, was because BPA was under investigation by OSHA and the NTSB, and OSHA’s release of its June 2019 Report. However, Mr. Watts did not know the author of the June 2019 OSHA Report, whether the author of the report was qualified to evaluate the performance of a CEI under Florida Statutes and the Florida Administrative Code, or whether the author of the OSHA report did anything to evaluate BPA’s performance relative to any other CEI, at the same time, and/or in the same community. DOT did not investigate the structure or organization of BPA to determine whether the issues raised in the OSHA report, regarding BPA’s performance of the CEI Contract, would reflect negatively on other groups or divisions within BPA that provided services exclusively under other non-CEI work categories (design services). Prior to issuance of the NOID, Mr. Watts did not undertake a review of BPA’s past performance or professional reputation--both of which were beyond reproach. DOT evaluates its consultants’ performance on all projects approximately every six to eight months. These evaluations produce a score that ranges from one to five, five being the highest possible score. A perfect score of five is uncommon and a score of four is outstanding. In the five years prior to the final hearing, DOT evaluated BPA’s performance on projects involving both design and CEI services. Specifically, DOT scored BPA’s performance in Work Groups 3.1, 3.2 (Highway Design), 4.12 (Bridge Design), 5.1 (Bridge Inspection), 7.2 (Traffic Operations Design), and 10.1 and 10.3 (CEI). During that period, BPA averaged a score of outstanding to nearly- outstanding on all projects, including outstanding and nearly-outstanding scores for inspection services on bridge rehabilitation projects, which involved cracking concrete elements. In May of 2019, prior to denying BPA’s request for qualifications for the fiscal year July 1, 2019, through June 20, 2020, Mr. Drummond personally presented BPA with an award from the American Council of Engineering Companies ("ACEC"), for excellence in major urban reconstruction. Specifically, the award was for CEI services on the State Road 7 project, and the ACEC recognized two-and-a-half-years of excellence in CEI services from late-2016/early-2017 through 2019. DOT's District Construction Engineer, District 6 Secretary, and Headquarters were intimately involved in the selection and vetting process that, ultimately, resulted in BPA receiving the award. In September 2019, after denying its request and three months after the release of the June 2019 OSHA Report, DOT voted that BPA receive another award for excellence in CEI services. As a member of the selection committee, DOT chose BPA to receive an award from the Florida Transportation Builders Association ("FTBA"), for excellence on the Baker’s Haulover Bridge rehabilitation project. By this award, FTBA and DOT recognized BPA’s excellence in CEI services, which spanned from one year before the collapse to one year after the collapse. The Experts 3 Gustavo Quesada, P.E. At the Final Hearing, BPA presented the expert testimony of Gustavo Quesada, P.E., a CEI with over 30 years of experience. The ALJ finds that Mr. Quesada is a qualified expert on the standard of care for a CEI and his opinions in that regard are based on competent substantial evidence. As explained by Mr. Quesada, the role of a CEI with respect to cracks in concrete is to identify the cracks and make sure they do not go unseen or undetected and that an EOR is engaged for purposes of addressing the cracking. Pursuant to the CPAM, when a CEI encounters cracks in concrete, a CEI is required to document the observation and make a disposition on the cracks based on Section 400 of the Standard Specifications. Moving forward, the CEI is also required to monitor any changes in the cracks. A CEI is not responsible for making a determination as to whether a crack is potentially dangerous. This is a determination for the EOR, who has an understanding of the structure, its design, and how the structure is expected to behave. A CEI is not charged with making judgment calls on the design of a structure or whether its integrity has been jeopardized. BPA documented, monitored, and reported the cracks on the project in compliance with the industry standards for CEIs working on Complex Category II Bridges, as well as the relevant sections of the CPAM and Section 400 of the Standard Specifications. BPA’s Senior Project Engineer, Mr. Morales, exercised his independent professional judgment in elevating 3 DOT intended to offer Mr. Watts at hearing as an expert to testify to the "good cause" DOT had when issuing the NOID to BPA. BPA filed a Motion in Limine to exclude or limit the testimony of both Mr. Watts and Mr. Robertson. The motion was argued at the outset of the final hearing. The undersigned precluded Mr. Watts from testifying as an expert in the field of CEI. Mr. Watts was allowed to testify as to DOT's qualification process and did so as a fact witness, rather than an expert. the issue of the cracks to the EOR even before he was required to do so under the CPAM and Section 400 of the Standard Specifications. At the meeting called by BPA on the morning of March 15, 2018, BPA exercised its independent professional judgment and complied with the applicable standard of care when Mr. Morales asked the EOR a series of questions in response to the EOR’s presentation and evaluation of the cracks on the bridge. According to Mr. Quesada, professional engineers are expected to rely on other engineers with superior or specialized knowledge when exercising their independent professional judgment. BPA’s role, responsibilities, and scope of work on the project as the CEI was largely that of a contract administrator, and a liaison between FIU and MCM--not as a structural engineer with the capability to analyze the structural behavior of the bridge sufficient to determine if the cracks posed any danger of collapse. Robert V. Robertson, P.E. DOT presented the testimony of Robert V. Roberson as an expert on the standard of care for CEIs. Mr. Robertson has served as DOT's State Structure’s Design Engineer for 13 years. Mr. Robertson has been a professional engineer for 35 years. Although preliminarily accepted by the undersigned as an expert in this field, it became apparent through cross-examination that Mr. Robertson has no significant CEI experience. Mr. Robertson has not worked in the CEI industry in the last 26 years, nor has he ever graded a CEI’s performance. Mr. Robertson was not involved in the Department’s evaluation of BPA’s performance of the CEI Contract. Accordingly, Mr. Robertson's testimony was of limited value. Mr. Robertson acknowledged that the FIU bridge was a complex concrete bridge structure that required a separate design qualification and that BPA did have such qualification. Mr. Robertson admitted that BPA’s contract with FIU did not require BPA to be qualified to inspect complex concrete bridges because BPA was allowed to satisfy that particular qualification requirement of the contract through a sub-consultant (Corradino). Mr. Robertson testified that any licensed engineer with a college degree in engineering should have known, based on the photographs in Crack Report #3, that the cracks were dangerous and should have acted to stop work on the project and close the road. However, DOT's LAP representative at the March 15, 2018, meeting held prior to the bridge collapse, Mr. Reyna, a licensed professional engineer with a college degree in engineering, failed to raise any concerns at the March 15th meeting or act to cease bridge work, shore the bridge, or close Southwest 8th Street under the bridge. Mr. Robertson opined that the re-tensioning operation of the bridge should have been peer reviewed. In his opinion, BPA failed to use sufficient independent judgment. BPA, as the CEI, should have recognized the bridge was in danger and known to stop traffic and shut down the road. However, Mr. Roberston admitted that he did only a cursory review of the PowerPoint presentation provided on the morning of March 15, 2018, in which FIGG, as the EOR, stated it had no safety concerns. Mr. Robertson stated that he performed no analysis on anything other than BPA's CEI work relative to the FIU bridge. He had no information about BPA's design group or its qualification in any work category. However, he suggested the denial of BPA's application for qualification across the board, in all work categories because he questioned "the culture at BPA." Significantly, concerns regarding "the culture" of BPA was not cited by DOT as a basis for the NOID. Most significantly, Mr. Robertson testified that six months prior to the issuance of the NOID, he had a conversation with Mr. Drummond during which Mr. Drummond recommended that the qualification of all parties involved with the FIU Pedestrian Bridge project should be suspended. Importantly, this was prior to the issuance of either the OSHA or NTSB reports and seemingly with no analysis of the role of any party to the possible prevention of the bridge collapse, injuries, or loss of life. Ultimate Findings of Fact DOT failed to demonstrate that BPA, as the CEI, fell below the standard of care by failing to exercise its independent professional judgment by not acting to cease bridge work, shore the bridge, or close Southwest 8th Street under the bridge in light of the documented cracking on the structure in the days leading up to the collapse. The evidence shows that BPA documented, monitored, and reported the cracks pursuant to the CPAM, Section 400 of the Standard Specifications, and industry standards. BPA involved the EOR in evaluating the cracks even before it was required by the CPAM, Section 400 of the Standard Specifications, and industry standards. BPA was assured time and again by the EOR that the bridge did not pose a danger to the travelling public and that the structure was safe. At the meeting on the morning of March 15, 2018, BPA inquired as to whether temporary shoring was needed, and the suggestion was rejected by the EOR who had inspected the cracks on the structure just moments before the meeting. There is no evidence that BPA deviated from the standard of care for CEIs on design-build projects or that BPA failed to exercise its independent professional judgment. To the contrary, BPA met all of its obligations pursuant to contract and state regulation. DOT failed to demonstrate that BPA, as the CEI, fell below the standard of care by failing to exercise independent professional judgment by not acting to cease bridge work, shore the bridge, and close Southwest 8th Street under the bridge pending a peer review of the re-tensioning plan proposed by the EOR at the March 15th meeting. At the March 15th meeting, BPA was reasonably convinced by the EOR that the structure was safe and that the re-tensioning plan was a temporary measure that should be implemented as soon as possible. BPA had already engaged the EOR to prepare an EAR to address the cracking observed on the bridge, which would have included signed and sealed calculations and a repair protocol that would have been implemented in a later phase of construction. On March 15, 2018, the cracks were not a safety concern such that BPA should have overridden the EOR’s directive to MCM and required that the re-tensioning operation be postponed pending a peer- review of the re-tensioning plan. There is no evidence in the record that BPA deviated from the standard of care for CEIs on design-build projects or allegedly failed to exercise its independent professional judgment by allowing the re-tensioning procedure to proceed as directed by the EOR. Conversely, the evidence supports a finding that BPA acted appropriately in relying on the recommendations of the EOR who was uniquely qualified to evaluate the safety of the structure and who had specialized knowledge of its design. DOT failed to demonstrate that BPA, as the CEI, fell below the standard of care by failing to exercise independent professional judgment by not acting to cease bridge work, shore the bridge, and close Southwest 8th Street under the bridge until the Corradino Group could arrive on the project site to observe the re-tensioning operation proposed by the EOR during the meeting on March 15, 2018. Corradino’s role on the project was to monitor and document post-tensioning operations. By the time the meeting was over, MCM’s specialty contractor, VSL, was mobilized and prepared to proceed with the re-tensioning operation. BPA was not involved in the pre- coordination of this work. Ultimately, the bridge collapsed due to an inherent design error in the plans and not due to Corradino’s absence from the re- tensioning operations. The findings of the OSHA report and the pendency of the NTSB investigation, standing alone, were insufficient "good cause" for DOT to deny BPA’s 2019 Request for Qualification.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered by the Department of Transportation finding that good cause does not exist to deny BPA’s 2019 Request for Qualification. DONE AND ENTERED this 17th day of April, 2020, in Tallahassee, Leon County, Florida. S MARY LI CREASY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of April, 2020. COPIES FURNISHED: George Spears Reynolds, IV, Esquire Florida Department of Transportation 605 Suwannee Street, Mail Stop 58 Tallahassee, Florida 32399-0450 (eServed) Scott Kirschbaum, Esquire Cole, Scott & Kissane, P.A. 9150 South Dadeland Boulevard, Suite 1400 Miami, Florida 33156 Anthony Lopez, Esquire Cole, Scott & Kissane, P.A. 9150 South Dadeland Boulevard, Suite 1400 Miami, Florida 33156 George Richard Truitt, Esquire Cole, Scott & Kissane, PA 9150 South Dadeland Boulevard, Suite 1400 Miami, Florida 33156 (eServed) John Ashley Peacock, Esquire Department of Transportation 605 Suwannee Street, Mail Stop 58 Tallahassee, Florida 32399-0450 (eServed) Andrea Shulthiess, Clerk of Agency Proceedings Department of Transportation Haydon Burns Building 605 Suwannee Street, Mail Stop 58 Tallahassee, Florida 32399-0450 (eServed) Erik Fenniman, General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street, Mail Stop 58 Tallahassee, Florida 32399-0450 (eServed) Kevin J. Thibault, P.E., Secretary Department of Transporation Haydon Burns Building 605 Suwannee Street, Mail Stop 57 Tallahassee, Florida 32399-0450 (eServed)
Findings Of Fact On January 20, 1988 the City made application to the Department for issuance of a dredge and fill permit to replace an existing wooden bridge known as the Lynnhaven Terrace Bridge which crosses Deep Bottom Creek in Duval County, Florida. At that time the existing bridge was a two lane timber bridge measuring approximately 20 feet wide, having two spans of 19 feet and 14 feet respectively with associated guardrails. The replacement bridge was to be 44 feet wide and 37 feet long. Subsequently, a revision was made to the permit application which called for reduction in the width of the bridge to 39 feet. A copy of the original application may be found as City's Exhibit 2 admitted into evidence and the revision was received as City's Exhibit 3. The bridge in its revised format would include two paved lane and two sidewalks on the outside of those lanes. This bridge too would have guardrails. The bridge replacement project would involve the dredging of approximately 122 cubic yards of material from the creek bottom and the installation of 12 concrete pilings along the riverbank. Approximately 4.75 cubic yards of fill will be placed below the mean high waterline and 690 cubic yards above that line. Stabilization of the north and south banks of the side of the bridge will be accomplished with 160 linear feet of sheet pile wall. The total acreage to be filled is approximately 1.1 acres with 0.002 acres being in wetlands or open waters within the Deep Bottom Creek. By this arrangement, part of the activities are within waters of the state and the upward extent of those waters and confer jurisdiction on the Department to require a dredge and fill permit and water quality certification. The jurisdiction of the Department extends to the mean high waterline of the creek in accordance with Section 403.913(2), Florida Statutes, and this takes into account the opportunity to examine the implications of dredging and filling associated with the project. The waters at issue are Class III waters. Black Bottom Creek is part of a drainage basin leading to the St. Johns River, a major water body. The reason for this project concerns the present bridge's deteriorating condition as shown in the City's Composite Exhibit 1, a series of photos. The bridge is in such disrepair that it has been downgraded in its load rating to three (3) tons, which is inadequate to support heavy vehicles, to include emergency vehicles such as firetrucks. With the advent of the concrete bridge, this problem would be rectified. An attempt to effect repairs on the existing bridge is not a reasonable choice for the City. The Department, in response to the application, conducted an assessment of that application or appraisal to include biological and water quality concerns. A copy of the report rendered in response to the application may be found as the Department's Exhibit 1. That report favors the grant of a permit in water quality certification and at the date of hearing that opinion was still held by the Department. The report points out that the project would straighten out a problem with a curve in the creek course by the choice of location for the new bridge. This arrangement will assist in the flow pattern and give a positive influence in preventing shoaling underneath the existing bridge. It will also positively affect the problem of the erosion in the upland area of the existing bridge which causes deposition of material into the creek bottom. The report describes the fact that steps to contain turbidity during the construction phase can be achieved. Having been satisfied concerning this application, an Intent to Issue a Permit and water quality certification was stated on April 15, 1988. A copy of the Intent to Issue may be found as Department's Exhibit 2 admitted into evidence. The permit was to be issued on condition concerning the question of authority to operate in waters of the state as contemplated by Chapter 253, Florida Statutes. That matter is not one for consideration in the present dispute. It also refers to preservation of historical and archeological artifacts. There has been no demonstration that such artifacts exist in the area of this project. The turbidity control mechanisms were mentioned as a special condition and as suggested before, those matters can be attended by this applicant and are expected to be. There is reference to doing the work at periods of average or low water, and there was no indication that this could not be accomplished by the applicant. On April 19, 1988 the actual permit was rendered and had attached letters of April 18, 1988 advising the City that it could contest the permit terms and the fact that others might promote objections to the permit and water quality certification. In fact, a number of land owners in the general vicinity of the project have contested this permit application leading to the present hearing. The petition and challenge to the intention to grant a permit was timely made. The Petitioners are Mr. and Mrs. John Jordan, Mr. and Mrs. Ian Ablett, Mr. Keith Kelly, Ms. Dorothy Brown, Mr. Hal Moyle, Ms. Holly Baker, Ms. Beatrice Diomont, J. H. Cater, Mr. and Mrs. W. Reed, Mr. and Mrs. H. Carrell, Mr. Harvey Jay, Ms. K. C. Walsh and Donald Braddock. Only Mr. and Mrs. Ablett, Mr. Kelly, and the Carrell's attended the hearing and established their standing to challenge the intended agency action. Moreover, the nature of their challenge as set forth in their petition has been restricted by a ruling which struck reference to the alleged influence which this project has on property values associated with a lack of sensitivity for aesthetics in exchanging the wooden bridge for a concrete pile bridge. Otherwise, the Petitioners through the presentation at hearing spoke in terms of shoaling at the site as a matter of their concern. This problem is not one which is attributable to the City and its activities, it is related to commercial activities upstream from the project site. As described, if anything, the project will alleviate those problems to some extent. Additional reasons which the Petitioners advanced in opposition concern the belief that they did not need a new bridge, that the bridge was too wide and that they did not need sidewalks and guardrails. Notwithstanding their perceptions, the overall public needs would favor the replacement of the bridge to include wider lanes and sidewalks for safe pedestrian passage. Again, at present, there are no sidewalks with the existing bridge. The expression of opposition by the Petitioners beyond the reference to the shoaling problem and the effects on water levels is not a matter of environmental concern contemplated by the permit application review process under consideration here. On May 13, 1988, the Department of the Army issued a permit for this project, a copy of which may be found as City's Exhibit 4 admitted into evidence. In addition, the Coast Guard has no opposition to this project and has said as much in its correspondence of May 2, 1988, a copy of which may be found as City's Exhibit 5 admitted into evidence. The immediate and long term impacts of this project are not violative of applicable state water quality standards, in that reasonable assurances have been given that those standards will not be exceeded. This project is not contrary to the public interest. It is not adverse to public health, safety or welfare or property of others. The project will not adversely affect the conservation of fish and wildlife, to include endangered or threatened species or other habitats. The project will not adversely affect navigation or the flow of water which will cause harmful erosion or shoaling. The project will not adversely affect the fishing or recreational values or marine productivity in the vicinity of the project. The project is permanent in nature but over time it will not have adverse impacts on the environment. Considering the current conditions and diminished value of environmental functions being performed by the area, they are not particularly significant at present and the project will not change that posture, in fact it may improve the circumstance. Specifically, at present no endangered or threatened species are found within the creek. There had been some wildlife activity, but continuing problems with silting or shoaling have occurred since the homeowners in the area dredged the creek bottom, and wildlife has decreased as a result. This relates to the upstream activities which continue to promote problems in the creek bottom. On the subject of navigation, limited navigation is available by small boats or canoes at present, and the elevations of the replacement bridge are such as to not interfere with that activity.
Findings Of Fact Leamington (Petitioner herein), is a road maintenance and construction contractor doing business since approximately 1985. John Hummell is Petitioner's President and is responsible for all bids submitted for contract awards. Petitioner contracts primarily with the Florida Department of Transportation (Respondent herein). Since 1985, Petitioner has entered into approximately forty-one (41) contracts with Respondent. Petitioner was one of seven bidders on State Job #17030-3536, Contract E-1706, let by Respondent in District I. Respondent notified Petitioner of its decision to award the bid to the second lowest bidder, Simco, by notice posted on April 19, 1993 stating that Leamington's bid was rejected because it was considered not to be responsible and was not in the best interest of the Department (to contract with Leamington). The work in question involves the repairs of the bridge located at SR- 789 at Little Ringling Causeway west of Sarasota in Sarasota County. The work entails removal and replacement of silicone sealant on the bridge deck and replacement and rejacketing of piling with grout epoxy. The bid tabulations revealed that Petitioner's bid was approximately $500.00 less than that of the second lowest bidder, Simco, Inc., of Sarasota. The Department has a procedure called the "district contracts procedure". Part of the procedure calls for the awards committee to review bids and determine who the bid should be awarded to. The awards committee, which was chaired by Glenn Ivey, the District Director of Operations, reviewed the bid submitted for project E-1706. The awards committee voted unanimously to reject Leamington's bid on Contract E-1706. The decision to reject Petitioner's bid, by the awards committee, was based on Petitioner's performance on its more recent Department contracts. Specifically, the awards committee considered projects E-1649, for sidewalk repair in several counties; contract E-1545, a concrete repair job in Lakeland; and contract E-1652, a roadway shoulder repair job. Leamington's contract on the concrete repair job (E-1545) was rated as being poor when Leamington was, in effect, asked to leave the job. Based on Leamington's poor workmanship and difficulties encountered on that contract, Respondent terminated work on the contract after approximately sixty percent (60 percent) of the work was completed. The remainder of that project was completed by another contractor. Specifically, Job No. E-1545 called for Petitioner to remove and replace portland concrete slabs on Memorial Boulevard in Lakeland. Petitioner failed to restore the concrete slabs to a smooth surface, making it necessary for Respondent to have the slabs ground such that motorists had a smooth driving surface. After several warnings, Respondent cancelled the project and, as noted, approximately forty percent (40 percent) of the work was completed by another contractor. Another project reviewed by the awards committee was Contract E-1652, a roadway shoulder repair contract. On that project, Petitioner was advised that the shoulder had to be graded at a certain angle and was shown, by several of Respondent's engineers, the proper manner in which to accomplish the task. Petitioner failed to grade the shoulder at the correct angle as requested. Petitioner also routinely failed to provide proper traffic control during the performance of Contract E-1652 and frequently disputed Respondent's employees advice as to work instructions and ways to eradicate the poor workmanship on that project. Additionally, Petitioner failed to use skilled workers and did not have ample equipment on the job to perform the work on Contract E-1652. Initially, Petitioner had limited equipment at the beginning of the work on Contract E-1652. After Petitioner received a letter from Respondent advising that there wasn't adequate equipment to complete the project, Petitioner obtained additional equipment. The Department terminated Petitioner's work under Contract E-1652 because Petitioner had approached the contract deadline for completion and due to of the numerous problems the Department experienced with Petitioner in getting the work completed acceptably. Bobby Cranford, the Assistant Maintenance Engineer for the Petitioner's Sarasota Maintenance Unit, recommended that Petitioner not be awarded any more roadway shoulder repair contracts based on the difficulties experienced by Petitioner's "poor" workmanship on contract E-1652. Another project reviewed by the awards committee was Petitioner's work performance on Contract E-1649, a sidewalk repair job which encompassed several counties. Petitioner did not have the required personnel and expertise to perform the sidewalk job correctly. Petitioner was kept informed of deficiencies and necessary corrections to correctly perform the sidewalk repair job, however, the proper repairs have not been made. The Respondent introduced a composite of twenty-three (23) photos showing the extent of the problems Petitioner needed to correct the sidewalk repairs with notes as to the corrective action that was needed. Specifically, Petitioner used little expansion joint materials and no edging tools were utilized on the project. Similar problems were found throughout the four county area in which Petitioner was engaged on the sidewalk project. By letter dated May 13, 1993, Respondent advised Petitioner of the numerous problems on contract E-1649. Specifically, Petitioner's President was told of visual inspections which showed substandard work on the original work as well as the work wherein Petitioner attempted to correct deficiencies which were discovered by Respondent. For example, Petitioner was advised that at 506 First and Main Streets in Wachula, there were sections of concrete sidewalk removed and scheduled for replacement with adjacent sections now damaged. Petitioner was further advised that workers had driven trucks on the sidewalk damaging several slabs not marked for replacement. Finally, Petitioner was asked to correct broken sprinklers at the work site and to resolve a claim filed by a Mrs. Campbell, which was registered with Respondent. The awards committee also relied upon an independent inspection report prepared by Bobby Cranford. That report is a forty (40) page report citing numerous deficiencies on the sidewalk repair project. Respondent requires that contractors employ english speaking superintendents at each work site to assist in communicating with its inspectors. Petitioner utilized superintendents who did not speak english and thereby created a language barrier making communication difficult with Respondent's personnel. Respondent had to monitor Petitioner's projects extensively and at a cost which increased the Department's overhead disproportionately when compared to other projects let to other district contractors. Based on a review of Respondent's work on Petitioner's recent contracts, no other contractors performing contracts in District I had a performance record as poor as Petitioner. When the awards committee made its decision to reject Petitioner's bid on the subject contract, it also relied on a memorandum from , Wally Clark, a District I attorney. In the memorandum it was concluded that Petitioner had subcontracted work to Hummell, Inc., a separate entity and that the required prior written approval of the subcontracting had not been obtained from Respondent. The investigation also revealed that the subcontractor, Hummell, Inc., had not been paid for its services (by Petitioner). An internal audit also prepared by Wall revealed that Hummell, Inc. was an unpaid subcontractor of Petitioner. The awards committee also considered allegations from Phillip Spears, a subcontractor of Petitioner, who had not been paid for work performed on Respondent's contracts. The committee also considers a newspaper article which stated that Petitioner was under investigation by local law enforcement officials for failure to pay subcontractors on the Interstate 75 project. Dennis Hall is the District Investigator for District I. Hall accompanied Wall, the author of the internal audit report, on investigations and interviews in compiling the audit report. One of the persons interviewed by Wall and Hall was Larry Zavitz. Zavitz was an inspector employed by Petitioner in excess of twenty- eight (28) years and had performed the inspection on Petitioner's sidewalk repair project under Contract E-1649. During the interview of Zavitz, he admitted to receiving a loan of $1,000.00 from John Hummell which Zavitz had not fully repaid at the time of the interview. Upon Zavitz admission of accepting the loan, he was asked and later resigned from the Department.
Recommendation Based on the foregoing, it is, hereby, RECOMMENDED that: Petitioner's protest of the rejection of its bid on Contract E-1706 be rejected and the Department enter its award of the subject contract to the second lowest responsible bidder, Simco, Inc. of Sarasota. DONE AND RECOMMENDED this 8th day of September, 1993, in Tallahassee, Leon County, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of September, 1993. COPIES FURNISHED: Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0458 Thornton J. Williams, Esquire General Counsel Haydon Burns Building 562 Suwannee Street Tallahassee, Florida 32399-0458 William H. Roberts, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458 Michael E. Riley, Esquire 106 East College Avenue Post Office Box 10507 Tallahassee, Florida 32302
Findings Of Fact (Because the Petitioner's findings of fact were not numbered, a number has been assigned to each paragraph beginning with the first paragraph of page 1). Partially adopted in findings of fact 5, 6, 8 and 9. The proposed finding that "the Petitioner continuously notified her employer of her medical condition by telephone" is rejected as misleading and not supported by competent substantial evidence. The proposed finding that the Petitioner was released on August 31, 1985 with physician's instructions to "go home and have complete bed rest" is rejected as not supported by competent substantial evidence. Partially adopted in findings of fact 4, 11, and 19. Matters not contained therein are rejected as misleading and/or a recitation of testimony. Covered in conclusions of law section. Rejected as legal argument. Partially adopted in findings of fact 4, 6, 7 and 15. Matters not contained therein are rejected as subordinate. Partially adopted in findings of fact 4 and 7. Matters not contained therein are rejected as subordinate. Partially adopted in finding of fact 10. Matters not contained therein are rejected as recitation of testimony. Adopted in findings of fact 11, 12, 13 and 14. RULINGS ON PROPOSED FINDINGS OF FACT, SUBMITTED BY THE RESPONDENT (None submitted)
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED THAT: The Department of Administration enter a final order re- instating Petitioner to her position as a toll collector at the Mathews Bridge toll facility in Jacksonville, Florida; and It is further Recommended that Petitioner's request for back pay and benefits from September 17, 1985 be DENIED. DONE and ORDERED this 21st day of March, 1986 in Tallahassee, Leon County, Florida. W. MATTHEW STEVENSON, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administration Hearings this 21st day March, 1986. COPIES FURNISHED: Charles G. Gardner, Esq. Department of Transportation Haydon Burns Bldg., M.S. 58 Tallahassee, Florida 32301-8064 Brenda Washington 28 West 28th Street Jacksonville, Florida 32206 Sharon A. Hood Staff Representative AFSCME, Florida Council 79 6308 N. Main Street Jacksonville, Florida 32208 Richard L. Ropel, Esq. Department of Administration 435 Carlton Building Tallahassee, Florida 32301 Kathryn L. Ward, Esq. 345 S. Magnolia Drive Suite F-21 Tallahassee, Florida 32301 Gilda H. Lambert Secretary Department of Administration 435 Carlton Building Tallahassee, Florida 32301 Augustus D. Aikens, Esq. General counsel Department of Administration 435 Carlton Building Tallahassee, Florida 32301 APPENDIX The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case.
The Issue Whether Respondent, Department of Transportation’s (“Department” or DOT”), notice of intent to award a contract to Intervenor, Archer Western De-Moya, Joint Venture (“AWD”), for a transportation project involving the design and reconstruction of federal and state roadways in Miami, Florida (“the Project”), is contrary to governing statutes, DOT’s rules, or the bid specifications; and, if so, whether the award is contrary to competition, clearly erroneous, or arbitrary and capricious.
Findings Of Fact Project, Parties & Participants Respondent, DOT, is the state agency authorized by section 334.30, Florida Statutes, to issue requests for proposals to solicit competitive bids for private-public (“P3”) partnership projects. The Project was located in District VI of the Department. Greg Schiess is the manager of the Strategic Initiatives Office for DOT. Mr. Schiess oversaw the Project and was the agency representative for DOT at the final hearing. Nadine Chinapoo was DOT’s procurement officer who oversaw the RFP process for the Project. The RFP had strict rules of contact between bidders and any DOT employee or officer. The Department designated Ms. Chinapoo as the “single contact and source of information” for the RFP. The Miami-Dade Expressway Authority (“MDX”) is a state agency created in 1994, authorized by Miami-Dade County, and funded through toll revenues. MDX has regional oversight of five expressways in Miami-Dade County, including State Road 836 (“SR 836”). On February 6, 2017, DOT issued the “Design-Build Request for Proposal for SR 836/I-395 from West of I-95 to MacArthur Causeway Bridge and I-95 Pavement Reconstruction and I-95 Southbound to SR 836 Westbound and SR-836 from West of NW 17th Avenue to Midtown Interchange (SR-836/I-395/I-95)” (“RFP”). The Department developed the RFP pursuant to section 334.30, Florida Statutes, which allows DOT to enter into a P3 to finance, design and build transportation construction and facilities. No one timely filed an objection to any of the RFP specifications. The RFP involves two contracts: (1) the DOT contract for federal interstates 95 (“I-95”) and 395 (“I-395”), and a portion of SR 836 leading to and from MacArthur Causeway Bridge; and (2) the MDX contract which involves another portion of SR 836 from Northwest 17th Avenue to the Midtown Exchange at I-95. A key component of the RFP was the replacement for “Bridge No. 8/9” of I-395, which would run east to west (“Signature Bridge”). According to the RFP, the Signature Bridge would take traffic over a portion of downtown Miami to and from the MacArthur Causeway. Ultimately, the winning bidder or design-build firm (“DB Firm”) would provide preliminary designs, coordinate design services with the Department to finalize the engineering and construction plans, and perform construction of the finalized designs. It would also need to self-finance the design and construction of the Project, because payment would be made by DOT into an escrow account and then disbursed to the selected DB Firm on periodic intervals. This form of payment was referred to as “gap financing.” BCC is a private civil engineering firm based in Florida specializing in roadway projects. The Department engaged BCC to advise and draft concept plans and portions of the RFP related to roadway design, roadway geometrics and temporary traffic control (also known as maintenance of traffic (“MOT”)). Staff from BCC also represented the Department in meetings with bidders as allowed by the RFP.4/ The Project Selection Committee (“PSC”) was made up of three members: Javier Rodriguez, Executive Director of MDX; Gerry O’Reilly, Secretary of DOT for District IV; and Dat Huynh, District Planning and Environmental Administrator of DOT for District VI. The PSC selected the Best Value Proposer (“BVP”) based on scores given for the bidders’ Technical Proposals, contract time, price proposals, and a passing grade for the bidder’s financial health. The PSC also met publicly at various times during the RFP process. The Technical Review Committee (“TRC”) was the group in the RFP process responsible for reviewing and scoring the Technical Proposal. The TRC was made up of four DOT engineers and one MDX engineer. The Technical Proposal was made up two volumes. Volume 1 was worth a total of 60 points and included criteria such as construction methods, MOT plans, and innovation. Volume 2 was worth up to 30 points, and addressed aesthetic criteria such as streetscapes, lighting and enhancements. The Aesthetic Review Committee (“ARC”) was the group assigned to review and pass acceptable Signature Bridge options. The ARC also was responsible for reviewing and scoring Volume 2 of the Technical Proposals from each bidder. There were originally five members: four non-DOT representatives from the local community; and Brian Blanchard, the DOT assistant secretary. Mr. Blanchard withdrew from the ARC prior to the scoring of Volume 2, when his duties at DOT increased after the DOT Secretary resigned. Each bidder could submit three bridge designs or options. The ARC members gave a “pass” or “fail” grade to each Signature Bridge option submitted. These pass/fail grades determined which proposals moved to the next phase of the RFP involving the technical aspects of the entire proposal. Although the ARC members also ranked each of the bidders’ options, these rankings were for “informational purposes only.” Leon Corbett, the Department’s finance manager for the RFP, was responsible for overseeing the final phase of the RFP process of evaluating the financial fitness of the intended DB Firm. Mr. Corbett was experienced in evaluating financial proposals submitted in response to requests for proposals, and specifically had experience in evaluating bidders for proposals involving P3s. Mr. Corbett and DOT staff evaluated the financial proposal of the highest scorer on a pass/fail basis. Petitioner, FAM, is a joint venture organized specifically to submit a response to the RFP. The corporate members of FAM are Fluor Enterprises, Inc. (“FEI”), Astaldi Construction Corporation and Munilla Construction Management, LLC (“MCM”). All three members of FAM are civil construction contractors that were prequalified by DOT to submit bids to the RFP. Hope Grumbles, FEI’s director of sales and infrastructure, served as the corporate representative for FAM at the hearing. AWD was also organized to submit a response to the RFP. AWD is composed of Archer Western Contractors, LLC (“Archer”), and the de Moya Group, Inc. (“de Moya”), both DOT- prequalified contractors. Ultimately, DOT issued a notice of intent that AWD had been chosen as the winning proposer or DB Firm. Kevin McGlinchey, the vice-president over Florida and the Caribbean for Archer, served as the corporate representative for AWD at the hearing. History and Groundwork for Project and RFP Planning for improvements to I-395 and the bridge to the MacArthur Causeway began in the early 1990s, but did not result in any renovations. Research on the project began again in 2004 with the beginning of a project development and environmental study (“PD&E”) and culminated in 2010 with the issuance of a Final Environmental Impact Statement and the Record of Decision.5/ The purpose of the PD&E study was to produce a recommendation for final designs and construction. Separate PD&E studies were done for the I-395 and SR 836 projects. The original PD&E premise was simply to replace the bridge on I-395, but that project did not move forward because of concerns that the bridge and the construction itself may have negative impacts on the area underneath and adjacent to the bridge, including Overtown, a historic black neighborhood located adjacent to I-395. At some point after the release of the PD&E studies, DOT created a Project Advisory Group which met numerous times until 2013. The Project Advisory Group consisted of representatives of numerous stakeholders in the road improvements, including governmental agencies and civic organizations from the local area. Meanwhile in 2010 and early 2011, BCC, on behalf of the Department, began developing the RFP language. Although it was not involved in the original I-395 PD&E, BCC reevaluated the PD&E for factors, such as environmental and socioeconomic impacts, traffic issues, and right-of-way requirements. These changes were incorporated in the concept plans and procurement language for the final advertisement requesting proposals for the Project. In 2013, a lawsuit filed against DOT in Miami-Dade County sought equitable relief relating to any bridge renovations by DOT. As a result, DOT agreed that any renovation or improvements by DOT to the I-395 interchange would include a “Signature Bridge” as part of the Project. In furtherance of this goal and to allow local input regarding the visual impact of the bridge on the area, DOT created an Aesthetic Steering Committee to review alternatives for the “Signature Bridge” and recommend a specific bridge design to DOT. Despite meeting numerous times, however, this committee was unable to reach consensus on any one specific design. The committee disbanded, but the concept of the committee’s role was incorporated in the RFP process in the form of the ARC. During this time, MDX also had plans to reconstruct portions of SR 836. DOT and MDX agreed to conduct the SR 836 renovations and the bridge replacement as part of the same project for convenience and to save resources. As a result, DOT partnered with MDX to conduct a multi-phased and comprehensive reconstruction project that would address the traffic and aesthetic concerns of the local citizens. The project would include three major components: (1) a “Signature Bridge”; (2) SR 836 renovations; and (3) I-395 renovations. Also as a result of the public’s concerns related to the visual impact of the Project to the surrounding areas, the Department developed an Aesthetic Manual (found at Joint Exhibit 3) for the Project. This manual focused on the Signature Bridge and area underneath the bridge. As explained in the Aesthetic Manual: [T]he signature bridge will be the crown jewel of the Project. The purpose of this structure is two-fold: to provide Downtown Miami with a contemporary infrastructure icon, and to improve the quality of the space below 1-395 by relieving it of obstructing piers and columns. . . . Irrespective of the ultimate design, the Signature bridge shall still adhere to [certain] constraints: [The] Signature bridge shall have a constant depth superstructure. The signature bridge shall be two fully independent bridges that are made to look like one form (e.g. twin basket handle bridges void of a visually unifying element will not be allowed). This structural autonomy is necessary because the EB and WB structures will be constructed sequentially, yet the stakeholders have insisted upon the appearance of one aesthetic entity. Concept Plans To provide bidders with an established set of design objectives (i.e., an idea of what it was looking for in the final product), DOT created concept plans that identified the project’s physical boundaries, the scope of the interstate reconstruction and proposed layouts. The RFP concept plans were developed and approved as part of the PD&E studies that were conducted for the I-395 and SR 836 projects prior to the issuance of the RFP. It is clear from the RFP itself and the testimony at the hearing that changes to the concept plans were anticipated and encouraged. A bidder’s improvements to the basic requirements and layouts to the concept plans could garner more points in the final bid score. The RFP described the purpose of concept plans. The Concept Plans have been developed to illustrate the work required for the Total Project. The Design-Build Firm may make use of the design in the Concept Plans as a starting point for the design. However, the Design-Build Firm is not limited to only the work identified in the Concept Plans but must stay within the constraints of the Department Commitments and the requirements of the RFP. Anthony Jorges, a civil engineer and the BCC consultant working with the Department on the roadway design, geometrics and MOT requirements of the RFP, gave clear and convincing testimony. He testified the concept plans were to serve as a launching pad for the proposals. [The concept plans are] essentially a starting point for the design-build teams. [I]t really is a conceptual level, about a 30 percent level design, but it gives the teams a point to start. It by no means is final or unmodifiable. It’s just a starting point . . . a baseline to start off with. No one timely filed any protest of the concept plans. RFP Timing and Process The procurement process took place over a year, from the date of advertisement to the selection of the DB Firm. The RFP process was broken down into four phases. Phase I: Short Listing Phase II: Aesthetic Signature Bridge Submission Pass/Fail Phase III: Technical Proposal Submissions and Scoring Phase IV: Price Proposal and Financial Proposal Submittals Although addressed in detail below, in summary, prequalified bidders were first required to submit a letter of response with specific preliminary information about the bidder. DOT then created a shortlist of bidders based on review of these letters. Each shortlisted entity was then given the opportunity to submit Aesthetic Signature Bridge Proposals. Each bidder that had a passing Aesthetic Bridge submission was permitted to submit a Technical Proposal and Financial Proposal. After the Technical Proposals were scored, the scores were announced along with each bidder’s price proposal and proposed contract time. After getting a pass grade on its financial proposal from the Department, the PSC selected the BVP. Phase I In Phase I, each proposer was to provide DOT a “Letter of Response” with general information, such as the proposer’s past projects and résumés of designated key staff positions. Specific to this protest, bidders were to designate a bridge architect and engineer of record for the Signature Bridge. Each timely Letter of Response submitted to the Department was to be evaluated on specific criteria by the PSC. DOT would then post a shortlist of bidders authorized to submit proposals. Petitioner and Intervenor submitted a Letter of Response and the PSC selected both for the shortlist, thereby advancing both to the second phase of the RFP process. Phase II Each proposer that was shortlisted provided a draft submittal of its Signature Bridge design or design options. These drafts were vetted by DOT through meetings that allowed the proposers and the Department to discuss any questions or concerns either had about the draft proposals. No members of PSC, TRC or ARC attended these “vetting” meetings; the meetings were solely intended to provide feedback and answer questions between DOT staff and the proposers. After the “vetting” meetings, each shortlisted proposer submitted up to three final Signature Bridge options to the ARC. Each ARC member then gave each option a “pass” or “fail” grade. If a proposer submitted more than one option, the ARC members ranked that proposer’s options by preference. These grades and rankings were provided to the PSC for review. To move to the third phase, a proposer must have received at least one “pass” rating. The RFP specifically provided the ARC’s rankings of individual options “are purely for informational purposes only, and will have no direct impact on the Pass/Fail decision or on the evaluation of the Proposer’s Technical Proposal.” On August 19, 2016, DOT issued the “Aesthetic Bridge Proposals Pass/Fail Posting Notice” indicating that the PSC had reviewed the ARC’s rankings. As allowed by the RFP, the PSC determined that the bidders that received three out of five passes would move on. AWD’s Signature Bridge proposal was a fountain-like design with multiple arches sprouting from a unified point. FAM’s Signature Bridge design consisted of two cabled structures that were similar, but inverted. Each had an arm with a rotating disk extending into the air. Ultimately, the PSC approved these submissions from FAM and AWD to proceed to the third phase of the RFP process. Phase III Whereas Phase II focused on the Signature Bridge, Phase III involved the Technical Proposals from the bidders. Each Technical Proposal was made up of a Technical Volume (Volume 1) and Aesthetic Volume (Volume 2). The TRC members reviewed and scored both volumes; the ARC members only scored Volume 2. According to the RFP, the technical scores were based on an “adjectival scoring system” that required each of the TRC and ARC members to review the volume or volumes of the proposals he or she was assigned and give each section an “excellent,” “very good,” “good,” “fair,” or “poor.” These descriptive ratings were later converted to a numerical value and announced at the public meeting held on April 24, 2017, to open the contract time and price proposals. Ms. Chinapoo provided the Technical Proposals, the individual scores of the evaluators, and a spreadsheet compiling all the scores to the PSC for review prior to the April 24 public meeting. Unlike the other bidder’s proposals, AWD’s Technical Proposal included a viaduct made up of two by-pass lanes in each direction on an elevated freeway along the center of the existing SR 836. The viaduct had construction and safety advantages over traditional “parallel lane” formats and would eliminate interaction between I-95 traffic and special event traffic in downtown Miami. Because this was a novel concept not addressed in the RFP or concept plans, AWD was required to get DOT’s approval before submitting the preliminary designs. After the TRC and ARC members reviewed the Technical Proposals, AWD received a 53.980 out of 60 points on Volume I and 24.389 out of 30 points on Volume II; FAM received 50.180 points for Volume I and 28.656 on Volume II. ATC Process Bidders were allowed to obtain permission to deviate from the concept plans and RFP requirements in certain aspects. The RFP outlined a process for approving requests for an Alternative Technical Concept (“ATC”), which included any deviation from a component of the technical requirements, or any proposed material or technology not addressed in the RFP. The RFP schedule anticipated that bidders would submit their ATC requests after Phase I and, if approved, incorporate them in the Technical Proposals submitted in Phase III. The purpose of the ATC process was to allow “innovation, flexibility, time and cost savings on the design and construction of Design-Build Projects while still meeting the Department Commitments.” The ATC process included one-on-one discussion meetings between the Department (or its representatives from BCC) with bidders “to describe proposed changes to supplied basic configurations, Project scope, design criteria, and/or construction criteria.” The purpose of these one-on-one ATC meetings was to discuss the ATC proposals, answer questions that the Department may have related to the requested deviations, review other relevant information, and establish whether the ATC proposal met the requirements for approval when possible. Representatives from the bidders and/or their engineers or designers, and DOT staff were involved as needed to provide feedback on the ATC. None of the TRC, ARC, and PSC members attended ATC meetings or participated in the ATC process. An ATC was deemed worthy of approval if the concept suggested was equal to or better than the existing requirements of the RFP, as determined by the Departments. ATC requests, which reduced scope, quality, performance or reliability, would be rejected. The Department retained discretion to approve or deny an ATC without a need to state justification. Once approved, an ATC was treated one of two ways: with an addendum to the RFP so all proposers were aware of the deviation; or (2) without an addendum so only the proposer that submitted the ATC would be permitted to utilize the approved ATC in its design. Not all concept plans or RFP requirements were modifiable; some could not be changed through an ATC. Specific to these proceedings, the RFP had “specific ATC restrictions” (or what the parties referred to as “nonmodifiables”) on the following requirements: Minimum basic number of lanes [for I-395 and I-95] as shown in Attachment A-33. All Signature Bridge components shall be part of the structural system that carries bridge Dead Load (DL) and Live Load (LL). Minimum basic number of lanes [for SR 836] as shown in Attachment MDXA-02. Minimum widths of mainline lanes and ramp lanes [for MDX]. Preliminary Plans and Confirmation Letter During Phase III, each remaining bidder was required to submit a technical proposal in which the bidder provided design concepts with preliminary plans. The RFP did not seek proposals of final designs that were ready for construction. Rather, as explicitly stated, the actual preparation of final plans and designs was to be part of the contract work being solicited, and would be performed after contract execution. As was clear from the RFP and testimony at the hearing, the goal of the procurement was not for the award recipient to provide final signed and sealed plans. Instead, it would provide plans as deliverables in the contract, submitted to DOT engineers for review, comment, and approval. More precisely, the RFP and contract required the winning bidder to submit--during contract performance--60- percent plans (plans that are 60-percent complete) for DOT comment and approval, followed by 90-percent plans for further DOT review. Only after the 90-percent plans were finalized, were they to be signed, sealed, and submitted to DOT for construction. In other words, the final design plans were to be developed by the DB Firm’s designers in collaboration with DOT’s (and MDX) staff as part of contract performance and deliverables--not as part of the procurement itself. Because of the unique fluid nature of the proposal drawings, the RFP provided that DOT may waive minor irregularities in proposals as follows: Waiver of Irregularities The Department may waive minor informalities or irregularities in Proposals received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other Proposers. Minor irregularities are defined as those that will not have an adverse effect on the Department’s interest and will not affect the price of the Proposals by giving a Proposer an advantage or benefit not enjoyed by other Proposers. Any design submittals that are part of a Proposal shall be deemed preliminary only. Preliminary design submittals may vary from the requirements of the Design and Construction Criteria. The Department, at their discretion, may elect to consider those variations in awarding points to the Proposal rather than rejecting the entire Proposal. In no event will any such elections by the Department be deemed to be a waiving of the Design and Construction Criteria. Because the proposal plans were merely preliminary, DOT required each bidder to submit a “Written Confirmation Letter” (“Compliance Letter”) stating that regardless of the preliminary plan, if chosen as the DB Firm, it would comply with and be bound by all requirements in the contract documents during contract performance. The winning bidder was required to fully comply with the Design and Construction Criteria and other RFP requirements for the price bid, regardless of the preliminary designs or if the proposal was based on a variation. AWD and FAM each submitted Compliance Letters. Phase IV and Selection of AWD as BVP In Phase IV, FAM, AWD, and two other bidders submitted their price proposal and total project calendar days. During the public meeting on April 24, 2017, price proposals from each proposer were opened. The price proposals also included each proposer’s total estimated contract time. Based on the formula set forth in the RFP, each proposal received a score for its price proposal. The members of the PSC were not involved in evaluating the price proposals or the contract time. Instead, the prices and contract times were evaluated by DOT staff, who were to alert the PSC members to issues with a proposer’s price or contract time. The record established DOT staff were not concerned and did not alert the PSC members to any issues. Both AWD and FAM received a score of 4.99 points for their price proposals. AWD proposed a total contract time of 1,460 days; FAM proposed a total contract time of 1,825 days. The RFP provided the formula for scoring the proposed contract times as: 5 x (a/b), where a = lowest number of calendar days proposed by any bidder; and b = number of calendar days proposed by that bidder. Using this formula, AWD received 5.00 out of 5 points; and FAM received 4.00 points. The total scores were then noticed by the Department. The next step in this phase was for the Department to evaluate the financial fitness of the intended award. The Department’s finance manager for the RFP, Leon Corbett, and DOT staff evaluated the financial proposal of the highest scorer on a pass/fail basis. As noticed in the RFP, the financial review portion for this RFP was to occur after the April 24 public meeting announcing the technical scores and price proposals. The RFP states that the “PSC shall select the BVP for the Total Project.” It also states that “[t]he Proposer with a responsive Proposal will be evaluated by the PSC for award of the I-395 Agreements as the Best Value Proposer as set forth in this RFP.” Finally, the RFP provides as follows: The PSC will review the evaluations of the Technical Proposal and the scores for the Proposed Contract Time and Scored Price Proposal for each Proposer and make a final determination of the highest score. The PSC has the right to correct any errors in the evaluation and selection process that may have been made. The Department is not obligated to award the I-395 Agreements and the PSC may decide to reject all Proposals. If the PSC decides not to reject all Proposals, the I-395 Agreements will be awarded to the Proposer determined by the PSC to be the Best Value Proposer. Before the scheduled PSC meeting on May 12, 2017, Ms. Chinapoo provided each PSC member with the technical proposals submitted by the vendors, the individual scores of the evaluators, and a spreadsheet compiling the scores. On May 12, 2017, the PSC met to consider the scores, as well as DOT staff’s evaluation of the AWD financial proposal. The PSC unanimously determined that AWD was the “Best Value Proposer” based on the highest technical score, the best value proposer and the best contract time. One PSC member, Mr. Rodriguez, testified that before the May 12 meeting he spent about 12 hours reviewing the material before making the final decision as to which bidder would be BVP. He also testified that he considered AWD the BVP because “they had the best score, after they were scored, they had a compliant price, and they had the best time.” Mr. Rodriguez indicated he would have asked any questions at the meeting had he seen anything unusual, untoward, or problematic about the scoring of the proposals. Mr. Rodriguez noted there was one anomaly in the technical scores of one ARC member who preferred the FAM’s proposal. Whereas the other members of the ARC gave AWD scores of 26.2, 24.6, and 17.80 out of 30 points for Volume 2, John Richard gave AWD a score of 7.20 points; while awarding FAM a nearly perfect score of 29.300. Mr. Richard awarded the other two proposals (not FAM or AWD) 9.00 and 2.5 points. Mr. Rodriguez considered, but was not concerned about Mr. Richard’s individual scores because Mr. Rodriguez felt the scores were based on “aesthetics” and just “an opinion” about which proposal Mr. Richard thought offered the prettier bridge. There is no evidence establishing the PSC failed in its responsibilities or did not follow the RFP process in selecting the BVP as described in the RFP. After the PSC determined the intended award, the Federal Highway Administration was required to concur, the DB Firm was required to submit final financial documents, and the parties would then execute the contracts. DOT’s Scoring In the Amended Protest, FAM asserts the bid award should be rejected because the Department used the wrong methodology for assigning the technical scores for Volume 2. DOT took all of the reviewers’ scores, added them together and divided them by the number of reviewers. FAM claims that correct methodology would be to take the ARC members’ individual scores and average them to one score (x); take the TRC members’ individual scores and average them to another score (y); and then average x and y to arrive at a technical score for Volume 2. Although the RFP was specific as to what criteria the ARC and TRC members were to use in grading the technical proposals, and how those grades were converted to numbers, it was silent as to how the individual reviewers’ scores would be combined to come up with one score for Volume 2. As explained previously, all members from the TRC and the ARC used an “adjectival scoring system” that required individual evaluators to rate portions of the proposals as “excellent,” “very good,” “good,” “fair,” or “poor.” Consistent with the RFP, non-reviewers (Mr. Schiess and a DOT in-house attorney) assigned numerical equivalents to the adjectival scores. These individual numerical conversions were delivered to Ms. Chinapoo, who kept them secure until the scores of all proposers were presented in a spreadsheet during a public meeting on April 24, 2017. As established by the evidence at the hearing, typically in DOT procurements there are technical reviewers scoring the technical part of proposals. In that situation all of the reviewers’ scores are averaged (i.e., added all together and divided by the total number of reviewers). Unlike other procurements that are based only on technical components and price, this RFP involved an additional component relating to aesthetics. Therefore, in this RFP process there were two separate scoring committees, ARC and TRC, each starting out with five members each. Mr. Rodriguez testified the method used by DOT-– calculating the final score by adding up the scores from the individual reviewers and then dividing it by the number of reviewers--was common practice. Theoretically, under this typical method, for the Aesthetic volume of the Technical Proposals, DOT would have added the scores from each of the ten committee members and divided by ten to reach the technical score. During the course of the procurement, however, one of the members, Brian Blanchard (the sole DOT representative on the ARC) resigned from the committee, and was not replaced. The RFP is silent as to how the absence of a committee member should be treated. DOT addressed the reduction in ARC membership by notifying the proposers that Mr. Blanchard was no longer on the ARC; and explaining the “scoring of your Technical Volume 1 will be done by the five-member Technical Review Committee (TRC), who will also score your Aesthetic Volume 2, along with the four remaining members of the ARC.” It did not clarify how the individual scores would be used to arrive at a total score. As reflected in Joint Exhibit 46, DOT converted the adjectival description provided by each ARC and TRC member and then calculated the scores of each of the reviewers to reach a total sum, which was then divided by the number of reviewers for each volume of the technical proposal. The language in DOT’s notice announcing Mr. Blanchard’s departure from the ARC is ambiguous. The fact, however, that the Department did not provide a formula (as it did for scoring the price proposal or contract time scores) and that it mentioned the “members,” and not the committees, supports the use of the typical averaging methodology, averaging scores of all nine evaluators. As Mr. Schiess testified, this is the way an evaluator’s scores would be treated in any other procurement. Q.: Do you know who made the decision on how to average those numbers? A.: The decision to average the scores has been something the Department has been doing. That’s just common practice. Q.: And what is the common practice? A.: To average the scores of the evaluators. Q.: Just take a straight average, add up all the evaluators and divide the scores by the number of evaluators? A.: Correct. Similarly, the testimony of the PSC members established this was common practice. Mr. Rodriquez testified that he has served on numerous DOT project selection committees over the years and that scores of evaluators are typically averaged. Dat Huynh, another PSC member, described the process as “regular averaging” as “just combining the number and dividing by the number of people that were in participation.” The testimony established any contrary method would need to have been clearly spelled out in the RFP. At the May 12 public hearing, FAM’s representatives raised the issue of the scoring and claimed it defeated the public’s role in the process. The evidence, however, established the public did have a key role in the selection of the Signature Bridge. The ARC’s role was to provide public input. In addition to scoring Volume 2, the ARC evaluated the Signature Bridge design proposals on a Pass/Fail basis and served as the “gate-keeper” keeping any designs it did not approve from moving further in the process.6/ John Morris, president of the third-place proposer, also indicated at the May 12 public meeting that based on his experience the process was not unusual: My team came in third in that process. And I’m not really here representing my joint venture team. I’m really more here as someone who has done a great deal of work with the Department of Transportation and bid on a lot of design-build projects over the last 20 years, and as far as I’m concerned, the DOT followed the process that they laid out in the RFP. Additionally, a plain reading of the RFP indicates it was the weight of the individual ARC members, not the ARC as a whole, that was valued. For example under the section titled “Aesthetic Signature Bridge Proposals Pass/Fail,” the RFP stated in relevant part: Each ARC member will independently pass or fail each option submitted. Each ARC member will also rank the options provided by a Proposer against the other options provided by the same Proposer against the other options provided by the same Proposer. * * * Although the ARC members will rank the different options . . . these rankings are purely for information purposes only, and will have no direct impact on Pass/Fail decision or on the evaluation of the Proposer’s Technical Proposal. * * * [T]he PSC will recalculate the options based on “passing” being lowered to three (3) out of five (5) passes from the ARC members. (RFP at 20)(emphasis added). There is also support for using individual scores in the RFP section titled “Final Selection Process,” which provides that at the public meeting where the price proposals are opened, “the Department will announce the adjectival scores for each member of the TRC and ARC, by category, for each Proposer.” (emphasis added). This interpretation makes sense given that the previous form of the ARC, the Aesthetic Steering Committee, could not come up with a consensus regarding a style or appearance for the Signature Bridge. Moreover, given that it was the DOT’s representative and not a public member that resigned, it cannot be said that the method used by DOT undermined the public’s participation in the process. There is no evidence that the method put forth by FAM is supported by the RFP, any rules or by any industry or departmental precedent; nor is there evidence that the ARC and TRC were to contribute to the scoring process equally. There is no evidence that the averaging methodology used by DOT is contrary to any statute or rule. The Department’s deriving the total score for Volume 2 by averaging all the evaluator’s scores was not clearly erroneous, contrary to competition or arbitrary and capricious. AWD’s Contract Time As stated previously, the RFP provided the formula for scoring the proposed contract times as: 5 x (a/b), where a = lowest number of calendar days proposed by any bidder; and b = number of calendar days proposed by that bidder. Additionally, the RFP noted: “The Proposed Contract Time should incorporate and set forth an aggressive but realistic time frame for the required completion of the Total Project.” According to the RFP, any time more than 1,825 days would be nonresponsive. AWD’s Proposed Contract Time was 1,460 days; FAM’s Proposed Contract Time was the maximum provided by the RFP-– 1,825 days. This comes out to be a 365-day or a one-year difference. As a result, using the formula in the RFP, AWD achieved a score of 5.0 out of 5 points for its contract time, and FAM achieved a score of 4.0 points. FAM challenges AWD’s contract time, claiming it was not realistic. FAM argues the 1,460 days proposed by AWD was unrealistic and insinuates this number was done solely to manipulate the scoring. AWD counters, not only was it realistic, it was aggressive, as requested by the RFP. There is no evidence of collusion or that AWD knew the individual technical scores before it came up with its proposal or that there was any kind of unethical or improper conduct relating to the contract time. Rather there was competent and convincing evidence that AWD’s shorter time proposal was realistic given its resources and experience. Kevin McGlinchey, who was involved in developing AWD’s contract time, testified the calculation of AWD’s contract time was an on-going process and was not finalized until a short time before the price and time submission was due. The evidence established AWD’s joint members had previous experience with DOT and P3/design-build projects. In addition, AWD was a very large contractor in the state with access to adequate local labor. Archer employs 1,300 workers in the area; de Moya employees up to 300 workers in the area. For example, depending on equipment availability AWD could have five eight-hour shifts, five ten-hour shifts, or six eight-hour shifts; or AWD could increase the number of crews working each shift. This access to labor afforded AWD the ability to increase its crews and shifts, thereby reducing the length of total work time. AWD also reduced its contract time over the procurement process by changes in its construction plan that allowed it to overlap construction phases and work on more than one segment of the Project concurrently, instead of running consecutively as originally anticipated when it submitted preliminary design documents and MOT plans. Mr. Schiess testified that he and a DOT bridge expert reviewed AWD’s Proposed Contract Time to determine whether it was realistic. This review was conducted between the time the scores were publicly released on April 24, 2017, and the PSC meeting on May 12, 2017. Mr. Schiess testified “based on our experience in Florida and other projects [with] these contractors [Archer and de Moya], that [1,460 days] was not an unrealistic time.” Because there was competent evidence AWD had the resources and a plan to complete the Project in the 1,460 days, its contract time proposal was aggressive, realistic, and responsive to the RFP. AWD’s Financial Proposal FAM also challenges the “Pass” grade DOT awarded AWD on its Financial Proposal. It argues (1) DOT failed in not reviewing FAM’s financial proposal; (2) AWD’s original financial proposal was non-responsive; and (3) DOT improperly allowed AWD to supplement information to its original financial proposal. Section VI, M., of the RFP addresses the financial requirements of the RFP and the documentation that must be provided by bidders. The financial evaluation is a two-step process with an initial Financial Proposal to be submitted on the due date for the price proposals. After the PSC chose a BVP, Mr. Corbett and his staff was also responsible for reviewing a final letter of commitment or credit provided by the DB Firm, which was due 15 days following the Department’s posting of its Intent to Award. Mr. Corbett and his staff conducted the initial financial review for this procurement after the public meeting, announcing the technical scores, price proposals and contract times. The Department was to give the highest scoring bidder either a pass/fail grade, which was relayed to the PSC to make its final decision. During this period, the RFP specifically allowed Mr. Corbett to obtain additional financial information. It states: The Department’s evaluation of a Financial Proposal is solely for the benefit of the Department and not for the benefit of the Design-Build Firm, any entity related thereto, the public or any member thereof, nor create for any third party rights. . . . The Departments evaluation of each Financial Proposal will be on a pass/fail basis. Analysis of the Design-Build Firm’s Financial Proposal by the Department will include, but not be limited to the following: * * * d. Review of the Lender Letter(s) of Commitment or Demonstration of Line(s) of Credit to determine if it meets the financing needs established in the Project Financial Plan. * * * The Department reserves the right to request any additional information or pursue other actions required to meet its obligations to complete the financial due diligence. (RFP at 70.) As an initial matter, although Mr. Corbett did not conduct a concurrent pass/fail review of the financial proposal submitted by FAM (or the other bidders who made it to Phase IV), nothing in the RFP required the Department to review and assess the financial proposals of all the bidders. FAM asserts by failing to have its financial proposal evaluated, the PSC was deprived of the option of awarding the contract to FAM. However, if the PSC had opted not to award the contract to AWD despite its status as the highest scoring bidder, nothing in the RFP would have precluded the Department from initiating a pass/fail review of the FAM financial proposal at that point to assess FAM’s financial viability for the contract award. The Department did not err in evaluating only the highest scoring bidder, AWD. Regarding AWD’s responsiveness to the financial requirements of the RFP, AWD timely submitted its financial proposal to DOT on August 24, 2017, which included a preliminary letter of commitment (“PLOC”) from BankUnited. According to the RFP, the PLOC was required to contain the following information at a minimum: The lender was interested in providing financial support for the project; The lender had reviewed the financial requirements of the RFP; The amount of financial support the Lender intended to provide (no minimum amount was required by the RFP); Any special conditions to the PLOC. After AWD was ranked as the highest scoring bidder, Mr. Corbett and his staff conducted DOT’s initial review of AWD’s financial proposal. There is no dispute that DOT had the right to request any additional information or pursue other actions required to meet its duty of due diligence. The evidence established the original financial proposal met the minimum requirements of the RFP, but DOT requested additional assurances and clarification regarding its PLOC, which AWD provided. As Mr. Corbett explained, AWD’s Financial Proposal was responsive to the RFP requirements, but he had questions relating to the PLOC. Q.: And so this determination of responsiveness was made after you had the original financial proposal, Archer Western- de Moya, the first supplemental proposal and a second supplemental proposal that we just went over, correct? A.: So I mean, there is responsiveness and there is pass/fail, and I think that’s where we have to explore a little bit more. The letter states responsive, meaning it meets the minimum requirements. And then there is the pass/fail, which I don’t know why I didn’t address pass/fail, why I didn’t say it’s a pass in the letter. But the pass came at that point, too, yes. * * * So my answer is it wasn’t an additional proposal, it was--the original proposal was what was evaluated for responsiveness. We asked for additional assurances to make sure they were headed towards a path of getting the resources necessary to finance the project. So the determination was made after receiving all that information. It is evident on the face of the BankUnited PLOC that it is responsive, as it complies with the following minimum RFP requirements. BankUnited confirmed “its interest in providing financing” for the project. BankUnited stated it “has taken careful consideration to review and understand the financial elements of the Project.” BankUnited specified it was “prepared to provide a credit facility up to” $125 million; and the $125 million credit facility consists of $75 million from BankUnited and another $50 million from other participating banks. It is this reference to “other participating banks” that triggered Mr. Corbett to request further information. Attached to the PLOC was a term sheet from BankUnited that sets forth the conditions for its $125 million credit facility. Although FAM contends that the BankUnited PLOC is nonresponsive because BankUnited is only committing to provide $75 million of the $125 million credit to AWD, the evidence at the hearing established BankUnited was proposing to provide a single credit facility totaling $125 million, some of which BankUnited may obtain through group or a “pool” of lenders. The financial proposal was that BankUnited would be the lead arranger of multiple banks participating in the “lending pool.” Nothing in the RFP prohibited this type of “pool,” and the testimony at the hearing established DOT has accepted this kind of loan structure in the past. Where a single credit facility in the form of a loan pool is being proposed, there is nothing in the RFP that precluded BankUnited, as the lead arranger, from submitting the PLOC on behalf of all of the lenders that are or would be participating in the credit facility. Regardless, even if BankUnited’s PLOC is treated as offering a credit facility in the amount of $75 million rather than the full $125 million, this does not render the AWD financial proposal nonresponsive since the RFP merely requires that the PLOC state the “amount the Lender intends to lend,” and does not require what amount that should be. The RFP only states that the commitments “should meet the required amount [of gap financing] identified in the Project Financial Plan.” Obviously, the goal was to ensure the winning bidder had the ability to secure preliminary commitments equaling the amount it may have to put forward for completion of the Project because DOT would be making period payments, but not until after the DB Firm had incurred the expenses. Given BankUnited’s PLOC meets the minimum requirements of the RFP, AWD’s financial proposal was responsive. Moreover, the RFP allowed DOT to look beyond the bare minimum requirements of the RFP to obtain a higher level of assurance before finalizing a “passing” grade. Mr. Corbett also wanted the information in anticipation of questions that the PSC members may have. Specifically, the evidence established that on April 25, 2017, Ms. Chinapoo’s requested AWD to provide additional information regarding the proposed pooling loan being offered by BankUnited. In particular, Mr. Corbett sought “additional assurances” that BankUnited would be able to obtain the balance of the “pool” financing from other participating banks. On April 27, 2017, AWD responded to DOT’s request for additional assurances. In this response, AWD reaffirmed that BankUnited was committed to provide the Final Letter of Commitment that was required under DOT’s RFP. Because AWD’s compliance with the request for information was provided prior to the agency’s announcement that it intended to award the contract to AWD, these additional documents did not violate section 120.57(3)(f). On April 28, 2017, AWD also confirmed to DOT that it had taken steps toward finalizing the $125 million pooling credit facility described in the BankUnited PLOC. AWD also provided another PLOC from Private Bank indicating Private Bank also had an interest in participating in the BankUnited credit facility. Private Bank’s PLOC proposed that it would participate in BankUnited’s credit facility (rather than offering its own credit facility) and that its proposed $50 million loan to the $125 million pool would be the same as the conditions set forth in BankUnited’s term sheet. AWD’s April 28 response also advised that it was continuing to explore the possibility of having BankUnited provide a credit facility for the entire $125 million in gap financing needed. The details regarding this alternative credit facility were described in a letter from BankUnited that was attached to AWD’s April 28 response. Mr. Corbett admitted he considered the additional information received from AWD before announcing his final decision to “pass” the AWD financial proposal; and this information solidified his decision to give AWD a passing grade. Although hypothetically it is possible that had AWD provided different information, Mr. Corbett would have not been assured and may have reached a different result, this is not evidence of an error. Rather it is the essence of conducting “due diligence.” It is also true the additional information BankUnited provided included information that was not contained in AWD’s April 24 financial proposal. Based on this, FAM argues that the April 27 and April 28 responses constitute modified or amended financial proposals that were submitted after the RFP’s financial proposal deadline in violation of section 120.57(3)(f). However, FAM’s position must be rejected for several reasons. First, the RFP expressly authorized DOT “to request any additional information or pursue other actions” in furtherance of its financial due diligence. This clearly is broad authority that does not limit DOT’s inquiry to information that merely clarifies the financial proposal. Having failed to challenge this “due diligence” language in the RFP provision within the time permitted by section 120.57(3)(b), FAM has waived any objection to DOT’s use of this provision. Further, in both its April 27 and 28 responses, AWD reaffirmed that it was prepared to move forward with the BankUnited credit facility proposed in AWD’s April 24 financial proposal. Although AWD’s April 28 response included information from Private Bank, this information did not propose a new or different credit structure, it simply provided additional information regarding the pool structure expressed originally by BankUnited. Because the BankUnited credit facility indicates that there would be other lenders participating in its credit facility, the identification of Private Bank is consistent with, rather than amending or modifying, the financing plan presented in AWD’s financial proposal. Again, the purpose of the Financial Proposal and PLOC was not to obtain a final commitment from the DB Firm to a particular financing arrangement with a particular lender. Instead, the RFP only required the proposer to present its “preliminary” or possible financing plans so that DOT could evaluate the likelihood that the final award would go to a proposer that had the financial resources necessary to finish the project on time. Only after the contract was awarded would AWD be required to present DOT with its final financing plan in the form of a final letter of commitment. Nothing in the RFP required that this final financing plan be identical to the preliminary financing plan that was presented in AWD’s initial Financial Proposal. As such, the Department’s request for and consideration of the information from AWD regarding the BankUnited PLOC and the pooling credit structure did not violate section 120.54(3)(f), and was not clearly erroneous, contrary to competition or arbitrary and capricious. FAM also argues the Preliminary Term Sheet (“PTS”) attached to the BankUnited PLOC conflicts with the RFP, which specifies the circumstances under which money paid under the proposed contract may be assigned to a lender as security for a loan. The RFP provision at issue, referred to by the parties as the “Assignment Clause,” states in relevant part, as follows: Reimbursement shall be made to the Design- Build Firm by warrant mailed to the Project Specific Escrow Account [“PSEA”] using a unique vendor number sequence. The Design-Build Firm may, with the express written consent of the Surety(ies) and the Lender(s) Financier(s), sell assign or pledge any monies paid into the Project Specific Escrow Account by the Department in favor of third parties and including but not limited to the Design-Build Firm’s Surety(ies) and Lender(s)/Financier(s); however, any such sale, assignment or pledge must only attach to payments made by the Department after such funds have been paid by warrant mailed to the Project Specific Escrow Account, and no sale, assignment or pledge of any receivable from the Department is authorized nor will be permitted by the Department. (RFP at 63)(emphasis added). AWD submitted with its Financial Proposal the BankUnited PLOC, which had an attachment with the following relevant language: Seller [AWD] proposes to sell the right of certain future [DOT] payments . . . to one or more Purchasers in order to finance the Project. As established by Mr. Corbett and Department e-mails, the intent of the Assignment Clause was to make “each [contract] payment payable to the vendor/contractor executing the agreement.” In this regard, the RFP treats the deposit of funds into the PSEA as payment to the contractor. The assignment is permitted under the RFP’s Assignment Clause if AWD’s assignment of a contract payment to a lender does not divert DOT’s payments away from the PSEA to BankUnited. In other words, there is no violation if the funds continue to be deposited into the PSEA. If, however, the assignment gives BankUnited the right to receive payments from DOT before the payments are mailed to the escrow account, it violates the RFP’s Assignment Clause. There is no dispute that the BankUnited PTS purports to assign certain rights held by AWD to the BankUnited as collateral for the proposed credit facility. The terminology used to describe the assignment is non-specific and creates ambiguity as to what the particular right is that is being assigned or sold. For instance, there is language in the PTS indicating that AWD is selling or assigning its “right to payment from DOT” without describing what that right is. In order to know what “right to payment” is being assigned, it has to be determined what right to payment AWD would actually have under its DOT contract since AWD cannot sell or assign contract rights that it does not have. See Cole v. Angora Enters., Inc., 403 So. 2d 1010 (Fla. 4th DCA 1981). As established by the RFP and testimony at the hearing, AWD will have no right under the DOT contract to receive payments directly from DOT; rather, payments from DOT will first be deposited into the PSEA, which will then be available for disbursement to the DB Firm. Because AWD will have no right to direct payment from DOT (as opposed to indirectly through disbursement from the PSEA), AWD cannot assign or sell a right to direct payments from DOT to any lender, including BankUnited. Stated differently, the only “right to payment” that AWD can assign is its right to payment from the PSEA. Moreover, the plain meaning of the PTS establishes AWD does not intend to assign or sell to BankUnited the right to receive payments from DOT before the payments are deposited into the Project Specific Escrow Account. The PTS states as follows: The Seller [AWD] shall establish a project specific escrow account (the “Project Specific Escrow Account”) with the Escrow Agent. All payments payable by DOT under the Department Contract will be deposited into the Project Specific Escrow Account. (emphasis added). Consistent with this directive, the PTS requires the parties, including BankUnited, to execute the “DOT Project Specific Escrow Account Form” as part of their financing transaction. As established by the Department’s exhibits, the purpose of DOT Project Specific Escrow Account Form, which must be signed by both the bidder and lender (or in this case AWD and BankUnited), is to “irrevocably” request, authorize and direct DOT “to process, issue and transmit any and all future payments otherwise payable directly to [the DB Firm] to now be processed, issued and transmitted using DB Firm’s Project Specific Escrow Account . . . in lieu of DB Firm’s regular vendor account. . . .” This irrevocable request to DOT would be made in the name of AWD as the DB Firm contracting with DOT. As the lender, BankUnited’s signature on the form would indicate its consent and agreement “to be so bound by the entirety of the terms of [AWD’s] Request for Specific Escrow Account ” In other words, by signing this form, BankUnited will be agreeing to be bound by AWD’s irrevocable request to have all DOT payments deposited into the Project Specific Escrow Account. This means that, in accordance with the RFP’s Assignment Clause, BankUnited will be irrevocably agreeing not to receive payments from DOT before payments are deposited into the Project Specific Escrow Account. The arrangement between AWD and BankUnited does not violate the Assignment Clause and is, therefore, responsive. AWD’s Technical Proposal FAM challenges a number of aspects of AWD’s technical plan as being non-responsive to the RFP. Specifically, it claims AWD’s proposal violates the non-modifiable requirements for the number of lanes on certain portions of the Project and the lane width requirements. Basic/Continuous Lane Requirements for I-395 (Attachment A-33) As described earlier, AWD made substantial changes to the RFP’s concept plans for I-395 and SR 836 by proposing a two- tiered road formation made up of a two-lane viaduct on an upper level and a collector road system on the lower level. In order to pursue this design, AWD submitted an ATC proposal which was eventually approved as “ATC 12C”. The proposed viaduct would have two continuous lanes in each direction between the two major highway systems, SR 836 and I-395, without being impeded by local SR 836 traffic. The local traffic would be carried on a lower roadway or Collector- Distributor (“CD”) road underneath the viaduct. This lower CD road would also have one continuous lane in each direction, for a total of three continuous lanes in each direction. DOT determined that the viaduct concept and changes were an improvement over the RFP concept plan. As explained by Anthony Jorges, a traffic roadway engineer for BCC: First with the viaduct, by separating the traffic, it provides you unimpeded access to and from Miami Beach to the east, so it improves the emergency evacuation and improves access for emergency services. This addresses the event traffic issue that I brought up earlier. While you have events that may cause backups on the lower level for local traffic, we do have a separate level for the mainline that’s going to carry through. So you have those two lanes on top free at all times. So that was a significant advantage that we were looking at. And in addition to that, there is also the additional lane on the westbound to northbound--I am sorry, the eastbound to northbound movement, and that is taking it from the one lane that was in the RFP concept to the two lanes that Archer Western de Moya provided. That provides significant improvements to the operations of the mainline. It also provides safety benefits because now traffic that was queuing up on this ramp back on to the mainline is separated. Whatever traffic queues up here is separate from the mainline, and you won’t have the possibility for the speed differential, which contributes significantly to accidents. FAM contends that DOT erred in approving a technical proposal ATC 12C, because the number of continuous basic lanes on the highway was a non-modifiable requirement of the RFP. According to the testimony at the hearing and American Association of State Highway and Transportation Officials Policy on Geometric Design of Highways and Streets (“AASHTO Manual”), highway lanes can be grouped into two categories: basic lanes and auxiliary lanes.7/ A basic lane is essentially one that is designated and maintained over a significant length of a route, irrespective of changes in traffic volume and lane balance needs. The parties also referred to a “basic lane” as a “continuous” lane-–one that allows traffic to move over a “significant length of route” without having to change lanes. An auxiliary lane is essentially all lanes other than the basic lanes. It is defined as “the portion of the roadway adjoining the through lanes for speed change, turning, storage for turning, weaving, truck climbing and other purposes that supplement through-traffic movement.” As part of the 2010 I-395 PD&E, DOT found that I-395 lacks sufficient capacity “for system linkage” with SR 836 and other roadways due, in part, to the fact that it has only one continuous lane in each direction while the linking roadways have three. One continuous lane on I-395 was inadequate to provide the necessary access or linkage to the other road systems. Initially, the Federal Highway Authority (“FHWA”) approved a plan to address I-395’s deficiencies which added one additional continuous lane in each direction. On June 15, 2015, however, the FHWA approved the Final Re-Evaluation (completed by BCC) for the I-395 PD&E. This version included a design change allowing “three (3) continuous lanes in each direction to match 836 on the west and MacArthur Causeway on the east.” (emphasis added). DOT noted that this design change was supported by AASHTO design principles, including the basic lane concept. A concept plan for the I-395 project, which included the three continuous lanes and later became the RFP concept plan, was attached to the Final Re-Evaluation. Section VI of the Final Re-Evaluation addressed DOT’s commitments for the I-395 project, including commitment number 14: “[m]aintain and enhance continuity between SR 836/I-95 facility on the west and the MacArthur Causeway on the east.” DOT concluded on page 18 of the Final Re-evaluation that the addition of the third continuous lane on I-395 was necessary to support this commitment, stating: STATUS: [ ] Design Changes No. 1 and No. 7 describe the need to add an additional lane in each direction and widen a portion of the westbound MacArthur Causeway Bridge in order to accommodate the changes to the ingress and egress points of the Port of Miami Tunnel. These changes allow the I-395 project to be compatible with both roadways to the east and west and provide system continuity. DOT also noted that the I-395 project would be constructed concurrently with the SR 836 project, which was the subject of a separate PD&E that was completed in 2011. The SR 836 PD&E Study noted on page 6: More specific improvements potentially involve the provision of a minimum of six continuous (i.e., 3 directional) mainline lanes and the provision of parallel collector distributor facilities to separate the system to system traffic from the local to system traffic. This language establishes MDX also intended that there be three continuous lanes in each direction as proposed by DOT for the I-395 project. In short, DOT’s intent was to have three continuous lanes that would extend from the western boundary of SR 836 to the eastern boundary of I-395. This would allow a driver in any of these lanes to travel from one end of the project to the other without having to change lanes. As a result of the re-evaluation of the PD&E, BCC developed the language for the RFP that related to continuous lane requirements also found in Attachment A08. This language states, in relevant part: The Department has prepared a set of Reference Documents, which include Concept Plans. These plans convey an established set of design objectives to which the Design-Build Firm is required to accomplish in [the I-395] component of the project. The Department’s design objectives include: * * * Provide 3 continuous through lanes to the I-395 Mainline in the Eastbound and Westbound direction. The RFP also provided “[t]he Design-Build Firm shall not modify the following requirements with an ATC Proposal . . . Minimum basic number of lanes shown in Attachment A-33.” Mr. Jorge’s testimony was that the purpose of this language was to be consistent with the objective to provide three continuous lanes in each direction on I-395 to and from the Signature Bridge. The reason the word “minimum” was included in there was we wanted to make sure that we were getting at least three lanes in each direction, and that is the intent behind having the word “minimum.” We did understand that there would be a possibility for changes. But we wanted to make sure that we had at least three lanes in each direction. Attachment A-33 is titled, “I-395 Lane Schematic” and includes information relating to the number of “basic lanes,” “auxiliary lanes,” and the “direction of lanes” at various points of entry via connector roads and ramps onto I-395. For the Signature Bridge, Attachment A-33 has a footnote that states, “The Signature Bridge Shall Accommodate a Minimum of Four 12’ Lanes in Each Direction[.]” The plain reading of Attachment A-33 in the context of the RFP is that the three continuous or basic lane requirements applied to the roadways, but that the Signature Bridge was required to have four continuous lanes. On its face, Attachment A-33 is a schematic drawing that shows all of the lanes in the RFP concept plan for I-395. Although four of the lanes depicted in Attachment A-33 are identified as auxiliary lanes, the rest are identified as basic lanes. However, absent is any indication of some “minimum” number of basic lanes that must be maintained and that cannot be altered through the ATC process, except at one location, which is at the Signature Bridge. For that specific location, Attachment A-33 states that there must be a “minimum of four 12’ lanes in each direction.” (emphasis added). The fact that a minimum is specified at one location on Attachment A-33, but not others, is an indication that DOT did not intend to establish a minimum for other locations on the schematic. Indeed, if DOT had intended for all basic lanes depicted at each location to be the minimum number of lanes for that location, then there would have been no point to including a specific note to express that the number of lanes at the Signature Bridge location was a minimum of four lanes. Mr. Jorges confirmed that this language requiring four lanes in each direction in Attachment A-33 applied only to the Signature Bridge. Q.: And what is the minimum number of basic lanes that there need to be at that [the Signature Bridge] location? A.: Four. Q.: And is a minimum number of basic lanes indicated on attachment A-33 at any other location? A.: No, it’s not. Q.: Can you explain how indicating a minimum number of lanes at the signature bridge is consistent with the PD&E? A.: The PD&E called for three lanes in each direction of I-395, so at the signature bridge, you have 16 a situation where you have the three lanes from I-395 plus the one lane from the eastbound connector, and that’s how we arrived at the four. Like I mentioned before, it was beyond the minimum three that we were expecting, and that’s why we felt it was necessary to identify minimum for that specific location. * * * Q.: Do you have a view or an opinion as to whether or not it would make sense to have a minimum basic number of lanes at every location that’s depicted on A-33? A.: Well, if every lane there was designated as a minimum requirement, there would be no room for any sort of modification or changes by the team, so it essentially eliminates any possibility for innovation and really negates the design- build process. Q.: Can you explain whether or not that would be consistent or inconsistent with the objective of the RFP? A.: It’s--the attachment is consistent with the objectives. One of the key objectives was to have three lanes in each direction. And there is other objectives stated, but they are not specific as to the number of lanes. Although Petitioner’s roadway engineer offered its own interpretation of the Attachment A-33 and the RFP language regarding continuous lanes, Mr. Jorges’ testimony was more reliable and convincing. Mr. Jorges was familiar with the history of “continuous lane” requirements and the reasons for including that requirement in the RFP. He and others from BCC were involved in drafting the concept plans and the RFP language that included the “three continuous-lane” requirement in the RFP. In reality, while the RFP stated the proposals were to “adhere to the number of lanes” in the concept plans, each bidder also had the option of pursuing an ATC that would allow it to deviate from this requirement. The purpose of the ATC process was to encourage the proposers to offer innovative solutions or an approach that was equal to or better than the RFP concept plans or other requirements in the RFP. The viaduct design offered by AWD was found to be “equal to or better” to the concept plan and thus meets the standard for issuing an ATC because (1) AWD’s ATC proposal does not preclude DOT from “meeting the Department Commitments,” which are defined to include the ones “listed in the PD&E, FEIS/ORS and any Reevaluations attached” and (2) AWD’s ATC proposal did not violate the Specific ATC Restrictions set forth in the RFP. Attachment A-33 plainly states there must be a minimum number of basic lanes at the Signature Bridge location only. FAM’s argument that every basic lane identified on Attachment A-33 should be treated as a “minimum” continuous lane that cannot be modified is rejected. The Department did not violate the RFP by issuing ATC 12C, and AWD’s proposal with this ATC is responsive to the RFP. Basic Lane Requirements for SR 836 (Attachment MDXA-02) FAM also challenges the number of lanes proposed by AWD for the MDX’s portion of SR 836 of the Project, which are established by attachment MDXA-02. Specifically, FAM argues AWD’s plan is “one basic lane short of the four basic lanes required by the RFP from Northwest 10th Avenue going eastbound through to I-395.” (FAM’s PRO, p. 16 at para. 45) The issue to be determined is whether the RFP and MDXA-02 requires four continuous lanes for this portion of the Project. Unlike Attachment A-33, Attachment MDXA-02 is not a schematic of all the lanes on the SR 836 concept plan. Instead, Attachment MDX-A02 contains only “typical sections” or a view of a cross-section (not a linear) of the roadway at a particular location. It is not possible to determine from only a cross- section view of a segment of the roadway whether any of the lanes are continuous over a significant length of SR 836. Thus, Attachment MDX-A02 does not reveal which lanes on SR 836 are basic or continuous. Although Mike Madison, FAM’s roadway engineer, testified it was “possible” by reference to the typical sections “to determine what the basic lane requirements are for State Road 836 even if they are not identified as basic lanes on those typical sheets,” he did not rely on (or even refer to) Attachment MDX-A02. Instead, he relied on the RFP concept plan and the industry definition of “basic lane.” The RFP’s SR 836 concept plan referenced by Mr. Madison does identify which lanes are continuous. Again, the concept plans were to serve as reference documents for proposers to build off of and improve. The SR 836 concept plan serves as “general information only,” except as “specifically set forth in the body of” the RFP. Regardless, both parties offered evidence that AWD’s SR 836 proposal includes three basic or continuous lanes. Mr. Jorges’ testimony established the SR 836 concept plan has three basic lanes on the mainline and no basic lanes on the adjacent collector ramp. Instead, the fourth lane that FAM claims was necessary and non-modifiable was actually an auxiliary lane, not a basic lane. The evidence established the “fourth lane” in question is a CD road. Although a CD road can be a continuous lane, here it was not. In the concept plan, the CD road merely collects traffic from Northwest 12th Avenue, which it then distributes to I-395 without providing any access to or from SR 836. Because the CD road on the concept plan does not serve traffic that originates from SR 836, the concept plan’s CD road does not serve the function of a continuous or basic lane for SR 836. Further, the alleged “fourth lane” on the RFP concept plan’s CD road is not continuous and, thus, cannot be considered a “basic” lane. Mr. Madison admitted the concept plan’s CD road does not originate at the western boundary of the SR 836 project. Instead, the concept plan’s CD road originates at Northwest 12th Avenue, nearly halfway between the Project’s western and eastern boundaries. Thus, traffic cannot navigate the length of the SR 836 project on this fourth lane without changing lanes as required by the PD&E. Hypothetically, as explained by Mr. Jorges, a driver would not have access to a continuous lane on the concept plan’s CD road; on the concept plan, a driver entering the CD road via the northbound Northwest 12th Avenue entrance cannot reach the interchange and I-395 without shifting to another lane. After the interchange, this same driver would be forced to shift to another lane again to reach the MacArthur Causeway. By contrast, a driver accessing AWD’s CD road at the western boundary of SR 836 would be able to reach the MacArthur Causeway with no lane changes. Finally, as noted above, the Final Re-Evaluation for the I-395 PD&E proposed the addition of a third continuous lane to I-395 so that I-395 would have “three continuous lanes to match 836 on the west.” (emphasis added). The goal of the I-395 project was therefore symmetry in the number of basic lanes to improve linkage between the I-395 and SR 836 systems. The RFP required three basic or continuous lanes for the MDX portion of SR 836. AWD’s proposal was responsive to this basic lane requirement. Minimum Lane Width Requirements FAM next contends AWD’s proposal is non-responsive because it reduces the lane width for the lane and ramps for the SR 836/I-95 interchange. There is no dispute AWD’s lanes were reduced by an ATC from 12 feet to 11 feet at the ramp in question, but at issue is whether the ramp is in the I-95 portion of the Project, which is modifiable (i.e., not subject to the ATC restrictions); or is in the MDX portion of the Project, which is non-modifiable. The RFP states that “services performed by the Design-Build Firm shall be in compliance with” DOT’s Plans Preparation Manual (“PPM”). (RFP at 77.) Included in the PPM is a 12-foot lane-width requirement. For that portion of the roadwork within the scope of the MDX project, the RFP states that the winning bidder “shall not modify” through the ATC process the “[m]inimum widths of mainline lanes and ramp lanes.” (RFP at 84.) However, pursuant to Addendum 11, this ATC restriction was removed from the RFP for roadwork that is part of DOT’s I-395 project. In ATC 12C, AWD indicated it would be reducing the lane width of the SR 836 west-north connector from 12 feet to 11 feet starting at the physical gore. A “gore” is the area where a ramp joins the mainline or where two streams of traffic converge. Although there was testimony about a “theoretical gore” as opposed to a “physical gore,” engineers use the physical gore to mark the point where the ramp ends and the highway begins. In this case, AWD, through ATC 12C, sought to narrow the width of the traffic lanes at the point where the northbound ramp physically joins and transitions onto I-95. According to FAM’s roadway engineer, this reduction in the lane width is necessary because this ramp connects eastbound SR 836, which has 12-foot lanes, with northbound I-95, which has 11-foot lanes. The evidence establishes the portion of the connector road at issue is not part of the MDX project because it is owned and maintained by DOT, not MDX. This is confirmed by the fact that DOT owns the Northwest 17th Street Bridge (Bridge ID 870369), which is on the connector road to the south of the lane-width reduction area. DOT’s ownership of the lane-width reduction area is also consistent with DOT’s I-395/I-95 maintenance map, which shows that DOT (and not MDX) maintains this part of the roadway. FAM does not rely on the jurisdictional or maintenance maps, but rather relies on two documents in AWD’s ATC 12C application in which AWD referred to “836” as the applicable “State Road Number” and “MDX” as the “Approving Agency” for the proposed lane-width reduction. FAM also noted that AWD used station markers referring to SR 836 to identify the lane-width reduction area. However, as confirmed by the attachments to the RFP, including the DOT maintenance maps and DOT’s bridge inspection report, AWD was mistaken that MDX owned this segment of the roadway. This does not make DOT’s granting of the ATC erroneous. Moreover, FAM offered no document prepared by either DOT or MDX, including the RFP itself, which established MDX’s jurisdiction over this portion of the roadway. Here, the lane-width reduction occurs north of the physical gore, which is the point where the lanes originating from the ramp become physically connected to the lanes on the existing highway, I-95, via pavement that lies between the converging lanes. For safety purposes, according to the AASHTO Manual, once a roadway becomes physically connected to the highway, it is good engineering practice to design the roadway to match the criteria for the highway (e.g., 11-foot lanes) rather than to continue using the ramp criteria (e.g., 12-foot lanes). Even FAM’s roadway engineer acknowledged that, at some point before reaching I-95, the lanes joining I-95 from the connector road must transition from 12 feet to 11 feet to match the I-95 lanes, and that good engineering practice requires that this transition be done gradually rather than “suddenly.” He conceded that the lane-width transition proposed by AWD was reasonable, but disagreed whether the ramp ended at the physical or theoretical gore point. Q.: Right. You agree with me that at some point the lanes that are coming in to I-95 have to transition from 12 to 11 to match? A.: They would have to at some point. Q.: You can’t just go from 12 and all of a sudden have an 11-foot lane, right, that’s bad engineering practice? A.: Yes. Q.: As a matter of fact, the PPM won’t let you do it that way and AASHTO, too, you’ve got to have a transition? A.: Correct. Q.: Okay. So we are not questioning the reasonableness of having a transition? A.: Reasonableness, no. Q.: Okay. So I think to figure out the disconnect again, do you think the ramp doesn’t end at the gore? A.: No, it ends north of the gore, the other side of the gore point. Q.: But you just said there are two points. A.: Theoretical gore points. Q.: You believe the ramp ends at the theoretical gore point? A.: Yes. At the same time, FAM offered no evidence to show that it would still be possible to comply with the gradual transition requirement in the PPM and AASHTO if the lane reduction were delayed until after the theoretical gore when there is no longer any pavement separating the 12-foot lanes from the connector road and the existing 11-foot I-95 lanes. Because MDX neither owns nor maintains that part of the roadway where the lane is narrowed to 11 feet, this road segment is not within MDX’s portion of the Project or jurisdiction. Because the portion of AWD’s proposed lane narrowing for the ramp to I-95 was in the Department’s I-95 jurisdiction, it was modifiable. Therefore, AWD’s ATC proposal with the lane-width reduction was responsive and also a reasonably safe way to transition traffic to I-95. FAM’s Proposal Prior to and at the hearing, AWD argued FAM’s proposal was non-responsive to the RFP and to DOT’s regulations in a number of ways: (1) FAM’s engineer of record, FIGG-WGI, was a joint venture and, as such, could not work on the Project; FAM’s bridge architect, Linda Figg, was not qualified to serve in that capacity; (3) FAM’s Financial Proposal lacked the requisite audited financial statements; and (4) FAM’s technical proposal was inconsistent with the RFP requirements. FIGG-WGI, Inc. First, AWD claims FAM’s designation of FIGG-WGI as an engineer of record violates Florida Administrative Code Rule 14- 75.003(2), which states as follows: (2) The Department shall not recognize joint ventures for purposes of qualifying consultants to work for the Department. Each individual or firm will be annually qualified based upon individual or firm capability. FAM designated in its Letter of Response both “FIGG Bridge Engineers, Inc.,” and “Wantman Group, Inc.” as two subcontractors as part of the FAM team. Later, however, FAM designated FIGG-WGI as FAM’s “Lead Design Firm.” Prior to submitting its Letter of Response, David Wantman asked DOT what information a design joint venture needed to submit to receive DOT approval to participate in this procurement. Carla Perry, a DOT procurement manager, was responsible for the prequalification process for this RFP. She informed FIGG-WGI engineering joint ventures “are not recognized” and that WGI would need to be designated as the engineering firm instead of the joint venture. She suggested the following: The foreign firm could sub to the Construction JV (or to Wantman), but the Engineering JV you referenced below would not be recognized for purposes of fulfilling the technical qualification in the engineering work types, and would be found non-responsive. . . . FAM’s position at final hearing and in its PRO was that FIGG–WGI was not a “legal joint venture.” This position is contrary to the evidence in FAM’s technical proposal noting FIGG–WGI was “organized as a fully integrated, single-purpose entity, which is the engineering firm of record” and the testimony at the hearing establishing FIGG-WGI was formed for legal reasons to insulate its members (Figg Engineering and Wantman) from third-party liability on large construction projects. FIGG-WGI is a joint venture and its participation in the Project, had FAM been chosen, would have violated DOT’s rules regarding what type of business structures can work on DOT projects. The violation, however, was curable. The RFP allows changes in designated key personnel and “teaming arrangements” subject to the Department’s approval. Approval of changes would be based on “whether or not the proposed substitutions in Partner/Teaming Arrangements are comparable to the Partner/Teaming Arrangements identified in the Letter of Response and/or Technical Proposal.” Here, the evidence establishes that the members of the joint venture are both individually prequalified to do work for DOT. In reality, their employees are the same employees of the joint venture which would have been working on the Project had FAM been chosen as the BVP. Moreover, the testimony at the hearing established that if FAM was chosen, both Figg Bridge Engineers, Inc., and Wantman Group, Inc., would have individually contracted with FAM in whatever corporate form would have been required by DOT. The RFP “Waiver or Irregularities” also provides FDOT may waive irregularities in proposals “where such is merely a matter of form and not of substance, and the correction . . . of which is not prejudicial to other Proposers.” Here, AWD failed to sufficiently establish how it suffered (either potentially or actually) from FAM’s designation of FIGG-WGI, LLC. Nor was there any evidence of how AWD would have been prejudiced if FAM was allowed to substitute the individual members of the joint venture, if FAM had been chosen to be the BVP. Any error in designating FIGG-WFI, LLC, as its lead designer and engineer of record was a curable minor irregularity that would not have made FAM’s proposal non-responsive. Linda Figg Second, AWD makes the same arguments regarding Linda Figg’s designation as “Bridge Architect” as it did in its pre- hearing motions as to why FAM’s proposal was non-responsive: the RFP required bidders to designate a bridge architect; and Linda Figg, the person designated by FAM, is not an architect. FAM designated Ms. Figg in its Letter of Response as its “Lead Bridge Architect.” Ms. Figg is not licensed as an architect with the State of Florida under chapter 481, Florida Statutes, (Architecture, Interior Design, and Landscape Architecture) nor is she licensed in any other state. The RFP is silent as to the qualifications of a bridge architect. Nothing in the RFP indicates the designated bridge architect must be registered or licensed; nor does it require the designated bridge architect to meet specific educational or other qualifications. No evidence was provided at the hearing as to how the Department defined “bridge architect.” In fact, FDOT did not join with AWD in this argument. Nor was there evidence at the hearing establishing the industry standard for defining a “bridge architect.” Merriam-Webster defines “architect” as “a person who designs buildings and advises in their construction.” Architect, Merriam-Webster Online (2017), https://www.merriam- webster.com/dictionary/architect (accessed on February 23, 2017). Ms. Figg meets this definition of “architect.” Moreover, Figg Engineering is prequalified by DOT and has available professional staff (other than Ms. Figg) who are licensed architects and/or professional engineers. As such, FAM’s designation of Ms. Figg as its Lead Bridge Engineer did not make its proposal non-responsive. FAM’s Bridge Design – Load AWD also asserts FAM’s Signature Bridge proposal violates the RFP’s non-modifiable requirement that “[a]ll Signature Bridge components shall be part of the structural system that carries bridge Dead Load (DL) and Live Load (LL).” “Dead load” is the actual weight of the bridge structure; “live load” is the added weight of the traffic traveling on the bridge. As explained at the hearing, “components” are the necessary parts of the bridge: superstructure (what cars drive on); substructure (pylons or columns); and foundation (what the pylons and columns are set on). In contrast, railings are safety devices and considered “appurtenances” as opposed to “components.” FAM’s bridge design contained two rotating disks, each on top of an extended arm. Bridge components that do not serve a purpose or carry any weight were not allowed by the RFP, and bidders could not obtain an ATC to change this requirement. FAM’s own bridge engineer, Denny Pate, testified that nonstructural parts of the bridge were prohibited by the RFP. Q.: Can you give the judge an example of a nonstructural bridge component that would be noncompliant under the RFP? A.: The RFP requirement, obviously, is--in my opinion, is saying: We don’t want fake bridge components. For example, there is a project development over here just west of Port St. Joe on the coast there called WindMark. And as part of their entrance to their development, they have a very standard short-span girder bridge, but they have put up steel, fake steel trusses along the sides that basically add interest to the bridge, make it visually more unique, but they don’t do anything. They are not structural. Mr. Pate went on to testify that the rings on the tops of FAM’s proposed bridges do not carry any live load. They were not necessary and could be removed without any effect on the bridge’s structural integrity.8/ This was consistent with the testimony of John Corven, AWD’s bridge engineering expert. Mr. Corven explained the loads in FAM’s Signature Bridge proposal picked up by the cables into the pylon did not find their way into the single arm with a rotating disc and, thus, the arm and disc would not be part of the load-carrying capability of the bridge. The inclusion of non-load bearing components was more than a minor irregularity. One could imagine a scenario where an aesthetic design may compromise safety concerns. More importantly, failure to adhere to the restriction requiring only load-carrying components had the potential of prejudicing other bidders who complied with this requirement from coming up with more eye-pleasing bridge designs. Mr. Corven testified: Q.: As an engineer, what would be the impact if that restriction were lifted in terms of the work you are doing from an engineering standpoint, meaning if you no longer had to worry about dead and live load components, how does that impact how you go about designing a structure? A.: Well, I think it would free the engineer to more artistic and aesthetic expressions for elements that might capture a visual appeal but not be functional structurally. Although the rotating ring may have been aesthetically and architecturally interesting, it was prohibited by the RFP. As such, FAM’s Signature Bridge design with the arm and rings was non-responsive. Twin Structures AWD also asserted FAM’s Signature Bridge proposal violated the RFP’s prohibition against “twin structures” found in the Aesthetic Manual for the RFP which states: The signature bridge shall be two fully independent bridges that are made to look like one form (e.g. twin basket handle bridges void of a visually unifying element will not be allowed). This structural autonomy is necessary because the EB and WB structures will be constructed sequentially, yet the stakeholders have insisted upon the appearance of one aesthetic entity. Elsewhere the RFP notes, the bridge proposals must adhere to the following minimum requirements: “No twin structures.” The common sense meaning of “twin structures” is two bridges that are identical or exact duplicates. Simply looking at the design, FAM’s proposal’s eastbound and westbound structures are not identical, but rather inversely similar. Moreover, as established by Mr. Pate’s unrefuted testimony, there were a number of “non-twinning” aspects of FAM’s Signature Bridge proposal. The westbound bridge runs straight, whereas the eastbound bridge contains a horizontal curve. The towers are mirrored so that the features are not in the same direction. The features on the two structures are staggered. There are a different number of spans in the overall length of the structures. The overall structures are different lengths: Bridge 8 (eastbound) has a signature bridge length of 980 feet and 1,432 feet of overall length between the spans; and Bridge 9 (westbound) has 977 feet for the Signature Bridge and 1,207 feet in overall length. FAM’s proposed Signature Bridge design did not contain twin structures prohibited by the RFP requirements. Constant Girder Depth AWD also challenges FAM’s Signature Bridge as being non-responsive to the Aesthetic Manual’s requirement “the signature bridge shall have a constant depth superstructure.” The language of the RFP does not include this reference, but does require “[g]irder depth on each side of the expansion joints shall be the same, i.e., no steps allowed.” As explained at the hearing “girder depth” is “basically what your eye sees as the distance from the top to the bottom of the roadway surface.” Both AWD’s and FAM’s bridge engineering experts testified the girder depth on each side of the expansion joint was the same in FAM’s Signature Bridge design and complied with the RFP language requiring equal girder depth on each side of the expansion joint. FAM’s Signature Bridge was responsive to the RFP’s girder depth requirement. MOT Plan Next, AWD contends FAM’s MOT plans are non-responsive because (1) the plans do not illustrate pedestrian access; (2) the plans do not have the requisite number of traffic lanes; and (3) the plans contain two reverse curves without a tangent. The RFP requires the following: The Construction Phasing/Sequencing Plan shall provide information regarding Traffic management for Total Project . . . [and] shall include a narrative describing the means by which the Design Build Firm will move vehicular, bicycle and pedestrian traffic along the Project Limits. The evidence established FAM provided a narrative description of pedestrian access in its technical proposal and submitted MOT plans that allow for the same level of pedestrian access as exists in the present condition. As such, FAM met the pedestrian access requirements of the RFP, and its MOT was responsive to the pedestrian access requirements. AWD next contends that the RFP requires that three lanes of traffic be maintained during all MOT phases because that is what exists in the present condition. However, DOT clarified in writing during the Q&A phase that proposers need only provide the same number of lanes shown in the RFP concept plans during MOT. The evidence at the hearing established FAM provides the same number of traffic lanes shown in the Concept Plans, and as such its MOT plans are responsive to this requirement. Finally, AWD contends FAM’s MOT plans are deficient because one of the ramps (Ramp D1) contains two reverse curves without a tangent. A tangent is the straightaway leading a driver in a certain direction when he or she comes around the curve. Although the testimony surrounding the curves in the MOT plan was highly technical, Mr. Madison, FAM’s roadway engineer, convincingly explained that the two reverse curves in FAM’s MOT are not super-elevated or abnormally cross-sloped. A cross-slope is the pitch of the roadway from one side to the other; a normal cross-slope is two percent. The testimony at trial established FAM’s MOT plan contains two curves that are two percent in one direction at all times and meet industry safety standards. Thus, they do not require a tangent. Regardless, even if the curves required a tangent, there was no evidence that failure to include this tangent put other bidders at a disadvantage. Finally, if Ramp D1 required a tangent, the plans AWD complains about are preliminary in nature. During the Q&A phase, DOT notified FAM that its Ramp D1 design needed a tangent between two curves or otherwise needed to be redesigned to meet the standards. FAM agreed to do so. Because this was a “modifiable” aspect of the MOT, had the PSC selected FAM as BVP, adjustments and corrections to Ramp D1 could be achieved per FAM’s commitment to comply with the RFP in its Confirmation Letter. FAM’s MOT plans were responsive to the RFP, and any need for an adjustment to include a tangent could have been provided in the final plans as allowed and anticipated by the RFP. Audited Financial Statements AWD argues FAM’s Financial Proposal was non- responsive because it did not contain audited financial statements from one of the members of its joint venture. The winning bidder was required to self-finance portions of its work as it would not receive full payment from DOT until after it had incurred costs for design and construction. This type of structure is often referred to as “gap financing.” The RFP required each bidder to submit a Financial Proposal “so the Department can be assured that the Design-Build Firm has sufficient financial resources to construct the Department Project within the allotted Contract Time, based on the Cash Availability Schedule.” To satisfy itself that the entity who would ultimately design and build the Project was able to finance the labor and construction costs, the Department required each bidder to provide a financial proposal that contained, among other things, audited financial statements. The RFP required the following in the Financial Proposals: The minimum required documents the Design- Build Firm must submit to the Department as part of the Design-Build Firm’s Financial Proposal shall include, but may not be limited to, the following: . . . Financial Statements of members of the Design-Build Firm or any partners of the joint venture that make-up [sic] the Design-Build Firm that will be responsible for the repayment of financial support related to the Department Project or directly provides financial support related to the Department Project. Lenders that are not members of the Design-Build Firm or partners of the joint venture that make up the Design-Build Firm are not required to provide Financial Statements. Financial Statements shall include: For the most recent two (2) fiscal years in which audited Financial Statements are available, audited Financial Statements prepared in accordance with U.S. Generally Accepted Accounting Principles. Required Financial Statements shall include: Opinion Letter (Auditor’s Report); Balance Sheet; Income Statement; Statement of Retained Earnings or Changes in Stockholders Equity; Statement of Cash Flows; and Notes to Financial Statements. * * * If audited Financial Statements are unavailable for the most recently completed fiscal year, unaudited Financial Statements, prepared in accordance with U.S. Generally Accepted Accounting Principles, shall be provided for such fiscal year. An affirmative statement shall be provided indicating that the Financial Statements for the most recently completed fiscal year are still being audited. These unaudited Financial Statements shall be certified as true, correct and complete by the Chief Financial Officer or treasurer of the entity. Requirements for unaudited Financial Statements are the same as for audited Financial Statements, except an Opinion Letter (Auditor’s Report) is not required. (RFP at 67–68.) As described in the RFP, the RFP required a joint- venture bidder to submit the audited financial statements of each of its members in accordance with U.S. Generally Accepted Accounting Principles (GAAP); if a partner of a joint-venture member would provide financial support for the project, that partner’s audited financial statements were required to be submitted as well. There is no dispute FAM did not and could not include any audited financial statements for one of its members, FEI, because FEI is not audited. There is also no dispute that FEI will be responsible for the repayment of financial support related to the Project or would directly provide financial support related to the Project. FAM did not qualify for the alternative included in the RFP for providing audited financial statements when such statements are unavailable for the most recent fiscal year. Moreover, it was clear from the testimony put on by FAM that such audited statements could not have been provided in a timely matter, even if the Department had allowed FAM to supplement its financial proposal. Brian Smith, the assistant corporate controller for Fluor Corporation, testified if FAM had been selected BVP and the Department had requested the audited financial statements for FEI, it could not have provided them until well after the May 18, 2017, date set forth in the RFP for selecting the BVP. Q.: Had you been asked by DOT for an FEI audited financial statement for 2016 back in April of 2017, what is the soonest that FEI could have provided that information to DOT? A.: An audit of this nature would generally take four to six weeks, on an expedited basis, probably four weeks. FAM counters it provided equivalent information and thus there was no effective harm. The RFP, however, specifically requires audited financial statements, not the information in those statements. This seems especially prudent given the size of the Project and when, as in this case, the bid was awarded as a public–private transportation facility under section 334.30, Florida Statutes, which emphasizes the financial health of bidders. Moreover, the failure to submit audited financial statements has been found to render a proposal non-responsive when such statements are required by an RFP. See Jani-King Gulf Coast Region v. Escambia Cnty. Sch. Bd., Case No. 16-2762BID, RO at 23 (Fla. DOAH Aug. 26, 2016) (explaining the importance of audited financial statements, noting they “provide a much higher level of assurance as to the validity of the financial information presented,” than unaudited statements). Nor can FAM satisfy the requirement for audited statements from FEI simply by submitting such statements from FEI parent corporation. See Consultec, Inc., d/b/a Gen. Am. Consultec, Inc. v. Fla. Dep’t of Admin., Case No. 91-5950BID, RO at 29 (Fla. DOAH Nov. 25, 1992) (finding submission of financial information from parent company failed to satisfy RFP requirement to provide audited financial statements and thus proposal was non-responsive). As explained in Consultec, FAM would have had an advantage had it not been required to provide such statements. Succinctly, . . . its failure to comply with the audited financial statement requirement of the RFP gave it an advantage not enjoyed by other bidders since by submitting the balance sheet of its parent company, as opposed to its own financial statements, HCPP effectively precluded any assessment of its own financial soundness. Id. As such, FAM’s failure to include the audited financial statements of FEI renders its Financial Proposal non- responsive.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered dismissing Petitioner Fluor-Astaldi-MCM, Joint Venture’s Amended Formal Written Protest, and affirming Respondent Florida Department of Transportation’s Notice of Intent to award to Intervenor Archer Western-de Moya, Joint Venture. DONE AND ENTERED this 10th day of April, 2018, in Tallahassee, Leon County, Florida. S HETAL DESAI Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of April, 2018.
Findings Of Fact DOT has been engaged for some years in a program to improve U.S. Highway 1, which runs through the Florida Keys. The program has involved highway paving, and reconstruction of most of the bridges. The roadway and bridge construction projects require large amounts of fill material. DOT has experienced an increase in the cost of obtaining fill material in the Florida Keys. To lessen the cost of the fill material DOT is seeking to open a borrow pit on Dudjoe Key. The pit, and an adjoining roadway would cover approximately fourteen acres. DOT initially filed a permit application with DER, seeking approval to construct the pit. DER ultimately issued a notice of intent to deny the application on the grounds that reasonable assurances had not been given that the short-term and long-term effects of the proposed project would not violate water quality standards set out in DER's rules and regulations. DOT thereafter filed a request for variance from the water quality standards so that the pit could be permitted. This proceeding ensued. Petitioner is a Florida corporation which does business in Monroe County, Florida. Petitioner has engaged in numerous public road and bridge construction projects in the Florida Keys and in the selling of fill material for road and bridge construction projects. Petitioner currently owns and operates a "borrow pit" on Cudjoe Key. Petitioner's pit is located within one- half mile of DOT's proposed pit. The purpose of the DOT pit would be to provide fill material which the Petitioner currently provides from its Cudjoe Key pit. DOT originally asserted that operation of a state borrow pit would result in savings of nine million dollars. This assertion has been scaled down to three million dollars, and more recently to 1.5 million dollars. Basically, DOT asserts that fill from a state-owned pit would be cheaper because the operation costs would be approximately the same, but no royalty would need to be paid for the material. DOT sought to establish the amount of potential savings at the hearing through two kinds of analysis: First, DOT offered the testimony of its former cost estimator as to the costs per cubic yard of fill from a state-owned pit as opposed to fill from a private contractor pit; and second, DOT offered bid submissions that have been made by contractors in recently bid projects in the Keys, and which had alternative bids for state-owned and private contractor supplied fill material. DOT's estimator calculated that the State would save approximately 1.5 million dollars through operation of a state-owned borrow pit. The testimony, however, is not of probative value, and cannot serve as the basis for a finding to that effect. In the first place, many of the estimator's figures were determined through private conversations that he had with various unnamed contractors. This hearsay evidence is not cumulative nor corroborative of other evidence, and cannot therefore serve as the basis for a finding of fact (See discussion at Paragraph 2 of the Conclusions of Law, infra.). Furthermore, the estimator underestimated the heavy equipment that would be required to operate the borrow pit; underestimated the cost of the equipment; did not include insurance, social security, and overtime in labor costs; overestimated by twice the number of swings that a dragline would be able to make; and underestimated the cost of moving equipment to the site. Methodology used by the State's estimator would appear to be the best that is available to the State in making initial estimates as to the cost of proposed road-building projects. The State does not have the detailed cost information available to it that private contractors have. While useful for the purpose of making preliminary estimates of the cost of proposed projects, the methodology is not adequate to support a finding of fact based as it is upon hearsay, and containing numerous miscalculations. The second line of analysis offered by DOT to establish the amount of possible savings was a comparison of recent bids submitted by contractors. Special provisions drafted by DOT for the Park and Bow bridge projects using two alternatives for embankment or fill material. Alternate "A" in the bid called for state-furnished material. The low bidder on the project was Atlantic Foundation Company, Inc. Under Alternate "A", Atlantic bid a price of $9.35 per cubic yard for embankment material, and $12.00 under Alternate "B". This would have resulted in a total of $222,574.00 lest using the Alternate "A" bid on the Park and Bow projects. The second low bidder, MCC of Florida, Inc., bid $11.13 for material under Alternate "A", and $14.02 under Alternate "B". Alternate "A" would have been $247,752.00 cheaper under the MCC bid. Petitioner was the next low bidder, and it bid $10.05 per cubic yard under Alternate "A", and $10.25 under Alternate "B". Hardaway Constructors, Inc., was the only other bidder, and it offered $10.00 under Alternate "A", and $10.25 under Alternate "B". The potential savings in favor of Alternate "A" under all of these bids is reduced somewhat by clearing and grubbing costs which were bid separately by the contractors. Clearing and grubbing costs would actually have made Alternate "B" cheaper under the bids submitted by Petitioner and Hardaway. Clearing and grubbing costs would not, however, continue as a cost item in subsequent projects, because once clearing and grubbing is accomplished, it would not need to be done again. DOT seeks to apply bid differentials submitted for the Park and Bow Channel jobs to determine the potential saving the State could realize by using a state-owned landfill for the remaining road and bridge projects in the Keys. Approximately 402,039 cubic yards of embankment material will be needed to complete the remaining projects. Using the high differential between Alternates "A" and "B" submitted for the Park and Bow Channels (that submitted by MCC), which was $2.89 per cubic yard, the potential saving would be $1,161,892.00. Using the low differential (twenty cents per cubic yard as submitted by Petitioner), savings would be $80,407.00. Subsequent to the hearing, DOT awarded the Park and Bow Channel construction to the low bidder, Atlantic Foundation, Inc. The Alternate "B" proposal was accepted. DOT did not accept that proposal because of a preference to do that, but rather so that the otherwise advantageous bid could be accepted despite the pendance of this proceeding. During the hearing, bids were opened for two new road and bridge projects in the Keys: the Kemp and Torch-Ramrod Channel Projects. The apparent low bidder on these projects was the Petitioner. Petitioner bided a price of $11.00 for embankment material if provided by a private contractor, and $10.80 if provided from a state-owned pit for the Kemp project, and $10.40 and $10.20 respectively for the Torch-Ramrod Project. The differences between the two reflect differences in hauling distance. The price differentials for contractor versus state provided embankment material in projects that have already been let cannot be used to determine with any precision the amount of saving that would inure to the State through opening its own borrow pits. Potential savings depend upon many factors. The primary of these factors is which contractor happens to make the lowest bid for the project, and this in turn depends upon the contractor's cost figures for many items other than embankment material will receive the bid only if the total bid is lower than that submitted by other contractors. It is clear that opening a state-owned borrow pit would result in some savings. It appears that $10.00 per cubic yard is the lowest possible price that could be expected for contractor- provided fill material. It appears that state-furnished material could reach a price as low as $7.00 per cubic yard, although none of the bids submitted up to the time of the hearing reflected such a price. It appears that the highest potential saving would be less than the approximately one million dollars that would have been saved if the price differential reflected in the Atlantic Foundation bid on the Park and Bow Channel projects became the differential in all subsequent projects. It also appears that the saving would be somewhat more than the eighty thousand dollar saving that would inure if the price differential reflected in the Petitioner's bid on the Park and Bow projects remained consistent. Beyond these parameters, the evidence would not support a finding as to the amount of savings. The fourteen-acre site of the proposed borrow pit is presently comprised entirely of tidally inundated wetland areas. Approximately two-thirds of the area has average water depths up to six inches. The southeastern portion of the site is dominated by buttonwood, and red, black and white mangrove. All of these species are wetland indicator species under DER's rules and regulations. A large number of mollusks inhabit the area, and it is a feeding area for birds, and for deer. The area of the proposed borrow pit is within the Key Deer Refuge, which is managed by the Refuse Division of the United States Fish and Wildlife Service. There is now a stable herd from 350 to 400 Key deer, an endangered species, and they feed primarily on mangrove. There are 15 to 20 deer in the Cudjoe Key area. The deer do presently feed in the area of the proposed borrow pit. The proposed pit, including the access roads, would comprise approximately fourteen acres. It would be located landward of a berm so that there would not be a constant exchange of waters between the pit and surrounding areas. There would be an initial two-foot drop form the edge of the pit, and then a slope of five-to-one extending into the pit. A ten-to-one slope would be preferable because ultimately vegetation would be ore easily established in such a slope area. The term "Borrow pit" is actually a euphemism for a mining operation. Material would be extracted from the pit to be used as embankment material on the Keys road and bridge projects. The pit would ultimately reach a depth of more than thirty feet. Construction of the borrow pit would result in obliteration of approximately fourteen acres of a natural wetland environment in the Keys. All the flora and fauna presently on the site would be destroyed. During the time that the pit is being constructed and actively operated, violations of DER's standards for turbidity, lead, oils and greases, and transparency would be likely. Once the mining operation terminates, these short-term impacts would lessen; however, violations of the Department's dissolved oxygen standards would be likely as long as the pit exists. A viable biologic community could be established along the fringes of the pit, but in the deeper areas, low dissolved oxygen levels would be a limiting factor. Other mining operations in the Keys and elsewhere in Florida confirm the likelihood of dissolved oxygen violations. Loss of the fourteen acres of feeding ground for the Florida Key deer would be a significant loss in terms of preservation of that species. The proposed borrow pit is located adjacent to U.S. Highway 1. On the other side of the highway, there is a housing development. Operation of the borrow pit, especially blasting activities would inevitably prove a nuisance to residents of that area. One witness testified that blasting would likely cause damage to the residences, but this was not confirmed by competent, scientific evidence.
The Issue The issue presented for decision in this case is whether Respondent, the Florida Department of Transportation ("FDOT"), acted contrary to the agency’s governing statutes, rules or policies, or the proposal specifications, in rejecting the proposal of Petitioner, Old Tampa Bay Enterprises, Inc. ("Old Tampa Bay"), to RFP-DOT-97/98-1003, Bridge Tending/Maintenance and Repair Services for Five Movable Bridges, Sarasota and Manatee Counties (the "RFP" or "RFP 1003"), and awarding the contract to Intervenor, General Electric Industrial Systems ("GE"). GE also raises the issue whether Old Tampa Bay lacks standing because it submitted a materially false or fraudulent proposal.
Findings Of Fact Based on the oral and documentary evidence adduced at the final hearing, and the entire record in this proceeding, the following findings of fact are made: On or about April 10, 1998, FDOT issued RFP 1003, requesting proposals for a bridge-tending, maintenance and repair service contract for five movable bridges within Manatee and Sarasota Counties. The contract would run for a period of one year, with an option for two annual renewals. FDOT contemporaneously issued RFP 1004, for the performance of identical bridge tending, preventive maintenance and repair services on four other movable bridges in Sarasota County. The RFP required, among other things, that proposers must employ an experienced bridge tender supervisor and an experienced registered electrical engineer. The RFP required that the contractor must be licensed to perform electrical and mechanical work in the State of Florida, and that a copy of the license be submitted as part of the proposal package. RFP 1003, Section 1.7.5. (In this and some other sections of the RFP, FDOT employed the undefined term "Consultant" rather than the term "Contractor" or "Proposer" used through the bulk of the RFPs. Absent a clarifying explanation, it is assumed that all three terms are used interchangeably.) The RFP required the proposers to provide the names of "key personnel," a resume for each of these individuals, and a description of the functions and responsibilities of each key person relative to the task to be performed. The approximate percent of time to be devoted exclusively to this project was also to be provided. FDOT’s prior written approval was required for the removal and substitution of any of the key personnel proposed. "Key personnel" included project engineers, bridge superintendents, mechanics, and electricians. Under the heading "preventive maintenance," the RFP required the proposers to provide "sufficient and competent personnel to perform the inspection, troubleshooting and work for all bid item requirements." The electrician must be "a licensed electrician with experience in industrial maintenance and troubleshooting." RFP 1003, Exhibit A-3, Section 3.0. The RFPs incorporated by reference the "Bridge Operations and Maintenance Manual" (the "Bridge Manual"), an FDOT document establishing procedures for bridge operations and maintenance requirements statewide. The Bridge Manual set forth the following qualifications for electricians: All electricians working on movable bridges or electrical equipment on any bridge must hold at least a journeyman electrician’s license in at least one Florida county and have skills in industrial electrical work. Ability to read and understand blueprints and written instructions. Ability to communicate effectively orally and in writing. Ability to plan, organize and coordinate work assignments. Ability to install, alter, repair and maintain electrical systems, equipment and fixtures. Bridge Manual, pages 2-3. Another section of the Bridge Manual elaborated on the minimum qualifications for electricians as follows: All electricians working on movable bridges or electrical equipment on any bridge must hold at least a journeyman electrician’s license in at least one Florida county and have at least two years experience in industrial electrical work. Vocational/training in industrial electricity can substitute at the rate of 720 classroom hours for each year of the required experience. After employment, they should attend the Bridge Inspection school and Movable Bridge Inspection school. They should also receive continuing training on motor controls, National Electric Code and applicable safety training. They should be able to read blueprints, and written instructions, communicate effectively, be able to plan, organize, and coordinate work assignments, and have the ability to install, alter, repair and maintain electrical systems, equipment and fixtures. Bridge Manual, pages 2-17 through 2-18. The RFP awarded a maximum of 100 points to responsive proposals. A maximum of 60 points could be awarded for the technical proposals, which were scored by a three-member technical committee that included Hendrik Ooms, FDOT’s assistant maintenance engineer for District One. Each member of the committee scored the proposals independently. Their scores were then averaged to arrive at the final technical score. The RFP listed Richard Marino, the head of contracts for District One, as the project manager who should receive all technical questions from prospective proposers. Regardless of the formal designation, Mr. Ooms was in fact the project manager and the person capable of answering technical questions. The technical proposal scoring subsumed a maximum of 35 points for the "management plan," including 20 points for identified "key personnel." A maximum of 35 points could be awarded for the price proposal. The low price proposal received the maximum 35 points, with the remaining proposals scored according to the formula: (Low price/proposer’s price) x Price points = Proposer’s total points. The technical committee was not aware of the contents of the price proposals prior to scoring the technical proposals. Finally, proposers could obtain 5 preference points for Disadvantaged Business Enterprise (DBE) participation of at least 10 percent of the total dollar amount of the contract, or 2 preference points for DBE participation of between 5 and 10% of the total dollar amount. On or about May 11, 1998, three companies submitted proposals for RFP 1003 and 1004: GE; Old Tampa Bay; and C & S Building Maintenance Corporation. GE is the incumbent vendor for these contracts. Until this bid, Old Tampa Bay was a subcontractor to GE on these contracts. On May 22, 1998, FDOT posted the proposal tabulations indicating the intended awardees of the two contracts. Old Tampa Bay was the apparent awardee of the contract for RFP 1003, the contract at issue in this case, with a total score of 79.67 points. GE was the second high scorer, with 79.45 points. GE was the apparent awardee of the contract for RFP 1004. As to RFP 1003, the averaged technical score for Old Tampa Bay was 39.67 points. The averaged technical score for GE was 49 points. All three members of the technical committee awarded GE more points than Old Tampa Bay, though Mr. Ooms saw a greater difference between the two bids than did the other committee members, Richard Marino and Kenneth Clark. Mr. Marino awarded 56 points to GE and 52 points to Old Tampa Bay. Mr. Clark awarded 53 points to GE and 47 points to Old Tampa Bay. Mr. Ooms awarded 38 points to GE and 20 points to Old Tampa Bay. Despite the difference in the technical proposals, Old Tampa Bay was named the intended awardee for RFP 1003 on the strength of 35 points for its significantly lower price proposal ($539,915 per year, versus $621,340 per year for GE) and obtaining the full 5 points for DBE participation. GE was awarded 30.45 price points according to the RFP formula and obtained no DBE points. No formal protest having been received, FDOT moved forward to the next step in the award process. The agency sent substantially identical letters to Old Tampa Bay as the intended awardee of the contract for RFP 1003 and to GE as the intended awardee of the contract for RFP 1004. The letters, dated June 15, 1998, and signed by Felipe Alvarez, FDOT’s purchasing agent, informed the vendors that they had each proposed the same people as "key personnel" who would devote 100 percent of their time to the project. This situation "concerned" FDOT, as these persons obviously could not devote 100 percent of their time to RFP 1003 as employees of Old Tampa Bay and 100 percent of their time to RFP 1004 as employees of GE. The letters requested each of the vendors to clarify the employment of the following persons: Mr. W. Bruce Chapman, whom GE had identified as its bridge superintendent and Old Tampa Bay had identified as its project manager; Mr. Gary Berkley, whom GE had identified as its mechanic and Old Tampa Bay had identified as its primary mechanic; Kelly Green, whom both GE and Old Tampa Bay had identified as primary electrician; and John Vance, whom both GE and Old Tampa Bay had identified as supporting electrician. The letters concluded with the following statement: The Proposal Package stated that if awarded the Agreement, the Consultant is to provide the services of the key personnel proposed. Removal and substitution of any of the key personnel proposed will require the Department’s prior written approval. Please advise the Department if your firm plans to provide the same key personnel or will be providing an equivalent substitution; equivalent meaning as of [sic] the same caliber, experience, and expertise or better than the individual originally proposed. (Emphasis added.) As noted in FDOT’s letter, the Old Tampa Bay proposal listed Kelly Green and John Vance as electricians. Old Tampa Bay’s proposal emphasized that Vance and Green were the current electricians performing electrical maintenance and repairs on the bridges, with nine years combined experience on the District One contract. Old Tampa Bay's proposal emphasized the ease of transition to the new contract that FDOT would enjoy should it select Old Tampa Bay: There will be no transition pain from the existing prime contractor [GE] to [Old Tampa Bay] as ALL personnel currently serving are already on the [Old Tampa Bay] payroll and have been for several years. FDOT will have no new relationships to establish or unknowns with which to be concerned. (Emphasis in original.) Old Tampa Bay’s proposal emphasized in several places that Old Tampa Bay would provide the same electricians who were already working on the bridges. In describing its technical approach to the electrical systems, Old Tampa Bay emphasized that its electricians would require no orientation before commencing work: The electrical system is a critical link in the operation of the bridge. Its maintenance is crucial to reliable operation. [Old Tampa Bay's] comprehensive maintenance program is designed to meet and exceed contract requirements. The [Old Tampa Bay] electrician (Resume attached) is knowledgeable and experienced in the performance of this program. He has performed this service under other FDOT contracts. Old Tampa Bay's proposal emphasized the experience of its electricians with respect to the electro-mechanical control systems, stating that "All [Old Tampa Bay] service personnel including electricians have been trained to work on, maintain, and troubleshoot as required each intricate system." Old Tampa Bay emphasized the experience of Vance and Green, and stated that they had "never failed to correct any problems on this system on any of the bridges in this contract." Old Tampa Bay made similar representations in regard to equipment malfunctions and computerized control systems, emphasizing the quick, successful responses by and experience of its electricians. The evidence indicated that Old Tampa Bay knew, or should have known, at the time it submitted its proposal, that John Vance had no intention of working for Old Tampa Bay on these contracts. Old Tampa Bay included Mr. Vance’s name and license in its proposal without his consent. Mr. Vance never stated orally or in writing that he agreed to be included in Old Tampa Bay's proposal. Old Tampa Bay never asked Mr. Vance’s permission to include his name as a proposed supporting electrician. Old Tampa Bay never asked Mr. Vance’s permission to include a copy of his electrical contractor’s license in Old Tampa Bay's proposal. About two weeks prior to the proposal submission date, Old Tampa Bay's president, Donald Abernathy, asked Mr. Vance for a copy of his license, but did not tell him that Old Tampa Bay intended to include the license in its proposal. Rather, Mr. Abernathy told Mr. Vance that Old Tampa Bay needed the license for purposes related to insurance. Mr. Vance refused to provide Old Tampa Bay with a copy of his license. Old Tampa Bay obtained a copy of Mr. Vance’s license by making a public records request to Manatee County, and submitted that copy with its proposal. Mr. Bruce Chapman has served for nearly four years as a bridge tender supervisor, employed by Old Tampa Bay under a GE contract with the FDOT. At the time of the hearing, Mr. Chapman was still an Old Tampa Bay employee. Mr. Chapman assisted Mr. Abernathy in trying to obtain permission of various people to use their names in Old Tampa Bay's proposal. Mr. Chapman testified that he knew from conversations with Mr. Vance that Mr. Vance did not want to work for Old Tampa Bay on the new contract. Old Tampa Bay also knew at the time of proposal submission that it had obtained no assurances from Kelly Green that he would work for Old Tampa Bay on the contract for RFP 1003. As detailed below, Mr. Green ultimately signed a letter-of-intent to work for GE on the contract for RFP 1004. Mr. Abernathy contended that Old Tampa Bay was entitled to include Vance and Green in its proposal without permission because they were Old Tampa Bay employees. However, Mr. Abernathy also conceded that Vance and Green were at-will employees, and his prior attempt to secure their permission to use their names in the Old Tampa Bay proposal was a tacit admission that Old Tampa Bay had no control over them. Further, in the fall of 1997, Mr. Abernathy attempted to obtain the signatures of Mr. Vance and several other bridge employees to a non-compete agreement for the purpose of binding them to Old Tampa Bay. Mr. Vance refused to sign the agreement. Old Tampa Bay provided payroll services to Vance and Green during their work on the bridges under GE’s existing contract with the FDOT, but Old Tampa Bay never supervised the work of the bridge electricians, never provided Vance or Green with the tools, equipment or supplies they used in their work as bridge electricians, and never had any control over the day-to- day activities of any electricians on any FDOT contract. The electricians worked on a daily basis with GE’s project engineer, Douglas Blake. Mr. Blake had trained Mr. Vance on bridge electrical equipment when the latter commenced work on the bridges. The electricians looked to Mr. Blake for technical and substantive assistance in working on the bridges. Mr. Vance testified that he considered himself an employee of GE. Mr. Green did not testify at the hearing. On June 26, 1998, both Old Tampa Bay and GE submitted responses to the FDOT letter of June 15, 1998. In a letter signed by William Trainor, contract leader, GE set forth its staffing plan for RFP 1004. GE identified the following as "key personnel" proposed for the positions discussed in the FDOT letters: John Vance as bridge superintendent (replacing W. Bruce Chapman); Bruce Morris as mechanic (replacing Gary Berkley); Kelly Green as primary electrician; and John Vance as Supporting electrician. GE attached résumés for each of these personnel. GE indicated that it would utilize PRM, Inc. as a subcontractor to secure the required contract personnel for the contract under RFP 1004, and GE attached letters-of-intent for employment for each of the named key personnel. Each of these letters was signed either by the named employee or by the president of PRM, Inc. FDOT accepted GE’s response in full. The award of the contract for RFP 1004 to GE was not protested. In a letter dated June 26, 1998, signed by Donald R. Abernathy, president, Old Tampa Bay proposed the following key personnel: W. Bruce Chapman as project manager; Gary Berkley as mechanic; Charles Adam Kenney as bridge superintendent (not mentioned in the FDOT letter); and Kelly Green as primary electrician. Old Tampa Bay attached résumés for each of these personnel. The letter made no mention of a supporting electrician. Old Tampa Bay also attached agreements of the employees to serve in their respective positions. However, the signature line on Kelly Green’s statement of acceptance was left blank. Mr. Abernathy testified that he asked Mr. Green to sign the document indicating his acceptance of employment with Old Tampa Bay, but Mr. Green refused. Mr. Abernathy did not reveal this information to FDOT, continuing to maintain that he was within his rights as Mr. Green's employer to include his name in the proposal. FDOT knew from its review of the GE submission that Mr. Green had in fact signed a letter of intent for employment with PRM, Inc. to work on the GE contract. Mr. Alvarez, the FDOT purchasing agent, acted chiefly as a coordinator and as the person ensuring that the procedural requirements of competitive bidding laws were met by FDOT. He admittedly lacked the expertise to make decisions as to the technical aspects of the project. Thus, Mr. Alvarez forwarded the vendors’ responses to Mr. Ooms, the project manager, for his evaluation. Mr. Ooms is a professional engineer, and for the past five years has supervised the operations of all nine bridges covered by RFPs 1003 and 1004. In a memorandum to Mr. Alvarez, dated July 2, 1998, Mr.. Ooms reported his findings and conclusions regarding the vendors’ submissions. As noted above, he found the GE submission acceptable in its identification of PRM, Inc. as a subcontractor and its naming of Vance, Morris, and Green as intended key personnel. Mr. Ooms found acceptable the submission of Old Tampa Bay insofar as it named Chapman, Kenney, and Berkley as key personnel. However, Mr. Ooms noted that the Old Tampa Bay submission provided no documentation of Kelly Green’s commitment to work for Old Tampa Bay. Mr. Ooms also noted that the Old Tampa Bay submission made no mention of John Vance, who had been listed as support electrician in Old Tampa Bay’s original proposal, and listed no substitute who would take over those duties. Mr. Vance had also accepted an offer from PRM, Inc. to work on the GE contract. Thus, Mr. Ooms concluded that the proposed key personnel roster submitted by Old Tampa Bay was not acceptable. By letter to Donald R. Abernathy dated July 8, 1998, Mr. Alvarez conveyed to Old Tampa Bay the "discrepancies" found by FDOT in the Old Tampa Bay submission of June 26, 1998. While stating that FDOT accepted the proposal of Chapman, Kenney, and Berkley for their respective positions, Mr. Alvarez pointed out the problems noted by Mr. Ooms as to Green and Vance. The letter concluded that "the Department still requires that your firm provide, in writing, clarification as to the positions of Primary and Supporting Electricians," and required the response by July 13, 1998. Old Tampa Bay responded by letter to Mr. Alvarez from Mr. Abernathy dated July 10, 1998. The letter provided no explanation as to Mr. Green’s unsigned agreement or Old Tampa Bay's failure to mention Mr. Vance or otherwise address the position of supporting electrician. The letter stated no objection to any of the conclusions contained in FDOT’s letter of July 8, 1998. The letter took no issue with the standard described for "equivalent" electricians. Old Tampa Bay's letter stated that it had selected Mr. Gary McCormick as its primary electrician. The letter noted that Mr. McCormick was finishing a project but would be available for this contract no later than July 27, 1998. The letter stated that while Mr. McCormick was a "skilled and valuable electrical and hydraulic specialist," he had never been required to have an electrician’s license by any prior employer. The letter requested that FDOT waive the license requirement for 90 days, during which time Mr. McCormick would obtain the required license. The letter attached Mr. McCormick’s résumé, which indicated that he had been involved with the Stickney Point bridge from September 1997 until July 1998. The résumé provided no dates for any of his other employment since 1973. The résumé indicated that most of Mr. McCormick’s electrical experience involved repair and installation of elevators. Old Tampa Bay's submission made no attempt to relate Mr. McCormick’s elevator experience to the electrical specifications of the RFP. The letter further stated that Old Tampa Bay was "actively seeking" a supporting electrician, and that Mr. Abernathy would fill the position until the search was completed over the "next few weeks." The letter gave no further indication of the status of Old Tampa Bay's attempt to locate a support electrician. The letter attached the résumé of Mr. Abernathy. Mr. Alvarez forwarded Old Tampa Bay’s July 10, 1998, letter to Mr. Ooms for his review. By memorandum dated July 15, 1998, Mr. Ooms responded to Mr. Alvarez, concluding that the proposed key personnel roster of Mr. McCormick and Mr. Abernathy as primary and supporting electricians was not acceptable. Mr. Ooms’ memorandum first addressed Old Tampa Bay's original statements in its proposal as to Vance and Green, noting that Old Tampa Bay represented both electricians as follows, in his words (punctuation and capitalization not corrected): [Mr. Green] "has worked on FDOT movable bridge contracts for the past 4 years in Sarasota and Manatee counties. His duties range from preventive maintenance to emergency repair" . . . "an intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Green has a Journeyman’s electricians license. * * * [Mr. Vance] has worked on FDOT movable bridge contracts for the past 5 years in Sarasota and Manatee counties. The maintenance he performs covers the entire bridge--the gates, lock motors, drive motors, variable frequency drives, programmable controllers, contactors, limit switches, control panels and resistors." "intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Vance has a [sic] Electrical Contractor’s license. Mr. Ooms contrasted Mr. Green’s qualifications with those of Mr. McCormick, whose résumé showed that he had less than one year’s experience with bridges, did not hold a journeyman electrician’s license, and thus was not "an equivalent substitution for Mr. Kelly Green." Mr. McCormick’s résumé listed his current employer as "Acutec Inc.," his position as "project electrical foreman," and stated that he was "currently finishing Stickney Point drawbridge rehabilitation project. In charge of electrical, PLC, and hydraulic systems installation, trouble-shooting, and start-up. Working closely with Gregg Martin of FDOT, Sarasota." Mr. Ooms testified that Mr. McCormick did not have the qualifications claimed in his résumé. He testified that Mr. McCormick was not in charge of electrical, PLC and hydraulic systems installation on the Stickney Point bridge. He testified that Mr. McCormick was strictly a "wire puller," with "no experience whatsoever to do this type of work." Mr. Ooms took issue with Mr. McCormick’s claim that he was "in charge" of the installation of the PLC, or programmable logic controls. Mr. Ooms testified that Mr. McCormick’s employer, Acutec, was involved with writing the PLC program, setting up the parameters, checking out the hydraulics, and performing the interfacing, but that Mr. McCormick was simply running wires from point-to-point pursuant to instructions from others. Mr. Ooms testified that he knew these facts from watching at first-hand the work being performed on the Stickney Point bridge. Mr. Ooms did not call Acutec to verify the statements in Mr. McCormick’s resume. Mr. Ooms stated that there was no need to call Acutec, as he was out on the bridge and could see for himself what Mr. McCormick was doing. PLCs, or programmable logic controls, are the means by which newer bridges are controlled by computer. The PLC sequences the computer program to constantly monitor the condition and operation of the bridge. The PLC technology is not unique to bridges. It is common in many manufacturing operations, and is in place on two of the five bridges covered by RFP 1003. The remaining three bridges have a manual relay control system. Old Tampa Bay did not dispute that PLC experience is necessary to perform the work as an electrician on this contract. Mr. Ooms noted that Mr. McCormick’s résumé claimed PLC experience, but that when the time came for the contractor to deliver the laptop computer with the PLC programs to run the renovated Stickney Point bridge, Mr. McCormick could not even run the program on the computer. Mr. Ooms testified that if one cannot run the computer program, one cannot do anything on a computer controlled bridge. Mr. Ooms’ testimony as to the qualifications of Mr. McCormick is credited. While Mr. Ooms might have confirmed his conclusions with Mr. McCormick’s employer, he cannot be found to have acted arbitrarily in relying on his own extensive observations of Mr. McCormick’s job performance. Old Tampa Bay offered no evidence to dispute the factual underpinnings of Mr. Ooms’ decision that Mr. McCormick was not an equivalent substitute for Kelly Green. Mr. Ooms’ July 15, 1998, memorandum also rejected Mr. Abernathy as the temporary supporting electrician. As quoted above, the memorandum noted Old Tampa Bay's representation that John Vance, the supporting electrician it originally proposed, has worked on FDOT movable bridge contracts for the past five years in Sarasota and Manatee counties, has intimate knowledge of these bridges, and has an electrical contractor’s license. Mr. Ooms noted that Mr. Abernathy does not have an electrical contractor’s license. Mr. Ooms also took issue with Mr. Abernathy’s résumé statement that he has acted as a bridge inspector for the past eight years for Kisinger Campo and Associates, a company that FDOT hires to perform bridge inspections. Mr. Ooms wrote that in the five years that FDOT has let out the operations and maintenance contracts, he has never "seen or known of Mr. Abernathy visiting a Sarasota or Manatee county bridge or troubleshooting a bridge problem." He testified that Kisinger Campo could not have used Mr. Abernathy as a bridge inspector because he lacked the required engineer’s license or certification as a bridge inspector. Mr. Ooms admitted that Kisinger Campo does not always tell him who is performing the inspections. Mr. Ooms made no inquiries of Kisinger Campo to verify Mr. Abernathy’s résumé. Mr. Abernathy testified that he was in fact an electrical inspector for Kisinger Campo for eight years and that in 1997 he personally performed inspections on every bridge covered by RFP 1003, including the electrical, lighting, and PLC systems. Mr. Abernathy conceded that he does not have an electrical contractor’s license. Mr. Abernathy’s testimony is credited as to his experience as a bridge inspector. In the case of Mr. McCormick, Mr. Ooms reasonably relied on his own extensive observations. As to Mr. Abernathy, Mr. Ooms attempted to rely on what he did not observe. Mr. Ooms chose to assume, without knowledge or verification, that Mr. Abernathy’s résumé was false. This assumption was arbitrary, and cannot be credited. Mr. Ooms’ decision to reject Mr. Abernathy was nonetheless reasonable. Mr. Abernathy did not possess the requisite license, and admitted that his most recent experience in actually performing bridge electrical maintenance and repair was more than twenty years ago. By letter to Mr. Abernathy dated July 17, 1998, Mr. Alvarez conveyed FDOT’s rejection of Old Tampa Bay’s proposal pertaining to the electrician positions. The reason for rejection was stated as follows: As stated within the Request for Proposal Package, if you are proposing to substitute key personnel you must provide an equivalent substitution; equivalent meaning as of [sic] the same caliber, experience, expertise or better than the individual originally proposed. . . . Please understand, the Department is looking forward in [sic] entering into an Agreement with your firm, [sic] however, it cannot accept anything less than what was originally proposed. Mr. Alvarez’ letter enclosed Mr. Ooms’ memorandum of July 15, 1998, and offered Old Tampa Bay another opportunity to submit substitute electricians no later than July 27, 1998. By letter from Mr. Abernathy to Mr. Alvarez, dated July 27, 1998, Old Tampa Bay submitted a new list of proposed substitutes. The text of the letter stated, in full: We have selected Mr. Steven Manning, Master Electrician License Number 3994, Hillsborough County to be our primary electrician. Attached is his resume. We have selected Mr. Adrian Cook as the supporting electrician, Journeyman License Number JE776, Hillsborough County. We have selected Mr. Wayne Cano as an electrician’s helper. Hillsborough County licenses have full reciprocity with Manatee and Sarasota Counties. Résumés of all three proposed employees were attached, along with copies of the relevant licenses and certificates of completion of various professional training courses. Mr. Manning’s résumé contained sketchy descriptions of the kinds of electrical work he had performed, and gave no indication that he had any experience working with computers or PLCs. Mr. Manning’s résumé revealed no experience with moveable bridge maintenance or repair. Mr. Manning had no experience as an electrician on the FDOT bridges. Mr. Manning’s résumé indicated that his experience included industrial electrical experience intermittently during eight years of electrical work. The résumé indicated "industrial and commercial electrical work," "working in fuel terminals, working with motor controls," "remodeling tenant spaces," "working with new commercial," "working with commercial remodeling, and service work," "traveling around Florida and Georgia remodeling Pizza Huts," "residential and commercial sales, estimating jobs, job foreman, billing and scheduling, handling of permits," and "working with industrial and commercial, service work, remodeling and new construction." Old Tampa Bay's submission offered no specific information or explanation of how Mr. Manning’s varied experience related to the specifications for electrical maintenance and repair in the RFP. Old Tampa Bay had obtained Mr. Manning’s name by calling an electrical company, Southern Power and Controls, and asking for recommendations of personnel with qualifications and experience equivalent to Mr. Green’s. Southern Power and Controls is an industrial electrical firm specializing in industrial controls, motor controls, switch gears, limit switches, and PLCs. Old Tampa Bay would have paid a finder's fee to Southern Power & Controls for any employees who went to work for Old Tampa Bay on this contract. Old Tampa Bay provided Southern Power and Controls with the documentation it had submitted to FDOT regarding the qualifications and experience of Vance and Green. Robert Harwell, a registered electrical engineer and principal of Old Tampa Bay, had discussions with Southern Power and Controls as to the qualifications of the candidates it sought. No person from Southern Power and Controls appeared at the hearing to explain the process by which they selected Mr. Manning. No person from Old Tampa Bay ever interviewed Mr. Manning. Mr. Manning did not testify at the hearing. Old Tampa Bay proposed Adrian Cook as a supporting electrician. Mr. Cook’s résumé indicated that he was a licensed journeyman electrician, with four years’ experience as an electrician and two years as an apprentice. Mr. Cook’s résumé indicated two years of unspecified commercial and industrial work, but no moveable bridge experience. Old Tampa Bay obtained Mr. Cook’s name from Southern Power & Controls, asking for personnel with qualifications and experience equivalent to Mr. Green’s. No person from Southern Power & Controls appeared at the hearing to explain the rationale for choosing Mr. Cook. No person from Old Tampa Bay ever interviewed Mr. Cook. Mr. Cook did not testify at the hearing. Old Tampa Bay submitted Mr. Wayne Cano as an "electrician’s helper." Old Tampa Bay did not specify what function Mr. Cano would serve or what actions he would perform as an "electrician’s helper." Neither the RFP nor Old Tampa Bay's proposal contains any mention of an "electrician’s helper." Mr. Cano’s résumé did not indicate an electrician’s license. Old Tampa Bay did not state that it had any intention to require Mr. Cano to obtain an electrician’s license. Mr. Cano’s résumé did not indicate any moveable bridge experience or experience on other FDOT projects. Again, Mr. Alvarez forwarded the Old Tampa Bay letter and attachments to Mr. Ooms for his review. Mr. Ooms provided his response by memorandum dated August 6, 1998. Again, Mr. Ooms outlined the qualifications and experience of the electricians originally proposed, Kelly Green and John Vance, as set forth in Old Tampa Bay's own proposal. Mr. Ooms wrote as follows (punctuation and capitalization not corrected): Mr. Green’s experience were [sic] listed as follows. "has worked on FDOT movable bridge contracts for the past 4 years in Sarasota and Manatee counties. His duties range from preventive maintenance to emergency repair . . . an intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Green has a Journeyman’s electrician license. Mr. Vance’s experience were [sic] listed as follows. "has worked on FDOT movable bridge contracts for the past 5 years in Sarasota and Manatee counties." "The maintenance he performs covers the entire bridge-- the gates, lock motors, drive motors, variable frequency drives, programmable controllers, contactors, limit switches, control panels and resistors." "intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Vance has a [sic] Electrical Contractor’s license. Mr. Green and Mr. Vance each have over four years of "on the Bridge" experience trouble shooting non functioning systems. They have worked on nine different bridges that were 30-40 years old with antique controll [sic] systems and on bridges recently rehabilitated with modern computer controlled systems. They have years of experience in reading and analyzing bridge ladder logic programs and trouble shooting problems and solutions. All these bridges were operational and any loss of service was quickly reported. An outage can easily block traffic for several miles in minutes generating calls from the sherrifs [sic] department. In addition, any breakdown in service has severe political consequences due to the Ringling bridge and Anna Maria Bridge replacement program. A problem on Ringling Bridge can cause a [sic] hour detour and missed flights. On page C-1 of the contract it states "The Contractor’s personnel that will perform the work required by this Section shall be trained and well experienced in start-up and maintenance of equipment . . . and will have headquarters within Sarasota/Manatee County" . . . On page A-3.2 is [sic] states "the Contractor shall initiate corrective action within fifteen (15) minutes following the malfunction." further down on Page C-1 of the contract "the Contractor agrees to provide men and equipment to a bridge sites [sic] within 30 minutes of notification of any emergency equipment failure". Mr. Ooms contrasted the experience and qualifications of the proposed substitutes as follows (punctuation and capitalization not corrected): Mr. Steven Manning experience [sic] in industrial electrical work does not start until 1997. It does not show any bridge related work. His training certificate in Electrical ladder Drawings" is for a one day 7 contact hours session. The "well experienced" requirement is not clearly indicated by his resume. Mr. Adrian Cook also does not show any bridge related work and the "well experienced". Mr. Wayne Cano has 11 years of industrial experience but no bridge experience or electricians license. In conclusion Old Tampa Bay enterprises needs to provide us with equivalent substitutions. Specifically licensed electricians with a minimum of four years experience in diverse bridge electrical configuration; with old relay logic operation, well experienced in PLC controllers from various manufactures [sic]; the ability to read and interpret ladder logic drawing; the ability to program plc’s. The Department’s inclusion of response time in the contract clearly indicates our desire for prompt and efficient emergency repair work. In other words the Department would like the equivalent of Mr. Green and Mr. Vance in the original proposal who’s [sic] experience will "keep bridge down time and repair time to a minimum." By letter to Mr. Abernathy dated August 13, 1998, Mr. Alvarez forwarded FDOT’s rejection of Old Tampa Bay’s proposed substitutes. The letter essentially reiterated the contents of the memorandum quoted above, and informed Old Tampa Bay that it would have one last opportunity to provide FDOT with equivalent or better substitutions for the electrical key personnel. Old Tampa Bay’s response would be due no later than August 24, 1998. Mr. Alvarez testified that as to this and his prior letters to Mr. Abernathy, he essentially acted as a conduit for the actual decision-maker, Mr. Ooms. Mr. Alvarez wrote the letters because he was the designated contact person in the FDOT contracts office, not because of any personal expertise or authority he possessed to deal with the issue of the qualifications of the proposed key personnel. By letter from Mr. Abernathy to Mr. Alvarez, dated August 21, 1998, Old Tampa Bay informed FDOT that "we are unable to locate electricians which meet or exceed the qualifications of those we proposed, i.e., Mr. Green and Mr. Vance. Please proceed as necessary." Old Tampa Bay’s letter did not take issue with any of the conclusions set forth in Mr. Alvarez’ letter of August 13, 1998. On August 24, 1998, FDOT posted a revised proposal tabulation finding Old Tampa Bay nonresponsive and listing GE as the intended awardee of the contract for RFP 1003. At the hearing, Mr. Ooms testified that he did not know Mr. Manning, Mr. Cook, or Mr. Cano, had no personal knowledge of their background or experience, and relied on their résumés in making his decision. Mr. Ooms felt that Mr. Manning, while a master electrician, lacked sufficient experience on PLCs and had no experience working on bridges. Mr. Ooms noted that the only indication of electrical ladder drawing or computer experience on Mr. Manning’s résumé was a seven-hour continuing education course in electrical ladder drawing. Mr. Ooms’ undisputed testimony was that a single seven-hour course was insufficient to provide the expertise needed to perform the duties required of an electrician on these bridges. Mr. Ooms admitted that John Vance and Kelly Green lacked PLC experience when they started working on the bridges, and were trained by FDOT. However, Mr. Ooms rejected Old Tampa Bay’s suggestion that Mr. Manning could be similarly trained on the job. Vance and Green were trained in connection with the installation of PLC equipment on the Cortez Bridge in 1996. Mr. Ooms testified that this training was simply a part of the rehabilitation of the bridge, and that PLC experience was not a prerequisite at the time Vance and Green were hired. Mr. Ooms further distinguished this situation by noting that the issue here is not simply qualifications, but equivalency. Mr. Ooms stated that because Old Tampa Bay’s winning proposal was based on the presence of Vance and Green, any substitutes for Vance and Green must not only meet the RFP specifications but must be equivalent to the experience of Vance and Green, which included PLC experience. Mr. Ooms testified that he rejected Adrian Cook for the same lack of PLC experience. Mr. Cook held the required journeyman electrician’s license, but his résumé gave no indication of PLC or troubleshooting experience. Mr. Ooms testified that he called Mr. Cook’s current employer, who vouched for him as a "good man," but provided no details as to his PLC experience. Mr. Ooms also admitted that he did not ask the employer about Mr. Cook’s PLC experience. As to Mr. Cano, Mr. Ooms testified that he appeared well qualified but lacked the required journeyman electrician’s license, and lacked bridge experience. Mr. Ooms was impressed by Mr. Cano’s PLC and ladder logic experience, and might have approved him but for the lack of the required license. Mr. Ooms acknowledged that Kelly Green did not have his journeyman electrician’s license when he started work on the bridges. Mr. Ooms testified that he was unaware of that fact at the time Mr. Green was hired. Douglas Blake, project engineer for GE, affirmed that in the five years GE has been performing bridge operations and maintenance, FDOT has never asked any electrician to produce a license. Mr. Blake testified that performance of an electrician’s job on these bridges does not require permitting, and that there is no license exposure to an electrician working these jobs. Mr. Blake’s opinion was that the license requirement is merely a contract tool FDOT can use to eliminate substandard bids. No witness for FDOT assented to Mr. Blake’s characterization of the license requirement. FDOT’s consistent position was that a prospective electrician must have at least a journeyman electrician’s license, as set forth in the RFP and the Bridge Manual. Mr. Blake testified that Manning, Cook, and Cano all appeared to be worthy candidates to be bridge electricians, insofar as their electrical technical qualifications appeared to compare favorably to those of Vance and Green. No evidence was presented that Mr. Ooms had any knowledge of Mr. Blake’s opinion at the time he made his decision, or that such knowledge would have altered that decision. Lane Tyus, a GE electrical engineer with experience on these bridges, likewise testified that the résumés of Manning, Cook, and Cano would pass his initial screening and that he would make a final decision in a face-to-face interview. No evidence was presented that Mr. Ooms had any knowledge of Mr. Tyus’ opinion at the time he made his decision, or that such knowledge would have altered that decision. At the hearing, Old Tampa Bay produced a list purporting to show 25 electricians whose hiring for bridge work was approved by FDOT for various districts during the period 1991 through 1998, despite the fact that none of the 25 had prior bridge experience. This list included Mr. Vance and Mr. Green in District One, where Mr. Ooms works. Mr. Ooms disclaimed knowledge as to the approval practices of other districts, which in any event have no relevance to this proceeding. Mr. Ooms again averred that this situation is different than that prevailing when Vance and Green were hired, because the substitutes here proffered by Old Tampa Bay must not only meet the RFP requirements but must be the equivalent of Vance and Green in experience and expertise. Mr. Abernathy testified that he believed the team of Manning, Cook and Cano was the equivalent of Vance and Green. He testified that any modern industrial electrician must have experience with PLCs, and will not necessarily spell-out that experience on his résumé. He testified that it was his "absolute firm belief" that no matter whose names he submitted to FDOT as substitute electricians, they would be rejected. Mr. Ooms testified that he neither favored GE nor disfavored Old Tampa Bay. He admitted having greater familiarity with GE’s personnel because they have been working on the bridges for the last five years. He testified that he considers it his professional obligation to work with whoever holds the contract. Aside from the obvious licensure deficiency for Mr. Cano, these proposed substitutes may well have been equivalent to Vance and Green. However, their equivalence could not be ascertained from Old Tampa Bay's submissions. Their résumés did not clearly establish their qualifications in areas that Old Tampa Bay knew or should have known were critical to FDOT. The agency made its expectations very clear to Old Tampa Bay as to what was expected of equivalent substitutes. Old Tampa Bay did nothing to expand upon the sketchy résumés of these persons, or to explicate the relationship between their experience and the work to be performed on the bridges. Mr. Ooms cannot be faulted for failing to consider information that the proposer did not provide. It is found that Mr. Ooms was not biased in rejecting Manning, Cook, and Cano. Old Tampa Bay argues that the disparity in the scoring of the technical proposals between Mr. Ooms and the other two evaluators demonstrates his bias in favor of GE. However, as noted above, all three evaluators gave GE the highest marks for RFP 1003. In fact, the scores for GE’s proposal given by the other two evaluators were significantly higher than the score Mr. Ooms gave to GE’s proposal. The fact that Mr. Ooms found an 18-point disparity between the proposal of GE and the proposals of the other two bidders does not of itself indicate bias in favor of GE on his part, any more than the fact that his score for GE was 15 to 18 points lower than the GE scores by the other evaluators indicates a bias against GE. FDOT demonstrated no bias against Old Tampa Bay in this process, providing Old Tampa Bay repeated opportunities to provide satisfactory substitutes for Green and Vance. Old Tampa Bay attempted to show disparate treatment by introducing evidence showing that FDOT allowed GE to substitute Kelly Green for an electrician named Charles Cave in 1995, after award of the previous contract, despite the fact that Green at the time had no experience working on the bridges and did not obtain a journeyman electrician’s license until approximately two months after he commenced work. Assuming arguendo that FDOT’s actions in awarding this contract may be attacked by showing different agency behavior in prior contracts, the evidence adduced by Old Tampa Bay is insufficient because it gives no indication of the qualifications of Charles Cave, the electrician replaced by Mr. Green. There is no way to determine whether Mr. Green was or was not an equivalent substitute for Mr. Cave, and thus no way to establish disparate treatment by FDOT from one contract to the next. Old Tampa Bay further asserts that FDOT’s treatment of Mr. Green when he commenced work indicates that FDOT had the discretion to allow Mr. McCormick to obtain his journeyman electrician’s license after commencing work. Assuming arguendo that Old Tampa Bay’s assertion is correct, the facts establish that the lack of a license was a secondary concern in the rejection of Mr. McCormick. Mr. Ooms testified that his rejection of Mr. McCormick was primarily based on lack of bridge and PLC experience, and the overstatement of qualifications on Mr. McCormick’s résumé. Even if Mr. McCormick possessed the required license, Mr. Ooms would have properly rejected him. Old Tampa Bay challenged FDOT’s allowing GE to make changes in its management personnel after being awarded the contract for RFP 1003. The three upper-level managers in question were located in Atlanta, had nothing directly to do with the operation of the bridges, and were not "key personnel" as described in the RFP and Bridge Manual. GE informed FDOT of the change in a courtesy letter, dated October 20, 1998, more than five months after submission of the original proposals. The RFP did not require these remote persons to be identified by name at all, let alone require GE to freeze them in place as a condition of its contract. As noted above, the facts established that Old Tampa Bay included the name of John Vance in its proposal though it knew or should have known that Mr. Vance had no intention of working for Old Tampa Bay on this project. Old Tampa Bay attempted to demonstrate that GE did substantially the same thing when it included the name of Mr. Lane Tyus in its proposal as its registered electrical engineer. Mr. Tyus indeed testified that he did not know that GE had included his name in the proposal at the time it was submitted, and was not made aware of his inclusion until some time after Old Tampa Bay filed its protest. However, Mr. Tyus also testified that he knew his résumé was kept on file by GE precisely for inclusion in proposals. Further, he testified that he has been involved with the contract for these bridges since 1992, that he was not surprised at his inclusion, and that he was prepared to undertake the tasks described in the GE proposal. Thus, there is no comparison between Mr. Tyus’ situation with GE and that of Mr. Vance with Old Tampa Bay. Finally, Old Tampa Bay attempted to demonstrate bias in the fact that FDOT allowed GE to submit John Vance's name as bridge superintendent for RFP 1004, despite his lack of experience in that position. However, Mr. Ooms testified that Mr. Vance was in fact more than qualified for the position, in that the training requirements set forth in the Bridge Manual for electricians such as Mr. Vance include all the requirements for bridge superintendents as well as electrical courses.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Department of Transportation enter a final order dismissing the protest filed by Old Tampa Bay Enterprises, Inc. and awarding the contract for RFP-DOT-97/98- 1003, Bridge Tending/Maintenance and Repair Services for Five Movable Bridges, Sarasota and Manatee Counties, to General Electric Industrial Systems. DONE AND ENTERED this 27th day of May, 1999, in Tallahassee, Leon County, Florida. LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 1999. COPIES FURNISHED: Jonathan Sjostrom, Esquire Steel, Hector & Davis LLP 215 South Monroe Street, Suite 601 Tallahassee, Florida 32301-1804 Brian F. McGrail, Esquire Office oif the General Counsel Department of Transportation 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Robert A. Rush, Esquire Robert A. Rush, P.A. 726 Northeast First Street Gainesville, Florida 32601 Thomas F. Barry, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Pamela Leslie, General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458
Findings Of Fact On January 8, 1988, the DOT published a Notice To Contractors that stated in pertinent part: The Florida Department of Transportation plans to receive bid proposals for the following design/build projects. This advertisement is issued to give advance notice of our design/build intentions; to allow interested parties to form design/build affiliations; and to submit letters of interest for specific project(s). For the advertised design/build projects, the contracting firm shall be prequalified with the Department in accordance with Rule 14-22 in construction class Hot Plant-Mix Bituminous Base & Surface Courses. Consultants affiliating with the contracting firm must be prequalified with the Department prior to final selection in the following types of work: Type B (Standard Roadway Design) Type K (Standard Contract Administration and Inspection) Firms shall submit a separate letter of interest for each of the following projects for which they wish to be considered: * * * State Project No. 01050-1519 CHARLOTTE COUNTY: Level, widen, and resurfacing of S.R. 776. The limits of the project will be from approximately 750 feet west of Sunnybrook Boulevard to 650 feet east of C.R. 771. Approximate length 3.3 miles. D.B.E. Goal 10.0 percent. Bonding Requirement $1,000,000. * * * Construction work may consist of resurfacing, construction of paved shoulders, extension of existing cross- drains, installation of mitered end sections on side drains, shoulder work, signing and pavement marking, sodding and grassing. Consultant services will include, but not be limited to, Construction Engineering Inspection and the preparation of construction plans in accordance with the FDOT Plans Preparation Manual (1985) and other applicable criteria, to include as appropriate: Utility Adjustment Plans, summary of pay items, signing and pavement marking plans, maintenance of traffic details, drainage design, pavement design, and Special Provisions. Any firm who has not been qualified by the Department and would like to be considered for these projects should request a Letter of Interest Submittal Package from the Bureau of Contractual Services in Tallahassee, 904/487-3487. The Department shall determine the relative ability of each firm to perform the services required for each project. Determination of ability shall be based upon staff training and experience, firm experience, location, past experience with the Departent, financial capacity, past performance and current and projected work load. The Department shall select (shortlist) not less than three firms deemed to be the most highly qualified to perform the required services to proceed with preparation of bid & technical proposals. Scope of services desired, schedules, blank contracts and special instructions will be provided at pre-bid/scope of services meeting, which will be held within 2 weeks following shortlisting. * * * SUBMITTAL REQUIREMENTS: Firms desiring consideration for this project must submit two (2) copies of their qualifications to the requesting unit listed below for each project that they are interested in. Information that must be included are the name of the project(s) to which the letter of interest applies, the names of the firms involved in the affiliation, firm's experience, location, past experience with the Department, and current and projected work load. RESPONSE EVALUATION: All respondents will be evaluated and must be determined by the Department to be qualified to do business in Florida and must be prequalified to perform the advertised work requirements prior to final selection. 2/ * * * Pursuant to DOT Rule 14-25.024(1), any person adversely affected by not being selected to provide aid proposals must file with the Clerk of Agency Proceedings, Mail Station 58, Room 562, Haydon Burns Building, 605 Suwannee Street, Tallahassee, Florida 32399-0458, a written Notice of Protest within 72 hours of the posting of the firms selected to prepare proposals. The firms selected to prepare bid proposals will be posted with the Clerk of Agency Proceedings on the 19th day of February, 1988. After filing a written Notice of Protest (within 72 hours of posting), a formal written protest setting forth a short and plain statement of the matters asserted by the Protestor shall be filed with the Clerk of Agency Proceedings within ten days after filing of the Notice of Protest. A failure to file a timely protest constitutes a waiver of Chapter 120 proceedings. At the time of the Notice To Contractors, and until March 13, 1988, there was no DOT rule establishing design-build procedures under Section 337.11(5), Florida Statutes (1987). Six design-build teams submitted letters of interest in response to the Notice To Contractors. Two teams later were eliminated, leaving four: (1) Ajax (the contractor)/Hole, Montes (the design consultant/construction engineering inspector (CEI)); (2) APAC/Harris; (3) Harper Bros./Aim Engineering; and (4) Wendel Kent-Gator Asphalt/Kunde, Sprecher, Yaskin. Before February 18, 1988, both DOT's central office in Tallahassee and its district office, District I, in Bartow, compiled rankings for the firms that had submitted letters of interest. Although both offices attempted to do the same thing--compile evaluations based on certain criteria--they set about their tasks differently. In Tallahassee, Mr. William Laufman and his staff developed evaluation forms complete with instructions. The forms outlined the weight to be assigned each criterion when evaluating the contractor, the design consultant, and the CEI (Construction Engineering Inspection) ability of the consultant firm. The instructions set forth the method by which the evaluations were to be done. The idea behind the evaluation forms was to promote uniformity among the evaluators. The forms were developed during the two weeks before February 16, 1988, and were completed on that date. The weight to be assigned each criterion was determined by a consensus of people within the construction, design, and CEI departments. These decisions were made when the forms were developed. The forms and the backup data used in Tallahassee to do the evaluations were "faxed" to the district office to be used when doing its evaluations. The letter of interest packets were also provided. According to the evaluation forms used in Tallahassee to evaluate contractors, the firms' overall experience, past DOT performance grades, and current and projected workload were most heavily weighted. These items were twice as important as financial capacity and location. For consultant firms and CEI ability, past performance grades on DOT jobs was most important while location was least important. The firm's experience, staff training, and current and projected workload were weighted equally. The information the central office considered necessary to do the evaluations included information contained in the letter of interest packets, the prequalification file of the contractors and consultants, and DOT documents regarding DOT experience. Some information related to certain criteria could only be gleaned from a review of the prequalification file. For example, overall firm experience and staff training and experience would be detailed in that file. All of this information was available to DOT to do the evaluations. The central office staff ranked APAC/Harris highest with a combined 82 score (contractor-62, design consultant-11, CEI consultant-9). The central office staff ranked Wendel Kent-Gator/Kunde, Sprecher & Yaskin second highest with a 78 score (contractors-56, design consultant-11, CEI consultant-11). The central office staff ranked Harper Brothers/Aim Engineering third highest with a 66 (contractor-48, design consultant-7, CEI consultant-11). The central office staff ranked Ajax/Holes, Montes fourth with a 63 (contractor-50, design consultant-7, CEI consultant-6). In contrast, the district office performed its evaluation and ranking on the morning of February 18, 1988, the date established for a teleconference meeting at which the "shortlist" would be determined. That morning, Mr. John Dewinkler, District I Director of Production, assigned Marshal Dougherty, District I Professional Services Engineer, the task of ranking the design-build teams. Dougherty had only a list identifying the teams from which to work. Dougherty ranked the design-CEI components of the teams and enlisted Donald Prescott, District I Assistant to District Construction Engineer, to rank the construction contractor component of the teams. Due to time constraints and problems experienced by the central office computer system that morning, neither was able to resort to information normally available in the central office. Dougherty relied on his own knowledge of team members and information available at the district office in Bartow. Prescott telephoned the four resident offices in District I for input on the relative abilities of the construction contractors. Prescott and Dougherty took 1 1/2 - 2 hours to do their work. Dougherty then prepared team rankings that combined his ranking with Prescott's, giving equal weight to each. Their evaluations did not strictly follow the weighted criteria set out in the central office evaluation forms. Of the four, Mr. Prescott ranked Harper Brothers first, Wendel Kent- Gator second, Gator third, APAC fourth, and Ajax fifth. The letter of interest using Gator Asphalt as the independent contractor was eliminated as a result of the competition conflict. Of the four, the district's overall rankings were Wendel Kent- Gator/Kunde first, Harper/Aim second, APAC/Harris third and Ajax/Hole, Montes last. On the afternoon of February 18, 1988, the Technical Committee convened by conference call to determine the shortlist for the projects listed on the Notice To Contractors. The members of the committee included Wally Giddens, Director of Division of Preconstruction and Design; Murray Yates, Director of Construction; John Dewinkler, Director of Production; and Donald Prescott, Assistant to District Construction Engineer in District I, Bartow. Messrs. Dewinkler and Prescott participated by telephone from their offices in Bartow; the others were in Tallahassee. Several other people were present in Tallahassee for the meeting. They included: William Laufman, Project Manager; Jack Trickey, Chief of the Bureau of Adjunct Value Engineering; Ken Morefield, Bill Dayo, and Chuck Robshaw. The central office staff (Tallahassee) recommended that Ajax be among the firms to be shortlisted. However, the district people, Messrs. Dewinkler and Prescott, expressed concerns over Ajax and requested Ajax not be placed on the shortlist. The district's "concerns" included lack of familiarity with Ajax's design team, present problems on current jobs with respect to performance and schedules, and the potential for claims on existing contracts. The concerns expressed by the district were not apparent in the information available to the central office, and some discussion was held. Since the project was going to be performed in the district, the committee deferred to the district's request and did not shortlist Ajax. The firms placed on the shortlist by the committee included: APAC/Harris; Wendell Kent-Gator/Kunde; and Harper/Aim. APAC is a top rated contractor with a lot of DOT experience. It was prequalified to do the type of work required for this project when it submitted its letter of interest. Its average grade on reports on past performance as a contractor or subcontractor for the DOT is 89.81. APAC's consultant, Harris, was also rated highly and has substantial DOT experience. Harper Brothers is a contractor prequalified for the work required for this project. While Harper Brothers has not done work for FDOT in the past three years, it still rates higher than any other contractor working in the Ft. Myers area based on past DOT work. Harper remains prequalified and has received an ability factor rating of 14, equating to a 93-98 ability score. Its design consultant, Aim Engineering, has DOT experience. Wendell Kent is a contractor that was not prequalified for the type of work required for this project--hot bituminous asphalt mix work--when it submitted its letter of interest. Wendell Kent has DOT experience, although not in this type of work, and that experience consists of only one job within the past eight years in the district where this job will be performed. Wendel Kent's average grade on reports of past performance as a contractor or subcontractor for the DOT is 93.86. Wendel Kent affiliated with Gator Asphalt, which was prequalified for this project. Gator Asphalt's average grade on reports of past performance as a contractor or subcontractor for the DOT is 89.84. Wendell Kent is to be the prime contractor on this project. It would be responsible for the overall administration of the project and construction of all items except the asphalt paving, which would be done by Gator. Wendel, Kent-Gator Asphalt's design consultant, Kunde, Sprecher, Yaskin has done design work for the DOT in the past and performed well. Ajax is prequalified and has DOT experience, including recent experience. In the last three years, Ajax has done eight or nine DOT jobs amounting to approximately $11.4 million of work. The DOT concedes that Ajax is a capable contractor. But Ajax's average grade on past performance as a contractor or subcontractor for the DOT is 86, lowest of the four. In addition, comments relating to Ajax are somewhat more negative than those of other contractors. Only Ajax received negative comments on its ability to schedule construction work, a factor to be specifically considered in the selection of a design/build contractor. For example, the comment for FDOT Project #01050-3514 in Charlotte County was: "They don't provide day-to-day supervision on the- project. They generally leave that up to whatever sub is working on the project. From a project engineer's standpoint, Ajax makes a good subcontractor but a poor prime contractor." For Project #12070-3513 in Lee County, the comment was: "This contractor could have taken more interest in controlling construction operations to achieve a better quality of construction." Ajax's more significant scheduling problems arose during the first few years of operations in Florida. After DOT criticism, Ajax has improved in this area. Of the eight or nine DOT jobs Ajax has done in the last three years, there has been a net total of four days overtime on all jobs. (This net total is arrived at by subtracting the number of days "undertime" from the overtime days to arrive at the net number of days over the time allowed by the contracts.) But of the last 13 jobs Ajax has done for the DOT, Ajax was behind schedule on seven. On two jobs started in 1984, Ajax was considerably behind schedule (15 days) on one and extremely behind schedule (51 days) on the other. Ajax knows of no potential claims on its current job. In the last three years, Ajax has had only one claim, for $6,000, that was resolved in favor of Ajax. Ajax does have a pending claim on a 1984 job that is not yet resolved. The claim is on behalf of a subcontractor. Until resolved, the claim is just a difference of opinion or a difference of contract interpretation. Ajax was also involved in a potential claim on a project known as "the embankment job." There was an error in the plans for this job at the time the contract was bid. Ajax brought this to the attention of Carson Carner, the resident engineer, who advised Ajax to bid the project as it was. Ajax did and was awarded the contract. Shortly, thereafter, Ajax requested a change order to allow for extra materials considered necessary due to the error Ajax saw-in the plans. Ajax pursued this because this error equalled approximately 10 percent of the job, which amounted to approximately $200,000. District DOT officials refused to see the error and denied the request for the change order. Ajax ultimately retained an attorney who convinced DOT of the error in the plans, and the change order was approved. Finally, mention should be made of the non-contractor components of the design/build teams. APAC's partner, Frederick R. Harris, has done design work for FDOT in the past. Harper Brothers' partner, Aim Engineering, has construction engineering inspection (CEI) experience with the Department, including a large amount of work in the Lee County area. Wendel Kent-Gator's consultant, Kunde, Sprecher and Yaskin, had considerable design experience with the Department and also had done CEI work for the agency. Ajax selected the design, CEI firm of Hole, Montes as its consultant. This firm was Ajax's second choice and was selected only when Aim Engineering was submitted by Harper Brothers. While prequalified to do so, Holes, Montes had done neither design nor CEI work for the Department.
Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Respondent, the Department of Transportation, enter a final order excluding the Ajax/Hole, Montes team from the short list for State Project No. 01050-1519 if that is how the DOT chooses A exercise its discretion. RECOMMENDED this 21st day of June, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of June, 1988.
The Issue The issues in this case are whether Respondent committed the allegations contained in the Amended Administrative Complaint and, if so, the penalty that should be imposed.
Findings Of Fact The Parties Petitioner Department of Health has regulatory jurisdiction over licensed dentists such as Respondent. In particular, Petitioner is authorized to file and prosecute an administrative complaint, as it has done in this instance, when a panel of the Board of Dentistry has found probable cause exists to suspect that the licensee has committed one or more disciplinable offenses. Respondent Pasquale Almerico, Jr., a graduate of the University of Pennsylvania School of Dental Medicine, has been licensed to practice dentistry in the State of Florida since 1984. Respondent's address of record is 704 North Alexander Street, Plant City, Florida. The Events On February 16, 2010, patient P.D., a 60-year-old female, presented to Respondent's dental office to discuss the replacement of a partial, removable denture that was causing discomfort. The partial denture, which another dentist installed some 15 years earlier to fill the gaps created by lost teeth in the lower-left portion of P.D.'s mouth——specifically, teeth numbers 18 and 19——was secured by a metal “C-clasp” attached to tooth number 20. Noticing immediately that the partial denture was ill fitting, Respondent recommended its replacement with a three- unit cantilever bridge at teeth numbers 19, 20, and 21. As explained during the final hearing, a cantilever is a type of fixed bridge that attaches to adjacent teeth on one end only. Thus, in this instance, abutment crowns on teeth numbers 20 and 21 would connect to a pontic (an artificial tooth) extending into the gap formerly occupied by tooth number 19. P.D. consented to the suggested treatment during the February 16 office visit, at which point Respondent removed the existing crown on tooth number 20, took a radiograph of the relevant area, and performed a thorough clinical examination of teeth numbers 20 and 21. Although Respondent observed some abrasion2/ on the distal surface of tooth number 20 where the C- clasp of the partial denture had been attached, the teeth otherwise appeared healthy——i.e., neither Respondent's direct visualization of the teeth nor his review of the radiograph suggested the presence of decay. At the conclusion of the February 16 visit, Respondent prepared teeth numbers 20 and 21 (a process that involves the use of a drill to remove enough enamel from the teeth so that the bridge will fit properly), took a final impression, and provided P.D. with a temporary bridge. P.D. returned to Respondent's office on March 3, 2010, at which time Respondent removed the temporary bridge and performed a “try-in” with the metal framework of the new bridge. During this process, Respondent directly visualized tooth number 20 and, as was the case during the previous visits, observed no signs of decay.3/ However, Respondent noticed that the metal framework would not seat correctly, which prompted him to take a new impression. Thereafter, on March 10, 2010, Respondent removed P.D.'s temporary bridge and conducted a try-in with the new metal framework——affording him a third opportunity to visualize tooth number 20. Once again, Respondent observed no indications of decay or any other issues. Of the opinion that the second impression had yielded a satisfactory framework, Respondent scheduled P.D. to return at a later date for the seating of her new bridge. Upon P.D.'s return on March 24, 2010, Respondent removed the temporary bridge and directly visualized tooth number 20 for a fourth time; no decay was observed. Respondent then proceeded to seat the cantilever bridge, which fit well and caused the patient no discomfort. At that point, it was anticipated that P.D. would follow up with Respondent in six months for routine cleaning and maintenance. As it happens, though, P.D. returned to Respondent's office a mere five days later, on March 29, 2010. During the visit, P.D. reported that her new bridge was “hurting” and that she was feeling “pressure constantly.” Notably, however, P.D. denied that the pain was of such intensity that it kept her awake at nighttime, which militated against a conclusion that the patient was suffering from an abscess.4/ In response to P.D.'s complaints, Respondent adjusted and flossed the bridge. That an adjustment was made so soon after the bridge's seating, although less than optimal, was by no means unusual; indeed, Petitioner's expert witness concedes that neither the timing of the March 29 visit nor P.D.'s report of pressure necessitated a clinical examination or the taking of an x-ray on that date.5/ Nine days later, on April 7, 2014, P.D. appeared at Respondent's office once again, this time with the complaint that she was biting her cheek. During the clinical examination that ensued, Respondent surmised that the cheek biting, if any, had been caused by a different, aging bridge located in the upper left of P.D.'s mouth (at teeth numbers 11 through 14).6/ Respondent did, however, notice that the new bridge was hitting high, which prompted him to make a minimal adjustment using a rubber wheel. Although Petitioner contends that Respondent should have taken an x-ray during the April 7 visit to rule out an abscess, the evidence demonstrates that P.D. exhibited none of the clinical symptoms sometimes attendant to such a condition. Save for her report of “cheek biting,” P.D. presented with no complaint of severe——or, for that matter, any——pain,7/ nor did she exhibit any discomfort during the adjustment. Moreover, P.D. did not react adversely when Respondent used the end of his examination mirror to perform percussion on the bridge. Finally, Respondent detected no inflammation below the gum line. Subsequently, on April 13, 2010, P.D. returned to Respondent's office and reported that the new bridge was “catching her lip.” P.D. complained of no other pain relating to the new bridge, and Respondent's clinical examination yielded no indications (e.g., thermal sensitivity or sensitivity to percussion) that the patient was suffering from an abscess.8/ Owing to the dearth of symptoms suggestive of endodontic involvement, Respondent determined that an x-ray was unnecessary. However, Respondent made a minimal adjustment to the new bridge and sent P.D. on her way, with the expectation that the patient would return in six months for a follow-up visit. Although P.D. would return a mere six days later, on April 19, 2010, her complaints at that time related only to the aging bridgework at teeth numbers 11 through 14 (seated years earlier by another dentist), which Respondent discovered was “hitting hard.” Significantly, P.D. raised no issues concerning her new bridge at teeth numbers 19 through 21, and Respondent's examination revealed, yet again, no signs of endodontic involvement.9/ As such, Respondent did nothing more than make a slight adjustment to the bridge at teeth numbers 11 through 14.10/ Soon thereafter, P.D. scheduled another appointment and returned to Respondent's office on April 27. On this occasion, as with the previous visit, P.D. voiced no complaints concerning her new bridge, and Respondent observed no signs of inflammation, cheek biting, or any problems. This time, however, P.D. accused Respondent of “breaking” the bridgework at teeth numbers 11 through 14 and suggested that he provide a replacement free of charge. Respondent was understandably dismayed by P.D.'s demand, for he had never caused any damage to the 11 through 14 bridge; moreover, the bridge in question, although in poor condition, was by no means “broken.” At that point, Respondent terminated his relationship with P.D. Expert Testimony As noted previously, Petitioner advances two unrelated theories in support of its charge that Respondent violated the minimum standard of care. First, Petitioner contends that, prior to the seating of the new bridge on March 24, 2010, Respondent failed to treat decay supposedly present on the distal surface (i.e., the part of the tooth that faces the back of the mouth) of tooth number 20. In light of Respondent's concession that the standard of care requires the removal of existing decay prior to the seating of a bridge, Petitioner's first theory boils down to a factual dispute over whether decay was present on tooth number 20 on March 24, 2010. In an attempt to establish the presence of decay, Petitioner adduced testimony from Dr. Solomon Brotman, an eminently qualified dentist with more than 30 years of practical experience. Although Dr. Brotman concedes that he never clinically examined P.D., he nevertheless maintains that the presence of “substantial” decay on tooth number 20 is demonstrated by x-rays in Respondent's possession when the bridge was seated.11/ Dr. Brotman further opines that the x-rays of tooth number 20 are not reasonably susceptible to any other interpretation (e.g., abrasion or erosion), and that Respondent may have missed the decay because it is “sometimes” tooth colored. Finally, Dr. Brotman asseverates that, in cases involving interproximal decay, it is appropriate to make a diagnosis based solely on an x-ray. Respondent counters with testimony from Dr. Robert Fish, an expert with an equally impressive background, who credibly asserts that the x-rays in question are not suggestive of decay but, rather, abrasion12/ that likely resulted from the ill-fitting “C-clasp” of the removable partial denture——an opinion that jibes with Respondent's persuasive testimony that he observed abrasion on the distal surface of tooth number 20. Dr. Fish further contends that, had decay been present, it is highly unlikely that Respondent would have missed it given the number of times he directly visualized tooth number 20 prior to the seating.13/ The short of it is that decay quite possibly existed on the distal surface of tooth number 20 at the time Respondent seated the bridge. However, Respondent's persuasive account of his clinical observations of the tooth, buttressed by the credible testimony of Dr. Fish, leaves the undersigned with substantial doubt on this point. As such, Petitioner has failed to sustain its burden of proof. The undersigned now turns to Petitioner's alternative theory, namely, that “continuing, localized dental pain” required Respondent to rule out the possibility of an abscess at the root of tooth number 20. In relevant part, the Amended Complaint alleges: Continuing, localized dental pain is a symptom of endodontic involvement. Minimum standards of diagnosis and treatment in the practice of dentistry require that when a patient complains of continued dental pain, a dentist take radiographic images of the symptomatic area to determine whether there is endodontic involvement. . . . Patient appointed with Respondent for relief of pain five times [after the bridge was seated] . . . . Respondent Dr. Almerico did not take radiographs of that area or otherwise rule out endodontic involvement during those visits. By failing to take radiographic images to determine possible endodontic involvement at bridge #19-21, Respondent failed to meet minimum standards of dental diagnosis and treatment when measured against generally prevailing peer performance. (emphasis added). Fairly read, the Amended Complaint alleges the standard of care as follows: when a patient reports continuing, localized dental pain, a practitioner must take an x-ray of the symptomatic area or otherwise rule out endodontic involvement. As Respondent correctly argues, however, the testimony of Petitioner's expert departs substantially from the theory pleaded in the charging document. First, contrary to paragraph 27 of the Amended Complaint, which alleges a failure to take x- rays “or otherwise rule out” an abscess, Dr. Brotman's formulation of the standard of care absolutely requires the taking of an x-ray to eliminate the possibility of endodontic involvement. To muddy the waters further, Dr. Brotman's articulation of the prevailing standard at times focused not on P.D.'s supposed reports of continued pain but, rather, the fact that Respondent made more than one adjustment to the new bridge subsequent to its seating: A Sure. I think we fell below the minimum standards on 4/7, 4/13 and 4/19 of 2010, because each of those visits, because the patient came back with the bite having shifted, which for that reason Dr. Almerico continued to adjust the bite on each visit. * * * BY MR. PRICE: Q Doctor, you just gave an opinion that is the standard of care that a patient with more than one adjustment, they automatically get an X-ray. You just gave that as a standard-of-care opinion, didn't you? A Yes, sir. (emphasis added).14/ In light of the significant degree to which Dr. Brotman's testimony deviates from the theory charged in the Amended Complaint, it is concluded that Petitioner has failed to convincingly articulate the minimum standard of performance against which the undersigned, as fact-finder, can independently evaluate Respondent's conduct. Even assuming that Petitioner had established the standard of care (as pleaded), there is a dearth of credible evidence that P.D. presented with continuing, localized pain relating to the new bridge. As detailed previously, P.D.'s report on April 7 that she was “biting her cheek” involved the older bridge at teeth numbers 11 through 14; on her next visit, she complained only that her new bridge was “catching her lip”; on April 19, P.D. merely informed Respondent that the older bridge was “hitting hard”; and, on her final visit, P.D. complained of nothing at all (save for her dubious request for a free replacement of the older bridge).15/ Such hardly constitutes a pattern of ongoing, localized pain. In any event, the persuasive evidence demonstrates that Respondent “otherwise ruled out” endodontic involvement through his clinical observations. Indeed, as Dr. Fish persuasively explained during his testimony, P.D. presented with none of the symptoms16/ sometimes associated with the presence of an abscess——e.g., sensitivity to temperature, exquisite pain, sensitivity to percussion, a fistula, or inflammation——during the office visits of April 7, 13, 19, and 27, 2010, thereby obviating the need for an x-ray. Ultimate Factual Determinations It is determined, as a matter of ultimate fact, that Respondent is not guilty of violating section 466.028(1)(x).
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered by the Board of Dentistry dismissing Count I of the Amended Administrative Complaint. DONE AND ENTERED this 9th day of July, 2014, in Tallahassee, Leon County, Florida. S EDWARD T. BAUER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of July, 2014.