RONALD T. HOPWOOD AND MILAN M. KNOR vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 80-000153 (1980)
Division of Administrative Hearings, Florida Number: 80-000153 Latest Update: Oct. 07, 1980

Findings Of Fact Petitioner Ronald T. Hopwood is president of Last Resort Fish Camp Association, Inc. (hereafter "Association"), the owner of Big Pine Island located in Lake County, Florida. Big Pine Island consists of approximately 26 acres of land above the mean high watermark and 166 acres of submerged and transitional zone lands. The Association's property is more accurately described by the Department's exhibit III, Map C. Petitioner Milan M. Knor submitted to the Department a dredge and fill permit application, File No. 35-20062-4E, to dredge 7,350 plus-or-minus cubic yards of fill material waterward of the lien of ordinary high water and adjacent to the Petitioner's uplands (Department's Exhibit 12). It is proposed that the fill material or spoil be deposited on the landward side of a perimeter canal which presently exists along the southwest one-third of the island. When the project is complete, the canal will encircle the entire island, the fill material resulting therefrom will be deposited on the island side of the perimeter canal below a 59.5-foot elevation (Department's Exhibit III, Map A). During the dredging, turbidity curtains would be utilized. As part of the project, Petitioners propose to install two (2) 42-inch diameter culverts at the east and west ends of a causeway which connects Big Pine Island to the mainland (Department's Exhibit III, Map B). The purposes of the proposed project are to improve the water quality of the adjacent canals and wetlands, provide fire protection, reduce algae blooms, and stabilize bottom sediments (Petitioners' Exhibit A, Department's Exhibit 1). The elevation of 59.5 feet above mean sea level was established by the St. John's River Water Management District as the ordinary high water elevation of Lake Griffin. The desirable levels of Lake Griffin vary between 58.07 and 59.38 feet. A dredge and fill permit was issued fro this project by the St. John's River Water Management District. In its final order granting the permit, the Governing Board of the District found, inter alia, that the water quality of the district would not be significantly diminished by the channelization of the marsh, that the new culverts would increase the rate of flow and the flushing of the marsh by providing increased northerly access for the water flow, that the excavation would enhance navigability and flow through the interior canal, and that the channelization would promote fire protection. The Board believed that the installation of the culvers ". . . will provide a positive benefit to the marshlands by correcting the prior damming effect of the causeway " (Petitioner's Exhibit D). The permit was issued by the Governing Board over the recommendation of its staff to deny the permit (Department's Exhibit 16). On July 26, 1979, Mr. James Morgan, a filed inspector with the Department, conducted an on-site field inspection of the proposed project. Mr. Morgan complied an appraisal report, Department's Exhibit 11, which evaluated the feasibility of extending the existing 1,200-foot canal by approximately 3,000 feet. Mr. Morgan found that a portion of the area to be excavated, approximately 600 feet, was previously cleared and vegetated by arrowhead (Sagittaria, Sp.), paragrass (Panicum purpurascens), bloodroot (Lacnanthes caroliniana) and sawgrass. 1/ Standing water was present in portions of the previously cleared area. The remaining 2,400 feet were in a natural state, dominated by willows (Tudwigia peruviana), wax myrtles (Myrica ceriferia), arrowhead and sawgrass. Surface waters of the Oklawaha River and Lake Griffin were present in part of this area; however, at the time of the field evaluation, Lake Griffin's surface waters were depressed by approximately six (6) inches below its established ordinary high water elevation. Raising the lake's elevation to its high water elevation, 59.5 feet, would result in the entire project site being inundated with surface waters. Dip net samples yielded organisms which constitute the lowest levels of an aquatic food chain including amphipods, dragonfly naiads, diptera larvae and mosquito fish. Mr. Morgan's report concluded that ". . . [d]ue to the severity of the anticipated impact of the proposed canal construction, no environmentally acceptable modification is available other than to permit the system to function naturally. . . ." This conclusion was based on the following negative aspects of the project. The collecting and storing of organic materials in the canal which would reduce the dissolved oxygen level during biodegradation to lethal levels for fish and other aquatic organisms; The physical alteration and elimination of a natural wetland community; The increase in turbidity during excavation; and The placement of spoil below the controlled elevation of Lake Griffin which would reduce the lake and river flood storage capacity as well as the area capable of supporting healthy aquatic plant and animal life. It was recommended that the proposed culverts be installed and that one canal- front lot be utilized as a common lot for all property owners, thereby providing open water access to all property owners. Lake Griffin is presently in a highly eutrophic stated caused by large amounts of algae growth and weeds in the water column. Agricultural farming, municipal sewage treatment plants, and citrus processing plants are among the sources of nutrients causing the high algae growth. The construction of the causeway between the mainland and Big Pine Island in 1958 has prevented virtually any water from circulating between the marsh area and canal south of the causeway and the marsh area and canal north of the causeway. Due to this blockage of flow, lower dissolved oxygen levels and lower temperatures exist on the north side of the causeway. The south canal helps to maintain oxygen levels in the south marsh above concentrations considered critical to maintain aquatic life. The presence of the causeway has reduced the outflow of Lake Griffin by half, thereby increasing the residence time in the lake and promoting nutrient level buildup in the system. By increasing the water flow through the marsh surrounding the island, the quality of water entering the Oklawaha River from eutrophic Lake Griffin should be greatly improved. The marsh to the north of the causeway presently serves a vital purpose by removing nutrients and other deleterious substances from the water flowing from Lake Griffin into the Oklawaha River. The marsh community acts in a matter similar to the human kidney by filtering deleterious substances from the surface water. Biological productivity of the north marsh area is directly proportional to the amount of flow. This area presently experiences water movement caused by the control of water elevations in the Oklawaha chain of lakes by a series of control structures. This "backwater" effect, which is caused by movement in the Oklawaha, is not a sheet flow. If a sheet flow could be created, the marsh area directly north of the causeway, which is severely distressed, could be improved. A sheet flow northward could be created by the proper placement of adequate size culverts under the causeway and the completion of the canal. The canal could facilitate the flow of water northward by permitting water to overflow the canal bank on the north side. This would be caused by the effects of a hydraulic gradient which exists between the water level in the canal and the ordinary mean high water lever maintained by the St. John's River Water Management District. The hydraulic gradient would cause the canal to overflow its unobstructed north bank and travel northward through the marsh into the Oklawaha River. Water would be blocked by overflowing on the southeast side of the island because of an existing berm. In order to restore circulation, it would also be necessary to construct a series of culverts evenly distributed under the causeway. The two- culvert system proposed by the Petitioners would have a cosmetic effect and not significantly improve the natural water flow between the canals. If the flow through the highly distressed marsh to the north of the causeway could be improved through the proper placement of culverts and construction of a perimeter canal, the positive aspects of the project would outweigh the negative impact of the elimination of approximately six (6) acres of productive marshland. If steps are not taken to reverse the continuing degradation of the marsh directly north of the causeway, a large and valuable area of wetlands will be lost. Artificial conditions already exist due to the finger canal on the north side of the causeway and the causeway itself. The proposed filling of the island which is to occur below the 59.5- foot elevation will reduce the river's flood storage capacity and the area capable of supporting plan and animal life. The private benefit of placing the spoil from the dredging project on the island below the 59.5-foot elevation is outweighed by the negative impact associated with the elimination of a significant amount of low lying marshland. Adequate alternative means exist to provide fire protection to the residents of the island, and the filling of outlying marshes on the island is not necessary to accomplish this purpose. Petitioners have not been denied the use of their property either by the Department's denial of this permit or the granting of this permit with conditions. The existing lots are suitable for residential purposes, including that portion of the island below the 59.5-foot elevation which may be used for residential development by placing housing on pilings or poles.

Recommendation Therefore, it is recommended that the Department issue a permit to Petitioners to complete construction of a perimeter canal surrounding Big Pine Island subject to the following conditions: That the applicants install culverts or other similar structures of appropriate size to facilitate an adequate exchange of water between the canals on the north and south sides of the causeway. The number and size of the culverts or other structures will be determined by the Department. That the fill or spoil resulting from the dredging of the canal not be placed on Big Pine Island or any surrounding property at any elevation below 59.5 feet in elevation. That the applicants utilize equipment including, but not limited to, turbidity curtains to keep turbidity at a minimum during the dredging process. DONE AND ORDERED this 25th day of August 1980, in Tallahassee, Leon County, Florida. SHARYN L. SMITH Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of August 1980.

Florida Laws (2) 120.57403.031
# 1
THOMAS L. SHEEHEY vs MICHAEL CHBAT AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 09-000948 (2009)
Division of Administrative Hearings, Florida Filed:Shalimar, Florida Feb. 18, 2009 Number: 09-000948 Latest Update: Apr. 14, 2010

The Issue Whether Michael Chbat's 2008 application for a Wetland Resource Permit (WRP) to construct a culvert extension across his property in Walton County, Florida, should be approved?

Findings Of Fact La Grange Bayou Estates La Grange Bayou Estates is a residential subdivision in Freeport, Walton County, Florida. The subdivision lies to the north of the shoreline of Choctawhatchee Bay. It can be viewed as divided roughly in half between bayfront lots south of an east-west road that transects the subdivision and lots that are north of the road. The subdivision is platted and the plat is in the public records of Walton County. Filed with the Clerk of the Circuit Court in and for Walton County, Florida, on September 15, 1982, the plat ("the 1982 Plat") shows 29 residential lots in the subdivision as of that date. See Petitioner's Ex. 6. Lots 1 through 16, according to the 1982 Plat, are the bayfront lots, south of a 40-foot wide road designated as a private road in the plat. That road is now known as Alden Lane. Wetlands over which the Department has jurisdiction ("jurisdictional wetlands") comprise much of the southern portion of bayfront lots and the drainage easement. Among the bayfront lots are both Lot 9 which belongs to Mr. Chbat and Lot 8 which belongs to Mr. Sheehey. A 50-foot easement lies between Lot 9 and Lot 8 and is described more fully below. The presence of jurisdictional wetlands on Mr. Chbat's lot over which he hopes to install the culvert extension requires that he obtain a WRP. To the north of Alden Lane are lots numbered by the 1982 Plat as 17 through 29. The lots are served by Alden Lane and, in what is roughly the northeast quadrant of the subdivision, by two other roads. One of the roads is shown on the 1982 Plat as a "40' PRIVATE ROAD." Id. A 2006 aerial photograph introduced into evidence by Chbat designates the road "unnamed." See Chbat Ex. 5. The other is designated as a "graded county road," on the 1982 Plat. By 2006, it had come to be known as Beatrice Point Road. Id. Beatrice Point Road transects a pond that runs roughly 340 feet (excluding about 30 feet of roadway) in a northeasterly direction from Alden Lane to the southern edge of an area north of the subdivision shown on the 1982 Plat to be un-platted. The pond is most likely the result of a "borrow pit" dug in order to obtain fill for the construction of the roads when the subdivision was initially developed. The southern boundary of the pond lies along approximately 140 feet of Alden Lane's northern edge. The pond is across the street from Lots 9, 10 and 11 of the subdivision. The pond is also not far northeast of the 50-foot easement (the "Drainage Easement") between Lots 9 and 8. The Drainage Easement The Drainage Easement is just to the west of Lot 9. It is noted on the 1982 Plat as a "50' EASEMENT (PRIVATE)." Id. The 50-foot wide Drainage Easement runs the length of the western boundary of Lot 9 and the length of the eastern boundary of Lot 8. The northeast corner of the Drainage Easement is approximately 30 feet from the southwest corner of the pond separated from the pond by the roadway of Alden Lane. The eastern boundary of the Drainage Easement is 226.37 feet in length, or if taken to the middle of Alden Lane, 246.3 feet. The western boundary is 206.13 feet long or if taken to the middle of the road, 226.65 feet. The purpose of the Drainage Easement, as is evident from its denomination in this recommended order, is drainage. As Mr. Street definitively put it at hearing, it is "now and always has been intended to drain stormwater to the [B]ay." Tr. Vol. III at 179. Mr. Street's opinion of the function of the Drainage Easement is supported by drawings submitted by Mr. Chbat as part of the WRP application. The drawings show that the Drainage Easement's function is facilitated by three culverts north of the Easement (referred to during the hearing as "pipes") each of which is intended to direct stormwater at its point of discharge toward the Drainage Easement. See Chbat Ex. 1. One of the culverts ("the Drainage Ditch Culvert") serves a drainage ditch that is to the north of the Easement and Alden Lane. According to the drawings, the drainage ditch lies on the other side of the "un-named road" from the pond, that is, to the west of the pond, and is some 40-to-50 feet north of the Drainage Easement. The Drainage Ditch Culvert extends from the ditch to the southern half of Alden Lane from where it appears from the application's drawings that stormwater would be conveyed to the western side of the Drainage Easement along it's border with Lot 8 and on toward the Bay. In fact, it is a functioning culvert that "conveys water from a swale on the side of the road into the [D]rainage [E]asement." Tr. 64. Once in the Drainage Easement, according to the drawings, the water should flow into the Bay out of a "cut," id., that is labeled on the drawings as an "existing trench." See Chbat Ex. 1. The trench, however, has been filled in with sand by tidal activity or sediment deposited by stormwater or both. The trench has not been maintained, and it no longer exists. The other two culverts (the "Pond Culverts") lie east of the Drainage Ditch Culvert. They catch overflow from the pond caused by stormwater and convey it under and through Alden Lane toward the Drainage Easement. The westernmost Pond Culvert (the "Western Pond Culvert") appears to terminate in Alden Lane near its southern edge just north of the Easement. At the time of hearing, however, it was not functioning properly. "[I]t is full of sand and silted up . . .", tr. Vol. I at 58; "[t]he pipe to the west is clogged and it is not functioning." Tr. Vol. I at 64. It is also at an elevation that would keep it from serving drainage purposes in all but the most severe storm events. See Chbat Ex. 9 at 22. The other Pond Culvert, (the "Eastern Pond Culvert") terminates in the northwest corner of Lot 9 at the border between Lot 9 and the Drainage Easement about 10 feet southeast of the terminus of the Western Pond Culvert. The Eastern Pond Culvert is the culvert with which the Amended Permit is concerned, that is, it is the culvert to be extended by the permit. Calling it a "pipe," Mr. Street offered the following about the assistance the Eastern Pond Culvert offers in conveying stormwater into the Drainage Easement and down to the Bay: There is currently a pipe that discharges into that easement. There . . . was an attempt to place the water from the . . . pond into the easement. And the natural flow of water on this entire property from the road to the [B]ay is north to south. At some point, at least 2004, that drainage easement contained a conveyance at its southern end that would safely discharge stormwater to the [B]ay. Tr. Vol. III at 179-80. Petitioner Sheehey and Lot 8 Thomas Sheehey is the owner of Lot 8, where he has a residence in which he makes his home. He has lived in the residence approximately five years. During that time, Mr. Sheehey has fished in the Bay and enjoyed the use of his kayak and his waverunner on the Bay. He also enjoys "sitting down having a cup of coffee and looking at it," tr. vol. III at 151, as well as watching his neighbors fish. The recreational uses to which he puts the Bay is the reason he chose to purchase a bayfront lot in La Grange Bayou Estates. Over the period of time that he has resided on Lot 8, Mr. Sheehey has observed the effects of rain events on his lot and well as lots close to Lot 8. He has also taken pictures of his property and the near-by lots. Among the photographs were four taken after rain events or "after a wet period," tr. vol. III at 88, at some point in the last four years. The four photos were introduced as a composite exhibit, Petitioner's Ex. 2, with each photograph marked as 2A, 2B, 2C or 2D. Mr. Sheehey could not specify when the pictures were taken in the past four years other than that if a picture had a certain dock in it, then it was taken after January of 2009. Petitioner's Ex. 2A was taken from Mr. Sheehey's lot looking toward the Bay. It shows an area of the lot under water separated from the Bay by a ridge. Petitioner's Ex. 2B is a picture taken from Lot 13 looking west across Lots 12, 11, 10, 9 "down through 8." Tr. Vol. III at 86. Much of what is photographed is among trees and vegetation emerging from water standing above the surface of the soil. Petitioner's Ex. 2C is a picture taken from Alden Lane looking south across Mr. Chbat's property. It shows a wide swath of water that extends from the road across most of the property to the Bay. The water is either in a swale or constitutes overflow outside the swale. The most recent of the four is Petitioner's Ex. 2D, which shows the dock referred to by Mr. Sheehey that was built in early 2009. It is a picture taken from Lot number 13 toward the west through Lots 12, 11, 10, 9. Like the others, it shows vegetation standing in water to the north of the Bay. Taken together, the four pictures in Petitioner's Exhibit 2 demonstrate that significant portions of the lots depicted are under water following sufficient amounts of recent rain. The four photographs that comprise Petitioner's Exhibit 2 are not the only photos taken by Mr. Sheehey that were introduced into evidence. Three other photographs of Mr. Sheehey's, Petitioner's Exhibits 7A, 7B and 7C, were admitted following testimony about them from a long-time observer of the flow of water from Alden Lane to the Bay. A Long-time Observer Thomas Eugene Cummins had lived in La Grange Estates "[t]wo months shy of 20 years," tr. vol. III at 7, at the time of his testimony. His house was the fourth to be constructed in the subdivision. Over the two decades of his residence, the pond between Alden Lane and the property north of the subdivision has been in existence. Consistent with the drawings submitted to DEP as part of the application, when asked where the pond overflows today, Mr. Cummins answered "it drains under Alden Lane on to Mr. Chbat's lot." Tr. Vol. III at 8. Asked by Mr. Chesser at hearing, "When the water comes out of the pond, is it possible to know where it spreads?"1/ Mr. Cummins testified: On really heavy rains, I have watched the normal color of the pond change from its dark blackish gray color into the reddish color that the clay has washed down into it, flow under Alden Lane and on to Mr. Chbat's lot, and then proceed west through the wetland on lots eight, seven, six, and my five, and turn reddish color even in my lot. Tr. Vol. III at 9-10. Mr. Cummins knew the source of the "red color" of the stormwater: red clay introduced to La Grange Estates by the County half a decade earlier. Mr. Cummins testified: Beatrice Point Road, which is the road that runs over the pond, about five years ago the county did some repair on the road and actually put red clay in certain spots to even it out. Tr. Vol. III at 9. Prior to the county's work on the road referred-to by Mr. Cummins, there had been no red clay in the neighborhood. Alden Way, for example, has no red clay. It is a road composed of shell. The only red clay in the subdivision is that which is on Beatrice Point Road. The water that runs onto Mr. Cummins' lot following a heavy rain rises to as much as 12 inches.2/ The water rises as high as it does because it is held back by a naturally-occurring land formation between the Bay and Mr. Cummins property. This geo-formation was referred-to at hearing as the ridge line or the ridge. The Ridge The Ridge was described by Mr. Cummins as a vegetated mass of earth that most of the time, even in heavy rains, sits above the water that collects on the bayfront lots of La Grange Estates. The Ridge prevents a substantial amount of stormwater runoff from entering the Bay from the wetlands on the southern portion of the subdivision's bayfront lots. For that reason, the ridge is called "our upland,3/" tr. vol. III at 13, according to Mr. Cummins. Between Lot 9 and Lot 5, the ridge varies in width "anywhere between 10 feet . . . up toward Mr. Chbat's lot, down to [Mr. Cummins'] lot where its around 30 or 40 feet [wide.]" Id. (It may extend, in fact, across all of the bayfront lots.) The ridge meanders not far from the shoreline. Id. In some places it is as narrow as five feet. The height of the ridge varies as well from as low as one foot to as high as two and half feet. Mr. Street also testified about the Ridge, referring to it in his testimony as a "ridge line": Now, there is a ridge line, and there's been a lot of testimony about this ridge line, that it exists across all of the lots. My testimony was, essentially, related to the review that I did, which was primarily associated with lots eight and nine, and the drainage easement between them. And from what I can tell, the elevation of that ridge line is give or take three. Elevation three, not a height of three. An elevation of three. It could be lower, and perhaps, is higher. And its subject to the vagaries of a number of factors, flow of stormwater, wave action, tidal influence, and the like. And these accretions and depositions of sand over time change that ridge line. And sometimes, it opens up. And sometimes it may not have a natural opening, depending on where you are along that entire stretch of beach. * * * [T]o the extent there is an opening in that ridge line, water will flow naturally to the bay. Tr. Vol. III at 180-181. An "east west flow of water," tr. vol. III at 181, along the bayfront lots, that is, a flow of water either in an easterly direction or a westerly one is contrary to the flow from Alden Lane north of the lots to the Bay south of the lots. Whether flowing east or west, the water in the southern portions of the bayfront lots is "controlled by the ridge line." Id. In other words, stormwater that flows from north to south across the bayfront lots, including Mr. Chbat's and the Drainage Easement, is going to collect and begin to flow from east to west or west to east at some point north of the Ridge before it drains into the Bay. The only exception to east-west flow, as made clear by Mr. Street, is when and if there is an opening in the Ridge that allows the water otherwise held back by the Ridge to flow southward into the Bay. The east-west flow of the water along the Ridge was described at hearing as "unnatural." Id. In fact, it is not un-natural. The Ridge is the cause of the east-west flow and, as Mr. Street testified, the Ridge is the result of natural processes such as tidal influence, wave action, accretion and deposition of sand.4/ The Ridge is shown in Petitioner's Exhibit 7A,5/ another photograph taken by Mr. Sheehey. The ridge as shown in the picture is well vegetated and above water to its north and higher than the Bay to its south. It is quite clear that if there is no opening in the ridge to the Bay, stormwater north of the ridge is forced to flow in east-west directions and is prevented from flowing into the Bay. Petitioners' Exhibit 7B is a photograph of the southern terminus of a swale (see paragraphs 40 - 49, below) on Mr. Chbat's property. It shows the swale cut through the Ridge. Water, however, does not appear to be running from the end of the swale into the bay. It appears that the end of the swale is a few feet from the Bay separated by a narrow sandy area on the shore. Nonetheless, the photograph shows that there is potential for stormwater to flow from the swale when the swale has more water in it. Petitioner's Exhibit 7C is a picture of the pond6/ across the street from Mr. Chbat's Lot 9. Mr. Chbat and Lot 9 Michael Chbat is the owner of Lot 9. He purchased the lot "[t]o build a house on it." Tr. Vol. I at 22. Because he has family close by (in Fort Walton Beach), Mr. Chbat expects to use a house built on the lot for weekend visits. His ultimate aspiration is to live in a house on Lot 9 after he retires from his position as a construction engineer with the City of Tallahassee. At hearing, Mr. Chbat described Lot 9 on the day he bought it: "the lot was overgrown. It drained from north to south. It had water standing on it. And it had a pipe [the Eastern Pond Culvert] on the northwest corner discharging." Tr. Vol. I at 23. He also described the state of the lot at the time of hearing. The Eastern Pond Culvert on the northwest corner was still there. The lot had been cleared to some extent to rid it of invasive species. Overgrown vegetation was trimmed or cleared to make room for a driveway permitted by the Department and "a parking pad in the front area of it, as well as an access pad in the uplands." Id. A dock had also been constructed from the property into the Bay. The most significant difference between the lot at the time of purchase and the lot at the time of hearing for purposes of this proceeding is that the lot now has a swale (the Swale) that runs from the point of discharge of the Eastern Pond Culvert "all of the way to the bay area." Id. The Swale The Swale was put in sometime after March 20, 2007, as the result of a Settlement Agreement fully executed on that date "By and Between Michael Chbat and Thomas L. Sheehey." Petitioner's Ex. 10. The Settlement Agreement followed events that commenced in 2004 when Mr. Chbat filed an application (the "2004 Application") with DEP for a WRP primarily to construct a house and a boardwalk leading from the house on Lot 9 to a dock in the Bay. The 2004 Application also proposed the extension of the Eastern Pond Culvert with a "pipe" along the western boundary of Chbat's property in a manner substantially similar to the culvert extension allowed by the Amended Permit that is the subject of this proceeding. On October 28, 2005, DEP proposed that the 2004 Application be granted. The permit (the "Proposed Original Permit") was assigned No. 66-0235320-001-DF. See Petitioner's Ex. 10, at 2. The Proposed Original Permit was challenged by Mr. Sheehey when he "filed a Petition for Administrative Hearing contesting certain action authorized under the [Proposed Original] Permit . . . specifically the relocation of a drainage pipe . . . ." Petitioner's Ex. 10, at 2. After referral of the petition to DOAH, Mr. Chbat and Mr. Sheehey wrote in the Settlement Agreement that they had "determined that it is in their best interests to settle this matter amicably pursuant to the terms hereafter". Id. Among the terms is that Chbat would file an Amended Application. See id. The agreed-to amendment to the 2004 Application was attached to the Settlement Agreement as Exhibit "A," a drawing of a "Drainage Swale Plan," produced by Genesis Group for Mr. Chbat. The drawing depicts a swale that runs from the discharge point of the Eastern Pond Culvert nearly the full length of the western boundary of Lot 9 to the Bay. See Exhibit "A" to Petitioner's Ex. 10. The Swale was designed to take the place of the 2004 Application's proposal for a "pipe"7/ attached to the point of the discharge from the Eastern Pond Culvert. The Settlement Agreement received the support of DEP because the Department believed that a swale would assist in improving the quality of the stormwater discharged to the Bay over the untreated discharge from the end of the "pipe." Pursuant to the terms of the Settlement Agreement the 2004 Application was amended. The Department amended the Proposed Original Permit accordingly and final agency action was taken with the issuance of a permit to Mr. Chbat (the "Final Original Permit") found in DEP Permit File No. 66-0235320-001- DF. Installation of the Swale The Swale was installed, but it did not work as intended. The result of the Swale's installation was more water on the lot rather than less. Mr. Chbat described the after-effects of the Swale: "it started bringing more water to the lot . . .". Tr. Vol. I at 31. The increased amount of water is the result of several factors, one of which is tidal influence: the tide from the Bay pushes water into the Swale. "[A]bout halfway on the swale . . . that water from the bay was meeting the water from the pipe . . .". Id. The water from the Bay tide and the stormwater conveyed by the Swale would meet at "about the middle of the span of the swale." Id. The result was "a lot more water," id., on the lot. Mr. Thomason confirmed Mr. Chbat's assessment that the reason the Swale did not function as effectively as necessary is tidal flow onto Lot 9 from the Bay particularly from high winds. But tidal flow onto Lot 9 and the interruption in the discharge of stormwater through the Swale are not the only problems. There is also a maintenance factor that accompanies tidal flow: sand deposition. Mr. Thomason elaborated: "[D]uring storm events or [just normal] wave action in the bay, sand is brought back up on to . . . the sandy area at the end of [Lot 9] next to the [Bay.]"8/ Tr. Vol. I at 62. The influx of sand onto Lot 9 is not just a problem for adequate functioning of the Swale. The Drainage Easement has "the same problem." Id. Both the Swale and the Drainage Easement are plagued by deposition of sand pushed landward by normal tidal influences and storm events. Maintenance of the Swale and the Drainage Easement, therefore, would assist the drainage of stormwater into the Bay. The tidal influence and maintenance issues that Mr. Chbat encountered with the Swale led him to apply for a different and new permit. That application was filed in 2008. The 2008 Application Mr. Chbat filed a "Joint Application for Works in the Waters of Florida" with DEP on August 1, 2008 (the "2008 Application"). See Chbat Exhibit 1. The work to be approved was similar to the work originally proposed in the 2004 Application in that both applications proposed installation of a "pipe" to be fixed to the discharge point of the Eastern Pond Culvert that would run along the western boundary of Lot 9 toward the Bay. A description of the work is contained in Section 10 of the 2008 Application: "Extension of an existing stormwater pipe within a private lot approximately 150 feet. The slope for the proposed pipe extension will be at minimum so that stormwater will be treated further, and minimizing erosion." Chbat Ex. 1 at 3. After the filing of the 2008 Application, Mr. Chbat learned that Mr. Sheehey objected to the newest Chbat proposal because he believed 150 feet is not lengthy enough to clear the Ridge. See Chbat Exhibit 2. In order to cure the objection, Mr. Chbat proposed a modification to the 2008 Application. He attached a "sealed and signed drawing," id., to a letter dated September 18, 2008, that he submitted to DEP. The drawing shows the extension to be 177 feet, 27 feet more than initially proposed by the 2008 Application. The additional 27 feet was intended to ensure that the discharge would be directly into the Bay in order to "eliminate any possible run-off impact to adjacent properties." Id. The modification was accepted by DEP." See exhibit number 19/ attached to the Amended Permit, Chbat Exhibit 4. There was conflicting evidence in the proceeding on whether the outfall from a culvert extension of 177 feet will be bayward of the Ridge. The issue was put to rest by Mr. Street’s testimony in rebuttal at the hearing. See Tr. Vol. III at 194 and 203-4. His testimony establishes that the point of discharge at the end of the culvert extension will clear the Ridge so that the discharge will be directly into the Bay. The Mound The culvert extension is designed at an elevation and with cover (presumably sod). The extension runs through jurisdictional wetlands and segments them. It does not, however, isolate any portion of the wetlands. The wetlands on Mr. Chbat's property and those to the immediate east and west of it, therefore, will retain their status as jurisdictional wetlands should the extension be installed. With its sod cover, the culvert extension will be a mini-berm (or a "mound" as Mr. Street called it) at an elevation of 17 to 18 inches above grade. Water that pools to its west will no longer be able to flow eastward of the mound (except rarely under the most extreme weather events.) Conversely, water that collects to its east will no longer be able to flow westward of the extension. It would have to be a severe storm event for water to rise above the mound. Mr. Chbat has never seen water rise to 18 inches above grade and Mr. Cummins testified the highest water ever gets on his property is roughly 12 inches. The Department approved the 2008 Application as modified to lengthen the extension to 177 feet and issued the Amended Permit. But an incorrect and critical assumption was made during review of the application that related to the mound. Review of the 2008 Application During his review of the application, Mr. Street, as DEP's stormwater engineer, assumed from the drawings that the Drainage Easement is functional.10/ The assumption was expressed in Mr. Street's testimony in the Department's case-in-chief: Q [D]id you determine whether the pipe, as it would be mounded . . . [the culvert extension covered in sod] . . . would create problems for storm water flow? A I looked at that. There were two conclusions that I drew. One was that the mound would create a higher water elevation on the Chbat property east of the mound, but would not create standing water west of the mound extending into the [Drainage E]asment . . . . Which on the drawings that I reviewed showed an existing trench at the south end of that easement. And it was my opinion that any water that fell west of the mound would exit through the easement. Tr. Vol. II at 92 (emphasis added.) Mr. Street's assumption that water would not pool to the west of the mound in the Drainage Easement and toward Mr. Sheehey's property was contradicted by Mr. Sheehey's stormwater engineer, Mr. Porterfield. THe Porterfield Testimony and Support for It at Hearing The testimony at hearing of Mr. Porterfield, who conducted a site visit, established the opposite of what Mr. Street assumed. The volume of stormwater runoff that pools east of the mound, that is, water on Lot 9, will not be as great as the volume as the water that pools west of the mound. Water that would have flowed onto Lot 9 from the Eastern Pond Culvert will flow directly to the Bay via the culvert extension. The extension will also protect the Drainage Easement and Lot 8 from water that would have flowed from the Eastern Pond Culvert onto that property. But there is a significant difference between stormwater to the west of the extension and to the east. To the extension's west, the Drainage Easement and Lot 8 will have to contend with stormwater from the Drainage Ditch Culvert, the culvert north of Alden Lane that does not convey stormwater from the pond but that like the Pond Culverts has a discharge point directed at the Drainage Easement. How often and to what extent pooling of stormwater will occur west of the mound due to its presence is difficult to determine on the state of this record.11/ No studies or analyses of the likelihood and severity of storm events and the volumes of stormwater runoff that would be produced by them were conducted by any of the stormwater engineers in the case nor were any such analyses done with regard to pooling caused by the presence of the covered culvert extension. The testimony of Mr. Porterfield, however, and other evidence, demonstrates that that additional collection of water west of the mound caused by the mound will occur following heavy rain. Mr. Street was present in the hearing room throughout the entire hearing, including during the presentation of Mr. Sheehey's case. As Mr. Street candidly testified on rebuttal after he had heard all the evidence: I would also maintain that the drainage easement which has signs of a historical usage as a drainage easement with a trench, in fact, that conveys water safely to the bay, that should be re-established and maintained. That’s what it’s there for.” Tr. Vol III at 181 (emphasis added.) Thus, it became clear to Mr. Street after listening to all the evidence in the case that the Drainage Easement has not been properly maintained. The trench that was expected to carry stormwater toward the Bay no longer exists. In short, the testimony of Mr. Street, for all his many strengths as a witness, falls short of supporting the position of the Department and Mr. Chbat. Having never visited the site,12/ he approved the project on the basis of drawings that do not conform to the on-site physical reality. When presented with the evidence at hearing that the Drainage Easement is not functioning, he championed re-establishment and maintenance of the Drainage Easement. Mr. Chbat placed part of the Swale's functionality problem on the tide pushing stormwater northward but his case also recognized the maintenance problem caused by deposition of sand that besets the Swale. Mr. Thomason, moreover, recognized that the Drainage Easement has the same maintenance issue. Mr. Chbat's stormwater engineer testified During storm events or just normal wave action in the bay, sand is brought back up on to. . . the sandy area at the end of [Chbat's] lot next to the water. And so that . . . tends to inhibit the natural flow down the swale . . . we have the same problem on the drainage easement . . . where sand builds up in that discharge. Tr. Vol. I at 62 (emphasis added). From this record, it is clear that neither the Swale nor the Drainage Easement functions properly. Their functional status, moreover, is due in significant part to lack of maintenance. It may be that maintenance ultimately will not solve the problem; maintenance efforts to keep the Swale and Drainage Easement clear of the sand deposited by tidal activity may require too much effort for them to be reasonably required. But that evidence was not produced. Indeed, the record was silent as to any maintenance efforts with regard to the Swale by Mr. Chbat or with regard to the Drainage Easement by the owner of the easement. The record is also silent as to whether DEP voiced any concern about the maintenance issues that beset the Swale. It is clear that concern was not raised by the Department in regard to the Drainage Easement until the rebuttal phase of the hearing, since the assumption was made that the easement was properly maintained. Whatever communication may have occurred with regard to maintenance issues among the parties, the Department issued the Amended Permit.13/ The Permit/Authorization Number for the Amended Permit is 66-235320-002-DF.14/ Issued December 19, 2008, the Amended Permit has an expiration date of December 19, 2013. The expiration date coincides with the construction phase of five years on the face of the Amended Permit. See Chbat Ex. 4. Mr. Sheehey Challenges the Amended Permit On January 6, 2009, Mr. Sheehey, pro se, filed with DEP a petition (the "Petition") seeking a formal administrative hearing with regard to "Amended Wetland Resource Permit 66- 00235320-002-DF." Although the Petition makes reference to the Amended Permit, it seeks in the first instance enforcement of the Settlement Agreement that relates to the Final Original Permit. The Petition states: "Petitioner believes that the Florida Department of Environmental Protection has jurisdiction over this matter and should enforce the March 20, 2007 Settlement Agreement which requires that Permittee act in conformance with Exhibit 'A' of the Agreement [the drawing of the Swale]." In the event that DEP declined to enforce the Settlement Agreement, the Petition sets out disputed issues of material fact that relate to issuance of the Amended Permit. The Petition was referred to DOAH on February 19, 2009. One week before the final hearing, the Department filed the motion in limine that is discussed in the Preliminary Statement of this Recommended Order. The motion was granted to the extent that it sought to preclude Sheehey from introducing evidence that supported enforcement of the Settlement Agreement since the 2008 Application, which, while bearing similarity to the 2004 Application, is nonetheless an independent application that should be approved or denied on its own merits without regard to the 2004 Application, the Proposed Original Permit, the Settlement Agreement or the Final Original Permit. The case proceeded to hearing on the remaining issues raised by the Petition: 1) whether Sheehey has standing to contest approval of the 2008 Application; 2) whether Chbat gave the notice required by Section 373.413, Florida Statutes, and 3) whether Chbat's application meets the criteria in statutes and rules for issuance of the Amended Permit. Standing The findings of fact relevant to Mr. Sheehey's standing are found in paragraph 9, above. Notice Notice of the 2008 Application was published in The Defuniak Springs Herald-Breeze, a newspaper published in Defuniak Springs, Walton County, Florida. The notice was published on October 23, 2008. The evidence presented by Mr. Sheehey concerning lack of legal notice consisted of testimony by Mr. Sheehey at hearing in response to questions from his counsel. See Tr. Vol. III at 134. The testimony does not establish that Mr. Sheehey was a person who had filed a written request for notification of any pending application affecting his particular area. The testimony of Mr. Sheehey, moreover, establishes that he was given oral notice of the application by Mr. O'Donnell within four days of its filing. WRP Permitting Criteria To obtain a WRP, an applicant must satisfy the criteria in Florida Administrative Code Chapter 62-312 and Section 373.414, Florida Statutes. These criteria govern a range of topics including water quality. Water Quality15/ Florida Administrative Code Rule 62-312.080 provides that no permit shall be issued unless the Department has been supplied with reasonable assurances that the proposed work will not violate water quality standards. Water that enters the pond spends some amount of time in the pond (residence time) before flowing out. During residence time, solids drop out of the water so that the quality of the stormwater that flows out of the pond is reasonably expected to be better than the quality of the stormwater runoff when it entered the pond. Vegetation surrounding the pond, furthermore, enhances the quality of the water in the pond, whether the water’s source is runoff or rain falling directly into the pond. The water that flows out of the pond north of Alden Lane is “existing discharge.” Tr. Vol. I at 65. It generally made its way to the Bay prior to the Swale. Some of it makes its way to the Bay via the Swale now; some of it outside the Swale as overflow. The culvert extension will convey that discharge to the Bay if the extension is installed. The quality of the water is not significantly less when it discharges to the Bay via the Swale or otherwise from the Chbat property than when it would enter the culvert extension should it be installed. It is true that the Swale would have provided filtration and additional treatment to the discharge from the Eastern Pond Culvert as does the Chbat property in general. But that does not mean that the quality of the culvert’s discharge is a concern. The Swale may have been an option preferable to the extension of the culvert as far as water quality goes but all parties agree that the Swale has failed as a conveyance (albeit Mr. Sheehey maintains that the Swale would work with proper maintenance.) That there is a discharge method that improves the quality of the discharge, such as a swale, does not mean that the discharge to the Bay via the culvert extension is of insufficient quality. None of the parties tested the quality of the discharge from the Eastern Pond Culvert. The Department, nonetheless, offered evidence with regard to its quality. The Department concluded that the quality of the pond and its discharge were not of concern. Had the pond been contaminated to an extent that would have given rise to concerns, moreover, the Swale or the culvert extension as a means of conveying the discharge to the Bay would not have made a “discernible difference.” Tr. Vol. II at 80. The Department provided evidence of assumptions made with regard to the quality of the water that led the Department to conclude that testing of the discharge was unnecessary. Mr. O’Donnell, the Department’s expert in the application of state rules and statutes in wetland resource permitting, detailed the assumptions at hearing: My assumption was that that pond was dug some time in the past as a way to provide fill for roads. That it was never any part of . . . [a] stormwater treatment system. And that it conveyed upstream water through the pond and then on down into Choctawhatchee Bay. It was strictly a [borrow pit and a conveyance pond.] It was never permitted as a treatment system in any way that I was aware of in my diligence [in determining whether the extension should be permitted.] Tr. Vol. II at 79. Once Mr. O’Donnell’s testimony entered the record at the behest of Mr. Chbat, the burden shifted to Mr. Sheehey to prove that the applicant had not provided reasonable assurance of water quality. Mr. Sheehey did not offer evidence of any testing of the discharge. Nor did he offer testimony that rebutted Mr. O’Donnell’s opinion. In fact, the testimony of Mr. Wilkinson (Mr.Sheehey's witness) supported Mr. O'Donnell's opinion with regard to water quality. See Tr. Vol. III at 112. In sum, the Department made assumptions that are found to be reasonable based on Mr. O’Donnell’s expertise and experience. Those assumptions were not shown to be unreasonable by Mr. Sheehey. The Department’s conclusions about water quality flow directly from Mr. O’Donnell’s reasonable assumptions. Reasonable assurances have been provided that the project will not violate water quality standards. Public Interest Test Choctawhatchee Bay is not designated as an “outstanding Florida water.” The test that Mr. Chbat must meet therefore is whether the activity proposed by the permit application is “not contrary to the public interest.” § 373.414, Fla. Stat. In making that determination, the Department is directed by the statute to consider and balance seven criteria. See § 373.414(a) 1-7, Fla. Stat. Of the seven, three are at issue once water quality is determined to be of no concern. Two of the three, “[w]hether the activity will be of a temporary or permanent nature,” Section 373.414(1)(a)5., Florida Statutes, and “[t]he current condition and relative value of functions being performed by areas affected by the proposed activity,” Section 373.414(1)(a)7., Florida Statutes, do not require in-depth consideration. With regard to the nature of the project time-wise, the evidence establishes that the culvert extension is intended to be permanent. With regard to current condition, the area affected by the proposed activity is a residential lot, a substantial portion of which is under water following heavy rain. To facilitate the conveyance of stormwater, the lot is served by the Swale. The Swale is not functioning optimally because of lack of maintenance and because of the Ridge. With regard to relative value from the standpoint of water quality, the function being performed by the lot and the Swale is little, at least as established by this record. While it is certainly true that the lot with or without the Swale will filtrate and otherwise treat stormwater runoff from the pond, the difference in the quality of the stormwater conveyed by the culvert extension from that which would enter the Bay without the extension is not significant. See the discussion above of Mr. O’Donnell’s accepted opinions. Of the seven statutory criteria to be weighed and balanced by the Department, the one that is central to this case is found in subparagraph 1., of subsection (1)(a): “[w]hether the [culvert extension] will adversely affect . . . the property of others.” The “property of others” in this case is the property of Mr. Sheehey. The Project’s Effect on the Property of Mr. Sheehey. For the reasons discussed in paragraphs 63-70, above, Mr. Chbat has failed to provide reasonable assurances that the project will not have a detrimental effect on the property of Mr. Sheehey. The extent of the detrimental effect to Mr. Sheehey's property is difficult to determine from this record but it is highly likely based on all the evidence of record that there will be a detrimental effect: additional flooding in heavy rain events.

Recommendation Based on the foregoing, it is recommended that the Department of Environmental Protection deny17/ the Amended Permit for the failure of Mr. Chbat to provide reasonable assurances that the project will not adversely affect Mr. Sheehey's property. DONE AND ENTERED this 14th day of January, 2010, in Tallahassee, Leon County, Florida. S DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of January, 2010.

Florida Laws (5) 120.569120.57206.13373.413373.414 Florida Administrative Code (1) 62-312.080
# 2
FREDERICK B. SPIEGEL vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-000233 (1978)
Division of Administrative Hearings, Florida Number: 78-000233 Latest Update: Apr. 06, 1979

Findings Of Fact Collier Development Corporation, Naples, Florida, owns a triangular tract of land consisting of approximately 16 acres in Naples, Florida. In 1958, the Trustees of the Internal Improvement Fund conveyed by quitclaim deed to Collier Development Corporation all its interests in the property. A 1958 affidavit of Collier's surveyor who prepared the legal description of the land was filed in the Collier County public records and states that the land conveyed by the quitclaim deed was "high land" erroneously shown as bay bottom land according to the original government survey, and that the deed was executed in exchange for the conveyance of certain parcels of bay bottom land in Naples Bay to the Trustees. (Exhibits 1-2) In 1976, Petitioner executed an option agreement with Collier Development Corporation to purchase the land in question, contingent upon certain conditions including a requirement to obtain any required fill permits. On December 27, 1976, Petitioner assigned the option agreement to Michael S. Spiegel and himself as joint tenants. On March 14, 1977, a "short form" application was filed by Petitioner, as authorized by Collier Development Corporation, with Respondent to fill the land above the mean high water line to building grade for future residential, multi-family, or commercial uses. The application reflected that 400 cubic yards of rock riprap would be placed at least five feet upland of the designated mean high water line along the boundary of the property that faced the Gordon River and Rock Creek. The riprap revetment is designed to provide a method of containing upland fill material. The application contemplates that a fabric-like material "Mirafi" will be placed on the ground and wrapped over the riprap barrier. The application further provides that approximately 90,000 pounds of fill material will be trucked into the site and placed behind the riprap material to fill the land to a minimum elevation of four feet. It is also proposed to slope the fill material behind the riprap and plant grass seed thereon. In October, 1977, Petitioner filed a "long form" application which merely amplified the original application. The mean high water line was established by a survey performed under standard procedures and which utilized the existing bulkhead line as a point of reference. The survey was conducted in 1977 and 1978, and the procedures used were approved by and the survey filed in the Department of Natural Resources on June 26, 1978. (Testimony of Park, Lawson, Exhibits 4, 6, 8, 11) By letter dated January 26, 1978, Respondent provided notice of its intent to deny the permit application pursuant to Chapters 253 and 403, Florida Statutes, and Public Law 92-500. The reasons stated for the proposed denial generally were that filling the land would destroy mangrove vegetation which provides a major input of organic material to estuarine tropic webs, and filters and assimilates pollutants from upland runoff. It was stated that the proposed project would eliminate approximately 15 acres of submerged lands and transition zones, as defined in Chapter 17-4, Florida Administrative Code, which would reduce the quality and quantity of the state's marine resources adjacent to Class II waters and "tend to cause degradation of water quality conditions." Thereafter, on January 25, 1978, Petitioner submitted a petition for hearing wherein the jurisdiction of the Respondent in the matter and its grounds for the proposed denial were challenged. (Exhibit 5) The land in question is located south and adjacent to the confluence of the Gordon River and Rock Creek along the north side of U.S. Highway 41. The Gordon River and Rock Creek are tributaries of Naples Bay and all are Class II waters. The area is vegetated by red mangroves with a lesser number of white and black mangroves. A pond of about one-half acre surrounded by red mangroves is located in the southern section of the tract which occasionally overflows into a ditch running parallel to U.S. 41 located within the highway right-of- way. There is a berm alongside the ditch designed to prevent highway runoff from flowing onto Petitioner's land. During high tides, most of the land is inundated to varied depths ranging from two to eight inches. Certain marine vegetational species are present on portions of the land, such as sea grape, sea purslane, sea daisy, and button wood. Certain marine animal life is present in the mangrove area, including coffee bean snails, ribbed mussels, marsh clams, mangrove crabs, fiddler crabs, and mosquito fish. Other marine species, such as common oysters, scorched mussels, and barnacles inhabit the Rock Creek shore line. There is sparse bird population on Petitioner's land that may in part be due to the proximity of Naples Airport. (Testimony of Lawson, Park, Carroll, Fields, M. Spiegel, Exhibits 3, 7, 10) The quality of water in the Gordon River and Rock Creek is adversely effected to some degree by receipt of sewage plant effluent, discharge from nearby canals and runoff from residential and commercial areas. As a result of high bacterial count in these waters, shell fishing and swimming is not permitted. The mangrove forest on Petitioner's property is in a stressed condition as evidenced by the thinness of the canopy. It is probable that this condition was caused primarily by the introduction of fresh water from canals into the surrounding waters. (Testimony of Carroll, Fields, Erwin, Yokel) Mangrove wetlands are an important component of the estuarine ecosystem which provide nutrient stabilization and transformation in the supply of an organic base to the estuarine food chain, filtration of upland runoff, and storage of storm waters. They are a nursery for fish and invertebrate species, and a fish and wildlife habitat. The mangrove system on Petitioner's property is productive and contributing to the needs of marine life in the Naples Bay area. In this respect, most of the detritus produced by the mangrove system occurs below the mean high water line. However, the tidal flow during storm conditions at certain times of the year can release accumulated organic matter from the higher areas. This generally occurs in late summer and early fall when feeding demands of organisms are high. (Testimony of Erwin, Yokel) Although no system for containing surface water runoff was set forth in Petitioner's permit application, it is planned that such runoff will be retained on the site by a site drainage plan that would be accomplished by grading and the use of the existing pond or other means of retention, in addition to the natural percolation into the sandy fill material. (Testimony of Park) The application did not specify the precise distance from the mean high water line at which fill would be placed, but Petitioner clarified this point at the hearing. Fill material will not be placed closer than 100 feet upland of the mean high water line. The mangrove area left intact below that point will enable the ecological system to survive. However, due to the fact that the Naples Bay area does not produce sufficient organic matter to fully support animal life in the area, the loss of a substantial portion of mangroves will impact on the detrital food chain to some extent. (Testimony of Carroll, Yokel)

Recommendation That Respondent issue the requested permit to Petitioner, subject to the modification thereto made at the hearing with regard to the 100' setback as set forth in paragraph 8 of the foregoing Findings of Fact. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 20th day of February, 1979. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 1979. COPIES FURNISHED: H. Ray Allen, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Howard Horowitz, Esquire 3550 Biscayne Boulevard Suite 402 Miami, Florida 33137 William Blackwell, Esquire 3003 North Miami Trail Naples, Florida

# 3
DEPARTMENT OF ENVIRONMENTAL REGULATION vs ELIZABETH MCSHEEHY, 91-007281 (1991)
Division of Administrative Hearings, Florida Filed:Mary Esther, Florida Nov. 13, 1991 Number: 91-007281 Latest Update: May 26, 1993

Findings Of Fact On June 26, 1986, the Department of Environmental Regulation (DER) issued a permit, No. 661168901, to Elizabeth R. McSheehy authorizing construction on the shore of Choctawhatchee Bay of a seawall 165 feet long and eight feet high "faced with rip-rap . . . and backfilled with 18 cubic yards of sand fill . . . in accordance with [an] attached map and drawing." Joint Exhibit No. 1. The permit application had proposed that the seawall "TIE INTO MR. HEATH['S] SEAWALL," and the attached drawing indicated a point of beginning along the seawall already protecting the lot to the east, then owned by Mr. Heath, now owned by Prentice M. Thomas. The drawing has no compass rose and does not specify the angle of either leg of the permitted seawall. The construction permit expired December 30, 1987 (well beyond the 120 days within which the application indicated it would be necessary to complete construction, once begun.) At hearing, the parties stipulated that Ms. McSheehy had erected or caused to be erected a seawall at the location permitted on or before December 30, 1987. DER does not dispute that the seawall functioned as such when built. Seawall Fails Ms. McSheehy received a letter from Mr. Thomas dated June 6, 1990 (in an envelope postmarked June 22, 1990) stating, "I recently visited my lot at Four Mile Post and regret to inform you that the seawall you installed on your property has been demolished by the winter and spring storms." Petitioner's Exhibit No. 2. The letter reported that her "lot was eroding at a rapid pace." Id. Afraid that his own lot would be affected, despite its well-maintained seawall and rip-rap he had added, Mr. Thomas "beseech[ed her]. . . to take action to arrest the erosion of [he]r shoreline." Petitioner's Exhibit No. 2. The lot west of Ms. McSheehy's has no seawall. T. 48. Its shoreline had also eroded, judging from photographs in evidence. Soon after receiving the letter, Ms. McSheehy inspected the property for the first time since the summer before. She found the piles on which the seawall had been constructed in 1986 or 1987, now standing as far as 30 feet out in the bay. Only the eastern 20 or 30 feet of the seawall remained intact. Remnants, including individual boards and wall fragments comprised of as many as four boards had washed up on the receded shoreline. When DER's James Eric Buckelew happened on the site on July 26, 1990, he concluded from the erosion that the seawall had ceased to function as such some months before. Bay waters reached 20 or 30 feet further inland, covering about a tenth of an acre landward of what remained of the seawall. Mr. Buckelew took photographs of the site. Petitioner's Exhibit No. 1. Seawall Now in Bay Before the month ended and apparently before anybody from DER communicated with Ms. McSheehy, the seawall was rebuilt in its original location. No additional fill has been placed landward of the seawall, which now has water on both sides. In various trips to the site and otherwise in responding to this turn of events, DER has expended at least $245.37. DER advised Ms. McSheehy that a permit could be issued for construction of another seawall along what seems to be the new mean high water line, but that she had acted illegally in having the seawall restored at a location now some 20 or 30 feet out in the Bay. (T. 115). After first applying for and receiving a permit to remove the existing seawall and construct a new one further landward, she took the position that restoration of the original seawall had been lawful, and these proceedings ensued.

Recommendation It is, accordingly, RECOMMENDED: That DER make final its proposed orders for corrective action, unless within a reasonable time DNR conveys or leases to respondent the property lying between the seawall and the mean high water line. DONE AND ENTERED this 24th day of February, 1993, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of February, 1993. APPENDIX TO RECOMMENDED ORDER CASE NO. 91-7281 Petitioner's proposed findings of fact numbers 2, 3, 5, 6 and 12 have been adopted, in substance, insofar as material. With regard to petitioner's proposed finding of fact number 1, the permit issued in 1986, but it is not clear that construction was accomplished in 1986. With regard to petitioner's proposed finding of fact number 4, the seawall failed sometime between the summer of 1989 and the spring of 1990. With regard to petitioner's proposed findings of fact numbers 7, 8, 9, 10 and 11, use of the word "unauthorized" renders these proposed conclusions of law. Respondent's "proposal for the ruling of the hearing officer" did not contain separately numbered proposed findings of fact. COPIES FURNISHED TO: Virginia B. Wetherell, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Richard L. Windsor, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Elizabeth R. McSheehy 516 Mooney Road Fort Walton Beach, Florida 32547

Florida Laws (8) 120.57120.68403.031403.087403.121403.161403.813403.905
# 4
DOROTHY B. LEAVENGOOD vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 77-000484 (1977)
Division of Administrative Hearings, Florida Number: 77-000484 Latest Update: Jan. 16, 1978

Findings Of Fact In 1950, Petitioner acquired lots 8 and 9, block 23, of Lone Palm Beach subdivision, third addition, which lots front on Boca Ciega Bay in Pinellas County, and she has held the property in free simple since. Petitioner's late husband, her predecessor in title, acquired the lots in 1941. They constitute the tip of man-made peninsula jutting bayward from a barrier island bordered on the other side by the Gulf of Mexico. In 1926, the lots did not exist as such, because the peninsula had not yet been built. Petitioner's exhibit No. 10. Since the creation of the lots, their aquatic periphery has varied continually, on account of accretion and reliction. In the first half of the last decade, wooden and metal stakes were sunk along the shoreline, landward of the water's edge. Since then, water has washed away Petitioner's beach, moving the shoreline inland an average distance of approximately thirty feet. Erosion has been more severe along the northern half of Petitioner's beach than along the southern half. Seawalls have been built along adjacent properties on either side of Petitioner's parcel. The evidence did not establish what proportion of this erosion may have been attributable to the effects of Hurricane Agnes or to the location of neighboring seawalls or to any other particular cause. In 1972, the Honorable C. Richard Leavengood, Petitioner's present husband, hired Rupert Osteen, a contractor, to build a seawall. Pinellas County issued a building permit to Mr. Osteen, covering a "Seawall - 356LF - Type D," Petitioner's Exhibit No. 5, on March 14, 1973. (In September of 1951, the Town of Redington Beach had issued a building permit for "Dredging and Filling behind Sea Wall Constructed on [what is now Petitioner's] Rear Property Line.") Construction began, but came to an abrupt halt in July of 1973, when Mr. Osteen was arrested for building a seawall "without having obtained the recommendation of the Chief of Engineers and the Authorization of the Secretary of the Army prior to beginning," a criminal offense of which he was subsequently convicted in the United States District Court for the Middle District of Florida. Respondent's Exhibit No. 4. Before work on the seawall stopped, Petitioner had caused some 4,500 cubic yards of fill dirt to be deposited on the lots. After Mr. Osteen's arrest, Petitioner applied for a fill permit to the Pinellas County Commission, sitting as the Pinellas County Water and Navigation Control Authority. The Authority granted the permit on March 19, 1974, on condition that the seawall be made to tie in with the existing seawall on lot 7, which adjoins Petitioner's property to the west. On or about August 16, 1974, Petitioner applied to the Department of the Army prior to beginning," a criminal offense of which he was subsequently convicted in the United State District Court for the Middle District of Florida. Respondent's Exhibit No. 4. Before work on the seawall stopped, Petitioner had caused some 4,500 cubic yards of fill dirt to be deposited on the lots. After Mr. Osteen's arrest, Petitioner applied for a fill permit to the Pinellas County Commission, sitting as the Pinellas County Water and Navigation Control Authority. The Authority granted the permit on March 19,1974, on condition that the seawall be made to tie in with the existing seawall on lot 7, which adjoins Petitioner's property to the west. On or about August 16, 1974, Petitioner applied to the Department of the Army for a permit, pursuant to Sections 403 and 1344 of Title 33, United States Code. Petitioner applied for the "after the fact" permit at issue in these proceedings on May 10, 1974. At one point in the course of negotiations between Petitioner and Respondent, Mr. Douglas Jones, Chief of Respondent's Bureau of Permitting, indicated that Respondent would permit Petitioner to erect another seawall along the present mean high water line. Eventually, Respondent's staff notified Petitioner that it would recommended denial of an after the fact permit for the existing seawall, and Petitioner filed a request for administrative hearing, which initiated these proceedings. Aerial photographs dating back to 1942 were received in evidence. Respondent's Exhibits Nos. 5 through 11. None of these phontographs show land as far out in the water as the portion of the seawall Mr. Osteen finished. The partially completed seawall is further waterward tan the 1971 interface between land and water. Respondent's Exhibits Nos. 9 and 10. In November of 1973, Alan J. Burdette, Jr., a marine biologist, who is now employed by Respondent, inspected lots 8 and 9 of Lone Palm Beach subdivision and found water in the low area landward of the seawall. More recent photographs indicate that the seawall still stands somewhat offshore. E.g.., Respondent's Exhibit No. 16, taken on September 7, 1977. Mr. Bardette's inspection revealed oyster and fiddler crabs inside the seawall and clams just outside. Mangroves, which were not there at the time construction began, had sprung up. Removal of the seawall would create additional shallow bottom where algae, clams, oysters, mangroves and other marine life could flourish. Mr. R. S. Murali, a hydorgraphic engineer employed by Respondent, visited Petitioner's property the day before the hearing in this matter was held. While he was on the site, the wind blew from the southwest and waves with an average height between eight and nine inches struck Petitioner's unfinished seawall every 1.2 seconds. Mr. Murali discovered evidence of erosion under the seawall, which was caused by wave action. If the seawall were placed more landward, so that waves travelled up a sloping beach before striking it, the erosion problem could be significantly alleviated.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That Petitioner's application for an after the fact fill permit authorizing the seawall which has already been constructed around lots 8 and 9, block 23, of Lone Palm Beach Subdivision, third addition, be denied. DONE and ENTERED this 30th day of November, 1977, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 904/488-9675 APPENDIX Paragraph one of Petitioner's Proposed Findings of Fact has been adopted, in substance, insofar as relevant:. Paragraph two of Petitioner's Proposed Findings of Fact has been adopted, in substance, insofar as relevant, except for the date of the permit issued by the Pinellas County Water and Navigation Control Authority, which is immaterial. Paragraph three of Petitioner's Proposed Findings of Fact is apparently predicated on Petitioner's Exhibit No. 12, an uncertified copy of page 74 of Pinellas County's Plat Book 20. Although a handwritten notation on the exhibit reads "Plat Recorded June 21, 1937" such extraneous handwriting on an uncertified copy is not "evidence of a type commonly relied upon by reasonably prudent persons in the conduct of their affairs.". Section 120.58(1)(a), Florida Statutes (1975). The question of the Butler Act's applicability is a question of law rather than of fact and it has not been necessary to decide the question. Paragraph four of Petitioner's Proposed Findings of Fact has not been adopted, for the most part, because of lack of support in the evidence. Paragraph five of Petitioner's Proposed Findings of fact emphasizes that the testimony as to flora and fauna related to a time considerably after application for the after the fact permit was made. While this is true, what is at issue is the ecological consequences of leaving the seawall, so that the relevant time period is the time period beginning when the application was made and extending indefinitely into the future. COPIES FURNISHED: Ms. Carol Haughey, Esq. Department of Environmental Regulation 2562 Executive Center Circle, East Montgomery Building Tallahassee, Florida 32301 Mr. Ross H. Stanton, Jr., Esq. 280 Florida Federal Building 26274th Street North St. Petersburg, Florida 33704 Ms. Patricia M. Duryee, Esq. Department of Environmental Regulation 2562 Executive Center Circle, East Montgomery Building Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION DOROTHY B. LEAVENGOOD, Petitioner, vs. CASE NOS. 77-484 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION, Respondents. /

Florida Laws (1) 120.57
# 5
TURTLE LAKE LAND TRUST vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 80-000379 (1980)
Division of Administrative Hearings, Florida Number: 80-000379 Latest Update: Nov. 01, 1991

The Issue The issue presented here concerns the entitlement of the Petitioner, Turtle Lake Land Trust, to be permitted by the Respondent, State of Florida, Department of Environmental Regulation, to dredge approximately 600,000 cubic yards of material in the area known as Turtle Lake, which is located near Jackson street and Fairfield Drive, Pensacola, Florida. The purpose of this project is to create a manmade lake. The dredged material world be placed on the lake shore.

Findings Of Fact On May 9, 1979, the Respondent, State of Florida, Department of Environmental Regulation, received an environmental permit application from the Petitioner, Turtle Lake Land Trust. The details of that permit application were contained in a form provided by the Department together with attachments to that form. A copy of this permit application may be found as the Respondent's Exhibit No. 2 admitted into evidence. By this application, Turtle Lake requested that it be allowed to dredge approximately 600,000 cubic yards of material in an area known as Turtle Lake, which is located near Jackson Street and Fairfield Drive, Pensacola, Florida. The purpose of the excavation was to establish a manmade lake approximately twelve (12) feet in depth in an area which is a cypress swamp and subject to periodic inundation by water. The materials removed from the dredging would be deposited on the shores of the lake, effectively raising the ground elevation at lakeside. The dredging would intersect the groundwater on the project site. The project is part of an overall development which would involve construction of residential housing and commercial facilities in the vicinity of the lake, with the lake to be used for fishing, sailing and other water recreation. The proposal of the Petitioner was reviewed by the Department and certain timely additional requests were made from the Department to the applicant to provide information necessary to evaluate the request for permit. The exhibits dealing with the request for additional information and responses to those requests may be found as Respondent's Exhibits 3, 5, 8, 9, 10 and 11 admitted into evidence. The Department solicited comments from the Florida Game and Freshwater Fish Commission on this subject and the comments were provided by correspondence from the Executive Director of the Commission. These comments may be found in Respondent's Exhibit No. 6 admitted into evidence, which is a copy of those remarks. The Department of Environmental Regulation, in keeping with the provision Subsection 253.124(3), Florida Statutes, performed a biological survey of the project site and submitted it to the Board of County Commissioners of Escambia County, Florida, for the Board's action. A copy of the survey may be found as Respondent's Exhibit No. 7 admitted into evidence. The Escambia County Board of County Commissioners, by Resolution dated October 11, 1979, approved the project subject to action by the Respondent and the United States Corps of Engineers. A copy of this Resolution may be found as the Respondent's Exhibit No. 12 admitted into evidence. Upon consideration of the permit request, the Department of Environmental Regulation notified the applicant of its intent to deny the permit request. This Letter of Intent to Deny was issued on January 31, 1980, and a copy of it may be found as Respondent's Exhibit No. 13 admitted into evidence. This matter has been presented for consideration before the State of Florida, Division of Administrative Hearings, upon referral by the Respondent of the original Petition and has been heard after opportunity for and amendment to that Petition. The hearing was conducted on September 23, 1980, as scheduled, in keeping with the provisions of Subsection 120.57(1), Florida Statutes. The project site is located in a cypress swamp which has also been referred to as a cypress head. The southern boundary of the project site east of Fairfield Drive has an impoundment area which is fringed by pine trees and other upland species, to include gallberry, southern brackin, blackberry and oak. There is within this area aquatic vegetation dominated by Eleocharis sp. and fragrant waterlily (nymphaea odorata). The cypress head itself, which is bounded on the west by Fairfield Drive, consists of cypress, blackgum, sweetbay and cinnamon fern, fragrant waterlily and pickerel weed (pontederia lanceolata). Within the zone of the cypress head standing water may be found, the dimensions and depths of which were not established at the hearing in sufficient detail to allow further comment in these findings. Fairfield Drive serves to contain the water found in the Turtle Lake swamp on the eastern side of that roadway; however, there is an exit from the cypress head under Fairfield Drive by a series of three 24-inch culverts which connect the manmade ditches. These ditches flow into Bayou Marcus and Bayou Marcus Creek and eventually into Perdido Bay. This water connection is a direct connection and Bayou Marcus, Bayou Marcus Creek and Perdido Bay are waters of the State. Immediately adjacent to Fairfield Drive east of that roadway in the vicinity the culverts water may be found standing and could be navigated and this may be seen by Respondent's Composite Exhibit No. 14. This water which although subject to navigation wad not identified sufficiently at the hearing to establish its length and breadth. The depth was two to three feet. This water adjacent to Fairfield Drive is not within that area of the proposed excavation. At present, the storm water runoff from the Forte subdivision located to the north and east of the project site, enters the cypress head swamp and at times of periodic inundation, this storm water runoff arrives at the area of the culverts into the ditch system and into Bayou Marcus, Bayou Marcus Creek and Perdido Bay. The oils and greases, fertilizers, pesticides, nutrients and other forms of pollutants which make up the storm water constituents are somewhat filtered by the cypress head swamp as it now exists, prior to the entry of those materials into the culvert area adjacent to Fairfield Drive and from there into the transport mechanism constituted of the ditches, bayou, creek and bay. If the project is built out, the dredging will remove those flora mentioned herein and the fauna which inhabit this swamp and will remove the cypress head from future use by the fauna which normally inhabit this form of environment. It would also take away the natural filtration to be provided by the swamp in the way of removing undesirable storm water constituents from the residential runoff in Forte subdivision and the proposed development associated with the lake construction. The removal of the swamp would destroy the capacity to convert raw nutrients into usable sources of food for indigenous dawn stream organisms. As can be seen in the Petitioner's Exhibit No. 1, the existing water table at the site is approximately 23 feet and ordinary highwater elevation has been measured at 24 feet with an existing grade of 21 feet. If the lake were excavated, the lake would show a water table with an elevation of 20 feet. The berm or dykes around the lake would have an elevation of 24 feet. Storm water from the current subdivision and the residential and commercial build-out associated with the project in question would be carried through underground storm water piping into four holding areas which have been referred to by the applicant as drainage corridors and retention area. These areas are separated from the lake by siltation screens and will serve the function of filtering out some storm water constituents which are solid particulates. The constituents which have been dissolved will flow through the siltation screen devices and into the lake proper. When the lake rises to a depth of 23 feet, the excess water will he transported through a proposed ditch into the area of the three culverts under Fairfield Drive and via those manmade conveyances into Bayou Marcus, Bayou Marcus Creek and Perdido Bay. Those storm water constituents such as oils and greases, fertilizers, pesticides, nutrients and other forms of pollutants which have not settled or been filtered will be transported through this system and deposited into waters of the State. In this connection, the drainage corridor and retention areas are not designed for long-term retention; they are primarily for short-term detention, depending on the amount of loading from the storm water runoff. The only pre-treatment associated with the storm water runoff is that filtration that occurs in the drainage corridor and retention area. (There was some discussion of possible gravel filters in conjunction with the drainage corridor and retention area but they were not part of the plan submitted to the Department in the process of project review.) In addition to the introduction of the storm water contaminants into the waters adjacent to Fairfield Drive at the area of the culverts and the bayou, creek and bay, these contaminants will be introduced into the ground water in the lake proper Although some increase in retention of storm water runoff may be expected, if the project were built, there would be a significant increase in the introduction of dissolved contaminants into waters over which the Respondent has jurisdiction, i.e., Bayou Marcus, Bayou Marcus Creek and Perdido Bay. Increases in these areas will occur in biochemical oxygen demand and undesirable nutrient and dissolved oxygen levels will decrease if this project is constructed. In association with this change, an increase in nuisance species would occur. The Petitioner has failed to do any background sampling to establish the natural background levels of the aforementioned conditions in waters of the State in order to identify whether water quality in the receiving waters would be degraded from existing conditions to the extent of violating the Department's water quality criteria.

Recommendation Based upon a full consideration of the facts as presented and the Conclusions of Law reached in this matter, it is RECOMMENDED that the Secretary of the State of Florida, Department of Environmental Regulation, deny the Petitioner a dredge and fill permit pursuant to Rule 17-4.28, Florida Administrative Code; a construction, operating and maintenance permit pursuant to Section 403.087, Florida Statutes; a ground water permit in accordance with Rules 17-3.071, Florida Administrative Code, and 17- 4.245, Florida Administrative Code; and be it further RECOMMENDED that the Secretary take no further action to require a permit(s) as might be indicated in keeping with Chapter 253, Florida statutes. 1/ DONE AND ENTERED this 22nd day of October, 1980, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The Collins Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of October, 1980.

Florida Laws (3) 120.57403.031403.087
# 6
SQUARE TWO, INC. vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 86-004761 (1986)
Division of Administrative Hearings, Florida Number: 86-004761 Latest Update: Mar. 30, 1987

The Issue Two issues, one of fact and one of law, are raised in this case as follows: Was the fill material placed in the waters of the state? Is the Petitioner estopped to assert its regulatory powers against the Respondent by the issuance of a permit by the county in which the site is located?

Findings Of Fact In early 1986 the Respondent caused approximately 663 cubic yards of fill material (See Petitioner's Exhibit 4) to be placed on the property at Lake Jackson containing approximately .73 acres (hereafter referred to as the site) described briefly as Section 32, Township 2 North, Range 1 West, Leon County, Florida. Respondent did not deny placing or causing the fill to be placed on the site. Respondent asserted that the point at which the fill was placed was not "waters of the state." In 1980, a predecessor in title to .47 acres of the .73 acres owned by Respondent applied for and received a permit from Leon County for filling on the .47 acres of the present site. This permit provided in part "Additional permits may be required by other regulatory agencies for the proposed projects. Any other required permits should be secured prior to initiation of any excavation or fill activities on these projects." Neither Respondent nor any of its predecessors in interest made application for or received a permit from the Florida Department of Environmental Regulation (DER) to place fill material in waters of the state on the site. When Respondent placed or caused the fill material to be placed on the site in 1986, the Respondent did not implement any of the special conditions or directives contained in the 1980 permit issued by the county. In February 1986, two months after the fill material was placed on the site, the county notified the Respondent by mail to remove the fill because it violated Leon County Ordinances and did not have the required DER dredge and fill permit. See Petitioner's Exhibit 9. Lake Jackson is located in Leon County, Florida. Its waters are waters of the state. The water level of Lake Jackson rises and falls, and would have submerged periodically the original elevation of the site at the point at which the fill was placed. See photographs of area taken in 1980, 1986, and 1987. On March, 1980 David Bickner visited the site. Bickner, a DER Field Inspector, observed and photographed a concrete and stone wall which had been built on the site roughly parallel to U.S. Highway 27. During the period of Bickner's inspection, the water level of Lake Jackson was lower than the elevation of the site; however, willows (Salix spp.) were growing landward of the wall. See Petitioner's Exhibit 8. In February and March of 1986 Roger Menendez visited the site. Menendez, a DER Field Inspector, observed and photographed the wall described above and the fill which had been placed landward of the wall, between the wall and U.S. Highway 27, and in the area north of the line of hay bales. Juncus Effusus, Nymphaea and willow, plant species identified by rule as submerged wetland species, were observed and photographed growing in the filled area and on the area adjacent to it. See Photographs, Petitioner's Exhibit A and B. In late 1986 and the week before the hearing, Todd Campbell visited the site. Campbell, a DER employee with degrees in zoology and ecology, observed the plant species growing in the undisturbed area adjacent to the filled area. All the plants (90-100 percent of the ground cover) were submerged species. Willows were observed by Campbell growing on the fill itself. Campbell made test borings on the fill site in many locations. The borings revealed that the soil beneath the fill was hydric soil typical of the soil immediately adjacent to the filled area. See Petitioner's Exhibits 6 and 7. It was Campbell's opinion based upon his observations of plant species and test borings of soil type that similar vegetation had grown at the original elevation of the site prior to the introduction of the fill. The 88 foot contour line has been established as the ordinary high water line for Lake Jackson based upon the agency's prior experience. All of the area filled was below the 88 foot contour line. See Petitioner's Exhibit 1. The site upon which the fill was placed is waters of the state based upon vegetation observed and photographed by Bickner, Menendez and Campbell. This finding is consistent with the fill being placed below the 88 foot contour line.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED That the Notice of Violation and Orders for Corrective Action should be made final against the Respondent. DONE and ORDERED this 30th day of March 1987, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of March, 1987. COPIES FURNISHED: Richard L. Windsor, Esquire Assistant General Counsel State of Florida, Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Ben H. Ervin, Esquire ERVIN & REICHMAN Post Office Box 41 Monticello, Florida 32344 Dale Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson, Esquire General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 CASE NO. 86-4761 RECOMMENDED ORDER ADDENDUM "A" LEGAL DESCRIPTION Commence at a concrete monument marking the Northeast corner of Section 5, Township 1 North, Range 1 West, Leon County, Florida, thence with the Easterly line of said Section run South 01 degrees 27 minutes 04 seconds East 587.15 feet, thence North 87 degrees 56 minutes 04 seconds West 6.24 feet to a point on the Southerly boundary of a 30 foot roadway thence with said Southerly Boundary run North 87 degrees 56 minutes 04 seconds West 1449.67 feet to a point of curve to the right on the Northeasterly right of way line of State Road No. 63 (U.S, No. 27), thence with said right of way line run with a radius of 11,519.20 feet, through a central angle of 03 degrees 00 minutes 46 seconds for an arc distance of 605.71 feet, thence North 42 degrees 36 minutes 52 seconds West 613.60 feet to the POINT OF BEGINNING, thence North 52 degrees 20 minutes 01 seconds East 66.06 feet to a point on the Randolph Meander Line of Lake Jackson, thence with said Meander Line run North 37 degrees 24 minutes 12 seconds West 149.48 feet, thence leaving said Meander Line run South 52 degrees 20 minutes 01 seconds West 82.29 feet to a point on the Northeasterly Right of Way of State Road No. 63 (U.S. No. 27), thence with said Northeasterly Right of Way run South 42 degrees 36 minutes 52 seconds East 150.00 feet to the POINT OF BEGINNING, containing 0.255 acres, more or less. Commence at a concrete monument marking the Northeast corner of Section 5, Township 1 North, Range 1 West, Leon County, Florida, thence with the Easterly line of said Section, run South 01 degrees 27 minutes 04 seconds East 587.15 feet, thence North 87 degrees 56 minutes 04 seconds West 6.24 feet to a point on the Southerly boundary of a 30 foot roadway, thence with said Southerly boundary, run North 87 degrees 56 minuets 04 second West 1449.67 feet to a point of curve to the right; to North easterly Right of Way of State Road No. 63 (U.S. No, 27), thence with said right of way run with a radius of 11,519.20 feet through a central angle of 03 degrees 00 minutes 46 seconds, for an arc distance of 605.71 feet, thence North 42 degrees 36 minutes 52 seconds West 763.60 feet to the POINT OF BEGINNING. From said POINT OF BEGINNING run thence North 52 degrees 20 minutes 01 seconds East 82.29 feet to a point on the Randolph Meander Line of Lake Jackson, thence with said Meander Line run North 36 degrees 24 minutes 12 seconds West 218.24 feet, thence leaving said Meander Line run South 52 degrees 20 minutes 01 seconds West 105.99 feet to a point on the Northeasterly Right of Way of State Road No. 63 (U.S. No. 27), thence with said Northeasterly Right of Way run South 42 degrees 36 minutes 52 seconds East 219.00 feet to the POINT OF BEGINNING, containing 0.47 acres, more or less.

Florida Laws (2) 403.141403.161
# 7
DAVID E. MUSSELMAN vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 92-001352 (1992)
Division of Administrative Hearings, Florida Filed:Key West, Florida Feb. 28, 1992 Number: 92-001352 Latest Update: Jul. 13, 1992

Findings Of Fact Background Petitioner, David E. Musselman, is the owner of Lot 23, Block 22, Cudjoe Gardens Eighth Addition, Cudjoe Key, Monroe County, Florida. The lot measures 127 feet along its front and rear property line, 135 feet along its side property lines and, similar to adjacent lots, its rear property line abuts an artificially created waterway. Currently, most of petitioner's lot enjoys an elevation of six feet; however, from the edge of the waterway landward a distance of approximately 20 feet [to what has been referred to as the "toe of the existing slope" in these proceedings] the surface consists of exposed caprock at an elevation of approximately four inches above mean high water. It is petitioner's desire to construct a single family residence upon such lot and, incident to such construction, to erect a seawall along the edge of the waterway such that the elevation at the waterway will be increased by two feet, and to backfill from the seawall to his home. Such backfilling would require the deposition of approximately 3,540 square feet of fill within the Department's jurisdiction, which was shown to extend from the edge of the waterway to the toe of the existing slope, and would raise the elevation in such area two feet above existing grade. On December 16, 1991, petitioner filed an application with respondent, Department of Environmental Regulation (Department), for an exemption from the Department's wetland permitting requirements. If approved, such exemption would allow petitioner to construct the vertical seawall along the waterway, and backfill from the seawall to his proposed home. By notice of agency action dated February 14, 1992, the Department proposed to deny petitioner's application predicated on its conclusion that his proposal did not meet the exemption criteria established by Rule 17- 312.050(1)(g), Florida Administrative Code. Petitioner filed a timely protest to contest the Department's conclusion. The exemption Pertinent to this case, Rule 17-312.050(1)(g), Florida Administrative Code, exempts from permitting the following activities: (g) Construction of seawalls or riprap, including only that backfilling needed to level the land behind the seawalls or riprap, in artificially created waterways where such construction will not violate existing water quality standards, impede navigation or adversely affect flood control. An artificially created waterway shall be defined as a body of water that has been totally dredged or excavated and which does not overlap natural surface waters of the state. For the purpose of this exemption, artificially created waterways shall also include existing residential canal systems . . . . At hearing, the parties stipulated that the waterway which abuts the rear property line of petitioner's lot is an artificially created waterway, as well as an existing residential canal, and that the proposed project will not violate existing water quality standards, impede navigation, or adversely affect flood control. Notwithstanding, the Department contends that petitioner's application should be denied because no need has been demonstrated that would support the construction of the seawall along the edge of the waterway, as opposed to locating it further inland, and therefore the amount of backfill, with its attendant loss of wetlands, is excessive. For the reasons set forth in the conclusions of law, the Department's position is untenable as a matter of law. 1/

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department enter a final order approving petitioner's application for an exemption to construct a seawall, and to backfill from such seawall to his proposed home, as applied for. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 4th day of June 1992. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of June 1992.

Florida Laws (2) 120.57403.813