Findings Of Fact Based upon the record evidence, the Hearing Officer makes the following findings of fact: Martin Gold is now, and has been since July, 1986, licensed by Petitioner as a Registered Specialty Contractor authorized to do painting and waterproofing work in Dade County. He holds license number RX 0051718, which expires June 30, 1989. Since receiving his license he has been disciplined twice by the Florida Construction Industry Licensing Board. Gold is the President of Team Leisure Corp., a construction company, and is also its "qualifying agent." On August 14, 1986, Team Leisure Corp. entered into a written contract with Terry Dudley and his wife, Patricia, in which it agreed, for $12,000, to build a two-room, 27-foot by 13- foot addition to the Dudley home located at 15510 Leisure Drive in Dade County and to install new windows in the existing structure. According to the terms of the agreement, Team Leisure was to do "no painting." In his capacity as President of Team Leisure Corp., Gold hired William Sernaker to directly oversee the completion of the construction work specified in the Dudley contract. At the time, Sernaker was licensed as a general contractor in Dade County. As part of his arrangement with Gold, Sernaker assumed responsibility for ensuring that all work permits and inspections necessary to complete the Dudley project were obtained. On September 4, 1986, Sernaker obtained a building permit for the Dudley project. Thereafter, work on the project commenced. The foundation for the addition was laid and, on September 10, 1989, it passed the inspection of James Tucker, a Dade County building inspector. Fifteen days later, Tucker conducted a tie beam inspection. This phase of the project also received his formal approval. Sernaker obtained a roofing permit on October 14, 1986. The exterior of the roof was inspected by Russell Bergsma, another Dade County building inspector, on October 21, 1986. It too passed inspection. An electrical permit was obtained for the Dudley project on November 17, 1986, by Robins Electric, a subcontractor. When the electrical work was initially inspected by Grant Morse, another Dade County building inspector, it was rejected because there were a "few outlets missing." The record is unclear as to the results of any subsequent electrical inspections. Morse also conducted an inspection of the framing work done on the Dudley project. He did so on or around November 21, 1986. In his view, the framing was "not to code." Accordingly, he left a "tag" at the job site on which he gave the following written explanation for his rejection of the framing work: All window bucks must be tight with caulking, no gaps. When the stucco meets the window frame, it should be set back at approximately a 45-degree angle at a width of one quarter to provide a groove to be filled with caulking. Continuous back bed of caulking must be maintained. A follow-up inspection of the framing work was performed by Bergsma on December 1, 1986. In Bergsma's opinion, while some corrections had been made, deficiencies remained. He therefore issued another rejection. A third framing inspection was conducted on December 3, 1986. Tucker was the inspector who performed this inspection. He approved the work that had been done. Prior to this inspection, Gold had paid another contractor $600 to "redo" the framing. This additional expense was not passed on to the Dudleys. Morse attempted to conduct a final building inspection on December 22, 1989. He was unable to do so, however, because "[n]o one was home." From the outset, Gold kept abreast of the progress that was being made on the Dudley project by communicating with Sernaker. He also visited the job site on at least a weekly basis. Gold also heard from the Dudleys concerning the status of the project. The Dudleys closely monitored the work of Sernaker and his crew. If the work was not done to their satisfaction, they expressed their disapproval to Sernaker and, if he did not rectify the matter, they complained to Gold over the telephone. The following were among the complaints made by the Dudleys: the foundation was not level; the roof did not contain any fiberglass material; the window frames did not fit properly; the wood used for the open beam ceilings had cracks in it and was unsightly; the walls in the den were not level and had cracks in them; the linoleum on the Dudleys' screened-in porch was ripped by workers putting up a wall; the outside stucco was cracking and peeling; and trash was left on the property. An effort was made to address the Dudleys' concerns. For instance, in response to the Dudleys' complaints, a "thin cap" was placed over the foundation to make it level. The roof was redone with fiberglass material. The Dudleys were reimbursed for the linoleum they needed to replace on their porch. A contractor was hired to correct the framing problem. Nonetheless, the Dudleys became increasingly dissatisfied with Team Leisure Corp.. Sometime shortly before January 6, 1987, they became so dissatisfied that they ordered Sernaker and his crew off their property and refused to make any additional payments. Following this incident, Gold met with the Dudleys and attempted to mollify them. This was his first face-to-face meeting with them. He offered to send another contractor to the Dudleys' home to perform the work the Dudleys believed needed to be done to satisfactorily complete the project. The Dudleys accepted this offer. On January 6, 1987, Gold sent the Dudleys a letter which read as follows: As per our mutual agreement, these are the items you requested be taken care of. Once taken care of, you agree to sign completion certificate so we can be funded. COMPLETED (please check upon satisfaction) 1.) Touch up outside windows. 2.) Windows to be locked in. 3.) Walls in den to be taken down and leveled out. 4.) Frame around closet door. 5.) Fix two windows; replace concrete in doors and windows. 6.) Clean up. 7.) Replace vinyl, in rear den. 8.) $100.00 dollars to Mrs. Dudley, for clean-up. 9.) 10 year guarantee- roof and release of lien [sic]. 10.) Concrete over build. 11.) Crack under window sill. 12.) Nail in door frame. 13.) Gaps in drywall bedroom. 14.) Stucco cracking outside. 15.) Electrical inspection. (not to be Mike Charles.) Accepted and Approved: x x After receiving this letter, Mr. Dudley checked all but items 2, 5, 6, 8, and 9 on the letter's "completion certificate." Neither he nor his wife, however, signed this "completion certificate." Although the cracks in the outside stucco had been repaired at the time Dudley checked item 14, the stucco subsequently started cracking again. A final building inspection of the Dudley project was conducted by Tucker on January 13, 1989. The project was "turned down" by Inspector Tucker because it was unpainted. Under their contractual agreement, the Dudleys, not Team Leisure Corp., were responsible for the painting of the project. The painting was not done because the Dudleys noticed cracks reappearing in the outside stucco. On or around March 4, 1987, Mr. Dudley telephoned Inspector Bergsma and asked him to conduct an informal field inspection of the project. Bergsma complied with Dudley's request. When he arrived at the Dudley home, Dudley showed him a "gap on the rear of the house ... where the two roofs are at different levels and come together." Bergsma told Dudley that "[i]t didn't belong there" and that it would have to be eliminated if the structure was to pass a final building inspection. As of the date of the hearing, the structure had not passed such an inspection. Team Leisure Corp. received $10,200 for the work done in connection with the Dudley project. The remaining $1,800 of the $12,000 that the Dudleys were to pay pursuant to the contract was held in escrow by a bank. Ultimately, this $1,800, along with approximately an additional $500 from Team Leisure Corp., was given to the Dudleys as part of a settlement between them and Team Leisure Corp.. The money was to be used by the Dudleys to pay another contractor to complete the project to their satisfaction.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order (1) finding Respondent guilty of contracting outside the scope of his license in violation of Section 489.129(1) (j) , Florida Statutes; (2) imposing a $750 administrative fine upon Respondent for said violation, and (3) dismissing the remaining charges against Respondent set forth in the instant administrative complaint. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 30th day of May, 1989. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of May, 1989. COPIES FURNISHED: Elizabeth Alsobrook, Esquire Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, Florida 323399-0792 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Carlos Garcia, Esquire 8603 Dixie Highway Suite 400 Miami, Florida 33143 =================================================================
The Issue Whether Petitioner is entitled to be certified by endorsement as a standard building inspector.
Findings Of Fact Respondent is the agency of the State of Florida that certifies standard building inspectors pursuant to the provisions of Part XII of Chapter 468, Florida Statutes (consisting of Sections 468.601 - 468.633). By application dated November 7, 1996, Petitioner applied for certification as a building inspector. This application contemplated that Petitioner would sit for the certification examination. Respondent determined that Petitioner was qualified to sit for the Principles and Practice portion and the Technical portion of the certification examination. Petitioner did not achieve a passing score on the certification examination. Consequently, his application for certification was rejected. By application dated December 22, 1997, Petitioner applied for certification as a building inspector without having to take the licensure examination. This was properly construed by Respondent to be an application for certification by endorsement. Petitioner requested Respondent to waive the certification examination pursuant to the provisions of Section 468.613, Florida Statutes, which provide as follows: The board shall examine other certification of training programs, as applicable, upon submission to the board for the consideration of an application for certification by endorsement. The board shall waive its examination, qualification, education, or training requirements to the extent that such examination, qualification, education, or training requirements are determined by the board to be comparable with those established by the board. By his application dated December 29, 1997, Petitioner sought certification based upon his qualifications1 and upon what his counsel referred to as "substantially equivalent" exams. The "substantially equivalent" exams to which counsel for Petitioner referred were to the examinations Petitioner passed in order to be licensed as a general contractor and as a roofing contractor. Petitioner's application reflects that he passed licensure examinations during 1983 in Broward County and in Dade County in the general contractor category. Petitioner passed a similar examination in Palm Beach County, Florida, in 1986. Part XII of Chapter 468, Florida Statutes, was created by Chapter 93-166, Laws of Florida. Prior to 1993, there was no state-wide certification of building inspectors. There was no evidence as to the contents of the examinations Petitioner passed in 1983 and 1986, and there was no evidence as to the contents of the certification examination administered by Respondent to candidates for certification as building inspectors. Consequently, there is no basis upon which a comparison of these examinations can be made.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner's application for certification by endorsement be denied. DONE AND ENTERED this 21st day of April, 1999, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 1999.
Findings Of Fact At all times relevant hereto, Respondent, Benjamin J. Eigner, held certified general contractor's license number CG C001534 issued by Petitioner, Department of Professional Regulation, Construction Industry Licensing Board. In 1980, Respondent was employed by the City of Tamarac as its chief building official. In that position his major function was to administrate and supervise employees who enforced the South Florida Building Code and the Code of Ordinances of the City of Tamarac. (Respondent's Exhibit 2). His duties included, inter alia, the review of qualifications and issuance of certificates of competency to contractors who wished to work within the City. On or about February 7, 1980, the Broward County Grand Jury issued a true bill or indictment against Respondent charging him with having solicited a bribe in his capacity as chief building official for the City of Tamarac. On or about July 3, 1980, Respondent entered a plea of nolo contendere in Broward County Circuit Court to the charge of bribery. Adjudication of guilt and imposition of sentence was withheld, and Respondent was placed on probation for a period of five years. As a special condition, Respondent was also required to spend one year in the Broward County Jail. (Respondent's Exhibit 1). Because of health problems, Respondent was medically discharged from serving the remainder of his one year incarceration on January 26, 1981.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be found guilty as charged in the Administrative Complaint and that his certified general contractor's license be suspended for a period of nine months from the date of the final order entered herein after which time it shall be automatically reinstated. DONE and ENTERED this 22nd day of October, 1981, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of October, 1981. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Myron B. Berman, Esquire P. O. Box 1113 North Miami Beach, Florida 33160 Mr. Benjamin J. Eigner 7850 Beechfern Circle Tamarac, Florida 33321
Findings Of Fact The Respondent, Thomas J. Embro holds two licenses issued by Petitioner. They are RG0021774, registered general contractor, and RC0021647, registered roofing contractor. He has held these licenses since 1974. Sometime in the fall of 1979 Respondent was hired by Richard F. Rogers to replace the roof on a residential structure located at 4119 N.W. 12th Avenue, Gainesville, Florida. At that time the house was for sale. Mr. Rogers, who is a real estate agent, wanted the roof replaced in anticipation of a Veterans Administration financed sale of the house to Mr. William Schrader. Prior to beginning work on the roof Mr. Embro did not obtain a building permit from the City of Gainesville for the job. On October 1, 1979 Mr. Schrader made a complaint to the Building Division of the City of Gainesville. His complaint stated that the roofing work performed by Respondent was unsatisfactory. Mr. Al Davis, a building inspector employed by Gainesville, reviewed the city records and determined that a permit had not been issued to Respondent for reroofing Mr. Schrader's house. On October 3, 1979 Mr. Davis wrote a letter to Mr. Embro which stated in its entirety: October 3, 1979 Mr. Thomas J. Embro 3816 SW 18 Street Gainesville, Florida Dear Sir: We have received a complaint from Mr. Bill Schrader of 4119 NW 12th Avenue on the reroofing that you performed on his residence. After receiving the complaint I investigated out records and the work performed by your company and found the following violations: Our records indicate that a permit was not issued to reroof the above address, this is a violation of Section 106.1 of the Southern Standard Building Code. The roof material was not installed correctly. Shingles shall be installed in accordance to manufacture [sic] re- quirements and some parts of the roof are too flat for shingles. Interior damage has been caused by the roof leaking from not installing the shingles as required. The above violations shall be corrected within 10 days from receipt of this letter. Your compliance will make further action unnecessary. Sincerely, /s/ Al Davis Building Official cc: Mr. Bill Dow, State Investigator Mr. Bill Schrader Mr. Embro applied on October 25, 1979 for a permit from Gainesville for the work at 4119 N.W. 12th Avenue. The permit was issued on December 6, 1979. It is not unusual in Gainesville for a contractor to begin a construction job before the appropriate permit is applied for or issued. When this is not a frequent practice of a particular contractor the City imposes no penalty. If the contractor habitually begins construction without permits, the City imposes a penalty by charging him double the regular permit application fee. Mr. Embro was not charged a penalty by the City in this case. In the course of his contracting business Mr. Embro frequently asked his wife to make permit applications for him before he begins work. In this case he believed that she had applied for the appropriate permit. The City of Gainesville allows persons other than the contractor to apply for a building permit on behalf of a contractor if the contractor has first filed an authorization with the City designating an agent. Mr. Embro filed such an authorization on February 13, 1980 for his wife to be his designated agent.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Professional Regulation, Florida Construction Industry Licensing Board enter a final order dismissing the Administrative Complaint against Thomas J. Embro. DONE and RECOMMENDED this 16th day of November, 1981, in Tallahassee, Florida. MICHAEL PEARCE DODSON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of November, 1981.
Findings Of Fact The foregoing findings of fact 1, 2, and 3 are incorporated herein by reference as if fully set forth anew. On January 8, 1987, the Respondent was found guilty of violating Sections 489.129(2), 489.129(3), and 489.129(1)(g) Florida Statutes, by the Construction Industry Licensing Board in DPR Case No. 60987, DOAH Case No. 88- 0002. The Respondent was not present at that Board meeting. He asserted this was due to lack of timely notice of the Board's meeting. Respondent was fined $1,000 by the Final Order of the aforementioned Board filed/served on February 20, 1987. The Respondent has failed to pay the fine. Respondent has not appealed the final order or fine. Respondent expressed himself at formal hearing as intending never to pay the lawfully imposed fine.
Conclusions The foregoing Conclusion of Law 14 is adopted and incorporated herein as if fully set forth anew. Respondent is charged with gross negligence, incompetence or misconduct in the practice of contracting pursuant to Section 489.129(1)(m), Florida Statutes, for failure to pay his $1,000 fine pursuant to the Board's February 20, 1987 final order. However, Petitioner has cited no statutory or rule authority which labels a licensee's refusal to pay a fine or obey a final order of the Construction Industry Licensing Board as gross negligence, incompetence, or misconduct in the practice of contracting. (Emphasis supplied, see definition of "contracting" at Section 489.105, Florida Statutes). Without such authority, the factual allegations of the administrative complaint, although proved, support no conclusion that a statute or rule has been violated. Petitioner's recourse lies not in this forum but in enforcement, execution, and collection actions in Circuit court.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that: The Construction Industry Licensing Board enter its final order dismissing the charge of a violation of Section 489.129(1)(m). DONE and RECOMMENDED this 30th day of September, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of September, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 88-0275, 88-0732 The following constitute rulings pursuant to Section 120.59(2), Florida Statutes, upon the parties' respective Proposed Findings of Fact (PFOF). DOAH CASE NO. 88-0275 Petitioner's PFOF have been accepted with certain modifications for greater clarity and to conform to the record as a whole. Respondent's Closing Statement is accepted in part in FOF 9. The remainder is rejected as mere argument or as based upon hearsay not properly in the record. DOAH CASE NO. 88-0732 Petitioner's PFOF have been accepted with certain modifications for greater clarity and to conform to the record as a whole. Respondent's Closing Statement is mere legal argument addressing the underlying facts of the previous final order finding Respondent guilty of certain violations and assessing a $1,000 fine. Absent a timely appeal, these matters are immaterial and rejected. These proposals are also rejected as mere argument. COPIES FURNISHED: Fred Seely, Executive Director Construction industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 G. W. Harrell, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 David L. Norris 3144 Northwest 39th Court Lauderdale Lakes, Florida 33309 Bruce D. Lamb, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
Findings Of Fact At all times material to this proceeding, Respondent was a registered roofing contractor, having been issued License No. RC0034672, in the name of John M. Sneed, Beall and Associates Roofing Corp., 7650 Southwest 135th Street, Miami, Florida 33156. Sometime during the month of October, 1951, Jerry Stamos entered into an oral agreement with Bill Parry and Billy Duncan, to have Parry and Duncan reroof Stamos's home at 441 Castonia Avenue, Coral Gables, Florida. The contract price for the reroofing work was $4,000. At no time was either Duncan or Parry licensed to perform roofing work. As a result, after Mr. Stamos was unable to obtain a building permit in his own name to perform the work, Duncan contacted Respondent, and requested that Respondent pull the building permit for the job. On October 20, 1981, Respondent obtained City of Coral Gables, Department of Building and Zoning Permit No. A48375 to perform the work on the Stamos's property. At the time the building permit was pulled by Respondent, no work had commenced on the job. Duncan and Parry were paid a total of $4,000 for the job, $100 in cash; $2,000 on October 13, 1981; and an additional $1,900 on October 22, 1981. Shortly after the building permit was pulled and work had been commenced on the property by Duncan and Parry, Duncan and Parry stopped work on the roof and never returned. Respondent was on the job site on at least one occasion when work was being performed. No notice was furnished to Mr. Stamos concerning cessation of work on the project, nor was he ever given an explanation of why work stopped and was never recommenced by Parry, Duncan, or Respondent. Respondent never supervised any of the work performed by Parry or Duncan, nor did he ever call for any inspection of the project by the City of Coral Gables, Department of Building and Zoning. The South Florida Building Code, Section 3401.1(b) provides as follows: INSPECTION. The Building Officials shall be notified by the permit holder and ample time for mandatory inspections to be made as follows: At the time the anchor sheet is being mopped to non-nailable decks. At the completion of mechanically fastening the anchor sheet to nailable decks and before mopping. During the operation of shingling or tiling. Upon completion of the roof covering. On December 1, 1981, Respondent contacted the City of Coral Gables, Department of Building and Zoning, and cancelled the permit previously obtained by him on October 20, 1981. At that time, Respondent represented to city officials that construction had never started on the project, although he knew that representation to he false. The building project remained unfinished for a period in excess of ninety days before Mr. Stamos had the job finished by another contractor.
The Issue The issue in the case is whether the Respondent violated Subsections 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(i), 489.129(1)(m), and 489.129(1)(o), Florida Statutes (2002), as alleged in the Petitioner's Administrative Complaint, and, if so, what penalty should be imposed.
Findings Of Fact The Petitioner is a state agency charged with the licensing and regulation of building contractors pursuant to Chapter 489, Florida Statutes. The Respondent is a Florida State Certified Building Contractor who holds license number CBC053702. On December 9, 2002, Mack Hayes entered into a contract with "McKay Engineering/Construction" to build an addition to the Hayes residence located at 3011 East Deleuil Avenue in Tampa, Florida. Although the contract refers to McKay Engineering/Construction rather than McKay Engineering Services, Inc., subsequent change orders to the contract show the Respondent's license number in the letterhead. In correspondence to the Petitioner, the Respondent also acknowledged that he was the contractor on the Hayes project. The Hayes contract did not contain a statement explaining the consumers' rights under the Construction Industries Recovery Fund. Counsel for the Petitioner, however, stated that Mr. Hayes remains eligible for assistance from the Fund. The original contract price for the construction was $54,700. Change orders created an adjusted price of $57,450. During the course of the construction, Mr. Hayes made four payments to the Respondent totaling $49,000. Not long after the construction commenced in January 2003, Mr. Hayes and his wife became frustrated with the slow pace of the construction. Mr. Hayes originally understood that the work would take about 90 days. Instead, the construction remained uncompleted after nine months. In July 2003, the pace of work on the Hayes' addition slowed substantially and in October, the Respondent ceased work altogether. The Respondent ceased work on the project despite the fact that he had not been fired or otherwise given a reason to cease work. In order to facilitate progress on the construction, Mr. Hayes paid the air conditioning subcontractor $1,836, the electrical subcontractor $1,000, and the stucco subcontractor $800, even though it was the Respondent's responsibility under the parties' contract to pay the subcontractors. The Respondent's construction of the new roof of the residence was of particular concern to Mr. Hayes. The tie-in of new roof framing with the existing roof was misaligned and otherwise improperly installed which caused the new roof to sag. The records of the City of Tampa indicate that the Respondent did not obtain a permit from the City for the roofing work at the Hayes residence. In an attempt to repair the roof, large holes were cut in the ceiling to gain access for cutting some of the rafters. The holes in the ceiling were not repaired by the Respondent. The plywood and other wood used on the unfinished eaves was left exposed to weather for months, which has resulted in water damage to the wood that will necessitate that it be replaced. Mr. Hayes obtained cost estimates from two other contractors to repair the roof, gables, and eaves installed by the Respondent. One estimate was $17,490 (including materials) and the other estimate was $15,550 (without materials). Numerous aspects of the construction project were never started or were started and then abandoned, including the gables and eaves, the door trim and hardware, internal electrical box, attic access, plumbing, and front trim. Mack Hayes paid $2,500 to Ezekial Bain and $2,500 to Drains, Etc. to finish some of this work after the Respondent abandoned the project. Taking into account the adjusted contract price of the construction, the amount paid to the Respondent by Mr. Hayes, the direct costs paid to subcontractors by Mr. Hayes, and the reasonable estimated costs for repair of the roof, gables, and eaves, the total financial damages that the Respondent caused to Mr. Hayes is $17,676. The Petitioner did not present expert testimony regarding the competency of the Respondent as a building contractor. Without such testimony, the record evidence is not sufficient to clearly and convincingly demonstrate that the problems associated with this particular project were due to incompetence. The problems could have been caused solely by the Respondent's mismanagement and misconduct. The Petitioner incurred investigative costs of $817.66 for the investigation and prosecution of this case.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order requiring: that the Respondent pay financial restitution to the Hayes of $17,676; that the Respondent obtain seven hours of continuing education in the area of Chapter 489, Part I, Florida Statutes, in addition to the hours required for renewal of the Respondent's certification; that the Respondent's license be suspended for two years; and that the Respondent reimburse the Petitioner for its investigative costs of $817.66. DONE AND ENTERED this 18th day of July, 2005, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of July, 2005. COPIES FURNISHED: Brian Elzweig, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Curt L. McKay 9726 Timmons Loop Thonotosassa, Florida 33592 Leon Biegalski, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Tim Vaccaro, Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792