The Issue Whether a certified general contractor's license issued to Francisco Vincente De Moya (Petitioner) that has been classified null and void should be reinstated pursuant to the "hardship" provision of section 455.271(6)(b), Florida Statutes.1
Findings Of Fact Respondent is the state agency that regulates general contractors in the State of Florida. In 1998, Respondent issued Petitioner certified general contractor license CGC 05992. Certified general contractors are required to take a total of 14 hours of continuing education courses in specified categories each biennial period.2 Credit is generally posted for the biennial period during which the course was taken. All continuing education courses discussed in this Recommended Order were taken by Petitioner using the internet and reported electronically. Respondent typically posts and maintains such credits electronically. Credits are typically posted for the biennial period in which the credits are earned. If a licensee had been deficient for a prior biennial period, Respondent's staff can manually post-date credits from a subsequent biennial period to the biennial period that is deficient. 2004-2006 Biennial Period On August 23, 2004, Petitioner submitted to Respondent a personal check in the amount of $209.00 as payment of renewal fees for his general contractor's license for the biennial period 2004-2006. Petitioner's general contractor's license was not renewed for the 2006-2008 biennial period because Petitioner had not completed sufficient continuing education hours during the 2004-2006 biennial period to meet his continuing education requirements. On September 1, 2006, Respondent classified the status of Petitioner's as "expired/delinquent." As of September 1, 2006, and as of the date of the formal hearing, Respondent's records reflected that Petitioner was deficient in his continuing education requirements for the biennial period 2004- 2006 by a total of six hours in three categories.3 One hour of the deficiency was in the category of advanced building code. Four hours of the deficiency were in the category of general. One hour of the deficiency was in the category of workers' compensation. 2006-2008 Biennial Period On September 29, 2006, Petitioner submitted to Respondent a payment in the amount of $309.00 for renewal fees and late fees for his general contractor's license for the biennial period 2006-2008. On October 20, 2006, Petitioner completed a four hour continuing education course in "core training." Petitioner testified that this credit was intended to be for the 2006-2008 biennial period. Prior to the renewal deadline of August 29, 2008, Petitioner requested and obtained from Respondent an extension of 30 days to submit proof of completion of continuing education credits for the 2006-2008 biennial period and payment of renewal fees for the 2008-2010 biennial period. 2008-2010 Biennial Period On September 29, 2008, Petitioner paid Respondent $209.00 as payment for renewal fees for his general contractor's license for the 2008-2010 biennial period. On September 28 and 29, 2008, Petitioner completed 14 hours of continuing education credit and submitted the certificates of completion for each course to Respondent with the notation "Please find Certificates of Completion for my G.C. license # CGC 059992 for 2006-2008." Respondent received the certificates of completion on October 1, 2008. These hours satisfied Petitioner's continuing education requirements for the 2006-2008 biennial period. On October 2, 2008, Petitioner's certified general contractor's license became "null and void."4 With knowledge that his contractor's license was considered null and void,5 Petitioner took 26 hours of continuing education credit between November 24, 2008, and August 7, 2009, and submitted his certificates of completion to Respondent. Respondent did not apply any of the 24 credits Petitioner earned between September 29 and December 11, 2008, to the 2004-2006 biennial period, nor was there any evidence that Petitioner requested Respondent to do so.6 In 2006, Petitioner's mother-in-law (Ms. Careaga) was diagnosed with degenerative dementia and began to deteriorate physically and mentally. From 2007 until her death on December 15, 2008, Ms. Careaga became immobile, more disoriented and confused, and required 24 hour supervision. Petitioner had a close relationship with his mother-in-law. Petitioner and Petitioner's wife became Ms. Careaga's 24-hour primary caregivers so she would not have to go to a nursing home. Petitioner continued to work full-time and serve as a primary caregiver until Ms. Careaga's death. During this period, Petitioner assisted other family members in closing down the restaurant that his mother-in-law had owned and operated. On January 12, 2011, Respondent denied Petitioner's application for the reinstatement of his general contractor's license. The Notice of Denial was not admitted as an exhibit in this proceeding. However, a "Notice of Intent to Deny," purporting to be the Respondent's proposed denial, was attached to the Petition for Formal Hearing. That Notice of Intent to Deny recites that the Petitioner's license expired due to "non payment" [sic] of renewal fees. That statement is incorrect. The license became null and void because of the deficient continuing education requirements for the 2004-2006 biennial period. The Notice of Intent to Deny also found that Petitioner failed to establish hardship within the meaning of section 455.271(6)(b). Petitioner is eligible to obtain a new license by retaking the licensure exam and by establishing that he is of good moral character and financially stable and responsible. His experience has been established by virtue of his prior license. Petitioner also holds licensure as an architect. That license also became null and void during the same time frame as his contractor's license. On February 17, 2011, the Florida Board of Architecture, considering the same facts described above, approved Petitioner's application for reinstatement of his architecture license.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order denying Petitioner's application for reinstatement of his certified general contractor's license based on the hardship provision set forth in section 455.271(6)(b). DONE AND ENTERED this 22nd day of August, 2011, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 2011.
The Issue The issue presented is whether the Respondent committed the offenses alleged in the Administrative Complaint, and, if so, what penalty should be imposed.
Findings Of Fact At all times material hereto, Respondent, Manuel Cabanas was licensed as an electrical contractor and held license number ER 0006946 issued by Petitioner, the Electrical Contractors' Licensing Board. On or around December 13, 1988, the Construction Trades Qualifying Board of Dade County, Florida (Board) charged Respondent with the misrepresentation of material facts concerning his employment or work status on documents submitted with his application to obtain a business certificate of competency. A hearing on the charge was held before the Board on January 3, 1989. At the hearing, Respondent initially pled not guilty, but changed his plea to no contest sometime after a Board member advised Respondent that his testimony indicated that he was actually guilty of the charge. On January 6, 1989, Respondent was notified by the Board that after hearing all the testimony, a determination had been made that Respondent was guilty of the charge. As discipline for his act, the Board revoked Respondent's certificate of competency.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered suspending Respondent's license number ER 0006946, conditioned upon reinstatement of the local license as long as Respondent intends to practice in the jurisdiction of the Construction Trades Qualifying Board of Dade County, Florida. As to any other jurisdiction, the appropriate penalty is suspension of Respondent's license number ER 0006946 for a period of six months. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 21st day of December 1989. JANE C. HAYMAN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division Administrative Hearings this 21st day of December 1989.
The Issue Whether the respondent committed the violations alleged in the Administrative Complaint, and, if so, the penalty which should be imposed.
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Department of Business and Professional Regulation is the state agency responsible for investigating and prosecuting complaints made to the Department for violations of the requirements of chapter 489, part I, Florida Statutes. Sections 489.131(7)(e) and 455.225, Fla. Stat. Pursuant to section 489.129(1), the Construction Industry Licensing Board ("Board") is the entity responsible for imposing discipline for the violations set out in that section. At all times material to this case, Mr. Cote was a certified general contractor operating under License Number CGC006199 issued by the Construction Industry Licensing Board. Mr. Cote currently holds this license, and he has been a licensed general contractor since 1973. At all times material to this case, Mr. Cote was the licensed qualifying agent for JLC Enterprises, Inc. On January 12, 1995, Noel Mais, on behalf of Noel Mais Roofing, contracted with Judith Braun to re-roof property she owned located at 8914 Northwest 26th Court, Coral Springs, Florida. The contract price was $7,000.00, with $3,000.00 required as a down-payment, $3,000.00 to be paid after the roof was dried in, and $1,000.00 to be paid on completion of the project. Neither Mr. Cote nor JLC Enterprises, Inc., was a party to this contract. In late January, 1995, Mr. Mais approached Mr. Cote and requested that he apply for the necessary building permit from the City of Coral Springs. He provided to Mr. Cote a workers' compensation waiver and exemption, a Certificate of Insurance for general commercial liability insurance, and a Certificate of Competency issued by Broward County, Florida, with an expiration date of August 31, 1995. Mr. Mais also told Mr. Cote that he had submitted all of the papers necessary to register his Broward County Certificate of Competency with the state but had not yet received his registration. Mr. Cote relied on the documents and the representations of Mr. Mais regarding his registration status with the state. On or about February 1, 1995,1 Mr. Cote submitted an application to the City of Coral Springs for a building permit to re-roof property owned by Ms. Braun and located at 8914 Northwest 26th Court, Coral Springs, Florida, naming JLC Enterprises, Inc., as the contractor and identifying the estimated cost of the project at $7,000.00. Mr. Mais gave Mr. Cote $300.00 when he applied for the permit. Mr. Cote used $150.00 of this money to pay the permit application fee and $60.00 to pay for two re- inspections which had to be done on the roof. On or about February 17, 1995, the City of Coral Springs issued Permit Number 95-443.2 Mr. Mais commenced work on the project a few weeks after the contract was signed, but before Mr. Cote applied for the permit. According to Ms. Braun, Mr. Mais started "like gangbusters" and quickly stripped the old tiles off of the roof and applied the tar paper. After Mr. Cote agreed to apply for the permit, he told Mr. Mais not to work on the project until the permit was issued. According to Mr. Cote, Mr. Mais returned to work the day after the permit was issued and, the "next day," the job failed inspection because the nail spacing was not consistent with the new code. Mr. Mais re-nailed the roof according to code, but it failed re-inspection because the flashing was not painted. This was done, and the job passed a second re-inspection. Mr. Cote looked in on the job a couple of times after this and saw that nothing was being done. He contacted Mr. Mais and asked why he was not working on the project, and Mr. Mais told him that he was waiting for Ms. Braun to give him some money so he could buy the tiles. When Ms. Braun called Mr. Cote and complained that no tile had been delivered, he went to Mr. Mais's home and insisted that he "get some tile on that roof." The next day, Mr. Mais brought a load of tiles and piled them on the roof.3 Ms. Braun paid Noel Mais the $3,000.00 down-payment specified in the contract by a check dated January 12, 1995, the day the contract was executed. Then, notwithstanding the payment schedule stated in the contract, Ms. Braun paid Mr. Mais $3,000.00 by check dated January 25, 1995. She paid Mr. Mais the remaining $1,000.00 due under the contract by checks dated March 28 and 31, 1995, and April 13, 1995. After receiving full payment, Mr. Mais abandoned the job, and, when Ms. Braun told Mr. Cote she had paid Noel Mais in full for the job, Mr. Cote refused to finish the work because he had not received any portion of the payment. In November, 1995, Ms. Braun contracted with R. J. Chambers Roofing, Inc., to complete the work on her roof for $4,500.00. The work was completed, and she paid Mr. Chambers the contract price. The evidence presented by the Department is sufficient to establish that Mr. Cote knew that Mr. Mais was not registered with the State of Florida as a roofing contractor and that Mr. Cote stated on the permit application that his company, JLC Enterprises, Inc., was the contractor for the Braun re-roofing job even though he was not a party to the contract.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board issue a Final Order finding that Jacques Cote violated section 489.129(1)(e) and (n), Florida Statutes; imposing an administrative fine in the total amount of $1,000.00, consisting of a $500.00 fine for each of the two violations; assessing the costs of investigating and prosecuting the violations; and requiring Mr. Cote to make restitution to Judith Braun in the amount of $1,000.00. DONE AND ENTERED this 6th day of May, 1997, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 6th day of May, 1997.
Findings Of Fact At all times relevant hereto, respondent, Pedro P. Landera, was a certified general contractor having been issued license number CG C005371 by petitioner, Department of Professional Regulation, Construction Industry Licensing Board (Board), in March 1973. In January 1986 the license was suspended by the Board for three years and, except for the charges pending in this proceeding, Landera would be eligible to have it reactivated in early 1989. Thus, Landera has been without authority to use his license for the last three years. Landera did not contest the Board's suspension action and, in a settlement stipulation, admitted he violated Subsections 489.129(1)(c), (d), (e), (f) and (m), Florida Statutes (1981), by certain conduct taken in December 1983. On August 11, 1986, an individual using the name of James Burke entered into a construction contract with Charlie E. Mincey, the owner of Charlie Tires Service, 1700 N. W. 79th Street, Miami, Florida. The contract, which has been received in evidence as petitioner's exhibit 4, called for Burke, "in a timely manner," to make the following additions to Mincey's tire shop: construct a 34' X 40' room onto the existing building, erect an aluminum shed across the front of the building, including a four foot concrete slab floor, and add a five foot wall across the back side of the building. Burke represented on the contract that he held license number 254514-4. However, a search of the Board's records revealed Burke held no state license. The total price for the work was $15,650. On August 13, Mincey paid Burke $3,000 as a down payment on the job. According to Mincey, Burke began work on the additions several weeks after the contract was executed and continued to do so on and off for a few months. Eventually, a concrete block wall for the 34' x 40' room was built, but it had no roof, windows, doors, electric wiring, plumbing or paint. The aluminum shed was never built nor did Burke construct a five foot wall at the rear of the building as required by the contract. During October and early November 1986 Mincey made additional payments to Burke in the amount of $3,175, 1,000, $500, $400, $300, $300, and $40. This made a total of $8,715 paid by Mincey to Burke. Despite these payments, several subcontractors came to the job site during the same time period to unload materials but requested payment from Mincey before they would release them. Mincey paid the subcontractors $2,593.64, as evidenced by receipts received in evidence as petitioner's exhibit 7. When Burke did not return to the job site, and the project was still far from completed, Mincey attempted to contact Burke but could not find him. When he left the job site for the final time, Burke gave Mincey no notice of his intention to leave the job unfinished or any reason for doing so. Burke's whereabouts are still unknown, and there is now pending an outstanding warrant for his arrest. On September 30, 1986, a building permit application was filed with the Metropolitan Dade County building and zoning department seeking a permit for work to be done on Mincey's business. The application was filled out with three different colors of ink and in more than one person's handwriting. A carbon copy of the application has been received in evidence as petitioner's exhibit 9. The document was authenticated by a permit clerk of the Metropolitan Dade building and zoning department who identified the cashier's validation stamp, issuance date and permit number affixed to the document, all being indicia that the application was received and processed by that department. Further, the clerk attested to the fact that the carbon copy was a document normally kept in the regular course of business by her department. The application carries the signature, license number and social security number of respondent. The authenticity of respondent's signature was confirmed by a questioned document examiner whose testimony has been accepted as being credible and persuasive and was corroborated by respondent's own admission that the signature was his own. The author of the remaining writings on the document is unknown. Pursuant to the above application, a building permit was issued on October 1, 1986, for the work performed by Burke. The inspection record, which has been received as petitioner's exhibit 8, reflected that the job site was inspected by a Dade County inspector on October 1 and November 12, 1986. Also, the inspection record reflected that Gila Construction Company (GCC) was the contractor on the job. GCC is a Miami firm that Landera qualified in March 1984. Its owner is Gilbert Castillo. Mincey's building remains unfinished as of this date, and he contends the value of the work is less than the $11,308 that he paid to Burke and the subcontractors. In attempting to resolve the matter, Mincey learned that Landera's license number was on the permit application, and a complaint was eventually filed with the Board. However, prior to hearing, Mincey had never seen or talked to Landera, knew nothing of GCC, and considered the business transaction to be between he and Burke. Landera denied knowing Burke or authorizing him to use his license. Also, he maintained that he has not used his suspended license since the Board's action in early 1986. He denied signing the application in question and had no explanation as to how his signature got on the application except to suggest that someone may have obtained one with his signature and then fraudulently used the same to obtain a permit. Even so, there was no reason for Landera to sign an application during this period of time since his license was under suspension. Castillo, who owns GCC, denied knowing Burke or Mincey or having any knowledge of or participation in the Mincey job.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that respondent be found guilty as set forth in the conclusions of law, that he pay a $3,500 fine, and that his license be suspended until January, 1991. DONE AND ORDERED this 10th day of February, 1989, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of February, 1989. APPENDIX Petitioner: 1-2. Covered in finding of fact 1. 3-4. Covered in finding of fact 2. Covered in findings of fact 3. and 5. Covered in finding of fact 4. Covered in finding of fact 6. Covered in finding of fact 1. Respondent: Covered in findings of fact 1 and 2. Covered in findings of fact 3 and 5. Covered in findings of fact 4 and 5. 4-5. Covered in finding of fact 8. Covered in findings of fact 2, 5 and 6. Covered in findings of fact 6 and 9. Covered in finding of fact 6. 9 Covered in findings of fact 9 and 10 COPIES FURNISHED: George W. Harrell, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Luis F. DeLaCruz, Jr., Esquire 300 Sevilla Avenue Suite 313 Coral Gables, Florida 33134 Kenneth E. Easley, Esquire General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201
The Issue Whether Respondent committed the violations alleged in the Administrative Complaint and, if so, what disciplinary action should be taken.
Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made: Respondent is now, and has been at all times material to the instant case, a Florida-licensed roofing contractor and general contractor. He received his roofing contractor's license on August 10, 2004, and his general contractor's license on October 13, 2005. At all times material to the instant case, GGC has held a certificate of authority authorizing it to engage in contracting in Florida through a qualifying agent. At all times material to the instant case, Respondent has been the primary qualifying agent for GGC. On January 5, 2007, GGC, through Respondent, entered into a written contract with Assad and Millicent Thompson, agreeing, for $37,135.00, to construct a rear porch lanai addition to the Thompsons' single family home in Royal Palm Beach, Florida (Project). The Thompsons paid GGC (by check) $11,140.50 at the time they entered into the contract. They made three subsequent payments to GGC (by check) totaling $21,232.50. The last of these payments was made on or about April 17, 2007. On January 9, 2007, GGC, through Respondent, applied for a permit from the Palm Beach County Planning, Zoning, and Building Department to perform the work it had agreed to do on the Thompsons' home. The permit was subsequently issued. In or around March of 2007, GGC began work on the Project. Dissatisfied with the progress GGC was making on the Project, the Thompsons, on June 5, 2007, sent the following letter to Respondent: With reference to the delay in completing the above construction, we are writing to request your immediate attention. We would like to know specifically: The reason for the delay[.] Your intention in writing as to your estimated time of completion of [the] specified project. Please note we have not physically seen you since April 19, 2007. We understand that inspection of the roof on May 10th resulted in certain violations and as per your conversation with Assad [Mr. Thompson] (when he called you on May 20th), you had problems contacting the Engineer. Please note that his name, telephone and fax are clearly indicated on the plan[s]. Per telephone conversation with him, he has not heard from you recently. You have indicated impatience and anxiety on our part, quite frankly the patience of JOB would have run out long ago. The pile of rubbish is a breeding room for all kinds of creatures and has been a disgusting sight not only for us, but for our neighbors. The open roof has created a vulnerable situation for us and can only deteriorate as we are now in hurricane season. We urge you to contact us urgently with your plan of action. Not having received a written response from Respondent, the Thompsons, on June 25, 2007, sent a follow-up letter to Respondent, which read as follows We note that you have ignored our previous letter of June 5th and you have also failed to honor your telephone promises of June 8th and June 19th to proceed with stucco/electric/rubbish removal etc. In fact absolutely nothing has been done on this job since May 18th. This is totally unacceptable. We have arrangements in place for use of the patio July 14th, cancellation of which will result in serious inconvenience for us. Please be advised that if no progress is made by June 30, 2007, we will be forced to seek all measures at our disposal to have the patio satisfactorily completed. We once again request your urgent co-operation in this matter. The next day, June 26, 2007, the Thompsons received a letter from Respondent (sent by facsimile transmission) acknowledging his receipt of the Thompsons' June 25, 2007, letter. In his letter, Respondent explained that he was "in a bad situation financially" due to circumstances "out of [his] control" related to another project, and he asked the Thompsons to "help [him] resolve[] this matter" by paying the "stucco man" $1,000.00 for materials and an additional $1,000.00 "when [the stucco work] was completed," as well as paying $400.00 for a dumpster to be brought to the Project site (which payments would go towards the monies the Thompsons had to pay for the Project under their contract with GGC). The Thompsons wrote back to Respondent that same day (June 26, 2007), advising him that they would pay for the materials for the stucco work "upon presentation of the invoice, then pay $1,000 for the job on completion as [Respondent had] requested," and that they also would "pay the dumpster charges on completion of the clean-up." Ernest Joseph was the "stucco man" that GGC sent to the Thompsons' home to work on the Project. He last worked on the Project in mid-July 2007. The Thompsons paid Mr. Joseph (by check) a total of $2,000.00 for labor and materials. They also paid Onyx Waste Services (by check) $416.91 to have a dumpster brought to the Project site. Neither GGC, nor anyone acting on its behalf, did any work on the Project after Mr. Joseph left the site in mid-July 2007. The Project was incomplete when the work ceased.2 GGC provided the Thompsons no explanation for the stoppage. In fact, the Thompsons did not hear from GGC at all. The Thompsons were anxious for the Project to be completed, and they did nothing to prevent GGC from accomplishing this objective. After more than 90 consecutive days had passed without any work having been done on the Project, the Thompsons hired another contractor to finish the Project. The Project was ultimately completed. The Thompsons paid $17,540.00 for the additional work that was necessary to complete the Project. The total amount that the Thompsons paid for the Project was $52,329.91 ($32,373 to GGC; $2,000 to Mr. Joseph; $416.91 to Onyx Waste Services; and $17,540.00 to finish the work GGC had failed to do). This was $15,194.91 more than the contract price. Petitioner has incurred a total of $182.90 in investigative and prosecutorial costs in connection with the instant case (excluding costs associated with any attorney's time).
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board issue a Final Order: (1) finding Respondent guilty of violating Section 489.129(1)(j) and (m), as alleged in Counts II and IV, respectively, of the Administrative Complaint; (2) suspending his license for a period of two years; (3) fining him $7,500.00; (4) requiring him to pay restitution in the amount of $15,194.91 to the Thompsons; (4) ordering him to reimburse the Department $182.90 for investigative and prosecutorial costs; and (5) dismissing Counts I and III of the Administrative Complaint. DONE AND ENTERED this 27th day of August, 2008, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of August, 2008.
The Issue Did respondent fail to properly supervise, direct and manage the contracting activities of the business of which he is the qualifier, and if so, what disciplinary action should be taken against respondent's contracting license?
Findings Of Fact At all times material to this proceeding the respondent was a certified building contractor licensed by the State of Florida and the qualifying agent for Custom Concrete of Naples, Inc. (Custom Concrete). Rodney Velez was the president of Custom Concrete and licensed only in concrete--concrete forming, placing and finishing. Susan Velez, Rodney Velez's wife, was an officer of Custom Concrete. On April 23, 1983, Custom Concrete, by and through Rodney Velez, entered into a contract with Mark and Penny Paterson to construct a home for $38,550.00. Mrs. Paterson had previously met Rodney Velez in the course of her work, and Velez had told her that he was a builder. Mrs. Paterson had suggested that Velez look at a floor plan that she and her husband had, and after certain negotiations, including a change of floor plan, the contract was entered into. During the course of the negotiations Mrs. Paterson never talked to the respondent and was unaware that the respondent was involved or would be involved in the construction of the home. Mrs. Paterson believed that Rodney Velez was the "builder"; however, the construction of the Paterson home was beyond the scope of Velez's concrete license. The respondent signed the application to secure the building permit for the Paterson residence, although he did not personally appear to procure the building permit. The clerk of the contractor's licensing section of the building code compliance department relied on the signature on the application because it was notarized. The notary was Susan Velez. Respondent did not supervise or direct the construction of the Paterson home. Neal Jackson, president of the company who did the electric work on the home, was unaware that respondent was involved in the project until well after the house was finished. Although it is usual for a supervisor or superintendent to be at the job site some of the time, Jackson never saw the respondent or Velez at the job site. Jeff Allain, the carpenter who did the framing and certain other work, was on the job site five or six days and saw the respondent once during the framing of the structure "just generally looking around." The respondent didn't say anything to Allain. David Isom did drywall work on the house. He had no contact with the respondent and did not see him at the construction site. Mrs. Paterson went by the construction site quite often and realized that the job was not being properly supervised. Velez was rarely there, and Mrs. Paterson never saw the respondent. The workmen on the site would ask the Patersons when Velez would be there because they had questions concerning the work. Neither of the building inspectors saw anyone supervising at the job site, although usually no one is at the job site when an inspection is made. Two days after the Patersons moved into their house, they compiled a "punch list" of the items that needed to be completed or corrected. The list was given to Velez, but the work was not corrected to the Paterson's satisfaction. Although Velez did not give the "punch list" to respondent, Velez discussed the problems with the respondent. Respondent did not take any steps to remedy the problems and said he thought "a lot of it was nonsense." Velez told respondent that he, Velez, would take care of it. Because of the unresolved problems with the house, Mrs. Paterson finally called the licensing board to file a complaint against Rodney Velez. At that time, she was informed that Rodney Velez was not the contractor; the contractor was the respondent. This was the first time that Mrs. Paterson was aware that the respondent was involved with the construction of the house. All of the Patersons dealings had been with Velez, and all checks for construction payments were made out to Velez personally. 2/ Even though the Patersons had not received satisfaction from Custom Concrete for the problems with the house, they signed the closing papers because Velez threatened to evict them. At closing the Patersons received a lien release from Custom Concrete which released all work prior to March 9, 1984. Subsequently, Velez filed a claim of lien against the Paterson property for work completed on February 9, 1984.
Recommendation Based upon the foregoing findings of fact and conclusions of law it is recommended that respondent be found guilty of violating Section 489.129(j), Florida Statutes, that he be fined $1,000.00, and that his license be suspended for 60 days from the date the Construction Industry Licensing Board enters its final order in this case. DONE and ORDERED this 30th day of January, 1985, in Tallahassee, Florida. DIANE A. GRUBBS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January, 1985.
The Issue Whether the Respondent, Miguel Diaz-Perna, committed the violations alleged in the administrative complaints and, if so, what penalty should be imposed.
Findings Of Fact The Department is the state agency charged with the responsibility of regulating construction industry licensees. At all times material to the allegations of these complaints, the Respondent was licensed as a certified general contractor, license number CGC026702. Respondent's license is held in his individual name. The company known as M.D.P. General Contractor, Inc., is not registered by the Construction Industry Licensing Board as a contractor. M.D.P. General Contractor, Inc., has not been qualified to practice contracting in the State of Florida. On November 18, 1992, an individual named Gum Lee contracted with Respondent who was doing business under the entity name M.D.P. General Contractor, Inc., for the roof of his hurricane-damaged home. While the contract identified Respondent as the president of the corporate entity and represented it to be a certified state general contractor, the contract did not bear Respondent's individual license number. Respondent's price for re-roofing the Gum Lee residence was $13,000. Gum Lee paid Respondent the full $13,000. Respondent began work at the Gum Lee resident in November 1992. Subsequently, in April 1993 Respondent, again doing business as M.D.P. Contractor, Inc., entered into a second agreement with Gum Lee to make an addition to the residence. This second contract also did not bear Respondent's license number. The contract price for this addition was to be $20,000. Subsequently, Respondent obtained a permit from the Metro-Dade Building Department for work at the Gum Lee residence. In July, 1993, Respondent executed an affidavit that all materialmen and subcontractors had been paid for labor and materials supplied to the Gum Lee projects. In fact, Respondent had failed to pay at least one company, Coma Cast Corporation, in the amount of $3,808.44. Coma Cast Corporation placed a valid lien on the Gum Lee property. Neither Respondent nor M.D.P. Contractor, Inc., satisfied the lien within 75 days. Moreover, as of the date of hearing, Respondent had not satisfied the lien. Despite having paid Respondent for the work and materials at his home, in order to satisfy the lien, Gum Lee was required to remit an additional $6,026.01 to Coma Cast. In November, 1992, Li Kam Ming and Wan Chang Lu contracted with Respondent, doing business as M.D.P. Contractor, Inc., for the roof of their home. This contract, like the proposal form used by Respondent in all instances in this cause, did not contain Respondent's license number. The contract price for the work for this project was $11,600 for which Respondent was paid in full. Respondent pulled a Metro-Dade Building Department permit for the Ming/Lu project on or about December 18, 1992. Respondent's individual license as a general contractor does not entitle him to perform roofing contracting in Florida. Respondent represented himself to Ming and Lu as a licensed roofing contractor. In November 1993, Coma Cast Corporation placed a valid lien against the Ming/Lu home in the amount of $2,872.86. This amount was due for materials furnished to this project and which were unpaid by Respondent or M.D.P. Contractor, Inc. Despite notice of the lien, Respondent failed to satisfy it within 75 days. On August 30, 1994, the property owners satisfied the lien by remitting $4,900. Following mediation in circuit court, Respondent was ordered to pay Ming and Lu the sum of $5,400 to resolve this matter, but he has failed or otherwise refused to do so. In February, 1993, Respondent contracted with Ethel Odwin for repairs at her hurricane-damaged home in Miami. As in the other cases, Respondent entered into this agreement as M.D.P. Contractor, Inc. No license number was included in the proposal form. A second project (and agreement for same) at the Odwin home was entered into by Respondent on October 11, 1993. This project required repairs to the swimming pool at the residence. The total contract price for both projects at the Odwin home was $46,664, of which Mrs. Odwin paid Respondent $44,917.40. Respondent pulled a Metro-Dade Building Department permit for work at the Odwin home, but did not obtain a permit for the swimming pool repair. At no time material to the allegations of this case has Respondent been licensed or certified to perform swimming pool contracting in the State of Florida. Respondent did not subcontract the swimming pool work to be performed at the Odwin residence. Respondent did not complete all work at the Odwin home and, in fact, as a percentage of the work completed, received more funds than he was entitled to under the parties' agreement. Mrs. Odwin was required to expend an additional $8,000 in order to complete the work at the home after Respondent abandoned the projects in February 1994. Respondent's excuse that his gravely ill son distracted him during the time frames of these cases cannot explain why he has failed to attend to the financial responsibilities of his business subsequent to his son's death.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order revoking Respondent's license, imposing an administrative fine in the amount of $15,000, and requiring financial restitution to the extent that same does not contravene federal bankruptcy law. DONE AND ORDERED this 10th day of September, 1997, in Tallahassee, Leon County, Florida. J. D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of September, 1997. COPIES FURNISHED: Rodney Hurst, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 John O. Williams, Esquire Boyd, Lindsey, Williams & Branch, P.A. 1407 Piedmont Drive, East Tallahassee, Florida 32317 Miguel Diaz-Perna 14631 Southwest 148th Street Circle Miami, Florida 33189