Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES A. RILEY, 88-000738 (1988)
Division of Administrative Hearings, Florida Number: 88-000738 Latest Update: Jun. 30, 1988

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times pertinent to this proceeding, the respondent James A. Riley was a certified building contractor in Florida, having been issued license number CB-C029035. On or about April 23, 1985, Marion Smith entered into a contract with William Ross to remodel two duplexes in Lakeland. At that time, Mr. Ross held himself out to Ms. Smith as a licensed contractor. Ms. Smith agreed to pay Mr. Ross $9,975.00 for the remodeling work, which included reroofing, painting inside and out, porch screening, redoing inside walls and bathrooms, and certain kitchen work. By Application for Permit dated April 23, 1985, and received by the City of Lakeland Building Inspection Division on April 24, 1985, James Riley requested a building permit to do certain work at the residence of Marion Smith. The description of the work to be done was "reroof - replace doors - panel - drywall - window - repair floor, etc., kitchen - bath, bedrooms, paint house." The permit application also stated that the work was to be done by "Riley Const." and that the name of the architect, designer or applicant was James Riley. Marion Smith never met or spoke with James Riley until August of 1985. William Ross commenced work on the duplexes within a week of the time that the April 23, 1985, contract was signed. He last worked on the project in June of 1985, after Marion Smith had paid him in full. At the time Mr. Ross left the project in June, the entire insides of the duplexes were incomplete. Mr. Ross was never licensed as a contractor in Florida, nor was he registered as a contractor in the City of Lakeland. Marion Smith learned from City of Lakeland officials that it was James Riley who had pulled the permit for work on her duplexes. On or about August 24, 1985, she and respondent Riley entered into an agreement whereby respondent agreed to complete the work and furnish all labor and materials. The agreement states that "We value this work at $3,200.00 to be paid by William Ross..." The agreement further provides that work will be started on August 27, 1985, and completed on or before October 7, 1985. Respondent Riley began work, plastered the ceilings and started to paint the walls. He last worked on the duplexes in October of 1985, leaving incomplete the bathroom work, the kitchen cabinet work, electrical fixture work and the remainder of the wall painting. Thereafter, Marion Smith had to employ others to complete the work originally contracted for by Mr. Ross and which respondent Riley subsequently agreed to complete. She paid approximately $3,500.00 to have the unfinished work completed. One of the duplexes was completed in December of 1985, and the other was completed sometime in 1986. Respondent Riley testified that he did not complete the work on the Smith duplexes because Ms. Smith took the keys away from him when she became dissatisfied that he was not finishing the job fast enough. He admits that he was only working part time on that project. Marion Smith's mother testified that respondent Riley told her he could not finish the work because Marion Smith never gave him any money. Two disciplinary actions have been brought against respondent Riley's registration as a contractor by the City of Lakeland. His registration with the City has been suspended twice for thirty days each time.

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that respondent James A. Riley be found guilty of violating Section 489.129(1)(e),(i),(j),(k) and (m), Florida Statutes, that his certification as a building contractor be suspended for a period of eighteen (18) months, and that an administrative fine of $1,500.00 be imposed. It is further RECOMMENDED that, should respondent provide written proof to the Board, within six (6) months of the date of the Final Order in this cause, that he has relieved Marion Smith of the additional monetary damages incurred to complete the construction work on the duplexes, the period of suspension be shortened to a period of six (6) months from the date such written proof is provided. Respectfully submitted and entered this 30th day of June, 1988, in Tallahassee, Florida. COPIES FURNISHED: Fred Seely, Executive Director DPR, Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Jack M. Larkin, Esquire 806 Jackson Street Tampa, Florida 33602 James A. Riley 1934 Lake Parker Drive West Lakeland, Florida 33805 DIANE D. TREMOR Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of June, 1988.

Florida Laws (2) 17.002489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MELVIN A. GROSZ, 82-003237 (1982)
Division of Administrative Hearings, Florida Number: 82-003237 Latest Update: Dec. 08, 1983

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, as well as the factual stipulations of the parties, the following relevant facts are found: Respondent Melvin A. Grosz is a registered residential contractor, having been issued license number RR 006311. He has been licensed since the 1960s. COUNT I In November of 1950, respondent entered into a contract with W. J. Murphy to install windows and do other renovation work on Mr. Murphy's residence located at 3312 N. San Miguel, Tampa, Florida. Respondent received from the Murphys an advancement in the amount of $1,250 for the work to be performed. While respondent did do some cleaning work, he failed to do any further work or supply any labor in performance of the contract. In February of 1951, respondent executed a "Stipulation of Settlement and Promissory Note" with the Murphys, agreeing that he failed to perform any work or supply any labor, acknowledging that he owed the Murphys $1,250 and agreeing to pay the Murphys $250 per month for five consecutive months beginning on March 10, 1951. As of the date of the hearing in this matter, respondent had made no payments to the Murphys. COUNT II On or about October 9, 1980, respondent entered into a contract with Vera Reid for the sum of $3,245 to do certain remodeling on her residence at 203 North Tampania Street, Tampa, Florida. After having completed about 40 percent of the construction work and after having received $3,100 of the contract amount, respondent abandoned the Reid construction project during December of 1950. COUNT III On or about December 19, 1980, respondent entered into a contract with James F. and Mary L. Stewart to construct a residence in Lutz, Florida, on a sliding total price basis not to exceed $25,000. Respondent was to be the general building contractor and as to coordinate and supervise all subcontractors and perform other duties. Pursuant to his contract with the Stewarts, respondent did obtain the first subcontractor and did some preliminary work. Respondent received $1,300 from the Stewarts, but performed only minimal work, valued at approximately $300, prior to abandoning the Stewart project. Respondent's promises to repay the Stewarts were never fulfilled. COUNT IV In June of 1981, a direct information was filed against the respondent charging that, on March 21, 1981, he unlawfully obtained or used windows belonging to another, the value of said windows being in excess of $100. On March 2, 1952, respondent entered a plea of nolo contendere to a charge of grand theft in the second degree. The Circuit Court of Hillsborough County entered an Order on March 2, 1952, withholding adjudication of guilt, and placing respondent on probation for a period of two years. As a condition of probation, respondent was to make restitution in the amount of $423.92, with probation to terminate automatically upon the payment of such restitution. The respondent did subsequently make the required restitution payment. COUNT V On or about September 1, 1951, the City of Tampa revoked respondent's Certificate of Competency due to his violation of Tampa Code, Chapter 45, Article III, Division 4, Section 45-75(c). This action was based upon his abandonment of the Reid project discussed in Findings of Fact (4) and (5) of this Recommended Order. MITIGATION Respondent admits the factual allegations and charges set forth above. He states that during the times involved in these charges, he was experiencing numerous family and financial problems, was taking antidepressant medication and was unable to function properly, and his daughter was involved in a serious accident. He no longer takes medication and feels that he is now capable of working. Respondent desires to pay the Murphys, Stewarts and Ms. Reid the monies he owes them and feels that he would be able to do so within 90 to 120 days if given the opportunity to work as a registered residential contractor.

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that respondent be found guilty of violating Section 459.129(1)(b),(h),(i) and Florida Statutes (1979), that an administrative fine in the amount of $500 be imposed against him and that respondent be placed on probation for a period of six (6) months. If, at the end of six (6) months respondent has not made restitution to the Murphys, the Stewarts and Ms. Reid, respondent's certificate of registration as a contractor should be revoked. Respectfully submitted and entered this 12th day of May, 1983, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of May, 1983. COPIES FURNISHED: John O. Williams, Esquire Mr. James Linnan 547 North Monroe Street (Suite 204) Executive Director Tallahassee, Florida 32301 Construction Industry Licensing Board Melvin A. Grosz Post Office Box 2 2511 Marlin Avenue Jacksonville, Florida 32202 Tampa, Florida 33611 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (1) 489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KENNETH H. CAIATA, 84-003443 (1984)
Division of Administrative Hearings, Florida Number: 84-003443 Latest Update: Dec. 04, 1990

The Issue Did respondent fail to properly supervise, direct and manage the contracting activities of the business of which he is the qualifier, and if so, what disciplinary action should be taken against respondent's contracting license?

Findings Of Fact At all times material to this proceeding the respondent was a certified building contractor licensed by the State of Florida and the qualifying agent for Custom Concrete of Naples, Inc. (Custom Concrete). Rodney Velez was the president of Custom Concrete and licensed only in concrete--concrete forming, placing and finishing. Susan Velez, Rodney Velez's wife, was an officer of Custom Concrete. On April 23, 1983, Custom Concrete, by and through Rodney Velez, entered into a contract with Mark and Penny Paterson to construct a home for $38,550.00. Mrs. Paterson had previously met Rodney Velez in the course of her work, and Velez had told her that he was a builder. Mrs. Paterson had suggested that Velez look at a floor plan that she and her husband had, and after certain negotiations, including a change of floor plan, the contract was entered into. During the course of the negotiations Mrs. Paterson never talked to the respondent and was unaware that the respondent was involved or would be involved in the construction of the home. Mrs. Paterson believed that Rodney Velez was the "builder"; however, the construction of the Paterson home was beyond the scope of Velez's concrete license. The respondent signed the application to secure the building permit for the Paterson residence, although he did not personally appear to procure the building permit. The clerk of the contractor's licensing section of the building code compliance department relied on the signature on the application because it was notarized. The notary was Susan Velez. Respondent did not supervise or direct the construction of the Paterson home. Neal Jackson, president of the company who did the electric work on the home, was unaware that respondent was involved in the project until well after the house was finished. Although it is usual for a supervisor or superintendent to be at the job site some of the time, Jackson never saw the respondent or Velez at the job site. Jeff Allain, the carpenter who did the framing and certain other work, was on the job site five or six days and saw the respondent once during the framing of the structure "just generally looking around." The respondent didn't say anything to Allain. David Isom did drywall work on the house. He had no contact with the respondent and did not see him at the construction site. Mrs. Paterson went by the construction site quite often and realized that the job was not being properly supervised. Velez was rarely there, and Mrs. Paterson never saw the respondent. The workmen on the site would ask the Patersons when Velez would be there because they had questions concerning the work. Neither of the building inspectors saw anyone supervising at the job site, although usually no one is at the job site when an inspection is made. Two days after the Patersons moved into their house, they compiled a "punch list" of the items that needed to be completed or corrected. The list was given to Velez, but the work was not corrected to the Paterson's satisfaction. Although Velez did not give the "punch list" to respondent, Velez discussed the problems with the respondent. Respondent did not take any steps to remedy the problems and said he thought "a lot of it was nonsense." Velez told respondent that he, Velez, would take care of it. Because of the unresolved problems with the house, Mrs. Paterson finally called the licensing board to file a complaint against Rodney Velez. At that time, she was informed that Rodney Velez was not the contractor; the contractor was the respondent. This was the first time that Mrs. Paterson was aware that the respondent was involved with the construction of the house. All of the Patersons dealings had been with Velez, and all checks for construction payments were made out to Velez personally. 2/ Even though the Patersons had not received satisfaction from Custom Concrete for the problems with the house, they signed the closing papers because Velez threatened to evict them. At closing the Patersons received a lien release from Custom Concrete which released all work prior to March 9, 1984. Subsequently, Velez filed a claim of lien against the Paterson property for work completed on February 9, 1984.

Recommendation Based upon the foregoing findings of fact and conclusions of law it is recommended that respondent be found guilty of violating Section 489.129(j), Florida Statutes, that he be fined $1,000.00, and that his license be suspended for 60 days from the date the Construction Industry Licensing Board enters its final order in this case. DONE and ORDERED this 30th day of January, 1985, in Tallahassee, Florida. DIANE A. GRUBBS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January, 1985.

Florida Laws (4) 120.57489.105489.119489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. E. J. LAMBERTH, III, 76-001241 (1976)
Division of Administrative Hearings, Florida Number: 76-001241 Latest Update: Jun. 03, 1977

Findings Of Fact E. J. Lamberth, III, is a certified general contractor having been licensed by the Florida Construction Industry Licensing Board. Mr. Lamberth's license was not renewed by the Florida Construction Industry Licensing Board when it expired in June, 1975. However, the Board does not question Mr. Lamberth's right to issuance of such a license pending the outcome of this hearing, and the failure of the Board to reissue Mr. Lamberth's license is an apparent administrative oversight. Mr. Lamberth applied and obtained building permits as a Construction Industry Licensing Board Certified General Contractor for construction of modifications or additions to the homes of Mr. and Mrs. Cohen, Mr. and Mrs. Retter, and Mr. and Mrs. DeChant. Copies of the applications for building permits were introduced in the evidence. Exhibit I is the application for the Retter's permit; Exhibit V is the application for the permit for the Cohen's permit; and Exhibit VII is the application for the DeChant's building permit. Lamberth notified the Board by letter received by the Board on or about December 24, 1974 of his resignation as qualifier for Addition Builders, Inc. Lamberth's employment with Addition Builders, Inc. began when he answered a newspaper advertisement for a certified general contractor placed by Richard Butler. Butler was looking for a certified general contractor to supervise construction and to obtain building permits for a construction business which he was at that time incorporating. Lamberth checked with the local Better Business Bureau and having determined that there were no complaints against Butler, entered into an employment agreement with Butler. Subsequently, Butler did incorporate and E. J. Lamberth be came Vice-president for Addition Builders, Inc., a Florida corporation. Lamberth's duties were to inspect plans for any modification or additions which Addition Builders, Inc. contracted to construct, to supervise construction, and to be the qualifying agent for Addition Builders, Inc. In August 1974, Richard Butler entered into a contract in behalf of Addition Builders, Inc. with Michael and Carol Retter for the construction of two-bedroom/one-bath addition to their house located at 460 N. W. Opa Locka Boulevard, North Miami, Florida. Construction of this addition was to take approximately three to six months. Construction began in September of 1974. The construction at the Retter's residence was supervised by the building superintendent or chief carpenter, Mr. Braddock. Construction on the addition was intermittent during September and slowed to a halt in October 1974. The Retters called Addition Builders, Inc. in November and were advised by Mr. Braddock that Mr. Butler had withdrawn from the business but that Braddock would continue with the construction and complete the addition. Construction on the Retter's addition was approximately 50 percent complete, the floor, roof and walls having been built but the windows, doors and plumbing fixtures not having been set. Braddock came and did some work and advised the Retters that he had taken over the business from Butler. Mrs. Retter testified that she was working full-time during this period but that on days when she and her husband were home the construction personnel came at 9:00 a.m. and left in mid-afternoon. The personnel who came, with the exception of Braddock, were subcontractors employed by Addition Builders, Inc. During this period, she did not see Mr. Lamberth who she saw for the first time the day of the formal hearing. The Retters first learned of Lamberth's association with Addition Builders, Inc. from the officials of the city of North Miami, who gave the Retters Lamberth's name as the party who had drawn the construction permit. In January the Retters contacted Mr. Lamberth who advised them that he had withdrawn from the company and could not help them. The contract price for the contract between the Retters and Addition Builders, Inc. was for $8,900 of which the Retters had paid $8,000 at the time construction of the addition ceased. It cost the Retters approximately $2,000 to finish the construction of the addition after Addition Builders, Inc. ceased to perform any work on the job. E. J. Lamberth, III, has been a full-time employee of the Dade County Recreation Department since January 9, 1963. He was employed by Richard Butler as a qualifying agent for Addition Builders, Inc. and was made Vice-president of that corporation. Addition Builders, Inc. began operation in late July or August of 1974. Lamberth performed the duties for which he was employed. He drew the construction permits required, inspected plans for modifications and additions to be built by Addition Builders, Inc., and visited the various construction sites of the corporation at noon and in the late afternoon to determine the progress being made by the subcontractors employed by Addition Builders, Inc. Through his contact with Mr. Braddock and the subcontractors employed by Addition Builders, Inc., Lamberth arranged for the scheduling of the subcontractors on the various jobs. At this time, Addition Builders, Inc. had between six and eight projects under construction. Lamberth was able to determine the progress being made on the various sites through his periodic inspections two to three times per week. These inspections and his conversations with the subcontractors revealed in early October that Butler was countermanding Lamberth's directions and canceling Lamberth's instructions given to subcontractors. Because of these activities, Lamberth advised Butler that he, Lamberth, would have to be in charge of the projects underway and schedule work on the projects or he would have to withdraw as qualifying agent for Addition Builders, Inc. Because of Butler's continued interference, Lamberth eventually resigned from his position with Addition Builders, Inc. in December 1974. Lamberth was not a stockholder in Addition Builders, Inc. When the work began on the various additions, Lamberth received 3 percent of the contract price as his compensation for his services to Addition Builders, Inc. Subsequent to being advised of the problems with Addition Builders, Inc., Lamberth attempted to locate Richard Butler. Richard Butler could not be located and has apparently left the State of Florida.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer recommends that the Florida Construction Industry Licensing Board take no action against the certificate of L. E. Lamberth, III. DONE and ORDERED this 12th day of October, 1976 in Tallahassee, Florida. COPIES FURNISHED: Barry Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida James W. Bowling, Esquire Vernis and Bowling Sailboat Bay - PH II 2951 South Bayshore Drive Coconut Grove, Florida 33133 STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO. 76-1241 E. J. LAMBERTH, III, CG C006734, P. O. Box 570444, Miami, Florida 33157. Respondent. /

# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer