Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
SUPERIOR PAVING, INC. vs. DEPARTMENT OF TRANSPORTATION, 86-000314BID (1986)
Division of Administrative Hearings, Florida Number: 86-000314BID Latest Update: Apr. 09, 1986

Findings Of Fact On or about December 16, 1985, Petitioners submitted an application requesting qualifications in five major classes of work and two incidental classes of work. At the hearing, qualification in cement paving was not pursued. The Department denied the applications for qualification to bid on contracts for Minor Bridges, Portland Cement Concrete, Hot Plant-mixed Bituminous Base and Surface courses, and the two incidental classes of fencing and grassing, seeding and sodding. Petitioner here contests the Minor Bridge, Hot Plant-mixed Bituminous Base and Surface courses and the two miscellaneous categories. Superior Paving has been in the road building business for many years and the sole basis for denying qualification for Hot Plant-mixed Bituminous Base and Surface courses is that Superior does not own an asphalt plant. During the years Petitioner has worked in road construction for DOT its work has been satisfactory, contracts have been completed on time, and there has been no default. Petitioner has the financial ability to perform the work for which qualification is requested and has experienced personnel necessary for this work. With respect to construction work on minor bridges, Petitioner's general manager and superintendent both have extensive experience in this work area. During the past two years, Petitioner has done no work on DOT projects as the result of a two year suspension for a contract crime. Prior thereto on DOT construction involving minor bridge work in which Superior was the prime contractor, this work was subcontracted out to a contractor specializing in bridge construction. However, Superior has the resources to obtain all equipment needed for minor bridge work. Also Petitioner has been the successful bidder on jobs involving fencing as well as grassing, seeding and sodding. Petitioner has used this type work to meet its quota for subcontracting at least ten percent of the job to minority and female subcontractors. On one occasion when the sodding subcontractor failed to complete the project, Petitioner used its own personnel and equipment to do so. Petitioner's request for qualification for these incidental classes was denied because its application failed to show that the company accomplished fencing, grassing, seeding and sodding with its own forces and equipment. (Exhibit 14.) Most of the evidence submitted in these proceedings involved the denial of qualification for the type work that has been Petitioner's primary category for many years, viz. asphalt paving. The sole reason for denying Petitioner qualification in this class of work is that Petitioner does not have its own asphalt plant (Exhibit 14.) This requirement imposed by Respondent is a recent one which was placed into effect in 1985 following the amendment to Rule 14- 22.03 F.A.C. That amendment added "and the adequacy of equipment to perform the specific classes of work." At the time this change to the rule was made DOT was applying the policy of requiring a contractor to own an asphalt plant in order to qualify for this work class. When asked why this unwritten policy was not included in the rule when amended in 1985, the witnesses involved in incorporating the change involving equipment into the rule replied he could not answer that. The policy of DOT that in order to qualify for asphalt paving the bidder must own an asphalt plant has general applicability and has been applied during the past year to all contractors bidding on DOT road projects. DOT personnel who testified in these proceedings stated the purpose of adding the phrase regarding having the necessary equipment to the requirement for qualification, was to bring the rule more in line with the statutory provisions. The adverse publicity DOT received in recent years because of contractor delays in completing projects and deficiencies in some of the work performed resulted in the tightening of the requirements for qualification. Two contractors in particular were late in completing contracts on which they were successful bidders and part of the delay was due to their inability to get the necessary road paving material. However, both of these contractors owned asphalt plants. One had delays in getting a permit from the Department of Environmental Regulation to erect a plant near Destin, Florida, and the other had a falling out with his supplier and could not get the required material. In neither of these cases did the ownership of an asphalt plant alleviate the problem. No evidence was presented showing that a delay in the completion of a project was due solely to the failure of the contractor to have his own asphalt plant. Several asphalt producers submitted letters to the effect that they had supplied paving material to Petitioner for many years and would continue to supply him as much as he would buy. One plant owner testified that he had been in the production and laying of asphalt pavement for many years and much preferred to have the role only of supplier. He also testified that most producers felt the same way. There is no policy or rule requiring contractors who bid on jobs requiring the use of road aggregates to have their own rock quarry in order to qualify for this work class. Petitioner has the necessary equipment to transport mix from the plant to the job site and to install the mix at the job site. Hot Plant-mixed Bituminous Base and Surface courses can be successfully trucked approximately 60 miles from the plant. Accordingly, under DOT's policy, a successful bidder will frequently have to erect an asphalt plant near the job site. This will require him to obtain permits and negotiate the environmental problems associated therewith. The effect of not being qualified for Minor Bridge and Hot Plant-mixed Bituminous classes is that Petitioner is not qualified to bid as a prime contractor when one or more of these classes, in the aggregate, comprises fifty percent or more of the work.

Florida Laws (2) 22.03337.14
# 1
WILLIAM BYRD vs CITY OF TREASURE ISLAND AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 95-004155 (1995)
Division of Administrative Hearings, Florida Filed:Treasure Island, Florida Aug. 24, 1995 Number: 95-004155 Latest Update: Jan. 17, 1996

Findings Of Fact At all times to the issues herein the Department of Environmental Protection was the state agency in Florida responsible for the regulation of water pollution and the issuance of dredge and fill permits in the specified waters of this state. Mr. Byrd has been a resident of the City of Treasure Island, Florida for many years and resides at 123 123rd Avenue in that city. His property is located on Boca Ciega Bay next to a public boat ramp operated by the City. On April 12, 1995, the City of Treasure Island applied to the Department of Environmental Protection for a permit to construct a dock six feet wide by seventy-five feet long, located on the edge of its property on which the public boat ramp is located. This property is located in a basin off Boca Ciega Bay, which is classified as a Class III Outstanding Florida Water. The dock involves the placement of pilings in the water, and the construction of a walkway thereon. In order to be obtain a permit, the applicant must provide the Department with reasonable assurances that the proposed project will not degrade water quality and will be in the public interest. The project is permanent in nature, but the temporary concerns raised by construction have been properly addressed in the permit. In the instant case, the dock is intended to accommodate the boating public which will utilize it to more safely launch, board, debark, and recover small boats at the ramp in issue. The dock will be equipped with a hand rail which will increase the safety of the project. Evidence establishes that without the dock, boaters have to enter the water to launch and recover their boats on a ramp can be slippery and dangerous. The site currently in use as a boat ramp, a part of which will be used for the dock, is almost totally free of any wildlife. No evidence could be seen of any sea grasses or marine life such as oysters, and there was no indication the proposed site is a marine habitat. Manatees do periodically inhabit the area, and warning signs would be required to require construction be stopped when manatee are in the area. The water depth in the immediate area and the width of the waterway is such that navigation would not be adversely impacted by the dock construction, nor is there any indication that water flow would be impeded. No adverse effect to significant historical or archaeological resources would occur and taken together, it is found that the applicant has provided reasonable assurances that the project is within the public interest. Concerning the issue of water quality, the applicant has proposed the use of turbidity curtains during construction which would provide reasonable assurances that water quality would not be degraded by or during construction. The water depths in the area are such that propeller dredging and turbidity associated therewith should not be a problem. No evidence was presented or, apparently is on file, to indicate any documented water quality violations at the site, and it is unlikely that water quality standards will be violated by the construction and operation of the structure. The best evidence available indicates there would be no significant cumulative impacts from this project. Impacts from presently existing similar projects and projects reasonably expected in the future, do not, when combined with the instant project, raise the possibility of adverse cumulative degradation of water quality or other factors of concern. By the same token, it is found that secondary impacts resulting from the construction of the project would be minimal. It is also found that this project is eligible for an exemption from the requirements to obtain a permit because of the Department's implementation on October 3, 1995 of new rules relating to environmental resources. However, the City has agreed to follow through with the permitting process notwithstanding the exemption and to accept the permit including all included conditions. This affords far more protection to the environment than would be provided if the conditions to the permit, now applicable to this project, were avoided under a reliance on the exemption to which the City is entitled under current rules. To be sure, evidence presented by Mr. Byrd clearly establishes the operation of the existing boat ramp creates noise, fumes, diminished water conditions and an atmosphere which is annoying, discomfiting, and unpleasant to him and to some of his neighbors who experience the same conditions. Many of the people using the facility openly use foul language and demonstrate a total lack of respect for others. Many of these people also show no respect for the property of others by parking on private property and contaminating the surrounding area with trash and other discardables. It may well be that the presently existing conditions so described were not contemplated when the ramp was built some twenty years ago. An increase in population using water craft, and the development and proliferation of alternative watercraft, such as the personal watercraft, (Ski-Doo), as well as an apparent decline in personal relations skills have magnified the noise and the problem of fumes and considerably. It is not likely, however, that these conditions, most of which do not relate to water quality standards and the other pertinent considerations involved here, will be increased or affected in any way by the construction of the dock in issue.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of Environmental Protection issue to the city the requested permit to construct the dock in issue at the existing public boat ramp at the east end of 123rd Avenue right of way in the City of Treasure Island. RECOMMENDED this 12th day of December, 1995, in Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of December, 1995. COPIES FURNISHED: Ronald Schnell, Esquire 3535 First Avenue North St. Petersburg, Florida 33713 James W. Denhardt, Esquire 2700 First Avenue North St. Petersburg, Florida 33713 Christine C. Stretesky, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Virginia B. Wetherell Secretary Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Kenneth Plante General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

Florida Laws (3) 120.57373.414403.021 Florida Administrative Code (2) 62-312.02062-312.080
# 2
DEPARTMENT OF HEALTH, BOARD OF DENISTRY vs MOUNIR ALBERT, D.D.S., 10-002907PL (2010)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida May 27, 2010 Number: 10-002907PL Latest Update: Jun. 30, 2024
# 3
BERNARD CAMPBELL AND BESSIE CAMPBELL vs SOUTHERN HY POWER CORPORATION AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 99-000696 (1999)
Division of Administrative Hearings, Florida Filed:Inglis, Florida Feb. 16, 1999 Number: 99-000696 Latest Update: May 17, 2000

The Issue Whether Southern Hy Power Corporation (Hy Power) has provided reasonable assurance, based on plans, test results, or other information, that its proposed hydroelectric facility will comply with the Management and Storage of Surface Water (MSSW) statutes and rules of Southwest Florida Water Management District (SWFWMD) and the Wetland Resource Management permit (WRM)/water quality certification statutes and rules of the Florida Department of Environmental Protection (DEP).

Findings Of Fact By Joint Prehearing Stipulation the parties agreed to the following description of the parties and the project: PARTIES: The Department of Environmental Protection (the Department) is a government agency in the State of Florida existing by virtue of Section 20.255, Florida Statutes, and operating pursuant to Chapters 253, 373, 376, and 403, Florida Statutes, and Title 62, Florida Administrative Code. Under an interagency agreement with SWFWMD, the Department also implements Title 40D, Florida Administrative Code. The Department is located in Tallahassee, Florida, and it has a district office in Tampa, Florida, which district includes Levy County. Southern Hy Power Corporation is a Florida Corporation whose principal offices are located at 7008 Southwest 30th Way in Gainesville, Florida. Betty Berger is an interested party with a mailing address of Post Office Box 83, Inglis, Florida. The Campbells are an interested party with a mailing address of 245 Palm Street, Inglis, Florida. Hy Power applied on August 31, 1993, to the Department for a WRM permit/water quality certification to construct a hydroelectric facility on the Inglis By-Pass Channel. The project is located in Section 12, Township 17 South, Range 16 East, within the town of Inglis in Levy County. The facility consists of a powerhouse located on the south side of the channel measuring about 28 feet wide by 115 feet long, drawing water from the Inglis By-Pass Channel, passing it through a single-pit type turbine and discharging downstream of the Inglis By-Pass Spillway Dam. Hy Power applied on August 4, 1998, to the Department for a MSSW permit for the same proposed hydroelectric facility on the Inglis By-Pass Channel. DESCRIPTION OF PROPOSED PROJECT The project involves the construction of an intake structure, powerhouse, and tailrace on a 0.61-acre area located on the south side of the existing Inglis By-Pass Spillway. The facility will take advantage of the existing hydrostatic head that exists on either side of the Spillway Dam, to generate electricity. The powerhouse will be constructed below grade and will contain a single megawatt turbine and generating unit. The intake structure will divert flows from the upstream side of the Spillway Dam through the powerhouse and back into the By-Pass Channel. A small one-story control building and low profile substation will be constructed above grade within the boundaries of the project area. The hydroelectric project is considered to be a "Run of the River" type of facility because it can only use that water which flows down the existing channel. The geometry of the channel restricts flow to a certain amount, therefore the project cannot create or use flows above those that the By-Pass Channel can provide. The overall authority for control of water levels in Lake Rousseau and flow to the lower Withlacoochee River will remain with the DEP. Lake Rousseau was created in 1909 when the Inglis Dam was constructed across the Withlachoochee River for the purposes of hydroelectric generation. The dam impounds over 11 miles of the Withlachoochee River and forms a lake approximately 3,000 to 4,000 acres in size. Prior to construction of the Barge Canal, water released from the Inglis Dam would flow down the lower portion of the Withlachoochee River about 10 miles before entering into the Gulf of Mexico. In the mid to late 1960's the Army Corps of Engineers (ACOE) built a portion of the Cross Florida Barge Canal between the Gulf of Mexico and Lake Rousseau. The canal severed the Withlachoochee River downstream of the Inglis Dam causing its flow to be diverted into the Barge Canal and then into the Gulf. In order to maintain the flow of freshwater from Lake Rousseau to the lower segment of the River, the 8,900-foot long Inglis By- Pass Channel and Spillway were constructed. The resulting downstream flow ensures navigation in the lower portion of the River and sustains its freshwater and estuarine environment. The water level in Lake Rousseau is generally maintained at an elevation of 27.5 feet above mean sea level (msl) by a combination of the Inglis Dam, the Inglis Lock, which is located in the Barge Canal, and the By-Pass Channel Spillway. These water control features are known collectively as the Inglis Project Works. The water levels in the lower Withlachoochee River immediately to the west of the By-Pass spillway are close to sea level. The resulting head provides the potential energy needed to drive the proposed generator turbine. Under normal conditions the majority of water released from Lake Rousseau flows over the Spillway Dam into the lower segment of the River. According to the DEP Office of Greenways and Trails (OGT), the maximum capacity of the existing By-Pass Channel Spillway is 1,540 cubic feet per second. The hydroelectric project will divert whatever flow is allowed around the existing spillway through the turbine and back into the channel. When the Cross Florida Barge Canal project was cancelled in the 1990's, the ACOE transferred ownership of the property to the State of Florida Board of Trustees, who in turn has leased the property to the DEP for use as the Cross Florida Greenbelt State Recreation and Conservation Area. Management of this property, the control of river flow and lake levels, and operation of the Inglis Project Works are exercised by the DEP's OGT. The OGT utilizes a document entitled "Water Control Plan for Inglis Project Works," dated September 1994, as a guide to operating the structures. The Water Control Plan is incorporated as part of the MSSW intent to issue. On or about April 25, 1995, the Governor and Cabinet, sitting as the Board of Trustees of the Internal Improvement Trust Fund ("Trustees"), approved a request from Hy Power to sublease 0.61 acres of Greenway property at the project site for the purpose of providing electric power. The request was challenged by Berger and the Campbells, and resulted in an administrative hearing held on November 3, 1995. As a result of the hearing, Administrative Law Judge Larry Sartin entered a Recommended Order on July 12, 1996, that the Board enter an order approving execution by the DEP of the proposed sublease and dismissing the petition of Berger and the Campbells. The Recommended Order was approved by the Trustees in its entirety in a Final Order dated April 12, 1996 ("Final Order"). Berger v. Southern Hy Power Corporation et al., Case No. 95-3589. A copy of the Final Order is listed as an exhibit to this Stipulation, and the Findings of Fact and Conclusions of Law contained therein are adopted herein. As previously ruled by the undersigned, the previous Final Order is res judicata as to Petitioners in this case, who are collaterally estopped from challenging any of the findings of fact or conclusions of law contained in the previous Final Order. Petitioners reserve the right to litigate issues of fact and law not addressed in the Findings of Fact or Conclusions of Law contained in that Final Order with regard to the permittability of this project under the WRM and MSSW permitting proposals, and to raise objections as to relevance to this proceedings of any of the Findings of Fact or Conclusions of Law in the Final Order. On February 21, 1995, Hy Power filed application with the Federal Energy Regulatory Commission (FERC) for a conduit exemption from the licensing requirements of Part I of the Federal Powers Act (FPA) for the proposed project. Petitioners and various other persons filed protests with FERC in opposition to the project. On April 21, 1997, FERC issued an Order Granting Conduit Exemption, a copy of which is listed as an exhibit to this Stipulation. Petitioners in this case are collaterally estopped from challenging any of the findings or conclusions contained in that Order Granting Conduit Exemption. Petitioners reserve the right to litigate issues of fact and law not addressed in the Findings of Fact or Conclusions of Law contained in that Order Granting Conduit Exemption with regard to the permittability of this project under the WRM and MSSW permitting proposals, and to raise objections as to relevance to this proceedings of any of the findings or conclusions in the Order Granting Conduit Exemption. FACTS ADDUCED AT HEARING OUTLINE OF PROJECT The proposed project calls for the construction of a water retention structure along the existing By-Pass spillway, the excavation of a large hole in which the powerhouse and turbine would be constructed "in-the-dry" south of the existing dam, and a millrace below the proposed project to return the water back into the existing water course. Conflicting testimony was received regarding the facts surrounding the construction of the project. These included: whether the proposed project will touch the existing wing walls of the existing dam; whether the water retention structure is a coffer dam; whether the proposed water retention structure will safely retain the water; whether the powerhouse and turbine have sufficient negative buoyancy to stay in the ground; whether the proposed excavation will weaken the existing dam; and whether the de-watering of the excavation site will adversely impact ground and surface water. PROJECT DESIGN AND ENGINEERING Engineering for the project was directed by witness Richard A. Volkin, a professional engineer and president and CEO of Engineering Company, Inc., based in Canton, Massachusetts. Mr. Volkin has extensive national and international experience in the design, management, and operation of hydroelectric facilities. Other engineers in Mr. Volkin’s firm worked on the project under Mr. Volkin’s direct supervision, including John May, who became registered as a professional engineer in Florida in order to sign and seal the engineering drawings for the project, which he initially did around 1994. Mr. May became ill and retired in 1998. Because of the length of time the application process has taken and the fact that Mr. May retired, there was a time while the application was pending, when Hy Power's design team was without a registered Florida engineer. When this was brought to the attention of Hy Power, Hy Power substituted Steven Crockett for Mr. May as the Florida-registered professional engineer of record for the project. DEP routinely accepts an applicant’s changing its engineer of record during the course of permit application or construction. Mr. Crockett is a civil and structural engineer who has considerable experience in preparing dam structural designs. Mr. Crockett independently reviewed and evaluated the engineering drawings for the project. Mr. Crockett resealed the drawings by using his drawn seal and signing the plans because his embossed seal was not readily available and time was of the essence. Mr. Crockett has advised DEP that he is now engineer of record for the project, using the appropriate DEP forms. Mr. Volkin’s firm performed all of the studies required by the various agencies, including a geotechnical study of the area, a 50-year analysis of water flow in and out of the Lake Rousseau regime, and water quality evaluations of water in the By-Pass Channel. The ACOE performed deep hole borings of the soils (approximately 36-40 feet below sea level) in the area of the project site to determine soil stabilization conditions at the site when they were constructing the Inglis Project Works. The soil conditions found can reasonably be expected to be similar today. Mr. Volkin’s company also took its own eight-foot deep surface core samples. The purpose of those samples was to verify the ACOE data. The new core samples verified the original core samples. Mr. Volkin also reviewed the ACOE’s engineering drawings developed from construction of the Spillway Dam. These show that the dam is founded on limestone bedding that has been stabilized with concrete. The hydroelectric facility will be constructed adjacent to and south of the dam structure and adjacent to and north of the barge canal. The same type of limestone bedrock is found in the area of the proposed construction. The facility design includes an intake channel on the upstream channel and a tailrace downstream. Those are the only structures that will be constructed next to the By-Pass Channel. The construction of the facility itself will be "in the dry." Hy Power will use coffer dams to seal off the construction site from the By-Pass Channel, so that there will not be water leakage from the Channel into the construction site. Water from the By-Pass Channel will enter the power plant when the coffer dams are lifted and the water is allowed to flow into the facility. The Petitioners presented the testimony of Bill Edwards, an individual with considerable experience in the construction of bridges, cofferdams, and similar concrete structures in aquatic and semi-aquatic conditions. Mr. Edwards is a former hard-hat diver who worked all over the world and worked in Florida for many years prior to his retirement. Based upon his experience and expertise in construction related to projects of this type, his testimony is credible and worthy of consideration. Mr. Edwards pointed out that if the proposed water retention structure did not touch the wing wall of the existing dam, it could not keep the water out and would not have the strength that it needed to retain the water. Hy Power’s witnesses explained that the retention structure would be set close enough to the existing wing wall that waterproofing materials could be placed between the two structures to keep the water out. Further, that the existing plans did not show interior bracing which would be included for structural strength and integrity. In sum, the retention structure will be in contact with existing dam’s wing wall, but will be free standing and not dependent upon the strength of the wing wall for its strength. Mr. Edwards pointed out that a cofferdam by definition has walls on all sides of the structure. The structure proposed by Hy Power did not have walls all the way around the proposed excavation. In rebuttal, Hy Power presented evidence that its plans were conceptual, design drawing and not construction plans. Hy Power represented that in actuality it would put as many walls as were necessary to keep the water out of the hole it intended to excavate. Trash racks will be constructed at the intake structures to protect aquatic life and make sure that trash and vegetation do not enter the intake structure or go down river. The trash rack bars will be two inches on center, which the U.S. Fish and Wildlife Service has determined as the appropriate size for the protection of fish. The turbine blades are "double regulated," and operate generally between 60 and 90 revolutions per minute. The design enables the turbine to operate at a constant speed to generate a consistent flow of electricity, notwithstanding the fact that the flow of the water may vary. The blade speed is not very fast, and the 2.5-meter blades provide a two to three-foot opening. This design acts to prevent fish mortality. There are four ways to shut off the flow of water through the proposed structure: close the pitch of the blades, close the wicket gates, allow the counter balance to the wicket gates to kick in and automatically close the gates, and close off the main gates. This is a fail safe system ("four level redundancy") designed to work upon any failure. Once water goes through the generator, its velocity is reduced to no greater than its intake rate which is a maximum of three feet per second. This prevents the water being discharged from the tailrace from causing erosion. If the head of water in the dam produces a flow exceeding three feet per second, it can be diverted over the other dams which will be functional. The power plant will be encased in concrete, except for a small access way that enables a person to go down a set of stairs to the plant. It will be a sealed, waterproof structure, as required by FERC and the ACOE. This will prevent penetration of groundwater, or flood waters in the event a massive flood overtops the plant. The only water entering the powerhouse will be through the turbine tunnel for power generation purposes. Mr. Edwards pointed out that the powerhouse was a closed structure and as such would have positive buoyancy, that is, it would float. Mr. Edwards pointed out that the proposed site is between the barge canal and By-Pass spillway and there is a great deal of groundwater and potentiometric pressure in the existing water table. In sum, there is a unlimited supply of groundwater at the site, and powerhouse could float out of the ground just like an empty swimming pool. Hy Power presented rebuttal evidence that the weight of the building, the turbine, and the water flowing through the turbine would be close to negative buoyancy, and they would add additional weight to the structure as necessary to keep it in place. The project is designed to generate three megawatts of electric power which is enough electricity to serve between 300 and 3000 homes, depending on usage. The project is designed to be unmanned. This is common for facilities such as this. The plant can be operated by remote control, unlike the existing controls at the By-Pass Dam, which are operated manually. DEP can access, monitor, and control remotely the generator's operation to include shutting the facility down at any time. There will be remote sensors to monitor water elevations. Flood protection will improve because of the ability of DEP to manage water flow from a remote location. If there is any major disruption, the plant will shut itself down. The project is classified as "green power." In other words, it generates natural energy without any disruption to the environment. The project will have minimal to no impact on the environment. There will be no significant changes in water quality compared to existing conditions as a result of either construction or operation of the facility. WRM Permit Criteria Hy Power has provided reasonable assurances that the proposed project will not cause a violation of state water quality standards of Section 403.918(a), Florida Statutes (1991). The parties stipulated that turbidity and dissolved oxygen were the two surface water quality issues of concern in this proceeding. The receiving water body is the Inglis By-Pass Channel. The Inglis By-Pass Channel is a Class III surface water. The project is not located in a OFW. While the lower Withlacoochee River is an OFW, the OFW designation runs up the natural river itself, and does not include the Spillway Dam, tailrace, or the remainder of the By-Pass Channel. There would be no degradation of water quality at the point of contact with the Withlacoochee River OFW. The DEP and FERC looked specifically at potential for turbidity and dissolved oxygen in determining whether the project would violate state water quality standards. The standards for turbidity and dissolved oxygen will not be violated. Because the By-Pass Dam is an under flow structure, a minimum of oxygenation currently occurs as water flows through the existing dam. The proposed project runs the water underground through the generator; however, Hy Power will measure the dissolved oxygen below the dam in the Lower Withlacoochee River. In the event there is any lowering of dissolved oxygen, Hy Power can install a "sparge ring" to reoxygenate the water going through the turbine so that dissolved oxygen remains at current levels. No turbidity will be added to the receiving water as a result of the project, because water velocity is low and the structure is encased in concrete and rip-rap. The only other potential for turbidity would occur when the coffer dams are removed after construction is complete. The coffer dams can be removed with the generator closed to permit any turbidity to settle. The amount of siltation that might occur when the generator is opened would be insignificant. Where a project is not in a OFW, an applicant must provide reasonable assurance that the project will not be contrary to public interest. See Section 403.918(2), Florida Statutes (1991). Hy Power has provided such assurances. The project will not directly affect public health, safety or welfare, or the property of others. See Section 403.918 (2)(a)1., Florida Statutes. There are concerns relating to the structural integrity of the proposed facility and adjacent structures which are discussed extensively below. The project will have no adverse impact upon the conservation of fish and wildlife, including threatened and endangered species and their habitat. See Section 403.918 (2)(a)2., Florida Statutes. While manatees are not likely to be found at the project site, the installation of the trash racks will eliminate any potential adverse impact on manatees. In fact, the racks will be an improvement over the current unprotected Spillway Dam. DEP procedures require a specific manatee control plan be implemented to deal with site specific concerns. The project will not adversely affect navigation or the flow of the water or cause harmful erosion or shoaling. See Section 403.918(2)(a)3., Florida Statutes. The project will not adversely affect fishing or recreation values or marine productivity in the vicinity of the project. See Section 403.918(2)(a)4., Florida Statutes. The permanent project and its construction will cause no significant environmental impacts. See Section 403.918(2)(a)5., Florida Statutes. There will be no adverse impacts to significant historical and archeological resources. Section 403.918(2)(a)6., Florida Statutes. With regard to the impact on current conditions and relative value of functions being performed by the areas affected by the proposed activity, there will be no negative impacts. See Section 403.918(2)(a)7., Florida Statutes. Improvement will result from better control of water flow at the project site, installation of trash racks and implementation of green power. THE FORESEEABLE ADVERSE SECONDARY OR CUMULATIVE IMPACTS Potential adverse secondary impacts related to power transmission are addressed through the fact that there is an existing power line corridor that can be used to transmit the electricity. Any need to change the corridor could be addressed by subsequent DEP permitting. Cumulative impacts are not at issue. Mr. Gammon, with Florida Power, acknowledged that the current electric company, presumably Florida Power, would be required by FERC to transport the electricity generated by Hy Power over its existing corridor and poles. No final decision has been made regarding how to access the site with equipment during construction. Several feasible construction options exist, and there are several ways of accessing the site with heavy equipment vehicles and without impacting wetlands. Any final decision would be subject to DEP approval. Since the project meets the public interest criteria of Section 403.918(2)(a), Florida Statutes, and wetland impacts are minimal, the project is permittable without the need for mitigation. See Section 403.918(2)(b), Florida Statutes. The ACOE has issued a permit for the facility. The permit varies slightly from the DEP intent to issue in the use of reinforced concrete rather than rip-rap on the bottom half of the intake channel. This is to comply with ACOE preference, but the variation has only an environmental benefit. Counsel for Petitioners sought to elicit testimony from Linda Sloan, Executive Director of the Withlacoochee Regional Planning Council, with regard to compliance of the proposed project with the Town of Inglis Comprehensive Plan and Land Development Code. Such compliance is not relevant to this proceeding. At any rate, Ms. Sloan conceded that any prohibition that might apply in the Land Development Code to construction of the proposed facility could potentially be alleviated by exemption or variance provisions in the Code. MSSW PERMIT CRITERIA The project will provide adequate flood protection and drainage in the conventional sense. See Rule 40D-4.301(1)(a), Florida Administrative Code. Because the amount of impervious area is minimal, runoff from the project will not in any way contribute to increased flooding or adversely impact drainage patterns. The total amount of impervious area of the facility is less than that of a single-family residence. SWFWMD rules do not even require MSSW permits for single-family residences because the impact is not significant. The only purpose for requiring a MSSW permit for the project is to review the project’s potential downstream impacts to the watershed, not stormwater runoff from the facility itself. The project will not cause adverse water quality or water quantity impacts on adjacent lands in violation of Chapter 373, Florida Statutes, or cause a discharge that violates state water quality standards. See Rule 40 D-4.301(1)(b), Florida Administrative Code. As indicated by the WRM water quality findings above, the project will not generally violate state surface water quality standards. See Rule 40 D-4.301(1)( c), Florida Administrative Code. The project will not generally cause adverse impact on surface or groundwater levels or flows. See Rule 40 D- 4.301(1)(d), Florida Administrative Code. Since the project is a run-of-the-river, it will not diminish the capability of a lake or other impoundment to fluctuate through the full range established for it under Chapter 40D-8, Florida Administrative Code. The project will not cause adverse environmental impacts, or adverse impacts to wetlands, fish, and wildlife or other natural resources. The project can be effectively operated and maintained. See Rule 40D-4.301(1)(g), Florida Administrative Code. The project is a slow speed, low maintenance facility. The design concept is well established and has been successfully used for many years. Possible adverse affects to public safety are discussed below. The project is consistent with the requirements of other public agencies. See Rule 40D-4.301(1)(i), Florida Administrative Code. Potential harm to water resources within the SWFWMD are discussed below. See Rule 40D-4.301(1)(j), Florida Administrative Code. The proposed project generally will not interfere with the legal rights of others. See Rule 40D-4.301(1)(k), Florida Administrative Code. The proposed project is not against public policy. See Rule 40D-4.301(1)(l), Florida Administrative Code. The project complies with the requirements contained in the Basis of Review. See Rule 40D-4.301(2), Florida Administrative Code. There is a dispute as to whether the project was within or at the edge of the 100-year flood plain. This dispute is related to how one interprets the rule as it relates to the millrace and the location of the facility which is under ground. In the conventional sense, the project is not in the flood plain. Further, the project is designed in such a way, that it is waterproof if it were topped with water. While in the past SWFWMD may have had concerns that the project might cause downstream flooding, SWFWMD currently has no such concerns, given the run-of-the-river status of the proposed project. The operation of the project will not cause downstream flooding. The DEP included in its intent to issue, conditions contained in the sublease between Hy Power and the DEP in order to ensure that the facility would remain run-of-the-river, would comply with the water control plan, and would otherwise comply with the terms of the sublease. The DEP has final control over water flow and can revoke the permit or otherwise take enforcement action against Hy Power if Hy Power fails to comply with the water control plan. GROUNDWATER IMPACTS Operation of the project will not cause groundwater contamination or otherwise have adverse groundwater impacts. Some concerns about groundwater during excavation of the construction site were raised. The conflicting evidence received regarding them is discussed below. An area of concern was the de-watering plan for the project. Everyone agrees there will be some water seepage into the construction site that will have to be pumped out. The parties disagree regarding the amount of water that will have to be removed. Their estimates of amount of water to be removed vary because their estimates of size and over-all depth of the site vary. Petitioners presented credible evidence that a potential exists for the construction site to have a large quantity of water because of its location between two sources of surface water (the By-Pass Channel and Barge Canal), because of the makeup of the subsurface, and because of the depth of the construction. Hy Power credibly represents that if excessive groundwater is found, it can address the adverse impacts through its de-watering plan that would have to be filed with FERC and DEP. The technology exists to address the de-watering of the project. Such plans are routinely considered by DEP after a construction permit is issued and before de-watering occurs. There is very little evidence of sinkhole activity in the project area, and the construction activities are not expected to cause any sinkhole activity. NOISE POLLUTION Mr. Bitter expressed concerns that FERC would require the facility to install a very loud siren that would result in sudden noise adverse to the well-being of neighbors. Mr. Bitter is unfamiliar with FERC siren requirements at run-of the-river hydroelectric facilities. In contrast, Mr. Volkin, who has substantial experience in this area, testified that the only alarm device that would be required would be for the protection of the workers during construction. The purpose of the alarm is to warn persons below a dam spillway of a change in the volume of water being let out of the impoundment. In the case of a run-of-the-river facility, the volume is near constant, changing only gradually. Therefore, even if a warning siren had to be installed its use would be limited to significant changes in flow or testing. This would not constitute a nuisance. Further, the facility is located in the vicinity of the Crystal River Nuclear Power Plant which has its own warning sirens. It would be prudent to make any warning devices required for this structure significantly different from those at the nuclear plant and to limit their use. DAM SAFETY AND FERC REVIEW In reviewing whether Hy Power’s applications complied with the relevant permitting criteria, the DEP took into consideration the review of the facility already performed by FERC. FERC will also be responsible for reviewing the project as it is being constructed. Mr. Edwards also raised concerns about the structural stability of the By-Pass Dam itself. This has been a subject of concern by those responsible for the dam, and a survey of the structure was conducted in 1993, referred to as the Greiner Report. The Greiner Report identified specific maintenance problems that have been and are being addressed by the DEP. However, DEP’s maintenance plan does not address specifically the possibility that the weight of the dam over time has caused some shifting in the dam. Hy Power has only a few core borings and only one at the location of the generator. Hy Power is using the ACOE’s original borings, as confirmed by several new ones, to develop its preliminary plans. The DEP considered FERC and the ACOE as responsible agencies for determining the structural integrity of the dam. DEP has taken FERC’s review of this facility into consideration as part of DEP’s own permitting review. It is normal for DEP to rely on outside sources and agencies for assistance in determining compliance with DEP permitting criteria such as public health and safety, and it is reasonable for DEP to do so in this instance. Most states do not have the full capability to evaluate dam safety, and so they rely on FERC and ACOE. On April 21, 1997, the project received a conduit exemption from FERC. The application process is illustrated in Hy Power Exhibit 11. Hy Power submitted to DEP detailed information about the dam, the associated structures and the proposed project which had been reviewed by FERC and the ACOE, the two agencies in the United States who are responsible for dam structure design, control, and administration. Included in the package was the Greiner Report and Hy Power’s review of it. FERC evaluated the project, the Inglis By-Pass Dam structure, and the proximity of the project to the Dam in relation to structural impact, upstream and downstream impacts, water quality, and environmental issues. Mr. Edwards raised concerns regarding the ability of the limestone bedrock to sustain additional construction in the area of proposed construction. This is a material issue in the controversy which impacts several aspects of the proposed construction. Mr. Edwards pointed out that the barge canal channel was constructed with the use of explosives that caused a fracturing of limestone bedrock. He pointed out that the steel panels, which Hy Power proposes to drive into the bedrock to construct the water retention structure necessary to excavate the hole into which the turbine and powerhouse would be placed, will further fracture this bedrock. This creates two potential dangers. It could permit water to move under and around the bottoms of the panels, potentially scouring the loosened material from the base of the panels and making them unstable and subject to failure. It could weaken the entire southern wing of the existing spillway dam. Mr. Edwards opined that this could result in catastrophic failure of the dam or the coffer dam. Such a failure would cause major destruction and loss of life to those persons living and working in and along the lower Withlacoochee River. Hy Power presented rebuttal evidence that it could and would, if necessary, inject concrete into the limestone to stabilize it and avoid the concerns raised by Mr. Edwards. FERC specifically evaluated concerns raised by project opponents over the poor physical condition of the By-Pass Channel Spillway structures, relying particularly on the 1993 Greiner Report. FERC noted that the DEP had entered into a contract to correct any deficiencies listed in the Greiner Report, which "did not conclude that the deficiencies at the By-Pass Spillway threaten downstream life and property." The FERC review concluded that the dam was safe. To ensure safety, FERC is requiring that Hy Power do a complete stability analysis of the dam prior to any construction. Articles 301 and 302 of the FERC exemption ensure that all final drawings and specifications be submitted to FERC prior to construction, along with a supporting design report consistent with FERC’s Engineering Guidelines; that FERC can require changes to assure a safe and adequate project; and that Hy Power must also submit approved coffer dam construction drawings and specifications at least 30 days prior to starting construction. FERC has its own engineering staff who will go to the site and do their own analysis, along with the ACOE, of the dam and structures, prior to any construction commencing. This is a detailed design review evaluation so that the latest information on the dam will be made known immediately prior to construction, and will prevent any catastrophic event from happening. Under FERC procedures, FERC requires the applicant to obtain the DEP permits prior to requiring applicant to submit more detailed construction designs for FERC's consideration. These more detailed designs in turn will be subject to further review by DEP and FERC. It is assumed that Hy Power will comply with the post- permitting procedures and requirements, and will present complete, detailed construction drawings for FREC and DEP approval. Hy Power’s failure to complete the process would result in denial of a construction permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED: That the DEP enter a Final Order that issues the two permits challenged in this proceedings, WRM Permit No. 38-237096-3.001 and MSSW Permit No. 38-0129249-002, subject to the conditions contained in the Intents to Issue in the respective WRM and MSSW Permits and as described in the Recommended Order. DONE AND ENTERED this 2nd day of March, 2000, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March, 2000. COPIES FURNISHED: Daniel H. Thompson, Esquire Berger Davis & Singerman 215 South Monroe Street, Suite 705 Tallahassee, Florida 32301 Andrew Zodrow, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 John S. Clardy, III, Esquire Crider Law Firm Plantation Point 521 West Fort Island Trail, Suite A Crystal River, Florida 34429 Teri Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Kathy Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Bernard M. Campbell Bessie H. Campbell 245 Palm Street Post Office Box 159 Inglis, Florida 34449 Sarah E. Berger Post Office Box 83 Inglis, Florida 34449

Florida Laws (6) 120.5720.255267.061373.026373.414471.025 Florida Administrative Code (6) 40D -4.30140D-4.09140D-4.30161G15-27.00162-4.08062-4.242
# 4
WILLIAM J. HELWIG AND A. W. ROWE vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 79-001570 (1979)
Division of Administrative Hearings, Florida Number: 79-001570 Latest Update: Dec. 10, 1979

Findings Of Fact Seago Group, Inc., the Applicant/Intervenor, owns a tract of land in Lee County Florida, which is completely surrounded by creeks and canals, including Indian Creek on the north. The Intervenor intends to develop the parcel and is seeking a permit from the Department to construct a bridge over Indian Creek to provide access. There is presently a cul-de-sac at the end of Indian Creek Drive on the north side of the creek. The bridge would extend Indian Creek Drive over the creek onto the applicant's property. The Intervenor held an option to purchase land for the right-of-way on the north side of the creek. The Petitioners own property adjacent to Indian Creek Drive. The Petitioner Helwig owns property upon which be resides, and which adjoins the proposed bridge site. The Petitioner Rowe owns property upon which he resides several lets up Indian Creek Drive from the proposed bridge site. The Intervenor originally made application to construct a road over Indian Creek at a different, but nearby location using a culvert rather than a bridge. The Department's staff appraised the application and recommended that it be denied because deposits of fill around the culverts would have eliminated productive submerged creek bottoms, interfered with the ability of the aquatic habitat to support fish and wildlife populations, and eliminated shoreline vegetation which serves to filter runoff which enters the creek, thus helping to preserve good water quality in the creek. The application was withdrawn by the Intervenor before final action was taken on the Department's staff recommendations. The Intervenor thereafter filed the instant application. The application was to construct: ... A 26 ft. wide by 50 ft. long vehicular bridge constructed with 21" prestressed slabs on pile bent abutments over Indian Creek in Lee County, Florida. The application further provided: All work will be conducted on upland with no need for any equipment or material required to be in the water. All equip- ment and material will be delivered by upland access. The application did not reflect that Intervenor had previously sought a permit for the culvert constructions, but the Department was clearly aware of the previous applications and its appraisal of the bridge application was treated as a supplement to the appraisal of the culvert application. In its Notice of Intent to Issue the Permit, the Department erroneously designated the bridge as a "two-span" bridge. The application is actually for a one-span bridge. In its notice the Department added the following specific conditions: Turbidity screens shall be used during construction. Drainage at bridges approaches shall be by swale and no ditches shall be constructed. Drainage shall meet county specifications. No dredging or filling in Indian Creek. No bridge construction shall take place until ownership or easement is obtained through Mr. David Ruch's property pursuant to letters on file with the Department. The Intervenor has acceded to the specific conditions and agreed to comply with them in the event the permit is ultimately issued. All of the pilings for the proposed bridge would be constructed at or above the mean high water line of Indian Creek. Some turbidity could be expected during construction, however, the use of turbidity screens would eliminate any significant impact upon the water quality, fish and other wildlife resources of Indian Creek during construction. The only potential source of pollution from the bridge after construction would be from runoff entering Indian Creek from the bridge. The amount of runoff that would result from a 50 ft. long by 26 ft. wide bridge is negligible. The limited impact that such runoff could have upon the creek can be eliminated by having drainage flow through a swale system. Since the Intervenor has agreed to utilize a swale system, it does not appear that the bridge would have any adverse impact upon the water quality of Indian Creek or any other water body. Neither does it appear that the bridge would adversely affect fish and wildlife resources. Since all bridge pilings would be constructed at or above the mean high water line, transitional zone vegetation can continue to flourish along the shoreline. The planned clearance between the creek elevation at mean high water and the bridge is seven feet. The bridge would thus impede traffic by any boats that protrude more than seven feet above the water line. This presents no significant navigational impact in Indian Creek. There are two avenues for navigating from the bridge site on Indian Creek to the Caloosahatchee River. One of these avenues is presently obstructed by a bridge with an elevation less than that proposed by the Intervenor. The other avenue is obstructed by a very shallow area that will not permit navigation by other than very small vessels. The Department in the past has denied applications to dredge that shallow area. The Intervenor and the Department have submitted Proposed Findings of Fact. To the extent that these proposed findings have not been included in the foregoing Findings of Fact, they are hereby adopted as fully as if set forth herein.

Florida Laws (1) 120.57
# 5
CITY OF COCONUT CREEK AND MR. AND MRS. W. H. LEE vs. BROWARD COMMUNITY COLLEGE AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-003672 (1983)
Division of Administrative Hearings, Florida Number: 83-003672 Latest Update: Oct. 30, 1984

Findings Of Fact Based on the stipulations of the parties, the exhibits received in evidence, and the testimony of the witnesses at the hearing, I make the following findings of fact: On April 21, 1983, the College filed an application with DER seeking a permit to relocate a drainage ditch that runs through the College property, to fill the existing drainage ditch, and to install a large culvert in the Coconut Creek Waterway which would serve as a road crossing connecting the proposed new College parking lot and N.W. 39th Avenue in Coconut Creek. Upon review of the original application, DER determined that it would not meet the DER's water quality criteria. On September 30, 1983, the College revised its application. It is the revised application which lies at the heart of the present controversy. The revised application no longer contains a proposal to fill in the entire ditch that runs through the College property. Rather, it is new proposed to install two 36-inch culverts in the existing ditch to provide access roads to the proposed new College parking lot. The College also proposed to dredge 832 cubic yards from .5 acres and to install a large structural culvert (measuring 14 feet, 1 inch, by 12 feet, 10 inches) in the Coconut Creek Canal. The existing ditch which runs through the College campus was originally constructed as a drainage ditch. The only water which would flow through that ditch would be provided by run off from the N.W. 11th Street area. At the present time the ditch through the College is plugged in two places. Some time in late July or early August of 1984, contractors employed by the College placed two earthen plugs in the ditch that runs through the College. This was done without benefit of a Department permit and was apparently the result of some confusion on the part of the contractors, the exact nature of which is not explained in the record in this case. The two earthen plugs were not installed in the manner proposed by the subject application, nor were they installed in the locations proposed in the subject application. In their present condition the two earthen plugs effectively prevent the flow of any water through the ditch that runs through the College. The north end of the ditch that runs through the College campus was formerly connected to Coconut Creek Canal. A portion of Coconut Creek Canal runs parallel to N.W. 11th Street. Following the installation of the earthen plugs there was a decrease in the water quality of the portion of Coconut Creek Canal that parallels N.W. 11th Street. The water became cloudier than before and there was some silting. There were fewer base and bluegills and more mudfish. There has also been an occasional unpleasant odor from the area which was not present prior to the installation of the earthen plugs. Also, the residents along N.W. 11th Street complain of an increased mosquito Population since the installation of the earthen plugs. 1/ The proposed 36-inch culverts are substantially larger than is necessary to handle the anticipated flow of water through the College ditch. Calculations made using the methodology approved by the Florida Department of Transportation indicates that 21-inch culverts would have been sufficient to handle any anticipated flow of water through the College ditch. Although the culverts will require some periodic maintenance, they have been designed to minimize the need for maintenance. Properly maintained, the proposed 36-inch culverts will not pose any impediment to the flow of water through the College ditch. There is usually no detectable current or water flow in either Coconut Creek Canal or the College ditch in the area where the College proposes to install the three culverts. Accordingly, inasmuch as there is usually no detectable flow of water, any impediment to water flow which might be caused by the culverts is insignificant. This is particularly true with regard to the issue of weed growth. While it has been contended that the culverts might reduce the rate of water flow to the extent that aquatic weed growth would be promoted because of the stillness of the water, long before this permit was ever applied for and long before the earthen plugs were installed the City of Coconut Creek had serious problems with aquatic weeds growing in all of its canals. As described by one of the City's former mayors, several years ago the hyacinths covered the canals solid from bank to bank and were growing so thick and solid that rabbits could actually run across the canals hopping on the hyacinths. This type of hyacinth growth only occurs in still water. The City has been able to control the hyacinth problem by an ongoing weed control program which consists of spraying chemicals on the plants several times each year. The small amount of water flow which does occur in Coconut Creek Canal is directly related to stormwater runoff, including water generated by the residents along N.W. 11th Street washing their cars and watering their lawns. The portion of Coconut Creek Canal which extends eastward from the College ditch is a dead end system in which the only flushing is due to water runoff from the street. The installation of the proposed large culvert in Coconut Creek Canal would never cause the water to back up in the canal or otherwise impede the flow of water in the canal. A tube 21 inches in diameter would be sufficient to carry away the worst expected rain water conditions and the proposed culvert is, in essence, a tube with an average diameter in excess of 13 feet. The large culvert would cause no change in the volume of water flowing through the canal. It might cause a de minimis headloss, which is a change in the water level from one side of the culvert to the other. Any such headloss would be on a magnitude of approximately 1/1000th of a foot; about 1/3 of a millimeter. The installation of the large culvert in the Coconut Creek Canal would actually increase the velocity of any water flow through the culvert. In conjunction with the installation of the large culvert, the depth of Coconut Creek Canal would be increased to an average of six or six and one-half feet from its present average of approximately five or five and one-half feet. Notwithstanding the decrease in the water quality of the portion of Coconut Creek Canal that parallels N.W 11th Street which apparently resulted from the unauthorized installation of the two earthen plugs, when the water in that portion of the canal was tested by the City's export witness some eight or nine months later, the water quality was within established state standards. And while the construction activity associated with the installation of the two 36-inch culverts in the College ditch effect on the water quality in Coconut Creek Canal, there is no evidence that water quality standards would be violated on either a short or long-term basis. A small amount of habitat would be destroyed, but it is likely that there would be rapid recolonization. No rare or endangered animal species would be affected. The habitat for birds would also recolonize and the birds and fish displaced by construction would return. Any turbidity problems during construction would be controlled by the use of turbidity screens. With regard to navigability, once installed the large culvert would provide a vertical clearance from the surface of the canal of approximately six feet. This clearance would prevent larger boats from passing through the culvert. The vertical clearance of existing canal bridges in the area varies from six and one-half to eight feet. Installation of the larger culvert would not seriously impede navigation. The large culvert would not constitute a navigational hazard nor would it impede the flow of navigable water. As compared to the situation which existed prior to the installation of the two earthen plugs, installation of the two 36-inch culverts would totally stop any boat traffic through the ditch that runs through the College. Nevertheless, curtailment of boat traffic through the College ditch would not seriously impede navigation because any destination which could be reached by traveling through the College ditch could be reached via alternative canal routes which are not affected by this project. As with the larger culvert, the 36-inch culverts would not constitute navigational hazards nor would they impede the flew of navigable water. If the total project envisioned by the College is completed, the culverts will provide a new route for motor vehicle access to an expanded College parking lot. The increased volume of motor vehicle traffic would produce an increased amount of air and noise pollution in the vicinity of N.W. 39th Avenue. A study of the results of the increased motor vehicle traffic based on a "worst case" scenario reveals that even with the additional air and noise pollution generated by the increased motor vehicle traffic, the air and noise pollution levels in the area would be far below the air and noise pollution standards established by the state and federal governments. In the formulation of the foregoing findings of fact I have, of necessity, relied to a large extent on the opinions of expert witnesses who testified in the case. Where there is conflict in the testimony of the expert witnesses, I have generally credited the testimony of the expert witnesses called by the College and the Department because I have found their testimony to be more consistent with other evidence in the case and have found that there is a better factual foundation in the record for their opinions than for the opposing opinions.

Recommendation For the foregoing reasons it is Recommended that the Department issue a Final Order which would GRANT the College's application to install two 36-inch culverts in the College ditch and a 14-foot, 1-inch, by 12-foot, 10-inch, culvert in the Coconut Creek Canal, subject to the conditions set forth in the Department's Notice of Intent to Issue. DONE and ORDERED this 8th day of October, 1984, in Tallahassee, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of October, 1984.

Florida Laws (1) 120.57
# 6
PAUL STILL vs SUWANNEE RIVER WATER MANAGEMENT DISTRICT AND BRADFORD COUNTY, FLORIDA,, 20-000091 (2020)
Division of Administrative Hearings, Florida Filed:Live Oak, Florida Jan. 09, 2020 Number: 20-000091 Latest Update: Jun. 30, 2024

The Issue The issue to be determined is whether Bradford County meets the criteria listed in Florida Administrative Code Rule 62-330.051(4)(e) for a road repair exemption.

Findings Of Fact Based upon the demeanor and credibility of the witnesses, the stipulations of the parties, and the evidentiary record of this proceeding, the following Findings of Fact are made: The Parties Dr. Still resides at 14167 Southwest 101st Avenue, Starke, Florida. That property abuts work that was performed pursuant to the Exemption. The District is a water management district created by section 373.069(1), Florida Statutes. It has the responsibility to conserve, protect, manage, and control the water resources within its geographic boundaries. See § 373.069(2)(a), Fla. Stat. The District, in concert with the Department of Environmental Protection, is authorized to administer and enforce chapter 373, and rules promulgated thereunder in chapter 62-330, regarding activities in surface waters of the state. The District is the permitting authority in this proceeding and issued the Exemption to the County. The County is a political subdivision of the State of Florida. The County is responsible for keeping county roads and structures within its boundary in good repair and for establishing the width and grade of such roads and structures. §§ 334.03(8) and 336.02(1)(a), Fla. Stat. 101st Avenue, a dirt road, was constructed decades ago and runs in a general north/south direction for several miles. It was in existence, publicly used, and under County maintenance long before January 1, 2002. Dr. Still acknowledged that when he purchased his property in 1996, the road was publicly used and was being maintained by the County. The centerline of 101st Avenue has existed in its current position as long as Mr. Welch, the Bradford County surveyor, has been familiar with the property, since at least 1996. The County owns and is allowed to use a 60-foot right-of-way (“ROW”) extending 30 feet to either side of the centerline. The driving surface of 101st Avenue has consistently been from 20 to 22 feet in width, with drainage structures extending further into the ROW. The evidence was convincing that 101st Avenue was regularly maintained or repaired by the County for more than seven years prior to the Exemption. The evidence was equally convincing that, during that period, the width of the road that actually has been maintained or repaired is substantially -- if not identically -- the same as the width of 101st Avenue after the road repairs under the Exemption were completed. 101st Avenue was, prior to the exempt road repair work, “very wet” during rainy periods, and cars and trucks would routinely get stuck in the mud. Mr. Welch testified credibly that 101st Avenue was “a mess” even before the events that led to the work covered by the Exemption. It is reasonable to conclude that the driving surface of 101st Avenue may have shifted by a matter of feet in either direction over the years prior to the exempt road repairs, which would have generally been the result of persons driving off of the driving surface to escape impassable areas, and of the imprecision inherent in grading a dirt road with a large motor grader. The evidence established that the County has maintained 101st Avenue at a location as close to the established centerline as possible, and has not intentionally moved or realigned 101st Avenue from its historic location. Mr. Welch was very familiar with 101st Avenue, having used it numerous times, including during the period leading up to the events that precipitated the road repair work at issue. He testified to two surveys he performed of the area, first in 1996, and again in the vicinity of the Still property in May 2017. He testified that 101st Avenue was under County ownership and maintenance prior to his first survey in 1996. Photographic evidence offered by Dr. Still showed 101st Avenue to be significantly degraded near his property for several years leading up to 2017. Turbidity of the waters passing alongside and under 101st Avenue was “a long ongoing issue with this road,” dating back to at least 2015. 101st Avenue “was in pretty poor shape” in January 2017. Cars would routinely go around wet areas on the driving surface and possibly onto Dr. Still’s property. That gave the appearance of a change in the eastern ROW. Over a period of years prior to the Exemption work, the ROW may have crept eastward as the road was graded, ditches were maintained, and residential traffic diverted around impassable areas. The shift could have been as much as 10 to 15 feet, but the evidence establishing such was neither precise nor compelling. However, even if the ROW shifted over time, the movement was not the result of intentional operation and maintenance by County staff, but was a gradual, unintentional movement over time. Such a gradual shift is common with dirt and limerock roads. Furthermore, the alignment of the travel surface was stable, and was always within the 60-foot ROW, although the stormwater structures may have gone beyond the ROW. In August 2017, a series of storm events caused 101st Avenue to be flooded. Dr. Still testified that the existing road and ditches and most of the areas adjacent to his property were “destroyed” by continued public use after the August 2017 rain event. He believed there was no way to ascertain the alignment of 101st Avenue. Around September 10, 2017, Hurricane Irma impacted the County, causing substantial flooding and damaging numerous dirt and limerock roads in the County, including 101st Avenue. 101st Avenue was partially damaged from flooded conditions, and rendered completely impassable at places along its path, which led motorists to drive off of the established roadway onto adjacent properties to get through. The diversion of traffic off of the road surface was due to the personal decisions of the public using the road, and was not the result of any direction, operation, or maintenance by County staff. 14 After Hurricane Irma, Governor Scott issued emergency orders that allowed local governments to undertake necessary repairs to roadways. The County issued similar emergency orders.1 In November 2017, Mr. Welch performed a survey to establish the alignment of the road. 101st Avenue was partially repaired consistent with the survey and pursuant to the emergency orders, with the work beginning in December 2017. As the work to repair 101st Avenue was proceeding, Dr. Still asserted that the ROW encroached onto his property. He and Mr. Welch walked the property line, noted that the ROW appeared to extend across a fence installed on the west side of 101st Avenue, and staked the disputed area. Though the County believed it was working within its ROW, it decided, more as a matter of convenience to avoid the time and expense of litigation, to purchase the disputed area. Thereafter, on January 5, 2018, the County purchased 1.78 acres of property from Dr. Still, which was incorporated into the County ROW.2 The purchase of the property, and establishment of the undisputed ROW, was completed well before the December 23, 2019, filing of the Petition. The travel surface of the road remained within the prescriptive and historical ROW. The “footprint” of 101st Avenue was the same before and after the road repair work. Dr. Still admitted that the road had not “physically moved.” However, he believes that the County’s use of the 1 Since the Exemption work was largely (and lawfully) performed under the emergency orders, the County’s Exemption application was filed after the repair work had begun on 101st Avenue, and is considered an after-the-fact application. The application for the Exemption was originally filed pursuant to rules 62-330.051(4)(b) and (e). The County thereafter withdrew its request for an exemption pursuant to rule 62-330.051(4)(b), and limited its Exemption to rule 62-330.051(4)(e), which establishes the standards at issue in this proceeding. The District’s December 10, 2019, proposed agency action granted the Exemption for resurfacing the entirety of the length of 101st Avenue. 2 The evidence was not sufficient to establish that the ROW actually encroached onto Dr. Still’s property. It is equally plausible that the fence encroached into the 101st Avenue ROW. Nonetheless, the issue was -- or should have been -- resolved when the County agreed to pay Dr. Still to extinguish any plausible claim to the property in dispute. 1.78 acres of purchased property for the ROW constitutes a realignment of 101st Avenue. From an engineering perspective, as long as a road surface is within an established ROW, and there has been no intentional change in its direction or trajectory, the road is not “realigned.” The evidence established that 101st Avenue remained within its established ROW, and there was no intentional change in its direction or trajectory from the repair work. The work performed under the exemption involved grading 101st Avenue along its entire length, and applying asphalt millings and a sealant to stabilize the travel surface. The asphalt millings placed on the 101st Avenue travel surface were applied on top of the “as-is” existing limerock. The millings provided structure and stability to the travel lanes, and eliminated erosion and the large muddy bogs that were a feature of the road during the rainy season and after storms. There was no persuasive evidence that the millings materially raised the height of the road travel surface. Mr. Rischar testified that 101st Avenue, after the road repair work, is now in good condition and intact. The asphalt millings are not “loose” but are bound together. The work stabilized the roadbed, provided structural integrity, and improved water quality as compared to a simple graded road. His testimony is accepted. Dr. Still produced several photographs depicting a small pile of dirt near a roadside ditch near the drainage culvert under 101st Avenue. The pile pre-dated the Exemption work. Ms. Diaz testified that the mounds had been “taken care of,” and they do not appear in any post-Exemption photographs. There was no evidence of any excavated material having been deposited at or near the Still property from the exempt road repair work. As part of the Exemption work, drainage structures were incorporated to receive and convey stormwater from the road surface. Rule 62- 330.051(4)(e)5. requires that work performed under a road repair exemption incorporate “[r]oadside swales or other effective means of stormwater treatment.” The evidence was not sufficient to demonstrate that the stormwater structures incorporated along 101st Avenue met the stringent criteria for “swales” as set forth in the Applicant’s Handbook, Volume II, §§ 5.5.1 and 5.5.2. However, the testimony was convincing that the drainage work incorporated into the road repairs was an “other effective means of stormwater treatment.” Dr. Still’s testimony as a “citizen scientist” was not sufficient to overcome the expert testimony offered by the County and the District. During the initial phases of the work, when the County was acting under the post-Irma emergency orders, the County had not installed silt fences. Dr. Still complained to the County, and silt fences and turbidity curtains were installed. Dr. Still admitted that they “functioned fairly well.” The silt fences and turbidity curtains were installed prior to the December 23, 2019, filing of the Petition. The turbidity curtains and silt screens met best management practices (“BMPs”). BMPs are generally construction-related practices, and are not designed for the “operation” of a facility after conditions have stabilized. Compliance with BMPs is intended to demonstrate compliance with water quality standards. Ms. Carr directed the County to remove the turbidity control curtains prior to her last inspection since the area had stabilized. While photographic evidence depicted differences in the appearance of water in the roadside ditches from that flowing under the road from forested areas to the west, the photographs were not sufficient to establish violations of state water quality standards for turbidity. A turbidity violation is, by definition, a reading of 29 Nephelometric Turbidity Units (NTUs) over background as measured by a meter. Fla. Admin. Code R. 62-302.530(69). Ms. Carr testified credibly that one cannot gauge water quality from a picture, and that the photographs she took on her December 20, 2018, site visit did not depict the conditions “in real life.” District employees who visited the area, including Ms. Carr, saw nothing that raised water quality concerns. The appearance of the water in photographs is not sufficient to demonstrate that the County failed to control turbidity, sedimentation, and erosion during and after construction to prevent violations of state water quality standards due to construction-related activities. Dr. Still was critical of the District inspectors for failing to take turbidity samples using calibrated meters. However, he did not take such samples himself, and was not able to offer proof of any violation of water quality standards due to the exempt road repairs. Rule 62-330.050(9)(b)5., read in conjunction with rule 62- 330.051(4)(e)8., provides that the “construction, alteration, and operation” of exempt road repair work shall not “[c]ause or contribute to a violation of state water quality standards,” and that “[t]urbidity, sedimentation, and erosion shall be controlled during and after construction to prevent violations of state water quality standards.” The rules establish that the standards and conditions apply to the exempt work being performed, and not to conditions in the area that may have existed prior to the exempt work. The issue of turbidity, though discussed at length during the hearing, was resolved conclusively when Dr. Still admitted that turbidity was not made worse by the road repairs. Furthermore, a preponderance of the evidence established that the structure and stability provided to the travel lanes improved the turbidity and sedimentation that pre-dated the road repair, and reduced erosion of the road, not only by the repair of the road itself, but by eliminating the need to drive off of the road surface to avoid and bypass impassable areas. The Exemption work included the replacement of a culvert under 101st Avenue. At some time between January 8, 2018, and January 19, 2018, an existing 30-inch culvert was removed and replaced with two 24-inch culverts. Dr. Still complained that the 24-inch culverts were resulting in flooding of his property. Therefore, on or about December 17, 2019, prior to the December 23, 2019, filing of the Petition, the 24-inch culverts were removed, and a 30-inch culvert was installed to match the size and capacity of the previously existing culvert, and return the area to its pre-existing condition. There was no evidence that the current 30-inch culvert has resulted in any flooding. Since the 30-inch culvert reestablished the pre-Exemption condition, a strong inference is drawn that the exempt work will not “cause adverse water quantity or flooding impacts to receiving water and adjacent lands.” Rather, the evidence establishes that water quantity impacts, if any, were in existence prior to the exempt road repairs.3 The work was not related to the alteration or maintenance of a “culverted roadway crossing,” despite the culvert work. Thus, the previous inclusion of rule 62-330.051(4)(b) as a basis for the County’s Exemption request was withdrawn. The District accepted that withdrawal, and its notice of Exemption did not include any reference to the culvert. As indicated in the Preliminary Statement and the amended disposition of the Motion in Limine, the road repair Exemption does not explicitly address culvert replacement. Therefore, any allegation that the replacement of the culvert was a violation of District permitting standards must be taken up with the District as an exercise of its enforcement discretion, and is not an issue in this proceeding. Dr. Still produced photographs that were described as depicting “sediment” that was deposited along a “canal” on his property between 101st Avenue and a cleared utility easement. To the extent the photographs depicted sediment as described, which was not visually apparent, they were not sufficient to prove when any such sediment was deposited, or whether the sediment was related to the road repairs performed under the Exemption. 3 Again, simplistically, work performed under the road repair exemption is not designed to make pre-existing water quality and water quantity issues better, it just cannot make those conditions worse. Mr. Rischar testified convincingly that there was no scientific data to support a determination that there are water quality issues, including turbidity, at the roadway. Dr. Still produced photographs of the post-Exemption condition of 101st Avenue with several comparatively tiny depressions that, if never maintained, would presumably develop into potholes. Despite the nascent depressions, the road appeared to be vastly improved from its condition prior to the repairs, as evidenced by Dr. Still’s pre-Irma photographs. Mr. Rischar testified credibly that any roadway, from the least developed dirt road to the most highly developed interstate highway can, and does, develop holes in the travel surface over time. For that reason, governmental bodies, including the County, maintain roads, including 101st Avenue. The photographs provide no support for a finding that the exempt road repairs have resulted in any violation of a standard in either rule 62-330.051(4)(e)8. or rule 62- 330.050(9)(b)5. The evidence established that 101st Avenue was regularly maintained and repaired by the County for more than seven years prior to the Exemption, and that the road repairs did not realign, expand the number of traffic lanes, or alter the width of the existing road. The evidence established that the work performed under the Exemption did not realign 101st Avenue. The repairs to 101st Avenue included work reasonably necessary to repair and stabilize the road using generally accepted roadway design standards. The evidence demonstrates that no excavated material related to the work under the Exemption was placed at or near Dr. Still’s property or, for that matter, anywhere along 101st Avenue. The evidence established that the repairs to 101st Avenue did not adversely impound or obstruct existing water flow, cause adverse impacts to existing surface water storage and conveyance capabilities, or otherwise cause adverse water quantity or flooding impacts to receiving waters and adjacent lands. The evidence was not sufficient to establish that the road repair work caused or contributed to a violation of state water quality standards. Ultimate Findings of Fact The greater weight of the competent substantial evidence establishes that 101st Avenue was in existence long before January 1, 2002, has been publicly used since that time, and has been regularly maintained and repaired by the County for more than seven years prior to the Exemption. Evidence to the contrary was not persuasive. The greater weight of the competent substantial evidence establishes that during its relevant period of existence, the width of 101st Avenue that actually has been maintained or repaired is substantially -- if not identically - - the same as the width of 101st Avenue after the road repairs under the Exemption were completed. The work performed under the Exemption did not realign or expand the number of traffic lanes of 101st Avenue. The repairs to 101st Avenue included work reasonably necessary to repair and stabilize the road using generally accepted roadway design standards. Evidence to the contrary was not persuasive. The greater weight of the competent substantial evidence establishes that no excavated material related to the work under the Exemption was placed at or near Dr. Still’s property or, for that matter, anywhere along 101st Avenue. Evidence to the contrary was not persuasive. The greater weight of the competent substantial evidence establishes that the repairs to 101st Avenue did not adversely impound or obstruct existing water flow, cause adverse impacts to existing surface water storage and conveyance capabilities, or otherwise cause adverse water quantity or flooding impacts to receiving waters and adjacent lands. Evidence to the contrary was not persuasive. The greater weight of the competent substantial evidence establishes that the road repair work incorporated effective means of stormwater treatment, and did not cause or contribute to a violation of state water quality standards. Evidence to the contrary was not persuasive. The greater weight of the competent substantial evidence establishes that turbidity, sedimentation, and erosion were controlled during and after construction, and continue to be controlled, to prevent violations of state water quality standards. Erosion and sediment control BMPs were installed and maintained in accordance with applicable guidelines and specifications. Evidence to the contrary was not persuasive.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Suwannee River Water Management District enter a final order: Approving the December 10, 2019, Environmental Resource Permit (ERP): Exemption, ERP-007-233697-2, determining that activities related to the repair of Southwest 101st Avenue in Bradford County, Florida, met the criteria to be an exempt activity pursuant to rule 62-330.051(4)(e); and Taking such action pursuant to section 120.595(1) as it deems appropriate. The undersigned retains jurisdiction to determine the award of costs and attorneys’ fees pursuant to section 120.595(1)(d), if the final order makes such an award and the case is remanded by the Suwannee River Water Management District to DOAH for that purpose. DONE AND ENTERED this 19th day of November, 2020, in Tallahassee, Leon County, Florida. S E. GARY EARLY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of November, 2020. COPIES FURNISHED: George T. Reeves, Esquire Davis, Schnitker, Reeves and Browning, P.A. Post Office Drawer 652 Madison, Florida 32341 (eServed) Paul Edward Still 14167 Southwest 101st Avenue Starke, Florida 32091 (eServed) Frederick T. Reeves, Esquire Frederick T. Reeves, P.A. 5709 Tidalwave Drive New Port Richey, Florida 34562 (eServed) William Edward Sexton, County Attorney Bradford County, Florida 945 North Temple Avenue Post Office Drawer B Starke, Florida 32091 (eServed) Hugh L. Thomas, Executive Director Suwannee River Water Management District 9225 County Road 49 Live Oak, Florida 32060 (eServed)

Florida Laws (10) 120.52120.56120.569120.57120.595120.68334.03336.02373.06995.361 Florida Administrative Code (5) 28-106.10428-106.21762-302.53062-330.05062-330.051 DOAH Case (4) 11-649513-051513-225420-0091
# 7
DEPARTMENT OF ENVIRONMENTAL PROTECTION vs RICHARD H. LEAGUE AND NANCY A. LEAGUE, 10-002196EF (2010)
Division of Administrative Hearings, Florida Filed:Jacksonville, Florida Apr. 23, 2010 Number: 10-002196EF Latest Update: Oct. 05, 2011

The Issue The issues to be determined in this case are whether Respondents, Richard H. League and Nancy A. League, violated a Department of Environmental Protection ("Department") rule that prohibits filling in wetlands and surface waters without a Department permit; and if so, whether Respondents should pay the administrative penalty and investigative costs and undertake the corrective actions that are demanded by the Department.

Findings Of Fact The Department is the state agency having the power and duty to protect Florida’s air and water resources and to administer and enforce the provisions of chapters 373 and 403, Florida Statutes, and the rules promulgated pursuant thereto in Florida Administrative Code Title 62. Respondents own property located at 1160 River Road, Orange Park, Clay County, Florida. The property is adjacent to the St. Johns River. Sometime before 1995, pieces of concrete were placed in the water along the bank of the St. Johns River in an area that includes the shoreline of the League property, in an apparent effort to prevent or reduce shoreline erosion. On August 14, 1995, the Department issued Permit No. 102752932 to Richard League to construct a dock and replace a stormwater ditch with a covered culvert. The 1995 permit did not authorize a seawall, riprap, or other erosion control structure. A drawing attached to the 1995 permit shows the “typical concrete fill pieces at water’s edge,” which are the concrete pieces that had been placed along shoreline before 1995. The Department referred to the existing concrete pieces as a riprap revetment. Following the issuance of the permit, Mr. League discussed with Michael Eaton, Environmental Manager for the Submerged Lands and Environmental Resources Program for the Department's Northeast District Office, Mr. League's desire to restore the riprap material along his shoreline because, according to Mr. League, the concrete pieces had been displaced by storm waves and were no longer protecting his shoreline from erosion. On October 27, 1995, Mr. Eaton sent a letter to Mr. League regarding the "Existing Riprap Revetment," stating that "movement and rearranging of the riprap material along the revetment will not require a permit from the Department." The letter did not authorize the construction of a seawall or the placement of new material along Respondents' shoreline. In May 2005, the Department received an anonymous complaint that Respondents were constructing an unauthorized dock at their property. An investigation was conducted, but no major violation was found. Mr. League claims that, at the time of the 2005 investigation, he had completed 60 percent of the wall structure that is the subject of this proceeding. Mr. League also claims that the Department investigators saw the structure, but expressed no objection to the structure. However, there is no photographic or other evidence to support Mr. League's claim that the structure was observable in May 2005. No mention was made in the Department's investigative report that a seawall or similar structure was under construction at the League property. The normal practice of the Department is to describe such structures and activities in the investigative report. The aerial photographs in evidence support the Department's claim that the structure did not exist in May 2005. In April 2009, the Department received another anonymous complaint that Respondents were constructing an unauthorized structure at the shoreline. The investigation of the complaint revealed that Respondents were constructing a wall of pre-existing concrete pieces and new concrete pieces. The wall or seawall was not located at the bank, but was 12 to 21 feet waterward of the bank. It was apparently Respondents' intent to place fill behind the seawall to extend the upland property waterward. When Department employees conducted another inspection in January 2010, they found that wetlands and surface waters which had previously been observed behind (landward of) the seawall had been partially filled. At the hearing Respondents claimed that the structure qualifies as riprap. However, in their post-hearing submittal, Respondents alternately claimed that the structure was a seawall, an upland retaining wall, or riprap, depending on what rule or statute Respondents perceived as helpful in arguing that the structure did not require a permit. Florida Administrative Code Rule 62-341.021(15) defines "riprap" as "a sloping retaining or stabilizing structure made to reduce the force of waves and to protect the shore from erosion, and consists of unconsolidated boulders, rocks, or clean concrete rubble with no exposed reinforcing rods or similar protrusions." Respondents' structure is a consolidated wall, made by stacking relatively flat pieces of concrete. It has virtually no slope. It is not an unconsolidated, sloping pile of material. In addition, Respondents' structure is not placed at the bank for the purpose of retaining the existing bank. The Department contends that Respondents' structure is a seawall, which is defined in rule 62-341.021(16) as "a man- made wall or encroachment, except riprap, which is made to break the force of waves and to protect the shore from erosion." The waters of the St. Johns River reach and extend landward of the seawall constructed by Respondents. Photographs of the seawall show water stains and rafted debris at the base deposited by the waters of the St. Johns River. There was wetland vegetation behind the seawall. Mr. League admitted at the hearing that the waters of the St. Johns River sometimes move through the porous wall and fill the void between the wall and the bank. The landward extent of the St. Johns River is landward of Respondents' structure. The Department showed that the value of the time spent by Jim Maher, Matthew Kershner, and Heather Anthony to investigate this matter exceeded $1,000. However, the Department is only seeking $1,000 from Respondents for the Department's investigative costs.

Florida Laws (5) 120.68373.129373.403403.121403.813
# 8
JAMES H. MOORE AND JERRILYN MOORE vs PAUL BRIDGES AND SUWANNEE RIVER WATER MANAGEMENT DISTRICT, 93-006656 (1993)
Division of Administrative Hearings, Florida Filed:Trenton, Florida Nov. 19, 1993 Number: 93-006656 Latest Update: Apr. 29, 1994

Findings Of Fact Petitioners own property located in Section 6, Township 9, Range 16 East, Gilchrist County, Florida (the "Moore property"). Mrs. Linda Bridges owns property adjacent to and south of the Moore property (the "Bridges property"). Respondent, Bridges ("Bridges"), is in possession and control of the Bridges property. Mr. Glenn Miller owns property adjacent to and south of the Bridges property (the "Miller property"). ITT-Rayonier owns property west of the Moore, Bridges, and Miller properties (the "ITT property"). A dirt road runs north and south in front of and along the western border of the Moore, Bridges, and Miller properties (the "road"). The road separates the ITT property, to the west, from the Moore, Bridges, and Miller properties, to the east. Prior to 1989, surfacewater historically flowed in a northeasterly direction. It flowed northeasterly from the ITT property through a 24 inch road culvert onto the Bridges property. It then flowed north through a 36 inch culvert on the southerly portion of the Moore property, across the Moore property, and into Weeks Lake to the north of the Moore property. In 1989, with the consent of Bridges but without a permit from the District, Petitioners began a construction plan that included the installation of two 62 inch culverts to enhance the northeasterly flow of surfacewater from the ITT property to Weeks Lake. One 62 inch culvert was intended to replace the 24 inch culvert under the road forming the westerly boundary between the ITT property and the Moore and Bridges properties. The second 62 inch culvert was intended to replace the 36 inch culvert on the southerly boundary of the Moore property. The second 62 inch culvert was needed so the same volume of surfacewater flowing from the ITT property through the 62 inch road culvert could continue its northerly flow from the Bridges property to the Moore property and on to Weeks Lake. Petitioners replaced the 24 inch road culvert with a 62 inch culvert but left intact the 36 inch culvert on the southerly portion of their property. Thus, a greater volume of surfacewater can flow from the ITT property through the 62 inch culvert onto the Bridges property but a lesser volume of surfacewater can flow from the Bridges property through the 36 inch culvert onto the Moore property. Petitioners removed fill material from the ITT property to widen and increase the height of the road bed on the westerly boundary between the ITT and Moore properties. The heightened road bed impounds a greater volume of surfacewater on the ITT property before it flows over the road onto the Moore property. This can increase the rate of flow of surfacewater through the 62 inch road culvert onto the Bridges property under certain circumstances. Petitioners increased the depth and width of existing ditches, and added new ditches along a portion of the road bed onto the Bridges property. The increased ditch capacity further increases the volume of surfacewater that can flow onto the Bridges property. Petitioners constructed a berm running east and west on the southerly boundary of the Moore property. This increases the volume of surfacewater that can be impounded on the Bridges property without flowing onto the Moore property through areas other than the 36 inch culvert that Petitioners left intact on the southerly portion of their property. The 62 inch road culvert, increased ditch capacity, heightened road bed between the ITT and Moore properties, the berm on the southerly portion of the Moore property, and the 36 inch culvert increase the volume of surfacewater that is impounded on the Bridges property before continuing its historic northeasterly flow. Surfacewater impounded on the Bridges property floods the Bridges property and properties to the south of the Bridges property. Although flooding occurred on the Bridges property prior to the 1989 construction, flooding on the Bridges property and properties south of the Bridges property is greater since Petitioners completed construction. In addition, the ITT property drains more readily. On or about October 13, 1993, Bridges applied to the District for a General Surfacewater Management Permit to replace the 62 inch road culvert with a 24 inch culvert pursuant to Florida Administrative Code Rule 40B-4.2010(1)(a). A General Surfacewater Management Permit is issued for activities that have little or no potential adverse impact to surfacewater resources for the District. The application satisfied all of the criteria for the permit at issue. ITT does not object to the proposed permit even though more surfacewater will be impounded on the ITT property. Issuance of the proposed permit will approximate the flow of surfacewater that existed prior to Petitioners' installation of a 62 inch road culvert without a permit in 1989.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent, Suwannee River Water Management District, enter a Final Order and therein GRANT Respondent, Paul Bridges', Application For Agriculture Or Forestry General Surfacewater Management Permit. DONE and ENTERED this 2nd day of March 1994, in Tallahassee, Florida. DANIEL S. MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 93-6656 Petitioners' Proposed Findings Of Fact. 1.-4. Rejected as immaterial 5. Rejected as recited testimony 6.-7. Rejected as not supported by credible and persuasive evidence 8. Rejected as irrelevant and immaterial 9.-13. Rejected as not supported by credible and persuasive evidence 14.-15. Rejected as irrelevant and immaterial 16.-19. Rejected as not supported by credible and persuasive evidence Rejected as irrelevant and immaterial Rejected as not supported by credible and persuasive evidence Rejected as recited testimony 23.-24. Rejected as not supported by credible and persuasive evidence Respondent, Paul Bridges, Proposed Findings Of Fact. Respondent, Bridges, did not submit proposed findings of fact. Respondent, Suwannee River Water Management District, Proposed Findings Of Fact. All of the District's proposed findings of fact are accepted in substance. COPIES FURNISHED: James H. and Jerrilyn Moore, pro se Route 2, Box 120-E Trenton, FL 32693 Paul Bridges, pro se Route 2, Box 120K-1 Trenton, FL 32693 Janice F. Bessinger, Esquire Brannon, Brown, Haley, Robinson & Cole Post Office Box 1029 Lake City, FL 32056-1029 Jerry Scarborough, Executive Director Suwannee River Water Management District Route 3, Box 64 Live Oak, FL 32060

Florida Laws (1) 120.57 Florida Administrative Code (2) 40B-4.201040B-4.2020
# 9
MICHAEL L. GUTTMANN vs ADR OF PENSACOLA AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 00-002524 (2000)
Division of Administrative Hearings, Florida Filed:Pensacola, Florida Jun. 16, 2000 Number: 00-002524 Latest Update: Mar. 18, 2002

The Issue The issue is whether ADR of Pensacola should be issued a wetland resource permit and sovereign submerged lands authorization allowing the construction of a 30-slip docking facility on Big Lagoon, Escambia County, Florida.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In this environmental permitting dispute, Petitioner, Michael L. Guttmann, who lives less than one mile from the project site, has challenged the proposed issuance by Respondent, Department of Environmental Protection (Department), of a Wetland Resource Permit (permit) and Sovereign Submerged Lands Authorization (authorization) which would allow Respondent, ADR of Pensacola (applicant), to construct a 30-slip docking facility on Big Lagoon, Escambia County, Florida. The facility will be part of a condominium project to be constructed on the upland portion of the property. As grounds for contesting the permit, Petitioner contended that the Department failed to consider "the long term health of Big Lagoon," navigational hazards created by the project, or public safety; failed to impose an adequate "monitoring program"; did not provide for a "contingency plan for hurricane activity"; failed to consider that the activity will degrade a nearby Outstanding Florida Water [OFW]; and failed to take into account "existing unused marina slips close by." The petition further alleged that the foregoing concerns constituted violations of Section 373.414, Florida Statutes (2000), and Rules 62-4.242, 62-302.300, 62-302.700, and 62- 312.080, Florida Administrative Code. The cited statute identifies "additional criteria" for issuing a permit while the first three rules pertain to OFWs. The last rule contains general standards for the issuance or denial of a permit. Petitioner raised no issues concerning the issuance of the authorization in his initial pleading. Until April 2000, the upland property was owned by the applicant. It was then sold to Harbour Pointe of Pensacola, Inc., which has subsequently entered into an agreement with the applicant allowing the applicant to construct the dock, operate the permit, and purchase a condominium unit. If the application is approved, applicant intends to construct a 442 feet x 4 feet access pier with seventeen 30 feet x 1.5 feet finger piers, thirteen 40 feet x 1.5 feet finger piers, and a 74 feet x 1.5 feet terminal platform, to form a 30-slip docking facility at 10901 Gulf Beach Highway on Big Lagoon, a Class III water in Escambia County, Florida. Approval to use the submerged lands is found in the authorization. The dock will be located in a "fairly pristine area" in Big Lagoon a few miles southwest of Pensacola, Florida. That body of water is six miles in length and is separated from the Gulf of Mexico by a slender coastal barrier island known as Perdido Key, which lies approximately one statute mile south of the project. Continuing west along the shoreline next to the project site are a string of single-family homes with small dock facilities, most of which are less than 1,000 square feet in size and thus exempt from Department permitting requirements. To the east of the undeveloped property are more undeveloped lots and a private yacht club with extensive docking facilities. The facility being challenged here will not be a public marina; rather, it will serve the residents of a proposed upland condominium (consisting of two buildings) to be constructed at the same location. The project is more commonly referred to as the Harbour Pointe Marina. It is fair to infer that Petitioner and adjoining property owners object not only to the dock, but also to the condominium project. The application and project When the application was originally filed with the Department in July 1995, it contained plans for a longer dock and more slips. Due to a reduction in the length of the pier and number of slips to conform to Department rules, other technical changes, and various requests by the Department for additional information, the draft permit was not issued by the Department until May 2000. The Department considers this a "major project" with "major [hydrographic and water quality] issues connected with it." In reviewing the application, the Department considered whether reasonable assurance had been given by the applicant that water quality standards would not be violated, and whether the additional criteria in Section 373.414(1)(a)1.-7., Florida Statutes (2000), had been satisfied. The Department concluded that water quality standards would not be degraded, and that the project, as designed and permitted, was not contrary to the public interest. In making the public interest determination, the Department typically assigns a plus, minus, or neutral score to each of the seven statutory factors. In this case, a neutral score was given to historical and archaeological resources [paragraph 373.414(1)(a)6.] since there were none, while the permanent nature of the project [paragraph 373.414(1)(a)5.] caused it to be rated "a little bit on the minus side"; all other factors were given a plus. Department witness Athnos then concluded that on balance the project "was a plus because it will not adversely affect any of these things." The access pier (dock) runs perpendicular from the shoreline and stretches out some 442 feet to where the water reaches a depth of seventeen feet, which is the deepest point in Big Lagoon. The unusual length of the dock is required so that the boat slips will begin past the seagrass colony (which lies closer to the shore), to prevent boat propeller blades from cutting the top of the seagrass, and to reduce the amount of sedimentation stirred up by the boat propellers. Aerial photographs confirm that when completed, the dock will probably be the largest in Big Lagoon, and much larger than the neighboring docks to the west. The use of boat slips will be limited to condominium owners. Only 19 slips will be constructed initially, since the applicant has secured approval at this time for only the first phase of the condominium project. When approval for the second phase is secured, the applicant intends to add an additional 11 slips. Water quality In his initial pleading, Petitioner made a general allegation that the Department failed to consider "the long term health of Big Lagoon"; there were no specific allegations regarding water quality standards. In his Proposed Recommended Order, however, he argues that the [a]pplicant failed to provide reasonable assurances that water quality standards would not be violated." Assuming arguendo that the issue has been properly raised, Petitioner has still failed to substantiate his allegation. That portion of Big Lagoon where the project will be located is a Class III water of the State. Studies on metals, greases, oils, and the like submitted by the applicant reflected that the "water quality [in that area] did not exceed the standards in Rule 62-302." To provide further reasonable assurance regarding water quality standards, the applicant has voluntarily agreed to use concrete piling and aluminum docks. Unlike wooden piling and docks, these types of materials do not leach toxic substances such as arsenic, copper, and acromiom into the water. In addition, special permit conditions require that sewage pumpout equipment be located at the site so that boats will not discharge raw sewage into the waters. Liveaboards are prohibited, and fueling will not be available at the facility. Finally, the cleaning of fish is not allowed, and boat owners cannot scrape their boat bottoms while docked at the facility. All of these conditions are designed to ensure that water quality standards will not be violated. Enforcement mechanisms for the above conditions are found in either the permit itself or Chapter 403, Florida Statutes. Also, one of the conditions in the draft permit expressly states that the applicant is not relieved of liability for harm or injury to humans, plants, or property caused by the construction of the dock. However, if a permit is issued, Condition 9 of the permit should be modified to require that trained personnel be available twenty-four hours per day, rather than just during standard business hours, to assist boaters with, and ensure that they use, the sewage pumpout equipment. Any permit issued should also require that boats be placed on lifts while using the docking facilities. This will prevent any leaching of paint from the boat bottoms into the waters. Otherwise, the paint would cause a degradation of the water. The more persuasive evidence supports a finding that, with the additional conditions, reasonable assurance has been given that the state water quality standards applicable to Class III waters will not be violated. Outstanding Florida Waters In his complaint, Petitioner has contended that "the proposed activity will degrade an [OFW] as a result of its close proximity to the Gulf Islands National Seashore," and that the"[D]epartment has made no analysis of this project['s] impact on the [OFW] which is adjacent to the proposed activity." The record discloses that the southern portion of Big Lagoon has been designated as an OFW. This area includes the waters around Gulf Islands National Seashore and Big Lagoon State Park; they begin approximately 650 to 700 feet south of the end of the dock. As noted earlier, the project is located within Class III waters. Because the Department found that no violation of state water quality standards in those waters would occur, it likewise concluded, properly in this case, that the project would have no impact on any OFW, even though such waters begin some 650 or 700 feet away. Under these circumstances, there would be no reason to assess the water quality in the OFWs or the projected impacts on those waters, as Petitioner suggests. In the absence of any credible evidence to the contrary, it is found that the project will not adversely impact an OFW. Hydrographic characteristics If a dock has more than ten boat slips, the Department routinely conducts a hydrographic (flushing) study to determine whether the structure will adversely affect the flow of the water in the area or cause erosion or shoaling on adjacent properties. In the summer of 1999, a Department engineer conducted a hydrographic study using a dye tracer and concluded that flushing characteristics were excellent and that there would be no adverse effects caused by the project. This conclusion has not been credibly contradicted. Therefore, it is found that the dock will not adversely affect the flow of water or cause harmful erosion or shoaling. Navigational issues In his initial pleading, Petitioner raised a contention that the project will create "navigational hazards" because the dock "extends nearly into a navigation channel which routinely carries commercial towboats transporting hazardous material, the spill of which would adversely affect Big Lagoon." He also alleges that the rupture of a vessel could impact public safety. Channel markers placed by the U.S. Army Corps of Engineers in the Intracoastal Waterway (of which Big Lagoon is a part) define a navigational channel for boats approximately 400- 500 feet south of the end of the proposed dock. That channel is used by both recreational and commercial traffic, including barges and other large watercraft which regularly haul oil, chemicals, and other products through the Intracoastal Waterway to and from Pensacola, Panama City, and St. Marks, Florida. The water in the marked channel is only thirteen feet deep. Because the U.S. Army Corps of Engineers has jurisdiction over the maintenance of the marked channel, the Department defers to that entity's judgment in determining whether a proposed structure will impede navigation in the marked channel. The proposed dock ends near the deepest part of the natural channel where the water reaches a depth of seventeen feet. Because of the deeper water to the north, which allows the boat captain to "get better steerage," the commercial boat traffic sometimes tends to follow the natural channel, rather than the marked channel formed by the navigational aids. When they do so, however, they are straying from the so-called "legal" channel. Petitioner's expert, a retired tugboat captain, opined that in a storm or squall, a commercial boat using the natural rather than the marked navigational channel might be blown extremely close to the dock or even strike it, thus causing a hazardous situation. He acknowledged, however, that he was not predicting more accidents because of the construction of the dock; he also admitted that the dock would not cause ships to "sudden[ly] have problems navigating that Big Lagoon." The location of the proposed dock was shown to the U.S. Army Corps of Engineers and the Florida Marine Patrol, and there were no adverse comments regarding this issue by either agency. In the absence of any negative comments by those agencies, and the acknowledgement by Petitioner's own witness that the dock will not cause accidents or create navigational problems for other boaters, the more persuasive evidence supports a finding that the project will not adversely affect navigation or public safety in Big Lagoon. Seagrass and monitoring Petitioner has alleged that Big Lagoon "is the healthiest body of water in Escambia County with a white sand bottom and abundant seagrass," and that the proposed project will adversely affect its "long term health." He also alleges that the Department has failed to provide a "remedy or punishment should the results [of the Department's monitoring plan] indicate that the seagrass has been harmed"; that the Department's monitoring plan is not "of sufficient duration to reasonably report the long-term effect of concentrated mooring and traffic" or "sufficiently specific to insure usable data"; and that the data relied upon by the Department [such as photographs] were not "sufficient" to determine the existing health of the seagrass. The evidence reflects that a "nice, healthy seagrass community" is found in the area where the dock will be constructed. It stretches out several hundred feet from the shoreline to where the water reaches a depth of around six feet. The Department considers seagrass to be a "most important resource" which should be protected. This is because seagrass is essential for "binding" the shoreline and stabilizing the sediments, and it serves as a nursery area for juvenile fish and shellfish. Indeed, due to these beneficial effects, far more species of shellfish are found in areas where seagrass thrives than in areas where no seagrass exists. To protect the seagrass, the dock has been extended out 442 feet from the shoreline so that the first boat slip begins at a depth of seven feet, or just past where the seagrass ends. This will prevent the scarring of the grass by boat propellers and reduce turbidity that is typically caused by propeller dredging and boat wakes. Thus, at least theoretically, no boat activity by condominium owners is contemplated in waters of less than seven feet. Because seagrass requires as much light as possible to survive, educational signs will be posted in the area to warn boaters that seagrass is found closer to the shoreline, and that mooring in that area is prohibited. There is, however, no enforcement mechanism to ensure that condominium owners or nonresidents comply with these warnings. Under the draft permit, the Department is allowed to access the premises at reasonable times for sampling or monitoring purposes. A special section of the draft permit includes a number of requirements pertaining to the monitoring of turbidity levels during dock construction while another section requires the applicant to take photographs of the existing seagrass beds at numerous locations before, during, and after construction of the dock. Condition 14 requires that the permittee maintain "records of monitoring information" for at least three years. The evidence supports a finding that if a permit is issued, a mapping of the seagrass should be made prior to construction of the dock and during the height of the growing season (September and October). When the photographing of the area is performed, the applicant should use a sampling protocol that is based on a scientifically determined method. Also, both affected and unaffected areas should be monitored to compare the effect of the additional boat traffic on the seagrass after the dock is constructed. All of these conditions should be incorporated into any issued permit. According to Dr. Heck, a marine biologist who specializes in the study of seagrass and testified as an expert on behalf of Petitioner, seagrass beds in Big Lagoon have been "shallowing up" or thinning out in recent years due to decreasing water clarity. In other words, as the water becomes cloudier from more and more boat activity, the sunlight cannot penetrate and the seagrass will not thrive. The seagrasses most susceptible to disappearing are those that are found at the deepest depth. Doctor Heck attributed the decline in seagrass to increased human activity in the area. This activity is related not only to the existing homeowners in the area, but also to the non-resident boaters (both recreational and commercial) who use the waters in that area. A Department study conducted in 1995 confirmed that the only seagrass area in North Florida "significantly affected" by propeller scarring was an area in Big Lagoon known as Scallop Cove, near Spanish Point. This study is consistent with those studies performed by Dr. Heck in the late 1990's, and one as recently as last year, that support a finding that seagrass in Big Lagoon is on the decline due to both propeller scarring and increased turbidity caused by wakes from larger recreational boats. For this reason, Dr. Heck concluded that the addition of thirty boats at the project site, some of which would be as large as 30 feet or so, would have a "negative effect" on the seagrass colony. This in turn will cause a negative effect on the marine productivity in the area, as well as the conservation of fish and their habitat. Doctor Heck's testimony on this issue is found to be the most persuasive. Other concerns Petitioner further contends that the Department failed to provide a "meaningful contingency plan for hurricane activity." This matter, however, is beyond the permitting jurisdiction of the Department. Petitioner has also contended that the Department failed to take into account "existing unused marina slips close by" which could be used by the condominium owners. Like the prior issue, this matter is not a consideration in the permitting scheme. Another issue raised by Petitioner, albeit untimely, was that the construction of this dock could lead to further development in Big Lagoon. There was, however, no evidentiary support for this contention. Indeed, there is no evidence that future permit applications with impacts similar to this application can reasonably be expected in the area. At hearing, Petitioner raised for the first time a contention that the applicant no longer owns the upland property and thus a permit/authorization cannot be issued to that entity. Aside from this issue being untimely, the fact that a permit holder does not own the upland property is not unusual. If this occurs, permits and authorizations (leases) are routinely transferred to the new owner once the Department receives the necessary title information. It is not a ground to defeat the application. Petitioner also raised for the first time at hearing a contention that the site plan approval for the condominium has expired under a provision of the Escambia County Land Development Code and therefore the permit should be denied. Again, the issue is untimely; more importantly, it should be addressed in another forum since the Department has no jurisdiction over this issue. Likewise, a legitimate concern by an adjoining property owner, witness Hobgood, and an area realtor, that Hobgood's single-family property would probably decline in value if the project is built is nonetheless beyond the Department's jurisdiction. Finally, a contention that the Department improperly calculated the maximum number of boat slips for an 88-unit condominium project has been rejected. The record contains a lengthy explanation by witness Athnos which shows that the Department's calculation under Rule 18-21.004(4)1., Florida Administrative Code, was correct. Those calculations are also detailed in Respondents' Exhibit 14.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department of Environmental Protection enter a final order denying the application of ADR of Pensacola for a wetland resource permit and sovereign submerged lands authorization. DONE AND ENTERED this 28th day of February, 2001, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (850) 488-9675, SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of February, 2001. COPIES FURNISHED: Kathy C. Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Michael L. Guttmann, Esquire 314 South Baylen Street, Suite 201 Pensacola, Florida 32501-5949 Charles T. Collette, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 David A. Sapp, Esquire 1017 North 12th Avenue Pensacola, Florida 32501-3306 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

Florida Laws (5) 120.569120.57253.77267.061373.414 Florida Administrative Code (6) 18-21.00428-106.20562-302.70062-312.06562-312.08062-4.242
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer