Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAMIAN C. DAVIS, 83-001230 (1983)
Division of Administrative Hearings, Florida Number: 83-001230 Latest Update: Sep. 22, 1983

The Issue The issues presented are as follow: Did the Respondent allow his registration to be used by an unlicensed and unregistered person to evade the provisions of Chapter 489, Florida Statutes? Did the Respondent combine and conspire to allow his registration to be used by an unlicensed or unregistered person to evade the provisions of Chapter 489, Florida Statutes? Did the Respondent engage in contracting in a name other than set forth on his certificate? Did the Respondent engage in contracting in a name of a business entity without first qualifying that business entity with the Construction Industry Licensing Board? The parties submitted post hearing findings of fact in the form of a proposed recommended order and correspondence. To the extent that the proposed findings of fact have not been included in the factual findings in this order, they are specifically rejected as being irrelevant, not being based upon the most credible evidence, or not being a finding of fact.

Findings Of Fact The Respondent, Damian C. Davis, is a certified general contractor holding license number CG C007059 issued by the Construction Industry Licensing Board through the Department of Professional Regulation. On or about August 29, 1980, the Respondent obtained building permit number B 45383 from the City of Tampa Building Department for construction to be performed by George Lacey at 910 East Osborne Street, Tampa, Florida, the residence of Martha Smith George Lacey was at that time uncertified and unregistered and was the contractor in fact on the work to be done for Martha Smith at 910 East Osborne Street in Tampa. The Respondent arranged for all building inspections by inspectors of the City of Tampa and was on the building site when said inspections were conducted. All work was approved by building inspectors of the City of Tampa, and there were no code problems. Subsequent to the completion of the work by Lacey, the owner had a problem with a leak over a sliding glass door which Lacey had contracted to repair. When this matter was brought to the Respondent's attention by officials of the Tampa Building Department, the Respondent fixed the leak to the owner's complete satisfaction. The building permit obtained by the Respondent was issued in the Respondent's name. All work the Respondent performed was done in the Respondent's name. The Respondent and Lacey frequently worked together in joint ventures; however, this was not such a project.

Recommendation Having found the Respondent, Damian C. Davis, guilty of one count (one offense) of violating Sections 489.129(1)(e) and (f), Florida Statutes, and considering the Respondent's prompt action to satisfy the owner, it is recommended that the Respondent be given a letter of reprimand and assessed a civil penalty of $500. DONE and RECOMMENDED this 28th day of July, 1983, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of July, 1983. COPIES FURNISHED: Stephanie A. Daniel, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Damian C Davis 1310 West Charter Street Tampa, Florida 33602 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 ================================================================= AMENDMENT TO AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, vs. CASE NO. 19791 DOAH CASE NO. 83-1230 DAMIAN C. DAVIS DAVIS & SEXTON, INC. 1302 West Sligh Avenue Tampa, Florida 33604, Respondent. / AMENDMENT TO FINAL ORDER The Final Order entered on September 22, 1983 in this cause incorrectly stated the fine imposed upon the Respondent. The correct amount is $250.00, to be paid within 30 days of this Order. DONE AND ORDERED in Jacksonville, Florida, this 30th day of November , 1983. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD Henry Bachara, Chairman

Florida Laws (2) 120.57489.129
# 1
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs ED J. ADAMS, 95-005908 (1995)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Dec. 04, 1995 Number: 95-005908 Latest Update: Aug. 14, 1996

The Issue The issues for determination are whether Respondent committed the acts alleged in the Administrative Complaint and, if so, what, if any, penalty should be imposed.

Findings Of Fact Petitioner is the governmental agency responsible for issuing licenses to practice as building contractors. Petitioner is also responsible for regulating such licensees on behalf of the state. At all times pertinent to this proceeding, Respondent has been licensed individually as a Certified General Contractor pursuant to license number CG C 0055328 issued by the Construction Industry Licensing Board (the "Board"). Respondent has never been licensed by the Board as the qualifying agent for Mr. Gary Butler ("Butler"), an unlicensed contractor. In 1993, Respondent entered into an agreement with Butler who has never been licensed by the Board. The terms of the agreement require Respondent to pull permits for construction projects entered into by Butler. Butler pays Respondent for each permit or weekly. Respondent supervises some, but not all, of the projects undertaken by Butler. In August, 1993, Mr. Lynn Kyler ("Kyler"), the owner of a residence constructed by Ms. Denise Pyke ("Pyke"), a Certified Residential Contractor, asked Pyke to find a contractor to build a new dock and boat house at Kyler's residence. The Kyler residence is a lake front home located at 10250 State Road 561 A, Clermont, Lake County, Florida. Kyler authorized Pyke to act as Kyler's agent for construction of the dock and boat house. Kyler resided in Indiana from August through late fall of 1993. Pyke obtained recommendations of various candidates including Butler. Butler represented himself as a licensed and insured builder of docks and boat houses. Butler provided Pyke with a business card representing that Butler is licensed and insured. Pyke obtained cost and design proposals from Butler and Norquist Construction Company and communicated the proposals to Kyler. Kyler chose Butler. Butler agreed to demolish the existing dock and construct a new dock and boat house (the "project"). Kyler paid Butler the full contract price of $6,897.60. Prior to the completion of the project, neither Respondent nor Butler disclosed to Pyke or Kyler that Butler was unlicensed. Nor did they disclose that Butler would use Respondent's license to pull the permit for the project. Respondent knew that Butler is not licensed as a contractor, in any capacity. On August 25, 1993, Respondent and Butler went to the Lake County Building Department. Respondent used his license to pull Permit Number T93- 04793 for the project. The permit was issued to Respondent, listed Respondent's license as the certified general contractor, and was maintained in the official records of the Lake County Building Department. Respondent listed himself on the permit as the contractor for the entire project without limitation and without reference to Butler. Respondent was not authorized by Pyke or Kyler to pull the permit or to participate in the project. At the time, neither Pyke nor Kyler were aware of Respondent's existence or his role in the project. Respondent did not participate and had no involvement in the project except pulling the permit. The project was commenced by Butler in August, 1993, and completed shortly thereafter. Respondent did not supervise or participate in the construction of the project. Butler began the project without first filing a Notice of Commencement. Butler constructed the project with only a 10 foot setback in violation of the 25 foot setback required in Lake County Code Ordinance 10.0401(3)(d). Butler also failed to obtain an electrical permit in violation of Standard Building Code, Section 103.1.1. (1991). The project, as built by Butler, has no value to Kyler. The project failed final inspection for violation of the 25 foot setback and failure to obtain an electrical permit. The roof tiles on the boat house had to be removed because they were falling off the roof. The project itself is coming apart. It will cost between $10,000 and $12,000 to bring the project into compliance with local code requirements and to make it usable. Respondent was aware of the 25 foot setback when he pulled the permit for the project. The project plans submitted for the permit reflect the 25 foot setback. Lake County allows contractors to withdraw permits that have already been pulled. Respondent never withdrew the permit for the project. Butler was unable to obtain a final inspection because he failed to file a Notice Of Commencement at the outset of the project. Pyke and Kyler filed the Notice Of Commencement in order to obtain the final inspection. As the contractor of record, it was Respondent's responsibility to ensure that a Notice of Commencement was filed and that the project passed final inspection. While obtaining the information necessary to file the Notice Of Commencement, Pyke and Kyler learned that Butler was unlicensed and uninsured and that Respondent had used his license to pull the permit. When confronted by Pyke, Respondent did not deny knowledge of the project and assured Pyke that the problems with the project would be corrected. Despite Respondent's assurances, the code violations have not been corrected. Nor have the defects in construction been corrected.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating: Sections 489.129(1)(c) and 455.227(1)(a); and Sections 489.129(1) (e), (f), (n), and (p). It is further recommended that the Board place Respondent on probation for three years, subject to reasonable conditions, impose an administrative fine of $5,000, and assess costs of $717.50 plus reasonable costs incurred by Petitioner subsequent to the date of this Recommended Order to investigate and prosecute this proceeding to its conclusion. RECOMMENDED this 28th day of March, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March 1996.

Florida Laws (3) 17.001455.227489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MORRIS MARDER, 82-002860 (1982)
Division of Administrative Hearings, Florida Number: 82-002860 Latest Update: Jan. 31, 1984

Findings Of Fact At all material times, the Respondent Morris Marder was a registered building contractor, having been issued license number RB 0004509. On March 4, 1980, the Respondent Marder contracted with Erwin and Joan Ravich to convert the garage of the Ravich home into a family room. The March 4, 1980 contract between the Raviches and Marder, who was also doing business as "Home Remodeler Morris Marder", 1/ was signed by the Raviches and accepted by M. Marder. An undated addendum to the contract, which was prepared by the Raviches' attorney, was signed by the Raviches and Dan Rossman, a salesman and contract estimator for the Respondent Marder. However, no evidence was presented that the Respondent Marder had knowledge of or signed the addendum, which required completion of the project by an unspecified date. The execution of the addendum delayed beginning construction on the project until May of 1980. The Respondent Marder subcontracted the performance of work on the Ravich job to Ken Nieset, who with his brother, Steve, a licensed general contractor, was doing business as Brothers Two Construction. During the course of the project, Nieset received three of the four payments made under the contract directly from the Raviches. Although Nieset worked for the Respondent previously, he was neither Marder's foreman nor employee. When additional subcontractors were required, they were hired for the Ravich job by Nieset. The Raviches paid a total of $9,190 under the contract. The first payment of $1,190 was made directly to Home Remodeler on May 3, 1980, the approximate date that work on the project actually began. A partial release of lien was furnished by Morris Marder to Erwin Ravich on May 6, 1980 based on the first payment. The second payment was made by Erwin Ravich on June 20, 1980 for $2,500. This check was made payable to Ken Nieset per authorization of lien furnished on June 20, 1980, in connection with the second payment. 2/ On June 27, 1980 and July 11, 1980, checks were issued to Ken Nieset by the Raviches for $3,500 and $2,000, respectively. The Raviches' received a release of lien for $2,000 from Nieset, but did not obtain a release of lien for the $3,500 payment. The release of lien for the $2,000 payment executed by Nieset did not involve Home Remodeler or the Respondent Marder. After receiving payments totaling $5,500 directly from the Raviches, Nieset abandoned the project. During the course of the Ravich job, the Respondent Marder employed Jorge Gamez, a draftsman/supervisor, who he believed was supervising the Ravich job. However, Gamez' involvement with the job was limited to drawing the plans and did not include supervising construction, since he was not a licensed general contractor. King Cole Plumbing, a state licensed contractor, subcontracted with Nieset to install the plumbing and septic tank at the job site. When King Cole left the job, the rough plumbing was installed and all that remained on the job was interior finishing. The septic tank with an appropriate cover was in place and all work performed by King Cole had passed inspection. The septic tank cover originally agreed to by the parties was required to be changed to a heavier type when the Raviches altered their plans and decided to continue using their driveway. This change resulted in a $512 charge from Sun Gold Industries, who supplied the new cover. Additionally, the original contract was modified to add higher grade plumbing fixtures, lighting fixtures, and tile. In August, 1980, the Respondent Marder entered Saint Frances Hospital for treatment of phlebitis. At the same time, Rossman, Marder's employee, left for vacation in California for seven to eight weeks. As a consequence, the Ravich job was delayed and an unauthorized payment of $2,500 to Nieset was made without securing the approval of the Respondent Marder or Rossman. The Respondent Marder calculated that approximately $2,000 was due as the balance of the job and an added $1,500 was due for extras to the contract. Faced with a substantial loss, the Respondent Marder contacted the Raviches and their attorney in August, 1980, and offered to finish the job and pay for the specified extras in return for Ravich placing $4,500 in escrow with his attorney. Ravich's attorney declined the Respondent's offer and ordered him off the job site. Subsequently, Dade County cancelled the Respondent's building permits, which effectively prohibited him from completing the work at the site. Subsequently, a lien was filed against the Ravich job by King Cole Plumbing for nonpayment of monies due from Ken Nieset. The lien was determined to have been filed in violation of Florida's Mechanics Lien Law and was voluntarily removed. The work performed by the Respondent and his subcontractors prior to being ordered off the job was satisfactory and passed periodic inspection by the Dade County Building Department. The charges in this administrative proceeding formed the basis of action taken against the Respondent by the Dade County Division of Construction Trades Qualifying Board on September 11, 1981, which resulted in revocation of the Respondent's certificate as a subgeneral building contractor in Dade County. The Respondent Marder has been in the construction business since 1954 and licensed as a general contractor in Florida since 1968. Other than the instant case, the Respondent has never been forced off a job. He has been in business in South Florida for many years and has been involved in thousands of construction jobs.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Petitioner Construction Industry Licensing Board enter a Final Order suspending the Respondent's license for a period of six (6) months. DONE and ENTERED this 27th day of September, 1983, in Tallahassee, Florida. SHARYN L. SMITH Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of September, 1983.

Florida Laws (3) 120.57489.119489.129
# 6
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs LEROY JONES, JR., 05-001496PL (2005)
Division of Administrative Hearings, Florida Filed:Miami, Florida Apr. 22, 2005 Number: 05-001496PL Latest Update: Dec. 13, 2005

The Issue Whether Respondent, a licensed general contractor, committed the violations alleged in the three-count Administrative Complaint filed by Petitioner and the penalties, if any, that should be imposed.

Findings Of Fact Respondent is the agency of the State of Florida with the responsibility to regulate building contracting. At all times relevant to this proceeding, Respondent has been licensed as a certified general contractor, having been issued license number CG C058340 in 1996. At all times relevant to this proceeding, Ms. McKinney owned and resided in a house (the House) in Opa Locka, Florida. Ms. McKinney’s mother, Mattie P. Mathis, also lived in the House. In 2001, Ms. McKinney solicited bids for an addition she wanted to put on the House. Ms. McKinney and her mother, Ms. Mathis, planned to pay for the addition with life insurance proceeds on the life of Ms. Mathis’s deceased daughter (Ms. McKinney’s sister). On the recommendation of a colleague at her work, Ms. McKinney asked Willie Muse, Jr., to bid on the work. Based on the bids she received, Ms. McKinney hired Mr. Muse to construct the addition to the House. Ms. McKinney told Mr. Muse that she wanted all work to comply with all applicable permitting requirements and laws. Mr. Muse represented to Ms. McKinney that he would get the necessary building permits and that the work would comply with all applicable laws. On July 18, 2001, Ms. McKinney and Ms. Mathis entered into a written contract with Mr. Muse whereby Mr. Muse agreed to construct the addition for the sum of $45,000.00. Mr. Muse has never been licensed as a general contractor in Florida. Ms. McKinney thought Mr. Muse was a licensed contractor and would not have entered into a contract with him if she had known that he was not licensed. Pursuant to the contract, Ms. McKinney and Ms. Mathis paid Mr. Muse the following amounts on the following dates: $6,000.00 on July 20, 2001; $7,500.00 on October 10, 2001; and $13,500.00 on November 2, 2001; for a total of $27,000.00. On or about August 21, 2001, Mr. Muse brought to Ms. McKinney a building permit application form for her to sign. The application form had been filled out before Mr. Muse presented it to Ms. McKinney. Respondent was not present when Mr. Muse presented the form to Ms. McKinney. Respondent’s name, signature, and contractor’s license number appeared on the application form when Mr. Muse presented the form to Ms. McKinney. Ms. McKinney signed the form on August 21, 2001. Ms. McKinney saw Respondent’s name for the first time when she read the building permit application form. Prior to that time, Ms. McKinney and Ms. Mathis had never known or heard of Respondent. At all times relevant to this proceeding, Respondent knew that Mr. Muse was not a licensed contractor. Mr. Muse submitted the building permit application form to the Miami-Dade County Building Department (Building Department), which issued a building permit for the work on the House on October 5, 2001. Mr. Muse commenced working on the House in October 2001, but he never finished. After he received the payment in November 2001, Mr. Muse stopped working on the House for an extended period of time. During that time, Ms. McKinney attempted on several occasions to persuade Mr. Muse to resume work on the House. Prior to stopping work on the House, Mr. Muse removed a portion of the roof of the existing structure, which exposed the interior of the House to the elements. That exposure resulted in extensive damages to the House, including the collapse of the kitchen ceiling from water intrusion. By letter dated April 15, 2002, the Building Department advised Ms. McKinney that her building permit would expire in approximately 30 days. That letter prompted Ms. McKinney to contact the Building Department, where she was told that Respondent was her contractor, not Mr. Muse. Ms. McKinney secured information (from the face of the building permit) that enabled her to contact Respondent’s mother.3 That contact resulted in two meetings between Ms. McKinney and Respondent towards the end of April 2002. During the first meeting, Ms. McKinney related to Respondent the history of the project, including the amounts that had been paid to Mr. Muse. She also showed him the work that had been done and the damages that had occurred. During the second meeting, Mr. Muse was in attendance. Ms. McKinney, Ms. Mathis, and Respondent reached a verbal understanding that was not reduced to writing. They agreed that Respondent would finish the work on the House for the unpaid balance of the contract price $45,000.00 less $27,000.00 paid to Mr. Muse, which equals $18,000.00.4 The parties agreed that Respondent would pay for labor and that Ms. McKinney and Ms. Mathis would pay material suppliers directly and receive credit toward the contract price for such payments. The parties contemplated that Mr. Muse would perform most of the labor because of the monies he had already received. On the basis of the verbal contract, Respondent resumed the work on the House. On June 12, 2002, Respondent presented a draw request for $3,500.00 for electrical, plumbing, and roofing work that had been performed. Ms. Mathis wrote Respondent a check in the amount of $3,500.00 for that work. Ms. McKinney was opposed to paying Respondent the sum of $3,500.00 because she believed he had not completed the work for which he was billing. Ms. Mathis paid that sum despite Ms. McKinney’s opposition. At some undetermined time following June 12, 2002, Ms. McKinney told Respondent that she did not want Mr. Muse working on the House. Respondent then asked to be paid in advance for work to be done on the House because he would have to pay his laborers. Ms. McKinney and Ms. Mathis would not agree to payment in advance. In July 2002, the project was not complete and Respondent’s progress on the work on the House became unsatisfactory to Ms. McKinney. On October 14, 2002, Ms. McKinney filed a complaint against Respondent with Petitioner, claiming, among other things, that Respondent had abandoned the project. Her complaint alleged that work ended on the project in July 2002. At some undetermined time between June and October 2002, Ms. McKinney filed a criminal complaint against Mr. Muse, which resulted in criminal misdemeanor charges being filed against him in Miami-Dade County Court. After she filed the criminal complaint against Mr. Muse, Ms. McKinney told Respondent that she wanted to wait to proceed with the project until she knew what was going to happen with her criminal complaint. In the criminal proceeding, the Court ordered Mr. Muse on April 11, 2003, to pay restitution to Ms. McKinney in the amount of $16,008.04, payable in monthly installments of $300.00. On March 2, 2004, the Court reduced the amount of restitution to $4,000.00, payable in monthly installments of $50.00 beginning April 1, 2004. As of the date of the final hearing in this proceeding, Mr. Muse had paid Ms. McKinney restitution in the total amount of $750.00. As part of the criminal proceeding, Respondent was asked to give his opinion as to the value of the work completed by Mr. Muse and his estimated cost of completing the work. Respondent valued the work completed by Mr. Muse at $14,073.75 (labor and materials). Respondent estimated that it would cost $22,200.00 to complete the project. Both estimates were dated March 23, 2003. On October 1, 2003, Theodore R. Gay, Assistant General Counsel for Petitioner wrote Ms. McKinney the following letter pertaining to the complaint she had filed in October 2002: The Legal Department has evaluated your complaint against the above named contractor [Respondent]. After reviewing the evidence gathered during the investigation of the referenced matter, we have determined that in accordance with the rules and policies of the Construction Industry Licensing Board, this case is appropriately closed with the issuance of a Letter of Caution to the contractor. Because this case has been dismissed without a finding of probable cause, the file will remain confidential and exempt from the public records. On January 6, 2004, Ms. McKinney wrote Mr. Gay a letter that provided, in part, as follows: This letter is a request to re-open the case [against Respondent] because as prior conversation (sic) when I spoke to you in late August 2003 or early September 2003, I informed you that Mr. Jones told me that he would help me as much as possible to complete the construction on my property. Since your letter that stated you didn’t find any error on Mr. Jones’ behalf, I have not heard or seen him since October 2003, nor has any work been performed on my property. . . . Respondent came back to the House after October 2003 and talked to Ms. McKinney about the work. Ms. McKinney told him that she would pay up to a total of $45,000.00 for the work, but that she would not pay above that figure. Because of the estimate Respondent provided in the criminal proceeding dated March 23, 2003, Ms. McKinney believed that Respondent wanted $22,0000.00 to complete the work. However, Respondent never told her that he would not complete the work for a sum equal to $45,000.00 less the sums that had already been paid. Ms. McKinney would not pay Respondent for work until after the work was completed. After Mr. Gay’s letter dismissing the complaint that Ms. McKinney had filed, Respondent did no further work on the House, but he did have further conversations about the project. Ms. McKinney and Respondent could not agree on payment terms for Respondent to complete the project. Ms. McKinney testified that she did not fire Respondent. However, it is clear that she would not let Mr. Muse do further work on her house and she would not pay Respondent until after the work had been done. Ms. McKinney changed the terms of her verbal contract with Respondent by prohibiting Mr. Muse from working on the project. In November 2003, Ms. McKinney and Ms. Mathis had an argument over the money that had been spent on the house. Ms. McKinney talked to Respondent about his helping her obtain a mortgage on the house to pay for the balance of the work on the House. Ms. McKinney told Respondent that she did not want Respondent to ask her mother for any more money. Ms. McKinney told Respondent that she would use him as the contractor to complete the work if she obtained the financing. Ms. McKinney was unable to get the financing due to the condition of the House. The permits obtained by Respondent are still valid. Ms. McKinney has hired various workers on her own in an effort to complete the work on the House. As of the final hearing, the work on the House had not been completed. As of May 19, 2005, Petitioner’s costs of investigation and prosecution of this case, excluding costs associated with attorney time, totaled $920.29.

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order that adopts the Findings of Facts and Conclusions of Law set forth in this Recommended Order. It is further recommended that the Final Order: Find Respondent guilty of the violation alleged in Count I of the Administrative Complaint and impose against him an administrative fine in the amount of $2,500.00; Find Respondent guilty of the violation alleged in Count II of the Administrative Complaint, but impose no additional administrative fine for that violation; Find Respondent not guilty of the violation alleged in Count III of the Administrative Complaint; Order that Respondent be jointly and severally liable to Ms. McKinney and Ms. Mathis with Mr. Muse for restitution in the amount of $4,000.00, minus $750.00 paid by Mr. Muse; and Order Respondent to pay costs of investigation and prosecution of this matter in the amount of $920.29. DONE AND ENTERED this 10th day of August, 2005, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 2005.

Florida Laws (9) 120.569120.5717.00117.002455.227489.1195489.125489.127489.129
# 8

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer