Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
JAMES D. ENGLISH, JR., AND CYPRESS CREEK PARTNERSHIP vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT AND TELEGRAPH CYPRESS WATER MANAGEMENT DISTRICT, 92-006900 (1992)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Nov. 18, 1992 Number: 92-006900 Latest Update: Jul. 10, 1995

The Issue Whether the application of Telegraph Cypress Water Management District to modify an existing surface water management system permit should be granted.

Findings Of Fact The South Florida Water Management District (District) is a public corporation in the State of Florida existing pursuant to Chapter 25270, Laws of Florida, 1949, and operating pursuant to Chapter 373, Florida Statutes, and Chapter 40E, Florida Administrative Code. The District is a multipurpose water management agency with principal offices in West Palm Beach, Florida. Telegraph Cypress Water Management District (TCWMD) is a water control district organized pursuant to Chapter 298, Florida Statutes. Agricultural operations have been conducted within the TCWMD for more than 30 years by the landowner, Babcock Florida Company. The TCWMD is the permittee of record. James D. English, Jr., owns, along with other members of his family, an orange grove and pasture in Lee County, Florida. The English family has owned the property for approximately 120 years. On November 10, 1992, James D. English, Jr., and the Panacea Timber Company filed a petition for formal administrative hearing challenging the District's intent to issue SWM Permit Modification No. 08-00004-S. Cypress Creek Partnership is a Florida General Partnership of which James D. English, Jr., is a principal. The partnership engages in agricultural activities in Lee County, Florida. The Alva Cemetery, Inc., is a Florida not-for-profit corporation which owns and manages a cemetery facility in Lee County Florida. The cemetery has been in active use for approximately 120 years. In recent years, Alva Cemetery has experienced occasions of excess water encroaching onto the cemetery property. On November 12, 1992, Alva Cemetery, Inc., filed a petition for administrative hearing challenging the District's intent to issue SWM Permit Modification No. 08-00004-S. James D. English, Jr., Cypress Creek Partnership and Alva Cemetery, Inc., are herein referred to as Petitioners. The TCWMD and the Petitioner English share a common property boundary. The Alva Cemetery is surrounded by the English property. All lands involved in this matter historically drain towards the Caloosahatchee River. The TCWMD includes approximately 89,120 acres of land located in Charlotte and Lee Counties, Florida. The land uses within the TCWMD include agricultural, cattle, and timber operations. Generally, the fields have been leased to third party farmers who use the field for several years. When the fields are not actively farmed, they are returned to a fallow state and used as pasture land until fertility is restored at which time they are reactivated for farming. Active farms fields are generally surrounded by a perimeter ditch and dike system. Pumps may be used to water and de-water the fields. When the field is returned to a fallow state, the ditch and dike system are not maintained and become less prominent either by action of weather or by intent. Pumps are not present. All of the TCWMD lies generally north to northwest of the property owned by the Petitioners. Surface waters flow onto the Petitioners' lands from the north. The Telegraph-Cypress system is unique and is the largest of its kind in South Florida Water Management District jurisdiction. The TCWMD system includes storage/detention facilities, control structures, pumping stations and an extensive network of internal canals. There are nine separate water management basins within the TCWMD. The Petitioners asserted that the water management basins identified by the District and the TCWMD are incorrect. The greater weight of the evidence establishes that the District's identification and delineation of the nine basins is based on historical hydrologic characteristics of the TCWMD and is a reasonable determination of basin boundaries. The land encompassed by the instant application for permit modification includes three of the nine basins and encompasses approximately 51,400 acres of the TCWMD. Surface water discharge from the relevant farm fields flows via the internal canal network and sheet flow to the three common detention basins: Telegraph Swamp, North Telegraph Swamp ("Telegraph North") and Curry Lake. The Telegraph North basin lies to the north of and discharges into the Telegraph Swamp basin and includes 13,799 acres of which 4,094 acres are farm fields. The drainage into the Curry Lake basin does not impact either the Telegraph North or Telegraph Swamp basins or the Petitioners' properties. The evidence establishes that as to the Telegraph North and Curry Lake drainage basins, the permit modification meets applicable permitting criteria. There is no credible evidence to the contrary. Telegraph Swamp is the largest of the three relevant detention systems. The Telegraph Swamp basin includes a total of 32,707 acres of which 4,381 acres are farm fields. Telegraph Swamp is a 4,390-acre wetland vegetated by cypress trees and sawgrass, with a base of muck soils, humus, topsoil, leaf litter and other organic material. Located at the south end of Telegraph Swamp are surface water management control structures (the Big Island Dike) built in 1975 and permitted in the original 1980 permit. The structures include three broad-crested weirs and one flash-board weir. Telegraph Swamp has been compared to a "sponge" capable of absorbing vast quantities of surface water discharges within the TCWMD before the control structures at the south end of the swamp are over-topped. Water discharged from the control structures flows through canals and creeks to the Caloosahatchee River. During storm events water is discharged over the control structures and into a swamp area south of Big Island Dike. From there, the water flows southerly, into Telegraph Creek, Big Island Canal and Cypress Creek and then into the Caloosahatchee. The Petitioners expressed concern that TCWMD could inappropriately discharge water from the control gates in the Telegraph Swamp weir. Based on evidence admitted at the hearing, the permit modification should include the following special condition: Discharge structures in the Telegraph Swamp basin shall remain fixed so that discharge cannot be made below the control elevations, except that structure gates and weirs may only be removed during emergency conditions upon notification to and consent by the District's Fort Myers Service Center regulatory area manager or designee. The Basis of Review for Surface Water Management Permit Applications within the South Florida Water Management District--September 1989, incorporated into Chapter 40E, Florida Administrative Code, provides the applicable water quantity permitting criteria relevant to this proceeding. The Petitioners assert that the control gates are required to be locked in accordance with Basis of Review section 3.2.4.1.b, which states: Discharge structures shall be fixed so that discharge cannot be made below the control elevation, except that emergency devices may be installed with secure locking devices. Either the District or an acceptable govern- mental agency will keep the keys for any such devices. The Petitioners are correct. The rule requires secure locking devices. Such condition should be added to the permit The keys may remain with the TCWMD as "an acceptable governmental agency." In 1980, the District issued Surface Water Management Permit No. 08- 00004-S for the TCWMD to operate an existing surface water management system for an existing agricultural operation. The 1980 permit specifically authorizes "[o]peration of a water management system serving 89,120 acres of agricultural lands by a vast network of internal drainage and irrigation canals, a major dike, a major canal and 4 water control structures discharging via small tributary creeks and sloughs into the Caloosahatchee River." Although the permit has been subsequently modified, the authorization to operate the system has not been amended. While District enforcement staff have occasionally noted "performance deficiencies" on the TCWMD property, there have been no permit violations by the permittee. Deficiencies which have been called to the TCWMD's attention have been resolved. Special condition number five to the 1980 permit provides that "[d]ischarges of water onto adjacent lands may be continued to the extent that increased problems are not caused by such discharges." The Petitioners assert that the District has failed to acknowledge that water discharged from the Telegraph Cypress system flows into the Cypress Creek canal and has failed to consider the impact on the Cypress Creek receiving body. However in the staff report to the 1980 permit states as follows: The Telegraph Cypress basin has three major drainage outlets. These are Trout Creek on the west, Telegraph Creek in the center and Cypress Creek to the east. There is a fourth outlet in the northeastern corner of the property known as Jack's Branch, however, this outlet is small compared to the three major ones. Much of Telegraph's southeastern area was previously drained by Spanish Creek and County Line Canal. This historical drainage pattern was blocked when a company which is presently known as Golden Grove constructed a dike across their northern boundary. This dike causes increased flow in a westerly direction around the west end of the dike, thence southerly towards Cypress Creek. This increased flow has caused excess water problems to property owners downstream. In addition, the dike has blocked virtually all flow to Spanish Creek. The evidence fails to establish that, as asserted by the Petitioners, the District has failed to acknowledge the discharge of water to Cypress Creek or to consider the condition of the Cypress Creek receiving body. In the instant case, the condition of the Cypress Creek receiving body was not re- addressed because the permit modification being sought will cause no additional adverse impacts on existing conditions. Although not individually numbered and identified in the original 1980 permit, the evidence establishes that in 1980, all of the farm fields which are subject to this permit modification application were in existence. The applicant seeks no new water control structures. Other than that required to reactivate fallow farm fields, there is no new construction proposed in the instant application. The Petitioners assert that the instant permit modification application will result in construction of new farm fields. The evidence is contrary to the assertion. Proposed permit special condition No. 10 states that the permit does not include the construction of any new farm fields. The farm fields covered in the staff report would be permitted for reactivation from a fallow state without further permitting activity in the future, and without individual retention for each farm field. The modifications to the original 1980 permit have increased the total farm land area. There is no evidence that, except as specifically permitted and approved by the District, there has been alteration of historical discharge rates or routes. There has been considerable confusion regarding the permitting status of the operations as farm fields have been reactivated. Such reactivation entails grading and leveling fields, reconstruction of ditches and dikes and installation of pumping equipment. In order to provide for standardization in farm field reactivation, and to better monitor such activities, the District requested that the TCWMD seek to modify the existing permit. On February 8, 1991, the TCWMD submitted an application to modify the existing permit for the purpose of reactivating the existing farm fields located within the Telegraph North, Telegraph Swamp, and Curry Lake drainage basins. The proposed SWM permit modification authorizes the continued use of the previously permitted surface water management system for existing active and fallow farm fields and allows the reactivation of currently fallow farm fields without further permit modification by the District. Proposed SWM permit special condition No. 16 states that the District requires notification in letter form 30 days prior to all farm field reactivation activities. The proposed modification of the permit will provide the District with an enhanced ability to inspect the reactivated farm fields. Inherent in such reactivation is ditching and diking of the fields. Such operations have been authorized since the 1980 permit was issued. The work associated with field reactivation will be conducted in accordance with existing design criteria as set forth in the application. Based on evidence admitted at the hearing, the permit modification should include the following special condition: Ditches and dikes associated with the farm fields encompassed by this authorization shall be constructed/maintained in conformance with the "Typical Field Layout And Detail Sheet," revised 10/12/93. The evidence establishes that the operations of the TCWMD as proposed by the permit modification application are within the authorization of the existing permit as previously modified. Otherwise stated, the award of this modification will have no substantial impact on the operation of the permitted surface water management system. The modification will result in no additional discharge of surface water from the control structures. The District has established water quantity criteria intended to insure that adverse impacts do not occur due to excess discharge. (Based upon the Hearing Officer's ruling on a District's Motion in Limine, water quality issues were not addressed at hearing.) The criteria are set forth at Chapter 40E-4.301, Florida Administrative Code, and in the Basis of Review. In relevant part, the District criteria require an applicant to provide reasonable assurances that the surface water management system provides adequate flood drainage and protection, that the system will not cause adverse water quantity impacts on receiving waters and adjacent lands, and that the system will not cause adverse impacts on surface and groundwater levels and flows. Modification of a permit must not result in additional adverse off-site impacts. In this case, reasonable assurances have been provided that the proposed modification will not exacerbate the historical and current drainage conditions. The permit modification application at issue does not propose to alter the rates or routes of water currently authorized for discharge from Telegraph Swamp. Reactivation of the farm fields will not impact receiving bodies in any manner different from that which presently exists under previous permits. In providing reasonable assurances, the TCWMD analyzed the water storage capacity available in the detention basins, performed flood routing projections and calculated peak discharge rates for the permit area. As required by the district, the TCWMD utilized a standard hypothetical 25-year/3- day storm event in order to determine whether sufficient capacity was available to handle the resulting stormwater. The projections provide reasonable assurances that the common detention areas have the capacity to provide adequate flood drainage and protection and are accepted. Rule 40E-4.091(1)(a), Florida Administrative Code, incorporates by reference a document identified as the "Basis of Review for Surface Water Management Permit Applications within the South Florida Water Management District--September 1989" Section 3.2.1.2.b requires that: the proposed project modification must meet the allowable discharge rate; and the allowable discharge rate for a previously permitted project is that which was set in the previous permit. The TCWMD prepared and submitted discharge calculations establishing that the post-development discharges will not exceed the discharge rate previously accepted by the District. Since 1984, the District has previously accepted a peak allowable discharge rate of 39 cubic feet per second per square mile (csm). The csm figure is based upon the historical TCWMD discharge rate within the Caloosahatchee River basin. As previously stated, reactivation of the farm fields will not impact the receiving bodies in any manner different from that which presently exists under previous permits. The District asserts that the 39csm discharge rate has been "permitted" since the 1984 modification was approved. The Petitioner asserts that the 39csm discharge rate has never been "permitted" by the District. The evidence establishes that since the 1984 application for permit modification, the discharge rate of 39csm has been utilized by TCWMD and has been accepted by the District, but that the actual permits do not specifically identify the discharge rate as 39csm. In projecting discharge rates, the TCWMD used a time of concentration of one hour. The time of concentration (T.O.C.) is the time in which water would move from the farm fields to the control structure in each sub-watershed. Otherwise stated, a projected T.O.C. of one hour means that the storm water would move from the field to the control structure in one hour. The T.O.C. of one hour is a conservative estimate and likely substantially overestimates the speed at which the water will move. The three basin areas contain a total of more than 80 square miles. Water will travel an average distance of two miles from field to detention basin through ditches, swales and existing low areas. Again conservatively, the TCWMD did not include projected travel time through such conveyances, resulting in a longer T.O.C. and resulting in a higher peak discharge rate than is probable. Although there appeared to be some confusion on the part of the District staff as to the application of the T.O.C. by the TCWMD, the TCWMD engineer who performed the calculation testified at hearing and was qualified as an expert witness in civil engineering, hydrology and surface water management. His testimony and projections are reasonable and are credited. Proposed SWM permit modification special condition No. 11 states that farm field discharge shall be directed to and conveyed via existing ditches, wetlands and/or sheetflow areas per existing site conditions. No new outfall ditches are permitted under this modification. Flood routings were calculated assuming all farm fields would be activated simultaneously and pumping the maximum capacity of 390 gallons per minute per acre (the equivalent of 20-21 inches of surface water pumped from each field daily). It is highly unlikely that all farm fields would be active simultaneously or that stormwater would continue to fall with such velocity to permit continued pumping at maximum capacity for an extended period. Even based on the conservative assumptions utilized by the TCWMD engineers, the projected peak discharge rate at the Telegraph Swamp control structure is 37csm to 38.5csm, within the maximum of 39csm previously accepted by the District. The computer modeling performed by the TCWMD engineer in calculating the peak discharge rate is accepted as reasonable. The TCWMD did not include offsite inflow in its analysis of projected capacity or discharge rates. There is anecdotal evidence that on occasion, water may flow into TCWMD from Jack's Branch or from across roadways to the north and west of the TCWMD; however, given the vast storage capacity of the TCWMD detention areas, there is no evidence that the quantity of offsite inflows is of such significance as to render the TCWMD projections unreasonable. As previously stated, the TCWMD calculations are reasonable and are accepted. The evidence establishes that the peak discharge rate resulting from approval of the instant permit modification will not exceed 39csm. The Petitioners offered their own peak discharge rate calculations, based on a "worst possible case scenario." The assumptions on which the Petitioners' projections are based are unreasonable and are rejected. Based on recommendations received at the hearing, the permit modification should include the following special condition: Pumped discharge from farm fields for which pumps are not currently installed shall be limited to 75 gallons per minute per acre of farmed area. Pumps are currently installed in fields number 7, 8, 9, 10, 12, 14, 15, 24 north and south, 28, east half of 34, 64, 67, 68, 69 and 80. The Petitioners assert that the system is currently causing adverse impacts to their properties in the form of flooding. The greater weight of the evidence establishes that the system presently does not cause adverse water quantity impacts on receiving waters and adjacent lands, and does not cause adverse impacts on surface and groundwater levels and flows. The evidence establishes that award of the application for permit modification will not adversely alter the current operations. It is clear that the Petitioners have been impacted by changes in the historical drainage patterns in the area; however, such changes had substantially occurred by 1980 when the original permit was issued. The greater weight of the credited evidence establishes that such impacts are not the result of the activities authorized in the original 1980 permit and in subsequent modifications, but instead are the result of unrelated actions by third parties not involved in this administrative proceeding. There is no credible evidence that the permit modification sought in the instant proceeding will adversely affect the Petitioners. The 1980 permit addresses existing water quantity problems in the area of the TCWMD project. For example, the construction of the Golden Grove Dike resulted in blockage of historical drainage towards Spanish Creek and the diversion of excess waters into Cypress Creek. During the 1980's the District required that culverts be installed in the Golden Grove Dike which eventually restored some surface water flow through the dike construction and on towards the south, although during some storm events water flow continues around the dike and into Cypress Creek. The Petitioners offered anecdotal evidence as to reduced water flows in some local creeks and increased flows thorough Cypress Creek. The Respondent offered evidence indicating that water flow through Cypress Creek may be less than 30 years ago, due to the digging of a canal between Spanish Creek and Cow Slough and the extension of the Clay Gully Canal's diversion of water into Telegraph Swamp. None of the evidence on this point was persuasive, however it is not relevant. Clearly, the instant permit modification application will not adversely affect the existing situation in the receiving bodies. The Petitioners assert that other receiving waterways have become clogged with vegetation, debris or soil, have accordingly reduced capacities, and are unable to accommodate historical discharge levels. Based on the lack of capacity, the Petitioners suggest that waters move towards the eastern portion of Telegraph Swamp and are discharged, flow towards, into and over the banks of Cypress Creek, and flood their properties. The TCWMD conducted a study of backwater profiles based upon credited field data. The study is found to be reasonable and is credited. Based upon the study, approximately 90 per cent of the water discharged from Telegraph Swamp is conveyed to the Caloosahatchee via Big Island Canal, Telegraph Creek and the swamp area south of the control structure. The remaining 10 per cent of the water enters the Bullhead Strand-Lightered Canal-Cypress Creek watercourse. Water flows from Telegraph Swamp into Cypress Creek via Bullhead Strand and the South Lightered Canal, however, the canal has become so restricted by vegetation that it provides little direct water flow between the strand and the creek and is more properly regarded as an area of enhanced sheet flow. The evidence does not establish that the surface water traveling from Bullhead Strand to Cypress Creek is of significance. Coupled with the existence of the Big Island Canal (which connects Telegraph Swamp to Telegraph Creek) it is unlikely that post-development surface water discharged from the Telegraph Swamp into Cypress Creek exceeds pre-development discharges. The Petitioners claim that two culverts in the Big Island canal restrict the flow of water through the canal and result in increased discharge to the east and to Cypress Creek. The greater weight of the evidence establishes that during period of time when the culverts are unable to accommodate water flow, the water travels into a broad flood plain, around the culverts and returns to the Big Island Canal. The evidence establishes that the proposed modification will not result in additional adverse off-site impacts. The adverse conditions affecting Cypress Creek existed at the time of the 1980 permit and are addressed in the staff report to that permit and to subsequent permit modifications. There is no credible evidence that modification of the permit as sought in this case will result in adverse impacts beyond those which have existed at the time of the award of the original permit. The Petitioners assert that the fields included within the permit modification application lack individual retention areas. The lack of individual detention areas is immaterial in this case where sufficient downstream detention capacity is available through the common detention areas. The Petitioners asserts that the Telegraph Swamp is an "above-ground impoundment" and that as such is fails to comply with requirements related to such water storage systems. The Telegraph Swamp is not a typical "above-ground impoundment" as that term is routinely applied by the District. The regulations addressed by the Petitioners clearly state that they are not intended to be inclusive and are intended to provide guidelines and basic performance criteria for commonly encountered south Florida situations. Telegraph Swamp is not a commonly encountered south Florida situation. There is no evidence that the decision not to apply the "above-ground impoundment" regulations to the Telegraph Swamp is unreasonable. The Petitioner suggest that the TCWMD application for permit modification is deficient and fails to provide information in compliance with the Basis of Review. The Basis of Review is directed towards applications for new construction. The District reasonably does not interpret the all elements of the Basis of Review to apply to existing operations. The original staff report for this permit modification application fails to acknowledge that Cypress Creek is a receiving body. However, as stated previously, the 1980 application and subsequent modifications have clearly addressed the fact that Telegraph Swamp waters discharge to Cypress Creek via intervening waterways. The failure to include the reference in the staff report to this application for modification is irrelevant.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the South Florida Water Management District enter a Final Order issuing Surface Water Management Permit Modification No. 08-00004-S including the additional permit conditions set forth herein, to the Telegraph Cypress Water Management District. DONE and RECOMMENDED this 1st day of April, 1994 in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of April, 1994. APPENDIX TO RECOMMENDED ORDER, CASES NO. 92-6900 and 92-6901 To comply with the requirements of Section 120.59(2), Florida Statutes, the following constitute rulings on proposed findings of facts submitted by the parties. Petitioners James D. English and Cypress Creek Partnership The proposed findings of fact submitted by Petitioners James D. English and Cypress Creek Partnership consist of unnumbered paragraphs. Pages forty-five through fifty-nine of the proposed findings of fact submitted by Petitioners James D. English and Cypress Creek Partnership were stricken as set forth in the Order On Motion To Strike issued March 29, 1994. The paragraphs of pages five through forty-four of the proposed findings of fact submitted by Petitioners James D. English and Cypress Creek Partnership have been consecutively numbered and are accepted as modified and incorporated in the Recommended Order except as follows: 1-2. Rejected, argument, not findings of fact. 7-9. Rejected, argument, not findings of fact. The staff report is not dispositive. 10-12. Rejected. The greater weight of the evidence establishes that, although the 39csm figure is not set forth in the permit, as of the 1984 modification, the TCWMD calculations have been based on a peak discharge rate of 39csm and that the District has accepted the calculations previously. The applicable criteria in the instant case require that the allowable discharge rate for a previously permitted project is that which was set in the previous permit. 13. Rejected, recitation of testimony is not finding of fact. 15-16. Rejected, argument, not finding of fact, irrelevant, cumulative. 17-18. Rejected, recitation of testimony is not finding of fact. 19. Rejected, contrary to the greater weight of credible and persuasive evidence which establishes that 39csm has been the peak discharge rate accepted by the District since 1984. The flow rate projected by the TCWMD does not exceed the accepted peak discharge rate. 24. Rejected, recitation of testimony is not finding of fact. 26-28. Rejected, recitation of testimony is not finding of fact. 29-30. Rejected, argument, not finding of fact. Rejected, irrelevant. Rejected, argument, not finding of fact. Rejected, irrelevant. The greater weight of the credible and persuasive evidence establishes that 39csm has been the District's accepted peak discharge rate and that this modification will not result in peak discharge rates in excess of that which has been previously accepted. Rejected, not supported by the greater weight of credible and persuasive evidence. The assumptions underlying the Petitioners' calculation of theoretical maximum discharge are rejected as unreasonable. Rejected, unnecessary. 36-45. Rejected, irrelevant. The anecdotal evidence fails to establish that offsite inflows are of such quantity as to render the TCWMD projections unreasonable. The proposed findings also consist of recitation of testimony or argument and are not findings of fact. 46-52. Rejected, contrary to the greater weight of credible and persuasive evidence. The evidence fails to establishes that the swamp is an "above-ground impoundment" as that term is routinely applied by the District. The proposed findings also consist of recitation of testimony or argument and are not findings of fact. 53-67. Rejected, irrelevant. An applicant for a permit modification is not required to supply every item on the checklist. An application for a modification to an existing permit often need not contain all the items described. 69. Rejected, cumulative. 70-71. Rejected, argument, not finding of fact. 72-81. Rejected, not supported by the greater weight of credible and persuasive evidence which establishes that the identification and delineation of the nine basins is based on historical hydrologic characteristics of the TCWMD and is a reasonable determination of basin boundaries. The proposed findings also consist of recitation of testimony or argument and are not findings of fact. 82. Rejected, subordinate. 83-85. Rejected, irrelevant. The confusion on the part of District staff as to what T.O.C. was utilized by the TCWMD engineer is irrelevant. This proceeding is not a review of preliminary staff activity. The applicant must establish entitlement to the permit at the hearing. 86-87. Rejected, recitation of testimony is not finding of fact. Rejected. The confusion on the part of District staff as to what T.O.C. was utilized by the TCWMD engineer is irrelevant. Rejected, unnecessary. Rejected, recitation of testimony is not finding of fact. 91-94. Rejected, irrelevant, the discharge projections calculated by the TCWMD as explicated at the hearing are credited. In any event, the evidence establishes that this modification will result in no additional discharge of surface water from the control structures. 95-97. Rejected, irrelevant. The evidence establishes that this modification will result in no additional discharge of surface water from the control structures. Petitioner Alva Cemetery Petitioner Alva Cemetery's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 2. Rejected, not supported by the greater weight of credible and persuasive evidence. 4-5. Rejected, irrelevant. Rejected, irrelevant. This is a de novo hearing, not a review of preliminary staff work. The evidence at hearing establishes that the permit modification will not cause additional adverse affect on existing receiving bodies. Rejected, irrelevant. The evidence fails to establish that Hall Creek and Fichter Creek are receiving bodies of such capacity that their omission from staff report is material. Rejected, irrelevant. Rejected, irrelevant. The evidence fails to establish that offsite inflows are of such quantity as to be relevant. 11. Rejected, not supported by the greater weight of credible and persuasive evidence. The Applicant's analysis is credited. As to T.O.C., even the less conservative T.O.C. projections indicate a peak discharge rate within that previously accepted by the District. 12-13. Rejected, irrelevant. Rejected, irrelevant. Such return overflows are unnecessary in this situation where the detention areas have the capacity to provide adequate flood drainage and protection. Rejected, not supported by the greater weight of credible and persuasive evidence. Rejected, not supported by the greater weight of credible and persuasive evidence. 18-20. Rejected, cumulative. 21. Rejected, immaterial. There is no evidence that this permit modification application will cause additional adverse impact on receiving bodies. The failure to address nonexistent impacts is immaterial. Rejected, errors in staff report are irrelevant. The evidence admitted at hearing is accepted as correct. First paragraph is rejected, cumulative. Second paragraph is rejected, not supported by the greater weight of credible and persuasive evidence. Rejected, anecdotal testimony is not supported by the greater weight of credible and persuasive evidence. Rejected. The greater weight of credible and persuasive evidence establishes that all farm fields affected by this permit modification application were in existence by the 1980 permit. Rejected, not supported by the greater weight of credible and persuasive evidence. The assumptions underlying the Petitioners' calculation of theoretical maximum discharge are rejected as unreasonable. Rejected, irrelevant. The greater weight of credible and persuasive evidence fails to establish that the cemetery flooding is related to actions by the TCWMD. Further, the evidence fails to establish that, even if the flooding was related to the TCWMD, the instant permit modification application will cause additional adverse impacts. Respondent Telegraph Cypress Water Management District Respondent Telegraph Cypress Water Management District's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 18. Rejected, subordinate. 19-20. Rejected, not credited and unnecessary. Rejected as to assertion that the 39csm discharge rate was set in the 1984 permit modification, not supported by the evidence. Review of the document admitted into evidence as the 1984 modification fails to reveal that the figure of 39csm is set forth therein. Rejected, cumulative. Rejected, unnecessary. Respondent South Florida Water Management District Respondent South Florida Water Management District's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 30. Rejected as to assertion that the 39csm discharge rate was set in the 1984 permit modification, not supported by the evidence. Review of the document admitted into evidence as the 1984 modification fails to reveal that the figure of 39csm is set forth therein. Pages 17-19 of the Proposed Recommended Order set forth revisions to the staff report which originally form the basis for the preliminary agency action in this matter. As the hearing is a de novo review of this matter, it is unnecessary for this Recommended Order to address the revision of the staff report, which has limited probative value. COPIES FURNISHED: Tilford C. Creel Executive Director South Florida Water Management District Post Office Box 24680 West Palm Beach, Florida 33416 Melville G. Brinson, Esquire 1415 Hendry Street Fort Myers, Florida 33902 Frank A. Pavese, Sr. Esquire 1833 Hendry Street Fort Myers, Florida 33902 Scott Barker, Esquire Post Office Box 159 Fort Myers, Florida 33902 John J. Fumero, Esquire Toni M. Leidy, Esquire South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33416

Florida Laws (7) 120.57120.68373.114373.413373.617380.06403.812 Florida Administrative Code (4) 40E-4.09140E-4.10140E-4.30140E-4.331
# 1
THOMAS HIRT vs SUN EAST DEVELOPMENT COMPANY AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 91-005689 (1991)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Sep. 05, 1991 Number: 91-005689 Latest Update: May 04, 1992

Findings Of Fact Parties Respondent Sun East is a corporation who seeks to create a Planned Unit Development, PUD 89-25, on its property located in Polk County, Florida. Petitioner Hirt owns and resides on property adjacent to the Planned Unit Development. The only geographical boundary between the proposed project and Petitioner's property is Watkins Road. Respondent SWFWMD is the water management district with permitting authority over the 5.36 acres involved in the permit application which is the subject of these proceedings. Jurisdictional Areas of Controversy Respondent Sun East began the application process for a surface water management general construction permit from SWFWMD for Phase I of its proposed development of PUD 89-25 on July 1, 1991. SWFWMD determined the application was complete on July 24, 1991. The permit which was issued the next day authorized Respondent Sun East to perform the work outlined in the permit and shown by the application, approved drawings, plans, and other documents on file with SWFWMD. Petitioner Hirt timely filed a formal administrative complaint in which he disputed the appropriateness of the permit issued. In support of his position, Petitioner identified a number of areas of controversy and alleged that the application and review process was insufficient. Petitioner's allegations in his complaint, which are properly before the Hearing Officer, are as follows: The approved surface water management system will cause surface water runoff from the project to flood Petitioner's property. One potential cause of such anticipated flooding is the lack of proper percolation design in the surface water management storage areas. Contrary to permit representations, the property and the retention pond required by SWFWMD are in the 100 year flood plain. The project is in an environmentally sensitive area. Respondent Sun East has neither complied with all local requirements nor obtained all necessary federal, state, local and special district authorizations prior to the start of any construction authorized by the permit. Site Information The parcel of land on which the project will be located lies partially within the geographical limits of the South Florida Water Management District (SFWMD). The remaining land lies within the boundaries of the Southwest Florida Water Management District. Originally, SFWMD gave Respondent Sun East a permit to construct Phase I of the project, along with conceptual approval for Phase II. The decision by Sun East to file the application for a surface water management general construction permit with SFWMD instead of SWFWMD was based upon advice from personnel at SWFWMD. When it was later determined that SWFWMD would need to review an application for Phase I in order for the project to be properly permitted, SWFWMD acted quickly to reduce any potential delay to the project which could be attributed to its prior incorrect jurisdictional analysis. The agency's efforts were unrelated to any political connections or family relationships the former landowner, Jack Watkins, may have with past or current members of the Florida Legislature or Congress. The grading plan for Phase I of the project coupled with the pre- development and post-development 25 year storm event analysis, assessed drainage concerns associated with Phase I of the PUD. Water flow analysis for the site that considered existing conditions and proposed improvements, demonstrates that the property west of Watkins Road is not part of the surface water management system for this project. The cross drain beneath Watkins Road to the south of the proposed project deals with a different, natural conveyance system to Lake Pierce which is utilized by property owners such as Petitioner Hirt on the east side of the roadway. The proposed surface water management system for Phase I will not affect the drainage conveyance system utilized by property owners on the east side of Watkins Road. The stormwater management collection and conveyance system for Phase I was designed to convey the stormwater runoff from a 25 year 24-hour rainfall event, as required. It was not overdesigned to deal with a more intense, longer rainfall or storm event. Essentially, stormwater treatment and attenuation will be provided by the two proposed detention ponds A & B, as depicted on the site plan. Runoff from the first inch of rainfall will be filtered through a proposed side berm filter system in Pond A. The Polk County Soil Survey and field observations were used to assist in the weir control structure design. The weir was designed to restrict the post-development 25 year discharge to the pre-developed 25 year runoff rate. The project does not rely on percolation to offset post-development changes in the surface water management system design. As a result, percolation rates are not a factor to be dealt with in a design review. Flood Plain The 100 year elevation of 79 feet above mean sea level delineates the 100 year flood plain on the property in Phase I. According to the contour map, the existing Ponds 1 and 2 have depression contours below the flood plain. The water level in Existing Pond 1 is 78.24 feet. The water level in Existing Pond 2 is 78.14 feet. These ponds are not a major or significant part of an existing, natural surface water storage system in the area. They are just minor surface depressions. None of the lots contained in Phase I encroach upon the 100 year flood plain level. Environmental Concerns The parties stipulated at hearing that SWFWMD rule criteria relating to wetland and natural resource impacts were met by Sun East's general surface water management permit application. Local Requirements Prior to making application to SWFWMD for a permit in this case, Respondent Sun East obtained approval for Phase I of PUD 89-25 from Polk County. Since that time, the zoning approval was quashed by the circuit court. Respondent Sun East was ordered to obtain the SWFWMD permit before reapplying for zoning approval. The limiting conditions which are part of the permit issued by SWFWMD state: The permittee shall comply with all applicable local subdivision regulations and other local requirements. In addition the permittee shall obtain all necessary Federal, State, local and special district authorizations prior to the start of any construction or alteration of works authorized by this permit. The permit limiting conditions do not require that all other permits be acquired prior to the application for this permit. Instead, the limiting conditions advise that all other necessary permits must be acquired prior to construction or alteration of works begun pursuant to this permit. Petitioner began construction authorized by the permit after SWFWMD issued its permit approval on July 25, 1991. The Petitions for Certiorari on the final approval for Phase I from Polk County was already filed when the application for a permit from SWFWMD was requested by Sun East. The completed application does not reflect that the Polk County zoning approval was being challenged, and SWFWMD was not made aware of the possibility that it could be overturned at a later date. The permit issued by SWFWMD was timely challenged by Petitioner, before the approval became final agency action. Sun East did not comply with the limiting condition in the permit that requires a permittee to obtain all necessary authorizations prior to construction as the zoning approval was still unsettled when construction began. Petitioner's challenge to the SWFWMD permit was filed in good faith as numerous disputes of fact existed regarding this permit prior to resolution in this Recommended Order. Based upon the information and documentation given to Petitioner when the permit was issued, it reasonably appeared that his substantial interests were affected by the proposed drainage plan associated with the development.

Recommendation Based upon the foregoing, it is RECOMMENDED: That SWFWMD issue the general construction permit for the surface water management system for Phase I, within the limits indicated in the intent to issue, subject to conditions contained therein. That SWFWMD initiate an inspection of the stormwater management system at its expense to ensure conformity with the approved plans and specifications. That appropriate action be taken under Chapter 373, Florida Statutes, to prevent the continued violation of the limiting condition in the permit relating to construction starts. RECOMMENDED this 24th day of March, 1992, in Tallahassee, Leon County, Florida. VERONICA E. DONNELLY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992. APPENDIX TO RECOMMENDED ORDER, CASE NO. 91-5689 Joint Proposed Findings of Fact filed by Respondents are addressed as follows: Accepted. See HO #3. Accepted. See HO #3. Accepted. See HO #2. Accepted. See HO #4. Accepted. See HO #4. Accepted. Accepted. Accepted. See HO #20. Accepted. Accepted. Accepted. Accepted. See HO #19. Accepted. See HO #19. Rejected. Irrelevant. Rejected. Irrelevant. Rejected. Irrelevant. Rejected. Irrelevant. Accepted. See HO #25. Accepted. Accepted. Accepted. Rejected. Irrelevant Rejected. Contrary to fact. See HO #28. COPIES FURNISHED: ROBERT PERSANTE ESQ MERKLE & MAGRI 7650 W COURTNEY CAMPBELL CAUSEWAY - STE 1120 TAMPA FL 33607 ANDREW R REILLY ESQ REILLY & LASSEIGNE PO BOX 2039 HAINES CITY FL 33845 EDWARD B HELVENSTON ESQ DEPUTY GENERAL COUNSEL SOUTHWEST FL WATER MANAGEMENT DISTRICT 2379 BROAD ST BROOKSVILLE FL 34609 6899 PETER G HUBBELL/EXECUTIVE DIRECTOR SOUTHWEST FL WATER MANAGEMENT DISTRICT 2379 BROAD ST BROOKSVILLE FL 34609 6899 CAROL BROWNER/SECRETARY DEPT OF ENVIRONMENTAL REGULATION TWIN TOWERS OFFICE BLDG 2600 BLAIRSTONE RD TALLAHASSEE FL 32399 2400

Florida Laws (4) 120.57373.403373.413373.423 Florida Administrative Code (3) 40D-4.10140D-4.30140D-4.461
# 2
CAPTIVA CIVIC ASSOCIATION, INC., AND SANIBEL CAPTIVA CONSERVATION FOUNDATION vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT AND PLANTATION DEVELOPMENT, LTD, 06-000805 (2006)
Division of Administrative Hearings, Florida Filed:Fort Myers Beach, Florida Jan. 03, 2007 Number: 06-000805 Latest Update: Feb. 14, 2008

The Issue The issue in this case is whether the South Florida Water Management District (SFWMD, or District) should issue a Modification to Environmental Resource Permit (ERP) No. 36-00583- S-02, Application No. 050408-15 to Plantation Development, Ltd. (PDL), for construction and operation of a surface water management system serving a 78.11-acre condominium development known as Harbour Pointe at South Seas Resort, with discharge into wetlands adjacent to Pine Island Sound.

Findings Of Fact Based on the evidence and arguments, the following facts are found: The Parties PDL, the applicant, is a limited partnership which is the successor to Mariner Group, Inc. (Mariner). SFWMD has jurisdiction over PDL's application, as amended, and has given notice of its intent to grant PDL's application, as amended, with certain conditions. Petitioners, CCA and SCCF, and Intervenor, CSWF, are Florida not-for-profit corporations that challenged the proposed ERP. Development and Permit History The property subject to PDL's application was part of approximately 310-acres on the northern end of Captiva Island in Lee County, Florida. Redfish Pass is to the immediate north, separating Captiva Island from North Captiva Island. Farther to the north is Cayo Costa Island, a large island to the south of Boca Grande Pass. Most of Cayo Costa is a State Park. To the south of Captiva Island is Sanibel Island, the site of the Ding Darling National Wildlife Refuge. To the northeast of Sanibel Island and to the east of the rest of the string of barrier islands just mentioned is Pine Island Sound, which is to the west of Pine Island. Pine Island Sound is a state-designated Aquatic Preserve and Outstanding Florida Water (OFW). Pine Island Sound also is state-designated Class II water, but shell-fishing is prohibited in the immediate vicinity of Captiva Island. To the east of Pineland Island is Little Pine Island, which is surrounded by the Matlacha Pass Aquatic Preserve, which includes the Matlacha Pass National Wildlife Refuge. All of these features are part of the Charlotte Harbor National Estuary (CHNE). San Carlos Bay is farther south. The Lee County mainland is to the east of Matlacha Pass and San Carlos Bay. The 310-acre site was purchased by Mariner in 1972 for development of a resort that became known as the “South Seas Plantation.” Mariner's property included both Captiva Island proper and a smaller island immediately to the east across Bryant Bayou to the north and Chadwick Bayou farther to the south. Bryant Bayou has a narrower inlet from the north, and Chadwick Bayou has a narrower inlet to the south. Both inlets lead to Pine Island Sound. When Mariner purchased the property, it theoretically was possible to develop a maximum of 3,900 dwelling units on the 310-acre property, pursuant to Lee County zoning. In 1973, Mariner submitted an application to Lee County for the right to develop of 912 dwelling units on its 310 acres. PDL characterizes this as a "voluntary down-zoning" for the purpose of protecting the environment and unusual for a developer to do at that point in time. However, it is speculative how much more than 912 dwelling units would have been approved by Lee County at the time. The purpose of Mariner’s application to Lee County was to create a resort where recreational, single family, multi- family, and some commercial uses would coexist in a resort setting. The overall development plan was to construct the resort while conserving many of the property’s natural resources, including several miles of mangrove and Gulf of Mexico shoreline. Lee County approved the rezoning and the concept of the South Seas Plantation in 1973. Mariner's development began with Captiva Island proper and included a marina, golf course, and a variety of residential condominiums and single-family home sites. Some of the residential units were sold, and others remained in Mariner's ownership. Mariner marketed the rental of units at South Seas Plantation and served as rental agent for units not owned by Mariner. Development of the marina included dredging, and spoil was deposited on the northern tip of the smaller island, helping to create approximately 1.4 acres of upland there. In the 1950's or 1960's, a natural sand-and-shell berm along the eastern shore of the smaller island was built up and maintained by addition of fill material to create a two-track sand/shell road, which was used for vehicular access to the northern tip via an east-west road that divided the smaller island roughly in half and connected it to Captiva Island proper and the main road at South Seas Plantation. At a later point in time, the east-west portion of the road was paved for better access to a drinking water plant, a wastewater treatment plant, and a helicopter pad used by the Lee County Mosquito Control District. In 1985, Mariner received from SFWMD a “Master Stormwater Permit” for its entire development (the 1985 Permit). At that time, SFWMD did not regulate wetland impacts, only surface water management systems. The Department of Environmental Regulation regulated wetland impacts through its dredge and fill permit program, and there was no evidence relating to any dredge and fill permitting on the property. The 1985 Permit was for surface water management systems for construction in uplands on the property. No surface water management systems were needed or permitted in any wetlands. The 1985 Permit included a surface water management system for an 18-unit hotel on the spoil uplands of the northern tip of the smaller island. Permit drawings showed plans for a golf course on much of the remainder of the smaller island, which consisted mostly of wetlands. Access to the facilities was envisioned to be by water taxi, with emergency access via the utility and sand/shell road. Together, the hotel and golf course was to become a part of the resort known as Harbour Pointe. The 1985 Permit was modified several times in the years since its initial issuance, during which time Chapter 373, Florida Statutes, was amended to give SFWMD authority to regulate activities in waters and wetlands. However, until the pending application, none of the modifications had wetland impacts. In 1998, Mariner negotiated the sale of ten resort properties it owned in Florida, including South Seas Plantation, to Capstar, which later became Meristar S.S. Plantation Co., LLC (Meristar). Meristar was a real estate investment trust which specialized in hotels. Because it was not in the development business, Meristar was not interested in purchasing the as-yet undeveloped Harbour Pointe portion of South Seas Plantation, or Mariner's remaining development rights. As a result, Meristar purchased all the developed land on South Seas Plantation but not the approximately 78 acres of undeveloped land which is the subject of the pending application, or any of Mariner's development rights. Thus, after the sale of South Seas Plantation, Mariner retained its development rights and the 78 acres of undeveloped land, which are the subject of PDL's application. In 2002, Lee County issued an Administrative Interpretation which clarified that those development rights consisted of a maximum of 35 more residential units. Eleven units subsequently were built, leaving a maximum of 24 residential units when PDL filed its application in this case. The 78-acre Harbour Pointe site consists of mangrove wetlands, privately owned submerged lands, the 1.4-acre upland area at the northern tip of Harbour Pointe and another 1.4 acres of upland, which contain a Calusa Indian mound, known as the Chadwick Mound for its location west of Chadwick Bayou. While agreements between Meristar and PDL contemplate that PDL's subsequent development at Harbour Pointe would be marketed as part of the South Seas Resort and share some amenities and services, the parcels which comprise the Harbour Pointe development are the only undeveloped lands PDL owns or controls. PDL has no contractual or other legal right to develop on property owned by Meristar. Because it was modified several times since issuance, the 1985 Permit has not expired. However, Harbour Pointe never was constructed, and that part of the 1985 Permit expired in that Mariner lost its entitlement to proceed with construction. Instead, development of Harbour Pointe would require a permit modification under the new laws and rules, which included the regulation of wetland impacts. The Application and Proposed ERP In October 2003, PDL applied to SFWMD to further modify the 1985 Permit for construction of a water taxi dock for access to Harbour Pointe. After being informed by SFWMD that modifications to the 1985 Permit for development of Harbour Pointe would be reviewed under current laws and regulations, PDL withdrew the application. In April 2005 PDL applied for modification of the 1985 Permit to construct six 9,500 square-foot, four-plex condominium buildings (each two stories over parking, and accommodating units having 3,600-3,800 square feet of air-conditioned living space), a pool and spa, a tennis court, an access road, a filter marsh and surface water management facilities. Additionally, the site plan deleted all boat docks, except for a single water taxi slip and possibly a dock for launching kayaks and canoes and proposed a drawbridge across the inlet to Bryant Bayou to connect the project site to the South Seas Resort and eliminate the need for the emergency access road on the smaller island. This application described a development site of 7.4 acres, which included 4.8 acres of direct impacts to (i.e., destruction and fill of) mangroves and .1 acre of shading impacts from construction of the drawbridge. The proposed mitigation for the mangrove impacts included: restoration (by removal and replanting) of .6 acre of the north-south sand/shell road, with resulting enhancement of the adjacent preserved mangrove wetlands through improved hydrologic connection across the former shell/sand road and improved tidal connection to Pine Island Sound to the east; and preservation of the rest of PDL's property. The preserved areas would include: approximately 36 acres of mangrove wetlands adjacent to and south of the impacted wetlands (included the road to be restored) (Parcel A); 24.5 acres of mangrove wetlands south of the utility road and east of the narrow inlet to Chadwick Bayou (Parcel B); 9.3 acres of mangrove wetlands (7.9 acres) and tropical hardwoods (1.4 acres, which includes the Chadwick Mound), south of the utility road and west of the inlet to Chadwick Bayou, (Parcel C); .9 acre of mangrove wetlands to the west of Parcel C and the South Seas Resort main road (Parcel D); and .8 acre of mangrove wetlands separated from Parcel A by Bryant Bayou and adjacent to the South Seas Resort main road. A monitoring program lasting at least five years was offered to ensure success of the restoration and mitigation proposal. The application itself incorporated some reduction and elimination of wetland impacts. The total site consists of five separate tax parcels which could be developed into a number of single-family home sites. Such a development plan would have greater direct impacts than the proposed project and would require the shell/sand road to be significantly widened to meet current code requirements. By using the bridge as access, .11 acre of wetlands would be disturbed, as compared to 3.9 acres of total impact that would occur because of the widening the road. This approach results in the entire project causing less wetland impact than would occur from the use of the road alone. After the application was filed, PDL responded to two written requests for additional information and several other questions raised during meetings, phone conversations, and email exchanges with one or more SFWMD staff members. During this process, the application was amended. The tennis court was eliminated, and the filter marsh was replaced by a five dry detention ponds. In addition, the resulting development was concentrated more into the northern tip of the island to reduce and eliminate the greater secondary impacts (from more "edge effect") to the preserved wetlands to be expected from a more linear site plan. These changes reduced the footprint of the proposed project to 5.24 acres, the building size to 6,400 square feet each, the residential unit size to 2,400 to 2,600 square feet each, and wetland impacts to 2.98 acres, plus .11 acre of shading impacts from construction of the drawbridge. In addition, since the project was more concentrated at the northern tip, another tenth of an acre of the sand/shell road was to be restored. A conservation easement was offered for the 73.31 acres to be preserved, including 71.10 acres of wetlands, in Parcels A through E. PDL also offered to purchase .11 credits of offsite mitigation from the Little Pine Island Wetland Mitigation Bank (LPIWMB). On February 2, 2006, SFWMD's staff recommended approval of the amended application with 19 standard general conditions and 30 special conditions. Some of the special conditions in the Staff Report addressed prevention of erosion, shoaling, silt, turbidity, and water quality problems during construction or operation; remediation of any such problems not prevented; and restoration of any temporary wetland impacts. A pre-construction meeting was required to discuss construction methods, including construction dewatering. Although PDL indicated that dewatering would not be necessary for construction of the project, the Staff Report recommended that a dewatering plan be submitted before any dewatering occurred and noted that PDL would have to obtain all necessary Water Use authorizations, unless the work qualified for a No-Notice Short-Term Dewatering permit pursuant to Rule 40E- 20.302(3) or is exempt pursuant to Rule 40E-2.051.1 On February 8, 2006, SFWMD's Governing Board gave notice of its intent to approve the amended application with two additional conditions that were added to the Staff Report: PDL was required to apply for and receive a permit modification for the roadway necessary to access the project (i.e., the road leading from the South Seas Resort main road to the proposed drawbridge), and the applicant for the road to the drawbridge was required to document that proposed construction was consistent with the design of the master surface water management system, including land use and site grading assumptions; and a perpetual maintenance program for restored and preserved areas, including removal of exotic and nuisance vegetation in excess of five percent of total cover between regular maintenance activities, or such vegetation dominating any one section, was required to ensure integrity and viability. The parties interpreted the first of the two additional conditions to mean that construction access to build the project would be via the new roadway and drawbridge. On May 30, 2006, to address certain issues raised by the pending challenge to SFWMD's intended action, PDL further amended the application to substitute two wet retention ponds and three dry retention ponds for the five dry detention ponds and to make associated minor changes to the proposed surface water management system's water quality treatment methods to further reduce water quality impacts from the discharge of the system into the adjacent preserved wetlands. In addition, in view of disagreements among the parties as to the ability of PDL's onsite mitigation proposal to offset wetland impacts, PDL offered to increase offsite mitigation by purchasing as many additional credits from the LPIWMB as necessary to completely offset wetland impacts, as determined by the Uniform Mitigation Assessment Methodology (UMAM). Water Quantity Impacts Pursuant to Rule 40E-4.301(1), an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: will not cause adverse water quantity impacts to receiving waters and adjacent lands; will not cause adverse flooding to on- site or off-site property; will not cause adverse impacts to existing surface water storage and conveyance capabilities. Section 6.0 of the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District (BOR), entitled Water Quantity Criteria, outlines the criteria that the applicant must meet for water quality at the project site. As outlined in BOR Section 6.2, the off-site discharge is limited to rates not causing adverse impacts to existing off- site properties. The proposed surface water management system consists of a series of swales, dry retention, and then a wet retention system with an outfall into the areas to the south. Ordinarily, stormwater runoff eventually will be absorbed into the ground. Any discharge associated with the system, typically only in conjunction with major rain events, will flow into a preserved wetland that will be hydrologically connected to Bryant Bayou and Pine Island Sound. As outlined in BOR Section 6.2, the off-site discharge rate is limited to historic discharge rates. As required by BOR Section 6.3, a storm event of 3-day duration and 25-year return frequency is used in computing off- site discharge rates. As required by BOR Section 6.4, building floors must be at or above the 100-year flood elevations. PDL conducted a hydrologic analysis of the existing condition of the property, analyzed the runoff patterns that would result during the 25-year rainfall event and then compared the development plan hydrologic analysis to the existing condition. The conclusion was that the development plan would not adversely affect offsite area. PDL analyzed a series of storm conditions for the protection of road elevations and the protection of finished floors. There are no off-site areas that contribute to runoff through this piece of property. The proposed system will not cause adverse water quantity impacts to waters and adjacent lands, flooding to onsite or offsite properties, or adversely impact existing surface water storage and conveyance capabilities. Water Quality Impacts Rule 40E-4.301(1)(e) requires an applicant to provide reasonable assurances that the proposed project will not adversely affect the quality of receiving waters so that State water quality standards will not be violated. BOR Section 5.0 is entitled Water Quality Criteria. BOR Section 5.1 states that projects shall be designed and operated so that offsite discharges will meet State water quality standards. BOR Section 5.2.1 requires that either retention or detention, or both retention and detention be provided in the overall system in one of the following three ways or equivalent combinations thereof: Wet detention volume shall be provided for the first inch of runoff from the developed project, or the total runoff of 2.5 inches times the percentage of imperviousness, whichever is greater. Dry detention volume shall be provided equal to 75 percent of the above amounts computed for wet detention. Retention volume shall be provided equal to 50 percent of the above amounts computed for wet detention. Retention volume included in flood protection calculations requires a guarantee of long term operation and maintenance of system bleed-down ability. BOR Section 5.9 states that all new drainage projects will be evaluated based on the ability of the system to prevent degradation of receiving water and the ability to conform to State water quality standards. In the design of the system, PDL proposed a series of best management practices. The first is to treat runoff through grassed swale areas adjacent to buildings and some of the internal roadways. From there, the water would discharge through a series of dry retention areas where there would be further removal and treatment. The water would discharge through a proposed wet retention area prior to outfall under more significant rainfall events, southward into the preserved wetland area. Because of the hydrological connection from there to Bryant Bayou and Pine Island Sound, a more detailed evaluation was conducted. PDL's detailed evaluation included source control measures. The first one is a construction pollution prevention plan. PDL also proposed an urban storm water management plan. PDL is going to provide guidance to property owners about pesticide and fertilizer management control. The Applicant also submitted a street-sweeping proposal. The design of the system incorporates an additional 50 percent water quality treatment volume, over and above the requirements of the BOR. The wet retention system, located to the north of the proposed outfall structure, incorporates submerged aquatic vegetation. That is not a requirement of the District. It is an extra measure that will remove additional levels of pollutants prior to outfall. PDL proposed an urban stormwater management plan. The plan requires annual inspection of the water management facilities, and it must be documented that the system is functioning as originally designed and built. The stormwater management system is capable, based on generally accepted engineering and scientific principles, of functioning as proposed. The stormwater management system satisfies the District's water quality criteria. Petitioners and Intervenor criticized the method used by PDL's water quality consultant, Dr. Harvey Harper, for projecting and evaluating water quality impacts to be expected from PDL's stormwater management design. They contended that the so-called "Harper method" has been criticized by other experts, none of whom testified. Dr. Harper ably defended himself against the criticism leveled at him. He testified that most if not all of the components he has incorporated into his evaluation method are not new but rather have been accepted and used by experts in his field for years. He also explained that he refined his evaluation method in response to some early criticism and that the method he used in this case has been peer-reviewed and accepted by the Department of Environmental Protection for evaluation of stormwater design criteria. While some of the assumptions incorporated in his evaluation method are simple averages of a relatively small samples, and sometimes averages of averages, Dr. Harper was confident in the ability of his method to accurately evaluate the expected water quality impacts from PDL's system. While there is potential for error in any projection, Dr. Harper's evaluation provided reasonable assurances that utilization of PDL's proposed stormwater management and treatment method will not result in violation of any State water quality standards or significantly degrade the water quality of Bryant Bayou or Pine Island Sound. Value of Wetland and Surface Water Functions In general, as part of the CHNE, the mangrove wetlands to be impacted by the proposed ERP are very important. The CHNE Coast Conservation Management Plan identifies three major threats to the estuary and local ecosystem: fish and wildlife habitat loss; water quality degradation; and hydrological alteration. The plan calls for the preservation of mangroves within the CHNE. A wide array of wildlife uses the habitat in the vicinity of the mangrove wetlands to be impacted. The site is in an important coastal fly-way for migratory birds, including numerous species of waterfowl and songbirds that migrate across the Caribbean and Gulf of Mexico to and from South and Central America. The project area also provides habitat for several listed wildlife species, including the American crocodile, wood stork, and West Indian manatee. The mangrove wetlands that will be impacted directly and indirectly by the proposed ERP are in relatively good condition and are very important due primarily to their location near Redfish Pass at the northern end of Captiva Island and to their relationship to the rest of the relatively large area of contiguous and relatively undisturbed wetlands in Parcels A through E. These attributes make them especially important as a nursery ground for several valuable fish species. Existing impacts attributable to the spoil and other disturbances in the adjacent uplands, the northernmost extent of the sand/shell road, and the South Seas Plantation/Resort development to the west across the inlet to Bryant Bayou keep these impacted wetlands from being of the very highest quality. Clearly, and obviously, the project will destroy and fill 2.98 acres of these wetlands. Indirect (secondary) impacts to the adjacent preserved wetlands will result from alteration of hydrology of the 2.98 acres of directly impacted wetlands. Instead of sheet-flowing across the uplands on the northern tip of Harbour Pointe into those wetlands, surface water on the 5.24- acre development project will be directed into a series of swales, to the dry retention ponds, and to the wet retention ponds with an outfall to the adjacent preserved wetlands to the south. Secondary impacts from the Harbour Pointe project will be similar to the existing secondary impacts to the 2.98 acres attributable to the adjacent spoil and the South Seas Plantation/Resort development, if not somewhat greater due to the absence of any buffer like the inlet. On the other hand, PDL's mitigation proposal will restore .7 acre of wetlands where the northern end of the north- south sand/shell road now exists. Eventually, the restored wetland would be expected to become an extension of the existing, adjacent red and basin black mangrove forest. In addition, the resulting improved hydrologic connection to Pine Island Sound will enhance the value of functions in the preserved wetlands, including possibly expanding the existing fish nursery and making it accessible to fish larvae and juvenile fish entering from the east as well as from the west via Bryant Bayou. There was much debate during the hearing as to whether the sand/shell road is natural or man-made and whether it is reducing what otherwise would be the natural tidal and hydrologic connection between the wetlands to the west of the road and Pine Island Sound. As indicated, a prior owner added fill material to the natural sand and shell berm in the 1950's and 1960's to create better vehicular access. See Finding 9, supra. The evidence was reasonably persuasive that those man-made changes have altered hydrology and tidal connection to some extent and that the restoration project will enhance the value and functions of the preserved wetlands to some extent. Impacts to the value of wetland and surface water functions, and corresponding mitigation for impacts, are required to be assessed using UMAM. See Fla. Admin. Code R. 62-345.100. While the mitigation assessment method might be uniform, its application and results are not. Three different experts used UMAM with differing results. SFWMD's expert, Mr. Cronyn, and PDL's consultants, Kevin L. Erwin Consulting Ecologist, Inc. (KLECE), conferred after their initial assessments, resulting in changed results by both (as well as correction of errors in initial scoring by Mr. Cronyn.) Dave Ceilley, an expert for Petitioners and Intervenor, scored the 2.98 acre impact area significantly higher in its current state than the final score of either Mr. Cronyn or KLECE, resulting in a higher functional loss from its destruction and filling. He also gave no credit for restoration of the sand/shell road, in contrast to KLECE and Mr. Cronyn, and scored PDL's mitigation proposal as it affected 36.6 acres of preserved wetlands (essentially, Parcel A) as a functional loss instead of a functional gain, as scored by KLECE and Mr. Cronyn. Mr. Ceilley also scored PDL's mitigation proposal as it affected 24.5 acres of preserved wetlands (Parcel B) as a functional loss instead of a functional gain, as scored by KLECE and Mr. Cronyn. Finally, he gave no credit for preservation of Parcels A through E via a conservation easement because he was under the mistaken impression that the land already was under a conservation easement in favor of Lee County. (Actually, PDL had agreed to preserve 65 acres of mangrove forest in return for the right to develop Harbour Pointe, although a conservation easement actually was imposed on only about six acres. Although not identified, the 65 acres probably would have included the preserved wetlands in the proposed ERP.) Mr. Cronyn gave credit for preservation of Parcels B through E. KLECE did not claim credit, because KLECE did not think it was necessary, but KLECE accepts Mr. Cronyn's assessment of those parcels. Mr. Ceilley's recent onsite field work was extremely limited, and much of his assessment was based general knowledge of the area and dated (14-year old) onsite field work. In addition, this was the first "real-life" UMAM assessment performed by Mr. Ceilley. His only other use of UMAM was for practice in training. Finally, his assessment was entirely independent without the input of any other consultants to aid him. In contrast, both KLECE and Mr. Cronyn had extensive prior experience using UMAM. In addition, KLECE functioned as a three- man team in performing its UMAM assessments and talked out any initial discrepancies and disagreements (albeit with Mr. Erwin being the final arbiter). KLECE and Mr. Cronyn also consulted with one another, as well as experts in other related fields before finalizing their respective UMAM assessments. KLECE was able to draw on field work conducted during over 200 man-hours onsite in recent years. While KLECE was the retained consultant and agent for the applicant in this case, Mr. Ceilley conceded that Mr. Erwin adheres to high ethical standards. Petitioners and Intervenor were critical of credit given in the UMAM assessments performed by Mr. Cronyn for preservation of Parcels B through E. (KLECE did not claim credit for their preservation in its UMAM assessment.) Petitioners and Intervenor contend that PDL already has agreed to preserve the wetlands in those parcels in return for the ability to utilize the remaining 24 residential units of development rights at Harbour Pointe and that development of the Chadwick Mound is unlikely. Actually, as found, PDL's agreement with the County only specified six of the 65 acres of wetlands to be preserved. Besides, the preserved wetlands in the proposed ERP would implement the agreement with the County. As for the Chadwick Mound, preservation without the proposed ERP is not a certainty, although residential development there would be difficult now that its existence is common knowledge. In any event, the relative unlikelihood of development in Parcels A through E, especially after development of 24 units at Harbour Pointe, was taken into consideration by Mr. Cronyn in determining the amount of credit to be given for their preservation. Taking all the evidence into account, Mr. Cronyn's UMAM assessment of the value of wetland functions with and without the proposed ERP are accepted. According to his assessment, the proposed ERP will result in a functional loss of .34 functional units, meaning an equivalent amount of mitigation credit would have to be purchased from the LPIWMB to offset wetland impacts. Based on the functional assessment used to permit that mitigation bank, approximately an additional .9 of a mitigation bank credit would be needed, in addition to the .11 already offered. The evidence as to cumulative impacts did not clearly define the pertinent drainage basin. Logically, the pertinent drainage basin either would encompass all land draining to surface waters connected to Pine Island Sound, which would include Little Pine Island, or would be limited to the land that is subject to the proposed ERP. If the former, all offsetting mitigation would be within the same drainage basin. If the latter, there would be no cumulative impacts, since the proposed ERP would complete all development. Reduction and Elimination of Wetland Impacts According to BOR Section 4.2.1.1, if a proposed surface water management system will result in adverse impacts to wetland or other surface water functions such that it does not meet the requirements of Sections 4.2.2 through 4.2.3.7, the District must consider whether the applicant has implemented practicable design modifications to reduce or eliminate such adverse impacts. The term "modification" does not mean not implementing the system in some form, or requiring a project that is significantly different in type or function, such as a commercial project instead of a residential project. Elimination and reduction also does not require an applicant to suffer extreme and disproportionate hardship--for example, having to construct a ten mile-long bridge to avoid half an acre of wetland impacts. However, Anita Bain, SFWMD's director of ERP regulation, agreed that, in interpreting and applying BOR Section 4.2.1.1, "the more important a wetland is the greater extent you would require elimination and reduction of impact." As reflected in Findings 17-19, supra, PDL explored several design modifications in order to reduce and eliminate impacts to wetland and other surface water functions. However, several options for further reducing and eliminating wetland impacts were declined. PDL declined to eliminate the swimming pool and move one or more buildings to the pool's location at the extreme northern tip of Harbour Pointe because that would not be a practicable means of reducing the Harbour Pointe footprint. First, the undisputed testimony was that a residential building could not be sited as close to the water's edge as a swimming pool could. Second, because it would block the view from some of Meristar's residential properties, and Meristar has the legal right to approve or disapprove PDL's development on Harbour Pointe. PDL declined to reduce the number of buildings because, without also reducing the number and/or size of the residential units, reducing the number of buildings would make it difficult if not impossible to accommodate all cul-de-sacs required by Lee County for use by emergency vehicles and meet parking needs beneath the buildings, as proposed. (In addition, it would reduce the number of prime corner residential units, which are more marketable and profitable.) PDL declined to further reduce unit size because a further reduction to 2,000 square feet would only reduce the footprint of the six proposed buildings by a total of 5,000 square feet--less than a ninth of an acre. Reducing unit size to much less than 2,000 square feet would make it difficult if not impossible to market the condos as "luxury" units, which is what PDL says "the market" is demanding at this time (and also what PDL would prefer, since it would maximize PDL's profits for the units.) But it was not proven that smaller condos could not be sold at a reasonable profit. PDL declined to reduce the number of condo units at Harbour Pointe (while maintaining the conservation easement on the remainder of PDL's acreage, which would not allow PDL to develop all of the 24 dwelling units it wants to develop and is entitled to develop on its 78 acres, according to Lee County). However, it was not proven that such an option for further reducing and eliminating wetland impacts would not be technically feasible, would endanger lives or property, or would not be economically viable. With respect to economic viability, SFWMD generally does not examine financial statements or profit-and-loss pro formas as part of an analysis of a site plan's economic viability. This type of information is rarely provided by an applicant, and SFWMD does not ask for it. As usual, SFWMD's reduction and elimination analysis in this case was conducted without the benefit of such information. Rather, when PDL represented that any reduction in the number of units would not be economically viable, SFWMD accepted the representation, judging that PDL had done enough elimination and reduction based on the amount of wetland impacts compared to the amount of wetlands preserved, in comparison with other projects SFWMD has evaluated. As Ms. Bain understands it, "it's almost like we know it when we see it; in that, you wouldn't ask an applicant to build a ten-mile bridge to avoid a half an acre wetland impact, so something that's so extreme that's obvious, rather than how much profit would a particular applicant make on a particular project." Although SFWMD did not inquire further into the economic viability of modifications to reduce and eliminate wetland and surface water impacts, Petitioners and Intervenor raised the issue and discovered some profit-and-loss pro formas that were presented and addressed during the hearing. A pro forma prepared in August 2003 projected a profit of $2.79 million for the first 8 of 12 units and an additional $1.72 million profit on the next four units (taking into account construction of a drawbridge and road to the west at a cost of $1.8 million). This would result in a total profit of $4.51 million, less $800,000 for a reserve to pay for maintenance of the drawbridge (which PDL said was required under timeshare laws). Another pro forma prepared in February 2004 projected profits of $11.99 million on 16 "big-sized" units (3,000 square feet), $11.81 million on 20 "mid-sized" units (2,200 square feet), and $13.43 million on 24 "mixed-size" units (16 "mid- sized" and 8 "small-sized" at 1,850 square feet), all taking into account the construction of the drawbridge and road at a cost of $1.8 million. After production of the earlier pro formas during discovery in this case, PDL prepared a pro forma on June 7, 2006. The 2006 pro forma projected net profit to be $4.9 million, before investment in the property. However, PFL did not make its investment in the property part of the evidence in the case. In addition, Petitioners and Intervenor questioned the validity of the 2006 pro forma. PDL answered some of the questions better than others. To arrive at the projected net profit, PDL projected significantly (33%) higher construction costs overall. The cost of the drawbridge and road to the west was projected to increase from $1.8 million to $2.5 million. Based on its experience, PDL attributed the increase in part to the effect of rebuilding activity after Hurricane Charlie and in part to the effect of Sanibel Causeway construction (both increased overweight charges and limitations on when construction vehicles could cross the causeway, resulting construction work having to be done at night, at a significantly higher cost). At the hearing, PDL did not present any up-to-date market surveys or other supporting information on construction costs, and the Sanibel Causeway construction is expected to be completed before construction on the Harbour Pointe project would begin. In addition, without a full enough explanation, PDL replaced the bridge operation and maintenance reserve of $800,000 with an unspecified bridge reserve fund of $2 million. On the revenue side of the 2006 pro forma, gross sales of $1.9 million per unit were projected, which is less than PDL was projecting per square foot in February 2004, despite the assumed increased construction costs. PDL also attributes this to the effects of Hurricane Charlie. Again, there were no market surveys or other information to support the pricing assumptions. Besides predicting lower price potential, the 2006 pro forma deducts a pricing contingency of $2.3 million. PDL did not calculate or present evidence on whether it could make a profit building and selling 16 or 20 units, thereby eliminating a building or two (and perhaps some road and stormwater facility requirements) from the project's footprint. The absence of that kind of evidence, combined with the unanswered questions about the 2006 pro forma for the maximum number of units PDL possibly can build, constituted a failure to give reasonable assurance that wetland and surface water impacts would be reduced and eliminated by design modifications to the extent practicable, especially given the very high importance of the wetlands being impacted. Public Interest Test An ERP applicant who proposes to construct a system located in, on, or over wetlands or other surface waters must provide reasonable assurances that the project will “not be contrary to the public interest, or if such an activity significantly degrades or is within an Outstanding Florida Water, that the activity will be clearly in the public interest.” § 373.414(1)(a), Fla. Stat.; Rule 40E-4.302(1)(a); and SFWMD BOR Section 4.2.3. This is known as the “Public Interest Test,” and is determined by balancing seven criteria, which need not be weighted equally. See Lott v. City of Deltona and SJRWMD, DOAH Case Nos. 05-3662 and 05-3664, 2006 Fla. Div. Adm. Hear. LEXIS 106 (DOAH 2006). The Public Interest criteria are as follows: Whether the activity will adversely affect the public health, safety or welfare or the property of others. There are no property owners adjacent to the site, and the closest property owners to the site are located across the inlet which connects Bryant Bayou to Pine Island Sound. While mangrove wetlands generally provide maximum protection from hurricanes, it does not appear from the evidence that existing conditions would provide appreciably more protection that the conditions contemplated by the proposed ERP. Otherwise, the project would not adversely affect the public health, safety or welfare, or property of others. Whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. The proposed ERP would impact (fill and destroy) 2.98 acres of very important, high quality mangrove wetlands. Even with the restoration or creation of .7 acre of probable former wetlands and improvements in the hydrologic connection of the 36.5-acre preserved wetland (Parcel A) to Pine Island Sound, the proposed ERP probably will have a negative effect on the conservation of fish and wildlife, including listed species. However, the negative effect would not be considered "adverse" if the elimination and reduction requirements of BOR 4.2.1.1 are met. Whether the activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling. The proposed drawbridge will be constructed over the inlet connecting Bryant Bayou with Pine Island Sound, a distance of approximately 65 feet. Boaters use the inlet for navigation. However, by its nature, a drawbridge allows for and not adversely affect navigation. The proposed ERP does not contain specifics on operation of the drawbridge, but PDL's consultant, Mr. Erwin, testified that there would be no adverse effect on navigation, assuming that the bridge would remain in the open position between use for crossings by road. The drawbridge would not adversely affect the flow of water or cause harmful erosion or shoaling. Whether the activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity. The question whether the proposed ERP will adversely affect fishing or recreational values is informed by both the UMAM functional assessment and the reduction and elimination analysis. If impacts to wetlands and surface waters are reduced and eliminated, and offset by mitigation, there should be no significant adverse effects on fishing and recreational values. Whether the activity will be of a temporary or permanent nature. The proposed development is permanent in nature. vi. Whether the activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, Florida Statutes. There are no significant archaeological resources on the Harbour Pointe project site. Although shell scatter left by the Calusa Indians has been found on Parcel A, they have been evaluated in the permit application process by Corbett Torrence, an archeologist, and found to be of limited historical or archaeological value. The reduced scope of the project avoids most of these areas. The proposed ERP will, however, enhance significant archaeological resources by placing a conservation easement on Parcel C, which is the site of the Chadwick Mound, one of the largest Calusa Indian mounds in Lee County. Further studies of this site could lead to a much better understanding of the Calusa culture. This Indian mound is a very valuable historical treasure, and its protection through inclusion in a conservation easement is very much in the public interest. vii. The current condition and relative value of functions being performed by areas affected by the proposed activity. This subject also was considered in the reduction and elimination analysis and in the UMAM functional assessment. As in the Findings the current condition and relative value of the functions being performed by the areas affected by the proposed activity are very valuable. That is why the reduction and elimination analysis is particularly important in this case. Assuming appropriate reduction and elimination, mitigation according to the UMAM assessment can offset unavoidable impacts to the functions performed by the areas affected by the proposed activity. Standing of CCA, SCCF, and CSWF CCA, SCCF, and CSWF each has at least 25 current members residing within Lee County and was formed at least one year prior to the date of the filing of PDL's application. CCA's mission statement includes protection of "our residents' safety, the island ecology, and the unique island ambience . . . ." CCA also is dedicated to "preserving and expanding, where possible, the amount of native vegetation on Captive Island" and preservation of natural resources and wildlife habitat on and around Sanibel and Captiva Islands. SCCF's mission is the preservation of natural resources and wildlife habitat on and around Sanibel and Captiva. It manages just over 1,800 acres of preserved lands, including mangrove forest habitat similar to that being proposed for development by PDL. Management activities involve invasive non- native plant control, surface water management, prescribed burning, native plant habitat restoration and wildlife monitoring. CSWF's purpose is to sustain and protect the natural environment of Southwest Florida through policy advocacy, research, land acquisition and other lawful means. Its four core programs are: environmental education; scientific research; wildlife rehabilitation; and environmental policy. Of CCA's 464 members, approximately 115 live within the boundaries of South Seas Plantation/Resort. Approximately 277 of SCCF's 3,156 members live on Captiva Island, and 40 live within the boundaries of South Seas Plantation/Resort. The members of CCA and SCCF who own property on Captiva Island rely on the mangrove systems for protection from storms. A substantial number of the Captiva Island residents and the other members of CCA and SCCF engage in recreational activities in the vicinity of PDL's property, including boating, fishing, bird-watching, wildlife observation, and nature study that would be adversely affected by significant water quality and wetland impacts from the proposed ERP. CSWF has 5,600 family memberships, approximately 400 in Lee County, and 14 on Sanibel. No members live on Captiva Island. There was no evidence as to how many of CSWF's members use the natural resources in the vicinity of the proposed ERP for recreational purposes or otherwise would be affected if there are water quality and wetland impacts from the proposed ERP.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the proposed ERP be denied; however, if wetland and surface water impacts are reduced and eliminated to the extent practicable, the proposed ERP should be issued with the additional conditions, as represented by PDL's witnesses: that the proposed drawbridge be left drawn except when in use for road access; that construction access be via the proposed drawbridge only; and that there be no construction dewatering. DONE AND ENTERED this 8th day of November, 2006, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th of November, 2006.

Florida Laws (8) 120.52120.569120.57267.061373.042373.4136373.414403.412 Florida Administrative Code (7) 40E-2.05140E-4.09140E-4.30140E-4.30262-302.30062-345.10062-4.242
# 3
SOUTH FLORIDA WATER MANAGEMENT DISTRICT, A PUBLIC CORPORATION vs SAMUEL HUBSCHMAN AND CONNIE HUBSCHMAN, AS TRUSTEES; BOB CADENHEAD; AND CADENHEAD & SONS CONSTRUCTION, 89-005737 (1989)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Oct. 23, 1989 Number: 89-005737 Latest Update: Nov. 09, 1990

Findings Of Fact Petitioner SFWMD is a public corporation of Florida. It is charged with the responsibility of issuing permits and enforcing orders relating to surface water management within its jurisdictional boundaries. Respondents Hubschman, as trustees, have full rights of ownership in 1,280 contiguous acres located in Sections 17 and 20, Township 47 South, Range 26 East, Lee County, Florida. These lands are known as Bonita Farms I and II. They are located within the jurisdictional boundaries of SFWMD. In their pre- developed state, these lands could generally be categorized as marsh and wetlands with cypress forest and some uplands in the northern half of the project area. After deciding to develop the acreage for use as pasture and farmland for small vegetable crops, Respondents Hubschman applied for a surface water management permit from SFWMD. The purpose of the permit was to allow the construction and operation of a water management system that would serve both farms. A system was designed to drain water off both parcels through a 62-acre retention area into a natural slough system which runs water into Kehl Canal. In order to create the system, the Respondents Hubschman had the following facilities designed for the site: internal ditches, dikes, pumps, a retention area and control structures. On April 15, 1982, SFWMD issued Surface Water Management Permit No. 36- 00315-S, and Respondents Hubschman were allowed to proceed with their proposed construction plan. A modification to the permit was issued on April 14, 1983. The retention area was enlarged from 62 acres to 88 acres by relocating the perimeter dike. The outfall structure was revised in that the two pumps and the weir were to be replaced by three 18" CMP culverts that would discharge the drained water by gravity flow from the retention area through the slough into Kehl Canal. The duration of the construction phase of its permit was a three-year period, unless the construction of the permitted project discharge structure or equivalent had been completed prior to that date. After the close of the three-year period, there was a dispute between the Respondents and SFWMD as to whether the permit had expired. The controversy was resolved through a compromise agreement. An application for the reissuance of Permit No. 36-00315-S was filed on October 13, 1986. Instead of reissuing Permit No. 36-00315-S, as requested by Respondents Hubschman, SFWMD decided to issue a new permit on May 14, 1987. As part of the processing procedures, SFWMD again reviewed and approved the entire surface water management system designed to serve the 1,280 acres of land proposed by Respondents. Because the additional work proposed for Section 17, the northern section was limited at this stage of development to the selective clearing of additional upland areas to create more improved pasture, the new permit directed attention to Section 20, the southern section of the land. The new permit advised the Respondents that if they wanted to propose additional development to Section 17, they were required to seek a modification of this new permit, Surface Water Management Permit No. 36-00764-S, to include those changes. The Respondents applied for a modification of Permit No. 36-00764-S on July 30, 1987. The proposed modification sought to change the status of the development of Section 17 from improved pasture to small vegetable farmland on 639 acres. The surface water management system plan was modified to drain water in Section 17 to the reservoir on Section 20. The water would be directed via a series of lateral ditches and swales. A six foot high dike and one 27,000 GPM pump were also required. Two additional 18" CMP culverts were required at the discharge facilities to accommodate the increased outflow. The Modification of Permit No. 36-00764-S was approved and issued on June 16, 1988. The original Permit NO. 36-00764-S and its modification are similar to a contract novation because the new permits substituted new obligations between the parties for the old ones under Permit No. 36-00315-S. Based upon this approach to the situation, SFWMD allowed the construction work completed under Permit No. 36-00315-S prior to the Stop Work Order of August 27, 1986, to vest. The completion of the berm around the reservoir in Section 20, as set forth in the letter from Elizabeth D. Ross, attorney for SFWMD, on September 19, 1986, was also allowed to vest. However, if the vested matters were changed in the subsequent permits, they became revisions. The revisions take precedence over the vested matters. Otherwise, completed construction under Permit No. 36- 00764-S as modified, and post Stop Work Order construction remains in effect perpetually for the operation portion of the permit. In order to determine with certainty what was permitted when the Notice of Violation was issued on December 20, 1988, the parties would have to look to the project work actually completed on August 27, 1986, the specific construction approved by SFWMD after that date, the subsequent Surface Water Management Permit No. 36-00764-S issued May 14, 1987, and its Modification issued June 16, 1988. The substantial compliance determination issued by Richard A. Rogers, P.E., Resource Control Department dated September 24, 1987, should also be considered as authorized activity. The Notice of Violation dated December 20, 1988, was issued to Respondent Samuel Hubschman, Trustee. He was advised that recent routine inspections indicate that current on-site activity was in violation of Special Conditions 2,3,4,7,14, 17 & 23 of Permit No. 36-00764-S (issued 5/14/87) and Special Conditions 5,16 & 22 of 36-00315-S (modified 6/16/88). A meeting to resolve these issued was suggested by SFWMD. Respondent Hubschman agreed to attend the meeting through his consultants. Both parties elected to attempt resolution of the Notice of Violation controversy through negotiations in a meeting scheduled for January 5, 1989. To demonstrate their sincerity, the parties agreed not to bring attorneys to the meeting. During the meeting, the parties resolved the controversy by agreeing to the following: SFWMD would no longer consider the project to be in violation of Florida law if the Respondents submitted certain items that would cause SFWMD to issue certain permits and modify others. The Respondents would promptly file an application for a dewatering permit so that the governing board could issue the permit at its March 9, 1989 meeting. The Respondent's contractor would make no field changes in the mitigation or excavation areas without first obtaining appropriate permit modification from SFWMD. Small jockey pumps were to be installed to pump water from the internal water management system into certain cypress and/or mitigation areas for the sole purpose of establishing wetland vegetation within the areas. Respondents were to apply for a modification of Permit No. 36-00764-S, as currently modified, to allow a single phase of mining for the entire affected area. The perimeter dike was to be made structurally adequate. Respondents were to submit an alternative proposal for the disposal of cap rock within ninety days. In the meantime, the contractor could continue to bury the cap rock within the mitigation areas. Both parties demonstrated their reliance on the settlement reached in the meeting by their subsequent actions towards completing and processing the applications for permit modifications and additional permits. Although the noted violations were not cured by these actions, the parties intended to reach a cure or to mitigate for present permit violations through new permit conditions. The preliminary staff review of the Respondents' application for modification of Permit No. 36-00764-S, as currently modified, was completed by March 31, 1989. The following information was requested by SFWMD staff: Revised engineering calculations which reflect that the permitted discharge structure is five 18" CMP culverts. An explanation as to why the 6.3 acre maidencane/juncus marsh designated as a preserve area and the adjacent western preserve area were excavated and otherwise disturbed by project activities. The scrapedown methodology for the replanting of mitigation areas. The Respondents' plans for the area delineated on the plans as pine, which is currently permitted as part of a cypress preservation area. Dike certification and reservoir certification. The above-listed information was required to be returned to the SFWMD within ninety days from the date of the written request. At the close of the ninety days, the information was not received. A second request for a response within thirty days was submitted by SFWMD on August 4, 1989. In September 1989, the Respondents attempted to comply with SFWMD's second request for information. Communications continued in regard to the filed application for modification of Permit No. 36-00764-S, as currently modified, into December 1989. After the thirty days expired for the response to the second request for information dated August 4, 1989, SFWMD filed the Administrative Complaint in these proceedings. After the second request for information, a partial response was received from Respondent Hubschman's consultants. The application continues to go through the review process. It has not yet been deemed complete by SFWMD. As part of the resolution of the Notice of Violation dated December 20, 1988, SFWMD issued permit No. 36-01023-W to Respondent Hubschman for construction dewatering, excavation of an irrigation pond, and water storage at the site. The permit was issued on March 9, 1989. Special condition No. 20 of this permit requires a 200-feet setback from the cypress mitigation area and the irrigation pond being dewatered. The setback is shown on Exhibit 10 of the Bonita Farms Dewatering Application which was made part of the permit. A copy of the permit was attached to the Administrative Complaint. No evidence was submitted by SFWMD regarding alleged violations of Special condition No. 20 which were allegedly observed and documented after the permit was issued, before the filing of the Administrative Complaint Respondent Bob Cadenhead is the contractor hired by Respondents Hubschman to construct the surface water management system. There was no evidence presented to show the connection of another party, Respondent, Cadenhead & Sons Construction, to the project.

Recommendation Based upon the foregoing, it is RECOMMENDED: That Surface Water Management Permit No. 36-00315-S be deemed to have vested as to all construction activity completed under the permit which was not addressed in the subsequent permit issued by SFWMD. The completion of the berm, as set forth in Attorney Ross' September 19, 1986 letter, should also be allowed to vest. That Permit No. 36-00764-S and its later modification be ordered to supercede the prior permit in all matters specifically addressed. That the parties be held to their prior agreements to resolve pending permit violations through the permit modification process. That the alleged dewatering violation in paragraph 19 of the Administrative Complaint be dismissed for lack of evidence. That a specific deadline be set to reasonably complete pending application modifications. That all future enforcement action specifically comply with Rule 40E- 1.612, Florida Administrative Code, and remain separate from any permit or permit modification applications. That the parties create a new, active permit file with current drawings and a specific construction schedule. That the Administrative Complaint and Order filed in these proceedings be dismissed. That future agreements be reduced to writing and signed by the proper parties before they are relied upon by either party. DONE and ENTERED this 9th day of November, 1990, in Tallahassee, Leon County, Florida. VERONICA E. DONNELLY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of November, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 89-5737 Petitioner's Proposed Findings of Fact are addressed as follows: Rejected. Irrelevant. Accepted. See HO number 4. Accepted. See HO number 3. Accepted. Rejected. Improper summary. Accepted. See HO number 6. Rejected. Improper opinion testimony. Rejected. Irrelevant. Argumentative. Rejected. Legal argument. Accepted. See HO number 5. Rejected. Legal argument. Rejected. Contrary to fact. See HO number 15. Rejected. Contrary to fact. See HO number 15. The argument presented in this paragraph is overly punctilious. It ignores the detrimental reliance of opposing parties to the agreement. Rejected. Contrary to fact. See HO number 15 and number 16. Rejected. Legal argument and improper opinion. Rejected. Contrary to fact. See HO number 15 and number 16. Rejected. Matters presented were either not ripe for these proceedings or not proved at hearing. See HO number 16-number 20 and HO number 23. Rejected. Contrary to fact and law. Rejected. Not set forth in pleadings. Irrelevant. Rejected. Not set forth in pleadings. Irrelevant. Rejected. Not set forth in pleadings as separate from the Notice of Violation. Irrelevant. Accepted as fact, resolved by agreement. Rejected. Improper opinion testimony. Rejected. Improper opinion testimony. Rejected. Irrelevant. Rejected. Irrelevant. See HO number 15. Rejected. Irrelevant. See HO number 15. Rejected. Irrelevant. Accepted. Rejected. See HO number 15. Rejected. Cumulative. Rejected. See HO number 11-number 12. Contrary to fact. Accepted. See HO number 9. Accepted. Accepted. See HO number 16-number 20. Rejected. Matter is still pending. See HO number 16-number 20. Rejected. Resolved through agreement. See HO number 15. Rejected. Matter is still pending. See HO number 16- number 20. Rejected. Legal argument. Rejected. Not in pleadings. Irrelevant. Rejected. Irrelevant. Accepted. See HO number 21. Accepted. Accepted. Rejected. Speculative. Respondent's Proposed Findings of Fact are addressed as follows: Accepted. See HO number 13. Rejected. See HO number 23. Contrary to fact and pleadings. Accepted. See HO number 14. Accepted. See HO number 15. Accepted. See HO number 15. Accepted. See HO number 20. Accepted. Rejected. Argumentative. See HO number 20. Accepted. See HO number 4-number 7. Rejected. Contrary to fact. The permit modifica- tion specifically required replacement of a pump with 3 culverts. See HO number 5. Accepted. See HO number 5. Accepted. Rejected. Irrelevant. See HO number 7. Rejected. Irrelevant. See HO number 7. Rejected. Irrelevant. Rejected. Contrary to fact. See HO number 7 and number 11. Rejected. Contrary to fact. See HO number 11. Accepted. Accepted. Rejected. See HO number 15. Additional matters were agreed upon which were not reflected in the letter. This is an incomplete summary. Rejected. Irrelevant. Rejected. Irrelevant to these proceedings. Rejected. Contrary to fact. Accepted. Accepted. Rejected. Contrary to fact. See HO number 8 and number 9. Rejected. See HO number 8 and number 9. Contrary to fact. Accepted. Accepted. Accepted. Rejected. Contrary to fact. Accepted. See HO number 23. Rejected. Contrary to fact. Accepted. COPIES FURNISHED: John J. Fumero, Esquire Office of General Counsel South Florida Water Management District Post Office Box 24680 West Palm Beach, FL 33416-4680 Kenneth G. Oertel, Esquire OERTEL HOFFMAN FERNANDEZ & COLE, P.A. Post Office Box 6507 Tallahassee, FL 32314-6507 Russell Schropp, Esquire HENDERSON FRANKLIN STARNES & HOLT, P.A. 1715 Monroe Street Fort Myers, Florida 33902 John R. Wodraska, Executive Director South Florida Water Management District 3301 Gun Club Road Post Office Box 24680 West Palm Beach, Florida 33416-4680

Florida Laws (4) 120.57373.119373.129373.136 Florida Administrative Code (1) 40E-4.321
# 4
CHARLES AND KIMBERLY JACOBS AND SOLAR SPORTSYSTEMS, INC. vs FAR NIENTE II, LLC, POLO FIELD ONE, LLC, AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 12-001056 (2012)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Mar. 20, 2012 Number: 12-001056 Latest Update: May 22, 2013

The Issue The issue to be determined is whether the applicants, Far Niente Stables II, LLC; Polo Field One, LLC; Stadium North, LLC; and Stadium South, LLC, are entitled to issuance of a permit by the South Florida Water Management District (SFWMD or District) for the modification of a surface-water management system to serve the 24.1-acre World Dressage Complex in Wellington, Florida.

Findings Of Fact The Parties Petitioners Charles Jacobs and Kimberly Jacobs are the owners of a residence at 2730 Polo Island Drive, Unit A-104, Wellington, Florida. The residence is used by the Jacobs on an annual basis, generally between October and Easter, which corresponds to the equestrian show season in Florida. Petitioners maintain their permanent address in Massachusetts. The District is a public corporation, existing by virtue of chapter 25270, Laws of Florida 1949. The District is responsible for administering chapter 373, Florida Statutes, and title 40E, Florida Administrative Code, within its geographic boundaries. The District’s statutory duties include the regulation and management of water resources, including water quality and water supply, and the issuance of environmental resource permits. The Applicants, Far Niente Stables II, LLC; Polo Field One, LLC; Stadium North, LLC; and Stadium South, LLC, are Florida limited-liability companies with business operations in Wellington, Florida. The Applicants are the owners of four parcels of property, parts of which comprise the complete 24.1- acre proposed Complex, and upon which the surface-water management facilities that are the subject of the Permit are to be constructed. Contiguous holdings of the four Applicants in the area consist of approximately 35 additional acres, primarily to the north and west of the Complex. Acme Improvement District The Acme Improvement District was created in the 1950s as a special drainage district. At the time of its creation, the Acme Improvement District encompassed 18,200 acres of land. As a result of additions over the years, the Acme Improvement District currently consists of approximately 20,000 acres of land that constitutes the Village of Wellington, and includes the Complex property. On March 16, 1978, the District issued a Surface Water Management Permit, No. 50-00548-S, for the Acme Improvement District (1978 Acme Permit) that authorized the construction and operation of a surface-water management system, and established design guidelines for subsequent work as development occurred in the Acme Improvement District. The total area covered by the 1978 Acme Permit was divided into basins, with the dividing line being, generally, Pierson Road. Basin A was designed so that its interconnected canals and drainage features would discharge to the north into the C-51 Canal, while Basin B was designed so that its interconnected canals and drainage features would discharge to the south into the C-40 Borrow Canal. Water management activities taking place within the boundaries of the Acme Improvement District are done through modifications to the 1978 Acme Permit. Over the years, there have been literally hundreds of modifications to that permit. The Property The Complex property is in Basin A of the Acme Improvement District, as is the property owned by Petitioners. Prior to January 1978, the property that is proposed for the Complex consisted of farm fields. At some time between January, 1978 and December 18, 1979, a very narrow body of water was dredged from abandoned farm fields to create what has been referred to in the course of this proceeding as “Moose Lake.” During that same period, Polo Island was created, and property to the east and west of Polo Island was filled and graded to create polo fields. Polo Island is surrounded by Moose Lake. When it was created, Polo Island was filled to a higher elevation than the adjacent polo fields to give the residents a view of the polo matches. Petitioners’ residence has a finished floor elevation of 18.38 feet NGVD, which is more than three-quarters of a foot above the 100-year flood elevation of 17.5 feet NGVD established for Basin A. The Complex and Petitioner’s residence both front on Moose Lake. There are no physical barriers that separate that part of the Moose Lake fronting Petitioners’ residence from that part of Moose Lake into which the Complex’s surface-water management system is designed to discharge. Moose Lake discharges into canals that are part of the C-51 Basin drainage system. Discharges occur through an outfall at the south end of Moose Lake that directs water into the C-23 canal, and through an outfall at the east end of Moose Lake that directs water into the C-6 canal. There are no wetlands or surface water bodies located on the Complex property. 2005-2007 Basin Study and 2007 Acme Permit Material changes in the Acme Drainage District since 1978 affected the assumptions upon which the 1978 ACME Permit was issued. The material changes that occurred over the years formed the rationale for a series of detailed basin studies performed from 2005 through 2007. The basin studies, undertaken by the District and the Village of Wellington, analyzed and modeled the areas encompassed by the 1978 Acme Permit in light of existing improvements within the Acme Improvement District. The changes to Basin A and Basin B land uses identified by the basin studies became the new baseline conditions upon which the District and the Village of Wellington established criteria for developing and redeveloping property in the Wellington area, and resulted in the development of updated information and assumptions to be used in the ERP program. On November 15, 2007, as a result of the basin studies, the District accepted the new criteria and issued a modification of the standards established by the 1978 Acme Permit (2007 Acme Permit). For purposes relevant to this proceeding, the 2007 Acme Permit approved the implementation of the new Permit Criteria and Best Management Practices Manual for Works in the Village of Wellington.1/ The language of the 2007 Acme Permit is somewhat ambiguous, and portions could be read in isolation to apply only to land in Basin B of the Acme Improvement District. Mr. Waterhouse testified that the language of the permit tended to focus on Basin B because it contained significant tracts of undeveloped property, the land in Basin A having been essentially built-out. However, he stated that it was the District’s intent that the Permit Criteria and Best Management Practices Manual for Works in the Village of Wellington adopted by the 2007 Acme Permit was to apply to all development and redevelopment in the Acme Improvement District, and that the District had applied the permit in that manner since its issuance. Mr. Waterhouse’s testimony was credible, reflects the District’s intent and application of the permit, and is accepted. The Proposed Complex The Complex is proposed for construction on the two polo fields to the west of Polo Island, and properties immediately adjacent and contiguous thereto.2/ The Complex is designed to consist of a large covered arena; several open-air equestrian arenas; four 96-stall stables, with associated covered manure bins and covered horse washing facilities, located between the stables; an event tent; a raised concrete vendor deck for spectators, exhibitors, and vendors that encircles three or four of the rings; and various paved access roads, parking areas, and support structures. Of the 96 stalls per stable, twenty percent would reasonably be used for storing tack, feed, and similar items. The surface-water management system that is the subject of the application consists of inlets and catch basins, underground drainage structures, dry detention areas, swales for conveying overland flows, and exfiltration trenches for treatment of water prior to its discharge at three outfall points to Moose Lake. The horse-washing facilities are designed to tie into the Village of Wellington’s sanitary sewer system, by-passing the surface water management system. The Permit Application On May 18, 2011, two of the Applicants, Far Niente Stables II, LLC, and Polo Field One, LLC, applied for a modification to the 1978 Acme Improvement District permit to construct a surface-water management system to serve the proposed Complex. At the time of the initial application, the proposed Complex encompassed 20 acres. There were no permitted surface water management facilities within its boundaries. The Complex application included, along with structural elements, the implementation of Best Management Practices (BMPs) for handling manure, horse-wash water, and other equestrian waste on the property. Properties adjacent to the Complex, and under common ownership of one or more of the Applicants, have been routinely used for equestrian events, including temporary support activities for events on the Complex property. For example, properties to the north of the Complex owned by Far Niente Stables II, LLC, and Polo Field One, LLC, have been used for show-jumping events, derby events, and grand prix competitions, as well as parking and warm-up areas for derby events and for dressage events at the Complex. Except for an earthen mound associated with the derby and grand prix field north of the Complex, there has been no development on those adjacent properties, and no requirement for a stormwater management system to serve those properties. Thus, the adjacent properties are not encompassed by the Application. Permit Issuance On November 22, 2011, Permit No. 50-00548-S-203 was issued by the District to Far Niente Stables II, LLC. Polo Field One, LLC, though an applicant, was not identified as a permittee. On January 13, 2012, the District issued a “Correction to Permit No. 50-00548-S-203.” The only change to the Permit issued on November 22, 2011, was the addition of Polo Field One, LLC, as a permittee. On January 25, 2012, the Applicants submitted a request for a letter modification of the Permit to authorize construction of a 1,190-linear foot landscape berm along the eastern property boundary. On February 16, 2012, the District acknowledged the application for the berm modification, and requested additional information regarding an access road and cul-de-sac on the west side of the Complex that extended into property owned by others. On that same date, the Applicants provided additional information, including evidence of ownership, that added Stadium North, LLC and Stadium South, LLC, as permittees. On March 26, 2012, the District issued the proposed modification to Permit No. 50-00548-S-203. On November 15, 2012, the Applicants’ engineer prepared a revised set of plans that added 2.85 acres of property to the Complex. The property, referred to as Basin 5, provided an additional dry detention stormwater storage area. On or shortly after December 3, 2012, the Applicants submitted a final Addendum to Surface Water Management Calculations that accounted for the addition of Basin 5 and other changes to the Permit application that increased the size of the Complex from 20 acres to 24.1 acres. On December 18, 2012, the Applicants submitted final revisions to the BMPs in an Updated BMP Plan. On January 7, 2013, the District issued the final proposed modification to the permit. The modification consisted of the addition of Basin 5, the deletion of a provision of special condition 14 that conflicted with elements of the staff report, the Updated BMP Plan, the recognition of an enforcement proceeding for unauthorized construction of the linear berm and other unauthorized works, and changes to the Permit to conform with additional information submitted by the Applicants. The final permitted surface-water management system consists of inlets and catch basins, underground drainage structures, a 0.64-acre dry detention area, swales for conveying overland flows, and 959-linear feet of exfiltration trench. For purposes of this proceeding, the “Permit” that constitutes the proposed agency action consists of the initial November 22, 2011, Permit; the January 13, 2012, Correction; the March 26, 2012, letter modification; and the January 7, 2013 modification. Post-Permit Activities at the Complex Work began on the Complex on or about November 28, 2011. Work continued until stopped on April 18, 2012, pursuant to a District issued Consent Order and Cease and Desist. As of the date of the final hearing, the majority of the work had been completed. In late August, 2012, the Wellington area was affected by rains associated with Tropical Storm Isaac that exceeded the rainfall totals of a 100-year storm event. Water ponded in places in the Polo Island subdivision. That ponded water was the result of water falling directly on Polo Island, and may have been exacerbated by blockages of Polo Island drainage structures designed to discharge water from Polo Island to Moose Lake. No residences were flooded as a result of the Tropical Storm Isaac rain event. The only flooding issue related to water elevations in Moose Lake was water overflowing the entrance road, which is at a lower elevation. The road remained passable. Road flooding is generally contemplated in the design of stormwater management systems and does not suggest a failure of the applicable system. Permitting Standards Standards applicable to the Permit are contained in Florida Administrative Code Rule 40E-4.301(1)(a)-(k), and in the District’s Basis of Review for Environmental Resource Permit Applications (BOR), which has been adopted by reference in rule 40E-4.091(1)(a). The parties stipulated that the standards in rules 40E-4.301(1)(d),(g) and (h) are not at issue in this proceeding. Permitting Standards - Water Quantity Those provisions of rule 40E-4.301 that remain at issue in this proceeding, and that pertain to water quantity, are as follows: In order to obtain a standard general, individual, or conceptual approval permit under this chapter . . . an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: Will not cause adverse water quantity impacts to receiving waters and adjacent lands; Will not cause adverse flooding to on- site or off-site property; Will not cause adverse impacts to existing surface water storage and conveyance capabilities. In addition to the preceding rules, section 6.6 of the BOR, entitled “Flood Plain Encroachment,” provides that “[n]o net encroachment into the floodplain, between the average wet season water table and that encompassed by the 100-year event, which will adversely affect the existing rights of others, will be allowed.” Section 6.7 of the BOR, entitled “Historic Basin Storage,” provides that “[p]rovision must be made to replace or otherwise mitigate the loss of historic basin storage provided by the project site.” The purpose of a pre-development versus post- development analysis is to ensure that, after development of a parcel of property, the property is capable of holding a volume of stormwater on-site that is the same or greater than that held in its pre-development condition. On-site storage includes surface storage and soil storage. Surface Storage Surface storage is calculated by determining the quantity of water stored on the surface of the site. Mr. Hall found no material errors in the Applicants’ calculations regarding surface storage. His concern was that the permitted surface storage, including the dry detention area added to the plans in December 2012, would not provide compensating water storage to account for the deficiencies he found in the soil storage calculations discussed herein. Based on the foregoing, the Applicants’ surface storage calculations are found to accurately assess the volume of stormwater that can be stored on the property without discharge to Moose Lake. Soil Storage Soil storage is water that is held between soil particles. Soil storage calculations take into consideration the soil type(s) and site-specific soil characteristics, including compaction. Soils on the Complex property consist of depressional soils. Such soils are less capable of storage than are sandier coastal soils. When compacted, the storage capacity of depressional soils is further reduced. The Applicants’ calculations indicated post- development storage on the Complex property to be 25.04 acre/feet. Mr. Hall’s post-development storage calculation of 25.03 acre/feet was substantively identical.3/ Thus, the evidence demonstrates the accuracy of Applicants’ post- development stormwater storage calculations. The Applicants’ calculations showed pre-development combined surface and soil storage capacity on the Property of 24.84 acre/feet. Mr. Hall calculated pre-development combined surface and soil storage, based upon presumed property conditions existing on March 16, 1978, of 35.12 acre/feet. Based on the foregoing, Mr. Hall concluded that the post-development storage capacity of the Complex had a deficit of 10.09 acre/feet of water as compared to the pre-development storage capacity of the Property, which he attributed to a deficiency in soil storage. The gist of Mr. Hall’s disagreement centered on the Applicants’ failure to consider the Complex’s pre-development condition as being farm fields, as they were at the time of issuance of the 1978 Acme Permit, and on the Applicants’ application of the 25-percent compaction rate for soils on the former polo fields. As applied to this case, the pre-development condition of the Complex as polo fields was a reasonable assumption for calculating soil storage, rather than the farm fields that existed in January 1978, and is consistent with the existing land uses identified in the 2005-2007 basin studies and 2007 Acme Permit. Given the use of the Complex property as polo fields, with the attendant filling, grading, rolling, mowing, horse traffic, parking, and other activities that occurred on the property over the years, the conclusion that the soils on the polo fields were compacted, and the application of the 25- percent compaction rate, was a reasonable assumption for calculating soil storage. Applying the Applicants’ assumptions regarding existing land uses for the Complex property, the greater weight of the evidence demonstrates that the proposed surface water management system will provide a total of 25.04-acre feet of combined soil and surface storage compared to pre-development soil and surface storage of 24.84-acre feet. Thus, the proposed Project will result in an increase of soil and surface storage over pre-development conditions, and will not cause or contribute to flooding or other issues related to water quantity.4/ Based on the foregoing, the Applicants have provided reasonable assurances that the proposed surface-water management system will meet standards regarding water quantity established in rule 40E-4.301(1)(a), (b), and (c), and sections 6.6 and 6.7 of the BOR. Permitting Standards - Water Quality Those provisions of rule 40E-4.301 that remain at issue in this proceeding, and that pertain to water quality, are as follows: In order to obtain a standard general, individual, or conceptual approval permit under this chapter . . . an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: * * * Will not adversely affect the quality of receiving waters such that the water quality standards . . . will be violated; Will not cause adverse secondary impacts to the water resources. Section 373.4142, entitled “[w]ater quality within stormwater treatment systems,” provides, in pertinent part, that: State surface water quality standards applicable to waters of the state . . . shall not apply within a stormwater management system which is designed, constructed, operated, and maintained for stormwater treatment Such inapplicability of state water quality standards shall be limited to that part of the stormwater management system located upstream of a manmade water control structure permitted, or approved under a noticed exemption, to retain or detain stormwater runoff in order to provide treatment of the stormwater . . . . Moose Lake is a component of a stormwater-management system that is located upstream of a manmade water control structure. The Permit application did not include a water quality monitoring plan, nor did the Permit require the Applicants to report on the water quality of Moose Lake. During October and November, 2012, Petitioners performed water quality sampling in Moose Lake in accordance with procedures that were sufficient to demonstrate the accuracy of the results. The sampling showed phosphorus levels in Moose Lake of greater than 50 parts per billion (ppb).5/ That figure, though not a numeric standard applicable to surface waters, was determined to be significant by Petitioners because phosphorus may not exceed 50 ppb at the point at which the C-51 Canal discharges from the Acme Improvement District into the Everglades system. Notwithstanding the levels of phosphorus in Moose Lake, Mr. Swakon admitted that “the calculations that are in the application for water quality treatment are, in fact, met. They’ve satisfied the criteria that are in the book.” In response to the question of whether “[t]he water quality requirements in the Basis of Review . . . the half inch or one inch of runoff, the dry versus wet detention . . . complied with those water quality requirements,” he further testified “[i]t did.” Mr. Swakon expressed his belief that, despite Applicants’ compliance with the standards established for water quality treatment, a stricter standard should apply because the pollutant-loading potential of the Complex, particularly phosphorus and nitrogen from animal waste, is significantly different than a standard project, e.g., a parking lot. No authority for requiring such additional non-rule standards was provided. The evidence demonstrates that the Applicants provided reasonable assurances that all applicable stormwater management system standards that pertain to water treatment and water quality were met. Permitting Standards - Design Features and BMPs Provisions of rule 40E-4.301 that remain at issue in this proceeding, and that constitute more general concerns regarding the design of the Complex, are as follows: In order to obtain a standard general, individual, or conceptual approval permit under this chapter . . . an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: * * * Will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed. Petitioners alleged that certain deficiencies in the Complex design and BMPs compromise the ability of the stormwater management system to be operated and function as proposed. Design Features Petitioners expressed concern that the manure bin, though roofed, had walls that did not extend to the roofline, thus allowing rain to enter. Photographs received in evidence suggest that the walls extend to a height of approximately six feet, with an opening of approximately two feet to the roof line. The plan detail sheet shows a roof overhang, though it was not scaled. Regardless, the slab is graded to the center so that it will collect any water that does enter through the openings. Based on the foregoing, the Applicants have provided reasonable assurances that the manure bins are sufficient to prevent uncontrolled releases of animal waste to the stormwater management system or Moose Lake. Petitioners suggested that the horse-washing facilities, which discharge to a sanitary sewer system rather than to the stormwater management facility, are inadequate for the number of horses expected to use the wash facilities. Petitioners opined that the inadequacy of the wash facilities would lead to washing being done outside of the facilities, and to the resulting waste and wash water entering the stormwater management system. Petitioners provided no basis for the supposition other than speculation. Mr. Stone testified that the horse-washing facilities are adequate to handle the horses boarded at the stables and those horses that would reasonably be expected to use the facility during events. His testimony in that regard was credible and is accepted. Based on the foregoing, the Applicants have provided reasonable assurances that the horse-washing facilities are adequate to prevent the release of wash water to the stormwater management system or Moose Lake. Petitioners expressed further concerns that horse washing outside of the horse-washing facilities would be facilitated due to the location of hose bibs along the exterior stable walls. However, Mr. Swakon testified that those concerns would be minimized if the hose bibs could be disabled to prevent the attachment of hoses. The December 2012 Updated BMP Plan requires such disabling, and Mr. Stone testified that the threads have been removed. Based on the foregoing, the Applicants have provided reasonable assurances that the presence of hose bibs on the exterior stable walls will not result in conditions that would allow for the release of wash water to the stormwater management system or Moose Lake. Best Management Practices The Updated BMP Plan for the Complex includes practices that are more advanced than the minimum requirements of the Village of Wellington, and more stringent than BMPs approved for other equestrian facilities in Wellington. Petitioners identified several issues related to the Updated BMP Plan that allegedly compromised the ability of the Complex to meet and maintain standards. Those issues included: the lack of a requirement that the Applicant provide the District with a copy of the contract with a Village of Wellington-approved manure hauler; the failure to require that BMP Officers be independent of the Applicants; the failure to require that the names and telephone numbers of the BMP Officers be listed in the permit; and the failure of the District to require that violations by tenants be reported to the District, rather than being maintained on-site as required. Mr. Stone testified that the BMP conditions included in the Updated BMP Plan were sufficient to assure compliance. His testimony is credited. Based on the foregoing, the Applicants have provided reasonable assurances that the terms and conditions of the Updated BMP Plan are capable of being implemented and enforced. Permitting Standards - Applicant Capabilities Provisions of rule 40E-4.301 that remain at issue in this proceeding, and that are based on the capabilities of the Applicants to implement the Permit, are as follows: In order to obtain a standard general, individual, or conceptual approval permit under this chapter . . . an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: * * * Will be conducted by an entity with the sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued. As the owners of the Complex property, the Applicants have the legal authority to ensure that their tenants, licensees, invitees, and agents exercise their rights to the property in a manner that does not violate applicable laws, rules, and conditions. Regarding the financial capability of the Applicants to ensure the successful and compliant operation of the Complex, Mr. Stone testified that the entity that owns the Applicants, Wellington Equestrian Partners, has considerable financial resources backing the Complex venture. Furthermore, the Applicants own the property on and adjacent to the Complex which is itself valuable. As to the administrative capabilities of the Applicants to ensure that the activities on the site will comply with relevant standards, Mr. Stone testified that an experienced and financially responsible related entity, Equestrian Sport Productions, by agreement with the Applicants, is charged with organizing and operating events at the Complex, and that the Applicants’ BMP Officers have sufficient authority to monitor activities and ensure compliance with the BMPs by tenants and invitees. Mr. Stone’s testimony that the Applicants have the financial and administrative capability to ensure that events and other operations will be conducted in a manner to ensure that the stormwater management system conditions, including BMPs, will be performed was persuasive and is accepted. The fact that the Applicants are financially and administratively backed by related parent and sibling entities does not diminish the reasonable assurances provided by the Applicants that the construction, operation, and maintenance of the Complex will be undertaken in accordance with the Permit. Petitioners assert that many of the events to be held at the Complex are sanctioned by international equestrian organizations, and that their event rules and requirements -- which include restrictions on the ability to remove competition teams from the grounds -- limit the Applicants’ ability to enforce the BMPs. Thus, the Petitioners suggest that reasonable assurances cannot be provided as a result of the restrictions imposed by those sanctioning bodies. The international event rules applicable to horses and riders are not so limiting as to diminish the reasonable assurances that have been provided by the Applicants. Based on the foregoing, the Applicants have provided reasonable assurances that construction and operation of the stormwater management system will be conducted by entities with sufficient financial, legal, and administrative capability to ensure compliance with the terms and conditions of the permit. As a related matter, Petitioners assert the Applicants failed to disclose all of their contiguous land holdings, thus making it impossible for the District to calculate the actual impact of the Complex. Although the application was, for a number of items, an evolving document, the evidence demonstrates that the Applicants advised the District of their complete 59+- acre holdings, and that the Permit was based on a complete disclosure. The circumstances of the disclosure of the Applicant’s property interests in the area adjacent to the Complex was not a violation of applicable standards, and is not a basis for denial of the Complex permit. Permitting Standards - C-51 Basin Rule The final provision of rule 40E-4.301 that is at issue in this proceeding is as follows: In order to obtain a standard general, individual, or conceptual approval permit under this chapter . . . an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: * * * Will comply with any applicable special basin or geographic area criteria established in Chapter 40E-41, F.A.C. Mr. Hall testified the Complex violated permitting standards partly because it failed to comply with the C-51 Basin rule, Florida Administrative Code Rule 40E-041, Part III, pertaining to on-site compensation for reductions in soil storage volume. Mr. Waterhouse testified that the C-51 Basin rule does not apply to the lands encompassed by the Acme Improvement District permits, including the Complex property. The C-51 Basin rule was promulgated in 1987, after the issuance of the original Acme Improvement District permit. The District does not apply new regulatory standards to properties that are the subject of a valid permit or its modifications. Therefore, the area encompassed by the 1978 Acme Permit, and activities permitted in that area as a modification to the 1978 Acme Permit, are not subject to the C-51 rule. The Joint Prehearing Stipulation provides that “Chapter 373, Fla. Stat., Chapter 40E-4, Fla. Admin. Code, and the Basis of Review for Environmental Resource Permit Applications within the South Florida Water Management District (July 4, 2010) are the applicable substantive provisions at issue in this proceeding.” The Stipulation did not identify chapter 40E-41 as being applicable in this proceeding. Given the testimony of Mr. Waterhouse, which correctly applies standards regarding the application of subsequently promulgated rules to existing permits, and the stipulation of the parties, the C-51 Basin rule, Florida Administrative Code Rule 40-E-041, Part III, does not apply to the permit that is the subject of this proceeding. Therefore, the stormwater management system does not violate rule 40E-4.301(1)(k). Consideration of Violations Florida Administrative Code Rule 40E-4.302(2), provides, in pertinent part, that: When determining whether the applicant has provided reasonable assurances that District permitting standards will be met, the District shall take into consideration a permit applicant’s violation of any . . . District rules adopted pursuant to Part IV, Chapter 373, F.S., relating to any other project or activity and efforts taken by the applicant to resolve these violations. . . . Petitioners have identified several violations of District rules on or adjacent to the Complex property during the course of construction, and violations of District rules associated with the Palm Beach International Equestrian Center (PBIEC), the owner of which shares common managers and officers with the Applicants, for consideration in determining whether reasonable assurances have been provided. Violations on or Adjacent to the Complex On March 22, 2012, the District performed an inspection of the Complex property. The inspection revealed that the Applicants had constructed the linear berm along the eastern side of the Property that was the subject of the January 25, 2012, application for modification of the Permit. The construction was performed before a permit modification was issued, and was therefore unauthorized. A Notice of Violation was issued to Far Niente Stables II, LLC, on March 22, 2012, that instructed Far Niente Stables II, LLC, to cease all work on the Complex. Several draft consent orders were provided to Far Niente Stables II, LLC, each of which instructed Far Niente Stables II, LLC, to cease and desist from further construction. Construction was not stopped until April 18, 2012. The matter was settled through the entry of a Consent Order on May 10, 2012 that called for payment of costs and civil penalties. The berm was authorized as part of the March 26, 2012 Complex permit modification. All compliance items were ultimately completed to the satisfaction of the District During inspections of the Complex by the parties to this proceeding, it was discovered that yard drains had been constructed between the stables and connected to the stormwater management system, and that a bathroom/utility room had been constructed at the north end of the horse-washing facility. The structures were not depicted in any plans submitted to the District, and were not authorized by the Permit. The yard drains had the potential to allow for animal waste to enter Moose Lake. The Applicants, under instruction from the District, have capped the yard drains. No other official compliance action has been taken by the District. A permit condition to ensure that the yard drains remain capped is appropriate and warranted. At some time during or before 2010, a mound of fill material was placed on the derby and grand prix field to the north of the Complex to be used as an event obstacle. Although there was a suggestion that a permit should have been obtained prior to the fill being placed, the District has taken no enforcement action regarding the earthen mound. Petitioners noted that the Complex is being operated, despite the fact that no notice of completion has been provided, and no conversion from the construction phase to the operation phase has been performed as required by General Condition Nos. 6 and 7 of the Complex permit. Such operations constitute a violation of the permit and, as such, a violation of District rules. However, the District has taken no official action to prohibit or restrict the operation of the Complex pending completion and certification of the permitted work and conversion of the permit to its operation phase. The construction of the berm, yard drains, and bathroom/utility room, and the operation of the Complex, causes concern regarding the willingness of the Applicants to work within the regulatory parameters designed to ensure protection of Florida’s resources. However, given the scope of the Complex as a whole, and given that the violations were resolved to the satisfaction of the District, the violations, though considered, do not demonstrate a lack of reasonable assurances that District permitting standards will be met. Violations related to the PBIEC At some time prior to February 13, 2008, one or more entities affiliated with Mark Bellissimo assumed control and operation of the PBIEC. When the facility was acquired, the show grounds were in poor condition, there were regulatory violations, it had no BMPs of consequence, there were no covered horse-wash racks, and the wash water was not discharged to a sanitary sewer system. After its acquisition by entities associated with Mr. Bellissimo, the PBIEC was substantially redesigned and rebuilt, and BMPs that met or exceeded the requirements of the Village of Wellington were implemented. The PBIEC currently has 12 arenas that include facilities for show jumping events, and nine horse-wash racks. The PBIEC has the capacity to handle approximately 1,700 horses. On March 14, 2008, the District issued a Notice of Violation to Far Niente Stables V, LLC, related to filling and grading of an existing stormwater management system and lake system at the PBIEC; the failure to maintain erosion and turbidity controls to prevent water quality violations in adjacent waters; the failure to maintain manure and equestrian waste BMPs; and the failure to transfer the PBIEC stormwater management permit to the current owner. On October 9, 2008, Far Niente Stables V, LLC, and the District entered into a Consent Order that resolved the violations at the PBIEC, required that improvements be made, required the implementation of advanced BMPs, and required payment of costs and civil penalties. On January 12, 2011, a notice was issued that identified deficiencies in the engineer’s construction completion certification for the stormwater management system improvements, horse-wash facility connections, and other activities on the PBIEC. Although completion of all items required by the Consent Order took longer -- in some instances significantly longer -- than the time frames set forth in the Consent Order,6/ all compliance items were ultimately completed to the satisfaction of the District. On January 7, 2011, the District issued a Notice of Violation and short-form Consent Order to Far Niente Stables, LLC, which set forth violations that related to the failure to obtain an environmental resource permit related to “Tract D and Equestrian Club Drive Realignment.” The short-form Consent Order was signed by Far Niente Stables, LLC, and the compliance items were ultimately completed to the satisfaction of the District. Based on the foregoing, the violations at the PBIEC, though considered, do not demonstrate a lack of reasonable assurances that District permitting standards will be met for the Complex Permit.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law set forth herein it is RECOMMENDED that the South Florida Water Management District enter a final order: Incorporating the June 29, 2012, Order of Standing and Timeliness; Approving the issuance of Surface Water Management System Permit No. 50-00548-S-203 to Far Niente Stables II, LLC; Polo Field One, LLC; Stadium North, LLC; and Stadium South, LLC.; and Imposing, as an additional condition, a requirement that the unpermitted yard drains constructed between the stables be permanently capped, and the area graded, to prevent the unauthorized introduction of equine waste from the area to the stormwater management system. DONE AND ENTERED this 26th day of April, 2013, in Tallahassee, Leon County, Florida. S E. GARY EARLY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 2013.

Florida Laws (4) 120.569120.57373.413373.4142
# 5
WILLIAM H. AND PATRICIA H. MELLOR, ET AL. vs. COUNTY LINE DRAINAGE DISTRICT AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 83-000082 (1983)
Division of Administrative Hearings, Florida Number: 83-000082 Latest Update: Jun. 21, 1991

Findings Of Fact The CLDD was established pursuant to Chapter 298, Florida Statutes, on August 4, 1967. Its purpose was to "reclaim" or render the land within its boundaries usable for agricultural purposes. The land comprising the CLDD consists of approximately 3,500 acres in Lee County, mostly planted in citrus trees. Pursuant to the requirements of Chapter 298, Florida Statutes, a "Plan of Reclamation" was prepared by consulting engineers for the CLDD's Board of Supervisors in August, 1967. That plan contains provisions for reclaiming lands within the CLDD's boundaries and for managing and controlling surface water within CLDD. The method of water control outlined in the 1967 reclamation plan included a dike and ditch system around the boundaries of CLDD with a series of interior canals to carry excess water away from the citrus trees. The land in the north part of he CLDD is higher than the south and water generally, naturally flows from north to south. The interior canals were designed to carry water in accordance with existing contours of the land and eventually discharge excess surface water to the rim ditches on the north and east sides of Spoil Area "M," which is south of the CLDD and which was then owned by the C&SFFCD, the predecessor agency to SFWMD. The system of drainage delineated in that 1967 plan, inaugurated pursuant to Chapter 298, Florida Statutes, was put into effect substantially as described therein. CLDD's 1967 plan was altered somewhat because of an agreement entered into on September 30, 1971, between the CLDD and neighboring landowner Kenneth Daniels. Pursuant to that agreement, the two parties agreed to extend the dike on the west side of the CLDD property and construct a ditch from a point 50 feet north of the northwest corner of the Petitioner Mellor's property, which new ditch was to run southwest across the Daniels' property and connect with Spanish Creek. That ditch or canal would thus connect the western rim ditch of the SFWMD's Spoil Area "M" with Spanish Creek and have the result that surface waters could be discharged from CLDD lands through the western rim ditch of Spoil Area "M" thence through the "Daniels' Ditch" finally discharging into the lower reaches of Spanish Creek. (see Exhibits 1 and 11) Because the western side or western rim canal of the SFWMD's Spoil Area "M" had not been used under the original plan of reclamation approved by the C&SFFCD, CLDD sought permission from C&SFFCD to use this western rim canal for the purpose stated pursuant to the agreement with Daniels. Thus, CLDD's proposed use of the rim canal of Spoil Area "M" would be confined to the western, northern and eastern perimeter canals and not the southern boundary canal. All affected landowners, Kenneth Daniels as well a Jake and Lilly Lee, agreed to those proposed installations and uses. The resulting agreement between CLDD and C&SFFCD was entered into on October 12, 1972, and describes the flood control District land to be used by CLDD as a 100 foot wide strip running along the west, north and east sides of Spoil Area "M," also know as "Aspic." This 100 foot wide strip of land running thusly is co-extensive with the rim ditch of Spoil Area "M." The CLDD was mandated by this agreement to install 72- inch pipes in the rim ditch at the southwest corner of the spoil area, just north of the Mellor property, giving a point of discharge from the western rim ditch into the Daniels' Ditch with similar pipes connecting that Daniels' Ditch with Spanish Creek, such that the canal between these two points could carry water from the west rim ditch to Spanish Creek. The easement incorporated in this agreement was to last for five years with an option for a five-year renewal, which option was exercised. At the end of this 10-year period, SFWMD, successor to C&SFFCD, notified CLDD that because its statutory authority had since changed, the easement could not be renewed and that CLDD would have to seek the subject permit so as to be authorized to use works and lands of the District. The requirements to be met by an applicant for a right-of-way permit such as this one are set out in Rule 40E-6.301, Florida Administrative Code, and SFWMD's permitting information manual, Vol. V, Criteria Manual for Use of Works of the District, July, 1981, which is incorporated by reference in that rule. In that connection, the permit at issue, if granted, would not cause an interference with the "works" of the District, that is dikes, ditches, flood control structures arid drainage structures because it would merely renew the pre-existing authorized use. The permit will not be inconsistent with an comprehensive water use plan developed by the District. Further, the permit applicant owns or leases the land adjacent to the portion of the "works of the District" involved herein that is the east, north and west rim ditches of Spoil Area "M," the Daniels' Ditch and the pipes at either end of it coupled with the water control structures at the southeast corner and southwest corners of Spoil Area "M," which control water entering the south rim ditch. CLDD has a surface water management permit, issued in August, 1980, which is a prerequisite to the granting of the subject right-of-way permit. It remains in full force and effect. That surface water management permit authorizes "operation of a water management system serving 3,642 acres of agricultural lands by a network of canals and control structures, with a perimeter dike and canal discharging into Cypress Creek." The "surface permit" authorized the system of drainage and discharge in existence at the time of its issuance, May 8, 1980. The system of drainage, at the day of the hearing, consisted of the same basic water flow and discharge pattern that existed for approximately 10 years, and this permit would allow that to be continued, thus, there will not be any additional effect on environmentally sensitive lands occasioned by an issuance of the subject right-of-way permit. The surface water management permit, by its terms, refers initially to the operation of a water management system" . . . discharging into Cypress Creek." The reference to "Cypress Creek" was an administrative error. The express language on the face of the permit authorization incorporates by reference the application, including all plans and specifications attached thereto, as addressed by the staff report, and those materials, including the staff report, are a part of the permit. The complete permit, including all those documents incorporated by reference, makes it clear that the authorization of the surface water management permit was that the system of drainage in existence at the time of permit issuance (1980) was that which was being approved, and that included discharge to Spanish Creek and not Cypress Creek. Discharge of water to Cypress Creek as an alternative was never recommended or authorized by that surface water management permit. This is clearly the intent expressed in the permit in view of the language contained in a special condition of that surface water management permit imposed by the SFWMD as a condition for issuance which stated as follows: Within 45 days of the issuance of this permit the permittee shall submit for staff approval a proposal and schedule for the elimination of the adverse impacts being created by the operation of the permittee's water management system, which can be legally and physically accomplished by the permittee. Adverse impacts are considered herein to be reduced flows to Spanish Creek and increased flows to Cypress Creek. Thus, it is obvious that the authorization of the surface water management permit was designed to provide for discharge into Spanish Creek and to enhance the flows to Spanish Creek pursuant to a required proposal which the permittee submitted to SFWMD. Thus, the right-of-way permit applied for herein is consistent with the valid surface water management permit held by the permit applicant in this proceeding. Petitioners William H. and Patricia H. Mellor are co-owners of parcels of property lying some distance south of Spoil Area "4" in the vicinity of the Caloosahatchee River. This property does not abut the spoil area at any point. Spanish Creek does cross their property several thousand feet south of the south boundary of the spoil area. In the past, particularly in 1982, water flowing from the south rim ditch of the spoil area through a break in the dike of that south rim ditch, has flowed through a ditch known as Dry Creek in a generally southerly direction under S.R. 78 and has washed out an access road constructed by William Mellor which leads from Highway 78 to his property. He had this washout repaired at his own expense in 1982. The washout was caused by water from CLDD flowing into the south rim canal of Spoil Area "M," that is, the ditch that traverses (and defines) the southerly boundary of the spoil area. Mr. Mellor admitted, however, that SFWMD had at least partially plugged the opening in the south rim ditch which had allowed flow down the Dry Creek ditch and wash out his road. If closed water control structures are maintained at the southwest and southeast corners of the spoil area ditches, then no water could flow into the south rim canal and no such injury could again be caused. Petitioner's Jim English and Patricia Mellor are co-owners of a 45- acre parcel of land located in the southwest corner of Spoil Area "M." The five acres forming the extreme southwest corner of the spoil area do not belong to these Petitioners, but are owned by one Lynwood Brown, who is not a party to this proceeding. The English/Mellor property forms a part of the spoil area, but does not adjoin or constitute any part of the spoil area which is sought to be used by CLDD through the proposed right-of-way use permit (as clarified by CLDD's stipulation). The south rim ditch, either part of, or adjoined by their property, has been used for water storage in the past (they maintain illegally) 1/ Mr. Tom Pancoast has observed Spanish Creek frequently over a nine- year period starting in approximately 1973. He has often used those waters during that period for fishing. During the early years of his use and observation of Spanish Creek, the water flowed out of Spanish Creek into the Caloosahatchee River. Beginning in about 1976, the water appeared to be flowing in the opposite direction, from the river into Spanish Creek. Contemporaneous with this hydrologic change, the creek has become increasingly characterized by siltation and hyacinth growth. Mr. William Mellor owns property along the course of Spanish Creek. He has used the stream for recreational purposes, picnicking where the stream traverses his property. In recent years there has occurred a marked increase in the growth or profusion of aquatic plants of unidentified types in the creek, reduced clarity and reduced flows or volumes of water in the creek. Witness English has made a similar observation. Witness James English has a substantial degree of training by formal education and experience in water management and drainage practices and methods, particularly as they relate to citrus grove development and management in southwest Florida. Mr. English has observed Spanish Creek regularly for most of his life, including the region of its headwaters in the "Cow Prairie Cypress," a remnant wetland cypress strand lying within the CLDD immediately north of Soil Area "M." The chief adverse impact of the CLDD water management system is reduced flow to Spanish Creek, especially its upper reaches since the advent of the "Daniels' Ditch" as a drainage route and discharge point into lower Spanish Creek. However, the only special condition on the issuance of the surface water management permit approving CLDD's extant water management system was the requirement that CLDD should submit a plan for eliminating that adverse effect, which it did (as Petitioner English admits). Beyond the submission of such a plan, no concrete action designed to restore historic flows to Spanish Creek has yet begun, however. The restoration of historic flows, adequate in volume and quality, to the entire creek system would require discharging water from CLDD's system to the Cow Prairie Cypress area at the headwaters of the creek rather than substantially further downstream at the present Daniels' Ditch site. The Petitioners' complaints (aside from the issue of adequacy of flows in Spanish Creek), although meritorious, are, because of stipulations asserted by CLDD during the course of this proceeding, now rendered moot. CLDD stipulated that it only seeks a permit to use the west, north and eastern spoil area ditches. It does not seek and stipulated that it will not use, at any time, the south rim ditch and will maintain water control structures so to block water from entering that ditch. This will alleviate the problem of potential storage of water on Petitioners English and Patricia Mellor's property and the erosion problem on Petitioners William and Patricia Mellor's property south of the spoil area. It was thus established that the issuance of the right-of-way permit will not cause the injuries these Petitioners have suffered in the past because of use of the south rim ditch for water drainage and storage.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence in the record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED: That the South Florida Water Management District grant the County Line Drainage District's application for a permit for utilization of works and lands of the District. Subject to the following special condition: Issuance of this right-of-way permit does not relieve the Respondent CLDD from the responsibility of complying with special condition number 1 of the surface water management permit number 36-00184-S. Respondent CLDD shall, within 30 days of date of permitting, submit a design to the satisfaction of the SFWMD staff which will prevent the ability of CLDD to discharge to the southern rim ditch, described above. DONE and ENTERED this 29th day of September, 1983, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of September, 1983.

Florida Laws (2) 120.57373.085 Florida Administrative Code (1) 40E-6.011
# 6
CITIZENS FOR SMART GROWTH, KATHIE SMITH, AND ODIAS SMITH vs DEPARTMENT OF TRANSPORTATION, MARTIN COUNTY BOARD OF COUNTY COMMISSIONERS, AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 10-003317 (2010)
Division of Administrative Hearings, Florida Filed:Stuart, Florida Jun. 16, 2010 Number: 10-003317 Latest Update: Feb. 14, 2011

The Issue The issues are whether to (a) issue an Environmental Resource Permit (ERP) to the Department of Transportation (DOT) and Martin County (County) authorizing construction and operation of a surface water management system to serve a project known as the Indian Street Bridge; (b) issue DOT a letter of modification of ERP No. 43-00785-S authorizing roadway and drainage modifications to the Kanner Highway/Indian Street intersection; and (c) issue DOT a letter of modification of ERP No. 43-01229-P authorizing roadway and drainage modifications to Indian Street between the intersections of Kanner Highway and Willoughby Boulevard.

Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: The Parties Petitioner Citizens for Smart Growth, Inc., is a Florida 501(c)(3) corporation with its principal place of business in Palm City, Florida. It was formed by Odias Smith in August 2001, who serves as its president. The original directors were Kathie Smith, Odias Smith, and Craig Smith, who is the Smiths' son. The composition of the Board has never changed. According to the original Articles of Incorporation, its objectives are "preserving and enhancing the present advantages of living in Martin County (Quality of Life) for the common good, through public education, and the encouragement of reasonable and considered decision making by full disclosure of impacts and alternatives for the most appropriate use of land, water and resources." The exact number of members fluctuates from time to time. There are no dues paid by any member. At his deposition, Mr. Smith stated that no membership list exists; however, Kathie Smith stated that she currently has a list of 125 names, consisting of persons who at one time or another have made a contribution, have attended a meeting, or asked to be "kept informed of what's going on or asked to be on a mailing list or a telephone list, so they could be advised when we have meetings." No meetings have been held since 2006. Therefore, the Petitions filed in these cases have never been discussed at any meetings of the members, although Ms. Smith indicated that telephone discussions periodically occur with various individuals. Kathie Smith believes that roughly 25 percent of the members reside in a mobile home park north of the project site on Kanner Highway on the eastern side of the St. Lucie River, she does not know how many members reside on the western side of the St. Lucie River, and she is unaware of any member who resides on the South Fork of the St. Lucie River immediately adjacent to the project. Although the three Petitions allege that "seventy percent of the members . . . reside and/or recreate on the St. Lucie River," and in greater detail they allege how those members use that water body or depend on it for their livelihood, no evidence was submitted to support these allegations that 70 percent (or any other percentage of members) use or depend on the South Fork of the St. Lucie River for recreational or other activities. Petitioners Odias Smith and Cathie Smith reside in Palm City, an unincorporated community just south of Stuart in Martin County. They have opposed the construction of the new bridge since they moved to Palm City in 2001. It is fair to infer that Mr. Smith formed the corporation primarily for the purpose of opposing the bridge. Their home faces north, overlooking the South Fork of the St. Lucie River, from which it is separated by Saint Lucie Shores Drive and a narrow strip of common-ownership property. A boat dock extends from the common-ownership property into the St. Lucie River, providing 5 slips for use by the Smiths and other co-owners. The home is located three blocks or approximately 1,000 feet from the proposed western landfall of the new bridge. Due to the direction that the house faces (north) and the site of the new bridge, the surface water management system elements associated with the bridge will not be visible from their property. Mr. Smith believes, however, that when looking south through a veranda window on the second floor of his home, he will be able to see at least a part of the new bridge. From the front of their house, they now have an unobstructed view of the existing Palm City Bridge, a large structure that crosses the St. Lucie River approximately six- tenths of a mile north of their home, and which is similar in size to the new bridge now being proposed by the Applicants. The Smiths' home is more than 500 feet from the Project's right- of-way, and they do not know of any impact on its value caused by the Project. While the Smiths currently engage in walking, boating, running, fishing, and watching wildlife in the neighborhood or the South Fork of the St. Lucie River, there was no credible evidence that the Project would prevent them from doing so after the bridge and other improvements are constructed. Also, there was no evidence showing that the ERP Letter Modifications will cause them to suffer any adverse impacts. In fact, as noted below, by DOT undertaking the Project, the neighborhood will be improved through reduced flooding, improved water quality, and new swales and ponds. The County is a political subdivision of the State. It filed one of the applications at issue in this proceeding. DOT is an agency of the State and filed the three applications being contested. The District has the power and duty to exercise regulatory jurisdiction over the administration and enforcement of ERP criteria pursuant to Part IV, Chapter 373, Florida Statutes, and Title 40E of the Florida Administrative Code. The Department of Environment Protection (DEP) has delegated certain authority to the District, including the authority to authorize an applicant to use sovereign submerged lands via a public easement within the District's geographic jurisdiction. The Project Construction of a new bridge over the St. Lucie River has been studied extensively by the Applicants for over twenty years. DOT has awarded the contract and nearly all of the right-of-way has been purchased. The Project will begin as soon as the remaining permits are acquired. The Project is fully funded through the American Recovery and Reinvestment Act of 2009 and County funding. The Project is located in the County and includes 62.06 acres of roadway bridge development and 12.45 acres of sovereign submerged lands. The Project begins on the west side of the St. Lucie River on County Road 714, approximately 1,300 feet west of Mapp Road in Palm City and ends on the east side of the St. Lucie River approximately 1,400 feet east of Kanner Highway (State Road 76) on Indian Street. It includes construction and operation of a surface water management system to serve the road and bridge project. The total length of the Project is approximately 1.96 miles (1.38 miles of roadway and 0.58 miles of bridge) while the total area is approximately 74.51 acres. After treatment, surface water runoff will discharge to the tidal South Fork of the St. Lucie River. The Project encompasses a bridge crossing the South Fork of the St. Lucie River and the Okeechobee Waterway. Both are classified as Class III waters. The bridge transitions from 4 to 6 lanes east of the Okeechobee Waterway and will require a 55-foot vertical clearance and a 200-foot horizontal clearance between the fender systems at the Okeechobee Waterway. The bridge will cross over a portion of Kiplinger Island owned and preserved by the County. A part of the island was donated to the County in 1993-1994 by The Kiplinger Washington Editors, Inc., and the Kiplinger Foundation, Inc. Audubon of Martin County owns another part of the island. The transfer of title to the County does not include any restriction on the use of the island for conservation purposes only. Documentation submitted at hearing refers to a "two hundred foot wide road right-of-way" easement that the bridge will cross and allows the County to designate where on the island parcel such an easement would be. Therefore, spanning the bridge over a portion of the island owned by the County is clearly permissible. The Project also includes the roadway transition and widening/reconstruction of (a) County Road 714 from the beginning of the Project to Mapp Road from 2-lane to a 4-lane divided roadway; (b) Southwest 36th Street from Mapp Road to the beginning of the bridge from a 2-lane rural roadway to a 4-lane divided roadway with wide roadway swales; and (c) Kanner Highway (along Indian Street) from a 4-lane to a 6-lane divided urban roadway. Drainage improvements on both sides of the St. Lucie River are associated with the roadway construction. DOT proposes to provide both on-site and off-site mitigation for wetland and surface waters impacts pursuant to a mitigation plan approved by the District. The ERP Permitting Criteria In order to obtain an ERP, an applicant must satisfy the conditions for issuance set forth in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. Besides these rules, certain related BOR provisions which implement the rules must also be considered. The conditions for issuance primarily focus on water quality, water quantity, and environmental criteria and form the basis of the District's ERP permitting program. The parties have stipulated that the Project either complies with the following rule provisions or they are not applicable: Rules 40E-4.301(1)(a), (b), (g), (g), (h), and (k), and 40E- 4.302(1)(a)3. and 6. All other provisions remain at issue. Where conflicting evidence on these issues was submitted, the undersigned has resolved all evidentiary conflicts in favor of the Applicants and District. Based on the parties' Stipulation, the following provisions in Rule 40E-4.301(1) are in dispute and require an applicant to provide reasonable assurances that the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system: will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters; will not adversely affect the quality of receiving waters such that the water quality standards set forth in chapters 62- 4, 62-302, 62-520, 62-522, 62-550, F.A.C., including any anti-degradation provisions of paragraphs 62-4.242(1)(a) and (b), subsections 62-4.242(2) and (3), and rule 62-302.300, F.A.C., and any special standards for Outstanding Florida Waters and Outstanding National Resource Waters set forth in subsections 62-4.242(2) and (3), F.A.C., will be violated; will not cause adverse secondary impacts to the water resources; will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed; will be conducted by an entity with sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued; These disputed criteria are discussed separately below. Surface Water Storage and Conveyance Rule 40E-4.301(1)(c) requires that an applicant provide reasonable assurances that a proposed activity will not cause adverse impacts to existing surface water storage and conveyance capabilities. Through unrefuted evidence, this requirement was shown to be satisfied. The evidence also establishes that the surface water in and around the Project will actually improve if the Project is constructed as permitted. Further, it will create improved and upgraded surface water management and treatment in areas that now lack features such as swales, retention/detention ponds, curbs and gutters, and improve the overall surface water storage and conveyance capabilities of the Project and surrounding areas. In its current pre-development condition, flooding has occurred in certain areas adjacent to and within the Project area due to poor conveyance, low storage volume, and high tailwater conditions that result from high tides. The Project will remedy historic flooding issues in the Old Palm City area which lies adjacent to a portion of the Project alignment. Surface water runoff will be captured, controlled, and treated by a system of swales, weirs, and retention/detention facilities for pretreatment prior to discharging into the South Fork of the St. Lucie River. Reasonable assurances have been given that existing surface water storage and conveyance capabilities will not be adversely affected. Value of Functions to Fish, Wildlife, and Species Rule 40E-4.301(1)(d) requires that an applicant provide reasonable assurances that a proposed activity will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. BOR Section 4.2.2 further implements this provision. For the following reasons, the rule and BOR have been satisfied. The evidence shows that the existing functions to fish and wildlife were assessed and analyzed by a number of federal and state fish and wildlife agencies. There were extensive review and site inspections by the District, DOT, United States Fish and Wildlife Service, United States Army Corps of Engineers, and National Marine Fisheries Commission to assess the existence of, and potential impact on, fish and wildlife that may result from the Project. These studies revealed that while portions of the South Fork of the St. Lucie River provide potential habitat for aquatic or wetland-dependent or threatened species of special concern, no nesting or roosting areas within the vicinity of the Project were observed. The evidence further supports a finding that "other surface waters" over and under the Project will not receive unacceptable impacts due to their current condition, the detrimental influences of Lake Okeechobee discharges, and tidal impacts. Many of the wetlands to be impacted by the Project were shown to have been impacted by historic activities, and they provide diminished functions to fish and wildlife. The wetland functions were assessed through the Uniform Mitigation Assessment Methodology (UMAM). The UMAM is a standardized procedure for assessing the functions provided by wetlands and other surface waters, the amount that those functions would be reduced by a proposed project, and the amount of mitigation necessary to offset that loss. Detailed UMAM assessments were prepared by the Applicants and the District. They demonstrate that while certain functional units will be lost, they will be fully offset by the proposed mitigation. No credible evidence to the contrary was presented. Water Quality of Receiving Waters Rule 40E-4.301(1)(e) requires an applicant to provide reasonable assurances that a project will not adversely affect the quality of receiving waters such that State water quality standards will be violated. BOR Section 4.2.4 implements this rule and requires that "reasonable assurances regarding water quality must be provided for both the short term and long term, addressing the proposed construction, . . . [and] operation of the system." The receiving water body is the South Fork of the St. Lucie River, which is designated as an impaired water body. The evidence establishes that the Applicants will avoid and minimize potential short-term impacts to water quality by using silt screens and turbidity barriers, and implementing other best management practices to contain turbidity during construction of the Project. They will also use a temporary trestle rather than barges in the shallow portions of the South Fork to avoid stirring up bottom sediments. Finally, a turbidity monitoring plan will be implemented during construction and dewatering activities for all in-water work. All of these construction techniques will minimize potential impacts during construction. The evidence further establishes that water quality standards will not be violated as a result of the Project. In fact, in some cases water quality will be enhanced due to the installation and maintenance of new or upgraded surface water management features in areas where they do not exist or have fallen into disrepair. Over the long term, the Project is expected to have a beneficial effect on water quality. By improving existing surface water management and adding new surface water treatment features, the Project will provide net improvement to water quality. Wetland Delineation and Impacts The Project includes unavoidable impacts to wetlands and other surface waters. A total of 18.53 acres of wetlands and other surface waters within the Project site will be impacted by the Project, including 3.83 acres of wetlands that will be directly impacted and 14.7 acres of wetlands and other surface waters that will be secondarily impacted. The delineated wetlands are depicted in the Staff Report as wetlands 2a, 19a, 19b, 22, 25-29, 30a, 30b, and 30c, with each having a detailed UMAM assessment of its values and condition. (Impacts to wetland 25 are not included in this Project because they were accounted for in a separate permit proceeding.) Using a conservative assessment and set of assumptions, the District determined that, with the exception of wetlands 19a, 19b, 22, and 27, all wetlands would be impacted by the Project. However, the wetlands that would be impacted suffer from varying historical adverse impacts that have compromised the functions and values they provide to fish, wildlife, and species. This is due to their proximity to urban development, vegetative connectivity, size, historic impacts, altered hydroperiod, and invasive plant species. Likewise, even though the wetlands to be impacted on Kiplinger Island provide certain resting and feeding functions for birds, the value of these functions is comparatively lower than other wetlands due to the presence of invasive species and lack of management. The preponderance of the evidence supports a finding that the Applicants provided reasonable assurances that the Project will not cause adverse impacts to fish, wildlife, or listed species. See Fla. Admin. Code R. 40E-4.301(1)(d). Secondary Impacts Rule 40E-4.301(1)(f) and BOR Sections 4.1.1(f) and 4.2.7. require a demonstration that the proposed activities will not cause adverse secondary impacts to the water resources, both from a wetlands and water quality standpoint. Secondary impacts are those that occur outside the footprint of the project, but which are very closely linked and causally related to the activity to be permitted. De minimis or remotely-related secondary impacts, however, are not considered unacceptable. See § 4.2.7.(a). There will be secondary impacts to 6.83 acres of freshwater wetlands and 7.87 acres of mangroves, or a total of 14.7 acres. To address these secondary impacts, the Applicants have established extensive secondary impact zones and buffers along the Project alignment, which were based in part on District experience with other road projects and another nearby proposed bridge project in an area where a State Preserve is located. While Petitioners' expert contended that a 250-foot buffer on both sides of the roadway's 200-foot right-of-way was insufficient to address secondary impacts to birds (who the expert opines may fly into the bridge or moving vehicles), the greater weight of evidence shows that bird mortality can be avoided and mitigated through various measures incorporated into the Project. Further, the bird mortality studies used by the expert involved significantly different projects and designs, and in some cases involved projects outside the United States with different species concerned. Engineering and Scientific Principles Rule 40E-301(1)(i) requires that an applicant give reasonable assurance that a project "be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed." Unrefuted evidence establishes that the proposed system will function and be maintained as proposed. Financial, Legal and Administrative Capability Rule 40E-4.301(1)(j) requires that an applicant give reasonable assurance that it has the financial, legal, and administrative capability to ensure that the activity will be undertaken in accordance with the terms of the permit. The evidence supports a finding that Applicants have complied with this requirement. Elimination and Reduction of Impacts Before establishing a mitigation plan, Rule 40E- 4.301(3) requires that an applicant implement practicable design modifications to eliminate and reduce wetland and other surface water impacts. In this case, there are unavoidable, temporary wetland impacts associated with the construction of the Project, as well as unavoidable wetland impacts for direct (project footprint), secondary, and cumulative impacts of the Project. The record shows that the Applicants have undertaken extensive efforts to eliminate and reduce wetland and other surface water impacts of the Project. For example, DOT examined and assessed several innovative construction techniques and bridge designs to eliminate and avoid wetland impacts. To eliminate and reduce temporary impacts occurring during construction, DOT has reduced the effect of scour on the pier foundation and reduced the depth of the footing to minimize the amount of excavation on the mangrove island. Also, during construction, the contractor is prohibited from using the 200- foot right-of-way on the mangrove island for staging or stockpiling of construction materials or equipment. The majority of the bridge width has been reduced to eliminate and avoid impacts. Also, the Project's alignment was adjusted to the north to avoid impacts to a tidal creek. Reasonable assurances have been given that all practicable design and project alternatives to the construction and placement of the Project were assessed with no practicable alternatives. Public Interest Test Besides complying with the requirements of Rule 40E- 4.301, an applicant must also address the seven factors in Rule 40E-4.302(1)(a)1.-7., which comprise the so-called "public interest" test. See also § 373.414(1)(a), Fla. Stat. In interpreting the seven factors, the District balances the potential positive and negative effects of a project to determine if it meets the public interest criteria. Because Petitioners agree that factors 3 and 6 of the rule are not at issue, only the remaining five factors will be considered. For the following reasons, the Project is positive when the criteria are weighed and balanced, and therefore the Project is not contrary to the public interest. Public Health, Safety, and Welfare The Applicants have provided reasonable assurance that the Project will not affect public health, safety, and welfare. Specifically, it will benefit the health, safety, and welfare of the citizens by improving traffic conditions and congestion, emergency and hurricane evacuation, and access to medical facilities. In terms of safety, navigation markers are included as part of the Project for safe boating by the public. See Fla. Admin. Code R. 40E-4.302(1)(a)1. Conservation of Fish and Wildlife The activity will not adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. The mitigation projects will offset any impacts to fish and wildlife, improve the abundance and diversity of fish and wildlife on Kiplinger Island, create mangrove habitat, and add to the marine productivity in the area by enhancing water quality. See Fla. Admin. Code R. 40E-302(1)(a)2. Fishing or Recreational Values The Project has features that allow for pedestrian and bicycle utilization and observation areas which should enhance recreational values. The Old Palm Bridge, approximately one mile north of the Project, has had no adverse impact on the fishing recreation along the South Fork of the St. Lucie River. Navigation will not be affected due to the height and design of the new bridge. Finally, the bridge is expected to be a destination for boating, kayaking, fishing, and bird watching. See Fla. Admin. Code R. 40E-4.302(1)(a)4. Whether the Activity is of a Permanent Nature The parties have stipulated that the Project is permanent in nature. No future activities or future phases of the project are contemplated. Temporary and permanent impacts are all being fully mitigated. See Fla. Admin. Code R. 40E- 4.302(1)(a)5. Values of Functions Being Performed in Affected Areas Due to historic impacts to the areas affected by the Project, the current condition is degraded and the relative value of functions is minimal. Although Kiplinger Island will have temporary impacts, that island is subject to exotic species and has no recreational use or access by boaters or members of the public. The Applicants propose mitigation which will improve and enhance these wetland functions and values in the areas. See Fla. Admin. Code R. 40E-4.302(1)(a)7. Summary The evidence supports a finding that the Project is positive as to whether it will affect the public health, safety, welfare, or property of others; that the Project is neutral with respect to navigation, erosion and shoaling, and water flow, as well as to historical and archaeological concerns; and that the Project is positive as to conservation of fish, wildlife, recreational values, marine productivity, permanency, and current values and functions. When weighed and balanced, the Project is not contrary to the public interest. Cumulative Impacts Rule 40E-4.302(1)(b) requires that an applicant give reasonable assurance that a project will not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in BOR Sections 4.28 through 4.2.8.2. Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin. An analysis is geographically based upon the drainage basins described in BOR Figure 4.4.1. Petitioners' contention that Figure 4.4.1 is inaccurate or not representative of the basin in which the Project is located has been rejected. In this case, the North St. Lucie Basin was used. To assess and quantify any potential unacceptable cumulative impacts in the basin, and supplement the analyses performed by the Applicants, the District prepared a Basin Map that depicted all the existing and permitted wetland impacts as well as those wetlands under some form of public ownership and/or subject to conservation restrictions or easements. The District's analysis found that the wetlands to be mitigated were of poor quality and provided minimal wildlife and water quality functions. Cumulative impacts from the Project to wetlands within the basin resulted in approximately a four percent loss basin-wide. This is an acceptable adverse cumulative impact. Therefore, the Project will not result in unacceptable cumulative impacts. Mitigation Adverse impacts to wetlands caused by a proposed activity must be offset by mitigation measures. See § 4.3. These may include on-site mitigation, off-site mitigation, off- site regional mitigation, or the purchase of mitigation credits from mitigation banks. The proposed mitigation must offset direct, secondary, and cumulative impacts to the values and functions of the wetlands impacted by the proposed activity. The ability to provide on-site mitigation for a DOT linear transportation project such as a bridge is limited and in this case consists of the creation of mangrove and other wetlands between the realigned St. Lucie Shores Boulevard and the west shore of the St. Lucie River, north and south of the proposed bridge crossing. BOR Section 4.3.1.2 specifically recognizes this limitation and allows off-site mitigation for linear projects that cannot effectively implement on-site mitigation requirements due to right-of-way constraints. Off-site mitigation will offset the majority of the wetland impacts. Because no single on-site or off-site location within the basin was available to provide mitigation necessary to offset all of the Project's impacts, DOT proposed off-site mitigation at two established and functioning mitigation areas known as Dupuis State Reserve (Dupuis), which is managed by the County and for which DOT has available mitigation credits, and the County's Estuarine Mitigation Site, a/k/a Florida Oceanographic Society (FOS) located on Hutchinson Island. Dupuis is outside the North St. Lucie Basin and was selected to offset direct and secondary impacts to freshwater wetlands. That site meets the ERP criteria in using it for this project. The FOS is within the North St. Lucie Basin and was selected to offset direct and secondary impacts to estuarine wetlands. Like Dupuis, this site also meets the ERP criteria for the project. The preponderance of the evidence establishes that the on-site and off-site mitigation projects fully offset any and all project impacts, and in most instances before the impacts will actually occur. Sovereign Submerged Lands and Heightened Public Concern Chapter 18-21 applies to requests for authorization to use sovereign submerged lands. The management policies, standards, and criteria used to determine whether to approve or deny a request are found in Rule 18-21.004. For purposes of granting a public easement to the Applicants, the District determined that the Project is not contrary to the public interest and that all requirements of the rule were satisfied. This determination was not disputed. The only issue raised by Petitioners concerning the use of submerged lands is whether the application should have been treated as one of "heightened public concern." See Fla. Admin. Code R. 18-21.0051(5). If a project falls within the purview of that rule, the Board of Trustees of the Internal Improvement Trust Fund (Board), rather than the District, must review and approve the application to use submerged lands. Review by the Board is appropriate whenever a proposed activity is reasonably expected to result in a heightened public concern because of its potential effect on the environment, natural resources, or controversial nature or location. Id. In accordance with established protocol, the ERP application was sent by the District to DEP's review panel in Tallahassee (acting as the Board's staff) to determine whether the Project required review by the Board. The panel concluded that the Project did not rise to the level of heightened public concern. Evidence by Petitioners that "many people" attended meetings and workshops concerning the Project over the last 20 years or so is insufficient to trigger the rule. Significantly, except for general project objections lodged by Petitioners and Audubon of Martin County, which did not include an objection to an easement, no adjacent property owner or other member of the public voiced objections to the construction of a new bridge. Revised Staff Report On October 20, 2010, the District issued a Revised Staff Report that merely corrected administrative errors or information that had been previously submitted to the District. Contrary to Petitioners' assertion, it did not constitute a material change to the earlier agency action either individually or cumulatively. Therefore, it was properly considered in this proceeding. Letter Modifications The Letter Modifications were used as a mechanism to capture minor alterations made to previously issued permits for Kanner Highway and Indian Street. Neither Letter Modification is significant in terms of water quality, water quantity, or environmental impacts. Both were issued in accordance with District rules and should be approved.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order granting Application Nos. 091021-8, 100316-7, and 100316-6. DONE AND ENTERED this 28th day of December, 2010, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of December, 2010. COPIES FURNISHED: Carol Ann Wehle, Executive Director South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33406-3007 Jeffrey W. Appel, Esquire Ray Quinney and Nebeker, P.C. 36 South State Street, Suite 1400 Salt Lake City, Florida 84111-1401 Bruce R. Conroy, Esquire Department of Transportation 605 Suwannee Street Mail Station 58 Tallahassee, Florida 32399-0458 David A. Acton, Esquire Senior Assistant County Attorney Martin County Administrative Center 2401 Southeast Monterey Road Stuart, Florida 34996-3397 John J. Fumero, Esquire Rose, Sundstrom & Bentley, P.A. 950 Peninsula Corporate Circle Suite 2020 Boca Raton, Florida 33487-1389 Keith L. Williams, Esquire South Florida Water Management District 3301 Gun Club Road Mail Stop 1410 West Palm Beach, Florida 33406-3007

Florida Laws (4) 120.569120.57373.413373.414 Florida Administrative Code (2) 40E-4.30140E-4.302
# 7
FRANCELL FREI vs CITY OF DELTONA AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 04-002404 (2004)
Division of Administrative Hearings, Florida Filed:Deltona, Florida Jul. 12, 2004 Number: 04-002404 Latest Update: Feb. 14, 2006

The Issue The issue is whether the applicant for an Environmental Resource Permit ("ERP"), the City of Deltona ("City" or "Applicant"), has provided reasonable assurance that the system proposed complies with the water quantity, environmental, and water quality criteria of the St. Johns River Water Management District's ("District") ERP regulations set forth in Florida Administrative Code Chapter 40C-4, and the Applicant's Handbook: Management and Storage of Surface Waters (2005).

Findings Of Fact The District is a special taxing district created by Chapter 373, Florida Statutes, charged with the duty to prevent harm to the water resources of the District, and to administer and enforce Chapter 373, Florida Statutes, and the rules promulgated thereunder. The City of Deltona is a municipal government established under the provisions of Chapter 165, Florida Statutes. The Lake Theresa Basin is comprised primarily of a system of interconnected lakes extending from Lake Macy in the City of Lake Helen to the Butler Chain of Lakes (Lake Butler and Lake Doyle). The Lake Theresa Basin is land-locked and does not have a natural outfall to Lake Monroe and the St. Johns River. In 2003, after an extended period of above-normal rainfall in the Deltona area, the lakes within the land-locked Lake Theresa Basin staged to extremely high elevations that resulted in standing water in residential yards, and rendered some septic systems inoperable. Lake levels within the Lake Theresa Basin continued to rise and were in danger of rising above the finished floor elevations of some residences within the basin. On March 25, 2003, the District issued an Emergency Order (F.O.R. No. 2003-38) authorizing the construction and short-term operation of the Lake Doyle and Lake Bethel Emergency Overflow Interconnection. Since wetland and surface water impacts would occur, the Emergency Order required the City of Deltona to obtain an ERP for the system. The project area is 4.1 acres, and the system consists of a variable water structure on the west shore of Lake Doyle connected to a series of pipes, swales, water control structures, and wetland systems which outfall to a finger canal of Lake Bethel, with ultimate discharge to Lake Monroe and the St. Johns River. The first segment of the system extends downstream from the weir structure on the west shore of Lake Doyle via a pipe entrenched in the upland berm of the Sheryl Drive right-of-way. The pipe passes under Doyle Road and through xeric pine-oak uplands to the northeast shore of a large (approximately 15 acres) deepwater marsh. Water flows south through the deepwater marsh where it outfalls through four pipes at Ledford Drive. Two of the four pipes are overflow structures, controlled by canal gates. The pipes at Ledford Drive discharge into a ditch and into a large (greater than 20 acres) shallow bay swamp. The south end of the bay swamp is defined (and somewhat impounded) by a 19th Century railroad grade. Water flows through the bay swamp where it outfalls through five pipes at the railroad grade. Three of the five pipes are overflow structures, controlled by channel boards. The pipes at the railroad grade discharge to a 1500-foot long finger canal that was dug some time during the period 1940-1972 from the north central shore of Lake Bethel. The overflow interconnection system has three locations whereby the system can be shut down: 1) Lake Doyle--a control weir, controlled by three sluice gates; 2) Ledford Drive--two thirty-inch reinforced concrete pipes, controlled by canal gates; and 3) railroad grade--three thirty-inch reinforced concrete pipes, controlled by channel boards (collectively referred to as "Overflow Structures"). The Overflow Structures are designed to carry the discharge of water from Lake Doyle to Lake Bethel. With the Overflow Structures closed the system returns to pre-construction characteristics, meaning there will be no increase or decrease in the quantity or quality of water throughout the path of the system as a result of the project. An unequivocal condition of the permit is that the system would operate with all of the Overflow Structures closed. As an added assurance, the City proposes to place a brick and mortar plug in the Lake Doyle weir structure outfall pipe to prevent any discharge from the weir. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the water level in Lake Doyle rises above an elevation of 24.5 feet. The District shall require a separate permit application to be submitted for such future plans. Petitioner, Barbara Ash, has lived on Lake Theresa for 19 years. Ms. Ash lives upstream from the area of the weir that will be plugged in accordance with the ERP. She does not trust either the City of Deltona to comply with or the District to enforce the conditions of the ERP applied for by the City. Petitioner, Barbara Ash, also served as the qualified representative for Petitioners, Francell Frei, Bernard J. and Virginia Patterson, and Ted and Carol Sullivan. Ms. Ash represented that Ms. Frei has lived on Lake Theresa for 12 years, and both the Pattersons and the Sullivans live on Lake Louise, which is within the area of concern in this proceeding. Petitioner, Diana Bauer, has lived on Lake Theresa since February 2004. She fears that the lake will become too dry if the system is allowed to flow. She also believes the wildlife will be adversely affected if the water levels are too low since many species need a swampy or wet environment to thrive. She fears her property value will decrease as a result of the approval of the ERP. She also does not trust either the City to comply with or the District to enforce the conditions of the ERP. Petitioner, Howard Ehmer, lives two to three hundred yards down Lake Theresa from Ms. Bauer. He is concerned about the lake bed being too dry and attracting people on all terrain vehicles who enjoy driving around the lake bottom. He is concerned about his property value decreasing if the lake bed is dry. Further, when the lake level is too low, people cannot enjoy water skiing, boating, and fishing on Lake Theresa. Petitioner, Phillip Lott, a Florida native, has also owned and lived on property abutting Lake Theresa since 1995. Mr. Lott has a Ph.D. in plant ecology, and M.P.A. in coastal zone studies, an M.B.A. in international business, and a B.S. in environmental resource management and planning. Mr. Lott has been well acquainted with the water levels on Lake Theresa for many years. Based upon his personal observations of the lake systems in the Deltona area over the years, Mr. Lott has seen levels fluctuate greatly based upon periods of heavy and light rainfall. Mr. Lott is concerned that the District will permit the City to open the weir to let water flow through the system and cause flooding in some areas and low water levels in other areas. He fears that the District will allow the water to flow and upset the environmental balance, but he admits that this ERP application is for a closed system that will not allow the water to flow as he fears. Mr. Lott similarly does not trust the City to comply with and the District to enforce the conditions of the ERP. Petitioners, James E. and Alicia M. Peake, who were represented by Steven L. Spratt at hearing as their qualified representative, live on Lake Louise, which is interconnected with the Lake Theresa basin. The Peakes are concerned that if the level of Lake Louise drops below 21 feet, nine inches, they will not be able to use the boat launch ramps on the lake. Petitioner, Steven L. Spratt, also lives on Lake Louise, and is concerned about the water levels becoming so low that he cannot use the boat launch on the lake. He has lived on the lake since 2000, and remembers when the water level was extremely low. He fears that approval of the ERP in this case will result in low levels of water once again. Petitioner, Gloria Benoit, has live on Lake Theresa for two years. She also enjoys watching recreational activities on the lake, and feels that approval of the ERP will devalue her lakefront property. Ms. Benoit appeared at the first day of the hearing, but offered no testimony on her behalf. J. Christy Wilson, Esquire, appeared prior to the final hearing as counsel of record for Petitioners, Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow. Neither Ms. Wilson nor any of the three Petitioners she represented appeared at any time during the hearing, filed any pleadings seeking to excuse themselves from appearing at the final hearing, or offered any evidence, testimony, pre- or post- hearing submittals. Petitioner, Gary Jensen, did not appear at hearing, did not file any pleadings or papers seeking to be excused from appearing at the final hearing, and did not offer any evidence, testimony, pre- or post-hearing submittals. Both the City and the District recognize that areas downstream from the project site, such as Stone Island and Sanford, have experienced flooding in the past in time of high amounts of rainfall. The system proposed by the City for this ERP will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel. So long as the overflow structures are closed, the system will mimic pre-construction flow patterns, with no increase in volume flowing downstream. The District has considered the environment in its proposed approval of the ERP. The area abutting the project is little urbanized and provides good aquatic and emergent marsh habitat. With the exception of the western shore area of the deepwater marsh ("west marsh area"), the bay swamp and remaining deepwater marsh area have good ecological value. In the 1940's, the west marsh area was incorporated into the drainage system of a poultry farm that occupied the site. This area apparently suffered increased nutrient influxes and sedimentation that contributed to a proliferation of floating mats of aquatic plants and organic debris. These tussocks reduced the deepwater marsh's open water and diminished the historical marsh habitat. Water under the tussocks is typically anoxic owing to total shading by tussocks and reduced water circulation. Thick, soft, anaerobic muck has accumulated under the matted vegetation. Exotic shrubs (primrose willow Ludwigia peruvania) and other plants (cattails Typha spp.) dominate the tussocks. The construction of the project, from the 2003 Emergency Order, resulted in adverse impacts to 1.3 acres of wetlands having moderately high- to high ecological value and 0.2 acres of other surface waters. The 0.2 acre impact to other surface waters was to the lake bottom and the shoreline of Lake Doyle where the weir structure was installed. The 0.3 acres of wetland impacts occurred at the upper end of the deepwater marsh where the pipe was installed. The largest wetland impact (1.0 acre) was to the bay swamp. The bay swamp is a shallow body dominated by low hummocks and pools connected inefficiently by shallow braided channels and one acre is filled with a 1-2 foot layer of sediment following swamp channelization. Disturbance plants (e.g., primrose willow, Ludwigia peruvania, and elderberry Sambucus Canadensis) now colonize the sediment plume. Pursuant to the District's elimination and reduction criteria, the applicant must implement practicable design modifications, which would reduce or eliminate adverse impacts to wetlands and other surface waters. A proposed modification, which is not technically capable of being done, is not economically viable, or which adversely affects public safety through endangerment of lives or property is not considered "practicable." The City reduced and/or eliminated the impacts to the lake bottom and shoreline of Lake Doyle and deepwater marsh, to the extent practicable. The impacts were the minimum necessary to install the weir structure and pipe for the system; the weir structure and pipe were carefully installed on the edges of the wetland and surface water systems, resulting in a minimum amount of grading and disturbance. To compensate for the loss of 1.3 acres of wetlands and 0.2 acres of other surface waters, the City proposes to preserve a total of 27.5 acres of wetlands, bay swamp, marsh, and contiguous uplands. Included in this 27.5 acres are 6.4 acres of the west marsh, which are to be restored. The parties stipulated that the mitigation plan would adequately compensate for losses of ecological function (e.g. wildlife habitat and biodiversity, etc.) resulting from the project. Water quality is a concern for the District. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies for nitrogen, phosphorous, and dissolved oxygen. Water quality data for Lake Monroe indicate the lake has experienced high levels of nitrogen and phosphorous and low levels of dissolved oxygen. Prior to construction of the project, there was no natural outfall from the Lake Theresa Basin to Lake Monroe and therefore no contribution from this basin to nitrogen and phosphorous loadings to Lake Monroe. Lake Colby, Three Island Lakes (a/k/a Lake Sixma), and the Savannah are surface waters within the Lake Theresa Basin for which minimum levels have been adopted pursuant to Florida Administrative Code Chapter 40C-8. The system will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel, resulting in no outfall from the Theresa Basin to Lake Monroe. Minimum flows established for surface waters within the Lake Theresa Basin will not be adversely impacted. Under the first part of the secondary impact test, the City must provide reasonable assurance that the secondary impacts from construction, alteration, and intended or reasonable expected use of the project will not adversely affect the functions of adjacent wetlands or surface waters. The system is designed as a low intensity project. As proposed, little activity and maintenance are expected in the project site area. The reasonably expected use of the system will not cause adverse impacts to the functions of the wetlands and other surface waters. None of the wetland areas adjacent to uplands are used by listed species for nesting or denning. In its pre-construction state, the project area did not cause or contribute to state water quality violations. Under the second part of the secondary impact test, the City must provide reasonable assurance that the construction, alteration, and intended or reasonably expected uses of the system will not adversely affect the ecological value of the uplands to aquatic or wetland dependent species for enabling existing nesting or denning by these species. There are no listed threatened or endangered species within the project site area. Under the third part of the secondary impact test, and as part of the public interest test, the District must consider any other relevant activities that are closely linked and causally related to any proposed dredging or filling which will cause impacts to significant historical and archaeological resources. When making this determination, the District is required, by rule, to consult with the Division of Historical Resources. The Division of Historical Resources indicated that no historical or archaeological resources are likely present on the site. No impacts to significant historical and archaeological resources are expected. Under the fourth part of the secondary impact test, the City must demonstrate that certain additional activities and future phases of a project will not result in adverse impacts to the functions of wetlands or water quality violations. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the level in Lake Doyle rises above an elevation of 24.5 feet. Based upon the plans and calculations submitted, the proposed future phase, without additional measures, could result in minor increases in the loadings of nitrogen and phosphorous to Lake Monroe. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies due to water quality data indicating the lake has experienced high levels of nitrogen and phosphorous, and low levels of dissolved oxygen. Under this potential future phase, there would be an outfall from the Lake Theresa Basin to Lake Monroe. To address the impact on water quality of this potential future phase, the City has submitted a loading reduction plan for nitrogen, phosphorous, and dissolved oxygen. The plan includes compensating treatment to fully offset the potential increased nutrient loadings to Lake Monroe. Specifically, the loading reduction plan includes: Construction and operation of compensating treatment systems to fully offset anticipated increased nutrient loadings to Lake Monroe. Weekly water quality monitoring of the discharge from Lake Doyle for total phosphorous and total nitrogen. A requirement that the overflow structure be closed if the total phosphorous level reaches 0.18 mg/l or higher or the total nitrogen level reaches 1.2 mg/l or higher in any given week and will remain closed until levels fall below those limits. The implementation of these water quality mitigation measures will result in a net improvement of the water quality in Lake Monroe for nitrogen, phosphorous, or dissolved oxygen. The future phase was conceptually evaluated by the District for impacts to wetland functions. The future phase as proposed could result in adverse impacts to wetland functions. Operation of the system with the overflow structures open could impact the bay swamp and deepwater marsh. The City has demonstrated that any adverse impacts could be offset through mitigation. Based upon the information provided by the City and general engineering principles, the system is capable of functioning as proposed. The City of Deltona will be responsible for the operation, maintenance, and repair of the surface waster management system. A local government is an acceptable operation and maintenance entity under District rules. The public interest test has seven criteria. The public interest test requires the District to evaluate only those parts of the project actually located in, on, or over surface waters or wetlands, to determine whether a factor is positive, neutral, or negative, and then to balance these factors against each other. The seven factors are as follows: the public health, safety, or welfare of others; conservation of fish and wildlife and their habitats; fishing, recreational value, and marine productivity; temporary or permanent nature; 5) navigation, water flow, erosion, and shoaling; 6) the current condition and relative value of functions; and 7) historical and archaeological resources. There are no identified environmental hazards or improvements to public health and safety. The District does not consider impacts to property values. To offset any adverse impacts to fish and wildlife and their habitats, the City has proposed mitigation. The areas of the project in, on, or over wetlands do not provide recreational opportunities. Construction and operation of the project located in, on, or over wetlands will be permanent in nature. Construction and operation of the project located in, on, or over wetlands will not cause shoaling, and does not provide navigational opportunities. The mitigation will offset the relative value of functions performed by areas affected by the proposed project. No historical or archaeological resources are likely on the site of the project. The mitigation of the project is located within the same drainage basin as the project and offsets the adverse impacts. The project is not expected to cause unacceptable cumulative impacts.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered granting the City of Deltona's application for an environmental resource permit with the conditions set forth in the Technical Staff Report, and dismissing the Petitions for Formal Administrative Hearing filed by Gary Jensen in Case No. 04-2405, and by Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow in Case No. 04-3048. DONE AND ENTERED this 27th day of May, 2005, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 2005. COPIES FURNISHED: George Trovato, Esquire City of Deltona 2345 Providence Boulevard Deltona, Florida 32725 Diana E. Bauer 1324 Tartan Avenue Deltona, Florida 32738 Barbara Ash, Qualified Representative 943 South Dean Circle Deltona, Florida 32738-6801 Phillip Lott 948 North Watt Circle Deltona, Florida Howard Ehmer Nina Ehmer 32738-7919 1081 Anza Court Deltona, Florida 32738 Francell Frei 1080 Peak Circle Deltona, Florida 32738 Bernard T. Patterson Virginia T. Patterson 2518 Sheffield Drive Deltona, Florida 32738 Kealey A. West, Esquire St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177 J. Christy Wilson, Esquire Wilson, Garber & Small, P.A. 437 North Magnolia Avenue Orlando, Florida 32801 Gloria Benoit 1300 Tartan Avenue Deltona, Florida 32738 Gary Jensen 1298 Tartan Avenue Deltona, Florida 32738 James E. Peake Alicia M. Peake 2442 Weatherford Drive Deltona, Florida 32738 Steven L. Spratt 2492 Weatherford Drive Deltona, Florida 32738 Ted Sullivan 1489 Timbercrest Drive Deltona, Florida 32738 Kirby Green, Executive Director St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177

Florida Laws (3) 120.569120.57373.086 Florida Administrative Code (6) 40C-4.30140C-4.30240C-4.33140C-4.75162-302.30062-4.242
# 8
FLORIDA WILDLIFE FEDERATION, JUPITER FARMS ENVIRONMENTAL COUNCIL, INC., D/B/A LOXAHATCHEE RIVER COALITION, AUDUBON SOCIETY OF THE EVERGLADES, MARGE KETTER, PALM BEACH COALITION, STEVEN BELL, ALEXANDRA LARSON, MICHAEL CHRISTIANSON, AND BARRY SILVER vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, PALM BEACH COUNTY, AND LANTANA FARMS ASSOCIATES, INC., 04-003064 (2004)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 31, 2004 Number: 04-003064 Latest Update: Dec. 13, 2004

The Issue Petitioners challenge the South Florida Water Management District’s (the District) proposed action to issue Individual Environmental Resource Permit (ERP) 50-06558-P to authorize conceptual approval of a surface water management (SWM) system to serve 1,919 acres of a phased, multiple-use development referred to as the Palm Beach County Biotechnolgy Research Park (BRP) and to authorize construction and operation of Phase 1A of that proposed project. The ultimate issue is whether the Applicants provided reasonable assurances that the proposed activities will not be harmful to the water resources of the District; will not be inconsistent with the overall objectives of the District; and will comply with the water quantity, environmental, and water quality criteria of the District’s ERP regulations, which are set forth in Part IV of Chapter 373, Florida Statutes, Florida Administrative Code Chapter 40E-4, et. seq.; and the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District – September 2003 (BOR).1

Findings Of Fact THE PARTIES The Florida Wildlife Federation, Audubon Society of the Everglades, and Jupiter Farms Environmental Council, Inc. (d/b/a Loxahatchee River Coalition) are not-for-profit corporations in existence prior to 2003 with more than 25 members in Palm Beach County. Palm Beach County Environmental Coalition was formed in 1997 and is a private, county-wide, non-profit citizen’s organization. Ms. Ketter, Mr. Bell, Ms. Larson, and Mr. Christensen are individuals affected by the proposed BRP. The Respondents stipulated that the parties who remained Petitioners after Mr. Silver’s withdrawal as a Petitioner have standing to bring this proceeding. The District, a public corporation existing by virtue of Chapter 25270, Laws of Florida, 1949, operates pursuant to Chapter 373, Florida Statutes, and Title 40E, Florida Administrative Code, as a multipurpose water management district with its principal office in West Palm Beach, Florida. The County is a duly-constituted governmental entity. THE PROJECT SITE AND ADJACENT LANDS The site of the project is generally referred to as the Mecca Farms, which is a contiguous tract of 1,919 acres of land. At present, the Mecca Farms is used for farming and mining operations. There presently exists a permitted, SWM system on the Mecca Farms that was first permitted in 1979, and has been modified from time to time since then. The existing SWM system includes 73 acres of ditches and a 272-acre above-ground impoundment area. The Mecca Farms site is located within the C-18 Basin. There are no jurisdictional wetlands or delineated surface waters on the Mecca Farms. The following, which is taken from the Staff Report (SFWMD Ex. 1), accurately describes the project site and its adjacent lands: The project site consists of 1,919 acres presently supporting an active orange grove with approximately 73 acres of associated drainage and irrigation ditches/canals and a 30-acre active sand mining operation. The ditches/canals are presently maintained at an elevation of approximately 17 feet NGVD.[3] These ditches/canals provide drainage conveyance to a 272-acre above- ground impoundment located in the northeast corner of the site utilizing four (4) 22,000 gpm pumps. The above-ground impoundment discharges to the west leg of the C-18 Canal via gravity discharge. Project site ditches and canals also connect directly to the C-18 Canal through an 18,000 gpm pump. An additional 224-acre agricultural area east of the 1,919 acres of orange groves is connected to and drains into the canal/ditch system on the project site. This adjacent area was leased from the adjacent land owner by the grove owner for use as row crops and was connected to the grove canal/ditch system for better control of drainage and irrigation. The area is no longer used for row crops. There is also a small area on the site that contains caretaker housing and an equipment maintenance building for the orange groves. These facilities were originally permitted in 1979 under Surface Water Management Permit No. 50-00689-S and subsequent modifications. The citrus grove and primary drainage facilities have been in existence since the 1960s. The Hungryland Slough is located north of the project site, separated from the project site by the C-18 Canal. This area is comprised primarily of publicly-owned natural areas, including an area referred to as Unit 11, which is owned in the majority by Palm Beach County. To the west is the J.W. Corbett Wildlife Management Area (CWMA) owned and managed by the Florida Fish and Wildlife Conservation Commission (FFWCC). To the east, a large area of low-intensity agricultural land exists under the ownership of Charles Vavrus and within the City of Palm Beach Gardens. These lands contain extensive wetlands that are adjacent to the Loxahatchee Slough to the east. The Acreage, a low-density residential area, is located directly to the south of the project site. The only access to the site at this time is an unpaved extension of Seminole Pratt-Whitney Road (SPW), connecting the site at its southwestern corner to the Acreage. THE PROPOSED PROJECT The subject application is for conceptual approval of the SWM system for the BRP and for construction and operation of Phase 1A of the project. All of the proposed Phase 1A construction will occur on the Mecca Farms site. The following, taken from the Staff Report, accurately describes the proposed project: The [BRP] is a phased multiple use development planned for approximately 1,919 acres and will consist of land uses related to science and technology, biotechnology, biomedical, and other related research and development industries and manufacturing. Additionally, proposed support and complementary land uses include educational, institutional, residential, commercial, and recreational facilities, along with utilities and a large created natural area. THE PROPOSED SWM SYSTEM The proposed SWM system will consist of several interconnected lakes that will provide wet detention for storm water runoff from the property site and from 39 acres of off- site flows from SPW Road and a proposed Florida Power and Light (FPL) Substation. The lakes will collect, store, and treat the runoff. The storm water will pass through the lakes, through a 247-acre area referred to as the “Natural Area” (which will be created as part of the mitigation plan), and discharged to the C-18 Canal. To provide additional water quality treatment, these lakes will include planted littoral zones and the southern lake will include a filter marsh. The Natural Area will, in subsequent construction phases, be constructed on the western boundary of the Mecca site with discharge to the C-18 canal, which is adjacent to the northern boundary of the Mecca Farms. The southern boundary of the Natural Area will be the north boundary of the lake that is to be constructed on the southern end of the property. This is the area that is available for use as a flow-way (which will be discussed in greater detail in a subsequent section of this Recommended Order). The Natural Area will be a wetland type system that will move water slowly through that system providing additional storage and water quality benefits prior to discharging through a gravity control structure into the C-18 Canal. The C-18 Canal discharges to either the Northwest or Southwest Fork of the Loxahatchee River, depending on how structures are operated downstream. Discharges travel in the C-18 Canal for approximately nine miles before reaching the Loxahatchee River. The existing SWM system for the Mecca Farms currently discharges to the C-18 Canal, as will the proposed SWM system. The proposed project will not discharge to the CWMA or the Hungryland Slough. The Grassy Waters Preserve and the Loxahatchee Slough are several miles from the project site and will not be affected by the project’s proposed activities. The following, which is taken from the Staff Report, accurately describes the proposed SWM system. The proposed conceptual surface water management system which will serve the 1,919-acre site will consist of site grading, storm water inlets and culverts which will direct all runoff to a series of interconnected lakes for water quality treatment and attenuation of the peak runoff rate. Pumps will control the runoff rate from the developed site into the adjacent onsite BRP natural area. The BRP natural area will discharge into the C-18 canal via a gravity control structure. The system has been designed to accommodate 39 acres of off-site flows from SPW [Road] and a proposed Florida Power and Light (FPL) Substation. The existing control elevation of the citrus grove is 17.0’ NGVD. The proposed control elevations are 18.0’ NGVD for the developed area and 19.0’ NGVD for the natural area. The control elevations are being raised to provide a “step down” of water elevations from wetlands to the north, west and east of the site (20.5’ to 21.0’) to lower elevations to the south (17.0’). PHASE 1A CONSTRUCTION The following, which is taken from the Staff Report, accurately describes the proposed Phase 1A construction: The Phase 1A construction activities will allow the applicant to proceed with lake excavation, clearing and site grading of 536 acres in the southern portion of the site. No permanent buildings or parking areas are proposed at this time. Stormwater from Phase 1A and the remainder of the site, to remain in agricultural use, will be treated in the Phase 1A lakes and then pumped into the existing impoundment for additional water quality treatment and attenuation prior to discharging to the west leg of the C-18 Canal via the existing weir structures. The existing 18,000 gpm pump that connects the on-site ditches and canals directly to the C-18 Canal will remain, but will only be used if the impoundment is full. (See Special Condition No. 21). Approval of Phase 1A authorizes the use of the existing, previously permitted surface water management facilities, therefore, the previous permit no. 50-00689-S is superceded by this permit. The 224 acre agricultural area east of the existing grove that is connected to the grove canal/ditch system will be severed as part of Phase 1A. The pipe connecting this area will be removed and portions of the berm around this area will be regraded so the area will sheetflow into the adjacent pasture land’s canal/ditch system as it did previously [sic] to being connected to the grove system. Of the 536 acres involved in the Phase 1A construction, 87 acres will become lake bottom and 449 acres will remain pervious area, subject only to grading. CONCEPTUAL APPROVAL Pertinent to this proceeding, Florida Administrative Code Rule 40E-4.021(5) defines the term “conceptual approval” to mean an ERP issued by the District which approves a conceptual master plan for a surface water management system or a mitigation bank. Florida Administrative Code Rule 40E-4.305, pertains to conceptual approvals and provides, in relevant part, as follows: Conceptual approvals constitute final District action and are binding to the extent that adequate data has been submitted for review by the applicant during the review process. A conceptual approval does not authorize construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system or the establishment and operation of a mitigation bank. * * * For phased projects, the approval process must begin with an application for a conceptual approval which shall be the first permit issued for the project. An application for construction authorization of the first phase(s) may also be included as a part of the initial application. As the permittee desires to construct additional phases, new applications shall be processed as individual or standard general environmental resource permit applications pursuant to the conceptual approval. The conceptual approval, individual and standard general permits shall be modified in accordance with conditions contained in Chapters 40E-4 and 40E-40, F.A.C. Issuance of a conceptual approval permit pursuant to Chapter 40E-4, F.A.C., shall not relieve the applicant of any requirements for obtaining a permit to construct, alter, operate, maintain, remove, or abandon a surface water management system or establish or operate a mitigation bank, nor shall the conceptual approval permit applicant be relieved of the District’s informational requirements or the need to meet the standards of issuance of permits pursuant to Chapters 40E-4 or 40E-40, F.A.C. . . . PERMITTING CRITERIA In order to obtain an ERP, an applicant must satisfy the conditions for issuance set forth in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. The conditions for issuance focus on water quantity criteria, environmental criteria, and water quality criteria. Florida Administrative Code Rule 40E-4.301 contains the following permitting conditions applicable to this proceeding: In order to obtain a standard general, individual, or conceptual approval permit ... an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system: will not cause adverse water quantity impacts to receiving waters and adjacent lands; will not cause adverse flooding to on-site or off-site property; will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters; will not adversely affect the quality of receiving waters ...; will not cause adverse secondary impacts to the water resources; will not adversely impact the maintenance of surface or ground water levels or surface water flows ...; will not cause adverse impacts to a work of the District ...; will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed; will be conducted by an entity with the sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued; and will comply with any applicable special basin or geographic area criteria established in Chapter 40E-41 F.A.C. Florida Administrative Code Rule 40E-4.302 provides the following Additional Conditions for Issuance of Permits applicable to this proceeding: In addition to the conditions set forth in section 40E-4.301, F.A.C., in order to obtain a standard general, individual, or conceptual approval permit under this chapter or Chapter 40E-40, F.A.C., an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal, and abandonment of a system: Located in, on, or over wetlands or other surface waters will not be contrary to the public interest, or if such an activity significantly degrades or is within an Outstanding Florida Water, that the activity will be clearly in the public interest, as determined by balancing the following criteria as set forth in subsections 4.2.3 through 4.2.3.7 of the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District: Whether the activity will adversely affect the public health, safety or welfare or the property of others; Whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activity will be of a temporary or permanent nature; Whether the activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S.; and The current condition and relative value of functions being performed by areas affected by the proposed activity. Will not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in subsections 4.2.8 through 4.2.8.2 of the Basis of Review. . . . THE BASIS OF REVIEW The District has adopted the BOR and incorporated it by reference by Florida Administrative Code Rule 40E- 4.091(1)(a). The standards and criteria found in the BOR are used to determine whether an applicant has given reasonable assurances that the conditions for issuance of an ERP have been satisfied. Section 1.3 of the BOR provides, in part, as follows: . . . Compliance with the criteria established herein [the BOR] constitutes a presumption that the project proposal is in conformance with the conditions for issuance set forth in Rules 40E-4.301 and 40E-4.302, F.A.C. WATER QUANTITY The term “control elevation” describes the level of freshwater water bodies established by a SWM system. The existing SWM system has a control elevation of 17’ NGVD. The control elevation for the proposed lake system will be raised to 18’ NGVD, and the control elevation for the proposed Natural Area will be raised to 19’ NGVD. Raising the control elevations will permit more treatment of storm water prior to discharge and will permit a more controlled discharge. In addition, raising the control elevation will lessen seepage onto the project site from adjacent wetlands. The Applicants provided reasonable assurances that the proposed project will not cause adverse water quantity impacts to receiving waters and adjacent lands, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E- 4.301(a). The Applicants provided reasonable assurances that the proposed project will not cause adverse flooding to on-site or off-site property, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E-4.301(b). The Applicants provided reasonable assurances that the proposed project will not cause adverse impacts to existing surface water storage and conveyance capabilities, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E-4.301(c). VALUE OF FUNCTIONS OF WETLANDS AND SURFACE WATERS Florida Administrative Code Rule 40E-4.301(d), requires the Applicants to establish that “. . . the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system . . .” “. . . will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters.” The District established that the term “value of functions,” as used in the rule, refers to habitat and life support functions. Because there are no wetlands or delineated surface waters on the Mecca Farms site, there are no direct adverse impacts to the functions that wetlands provide to fish and wildlife. The Applicants have provided reasonable assurances to demonstrate that the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters will not be adversely affected. The existing project site does not contain nesting areas for wetland-dependent endangered or threatened wildlife species or species of special concern. The potential for use of the existing project site for nesting by such species is minimal. The existing project site does contain habitat for the American Alligator and foraging habitat for wading birds and birds of prey. The primary foraging habitat on the existing site is around the perimeter of the existing 272-acre impoundment area in the northeast portion of the site. The existing impoundment will be replaced by on-site storm water treatment lakes and the BRP Natural Area that will have shallow banks planted with wetland plant species common to the area. Wildlife is opportunistic; and wading birds commonly feed in areas where there is water, wetland vegetation and wetland plants. The end result will be that the proposed project will have more and better foraging habitat acreage than the existing site. The Natural Area will provide a wetland buffer between the developed area and CWMA that will prevent any adverse impacts both to the wetlands and other surface waters in CWMA and to the value of the functions those wetlands and other surface waters provide to fish, wildlife, and listed species. The Natural Area will provide a wetland buffer between the developed area and Unit 11 that will prevent any adverse impacts both to the wetlands and other surface waters in Unit 11 and to the value of the functions those wetlands and other surface waters provide to fish, wildlife, and listed species. There was no competent evidence that the proposed project would impact the ability of the Florida Fish and Wildlife Conservation Commission to manage the CWMA through control burns or otherwise, thereby adversely affecting the diversity or abundance of fish and wildlife (including endangered species and their habitats). Petitioners attempted to raise the issue of mosquito control in their Petitions and at the Final Hearing. The allegations pertaining to mosquito control were struck by the District and Special Condition Number 26 was added before the Petitions were referred to DOAH. Petitioners made no attempt to amend their Petitions and have not challenged Special Condition 26. The Addendum to Staff Report (SFWMD Ex. 2) contains the following Special Condition Number 26: “Upon submittal of an application for construction of any buildings, the permittee shall submit a mosquito control plan for review and approval by District Staff.” Since there will be no buildings containing people or other facilities which would encourage the use of mosquito spraying, it is appropriate for the mosquito control condition to apply to only future phases of construction. There was no competent evidence of impacts attributable to pesticides associated with the application for the SWM system or for Phase 1A construction and operation that would adversely affect the diversity or abundance of fish and wildlife including endangered species and their habitats. The Applicants have satisfied the criteria set forth in Florida Administrative Code Rule 40E-4.301(d). WATER QUALITY The primary concern during Phase 1A construction will be erosion control. Best Management Practices (“BMPs”) are operational and design elements used to either eliminate or reduce the amount of pollutants at the source so they do not get into a SWM system or move downstream. To contain erosion in Phase 1A, the Applicants will use the following BMPs: Silt screens and turbidity barriers within existing ditches and around the perimeter of property. Planned construction sequencing to reduce movement and stock piling of material; Slope stabilization and seeding or sodding of graded areas; and Containment of construction materials with berms. All erosion and turbidity control measures will remain in place until the completion of the on-site construction and approval by the District’s post-permit compliance staff. The Applicants provided reasonable assurances that the proposed Phase 1A construction activities will not adversely impact the quality of receiving waters and that those activities will not violate State water quality standards. Section 5.2.1, BOR, requires that a SWM system provide wet detention for the first one inch of runoff. The proposed SWM system will provide wet detention for one and one-half inches of runoff. The Applicants provided reasonable assurances to demonstrate that the technical criteria in the BOR will be met. Under Section 1.3 of the BOR, compliance with the criteria in the BOR constitutes a presumption that the Proposed Project is in conformance with the conditions for issuance. This presumption was not rebutted by the Petitioners. The lake system will include planted littoral zones to provide additional uptake of pollutants. A filter marsh is also included in the southern lake. All of the storm water runoff from the lakes will pass through the filter marsh, which will be planted with wetland plants. The filter marsh will provide additional polishing of pollutants, uptake, and filtering through the plants. The discharge will then go into the BRP, which will provide the discharge additional uptake and filtering. BMPs utilized during the Operations and Maintenance phase will include regular maintenance inspections and cleaning of the SWM system, street-sweeping, litter control programs, roadway maintenance inspections and repair schedule, municipal waste collection, pollution prevention education programs, pesticides, herbicides and fertilizer storage, and application training and education. The littoral zones, filter marsh, BRP natural area, and BMPs were not included in the water quality calculations and are over and above rule requirements. The Applicants provided reasonable assurances to demonstrate that the proposed project will not adversely affect the quality of receiving waters. Therefore, Rule 40E- 4.301(1)(e), F.A.C., will be satisfied and water quality standards will not be violated. HAZARDOUS SUBSTANCES Pursuant to Section 5.5.5 of the BOR, commercial or industrial zoned projects shall provide at least one-half inch of dry detention or retention pretreatment as part of the required retention/detention, unless reasonable assurances can be offered that hazardous materials will not enter the project's SWM system. The Addendum to Staff Report reflects the following Special Condition 25 pertaining to hazardous materials: Upon submittal of an application for construction of commercial or industrial uses the permittee shall submit a plan that provides reasonable assurances that hazardous materials will not enter the surface water management system pursuant to the requirements of section 5.2.2(a) of the Basis of Review. Applicable permitting criteria does not require the Applicants to present a hazardous substances plan at this point because no facilities that will contain hazardous materials are part of the Phase 1A construction. SECONDARY IMPACTS Florida Administrative Code Rule 40E-4.301(1)(f) and Section 4.1.1(f) of the BOR, require an applicant to provide reasonable assurances that the proposed activities will not cause adverse secondary impacts to the water resources. A secondary impact is an indirect effect of a project resulting in adverse effects to wetlands or other surface waters. The District considers those adverse effects that would not occur "but for" the activities that are closely linked and causally related to the activity under review. This standard is discussed further in the Conclusions of Law section of this Recommended Order. The County’s Exhibit 3 is a secondary impact analysis identifying the secondary impacts that may potentially result from the proposed project. These impacts are: 1) the widening of SPW Road; 2) the construction of an FPL substation; 3) the extension of PGA Boulevard; and 4) the potential relocation of a runway at North County Airport. The secondary impact analysis performed pursuant to the Uniform Mitigation Assessment Method (UMAM) contained in Florida Administrative Code Chapter 62-345 reflects that up to 153.3 acres of wetlands may be partially or completely impacted by these secondary impacts, resulting in approximately 71.21 units of functional loss. Where future activities are expected to directly impact wetlands, secondary impacts were assessed based on the loss of all current functional value within the direct footprint of that activity. Additionally, an assessment was conducted to determine the degree of partial functional loss where impacts beyond the footprint of these activities are anticipated. SPW Road is an existing dirt road which is in the County's five-year road plan to widen as a four-lane paved road. Because the widening of the existing dirt road to a four-lane paved road is part of the five-year road plan, the impacts of that widening are not attributable to the subject project. However, as part of the proposed project, it is proposed to widen SPW Road to a six-lane paved road. The additional impacts associated with the widening from four to six lanes will be caused by, and are linked to, the proposed project. These impacts amount to approximately 2.2 acres. The FPL substation, which is proposed to service the proposed project, may result in 1.6 acres of potential direct impacts to wetlands. In addition, 1.0 acre of potential indirect secondary impacts may occur to wetlands that are not going to be dredged and filled. Those indirect secondary impacts may have some adverse impact on the functional value to those wetlands for wildlife utilization. The extension of PGA Boulevard to the Mecca Farms site has the potential to result in 45.6 acres of direct impacts to wetlands and 56.6 acres of indirect secondary wetland impacts which will not be dredged or filled, but will be in close proximity to the road. The secondary impact assessment for PGA Boulevard assumed the incorporation of wildlife crossings to minimize habitat fragmentation. If the airport runway needs to be shifted, potential direct wetland impacts to an additional 22.7 acres may occur. Indirect impacts to 23.6 acres of wetlands in close proximity could also occur. Runway relocation may or may not be necessary due to the PGA Boulevard extension; however, the analysis assumed the need for the relocation. Each of the projects listed above as potential secondary impacts will require a separate construction and operation permit from the District. The issuance of this permit does not in any way guarantee the issuance of permits for any of these identified potential secondary impacts. MITIGATION PLAN The Applicants provided a conceptual mitigation plan using UMAM to demonstrate how potential secondary impacts could be offset. Mitigation options have the potential to provide more than twice the functional gain than the functional loss from the identified secondary impacts. The conceptual mitigation options include: 194 acres of the land that had been acquired for future mitigation needs in Unit 11. 227 acres of the BRP natural area. 32.6 acres in the southern lake wetland along with proposed upland habitat. Sufficient mitigation is available in these options to offset the potential secondary impacts. The mitigation for the four potential secondary impacts is not required to be implemented now because the impacts are not occurring now. Section 4.2.7 of the BOR requires that the District consider those future impacts now and that a conceptual mitigation plan be provided to demonstrate and provide reasonable assurances that those impacts, in fact, can be offset in the future. The Governor and Cabinet sitting as the Board of Trustees considered and approved a request for public easement of approximately 30 acres to use a portion of CWMA for SPW Road, an FPL substation, and the land area that may be needed by District in the future for the connection to the flow-way. As consideration in exchange for the public easement over 30 acres, the County will transfer fee simple title of 60 acres to the State. This public easement also provides a benefit for CERP as it includes the small portion that the District is going to need for its future CERP project to connect to the flow-way on the proposed project site. The Applicants provided reasonable assurances that mitigation will offset secondary impacts to wetlands and other surface waters. UNIDENTIFIED SECONDARY IMPACTS Testimony at the final hearing raised a question as to whether there is nesting or roosting by listed wading bird species in adjacent off-site wetlands outside the eastern boundary of the project site. Evidence was inconclusive on nesting or roosting in these areas. Because the status of adjacent listed wading bird nesting or roosting is uncertain, the District suggested in its Proposed Recommended Order that a special condition requiring a wildlife survey prior to construction near the eastern project boundary be added to the permit as follows: Prior to application for construction within 1000 feet of the eastern boundary of the above-ground impoundment, the applicant shall conduct a wildlife survey to identify any nesting or roosting areas in the adjoining off-site wetlands utilized by listed species of wading birds. If such nesting or roosting areas are found the permittee shall, if determined necessary by the District, incorporate additional buffers or other appropriate measures to ensure protection of these wetland functions. The District represented in its Proposed Recommended Order that the County has no objection to adding the foregoing condition. CUMULATIVE IMPACTS Pursuant to Section 373.414(8), Florida Statutes, the District is required to consider cumulative impacts upon wetlands and other surface waters delineated in Section 373.421(1), Florida Statutes, within the same drainage basin. Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin. The cumulative impact analysis is geographically based upon the drainage basins described in Figure 4.2.8-1 of the BOR. Cumulative impacts are unacceptable when they would result in unacceptable adverse impacts to the functions of wetlands and surface waters within a drainage basin. There are no wetlands or other surface waters delineated pursuant to Section 373.421(1), Florida Statutes, on the Mecca Farms site. Therefore, no cumulative impacts are created by the direct impacts of the project. Cumulative impacts may be created by a project's secondary impacts. If a wetland impact has been appropriately mitigated on-site within the drainage basin, there is no residual impact, and therefore no cumulative impact. The PGA Boulevard extension, a portion of the SPW Road widening, and the airport runway relocation are located within the C-18 Basin. The proposed mitigation options are all located in the C-18 Basin and will offset those impacts. Those potential secondary impacts are considered to meet the cumulative impact requirements of Section 373.414(8), Florida Statutes. The Applicants provided reasonable assurances that the proposed project will not result in cumulative impacts to the C-18 Basin. The FPL substation is located within the L-8 Drainage Basin. The majority of the SPW Road expansion is located within the C-18 Basin, but a portion is located on the basin line between the C-18 Basin and the L-8 Basin. Because the mitigation for the L-8 impacts are proposed in a different basin, the Applicants were required to conduct a cumulative impact analysis for the L-8 Basin impacts. Based on the Florida Land Use Cover Classification System, there are 43,457 acres of freshwater wetlands within the L-8 Basin. Approximately 41,000 acres of the wetlands in L-8 Basin are in public ownership. This total constitutes approximately 95 percent of all the wetlands in the L-8 Basin. Public ownership of these wetlands provide a high level of assurance that these lands will be protected in perpetuity. The Respondents established that proposed mitigation can fully offset the potential impacts from the SPW Road expansion and the FPL substation and the approximately four acres of impacted wetlands in the L-8 Basin. The Applicants provided reasonable assurances that there are no unacceptable adverse cumulative impacts on the L-8 Basin.4 GROUND WATER FLOWS, SURFACE WATER FLOWS, AND MINIMUM FLOWS AND LEVELS Florida Administrative Code Rule 40E-4.301(1)(g) requires an applicant to provide reasonable assurances that the proposed activity will not adversely impact the maintenance of surface or ground water levels or surface water flows established pursuant to Section 373.042, Florida Statutes. The term "maintenance of surface and groundwater levels or surface water flows" in Florida Administrative Code Rule 40E-4.301(1)(g) means that a project will not adversely impact the maintenance of surface water flows that contribute to meeting the minimum flow for the water body. An adverse impact to the maintenance of surface or groundwater levels or surface water flows may occur when a project discharging to a water body with a designated minimum flow level is proposed to be diverted. An analysis was done to compare the peak discharge rate from the existing SWM system on the Mecca Farms site with the projected peak discharge rate from the proposed SWM system. The analysis showed that the peak discharge rate under the proposed system will be less than that of the existing system. That result was expected since the proposed system will have higher control elevations, which, as noted above, will provide better treatment and permit a better control of the discharge into the C-18 Canal. Under the existing SWM system, storm event water in a dry period is frequently stored in the existing impoundment for future irrigation purposes. Under the proposed SWM system such storm event water will be discharged downstream, which will benefit those downstream areas during dry periods. The proposed system will also provide better control over pulse discharges during heavy storm events. The Applicants provided reasonable assurances that the proposed activities will not adversely impact the maintenance of surface or ground levels or surface water flows as required by Florida Administrative Code Rule 40E-4.301(1)(g). THE DISTRICT’S OBJECTIVES Sections 373.414 and 373.416, Florida Statutes, require an applicant to provide reasonable assurances that a regulated activity will not be harmful to the water resources and will not be inconsistent with the overall objectives of the District. Congress initially authorized the Central and Southern Florida (“C&SF”) Project in 1948. Thereafter extensive work was undertaken pertaining to flood control; water supply for municipal, industrial, and agricultural uses; prevention of saltwater intrusion; and protection of fish and wildlife. The work included construction of a primary system of 1000 miles each of levees and canals, 150 water-control structures, and 16 major pump stations. Unintended consequences of the C&SF Project have included the irreversible loss of vast areas of wetlands, including half of the original Everglades; the alteration in the water storage, timing, and flow capacities of natural drainage systems; and the degradation of water quality and habitat due to over-drainage or extreme fluctuations in the timing and delivery of fresh water into the coastal wetlands and estuaries. In 1992, Congress authorized the C&SF Project Comprehensive Review Study, which is generally referred to as the “Restudy.” The objective of the Restudy was to reexamine the C&SF Project to determine the feasibility of modifying the project to restore the South Florida ecosystem and provide for the other water-related needs of the region, such as water supply and flood protection. In April 1999, the U.S. Army Corps of Engineers issued the Central and Southern Florida Project Comprehensive Review Study Final Integrated Feasibility Report and Programmatic Environmental Impact Statement (“Restudy Report”). The Restudy Report recommends a comprehensive plan for the restoration, protection, and preservation of the water resources of Central and South Florida. The resulting plan is known as CERP. The North Palm Beach County Part I project, which includes restoration of the Northwest Fork of the Loxahatchee River (“NWFLR”), is a component of CERP. The successful completion of CERP and the successful restoration of the NWFLR are high-priority objectives of the District. The Loxahatchee River is an important feature of the South Florida ecosystem, nationally and internationally unique, and an important natural and economic resource. Rules pertaining to MFL for the NWFLR and for the recovery of the NWFLR are found at Florida Administrative Code Rule 40E-8.011; 40E-8.221(4); and 40E-8.421. Recovery goals, which are not presently being met, have been established; and strategies to meet those goals have been identified. The Mecca Farms site is located within the boundaries of the CERP North Palm Beach County Part I project and has the potential to affect CERP and the restoration of the NWFLR. Projects that potentially would affect or would be within or adjacent to a CERP project are evaluated on a case-by- case basis to determine whether a proposed project would not be inconsistent with CERP and other District objectives. There was a dispute between Respondents and Petitioners as to whether the proposed project was inconsistent with the District’s objectives, including CERP and its goals pertaining to the restoration of the NWFLR. Petitioners contend that the District has insufficient evidence that the Mecca Farms will not be needed for the construction of a reservoir. That contention is rejected. The greater weight of the credible evidence established that sufficient storage is available at a superior site known as the Palm Beach Aggregates (PBA) site in the L-8 Basin, which is a unique geological site that will provide in-ground storage of water.5 Water from the PBA storage site can be conveyed to the NWFLR to increase dry season flows. Water can be stored at the PBA site in the wet season to prevent potentially damaging high flows. The L-8 Basin, which is adjacent to the C-18 Basin, receives more water during the wet season than it uses. This means that at present a significant amount of water must be discharged to tide (lost) during the wet season to provide for flood protection in this area. As envisioned, the water currently lost to tide could be stored at the PBA site for use during the dry season. By combining the water storage in the L-8 Basin with connective flow-ways to the C-18 Canal, water demands within the C-18 Basin, including the NWFLR, can also be met by the PBA storage site.6 An increase in freshwater flows to the NWFLR will further the District’s restoration goals for the NWFLR. Storage at PBA has regional benefits for other significant natural areas because it will provide additional flows to the Loxahatchee Slough and Grassy Waters Preserve. Those additional flows will further the District’s CERP goals. Since October of 2003, County staff and the District’s ERP staff have coordinated review of the subject project with the District’s CERP Planning and Federal Projects Division and other District staff working on projects in this region. The County asked the District to determine if the Mecca Farms’ site could in some way accommodate CERP objectives, and three alternatives were considered: 1) no action; 2) a reservoir; and 3) a flow-way. As opposed to a reservoir, the more valuable and the more practical, use of the Mecca Farms site would be as part of the system to convey the stored water to the areas that would most benefit from its discharge. The proposed flow-way in the BRP Natural Area would be an integral part of that conveyance system and would provide the District with greater flexibility in managing and directing the discharge of the water stored at the PBA site. Prior to the development of the flow-way concept as part of the proposed development, CERP identified a single route to take water from PBA to the NWFLR. The flow-way will provide an additional route from PBA to the NWFLR. That additional route will provide the District with greater operational flexibility. The flow-way will complement the L-8 Basin flow- way and help reduce peak flows to the NWFLR and the Estuary. The flow-way also provides a potential route allowing excess water to be brought back from the C-18 Basin to the PBA site for storage. There are no other potential routes that allow water to be directed from the C-18 Basin in the wet season to the PBA site. The flow-way provides a feature that was not part of the CERP original plan and is therefore an unanticipated benefit for CERP. The Applicants provided reasonable assurances that the proposed project is not inconsistent with the District’s objectives.7

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that the District issue the subject ERP for the conceptual approval of the SWM system for the BRP and the Phase 1A construction and operation subject to the general and special conditions set forth in the Staff Report and the Amended Staff Report. It is further RECOMMENDED that the District add the following special condition: Prior to application for construction within 1000 feet of the eastern boundary of the above-ground impoundment, the applicants shall conduct a wildlife survey to identify any nesting or roosting areas in the adjoining off-site wetlands utilized by listed species of wading birds. If such nesting or roosting areas are found the permittee shall, if determined necessary by the District, incorporate additional buffers or other appropriate measures to ensure protection of these wetland functions. DONE AND ENTERED this 3rd day of December, 2004, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 3rd day of December, 2004.

Florida Laws (9) 120.569120.57120.574267.061373.042373.414373.416373.421403.973
# 9
HOWARD EHMER AND NINA EHMER vs CITY OF DELTONA AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 04-002403 (2004)
Division of Administrative Hearings, Florida Filed:Deltona, Florida Jul. 12, 2004 Number: 04-002403 Latest Update: Jul. 25, 2005

The Issue The issue is whether the applicant for an Environmental Resource Permit ("ERP"), the City of Deltona ("City" or "Applicant"), has provided reasonable assurance that the system proposed complies with the water quantity, environmental, and water quality criteria of the St. Johns River Water Management District's ("District") ERP regulations set forth in Florida Administrative Code Chapter 40C-4, and the Applicant's Handbook: Management and Storage of Surface Waters (2005).

Findings Of Fact The District is a special taxing district created by Chapter 373, Florida Statutes, charged with the duty to prevent harm to the water resources of the District, and to administer and enforce Chapter 373, Florida Statutes, and the rules promulgated thereunder. The City of Deltona is a municipal government established under the provisions of Chapter 165, Florida Statutes. The Lake Theresa Basin is comprised primarily of a system of interconnected lakes extending from Lake Macy in the City of Lake Helen to the Butler Chain of Lakes (Lake Butler and Lake Doyle). The Lake Theresa Basin is land-locked and does not have a natural outfall to Lake Monroe and the St. Johns River. In 2003, after an extended period of above-normal rainfall in the Deltona area, the lakes within the land-locked Lake Theresa Basin staged to extremely high elevations that resulted in standing water in residential yards, and rendered some septic systems inoperable. Lake levels within the Lake Theresa Basin continued to rise and were in danger of rising above the finished floor elevations of some residences within the basin. On March 25, 2003, the District issued an Emergency Order (F.O.R. No. 2003-38) authorizing the construction and short-term operation of the Lake Doyle and Lake Bethel Emergency Overflow Interconnection. Since wetland and surface water impacts would occur, the Emergency Order required the City of Deltona to obtain an ERP for the system. The project area is 4.1 acres, and the system consists of a variable water structure on the west shore of Lake Doyle connected to a series of pipes, swales, water control structures, and wetland systems which outfall to a finger canal of Lake Bethel, with ultimate discharge to Lake Monroe and the St. Johns River. The first segment of the system extends downstream from the weir structure on the west shore of Lake Doyle via a pipe entrenched in the upland berm of the Sheryl Drive right-of-way. The pipe passes under Doyle Road and through xeric pine-oak uplands to the northeast shore of a large (approximately 15 acres) deepwater marsh. Water flows south through the deepwater marsh where it outfalls through four pipes at Ledford Drive. Two of the four pipes are overflow structures, controlled by canal gates. The pipes at Ledford Drive discharge into a ditch and into a large (greater than 20 acres) shallow bay swamp. The south end of the bay swamp is defined (and somewhat impounded) by a 19th Century railroad grade. Water flows through the bay swamp where it outfalls through five pipes at the railroad grade. Three of the five pipes are overflow structures, controlled by channel boards. The pipes at the railroad grade discharge to a 1500-foot long finger canal that was dug some time during the period 1940-1972 from the north central shore of Lake Bethel. The overflow interconnection system has three locations whereby the system can be shut down: 1) Lake Doyle--a control weir, controlled by three sluice gates; 2) Ledford Drive--two thirty-inch reinforced concrete pipes, controlled by canal gates; and 3) railroad grade--three thirty-inch reinforced concrete pipes, controlled by channel boards (collectively referred to as "Overflow Structures"). The Overflow Structures are designed to carry the discharge of water from Lake Doyle to Lake Bethel. With the Overflow Structures closed the system returns to pre-construction characteristics, meaning there will be no increase or decrease in the quantity or quality of water throughout the path of the system as a result of the project. An unequivocal condition of the permit is that the system would operate with all of the Overflow Structures closed. As an added assurance, the City proposes to place a brick and mortar plug in the Lake Doyle weir structure outfall pipe to prevent any discharge from the weir. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the water level in Lake Doyle rises above an elevation of 24.5 feet. The District shall require a separate permit application to be submitted for such future plans. Petitioner, Barbara Ash, has lived on Lake Theresa for 19 years. Ms. Ash lives upstream from the area of the weir that will be plugged in accordance with the ERP. She does not trust either the City of Deltona to comply with or the District to enforce the conditions of the ERP applied for by the City. Petitioner, Barbara Ash, also served as the qualified representative for Petitioners, Francell Frei, Bernard J. and Virginia Patterson, and Ted and Carol Sullivan. Ms. Ash represented that Ms. Frei has lived on Lake Theresa for 12 years, and both the Pattersons and the Sullivans live on Lake Louise, which is within the area of concern in this proceeding. Petitioner, Diana Bauer, has lived on Lake Theresa since February 2004. She fears that the lake will become too dry if the system is allowed to flow. She also believes the wildlife will be adversely affected if the water levels are too low since many species need a swampy or wet environment to thrive. She fears her property value will decrease as a result of the approval of the ERP. She also does not trust either the City to comply with or the District to enforce the conditions of the ERP. Petitioner, Howard Ehmer, lives two to three hundred yards down Lake Theresa from Ms. Bauer. He is concerned about the lake bed being too dry and attracting people on all terrain vehicles who enjoy driving around the lake bottom. He is concerned about his property value decreasing if the lake bed is dry. Further, when the lake level is too low, people cannot enjoy water skiing, boating, and fishing on Lake Theresa. Petitioner, Phillip Lott, a Florida native, has also owned and lived on property abutting Lake Theresa since 1995. Mr. Lott has a Ph.D. in plant ecology, and M.P.A. in coastal zone studies, an M.B.A. in international business, and a B.S. in environmental resource management and planning. Mr. Lott has been well acquainted with the water levels on Lake Theresa for many years. Based upon his personal observations of the lake systems in the Deltona area over the years, Mr. Lott has seen levels fluctuate greatly based upon periods of heavy and light rainfall. Mr. Lott is concerned that the District will permit the City to open the weir to let water flow through the system and cause flooding in some areas and low water levels in other areas. He fears that the District will allow the water to flow and upset the environmental balance, but he admits that this ERP application is for a closed system that will not allow the water to flow as he fears. Mr. Lott similarly does not trust the City to comply with and the District to enforce the conditions of the ERP. Petitioners, James E. and Alicia M. Peake, who were represented by Steven L. Spratt at hearing as their qualified representative, live on Lake Louise, which is interconnected with the Lake Theresa basin. The Peakes are concerned that if the level of Lake Louise drops below 21 feet, nine inches, they will not be able to use the boat launch ramps on the lake. Petitioner, Steven L. Spratt, also lives on Lake Louise, and is concerned about the water levels becoming so low that he cannot use the boat launch on the lake. He has lived on the lake since 2000, and remembers when the water level was extremely low. He fears that approval of the ERP in this case will result in low levels of water once again. Petitioner, Gloria Benoit, has live on Lake Theresa for two years. She also enjoys watching recreational activities on the lake, and feels that approval of the ERP will devalue her lakefront property. Ms. Benoit appeared at the first day of the hearing, but offered no testimony on her behalf. J. Christy Wilson, Esquire, appeared prior to the final hearing as counsel of record for Petitioners, Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow. Neither Ms. Wilson nor any of the three Petitioners she represented appeared at any time during the hearing, filed any pleadings seeking to excuse themselves from appearing at the final hearing, or offered any evidence, testimony, pre- or post- hearing submittals. Petitioner, Gary Jensen, did not appear at hearing, did not file any pleadings or papers seeking to be excused from appearing at the final hearing, and did not offer any evidence, testimony, pre- or post-hearing submittals. Both the City and the District recognize that areas downstream from the project site, such as Stone Island and Sanford, have experienced flooding in the past in time of high amounts of rainfall. The system proposed by the City for this ERP will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel. So long as the overflow structures are closed, the system will mimic pre-construction flow patterns, with no increase in volume flowing downstream. The District has considered the environment in its proposed approval of the ERP. The area abutting the project is little urbanized and provides good aquatic and emergent marsh habitat. With the exception of the western shore area of the deepwater marsh ("west marsh area"), the bay swamp and remaining deepwater marsh area have good ecological value. In the 1940's, the west marsh area was incorporated into the drainage system of a poultry farm that occupied the site. This area apparently suffered increased nutrient influxes and sedimentation that contributed to a proliferation of floating mats of aquatic plants and organic debris. These tussocks reduced the deepwater marsh's open water and diminished the historical marsh habitat. Water under the tussocks is typically anoxic owing to total shading by tussocks and reduced water circulation. Thick, soft, anaerobic muck has accumulated under the matted vegetation. Exotic shrubs (primrose willow Ludwigia peruvania) and other plants (cattails Typha spp.) dominate the tussocks. The construction of the project, from the 2003 Emergency Order, resulted in adverse impacts to 1.3 acres of wetlands having moderately high- to high ecological value and 0.2 acres of other surface waters. The 0.2 acre impact to other surface waters was to the lake bottom and the shoreline of Lake Doyle where the weir structure was installed. The 0.3 acres of wetland impacts occurred at the upper end of the deepwater marsh where the pipe was installed. The largest wetland impact (1.0 acre) was to the bay swamp. The bay swamp is a shallow body dominated by low hummocks and pools connected inefficiently by shallow braided channels and one acre is filled with a 1-2 foot layer of sediment following swamp channelization. Disturbance plants (e.g., primrose willow, Ludwigia peruvania, and elderberry Sambucus Canadensis) now colonize the sediment plume. Pursuant to the District's elimination and reduction criteria, the applicant must implement practicable design modifications, which would reduce or eliminate adverse impacts to wetlands and other surface waters. A proposed modification, which is not technically capable of being done, is not economically viable, or which adversely affects public safety through endangerment of lives or property is not considered "practicable." The City reduced and/or eliminated the impacts to the lake bottom and shoreline of Lake Doyle and deepwater marsh, to the extent practicable. The impacts were the minimum necessary to install the weir structure and pipe for the system; the weir structure and pipe were carefully installed on the edges of the wetland and surface water systems, resulting in a minimum amount of grading and disturbance. To compensate for the loss of 1.3 acres of wetlands and 0.2 acres of other surface waters, the City proposes to preserve a total of 27.5 acres of wetlands, bay swamp, marsh, and contiguous uplands. Included in this 27.5 acres are 6.4 acres of the west marsh, which are to be restored. The parties stipulated that the mitigation plan would adequately compensate for losses of ecological function (e.g. wildlife habitat and biodiversity, etc.) resulting from the project. Water quality is a concern for the District. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies for nitrogen, phosphorous, and dissolved oxygen. Water quality data for Lake Monroe indicate the lake has experienced high levels of nitrogen and phosphorous and low levels of dissolved oxygen. Prior to construction of the project, there was no natural outfall from the Lake Theresa Basin to Lake Monroe and therefore no contribution from this basin to nitrogen and phosphorous loadings to Lake Monroe. Lake Colby, Three Island Lakes (a/k/a Lake Sixma), and the Savannah are surface waters within the Lake Theresa Basin for which minimum levels have been adopted pursuant to Florida Administrative Code Chapter 40C-8. The system will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel, resulting in no outfall from the Theresa Basin to Lake Monroe. Minimum flows established for surface waters within the Lake Theresa Basin will not be adversely impacted. Under the first part of the secondary impact test, the City must provide reasonable assurance that the secondary impacts from construction, alteration, and intended or reasonable expected use of the project will not adversely affect the functions of adjacent wetlands or surface waters. The system is designed as a low intensity project. As proposed, little activity and maintenance are expected in the project site area. The reasonably expected use of the system will not cause adverse impacts to the functions of the wetlands and other surface waters. None of the wetland areas adjacent to uplands are used by listed species for nesting or denning. In its pre-construction state, the project area did not cause or contribute to state water quality violations. Under the second part of the secondary impact test, the City must provide reasonable assurance that the construction, alteration, and intended or reasonably expected uses of the system will not adversely affect the ecological value of the uplands to aquatic or wetland dependent species for enabling existing nesting or denning by these species. There are no listed threatened or endangered species within the project site area. Under the third part of the secondary impact test, and as part of the public interest test, the District must consider any other relevant activities that are closely linked and causally related to any proposed dredging or filling which will cause impacts to significant historical and archaeological resources. When making this determination, the District is required, by rule, to consult with the Division of Historical Resources. The Division of Historical Resources indicated that no historical or archaeological resources are likely present on the site. No impacts to significant historical and archaeological resources are expected. Under the fourth part of the secondary impact test, the City must demonstrate that certain additional activities and future phases of a project will not result in adverse impacts to the functions of wetlands or water quality violations. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the level in Lake Doyle rises above an elevation of 24.5 feet. Based upon the plans and calculations submitted, the proposed future phase, without additional measures, could result in minor increases in the loadings of nitrogen and phosphorous to Lake Monroe. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies due to water quality data indicating the lake has experienced high levels of nitrogen and phosphorous, and low levels of dissolved oxygen. Under this potential future phase, there would be an outfall from the Lake Theresa Basin to Lake Monroe. To address the impact on water quality of this potential future phase, the City has submitted a loading reduction plan for nitrogen, phosphorous, and dissolved oxygen. The plan includes compensating treatment to fully offset the potential increased nutrient loadings to Lake Monroe. Specifically, the loading reduction plan includes: Construction and operation of compensating treatment systems to fully offset anticipated increased nutrient loadings to Lake Monroe. Weekly water quality monitoring of the discharge from Lake Doyle for total phosphorous and total nitrogen. A requirement that the overflow structure be closed if the total phosphorous level reaches 0.18 mg/l or higher or the total nitrogen level reaches 1.2 mg/l or higher in any given week and will remain closed until levels fall below those limits. The implementation of these water quality mitigation measures will result in a net improvement of the water quality in Lake Monroe for nitrogen, phosphorous, or dissolved oxygen. The future phase was conceptually evaluated by the District for impacts to wetland functions. The future phase as proposed could result in adverse impacts to wetland functions. Operation of the system with the overflow structures open could impact the bay swamp and deepwater marsh. The City has demonstrated that any adverse impacts could be offset through mitigation. Based upon the information provided by the City and general engineering principles, the system is capable of functioning as proposed. The City of Deltona will be responsible for the operation, maintenance, and repair of the surface waster management system. A local government is an acceptable operation and maintenance entity under District rules. The public interest test has seven criteria. The public interest test requires the District to evaluate only those parts of the project actually located in, on, or over surface waters or wetlands, to determine whether a factor is positive, neutral, or negative, and then to balance these factors against each other. The seven factors are as follows: the public health, safety, or welfare of others; conservation of fish and wildlife and their habitats; fishing, recreational value, and marine productivity; temporary or permanent nature; 5) navigation, water flow, erosion, and shoaling; 6) the current condition and relative value of functions; and 7) historical and archaeological resources. There are no identified environmental hazards or improvements to public health and safety. The District does not consider impacts to property values. To offset any adverse impacts to fish and wildlife and their habitats, the City has proposed mitigation. The areas of the project in, on, or over wetlands do not provide recreational opportunities. Construction and operation of the project located in, on, or over wetlands will be permanent in nature. Construction and operation of the project located in, on, or over wetlands will not cause shoaling, and does not provide navigational opportunities. The mitigation will offset the relative value of functions performed by areas affected by the proposed project. No historical or archaeological resources are likely on the site of the project. The mitigation of the project is located within the same drainage basin as the project and offsets the adverse impacts. The project is not expected to cause unacceptable cumulative impacts.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered granting the City of Deltona's application for an environmental resource permit with the conditions set forth in the Technical Staff Report, and dismissing the Petitions for Formal Administrative Hearing filed by Gary Jensen in Case No. 04-2405, and by Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow in Case No. 04-3048. DONE AND ENTERED this 27th day of May, 2005, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 2005. COPIES FURNISHED: George Trovato, Esquire City of Deltona 2345 Providence Boulevard Deltona, Florida 32725 Diana E. Bauer 1324 Tartan Avenue Deltona, Florida 32738 Barbara Ash, Qualified Representative 943 South Dean Circle Deltona, Florida 32738-6801 Phillip Lott 948 North Watt Circle Deltona, Florida Howard Ehmer Nina Ehmer 32738-7919 1081 Anza Court Deltona, Florida 32738 Francell Frei 1080 Peak Circle Deltona, Florida 32738 Bernard T. Patterson Virginia T. Patterson 2518 Sheffield Drive Deltona, Florida 32738 Kealey A. West, Esquire St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177 J. Christy Wilson, Esquire Wilson, Garber & Small, P.A. 437 North Magnolia Avenue Orlando, Florida 32801 Gloria Benoit 1300 Tartan Avenue Deltona, Florida 32738 Gary Jensen 1298 Tartan Avenue Deltona, Florida 32738 James E. Peake Alicia M. Peake 2442 Weatherford Drive Deltona, Florida 32738 Steven L. Spratt 2492 Weatherford Drive Deltona, Florida 32738 Ted Sullivan 1489 Timbercrest Drive Deltona, Florida 32738 Kirby Green, Executive Director St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177

Florida Laws (3) 120.569120.57373.086 Florida Administrative Code (6) 40C-4.30140C-4.30240C-4.33140C-4.75162-302.30062-4.242
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer