Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES J. RUSSO, 82-000446 (1982)
Division of Administrative Hearings, Florida Number: 82-000446 Latest Update: Apr. 01, 1983

Findings Of Fact The Respondent is a registered building contractor having been issued license No. RB0032203. At all times material to this proceeding, he was the president and qualifying officer of RBR Construction Corporation. The Petitioner is an agency of the State of Florida charged with the licensing, regulation of licensure status and appropriate practice standards as pertinent hereto of construction contractors in the State of Florida. On April 11, 1979, the Respondent, doing business as RBR Construction Corporation, entered into a contract with Kathleen R. and George K. Beebe, pursuant to which he was to construct a duplex for the Beebes for a net contracted amount of $47,500. The Respondent engaged in the construction of the duplex until it was approximately 86 percent complete and then ceased all work on the project. At the time the Respondent ceased work on it, he had already received $44,290 of the contracted price. During the course of the construction, at various times, the Respondent requested and received payments or draws from the First Federal Savings and Loan Association of Broward County in the following amounts for the following purposes: Approximately $1,500 for electrical work; Approximately $1,744.32 for mill- work (cabinetry, door trim, etc.); Approximately $1,331 for installation of insulation in the duplex. The Respondent was established to have failed to pay these sums to the appropriate subcontractors who did the work. On or about March 7, 1980, the Respondent signed an affidavit required to obtain a draw payment from First Federal of Broward County. The Respondent stated in the affidavit that the millwork and trim for the duplex had been paid or would be paid from the proceeds of that draw request, which was $5,150. At the time he signed that affidavit, however, the millwork and trim had not been (as yet) paid, and they remained unpaid through the date of the hearing in the amount of $1,744.32. On or about February 13, 1980, the Respondent executed a similar affidavit in conjunction with a request for a draw payment from First Federal for the stated purpose of paying for insulation installed in the duplex. That draw amounted to $13,905. At the time he signed that affidavit, the insulation had not been paid for and remained unpaid through the date of the hearing in the amount of $1,331. On January 21, 1980, the Respondent executed a similar affidavit supporting a request for a draw payment from First Federal of Broward. In that affidavit, the Respondent affirmed that the electrical work provided for in the construction plans for the duplex had been paid for or would be paid from the proceeds of that draw request, which was in a total amount of $2,060. At the time the Respondent signed the affidavit, however, the electrical work had not yet been paid for, and it remained unpaid through the date of the hearing to the extent of $1,500.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is RECOMMENDED: That the Respondent be found guilty of violating the statutory authorities cited hereinabove in that he abandoned the subject construction project, diverted funds received for the construction of the project with the result that he could not fulfill his obligations with regard to the project, that he signed three separate false statements with respect to the construction of the project, and is guilty of misconduct in the practice of contracting. For these violations, his license should be suspended for a period of one (1) year. DONE and ENTERED this 20th day of January, 1983, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of January, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 A. J. Ryan, Jr., Esquire A. J. Ryan, III, Esquire Hollywood Federal Bldg. 700 East Dania Beach Blvd. Dania, Florida 33004 James Linnan, Executive Director Construction Industry Licensing Board Dept. of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Samuel R. Shorstein, Secretary Dept. of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, DPR Case No. 0011535 DOAH Case No. 82-446 vs. JAMES J. RUSSO R-B-R Construction Corp. RB 0032203 1412 Washington Street Hollywood, Florida 33020 Respondent. /

Florida Laws (2) 120.57489.129
# 1
TRITON CONSTRUCTION COMPANY vs. DEPARTMENT OF REVENUE, 77-001067 (1977)
Division of Administrative Hearings, Florida Number: 77-001067 Latest Update: Jun. 26, 1978

Findings Of Fact Triton is a Florida corporation located in Brooksville Florida, which performs land development and construction work for Gulf Coast Diversified Corporation, owned by the same people who own Triton. Triton owns an asphalt "hatching" plant which mixes sand and aggregate with liquid asphalt which is then used as paving material. All asphalt so mixed was used by Triton and no outside sales were made. Gulf Coast Diversified Corporation contracted with Triton for site development of certain realty. The contract included the construction of roads and parking lots. The contract price was computed on a lineal foot basis for the roads and on a square yard basis for parking lots. Triton, using the asphalt mixed in its batching plant, completed the work contracted for. In addition, Triton contracted with Gulf Coast Diversified Corporation for sewer construction which included the construction of manholes fabricated from concrete batched by Triton. No concrete was ever sold to any other outsiders. The cost of the concrete was included in the overall contract price and was not separately itemized. Triton's books of account show concrete sales in the amount of $168,569.36 during the audit period. This figure reflects a $20.00 per yard "market" value of concrete which Triton picked up in its books for its own internal accounting purposes. The figure represents some 8,428 yards of concrete actually sold. For sales tax purposes, Triton valued the concrete at about $13.74 per yard, a figure established by DOR in a previous audit, and remitted 4 percent of the total value of $115,835.25 of the State of Florida. During the audit, DOR noted that 4 percent of the bookkeeping entry for concrete sales was $6,742.77, while only $4,633.41 was received as sales tax. Consequently DOR assessed Triton an additional $2,109.36 plus penalties and interest. The difference, however, reflects only differential per yard valuation of the concrete and not additional concrete yardage.

Florida Laws (1) 212.06
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MICHAEL J. IPSEN, 82-000542 (1982)
Division of Administrative Hearings, Florida Number: 82-000542 Latest Update: Dec. 04, 1990

Findings Of Fact Respondent is a registered roofing contractor holding Florida license number RC0034000. He was so licensed at all times relevant to this proceeding. About April 11, 1980, Alexander D. Wynn contracted with Darryl Saibic, owner of Darric Construction, Inc., to reroof Wynn's home in Plantation, Florida. Work began on April 17, 1980, although no building permit had been obtained from the Plantation Building Department. In response to Wynn's complaint, the Plantation Building Department issued a violation notice and stop order to Darric Construction, Inc. on April 17, the same day work started. Richard Kessel, President of Darric Construction, Inc., had no one to qualify the company to perform roofing work and asked Respondent to act as the qualifier. Respondent agreed and he and Kessel drove to the Broward County and Plantation Building Departments on April 17, where Kessel turned in the paperwork necessary to qualify Respondent. Respondent signed a building permit application for the Wynn job, and a permit was issued to Darric Construction, Inc., later that day. Respondent did not supervise or in any way participate in the Wynn project, but merely loaned his license to Kessel as a personal favor. Respondent filed his application to qualify Darric Construction, Inc., with the State of Florida on April 18, but did not receive the registration until July 14, 1980. Thus, work began before Respondent had applied for this registration and was not issued until several months later, after the Wynn project was completed. The Wynn contract, ostensibly with Darric Construction, Inc., had the name William P. Doe Company, Roofing and Construction Contractors, listed at the top of the document. No reference was made to Darric Construction, Inc., the company which Respondent attempted to qualify, nor was Respondent's registration number entered on this contract. See Petitioner's Exhibits one and three.

Recommendation From the foregoing, it is RECOMMENDED: That Petitioner enter its Final Order finding Respondent guilty of the charges contained in the Administrative Complaint and suspending his roofing contractor's license for a period of one year; with reinstatement thereafter only upon demonstration by Respondent that he understands the provisions of law which apply to roofing contractors and that he is capable of adhering to these requirements. DONE and ENTERED this 28th day of July, 1982 in Tallahassee, Florida. R. T. CARPENTER, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of July, 1982. COPIES FURNISHED: Michael J. Cohen, Esquire 101 Kristen Building 2715 East Oakland Park Blvd. Ft. Lauderdale, Florida 33306 Mr. Michael J. Ipsen 1229 North West 7th Terrace Ft. Lauderdale, Florida 33311 James Linnan Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Samuel R. Shorstein Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (3) 455.227489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs LOUIS ROTH, 96-004580 (1996)
Division of Administrative Hearings, Florida Filed:Miami, Florida Sep. 27, 1996 Number: 96-004580 Latest Update: Jul. 15, 2004

The Issue Whether the Respondent, a licensed general contractor, committed the offenses alleged in the three administrative complaints and the penalties, if any, that should be imposed.

Findings Of Fact Petitioner is the state agency charged with regulating the practice of contracting pursuant to Section 20.165, Florida Statutes, and Chapters 455 and 489, Florida Statutes. At all times pertinent to this proceeding, Respondent has been licensed as a general contractor by the Petitioner. Respondent was issued license number CG C010162 in 1975 and has held that licensure ever since. The first complaint against Respondent’s licensure, like the three complaints at issue in this proceeding, arose from a post-Hurricane Andrew contract. That complaint was resolved by stipulation of the parties. Respondent did not admit to wrongdoing in his stipulation. Respondent was financially unable to comply with the terms of the settlement. Consequently, his license was suspended at the time of the formal hearing. There was no explanation as to why this complaint, which occurred at approximately the same time as the three contracts at issue in this proceeding, was prosecuted separately. At all times pertinent to this proceeding, Respondent was the qualifier for Allstate Construction Management, Inc. (Allstate), a Florida corporation. THE RODRIGUEZ CONTRACT (DOAH CASE 96-4580) On March 17, 1993, Allstate entered into a contract with Anthony Rodriguez to build a garage at 15525 SW 209th Avenue, Miami, Florida. The contract price was $16,250.00, which included “plans, permit and cleanup.” Allstate was paid the sum of $4,062.50 on March 17, 1993. Allstate obtained the Dade County building permit for the project on March 26, 1993. Allstate was paid the sum of $5,593.75 on April 5, 1993, after the concrete blocks were installed. On April 8, 1993, Allstate requested a tie beam/reinforcing inspection from the Dade County building department. In response to that request, Antonio Varona inspected the project on April 12, 1993. The inspector noted that the project was not ready for inspection because no truss plans were available. Respondent testified, credibly, that he had to construct the roof conventionally because of the difficulty in obtaining pre-fabricated trusses; however, that testimony does not explain why there were no truss plans available for inspection. Appropriately engineered truss plans are required for a roof to pass inspection. Despite the failure of the project to pass inspection, Mr. Rodriguez accepted the roof and paid Allstate $4,968.75 on May 21, 1993. As of May 21, 1993, there remained a final payment of $1,625 on the contract. After May 21, 1993, Respondent and Allstate left the Rodriguez job. There was a dispute in the evidence as to whether Mr. Rodriguez fired Allstate or whether Allstate abandoned the project. This dispute is resolved by finding that the evidence was insufficient to establish by clear and convincing evidence that Allstate abandoned the Rodriguez project. When Allstate left the Rodriguez job, there were sufficient funds remaining unpaid to complete the project. Because he had obtained the initial building permit, it was incumbent upon Respondent to either obtain a final inspection of the project or notify the building department that his company had been terminated by the owner. Respondent did neither. THE ELLIS CONTRACT (DOAH CASE 96-4581) At the times pertinent to this proceeding, William R. Ellis owned the Arleen House, which is an apartment building located at 2191 N.E. 168th Street, North Miami Beach, Florida. This building suffered damages from Hurricane Andrew. On September 11, 1992, Respondent and Mr. Ellis inspected the building and Respondent prepared an estimate as to the items that had been damaged by the hurricane and other non-hurricane related repairs that should be made. The mansard roof for this building had been damaged by Hurricane Andrew to the extent that it contained gaping holes. Shortly after that inspection, Mr. Ellis met with his insurance adjuster who gave him a check in the amount of $13,000 to repair the roof. It was necessary to dry in the roof and repair the mansard as soon as possible to avoid additional damage to the building from rains. While there was a dispute as to the extent of the services Allstate was to provide Mr. Ellis, the record is clear that Respondent, on behalf of Allstate, agreed to undertake the roof repair for the sum of $13,000. Respondent told Mr. Ellis that his company had a roofing crew ready to begin work on the roof repairs as soon as Mr. Ellis paid the sum of $13,000. Between September 11 and September 15, 1992, Mr. Ellis gave Allstate a check in the amount of $13,000 with the understanding that the check he had received from the insurance company had to clear before his bank would honor the check he was giving to Allstate. Immediately thereafter1 Allstate sent a roofing crew to the project for the purpose of temporarily covering exposed areas. Despite having been told by Mr. Ellis that the check he was giving Allstate would not be good until after the check for the insurance proceeds had cleared, Allstate did not wait to deposit Mr. Ellis’ check. Respondent was promptly notified that the check Mr. Ellis had given him would not be honored by Mr. Ellis’ bank. Respondent immediately thereafter withdrew the roofing crew from the project. The roofing crew had made only minor repairs at the time they were withdrawn from the project. Respondent knew, or should have known, that the building was vulnerable to further damage from rain. On September 15, 1992, Mr. Ellis gave Respondent a second check in the amount of $13,000. This check cleared the banking process on September 18, 1992. Mr. Ellis made repeated efforts to have Allstate send a crew to repair the roof. After it withdrew the crew that had been sent to the property when Allstate received the first check, Allstate did not take action to protect the property by repairing the exposed areas of the roof. Towards the end of September 1992, a heavy rainstorm caused additional damages to Mr. Ellis’ building. Allstate did not send a crew to the project again until October 6, 1992. Mr. Ellis hired this crew away from Allstate. He testified he did so because the crew complained about Allstate not paying for the materials they were using to repair the roof and because the workmen were threatening to file liens against the property. Mr. Ellis paid this crew the sum of $3,400 to temporarily repair the roof. He then entered into a contract with another contractor to complete the roofing repairs for the sum of $17,500. Mr. Ellis demanded the return of the $13,000 he paid to Allstate, but, as of the time of the formal hearing, he had not been repaid. THE KUCHENBACKER CONTRACT (DOAH CASE 96-4582) On November 6, 1992, Allstate entered into a contract with Carl F. Kuchenbacker to repair his residence at 18500 SW 88th Road, Miami, Florida. Mr. Kuchenbacker’s residence had been damaged by Hurricane Andrew. The initial contract price was $33,375.00. Respondent secured the building permit and Allstate began work on the project. During the course of the work, additional work was added to the contract, which raised the total contract price to $38,015.00. In late February or early March, 1993, Allstate abandoned the project without just cause and without notice to the owner. At the time it abandoned the project, Allstate had been paid the sum of $26,620.00. Allstate failed to pay all of the subcontractors and materialmen who had performed work or provided material for the Kuchenbacker job. As a result of that failure, valid liens were recorded against Mr. Kuchenbacker’s property. The following liens were recorded: Rite-Way Plumbing and Plastery, Inc. in the amount of $3,520.00; Commercial Lighting and Maintenance, Inc., in the amount of $1,835.00; and Scott Bornstein Plumbing, Inc., in the amount of $798.00. Allstate had received sufficient funds from the owner to pay these liens, but neither Respondent nor Allstate paid these liens. Mr. Kuchenbacker and Petitioner’s expert witness testified that the value of the work performed by Allstate before it abandoned the job was $21,000.00. Mr. Kuchenbacker also testified as to the items that remained undone and as to the percentage of the work that had been completed. From that testimony and from the testimony as to the estimated costs of completing the job, it is found that the sum of $11,395.00, which was the difference between the total contract price and the total amount that was paid to Allstate, was sufficient to complete the project and pay off the liens on the property. Respondent did not call for a final inspection of the property and he did not advise the Dade County Building Department that he was abandoning the project. Allstate abandoned the Kuchenbacker project because it went out of business.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that that Petitioner enter a final order that adopts the findings of fact and conclusions of law contained herein. It is further recommended that Petitioner impose fines totaling $5,000 against Respondent’s licensure as follows: For the violation established by Count I of DOAH Case 96-4580, an administrative fine in the amount of $500. For the violation established by Count II of DOAH Case 96-4580, an administrative fine in the amount of $500. For the violation established by Count IV of DOAH Case 96-4580, an administrative fine in the amount of $250. For the violation established by DOAH Case 96-4581, an administrative fine in the amount of $500. For the violation established by Count I of DOAH Case 96-4582, an administrative fine in the amount of $750. For the violation established by Count II of DOAH Case 96-4582, an administrative fine in the amount of $2,000. For the violation established by Count III of DOAH Case 96-4582, an administrative fine in the amount of $500. IT IS FURTHER RECOMMENDED THAT in addition to the fines recommended for the violations found in DOAH Case 96-4581, Respondent’s licensure be suspended for two years. IT IS FURTHER RECOMMENDED THAT in addition to the fines recommended for the violations found DOAH Case 96-4582, Respondent’s licensure be suspended for two years, to run concurrently with the suspension recommended for DOAH Case 96- 4581. DONE AND ENTERED this 23rd day of May, 1997, in Tallahassee, Leon County, Florida. Hearings Hearings CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative this 23rd day of May, 1997

Florida Laws (4) 120.5720.165489.1195489.129 Florida Administrative Code (3) 61G4-17.00161G4-17.00261G4-17.003
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs JOSEPH W. KAMINSKY, 93-006523 (1993)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Nov. 12, 1993 Number: 93-006523 Latest Update: May 29, 1996

Findings Of Fact At all times material hereto, Respondent has been a certified general contractor in the state of Florida, having been issued license number CG C027718. At all times material hereto, Respondent has been the qualifying agent for Classic Design Builders. William R. DeFreitas describes himself as a broker of building materials for third world countries. His wife is also employed in that same business. They had their office building constructed for them. When they subsequently determined to add an addition to their residence, they solicited bids from that contractor and from two other persons. Aaron Ware, who held himself out to be an architect and the president of a company known as L. A. Designs, Inc., was one of the persons from whom the DeFreitases solicited a bid. He submitted a bid dated April 26, 1990, and a draw schedule on May 3, 1990. The extent of the work to be performed was finalized on June 6, 1990, when Mr. DeFreitas initialed the changes to the initial bid. The construction project contemplated under that contract was the addition of a family room, a laundry room, a shower off the master bath, and a small bath at the front of the house. The June 6, 1990, contract also called for replacement of the garage door and "painting of some interior doors." The total contract price was $50,000. While Ware was negotiating with the DeFreitases, he was also discussing with Respondent entering into a joint venture agreement between Classic Design Builders and L.A. Designs for the DeFreitas construction project. Their verbal agreement was memorialized in a written agreement dated June 18, 1990. Thereafter, Respondent did not advise Petitioner that he had entered into a joint venture agreement and, similarly, did not qualify the joint venture as a separate business entity for licensure purposes. Pursuant to instructions from Ware, Mr. DeFreitas directed a letter to the City of Boca Raton advising the building department that he had entered into a contract to construct an addition to his residence with "L.A. Designs/ Classic Designs." On July 2, 1990, Respondent on behalf of Classic Design Builders obtained a building permit from the City of Boca Raton for the DeFreitas addition. On July 6, Ware began work on the addition. Ware worked on the project from July of 1990 through the end of that year. During the course of that construction, the DeFreitases made many changes in the scope of the work contemplated by the original contract, which increased the contract price to above $56,000. Additional work was performed, which was not covered by the contract and which the DeFreitases agreed to pay for directly to the supplier or subcontractor. On February 4, 1991, the DeFreitases directed a letter to Ware advising him that the construction was close to completion and that it was time for them to "settle our account" as to the extras for which the DeFreitases had not paid. In that letter, the DeFreitases also offered to produce the invoices for materials and labor that they had agreed to pay to finish the job. In July of 1991 the DeFreitases complained to the City of Boca Raton. Respondent, as the holder of the building permit, was contacted and advised that the DeFreitases were alleging that their contractor had failed to complete the project. Respondent immediately went to the DeFreitases' business, met with Mr. DeFreitas, inspected the home, and prepared a punch list of items to be completed, many of which were not covered by the construction contract but were done by Respondent in an attempt to achieve customer satisfaction. Respondent completed the project, obtained the final inspections, and presented the DeFreitases with a warranty and release of lien. The DeFreitases refused to accept the warranty or release of lien. As a result of the DeFreitases' complaints, Respondent and Ware were charged with violating local ordinances. In those prosecutions, as well as in this case, the DeFreitases have attempted to obtain $11,000 from Respondent as "restitution" for moneys they have had to spend or will have to spend to complete the work envisioned by their contract with L.A. Designs, Inc. Most of the items listed as components of the claim for restitution are not even part of the construction contract. Of those few items covered by the contract, the money claimed is not. For example, the contract allocated $500 to be expended on the bathroom cabinets. The DeFreitases spent $1,670 on the cabinets and, surprisingly, are claiming that Respondent should pay them the difference because they spent more than their contractual allowance. Finally, they have claimed the cost of replacing inferior building materials provided by them, such as wood French doors. The DeFreitases paid to Ware approximately $4,000 less than they had promised to pay him as a result of the work completed by L.A. Designs. Rather than suffering a loss, the DeFreitases have actually received a windfall. At no time material hereto was either Ware or L.A. Designs licensed in the state of Florida as a contractor, architect, professional engineer, or landscape architect. Respondent knew that Ware and L.A. Designs were not licensed. At the time that Classic Design Builders and L.A. Designs entered into their written joint venture agreement and at all other times material hereto, Respondent was not an officer, director, stockholder, or employee of L.A. Designs, and Ware was not an officer, director, stockholder, or employee of Classic Design Builders. When Ware approached Respondent about entering into a joint venture for the DeFreitas project, Respondent had already suffered a minor heart attack and two mini-strokes. The joint venture agreement itself recites Respondent's need to limit his activities due to health reasons. In July of 1990 Respondent additionally tore an Achilles tendon in his left leg and was in a cast until Christmas of 1990. Due to his immobility during that time period, Respondent delegated all of his construction jobs to others, understanding that he was ultimately responsible for those projects since he was the contractor of record on them. In the same way, he delegated to Ware the day-to-day responsibility for the DeFreitas project. Other than "pulling the permit" for the DeFreitas project, Respondent's only other involvement in the job until the time that he was contacted as a result of the DeFreitases' complaints to the City of Boca Raton in July of 1991, was right after the job was commenced regarding some problem concerning the lot line. He was able to resolve that problem with the City of Boca Raton by telephone. The DeFreitases did not know that Respondent was the contractor for their construction project and ultimately responsible for that work. Although Ware had advised them that a "buddy" would somehow be involved in the construction, and although Mr. DeFreitas referred to both L.A. Design and Classic Design Builders in his letter to the City of Boca Raton authorizing a building permit to be issued, the evidence is clear that had the DeFreitases known of Respondent's responsibility, they would have been insisting that he perform services months earlier. In 1987 Respondent was charged with abandoning a construction project and/or failing to timely complete it. Respondent entered into a settlement stipulation admitting that fact and agreeing to pay a fine to the Construction Industry Licensing Board in the amount of $1,000. A Final Order Approving Settlement Stipulation was entered on June 8, 1988. Respondent received no money from the DeFreitases or from Ware for the work Respondent performed on the DeFreitas addition. Respondent's out-of-pocket expenses for labor and materials on the DeFreitas residence between July of 1991 and June of 1992 total $1,747.50.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered: Finding Respondent guilty of Counts I, II and VII of the Administrative Complaint filed against him; Finding Respondent not guilty of Counts III, IV, and V of the Administrative Complaint filed against him; Requiring Respondent to pay an administrative fine in the amount of $1,000; and Placing Respondent's license number CG C027718 on probation for a period of two years. DONE and ENTERED this 16th day of November, 1994, at Tallahassee, Florida. LINDA M. RIGOT Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of November, 1994. APPENDIX TO RECOMMENDED ORDER Petitioner's proposed findings of fact numbered 2-10, 16-20, and 22 have been adopted either verbatim or in substance in this Recommended Order. Petitioner's proposed findings of fact numbered 11-15, 21, and 24 have been rejected as not being supported by the weight of the evidence in this cause. Petitioner's proposed finding of fact numbered 1 has been rejected as not constituting a finding of fact but rather as constituting a conclusion of law. Petitioner's proposed finding of fact numbered 23 has been rejected as being subordinate. COPIES FURNISHED: John David Ashburn, Esquire Department of Business and Professional Regulation 3932 RCA Boulevard, Suite 3210 Palm Beach Gardens, Florida 33410 Diane Perera, Esquire Department of Business and Professional Regulation 401 N.W. 2nd Avenue, Suite N-607 Miami, Florida 33128 Peter Mineo, Jr., Esquire 8220 State Road 84 Fort Lauderdale, Florida 33324 Copies furnished, continued Richard Hickok, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Jack McRay, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (4) 120.57455.227489.119489.129 Florida Administrative Code (2) 61G4-15.002261G4-17.001
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILLIAM B. GARRISON, 83-002289 (1983)
Division of Administrative Hearings, Florida Number: 83-002289 Latest Update: Dec. 04, 1990

The Issue The issues in this matter are as promoted by an administrative complaint brought by the State of Florida, Department of Professional Regulation against William B. Garrison. In particular, the respondent is charged with having diverted funds or property received for the completion of a specific project in violation of Section 489.129(1)(h), Florida Statutes (1979). In addition, the respondent is charged with signing a statement falsely indicating that payment had been made for all subcontracting work, in violation of Section 489.129(1)(1), Florida Statutes (1979), and of making misleading, deceptive, untrue or fraudulent representations in the practice of his profession in violation of Section 455.227(1)(a), Florida Statutes (1979). It is the respondent's denial of these accusations and request for formal hearing which eventuated in this recommended order.

Findings Of Fact Respondent is a holder of a registered building contractor's license issued by the Florida Construction Industry Licensing Board. That license number is RB0029142, first issued in 1975. Respondent has been associated with the construction business on a full time basis since 1970. From 1975 through 1981 respondent operated as Garrison Builders of Tallahassee, Inc. At all times relevant to the administrative complaint, respondent was the qualifier of Garrison Builders of Tallahassee, Inc., pursuant to Section 489.119, Florida Statutes. On August 6, 1980, Garrison Builders of Tallahassee, Inc., contracted with TBW, Inc., to build eight townhouses at Larette Drive, in Tallahassee, Florida, for a contract price of $269,424.00. That base contract price was subject to change orders, the first of which decreased the contract price by $8,000 and the second which increased the contract price by $864.00. As a consequence, the final contract price was $262,388.00. Garrison Builders of Tallahassee, Inc., was paid a total of $257,598.38 under the terms of the contract. Garrison Builders paid out, related to the account for this project, $257,890.01. As of March 31, 1981, respondent had failed to pay the following subcontractors and materialmen in the amounts designated: Butterfield's Floor Covering, Inc. $ 277.10* Barineau & Sons Heating and Air Conditioning 2,420.00 Big Bend Rental Center, Store #1 596.96 Sam Crowder Co. 61.39 Discount Lumber, Inc. 445.33* Ken Driggers, Inc. 32.14 Deep South Insulation Co. 600.00 John T. Daniel Cabinet Co. 3,400.00 Miller Sheet Metal 1,292.00 Melco Wood fixtures 1,502.59 Maples Concrete Products Co., Inc. 1,571.31 Quality Plumbing, Inc. 5,864.00* Tallahassee Glass & Screen 690.56 Tallahassee Rug Co. 1,486.51 Yarbrough Paint & Decorating Center 1,589.15 City Building Department-Systems Charges 1,790.10 Wallpaper Installation-50 rolls @ $7.00/roll 350.00* Total $23,969.14 *Billing not complete The contract between Garrison Builders and TBW was to be performed in 150 days after August 6, 1980, subject to allowances for rain days, etc. Garrison Builders was responsible for satisfying the claims of the materialmen and subcontractors as reflected above, in keeping with the terms of the contract. Respondent, as president of Garrison Builders, was responsible for the overall project. In keeping with the contract terms, respondent and the job foreman for the subject project made application and certification for payment. These applications and certifications may be found as part of the petitioner's composite Exhibit Number 2, admitted into evidence. The last of those applications was made by the respondent on February 17, 1984. Prior to that payment, Garrison Builders had been paid $247,136.70. On that occasion, as on other occasions, respondent certified, "that all amounts have been paid by him for work for which previous certificates for payment were issued and payments received from the owner. . . ." in signing the certification for an additional $10,461.68 draw. At that point in time approximately 98 percent of the job had been completed. Nonetheless, contrary to the certification statement, materialmen and suppliers had not been paid as demonstrated in the accounting set forth above showing that as of March 31, 1981, $23,969.14 was still owed, which amount far exceeds the difference between the contract price of $262,388.00, and the amount Garrison Builders had been paid prior to the last draw, i.e., $247,136.70. That differential is $15,251.30. In a meeting in March 1981 at which respondent attended and was represented by counsel, respondent admitted to a representative of TBW that materialmen and suppliers had not been satisfied in terms of payment. By affidavit of April 3, 1981, a copy of which is petitioner's Exhibit Number 5 admitted into evidence, he acknowledged the $23,969.14 of outstanding claims effective March 31, 1981. Moreover, in a court appearance involving TBW and some of the materialmen and suppliers in which the question of possible liens by those latter entities was litigated, respondent admitted that he had lied in his statement of certification in the contractor's application and certificate for payment, wherein he stated that all materialmen and suppliers had been satisfied before obtaining payments under the contract. This admission, taken in the context of the other facts found, indicates that the respondent appreciated that materialmen and suppliers had not been paid when he made application for the February 17, 1981, draw and swore that they had. This oath as to that circumstance was not one of mistake or inadvertence. It was a comment made with the knowledge of the implications of the oath. Thus, the effect was to be false, misleading, deceptive, untrue and fraudulent, contributing to a loss of $277.10 which the owner paid Butterfield Floor Covering without reimbursement. Respondent was not paid the balance of the contract price, the owner having claimed that the contract was 90 days beyond the contract date for completion, and upon the assertion by the owner that additional funds had to be expended to complete the contract over and above the contract amount. Respondent claims that the reason for late completion concerned a problem with a subcontractor who was providing cabinets, one John Daniel. In addition, respondent alludes to the fact that he was in the hospital from November 10, 1980, through November 20, 1980, and again from December 2 through 19, 1980, and as a consequence was unable to supervise the job in a manner which he preferred. Daniel was a subcontractor chosen by the owner and accepted by the respondent. From a review of the evidence, it is unclear whether Daniel was the responsible agency for the project being approximately 90 days over the contract period. It is also uncertain whether the essentially 90 day delay was in view of respondent's failures as responsible agent for Garrison Builders. Had Garrison Builders been responsible the owner would have been entitled to deduct essentially $20 a day for late penalties. Finally, the owner's claim of expenditures in excess of $10,000 to complete the job was not satisfactorily proven. In summary, the job was late for reasons unestablished. Certificates of occupancy were issued for the eight units in March 1983 signaling the completion of the job. On the subject of whether respondent diverted funds and property from this project into other projects thereby affecting the outcome of the project, the proof on balance demonstrates that Garrison Builders, under the aegis of the respondent, made a bad bargain by underbidding this project as opposed to diverting funds and property to other pursuits.

Recommendation Upon consideration of the findings of facts and conclusions of law, it is RECOMMENDED that a final order be entered which finds the respondent guilty of a violation of Section 489.129(1)(1), Florida Statutes, and Section 455.227(1)(a), Florida Statutes, and dismisses the allegation of a violation of Section 489.129(1)(h), Florida Statutes. For the violations established, a penalty of a 60 day suspension should be imposed against the respondent. DONE AND ENTERED this 11th day of September 1984 in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of September 1984. COPIES FURNISHED: Michael Egan, Esquire ROBERTS, EGAN & ROUTA, P.A. 217 South Adams Street Tallahassee, Florida 32302 Jeffrey H. Savlov, Esquire Post Office Box 10082 Tallahassee, Florida 32302 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 James Linnan, Executive Director Board of Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (6) 120.57455.227489.119489.129589.15790.10
# 7
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs OSCAR S. BENITEZ, 01-000366PL (2001)
Division of Administrative Hearings, Florida Filed:Miami, Florida Jan. 26, 2001 Number: 01-000366PL Latest Update: Feb. 15, 2002

The Issue Whether the Respondent committed the violations alleged in the Administrative Complaints and, if so, what penalty should be imposed.

Findings Of Fact The Department is the state agency charged with regulating the construction industry within the State of Florida. At all times material to the allegations of these cases, the Respondent was licensed by the Department as a certified general contractor, license number CG C007009. Additionally, due to the time period from which the Respondent held his license he was "grand- fathered" to perform roofing construction. The Respondent was the qualifying agent of O. Benitez & Associates, Inc., a Florida corporation. On November 13, 1997, the Respondent executed a contract with Maricel Alayon to construct a terrace for a home located at 1215 West 82nd Street, Hialeah, Florida. While Ms. Alayon referred to the structure as a "terrace," it was to be a covered (roofed) open porch attached to her home at the rear of the property. The price for the addition was $14,125.00. The contract that was prepared by the Respondent for Ms. Alayon's signature did not contain the Respondent's license number or a written notice of the consumer's rights under the Construction Industry's Recoveries Fund. Ms. Alayon paid the Respondent the full $14,125.00 on or about November 17, 1997. Despite having been paid the full amount, the Respondent did not complete the Alayon project. The work was begun on or about November 27, 1997, but was never finished. Ms. Alayon did not fire the Respondent, did not refuse access to her property, and never refused to pay the Respondent monies owed for the work. Curiously, the Respondent obtained the building permit for the Alayon project on January 27, 1998. The Respondent never called for a final inspection on the job and, as of March 29, 2001, a final passing inspection for the project had not been performed by building officials. In addition to the contract amount, Ms. Alayon paid $3,575.00 for materials that were used in the construction of the porch. The Respondent did not reimburse Ms. Alayon for that amount. In May of 1998, the Respondent began negotiations with Mr. and Mrs. Piloto for the construction of an addition to their home to include an in-ground swimming pool. From the beginning of the talks, Mr. Piloto advised the Respondent that the couple could only invest $38,000 for the remodeling work as that was the amount the bank had approved for the project. The Pilotos wanted to build a bedroom, an expanded bathroom, and a swimming pool at the rear of their home located at 750 West 73rd Place, Hialeah, Florida. Eventually the Respondent telephoned the Pilotos to advise them that they could get what they wanted within the budget set by the bank. The contract executed by the Pilotos called for the remodeling for a price of $37,890.00. The contract, prepared by the Respondent, did not contain the Respondent's license number or a notice of consumer's rights pursuant to the Construction Industries Recovery Fund. At all times material to the Piloto project, the Respondent did not hold a valid architect's license. In fact, in December of 1997, the Board of Architecture and Interior Design had fined the Respondent for having practiced architecture with a delinquent license. Nevertheless, the Respondent represented himself as an architect to the Pilotos and charged them for blueprints for the remodeling project. Moreover, the Respondent submitted the signed and sealed plans for the Piloto project to the Building Department in order to obtain a building permit for this project. Such plans were filed on or about August 12, 1998. Pursuant to their agreement with the Respondent, the Pilotos paid the Respondent a total of $26,664.00 for the project. In comparison, the value of the work performed by the Respondent did not exceed $10,000. The Respondent asked the Pilotos to increase the amount for the contract to $50,395.75, but they refused. Despite the fact that he had caused their home to be reduced to a dangerous condition (by virtue of exposed wiring and open walls), the Respondent refused to complete the work on the Piloto project for the contracted amount. Instead, he abandoned the project. The Pilotos did not fire the Respondent. They refused to increase the amount of the contract. The Pilotos did not stop the work or refuse workers access to the property. A lien was placed on the Piloto property by a subcontractor to whom the Respondent owed monies. The Pilotos were required to pay the subcontractor in order to satisfy the lien amount. The Respondent has failed or refused to repay the lien amount. The Respondent grossly under estimated the cost of remodeling the Piloto home. He did so either negligently or intentionally. The Piloto home was compromised by the demolition work done by the Respondent's crew. The Pilotos were faced with paying the additional monies to comply with the Respondent's demand or living with their home in an uninhabitable condition. They chose the latter. On or about May 11, 1999, the Respondent applied for and obtained a building permit to re-roof the home of Sam and Daisy Carpenter. The contract for the work was with Banos Remodeling Services, an unlicensed entity, not the Respondent or his company. The Respondent has been the subject of prior disciplinary actions filed by the Department. He settled such actions without admitting or denying the allegations against him. As to his architectural license, it is undisputed that at all times material to these cases, the Respondent did not hold a valid architect's license. The Petitioner has incurred expenses and costs in the investigation of and the prosecution of the instant cases against this Respondent. The Respondent provided no credible explanation for the failure to complete the work contracted for regarding the Alayon and Piloto homes.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board, enter a final order sustaining the violations outlined by the Conclusions of Law, imposing an administrative fine in the amount of $5000.00, requiring the Respondent to make restitution to the Pilotos and Ms. Alayon, requiring the Respondent to remit the costs of investigation and prosecution of these cases, and revoking the Respondent's license until all amounts are fully paid. DONE AND ENTERED this 23rd day of October, 2001, in Tallahassee, Leon County, Florida. ______________________________ J. D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 2001. COPIES FURNISHED: Kathleen O'Dowd, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Hardy L. Roberts, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2201 Oscar S. Benitez 3894 Southwest 107th Avenue Miami, Florida 33165 Theodore R. Gay, Esquire Department of Business and Professional Regulation 401 Northwest Second Avenue Suite N-607 Miami, Florida 33128-1765

Florida Laws (4) 120.57489.119489.129489.1425
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CLARENCE S. TATE, 84-000992 (1984)
Division of Administrative Hearings, Florida Number: 84-000992 Latest Update: Dec. 04, 1990

Findings Of Fact Respondent holds certification with the Florida Construction Industry Licensing Board as a general contractor and a registered roofing contractor, having been issued license numbers CG C009484 and RC0043155, respectively. Tate has qualified a company known as Allstate Roofing and Construction, Co., under the terms of the aforementioned licenses, and at times relevant to this inquiry, operated under that company name. On February 17, 1983, respondent through his business name, Allstate Roofing and Construction, contracted with Wayne Lackey to furnish the necessary labor and materials to build a 28' by 78'brick-veneered housing shell in Clay County, Florida. The specified amount of the contract was $34,365 to be paid in four equal draws, or installments, in the amount of $8,591.25, following the completion of work related to each of the phases. In accordance with the contract terms, Lackey paid the respondent three draws in the amount of $8,591.25, upon assurances that respondent had satisfied the expenses related to subcontractors, suppliers, and materialmen. Respondent requested advance payment of the final draw and indicated to Lackey that this money was to be used to pay for materials related to the construction of the housing shell. Lackey complied with this request and made two advanced payments on the fourth draw in the amount of $2,700 and $500. The total amount of the three draws and the advance payments related to the fourth draw was $28,973.75. At the point of paying the advance on the fourth draw, Tate had also told Lackey that all subcontractors, materialmen and suppliers had been paid, and indicated to Lackey that a written lien affidavit acknowledging that all the costs had been satisfied would be provided to Lackey at the conclusion of the construction. While respondent was still obligated under the terms of the contract, Lackey began to receive phone calls and statutory notices of intentions on the part of materialmen, subcontractors and suppliers indicating that they would lien the homesite of the owner, Lackey. These demands were made on the basis that several of these claimants had not been paid for services or' supplies. When Lackey confronted the respondent, the respondent initially told Lackey to ignore those notices and that they had been paid on checks drawn on the Allstate account. In fact, the claimants had either not been paid, or had been paid with checks upon which insufficient funds were available to honor the checks drawn on respondent's business account. Under the circumstances, the claimants continued to press Lackey for satisfaction of their claims for labor and supplies. As a consequence the Lackey's had to expend money of their own to satisfy the contract conditions on the subject of costs for services by subcontractors, materialmen, and suppliers. These costs should have been defrayed by respondent pursuant to the terms of the contract. Some of the expenses, which are recounted below, were expenses incurred prior to the respondent's entitlement to his fourth draw. Payments by the owners to the claimants are as follows: Acorn Windows Mr. Silvers, carpenter Mr. Bruning for fill material Joe Williamson, brickmason & concrete =$1,875.50 =$1,183.57 =$ 551.00 =$1,100.00 Taylor Concrete =$1,629.85 Mr. Karneol, clean-up =$ 200.00 United Electric =$1,523.00 SUBTOTAL PAID BY CHECK BY THE LACKEYS =$8,060.92 Cash payments for which receipts were given: Williamson =$1,000.00 United Electric =$ 800.00 door hardware =$ 136.08 TOTAL EXPENDITURE BY THE OWNERS =$10,003.00 When the amount paid by the Lackeys to subcontractors, materialmen, and suppliers is added to the $28,973.75 paid directly to the respondent, the expenditure on the part of the Lackeys' was $38,976.75. Respondent is due credits for extras in the amount of $200 for rear concrete slab, $160 for extra brick, and $70 for an interior door. That sum of $430 when subtracted from the overall payments of the Lackeys leaves $38,546.75 expended by the Lackeys, which exceeds the agreement, or contract price, between the respondent and the Lackeys by $4,181.75. From the facts presented, it is evident that the Lackeys did not receive the performance from the respondent which they were entitled to under the terms of the contract, and as a consequence, had to pay an additional $4,181.75 above the contract price, before receiving what they had bargained for. This was at some considerable inconvenience in time as well as money. The proof is not clear on whether the respondent diverted monies or property which he had received to carry out the contract with the Lackeys into some other pursuit or whether respondent made a bargain with the Lackeys which could not be concluded with the amount of available funds which the respondent had accepted by contract as being sufficient for the Lackeys to perform their obligation under the contract.

Florida Laws (5) 120.57120.68136.08489.129591.25
# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer