Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
WINKO-MATIC SIGNAL COMPANY vs. DEPARTMENT OF TRANSPORTATION, 84-002250 (1984)
Division of Administrative Hearings, Florida Number: 84-002250 Latest Update: Jan. 18, 1985

Findings Of Fact On March 1, 1984, Respondent gave notice to qualified contractors that it would receive sealed bids for State Project No. 72000-3541, referred to as Federal-Aid Project No. M 9041(10). This project involves the installation of a computerized traffic control system for the City of Jacksonville. In response to the opportunity to bid, the Department of Transportation received four bids. Petitioner, Winko-Matic Signal Company, was among the bidders. The other bidders were Georgia Electric Company, Traffic Control Devices, Inc., and Sperry Systems Management. The bids of Traffic Control Devices and Sperry Systems were rejected based upon an error in bid tabulations on the part of Traffic Control, a mistake on the quantities page, with the Sperry rejection being based upon a bid bond problem. Traffic Control had been the apparent low bidder with a bid of $1,964,115. Winko-Matic was the second apparent low bidder with a bid of $2,279,604.70. The Department of Transportation had estimated that the total cost of the Jacksonville project would be $ 2,024,680.61. Having discarded the bid of Traffic Control Devices, the Department of Transportation telegrammed Winko-Matic on April 4, 1984, advising Winko-Matic that it was the apparent low bidder for the Jacksonville project. Subsequently, the awards committee of the Department of Transportation met on April 18, 1984, and determined to reject all bids and re-advertise the job. In the course of this meeting the awards committee was told that there were erratic bids received on contract items, pointing to some perceived confusion among the contractors as to requirements of the contract. Discussion was also held on the possibility of establishing a pre-bid conference if the project was re advertised. The awards committee then voted to reject the bids on the basis that the apparent low bidder, Winko-Matic, had submitted a bid which-was 12.6 percent over the Department's estimate, instead of being within 7 percent of the Department of Transportation's pre-bid estimate, a point above which the Department of Transportation in its non-rule policy would call to question to the acceptability of the apparent low bid. In addition to deciding to reject all bids and re-advertise, it was determined that a pre-bid conference should be scheduled at least 30 days prior to the bid-letting date. Winko-Matic was advised that the Department of Transportation's decision to reject all bids by correspondence of May 4, 1984, in which it was indicated that all bids had been rejected based upon the fact that they were too high. In response to this notice of rejection, Winko-Matic, effective May 17, 1984, filed a written notice of protest. The case was subsequently referred to the Division of Administrative Hearings on June 20, 1984, and a final hearing date was established by Notice of Hearing of July 5, 1984. The hearing date in this cause was September 12, 1984. The Jacksonville project in question requires the utilization of what has been referred to "UTCS Enhanced" software. This software package is unique and has only been used in a limited number of locations within the country. Those locations are Los Angeles, California; San Diego, California; Broward County, Florida; and Birmingham, Alabama. Another unique feature within the project design is the use of an associated coaxial computer sys gem. Given the unique nature of this project and the fact that the Department of Transportation had never advertised for bids related to UTCS software, Department of Transportation obtained assistance from a consulting firm, Harland, Bartholomew & Associates. In fulfilling its function Harland gave estimates to include an estimate related to the projected cost of the software, Item 681-102. The Harland estimate for the overall project was $2,143,130 including a $100,000 estimate for the software system. That estimate relating to the software was subsequently adjusted by the Department of Transportation to depict a cost of $13,780. The Department of Transportation estimate was based upon information within its computer related to a system unlike the enhanced software contemplated by the plans and specifications. In other words, the stored information in the Department of Transportation computer was not the same as contemplated by the plans and specifications in the Jacksonville project. Moreover, the initial estimate of Harland was based upon the idea of an extended software system, as opposed to an enhanced software system. Winko-Matic had bid $389,500 for the software in Item 681-102. That estimate was premised upon figures obtained from JHK and Associates, the group which Winko-Matic intended to use as its subcontractor for the enhanced software portion of the project. JHK developed the software and was responsible for systems integration of the Los Angeles, California, project, one of the locations in which UTCS enhanced software has been utilized. JHK premised its estimate for the software hare upon experience in Los Angeles and an evaluation of the tasks to be performed related to the enhanced software. This included general software development activities, hardware innovation, installation costs during the period of acceptance and testing, and the preparation of data base. The JHK bid price was $339,500. Another $50,000 was added to that price related to what the Petitioner describes as its management costs for that item. By June 20, 1984, when a further meeting was held by the awards committee on the subject of the Jacksonville project, it was concluded that the estimate made by the Department of Transportation of $13,780 was not correct, on the topic of the enhanced software. A more reasonable estimate, according to the information imparted in this session, would be $200,000 for enhanced software as called for in this project, with a $100,000 amount being a reasonable estimate had they chosen to use extended software. Adjusting the initial price related to the UTCS enhanced software to reflect a corrected estimate of the Department of Transportation in its original advertised bid, that estimate becomes $2,210,900.61 and its consultant Harland's estimate becomes $2,243,130. With this adjustment, the differential in the estimate made by the Department of Transportation and the Petitioner approaches 3 percent and not the 12.6 percent originally found. The 3 percent is below the threshold of 7 percent used as the policy for determining whether a bid might be rejected as being far beyond the acceptable limits set forth in the Department of Transportation's estimate. In the aforementioned June 20, 1984, awards committee meeting, the Department of Transportation continued to hold the opinion that all bids in the Jacksonville project should be rejected and the matter re-advertised. Although the problem pertaining to the estimate of the cost of the enhanced software package had been addressed, the committee continued to feel that the prices received in the bid letting were erratic Reference was also made to revisions or modifications to the project plan which would be offered if the matter were re- advertised. It was also pointed out that the Federal Highway Administration would concur in the Department's decision to reject all bids and would accept modifications. The awards committee again voted to reject the bids. The matter was again considered by the awards committee on August 31, 1984. On that occasion, it was pointed out that the revisions contemplated by the Department of Transportation, should the matter be re-advertised, would not affect in a substantial way the cost estimate for the project with the exception of Item 680-101, the system control equipment (CPU), which would promote a lower price for the project. The committee determined in the August, 1984, meeting to reject all bids and re-advertise. While the initial notice of rejection of May 4, 1984, had suggested the basis for rejection as being the fact that Petitioner's bid far exceeded the 7 percent allowance for price above the Department of Transportation's estimate of costs, the meetings of the awards committee and the suggestion of the Respondent in the course of the final hearing in this case indicated that there were other reasons for the decision to reject. Those Were: (a) an apparent lack of clarity among bidders regarding specifications for the Jacksonville job, (b) the desire of the Respondent to revise specifications on the Jacksonville project; and (c) a lack of sufficient competition in the bids. In connection with the first of the additional reasons Respondent suggests that variations within the bid responses related to particular line items within the specifications point out a lack of clarity in the project's specifications or confusion by bidders related to those specifications. Respondent did not bring forth any of the bidders who might speak to the matter of possible confusion or misunderstanding concerning some of the bid items. By contrast, the Petitioner's president; the president of JHK & Associates and James Robinson, Harland's project manager for the Jacksonville job, did not find the specifications in the original documents to be confusing. In addition, the testimony of those individuals established the fact that bid variations related to particular line items are not extraordinary and do not establish any apparent confusion by the bidders as to the requirements of those line items. In effect, what the differentials demonstrate are variations related to the manufacture or in-house capabilities of the bidders and an effort to allocate discretionary costs in various places as to line items. Moreover, they might indicate last- minute adjustments in the bid quote prior to the opening and a possible effort by a contractor to enter into a new job market. Finally, they demonstrate offsetting which is the allocation of item prices by a contractor to maximize profits. To do this, a contractor submits high bids on items representing quantities which the contractor feels will increase after the contract is awarded and submits low bids on items representing quantities which are not likely to change. In summary, while the Department of Transportation in its presentation expressed some concern about the variations in the pricing in the bid quotations offered by the respective bidders in this project, its suspicions on the question of the possible clarity of its specifications were not confirmed and are not convincing. On the topic of revisions which the Department of Transportation would offer if the matter were re-advertised, with one exception those matters appear to be items that could be attended through change orders or supplemental agreements. They are not matters which necessarily must be addressed through a rejection of all bids and a re-advertising of the project. The lone exception to this is the possibility that the Department of Transportation may not be able to protect its proprietary rights in the enhanced software which is being developed for the project, under the terms of the present bid documents. Given that uncertainty, the Respondent would wish to re-advertise the project and make certain that its proprietary interests are protected. Finally, Respondent has alluded to the fact that the Jacksonville project should be re-advertised in view of the lack of competition in the initial letting. Only four bidders expressed an interest in this project at the time of the first letting. Of those, two bidders were found to be responsive. While this is a low number of bidders, there does not appear to be any agency practice on the part of' the Department of Transportation to the effect that this number of bidders would not be accepted. Moreover, no indication has been given that should the matter be re-advertised a greater number of bidders would express an interest than was the case in the first letting. Consequently, this reason for bid rejection is not acceptable. If Respondent did not reject the bids and re-advertise the project, Winko-Matic would be the successful bidder in the Jacksonville project.

Florida Laws (3) 120.53120.57337.11
# 1
ANSWERPHONE OF FLORIDA, INC. vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 88-006073BID (1988)
Division of Administrative Hearings, Florida Number: 88-006073BID Latest Update: Jan. 12, 1989

The Issue Whether the Petitioner was the lowest responsive bidder in Bid No. 88-8-1, and therefore entitled to the contract award. Whether the special conditions set forth in the bid documents were timely objected to by the Petitioner, and so ambiguous as to warrant a rejection of all bids in Bid No. 88-8-1.

Findings Of Fact The Department sent invitations to bid in Bid No. 88-4-2 to various providers of telephone answering services within the Brevard County area. The purpose of the invitations was to obtain the lowest responsive bid for an after- hours telephone answering service for a one year period at the Department's Monroe Center in Cocoa Beach, Florida. When the results of the bidding were made known at the public bid opening, Answerphone's bid was recommended for the award as the low bidder. On June 16, 1988, the bidders were notified by mail that the bid would not be awarded as recommended at the public bid opening. The bidders were told that the bids were being reevaluated, and they would be notified later as to when the award would occur. On June 24,1988, the bidders in Bid No. 88-4-2 were notified that the Department rejected all bids because of the belated discovery of inherent ambiguities in the solicitation which made it impossible for the Department to determine the lowest and best bid. The Department did not receive any notices of protest based upon its decision to reject all bids, and the decision became final seventy-two hours after the bidders were notified of the rejection. New bid specifications were created, and the Department sent invitations to bid to Bid No. 88-8-1 to the same list of providers who had received invitations in Bid No. 88-4-2. In paragraph 2 of the new invitation to bid, prospective bidders were notified that questions concerning specifications should be directed in writing to 705 Avocado Avenue, Cocoa, Florida. The invitation cautioned that no interpretation of the specifications should be binding on the Department unless provided in writing. Paragraph 4 of the special bid conditions attached to the invitation allowed the bidders to orally present questions about the bid requirements at the pre-bid conference held on August 30, 1988. Paragraph 6 of the special bid conditions required prospective bidders to file a notice of protest within seventy-two hours after receipt of the bid solicitations if there were concerns about the reasonableness, necessity, or competitiveness of the terms and conditions of the invitation to bid. The Petitioner was represented at the conference and the Department was asked to explain what was meant by the specification which required that the system have the capability of receiving and patching or paging multiple calls at one time if necessary. The Petitioner's representative was told that the system must be able to handle multiple calls at one time without losing a call. The provider should have an adequate system of holding, handling, and routing these calls as specified in items one through four of the list of services required in the bid documents. The Answerphone representative indicated to the Department that all of his questions had been satisfactorily answered before the pre-bid conference was brought to a close. No requests were made to the Department to place its explanation in writing and no written interpretation was provided. A notice of protest by Answerphone about the specifications in the bid solicitation was not filed with the Department prior to the Department's acceptance of bids in Bid No. 88-8-1. When the bids were opened on September 6, 1988, Elite Answer Service, Ltd., was the apparent responsive low bidder in Bid No. 88-8-1. Answerphone filed a protest to contest the award because Elite does not have the technological capacity to complete the contract under the specifications, as interpreted by Answerphone. During the administrative hearing, it was learned that the Department meant the following interpretation to be given to its specification which requires the service to handle multiple calls: During after hours, the Department has one telephone line and one telephone number linked to an answering service. When an incoming call to that number is received by the service, no other callers can dial that number and gain access to the service. The second caller will receive a busy signal. The service must have the capacity to take the call which has been received and call the necessary people at other telephone numbers who might need to speak with each other or the caller, together or separately. Therefore, the service must be able to place various people on hold at different times in the sequence, and patch the appropriate people together at the proper times when the service has been directed to do so. Answerphone interpreted the specifications to mean that the service should be able to handle more than one incoming call to the one local HRS telephone number and telephone line which is available to the public at night. For example, if three different calls were dialed to the local number, all three would be received by the service instead of two receiving a busy signal. The service would then proceed to dispatch the different callers to all of the different people as described above in paragraph 14 of the Findings of Fact. Answerphone has the technological capacity to accomplish this feat. Elite does not.. Answerphone's interpretation of the bid specifications was an untenable one in that it restricted competition instead of promoting it. This is contrary to the clear intent of the Department as set forth in the invitation to bid. The bid specifications were clear and unambiguous in that the Department's requirements from the after-hours answering service were to begin after the dialer's telephone call rang into the answering service. The Department's opportunity to handle more than one incoming call dialed during the time the one line at Monroe Center was already in use was never addressed in the specifications. The mistake in the interpretation of the bid specifications belonged to the petitioner. Paragraph 4(c) of the general conditions place the risk of mistake on the Petitioner. Opportunities to correct possible mistakes in interpretation by the prospective bidders were provided during the bid process. The Petitioner did not avail itself of these opportunities.

Florida Laws (3) 120.53120.57287.057
# 2
SHAFER AND MILLER, INC. vs. DEPARTMENT OF GENERAL SERVICES, 76-001375 (1976)
Division of Administrative Hearings, Florida Number: 76-001375 Latest Update: Oct. 05, 1977

The Issue Whether Petitioner should be granted an equitable adjustment to increase the contract price in the amount of $337,714 for a mistake in bid on project No. BR-7702/8701, Library/Auditorium, Florida International University.

Findings Of Fact In April 1974, Respondent advertised for bids for the construction of a library-auditorium building at Florida International University, Miami, Florida, State Project No. B.R. 7702/8701. Respondent's representative for this project was the architectural firm of Ferendino/Grafton/Spillis/Candela, Coral Gables, Florida. The advertisement for bids specified that sealed bids would be received until 2:00 p.m. on May 16, 1974, at which time they would be publicly opened and read aloud. In fact, the advertised time period was extended until the same hour on May 23, 1974. The advertisement provided that bids must be submitted on the proposal form furnished by the architect/engineer and be accompanied by a bid bond or an equivalent cash amount in a sum not less than five per cent of the amount of the base bid as a guarantee that the bidder would enter into an agreement with the owner if this bid was accepted. It further provided that the bid would remain in force for thirty (30) days after the time of opening. The advertisement also contained the following statement: "The Department of General Services reserves the right to reject any and all bids and to waive informalities in any bid whenever such rejection or waiver is in the interest of the State of Florida." (Exhibit 1a, testimony of Williams) In preparing its bid on the project, Petitioner utilized two company forms. One included columns for the various portions of the work with blocks opposite each portion for the insertion of the names of subcontractors and the amounts of their bids. The other form was a recapitulation of the low subcontractors' bid by the various segments of the contract, and the form also included spaces and amounts for the work to be accomplished by the contractor itself. The normal procedure followed by Petitioner in this and prior projects was to enter subcontractors' bids on the subcontractor's bid tabulation form when received over the telephone and, when all such bids had been received shortly before the deadline for submission of bids by the prime contractors on the project, to enter each low subcontractor bid on the recapitulation form. This would then be totaled to arrive at Petitioner's bid to be submitted to Respondent. (Testimony of Kearns). The subcontractor tabulation form for the instant project listed an item for "PRECAST STRUCTURAL." Opposite this entry in blocks on the form had been printed the names of subcontractors from whom Petitioner expected to receive bids, including Pre-Stressed Systems, Inc. (P.S.I.), Meekins, Stresscon, and Houdaille. However, since there were two different pre-case structural items called for under the specification, i.e., joists under section 3-B and pre-case panels under section 3-C, the words and figures "3B Joists" and "3C panels" were penciled in above and below the printed words "PRE-CAST STRUCTURAL" to show the need for entering bid figures for both items. However, there was no separation of these items in the various blocks for subcontractor's bids. (Exhibits 1b, 1c, Testimony of Kearns) Usually bids of major subcontractors were not received until the morning of the final day for submission of the total bids, and many were not received until immediately prior to the time the bid must be tallied and submitted. On the morning of May 23, 1974, the day for bid opening, Petitioner's employee, Edward A. Kearns, Jr., an estimator, was responsible for preparing Petitioner's bid. The only bid Petitioner had received for precast joists was that submitted by P.S.I. in the base amount of $460,000. This sum was entered on the bid tabulation from in pencil under the printed name P.S.I. Bids for the pre-cast panels were received from two of the subcontractors whose names were printed on the form an the amounts were entered in pencil as follows: "Meekins - 399,800, Stresscon - 400,00." No bid was entered for Houdaille. About 11:00 a.m., a telephonic bid on the panels was received from Cast-Crete Corporation of Kissimmee. This bid was considerably lower than that of Meekins and, because Petitioner had not heard of or dealt with Cast-Crete in the past, it asked all three bidders on the panels to verify the requirements and prices. While awaiting the return of this information, the Cast-Crete bid was not entered on the bid tabulation form. Thereafter, Cast-Crete informed Petitioner that it was raising its bid somewhat and this information was placed on a separate subcontractor bid form for cast-Crete, but not entered on the tabulation form containing all bids. The final Cast-Crete bid was in the amount of $337,714. By this time, Petitioner's office was quite hectic in that other bids were coming in at a fast pace and the phone was ringing continuously. Many bidders sought clarification on items or had to give their bids to Kearns which was time-consuming. As the time for submission by Petitioner to Respondent drew near, Kearns took the low subcontractor bids from the bid tabulation form and transferred them for each category of work to the recapitulation form. On this form, there was a single line for "Precast structural" and, on that line, Kearns entered the bid that had been received from P.S.I. for precast joists, but forgot to include any bid for the precast panes. Since no breakdown for joists and panels was shown on the recapitulation form, he assumed that bids for all portions of the work hand been included. All items on the recapitulation form were added and Petitioner arrived at a total base bid of $3,999,259, which did not include the bid for precast panels in the amount of $337,714. (Testimony of Shafer, Sr., Kearns, Exhibits 1b, 1c, 1f) Petitioner's employee, Ron Shafer, Jr., previously had been sent to the place of bid opening at Florida International University with the formal bid letter with the amounts left blank. Shortly before 2:00 p.m., Petitioner provided him by telephone with the amounts to place on the be bid form and submit to the Respondent's representative. He submitted the formal bid just prior to the deadline. The bids were thereafter opened and, although Ron Shafer, Jr., noted that Petitioner's bid was some $400,000 lower than the next lowest bidder, he was unaware of the circumstances of the mistake and returned to the office. The representative of Respondent had opened the bids and an officer of the architectural firm, Freeman J. Williams, was also present. Nothing was said at the time concerning the large disparity between Petitioner's bid and the other bids, and Williams saw no need to ask Petitioner to verify its bid at that time. (Testimony of Shafer, Jr., Williams, Exhibits 1d, 1v) Meanwhile, after Kearns had tallied the final bid figures and they had been called in to the employee at Florida International University, Petitioner's personnel sat around the office and discussed the job for several minutes. They then started to gather up all the sub-bids to put in a folder when they discovered a "subcontractor's bid form" for Cast-Crete Corporation and realized that it had not been included on the tabulation sheet or on the final recap sheet. Immediate attempts were made to telephone the architect about the mistake. When Williams was reached at his office some thirty minutes after he had left Florida International University, Petitioner requested that its bid be withdrawn after explaining the circumstances. Williams suggested that Petitioner immediately send a telegram to Respondent explaining this situation. Petitioner did so in the following language: "In reviewing our bid, we discovered we had omitted the cost of precast panels manufacturers bid from our tabulation sheet, in the amount of $282,714. We, therefor, regretfully must with- draw our bid on the FIU library and auditorium building. We could, however, accept award of contract if this amount could be added to either of our base bids. Please advise. SHAFER AND MILLER, INC. R C Shafer" In the telegram, an additional mistake was made by using the figure of $282,714 which did not include the erection of the panels in the amount of $55,000 that had been the subject of a separate bid by Cast-Crete. After receipt of the telegram, Respondent's representatives requested that Petitioner come to Tallahassee with their pertinent documents relating to the bid to discuss the matter. They did so and thereafter heard nothing further until June 5, 1974, at which time a letter was received from the Department of General Services, dated May 31, 1974, advising that, subject to final approval by the Governor and the Cabinet, it was propose to recommend acceptance of Petitioner's low bid and award the contract to it in the amount of $4,122,000 for Base Bid 1 and Priority 1 Alternate A, Priority 2, Alternate C, and Priority 3, Alternate D. The meeting of the Cabinet at which the award was to be recommended was stated in the letter to be held on June 4, 1975. Since Petitioner did not receive the letter until June 5, it had no opportunity to be present at the time matter was considered. By separate letter of May 31, 1974, the Department of General Services enclosed four copies of a standard form of agreement and performance and payment bond to be executed and returned. (Testimony of Williams, Shafer, Sr., Kearns, Exhibits 1e, 1g, 1h) Petitioner contacted legal counsel, James E. Glass, on June 5. He checked into the matter and found that the contract had already been awarded on June 4 by the Cabinet. He then telephoned Arnold Greenfield, General Counsel for the Department of General Services, and asked if the state could rebid the job at which time Petitioner would submit its original intended bid. Greenfield stated that the project was critical from a budget standpoint and that the state would not rebid it, and insisted that the Petitioner proceed or else forfeit its bid bond and be subject to suit for any excess costs of performance. Glass reminded Greenfield that Petitioner proceed or else forfeit its bid bond and be subject to suit for any excess costs of performance. Glass reminded Greenfield that Petitioner could seek injunctive relief in the matter, and the latter then stated that if Petitioner would proceed with the contract, Respondent would acknowledge its right to claim a modification of the contract. This conversation was confirmed in a letter from Greenfield to Glass, dated June 7, 1974, wherein it was stated "We further understand that your client may wish to seek a modification of such contract, after execution." Glass, in a return letter dated June 12, returned the executed contracts and bonds, stating that Petitioner was doing so in order to act "equitably and in good faith", and was fully reserving its rights to contest the erroneous bid by judicial action for equitable relief. Thereafter, Petitioner received notice to proceed with the work and in due course satisfactorily completed the contract within the required period. This was evidenced by a certificate of acceptance of the building by the using agency, which was approved by Respondent on December 4, 1975. (Testimony of Glass, Exhibit 1e, 1g, 1h, 1i, 1j, 11, 1m, 1s) In December, 1974, Petitioner had submitted its claim for an equitable adjustment in the amount of $337,714 which was the amount of the omitted Cast- Crete bid. During the ensuing year Petitioner submitted audits of its expenses on the job to Respondent and in January, 1976, further audit information was provided at the request of Respondent. On May 6, 1976, Respondent informed Petitioner that it would not approve any increase in the contract amount. Thereafter, on June 11, Petitioner filed its petition herein seeking an equitable adjustment in the amount of $337,714. The petition was referred to the Division of Administrative Hearings by the Respondent on August 2, 1976, and the undersigned Hearing Officer was assigned to conduct the hearing therein. (Exhibit 1r, 2, 4, 5, 6) By a Motion to Abate, dated August 23, 1976, Respondent requested that the matter be held in abeyance pending the submission of the petition to the project architect and his rendering of a determination indicating whether the relief should be granted or denied, as a "condition precedent to the contractor obtaining consideration of said petition in any proceeding authorized by Chapter 120, Florida Statutes." Respondent stated in its motion that the contract clearly provided that nay and all claims or disputes should be first submitted to the architect for determination, and that thereafter, either party could obtain administrative review of the determination by filing a written appeal to the Department of General Services within thirty days. The motion further stated that since this prerequisite had not been accomplished, there was no basis for an administrative appeal at that time. On the same date, Respondent advised the architect of the situation and requested expeditious consideration of the matter. On August 27, the architect issued its determination stating "From our personal knowledge of the events during the bid opening process, and the subsequent events that led to the awarding of the bid, we concur in the contractor's request." In November 1976, Respondent's general counsel advised the Hearing Officer that settlement efforts were in progress but requested that the matter be scheduled for hearing nevertheless. Notice of hearing was issued on December 15, 1976, and the case was heard on January 27, 1977. (Exhibits 1t, 1u, Pleadings) Petitioner's intended total bid, including alternates, amounted to $4,459,714. A change order of $194 was issued during the course of the work, amounting to a total of $4,459,908. Petitioner's direct costs on the project were $4,094,890. Overhead was computed at 2.85 per cent of direct costs in the amount of $116,705, for a total cost of $4,211,595. Overhead was computed based on the ratio of total general and administrative expense to total direct costs incurred on all of Petitioner's jobs in process for the year ending May 31, 1975. However, the audit reports included payment in the amount of $335,634 to Cast-Crete Corporation. The actual amount paid to that firm was $325,234 - difference of $10,400, making Petitioner's actual costs $4,201,195. During the course of the contract, Respondent paid Petitioner $4,122,194, resulting in a net loss to Petitioner of $79,001. An anticipated profit for performance of the contract was computed on the basis of the average profit on other jobs of 4.4 per cent, amounting to the sum of $180,377. The latter two sums total $259,378, and it is found that figure is the reasonable amount of Petitioner's claim. (Exhibits 2-5)

Recommendation That Petitioner's claim for equitable adjustment under Project No. BR- 7702/8701 be granted and that a change order be issued increasing the contract price by $259,378.00. DONE and ENTERED this 21st day of March, 1977, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 530 Carlton Building Tallahassee, Florida 32304 (904) 388-9675 COPIES FURNISHED: Donna H. Stinson and Daniel S. Dearing, Esquires Post Office Box 1118 Tallahassee, Florida 32302 James E. Glass, Esquire 2600 First Federal Building 1 Southeast 3rd Avenue Miami, Florida 33131 John A. Barley, Esquire General Counsel Department of General Services Room 110 Larson Building Tallahassee, Florida 32301

Florida Laws (1) 120.57
# 3
KELLOGG AND KIMSEY, INC. vs LEE COUNTY SCHOOL BOARD, 91-007597BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Nov. 26, 1991 Number: 91-007597BID Latest Update: Mar. 02, 1992

Findings Of Fact Upon consideration of the oral and documentary evidence addressed at the hearing, the following relevant findings of fact are made: The request for sealed bids for the construction of the Project was advertised on October 9, 16 and 23, 1991. There were six addenda to the original bid documents which added, deleted or modified provisions of the original bidding requirements, contract requirements, administrative requirements and technical specifications. The original bid documents plus the six addenda will be referred to herein as the "bid documents". The bid documents required that all bids be in full accord with the contract documents. Sealed bids for the Project were opened on October 30, 1991. Wright submitted the lowest lump sum bid for the Project, with Sovran submitting the second lowest lump sum bid and Kellogg submitting the third lowest lump sum bid. At the time of the bid opening, the bid documents listed only four casework manufacturers that were approved to furnish casework for the Project. Empire Custom Cabinets, Inc. (Empire) was not listed as one of the four approved casework manufacturers in the bid documents. The bid documents did not require the bidder to list the casework manufacturer it intended to obtain the casework from, but only that the bidder name the casework subcontractor. The only work item in the bid documents which requires identifying the name of the manufacturer on the subcontractor's list is the metal roof system. Because Empire's bid on the casework was extremely low compared to other bids received by Wright on the casework, Wright called Empire prior to submitting its bid to confirm that Empire's bid was submitted per plans and specifications. Although Wright did not specifically inquire of Empire at this time as to which manufacturer Empire was obtaining the casework from for the Project, Empire did advise Wright that Empire's bid on the casework was according to plans and specifications. Additionally, Empire did not divulge or advise Wright at this time that the bid was based on Empire manufacturing the casework for the Project. Based on this representation from Empire, Wright listed Empire as its casework subcontractor, and calculated its lump sum bid for the Project using Empire's bid. Although Wright listed Empire as its casework subcontractor in its bid, this did not create an irregularity in Wright's bid since Wright's bid was per plans and specification without exception or exclusion. This would require Wright to furnish casework for the Project manufactured by one of the four approved casework manufacturers listed in the bid documents regardless of which subcontractor Wright listed as the subcontractor for casework. By letter dated November 1, 1991, the Board's architect for the Project requested Wright to have Empire submit written certification by one of the four approved casework manufacturers that its casework was being furnished to Empire for the project. By letter dated November 4, 1991, Empire advised Wright that Empire's bid on the casework for the Project was based on casework to be manufactured by Empire. On the same day, Wright furnished the architect for the Project a copy of Empire's letter of November 4, 1991. In response to a request by the Board, Wright, by letter dated November 7, 1991, advised the Board that Wright would furnish casework manufactured by one of the four approved manufacturers listed in the bid documents for the Project. By letter dated December 3, 1991, Empire advised Wright that Empire would need to withdraw its bid if Empire was required to use casework manufactured by one of the four approved casework manufacturers listed in the bid documents. On that same day, Wright furnished the Board a copy of Empire's letter and requested that the Board allow Wright to remove and replace Empire with Steven Ward and Associates, Inc. (Ward), as the casework subcontractor since Ward would be able to furnish and install casework manufactured by LSI Corporation of America, Inc., one of the four approved casework manufacturers. No Action has been taken on that request. The bid documents provide for a subcontractor to be removed and replaced from the list of subcontractors after the bid is opened if there is a showing of good cause and written approval by the Board and the Project architect is obtained. Although Empire's bid on the casework for the Project submitted to Wright was based on Empire manufacturing the casework, there is competent substantial evidence in the record to establish facts to show that at the time Wright submitted its bid on the Project it had reasonable grounds to believe that Empire's bid on the casework was based on Empire furnishing and installing casework manufactured by one of the four approved casework manufacturers. After determining that Empire could not perform under its bid, Wright obtained a bid from Ward for furnishing and installing the casework for the Project which was less than Ward's original bid submitted to Wright before the bid opening. However, this bid was substantially more than Empire's bid, and if Wright is allowed to substitute Ward for Empire, Wright will have to absorb the additional costs since the bids were lump sum bids. Wright is neither attempting to furnish casework from a manufacturer that is not approved, nor is Wright requesting an increase in the lump sum bid price. The advertisement for Sealed Bids for the Project required that all bidders be prequalified by the Board prior to the bid date. Sovran and one other bidder were not prequalified by the Board prior to the bid date in accordance with Advertisement for Sealed Bids for the Project. Sovran received the bid documents for the Project approximately one month before the bid date but did not file a Notice of Protest of the prequalification requirement contained in the Advertisement for Sealed Bids for the Project. Sovran holds a certificate as a general contractor licensed in the State of Florida in accordance with Chapter 489, Florida Statutes. As a certified general contractor Sovran, pursuant to Section 489.125, Florida Statutes, was authorized to bid on the Project notwithstanding the Board's prequalification requirement. This was explained by the Board's representative at the bid opening. The bid documents required that a subcontractor list be submitted by all bidders, and when submitted with the bid becomes an integral part of the bid. The purpose of the subcontractor list was to prevent bid shopping, and to allow the Board an opportunity to review the subcontractors to determine if any subcontractor on the list had performed unsatisfactorily on previous Board projects. Neither the statutes relating to competitive bidding nor the bid documents prohibit the listing of the general contractor together with a subcontractor on a subcontractor list. The subcontractor list submitted by Sovran indicated "Sovran Constr/Naples" as the name of the subcontractor for the masonry work and "Sovran/Naples" as the name of the subcontractor for the poured-in-place concrete work. "Naples" is Naples Concrete and Masonry Work, Inc. The bid received by Sovran from Naples was for both labor and materials for the poured-in-place concrete and masonry work. Sovran neither requested nor did Naples furnish Sovran a bid to provide labor only for the poured-in-place concrete and masonry work. There was no agreement between Sovran and Naples whereby Sovran would supply the materials and Naples would furnish the labor for the poured-in-place concrete and masonry work. Sovran did request and receive bids from other companies for furnishing materials only for the poured-in-place concrete and masonry work. Sovran listed itself, the general contractor, along with Naples on the subcontractor list for the purpose of supplying the materials for the poured-in- place concrete and masonry work. Sovran's main reason for supplying the materials was that Naples was not bondable. Without a payment bond from Naples, Sovran would be without protection and could be forced into paying double for the materials in the event Naples failed to pay the material suppliers. Although the Superintendent of the Lee County Schools has recommended to the Board that the Board accept Wright's bid for the Project, the Board has not voted on that recommendation. The fact that Wright used Empire's bid to calculate its lump sum bid in no way excuses Wright for the requirement set out in the bid documents that casework used for the Project (when the time comes) be manufactured by one of the four approved casework manufacturers. Wright gains no economic advantage in this regard since the lump sum bid price remains the same. The advertisement for Sealed Bids on the Project provides that the Board reserves the right to waive any and all irregularities of any bid received.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, accordingly RECOMMENDED: That the Board enter a Final Order dismissing the instant bid protest and awarding to Wright the contract for the construction of Elementary School "C", Job No. 91063. DONE and ORDERED this 13th day of February, 1992, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13 day of February, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NUMBER 91-7597B1D The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 3(1,2 and 3 , respectively); 4 - 5(6); 6(4); 7 - 9(5); 12(10); 13(11); 15 - 16(12); 17(13); 18 - 19(16); 20(29); 21(18); 23(19); 24 - 25(20); 26(22); 27(23); 28(22); 29 - 30(29); 32 - 33(25); and 34(26). Proposed finding of fact 10 is rejected as not being supported by competent substantial evidence in the record in that Wright's bid was as per plans and specifications without exceptions or exclusions which included the use of casework manufactured by one of the approved casework manufacturers. Proposed finding of fact 11 is rejected as not being supported by competent, substantial evidence in the record in that the Board knew of Empire's bid being based on nonconforming materials prior to issuing its Notice of Intent. However, the only information the Board had in reference to Wright's bid before issuing its Notice of Intent was that Wright had bid as per plans and specifications and would be installing casework manufactured by one of the approved manufacturers. The only question was whether Empire could furnish casework manufactured by one of the approved manufacturers. Proposed finding of fact 14 is neither material nor relevant. How the Board's architect interpreted Wright's bid is neither material nor relevant to this proceeding. Proposed finding of fact 22 is unnecessary to the conclusion reached in the Recommended Order. Proposed finding of fact 31 is more in the way of an argument than a finding of fact. Proposed findings of fact 35 and 36 are covered in the Preliminary Statement. The timeliness of Kellogg's protest is not an issue and therefore, a finding that it was timely is unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent While not specifically adopting proposed finding of fact 1, where material or relevant or necessary to this proceeding, and supported by competent, substantial evidence in the record the stipulated facts have been adopted. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2(4,5); 3(9); 4 - 5(7); 7 - 8(8); 10(16); 11(14); 12(31); 13(21); and 15(23). Proposed finding of fact 6 is more in the way of an argument than a finding of fact. Proposed finding of fact 9 and 14 are neither material nor relevant. Rulings on Proposed Findings of Fact Submitted by the Intervenor See ruling on Respondent's proposed finding of fact Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2 - 3(21); 4(24); 5 - 6(21); 13(23); 14(24,28); 15(22); 16 - 17(23,24); and 18(28). Proposed findings of fact 7 through 12 are neither material nor relevant to this proceeding. COPIES FURNISHED: David E. Gurley, Esquire Norton, Gurley & Darnell, P.A. 1819 Main Street, Suite 610 Sarasota, FL 34236 Marianne Kantor, Esquire The School Board of Lee County 2055 Central Avenue Fort Myers, FL 33901 James M. Talley, Esquire Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, P.A. Post Office Box 712 Orlando, FL 32802 Karl Engel Superintendent Lee County School Board 2055 Central Avenue Ft. Myers, FL 33901 Honorable Betty Castor Commissioner of Education The Capitol Tallahassee, FL 32399-0400

Florida Laws (3) 120.53120.57489.125
# 4
DOUGLAS PRINTING COMPANY, INC. vs. DEPARTMENT OF AGRICULTURE AND CONSUMER SERVICES, DIVISION OF FORESTRY, 83-001984 (1983)
Division of Administrative Hearings, Florida Number: 83-001984 Latest Update: Jul. 03, 1990

Findings Of Fact On May 19, 1983, Respondent mailed official Invitations to Bid (IFB) forms to 18 different firms, including Petitioner, soliciting bids for Class VI printing in accordance with the specifications and conditions attached to the letter, signed by R. E. Read, Jr. This letter contained the comment, "As the best interests of the State may require, the right is reserved to reject any and all bids and to waive any irregularities in bids received." This letter also advised prospective bidders who had questions regarding the IFB to call Larry Amison, the individual who had drafted the accompanying specifications. The notice of IFB, published in the Tallahassee Democrat on Thursday, May 19, 1983, also contained a notice of reservation of the right to reject all bids. Only five IFB forms were returned. Three of the five were returned without bids for various reasons, such as "Not Competitive," "Unable to meet specified delivery date" and "Cannot schedule job of this proportion at this time." This type of explanation, in government procurement circles, need not be taken at face value, but is often used to signal the recipient's thanks for the invitation to bid and a desire to be invited to bid again at some time in the future. The other two forms received were bids: one from Zenith Communications Group, and one from Petitioner. This procurement was somewhat unusual in that the IFB stipulated the amount of money the agency had to spend and requested a hid as to the most product it could get for that money. There were two publications involved: "A" and "B." An alternative was given on delivery date options: one within 30 working days of receipt of approved proofs, and one within 45. Zenith offered to provide 7,180 copies of Book "A" and 7,155 copies of Book "B" (14,335 total books) for a total price of $53,400 1/ within 30 working days. Petitioner offered to provide 9,473 copies of Book "A" and 4,950 copies of Book "B" (15,423 total books) for a total price of $53,344.64 within 45 days. The bids were opened on June 1, 1983, and published from June 1 through June 10, 1983. They were brought to the Director for consideration upon opening. It is his responsibility to evaluate the bids and make a recommendation to the Commissioner of Agriculture on the successful low bidder. Since there was only one bid on each delivery date, the Director felt there were not two comparative bids. As a result, he forwarded the bid package to Ms. Grace Harrison, a purchasing agent with the Department of Agriculture and Consumer Services and an individual very familiar with the procurement of printing services. After a review of the entire bid package, Ms. Harrison's studied opinion was that there were two valid bids and Douglas was the low bidder, and it is so found. Ms. Harrison also felt it was unusual not to receive any more responses than were received on a procurement of this magnitude. This same opinion is held by Mr. Amison, who drafted the specifications. Others have differing opinions, however. Whether it was unusual or not, however, is immaterial. There were two valid bids, and only two are required for an award. However, even in the case of two bids, the agency reserved the right to reject any and all bids. As a result, on or about June 6, 1983, the Director decided, based on his understanding of state policy on the matter and in light of the size of the procurement, to seek more bids through rebidding. In this case, the Director felt more bids were available because of the responses of the nonbidders which referred to the response times being so short. Therefore, he directed a rebid, and this information was communicated to all bidders, including Petitioner. On June 7, 1983, Petitioner wrote to the Director, disagreeing with his decision and notifying him of its protest. On the following day, the Director notified Petitioner the rebidding was being delayed, giving Petitioner 10 days to file a formal notice of protest. This was done in a timely manner. The phrase regarding the agency's right to reject bids is contained in every State IFB. Its purpose is to permit state agencies to reject bids where it becomes apparent there is a valid and legitimate benefit to be gained by the agency in doing so. One such situation is when, in the bona fide opinion of the agency, there are insufficient bids. While there is a difference of opinion as to whether only two bids are unusual in a procurement of this nature, there is no dispute that it would have been beneficial to the agency to have received more than two, since more bids would increase competition. To rebid the contract at this juncture would undoubtedly increase competition to the potential benefit of the Respondent. However, Petitioner claims it would also work to its detriment because other potential bidders would have access to the details of the two present bids and would thereby gain an advantage. This may be the result of rebidding.

Recommendation In light of the foregoing, it is RECOMMENDED: That Petitioner, Douglas Printing Company, Inc., be awarded Contract DOF- ADM-79. RECOMMENDED this 8th day of September, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of September, 1983.

Florida Laws (1) 120.57
# 5
NAPLES BUSINESS EQUIPMENT AND SYSTEMS, INC. vs. LEE COUNTY SCHOOL BOARD, 88-000690BID (1988)
Division of Administrative Hearings, Florida Number: 88-000690BID Latest Update: Mar. 30, 1988

The Issue The first issue to be determined is whether the BOARD can reject all bids, with or without cause. The second issue is to determine if the BOARD is required to have cause, was there a sufficient basis for the rejection of all bids in Bid NO. 3996?

Findings Of Fact On December 14, 1987, the BOARD sent invitations to bid to a list of approved vendors in Bid NO. 3996. The purpose of the invitation was to obtain the lowest responsible bid on a purchase of one hundred and fifty typewriters. The bids were to be submitted prior to January 11, 1988 at 2:00 P.M.. They were opened by the BOARD on the same day. OFFICE did not receive an invitation to bid despite its request to be placed on the approved vendor's list in November of 1987. When OFFICE learned of the outstanding invitation to bid, its representative, Mr. Richard Foss, went to the BOARD's Purchasing Department and requested a bid package. The bid documents given to OFFICE mistakenly gave January 14, 1988 at 2:00 P.M. as the deadline for the bid submission. Because of the later date given by the BOARD to OFFICE, the company's bid was received after the opening of the bids. When the results of the bidding were made known at the public bid opening, NAPLES bid was the lowest received. On January 14, 1988, after 10:42 A.M., it was discovered by the BOARD that OFFICE's bid price was lower than the price submitted by NAPLES. At this time, NAPLES bid had not yet been accepted by the BOARD, and no formal announcement had been made awarding the contract to NAPLES. During the BOARD's Purchasing Department's bid analysis, a request was made to reject all bids in Bid NO. 3996. The reason given by Purchasing for the request for rejection was that the specifications were being revised. The bids were rejected on the same date. The written reason sent to the vendors on January 14, 1988 for the bid rejection was that one vendor had been given an incorrect opening date. Attached to the written notice to the vendors was a new bid invitation for Bid NO. 4013. The BOARD explained its mistake was unfair to the one vendor. A new bid opening date was given of February 1, 1988. On January 14, 1988, in addition to the required bid documents, OFFICE submitted a letter which listed additional offerings or incentives that OFFICE would give the BOARD if OFFICE was awarded the contract. These additional purchasing incentives were: wall charts and teacher/student manuals for each typing classroom in the county. OFFICE also informed the BOARD that one of the BOARD's own service personnel was already trained in the servicing of Swintec typewriters. The bid submitted by OFFICE did not meet either the weight or the print wheel specifications as set forth in Bid NO. 3996. The specifications as written in Bid NO. 3996 were not written to eliminate all other typewriters but the Brothers 511-11. Weight specifications required were below the Brother's minimum weight, and at least two other manufacturers provide protected drop-in cassette print wheels in electronic typewriters. The Invitation to Bid contained specific provisions which encouraged the bidding of typewriters other than the Brother 511-11, and set up procedures under which other typewriters, which substantially meet the specifications, could be reviewed on their merits. NAPLES was the lowest responsible bidder for the electronic typewriter contract in the prior school year. The BOARD had rejected all bids at that time because of the decision to consider a different brand of typewriter once bids were opened. A notice of protest was filed by NAPLES, and the BOARD agreed to honor NAPLES bid and award the company the contract. The BOARD revised its bid specifications from last year prior to its solicitations for bids in Bid NO. 3996. The protected drop-in cassette print wheel and the weight requirements were two new technical specifications. During the hearing, the BOARD was unable to determine whether the weight factor or the protected drop-in cassette print wheel requirement will continue to be included in future revisions of the specifications.

Recommendation Based on the foregoing, it is RECOMMENDED: That the BOARD reject the bid submitted by OFFICE as it was nonconforming and sought an advantage not enjoyed by the other bidders. Reinstate the bids which were rejected in Bid NO. 3996, consider the bids, and make an award of the contract to NAPLES. DONE and ENTERED this 30th day of March, 1988, in Tallahassee, Florida. VERONICA D. DONNELLY Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of March, 1988. COPIES FURNISHED: Stephen Emens, President Naples Business Equipment and Systems, Inc. 859 4th Avenue South Naples, Florida 33940 Harry A. Blair, Esquire 2138-40 Hoople Street Ft. Myers, Florida 33901 Richard Foss, Typewriter Sales Manager 8A-Del Prado Boulevard Cape Coral, Florida 33904 Karl Engel, Superintendent Lee County Public Schools The School Board of Lee County 2055 Central Avenue Fort Myers, Florida 33901

Florida Laws (2) 120.53120.57
# 6
TOSHIBA BUSINESS SOLUTIONS (USA), INC., A DELAWARE CORPORATION vs SCHOOL BOARD OF BROWARD COUNTY, 14-005300BID (2014)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Nov. 13, 2014 Number: 14-005300BID Latest Update: Aug. 12, 2015

The Issue Whether, in issuing the Revised Recommendation/Tabulation for contracts for Items 1 and 3 for Invitation to Bid No. 15- 048E, Multifunctional Devices, Cost-Per-Copy, Respondent acted contrary to one or more governing statutes, rules, policies, or procurement specifications, or any combination thereof; and if so, for each such instance, whether the misstep was clearly erroneous, arbitrary or capricious, or contrary to competition.

Findings Of Fact On June 3, 2014, SBBC issued ITB No. 15-048E (the ITB) entitled "Multifunctional Devices, Cost-Per-Copy" for the provision and maintenance of copying devices during the contract term. The listed Submittal Requirements were: Manufacturer's Authorization Special Condition 8; Descriptive Literature Special Condition 6; and Material Safety Data Sheets Special Condition 16. A Bidder's Preference Statement was not identified as a Submittal Requirement. Section 4, Paragraph 2, of the ITB was entitled "TERM" and notified bidders that SBBC sought through the award of this bid to "establish a contract for the period beginning from the date of award and continuing through June 30, 2017." The Bid Summary Sheet found at Section 5 of the ITB requested bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months and for 36 months. Page 1 of the ITB contained a certification to be executed by each bidder's authorized representative which stated in pertinent part as follows: Bidder agrees to be bound to any and all specifications, terms and conditions contained in the ITB, and any released Addenda and understand that the following are requirements of this ITB and failure to comply will result in disqualification of bid submitted. All bidders submitted a signed bidder certification. Section 3, Paragraph 1(a), of the General Conditions of the ITB provided as follows: SEALED BID REQUIREMENTS: The "Bidder Acknowledgment Section" must be completed, signed and returned with the bid. The Bid Summary Sheet pages on which the Bidder actually submits a bid, and any pages, upon which information is required to be inserted, must be completed and submitted with the bid. The School Board of Broward County (SBBC) reserves the right to reject any bid that fails to comply with these submittal requirements. BIDDER'S RESPONSIBILITY: It is the responsibility of the Bidder to be certain that all numbered pages of the bid and all attachments thereto are received and all Addendum released are received prior to submitting a bid without regard to how a copy of this ITB was obtained. All bids are subject to the conditions specified herein on the attached bid documents and on any Addenda issued thereto. Section 3, Paragraph 6, of the General Conditions of the ITB provided as follows: AWARDS: In the best interest of SBBC, the Board reserves the right to: 1) withdraw this bid at any time prior to the time and date specified for the bid opening; 2) to reject any or all bids received when there are sound documented business reasons that serve the best interest of SBBC; 3) to accept any item or group of items unless qualified by Bidder; and 4) to acquire additional quantities at prices quoted on this ITB unless additional quantities are not acceptable, in which case, the bid sheets must be noted "BID IS FOR SPECIFIED QUANTITY ONLY." On June 18, 2014, SBBC issued Addendum Number 1 for the ITB which replaced a number of pages within the bidding documents and contained responses to questions posed by prospective bidders. Addendum Number 1 included Question No. 6 in which Xerox inquired whether SBBC "would . . . consider a change to the contract term of the contract to 48 or 60-month term?" SBBC responded through Addendum Number 1 that it had amended the bid "to include additional pricing for 48 or 60-months term[s]," and SBBC continued to request proposals for a 36-month contract term. Addendum Number 1 revised Section 4, Paragraph 2, of the Special Conditions of the ITB to state as follows: TERM: The award of this bid shall establish a contract for the period beginning from the date of award and continuing through an award for a term of 36, 48 or 60 months. Bids will not be considered for a shorter period of time. All prices quoted must be firm throughout the contract period. Items will be ordered on an as needed basis. Addendum Number 1 included an Appendix A–Summary Cost Sheet which required bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months, 36 months, 48 months, and 60 months. On June 20, 2014, SBBC issued Addendum Number 2 for the ITB. The first page of Addendum Number 2 advised prospective bidders, "This Addendum amends the above referenced bid in the following particulars only: 1. DELETE: Appendix A–Cost Summary Sheet INSERT: Revised Appendix A–Cost Summary Sheet." The first page of Addendum Number 2 further cautioned bidders that "[i]t is important to include the REVISED page when submitting your response." Addendum Number 2 went on to provide a Revised- Appendix A-Summary Cost Sheet which stated "A Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months" and included a cost summary sheet for each of those three options. The ITB and addenda numbers 1 and 2 were released by SBBC via Onvia DemandStar, with email notices thereof to prospective vendors who subscribed to its bid notification service. Toshiba downloaded the ITB, Addendum Number 1, and at least the first page of Addendum Number 2 from DemandStar prior to the submission of its bid to SBBC. Again, the first page of Addendum Number 2 cautioned bidders that Appendix A–Summary Cost Sheet had been deleted and replaced and that it was "important to include the REVISED page when submitting your response." No bid specifications protest was filed by any person or entity concerning the ITB or addenda numbers 1 or 2. On July 3, 2014, SBBC opened bids timely submitted in response to the ITB by: Toshiba; ImageNet; Innovative; Lexmark International, Inc.; and Ricoh. Konica had also presented a bid to SBBC in the bid opening room prior to the opening of bids but after the announced time for submittal of bids. The Konica bid was delivered to SBBC but was not opened at the time of the bid opening. Toshiba, the incumbent, was the only bidder that violated the pricing requirements of the ITB. The bid submitted by Toshiba utilized the version of Appendix A-Summary Cost Sheet that was released under Addendum Number 1 and only offered cost- per-copy pricing for the 60-month term option. Toshiba's bid did not submit the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, nor did it contain any bids offering cost per copy pricing to SBBC for the 36 or 48-month term options. Although Toshiba's bid was not rejected as non-responsive for failing to bid on the 36 and 48-month term options and for failing to utilize and complete the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, SBBC's staff later concluded in hindsight that it should have been rejected for such non-compliance. Toshiba's bid included a "Pricing" note immediately prior to its Appendix A–Summary Cost Sheet that stated: [Toshiba] is proposing a 60 month CPC as a response to the [ITB]. Based on the fact the [ITB] has no minimum, cancellation for convenience, ability to upgrade and downgrade with no penalty, it is in the best interest of our organization to bid a term of 60 months. This term allows us to provide the most aggressive price to the [SBBC] and maintain the excellent service and support level in place. SBBC's staff recommended that an award be made under the ITB for pricing offered for a 36-month contract term for Items 1, 2, and 3 for a contract period of August 6, 2014, through September 30, 2017. On July 10, 2014, SBBC posted its initial ITB Recommendation/Tabulation which did not consider the Konica bid. The initial posted Recommendation/Tabulation notified bidders of SBBC's intended award of contracts for Items 1 and 2 to ImageNet as the primary awardee and to Innovative as the alternate awardee for a contract period of August 6, 2014, through September 30, 2017, and recommended the award of contracts for Item 3 to Ricoh as primary awardee and to ImageNet as alternate awardee for a contract period of August 6, 2014, through September 30, 2017. Timely bid protests and bid protest bonds were filed by Konica and by Toshiba concerning SBBC's initial Recommendation/Tabulation of July 10, 2014. SBBC's Bid Protest Committee conducted a meeting with the protestors on August 26, 2014, and determined that Konica's bid had been timely submitted and directed SBBC's Procurement and Warehousing Services Department (the Department) to evaluate Konica's bid for responsiveness. It also directed the Department to revise its recommendation on the ITB to reject Toshiba's bid for Item 2 as the device offered by Toshiba for that item did not meet the ITB's specifications which called for a single device capable of performing 95 copies per minute (cpm) and Toshiba instead offered two devices that performed at 85 cpm. After reviewing Konica's bid for responsiveness, SBBC posted a Revised Recommendation/Tabulation for the ITB on August 29, 2014, which (a) recommended award of Item 1 to ImageNet for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to Innovative as the alternate awardee; (b) recommended award of Item 3 to Ricoh for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to ImageNet as the alternate awardee; and (c) recommended the rejection of Toshiba's bid for Item 2 for its failure to meet the specifications for that Item. On September 4, 2014, Toshiba timely filed its notice of intent to protest the August 29, 2014, posted Revised Recommendation/Tabulation. On September 15, 2014, Toshiba timely filed its Amended Formal Petition Protesting Proposed Revised Recommendation/Tabulation. SBBC's Bid Protest Committee conducted a meeting with Toshiba on November 5, 2014, pursuant to section 120.57(3), SBBC Purchasing Policy 3320, and the ITB, and rejected Toshiba's bid protest. On November 10, 2014, Toshiba timely requested that SBBC forward its bid protest to DOAH for a formal hearing. Toshiba has presented a number of arguments in these proceedings seeking to avoid the circumstances Toshiba created for itself when it failed to comply with Addendum Number 2 and violated the ITB's pricing requirements and the ITB's requirement as to the term of the contract to be awarded, when Toshiba only submitted a single bid and restricted the contract term for which it would be considered to 60 months. First, Toshiba attempts to divest SBBC of its express authority to select proposals for any contract duration for which it solicited bids other than for a month term. Second, Toshiba argues that SBBC was somehow obligated to specify within the bid specifications those business considerations that would inform SBBC's selection of the duration of the contract term to be awarded under the ITB. Third, Toshiba argues that ImageNet was non-responsive regarding the ITB's specifications concerning manufacturer's certifications. Toshiba also argues that all bidders, including itself, were non- responsive with regard to the ITB's specifications regarding bidding preference laws. None of the arguments presented by Toshiba in opposition to SBBC's intended award of Items 1 and 3 are persuasive. The Selection of the 36-Month Term SBBC's recommended award for a 36-month contract period from October 7, 2014, through November 30, 2017, is consistent with the terms and conditions of the ITB and its addenda. At the very start of this competitive solicitation, SBBC informed bidders through Section 4, Paragraph 2, of the ITB and the Bid Summary Sheet at Section 5 of the ITB that it was seeking a contract through June 30, 2017-–i.e., a 36-month contract. SBBC also made it clear in its response to Question No. 6 of Addendum Number 1 that "[t]he contract will be for a full 36 months." Although SBBC revised the bid specifications through Addendum Number 1 to allow bidders to submit "additional pricing for 48 and 60 months term[s]," "to allow the School District to consider a 48 and/or 60 months term contract," and revised Section 4, Paragraph 2, of the ITB to provide for "an award for a term of 36, 48 or 60 months," it was clear under the ITB that SBBC contemplated that a 36-month contract could serve its needs. Addendum Number 2 further revised the bid specifications by providing the Revised–Appendix A–Summary Cost Sheet which informed bidders that "a Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months." SBBC intended to review the additional pricing offered for 48 and 60- month contract terms to determine whether those particular options were a better business decision for SBBC. Several factors were considered by SBBC in selecting the contract duration for the award under the ITB. The selection of the shorter 36-month contract term was consistent with the expressed terms of the ITB and addenda and the expressed preference of SBBC's governing board to refrain from entering into long-term contracts and enabled SBBC to be flexible in finding solutions to its copying needs and to take advantage of changes that may arise in technology; avoided problems the school district was currently experiencing with a long-term cost-per- copy contract which ranged from equipment performance issues to the long-term placement of technology in schools; and enabled the school district to conduct research to determine whether future implementation of a managed print solution would provide the school district with additional cost savings or financial benefits in contrast to the cost-per-copy services being procured through the ITB. Clearly, this selection was neither arbitrary nor capricious. SBBC's elected governing board has made it known by its actions taken at public meetings that it disfavors long-term contracts for the procurement of goods and services and has gone so far as to reduce the term of contracts from the dais. SBBC's staff determined that the pricing offered to SBBC for a 60-month contract term was not significant enough to recommend a contract longer than the 36-month term SBBC had been requesting since the release of the ITB. Any cost advantages offered by Toshiba's bids for Items 1, 2, and 3 were reduced by $525,000 per year due to the disqualification of its bid for Item 2, which failed to meet the ITB's specifications. Consideration of Managed Print Services Xerox Corporation informed SBBC that a managed print services (MPS) program could save millions of dollars per year and later submitted a no bid response to SBBC regarding the ITB because SBBC was not implementing a MPS program under the ITB. SBBC had also received proposals from vendors in October 2013 concerning a MPS program and concluded that there existed a potential annual savings of millions of dollars if such a program could be implemented. All of which were additional reasonable, rational reasons for SBBC to remain consistent with its decision to award the contracts for a term of 36 months and not something longer. The ITB contains standard terms and conditions which enable SBBC to terminate an awarded contract regardless of reason and with or without cause upon 30 days written notice to the other party. Toshiba wants SBBC to rescue Toshiba from its failure to submit required bids for 36-month and 48-month periods by forcing SBBC to award a contract obligating the agency for a longer duration under the ITB than desired by the agency and then have SBBC terminate the 60-month contract award for convenience after 36 months. SBBC includes termination for convenience provisions within its contracts for goods and services due to section 1011.14, Florida Statutes, which restricts the ability of district school boards to obligate public funds for a period beyond one year. The inclusion of the standard termination for convenience clauses in its ITBs enables SBBC to enter into contracts exceeding one year which affords the school district opportunities to obtain continuity of service and price advantages that would not be available under shorter contracts. While SBBC has the ability under the ITB to terminate contracts for convenience upon 30 days' notice, it rarely does so. SBBC has never exercised its right to terminate its two prior contracts for the services sought under this ITB. Any such termination requires action by SBBC's governing board during a public meeting. SBBC's staff would not engage in the sham of recommending a contract to its governing board for a contract term longer than the period for which it intends to procure services from a vendor. SBBC's procurement staff believes that using the termination for convenience clause in the manner Toshiba recommends can have an adverse effect upon the school district's ability to encourage bidders to participate in its competitive solicitations or to offer it their best pricing. Questions 1 and 59 of Addendum Number 1 of the ITB provide evidence of concern within the bidding marketplace that SBBC might exercise its termination for convenience clauses with regard to the services being procured under the ITB and support the perception of SBBC's that it should avoid a reputation for exercising such termination authority. Toshiba argues that SBBC somehow materially misled bidders through the ITB by stating in response to Question No. 3 concerning MPS of Addendum Number 1 that: The School District is not planning to implement a Managed Print Services at this time. The School District would like to receive Additional information regarding other districts that have implemented a Managed Print Services. There are no evaluation points associated with this ITB. SBBC's responses to Question No. 3 of Addendum Number 1 were accurate and did not mislead bidders. Toshiba is the only bidder to claim to have been misled. Section 6, Paragraph 10, of the ITB requested bidders provide SBBC with information about how the awardee could transition SBBC to a MPS model from the cost-per-copy model being offered under its bid. While SBBC requested such information from vendors within the bidding marketplace, there is no evidence that any bidder's provision or omission of such information within its bid submission was considered in the selection of the recommended awardees. In fact, ImageNet was recommended for award even though it did not provide this ancillary information about transition to a MPS delivery model. Rather, the recommended awardees for a 36-month contract term for Items 1 and 3 were determined solely on the basis of cost submitted for those items by the bidders, all in accordance with the ITB. A MPS program was a possible initiative being considered by SBBC's former Chief Information Officer prior to his departure from SBBC in February 2014, at which time the school district's current cost-per-copy contract was nearing its expiration. Although SBBC still had an interest in the possibility of a MPS program, it was not going in that direction at the time it needed to release a bid for copying services to replace its current expiring contract. Toshiba contends that SBBC was somehow required to disclose to bidders whether the potential future implementation of a MPS program might impact the contract award period that SBBC might choose under the ITB. A myriad of business considerations may inform an agency in selecting the length of its contracts for goods and services, and there is no law or rule that requires an agency to specify those factors within an ITB. Responsiveness of the Bidders Toshiba has attempted to argue that ImageNet, the recommended awardee for Item 1 and the alternate awardee for Item 3, was somehow non-responsive under the ITB and ineligible for award. In support of this argument, Toshiba has referenced Section 4, Paragraph 8, of the Special Conditions of the ITB which state as follows: MANUFACTURER'S CERTIFICATION: Bidder must submit with their ITB a notarized letter from manufacturer certifying that bidder is authorized to sell, service and warrant the multifunctional devices offered within this ITB. Failure of the bidder to provide this letter with their submitted bid or upon request shall result in disqualification of entire bid. If the bidder is the manufacturer, then bidder should state that their company is the manufacturer of the equipment provided in this bid (the letter does not need to be notarized). A bid is only disqualified under Section 4, Paragraph 8, of the ITB if (1) a notarized manufacturer's letter is omitted from the bid; and (2) the bidder fails to comply with a subsequent request from SBBC to provide the letter. No bidder, including Toshiba and ImageNet, included a notarized letter from a manufacturer with its bid. SBBC did not request any of the bidders to submit a notarized manufacturer's letter at any time after the submission of bids. As a result, none of the bids, including that of ImageNet, was non-responsive for a failure to satisfy Paragraph 8 of Section 4 of the ITB. Toshiba has also argued that all bids should be rejected due to Section 3, Paragraph 1(d), of the General Conditions of the ITB which concerns bidders' preference laws and states as follows: d) BIDDING PREFERENCE LAWS: ALL BIDDERS MUST COMPLETE AND SUBMIT THE LEGAL OPINION OF BIDDER'S PREFERENCE FORM IN ORDER TO BE CONSIDERED [sic] FOR AWARD. The State of Florida provides a Bidder's preference for Florida vendors for the purchase of personal property. The local preference is five (5) percent. Bidders outside the State of Florida must have an Attorney, licensed to practice law in the out-of-state jurisdiction, as required by Florida Statute 287.084(2), execute the "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form and must submit this form with the submitted bid. Such opinion should permit SBBC's reliance on such attorney's opinion for purposes of complying with Florida Statute 287.084. Florida Bidders must also complete its portion of the form. Failure to submit and execute this form, with the bid, shall result in bid being considered "non-responsive" and bid rejected. No bidder, including Toshiba, included an "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form with its bid. Each bidder's omission of that form was for good reason. Section 3, Paragraph 1(d), of the General Conditions of the ITB is a boilerplate provision within SBBC's standard bidding documents that is included pursuant to section 297.084(2), Florida Statutes, for any competitive solicitations in which personal property is to be purchased by SBBC. In instances in which it solicits bids to purchase personal property, SBBC includes a "Bidder's Preference Statement" form and includes that form among the checked "Submittal Requirements" listed in Section 2, Page 1, of the ITB. This ITB did not include a "Bidders Preference Statement" form among the bidding documents or list it as one of the required submittals. The state law and the boilerplate provision at Section 3, Paragraph 1(d), of the General Conditions of the ITB are only applicable to competitive solicitations for the purchase of personal property and do not extend to competitive solicitations for the purchase of services. As Section 4, Paragraph 12, of the Special Conditions of the ITB makes it clear that the multi-functional devices to be provided by the awardee under the ITB will "remain the property of the vendor," the standard bidder's preference provision contained within the ITB is plainly inapplicable to this procurement.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a final order that adopts the Findings of Fact and Conclusions of Law contained herein, dismisses the protest filed by Toshiba Business Solutions (USA), Inc., and upholds the awards of contracts under the procurement for a 36-month term from October 7, 2014, through November 30, 2017, to ImageNet Consulting of Miami, Inc., as the primary awardee for Item 1 and to Innovative Software Solution, Inc., as the alternate awardee for Item 1, and to Ricoh USA, Inc., as the primary awardee for Item 3 and to ImageNet Consulting of Miami, Inc., as the alternate awardee for Item 3. DONE AND ENTERED this 15th day of June, 2015, in Tallahassee, Leon County, Florida. S MARY LI CREASY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of June, 2015. COPIES FURNISHED: Robert Paul Vignola, Esquire Office of the General Counsel Eleventh Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) William G. Salim, Jr., Esquire Moskowitz, Mandell, Salim and Simowitz, P.A. 800 Corporate Drive, Suite 500 Fort Lauderdale, Florida 33334 (eServed) Eric J. Rayman, Esquire Genovese, Joblove and Battista, P.A. PNC Center, Suite 1110 200 East Broward Boulevard Fort Lauderdale, Florida 33301 (eServed) Albert E. Dotson, Esquire Wendy Francois, Esquire Bilzin, Sumberg, Baena, Price and Axelrod, LLP 1450 Brickell Avenue, Suite 2300 Miami, Florida 33131 (eServed) Matthew Mears, General Counsel Department of Education Turlington Building, Suite 1244 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed) Robert W. Runcie, Superintendent Broward County School Board Tenth Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) Pam Stewart Commissioner of Education Department of Education Turlington Building, Suite 1514 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed)

Florida Laws (6) 1011.14120.53120.569120.57120.68287.084
# 7
TALLAHASSEE ASSOCIATES, LTD. vs DIVISION OF LICENSING AND CROSSLAND AGENCY, 91-001306BID (1991)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 26, 1991 Number: 91-001306BID Latest Update: Mar. 22, 1991

Findings Of Fact In November, 1990, the Respondent, the Department of State, sought proposals for the lease of office space for its Division of Licensing. On or prior to December 7, 1990, the proposal opening date, at least six proposals were received by the Respondent. Those proposals were designated by the Respondent as "Tallahassee Associates" (the Petitioner's proposal), "Crossland Agency" (the Intervenor's proposal), "Woodcrest A", "Woodcrest B", "T.C.S." and "DeVoe". On January 2, 1991, the Respondent posted a standard form Bid Tabulation indicating that the following scores had been awarded to the following proposals: Proposal Score Woodcrest A 82 Woodcrest B 82 Tallahassee Associates 73 Crossland Agency 85 DeVoe 54 The proposal of T.C.S. was not evaluated by the Respondent because it was determined to be non-responsive. The Respondent also posted a copy of a memorandum dated January 2, 1991, with the January 2, 1991, Bid Tabulation. The memorandum was from John M. Russi, Director of the Division of Licensing, to Ira Chester, Chief of the Bureau of General Services. Mr. Russi indicated in the memorandum that the Intervenor would be awarded the lease. Attached to Mr. Russi's January 2, 1991, memorandum was a Lease Evaluation Worksheet which indicated the scores which had been awarded by the evaluation committee to the responsive bidders for each of the criteria to be considered in determining the winning bidder. Printed at the top-center of the January 2, 1991, Bid Tabulation was the following notice: FAILURE TO FILE A PROTEST WITHIN THE TIME PRESCRIBED IN SECTION 120.53(5), FLORIDA STATUTES, SHALL CONSTITUTE A WAIVER OF PROCEEDINGS UNDER CHAPTER 120, FLORIDA STATUTES. . . . The January 2, 1991, Bid Tabulation was posted at 1:00 p.m., January 2, 1991. Therefore, pursuant to Section 120.53(5), Florida Statutes, any bidder desiring to contest the Respondent's proposed award of the lease was required to file a notice of protest with the Respondent no later than 1:00 p.m., January 5, 1991, and a formal written protest on or before January 15, 1991. T.C.S. filed a notice of protest and a formal written protest to the January 2, 1991, Bid Tabulation within the time periods prescribed by Section 120.53(5), Florida Statutes. T.C.S. contested the Respondent's determination that it was not responsive. The Petitioner did not file a notice of protest or a formal written protest to the January 2, 1991, Bid Tabulation within the time periods prescribed by Section 120.53(5), Florida Statutes. Pursuant to Section 120.53(5), Florida Statutes, the Respondent reviewed the formal written protest filed by T.C.S. and agreed that T.C.S. was responsive. After agreeing that T.C.S. was responsive, the Respondent evaluated T.C.S.'s proposal and awarded points for each of the criteria to be considered. Toward the end of January, 1991, after deciding that T.C.S.'s proposal was to be evaluated, the Respondent notified all other bidders of its decision in a document titled Posting of Notice of Agency Decision. The Posting of Notice of Agency Decision was signed by the Respondent's General Counsel and was addressed to "All Responsive Bidders". The Posting of Notice of Agency Decision provided, in pertinent part: Notice is hereby given that the Florida Department of State, Division of Licensing, is reviewing the bid tabulation which was posted at 1:00 P.M., January 2, 1991 for Lease No. 450:0070. The revised bid tabulation will be posted at 8:00 A.M. on February 4, 1991 at the Purchasing Office of the Department of State . . . . Failure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes, shall constitute a waiver of proceeding under Chapter 120, Florida Statutes. Any person interested in the new tabulation should contact . . . after the posting time listed above. The Petitioner filed a notice of protest and a formal written protest challenging the Posting of Notice of Agency Decision within the times prescribed by Section 120.53(5), Florida Statutes. The Respondent dismissed this formal written protest by final order dated February 22, 1991. On or about January 31, 1991, more than four weeks after the posting of the January 2, 1991, Bid Tabulation, Ocie Allen spoke by telephone with Phyllis Slater, the Respondent's General Counsel. Ms. Slater told Mr. Allen that all proposals would be reevaluated as a result of T.C.S.'s protest. Mr. Allen was a lobbyist for the Petitioner in January, 1991. On February 4, 1991, the Respondent posted another standard form Bid Tabulation indicating that the following scores had been awarded to the following proposals: Proposal Score Crossland Agency 83 Woodcrest A 80 Woodcrest B 80 Tallahassee Associates 71 T.C.S. 71 DeVoe 51 The differences in the scores of the proposals which had been listed on the January 2, 1991, Bid Tabulation, which are reflected in the February 4, 1991, Bid Tabulation were caused by automatic changes in the scores resulting from the addition of T.C.S. and the fact that T.C.S. had the lowest priced bid. The points awarded for the "rental" criterion, which was worth up to 25 points, were determined by a mathematical formula by which the scores of each bidder are calculated based upon the proposed rental charges of all bidders. The award of points for this criterion was determined objectively based upon the mathematical formula. By adding another bidder, T.C.S., the points awarded to all the proposals automatically changed. The scores of the proposals which had been listed on the January 2, 1991, Bid Tabulation, were not otherwise changed. Nor were the proposals of any bidder reevaluated. The Respondent also posted a copy of a memorandum dated January 24, 1991, with the February 4, 1991, Bid Tabulation. The memorandum was from John M. Russi, Director of the Division of Licensing, to Ira Chester, Chief of the Bureau of General Services. Mr. Russi indicated the following in the memorandum: Pursuant to the settlement stipulation signed by Counsel for T.C.S. Associates on January 23, 1991, in reference to the Bid Protest filed January 11, 1991, the attached "Lease Evaluation Work Sheet" is provided for you to re-post. After reevaluating six bid proposals, the evaluating committee concludes that Crossland Agency should be awarded this bid. Each bidder needs to be notified by certified mail of this action. . . . . Attached to Mr. Russi's January 24, 1991, memorandum was a Lease Evaluation Worksheet which indicated the scores of the responsive bidders which had been awarded by the evaluation committee for each of the criteria to be considered in determining the winning bidder. On February 6, 1991, the Petitioner filed a notice of protest to the February 4, 1991, Bid Tabulation. The Petitioner filed a Formal Written Protest, Request for Formal Hearing and Motion for Stay with the Respondent on February 18, 1991. These documents were filed within the time periods specified in Section 120.53(5), Florida Statutes. The Petitioner's Formal Written Protest was filed with the Division of Administrative Hearings by the Respondent on February 28, 1991. Crossland Agency, Inc., was allowed to intervene in the proceeding. On March 1, 1991, the Respondent and Intervenor filed a Motion to Dismiss. A motion hearing was conducted on March 6, 1991, to consider the Motion to Dismiss.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be issued by the Respondent granting the Motion to Dismiss and dismissing this case, with prejudice. DONE and ENTERED this 22nd day of March, 1991, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of March, 1991. APPENDIX TO RECOMMENDED ORDER The parties have submitted proposed findings of fact. It has been noted below which proposed findings of fact have been generally accepted and the paragraph number(s) in the Recommended Order where they have been accepted, if any. Those proposed findings of fact which have been rejected and the reason for their rejection have also been noted. The Petitioner's Proposed Findings of Fact Proposed Finding Paragraph Number in Recommended Order of Fact Number of Acceptance or Reason for Rejection 1 3, 5 and 9. 2 12-13. 3 15-16 and 18-21. See 14. 15. The weight of the evidence failed to prove that the scores of the bidders for the "option period" criterion reflected on the January 2, 1991, Bid Tabulation were modified or reconsidered on the February 4, 1991, Bid Tabulation. The suggestion that "the department had discretion to change scores in any of the remaining eight categories" is a conclusion of law and is rejected. These proposed facts are not relevant to the issue raised in the Motion to Dismiss. Nor was any evidence presented to support these proposed findings. 12. The last sentence is a conclusion of law and is rejected. Proposed Findings of Fact of the Respondent and Intervenor Proposed Finding Paragraph Number in Recommended Order of Fact Number of Acceptance or Reason for Rejection 1 1-2. 3 and 7. 5-6 and hereby accepted. 4 8-12. 5 See 14. 6 15 and 17. 18. The last sentence involves an issue not raised in the Motion to Dismiss or at the motion hearing. Nor was any evidence presented to support these proposed findings. See the Preliminary Statement. COPIES FURNISHED: Linda G. Miklowitz, Esquire 1589 Metropolitan Boulevard Tallahassee, Florida 32308 Benjamin E. Poitevent Assistant General Counsel Department of State The Capitol, MS #4 Tallahassee, Florida 32399-0250 M. Christopher Bryant, Esquire Post Office Box 6507 Tallahassee, Florida 32314-6507 Honorable Jim Smith Secretary of State The Capitol Tallahassee, Florida 32399-0250

Florida Laws (3) 120.53120.57255.25
# 8
DADE COUNTY INVESTMENTS COMPANY AND LUTZ CRUZ vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 91-004470BID (1991)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 19, 1991 Number: 91-004470BID Latest Update: Oct. 31, 1991

The Issue Whether Respondent should sustain Petitioners' challenge to the preliminary determination to reject their bid as not responsive to Respondent's Invitation to Bid for Lease No. 590: 2286? 1/

Findings Of Fact Based on the record evidence, the following Findings of Fact are made: Earlier this year, Respondent issued an Invitation to Bid for Lease No. 590: 2286 (hereinafter referred to as the "ITB"). The first page of the ITB contained the Bid Advertisement, which read as follows: The State of Florida, Department of Health and Rehabilitative Services is seeking an existing facility in Dade County to lease for use as office space containing approximately 30,086 net rentable square feet. The space proposed must be an office environment. Converted factories/warehouses in industrial areas are not acceptable. The facility shall be located within the following boundaries: North By S.W. 8th Street, South By S.W. 88th Street, East By S.W. 37th Avenue, Southeast By South Dixie Highway, and West By S.W. 87th Avenue. Any facility located on a parcel of land which abuts any of the street boundaries is consider[ed] within the boundaries. Occupancy date of 8/01/91. Desire a Ten (10) year lease with three (3)- two (2) year renewal options. Information and specifications may be obtained from Mr. Philip A. Davis, Facilities Services Manager, 401 N.W. 2nd Avenue, Suite S721, Miami, Florida 3312, (305) 377-5710. Please reference lease number 590: 2286. Program requirements will be discussed at a pre-proposal conference to be held at 10:00 a.m. on 4/22/91 at 401 N.W. 2nd Avenue, Suite S721 Miami, Florida 33128. Bid opening date will be on 5/30/91 at 10:00 a.m. at the above mentioned address. Minority business enterprises are encouraged to attend the pre-proposal conference and participate in the bid process. The Florida Department of Health and Rehabilitative Services reserves the right to reject any and all bids and award to the bid judged to be in the best interest of the state. The second page of the ITB contained the definitions of various terms used in the ITB. Among the terms defined were "dry and measurable" and "existing building." "Dry and measurable" was defined as follows: These are essential characteristics to describe "existing" proposed space. To be considered as "dry and measurable" the proposed space must be enclosed with finished roof and exterior walls in place. Interior floors need not be completed. Exterior windows and doors need not be installed. The proposed area is not required to be completed. These characteristics conform to standard lessor construction practices. This definition is identical to the definition of this term found on page 1-5 of Respondent's leasing manual, HRSM 70-1. "Existing building" was defined as follows: To be considered as existing the entire space being bid must be dry and capable of being physically measured to determine net rentable square footage. at the time of bid submittal. On the ninth page of the ITB, the following advisements, among others, were given: The department reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida. Such rejec- tion shall not be arbitrary, but be based on strong justification which shall be communi- cated to each rejected bidder by certified mail. * * * The department reserves the right to waive any minor informalities or technicality and seek clarification of bids received when such is in the best interest of the state, but not limited to the correction of simple mistakes or typo- graphical errors. Such corrections will be initiated [sic] and dated on the original bid submittal by the bidder. Attached to the ITB and incorporated therein was a document entitled "Standard Method of Space Measurement." It read as follows: The purpose of this standard is to permit communication and computation on a clear and understandable basis. Another important purpose is to allow comparison of values on the basis of a generally agreed upon unit of measurement (net square footage). It should also be noted that this standard can and should be used in measuring office space in old as well as new buildings, leased office space as well as State-owned office space. It is applicable to any architectural design or type of construction because it is based on the premise that the area being measured is that which the agency may occupy and use for its furnishings and its people. This standard method of measuring office space measures only occupiable space, undistorted by variances in design from one building to another. It measures the area of office building that actually has usable (rental) value and, therefore, as a standard can be used by all parties with confidence and a clear understanding of what is being measured. Area Measurement in office buildings is based in all cases upon the typical floor plans, and barring structural changes which affect materially the typical floor, such measurements stand for the life of the building, regardless of readjustments incident to agency layouts. All usable (rentable) office space, private sector leased, State-owned, or other publicly owned shall be computed by: Measuring to the inside finish of permanent outer building walls to the office side of corridors and/or other permanent partitions, and to the center of partitions that separate the premises from adjoining usable areas. This usable (rentable) area shall EXCLUDE: bathrooms, public corridors, stairs, elevator shafts, flues, pipe shafts, vertical ducts, air-conditioning rooms, fan rooms, janitor closets, electrical closets, telephone equipment rooms, - - and such other rooms not actually available to the tenant for his furnishings and personnel - - and their enclosing walls. No deductions shall be made for columns and projections structurally necessary to the building. The attached typical floor plan illustrates the application of this standard. 3/ Petitioners submitted a bid in response to the ITB. 4/ In their bid they proposed to lease to Respondent space on the first and second floors of a building located at 8500 S.W. 8th Street in Miami, Florida. The space offered by Petitioners is currently occupied. At the time of bid submittal, all of the proposed space on the second floor was "dry and measurable," as that term is defined in the ITB. It encompassed a total of 26,540 square feet. At the time of bid submittal, only a portion of the proposed space on the first floor, amounting to 4,400 square feet, was "dry and measurable," as that term is defined in the ITB, inasmuch as the proposed space on this floor included a breezeway area that did not have either a front or back exterior wall in place. 5/ Subsequent to the submission and opening of bids, Petitioners enclosed this breezeway area by erecting exterior walls. Accordingly, the entire space offered by Petitioners was not "dry and measurable" at the time of bid submittal as required by the ITB. Bids were opened by Respondent on May 30, 1991. By letter dated June 18, 1991, Respondent notified Petitioners that their bid had been deemed non-responsive. The letter read as follows: The bid you submitted for lease No. 590: 2286 has been determined to be non-responsive because the proposed space is not dry and measurable. The breezeway area proposed on the ground level of your premises at 8500 S.W. 8 Street, Miami, does not have exterior walls in place. The invitation to bid on lease No. 590: 2286 provides on page 2: "Dry and Measurable- These are essential characteristics to describe "existing" proposed space. To be considered as "dry and measur- able," the proposed space must be enclosed with finished roof and exterior walls in place. You have the right to file a protest. The protest must be filed in accordance with S.120.53(5), Florida Statutes and Chapter 10-13.11 Florida Administrative Code. Failure to file a protest within the time prescribed in S.120.53(5), Florida Statutes, shall constitute a waiver of proceedings under chapter 120, Florida Statutes. To comply with the referenced statute, a written notice of intent to protest must be filed with the contact person listed on the Invitation to Bid for lease No. 590: 2286 within 72 hours after receipt of this notice. Within ten calendar days after the notice of protest is filed, a formal written protest and protest bond must be filed with the contact person. The bond must be payable to the department in an amount equal to one percent of the total lease payments over the term of the lease or $5,000, whichever is less. This determination was the product of, not any unlawful bias or prejudice against Petitioners, but rather the honest exercise of the agency's discretion. Petitioners subsequently filed a protest of this preliminary determination to find their bid non-responsive. It is this preliminary determination that is the subject of the instant bid protest proceeding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby recommended that the Department of Health and Rehabilitative Services enter a final order rejecting Petitioners' bid for Lease No. 590: 2286 on the ground that said bid is non-responsive. RECOMMENDED in Tallahassee, Leon County, Florida, this 25th day of September, 1991. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of September, 1991.

Florida Laws (2) 255.249255.25
# 9
DAVID NIXON, INC. vs DEPARTMENT OF CORRECTIONS, 90-006278BID (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 05, 1990 Number: 90-006278BID Latest Update: Jan. 15, 1991

The Issue The Department of Corrections sought bids for construction of a health services building for a correctional facility. A discrepancy existed between the written specifications and the architectural drawings for the project. An addendum was issued to clarify the matter. The low bidder (Intervenor) did not acknowledge receipt of the addendum until several hours after the opening of bids. The Department accepted the Intervenor's bid. The Petitioner timely protested the action. The issue in this case is whether, in accepting the Intervenor's bid, the Department acted contrary to the requirements of law.

Findings Of Fact On July 31, 1990, the Department of Corrections (hereinafter "Department") issued an Invitation To Bid ("ITB") for PR-35-JRA, Project #90015, consisting of the construction of a Health Classification Building at the Columbia County Correctional Institution. In relevant part, the ITB requested price proposals for said construction, provided that the bid would be awarded to the responsive bidder submitting the lowest cost proposal, provided that "in the interest" of the Department, "any informality" in bids could be waived, and provided space on the bid form for acknowledgment of receipt of all addenda to the ITB. Bids were to be filed no later than 2:00 p.m. on September 11, 1990, the time scheduled for bid opening. Documents issued with the ITB included architectural drawings and written specifications for the building. The architectural firm of Jim Roberson and Associates, (hereinafter "JRA") had been employed by the Department to prepare the drawings and specifications. JRA was responsible for preparation and distribution of related addenda. Further, a JRA representative presided over the opening of bids on behalf of the Department. Following release of the ITB and supporting documents, JRA became aware of a conflict between sink faucets required by the drawings and those required by the written specifications. The specifications provided that sink faucets operated by hand levers or foot pedals were to be installed in the facility. The architectural drawings JRA indicated that sink faucets were to operate by means of "electric-eye" activators, rather than by hand levers or foot pedals. On September 10, 1990, JRA issued an addendum (identified as Addendum #2) 1/ to clarify that "electric-eye" type operators were to be included in the bids. The addendum was sent by telephone facsimile machine to all anticipated bidders. In part the addendum provides as follows: "This Addendum forms a part of the Contract Documents and modifies the original Specifications and Drawings, dated 31 July 1990, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to Disqualification." On September 11, 1990, the eight bids submitted in response to the ITB were opened by the JRA representative. The Intervenor, Custom Construction (hereinafter "Custom"), submitted the lowest bid at $898,898. The Petitioner, David Nixon (hereinafter "Nixon"), submitted the next lowest bid at $900,000. The bid form provided by the Department as part of the ITB materials to prospective bidders provided space for acknowledgment of addenda to the ITB documents. Upon opening the bid submitted by Custom, the JRA representative officiating at the opening noted that the Custom bid failed to acknowledge Addendum #2 in the appropriate space on the bid form. 2/ Robert L. Harris, president of Custom Construction, attended the bid opening. When the JRA representative noted the lack of acknowledgment of Addendum #2, Mr. Harris stated that he was unaware of the addendum. At hearing, Mr. Harris testified that his secretary told him that Addendum #2 was not received by his office. The JRA representative testified that his review of JRA's FAX transmission records indicated that the FAXed Addendum #2 was received by all bidders. The greater weight of the evidence establishes that Addendum #2 was transmitted to and received by, all bidders. Upon leaving the bid opening, Mr. Harris immediately contacted his plumbing subcontractor, Jerry Stratyon, and discussed the situation. Approximately two hours after the bid opening, and after talking with Mr. Stratton, Mr. Harris notified JRA, in a letter transmitted by FAX machine to JRA, that his bid price did include plumbing fixtures required by Addendum #2. Mr. Harris concluded the letter, "[w]hen can we start work. I know you don't want the alternate." On October 8, 1990, JRA recommended to the Department, that the Custom bid be accepted. The letter of recommendation, in part, provides: The apparent low bidder however, did not verify receipt of Addendum No. 2 on the Bid Proposal. Our office did receive a, facsimile after the bid verifying Addendum NO. 2 receipt from the Contractor's Office." However, the actual letter from Custom to JRA states, not that Addendum #2 was received, but that it was included in the price bid by Custom's plumbing subcontractor. Both Nixon and Custom obtained plumbing bids from the same subcontractor, Jerry Stratton. The cost increase attendant to the requirements of Addendum #2 is approximately $2,400 over the plumbing fixtures indicated in the written project specifications. Mr. Stratton was aware of Addendum #2 and testified that the requirements of Addendum #2 were reflected in his price quotes to both bidders. Mr. Stratton provided the same price bid to Nixon and Custom. Mr. Stratton also provided bids to Nixon and Custom for HVAC work. Mr. Stratton was accepted as Custom's HVAC subcontractor. Nixon's bid indicates that another HVAC subcontractor will perform the cork should Nixon receive the contract. The ITB provided that bid modification or withdrawal was permitted on written or telegraphic request received from a bidder prior to the time fixed for opening. Mr. Harris did not attempt to either withdraw or modify Custom's bid prior to bid opening. No bid modification was permitted subsequent to the bid opening. The Department's policy is to waive minor irregularities when to do so would be in the best interests of the State and would not be unfair to other bidders. The evidence does not establish that Custom Construction's failure to acknowledge the addendum was purposefully designed to permit withdrawal of their bid subsequent to the public bid opening. The omission of acknowledgment of Addendum #2 provided Custom an opportunity to withdraw the bid that was not available to other bidders. Custom could have informed the Department that the bid price did not include the requirements of Addendum #2, and the bid could have been withdrawn. Custom was therefore provided with a substantial advantage or benefit not enjoyed by the other bidders. The other bidders, all of whom acknowledged receipt of Addendum #2, had no opportunity to, and would not have been permitted to, withdraw their aids. The fact that Custom did not withdraw the bid is irrelevant.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Corrections enter a Final Order rejecting the bid submitted by Intervenor as nonresponsive and awarding the contract to the Petitioner. DONE and RECOMMENDED this 15th day of January, 1991, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of January, 1991.

Florida Laws (4) 120.53120.57120.68255.29
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer