Findings Of Fact Petitioner, in conjunction with the Construction Industry Licensing Board, is the state agency charged with the responsibility to prosecute administrative complaints pursuant to Chapters 120, 455 and 489, Florida Statutes and rules and regulations promulgated thereunder. During times material, Respondent, Donald F. Colombo, was licensed as a certified pool contractor in Florida, having been issued license number CP 15343. During times material, Respondent's license was registered with Petitioner as the qualifying agent for National and Spa Builders, Inc. (National). On or about May 27, 1988, National, the entity which Respondent was the qualifying agent, contracted with Diane and Leonard Cline to construct a pool at the Cline's residence in Tarpon Springs, Florida, for the contract price of $9825.00. The Clines financed the construction of the pool by placing a security interest against their property for the full purchase price of the pool. The full contract price of $9825.00 was paid to National and after National completed approximately 40% of the pool construction, National abandoned the project without notice or just cause. National never completed construction of the pool and the Clines obtained a homeowner's building permit and completed the pool project at an additional cost of approximately $5,000.00. Additionally, liens were filed against the property of the Clines by Florida Mining and Materials Concrete Corporation in the amount of $682.00 and Jim's Custom Pool Work in the amount of $135.00. The above-referred liens were for work performed and/or materials supplied in the construction of the Cline pool project by National. On or about May 20, 1988, National entered into a contract with Ben and Linda Thomas to construct a pool at their residence in Lutz, Florida, for the contract price of $9000.00. Following commencement of construction, National received approximately 60% of the contract price ($5,400.00) and later abandoned the project without notification or just cause to the Thomas's. The Thomas's subsequently completed their pool at an additional cost of approximately $1,000.00 over and above National's original contract price. On or about January 11, 1989, Respondent was disciplined by the Hillsborough County Building Department, Building Board of Adjustments, Appeals and Examiners for alleged violation of local laws including abandoning a construction project; alleged willful and deliberate disregard of applicable building codes; allegedly allowing liens to be filed against a project for which he was the contractor and for allegedly diverting funds from a construction project. Respondent was assessed an administrative penalty of a 30-day suspension of his permitting privileges by the Hillsborough County Building Department. Respondent was the qualifying agent for National during the 90-day period commencing April 1 through June 30,1988. Respondent formally terminated his status as qualifying agent for National and also tendered his resignation from that entity based on difficulties that he ecountered respecting his attempts to serve as qualifier to include his inability to control the finances, to be kept apprised of accounts receivable, accounts payable, an inability to select contractors and material suppliers and to assure that the payments for such services were timely remitted. Prior to Respondent's engagement with National as a pool salesman and later as qualifier, National was a well reputed pool company, having been in existence in excess of twelve years. National annually constructed approximately 750 pools with accounts receivable in the $10 to $12 million dollar range. Prior to April 1988, National was a secure and stable company that regularly paid its bills and grew at a rapid pace. While engaged with National, Respondent was unaware that there was internal collusion among its owners respecting diversion of funds. Respondent repeatedly attempted to gather a handle on the internal financial operations of the company and on each occasion he was rebuffed. within the first month that Respondent qualified National, he began to seek advice as to the proper means of salvaging his license by contacting a local attorney, the local office of Petitioner, and Petitioner's headquarters in Tallahassee seeking the proper procedures for ending his relationship with National. This came about once it became apparent that he was unable to effectively manage or otherwise perform the functions of a qualifying agent. Respondent formally severed his relationship as qualifying agent for National on June 30, 1988. Subsequent to ending his status as qualifying agent for National, Respondent assisted the Clines in the completion of their pool. Mr. Cline specifically recalled that Respondent assisted him in locating other subcontractors and with the purchase of plumbing supplies for his pool without remuneration from the Clines. (Petitioner's Exhibit 1F; Tr. 30-32.) Likewise, Respondent also assisted the Thomas's in completing their pool. (Tr. 45, lines 23-24.) Respondent demonstrated compassion and a proper concern which was evident based on the testimony of the complaining witnesses who appeared at the formal hearing. Significantly, Petitioner's investigator, H. Dennis Force, related that Respondent assisted him in his investigation of the subject charges. To this end, Respondent supplied him with the names of all customers with which National had contracts with during the period that he was National's qualifying agent. It is unfortunate that Respondent was not able to control the fiscal policies of National during the period that he was the qualifying agent, although from a review of the evidence herein, it is apparent that this was not based on his failure to attempt to gain control over the situation as a qualifying agent, but was rather based on the collusion of National's higher-ups who was determined to keep Respondent in the dark. Noteworthy was the fact that within a three-month period, National changed banks at least eight times. It would have been, at best, difficult if not impossible for Respondent to have gained a handle on National's financial condition and to do the things with which a qualifying agent is charged with during the short period during which Respondent was National's qualifying agent.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Petitioner enter a Final Order imposing an administrative fine against Respondent in the amount of $1,000.00 and placing his certified pool contractor's license on probation for a period of six (6) months. 1/ DONE and ENTERED this 7th day of March, 1991, in Tallahassee, Leon County, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of March, 1991.
The Issue Whether the claimants herein are entitled to payment from the Construction Industries Recovery Fund and, if so, the amount of the payment to which each claimant is entitled. Whether the license of the Petitioner is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998).
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Fund is established by Section 489.140, Florida Statutes, for the purpose of reimbursing those persons who meet the eligibility requirements set forth in Section 489.141, Florida Statutes. The Board is the entity responsible for reviewing applications for payment from the Fund and entering orders approving or disapproving the applications. Sections 489.140(1) and 489.143(1), Florida Statutes. Mr. Kiselius is a licensed residential pool/spa contractor, having been first issued such a license in 1984. Mr. Kiselius's license is currently on inactive status, but at the times material to this action, Mr. Kiselius's license was active. Pool Masters was a Florida corporation incorporated on August 10, 1995. Frederick H. Martin and Abraham Zafrani were the sole shareholders of the corporation, and Mr. Martin was the President and Secretary of the corporation, and Mr. Zafrani was the Vice-President and Treasurer. From on or about October 24, 1995, until November 14, 1997, Mr. Kiselius was the qualifying agent for Pool Masters. The record does not reflect the date on which Pool Masters was issued its certificate of authority allowing it to engage in contracting as a business organization, but it was assigned Qualified Business Organization License Number QB0002327 on or about November 6, 1996. Pool Masters filed for bankruptcy pursuant to Chapter 7 of the United States Bankruptcy Code on January 1, 1998, and the corporation was administratively dissolved on October 16, 1998. DOAH Case No. 99-1665: Santibanez and Pappas Eugene Santibanez and Alexander Pappas entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 25, 1997. The total price stated in the contract was $21,000.00; a change order was executed on November 4, 1997, for an additional price of $2,890.00. Pool Masters represented to Mr. Santibanez and Mr. Pappas that it was a licensed swimming pool contractor. Pool Masters began work on the pool on or about May 17, 1997. Mr. Santibanez and Mr. Pappas made payments to Pool Masters pursuant to the contract, and Pool Masters excavated the hole for the pool, put in the foundation, and poured the concrete. Pool Masters ceased work on the swimming pool in late November 1997, after the concrete was poured. A week later, Mr. Santibanez heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. Santibanez and Mr. Pappas had paid Pool Masters a total of $19,690.00 for work done pursuant to the contract and change order. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. At least one lien was filed against Mr. Santibanez's and Mr. Pappas's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Santibanez and Mr. Pappas submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Santibanez and Mr. Pappas to file suit against Pool Masters. Mr. Santibanez and Mr. Pappas filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Santibanez and Mr. Pappas alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 3/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 4/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 5/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 6/ ] Mr. Santibanez and Mr. Pappas further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $17,975.50, and they included in the complaint an itemized list of expenditures to support their claim. The circuit court entered a Default Final Judgment on August 4, 1998, awarding Mr. Santibanez and Mr. Pappas $17,675.50, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Santibanez and Mr. Pappas submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Santibanez and Mr. Pappas did not receive any funds from the bankruptcy estate or any other source to satisfy the judgment against Pool Masters. Mr. Santibanez and Mr. Pappas satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $17,675.50. DOAH Case No. 99-1666: Klaus and Lucrecia Mueller Klaus and Lucrecia Mueller entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about February 24, 1997. The total price stated in the contract was $16,400.00. Pool Masters represented to Mr. and Mrs. Mueller that it was a licensed swimming pool contractor. Pool Masters began work on the pool in Spring 1997, and Mr. and Mrs. Mueller made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool, installed the steel frame, poured gunnite at the shallow end of the pool, and installed the brick and tile around the pool. Pool Masters last worked on the swimming pool in late November 1997. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Mueller had paid Pool Masters approximately $12,900.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Mueller's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Mueller submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Mueller to file suit against Pool Masters. Mr. and Mrs. Mueller filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Mueller alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 7/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 8/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 9/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 10/ ] Mr. and Mrs. Mueller further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,299.51. The matter was presented to the circuit court, ex parte, upon Mr. and Mrs. Mueller's Motion for Default Final Judgment. The court entered a Default Final Judgment in June 1998, awarding Mr. and Mrs. Mueller $13,299.51, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated June 23, 1998, Mr. and Mrs. Mueller submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Mueller did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Mueller satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $13,299.51. DOAH Case No. 99-1667: Mario and Martha Alboniga Mario and Martha Alboniga entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 17, 1997. The total price stated in the contract was $24,000.00. Pool Masters represented to Mr. and Mrs. Alboniga that it was a licensed swimming pool contractor. Pool Masters began work on the pool on November 10, 1997, and Mr. and Mrs. Alboniga made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and poured the concrete form of the pool. The last day Pool Masters worked on the swimming pool was November 19, 1997. Mr. and Mrs. Alboniga later heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Alboniga had paid Pool Masters a total of $15,200.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Alboniga’s property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Alboniga submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Alboniga to file suit against Pool Masters. Mr. and Mrs. Alboniga filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Alboniga alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 11/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 12/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 13/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 14/ ] Mr. and Mrs. Alboniga further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $10,541.77. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. and Mrs. Alboniga $10,541.77, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. and Mrs. Alboniga submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Alboniga did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Alboniga satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $10,541.77. DOAH Case No. 99-1668: Salvator Militello and Sharon Sidorski Salvator Militello and Sharon Sidorski entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about April 6, 1997. The total price stated in the contract was $24,295.00. Pool Masters represented to Mr. Militello and Ms. Sidorski that it was a licensed swimming pool contractor. Mr. Militello and Ms. Sidorski made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and spa, installed basic plumbing, and poured the concrete for the pool. Pool Masters last worked on the swimming pool in October 1997. At the time Pool Masters ceased work on the pool, Mr. Militello and Ms. Sidorski had paid Pool Masters $19,389.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. Militello's and Ms. Sidorski's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Militello and Ms. Sidorski submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Militello and Ms. Sidorski to file suit against Pool Masters. Mr. Militello and Ms. Sidorski filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Militello and Ms. Sidorski alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 15/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 16/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 17/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 18/ ] Mr. Militello and Ms. Sidorski further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,544.00 and that they paid $1,641.68 to satisfy liens and unpaid subcontractors and materialmen, for total damages of $15,185.68. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. Militello and Ms. Sidorski $15,185.68, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Militello and Ms. Sidorski submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Militello and Ms. Sidorski did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. Militello and Ms. Sidorski satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $15,185.68. DOAH Case No. 00-0024: Jack and Paula Tieger Jack and Paula Tieger entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about December 17, 1995. The total price stated in the contract was $28,200.00. Pursuant to the contract, Pool Masters built a pool and screen enclosure, and Mr. and Mrs. Tieger paid Pool Masters the price specified in the contract. Mr. and Mrs. Tieger were not, however, satisfied with the work done by Pool Masters, and, in or around 1997, they filed a complaint for breach of contract against Pool Masters in the Circuit Court of the Seventeenth Judicial Circuit, in Broward County, Florida. In the complaint, Mr. and Mrs. Tieger alleged that Pool Masters had breached the contract: By failing to adequately explain the technical terms used in the Agreement to the TIEGERS; By failing to install a vacuum line with valve as specified in the Agreement; By failing to install anti-corrosive handrails in the swimming pool; By failing to properly install and/or provide a properly functioning waterfall as specified in the Agreement; By failing to properly fill the area behind the waterfall; By unilaterally, and or the TIEGERS' [sic] objection, placing a tile with the "Pool Masters" logo on the steps heading into the pool: By failing to re-route the TIEGERS' [sic] sprinkler system in a timely manner; By failing to advise the TIEGERS that they were going to need to pay for and install a separate circuit breaker box as part of the installation of the swimming pool; and By failing to install the second screen door as specified in the Agreement. Mr. and Mrs. Tieger did not identify the amount of damages they allegedly suffered as a result of Pool Masters's alleged breach of contract. Mr. and Mrs. Tieger were not aware that Pool Masters had declared bankruptcy until January 1998, when Mrs. Tieger went to Pool Masters' office and found the notice on the door. A non-jury trial was held before the circuit court on March 5, 1998; Pool Masters did not attend the trial. In a Final Judgment entered on March 25, 1998, the court awarded Mr. and Mrs. Tieger $4,200 as compensatory damages to be recovered from Pool Masters. In a Proof of Claim dated May 13, 1998, and filed with the United States Bankruptcy Court of the Southern District of Florida, Mr. and Mrs. Tieger submitted an unsecured claim against Pool Masters' bankruptcy estate in the amount of $7,300.00, which represented the compensatory damages awarded in the final judgment, together with attorney's fees and costs. Mr. and Mrs. Tieger have not collected any portion of their judgment against Pool Masters. Mr. and Mrs. Tieger submitted to the Board a Construction Industries Recovery Fund Claim Form dated December 5, 1998, and the Board awarded Mr. and Mrs. Tieger $800.00, representing the cost of the vacuum line with valve and the second screen door which Pool Masters had not installed. Mr. and Mrs. Tieger do not satisfy the statutory criteria for eligibility for payment from the Fund. Mr. and Mrs. Tieger failed to establish that they filed their claim with the Board within two years of the date they discovered the alleged deficiencies in the pool, and they failed to establish that the final judgment against Pool Masters was based on a violation of Section 489.129(1)(g), (j), or (k), Florida Statutes (Supp. 1998). The evidence presented herein is not sufficient to establish that Mr. Kiselius is the licensee against whom the claimants obtained final judgments.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, 25/ it is RECOMMENDED that the Construction Industry Licensing Board: Enter final orders as follows: In DOAH Case No. 99-1665, finding Eugene Santibanez and Alexander Pappas eligible for payment from the Fund in the amount of $17,675.00, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1666, finding Klaus and Lucrecia Mueller eligible for payment from the Fund in the amount of $13,299.51, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1667, finding Mario and Martha Alboniga eligible for payment from the Fund in the amount of $10,541.77, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1668, finding Salvator Militello and Sharon Sidorski eligible for payment from the Fund in the amount of $15,185.68, in satisfaction of a final judgment against Pool Masters, Inc.; and In DOAH Case No. 00-0024, dismissing the claim of Jack and Linda Tieger for payment from the Fund. Determine that Christopher P. Kiselius is not the "licensee" whose license is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998), as a result of payments to the claimants in DOAH Case Nos. 99- 1665, 99-1666, 99-1667, and 99-1668. DONE AND ENTERED this 31st day of August, 2000, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 2000.
Findings Of Fact Respondent is a certified pool contractor, holding license number CP CO27486. Respondent obtained his certificate in October, 1983. His only prior discipline consists of a letter of guidance in late 1989 or early 1990. At all material times, Respondent was qualifying agent for Gold Medallion Pcol, Inc. On March 27, 1986, Respondent and Mr. and Mrs. Don Burson entered into a contract for the construction cf a swimming pool at the Bursons' residence. The Bursons had purchased the residence while it was still under construction in May or June, 1985. The lot was low and had required fill. Clearly visible behind the lot is a large marshy wetland. The contract called for the Bursons to pay $16,315 for the construction of a 20' by 40' concrete lap pool with depths of 3' at either end and 6' in the center. Paragraph 4 of the contract provides: The Owner is responsible for increased costs incurred by the Contractor due to underground conditions which may be encountered during construction, such as but not limited to, muck, inadequate soil-bearing capacity, and excessive ground water. The Contractor, upon encountering such conditions, shall notify the Owner of their existence and give him an approximate cost estimate to rectify the problem. The Owner shall have five (5) days from the receipt of the approximate cost estimate to instruct the Contractor not to proceed with the pool. . . . If the Contractor determines that additional testing is required prior to furnishing approximate costs estimates to determine the exact nature or extent of the underground condition encountered, the Owner shall be responsible for the cost of all testing and/or engineering required by the Contractor. Paragraph 8.D states that the Owner warrants that there [is] no . . . mock . . . in that portion of the owner's property which the contractor will construct the pool [and] decking . . .. The owner is responsible for the removal, repair or replacement of any underground conditions . . . encountered during construction unless he elects to terminate the contract and pay damages to the contractor as set forth in the clause on underground conditions. Paragraph 11.A provides: Contractor warrants to the original owner for the lifetime of the original purchaser, the swimming pool structure, the shell, will not leak due to cracking. . . . This Limited Structural Warranty does not cover damage to the pool shell caused by fluctuations of the water table, construction in the vicinity of the pool site, or natural phenomenon. . . . The contractor's responsibility under this Limited Structural Warranty shall be to repair the shell so that it holds water without cost to the original owner. . . . The method of repair shall be at the discretion of the contractor. THE CONTRACTOR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES INCLUDING THE WARRANTY OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE IN REGARDS TO THE POOL STRUCTURE, THE SHELL. Paragraph 11.B.2, which further describes the limited warranty, states: It is anticipated the concrete deck and deck coatings may crack due to settling of deck or weather. Cracks one-quarter inch or less with no substantial deviation in elevation are not covered. . . . The plot plan, which is part of the contract, shows the pool located on the east side of the house. The pool is oriented in a north-south direction. The southern end of the pool runs toward the back of the lot, which is on a steep slope. The southern end of the pool adjoins the widest section of decking, which Respondent constructed at the time of the construction of the pool. The plot plan also shows that excavated dirt was to be placed just south of the decking on the south end of the pool. Shortly after pulling a building permit from the Seminole County Building Department on March 27, 1986, Respondent began construction of the pool. The actual construction was performed by Mid-Florida Pool Company, which is a major pool construction company in Central Florida. Construction was completed on April 23, 1986, and the Bursons paid the amount required under the contract. Prior to commencement of construction of the pool, this area of the Bursons' lot had been filled with about 2 1/2 to 3 feet of dirt. In order to construct the pool, Respondent or his subcontractors added another 2 1/2 to 3 feet of fill, at least to the southern end of site of the pool and decking. It is at this point that the land begins to slope most steeply toward the marsh in the back. Neither Respondent nor any of his subcontractors conducted any soil tests prior to commencing construction or compressed or compacted the soil beneath the pool prior to installing the shell. This omission constitutes a departure from sound contracting practices under the facts cf this case. Respondent constructed several pilasters under the southern end of the deck, but these structural supports were designed to support the deck, not the pool. In general, the depth of the excavation had to exceed the depth of the pool by one foot in order to accommodate the shell. Thus, the extreme southern end of the shell required a hole only about four feet deep. An excavation of this depth did not exceed the combined depth of the old and new fill. There is no indication that Respondent or his subcontractors encountered muck during the excavation or construction of the pool. Likewise, there is no indication that Respondent or any of subcontractors was aware that mucky, unstable soils underlaid the location of the pool, especially the southern end. The pool was completed to the initial satisfaction of the Bursons. However, within 90 days of completion, the southern half of the shell developed five or six major cracks as a result of the settlement of the southern end of the pool. This portion of the pool settled because the underlying muck had been compressed by the weight of the shell and water. Gradually, the water loss from the settlement cracks, which were mostly below the waterline, became significant. At Respondent's suggestion, the Bursons agreed to wait through the winter before commencing repairs in order to allow the cracking to stabilize. In the spring of 1987, the Bursons drained the pool at Respondent's direction. Respondent then scored the cracks with a screwdriver and applied a filling compound in order to seal any leaks. As directed by Respondent, the Bursons then refilled the pool, but before more than two feet of water had been added, the filling compound fell out of the cracks. When the Bursons informed Respondent of the failure of the repair, he responded that he had performed under the contract and had no further obligation. The Bursons exercised their right to arbitrate, as provided in the contract. The arbitrators conducted a limited investigation. Expressly noting that they were not soil engineers and thus could not determine why the soil under the pool failed to support the shell, the arbitrators determined that the contractor was not responsible for any damage to the pool, "which was built to industry standards." The Bursons next contacted various pool contractors about repair options. Most of the contractors suggested a V-cut about 2 1/2 inches deep followed by the injection of hydraulic cement. When the Bursbns informed Respondent that this type of repair appeared necessary, he refused to undertake such work. By this time, one of the contractors documented that five of the cracks, which ranged from 1/16" to 1/4" wide, were pulling water out of the pool at a rate of 1-3" daily. This contractor charged the Bursons $125 for his services. After contacting the Seminole County Building Department, the Bursons learned that the pool had never passed a final inspection. When they had an inspector visit the site on September 13, 1991, he failed the job due to, among ether things, "massive deck cracks." At the insistence of Seminole County officials, the Bursons obtained expert opinions as to the cause of the cracks in preparation for the local hearing on the Bursons' charges against Respondent. In July, 1990, the American Testing Laboratories, Inc. conducted tests and opined that the south end of the pool had settled due to muck at a level of five feet below the bottom of the shell. Additional testing found muck at depths of 3-7 feet at two points just east of the south end of the pool. These tests cost the Bursons $498. When the Seminole County officials insisted upon further testing, the Bursons hired Jammal & Associates, Inc., which performed soil borings on August 23, 1990. The boring sites were just east of a point about midway along the southern half of the pool and a point just south of the southern end of the pool. The latter boring site revealed muck after penetrating about six feet of fill. At the request of Respondent, a Jammal employee returned to the site on November 13, 1990, to determine the potential cause of the cracking of the pool shell and deck. Jammal concluded that the cracking is the result of consolidation of the highly compressible peat layer found in the [southern] boring. Based upon the [cracking] observed, we suspect the southern 1/3 or so of the pool and deck area are underlain by the buried peat layer. The remainder of the pool and deck are most likely underlain by sandy soils. Because of the nature of the buried organic soils, the pool and deck will probably continue to settle at a diminishing rate for several years. Addition of new loads such as placement of additional fill around the pool and deck area, or a significant drop in the groundwater table could cause additional and accelerated settlement of the pool and deck. Jammal offered three repair options. The first was to patch the cracks. Jammal assumed that, although continued cracking could be expected, it would occur at a lesser rate because most of the settlement of the buried muck had already taken place. The second option was to remove the pool and then remove the underlying muck. The third option was to install inside the shell a fiberglass liner. The last option had been first suggested by Respondent. If not rigidly attached to the shell, the liner probably would not reflect further cracking of the shell. The Bursons paid Jammal the sum of $300 for its services. Ultimately, the Bursons decided to install a fiberglass liner and entered into a contract on November 19, 1990, with Fibre Tech for the work. The total cost of the project was $5415. This cost excludes the cost of replacing a pool vacuum for which Respondent does not appear responsible. The liner was later installed, and the Bursons paid the contract price. In the meantime, at a meeting on October 16, 1990, the Seminole County Swimming Pool Contractor's Board revoked Respondent's County certificate of competency until he repaired the pool or made restitution to the owners. This action was based upon a violation of Seminole County Code Section 40.151 and 40.34(2) and (9). Section 40.151 provides that "[a]11 completed pools shall be absolutely watertight." Section 40.34(a) allows the Board to revoke a certificate of competency if the contractor: (2) Continue[s] performance of building work in a negligent, incompetent or unworkmanlike manner. (9) Violate[s] any provision of this Chapter. The determination of the Seminole County Swimming Pool Board became final when Respondent failed to take a timely appeal of the order.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order imposing an administrative fine of $2500 and suspending Respondent's license until he makes restitution to the Bursons in the amount of $6338. ENTERED this 29th day of October, 1991, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of October, 1991. COPIES FURNISHED: Jack McCray, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Craig M. Dickinson, Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Merwin C. Carter, pro se 611 Ensenada Avenue Orlando, FL 32825
Findings Of Fact At all times material hereto Respondent, George W. Boukater, was a certified general contractor, license number CG C012598, and a registered pool contractor, license number RP 0032042. Respondent was the qualifier for Swimming Pools by M.J. Donohue, Inc. (Donohue), under license number RP 0032042, from February 1979 until June 30, 1985. On July 29, 1984 Donohue contracted to construct a swimming pool at the residence of Ms. Loretta Hunley in Fort Lauderdale, Florida, for the sum of $6,400.00. Respondent, on behalf of Donohue, applied for and received the building and plumbing permits for the pool. Apart from securing the permits, Respondent had no contact with the job and never inspected its progress. By August 30, 1984, Donohue had substantially completed the pool. All that remained to be done was to marcite the pool, hook up the pool light and plumbing, and install the pumps. However, before these items could be completed it was necessary that the area surrounding the pool be backfilled, the patio poured, and the electric installed. Under the July 29, 1984 contract Ms. Hunley did not contract with Donohue for any patio, electric or fence work. She expressly retained responsibility for that work in an effort to save money on the pool construction. The area surrounding the pool was not backfilled and the patio slab approved by the Broward County Building and Zoning Department (County) until September 14, 1984. As of September 5, 1985, the fence work was still in violation of the County code. The electric work received the County's final approval on January 8, 1986. In October 1984 demands were exchanged between Ms. Hunley and Donohue. Ms. Hunley demanded that the pool be completed. Donohue demanded adequate electrical service so the pool could be pumped and cleaned for marciting, and dates when someone would be available at the premises. In November 1984 Donohue got its pumps in operation, however Ms. Hunley disconnected them in the evenings. Consequently, the pool could not be drained and cleaned to marcite it. In November 1984 Ms. Hunley ejected Donohue from the job site. Subsequently, Ms. Hunley and Donohue formally settled their dispute.
The Issue This case concerns the issue of whether the Respondent's license as a certified general contractor should be suspended, revoked, or otherwise disciplined for multiple violations of Chapter 489 of the Florida Statutes. Specifically, the Respondent is charged with having been found guilty of a crime which relates directly to the practice of contracting in violation of 489.129(1)(b)(1979); willfully or deliberately disregarding and violating the applicable building code in violation of Florida Statute 489.129(1)(d)(1979); aiding and abetting an unlicensed person in his evasion of the Contracting Practice Act in violation of 489.129 (1)(e)(1979); knowingly combining or conspiring with an unlicensed person by allowing Respondent's license to be used by said unlicensed person with the intent to evade the provisions of the Contracting Practice Act in violation of Florida Statute 489.129 (1)(f)(1979); and, violating Florida Statute 489.129(1)(j)(1979) by failing to renew his license every two years and by failing to supervise a construction project. At the formal hearing, the Petitioner called as witnesses the Respondent, Frederick G. Gervia, Leroy S. Duncan, John Knezevich, and Evodio Llevado. Respondent testified on his own behalf and also called as a witness Mr. L. Perry Curtis. Petitioner offered and had admitted without objection eight exhibits. The Respondent offered no exhibits into evidence.
Findings Of Fact The Respondent is a certified general contractor holding License No. CG C003114. Respondent is also a registered general contractor having been issued License No. RG 0009802. Respondent's license CGC003114 was delinquent as of December 7, 1981, and had not been renewed for the 1981-83 licensing period. On October 11, 1981, Fiberglass Pools of South Florida, Inc. entered into a contract with Mr. Leroy Duncan to construct a fiberglass pool at Mr. Duncan's residence located at 1385 N.W. 192nd Terrace, Miami, Florida. On November 10, 1981, Respondent applied for a building permit (see Petitioner's Exhibit 2) for the pool construction at Mr. Duncan's home. The Respondent signed the application in the block designated "Signature of Qualifier or Owner-Builder". The application named Gervia Construction Company, address 2810 S.W. 78th Court as the building contractor. Gervia Construction Company was neither the general contractor nor a subcontractor in connection with the construction of the Duncan pool. At the time that he applied for the building permit, Respondent was qualifying agent for Gervia Construction Company, 2810 S.W. 78th Court, Miami, Florida 33155. The Respondent has made no request to qualify under either of his licenses as the qualifying agent for Fiberglass Pools of South Florida, Inc. Neither Fiberglass Pools of South Florida, Inc. or its principals were licensed. Prior to and during construction, Mr. Leroy Duncan had no dealings at all with the Respondent or Gervia Construction Company. Mr. Duncan's dealings were primarily with Douglas Lake of Fiberglass Pools of South Florida, Inc. Mr. Duncan observed a substantial portion of the construction, but was not present during the form work for the deck. At no time did Mr. Duncan observe the Respondent working on the construction of the pool at his home. The only work performed by Mr. Gervia on the Duncan pool contract was to check the plumbing prior to the county inspection. The pool was actually installed by two principals of Fiberglass Pools of South Florida, Inc. and two helpers. These persons were neither supervised nor controlled by the Respondent during construction. During the time period October 11, 1980, through initial construction of the Duncan pool, the Respondent was employed by Fiberglass Pools of South Florida, Inc. at a salary of $350 per week. One of his duties was to pull permits. Although the Respondent was also hired to supervise all field construction, at the time the Duncan pool was contracted for and constructed, his supervisory status had been eliminated. The Respondent performed no supervisory duties in connection with the Duncan pool construction. All payments from Mr. Duncan, including two checks totaling $950 and a cash payment of $6,230 were made to Fiberglass Pools of South Florida, Inc. No payments were made to the Respondent or Gervia Construction Company. Mr. Gervia did not hire or fire any of the persons who worked on the Duncan pool and kept no records relating to payments received or monies spent on the job at the Duncan residence. Subsequent to the pool being completed, substantial problems and flaws in the Duncan pool developed. The following problems were present in the pool: (See Petitioner's Exhibit 5.) Seven patches on South wall, below water line, are rough, discolored and flaking. The largest two are approximately 12" in diameter and 12" x 4". There is a very small depression in the shallow end seat. The pool flange at the ladder is full of depres- sions, making the edge very rough. Flange cracks at three corners are excessive and need repair. The Southwest corner has a vertical crack down the wall about 1'. See exhibits II, III, IV, and V. The pool wall thickness at corners was 3/8" but north, south and west wall were 7/32" to 1/4" thick. Several dark circles about 2" in diameter are located around perimeter flange and show where holes were drilled and patched poorly. . . Four hydrostatic valves seem high to effectively counteract buoyancy, but approved plan approves 1' above floor at deep end plus one valve in main drain [could not check with pool full]. See notes 9, 10 & 11 - William Meyers plan. 13' x 30' x 72" pool actually measures 12'-11" x 29'-8" x 71 1/8" deep. Vertical floor variations in shallow end are about 1 3/4". Seems depressions occur between ribs. A small bow occurs at Northwest corner near surface of water. Area covers about 18" square. Some concrete voids occur beneath pool lip. Pursuant to an agreement with Mr. Duncan, the Respondent and Fiberglass Pools of South Florida, Inc. have repaired those items listed in paragraph 9 in an excellent manner and to the full satisfaction of the owner, Leroy Duncan. On November 17, 1982, the Respondent was convicted in the County Court of Dade County, Florida, of unlawfully aiding and abetting an unlicensed contractor in violation of Section 10-22(h) of the Metropolitan Dade County Code. Adjudication of guilt was withheld and Respondent was required to pay a $500 fine. The Respondent has been a licensed certified general contractor in the State of Florida since November, 1971, and has had no other charges or actions against his license. There have also been no other complaints filed with the Petitioner regarding the Respondent.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Respondent be found guilty of those specific violations as set forth in the Conclusions of Law above and that his license as a certified general contractor be suspended for a period of six months and that the Respondent be required to pay an administrative fine of $250.00. DONE and ENTERED this 20th day of July, 1983, in Tallahassee, Florida. MARVIN E. CHAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of July, 1983. COPIES FURNISHED: Harold M. Braxton, Esquire 45 Southwest 36th Court Miami, Florida 33135 Frederick G. Gervia 2810 Southwest 78th Court Miami, Florida 33155 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202
Findings Of Fact Brian E. Michaels, the Codes Administrator for Putnam County testified that he regulates the building codes in Putnam County and is in charge with the effective administration thereof. He testified that the pertinent regulations and codes relative to the construction of swimming pools in Putnam County are Ordinances 73-6 and 75-4. (See Petitioner's Exhibits number 2, and number 3, received in evidence). Michaels testified that after seeing an advertisement in the Palatka Daily News on august 6, 1975, his office advised Respondent's office on two occasions to apprise him of certain local laws regulating contractors and the business of contracting. When Respondent failed to respond to approximately three phone calls to its office, Michaels advised Respondent by certified letter dated August 28, 1975, that swimming pool contractors desiring to operate in Putnam County must be locally certified even if they hold state registration. He advised Respondent that if he in fact was state certified that he could send a copy of his certificate for Putnam County official files and to discuss with their office procedures for obtaining a certification in Putnam County. He further advised that the county had adopted the standard swimming pool code, 1974 edition, which requires a plot plan as well as a plan approved before a pool permit could be issued. (See Petitioner's Composite Exhibit number 5). Michaels explained the procedures for complying with the County's certification process which included the filing of an application; taking an exam and receiving a score of at least 70 percent; posting of a $5,000.00 bond; payment of a $50.00 fee which should be included with the application which should also have included a recent photo and the issuance of an occupational license. Additionally, he advised that it was necessary to comply with registration and requirements of the Florida Construction Industry Licensing Board under Chapter 468; Florida Statutes, within 90 days. Michaels testified that Respondent received his certified letter dated August 28, 1975, the following day. (See Petitioner's Composite Exhibit number 5). Section 1020 of Ordinance No. 75-6 of the zone ordinances of Putnam County states in pertinent part that building and related permits issued by the chief building official are required in advance of the construction, erection, demolition, moving, destruction, or alteration of any building or structure with a completed evaluation of $1,000.00. (See Petitioner's Exhibit number 6). On May 27, 1975, the Putnam County Board of County Commissioners enacted Putnam County Ordinance no. 75-4, which ordinance adopted by reference the Southern Standard Swimming Pool Code, 1974 edition, which provided for the adoption of a fee schedule and charges for the issuance of permits to "defray the costs of inspections". (See Petitioner's Exhibit number 7). Jerrell Sparks of Crescent City, testified that he contacted Respondent regarding the construction of a swimming pool during the fall of 1975 following his visit to a building show. On October 21, 1975, Sparks entered into a contract with Terry Michaels, a partner of Respondent, Steve Klapach, d/b/a Starfish Pools for a total price of $5,150.00. At the execution of the contract, Sparks paid Respondent $200.00 and agreed to pay an additional $1,300.00 on November 5, 1975. (See Petitioner's Exhibit number 8, received and made a part herein). Sparks testified that Respondent made the financial arrangements with a mortgage broker in Jacksonville and that Respondent was paid $4,650.00. The construction completed by Respondent consisted of the excavation for the pool and delivery of the pool shell. He testified that he obtained a homeowner's permit but that Respondent did not obtain a permit for the installation of the swimming pool. Tom McConnell of Palatka, testified that he contacted the Respondent regarding a $2,000.00 pool kit which he had seen advertised. He testified that Respondent's partner, Tony Michaels, visited his home on October 14, 1975, at which time he executed a contract for the installation of a pool for a total price of $5,714.00. When the contract was executed, McConnell secured it by an advance payment of $500.00 and he thereafter was never able to contact Respondent. (See Petitioner's Exhibit number 9, received in evidence and made a part hereof). Kenneth L. Rue of Ormond Beach contacted the Respondent based on an ad which appeared in the Sunday supplement of the Daytona Beach News Paper. On August 21, 1975, Rue entered into a contract with Respondent's partner, Tony Michaels and a Mr. Charles Van Dent for the construction of a pool for the total price of $5,200.00. He paid Respondent $500.00 when the contract was executed and paid an additional $4,200.00 when the pool was delivered. He testified that Respondent removed shrubbery and palm trees where the pool was to be positioned and thereafter the excavation and the necessary site preparation was readied. Thereafter the pool was positioned and the plumbing and electrical-fixtures were connected. He testified that the pool did not comply with the specifications as called for in the contract which by its term called for a kidney shaped pool with dimensions of 27' X 13' and a depth of a minimum of 3 and a maximum of 5 feet. He testified that the actual dimensions of the pool installed was 25' x 11' and the depth ranged from 26" to 47". He testified that after the pool was installed it began leaking around the "circulation area" and that when he contacted the Respondent, the pool was removed and Respondent agreed to install any size pool that he desired. The pool called for in the contract was a fiberglass pool however Respondent opted for the installation of a vinyl liner pool. On November 11, 1975, Respondent sent two employees out to make forms for the construction of the pool but since that time, he has had no further contact with Respondent despite repeated attempts. He paid Respondent approximately $4,700.00 of the $5,200.00 contract price and paid another contractor an additional $2,300.00 to complete construction of the swimming pool. (See Petitioner's Composite Exhibit number 10) Brian Michaels was recalled and testified that Respondent never was issued building permits for the McConnell or Sparks projects. The Board introduced into evidence documents showing that Respondent, Steve A. Klapach, RP22049 was registered with the Florida Construction Industry Licensing Board as an active swimming pool contractor during 1975 in the period September, 1975 to December, 1975. (See Petitioner's Exhibit number 1).
Findings Of Fact Based on the evidence presented, the following facts were found: At all times pertinent to this case, Respondent held two active contractor's licenses issued by the State of Florida, RP 0033354 and CP 015029. Respondent's current address is 1316 Hoffner Avenue, Orlando, Florida 32809. At all times pertinent to this case, Respondent owned the firm Family Pools and did business as a pool contractor under that name. At no time did Respondent ever qualify his firm, under whose name he did business, with the Florida Construction Industry Licensing Board (CILB). On some date not specified, in June, 1980, Alphonse J. and Pauline L. Rodier contracted with Family Pools to build a pool at their residence at 601 Michigan Avenue, Englewood, Sarasota County, Florida for a price of 6,700. The contract was signed by Respondent for Family Pools. The pool price was to include a screened enclosure and deck, and the entire package was to be completed by July 4, 1980. The pool was paid for by two checks from Coast Federal Sayings and Loan Association in Sarasota from the proceeds of a home improvement loan and by a final check in the amount of $900 from the Rodiers, direct, on October 13, 1980. Respondent subcontracted the pool enclosure to Climatrol Screen Company of Enqlewood, Florida, for $2,065 but failed to pay this subcontractor. As a result, on November 26, 1980, Climatrol filed a lien against Rodier's property which was released only when the Rodiers paid an additional $790 which had not been satisfied by the Respondent. Respondent had satisfied part of the debt to Climatrol by relinquishing title to a truck he owned. On July 3, 1980, Family Pools contracted with Elmer J. and Carla T. Taylor, of Bunnell, Florida, to build an above-ground pool on their property for $4,800.00. The pool was to have a one year warranty against defective parts and a 20-year prorated replacement policy. According to the contract, the pool price included the pump, liner, filter, and walls, along with all other parts. The pool was constructed by employees of Family Pools about three or four weeks after the contract was signed. Not long after the pool was completed and filled, Mr. Taylor noticed that the vinyl liner was protruding out beneath the bottom of the metal retaining wall. His calls to Family Pools were never answered by Respondent with whom he asked to talk and repair work on this problem was not accomplished by the Respondent or Family Pools. Mr. Taylor had to do the work himself and Family Pools would not honor the warranty. Respondent offers the completion certificate executed by the Taylors on August 21, 1980,as evidence the pool was installed properly and the Taylors were satisfied. Mr. Taylor indicates he signed that certificate in blank under pressure from Respondent's agent, who cajoled him into doing it on the basis that if he did not, Family Pools could not be paid by the finance company under the installment sales contract. Also, during the period of the one year warranty, the pool pump burned out. Mr. Taylor had to replace that and pay for it himself, as the warranty was not honored. Respondent contends only a 90-day warranty on the pump, but that appears nowhere in the contract, which, in its description of the pool covered by the one year warranty, includes the pump. On August 29, 1980, Family Pools contracted with Janice Conover to build a swimming pool at her home in Venice, Florida for $4,780. The pool was to be completed approximately 30 days after excavation at the site. Between August 29, 1980, and December, 1980, Ms. Conover paid Family Pools a total of $4,741 by checks which were endorsed by "P. Vescera d/b/a Family Pools" or "Pasquale M. Vescera." On October 2, 1980, Respondent pulled a permit No. 7330- N from the Sarasota County Building Department, in his own name, to construct Ms. Conover's pool. In February, 1981, when the pool was only about fifty percent complete, Respondent ceased work on Ms. Conover's pool without giving her any notice or reason therefor. When Respondent stopped work, he had only dug the hole for the pool. The liner had been delivered but was not installed. The braces were there but not affixed, notwithstanding Ms. Conover had paid almost in full for the pool. As a result, she contracted with Richard Thompson, Respondent's former employee, to finish the work Respondent had started because at this point she could not find the Respondent. Thompson installed the brackets, the liner, and the deck. She had to pay extra for the pump, the chemicals, and the sweep--all of which, except for the sweep, she had paid for when she paid Respondent's price. Respondent never returned to complete Ms. Conover's pool. On July 7, 1980, Family Pools contracted with Robert A. and Florence L. Peipher to build a pool at their property in Port Charlotte, Florida, for a price of $6,900. Between July 7 and November 28, 1980, the Peiphers paid Family Pools, by checks, the sum of $6,905. All checks-were endorsed for deposit, "P. Vescera d/b/a Family Pools." The pool price was to include a screened pool enclosure and in September 1980, Family Pools contracted with Climatrol to build the screened enclosure for Peipher's pool for $1,807. Respondent and Family Pools failed to pay Climatrol for the enclosure and as a result, Climatrol filed a lien against the Peipher's property for $1,807 which was satisfied on March 9, 1981, by the Peiphers who paid Climatrol the amount owed. On March 2, 1981, the Peiphers filed a complaint against Respondent with the Contractor License Division of the Charlotte County Building Department because of Respondent's failure to pay Climatrol and the resultant cost to them. As a result of this complaint and the subsequent investigation into the allegations, the matter was referred to the Charlotte County Building Board which, at its meeting on May 7, 1981, after notice to Respondent, voted to revoke Respondent's permit privileges in Charlotte County until he made restitution to the Peiphers and to notify the State of Respondent's actions requesting state action against his license. Respondent suffered severe financial setbacks just about the time of these incidents. He was hospitalized for a period of five or six weeks and upon his return to his business found that he had been "robbed" of approximately $50,000 worth of fully paid for inventory. When he reported the shortage to the local law enforcement officials, they told him that since there was no evidence of a breaking in, they could do nothing about it. In addition, he could not recover from his insurance company for the same reason. There was no evidence other than Respondent's sworn testimony that there was a shortage or that he reported the loss to either agency. Respondent has been in the pool business in Florida for five years and in New Jersey for 32 years before that. He feels the cause of his problem is the fact that he trusted the people who worked for him who took advantage of him. During the entire period of time he was in business in Florida he took no money from the company for his personal use, living instead on income from a mortgage he owned in New Jersey. He subsequently filed for bankruptcy on March 9, 1981. The $15,000 in current accounts receivable he had on the books at that time was utilized in the bankruptcy proceeding to pay creditors. He got-none of it. He is now working in Orlando, Florida, for a pool rehabilitation company owned by his wife and her father. Respondent alleges that on July 15, 1980, he paid Richard Thompson $1,100 to complete work started on several pools, including that of Ms. Conover. Review of the prior findings of fact, however, shows that the contract with Ms. Conover was not entered into until approximately 45 days after Respondent supposedly made this payment to cover the work left undone on her pool. In light of that development, I find his contention completely without merit or basis in fact. Respondent admits that people were hurt as a result of his actions and he regrets this. However, he claims these few incidents are insignificant when compared with the over 500 satisfied customers he alleges he has served over the years. Finally, Respondent contends that early in 1980, after being advised that he had passed the test to be a certified pool contractor, he wrote to Petitioner and, after advising how he was registered and doing business, asked if he needed to make any changes in license registration. He did in fact do this and received no reply. He thereafter assumed he was acting correctly in that regard and that appears to be a justified assumption.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's license as a contractor be suspended for two years and that he be assessed an administrative fine of $500. RECOMMENDED this 16th day of May, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of May, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Pasquale M. Vescera 1316 Hoffner Avenue Orlando, Florida 32809 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue The issue is whether Respondent violated Subsection 489.129(1)(m), Florida Statutes (1997), by allegedly committing incompetence or misconduct by "poor soil compaction" and by failing to honor the terms of a written warranty.
Findings Of Fact The four-count Administrative Complaint contains factual allegations in 15 numbered paragraphs. Respondent does not dispute paragraphs 1 through 9, 14, and 15. Petitioner is the state agency statutorily charged with regulating pool contracting in the state. At all times material to this proceeding, Respondent has been licensed as a pool contractor pursuant to license number CP C052509. Respondent's business address is Bazar Pools, Inc., 6214 All America Boulevard, Orlando, Florida 32810. On March 6, 1998, Respondent entered into a written contract with Mr. Rex Davidson (the contract). Respondent agreed to construct a residential cantilever deck swimming pool at Davidson's residence located at 2800 Granada Boulevard, Kissimmee, Florida (the pool). Mr. Davidson agreed to pay $19,300 for the pool. Respondent completed the pool sometime in April 1998. Mr. Davidson paid the full amount due under the contract. The contract warranted the "pool structure" for the time that Mr. Davidson owned the pool. Sometime in July of 2000, a crack emerged around the top edge of the pool above the tiles that lined the upper edge of the pool. As the crack worsened, the tiles began to fall off the pool. Respondent did not repair the crack and tiles. Mr. Davidson paid approximately $7,025 to a company identified in the record as Blue Diamond to repair the crack and tile. The contract did not include Respondent's license number. Respondent did not obtain a certificate of authority to do business as Bazar Pools, Inc., at the time he entered into the contract. The contract did not contain a written explanation of consumer rights under the Construction Industry Recovery Fund. Respondent does not dispute Counts II through IV of the Administrative Complaint charging that the acts described in this paragraph violated Subsection 489.129(1)(i), Florida Statutes (1997). Respondent disputes the charge in Count I of the Administrative Complaint that Respondent committed incompetence or misconduct. Paragraphs 10 through 12 of the Administrative Complaint contain the only factual allegations relevant to the charge of incompetence or misconduct. The disputed factual allegations state: Around July of 2000, the pool developed a crack which extended around the entire perimeter and caused the tiles to fall off because of poor soil compaction. The pool's structure is warranted to remain structurally sound for the period of time that it is owned by the original owner. Mr. Davidson contacted Respondent to get the pool repaired, but Respondent failed to take corrective action. The literal terms of allegations in paragraph 10 of the Administrative Complaint led the trier of fact to expect Petitioner to show that Respondent improperly compacted soil under the deck and thereby allowed the deck to settle. However, Petitioner submitted little, if any, evidence pertaining to how Respondent compacted the soil under the deck before Respondent poured the concrete deck. Respondent obtained the three required county inspection approvals before each step in the construction of the pool. The inspections included an inspection to ensure proper soil grade prior to pouring the pool deck. The inspections ensured that Respondent constructed the pool in accordance with stamped engineering drawings that the county required Respondent to file as a prerequisite for a building permit from the county. The vast majority of the evidence that Petitioner submitted during the hearing was relevant to allegations that Respondent committed incompetence and misconduct in two ways. First, Respondent arguably constructed the pool shell and deck as a unitized structure so that the crack and tile problems evolved as the deck settled when underlying soil compacted. Second, Respondent arguably failed to honor the warranty in the contract. As a threshold matter, paragraph 10 in the Administrative Complaint does not allege that Respondent committed incompetence or misconduct by poor pool construction. Rather, paragraph 10 alleges only that a crack developed in the pool and tiles fell off because of "poor soil compaction." Nevertheless, the parties spent substantial hearing time submitting evidence relevant to allegations of incompetence and misconduct not specifically alleged in the Administrative Complaint. In order to prove that Respondent committed incompetence and misconduct by poor pool construction, Petitioner relies on expert opinion to show that Respondent constructed the pool and deck as a unitized structure. Petitioner's expert opined that Respondent must have connected the concrete pool shell to the concrete deck either by steel rods, identified in the record as rebar, or by a mechanical bond between the top of the pool shell and the bottom of the deck. The expert reasoned that settling of the deck could not have caused the crack in the pool unless the deck and pool shell were connected as a unitized body. Several flaws in the expert opinion offered by Petitioner prevent that testimony from reaching the level of clear and convincing evidence. Petitioner's expert did not relate his opinion to facts in evidence. First, Petitioner's expert never inspected the original construction of the pool. The expert visually inspected only the repaired pool and based his opinion on an hour and a-half inspection of the repaired pool. Counsel for Petitioner illustrated the inherent problem in such testimony when he objected to the testimony of one of Respondent's experts on the grounds that the opinion was based on a post-repair inspection. Counsel for Petitioner explained the problem as follows: Objection. Your Honor, [Respondent's expert] is testifying based on his observations of the pool as repaired by Blue Diamond. He never did - he never has made a personal observation of the pool prior to that repair when it was in the condition attributable to [Respondent's] construction method. So, he's testifying without any particular personal knowledge relative to [Respondent's] conduct. Transcript (TR) at 220-221. When Petitioner's expert inspected the post-repair pool, he did not remove the deck to determine whether the top of the pool shell was, in fact, either connected by steel to the deck or otherwise mechanically bonded to the deck. The only competent and substantial evidence in the record of whether the pool shell and the deck were constructed as a unitized structure came from Respondent. Respondent did not use rebar to connect the pool shell to the pool deck. Respondent stopped the rebar approximately two inches below the top of the pool shell. Respondent used mortar, identified in the record as "mud," to smooth variations or undulations, in the top edge of the pool shell and thereby bring the entire top edge of the pool shell up to "dead level." The maximum variation in the top edge of the pool shell prior to leveling did not exceed 1.25 inches. After the mud dried, Respondent intentionally did not clean the top edge of the pool shell. The dirt and debris remaining on the top edge of the pool shell would normally prevent a mechanical bond between the top of the pool shell and the bottom of the concrete deck. The construction technique used by Respondent to construct the pool complies with generally accepted standards for the industry. Respondent has constructed over a thousand pools since 1987 using the same or similar construction techniques. He generally constructs large residential pools in "high-end" neighborhoods that cost customers $40,000 or more, but has constructed some commercial pools. Respondent has never had this problem with his other pools and has never had any previous discipline against his license. The expert opinion offered by Petitioner has another flaw that keeps the testimony from being clear and convincing to the trier of fact. The expert concludes that the deck settled, in relevant part, because "the pool cracked and the tile fell off." In an interrelated ratiocination, the expert concludes that the pool cracked and the tile fell off because the deck settled. Petitioner's expert also concluded that the deck settled because he observed cracks in the deck when he visually inspected the post-repair pool in 2004. He concluded from the cracks he observed in 2004 that settling of the deck in 2000 caused the crack in the pool and the tile problems. Petitioner's expert did not measure the cracks or inspect them to determine if any differential existed in the cracks that would suggest soil compaction under the deck. Petitioner's expert is an expert in pool construction, but is not an expert in pool engineering and design. One of Respondent's expert witnesses is an expert in pool engineering and design. He concluded that the deck did not settle in 2000. The characteristics of the cracks in the post-repair deck in 2004 were consistent with cracks caused by heat expansion and contraction from cooling when joints in the concrete were improperly spaced. The cracks did not exhibit differential settling of the deck. The theory that the crack in the pool and tile problems could not have occurred "but for" the settling of the deck is less than clear and convincing. Faulty installation of the tile by subcontractors is a more likely cause of the problems with the pool and the tile. However, Petitioner neither alleged that Respondent engaged in such acts or that Respondent's license is subject to discipline for the acts of his subcontractors. Finally, the testimony of Petitioner's expert is based on subjective standards while the testimony of Respondent's experts is based on intelligible standards published for the entire industry. Petitioner's expert opined that Respondent committed incompetence and misconduct in constructing the pool based on the expert's personal experience and on the way the expert has constructed pools for many years. Respondent's two experts opined that Respondent complied with written standards of workmanship published by the National Spa and Pool Institute in June 1996 (Workmanship Standards). Aside from whether the pool and deck were joined as a unitized structure, Petitioner's expert opined that Respondent "shot" the pool shell about two inches short of where it should have been, used mud to build up the pool shell, and applied tile over the resulting "cold joint" between the top of the pool shell and the bottom of the deck. Petitioner's expert opined that laying tile over a cold joint is incompetence and misconduct in his experience. Respondent's experts disagree. They opined that laying tile over a cold joint is the normal practice in the industry. Petitioner's expert agreed that it is commonplace for contractors to lay tile over a cold joint and that problems arise in only one in fifty jobs. The trier of fact has discussed the competing testimony of the parties' experts to illustrate that the burden of proof is the fulcrum of decision in this case. The applicable burden of proof does not require a preponderance of evidence to show that Respondent constructed the pool in a competent manner. Rather, the trier of fact need only find that the evidence is less than clear and convincing that Respondent committed incompetence or misconduct in constructing the pool. The remaining allegation is that Respondent committed incompetence and misconduct by failing to honor the warranty and repair the pool. The evidence is less than clear and convincing that Respondent failed to honor the warranty. Sometime in June 2001, Mr. Davidson verbally complained to Respondent that a crack around the pool above the tile line had developed and that tiles around the top edge of the pool were detaching from the pool. Respondent sent a company representative to the site to evaluate the problem. Respondent also sent a service representative to the site to retrieve some of the tiles. Sometime in July 2001, Mr. Davidson again verbally complained to Respondent about the crack and tiles. By letter dated August 8, 2001, Mr. Davidson notified Respondent that a crack had developed behind the tiles sometime in the summer of 2000. The letter stated that the tiles were falling off of the side of the pool. Respondent offered to provide Mr. Davidson with an estimate of the cost of repair. Mr. Davidson elected to have Blue Diamond make the repairs. The pool structure was warranted for the time that Mr. Davidson owned the pool. It is undisputed that the pool shell was well made and water tight. The parties dispute whether the pool structure included the one or two-inch area between the top of the pool shell and the deck, as well as the deck. The contract defined the pool structure by excluding the deck, equipment, tile, and any item other than the pool shell. The definition in the contract is consistent with that in the Workmanship Standards. Petitioner's attempt to rely on a general definition of the term "structure" in a dictionary is not persuasive when considered in the light of the definitions in the contract and the Workmanship Standards. Alternatively, Petitioner argues that the pool structure included the deck and intervening area because all of the parts were constructed as a unitized structure. Based on previous findings, the evidence is less than clear and convincing that the pool shell and deck were constructed as a unitized structure.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a final order finding Respondent guilty of Counts II through IV of the Administrative Complaint and not guilty of Count I. DONE AND ENTERED this 21st day of December, 2004, in Tallahassee, Leon County, Florida. S DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of December, 2004. COPIES FURNISHED: Charles J. Pellegrini, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 John A. Shughart, Jr., Esquire Law Offices of John A. Shughart, Jr. 500 North Maitland Avenue, Suite 305A Maitland, Florida 32751 Miriam S. Wilkinson, Esquire McConnaughhay, Duffy, Coonrod, Pope & Weaver, P.A. 101 North Monroe Street, Suite 900 Post Office Drawer 229 Tallahassee, Florida 32302 Leon Biegalski, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Tim Vaccaro, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
Findings Of Fact The Petitioner is the Department of Professional Regulation. The Respondent is Phillip Whitaker, Jr., holder of certified pool contractor license number CP-C008325 at all times pertinent to these proceedings. He is the qualifying agent for the business known as Sunshine State Pools pursuant to requirements of Chapter 489, Florida Statutes. He is responsible for actions of that business relating to construction of the swimming pool which is the subject of this proceeding. His address of record is Miami, Florida. The customer, Ken Gibson, signed a contract with Sunshine State Pools on September 15, 1986. The contract called for construction of a residential swimming pool at 15840 S.W. 155th Avenue, Miami, Florida. The total contract price was $12,700. Testimony adduced at hearing establishes that Sunshine State Pools completed the layout of the customer's swimming pool and the excavation of soil from the proposed pool site by October 1, 1986. These tasks were accomplished under the Respondent's supervision. Metropolitan Dade County issued a building permit for construction of the swimming pool in response to a permit application bearing the signature of Phillip E. Whitaker. The permit and application are both dated October 10, 1986. At hearing, the Respondent acknowledged that initiation of construction prior to pulling the permit and termed this action an "oversight." Based on the candor, demeanor and experience of the Respondent, his explanation of the failure to timely obtain the construction permit is not credited. Initiation of construction for a swimming pool prior to obtaining permits constitutes a violation of part 301.1(n), of the South Florida Building Code and, by stipulation of the parties at hearing, the building code of Metropolitan Dade County. The Respondent was responsible for supervision of the actual pool shell construction. After completion and removal of the wood forms used in the process, steel rods or "rebar pins" required as support during the construction process were not removed. These rods extended some distance above the ground and posed a substantial hazard to Respondent's children while playing. Finally, the steel rods were removed by the customer a week after he requested the Respondent to remove them. Respondent admitted some of these reinforcements could have been left by his subordinates. Respondent admits responsibility for the "back fill" process completed on October 25, 1986. This was originally a responsibility of the customer under the contract as the party responsible for deck construction. The "back fill" process consists of compacting loose soil between the outside of the pool walls and surrounding earth by use of special tamping or pounding equipment. Under terms of the contract, the customer was responsible for construction of a sizeable two part deck surrounding at least sixty percent of the pool's circumference. There now exists a substantial height difference between the coping surrounding the perimeter of the pool and the deck or patio surface. The coping is elevated above the top of the patio approximately two to four inches. As adduced from testimony of Ben Sirkus (stipulated by both parties as an expert in swimming pools and swimming pool construction), coping along the top of the pool walls consists of flagstone rock in conformity with the contract terms. Some of the rocks are cracked. The rocky edge of the coping extends over the pool wall and has a dangerously sharp edge. The sharp edge of the coping overhang could have been avoided by cutting the flagstone coping smooth prior to installation, the acceptable practice among pool contractors. The bottom step to one set of the pool steps has a hazardous 19 inch riser as opposed to the 12 inch distance required by the building code. No hand rail is present. Hollow space under some of the coping stones are the result of either improper installation, dirty cement or sinking of the deck as a result of improper "back filling" upon completion of the pool shell. On one occasion, Respondent admitted responsibility for deficiencies in the pool coping to an employee named Rick Miro. The Respondent further stated to this employee that he intended to do nothing about the problem. Respondent was present during some, but not all, of the coping installation. The "skimmer," the apparatus by which debris is cleared from the pool water, is inoperable as a result of faulty construction of the pool. The failure of the Respondent, who admits to successful completion of approximately 2500 pools with only three complaints, to properly supervise job site activities was the major cause of the pool deficiencies identified at hearing.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be placed on probation for a period of two years upon such terms and conditions as may be determined by the Construction Industry Licensing Board and assessed an administrative penalty in the amount of $1500. DONE AND RECOMMENDED this 29th day of February, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5053 The following constitutes my specific ruling on proposed findings of fact submitted by the parties. Petitioner's Proposed Findings Included in finding 2. Included in finding 3. Included in finding 4. Included in findings 5, 6 and 7. Included in findings 5 and 6. Included in finding 8. Included in finding 10 with exception of hearsay statement. Included in finding 11.1 Included in finding 12. Included in finding 11. Included in finding 11. Included in finding 11. Included in finding 11. Rejected as unnecessary. Rejected as unnecessary. Included in finding 11. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mark D. Press, Esquire 2250 Southwest Third Avenue 5th Floor Miami, Florida 33129 William O'Neil General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 =================================================================
Findings Of Fact Melnikoff is the holder of a certified pool contractor's license, having been issued license No. CP C032540. Melnikoff used this license to qualify Ken-Mel Enterprises and license no. CB C029067 was issued to Melnikoff qualifying Ken-Mel Enterprises. Ken-Mel entered into a contract with John and Edythe Milton to construct a residential pool at 7336 Pineville Drive, Jacksonville, Florida. Melnikoff applied for a building permit with the City of Jacksonville to construct the pool for the Miltons. His application included a set of plans and a site plan to be approved by the City of Jacksonville. The City of Jacksonville issued a building permit and provided an inspection sign-off card to be placed at the residence where the pool was to be constructed. Melnikoff and Ken-Mel constructed the pool and were paid in full. Melnikoff failed to request or obtain any inspections of the pool construction. This is a violation of the City of Jacksonville Building Code, Section 320.504. The pool is constructed in such a way that it is flawed, deficient and hazardous. Specifically, the water slide is hooked to a potable water system and to the hot water, which is both a serious code violation and a serious and hazardous condition. The water slide is positioned improperly and attached incorrectly, such that there is a danger of injury and this is a hazardous condition. The marcite is very rough and has started to peel away from the gunnite. The marcite is stained from the finish of the pool deck. The slurry from the gunnite and pool deck is buried near the pool and is improperly disposed of. Persons are mildly shocked when touching the railing in the pool, indicating that the pool is not properly bonded, which is a hazardous condition. The pool is not level or symmetrical and there are many imperfections in the continuous curve of the wall. Steel reinforcing bars are actually protruding through the concrete near the top of the pool. Building Code requires that there be a minimum coverage of 1 1/2" of concrete. The ceramic tile is falling off the wall and it is a very poor ceramic tile job. The expansion joints are improperly placed. The main drain cover has not been fastened down, which is a very dangerous situation and a code violation. There is no means or plan for discharging water from the pool, in violation of code. Part of the deck drain is under the slab of the Milton's house which is a serious problem. The pool is deeper than the plans indicated, in violation of the building code. The pool deck is very rough in places, does not drain away from the pool, and is cracked from improper compaction and improper placement of expansion materials. All of these defects and hazardous conditions establish that Melnikoff was grossly negligent and incompetent in the construction of this pool.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order finding Steve A. Melnikoff guilty of the violations charged and revoking Melnikoff's license as a certified pool contractor. DONE and ORDERED this 29th day of June, 1988, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1988. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 88-0567 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the Petitioner in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, Department of Professional Regulation, Construction Industry Licensing Board 1. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(1); 2(2); 3-5(3); 6(4); 7(5); and 8 & 9 (6) COPIES FURNISHED: John O. Williams, Attorney at Law 1343 E. Tennessee St. Tallahassee, Florida 32308 Steven A. Melnikoff 710 Rosedale Drive Stephens City, VA 22655 Tom Gallagher, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750