SUMTER CITIZENS AGAINST IRRESPONSIBLE DEVELOPMENT, INC.; KENNETH ROOP; AND AUBREY VARNUM vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT AND NORTH SUMTER UTILITY COMPANY, 02-001122 (2002)
Division of Administrative Hearings, Florida Filed:Bushnell, Florida Mar. 20, 2002 Number: 02-001122 Latest Update: Aug. 12, 2002

The Issue Whether proposed Water Use Permits Nos. 20012236.000 (the Potable Water Permit) and 20012239.000 (the Irrigation Permit) and proposed Environmental Resource Permit No. 43020198.001 (the ERP) should be issued by the Respondent, Southwest Florida Water Management District (the District).

Findings Of Fact The Parties The individual Petitioners, Farnsworth, Roop, and Varnum are all Florida citizens and residents of Sumter County. None of the individual Petitioners offered any evidence relating to direct impacts that the ERP would have on their property. With respect to the Potable Water and Irrigation Permits, anecdotal testimony was presented by Petitioners and Wing and Weir relating to well failures and sinkholes in the area. Two Petitioners, Roop and Varnum, live in close proximity to the property encompassed by the three permits. Petitioner Farnsworth’s property is approximately three and a half miles from the project boundary. Wing and Weir live approximately four and a half to five and 18 miles from the project site, respectively. SCAID is a Florida not-for-profit corporation that has approximately 130 members. Farnsworth, the president of SCAID, identified only Roop and Varnum as members who will be directly affected by the activities to be authorized by the permits. The District is the administrative agency charged with the responsibility to conserve, protect, manage, and control water resources within its boundaries. The Utility and the Authority are limited liability companies, of which the Villages Inc. is the managing partner. The Villages Inc. is a Florida corporation. The Utility, which will serve as a provider of potable water, is regulated by the Public Service Commission, while the Authority which will provide irrigation water, is not. The Villages Inc., Development The Villages Inc. is a phased, mixed use, retirement community, which is located at the intersecting borders of Lake, Marion, and Sumter Counties. Development has been on going since at least 1983, with a current planning horizon of the year 2019. Currently, there are 15,362 constructed dwelling units in the built-out portion of the Villages Inc. that are located in Lake County and the extreme northeast corner of Sumter County. The portion located in Marion County is 60 percent complete, with 750 homes completed and another 600 under construction. Approximately another 22,000 residences are planned for development in Sumter County by the year 2012, with an additional 10,200 by the year 2019. However, the Potable Water and Irrigation Permits are only for a six-year duration, and the ERP has a duration of only six years. None of the permits authorize development activities beyond that time frame. Generally speaking, the three permits at issue include an area owned by the Villages Inc. that lies in northeast Sumter County South of County Road 466 and North of County Road 466A. However, it is not projected that this entire area will be built-out during the terms of three proposed permits. Area Hydrology and Topography In the area of the Villages Inc., there is a layer of approximately five to ten feet of sand at the land surface, which is underlain by ten to 70 feet of a clayey sand. Both of these constitute the surficial aquifer and are extremely leaky, allowing water to percolate easily through to a lower layer. Except in the vicinity of Lake Miona, there is no water in the surficial aquifer except after rainfall events. The clayey sand layer is underlain by the Upper Floridan, a limestone unit. The top of this limestone layer ("the top of the rock") occurs at fluctuating depths of between 30 and 70 feet. At approximately 350 to 400 feet below the land surface, there begins a transition to a denser unit that serves as a confining layer between the Upper Floridan production zone and the Lower Floridan production zone. This confining layer, which was confirmed by drilling at three locations in the Villages Inc. is approximately 150 feet thick in the area of the Villages Inc. Another transition, this time to a less dense formation, begins at approximately 550 to 600 feet, which is considered the top of the Lower Floridan production zone. While testing conducted on the project site indicated almost no leakage between the Upper and Lower Floridan production zones, it is generally known by experts that there is some exchange of water between the two layers. Both the Upper and the Lower Floridan contain water that meets potable water standards and both are considered water production zones. The water quality of the two zones is not significantly different. The project area is prone to karst activity, that is, the formation of sinkholes. Sinkholes are formed as a result of the collapse of the overburden above subsurface cavities which have been formed through a very gradual dissolution of limestone, thus resulting in a "sink" at the land surface. Surface water bodies in the area include Lake Miona, Black Lake, Cherry Lake, and Dry Prairie, as well as several other small wetlands. The Potable Water and Irrigation Permits The potable water permit is for the withdrawal from the Upper Floridan Aquifer of 1.164 million gallons of water per day (MGD), on an annual average, for potable use in residences and both commercial and recreational establishments. It also limits the maximum withdrawal during peak months to 2.909 MGD. The Irrigation Permit is for the withdrawal from the Lower Floridan Aquifer of 2.850 MGD, on an annual average, for use in irrigation. The peak month usage rate permissible under the proposed permit would be 9.090 MGD. Water withdrawal under the Irrigation Permit will be used for the irrigation of residential lawns, common areas, commercial landscaping, and golf courses. Modeling of Drawdowns In assessing the impacts of proposed water withdrawals from an aquifer, District personnel considered effects on the aquifers and on-surface water features in the area. Computer- generated models of the predicted effects of the Potable Water and Irrigation Permits withdrawals provided one of the principal bases for this assessment. The primary geologist assigned to review the permit applications reviewed two of the models submitted by the Utility and the Authority (jointly the WUP Applicants) and ran one personal model of her own in order to predict the effects of the proposed withdrawals on the aquifers, as well as on any wetlands and other surface water bodies. In particular, the models predict both the vertical and horizontal extent to which the withdrawals may lower the level of water within the aquifers and in-surface waters under various conditions. One of the models submitted by the WUP Applicants predicted drawdowns during a 90-day period of no rainfall while the other predicted the impacts of the withdrawals over the life of the permits, considered cumulatively with the effects of withdrawals from the already-existing Villages' development in Sumter, Marion, and Lake Counties. The District’s geologist modeled the impacts of the withdrawals over the life of the permits and included the cumulative effects of all of the current Villages' withdrawals in Sumter County. All of these models included the combined effects of both the proposed Potable Water and the Irrigation Permits. Based upon these models, it is concluded that there will be no significant drawdowns as a result of the withdrawals authorized by the proposed water use permits. Specifically, the only predicted drawdown in the surficial aquifer (0.25 feet of drawdown) is in an area where there are no natural surface water features. Drawdown in the Upper Floridan is predicted at between 0.1 and 0.2 feet, while the drawdown in the Lower Floridan is predicted at a maximum of 1.5 feet. These minor drawdowns are not expected to cause any adverse impacts. Transmissivity is the rate at which water moves horizontally through the aquifer. In areas with high transmissivity, the results of water withdrawals from an aquifer will generally be low in magnitude, but broad in lateral extent. Water withdrawals from areas of low transmissivity will result in cones of depression that are more limited in lateral extent, but steeper vertically. The use of too high a transmissivity rate in a model, would overpredict the horizontal distance of the drawdowns caused by withdrawals, but would underpredict the vertical drawdown in the immediate vicinity of the withdrawal. Conversely, use of too low a transmissivity would over-predict the effects in the immediate vicinity of the withdrawal but underpredict the lateral extent of the drawdown. The WUP Applicants’ models used a transmissivity value for the Lower Floridan Aquifer of 100,000 feet squared per day ("ft.2/d'). The WUP Applicants’ consultant derived the transmissivity values from a regional model prepared by the University of Florida. The regional model uses a transmissivity value for the entire region of 200,000 ft.2/d for the Lower Floridan. While that transmissivity is appropriate for assessing large-scale impacts, on a more localized level, the transmissivity of the aquifer may be lower. Therefore, the WUP Applicants’ consultant met with District representatives and agreed to use a value half that used in the University of Florida model. A similar approach was used for the transmissivity value used in modeling effects in the Upper Floridan. Notably, specific transmissivity values recorded in four wells in the Villages Inc. area were not used because two of these wells were only cased to a depth of just over 250 feet, with an open hole below that to a depth of 590 feet. Thus, the transmissivity measured in these wells reflect conditions in the confining layer at the immediate location of the wells - not the transmissivity of the Lower Floridan production zone. Further, site-specific information on transmissivity, measured during pump tests at individual wells, does not correlate well to the transmissivity of the aquifer, even at short distances from the well. Transmissivities measured at individual wells are used to determine the depth at which the pump should be set in the well, not to determine the transmissivity of the aquifer. Thus, the use of transmissivities derived from the regional model, but adjusted to be conservative, is entirely appropriate. Moreover, using a transmissivity in her modeling of the project impacts of 27,000 ft.2/d for the Lower Floridan Aquifer, the district geologist’s model predicted no adverse impacts. Leakance is the measure of the resistance of movement vertically through confining units of the aquifer. The leakance value used by the District for the confining layer between the Upper and Lower Floridan was taken from the University of Florida model. Tests conducted on the site actually measured even lower leakance values. Thus, the evidence establishes that the leakance value used in the WUP Applicants’ and the District’s modeling for the Floridan confining layer was reasonable and appropriate. Competent, substantial evidence also establishes that the leakance value used for Lake Miona was reasonable. The WUP Applicants submitted to the District substantial data, gathered over several years, reflecting the balance of water flowing into Lake Miona and the lake’s levels in relation to the potentiometric surface. This documentation verified the leakance value used for Lake Miona in the modeling. Finally, the District modeling used appropriate boundary condition parameters. The District modeling used what is known as the "constant head" boundary and assumes the existence of water generated off-site at the boundaries. Such a boundary simulates the discharge of the aquifer at a certain level. The use of constant head boundaries is an accepted practice. The modeling conducted on behalf of the District and the Applicants provides a reasonable assurances that the Potable Water and Irrigation Permits will not cause adverse water quality or quantity changes to surface or groundwater resources, will not cause adverse environmental impacts to natural resources, and will not cause pollution of the aquifer. Furthermore, because the predicted drawdowns are so insignificant, reasonable assurances have been provided that the withdrawals will not adversely impact existing off-site land uses or existing legal withdrawals. The modeling also provides reasonable assurances that the withdrawals will not be harmful to the water resources of the District. Moreover, monitoring requirements included in the proposed Potable Water and Irrigation Permits provide additional reasonable assurance that – should the withdrawal effects exceed those predicted by the modeling – such effects are identified and necessary steps are taken to mitigate for any potential impacts. The District has reserved the right to modify or revoke all or portions of the water use permits under certain circumstances. Specifically, the proposed Potable Water Permit requires a monitoring plan that includes the following pertinent provisions: There shall be no less than three control wetland and ten onsite wetland monitoring sites; A baseline monitoring report, outlining the current wetland conditions; * * * A statement indicating that an analysis of the water level records for area lakes, including Miona Lake, Black Lake, Cherry Lake, Lake Deaton and Lake Griffin, will be included in the annual report; A statement indicating that an analysis of the spring flow records for Gum Spring, Silver Spring, and Fenney Spring, will be included in the annual report; * * * Wildlife analyses for potentially impacted wetlands, lakes, and adjacent property owner uses or wells, including methods to determine success of the mitigation; A mitigation plan for potentially impacted wetlands, lakes, and adjacent property owner uses or wells, including methods and thresholds to determine success of the mitigation; An annual report of an analysis of the monitoring data . . . . Similar provisions are included in the proposed irrigation permit. The WUP Applicants, in conjunction with the District, have developed sites and methodologies for this monitoring. Reasonable Demand The water to be withdrawn under the proposed Potable Water Permit will serve 10,783 people. This total results from the simple multiplication of the number of residences to be built during the next six years (5,675) by the average number of residents per household (1.9). Those numbers are based upon historical absorption rates within the Villages Inc. development since 1983, an absorption rate that doubles approximately every five years. The Utility proposed a per capita use rate of 108 gallons per day for potable use only. District personnel independently verified that per capita rate, based upon current usage in the existing portions of the Villages Inc. and determined that the rate was reasonable. Based upon the population projections and the per capita rate, the District determined that there is a reasonable demand for the withdrawal of the amount of water, for potable purposes, that is reflected in the Potable Water Permit. The Utility has provided reasonable assurance regarding the Utility’s satisfaction of this permitting criterion. As to the irrigation permit, the Villages Inc. plans, within the next six years, to complete the construction of 1,911 acres of property that will require irrigation. The amount of water originally requested by the Authority for irrigation withdrawals was reduced during the course of the application process at the request of the District. The District determined the reasonable amount of irrigation water needed through the application of AGMOD, a computer model that predicts the irrigation needs of various vegetative covers. Since the Authority intends to utilize treated wastewater effluent as another source of irrigation water, the District reduced the amount of water that it would permit to be withdrawn from the Lower Floridan for irrigation. The District, thus, determined that the Authority would need 1.59 MGD annual average for recreational and aesthetic area irrigation and 1.26 MGD annual average for residential lawn irrigation, for a total of 2.85 MGD. The Villages Inc. also plans to accumulate stormwater in lined ponds for irrigation use. However, unlike its treatment of wastewater effluent, the District did not deduct accumulated stormwater from the amount of water deemed necessary for irrigation. This approach was adopted due to the inability to predict short-term rainfall amounts. The uncontroverted evidence of record establishes reasonable assurances that there is a reasonable demand for the amount of water to be withdrawn under the proposed irrigation permit. Conservation and Reuse Measures Both the Utility and the Authority applications included proposed measures for the conservation and reuse of water. The conservation plan submitted in conjunction with the irrigation permit application provides for control valves to regulate both the pressure and timing of irrigation by residential users; contractual restrictions on water use by commercial users; xeriscaping; and an irrigation control system for golf course irrigation that is designed to maximize the efficient use of water. In addition, in the proposed permits, the District requires the Utility and the Authority to expand upon these conservation measures through such measures as educational efforts, inclined block rate structures, and annual reporting to assess the success of conservation measures. The Authority also committed to reduce its dependence on groundwater withdrawals through the reuse of wastewater effluent, both from the on-site wastewater treatment facility and through contract with the City of Wildwood. Reasonable assurances have been provided that conservation measures have been incorporated and that, to the maximum extent practicable, reuse measures have been incorporated. Use of Lowest Available Quality of Water In addition to the reuse of treated wastewater effluent, the Authority intends to minimize its dependence on groundwater withdrawals for irrigation use through the reuse of stormwater accumulated in lined ponds. Thirty-one of the lined stormwater retention ponds to be constructed by the Villages Inc. are designed as a component of the irrigation system on-site. Ponds will be grouped with the individual ponds within each group linked through underground piping. There will be an electronically controlled valve in the stormwater pond at the end of the pipe that will be used to draw out water for irrigation purposes. These lined stormwater ponds serve several purposes. However, the design feature that is pertinent to the reuse of stormwater for irrigation is the inclusion of additional storage capacity below the top of the pond liner. No groundwater will be withdrawn for irrigation purposes unless the level of stormwater in these lined ponds drops below a designed minimum irrigation level. Groundwater pumped into these ponds will then be pumped out for irrigation. Thus, the use of groundwater for irrigation is minimized. The Authority has met its burden of proving that it will use the lowest quality of water available. With respect to the potable permit, the evidence establishes that there are only minor differences between the water quality in the Upper Floridan and Lower Floridan in this area. The Upper Floridan is a reasonable source for potable supply in this area. Thus, reasonable assurances have been provided by the Utility that it will utilize the lowest water quality that it has the ability to use for potable purposes. Waste of Water In regard to concerns that the design of the Villages Inc.'s stormwater/irrigation system will result in wasteful losses of water due to evaporation from the surface of the lined ponds, it must be noted that there are no artesian wells relating to this project and nothing in the record to suggest that the groundwater withdrawals by either the Utility or the Authority will cause excess water to run into the surface water system. Additionally, the evidence establishes that, to the extent groundwater will be withdrawn from the Lower Floridan and pumped into lined stormwater ponds, such augmentation is not for an aesthetic purpose. Instead, the groundwater added to those ponds will be utilized as an integral part of the irrigation system and will be limited in quantity to the amount necessary for immediate irrigation needs. Finally, the water to be withdrawn will be put to beneficial potable and irrigation uses, rather than wasteful purposes. Under current regulation, water lost from lined stormwater ponds through evaporation is not considered as waste. Thus, the Authority and the Utility have provided reasonable assurances that their withdrawals of groundwater will not result in waste. The ERP The stormwater management system proposed by the Villages Inc. will eventually serve 5,016 acres on which residential, commercial, golf course, and other recreational development will ultimately be constructed. However, the proposed permit currently at issue is preliminary in nature and will only authorize the construction of stormwater ponds, earthworks relating to the construction of compensating flood storage, and wetland mitigation. Water Quality Impacts The stormwater management system will include eight shallow treatment ponds that will be adjacent to Lake Miona and Black Lake and 45 lined retention ponds. Thirty-one of these lined ponds will serve as part of the irrigation system for a portion of the Villages Inc.'s development. All of these ponds provide water quality treatment. The unlined ponds will retain the first one inch of stormwater and then overflow into the lakes. The ponds provide water quality treatment of such water before it is discharged into the lakes. The water quality treatment provided by these ponds provides reasonable assurances that the project will not adversely impact the water quality of receiving waters. While they do not discharge directly to surface receiving waters, the lined retention ponds do provide protection against adverse water quality impacts on groundwater. There will be some percolation from these ponds, from the sides at heights above the top of the liner. However, the liners will prevent the discharge of pollutants through the highly permeable surface strata into the groundwater. The Villages Inc. designed the system in this manner in response to concerns voiced by the Department of Environmental Protection during the DRI process regarding potential pollutant loading of the aquifer at the retention pond sites. Furthermore, by distributing the accumulated stormwater - through the irrigation system - over a wider expanse of vegetated land surface, a greater degree of water quality treatment will be achieved than if the stormwater were simply permitted to percolate directly through the pond bottom. There is no reasonable expectation that pollutants will be discharged into the aquifer from the lined ponds. If dry ponds were used, there would be an accumulation of pollutants in the pond bottom. These measures provide reasonable assurances that there will be no adverse impact on the quality of receiving waters. Water Quantity Impacts With regard to the use of lined retention ponds, as part of the Villages Inc.’s stormwater system and the impact of such ponds on water quantity, the evaporative losses from lined ponds as opposed to unlined ponds is a differential of approximately one (1) inch of net recharge. The acreage of the lined ponds - even measured at the very top of the pond banks - is only 445 acres. That differential, in terms of a gross water balance, is not significant, in view of the other benefits provided by the lined ponds. As part of the project, wetlands will be created and expanded and other water bodies will be created. After rainfalls, these unlined ponds will be filled with water and will lose as much water through evaporation as would any other water body. The design proposed by the Villages Inc., however, will distribute the accumulated stormwater across the project site through the irrigation of vegetated areas. The documentation submitted by the Villages Inc. establishes that the ERP will not cause adverse water quantity impacts. The Villages Inc. has carried its burden as to this permitting criterion. Flooding, Surface Water Conveyance, and Storage Impacts Parts of the project are located in areas designated by the Federal Emergency Management Administration (FEMA) as 100-year flood zones. Specifically, these areas are located along Lake Miona, Black Lake, between Black Lake and Cherry Lake, and at some locations south of Black Lake. Under the District’s rules, compensation must be provided for any loss of flood zone in filled areas by the excavation of other areas. The District has determined, based upon the documentation provided with the Villages Inc.’s application, work on the site will encroach on 871.37 acre feet of the FEMA 100-year flood zone. However, 1,051.70 acre feet of compensating flood zone is being created. The Villages Inc. proposes to mitigate for the loss of flood zone primarily in the areas of Dry Prairie and Cherry Lake. At present, Cherry Lake is the location of a peat mining operation authorized by DEP permit. Mining has occurred at that site since the early 1980s. The flood zone mitigation proposed by the Villages Inc. provides reasonable assurance that it will sufficiently compensate for any loss of flood basin storage. The Villages Inc.'s project provides reasonable assurance that it will neither adversely affect surface water storage or conveyance capabilities, surface or groundwater levels or surface water flows nor cause adverse flooding. Each of the 45 retention ponds to be constructed on-site will include sufficient capacity, above the top of the pond liner, to hold a 100-year/24-hour storm event. This includes stormwater drainage from off-site. In addition, these ponds are designed to have an extra one foot of freeboard above that needed for the 100-year/24-hour storm, thus providing approximately an additional 100 acres of flood storage beyond that which will be lost through construction on-site. Furthermore, the Villages Inc. has proposed an emergency flood plan. In the event of a severe flood event, excess water will be pumped from Dry Prairie, Cherry Lake, and Lake Miona and delivered to the retention ponds and to certain golf course fairways located such that habitable living spaces would not be endangered. Environmental Impacts and Mitigation There are 601 acres of wetlands and surface waters of various kinds in the Villages Inc.’s project area. Forty-one acres of wetlands will be impacted by the work that is authorized under the ERP. Each of these impacted wetlands, along with the extent of the impact, is listed in the ERP. The impacts include both fill and excavation and all will be permanent. When assessing wetland impacts and proposed mitigation for those impacts, the District seeks to ensure that the activities proposed will not result in a net loss of wetland functionality. The object is to ensure that the end result will function at least as well as did the wetlands in their pre-impact condition. Functional value is judged, at least in part, by the long term viability of the wetland. While small, isolated wetlands are not completely without value, large wetland ecosystems – which are less susceptible to surrounding development – generally have greater long-term habitat value. The District’s policy is that an applicant need not provide any mitigation for the loss of habitat in wetlands of less than 0.5 acre, except under certain limited circumstances, including where the wetland is utilized by threatened or endangered species. Some wetlands that will be impacted by the Villages Inc.’s project are of high functional value and some are not as good. The Villages Inc. proposes a variety of types of mitigation for the wetlands impacts that will result from its project, all of which are summarized in the ERP. In all, 331.55 acres of mitigation are proposed by the Villages Inc. First, the District proposes to create new wetlands. Approximately 11 acres of this new wetland will consist of a marsh, which is to be created east of Cherry Lake. Second, it proposes to undertake substantial enhancement of Dry Prairie, a 126-acre wetland. Currently – and since at least the early nineties – Dry Prairie received discharge water from the peat mining operation at Cherry Lake. Without intervention, when the mining operations stop, Dry Prairie would naturally become drier than it has been for several years and would lose some of the habitat function that it has been providing. The Villages Inc.’s proposed enhancement is designed to match the current hydroperiods of Dry Prairie, thus ensuring its continued habitat value. Third, the Villages Inc. has proposed to enhance upland buffers around wetlands and surface waters by planting natural vegetation, thus providing a natural barrier. Placement of these buffers in conservation easements does not provide the Villages Inc. with mitigation credit, since a 25-foot buffer is required anyway. However, the District determined that the enhancement of these areas provided functional value to the wetlands and surface waters that would not be served by the easements alone. Fourth, the Villages Inc. will place a conservation easement over certain areas, including a 1500-foot radius preserve required by the Fish and Wildlife Conservation Commission (FWCC) around an identified eagles’ nest. These areas will also be used for the relocation of gopher tortoises and, if any are subsequently located, of gopher frogs. While the Villages Inc. is also performing some enhancement of this area, it will receive no mitigation credit for such enhancement – which was required to meet FWCC requirements. However, since the conservation easement will remain in effect in perpetuity, regardless of whether the eagles continue to use the nest, the easement ensures the continued, viability of the area’s wetlands and provides threatened and endangered species habitat. In order to provide additional assurances that these mitigation efforts will be successful, the District has included a condition in the proposed permit establishing wetland mitigation success criteria for the various types of proposed mitigation. If these success criteria are not achieved, additional mitigation must be provided. With the above described mitigation, the activities authorized under the ERP will not adversely impact the functional value of wetlands and other surface waters to fish or wildlife. The Villages Inc. has met its burden of providing reasonable assurances relating to this permit criterion. Capability of Performing Effectively The Villages Inc. has also provided reasonable assurances that the stormwater management system proposed is capable of functioning as designed. The retention ponds proposed are generally of a standard-type design and will not require complicated maintenance procedures. In its assessment of the functional capability of the system, the District did not concern itself with the amount of stormwater that the system might contribute for irrigation purposes. Rather, it focused its consideration on the stormwater management functions of the system. The question of the effectiveness of the system for irrigation purposes is not relevant to the determination of whether the Villages Inc. has met the criteria for permit issuance. Consequently, the record establishes that the documentation provided by the Villages Inc. contains reasonable assurances that the stormwater system will function effectively and as proposed. Operation Entity The Villages Inc. has created Community Development District No. 5 (CDD No. 5), which will serve as the entity responsible for the construction and maintenance of the stormwater system. CDD No. 5 will finance the construction through special revenue assessment bonds and will finance maintenance through the annual assessments. Similar community development districts were established to be responsible for earlier phases of the Villages Inc. The ERP includes a specific condition that, prior to any wetlands impacts, the Villages Inc. will either have to provide the District with documentation of the creation of a community development district or present the District with a performance bond in the amount of $1,698,696.00. Since the undisputed testimony at hearing was that CDD No. 5 has, in fact, now been created, there are reasonable assurances of financial responsibility. Secondary and Cumulative Impacts The Villages Inc.’s application also provides accurate and reliable information sufficient to establish that there are reasonable assurances that the proposed stormwater system will not cause unacceptable cumulative impacts upon wetlands or other surface waters or adverse secondary impacts to water resources. The system is designed in a manner that will meet water treatment criteria and there will be no secondary water quality impacts. Further, the use of buffers will prevent secondary impacts to wetlands and wetland habitats and there will be no secondary impacts to archeological or historical resources. In this instance, the stormwater system proposed by the Villages Inc. will function in a manner that replaces any water quantity or water quality functions lost by construction of the system. In its assessment of the possible cumulative impacts of the system, the District considered areas beyond the bounds of the current project, including the area to the south that is currently being reviewed under the DRI process as a substantial deviation. The District’s environmental scientist, Leonard Bartos, also reviewed that portion of the substantial deviation north of County Road 466A, in order to determine the types of wetlands present there. Furthermore, the District is one of the review agencies that comments on DRI and substantial deviation applications. When such an application is received by the District’s planning division, it is routed to the regulatory division for review. The District includes its knowledge of the DRIs in its determination that there are no cumulative impacts. Reasonable assurances have been provided as to these permitting criteria. Public Interest Balancing Test Because the proposed stormwater system will be located in, on, and over certain wetlands, the Villages Inc. must provide reasonable assurances that the system will not be contrary to the public interest. This assessment of this permitting criteria requires that the District balance seven factors. While the effects of the proposed activity will be permanent, the Villages Inc. has provided reasonable assurances that it will not have an adverse impact on the public health, safety, or welfare; on fishing or recreational values; on the flow of water; on environmental resources, including fish and wildlife and surface water resources; or on off-site properties. Furthermore, the District has carefully assessed the current functions being provided by the affected wetland areas. With respect to historical or archeological resources, the Villages Inc. has received letters from the Florida Department of State, Division of Historical Resources, stating that there are no significant historical or archeological resources on the project site that is the subject of this permit proceeding. Thus, the evidence establishes reasonable assurances that the Villages Inc.'s stormwater system will not be contrary to the public interest. Additionally, the District and Applicant presented uncontroverted evidence that the proposed project will not adversely impact a work of the District, and that there are no applicable special basin or geographic area criteria.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is: RECOMMENDED that a final order be entered issuing Water Use Permit Nos. 20012236.000 and 20012239.000 and Environmental Resource Permit No. 43020198.001, in accordance with the District’s proposed agency action. DONE AND ENTERED this 24th day of June, 2002, in Tallahassee, Leon County, Florida. DON W. DAVIS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of June, 2002.

Florida Laws (5) 120.569120.57373.203380.06403.412
# 1
STRAZZULLA BROTHERS, INC. vs. SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 82-001639 (1982)
Division of Administrative Hearings, Florida Number: 82-001639 Latest Update: Jun. 21, 1991

Findings Of Fact The property has been annexed into the Acme Improvement District (Intervenor) by Special Act of the Florida Legislature. Petitioner purchased 487.7 acres of this tract from private owners in 1954. Subsequently, Petitioner purchased 653.59 acres from the Trustees of the Internal Improvement Fund of the State of Florida on or about March 4, 1960. The balance of the land constituting the property is a 224 acre hiatus tract owned by Marshall Brown with whom Petitioner has an agricultural use agreement. A parcel of Petitioner's land within the property includes a commercial lease to Malrite Corporation for siting a television antenna, consisting of 111 acres in the southeast corner of the property. This area is within the permit application. The tract is otherwise undeveloped and is currently submerged or semi- submerged during much of the year. Petitioner's development plan envisions drainage of this tract and use of the property for cultivation. The property is bounded on the north by Acme Improvement District, on the east by a subdivision called Homeland, on the west by Water Conservation Area #1, also known as the Loxahatchee Refuge, and on the south by undeveloped lands. The boundaries of the Loxahatchee Refuge actually encroach by approximately 300 feet into the property. The property development plan, which is the basis of this application, was prepared by the engineering firm Gee and Jensen. This plan calls for the creation of a 240 acre reservoir of a proposed 3 foot maximum depth. This reservoir would hold the internal stormwater runoff for subsequent agricultural irrigation. Perimeter dikes are to be constructed to prevent surface water runoff from outside areas entering the project and perimeter ditches are to be developed for the deliverance of stormwater runoff from the internal agricultural system to proposed pump stations located at the southwest corner of the development area. On the northwest corner of the proposed reservoir, the existing Acme Improvement District pump station No. 2 would be increased in capacity by 27,000 gallons per minute. Under Acme's charter and its statutory annexation of the property, the proposed reservoir and water management works would become a unit of development controlled by Acme. Under Petitioner's agreement with the hiatus tract owner, Acme would be the exclusive manager and operator of the proposed system, and the property would become an integral part of Acme's water management system. The Acme Water Improvement District is not solely an agricultural support enterprise but serves the various uses which may evolve within its boundaries. The area is currently zoned for limited residential development as well as agricultural. The television antenna facility located on the property is an example of a non-agricultural use. Petitioner's surface water management system is proposed to discharge into the Acme system, which in turn discharges offsite. Discharge into the Acme system is of a limited nature, but the system is designed to discharge for successive days under wet conditions. The design discharge is not limited to an extreme rainfall event but would probably occur during the traditional hydrologic cycle of south Florida. Under conditions which reflect actual rainfall over the past 20 years, the proposed surface water management system would have discharged 19 out of 20 years into the Water Conservation Area (Loxahatchee Refuge). In some years this discharge would have continued for approximately three months. The unrebutted testimony of expert witnesses called by Respondent established that the entire 1,393 acre tract referred to herein as "the property" is a freshwater wetland habitat. The western half is emergent marsh land, while the eastern half is forested with woody species. The wetlands on the property form a valuable wildlife habitat. Environmentally, they are in excellent condition. This area has not been adversely affected by drainage, fire or exotic species. These marshes also have good habitat diversity. The populations of aquatic invertebrates and forage fishes that are produced in these Everglades marshes are utilized by the many species of wading birds that feed in these wetlands. The proposed project will adversely affect wildlife species, including a variety of wading birds which will likely be unable to relocate. While this is undesirable from an environmental standpoint, conversion of this land would provide benefits from an agricultural standpoint, and would create additional water recreational facilities.

Recommendation From the foregoing, it is RECOMMENDED: That Respondent enter a final order denying the application. DONE and ORDERED this 30th day of November, 1983, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of November, 1983.

Florida Laws (6) 120.60373.044373.116373.403373.406373.413 Florida Administrative Code (3) 40E-1.60340E-4.09140E-4.301
# 2
THE SIERRA CLUB vs ST. JOHNS RIVER WATER MANAGEMENT DISTRICT AND HINES INTERESTS LIMITED PARTNERSHIP, 00-002231 (2000)
Division of Administrative Hearings, Florida Filed:St. Augustine, Florida May 26, 2000 Number: 00-002231 Latest Update: Jul. 12, 2004

The Issue The issues to be resolved in this proceedings concern whether Environmental Resource Permit (ERP) No. 4-109-0216-ERP, should be modified to allow construction and operation of a surface water management system (project) related to the construction and operation of single-family homes on "Marshall Creek" (Parcel D) in a manner consistent with the standards for issuance of an ERP in accordance with Rules 40C-4.301 and 40C-4.302, Florida Administrative Code.

Findings Of Fact The Project The project is a 29.9-acre residential development and associated stormwater system in a wetland mitigation area known as "Parcel D." It lies within the much larger Marshall Creek DRI in St. Johns County, Florida, bounded on the northeast by Marshall Creek, on the south and southeast by a previously permitted golf course holes sixteen and seventeen, and on the north by the "Loop Road." The project consists of thirty residential lots of approximately one-half acre in size; a short segment of Loop Road to access Parcel D; an internal road system; expansion of previously permitted Pond N, a wet detention stormwater management pond lying north of the Loop Road and wetland mitigation areas. Approximately 1.15 acres of wetlands are located on the Parcel D site. The project plan calls for filling 0.63 acres of the wetlands for purposes of constructing a road and residential lots for Parcel D. Part of that 0.63-acre impact area, 0.11 acres, is comprised of a 760-foot-long, narrow drainageway, with 0.52 acres of adjacent wetland. Downstream of the fill area, 0.52 acres of higher quality wetland is to be preserved. Hines proposes to preserve 4.5 acres of existing wetland and 2.49 acres of upland, as well as to create .82 acres of forested wetland as mitigation for the proposed impact of the project. Additionally, as part of the project, Hines will implement a nutrient and pesticide management plan. The only pesticides to be used at the project will be approved by the Department of Agriculture for use with soil types prevailing at the site and only pesticides approved by the Environmental Protection Agency may be used on the site. All pesticides to be used on the project site must be selected to minimize impacts to ground and surface water, including having a maximum 70-day half-life. Stormwater Management System The majority of surface runoff from Parcel D will be diverted to a stormwater collection system and thence through drainage pipes and a swale into Phase I of Pond N. After treatment in Pond N, the water will discharge to an upland area adjacent to wetlands associated with Marshall Creek and then flow into Marshall Creek. The system will discharge to Marshall Creek. In addition to the area served by Pond N, a portion of lots fourteen though twenty drain through a vegetated, natural buffer zone and ultimately through the soil into Marshall Creek. Water quality treatment for that stormwater runoff will be achieved by percolating water into the ground and allowing natural soil treatment. The fifty-foot, vegetated, natural buffer is adequate to treat the stormwater runoff to water quality standards for Lots 14, 15 and 20. Lots 16, 17, 18 and 19, will have only a twenty-five foot buffer, so additional measures must be adopted for those lots to require either that the owners of them direct all runoff from the roofs and driveways of houses to be constructed on those lots to the collection system for Pond N or placement of an additional twenty-five foot barrier of xeriscape plants, with all non- vegetated areas being mulched, with no pesticide or fertilizer use. An additional mandatory permit condition, specifying that either of these measures must be employed for Lots 16, 17, 18 and 19, is necessary to ensure that water quality standards will be met. Pond N is a wet detention-type stormwater pond. Wet detention systems function similarly to natural lakes and are permanently wet, with a depth of six to twelve feet. When stormwater enters a wet detention pond it mixes with existing water and physical, chemical and biological processes work to remove the pollutants from the stormwater. Pond N is designed for a twenty-five year, twenty-four- hour storm event (design storm). The pre-development peak rate of discharge from the Pond N drainage area for the design storm event is forty cubic feet per second. The post-development peak rate of discharge for the design storm event will be approximately twenty-eight cubic feet per second. The discharge rate for the less severe, "mean annual storm" would be approximately eleven cubic feet per second, pre-development peak rate and the post-development peak rate of discharge would be approximately five cubic feet per second. Consequently, the post-development peak rate of discharge does not exceed the pre- development peak rate of discharge. Pond N is designed to meet the engineering requirements of Rule 40C-42.026(4), Florida Administrative Code. Because the pond is not designed with a littoral zone, the permanent pool volume has been increased by fifty-percent. Additionally, because Pond N discharges to the Class II waters of Marshall Creek, an additional fifty-percent of treatment volume is included in the pond design. The system design addresses surface water velocity and erosion issues through incorporation of best management practices promulgated by the District to prevent erosion and sedimentation, including; designing side slopes of 4:1; siding and seeding disturbed areas to stabilize soil; and the use of riprap at the outfall from Pond N. During construction, short- term water quality impacts will be addressed through installation of silt fences and hay bales. The majority of the eighteen-acre drainage basin which flows into the Parcel D wetland lies to the south and southwest of Parcel D. In accordance with the prior permit, water from those off-site acres will be intercepted and routed to stormwater ponds serving golf course holes sixteen and seventeen. The system design will prevent adverse impacts to the hydroperiod of remaining on-site and off-site wetlands. The remaining wetlands will be hydrated through groundwater flow. Surface waters will continue to flow to the wetlands adjacent to lots fourteen through twenty because drainage from those lots will be directed across a vegetated, natural buffer to those wetlands. There is no diversion of water from the natural drainage basin, because Pond N discharges to a wetland adjacent to Marshall Creek, slightly upstream from the current discharge point for the wetland which is to be impacted. This ensures that Marshall Creek will continue to receive that fresh-water source. An underground "PVC cut-off wall" will be installed around Pond N to ensure that the pond will not draw down the water table below the wetlands near the pond. Pond N has been designed to treat stormwater prior to discharge, in part to remove turbidity and sedimentation. This means that discharge from the pond will not carry sediment and that the system will not result in shoaling. There will be no septic tanks in the project. The system is a gravity flow system with no mechanical or moving parts. It will be constructed in accordance with standard industry materials readily available and there will be nothing extraordinary about its design or operation. The system is capable of being effectively operated and maintained and the owner of the system will be the Marshall Creek Community Development District (CDD). Water Quality Water entering Pond N will have a residence time of approximately 200 days or about fifteen times higher than the design criteria listed in the below-cited rule. During that time, the treatment and removal process described herein will occur, removing most of the pollutants. Discharge from the pond will enter Marshall Creek, a Class II water body. The discharges must therefore meet Class II water quality numerical and anti-degradation standards. The design for the pond complies with the design criteria for wet detention systems listed in Rule 40C-42.026(4), Florida Administrative Code. In addition to meeting applicable design criteria, the potential discharge will meet water quality standards. The pond will have low levels of nitrogen and phosphorous resulting in low algae production in the pond. The long residence time of the water in the pond will provide an adequate amount of time for pesticides to volatilize or degrade, minimizing the potential for pesticide discharge. Due to the clear characteristics of the water column, neither thermal stratification nor chemical stratification are expected. Periodically, fecal coliform and total coliform levels are exceeded under current, pre-development conditions. These are common natural background conditions. Because the detention time in the pond will be an average of 200 days, and because the life span of fecal coliform bacteria is approximately seven to fourteen days the levels for coliforms in the pond will be very low. Discharges from the pond will enhance water quality of the Class II receiving waters because the levels of fecal coliform and total coliform will be reduced. The discharge will be characterized by approximately 100 micrograms per liter total nitrogen, compared with a background of 250 micrograms per liter presently existing in the receiving waters of Marshall Creek. The discharge will contain approximately three micrograms per liter of phosphorous, compared with sixty-three micrograms per liter presently existing in Marshall Creek. Total suspended solids in the discharge will be less than one-milligram per liter compared with seventy-two milligrams per liter in the present waters of Marshall Creek. Biochemical oxygen demand will be approximately a 0.3 level in the discharge, compared with a level of 2.4 in Marshall Creek. Consequently, the water quality discharging from the pond will be of better quality than the water in Marshall Creek or the water discharging from the wetland today. The pollutant loading in the discharge from the stormwater management system will have water quality values several times lower than pre-development discharges from the same site. Comparison of pre-development and post-development mass loadings of pollutants demonstrates that post-development discharges will be substantially lower than pre-development discharges. Currently, Marshall Creek periodically does not meet Class II water quality standards for dissolved oxygen. Construction and operation of the project will improve water quality in the creek concerning dissolved oxygen values because discharges from Pond N will be subjected to additional aeration. This results from design features such as discharge from the surface of the system, where the highest level of dissolved oxygen exists, and the discharge water draining through an orifice and then free falling to a stormwater structure, providing additional aeration. Discharges from the system will maintain existing uses of the Class II waters of Marshall Creek because there will be no degradation of water quality. Discharges will not cause new violations or contribute to existing violations because the discharge from the system will contain less pollutant loading for coliform and will be at a higher quality or value for dissolved oxygen. Discharges from the system as to water quality will not adversely affect marine fisheries or marine productivity because the water will be clear so there will be no potential for thermal stratification; the post-development discharges will remain freshwater so there will be no change to the salinity regime; and the gradual pre-development discharges will be replicated in post-development discharges. Several factors minimize potential for discharge of pesticide related pollutants: (1) only EPA-approved pesticides can be used; (2) only pesticides approved for site-specific soils can be used; (3) pesticides must be selected so as to minimize impacts on surface and groundwater; (4) pesticides must have a maximum half-life of 70 days; and (5) the system design will maximize such pollutant removal. Archaeological Resources The applicant conducted an archaeological resource assessment of the project and area. This was intended to locate and define the boundaries of any historical or archaeological sites and to assess any site, if such exists, as to its potential eligibility for listing in the National Register of Historic Places (National Register). Only a portion of one archaeological site was located on the project tract. Site 8SJ3473, according to witness Anne Stokes, an expert in the field of archaeological assessment, contains trace artifacts dating to the so-called "Orange Period," a time horizon for human archaeological pre-history in Florida dating to approximately 2,300 B.C. The site may have been only a small campsite, however, since only five pottery fragments and two chert flakes, residuals from tool-making were found. Moreover, there is little possibility that the site would add to knowledge concerning the Orange Period or pre-history because it is a very common type of site for northeast Florida and is not an extensive village site. There are likely other campsites around and very few artifacts were found. No artifacts were found which would associate the site with historic events or persons. The applicant provided the findings of its cultural resource assessment, made by Dr. Stokes, to the Florida Division of Historical Resources. That agency is charged with the responsibility of reviewing cultural resource assessments to determine if significant historic or archaeological resources will be impacted. The division reviewed the survey techniques used by Dr. Stokes, including shovel testing, sub-surface testing and pedestrian walk-over and investigation. The division determined that the site in question is not of a significant historical or archaeological nature as a resource because it does not meet any of the four criteria for inclusion in the National Register.1 Thus the referenced agency determined that the site in question is not a significant historical or archaeological resource and that construction may proceed in that area without further investigation, insofar as its regulatory jurisdiction is concerned. Wetlands The wetlands to be impacted by the project consist of a 1,000 foot drainage-way made up of a 0.11 acre open-water channel, approximately four feet wide, and an adjacent vegetated wetland area of approximately 0.52 acres containing fewer than 30 trees. The open-water channel is intermittent in that it flows during periods of heavy rainfall and recedes to a series of small, standing pools of water during drier periods. The Parcel D wetland is hydrologically connected to Marshall Creek, although its ephemeral nature means that the connection does not always flow. The wetland at times consists only of isolated pools that do not connect it to Marshall Creek. Although it provides detrital material export, that function is negligible because the productivity of the adjacent marsh is so much greater than that of the wetland with its very small drainage area. Because of the intermittent flow in the wetland, base flow maintenance and nursery habitat functions are not attributed to the wetland. The Parcel D wetland is not unique. The predominant tree species and the small amount of vegetated wetland are water oak and swamp bay. Faunal utilization of the wetland is negligible. The wetland drainage-way functions like a ditch because it lacks the typical characteristics of a creek, such as a swampy, hardwood floodplain headwater system that channelizes and contains adjacent hardwood floodplains. The location of the wetland is an area designated by the St. Johns County comprehensive plan as a development parcel. The Florida Natural Areas Inventories maps indicate that the wetland is not within any unique wildlife or vegetative habitats. The wetland is to be impacted as a freshwater system and is not located in a lagoon or estuary. It contains no vegetation that is consistent with a saltwater wetland. The retaining wall at the end of the impact area is located 1.7 feet above the mean high water line. Wetland Impacts The proposed 0.63 acre wetland impact area will run approximately 760 linear feet from the existing trail road to the proposed retaining wall. If the wetland were preserved, development would surround the wetland, adversely affecting its long-term functions. Mitigation of the wetland functions is proposed, which will provide greater long-term ecological value than the wetland to be adversely affected. The wetland to be impacted does not provide a unique or special wetland function or good habitat source for fish or wildlife. The wetland does not provide the thick cover that would make it valuable as Black Bear habitat and is so narrow and ephemeral that it would not provide good habitat for aquatic-dependent and wetland-dependent species. Its does not, for instance, provide good habitat for woodstorks due to the lack of a fish population and its closed- in tree canopy. Minnow sized fish (Gambusia) and crabs were seen in portions of the wetland, but those areas are downstream of the proposed area of impact. Mitigation Mitigation is offered as compensation for any wetland impacts as part of an overall mitigation plan for the Marshall Creek DRI. The overall mitigation plan is described in the development order, the mitigation offered for the subject permit and mitigation required by prior permits. A total of 27 acres of the more than 287 acres of wetlands in the total 1,300-acre DRI tract are anticipated to be impacted by the DRI. Approximately 14.5 acres of impacted area out of that 27 acres has already been previously authorized by prior permits. The overall mitigation plan for the DRI as a whole will preserve all of the remaining wetlands in the DRI after development occurs. Approximately one-half of that preserved area already has been committed to preservation as a condition of prior permits not at issue in this case. Also, as part of prior permitting, wetland creation areas have been required, as well as preserved upland buffers which further protect the preserved wetlands. The mitigation area for the project lies within the Tolomato River Basin. The development order governing the total DRI requires that 66 acres of uplands must also be preserved adjacent to preserved wetlands. The overall mitigation plan for the DRI preserves or enhances approximately 260 acres of wetlands; preserves a minimum of 66 acres of uplands and creates enhancement or restores additional wetlands to offset wetland impacts. The preserved wetlands and uplands constitute the majority of Marshall Creek, and Stokes Creek which are tributaries of the Tolomato River Basin, a designated Outstanding Florida Water (OFW). Preservation of these areas prevents them from being timbered and ensures that they will not be developed in the future. The overall DRI mitigation plan provides regional ecological value because it encompasses wetlands and uplands they are adjacent to and in close proximity to the following regionally significant resources: (1) the 55,000 acre Guana- Tolomato-Matanzas National Estuarine Research Reserve; (2) the Guana River State Park; (3) the Guana Wildlife Management Area; (4) an aquatic preserve; (5) an OFW; and (6) the 22,000 acre Cummer Tract Preserve. The mitigation plan will provide for a wildlife corridor between these resources, preserve their habitat and insure protection of the water quality for these regionally significant resources. The mitigation offered to offset wetland impacts associated with Parcel D includes: (1) wetland preservation of 0.52 acres of bottom land forest along the northeast property boundary (wetland EP); (2) wetland preservation of 3.98 acres of bottom land forest on a tributary of Marshall Creek contained in the DRI boundaries (Wetlands EEE and HHH); (3) upland preservation of 2.49 acres, including a 25-foot buffer along the preserved Wetlands EEE and HHH and a 50-foot buffer adjacent to Marshall Creek and preserved Wetland EP; (4) a wetland creation area of 0.82 acres, contiguous with the wetland preservation area; and (5) an upland buffer located adjacent to the wetland creation area. The wetland creation area will be graded to match the grades of the adjacent bottomland swamp and planted with wetland tree species. Small ponds of varying depths will be constructed in the wetland creation area to provide varying hydrologic conditions similar to those of the wetland to be impacted. The wetland creation area is designed so as to not de-water the adjacent wetlands. All of the mitigation lands will be encumbered with a conservation easement consistent with the requirements of Section 704.06, Florida Statutes. The proposed mitigation will offset the wetland functions and values lost through the wetland impact on Parcel D. The wetland creation is designed to mimic the functions of the impact area, but is located within a larger ecological system that includes hardwood wetland headwaters. The long-term ecological value of the mitigation area will be greater than the long-term value of the wetland to be impacted because; (1) the mitigation area is part of a larger ecological system; (2) the mitigation area is part of an intact wetland system; (3) the wetland to be impacted will be unlikely to maintain its functions in the long-term; and (4) the mitigation area provides additional habitat for animal species not present in the wetland to be impacted. Certain features will prevent adverse secondary impacts in the vicinity of the roadway such as: (1) a retaining wall which would prevent migration of wetland animals onto the road; (2) a guard rail to prevent people from moving from the uplands into wetlands; and (3) a vegetated hedge to prevent intrusion of light and noise caused by automotive use of the roadway.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is RECOMMENDED: That a final order be entered granting the subject application for modification of Permit 4-109-0216A-ERP so as to allow construction and operation of the Parcel D project at issue, with the addition of the inclusion of a supplemental permit condition regarding the vegetated natural buffers for Lots 16 through 19 described and determined above. DONE AND ENTERED this 9th day of April, 2001, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 2001.

Florida Laws (5) 120.57267.061373.086373.414704.06 Florida Administrative Code (5) 40C-4.09140C-4.30140C-4.30240C-42.02340C-42.026
# 3
DEPARTMENT OF COMMUNITY AFFAIRS vs ROBERT CROWDER AND POLK COUNTY, 92-002959DRI (1992)
Division of Administrative Hearings, Florida Filed:Bartow, Florida May 14, 1992 Number: 92-002959DRI Latest Update: Jun. 06, 1996

The Issue The issue in this case is whether the development order issued by Polk County for Robert Crowder's development known as Paradise Country Estates complies with Chapter 380, Fla. Stat. (1991). The Department of Community Affairs' Petition for Appeal of Development Order (the DCA Petition) alleges that the development order is contrary to Polk County's 1985 comprehensive plan for the following reasons: Paragraph 11 of the DCA Petition alleges that the development order is contrary to the provisions of Policy 9, Objective III, "Natural Resources," of the Land Use Element (LUE) of the 1985 Plan. Policy 9 states: "Structures should be placed in a manner which will not adversely affect the natural flow regime and which will not reduce the recharge capabilities." Paragraph 12 of the DCA Petition alleges that the development order is contrary to the provisions of Policy 10, Objective III, "Natural Resources," of the LUE. Policy 10 states: "Placement of structures shall be consistent with sound flood plain management practices such as compliance with the Flood Disaster Protection Act of 1973." Paragraph 13 of the DCA Petition alleges that the development order is contrary to the provisions of Policy 11, Objective III, "Natural Resources," of the LUE and Policies 9 and 10 of the "Water Resource Objective" of the Conservation Element of the Plan. Respectively, these policies state: 11. Groundwater withdrawal should not exceed the safe yield per acre as determined by Water Management Districts or successor agencies. * * * Minimize the adverse impacts of development on resources of the Floridan Aquifer, wetlands and flood-detention areas. Protect the normal quantity, quality and flow of ground water and surface water which are necessary for the protection of resources of state and regional concern. Paragraph 14 of the DCA Petition alleges that the development order is contrary to a section of Part II of the Conservation Element of the Polk County Comprehensive Plan entitled "Rare and Unique Natural Resources," which describes the Green Swamp as a "rare and unique land area resource for conservation consideration" and also states: The potentiometric high of the Floridan Aquifer lies within this area. . . . The area has a high potential for recreational and natural enjoyment. . . . The Green Swamp area is the largest expanse of forest in Polk County, with abundant water and wooded areas to provide for wildlife habitats. This area has great significance as an area for conservation of land, air, water, open space and wildlife habitats. Paragraph 15 of the DCA Petition alleges that the development order is contrary to the following section on "Density" found in Part IV of the Conservation Element, entitled "Summary of Special Problems, Areas, Issues, and Relationships": The subject of development density is a particular issue of vital importance to the county. Low density development in some areas and high density in other areas is important so that demands for public facilities can be economically and efficiently handled, so that environmental degradation is minimized, and so that land, not suitable for development, can be saved for important natural functions. The present zoning ordinance classifies most of the county in a Rural Conservation (RC) classification that permits low density development without proper regard for those areas that are best suited for development. Portions of the county should be protected from development pressures and appropriate areas should be zoned to accommodate rational densities. The present level of protection, provided by the zoning system is not brought to bear for conservation purposes. Paragraph 16 of the DCA Petition alleges that the development order is contrary to Policy 14 of the "Water Resource Objective" of the Conservation Element of the Plan: "Protect or improve existing ground and surface-water quality." Paragraph 17 of the DCA Petition alleges that the development order is contrary to Policy 2, Objective I, "Agricultural Uses," in Part V of the LUE: Protect, to the maximum extent possible, agricultural lands from encroachment of incompatible land uses and any detrimental effects of development adjacent to agricultural areas. Paragraph 19 1/ of the DCA Petition alleges that the development order is contrary to Policy 2, Objective IV, "Residential Uses," in Part V of the LUE: Promote and encourage new residential development adjacent to established growth centers, to ensure the orderly use of land and the efficient provision of facilities and services. Paragraph 20 of the DCA Petition alleges that the development order is contrary to Section 5-1(6) of Polk County Ordinance 81-28 (the County Flood Protection and Surface Water Management Code). 2/ Article V is entitled "Flood Protection Standards." Section 5-1 provides in pertinent part: GENERAL STANDARDS: The following minimum standards shall apply to new construction and substantial improvements in all areas of special flood hazard, and to any development, other than phosphate mining, within 100 feet of a watercourse: * * * (6) On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding. Paragraph 21 of the DCA Petition alleges that the development order is contrary to Section 5-2(4) of Polk County Ordinance 81-28. 3/ Section 5-2 provides in pertinent part: SPECIFIC STANDARDS: The following minimum standards shall apply in all areas of special flood hazard where base flood elevation data has been provided: * * * Subdivision Proposals: All subdivision proposals and other proposed developments shall be reviewed by the County Engineer. [I]f the proposal is in an area of special flood hazard, it shall be reviewed to assure that the following standards are met: All such proposals shall be reasonably safe from flood waters resulting from the base flood. All such proposals shall have public utilities and facilities such as sewer, gas, electrical and water systems located and constructed to minimize flood damage. Base flood elevation data shall be provided for all such proposals. Roads shall be reasonably safe from flood waters resulting from the base flood. Paragraph 22 of the DCA Petition alleges that the development order is contrary to Section 6-2(3)(a) of Polk County Ordinance 81-28. Article VI of Polk County's Flood Protection and Surface Water Management Code is entitled "Water Management Standards." Section 6-2 provides in pertinent part: GENERAL STANDARDS: The following minimum standards shall apply to all development which occurs within an area of special flood hazard and to any man-made change to improved or unimproved real estate . . .. * * * (3) (a) The amount of site alteration within a wetlands soil association shall be limited to ten percent (10%) of the area of wetlands soil association within any given total site.

Findings Of Fact The Proposed Project and Location. The project site is on Dean Still Road in Polk County, approximately 2 miles west of State Road 33. It is approximately 6 and 1/2 miles from Polk City and 15 miles from the City of Lakeland. The proposed project is comprised of 356 lots on approximately 1280 acres with a gross density of 1 unit per 3.6 acres. Although the average lot size varies, the project was reviewed under the Southwest Florida Water Management District's (SWFWMD) criteria for rural development which requires that at least 90% of the lots be at least 2 acres in size (excluding jurisdictional wetlands), and 10% of the lots be at least 1 acre (excluding jurisdictional wetlands). The site has been zoned Rural Conservation under Polk County's Zoning Code for approximately 12 years. This designation allows a density up to 1 unit per acre. Individual water wells and on-site waste disposal systems (septic tanks) will be utilized for each home. There are no water or sewer extensions proposed for the site or for adjacent areas by any governmental entity. Access to the site from Polk City is along Dean Still Road, which is unpaved at this time. The County has plans to pave it in the near future. Of the 1280 acres comprising the project site, 362 acres have been claimed as jurisdictional wetlands and approximately 642 acres have been mapped within the 100-year floodplain by the Federal Emergency Management Agency (FEMA). 51 of the lots platted in the project are entirely within the FEMA 100- year flood plain. Several other lots contain large portions within FEMA 100- year flood plain. Despite the significant amount of wetlands and floodplains on the site, the project is designed so that no net loss will occur in the floodplains and less than 1% (.59%) of the jurisdictional wetlands will be impacted by development. Impervious conditions on the site will only increase by 2.8% after development. All structures will be set at or above the 100 year flood elevation, as calculated by the project engineers, and will be constructed in accordance with the County's flood protection standards. The project is designed so that post-development runoff is less than pre-development runoff and post-development drainage basins conform to pre-development drainage basins. Existing drainage patterns for the site are designed to be maintained. The property comprising the project has been used through the years for a variety agricultural purposes, including harvesting watermelons, soybeans, corn, and silage. It has been drained and ditched to facilitate these activities. It is currently being used for grazing cattle. A sod farm is located to the south of the property. Additional cattle grazing lands run south from there to Polk City. To the north of the site are ranchlands which run to the border of the Withlacoochee Wildlife Area. Immediately to the west of the site are 20-30 scattered mobile homes and additional ranchlands in a subdivision known as Evans Acres. This subdivision was initially approved by DCA in 1983, and was comprised of 48 lots on approximately 1,290 acres. The original lots ranged in size from 5 to 60 acres. Apparently, individuals have since split their lots and many of the existing lots are 2 to 5 acres in size. A few of the original lots are used for both residential and ranching purposes. Including the large and small lots, there are approximately 163 lots on the property comprising Evans Acres. On the property directly to the east of the site are approximately 16 mobile homes along Melody Lane. These existing homesite numbers are small and scattered when compared to the 356 lots proposed for Paradise Country Estates. Approximately 120 families live in the general vicinity of the proposed project. The Green Swamp. The project is within the Green Swamp Area of Critical State Concern (ACSC). The site is within the drainage basin of the Withlacoochee River, which has been designated an Outstanding Florida Water (OFW) and is approximately three and a half miles to the north. The Green Swamp ACSC was designated by the Legislature. Chapter 79- 73, 380.0551, Florida Statutes (1991). It was the second area to be designated and now is one of only four areas in the State retaining this designation. The Green Swamp was designated because the area's natural resources were considered to be of regional and statewide importance and because of concerns that uncoordinated development could endanger these resources. The Green Swamp is a regionally significant area for recharge of the Floridan Aquifer. The Green Swamp is unique because the top of the Floridan Aquifer is at or near the surface over much of the area. This creates what is known as the potentiometric high of the Floridan Aquifer. The potentiometric high pressurizes the Floridan Aquifer, permitting it to be used for drinking water wells. The Florida Aquifer serves as the principal source of drinking water for central Florida. It supplies the entire State with about 48 percent of its ground water supply. The potentiometric high also serves to hold back salt water intrusion into the Floridan. Recharge is important in maintaining the potentiometric high of the Floridan Aquifer. Although the Green Swamp has been characterized as a recharge area for the Floridan Aquifer, the actual recharge capabilities of the Green Swamp vary considerably throughout the region. Some areas within the Green Swamp, such as the high, dry, sandy ridge on the eastern boundary of the Green Swamp clearly are high recharge areas. In some areas, the Floridan Aquifer rises essentially to the ground surface, with no confining layer above it. In those areas, a considerable amount of surface water filters into the Floridan Aquifer. In other areas, including in the vicinity of the project site, recharge capability is considerably less. See "G. Review under the 1985 Plan and the Flood Protection and Surface Water Management Code, (3) Ground Water Recharge." The head waters of several rivers, including the Withlacoochee River, are in the Green Swamp. Polk County's Comprehensive Plan. Polk County's Comprehensive Plan, as amended by Polk County Ordinance 85-08 (Ordinance 85-08), is referred to as Polk County's 1985 comprehensive plan, or the 1985 plan. It includes a Land Use Element (LUE) and a Conservation Element. The Land Use Element. The 1985 Plan is a "policy plan." As a "policy plan," the LUE does not map land use classifications or densities or intensities of development. The different parts of the plan must be considered together to ascertain their meaning. As stated in the Foreward to the LUE: The Policy Plan is a flexible and realistic guide to future public decisions. Existing conditions are first determined and analyzed. Then, community goals are identified providing a process of finding out where we are and where we want to go. * * * . . .. The challenge is to determine the means of achieving the identified community goals at minimal cost and the least possible hardship on any segment of our society. Under the policies planning process this is accomplished by developing all possible alternative courses of action that will advance the community toward the desire goal. The policies are then a general statement of purpose and outlining broad principles toward which the plan is guided in the implementation stage. A policy plan does not detail specific actions or locations on a map. Rather it provides a broad framework within which day-to-day decisions are made in a consistent manner toward an identified goal. The ultimate product of those community goals will be the heritage of Polk County's future. At 4-2, the LUE discusses the need to give attention to "the proper distribution of population densities in keeping with sound planning practices, the physical capabilities of the land, and the relationship of the population and housing densities to existing or proposed transportation facilities and other community services." It then speaks to "Retention of Open Spaces": A second potential problem to be faced, as urban growth continues, is the potential loss of the open space characteristics that now contribute substantially to its desirability as a community in which to live and visit. To a large extent, the desirable characteristics are provided by extensive agricultural areas. Such uses are compatible with residential and other types of urban land uses and should be encouraged to remain to the maximum extent possible. Desirable open space is also presently provided by . . . wetland areas not suited for urban development. By encouraging such areas to remain in their present condition, a substantial amount of open space can be retained to provide the needed visual relief and openness necessary within a highly urbanized community. At 4-5, discussing "Retention of Unique Agricultural Lands," the LUE states that cattle raising and field crops are subject to potential intrusion by urban development and states: "The development of planning techniques, which will encourage the retention of important agricultural lands and provide for orderly urban development, thus becomes a matter of considerable importance." The Goals, Objectives, and Policies (GOPs) of the LUE starting at 5-1 include the following: General Goal: To maintain productive and mutually compatible use of lands and waters within Polk County in a manner consistent with the economic, physical and social needs, capabilities, and desires of Polk County and its citizens. Objective I - Agricultural Uses: To ensure that a sufficient quantity of appropriate lands are available and protected for productive agricultural uses necessary to a sound economic base. Policies: * * * 2. Protect, to the maximum extent possible, agricultural lands from encroachment of incompatible land uses and any detrimental effects of development adjacent to agricultural areas. * * * 5. Provide all possible incentives for the retention of lands into agricultural production. * * * Objective III - Natural Resources Minimize adverse impacts of development on valuable natural resources including the protection of water quality and quantity in surface and ground waters. Policies: * * * 2. The subdivision and platting of land shall be permitted in accordance with the zoning district applied to the property and in compliance with the Polk County Subdivision Regulations and Flood Protection/Surface Water Management Ordinance. * * * Site alteration should be permitted only when such alteration will not adversely affect the natural flow regime or the natural recharge capabilities of the site. Site alteration should be permitted only when such alteration will not result in the siltation of wetlands or reduce the natural retention and filtering capabilities of wetlands. Site alteration activities should provide for water retention and settling facilities; should maintain an overall site runoff equivalent to the natural flow regime prior to alteration and should maintain a runoff rate which does not cause erosion. * * * Storm water runoff should be released into the wetlands in a manner approximating the natural flow regime. Structures should be placed in a manner which will not adversely affect the natural flow regime and which well not reduce the recharge capabilities. Placement of structures shall be consistent with sound flood plain management practices such as compliance with the Flood Disaster Protection Act of 1973. Groundwater withdrawal should not exceed the safe yield per acre as determined by Water Management Districts or successor agencies. Objective IV - Residential Areas To ensure that an adequate supply of appropriately located lands are available for the development and maintenance of residential areas that can be efficiently and effectively provided with necessary public facilities and services. Policies: Promote and encourage the provision of a wide range of housing opportunities, in appropriate locations, to permit a choice of housing types to suit the particular needs of all citizens. Promote and encourage new residential development adjacent to established growth centers, to ensure the orderly use of land and the efficient provision of facilities and services. * * * Encourage new residential development that can be effectively served by the existing transportation facilities. Promote new residential development in non-urban areas, that is properly designed to combine with future adjacent development, to create a neighborhood of sufficient size to facilitate the efficient and effective provision of all necessary public facilities and services. Part VI of the LUE, entitled "Alternate Approaches," discusses the pros and cons of different concepts for planning and managing of growth. It settles on a "Resource-Responsive Concept" as the preferred growth alternative. This concept holds in part: Wherever possible, future growth should be encouraged to take place in or near established urbanized areas. Scattered growth incapable of functioning as meaningful self-contained communities should be discouraged. And it is preferable that the urbanizing area, as it extends over extensive areas within the County, not be developed in one continuous, monotonous maze of residential, commercial, and industrial uses - but that there be open space provided at appropriate intervals so as to provide visual relief and a sense of scale to the overall urban community. Such open space areas can be productively utilized for agricultural and conservation purposes or recreation areas, public facilities and services required. It is proposed that the most appropriate urban growth concept to meet such guide-lines and the policy statements of this land use plan be a resource-responsive growth concept. Under this concept, urban growth and development will be guided and encouraged with respect to its responsiveness to the natural and human resource capabilities of the County. Within any given area of the County, the resources will be careful evaluated in terms of their capability to support growth, and the physical form and intensity of development will be then shaped to provide the physical form and intensity of development will be then shaped to provide a balance with such resources. Prime resources to be considered are as follows: Natural Resources Topography and soil conditions Vegetation and tree cover Wildlife habitats present Drainage characteristics; relationship to rivers and lakes Natural water supply capabilities General aesthetic qualities Human Resources Transportation facilities (roads, railroads, airports) Available water supply and sewage facilities Community facilities, such as schools, parks, libraries Protective services, such as fire and police Established land uses within the area Economic conditions and potentials. Part VII of the LUE, entitled "Implementation," states: "Initial implementation of a Comprehensive Plan and initiation of the continuing planning process for growth management requires the establishment of principals and standards for measurement of proposed activities against the adopted policies of the community." It includes a section entitled "Principles and Standards for the Control and Distribution of Population Densities and Structural/Development Intensity," which provides in part: All Types of Urban Development: * * * Each new development or land use should follow sound land planning principles to maximize site advantages, avoiding when possible, adverse impacts on the natural resources and hazards to health, safety, or general welfare. * * * Residential Development: Low-density single-family development (1-4 units/acre), other than rural residences related to agricultural operations, shall be located in areas capable of being developed into stable, cohesive neighborhoods. In a section entitled "Legal Requirements of Implementation," it states that "all actions taken by local government, whether in the form of permitting private development to occur or in the provision of public facilities and services, are required to be fully consistent with the adopted Comprehensive Plan. The plan, once adopted, must occupy a central position in the consideration of all proposed development." In another section, entitled "Coordination with Other Plan Elements," it states that the "land use element cannot be implemented alone [but] must be coordinated with the [other elements]." In another section, entitled "Needed Improvements in the Zoning Ordinance," it is recognized that "it will be essential that a thorough review of the zoning ordinance be undertaken and that the ordinance be revised as appropriate to achieve consistency with overall planning objectives." It acknowledges that there were "major identified deficiencies in the current zoning regulations" and advises that "the following needs among others should be addressed as a minimum in making revisions to the zoning ordinance": "Revision of the Density Requirement in Residential Districts." Despite the admonitions in the 1985 Plan, to date there has been no revision of the land use classifications, densities, or intensities in the County's zoning code. As before the 1985 Plan was adopted, zoning in the Green Swamp ACSC remains Rural Conservation (RC) and allows up to one unit per acre residential development. The Conservation Element. Part II of the Conservation Element of the Polk County Comprehensive Plan is a "Summary of Natural Resources." At 2-18, there appears a section entitled "Rare and Unique Natural Resources," which describes the Green Swamp, as well as other natural resources in the County, as a "rare and unique land area resource for conservation consideration." At 2-19, as amended by Ordinance 85-08, this element of the comprehensive plan also states: This area comprises the hydrologic heartland of Central Florida and contains the headwaters of the Withlacoochee, Hillsborough, Peace and Oklawaha Rivers. The potentiometric high of the Floridan Aquifer lies within this area. . . . The area has a high potential for recreational and natural enjoyment. . . . The Green Swamp area is the largest expanse of forest in Polk County, with abundant water and wooded areas to provide for wildlife habitats. This area has great significance as an area for conservation of land, air, water, open space and wildlife habitats. Part IV of the Conservation Element is a "Summary of Special Problems, Areas, Issues, and Relationships." Starting at 4-2, it addresses the following: Displacement . . .. Cities in Polk County have historically developed on the ridges and the urbanized areas are spreading outward rapidly into the prime citrus lands and the "marginal" (flood prone) lands. There is considerable concern about urban development in wetland soils and flood prone areas. The double barreled concern for development in wetland soils and wetland areas is that they might well serve valuable natural functions and the private and public problems created by development subjected to flood damages. This property damage promotes public pressure for drainage in wet areas. The issue in wetland drainage and flood control is the jeopardy of natural functions that wetlands and water fluctuations provide in natural systems and flood damage costs. . . . [C]oncern for the growing demand for uplands development which steadily displaces [good pasture land] . . . relate[s] to the use of good pasture land for development. Density The subject of development density is a particular issue of vital importance to the county. Low density development in some areas and high density in other areas is important so that demands for public facilities can be economically and efficiently handled, so that environmental degradation is minimized, and so that land, not suitable for development, can be saved for important natural functions. The present zoning ordinance classifies most of the county in a Rural Conservation (RC) classification that permits low density development without proper regard for those areas that are best suited for development. Portions of the county should be protected from development pressures and appropriate areas should be zoned to accommodate rational densities. The present level of protection, provided by the zoning system is not brought to bear for conservation purposes. * * * Water * * * Another area of concern relates to the draw down and recha[r]ge of the Floridan Aquifer and is claimed to be a rational concern of an area much larger than Polk County. * * * Pollution Environmental pollution, as it relates to water, is a major local concern. * * * Water pollution is concerned because of its effects on recreation and tourism. Water degradation and the pollution of lakes and rivers tends to remove the intangible value that Polk County enjoys in thee form of its surface water resources. * * * Also, the related cost issues of municipal sewage treatment and disposal, effluent disposal techniques, septic tank useage are environmentally economic choices to be made by the public. Discussing the topic, "Preservation and Management," starting at 4-4, Part IV of the Conservation Element states in part: Many issues relate to what, how, or when something should be conserved. * * * Lakes, rivers and canals of the county are of concern as sources of flooding and as resources for flood control, if properly managed. Flood prone areas surrounding surface water have been identified for much of the county. These water bodies are also legitimate concerns as the habitat for fish and other wildlife that provide a significant value in their own right. The area of these water bodies are also special scenic and recreational values that contribute to tourism and development. Part V of the Conservation Element is where the "Goals, Objectives and Policies" are found. It start with some general observations, including in part: . . .. It can be expected, therefore, that the natural environment of the county will continue to undergo modification of one type or another in response to the needs of people. . . . The inventory of total space will, therefore, diminish as these changes take place, resulting in corresponding losses within particular categories of natural resources. What is important is that no critical loss of impairment of a natural resource take place; that development be managed so as to create minimum disturbance of the remaining natural resource systems; and that there be compensation replenishments of resources wherever possible. It then lists a General Goal and several resource-specific objectives and policies: General Goal: Maintain, protect, develop and utilized the natural resources in a manner that will balance and replenish the natural ecological systems and will best serve and promote the desired quality of life for Polk County resident, present and future. * * * Water Resource Objective: To conserve and protect the quality and quantity of water resources through proper management. * * * 6. Identify and protect significant acquifer [sic] recharge areas for maximum recharge capability and protect the water available for aquifer recharge. * * * Minimize the adverse impacts of development on resources of the Floridan Aquifer, wetlands and flood-detention areas. Protect the normal quantity, quality and flow of ground water and surface water which are necessary for the protection of resources of state and regional concern. Protect the functions of the Potentiometric High of the Floridan Aquifer. Prevent further salt-water intrusion into the Floridan Aquifer. Protect or improve existing ground and surface-water quality. Protect the water retention and biological-filtering capabilities of wetlands. Protect the natural flow regime of drainage basins. Rare and Unique Natural Resource Objective: To conserve and protect, through proper resources management, areas having unique natural characteristics and particularly sensitive environmental balance. * * * Policies: Identify all significant areas in Polk County deemed to have unique natural resource characteristics. Encourage proper management of unique wetland areas of the County as a vital water resource. Encourage a proper system for control of development in flood prone and wetland areas to regulate alternation [sic] of the natural system of water retention and storage during periods of heavy rainfall. Preserve and protect, to the maximum extent possible, all delineated areas having valuable unique resource characteristics. Part V of the Conservation Element concludes with a "Summary," which states in part: The objectives and policies set forth above should not be considered as controls to be rigidly applied in every instance of decision-making dealing with the natural environment. Rather, in dealing with resource conservation issues, guidance is preferable to control. . . . A number of potential implementation actions and programs, presented in the following part, will further assist in establishing the direction and scope of conservation activities in the County. Part VI of the Conservation Element is entitled "Implementation." While acknowledging at 6-1 that Polk County cannot establish an implementation program unilaterally, without regard to the co-responsibilities of other governmental authorities at the regional state and federal levels, it states at 6-2 that Polk County "can and should": Utilize the general objectives and policies established by this Element as considerations in all decision making concerning the use and improvement of land within the County. * * * 3. Utilize, to the fullest extent possible, the policies and implementation controls of other elements of the Polk County Comprehensive Plan, and those of other governmental entities having jurisdiction, to further the conservation of natural resources. Starting at 6-3, Part VI discusses the Conservation Element's "Relationship to Other Plans." At 6-4, after stating that the Conservation Element will be largely implemented through the policies and programs of other comprehensive plan elements, Part VI provides: Land Use Element - This element will provide the overall framework for conservation [sic] potentialities through the manner in which land uses are distributed, arranged, and interrelated throughout Polk County. Policies and implementation programs of this element will determine the degree to which new development is properly related to soil types and capabilities, natural habitats, flood prone areas, wetlands and unique resource areas of the County. Land regulatory controls such as zoning, subdivision regulations and development impact reviews provide the basic tools for implementation of the policies of the Land Use Element. Starting at 6-5, Part VI discusses "Guidelines for Implementation." At 6-5, it points out: The nature of conservation policy, being of such broad application and diversity of interest, requires that its effective implementation utilize many approaches, techniques and procedures. Its application is carried out, for the most part, in an indirect way as a by-product of other more direct decisions and actions relation to the development and growth of the County. It is essential, therefore, that Polk County draw upon all possible alternative mechanisms and techniques which will lead to the effective conservation of its natural resource systems. Among the various approaches which Polk County may utilize to further its conservation objectives are the following. * * * Influence in the allocation of resources to achieve the objectives of the conservation plan. Control of events which determine resources allocation in keeping with the conservation plan. * * * Specific procedures and techniques which may be utilized to facilitate the implementation process include the following. * * * 7. Protect natural water bodies and adjacent wetland areas through the regulation of development densities and proper management of stormwater runoff. This would require a cooperative effort with the Water Management Districts in identifying flood plains for various flood frequencies. Polk County's Flood Protection and Surface Water Management Code. Polk County's Flood Protection and Surface Water Management Code was enacted as Ordinance 81-28 and was amended by Ordinance 85-07. Article V is entitled "Flood Protection Standards." Section 5-1 provides in pertinent part: GENERAL STANDARDS: The following minimum standards shall apply to new construction and substantial improvements in all areas of special flood hazard, and to any development, other than phosphate mining, within 100 feet of a watercourse: * * * (6) On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding. Section 5-2 provides in pertinent part: SPECIFIC STANDARDS: The following minimum standards shall apply in all areas of special flood hazard where base flood elevation data has been provided: * * * Subdivision Proposals: All subdivision proposals and other proposed developments shall be reviewed by the County Engineer. [I]f the proposal is in an area of special flood hazard, it shall be reviewed to assure that the following standards are met: All such proposals shall be reasonably safe from flood waters resulting from the base flood. All such proposals shall have public utilities and facilities such as sewer, gas electrical and water systems located and constructed to minimize flood damage. Base flood elevation data shall be provided for all such proposals. Roads shall be reasonably safe from flood waters resulting from the base flood. Article VI of Polk County's Flood Protection and Surface Water Management Code is entitled "Water Management Standards." Section 6-2 provides in pertinent part: GENERAL STANDARDS: The following minimum standards shall apply to all development which occurs within an area of special flood hazard and to any man-made change to improved or unimproved real estate . . .. * * * (3) (a) The amount of site alteration within a wetlands soil association shall be limited to ten percent (10%) of the area of wetlands soil association within any given total site. Review under the 1985 Plan and the Flood Protection and Surface Water Management Code. Land Use, Density and Intensity. DCA alleges that the land use, density and intensity of the development Crowder proposes for the site is inconsistent with: (1) the section on "Density" found in Part IV of the Conservation Element, entitled "Summary of Special Problems, Areas, Issues, and Relationships"; (2) a section of Part II of the Conservation Element of the Polk County Comprehensive Plan entitled "Rare and Unique Natural Resources"; (3) Policy 2, Objective I, "Agricultural Uses," in Part V of the LUE; and (4) Policy 2, Objective IV, "Residential Uses," in Part V of the LUE. 6/ As previously stated, the 1985 Plan is a policy plan that does not map land use classifications or densities or intensities of development. Crowder's Paradise Country Estates is consistent with the County's Zoning Code, which has not changed since before the 1985 plan, and Zoning Map. The development was not otherwise reviewed for land use, density or intensity. But it is clear that the 1985 plan does not condone exclusive resort to the zoning code to determine the appropriateness of the land use, density and intensity for development in the Green Swamp ACSC. See, especially, the section entitled "Density" in Part IV of the Conservation Element of the Plan. In the Green Swamp ACSC, especially, reference must also be made to the Plan itself. See Part VII of the LUE, entitled "Implementation." It is not found that all residential use on the Crowder property would be, in itself, inconsistent with the 1985 Plan. But, taking into consideration all of its land use, density and intensity provisions, it must be found that the development order issued in this case, especially at its level of density and intensity and especially in the manner of its issuance, is inconsistent with the 1985 Plan. The crux of the problem with this development, like others in the Green Swamp ACSC already permitted by County development orders, is that, first, the 1985 comprehensive plan and the County zoning regulations in place at the time were inadequate and, second, the steps envisioned in the plan to make them adequate have not been taken. For the plan and the zoning regulations to be adequate, and for a development order for a project in the Green Swamp ACSC in Polk County to be consistent with the 1985 comprehensive plan, either: (1) the plan must be amended to map land use classifications, densities and intensities of development in the Green Swamp ACSC; (2) the zoning code must be amended as envisioned in the comprehensive plan for the Green Swamp ACSC; or (3) the County must evaluate development orders for projects in the Green Swamp ACSC on a case- by-case basis for consistency with the comprehensive plan. None of these three possibilities happened in this case. 7/ Flood Plain Delineation. Paragraph 12 of the DCA Petition alleges that the Crowder development violates Policy 10 of Objective III, "Natural Resources," of the LUE: "Placement of structures shall be consistent with sound flood plain management practices such as compliance with the Flood Disaster Protection Act of 1973." Specifically, it is alleged that the use of a Federal Emergency Management Agency (FEMA) undetailed "A" zone to map the flood prone area on the site, and the failure to perform a detailed study, did not comply with the Flood Disaster Protection Act of 1973. Other allegations in the DCA Petition also implicate the delineation of the flood prone areas on the site. See, (5) Ground and Surface Water Quality, below. A FEMA "A" zone is the zone depicting the area determined by FEMA to be flood prone. In this context, FEMA defines a "flood prone" area as an area flooded in a 100-year, 24-hour storm. At the time Polk County reviewed the Crowder project for approval of the roadway and construction drainage plans, FEMA was requiring that a detailed study be performed to delineate the flood prone area. Polk County apparently was not aware of this requirement and was not enforcing it. Nor, apparently, was Crowder's engineer aware of it. In any event, Crowder did not have a detailed study performed to delineate the flood prone area on the site, and the County did not require it. In approximately March, 1992, Polk County received a written communication from FEMA advising of the requirement for a detailed study of the flood prone area in the case of developments like Crowder's. Polk County now requires compliance with this FEMA requirement. Crowder did not rely simply on the FEMA undetailed "A" zone to map the flood prone area on the site. Crowder's engineers used the existing undetailed FEMA maps as a starting point for determining base flood elevations. The engineers digitized the areas which had been designated as flood prone on the FEMA panels. The engineer then overlayed the digitized FEMA map with the on- site wetlands survey of the property, which had been field-staked and field- shot. Topographical field shots of the property which had been conducted throughout the site at one foot intervals were also overlayed on the digitized FEMA map. In addition, the engineer took into consideration mapped wetlands soils and compared flooding conditions which had occurred on adjacent property to assess whether all areas actually prone to flooding had been characterized as flood prone on the FEMA map. The methodology used by the project engineers was based on sound engineering practices. Nonetheless, it does not qualify as a "detailed study" as far as FEMA is concerned. A "detailed study" would include the application of a computer program that would "route" hypothetical flood waters onto and through the property to ascertain flood elevations in different stages of the hypothetical flood. It is not possible to determine how a detailed study would change the delineation of the flood prone area in Crowder's proposal. The total area of flood prone area could either increase or decrease; it could increase in some places and decrease in others. As it is, several of the lots platted in the Crowder development would be entirely within both the FEMA undetailed "A" zone and the flood prone area mapped by Crowder's engineers. Ground Water Recharge. DCA alleges that platting Paradise Country Estates will adversely impact recharge of the Floridan Aquifer, contrary to Policy 9 and 11, Objective III, "Natural Resources," of the LUE, and Policies 9 and 10 of the "Water Resource Objective" of the Conservation Element, of the 1985 comprehensive plan. In the vicinity of the project site, the Floridan Aquifer comes to within 35 feet approximately of the ground surface. Above the Floridan Aquifer is a shallow aquifer, which rises to within approximately 12 inches of the surface. There is a layer of clastic soils (sand and clay) between the surficial aquifer and the Floridan Aquifer. This confining layer slows the rate of recharge to the Floridan. As a result, the project site is in an area having low, or even very low, to moderate recharge capabilities, at best. USGS Professional Paper 1403-E, which was released in 1990, uses groundwater modelling to quantify recharge rates, instead of using qualitative terms such as "low," or "poor," "moderate" and "high" to describe recharge capabilities. USGS Professional paper 1403-E reports that many areas in the Green Swamp previously labeled as good, moderate or high recharge areas are actually capable of only recharging at rates of 3 to 4 inches per year. The subject property appears to be in the 2 to 3 inch range per year for recharge according to USGS Professional Paper 1403-E. Only three known sample soil borings have been taken on the project site. As a result, the extent of permeability and overall thickness of the confining layer between the surficial and Floridan aquifers is not certain. But there is no reason to believe that there are any karst features or other geologic faults in the area that would allow for direct connections between the surficial and Floridan aquifers. The soil borings that have been taken on the site verify the various geological surveys and studies describing the recharge capabilities in the area. Due to the site's limited capabilities as a recharge area, it is unlikely that the platting of this site will result in any significant reduction in its natural recharge rate. The project is not inconsistent with Policy 9 or 11, Objective III, "Natural Resources," of the LUE, or Policies 9 or 10 of the "Water Resource Objective" of the Conservation Element, of the 1985 comprehensive plan. Individual Water Well Use. DCA alleges that the planned use of individual water wells in Crowder's Paradise Country Estates will impact the quantity of the Floridan Aquifer (and the surficial aquifer) contrary to Policy 11, Objective III, "Natural Resources," of the LUE, and Policies 9 and 10 of the "Water Resource Objective" of the Conservation Element, of the 1985 comprehensive plan. The potentiometric level of the Floridan Aquifer protects the Floridan Aquifer from salt-water intrusion. Significant de-watering of the aquifer caused by large municipal or industrial wells extracting a high volume of water from the aquifer at an intense rate can lower the potentiometric pressure, thus increasing the potential for salt-water intrusion into the aquifer. (Furthermore, the lowered potentiometric pressure creates a hydraulic gradient which encourages surface waters to percolate downward at a faster rate due to the decreased pressure in the Floridan Aquifer. See the preceding sections on Ground Water Recharge and the following section on Ground and Surface Water Quality.) Large municipal, industrial or agricultural wells which exceed 6 inches in diameter must obtain consumptive use permits from the SWFWMD. The Water Management District takes into account what the District determines to be a safe yield per acre when issuing a consumptive use permit. Small, residential wells are not subject to this permitting process as their impacts are much smaller and less intense, and not a concern with regard to their effect on the potentiometric pressure. For this reason, some coastal areas have begun using smaller, individual wells as an alternative to larger municipal wells. The Floridan Aquifer is replenishing itself fast enough for residential wells not to "de-water" or "draw down" the aquifer's supply of ground water. Residential wells do not lower the potentiometric pressure of the Floridan to a significant degree. Nor would they affect the normal supply of ground water, or contribute to salt-water intrusion. Pumping tests performed within two to three miles west of the project site which utilized several residential-size wells support the foregoing conclusions. For these reasons, it is found that the development will not adversely impact the normal supply of ground water and thus will not interfere with the functions of the potentiometric high of the Floridan Aquifer, including its protection against salt-water intrusion. Since the water wells would pump only from the Floridan Aquifer, they would not impact the supply of surface water. In regard to the use of water wells, the project is not inconsistent with Policy 11, Objective III, "Natural Resources," of the LUE, or with Policies 9 or 10 of the "Water Resource Objective" of the Conservation Element, of the 1985 comprehensive plan. Ground and Surface Water Quality. DCA alleges that Paradise Country Estates will result in unacceptable contamination of the Floridan Aquifer, the surficial aquifer, and the surface water (particularly the Withlacoochee River) contrary to Policies 9, 10 and 14 of the "Water Resource Objective" of the Conservation Element. Paragraph 20 of the DCA Petition alleges that the use of individual on-site disposal systems (OSDS), or septic tank systems, in violation of Section 5-1(6) of Polk County Ordinance 81-28 (the County Flood Protection and Surface Water Management Code), 8/ in particular, will be part of the cause of the unacceptable contamination (other causes being from lawn and garden maintenance and automotive wastes.) On-Site Disposal Systems. Chapter 10D-6, Florida Administrative Code, sets forth requirements for the use of on-site waste disposal, or septic tank, systems in the State of Florida. That chapter, which is administered by the Department of Health and Rehabilitative Services ("HRS") through local health departments, provides construction standards for the installation of on-site waste disposal systems. The septic tank serves as a holding tank designed to separate solids and floatable materials and allows anaerobic digestion of organic materials. The remaining effluent exits the tank into the soil infiltrative process, which is referred to as the drainfield. The drainfield is composed of gravel placed around perforated pipes, which are designed to evenly distribute and release the effluent into soil material where the effluent undergoes aerobic digestion. Eventually, any constituents remaining in the effluent which have not been absorbed by the root zone or otherwise decomposed reach the subsurface waters which are referred to as the surficial water table. Each individual lot owner will be required to obtain a permit from the local health department prior to installing an on-site waste disposal system. Prior to issuing a permit, HRS inspects each site to assess soil limitations and to conduct a percolation test to determine the seasonal high water table for the site. Because the soils on the site are severely limited for filtration purposes and the high water table is only 10 to 12 inches below the surface, individual lot owners will be required to mound their on-site waste disposal systems to overcome these limitations. Although the fill used to mound the systems will be comprised of suitable soils, it is possible that the foreign soils will absorb moisture from the existing soils on this site, a phenomenon referred to as capillary fringe affect. This phenomenon can cause those portions of the fill which come in direct contact with the existing soils on the site to lose their filtration capabilities. Unless the fill becomes saturated from other sources, it is unlikely that capillary fringe affect will render the filtration process ineffective. The effects of capillary fringe affect can be lessened by mixing fill with soils found on the site, a practice undertaken by contractors when installing on-site waste disposal systems. In addition, increasing the amount of fill used to mound the system would decrease the potential affects of this phenomenon. 9/ Floridan Aquifer Water Quality. In some areas of the Green Swamp, the Floridan Aquifer is actually considered a surficial aquifer since no confining layers of soil or clay separate the subsurface water from the Floridan Aquifer. These areas would typically be characterized as areas with high recharge capabilities (or high potential for contamination). However, throughout the project site, a confining layer exists which is composed of clayey sands which have a very low permeability. Therefore, there is relatively little interaction between the surficial aquifer and the Floridan Aquifer on this particular site. For this reason, the use of individual on-site waste disposal systems on this site would pose no significant risk to the water quality of the Floridan Aquifer. Surficial Aquifer and Surface Water Quality.-- As for the surficial aquifer and surface water quality, Chapter 10D-6, Florida Administrative Code, requires on-site waste disposal systems be located at least 75 feet from waterbodies. Normally, and when the systems are operating properly, this assures that adequate filtration and decomposition occurs before wastewater reaches surface waters on or near the site. But, in the case of the Crowder proposal, it is necessary to consider that at least some of the mounded systems will be subjected to flooding and will become saturated. Even based on the analysis by Crowder's engineers, 51 of the lots in Paradise Country Estates are entirely flood prone; there is no place to put an OSDS on those lots that is not flood prone. If a "detailed study" had been done, it is possible that more lots would be entirely within the flood hazard zone. Other lots not entirely within the flood zone may not be able to accommodate an OSDS on the part of the lot not within the flood zone. If the OSDS mound is saturated during flood conditions, the system will fail, and untreated waste, or inadequately treated waste, will be released into the surface flood waters. This waste water will move laterally across the project site. Roots may absorb some nitrates or other organic compounds; 10/ otherwise, the waste water and its constituents will remain in the surface water. Lateral movement across the site generally will be slow, as the site is relatively flat. Some of the waste water and its constituents will get into the surficial aquifer. There are ditches or canals alongside and on the site that will direct the rest of the surface water into Pony Creek and other tributories of the Withlacoochee River, an Outstanding Florida Water approximately three and a half miles to the north. The Department of Environmental Regulation issued a dredge and fill permit for the project's road network's impact on wetlands on the site. But it did not pass on the use of OSDS in the individual lots. It also erroneously referred to the Withlacoochee as a natural Class III, instead of an Outstanding Florida Water. See F.A.C. Rule 17-302.700(9)(i). The Southwest Florida Water Management District (SWFWMD) issued a surface water management permit for the project. In evaluating a permit application, SWFWMD considers surface water quality. But the focus of SWFWMD's inquiry is the pre- and post-development peak flows. Also, when it considers water quality, SWFWMD considers the impact of site alteration on water quality, not the impact of the use of OSDS on the site. In addition, the Crowder project was reviewed under special criteria for low-density rural subdivisions that do not require the submission of as much information. It was not clear from the evidence precisely how SWFMD evaluates water quality under those criteria. For these reasons, based on the evidence, it cannot be said that the Crowder project's OSDS will be meet the minimum standard of being "located to avoid impairment to them or contamination from them during flooding," as required by Section 5-1(6) of Polk County Flood Protection and Surface Water Management Code, or that the project will "protect the normal . . . quality of ground and surface water . . . necessary for the protection of resources of state and regional concern," as required by Policy 10 of the "Water Resource Objective" of the Conservation Element of the Plan. Finally, the project will not "protect or improve existing ground and surface-water quality," as required by Policy 14 of the "Water Resource Objective" of the Conservation Element of the Plan. Other Appeal Issues. Except as set forth above, the Crowder development did not violate the 1985 comprehensive plan and Flood Protection and Surface Water Management Code provisions cited in the DCA Petition. Agency Practice - Other Development in the Area. As previously described, Evans Acres, to the west of the Crowder site, was approved by DCA in 1983. (See Finding 10, above.) As approved, it was comprised of 48 lots on approximately 1,290 acres (a density of one unit per 27 acres). The original lots ranged in size from 5 to 60 acres. Unbeknownst to the DCA, individuals apparently have since split their lots and many of the existing lots are 2 to 5 acres in size. A proposed development known as Turkey Creek is located between the project site and Evans Acres. Turkey Creek is comprised of approximately 57 lots on 170 acres with a gross density of 1 unit per 3 acres. The physical characteristics of the Turkey Creek property, including the abundance of wetlands and floodplains, are essentially the same as the proposed project site. DCA appealed Turkey Creek in June of 1992. However, in that case, the County had been approximately two years late in rendering the Turkey Creek development order to the DCA. Meanwhile, the developer incurred development expenses and already had constructed roads and drainage facilities for the development. The developer, the County and DCA executed a settlement agreement which allows the development to proceed according to the original construction plans, but requires homeowners to install dual septic tank systems and have their septic tanks cleaned and inspected every three years. Several other developments, which are in the general vicinity of the project site and have many of the same physical characteristics, including Yearling Trace and Buck Hill, have been appealed by DCA. Yearling Trace is comprised of 108 units on approximately 544 acres. Buck Hill is comprised of 55 units on approximately 214 acres. Those projects were appealed by DCA in June and April, 1992. In some of these cases, the County did not timely render development orders to DCA in a timely manner. In the case of Buck Hill, the DCA had been mailed an unapproved copy of development plans in October, 1990; in early 1992, DCA contacted the County to inquire, as no County-approved development plans ever had been sent to the DCA. In many of these cases, substantial development expenses had been incurred; in some cases, roads and drainage facilities already had been constructed. DCA decided to settle the pending appeals in which the County was late rendering the development order, and in which the developer already had constructed roads and drainage facilities, consistent with the Turkey Creek settlement. In cases where the County was late rendering the development order, but the developer had not already constructed roads and drainage facilities, the DCA determined to settle not only for stipulations to upgrade the OSDS, as in the Turkey Creek settlement, but also for requirements that a "detailed" flood zone study be done, in accordance with the FEMA requirements. Prior to the DCA appeal, Crowder had expended approximately $31,000 in permit fees. In addition, he has incurred development costs, primarily for engineering fees and related services. Through the time of the final hearing, he had spent approximately $99,000 on engineering fees and services. (The evidence was not clear how much had been incurred by the time of the DCA appeal.) However, the County was not late in rendering the Crowder development order, and Crowder has not constructed roads or drainage facilities. In view of the different circumstances in Crowder's case, DCA's prior agency practices do not compel that Crowder's development be treated in the same manner, i.e., be settled on the same terms, as the Turkey Creek and the others. DCA has argued that FLWAC's Final Order in the case of Dept. of Community Affairs v. Narbi International Company, Inc. and Lake County, 14 FALR 3223 (1992), controls this case and requires the Crowder development order to be overturned on appeal. Narbi involved development Green Swamp ACSC, albeit in Lake County. Factually, there are many differences between Narbi and this case. The Narbi development order was a rezoning from agricultural with a residential density of up to one unit per five acres to a residential planned unit development (PUD) zoning with a density of one unit per 1.35 acres. Also, Lake County's comprehensive plan had an "urban containment policy," which DCA equated with its non-rule policy preventing "urban sprawl" or "leap-frog development." Thirdly, in Narbi, it was found that a geologic fault existed on the project site which allowed a direct connection from the surficial aquifer to the Floridan Aquifer. Because of the factual differences, Narbi does not control the outcome of Crowder's case. Conditions for Approval. Based on the testimony of its witnesses, DCA has proposed that, notwithstanding its deficiencies, the Crowder project can be approved if its density is lowered to between one unit per ten acres and one unit per 20 acres. The rationale of DCA's witnesses seems to be that the proposed lower density, in and of itself, would cure at least the most significant of the deficiencies. Since the Crowder development order under review was for approval of particular road and drainage plans, the plans would have to be redrawn at the lower density and resubmitted for approval by the County subject to the final order to be entered in this case. It is not possible for the Commission to approve, on condition of lowered density, the plans that were the subject of the development order in this case.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Florida Land and Water Adjudicatory Commission enter a final order rescinding and denying approval for the development order in this case. RECOMMENDED this 10th day of March, 1993, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of March, 1993.

Florida Laws (4) 163.3184380.05380.0551380.07 Florida Administrative Code (5) 28-26.00228-26.00328-27.0079J-9.0039J-9.004
# 4
WYATT S. BISHOP, JR. vs SARASOTA COUNTY PUBLIC HOSPITAL BOARD, D/B/A SARASOTA MEMORIAL HOSPITAL, 91-002704 (1991)
Division of Administrative Hearings, Florida Filed:Sarasota, Florida May 01, 1991 Number: 91-002704 Latest Update: Sep. 30, 1991

The Issue The issue for consideration herein is whether Sarasota County Utilities should be issued a consumptive use permit to draw water from the 14 wells in issue here located in Sarasota County.

Findings Of Fact At all times pertinent to the issues herein, the Respondent, District, was the state agency responsible for themanagement of water resources within its area of geographical jurisdiction. Included therein was the responsibility for the permitting of consumptive water use. The Respondent, Sarasota County, is a political subdivision of the State of Florida and operates a public utilities division which is charged with meeting, among other things, the potable water needs of the residents of the County. Petitioners Wyatt S. Bishop and Joan Jones are both residents of Sarasota County and both draw their potable water from wells which utilize the aquifers pertinent to the wells for which the permit in issue here relate. Mr. Bishop lives approximately 7.5 miles north of the Carlton Reserve, the property on which the wells in issue are located, and Ms. Jones lives approximately 7 miles from the Reserve, but in a different direction. Sarasota County filed an application for a consumptive use permit with the District on January 28, 1987 requesting an average daily withdrawal of 10.71 million gallons per day, (mgd), and a peak monthly withdrawal of 15.55 mgd. This application, assigned number 208836.00, was, over the next three years, amended by the County four separate times. These amendments reflected revised water demand determinations and were submitted to provide additional information requested by the District. The District issued a preliminary staff report and proposed intent on March 26, 1991 reflecting an approved withdrawal in the amount of 7.28 mgd average daily withdrawal and 11.1 mgd peak monthly withdrawal. These figures were revised, however, byan amendment by the District on July 8, 1991, and as amended, authorize 7.303 mgd average daily withdrawal and 9.625 mgd peak monthly withdrawal. The County's application was reviewed by an experienced hydrologist in the District office with extensive permit review experience who utilized, in his evaluation of the permit, the pertinent District rules and policies. By way of background, to more easily understand the circumstances here, Sarasota entered into a contract with Manatee County in 1973 which called for the latter to provide up to 10 mgd of water for a period of 40 years, up to and including the year 2013. However, in 1979, Manatee County's utilities director advised Sarasota County that it, Sarasota County, could not continue to rely on Manatee County's water after the expiration of the current contract, and would, therefore, have to become self sufficient in water. Since the MacArthur tract, now known as the Carlton Reserve, had just recently been identified by, inter alia, the United States Geological Service as a potential long term water source for Sarasota County, after Manatee County advised Sarasota County of its future expectations, Sarasota County and the Manasota Basin Board hired a consulting firm to conduct hydrological testing on the Carlton Reserve. This study concluded that the Reserve had sufficient water resources to satisfy the needs of the unincorporated areas of Sarasota County for an extended time into the future. In 1985, because of its increased water needs and thetime necessary to complete required studies on the utilization of the Myakka River, a surface water resource, Sarasota County concluded that it was suffering a water supply shortage and entered into a supplemental contract with Manatee County to provide 2 million gallons of water per day over a 5 year period which would expire in 1990. Sarasota County had not, however, been idle with regard to the investigation of other water resources. Studies done included not only the Myakka River mentioned above but a reservoir owned by the City of Bradenton, and the Peace River. Nonetheless, it was determined that the Carlton Reserve was the best source available overall, and in 1987, the County filed the application in issue here. The permit was under consideration for approximately 3 1/2 years before the initial decision by the District to grant it. During that time the County experienced a significant deficiency in its water sources and found it necessary, on February 5, 1991, to enter into another contract with Manatee County to supply an addition 5 mgd. Terms of that contract clearly indicate the expectations of both parties that Sarasota County will take reasonable steps to develop its own water resources. It is not as though Sarasota County sat quietly in the interim, however, and allowed the situation to develop. A building moratorium to halt additional construction was proposed and as a result, economic forces in the County indicated a potential loss of jobs to County residents. None of this would be desirable from an economicstandpoint. In the course of the permit application process, 12 test wells were sunk to conduct aquifer pump tests; to assess water quality, amounts and availability, aquifer characteristics and drawdown; and to determine the impact of withdrawal on water quality. Eight of these 12 wells are located on the Carlton Reserve. The other 4 are located on property owned by the MacArthur Foundation which is contiguous to the Carlton Reserve property and from which Sarasota has a right by easement to draw water. The 2 wells yet to be constructed will be on Sarasota County property. Sarasota County currently receives 10 mgd of water under its contract with Manatee County; an additional 5 mgd under the February 5, 1991 contract; 2 mgd from the University wellfield, (with a peak withdrawal rate of 3 mgd); and .9 mgd from the Sorrento wellfield, (with a peak withdrawal rate of 1.1 mgd). This latter source is only producing currently .6 mgd of potable water due to constraints imposed by the water treatment requirements. Taken together, the current Sarasota County supply constitutes 18.6 mgd. The above does not take into account the County's agreement with the City of Sarasota calling for the purchase of up to 2 mgd. Since this source is not reliable, it is not included in the total, and the City is not considered an available water source. In addition, the District and Sarasota County stipulated on July 15, 1991 that within 30 days, the County would apply tophase out routine water production from the Sorrento wellfield, relying on it only in emergency situations with District consent. For this reason, it, too, is not considered an available water supply source. These currently existing sources, with modifications as described, will be the primary sources of potable water provided to 6 major service areas in Sarasota County when the County's water treatment plant and transmission system are complete in 1993. In attempting to define the County's future water requirements, two major criteria were considered. The first was the County's historical water demand, and the second, modifying it, relates to the demand arising as a result of new water users being added to the system as a result of the County's capital improvements and acquisition program. Water resources are not unlimited. Current resources come primarily from Manatee County and there are constraints on this supply as it is made available to Sarasota County. For example, the 10 mgd contract expires in 2013. The 5 mgd contract expires in 2001. Though the latter is subject to renewal, renewal is contingent upon the availability of water supply at that time, and that is not a sure thing. It can, therefore, readily be seen that 15 out of the 18.6 mgd routinely available now comes from Manatee County, and those sources are not perpetual. In addition, it is conceivable that Manatee County may pre-blend the water it delivers to Sarasota County with water of lesser quality, so that the delivered water may exceed the total dissolved solids standard of 500 ppm for potable water. If thewater from Manatee County were reduced to that quality, the University wellfield supply, which currently exceeds standards itself, and which relies on blending with better quality Manatee County water to be potable, would also be removed as a source of potable water to Sarasota County. In order to comply with the provisions of Section 373.171, Florida Statutes, which requires the District to regulate the use of water by apportionment, limitation, or rotating uses, to obtain the most beneficial use of water resources and to protect the public health, safety and welfare, the District analyzed the available water sources and determined that Sarasota County relies upon its 10 mgd supply from Manatee County and the 2 mgd supply from University wellfield to constitute 12 mgd usable water. The 5 mgd from Manatee County would be used only in an emergency situation, and the Sorrento wellfield would be abandoned. Future water demands must be predicted relying in great part upon an historic record of prior water use. Utilizing a statistical procedure called linear regression, a methodology accepted by the District, indicated a water demand figure for the period from 1992 to 1997 based upon six use points extending from 1985 to 1990. These use records reflected a low of 9.733 mgd and a high of 12.808 mgd, the former being in 1985 and the latter in 1990. In addition, the County estimated that its capital improvement program would add between 10 and 12 thousand customers who presently use private wells, whose water use would constitute approximately 2 mgd of additional demand. The County's program toacquire some 42 private franchises now serving customers would add an additional demand of 2 mgd. Taken together, these programs would add in approximately 1.8 mgd per year to the need assessment, and it would therefore appear that by 1997, the County's average daily demand, considering all new users, would be 17.84 mgd. The water to be drawn from the Carlton Reserve is not currently potable and will require some form of treatment to render it so. Sarasota County proposes to use the Electrodialysis Reversal process, (EDR), because, in the County's judgement, it is more efficient than others such as reverse osmosis and ion exchange. Whereas EDR is rated at up to 85% efficient, the others range between 50% to 75% efficient. In that regard, in order to determine the maximum amount of water to be drawn, providing a safety factor for a treatment plant operation that is not working up to peak capacity in computing the water needs, the EDR process was determined to be no more than 80% efficient. Factoring in that efficiency potential, when the 1997 average daily demand is subtracted from the County's projected water capacity, the withdrawal need in 1997 is determined to be 7.303 mgd. However, as a part of its permitting process, the County also calculated its peak month daily demand. This is a figure which represents the maximum amount permitted to be drawn on a daily basis during the peak demand period. This peak period was determined under Section b 3.2 of the District's Basis of Review by taking the 1989 daily flow and using a sliding 31 day calendar to determine the highest historical 31 day flow. Thisresulted in a peak month coefficient of 6.16 which was then multiplied by the 1997 average daily demand of 17.842 mgd which resulted in a peak month daily demand of 20.7 mgd. When existing water supplies are removed and the 80% EDR treatment process factor is applied, the amount of raw water needed from the wellfield in issue on a peak monthly basis would be 9.625 mgd. This peak monthly basis figure is considered because of the intermittent periods of low rainfall and high water demand within the County. Accepting the 1.8 gpd yearly increase; the peak factor of 1.16; and the assumed water supply capacity of 18.6 mgd; Sarasota County's need will exceed its available supplies by 1993. In fact, the County is already experiencing low water pressure in part of its service area during peak demand periods. County experts estimate that without the requested water from the Carlton Tract, Sarasota County can expect to experience dry periods as early as 1993 during the periods of peak water usage, generally between April and June. For the above reason, when the application and its supporting information was reviewed by Mr. Basso, the District hydrologist with extensive experience reviewing more than 300 water use application, he determined that the water supplies requested are necessary to meet the County's certain reasonable demand, and that this meets the criteria set out in Rule 40D - 2.301(1)(a), F.A.C. Turning to the issue of hydrologic and environmental impacts, the District's Basis For Review of Water Permit Applications provides for the use of a "water use model" inevaluating water needs and the appropriateness of a proposed withdrawal. In preparing its submittal to the District, Sarasota County performed certain tests and modeling to derive the statistical and scientific information used in support of its application. Specifically it used the USGS' MODFLOW model utilizing information obtained from the pump tests run on the wells in the pertinent areas. Consistent with the District's rule, the water data and aquifer drawdown were determined by simulated pumping. The tests run also provided the information on water quality in the aquifer and physical characteristics including transmissivity, storage coefficient, specific yield and leakance between aquifers. This data also helped in defining the hydrogeologic framework of the Carlton Reserve. The Carlton Reserve's hydrogeology listed in descending order from the surface, includes a surficial aquifer which varies in depth between 19 and 70 feet across the Reserve; a semi-confining clay unit separating it from the intermediate aquifer; the upper intermediate and lower intermediate aquifer which range in depth from 140 to 180 feet across the Reserve; another confining layer, and the Upper and Lower Floridan aquifers. The hydrology and groundwater modeling expert who constructed the model used in Sarasota County's permit application concluded that the water table drawdown at the Reserve property boundary in the surficial aquifer would be less than .3 of a foot; less than .4 of a foot in the intermediate aquifer; and 2.9 feet in the Upper Florida aquifer. The water to be drawn consistentwith this instant permit, if approved, would come from the Upper Floridan aquifer on the Reserve. The County's experts were conservative in the assumptions used in the groundwater model. It was assumed there would be no lateral water flow into the model area and no recharge. In addition, the model called for all pumps to run simultaneously at a maximum drawdown of 12.65 mgd for 90 days rather than at the requested quantity of 9.625 mgd. Utilization of these assumptions provided a scenario wherein "severe" impacts would be encountered. Based on the testing and the modeling done, expert opinion was that there would be no quantity or quality changes that would adversely effect water resources including ground and surface water. This meets the criteria of Rule 40D-2.301. This opinion was concurred in the District's hydrology expert. Nonetheless, in its proposed approval, the District has imposed special permitting conditions which require the County to monitor, analyze, and report water quality and water table level information to the District on a monthly and annual basis. When it evaluates the information supplied by an applicant relating to ground water monitoring, the District is required to consider certain presumptions set forth in its Basis For Review. For example, the District presumes that if there is a drawdown of more than 1 foot in the surficial aquifer at a wetland, adverse environmental impacts will occur. In the instant case, the County model concluded that the actual drawdown in the surficial aquifer at the Carlton Reserve is less than .6 of onefoot and, therefore, there should be no adverse environmental impact resulting from the withdrawal. Nonetheless, the County has developed several plans designed to provide information on environmental impacts which will continuously monitor such parameters as rainfall and evaporation, wetlands hydroperiod changes and vegetative changes in the wetlands to detect any changes which might be attributed to the water pumping. These plans have been made special conditions to the water use permit, and in the opinion of the County's ecology and hydrology expert, would enable the County to adequately monitor and detect any pertinent changes to the pertinent factors concerned on the Carlton Reserve. If wetland changes are detected, a contingency plan will be in effect which will require an alteration of pumping schedules or other action to minimize any adverse impacts. The District expert in wetlands and wildlife habitat has opined that these measures, with which he is familiar, are adequate to insure that adverse impacts to the wetlands will not occur. This is consistent with the provisions of Rule 40D-2.301(1). As was stated previously, the water to be drawn pursuant to this permit will be drawn from the Upper Floridan aquifer. This water is not potable but is treatable and is the lowest quality water which can be economically used by the County. Water of a lower quality does exist in the Lower Florida aquifer, but it is not economically treatable, and, in addition, use of this Lower Floridan aquifer might cause vertical movement of the poorer quality water into the upper strata. For all practical purposes,then, the lowest quality water available to it will be used by the County and this is consistent with the District's basis for review. Expert testimony indicates that saline water will not be infused into the Upper Floridan aquifer. Salt water intrusion generally occurs when groundwater is brought to a level below sea level. Even at the point of maximum actual drawdown as a result of pumping on the Reserve, the fresh water level will remain at least 20 feet above sea level, and as a result of the difference in water level, no saline water intrusion into the fresh water supply will occur even though salt water intrusion can also occur as a result of upward vertical movement of lower quality water due to withdrawal. The District's hydrologist and reviewing official also concluded that because of the confining layer below the aquifer from which water will be withdrawn, there would not be any significant upward movement of lesser quality water. The District's basis of review also envisions an aquifer pollution if a proposed withdrawal would spread an identified contamination plume. Here no contamination has been identified in the area from which the water will be drawn, and therefore, contamination would not be spread. The Basis for Review also infers there will be adverse impact to off site land if there is a significant drawdown of surface water bodies or if damage to crops or other vegetation can be expected. Here, the water table drawdown at the boundary of the Carlton Reserve is anticipated at less than .3 of one foot and any drawdown further out from the Reserve can be expected tobe even less. As a result, no adverse impact to existing off site land useage is expected. With regard to Rule 40D-2.301(1)(i), relating to an adverse impact on existing legal uses, the District presumes that no adverse impact will exist if the drawdown in the water table is no more than 2 feet at an affected well, or the potentiometric surface at the well is not lowered by more than 5 feet. Here, again applying the County's groundwater modeling demonstrates that the drawdown at its worst, in the Upper Floridan aquifer, would be no more than 2.9 feet at the Reserve boundary and much less at the Petitioners' wells. Both Mr Bishop's and Ms. Jones' wells are approximately 7.5 and 7 miles, respectively, from the closest well on the Reserve property. Ms. Jones' well is drilled into the intermediate aquifer which is above that which the County proposes to use and should not be impacted. Mr. Bishop draws water from the intermediate and surficial aquifers, both of which are above the Upper Florida aquifer identified for use here, and the groundwater modeling would suggest that his well would not be impacted either. Sarasota County's application contains reference to numerous proposals for water conservation measures which it intends to implement or has already implemented. It has adopted ordinances to enforce the District's watering restrictions and is currently implementing a block inverted use rate structure to promote conservation. It has developed programs for use in the schools outlining water conservation efforts and is developing programs topromote the increased use of treated waste water for golf course irrigation. The requirement for a water conservation plan such as is described and envisioned by the County is a condition of the water use permit proposed, and in addition, the County has adopted an Ordinance, (90-38) which modifies its building code to require installation of water conservation devices in new buildings erected in the County. It has developed proposals for conservation measures such as water auditing, meter testing, leak detection, system looping, and pressure reduction, and has selected the EDR process of water purification as the most efficient use of groundwater resources. Petitioner, Bishop, testified to his belief that approval of this permit and the resultant water withdrawal on the Carlton Reserve would necessitate an expansion of the boundaries of the District's Eastern Tampa Bay Water Use Caution Area to a point where his property would be encompassed therein. In support of his position, Mr. Bishop offered a notice to the effect that new ground water withdrawals would not be permitted within a certain "most impacted area" within the caution area. There was, however, no independent evidence from hydrologists, geologists, or other conservationists, or individuals familiar with the water conservation process, to support Mr. Bishop's contention that either the boundaries would be expanded or that withdrawal of the proposed permitted amounts of water from the Carlton Reserve would cause the boundaries to be expanded. By the same token, Mr. Bishop's contention that theproposed withdrawal from the wells here in issue would adversely effect his ability to draw water from his existing well was not supported by any expert testimony or documentary evidence tending to support or confirm his contention. He had no evidence tending to contradict the County's and District's experts, all of whom indicated there would be no adverse impact on the environment or water resources as a result of the instant permit. Similarly, neither Petitioner offered any evidence of a demonstrative nature that would draw any connection between the proposed permitted withdrawals and potential salt water intrusion and water level drawdown in their wells. The County introduced construction permits issued by its own health department covering 8 of the 12 wells which have been drilled on the Carlton Reserve as test wells. These wells were clearly sunk pursuant to an agreement between the District and the County's public health unit which delegates authority for water well construction permitting to the County. Taken together the documentation indicates that these 12 wells on the Reserve were installed and permitted pursuant to and consistent with appropriate permitting processes, and the testimony of Mr. Bassarab, the County's expert who oversaw the installation of the wells, reflects they are appropriately grouted and sealed. Therefore, there will be no mixing of lower quality water from the lower portion of the Floridan aquifer with the better quality water from the upper portion of that aquifer. The County's evidence clearly refutes the allegation by Mr. Bishop that the 12 test wells currently existingon the Carlton Reserve were neither permitted nor inspected as required by the District. County Commissioner Hill, who testified on behalf of the Petitioners, indicated that the wells applied for here are unnecessary and an inappropriate expenditure of County funds. She claimed there are other valid sources of water available to the County, including that extracted from excavated shell pits and seawater from the Gulf of Mexico which could be treated and desalinated. The Commissioner's comments as to alternate sources are not specifically rebutted. However, she is neither an expert in hydrology or hydrogeology, and her testimony is not persuasive. While other water sources may exist, the better evidence clearly indicates that those sources are not sufficient to meet the County's needs or are otherwise inappropriate for use by the County in sufficient quantity to satisfy those needs.

Recommendation Based on the foregoing Findings of fact and Conclusions of Law, it is, therefore: RECOMMENDED that consumptive water use permit No. 208836.00, providing for authorized quantities as outlined in the intent to issue, subject to conditions contained therein, be issued to Sarasota County. RECOMMENDED in Tallahassee, Florida this 5th day of September, 1991. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1991. APPENDIX TO RECOMMENDED ORDER The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONERS: Rejected as not supported by the evidence. Accepted. Accepted. - 8. Resolved against the Petitioners on the basis information presented by Respondents. 9.- 13. Accepted and incorporated herein. 14. - 16. Accepted and incorporated herein. Accepted and incorporated herein. & 19. Accepted and incorporated herein. 20. - 23. Accepted. Accepted but not dispositive of any issue. Accepted. & 27. Noted as citation of authority. Rejected. & 30. Accepted as restatements of evidence but not as Findings of Fact. 31. Irrelevant. 32. Rejected 33. & 34. Not a error is, in fact, it is such. 35. - 38. Irrelevant. 39. - 43. Accepted. 44. Accepted. 45. Rejected. 46. Accepted and incorporated herein. 47. & 48. Rejected as a mere citation of testimony. 49. Not understandable. Not a Finding of Fact. 50. Accepted. 51. Evidence is acceptable. 52. Not sufficiently specific to rule upon. 53. Not proven. 54. Not specific. 55. & 56. Rejected. FOR THE RESPONDENTS: 1. - 4. Accepted and incorporated herein. 5. & 6. Accepted and incorporated herein. 7. & 8. Accepted and incorporated herein. 9. - 14. Accepted and incorporated herein. 15. - 17. Accepted and incorporated herein. 18. - 21. Accepted and incorporated herein. 22. & 23. Accepted and incorporated herein. Accepted. - 27. Accepted and incorporated herein. 28. & 29. Accepted and incorporated herein. 30. - 32. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted. - 37. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. - 43. Accepted and incorporated herein. Accepted. Accepted and incorporated herein, - 48. Accepted and incorporated herein. Accepted - not a Finding of Fact. Accepted and incorporated in substance herein. Not correct as stated. Sarasota County will not be withdrawing saline water from the upper Floridan aquifer. The remaining discussion is accepted. Accepted and utilized. & 54. Accepted. Accepted and incorporated herein. Accepted. - 59. Accepted and incorporated herein. 60. Accepted. 61 - 63. Not Findings of Fact but comments on the evidence. Accepted and incorporated herein. & 66. Not Findings of Fact. COPIES FURNISHED: Wyatt S. Bishop, Jr. 5153 Tucumcari Trail Sarasota, Florida 34241 Joan Jones 719 East Baffin Road Venice, Florida 34293 William A. Dooley, Esquire Nelson, Hesse, Cyril, Smith, Widman, Herb, Causey & Dooley 2070 Ringling Blvd. Sarasota, Florida 34237 Cathy Sellers, Esquire Steel, Hector & Davis 215 S. Monroe Street Tallahassee, Florida 32301-1804 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Edward B. Helvenston, Esquire Vivian Arenas, Esquire SWFWMD 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (4) 120.57373.171373.2237.28 Florida Administrative Code (2) 40D-2.04140D-2.301
# 5
MARION COUNTY, FLORIDA vs C. RAY GREENE, III; ANGUS S. HASTINGS; AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 06-002464 (2006)
Division of Administrative Hearings, Florida Filed:Ocala, Florida Jul. 14, 2006 Number: 06-002464 Latest Update: Apr. 13, 2009

The Issue The issue in this case is whether the portion of Consumptive Use Permit (CUP) Application Number 97106 seeking an allocation of 499,000 gallons per day (gpd) of groundwater for commercial/industrial uses (supply bulk water to bottling plants) meets the conditions for issuance as established in Section 373.223, Florida Statutes, Florida Administrative Code Rule 40C-2.301, and the Applicant’s Handbook, Consumptive Uses of Water.1 The County does not oppose or contest the portion of the CUP application authorizing use of 6.0 million gpd of surface water for limerock mining operations.

Findings Of Fact The Parties The County is a political subdivision of the State of Florida. The County operates a water supply utility that supplies water for a variety of uses, including providing untreated water, in bulk, for bottling purposes. The County is currently engaged in a long-range planning effort designed to assess water supply demands and sources to supply those demands in the County over the next 50 years. The County also has completed a study of the two major springs in the County (Rainbow Springs and Silver Springs), and the County’s Board of County Commissioners is in the process of enacting certain recommendations contained in the study. The well for the proposed CUP allocation is located on approximately 160 acres in northern Marion County. Hastings and Greene's father owned the property from 1978 until the latter's death. In 1993, the latter's interest was transferred to Greene and two brothers, who now hold title to the property along with Hastings. The District is a special taxing district created by Chapter 373, Florida Statutes, and is charged with the duty to prevent harm to water resources of the District, and to administer and enforce Chapter 373, Florida Statutes, and the rules promulgated thereunder. The District has implemented Chapter 373, Florida Statutes, in part, through the adoption of Rule Chapters 40C-2 and 40C-20, and the Applicant’s Handbook, Consumptive Uses of Water. Historic Uses of Water on the Mine Site Since the 1980s, the property where the proposed withdrawals will occur has been used for mining of limerock and has been known as the “Black Sink Mine." A ten-inch diameter well has been located on the Black Sink Mine property for 35 years. The well was originally used to provide water to augment water levels in canals in and around the Black Sink Mine property. Later the well was used to irrigate watermelons grown on the property before the mining operation began. The limerock mining operation at Black Sink Mine uses approximately 6 million gpd of surface water. The mine pit at the site is divided by an earthen berm that separates a larger, previously mined area from a smaller area where active mining is occurring. Surface water is pumped from the actively mined portion of the pit to the larger, previously mined portion of the pit, to enable mining of the limerock material to be conducted at levels below the water table. Dewatering is necessary in order to remove the limerock. A majority of the property is mined to a depth of 55 feet below land surface. The limerock material extracted from the site is transported by trucks from the site, approximately 100 trucks per day, to various sites across North Florida. The Need for the Proposed Use of Groundwater If mining of limerock continues at the current pace, the limerock material at the Black Sink Mine will be exhausted within a year. Recognizing that the productive use of the property for limerock mining was nearing an end, Greene and Hastings began exploring other potential uses for the property, including use of the existing well on the property for production of bottled water. To explore the feasibility of producing water for bottling from the existing well, in 2004 Greene and Hastings engaged an engineering firm with expertise in water resources to conduct a hydrogeologic study of the mine property and well. The results of the study, showing water of sufficient quality and quantity for production of bottled water, motivated Greene and Hastings to submit the CUP application which was the subject of the hearing. The study also determined that water withdrawn from the well could be marketed as spring water. Greene and Hastings also determined through market research that the demand for bottled water has increased at the rate of ten percent per year for the last 4-5 years and that Florida bottlers were interested in purchasing water from the well on the mine site in bulk for bottling. In order to provide reasonable assurance that the water use proposed by Greene and Hastings is in such quantity as is necessary for economic and efficient utilization, Greene and Hastings must show that the amount to be used is consistent with what would typically be required for the activity being supplied; that the water will be used efficiently with loss or waste minimized; and that there is a demonstrated need for the water proposed for allocation. To demonstrate a need for the 499,000 gpd of groundwater requested in the application for an allocation of 499,000 gpd of groundwater, Greene and Hastings provided letters from two businesses engaged in bottling of water stating an intent to purchase specific quantities of water produced from the Greene and Hastings well should the CUP be granted. One of the letters of intent came from a bottler in Jacksonville, Florida, stating its intention to initially purchase 100,000 gpd of Greene and Hastings’s water. The other was from a bottler in Stuart, Florida, dated January 9, 2006, stating its intention to purchase 125,000 gpd of water from Greene and Hastings within “the next 12-24 months.” Based on these letters Greene and Hastings initially requested an allocation of 200,000 gpd of groundwater for the first year of the permit. Prior to completion of the CUP application, Greene and Hastings learned that because the Stuart bottler’s facility was located outside the geographic boundaries of the District, to transport water from the Black Sink Mine to the Stuart facility would require additional data and information related to inter- district transfers of groundwater. Greene and Hastings elected to reduce the requested allocation for the first year of the permit to 100,000 gpd, relying on the letter from the Jacksonville bottler. Based on the current market demand for bottled water, and based on the fact that there are other bottlers of water within the boundaries of the District purchasing water for bottling, it is reasonable to conclude that Greene and Hastings can sell 499,000 gpd of water from the well on the Black Sink Mine property by the end of the fifth year of the proposed CUP. These facts support the conclusion that there is a need for the amount of water requested by Greene and Hastings. In addition, the permit is conditioned to require a compliance review at five-year intervals during the term of the permit. Should Greene and Hastings not be successful in selling the full 499,000 gpd allocated by the fifth year of the permit, the District has the ability as part of the five-year compliance review to modify the permit to reduce the allocation based on the amount of water actually used for bottled water. Efficiency of the Proposed Use of Water The production of water in bulk for shipment to a bottler is a highly efficient use of water. There is very little if any water lost in the withdrawal and loading of the water; almost all the water goes to the end product. The evidence establishes that the use proposed by Greene and Hastings is an efficient use of water. Potential Impacts from the Proposed Groundwater Allocation The source of the groundwater proposed for use by Greene and Hastings is the Floridan aquifer. Because there is no confining layer in the vicinity of the Black Sink Mine that would retard movement of water between the Upper Floridan aquifer and the surficial aquifer, both the Upper Floridan aquifer and the surficial aquifer essentially behave as one unit. Thus, any drawdown in the surficial aquifer associated with groundwater withdrawals at this location will be the same as the related drawdown in the Upper Floridan aquifer as a result of groundwater withdrawals. The Floridan aquifer is capable of producing the amount of groundwater requested by Greene and Hastings in the application. To assess the level of drawdown expected to occur in both the Floridan aquifer and the surficial aquifer as a consequence of the proposed groundwater withdrawals, Greene and Hastings engaged a consultant, Andreyev Engineering, Inc., to run a groundwater model to simulate the proposed withdrawal and predict the anticipated drawdown. The groundwater model selected for use for this application was the North Central Florida Regional Groundwater Flow Model, a model developed for the District by the University of Florida for use in Marion County and surrounding areas. This model is an accepted and reliable tool for predicting aquifer drawdown associated with groundwater withdrawals at the location of the withdrawals proposed in this application and is used extensively by the District in its CUP program. To simulate the drawdown associated with the withdrawal of 499,000 gpd from the Florida aquifer, Greene and Hastings’s consultant inserted a pumping well in the model grid where the Black Sink Mine is located. The model then simulated pumping from the well at 499,000 gpd. The model results are graphically depicted on maps showing drawdown contours overlain on the Black Sink Mine Site, illustrating the level of drawdown in the aquifer and the distance the level of drawdown extends out from the well site. The model predicts a drawdown of 0.03 feet in the Floridan and surficial aquifers in the immediate vicinity of the well on the Black Sink Mine property, and a drawdown of 0.02 feet in the Floridan and surficial aquifers extending out to a distance of approximately 5,000 feet from the well, less than 1/3 of an inch of drawdown. The model results represent a reasonable estimation of the drawdown that will occur as a consequence of withdrawal of 499,000 gpd of groundwater at the Black Sink Mine as proposed in the application. The impact of the 0.02-0.03 foot drawdown predicted by the model was variously characterized by the experts who testified at the final hearing as “not practically measurable,” an “insignificant impact,” “very small,” or “de minimus.” The use of water proposed by Greene and Hastings will not cause significant saline water intrusion, nor will it further aggravate any existing saline water intrusion problems. The use of water proposed by Greene and Hastings will not induce significant saline water intrusion to such an extent as to be inconsistent with the public interest. Because the predicted drawdown is so small, it will not interfere with any existing legal uses of water. Neither will the predicted drawdown cause serious harm to the quality of the source of the water proposed for use by Greene and Hastings. With regard to the issue of interference with existing legal users, the County argued that the District should have considered whether there is sufficient groundwater available to meet all projected needs for water in the County during the 20- year term of the permit, as well as the additional cost County citizens will need to bear to secure alternative water supplies as a result of any future shortfalls in available groundwater. The County projects, based on planning estimates, that use of groundwater to supply all anticipated uses of water in the County will be limited within 20-30 years from the present. Such “limits” would not become an issue until after the Greene and Hastings permit expires. Thereafter, water users in the County will have to rely on alternative water sources, conservation, reuse of reclaimed water, and surface water. The anticipated growth in demand in the County’s planning estimates includes anticipated growth in the commercial/industrial category of uses. The County’s estimated limits on groundwater use will occur whether or not the CUP requested by Greene and Hastings is approved. The District does not base its permitting decisions on a pending CUP application on the possibility that the source of water may become limited at some future time for water uses not presently permitted, provided the application meets all permitting criteria. The District allocates water for recognized beneficial uses of water, such as commercial/industrial uses, as long as the water is available and the application meets District criteria. The District allocates water as long as an allocation does not cause harm to the resource. Based on these facts, the proposed use of water by Greene and Hastings will not interfere with any existing legal use of water. No Evidence of Economic or Environmental Harm Because the predicted drawdown associated with the proposed use of water is so small, and because no impacts are anticipated on any surrounding properties or water uses, Greene and Hastings have provided reasonable assurance that any economic harm caused by the proposed use has been reduced to an acceptable amount. For purposes of determining whether an applicant has provided reasonable assurance that any environmental harm caused by a proposed use of water is reduced to an acceptable amount, the District examines modeling results showing the level of drawdown predicted for the use and also examines the resources in and around the site of a withdrawal to determine the likely impact of the drawdown predicted for the withdrawal on those resources. The District’s environmental scientists examined the Black Sink Mine site and the surrounding landscape and determined that, based on the characteristics of the landscape in and around the site of the proposed withdrawal and based on the negligible drawdown impact predicted for the proposed water use in both the Floridan and surficial aquifers, there will be no environmental harm resulting from the allocation of groundwater contained in the CUP. The use of water proposed by Greene and Hastings will not cause damage to crops, wetlands, or other types of vegetation. The use of water proposed by Greene and Hastings will not cause the water table to be lowered so that stages or vegetation will be adversely and significantly affected on lands other than those owned, leased, or otherwise controlled by Greene and Hastings. The CUP will not use water that the District has reserved pursuant to Section 373.223(3), Florida Statutes, and Rule 40C-2.301(4). No Impact on Established Minimum Flows or Levels No minimum surface or groundwater levels or surface water flows have been established by the District pursuant to Rule Chapter 40C-8 for any of the water bodies in Marion County that may be affected by the proposed water use. The closest water body for which the District has established a minimum flow is the St. Johns River at the State Road 44 bridge located more than 50 miles from the Black Sink Mine property. The closest water body for which the District has established a minimum level is Star Lake in Northwest Putnam County, more than nine miles from the mine site. Because of the distance of these water bodies from the withdrawal site and because of the negligible drawdown expected to be caused by the proposed use of water, the use will not cause an established minimum flow or level to be exceeded during the term of the permit. Other Reasonable-Beneficial Use Considerations All available conservation measures that are economically, environmentally, and technically feasible are proposed for implementation in the application by Greene and Hastings for the uses proposed by them. Greene and Hastings submitted to the District, as part of the application, a conservation plan that complies with the requirements of A.H. Section 10.3(e). Reclaimed water, as defined in the District’s rules, is not currently available to be used in place of the water proposed for use by Greene and Hastings in the application. The use of water proposed by Greene and Hastings in the application will not cause or contribute to a violation of water quality standards in receiving waters of the state. The use of water proposed by Greene and Hastings in the application will not cause or contribute to flood damage. The Use is Consistent With the Public Interest With regard to the determination of whether reasonable assurance was provided that the proposed use is consistent with the public interest, the County contends that: 1) Greene and Hastings must show that any necessary approvals required by the County’s Comprehensive Plan and/or its LDRs for use of the site for producing bottled water have been obtained; 2) that the District did not properly consider the effect of existence of lawn watering restrictions affecting citizens in the County in evaluating the application; and 3) that the District should have considered the amount of money the applicant may stand to gain from the use of the water requested in the application. In examining whether an application is consistent with the public interest, the District considers whether a particular use of water is going to be beneficial or detrimental to the people of the area and to water resources within the state. In this inquiry, the District considers whether the use of water is efficient, whether there is a need for the water requested, and whether the use is for a legitimate purpose; and the inquiry focuses on the impact of the use on water resources and existing legal users. Sale of water for bottling for human consumption is recognized by the District as a legitimate, beneficial economic enterprise. Use of water for human consumption is among the highest and best uses permitted by the District. For reasons outlined above in the Recommended Order, there are no detrimental impacts that will result from this use of water. The District does not consider whether local government approvals have been obtained prior to issuance of a CUP for purposes of determining whether the application is consistent with the public interest. Neither does the District consider impacts related to local roads from trucks transporting the water or other impacts not related to water resources. No such requirements are included in the District’s adopted permitting criteria. There are no water shortage orders in effect in the District at present. In evaluating a CUP application, the District considers whether its permitting criteria will be met during periods of normal weather as well as during periods of drought. Withdrawals authorized in CUPs can be restricted by order of the District during periods of water shortage, such as droughts. Thus, the possibility of a water shortage order being entered in the County in the future, or the fact that such orders may have been in effect there in the past, does not mean the application is not consistent with the public interest. The District critically examines the efficiency of all water uses for purposes of enacting its regulatory requirements regarding CUPs and in evaluating CUP applications. The District has adopted restrictions on landscape irrigation (which apply to all such users throughout the District’s jurisdiction, not just in Marion County) limiting landscape irrigation to no more than two days per week. The limitations on landscape irrigation exist because this type of use has been determined to be a highly inefficient, wasteful use of water without such restrictions. By contrast, the use of water proposed by Greene and Hastings is a highly efficient use of water, resulting in little or no loss or waste of water. The District does not consider the level of financial gain or benefit an applicant will derive from a permitted use of water for purposes of determining whether the proposed use is consistent with the public interest. Most, if not all permitted users of water derive some level of economic benefit from the water they use, and the District’s rule criteria do not provide standards for evaluating such gain or that otherwise limit the amount of such gain. For the foregoing reasons, the Applicant has provided reasonable assurance that the use of water proposed in the application is consistent with the public interest. Groundwater is the Lowest Quality Source for this Use The County contends that groundwater is not the lowest quality source of water available for the use proposed by Greene and Hastings, in that surface water from the mine pit on the site could be treated and used for bottling in place of groundwater. From the testimony, it is clear that Greene and Hastings’s ability to market water for bottling from the Black Sink Mine is dependent on such water being capable of being labeled as spring water, and on such water being delivered without having gone through any treatment processes. The testimony also establishes that because of the connection between the surficial aquifer and the Upper Floridan aquifer at the site, using surface water instead of groundwater to supply the proposed use would result in little if any reduction in impacts to the Floridan aquifer. More importantly, because the application proposes use of water for direct human consumption, the District’s rules do not require use of a lower quality source of water. For the foregoing reasons, groundwater is the lowest quality source of water suitable for use for bottled water for human consumption. The District’s Noticing Was Adequate and Appropriate The District provided notice of its receipt of the Greene and Hastings CUP application by publishing notice in the Ocala Star-Banner, a newspaper of general circulation in Marion County, on January 25, 2005, with an amended notice being published on February 16, 2005, and also by letters to the County dated January 20, 2005, and February 10, 2005. In each notice, the location of the proposed use was identified by section, township, and range. The County responded to the notices by sending a letter of objection to the application dated February 14, 2005. Thus, the County received sufficient information regarding the location of the proposed use to enable it to prepare and file a letter of objection to the application, and suffered no prejudice as a consequence of the notice. The District provided personal notice of its intent to issue a CUP to Greene and Hastings by letter dated April 5, 2006. In this notice, the location of the proposed use was identified by section, township, and range. The County responded by filing petitions that have resulted in this proceeding. Thus, the County received sufficient notice of the location of the use addressed in the District’s intent to issue to enable it to initiate administrative proceedings regarding the permit, and suffered no prejudice as a consequence of the notice.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the District enter an order granting CUP No. 97106 to Greene and Hastings with the conditions recommended in the District’s Technical Staff Report. DONE AND ENTERED this 9th day of January, 2007, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th of January, 2007.

Florida Laws (3) 120.57373.223373.229
# 6
BOBBY C. BILLIE AND SHANNON LARSEN vs ST. JOHNS RIVER WATER MANAGEMENT DISTRICT AND HINES INTERESTS LIMITED PARTNERSHIP, 00-002230 (2000)
Division of Administrative Hearings, Florida Filed:St. Augustine, Florida May 26, 2000 Number: 00-002230 Latest Update: Jul. 12, 2004

The Issue The issues to be resolved in this proceedings concern whether Environmental Resource Permit (ERP) No. 4-109-0216-ERP, should be modified to allow construction and operation of a surface water management system (project) related to the construction and operation of single-family homes on "Marshall Creek" (Parcel D) in a manner consistent with the standards for issuance of an ERP in accordance with Rules 40C-4.301 and 40C-4.302, Florida Administrative Code.

Findings Of Fact The Project The project is a 29.9-acre residential development and associated stormwater system in a wetland mitigation area known as "Parcel D." It lies within the much larger Marshall Creek DRI in St. Johns County, Florida, bounded on the northeast by Marshall Creek, on the south and southeast by a previously permitted golf course holes sixteen and seventeen, and on the north by the "Loop Road." The project consists of thirty residential lots of approximately one-half acre in size; a short segment of Loop Road to access Parcel D; an internal road system; expansion of previously permitted Pond N, a wet detention stormwater management pond lying north of the Loop Road and wetland mitigation areas. Approximately 1.15 acres of wetlands are located on the Parcel D site. The project plan calls for filling 0.63 acres of the wetlands for purposes of constructing a road and residential lots for Parcel D. Part of that 0.63-acre impact area, 0.11 acres, is comprised of a 760-foot-long, narrow drainageway, with 0.52 acres of adjacent wetland. Downstream of the fill area, 0.52 acres of higher quality wetland is to be preserved. Hines proposes to preserve 4.5 acres of existing wetland and 2.49 acres of upland, as well as to create .82 acres of forested wetland as mitigation for the proposed impact of the project. Additionally, as part of the project, Hines will implement a nutrient and pesticide management plan. The only pesticides to be used at the project will be approved by the Department of Agriculture for use with soil types prevailing at the site and only pesticides approved by the Environmental Protection Agency may be used on the site. All pesticides to be used on the project site must be selected to minimize impacts to ground and surface water, including having a maximum 70-day half-life. Stormwater Management System The majority of surface runoff from Parcel D will be diverted to a stormwater collection system and thence through drainage pipes and a swale into Phase I of Pond N. After treatment in Pond N, the water will discharge to an upland area adjacent to wetlands associated with Marshall Creek and then flow into Marshall Creek. The system will discharge to Marshall Creek. In addition to the area served by Pond N, a portion of lots fourteen though twenty drain through a vegetated, natural buffer zone and ultimately through the soil into Marshall Creek. Water quality treatment for that stormwater runoff will be achieved by percolating water into the ground and allowing natural soil treatment. The fifty-foot, vegetated, natural buffer is adequate to treat the stormwater runoff to water quality standards for Lots 14, 15 and 20. Lots 16, 17, 18 and 19, will have only a twenty-five foot buffer, so additional measures must be adopted for those lots to require either that the owners of them direct all runoff from the roofs and driveways of houses to be constructed on those lots to the collection system for Pond N or placement of an additional twenty-five foot barrier of xeriscape plants, with all non- vegetated areas being mulched, with no pesticide or fertilizer use. An additional mandatory permit condition, specifying that either of these measures must be employed for Lots 16, 17, 18 and 19, is necessary to ensure that water quality standards will be met. Pond N is a wet detention-type stormwater pond. Wet detention systems function similarly to natural lakes and are permanently wet, with a depth of six to twelve feet. When stormwater enters a wet detention pond it mixes with existing water and physical, chemical and biological processes work to remove the pollutants from the stormwater. Pond N is designed for a twenty-five year, twenty-four- hour storm event (design storm). The pre-development peak rate of discharge from the Pond N drainage area for the design storm event is forty cubic feet per second. The post-development peak rate of discharge for the design storm event will be approximately twenty-eight cubic feet per second. The discharge rate for the less severe, "mean annual storm" would be approximately eleven cubic feet per second, pre-development peak rate and the post-development peak rate of discharge would be approximately five cubic feet per second. Consequently, the post-development peak rate of discharge does not exceed the pre- development peak rate of discharge. Pond N is designed to meet the engineering requirements of Rule 40C-42.026(4), Florida Administrative Code. Because the pond is not designed with a littoral zone, the permanent pool volume has been increased by fifty-percent. Additionally, because Pond N discharges to the Class II waters of Marshall Creek, an additional fifty-percent of treatment volume is included in the pond design. The system design addresses surface water velocity and erosion issues through incorporation of best management practices promulgated by the District to prevent erosion and sedimentation, including; designing side slopes of 4:1; siding and seeding disturbed areas to stabilize soil; and the use of riprap at the outfall from Pond N. During construction, short- term water quality impacts will be addressed through installation of silt fences and hay bales. The majority of the eighteen-acre drainage basin which flows into the Parcel D wetland lies to the south and southwest of Parcel D. In accordance with the prior permit, water from those off-site acres will be intercepted and routed to stormwater ponds serving golf course holes sixteen and seventeen. The system design will prevent adverse impacts to the hydroperiod of remaining on-site and off-site wetlands. The remaining wetlands will be hydrated through groundwater flow. Surface waters will continue to flow to the wetlands adjacent to lots fourteen through twenty because drainage from those lots will be directed across a vegetated, natural buffer to those wetlands. There is no diversion of water from the natural drainage basin, because Pond N discharges to a wetland adjacent to Marshall Creek, slightly upstream from the current discharge point for the wetland which is to be impacted. This ensures that Marshall Creek will continue to receive that fresh-water source. An underground "PVC cut-off wall" will be installed around Pond N to ensure that the pond will not draw down the water table below the wetlands near the pond. Pond N has been designed to treat stormwater prior to discharge, in part to remove turbidity and sedimentation. This means that discharge from the pond will not carry sediment and that the system will not result in shoaling. There will be no septic tanks in the project. The system is a gravity flow system with no mechanical or moving parts. It will be constructed in accordance with standard industry materials readily available and there will be nothing extraordinary about its design or operation. The system is capable of being effectively operated and maintained and the owner of the system will be the Marshall Creek Community Development District (CDD). Water Quality Water entering Pond N will have a residence time of approximately 200 days or about fifteen times higher than the design criteria listed in the below-cited rule. During that time, the treatment and removal process described herein will occur, removing most of the pollutants. Discharge from the pond will enter Marshall Creek, a Class II water body. The discharges must therefore meet Class II water quality numerical and anti-degradation standards. The design for the pond complies with the design criteria for wet detention systems listed in Rule 40C-42.026(4), Florida Administrative Code. In addition to meeting applicable design criteria, the potential discharge will meet water quality standards. The pond will have low levels of nitrogen and phosphorous resulting in low algae production in the pond. The long residence time of the water in the pond will provide an adequate amount of time for pesticides to volatilize or degrade, minimizing the potential for pesticide discharge. Due to the clear characteristics of the water column, neither thermal stratification nor chemical stratification are expected. Periodically, fecal coliform and total coliform levels are exceeded under current, pre-development conditions. These are common natural background conditions. Because the detention time in the pond will be an average of 200 days, and because the life span of fecal coliform bacteria is approximately seven to fourteen days the levels for coliforms in the pond will be very low. Discharges from the pond will enhance water quality of the Class II receiving waters because the levels of fecal coliform and total coliform will be reduced. The discharge will be characterized by approximately 100 micrograms per liter total nitrogen, compared with a background of 250 micrograms per liter presently existing in the receiving waters of Marshall Creek. The discharge will contain approximately three micrograms per liter of phosphorous, compared with sixty-three micrograms per liter presently existing in Marshall Creek. Total suspended solids in the discharge will be less than one-milligram per liter compared with seventy-two milligrams per liter in the present waters of Marshall Creek. Biochemical oxygen demand will be approximately a 0.3 level in the discharge, compared with a level of 2.4 in Marshall Creek. Consequently, the water quality discharging from the pond will be of better quality than the water in Marshall Creek or the water discharging from the wetland today. The pollutant loading in the discharge from the stormwater management system will have water quality values several times lower than pre-development discharges from the same site. Comparison of pre-development and post-development mass loadings of pollutants demonstrates that post-development discharges will be substantially lower than pre-development discharges. Currently, Marshall Creek periodically does not meet Class II water quality standards for dissolved oxygen. Construction and operation of the project will improve water quality in the creek concerning dissolved oxygen values because discharges from Pond N will be subjected to additional aeration. This results from design features such as discharge from the surface of the system, where the highest level of dissolved oxygen exists, and the discharge water draining through an orifice and then free falling to a stormwater structure, providing additional aeration. Discharges from the system will maintain existing uses of the Class II waters of Marshall Creek because there will be no degradation of water quality. Discharges will not cause new violations or contribute to existing violations because the discharge from the system will contain less pollutant loading for coliform and will be at a higher quality or value for dissolved oxygen. Discharges from the system as to water quality will not adversely affect marine fisheries or marine productivity because the water will be clear so there will be no potential for thermal stratification; the post-development discharges will remain freshwater so there will be no change to the salinity regime; and the gradual pre-development discharges will be replicated in post-development discharges. Several factors minimize potential for discharge of pesticide related pollutants: (1) only EPA-approved pesticides can be used; (2) only pesticides approved for site-specific soils can be used; (3) pesticides must be selected so as to minimize impacts on surface and groundwater; (4) pesticides must have a maximum half-life of 70 days; and (5) the system design will maximize such pollutant removal. Archaeological Resources The applicant conducted an archaeological resource assessment of the project and area. This was intended to locate and define the boundaries of any historical or archaeological sites and to assess any site, if such exists, as to its potential eligibility for listing in the National Register of Historic Places (National Register). Only a portion of one archaeological site was located on the project tract. Site 8SJ3473, according to witness Anne Stokes, an expert in the field of archaeological assessment, contains trace artifacts dating to the so-called "Orange Period," a time horizon for human archaeological pre-history in Florida dating to approximately 2,300 B.C. The site may have been only a small campsite, however, since only five pottery fragments and two chert flakes, residuals from tool-making were found. Moreover, there is little possibility that the site would add to knowledge concerning the Orange Period or pre-history because it is a very common type of site for northeast Florida and is not an extensive village site. There are likely other campsites around and very few artifacts were found. No artifacts were found which would associate the site with historic events or persons. The applicant provided the findings of its cultural resource assessment, made by Dr. Stokes, to the Florida Division of Historical Resources. That agency is charged with the responsibility of reviewing cultural resource assessments to determine if significant historic or archaeological resources will be impacted. The division reviewed the survey techniques used by Dr. Stokes, including shovel testing, sub-surface testing and pedestrian walk-over and investigation. The division determined that the site in question is not of a significant historical or archaeological nature as a resource because it does not meet any of the four criteria for inclusion in the National Register.1 Thus the referenced agency determined that the site in question is not a significant historical or archaeological resource and that construction may proceed in that area without further investigation, insofar as its regulatory jurisdiction is concerned. Wetlands The wetlands to be impacted by the project consist of a 1,000 foot drainage-way made up of a 0.11 acre open-water channel, approximately four feet wide, and an adjacent vegetated wetland area of approximately 0.52 acres containing fewer than 30 trees. The open-water channel is intermittent in that it flows during periods of heavy rainfall and recedes to a series of small, standing pools of water during drier periods. The Parcel D wetland is hydrologically connected to Marshall Creek, although its ephemeral nature means that the connection does not always flow. The wetland at times consists only of isolated pools that do not connect it to Marshall Creek. Although it provides detrital material export, that function is negligible because the productivity of the adjacent marsh is so much greater than that of the wetland with its very small drainage area. Because of the intermittent flow in the wetland, base flow maintenance and nursery habitat functions are not attributed to the wetland. The Parcel D wetland is not unique. The predominant tree species and the small amount of vegetated wetland are water oak and swamp bay. Faunal utilization of the wetland is negligible. The wetland drainage-way functions like a ditch because it lacks the typical characteristics of a creek, such as a swampy, hardwood floodplain headwater system that channelizes and contains adjacent hardwood floodplains. The location of the wetland is an area designated by the St. Johns County comprehensive plan as a development parcel. The Florida Natural Areas Inventories maps indicate that the wetland is not within any unique wildlife or vegetative habitats. The wetland is to be impacted as a freshwater system and is not located in a lagoon or estuary. It contains no vegetation that is consistent with a saltwater wetland. The retaining wall at the end of the impact area is located 1.7 feet above the mean high water line. Wetland Impacts The proposed 0.63 acre wetland impact area will run approximately 760 linear feet from the existing trail road to the proposed retaining wall. If the wetland were preserved, development would surround the wetland, adversely affecting its long-term functions. Mitigation of the wetland functions is proposed, which will provide greater long-term ecological value than the wetland to be adversely affected. The wetland to be impacted does not provide a unique or special wetland function or good habitat source for fish or wildlife. The wetland does not provide the thick cover that would make it valuable as Black Bear habitat and is so narrow and ephemeral that it would not provide good habitat for aquatic-dependent and wetland-dependent species. Its does not, for instance, provide good habitat for woodstorks due to the lack of a fish population and its closed- in tree canopy. Minnow sized fish (Gambusia) and crabs were seen in portions of the wetland, but those areas are downstream of the proposed area of impact. Mitigation Mitigation is offered as compensation for any wetland impacts as part of an overall mitigation plan for the Marshall Creek DRI. The overall mitigation plan is described in the development order, the mitigation offered for the subject permit and mitigation required by prior permits. A total of 27 acres of the more than 287 acres of wetlands in the total 1,300-acre DRI tract are anticipated to be impacted by the DRI. Approximately 14.5 acres of impacted area out of that 27 acres has already been previously authorized by prior permits. The overall mitigation plan for the DRI as a whole will preserve all of the remaining wetlands in the DRI after development occurs. Approximately one-half of that preserved area already has been committed to preservation as a condition of prior permits not at issue in this case. Also, as part of prior permitting, wetland creation areas have been required, as well as preserved upland buffers which further protect the preserved wetlands. The mitigation area for the project lies within the Tolomato River Basin. The development order governing the total DRI requires that 66 acres of uplands must also be preserved adjacent to preserved wetlands. The overall mitigation plan for the DRI preserves or enhances approximately 260 acres of wetlands; preserves a minimum of 66 acres of uplands and creates enhancement or restores additional wetlands to offset wetland impacts. The preserved wetlands and uplands constitute the majority of Marshall Creek, and Stokes Creek which are tributaries of the Tolomato River Basin, a designated Outstanding Florida Water (OFW). Preservation of these areas prevents them from being timbered and ensures that they will not be developed in the future. The overall DRI mitigation plan provides regional ecological value because it encompasses wetlands and uplands they are adjacent to and in close proximity to the following regionally significant resources: (1) the 55,000 acre Guana- Tolomato-Matanzas National Estuarine Research Reserve; (2) the Guana River State Park; (3) the Guana Wildlife Management Area; (4) an aquatic preserve; (5) an OFW; and (6) the 22,000 acre Cummer Tract Preserve. The mitigation plan will provide for a wildlife corridor between these resources, preserve their habitat and insure protection of the water quality for these regionally significant resources. The mitigation offered to offset wetland impacts associated with Parcel D includes: (1) wetland preservation of 0.52 acres of bottom land forest along the northeast property boundary (wetland EP); (2) wetland preservation of 3.98 acres of bottom land forest on a tributary of Marshall Creek contained in the DRI boundaries (Wetlands EEE and HHH); (3) upland preservation of 2.49 acres, including a 25-foot buffer along the preserved Wetlands EEE and HHH and a 50-foot buffer adjacent to Marshall Creek and preserved Wetland EP; (4) a wetland creation area of 0.82 acres, contiguous with the wetland preservation area; and (5) an upland buffer located adjacent to the wetland creation area. The wetland creation area will be graded to match the grades of the adjacent bottomland swamp and planted with wetland tree species. Small ponds of varying depths will be constructed in the wetland creation area to provide varying hydrologic conditions similar to those of the wetland to be impacted. The wetland creation area is designed so as to not de-water the adjacent wetlands. All of the mitigation lands will be encumbered with a conservation easement consistent with the requirements of Section 704.06, Florida Statutes. The proposed mitigation will offset the wetland functions and values lost through the wetland impact on Parcel D. The wetland creation is designed to mimic the functions of the impact area, but is located within a larger ecological system that includes hardwood wetland headwaters. The long-term ecological value of the mitigation area will be greater than the long-term value of the wetland to be impacted because; (1) the mitigation area is part of a larger ecological system; (2) the mitigation area is part of an intact wetland system; (3) the wetland to be impacted will be unlikely to maintain its functions in the long-term; and (4) the mitigation area provides additional habitat for animal species not present in the wetland to be impacted. Certain features will prevent adverse secondary impacts in the vicinity of the roadway such as: (1) a retaining wall which would prevent migration of wetland animals onto the road; (2) a guard rail to prevent people from moving from the uplands into wetlands; and (3) a vegetated hedge to prevent intrusion of light and noise caused by automotive use of the roadway.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is RECOMMENDED: That a final order be entered granting the subject application for modification of Permit 4-109-0216A-ERP so as to allow construction and operation of the Parcel D project at issue, with the addition of the inclusion of a supplemental permit condition regarding the vegetated natural buffers for Lots 16 through 19 described and determined above. DONE AND ENTERED this 9th day of April, 2001, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 2001.

Florida Laws (5) 120.57267.061373.086373.414704.06 Florida Administrative Code (5) 40C-4.09140C-4.30140C-4.30240C-42.02340C-42.026
# 7
OSCEOLA COUNTY vs SOUTH BREVARD WATER AUTHORITY, 91-001779 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Mar. 22, 1991 Number: 91-001779 Latest Update: Jun. 12, 1992

The Issue As reflected in the parties' prehearing stipulation filed on August 28, 1991, the issue in this case is whether the St. Johns River Water Management District (SJRWMD) should approve South Brevard Water Authority's (SBWA) consumptive use permit (CUP) application. The SBWA is seeking permission to withdraw an annual average daily rate of 18.8 million gallons (mgd) and a maximum daily rate of 21.4 mgd. The District proposes to grant the permit with specified conditions. Petitioners challenge the issuance of the permit, alleging that applicable requirements of Chapter 373, F.S. and Chapter 40C-2, F.A.C. and other applicable law are not met. The standing of Petitioners, other than Osceola County, is at issue. Also at issue is whether the relevant criteria include consideration of the adequacy of existing sources of water, and the consideration of costs of utilizing existing sources versus the cost of the proposed new source of water.

Findings Of Fact The Parties The applicant, South Brevard Water Authority (SBWA) was created by special act of the legislature, Chapter 83-375, Laws of Florida. Its principal office is located in Melbourne, Brevard County, Florida. Its general mission is described in Section 1, of Chapter 83-375, Laws of Florida, as amended by Chapter 87-481, Laws of Florida: Section 1. It is hereby declared and determined by the Legislature that a regional water authority is the most responsive, efficient, and effective local government entity to secure, operate, and maintain an adequate, dependable, and safe water supply for the district and customers of the district. It is the intent of the Legislature that such regional water authority possess the full power and authority to implement, finance, and operate a single coordinated program of water supply transmission and distribution to meet the future quantity and quality needs of the district and for customers of the district. There is a paramount public need to develop a safe, reliable, and energy-efficient source of public water for the district residents and to contruct the wellfields, transmission lines, and other facilities necessary to supply such water. The St. Johns River Water Management District (SJRWMD or District) is an agency created pursuant to Chapter 373, F.S. in charge of regulating consumptive uses of water in a 19-county area of the State of Florida, including all of Brevard and part of Osceola County. The geographical boundaries of the District are described in Section 373.069(2)(c), F.S. Osceola County is a political subdivision of the state, west of, and contiguous to, south Brevard County. The Corporation of the President of the Church of Jesus Christ of Latter Day Saints (Deseret) is a Utah corporation authorized to conduct business in the State of Florida. Deseret owns real property in Osceola County to the north and east of the proposed wellfield. Deseret possesses a valid consumptive use permit authorizing the withdrawal of water for this property. East Central Florida Services (ECFS) does not own land or possess a consumptive use permit (CUP). Its purpose is to take over the water management program for the Deseret property. It has applied to the Public Service Commission for certification. Notwithstanding the parties' stipulation that "Triple E Corporation" and "Triple N Corporation" own real property in Osceola County near the proposed wellfield (prehearing stipulation, filed 8/28/91, p. 5), no such corporations are registered in the State of Florida. The lands identified as Triple E and Triple N are owned by multiple parties through trusts, primarily managed by Maury L. Carter, one of the owners. Neither Triple E nor Triple N properties have CUP's. The properties are used for agricultural purposes and the Triple N property has a well and recreational camp. The Site of the Proposed Use The proposed wellfield is located on property owned by the SJRWMD, the Bull Creek Wildlife Management Area (BCWMA), located entirely in eastern Osceola County. The BCWMA is comprised of 22,206 acres within the drainage area of the St. Johns River. The northern third of the management area is drained by Crabgrass Creek, and the southern two-thirds is drained by Bull Creek. The easternmost boundary is located approximately one mile from the Brevard County boundary. Currently all 22,206 acres of the BCWMA are under lease to the Florida Game and Fresh Water Fish Commission, which agency manages the area as a public recreation facility for hunting, fishing, hiking, horseback riding, camping and archeological studies. The sparsely populated area has historically been used for logging and cattle grazing. It was acquired for a detention area and it currently provides nonstructural flood protection. Its surface topography is relatively flat, with uplands and wetlands separated by only inches in vertical elevation. Upland communities include pine flatwoods, saw palmetto prairies, pine savannahs and sand oaks. Wetland communities include cypress domes, mixed shallow marshes, sawgrass marsh, wet prairies and transitional prairies. The BCWMA is classified as a "conservation area" in the District's current adopted Five Year Land Plan which summarizes the agency's land acquisition and management policies. A "conservation area" is defined as "...an area acquired for water resource conservation and protection in an environmentally-acceptable manner". The term includes water supply areas, including areas for public wellfield location. (Osceola Co. exhibit #33, p. 15) Facilities Associated with the Proposed Consumptive Use Although the precise siting of the wells has not been established, the wellfield will be located at the northern end of the BCWMA, east-west into a "panhandle" area, and extending south, for an inverted "L" shape. The wellfield will consist of 12 production wells in 2000 ft. intervals. Wells 1-9 will lie along an east-west axis adjacent to Crabgrass Creek, while wells 10-12 will lie along a north-south axis below well 9, the eastern-most well. The capacity of each well is designed at 3,000 gallons per minute or approximately 4.30 million gallons a day (mgd). Each well consists of 20" diameter casing pipe extending 700' below the ground surface. From there, an open hole for production will extend another 250 feet in depth. A small, 20 ft. by 30 ft., concrete building will enclose the motor and other equipment associated with each well, in order to eliminate vandalism and to baffle the noise. The wells will be sited to avoid jurisdictional wetlands. In addition to the production wells, monitoring wells will be constructed to comply with permit conditions. Because the water drawn from the proposed wellfield will exceed potable standards, reverse osmosis (RO) desalinization treatment is required. A below ground header pipeline will carry raw water from the wellfield to an RO treatment facility in Brevard County. The RO treatment facility will process 75 percent of water coming from the wellfield, 85 percent of which is recovered as finished water, and 15 percent of which is disposed of as brine by deep well injection. The 25 percent of raw water which bypasses the treatment process will be blended with the finished water to yield water which meets drinking water standards for chloride levels. The yield is anticipated to be 16.67 mgd on an average day and 18.9 mgd on a maximum day. However, the finished water yield could be higher if raw water quality permits greater blending and less reject water. On the finished water side, the water will need to be treated again to assure that it will be compatible with water from the City of Melbourne plant. Failure to balance the blended waters chemically could result in corrosion of pipes, leaching of pipes, discoloration, rusty water, and odorous water. A proper process, therefore, is essential and is highly sophisticated. From the treatment facility the water will travel in underground pipes, beneath the St. Johns River, beneath I-95 and east to the Melbourne distribution system. From there some water is anticipated to travel south to connect to the General Development Utilities (GDU) system. Hydrogeologic Characteristics of the Site For modelling purposes, the aquifer system in the region is represented by sequential layers of differing characteristics in the flow and movement of water. The SBWA model contains 6 layers; the Osceola model contains 7 layers. In both models, layer 1 corresponds to the surficial (water table) aquifer; layer 2 corresponds to the Hawthorn formation (the upper confirming layer); layer 3 is the Upper Floridan aquifer; layer 4 describes the 200 ft. thick portion of the Upper Floridan called the "production zone"; layer 5 in the SBWA model is approximately 450 ft. thick and is called a confining unit; Osceola's consultants consider this layer less permeable or semi-confirming; layer 6 is the lower Floridan; and layer 7 in the Osceola model is the bottom reaches of the lower Floridan. The surficial aquifer consists of sand and shell deposits and extends to a depth of approximately 100 feet below land surface. The surficial aquifer is capable of producing small to moderate amounts of water for domestic uses. The Hawthorn is an interbedded formation consisting of clay, limestone and phosphate. Due to its extremely low permeability, this layer restricts both the vertical and horizontal movement of water. The Hawthorn is thicker in Central Florida than in other portions of the state. At the BCWMA the thickness of the Hawthorn ranges from 240 feet in the area northwest of the management area to 80 feet in the southeastern portion of the management area. The upper Floridan Aquifer at the BCWMA, as characterized by the SBWA's consultant and based on site specific data, extends from the base of the Hawthorn to a depth of approximately 900 feet below land surface. That portion of the upper Floridan Aquifer between the bottom of the Hawthorn and 700 feet below land surface consists of fine grained limestone with relatively low permeability. This zone corresponds with layer 3 in the groundwater modeling done by the SBWA. The portion of the upper Floridan between the bottom of the Hawthorn and 700 feet below land surface is less capable of producing water than the portions below this level. That portion of the upper Floridan Aquifer between 700 feet and 900 feet of depth consists of hard dolomites. Dolomitic zones are the most productive zones of water within the Floridan in this part of the state because these formations contain solution fractures and cavities. This zone corresponds with layer 4 in the groundwater modeling done by the SBWA. Several researchers and modelers have suggested the existence of a zone, variously referred to as a semi-confining unit, a zone of lower permeability or a middle semi-confining unit, located between the upper and lower Floridan Aquifer. This area between 900 feet and 1350 feet below land surface consists largely of hard dolomites similar in nature to those in the zone immediately above it. This zone corresponds to layer 5 in the groundwater modeling done by SBWA. Previous regional modeling efforts have utilized model derived values to describe the middle semi-confining unit rather than site specific information showing the location, thickness or hydrogeological characteristics of the zone. Site specific data tends to confirm the lower permeability of this zone relative to the layers above and below it. Site specific data consists of a core sample, mineral content observed during the drilling of the test monitor well, and a Neumann-Witherspoon ratio analysis conducted during the aquifer performance test. The area between 1350 feet and 1450 feet below land surface also consists of dolomites but with greater permeability and greater transmissivity (the measure of an aquifer's ability to transmit water in a horizontal direction). This area corresponds to layer 6 in the groundwater modeling done by the SBWA. No site specific data exists beneath 1483 feet, representing the total depth of test well TM. Regional data does exist which characterizes the areas from 1500 feet below land surface to the bottom of the lower Floridan Aquifer as consisting of zones of varying lithology, and varying permeabilities. This zone which corresponds to layer 7 in the groundwater modeling done by Osceola County is not homogeneous or uniform over its entire thickness according to available regional data, consisting of geologic reports of deep wells in the east-central Florida area. All parties agree that in the area of the proposed wellfield, horizontal movement of water in the Floridan aquifer is from west, where the greatest recharge occurs along the Lake Wales Ridge, to east, where there is little or no recharge. Water quality in the upper Floridan as measured by chloride concentrations deteriorates as one moves from west to east. The Floridan aquifer beneath the BCWMA represents a transition zone between the recharge area to the west and high saline formation waters in the east. The dominant geochemical components in water beneath the BCWMA are biocarbonates. Water quality, as measured by chloride concentrations, also deteriorates with depth. Chloride concentrations, based on data derived from the drilling of well TM at the BCWMA, increase gradually from 306 milligrams per liter (mgl) at 410 feet, to 658 mgl at 1473 feet below land surface. Chloride concentrations increase abruptly to 1980 mgl in well TM at 1483 feet of depth. Evidence is inconclusive as to whether all of the proposed production wells will draw water exceeding 250 mgl in chloride concentrations. It is undisputed that most will, but chloride contours initially provided by SBWA's consultant indicate that the southernmost wells may produce water between 150 and 250 mgl. A comprehensive aquifer performance test (APT) was conducted at the BCWMA by the SBWA's consultant, Post, Buckley Schuh, and Jernigan, Inc. (PBSJ). The test was designed by the staff of the SJRWMD in consultation with the U.S. Geological Survey (USGS). This test yielded data which enabled PBSJ to calculate several aquifer characteristics for use in the groundwater modeling which was later done by SBWA's modeling consultant, Environmental Science and Engineering, Inc. (ESE). Eight wells were utilized in connection with the APT conducted at the BCWMA in January and February 1990. Three of the wells were dual zone monitoring wells capable of monitoring events in two different geologic units simultaneously. Three wells, including the test production well (TP) were open to the interval between 700 and 900 feet below land surface which was identified by the SBWA as the production zone. Typically APT's are run for 12 to 72 hours in Florida. Well TP was pumped for approximately 10 days at a rate equivalent to that expected during actual production while observations were made of water levels in all wells, including three off-site wells (the Holopaw test well, the Kempfer well and the Bruner well). All of the information the SBWA needed from the APT was obtained in the first hours of the test. Water levels in the area monitored during the APT ceased dropping due to pumpage within 1 hour after the pumping started. Three different analytical models were used to calculate a transmissivity value for the production zone, utilizing data derived during the APT. The result showed transmissivity in this zone to be approximately 2 million gallons per foot per day. This is a very high transmissivity value indicating a comparatively prolific aquifer, capable of producing the volumes of water requested in the application. As transmissivity increases, the cone of depression associated with pumpage tends to flatten out and be less steep. The cone of depression extends further out, creating a wider area of drawdown. Hydraulic conductivity is the measure of an aquifer's resistance to flow either in a vertical (KV) or horizontal (KH) direction. Two methods were used to calculate the hydraulic conductivity of the Hawthon Formation by PBSJ: laboratory analysis of a core sample taken from this unit, and a bail test (measuring an increase in water level over time) conducted on a well on site by the SJRWMD. Two different methods were used by PBSJ to calculate the hydraulic conductivity of layer 5: laboratory analysis of a core sample taken from that zone, and the Neuman-Witherspoon ratio analysis method. Porosity is the void space in porous media through which transport of particles, such as chlorides, can occur. Effective porosity has an impact on the ability of saline or dense water to move upward from depth toward a pumping well. The lower the effective porosity within an aquifer, the greater the potential for upconing of saline water within that aquifer. Effective porosity for layers 4 and 5 was calculated using two different methods, those being laboratory analysis of core samples taken from these zones, and analysis of acoustic logs generated during the APT. Each of these methods is accepted in the field of hydrogeology. Anticipated Impacts to Groundwater Levels and Flows as a Result of the Proposed Consumptive Use A numeric groundwater flow model is a computer code representing the groundwater flow process. Both SBWA and Osceola used numeric groundwater flow models developed by their consultants to predict and simulate the impacts associated with withdrawals proposed in the application. The SBWA used a finite difference model called INTERSAT for its simulations. INTERSAT is a widely used and accepted groundwater flow model. The model was run by ESE for the SBWA in the impact or drawdown mode. Drawdown or impact models simulate changes in water levels in response to a stress such as a pumping well. Drawdown models are an accepted and frequently used method to evaluate wellfield stress, particularly in association with a CUP application. ESE and PBSJ utilized several analytical models to first determine and later to verify the area to which the boundaries of their model would extend. The radius of influence of a well or wellfield is the distance from the center of pumpage extending out to where drawdowns caused by that pumpage reach zero. The boundary for a numeric groundwater model should be set at, or beyond, the radius of influence of the pumpage being simulated by the model. Based on the analytical models run by ESE and PBSJ the radius of influence of the wellfield proposed in the application is 43,000 to 45,000 feet. The approximate distances of the boundaries set in INTERSAT model from well TP were 50,000 feet to the east, 40,000 feet to the west, 40,000 feet to the north and 50,000 feet to the south. The INTERSAT model covers a total area of 320 square miles. This size falls somewhere between a regional model and a local model, and is adequate in size to address the impacts associated with the proposed withdrawals. The vertical boundary of SBWA's model extends to 1450 feet below land surface and, as stated above, is divided into 6 layers. The 1450 feet depth generally coincides with the limits of site specific data generated during the APT. The six layers in the SBWA flow model coincide with the six distinct geologic units identified by PBSJ in their APT report. The site specific data generated by the APT was utilized, along with other regional modeling studies, to arrive at a set of "conservative" aquifer parameters to be utilized in the INTERSAT model. "Conservative" parameters for purposes of this application are those which would tend to overpredict drawdown in the surficial aquifer and the production zone, while allowing for more upconing of dense water from the bottom of the model. The selection of "conservative" aquifer parameters by SBWA involved taking site specific values, comparing them with the ranges of values reported in the other available regional models and selecting values which, while still within the range of reported values used in other studies, would tend to show greater impacts for the areas of primary concern than the site specific values. Every aquifer parameter utilized in SBWA's groundwater flow model falls within the range of values reported in at least one of the groundwater modeling studies previously done in this region. The size of the grids utilized in the SBWA model were 500 feet by 500 feet within the vicinity of the wellfield. Grid sizes expand as one moves toward the outer boundaries of the model. The fineness of the grids used by ESE, particularly in the wellfield area, allows for accurate representation and resolution of surface water features, impacts in the production zone and for evaluating the effects of saltwater upcoming in the transport model also done by ESE. Within the radius of influence of the proposed wellfield, there are no existing wells in layers 5 or 6. The ESE model simulations for 18.8 mgd pumpage predict a maximum drawdown in the surficial aquifer (layer 1) of 0.14 feet centered primarily within the BCWMA. At a distance of 1 mile from the wellfield the impact drops to 0.12 feet. None of the existing legal users of water in layer 1 within the radius of influence of the proposed wellfield will suffer a ten percent or greater reduction in withdrawal capacity from their wells solely as a result of the proposed withdrawals, since 10 percent reduction would require at least 3 feet of drawdown. The ESE model simulations predict a maximum drawdown caused by the proposed pumpage of 4.5 feet in layer 3 centered along the alignment of wells and primarily within the BCWMA. At a distance of 2 miles, the drawdown drops to 2 feet. At the Brevard-Osceola County line the drawdown in layer 3 is approximately .5 feet. Petitioner Deseret's flowing wells are drilled in layer 3 and are located within the area where a drawdown of 1 foot is predicted in layer 3 by the ESE model. Deseret uses its property for a cow/calf ranching operation and has approximately 32,000 head of cows. Deseret uses 39 flowing wells east of state road 192 to irrigate pasture, water cattle and supply drinking water. Deseret possesses a valid CUP for a portion of the total flow capacity from those wells. Seasonally, the wells flow at different rates, but they are most relied upon in dry conditions when the natural flow would be decreased. It is unlikely that the proposed SBWA withdrawals will stop the flow of any of Deseret's wells; and it is unlikely that the flow will be reduced by more than 10 percent. Deseret and Osceola's consultants do predict a greater drawdown and opine that approximately 12 of Deseret's wells will cease flowing as a result of the SBWA withdraw As addressed below, the modelling by Petitioner's consultants, upon which those predictions are based, is less reliable than that of SBWA's consultants. If the effects are greater than predicted, mitigation in the form of installation of pumps is possible, albeit inconvenient and expensive. Mitigation would have to be provided by the applicant, SBWA. The drawdowns predicted by the ESE model for layer 4 are not significantly different from those for layer 3. It is anticipated that no legal user of water within the radius of influence of the proposed wellfield will suffer a 10 percent or greater reduction in withdrawal capacity for its wells, as a result of SBWA's proposed withdrawals. Petitioners' consultants, Hartman and Associates, (Hartman) modeled a significantly larger (4900 square miles) and deeper (3000 feet) area than did SBWA. The model makes its predictions based on one data point for every 49 square miles within the modeled area. Petitioners utilized much larger model grids in the wellfield area (2000 feet by 2000 feet) than did the SBWA. Grid of this size lacks the resolution necessary to evaluate wellfield impacts. Petitioners selected their aquifer parameters from another regional modeling study done in 1985 rather than using site specific data. Those parameters were then adjusted or calibrated until a match was obtained to a computer created potentiometric surface which was supposed to reflect the potentiometric surface for May 1990, an uncharacteristically dry period. The created potentiometric surface to which Hartman calibrated its model varies greatly from the potentiometric surface as reflected in the actual data points from which USGS derives its potentiometric surface maps. While no model is perfect, and actual data is preferable, in the absence of all the actual data that is needed, the ESE model is a more credible predictor of drawdowns. Anticipated Impacts to Groundwater Quality as a Result of the Proposed Consumptive Use Solute transport models are computer models designed to simulate the movement of mass, in this case -- chlorides -- through a groundwater flow system. These models are linked to, and are dependent on flow fields generated by groundwater flow models. In order to predict changes in water quality anticipated to occur as a result of its proposed withdrawals, SBWA's consultants used a solute transport model called HST3D. Developed by the USGS, this model is widely used and accepted. For simulations using the HST3D model, SBWA used the flow field and a portion of the grid generated by its INTERSAT groundwater flow model. The HST3D simulations run by ESE utilized a cross section of the INTERSAT model grid extending through row 26 of that grid, which is the row containing the line of 9 proposed wells running on an east-west axis. Use of a cross sectional grid is an appropriate method by which to examine salt water intrusion. Upconing, to the extent that it will occur as a result of the proposed pumpage, would be greatest within the cross section containing the 9 wells. The cross section extends two miles through the wellfield to the west. As chloride concentrations in water increase, the density of the water increases. Density can retard the degree of upconing when chloride concentrations are as low as 1000-2000 parts per million and becomes significant at 3000-5000 parts per million. Failure of a model to consider density effects, when appropriate, would tend to overstate upconing. HST3D does consider density effects. SBWA's consultant ran several simulations with the HST3D model to predict changes that would occur as a result of the proposed pumpage in chloride concentrations over 7, 14 and 30 year time periods. These simulations utilized the same aquifer parameters as the INTERSAT model together with the effective porosity values derived from site specific data. Assuming a starting chloride concentration of 1000 mgl at the bottom of layer 5, the measured concentration at that level in well TM on the BCWMA site, after 30 years of pumpage at 18.8 mgd, the chloride concentrations in layer 4 would increase by only 100 mgl. The simulations for 7 years of pumpage which is the duration of the proposed permit, show that the predicted increase in chloride levels would be substantially less than 100 mgl. Other HST3D simulations were run by SBWA for a pumpage rate of 35 mgd utilizing beginning chloride concentrations of 5,000 mgl and 10,000 mgl, respectively at the bottom of layers. The results did not show any significant changes in chloride concentrations in layer 4 over and above those shown when a lower starting chloride concentration was assumed. In a circumstance where, as here, the chloride concentrations in the zone from which water is proposed to be withdrawn exceeds secondary drinking water standards (250 mgl), the SJRWMD evaluates the existing legal water uses within the area that would be impacted by the proposed use. If it is determined that the increase in chloride concentrations caused by a proposed use would detrimentally affect other existing legal users or the applicant, only then is the increase deemed to be "significant". Within the layers of the aquifer which would experience increases in chloride concentrations as a result of the proposed withdrawal, layers 4, 5 and 6, no existing users of water would be detrimentally affected. Petitioner Deseret's closest wells to the proposed wellfield are in layer 3 where chloride levels will not be affected by the proposed wellfield within the 7 year duration of the proposed permit or even beyond that period. Further, the use Deseret makes of the water from the wells in closest proximity to the proposed wellfield, pasture irrigation, can tolerate significantly higher chloride concentrations than will exist even directly beneath the wellfield in level 4 after 30 years of pumping. Use of water for public supply purposes is considered by SJRWMD to be in the public interest. Utilization of the water beneath BCWMA for public supply purposes, even with some increase in chloride concentrations in the source of the water over the life of the permit, does not on balance detrimentally affect the public interest. Two different solute transport models were done by Petitioners' consultants, one a numeric model and the other an analytical model. The numeric model done by Hartman, RANDOMWALK, does not predict changes in chloride concentrations within an aquifer, but rather tracks movement of particles. RANDOMWALK does not account for density effects. The analytical model done by Prickett for the Petitioners relies on assumptions, many of which are not met in the aquifer system at BCWMA. Those assumptions relate to uniformity of the system, for example: porosity and permeabilities, and lack of regional gradients. The solute transport models utilized by the Petitioners are less reliable for predicting water quality changes resulting from the proposed pumpage than the model utilized by the SBWA. Salt water intrusion is a dramatic increase of chloride levels in an aquifer layer. The saline water encroachment which occurs from the wellfield stress will be in the lower confining unit. There will be limited degradation in the lower part of the production zone. The wellfield will not induce significant lateral intrusion from the east. There will not be any dramatic changes in chlorides. The movement of the chlorides is confined to the locality of the wellfield. Most of the movement is vertical and is of limited increase. The proposed Bull Creek withdrawals will not aggravate any currently existing salt water intrusion problems. The reject brine water from the RO treatment plant will be disposed of in deep injection wells in Brevard County. These injection wells would deposit the brine into a receiving body of water in the Oldsmar geologic formation. The brine reject will have a total dissolved solids (TDS) concentration of approximately 7,000 mgl. The receiving water into which the brine will be injected approximates sea water, with TDS concentrations in the range of 36,000 mgl. The receiving body will obviously not be further degraded. Environmental Impacts of the Proposed Consumptive Use District staff, SBWA consultants and Osceola's consultants independently conducted onsite field investigations of the BCWMA to evaluate the vegetative communities and land uses which exist on site. Each consultant prepared a habitat map identifying the various vegetative communities found at the site. While relatively pristine, the BCWMA has been logged and grazed by cattle in the past. The impacts of man's activities have been remediated by ceasing the activity. There are few permanent incursions, such as roads, canals and buildings. The area is a very diverse landscape, with a mosaic of different types of plant communities. There are various upland and wetland habitats. The variety of wetlands are forested and non-forested, deep and shallow, open and closed. These wetlands perform important functions, including water storage and purification, aquifer recharge, flood control, and provision of food sources and habitat for wildlife, and they are "factories" for producing the materials needed by many higher organisms. The wetlands on site are structurally complex and are good habitat for macro- invertebrates and the fish and higher organisms that feed on them. A number of these wetlands are shallow, isolated wetlands. During periods of inundation, when the wetlands fill up with water and interconnect with the Bull Creek drainage system, the system exports various organisms to the wetlands. Fish that are live bearers move into isolated wetlands during periods of inundation, and they and their offspring become a source of food for birds. Fish species that lay eggs can withstand desiccation (total drying out) can survive the temporary drying of wetlands, but live bearers must repopulate during periods of inundation. The mixed wetland hardwoods on site contain a diversity of bugs, crawfish, mayflies, damsel flies, midges, and snails. Some of these are important food sources for higher organisms. The apple snail, for example, is an important food source for such birds as the limpkin and the endangered snail kite, and its eggs are food for crawfish and other organisms. The biological communities that exist in the wetlands and uplands at the site are determined by a number of factors, including the depth and duration of the hydroperiod, soils, climate, temperature, and availability of sunlight. These communities and their habitats will react to changes in light, water, temperature, and many other subtle effects, causing changes in plant diversity and structure, the areal extent of certain types of habitats and wetlands, and utilization by wildlife. Natural fluctuations in the hydroperiod also cause these changes, generally from the exterior edges of a wetland to the interior. The wetlands in the BCWMA have been able to withstand the natural drought and flood periods, or they wouldn't be there today. Periodic burning is essential to the health of ecosystems such as in the Bull Creek area. Fires reduce the prevalence of species less tolerant to fire, allow other species to strengthen their presence, return organic material to the soil, and reduce the fuel available for wild fires. Originally occurring naturally as a result of lightening strikes, prescribed burns are now undertaken by agencies such as the Division of Forestry and the Game and Fresh Water Fish Commission to replicate the beneficial functions of natural periodic burning. Fire management is used as a land management technique at BCWMA and continued fire management at the BCWMA will maintain a natural ecological setting typical of Florida. Slight variations in elevation which mark the difference between wetlands and uplands can result in utilization of the areas by different animal communities. Where different types of plant communities meet, an "ecotone" is created. Where an ecotone exists, the "edge effect" of the competition between the two communities occurs. The result of the edge effect is higher plant and animal species diversity, which is extremely important to the natural community. Some animals make specific use of the ecotone for habitat and food resources. Many amphibians, frogs in particular, live in the ecotone. Some birds will not roost in the upland forests but will roost in the edge of the forest adjacent to wetlands. Wetlands in the BCWMA are connected to the remainder of the Bull Creek system through groundwater resources. Their biological and ecological communities are also connected as the same organisms move throughout the system. Isolated wetlands also exhibit a "moving edge" effect, where changes in the surface water and water table levels cause different plants, or plants at different levels of maturity, to exist in the wetland and its perimeter. This increases the productivity of the wetland by making it attractive to a wider variety of plant and animal species. If the expansion and contraction of isolated wetlands is reduced by lowered water levels, the smaller wetlands would exhibit a reduced edge effect, and the cumulative effect of this reduction over time would disrupt the functioning of the wetland-upland system. Isolated wetland systems are more sensitive to drawdowns in the surficial aquifer than connected wetland systems because the drainage area contributing water to the wetland system is smaller. Isolated herbaceous wetland communities are the most sensitive of the vegetative communities on BCWMA to drawdowns in the surficial aquifer. The surficial aquifer fluctuates naturally as much as five feet annually. Rainfall is the primary source of water for the surficial aquifer. Water levels in the surficial aquifer respond very quickly to rainfall events. Hydroperiods of the wetland systems in the BCWMA respond to rainfall and surficial aquifer levels. The wetland hydroperiods vary from year to year, and wetland ecosystems have adopted to those annual changes. But a groundwater withdrawal from the surficial aquifer in the Bull Creek area would cause a corresponding lowering of the surface water level, since the wetlands are not "perched", or separated from the aquifer by a confining layer. A drawdown would lower water levels throughout the hydroperiod, under both high water and low water conditions, with a more pronounced effect during the dry season and drought periods. Some of the over twenty threatened and endangered plant species present at Bull Creek grow in shallow, marginally wet areas. Changes in even a few inches of groundwater would cause these plant species to be retarded in growth, and their abundance would decrease or they would die out at the site. Many of the wetlands are shallow, broad, sloping areas, and groundwater elevation changes of just a few inches will cause changes in the areal extent of these wetlands. Even the .14 foot drawdown predicted by SBWA's modeling would affect shallow inundated or saturated systems by changing the moisture level at the surface, particularly by affecting the lowest water levels. Changes in the vegetative composition of wetlands will affect the macro-invertebrate characteristics of a site. For example, as water levels change, the density of the vegetation (in terms of number of plant stems per acre) can decrease, leaving fewer places for the macro-invertebrates to hide, and the populations of macro-invertebrates will decrease through predation. As food sources, habitat and breeding grounds decrease, those animal species that can relocate will attempt to do so. Relocation can adversely affect the survival of the species; for example, a wood stork unable to find a particular food upon which it is dependent at a particular interval in its life cycle may abandon its nest and its young. Animals that attempt to relocate may find that there is not a suitable similar habitat available, making their attempt to adjust to the change in their environment unsuccessful. The proposed use will not significantly affect the stages or vegetation of the upland communities at the BCWMA because they are not as dependent on saturation or inundation as a wetland community. Forested wetland systems, be they isolated or connected, will not be influenced by a drawdown of the magnitude predicted by SBWA for the surficial aquifer. Forested systems have deep root zones and the canopy provides shading to the strata below. Forested systems are able to tolerate natural changes in hydrology. The SBWA assessment does not offer any detailed cataloguing of the plant and animal communities on site, or a description of how the systems operate or interface with each other. It does not provide sufficient information to be able to assess the impacts of the proposed wellfield on these systems. There was insufficient information presented by the applicant to conclude that the environmental harm to be caused by operation of a wellfield at the BCWMA has been reduced to an acceptable level. The applicant relied on the fact that drawdowns in the surficial aquifer will be minimal, without fully considering the impact of those minimal drawdowns on a fragile wetland ecosystem during a dry period. Water Demand The SBWA was created by special act in 1983 as a dependent special district for the purpose of developing regional water supplies and transmission of water to water distribution systems. In its existence so far, its labors have been in the former, and none in the latter category. Efforts to develop a regional water supply have been frustrated by litigation, by reluctance of local public systems to give up their authority and by delays in pursuing and processing CUP applications, two of which are still pending, in addition to the instant application. The City of Melbourne's public water system provides water to Melbourne, Palm Bay and West Melbourne, and to some unincorporated areas surrounding Melbourne. It also supplies water to the area called south beaches, comprised of the Brevard County area south of Patrick Air Force Base, including Satellite Beach, Melbourne Beach, Indiatlantic and Indian Harbor Beach. The current water supply is Lake Washington, which is part of the chain of lakes on the St. Johns River. The city of Melbourne was granted a CUP on January 15, 1991, for withdrawals from Lake Washington, ranging from 27.15 million gallons maximum daily withdrawals in 1991 to 21.7 million gallons maximum daily withdrawals in 1998. In addition, Melbourne has planned a new facility and has the CUP to withdraw 8.13 million gallons a day from the Floridan Aquifer commencing in 1993. After reverse osmosis treatment, the groundwater withdrawal will yield 6.5 million gallons a day finished water, making up the difference from reduced withdrawals from Lake Washington. Approximately 56 potable water systems have been identified by SBWA in South Brevard, south of the Pineda Causeway. Almost all are small private systems. Besides Melbourne, the other major water supplier in the area is General Development Utilities (GDU), serving the City of Palm Bay. GDU's CUP expires in 1993 with an average daily withdrawal of 6.5 mgd and maximum daily withdrawal of 8.5 mgd. It has ample capacity until 1996, and beyond to the year 2000, if an additional Department of Environmental Regulation capacity rating is obtained. The total capacity of the two major existing facilities is approximately 30 mgd and total existing consumptive use quantities (including existing CUPs with expiration dates varying from 1993 to 1998) approach 40 mgd. The current SBWA water master plan assumes that existing sources need replacing. More specifically, SBWA, if this CUP is granted, seeks to replace Lake Washington as the primary source of water in the area with the groundwater obtained from the BCWMA wellfield. An agreement between the City of Melbourne and SBWA provides that the City will initially purchase 8 mgd, plus all future needs of water from the SBWA. This 8 mgd would be used by Melbourne prior to using its 6.5 mgd finished water from the RO facility, and the RO water would be used prior to withdrawals from Lake Washington. The agreement, dated January 9, 1991, acknowledges the need for, and specifically authorizes improvements to Melbourne's Lake Washington Water Treatment Plant, including the conversion of the existing high service pumping station to a low service pumping station with average daily capacity of 20 mgd and maximum capacity of 25 mgd. (SBWA Ex. 49) GDU is a private utility and currently is outside the jurisdiction of the SBWA. General Development Corporation is in receivership and the City of Palm Bay is negotiating for purchase of the utility. If the purchase is successful, the supply will become publicly owned and subject to the jurisdiction of the SBWA. The City of Palm Bay is not bound to purchase GDU at any price, and the requirement that it would shut down its newly purchased facility to receive water from SBWA is a disincentive to the acquisition. In the meantime, GDU has no incentive to reduce CUP capacity and devalue its facility. GDU's service has been uninterrupted and reliable. Contamination to the surface aquifer utilized by GDU has been successfully treated. Although septic tanks proliferate in Palm Bay, their location, as well as the presence of confining layers in the surficial aquifer, reduce the susceptibility of GDU wells to contamination from septic tanks. The applicant's concerns about unreliability and safety of Lake Washington as a continued water source are unsubstantiated by the weight of evidence in this proceeding. Surface water facilities have been used in Florida since before the turn of the century and no major facility has ever been off-line one day due to raw water contamination. Nor has any major Florida surface water plant ever been sabotaged. There is a greater chance in Florida of problems with pipeline failures, and the miles of pipes planned to transmit ground water from Bull Creek east to SBWA consumers increase the chances of those problems. Recently, the SJRWMD Upper Basin Project has significantly improved the water quality and quantity in Lake Washington through restoration of marshlands in the upper basin and capping flowing wells. Restored marsh areas will allow for additional removal of nutrients and provide an additional storage to the Lake Washington/Upper Basin system, significantly improving safe yield quantities. Comparisons of concentrations of raw water chlorides and total dissolved solids for the drought years of 1989 and 1990, show significant reductions for the latter time frame. Recent evaluations indicate that Lake Washington would be acceptable in terms of chlorides and TDS concentrations for a 35 mgd withdrawal, even during 50 and 100 year droughts. Water quality improvements to Lake Washington can be directly related to the Upper Basin project. Trihalomethanes are regulated by the Safe Drinking Water Act. They are produced by the disinfection process of treating raw water with chlorines, and they are carcinogenic. A previously experienced problem at the Melbourne plant has been corrected with operational changes. As recently as 1988, an internal staff report by SJRWMD staff provided: Lake Washington has been a reliable source of public water supply since 1960 and can remain so in the future with the continuation of sound basin planning and watershed management by the St. John's river Water Management District. The quality of the raw water from Lake Washington is subject to annual and seasonal variations that make the treatment process more difficult, and the quality of the delivered water less consistent, than would be the case with a groundwater supply. A supplemental water source near Lake Washington would improve the quality of the water delivered to the users, would increase the total volume that could be taken from the lake in times of stress, and would provide a reliable alternative in case of emergency. The upper zone of the Floridan Aquifer within south Brevard County has the potential to supply a significant portion of the area's future water needs with existing low-pressure, reverse osmosis technology at a cost that is comparable to current supplies.

Recommendation Based on the foregoing, it is hereby, recommended that the SBWA application for CUP be denied. RECOMMENDED this 12th day of March, 1992, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of March, 1992. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 91-1779, 91-1780, & 91-1781 The following constitute disposition of the findings of fact proposed by each party. Petitioner, Osceola County These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-5, 7-8, 14, 21-22, 24-25, 27-28, 30, 32, 35, 62-65, 73, 104, 113, 116-125, 127, 129-130, 132-138, 140, 154, 157-158, 164, 167-168, 183, 186, 189, 191-195, 197-200, 202-204, 209, 212. These findings are rejected as contrary to or unsupported by the weight of evidence: 37-38, 48, 51, 53, 56, 66, 79-81, 84-90, 92-94, 102-103, 105-107, 110-112, 115, 128, 171-172, 212(d), (f) and (g), 213-214. These findings are rejected as cumulative, unnecessary or irrelevant: 6, 9- 13, 15-20, 23, 26, 29, 31, 33-34, 36, 39-47, 49-50, 52, 54-55, 57-61, 67-72, 74- 78, 82-83, 91, 95-101, 108-109, 114, 126, 131, 139, 141-153, 155-156, 159-163, 165-166, 169-170, 173-182, 184-185, 190, 196, 201, 205-208, 210-211, 212(e), 215. Petitioners, Triple E, Triple N, East Central Florida Services, Inc., and Deseret These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-6, 8-9, 16-20, 22-25, 27-28, 30-31, 50- 56, 59-60. These findings are rejected as contrary to or unsupported by the weight of evidence: 7, 12, 32, 34-37, 40, 42, 44, 48, 49, 58. These findings are rejected as cumulative, unnecessary or irrelevant: 10- 11, 13-15, 21, 26, 29, 33, 38-39, 41, 43, 45-47, 57, 61-63. Respondent, South Brevard Water Authority These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-6, 9-11, 13, 16-24, 28, 30-34, 36, 38, 46-48, 61, 64, 70, 72-74, 90-91, 94-98, 105-108, 110-111, 113, 115-116, 121, 126-129, 133, 149, 152, 157, 169, 179, 181-190, 192-194. These findings are rejected as contrary to or unsupported by the weight of evidence: 41, 130-132, 156, 158, 167, 174, 177. These findings are rejected as cumulative, unnecessary or irrelevant: 7-8, 12, 14-15, 25-27, 29, 35, 37, 39-40, 42-45, 49-60, 62-63, 65-69, 71, 75-89, 92- 93, 100-104, 109, 112, 114, 117-120, 122-125, 134-148, 150-151, 153-155, 159- 166, 168, 170-173, 175-176, 178, 180, 191. Respondent, St. Johns River Water Management District These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-8, 10-22, 24-36, 38-44, 47-62, 64-88, 90, 92-116, 118-122, 124-130, 132-142, 144-151, 159-160, 164, 166-167, 169, 171, 174-175, 177, 193-196, 198, 202, 206. These findings are rejected as contrary to or unsupported by the weight of evidence: 131 (the conclusion), 153-154, 156-157, 161-162, 197, 204, 207. These findings are rejected as cumulative, unnecessary or irrelevant: 9, 23, 37, 45-46, 63, 89, 91, 117, 123, 143, 150, 152, 155, 158, 163, 165, 168, 170, 172-173, 176, 178-192, 199-201, 203, 208-210. COPIES FURNISHED: Segundo J. Fernandez, Esquire Scott Shirley, Esquire OERTEL, HOFFMAN, FERNANDEZ & COLE, P.A. Post Office Box 6507 Tallahassee, FL 32314-6507 Douglas P. Manson, Esquire BLAIN & CONE, P.A. 202 Madison Street Tampa, FL 33602 Clifton A. McClelland, Esquire POTTER, McCLELLAND, MARKS & HEALY, P.A. Post Office Box 2523 Melbourne, FL 32902-2523 Wayne Flowers, Esquire Nancy B. Barnard, Esquire St. Johns River Water Management District Post Office Box 1429 Palatka, FL 32178-1429 Neal D. Bowen, County Attorney Osceola County Room 117 17 South Vernon Avenue Kissimmee, FL 32741 Carol Browner, Secretary Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (7) 120.52120.5727.15373.019373.042373.069373.223 Florida Administrative Code (1) 40C-2.301
# 8
DEFENDERS OF CROOKED LAKE, INC., AND PHILLIP AND PRISCILLA GERARD vs KRISTA HOWARD AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 17-005328 (2017)
Division of Administrative Hearings, Florida Filed:Lakeland, Florida Sep. 22, 2017 Number: 17-005328 Latest Update: Aug. 16, 2018

The Issue The issue is whether Respondent, Krista Howard,2/ is entitled to issuance of the Consolidated Environmental Resource Permit and Recommended Intent to Grant Sovereignty Submerged Lands Authorization, Permit No. 53-0351424-001-EI, as announced by Respondent, Department of Environmental Protection, in the Consolidated Notice of Intent to Issue Environmental Resource Permit and Lease to Use Sovereignty Submerged Lands issued on July 28, 2017, and subsequently amended on January 11, 2018.3/

Findings Of Fact The Parties Petitioner Defenders is a Florida non-profit corporation that has been in existence since the mid-1980s or earlier. Defenders' primary purpose is to protect and preserve Crooked Lake so that it may remain an Outstanding Florida Water ("OFW") for all members of the public to use and enjoy. Defenders has more than 25 members who reside in Polk County, Florida. Its membership consists of approximately 100 family memberships, mostly comprised of persons who live on or near Crooked Lake. Petitioners Gerards are riparian landowners on Crooked Lake, whose property is located immediately adjacent to, and slightly to the northwest of, Respondent Howard's property. The Gerards' home address is 1055 Scenic Highway North, Babson Park, Florida 33827. Respondent Howard is the applicant for the Consolidated Authorization for the Dock. Howard's property, which is riparian to Crooked Lake, is located at 1045 Scenic Highway North, Babson Park, Florida 33827. Respondent DEP is the administrative agency of the State of Florida statutorily charged with, among other things, protecting Florida's water resources. As part of DEP's performance of these duties, it administers and enforces the provisions of chapter 373, part IV, Florida Statutes, and the rules adopted pursuant to that statute. Pursuant to that authority, DEP determines whether to issue or deny applications for ERPs. Pursuant to section 253.002, Florida Statutes, DEP also serves as staff to the Board of Trustees of the Internal Improvement Trust Fund ("Board of Trustees") and, in that capacity, reviews and determines whether to issue or deny, applications for approval to use sovereignty submerged lands.5/ DEP Review of the Application The Dock is proposed to be located on sovereignty submerged lands and in surface waters subject to State of Florida regulatory jurisdiction. Therefore, an environmental resource permit and a sovereignty submerged lands lease are required. On or about February 14, 2017, Todd Rickman, Howard's professional contractor who designed the Dock, filed an Application for a Sovereignty Submerged Lands Lease for Existing Structures and Activities6/ ("Application") with DEP's Southwest District Office, seeking approval to construct and operate the Dock. On or about March 15, 2017, DEP requested additional information regarding the project. Howard submitted the requested items, and the Application was determined complete on May 30, 2017. Notice of DEP's receipt of the Lease portion of the Application was provided as required by section 253.115. The comment period commenced on June 15, 2017, and ended on July 6, 2017. As previously noted, on July 28, 2017, DEP issued the Consolidated Notice of Intent, proposing to issue the Consolidated Authorization to construct and operate the Dock. On January 11, 2018, DEP amended the Consolidated Notice of Intent to accurately reflect the "clearly in the public interest" permitting standard for the ERP portion of the Consolidated Authorization, which is applicable to projects proposed in OFWs. Background Crooked Lake Crooked Lake (also, "Lake") is an approximately 4,247-acre freshwater lake in Polk County, Florida. It is an irregularly shaped karst lake roughly resembling an inverted "L," with the longer axis running north to south. It is located on the Lake Wales Ridge. Crooked Lake is designated an OFW by Florida Administrative Code Rule 62-302.700(9)(i)9.7/ The Lake is classified as a Class III waterbody pursuant to Florida Administrative Code Rule 62-302.400(15).8/ The elevations and bottom contours in Crooked Lake vary substantially throughout the Lake. Thus, water depths may, and generally do, vary substantially from one location to another throughout the Lake. The water levels in Crooked Lake fluctuate frequently and, at times, dramatically, depending on rainfall frequency and amounts. A graph prepared by Petitioners' Witness James Tully, using Southwest Florida Water Management District ("SWFWMD") historical water level data for Crooked Lake measured in National Geodetic Vertical Datum of 1929 ("NGVD") shows water levels historically fluctuating from as low as approximately 106 feet in or around 1991, to as high as 123 feet NGVD in or around 1951, 1961, and 2004. Rickman generated a water level graph using the Polk County Water Atlas ("Atlas") website. This graph, which covers the period of 2008 through mid-2017, shows that the water levels in Crooked Lake, for this most recent ten-year period, fluctuated approximately five feet, with the lowest levels falling slightly below 114 feet NGVD for relatively short periods in 2012 and 2013, and the highest level rising to approximately 119 feet NGVD in mid-2017. The competent, credible evidence shows that although water levels in Crooked Lake may occasionally rise to levels at or around 123 feet NGVD, those conditions have been associated with extreme weather events such as hurricanes, are atypical, and are relatively short-lived. The maximum water level in Crooked Lake is subject to control by a weir located south of the Lake. Discharge from the weir occurs at a control elevation of 120 feet NGVD. As such, the water level in parts of Crooked Lake may, at times, temporarily exceed 120 feet NGVD, but will eventually decrease to 120 feet NGVD as the water flows south and is discharged through the weir. To the extent rainfall does not recharge the Lake, water levels may fall below 120 feet NGVD. The ordinary high water line ("OHWL"), which constitutes the boundary between privately-owned uplands and sovereignty submerged lands, has been established at 120.0 feet NGVD for Crooked Lake. Crooked Lake is used for recreational activities such as fishing, swimming, boating, and jet ski use, and there are public and private boat ramps at various points on the lake that provide access to the Lake. There is no marina having a fueling station on the Lake. The credible evidence shows that the northeast portion of the Lake, where the Dock is proposed to be located, experiences a substantial amount of boat and jet ski traffic. This portion of the Lake also is used for swimming, water- skiing, wakeboarding, the use of "towables" such as inner tubes, and for other in-water recreational uses. The Proposed Dock Howard holds fee title by warranty deed to parcel no. 333028-000000-033140 located at 1045 Scenic Highway, Babson Park, Florida.9/ This parcel has approximately 110 linear feet of riparian shoreline on Crooked Lake. The Dock is proposed to be constructed and operated on sovereignty submerged lands adjacent to this riparian upland parcel, which is located on the eastern shore of the northeastern portion of Crooked Lake. The Dock, as proposed, is a private single-family residential dock that will be used by Howard for water-dependent recreational purposes, such as specifically, boating, fishing, swimming, and sunbathing. The Dock is not proposed to be constructed or used by, or to otherwise serve, commercial or multifamily residential development. The Dock is configured as a "T," supported by pilings and consisting of a 4-foot-wide by 152-foot-long access walkway, and an approximately 1,983-square-foot terminal platform comprised of a lower-level platform having four vessel slips and a flat platform roof. Two sets of stairs lead from the lower level of the terminal platform to the platform roof, which will be elevated eight feet above the lower-level platform and will have a railed perimeter. The platform roof will function as a roof for the boat storage area below and a sundeck. The four slips on the Dock's lower-level platform will be used for permanent mooring for up to six watercraft: a 23-foot-long ski boat,10/ a 20-foot-long fishing boat, and four jet skis. As proposed, the Dock will occupy a total area of approximately 2,591 square feet. The lower platform of the Dock is proposed to be constructed at an elevation of 121 feet NGVD. The roof/upper platform will be constructed eight feet above that, at an elevation of 129 feet NGVD. The pilings supporting the Dock will be wrapped in an impervious material to prevent leaching of metals and other pollutants into the water. Pursuant to the Specific Purpose Field Survey ("Survey") for the Lease submitted as part of the Application, the Lease will preempt approximately 2,591 square feet, and closely corresponds to the footprint of the Dock. The submerged lands surrounding the Dock that are not occupied by the footprint of the Dock, including the area between terminal platform and the shoreline, are not included in the preempted area of the Lease.11/ The Survey shows "approximate riparian lines" which delineate Howard's riparian area oriented to the center of the waterbody and to the primary navigation channel in the northeast portion of Crooked Lake. As shown on the version of the Survey initially filed as part of the Application, the Dock was proposed to be located approximately 4.7 feet, at its closest point, from the southern riparian line. However, in response to DEP's request for additional information, the Survey was modified in April 2017, to shift the Dock northward within Howard's riparian area. The Dock is now proposed to be located 25.1 feet, at its closest point, from the southern riparian line, and 29.4 feet, at its closest point, from the northern riparian line. The walkway of the Dock will commence at an approximate elevation of 120 feet NGVD, which corresponds to the OHWL established for Crooked Lake. As previously noted above, the walkway will extend waterward approximately 152 feet, where it will intersect with the terminal platform. The terminal platform will extend another 52 feet waterward. In total, the Dock is proposed to extend waterward approximately 204 feet from the OHWL. Although the Dock would be one of the longest and largest docks on Crooked Lake, the credible evidence establishes that there are several other docks of similar size and/or length on the Lake. Rickman testified that he obtained approvals for, or was otherwise aware of, several docks over 2,000 square feet on the Lake. Additionally, the evidence showed that eight other docks on the Lake are longer than the proposed Dock.12/ Rickman testified that most of the larger docks on Crooked Lake have roofs, and that most of these roofs are pitched, rather than flat.13/ As noted above, the water level in Crooked Lake frequently and, at times, extensively fluctuates. As a result, there are periods during which water depths in parts of the Lake are extremely shallow. Rickman testified that the Dock was designed to extend far enough out into Crooked Lake to reach sufficient water depth to enable Howard to maximize the use of the Dock for boating throughout the year. The Dock is designed to extend out to the point at which the bottom elevation of the Lake is approximately 109.9 feet NGVD. Based on the Atlas' ten-year water level graph for Crooked Lake referenced above, Rickman projected that at this point, the water depth typically would be sufficient to allow Howard to operate her largest vessel, the 23-foot ski boat. The ski boat has a 25-inch draft.14/ The boat will be stored out of the water on a boat lift on the Dock, attached by cables to a sub-roof immediately beneath the platform roof. When being lowered into or hoisted from the water, the boat will be placed in a boat cradle consisting of two containment railings approximately 18 inches high each on either side, and a "V" shaped aluminum bottom with bunks on which the boat is cradled. The aluminum bottom of the cradle was estimated to be two to three inches thick. Although the boat cradle is approximately 18 to 21 inches in "total height,"15/ the cradle does not have to be completely lowered its entire 18- to 21-inch height into the water when used. Steven Howard explained, credibly, that the cradle needs to be lowered into the water only a few inches lower than the ski boat's 25-inch draft to enable the boat to float into or out of the cradle. To that point, Rickman testified that taking into account the 25-inch draft of the ski boat and the "total height" of the boat cradle, between 40 and 44 inches of water depth would be required when the cradle is used in order to avoid coming into contact with the Lake bottom. Based on the Atlas graph showing the lowest water levels for the previous ten-year period at approximately 114 feet NGVD, Rickman designed the Dock to extend out to the 109.9-foot NGVD bottom elevation point. At this point, the projected water depth would be slightly more than four feet during periods of the lowest projected water levels for Crooked Lake. For the Dock to be able to wharf out to 109.9 feet NGVD bottom elevation, it must extend a total of approximately 204 feet waterward into the Lake. The credible evidence establishes that while Howard's ski boat is one of the largest, it is not the largest boat operated on Crooked Lake. Impacts Assessment for Environmental Resource Permit Water Quality Impacts As noted above, Crooked Lake is a Class III waterbody. Accordingly, the surface water quality standards and criteria applicable to Class III waters in Florida codified in rule 62-302.300 apply to Crooked Lake. The Dock, as proposed to be constructed and operated, is not anticipated to adversely affect or degrade water quality in Crooked Lake. Specifically, as required by the Consolidated Authorization, a floating turbidity curtain will be installed around the boundary of the construction area before construction commences, and it must be left in place until construction is complete and turbidity levels in the work area have returned to background levels. Additionally, as noted, the pilings supporting the Dock must be wrapped in an impervious material to prevent leaching of metals and other pollutants into the water over the life of the structure. The Consolidated Authorization also prohibits the installation and use of fueling equipment at the Dock; prohibits the discharge of sewage or other waste into the water; prohibits liveaboards; prohibits fish cleaning or the installation of fish cleaning stations unless sufficient measures such as sink screens and waste receptacles are in place; and prohibits repair and maintenance activities involving scraping, sanding, painting, stripping, recoating, and other activities that may degrade water quality or release pollutants into the water. Although the Consolidated Authorization imposes a specific condition requiring, for all vessels using the Dock, a minimum 12-inch clearance between the deepest draft of the vessel (with motor in the down position) and the top of submerged resources, it does not specifically address circumstances where the use of the boat cradle, rather than the vessel itself, may come into contact with the Lake bottom. DEP's witness acknowledged that if the boat cradle were to come into contact with the Lake bottom, water quality standards may be violated. Given the information presented at the final hearing regarding the operation of the boat lift and the need for sufficient clearance between the bottom of the boat cradle and the lake bottom, the undersigned recommends that a specific condition be included in the Consolidated Authorization prohibiting contact of the Lake bottom by the boat cradle. This recommended condition is set forth in paragraph 73.A., below. Upon consideration of the conditions imposed by the Consolidated Authorization discussed above, including imposing a specific condition that prohibits contact of the boat cradle with the Lake bottom, the undersigned finds that the Dock will not adversely affect or degrade the water quality of Crooked Lake. Water Quantity Impacts The Dock, as proposed, is a piling-supported structure that will not impound, store, or impede the flow of surface waters. As such, the Dock will not cause adverse flooding to on-site or offsite property, will not result in adverse impacts to surface water storage and conveyance capabilities, and will not result in adverse impacts to the maintenance of surface or ground water levels. Impacts to Fish, Wildlife, and Listed Species and Habitat The Application states, in section 5, question 6, that there is no vegetation on Howard's riparian shoreline. However, the Survey depicts an area of emergent grasses approximately 60 feet wide and extending diagonally approximately 70 feet waterward into the Lake. The Survey depicts this grassed area as straddling the riparian line between Howard's property and the adjacent parcel to the south. The Survey shows the Dock as being located a significant distance waterward of the grassed area, such that no portion of the Dock will be located on or near this grassed area. Additionally, an aerial photograph of Howard's property and the Lake waterward of Howard's property shows a smaller patch of what appears to be emergent grasses further offshore. This grassed area is not shown on the Survey, and it cannot definitively be determined, by examining the Survey and the aerial photograph, whether this grassed area is growing in an area that will be impacted by the Dock. Steven Howard acknowledged that this smaller grassed area may be located at or near the jet ski slip on the southeastern side of the Dock. An environmental assessment of this smaller grassed area was not performed or submitted as part of the Application. Thus, any value that this area may have as fish and wildlife habitat was not assessed as part of DEP's determination that the Dock will not adversely impact the value of functions provided to fish, wildlife, and to listed species and their habitat. In order to provide reasonable assurance that the Dock will not adversely impact the value of functions provided to fish, wildlife, and to listed species and their habitat, the undersigned recommends including a specific condition in the Consolidated Authorization requiring this smaller grassed area to be completely avoided during construction and operation of the Dock, or, if avoidance is not feasible, that an environmental assessment be performed prior to construction so that the value of this grassed area, if any, to fish, wildlife, and listed species can be evaluated to determine whether minimization and compensatory mitigation should be required. This recommended condition is set forth in paragraph 73.B., below. As previously noted, the Consolidated Authorization contains a specific condition requiring a minimum 12-inch clearance between the deepest draft of the vessel (with the motor in the down position) and the top of submerged resources for all vessels that will use the docking facility. Compliance with this condition will help ensure that the value of functions provided to fish and wildlife and to listed species and their habitat of any such submerged resources is not adversely impacted by vessels using the Dock. The Consolidated Authorization also contains a specific condition requiring handrails to be installed on the Dock to prevent mooring access to portions of the Dock other than the wetslips. This will help protect submerged resources in shallower areas in the vicinity of the Dock. Fish populations in the immediate area of the Dock site may temporarily be affected during construction of the Dock; however, those impacts are not anticipated to be permanent. Additionally, as previously discussed, the Dock pilings must be wrapped with an impervious material to prevent leaching of pollutants into the water, and once installed, the pilings may provide habitat for fish and a substrate for benthic organisms. Provided that the conditions set forth in the draft Consolidated Authorization, as well as the recommendation regarding the smaller grassed area, are included in the final version of the Consolidated Authorization, it is determined that the construction and operation of the Dock will not adversely impact the value of functions provided to fish, wildlife, or to listed species or their habitat.16/ Impact on Navigation Petitioners assert that the Dock will constitute a hazard to navigation in the northeast portion of Crooked Lake. Specifically, they assert that because the Dock will extend out approximately 204 feet into the Lake, it necessarily will create a navigational hazard to boaters in the vicinity. As support, Petitioners presented evidence consisting of Steven Howard's testimony that an inner tube on which his nephew was riding, that was being pulled behind a motor boat, collided with the Gerards' 84-foot-long floating dock adjacent to Howard's riparian area. Petitioners argue that if an 84-foot-long dock creates a navigational hazard, a 204-foot-long dock would create an even greater navigational hazard. The undersigned does not find this argument persuasive. The portion of Crooked Lake on which the Dock is proposed to be located is approximately a mile and a half to two miles long and one-half to three-quarters of a mile wide. Although this portion of Crooked Lake experiences substantial boat traffic, the evidence shows that the Lake is sufficiently large in this area, even with the Dock in place, to allow safe navigation. To this point, it is noted that there are two other longer docks in the northeastern portion of Crooked Lake, extending 220 and 244 feet into the Lake from the shoreline. There was no evidence presented showing that either of these docks constitutes a navigational hazard.17/ Petitioners also assert that during periods of high water in this portion of Crooked Lake, the Dock will be underwater and thus will present a navigational hazard. In support, they presented photographs taken on October 30, 2017—— approximately six weeks after Hurricane Irma struck central Florida——showing ten docks, out of the 109 docks on Crooked Lake, that were partially or completely submerged.18/ When the photographs were taken, the approximate water elevation was 119.2 feet NGVD. All or a portion of the submerged docks had been constructed at or below the 119.2-foot NGVD elevation. The docks without roofs were mostly or completely invisible under the water. However, for the roofed docks, the roofs remained visible above the water even when their docking platforms were submerged. Here, although the walkway and lower platform of Howard's Dock is proposed to be constructed at an elevation of 121 feet NGVD, the roof will be constructed at an elevation of 129 feet NGVD. Thus, even during the relatively infrequent periods19/ during which the water level in Crooked Lake may exceed 121 feet NGVD, the platform roof will still be visible to vessels navigating in this portion of the Lake. Additionally, the Consolidated Authorization contains a specific condition requiring the waterward end of the Dock to be marked with a sufficient number of reflectors to be visible from the water at night by reflected light. This condition provides additional assurance that the Dock will not present a navigational hazard. For these reasons, it is determined that the Dock will not adversely affect navigation. Other ERP-Related Issues The evidence did not show that the Dock is proposed to be located in or proximate to a "work of the District," as defined in section 373.019(28). The only "work of the District" about which evidence was presented is the weir located south of Crooked Lake. This structure is many thousands of feet south of the Dock. There was no evidence presented showing that the Dock would have any impact on this weir. The Dock, as proposed, was designed by an experienced professional contractor who has designed and installed many docks on Crooked Lake, and, as such, is anticipated to function as proposed. The Dock must be built according to engineering diagrams to the Consolidated Authorization, and as-built drawings must be submitted when Dock construction is complete so that DEP can confirm that the Dock is constructed in accordance with the approved design. The evidence establishes that Howard, as the applicant, and Rickman, as the professional contractor in charge of construction, are financially, legally, and administratively capable of ensuring that the activity will be undertaken in accordance with the terms and conditions of the Consolidated Authorization. No evidence to the contrary was presented. The Dock will be located in the waters of Crooked Lake and will be affixed to the submerged bottom. The Department of State, Division of Historical Resources ("DHR"), did not provide any comments indicating that historical or archaeological resources are anticipated to be impacted by the project. Additionally, the Consolidated Authorization contains a general condition requiring subsurface activity associated with construction of the Dock to immediately cease, and DHR to be contacted, if any prehistoric or historic artifacts, such as pottery or ceramics, stone tools or implements, dugout canoes, or other physical remains that could be associated with Native American cultures or early colonial or American settlements are encountered at any time within the project site area. Additional Recommended Conditions Based on the foregoing, the undersigned recommends that the following specific conditions be included in the Consolidated Authorization, Permit No. 53-0351424-001-EI: A minimum six-inch clearance shall be maintained between the top of all submerged resources and the deepest draft of the cradle of the boat lift while in use. For purposes of this condition, submerged resources consist of the bottom sediment and/or any submerged grasses or other aquatic organisms. Any emergent grasses in the permittee's riparian area shall be avoided during the construction and operation of the Dock. If it is not feasible to avoid these grasses, an environmental assessment of the grassed area shall be performed and submitted to the Department prior to commencing construction, so that the value of this grassed area, if any, to fish, wildlife, and listed species can be evaluated and the extent to which minimization and/or compensatory mitigation is appropriate can be determined. Clearly in the Public Interest Florida Administrative Code Rule 62-4.070, Standards for Issuing or Denying Permits, states in pertinent part: A permit shall be issued to the applicant upon such conditions as the Department may direct, only if the applicant affirmatively provides the Department with reasonable assurance based on plans, test results, installation of pollution control equipment, or other information, that the construction, expansion, modification, operation, or activity of the installation will not discharge, emit, or cause pollution in contravention of Department standards or rules. In addition to the foregoing permitting requirements, because the Dock is proposed to be located in an OFW, Howard also must provide reasonable assurance that the Dock meets the "clearly in the public interest" standard. The "clearly in the public interest" standard does not require the applicant to demonstrate need for the project or a net public benefit from the project. Rather, this standard requires the applicant to provide greater assurances, under the circumstances specific to the project, that the project will comply with the applicable permitting requirements.20/ For the reasons discussed above, and with the inclusion of the additional recommended conditions in paragraphs 73.A. and 73.B., it is determined that the proposed Dock meets the applicable permitting requirements and the "clearly in the public interest" standard for issuance of the ERP. Impacts Assessment for Sovereignty Submerged Lands Lease Water-Dependency of the Proposed Dock A water-dependent activity is one which can only be conducted in, on, over, or adjacent to water areas because the activity requires direct access to the water body or sovereignty submerged lands for specified activities, including recreation, and where the use of water or sovereignty submerged lands is an integral part of the activity. See Fla. Admin. Code R. 18-21.003(71). Petitioners argue that the Dock will not constitute a water-dependent activity because the depth of water in the slips may, at times, be insufficient to allow operation of Howard's vessels while complying with the requirement that a minimum 12- inch clearance be maintained between the lowest draft of the vessel and submerged resources. The undersigned finds this argument unpersuasive. The Dock is being constructed specifically for the purpose of enabling Howard to use her vessels for boating——a recreational activity for which use of the water indisputably is an integral part. The Dock's primary purpose is to moor vessels that will be used for the water-dependent recreational activities of boating and fishing, and other water-dependent recreational uses of the Dock include fishing, swimming and sunbathing. Case law interpreting the Florida Administrative Code Chapter 18-21 makes clear that because docks are used for mooring vessels or conducting other in-water recreational uses, they are "water-dependent" activities for purposes of the rules.21/ Thus, even if water depths in the Dock's slips are at times insufficient for vessel mooring or launching,22/ this does not render the Dock not a "water-dependent activity." Resource Management Requirements The preempted area of the Lease is proposed to be used for a Dock that will be used for boating, fishing, and swimming. These traditional in-water recreational uses are consistent with the management purposes of sovereignty submerged lands as described in rule 18-21.004(2)(a). With the inclusion of the conditions currently proposed in the draft Consolidated Approval, as well as the recommended conditions in paragraphs 73.A. and 73.B., the undersigned determines that the Dock will not result in adverse impacts to sovereignty submerged lands and associated resources. With the inclusion of the conditions currently proposed in the draft Consolidated Approval, as well as the recommended conditions in paragraphs 73.A. and 73.B., the undersigned determines that the Dock is designed to minimize or eliminate impacts to fish and wildlife habitat and submerged resources. With the inclusion of the currently proposed conditions in the draft Consolidated Authorization, as well as the recommended conditions set forth in paragraphs 73.A. and 73.B., it is determined that the Dock, as designed and constructed, will minimize or eliminate cutting, removal, or destruction of wetland vegetation. Additionally, as discussed above, the proposed Consolidated Approval requires the avoidance of adverse impacts to historic and cultural resources. Riparian Rights Consistent with rule 18-21.004(3)(d), the Dock is proposed to be constructed in Howard's riparian area and will be set back more than 25 feet from the northerly and southerly riparian lines shown on the Survey. Rule 18-21.004(3)(a) prohibits activities authorized under chapter 18-21 from being implemented in a manner that would unreasonably infringe on traditional common law riparian rights, as defined in section 253.141, of upland owners adjacent to sovereignty submerged lands. Similarly, rule 18-21.004(3)(c) requires all structures and activities to be designed and conducted in a manner that will not unreasonably restrict or infringe upon the riparian rights of adjacent riparian owners. Collectively, these provisions prohibit an activity that will occur on sovereignty submerged lands from unreasonably infringing on or unreasonably restricting the riparian rights of upland riparian owners. Riparian rights are rights appurtenant to, and inseparable from, riparian land that borders on navigable waters. § 253.141, Fla. Stat.; Broward v. Mabry, 50 So. 830 (Fla. 1909). At common law, riparian rights include the rights of navigation, fishing, boating, and commerce. Hayes v. Bowman, 91 So. 2d 795 (Fla. 1957). The right of navigation necessarily includes the right to construct and operate a dock to access navigable waters. Belvedere Dev. Corp. v. Dep't of Transp., 476 So. 2d 649 (Fla. 1985); Shore Vill. Prop. Owners' Ass'n v. Dep't of Envtl. Prot., 824 So. 2d 208, 211 (Fla. 4th DCA 2002). Common law riparian rights also include the right to an obstructed view. Lee Cnty v. Kiesel, 705 So. 2d 1013 (Fla. 2d DCA 1998). Many of these common law riparian rights have been statutorily codified in section 253.141. Statutory riparian rights include the "rights of ingress, egress, boating, bathing, and fishing and such others as may be or have been defined by law." § 253.141(1), Fla. Stat. At issue in this case are the competing riparian rights of next-door neighbors——i.e., Howard's right to wharf out to navigable waters for purposes of boating and other water- dependent recreational activities, and the Gerards' right to an unobstructed view. The question is whether Howard's proposed construction and operation of a dock of sufficient length to enable her to use her boats would unreasonably infringe on or unreasonably restrict the Gerards' right to an unobstructed view of the Lake. By virtue of the riparian rights appurtenant to Howard's riparian property, she is entitled to wharf out to water deep enough to enable her to navigate. She owns two boats, one of which pulls a draft of 25 inches, and the other, a draft of 20 inches, which she uses to navigate the Lake. Thus, an essential aspect of Howard's riparian right of navigation is her ability to construct and operate a dock long enough to enable her to reach water depths sufficient to use these boats. However, as noted above, this right is not unfettered. Howard's exercise of her riparian navigation right cannot unreasonably infringe on Gerard's right to an unobstructed view. Florida case law holds that the right to an "unobstructed" view does not entail a view free of any infringement or restriction whatsoever by neighboring structures or activities. In Hayes, the court defined the right as "a direct, unobstructed view of the [c]hannel and as well a direct, unobstructed means of ingress and egress . . . to the [c]hannel." Id. at 801 (emphasis added). The court then prescribed the rule that "in any given case, the riparian rights of an upland owner must be preserved over an area 'as near as practicable' in the direction of the [c]hannel so as to distribute equitably the submerged lands between the upland and the [c]hannel." Id. (emphasis added). To the extent there is no channel in this portion of the Lake, Hayes dictates that riparian rights must be apportioned equitably, so that a riparian owner's right to an unobstructed view can extend only from the owner's property in the direction of the center of the Lake. Kling v. Dep't of Envtl. Reg., Case No. 77-1224 (Fla. DOAH Oct. 6, 1977; Fla. DER Nov. 18, 1977) at ¶¶ 11-12 (emphasis added). Here, no evidence was presented showing that the Dock——which will be located immediately south and east of the Gerards' riparian property and attendant riparian area——will present an obstruction to the Gerards' view of the Lake channel. Additionally, the evidence did not establish that Howard's Dock would obstruct the Gerards' view of the center of the northeast portion of Crooked Lake, which is located west and slightly south of their property.23/ Administrative precedent in Florida provides additional support for the determination that the Dock will not unreasonably infringe on the Gerards' right to an unobstructed view. In O'Donnell v. Atlantic Dry Dock Corporation, Case No. 04-2240 (Fla. DOAH May 23, 2005; Fla. DEP Sept. 6, 2005), riparian owners challenged the proposed approval of expansions of sovereignty submerged lands leases authorizing Atlantic Dry Dock, a neighboring commercial shipyard, to expand its shipyard facilities and install new docking facilities. The administrative law judge noted that although the expanded shipyard would further encroach on the riparian owners' already somewhat-restricted view from their property, it would not substantially and materially obstruct the Petitioners' view to the channel. He commented: "it [their view] may be further obstructed to the west in the direction of the Atlantic Marine yard, but not in the direction of the channel." To that point, he found that although "any lateral encroachment on the Petitioners' line-of-sight to the channel by the large eastern dry dock proposed will be an annoyance, . . . [it] will not rise to the level of a substantial and material interference or obstruction of the Petitioners' view to the channel." Id. at ¶ 119. He found that "there is no 'special riparian right' to a view of the sunset, just as there was no right to a particular object of view . . . by the riparian owners complaining in the Hayes case." Id. at ¶ 120. Castoro v. Palmer, Case Nos. 96-0736, 96-5879 (Fla. DOAH Sept. 1, 1998; Fla. DEP Oct. 19, 1998), also is instructive. In Castoro, neighboring riparian owners challenged the proposed issuance of an environmental approval and sovereignty submerged lands lease for a 227-foot-long dock having a terminal platform with boat lift. The owners contended that due to the dock's length, it would impermissibly obstruct their views of the water. The administrative law judge rejected that contention, distinguishing the circumstances from those in Lee County v. Kiesel, 705 So. 2d 1013 (Fla. 2d DCA 1998), in which the construction of a bridge that blocked 80 percent of the riparian owners' view of the channel was held to constitute a "substantial and material" obstruction to the riparian right of view. The ALJ noted that although the dock would have "some impact on the neighbors' views" and their use of the waterbody, it did not unreasonably impact their riparian rights to an unobstructed view or to use of the waterbody. Id. at ¶¶ 73-74. In Trump Plaza of the Palm Beaches Condominium v. Palm Beach County, Case No. 08-4752 (Fla. DOAH Sept. 24, 2009; Fla. DEP Oct. 8, 2009), a condominium association challenged the proposed issuance of a sovereignty submerged lands use approval to fill in a dredged area and create mangrove islands in the Lake Worth Lagoon, alleging, among other things, that the creation of the mangrove islands would unreasonably infringe on their riparian right to an unobstructed view. In rejecting this position and recommending issuance of the submerged lands use approval, the ALJ noted that the area obstructed by the mangrove islands would be negligible compared to the remaining expanse of the view, and further noted that the owners' real concern was directed at the aesthetics of the project——specifically, they did not want to view mangrove islands. The ALJ stated: "[t]he evidence supports a finding that while the project will undoubtedly alter the view of the water from [the riparian owners' property], the impact on view is not so significant as to constitute an unreasonable infringement of their riparian rights." Id. at ¶ 86. Applying these case law principles, it is determined that the Dock will not unreasonably infringe on or unreasonably restrict the Gerards' riparian right to an unobstructed view. To that point, the cases make clear that the right to an "unobstructed" view is not an unfettered right to a view of the water completely free of any lateral encroachment, but, instead is the right of a view toward the channel or the center of a lake without unreasonable infringement or restriction. Here, although the Dock will laterally encroach on the Gerards' full panoramic view of the Lake——and, as such, may even constitute an annoyance, the evidence did not show that the Dock will obstruct or otherwise restrict their view to the channel or the center of the Lake. Moreover, to the extent the Gerards have expressed concern about the Dock interfering with their view of the south shore of the Lake, O'Donnell makes clear the desire to have a particular object of view——here, the south shore of the Lake——is not a legally protected riparian right. It is also found that the Dock will not unreasonably interfere with the Gerards' riparian rights of ingress, egress, boating, or navigation. As previously noted, the Dock will be located at least 25 feet inside the riparian lines established for Howard's upland property, and, it will not be constructed in a location or operated in a manner that will obstruct, interfere with, or restrict the Gerards' access to the Lake or to sufficient water depths to enable navigation.24/ The evidence also did not establish that the Dock will restrict or otherwise interfere with the Gerards' use of their riparian area for ingress and egress, boating, fishing, bathing, or other riparian uses. In sum, it is concluded that the Dock will not unreasonably infringe on or restrict the riparian rights of adjacent upland riparian owners. Accordingly, it is determined that the Dock will meet the requirements and standards in rule 18-21.004(3) regarding riparian rights. Navigational Hazard For the reasons discussed in paragraphs 63 through 67, it is determined that the Dock will not constitute a navigational hazard in violation of rule 18-21.004(7)(g). Not Contrary to the Public Interest Rule 18-21.004(1)(a) requires an applicant to demonstrate that an activity proposed to be conducted on sovereignty submerged lands will not be contrary to the public interest. To meet this standard, it is not necessary that the applicant show that the activity is affirmatively in the "public interest," as that term is defined in rule 18-21.003(51). Rather, it is sufficient that the applicant show that there are few, if any, "demonstrable environmental, social, and economic costs" of the proposed activity. Castoro, at ¶ 69. For the reasons discussed above, and with the inclusion of the additional recommended conditions in paragraphs 73.A. and 73.B., it is determined that the proposed Dock meets the "not contrary to the public interest" standard required for issuance of the Lease. Demonstration of Entitlement to ERP Howard met her burden under section 120.569(2)(p) to present a prima facie case of entitlement to the ERP by entering into evidence the Application, the Notice of Intent, and supporting information regarding the proposed Dock. She also presented credible, competent, and substantial evidence beyond that required to meet her burden under section 120.569(2)(p) to demonstrate prima facie entitlement to the ERP. The burden then shifted to Petitioners to demonstrate, by a preponderance of the competent substantial evidence, that the Dock does not comply with section 373.414 and applicable ERP rules. For the reasons discussed above, it is determined that Petitioners did not meet their burden of persuasion under section 120.569(2)(p) in this proceeding. Accordingly, for the reasons addressed above, it is determined that Howard is entitled to issuance of the ERP for the Dock. Demonstration of Entitlement to Lease As previously discussed, Howard bore the burden of proof in this proceeding to demonstrate, by a preponderance of the evidence, that the Dock meets all applicable statutory and rule requirements for issuance of the Lease for the Dock. For the reasons discussed above, it is determined that Howard met this burden, and, therefore, is entitled to issuance of the sovereignty submerged lands lease for the Dock. Petitioners' Standing Defenders' Standing As stipulated by the parties and noted above, Defenders is an incorporated non-profit entity created for the primary purpose of protecting and preserving Crooked Lake so that it may remain an OFW for all members of the public to enjoy. Defenders has been in existence since at least the mid- 1980s. Robert Luther, the president of Defenders, testified that the organization's purpose also entails providing education and promoting public awareness in order to preserve the natural beauty, water quality, ecological value, and quality of life around Crooked Lake. As stipulated by the parties and noted above, Defenders has more than 25 members. Luther testified that Defenders has approximately 100 family members, most of whom live on or around Crooked Lake. He noted that many of Defenders' members own boats, which they park at a local boat landing on the Lake. Based on this testimony, it is inferred that these members operate their boats on Crooked Lake. After receiving the public notice of the project, Defenders' board of directors voted to oppose issuance of the Consolidated Authorization for the Dock. Luther testified that the board's decision was based on the determination that "it was clearly within the public interest" to oppose the Dock. Gerards' Standing The Gerards reside at 1055 Scenic Highway, Babson Park, Florida. Their riparian property is immediately adjacent to, and northwest of, Howard's property. The Gerards own a floating dock that is located within their riparian area.25/ The dock consists of two 4-foot- wide by 30-foot-long ramps attached to a 24-foot-long by 8-foot- wide pontoon boat. Priscilla Gerard testified that she enjoys spending time sitting and reading books on the beach in front of her property, and that having that area to sit and read is a significant aspect of her enjoyment of her lakefront property. Ms. Gerard observed that extensive boating activities in the northeast portion of the Lake on weekends is disruptive, and interferes with her use of her beach for relaxing and reading. She particularly noted that boats operating very close to the shore cause waves to splash up on her beach, interfering with her ability to sit and read close to the shore. She did not contend that Howard's use of the Dock for boating would contribute to the disruptive nature of existing boat traffic in the vicinity. Ms. Gerard has viewed the plans for the proposed Dock and is very concerned that due to its size, her view of the south side of the Lake will be completely blocked. She acknowledged, and other competent, credible evidence showed, that there are other docks on the Lake in the vicinity of her riparian property. The evidence shows that existing docks having lengths of 145 feet and 170 feet are located in the vicinity of, and are visible from, the Gerards' property. She testified that an existing dock and tiki hut block her view of the Lake to the north. She acknowledged that although Howard's Dock, if constructed as proposed, may somewhat obstruct her view to the left (south) of her property, it would not block her view straight out into the Lake. Phillip Gerard testified that he has boated extensively on Crooked Lake in a variety of vessel types. He further testified that he has observed a range of boating practices on Crooked Lake, including seeing water skiers and persons being towed behind motorized vessels on inner tubes and other types of "towables." He testified that, based on his personal observations, persons being towed do not have independent control of the speed or direction of the "towable"; thus, depending on the direction in which the towing vessel turns, the towable may be slung to the left or the right. Gerard commented that such lack of control could result in a person riding on a towable colliding with a dock, and he noted that Howard's nephew, who was riding on an inner tube being towed by a boat, was involved in such a collection with his (Mr. Gerard's) own dock. Mr. Gerard did not testify that the Dock would present a navigational hazard to, or otherwise interfere with, the Gerards' riparian right of ingress and egress. Neither of the Gerards testified that the Dock would impact their ability to access navigable waters in the Lake. Mr. Gerard acknowledged that if Howard's Dock were constructed, boats that currently travel very close to the shoreline of his property would be forced to swing further out in the Lake, away from his riparian shoreline, in order to avoid the Dock.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order approving the issuance of Consolidated Environmental Resource Permit and Recommended Intent to Grant Sovereignty Submerged Lands Authorization, Permit No. 53-0351424-001-EI, on the terms and conditions set forth in the Consolidated Notice of Intent and attached draft of Permit No. 53-0351424-001-EI, as modified to include the Additional Recommended Conditions set forth in paragraphs 73.A. and 73B. DONE AND ENTERED this 5th day of July, 2018, in Tallahassee, Leon County, Florida. S CATHY M. SELLERS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of July, 2018.

Florida Laws (21) 120.52120.569120.57120.6820.331253.001253.002253.115253.141267.061373.019373.042373.086373.4132373.414373.421373.427403.031403.061403.41290.202 Florida Administrative Code (5) 18-21.00318-21.00462-302.40062-4.00162-4.070
# 9
SHIRLEY B. HAYNES vs KGB LAKE HOWELL, LLC, AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 01-004250 (2001)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Oct. 30, 2001 Number: 01-004250 Latest Update: Mar. 31, 2003

The Issue The issue is whether an Environmental Resource Permit should be issued to KGB Lake Howell, LLC, authorizing the construction of a surface water management system to serve an apartment complex known as the Estates at Lake Howell in the City of Casselberry, Florida.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In this proceeding, Respondent, St. Johns River Water Management District (District), proposes to issue an Environmental Resource Permit to Respondent, KGB Lake Howell, LLC (Applicant), authorizing the construction of a stormwater management system to serve a 240-unit apartment complex known as the Estates of Lake Howell. The project will be located on an undeveloped tract of land in the City of Casselberry (City), Seminole County, Florida, just north of the Orange County line. It will include ten three-story buildings, parking, clubhouse/ administration building, amenity complex, and wet detention pond. The project also incorporates a 3.62-acre stormwater pond, now owned and used by Seminole County (County), lying east of Lake Ann Lane across from the project site, which was included in the overall acreage calculations for the purpose of increasing apartment density on the site. The Applicant has authorization from the County to apply for the permit incorporating that tract of land. The pond will continue to function as a stormwater facility for the County and will not accommodate stormwater from the project site. The project site consists of 38.9 acres located on the north side of Howell Branch Road, east of State Road 436 (also known as Semoran Boulevard), and west of Lake Ann Lane in the City. The site is currently undeveloped and includes an abandoned orange grove and upland pine flatwoods community, which make up approximately 14.6 acres, while the remaining 24.3 acres is a mixed forested wetland system. The property is now owned by the Harold Kasik Living Trust (Kasik property), which has a contract for purchase with the Applicant. The Kasik property is in the shape of a rectangle, 648 feet by 2,530 feet, with its long sides running north- south. It is bordered on the north and east by single-family residential and vacant land, to the south by commercial development, and to the west by high-density residential and commercial development. The property has a high elevation of approximately 83 feet on its southeastern corner and falls to the north/northeast, where the edge of the wetland system is at an elevation of 63 or 64 feet. The major development constraint on the site is the large wetland tract on the northern portion of the property. In order to minimize proposed impacts to the wetlands, the Applicant proposed the transfer of the development entitlements from the County land to benefit the Applicant's property. More specifically, the Applicant will acquire the County property, the Applicant will simultaneously grant a perpetual drainage easement over the property to the County, the Applicant will maintain the landscaping of the property in perpetuity, the Applicant will convey around five acres of wetlands on the northern end of the Kasik property to the County in fee simple, and the City will allow the transfer of development rights from the property. The project will adversely impact 0.99 acres of low- quality wetlands, of which 0.72 acres are to be dredged and 0.27 acres are to be filled to provide the fencing around the wet detention facility. To offset this impact, the Applicant proposes to preserve 17.8 acres of forested wetlands, plus 1.2 acres of forested uplands, or a mitigation ratio of 18:1. The District's guidelines for preservation mitigation applicable to this project are 10:1 to 60:1 for wetland impacts and 3:1 to 20:1 for upland impacts; thus, the mitigation plan falls within these guidelines. Under current conditions, stormwater runoff from the project site sheet flows into the on-site wetland and ultimately Lake Howell (the Lake), a Class III water body which meets all applicable water quality standards and is not an Outstanding Florida Water. After development occurs, stormwater from the developed portions of the property will be conveyed to a wet detention pond for required water quality treatment and peak discharge rate attenuation. After treatment in the detention pond, the water will discharge to the on-site wetland, as it does now, and eventually will be conveyed into the Lake. Off-site flows will continue to be conveyed into the on-site wetland. The wet detention pond, which has a minimum depth of twelve feet and a permanent pool of water with a mean depth of two to eight feet, has been designed to accommodate a 25-year, 24-hour storm. Post-development discharge will be less than pre-development, and the outfall structure has been designed to avoid channelization in the wetlands after the point of discharge. Since at least the late 1940's, Petitioner, Shirley Haynes, or her relatives, have owned, or resided on, a multi-acre tract of land just north of the project site at 2764 Lake Howell Lane. She has substantial frontage on the south side of the Lake. The southern portion of her property, which are wetlands, adjoins the northern boundary of the project site. For the past three years, Petitioner, Egerton van den Berg, has resided on a ten-acre tract of land at 1245 Howell Point, which is northeast of the project site. He has approximately 235 feet of frontage on the south side of the Lake. As argued in their Proposed Recommended Order, Petitioners generally contend that the application is "materially deficient" in several respects in violation of Rule 40C-4.101; that the Applicant has failed to satisfy Rule 40C-4.301(1)(c) and (d), which in turn constitutes a failure to meet the requirements of Rule 40C-4.302(1)(a)-(c); that the Applicant failed to satisfy the criteria in Sections 12.2.3(a)-(f), 12.2.1, 12.2.1.1, 12.2.1.3, 12.2.2.3(a)-(e), 12.2.2.4(a) and (b), 12.3.2.2(c), and 12.3.8(a) of the Applicant's Handbook: Management and Storage of Surface Waters (Applicant's Handbook); that the District did not adequately consider the cumulative impacts of the project as required by Section 373.414(8)(a), Florida Statutes; that a low flow analysis of the Lake was not performed, as required by Rule 40C-8.011(5); that the Applicant did not submit detailed mitigation plans as required by Section 12.3.3.2 of the Applicant's Handbook; that the 18:1 ratio for mitigation proposed by the Applicant is inappropriate; and that the District should not approve the density of the apartments established by the City. These concerns, to the extent they have been identified as issues in the parties' Pre-Hearing Stipulation, are addressed in the findings below. Where contentions have been raised by Petitioners, such as the placement of the detention pond over a depressional area, and they have not been argued in the Proposed Recommended Order, they have been deemed to be abandoned. Conditions for issuance of permits Rule 40C-4.301(1)(a)-(k), Florida Administrative Code, specifies eleven substantive requirements for which reasonable assurance must be given in order for a standard permit to be issued. Subsection (3) of the same Rule provides that the standards and criteria contained in the Applicant's Handbook shall determine whether the foregoing reasonable assurances have been given. Additional conditions for the issuance of a permit are found in Rule 40C-4.302(1) when the project, or any part of it, is located in, on, or over wetlands or other surface waters. Therefore, because a part of the Applicant's system will be located in wetlands, the Applicant must also give reasonable assurance that the project will not be contrary to the public interest, and that it will not cause unacceptable cumulative impacts upon the wetlands or surface waters. a. Rule 40C-4.301 Paragraphs (a)-(c) of the Rule require that an applicant provide reasonable assurance that the project will not cause adverse water quantity impacts to receiving waters and adjacent lands, adverse flooding to on-site or off-site property, or adverse impacts to existing surface water storage and conveyance capabilities. If a system meets the requirements of Section 10.2.1(a) through (d) of the Applicant's Handbook, there is a presumption that the system complies with the requirements of Paragraphs (a) through (c). This presumption has been met since the evidence supports a finding that the post- development peak rate of discharge will be lower than the pre- development peak rate of discharge for a 24-hour, 25-year storm event. Therefore, the Applicant's system meets the requirements of these Paragraphs. Paragraph (d) of the Rule requires that an applicant give reasonable assurance that the project "will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters." To satisfy this requirement, an applicant must also demonstrate compliance with the two-prong test in Sections 12.2.2 and 12.2.2.4 of the Applicant's Handbook. Section 12.2.2 requires that an applicant provide reasonable assurance that a regulated activity will not impact the values of wetlands and other surface water functions so as to cause adverse impacts to the abundance, diversity, and habitat of fish, wildlife, and listed species. In its proposal, the Applicant proposes to fill a total of 0.99 acres of wetlands. Since these impacts will eliminate the ability of the filled part of the on-site wetland to provide functions to fish and wildlife, the filling will cause adverse impacts. Under these circumstances, Section 12.2.1.1 requires that the Applicant either implement practicable design modifications to reduce or eliminate these adverse impacts or meet one of the exceptions under Section 12.2.1.2. Under Section 12.2.1.1, a proposed modification which is not technically capable of being done, is not economically viable, or which adversely affects public safety through the endangerment of lives or property is not considered practicable. The Applicant’s design for the proposed project went through a number of iterations prior to submittal to the District to reduce adverse impacts to the wetlands. During the permitting process, the District requested that the Applicant consider a number of other suggestions to reduce or eliminate the adverse impacts to wetlands such as adding a fourth floor to the apartment buildings to eliminate the need for one apartment building, building a parking garage for the tenants, and eliminating the tennis and volleyball courts. Because the Applicant provided detailed reasons why none of those suggestions were practicable, it was not required to implement any of those design modifications. In addition, the Applicant’s decision not to include a littoral zone around the stormwater pond did not increase the amount of wetland impacts as that engineering decision resulted in a stormwater pond that was simply deeper and not wider. Therefore, the Applicant has met the requirement to reduce or eliminate adverse wetland impacts. Section 12.2.1.1 only requires an elimination and reduction analysis when: (1) a proposed system will result in adverse impacts to wetland functions and other surface water functions so that it does not meet the requirements of Sections 12.2.2 through 12.2.3.7, or (2) neither one of the two exceptions within Section 12.2.1.2 applies. In determining whether one of the two exceptions in Section 12.2.1.2 applies, the District must evaluate the long- term ecological value of the mitigation proposed by the Applicant. If the mitigation is not adequate to offset the adverse impacts of the proposed system, then it is unlikely either exception in Section 12.2.1.2 will apply. As noted above, the Applicant’s proposed dredging and filling of the southern edge of the wetlands on the project site will eliminate the ability of that wetland area to provide functions to fish and wildlife. However, the Applicant’s mitigation plan of placing 17.8 acres of wetlands and 1.2 acres of uplands under a conservation easement to preserve that property in its natural state in perpetuity will fully replace the types of functions that the part of the wetlands proposed to be impacted provides to fish and wildlife. The mitigation plan will also offset the adverse impacts that this project will have on the value and functions provided to fish and wildlife by the impacted part of the wetlands. In this case, the first exception under Section 12.2.1.2(a) applies as it meets that Section's two requirements: the ecological value of the functions provided by the area of wetland to be adversely affected is low, and the proposed mitigation will provide greater long-term ecological value than the area or wetland to be adversely affected. Also, the quality of the wetland to be impacted is low. All of the proposed impacts will occur in the area of the wetland that was historically disturbed and in which nuisance and exotic species are prevalent. Due to nuisance and exotic vegetation, the ecological value provided by that area to wildlife is low. The mitigation for the proposed project will provide greater long-term ecological value to fish and wildlife than the part of the wetland proposed to be impacted because the proposed mitigation will preserve eighteen times more wetlands that are of higher quality and provide greater value than the wetland area to be impacted. The type of wetland to be preserved, a mixed forested wetland containing hardwoods, is rare for the area. Although the mitigation plan will provide greater long-term ecological value to fish and wildlife than the part of the wetland proposed to be impacted, the Applicant did not meet the second exception in the elimination and reduction rule under Section 12.2.1.2(b) because the wetlands to be preserved are not regionally significant. In addition to meeting the elimination and reduction rule through implementation of practicable design modifications, the Applicant also satisfied the same rule by meeting the first exception found in Section 12.2.1.2(a). Thus, the Applicant has satisfied Section 12.2.2, which is the first prong of the test to determine compliance with Paragraph (d). The second prong of the test to determine whether Paragraph (d) of the Rule has been satisfied is found in Section 12.2.2.4. That Section requires that an applicant give reasonable assurance that the activity will not change the hydroperiod of a wetland so as to affect wetland functions. For the following reasons, that prong of the test has been satisfied. Since the wetlands are primarily groundwater-influenced, the construction of the stormwater pond between the project and the wetlands will not adversely affect the wetlands. As the soils surrounding the pond are very porous with a high infiltration and percolation rate, water from the stormwater pond will still reach the wetlands through lateral seepage. Further, the Applicant will install an energy dissipating device on the outfall spout at the point of discharge so that water will be spread out from the stormwater pond as it discharges into the receiving wetlands. As noted earlier, this will prevent an adverse channelization effect. Finally, stormwater runoff from the surrounding basins that currently discharge into the wetlands will not be affected by the construction of the stormwater system. That runoff will continue to flow into the wetlands on the project site. Because the Applicant has satisfied Sections 12.2.2 and 12.2.2.4, Paragraph (d) of the Rule has been met. Paragraph (e) of the Rule generally requires that an applicant provide reasonable assurance that a project will not adversely affect the quality of receiving waters. Here, the Applicant has provided such assurance. This is because the system has been designed in accordance with all relevant District criteria. Also, the Applicant has proposed to revise Permit Condition 26 as follows: Condition 26. This permit authorizes construction and operation of a surface water management system as shown on the plans received by the District on June 14, 2001, and as amended by plan sheet C4 (Sheet 07 of 207) received by the District on January 23, 2002. In view of this revision, the Applicant's wet detention system complies with all of the design criteria contained in Rule 40C-42.026(4). Under Rule 40C-42.023(2)(a), compliance with the design criteria contained in Rule 40C-42.026 creates a presumption that state water quality standards, including those for Outstanding Florida Waters, will be met. This presumption has not been rebutted; therefore, the requirements of Paragraph (e) of the Rule have been satisfied. Further, Sections 12.2.4.1 and 12.2.4.2 state, in part, that reasonable assurance regarding water quality must be provided both for the short term and the long term, addressing the proposed construction, alteration, operation, maintenance, removal, and abandonment of the system. The Applicant has provided reasonable assurance that this requirement is met through the design of its surface water management system, its long-term maintenance plan for the system, and the long and short-term erosion and turbidity control measures it proposes. If issued, the permit will require that the surface water management system be constructed and operated in accordance with the plans approved by the District. The permit will also require that the proposed erosion and turbidity control measures be implemented. Section 12.2.4.5 does not apply because there are no exceedances of any water quality standards at the proposed receiving water. Also, Sections 12.2.4.3 and 12.2.4.4 do not apply because the Applicant has not proposed any docking facilities or temporary mixing zones. Paragraph (f) of the Rule requires that an applicant not cause adverse secondary impacts to the water resources. Compliance with this requirement is determined by applying the four-part test in Section 12.2.7(a) through (d). As to Section 12.2.7(a), there are no secondary impacts from construction, alteration, and intended or reasonably expected uses of the proposed system that will cause water quality violations or adverse impacts to the wetland functions. The Applicant chose not to provide buffers abutting the wetlands but rather chose measures other than buffers to meet this requirement. The Applicant has provided reasonable assurance that secondary impacts will not occur by placing the stormwater pond between the planned project and the wetlands, so that the pond itself will serve as a buffer by shielding the wetland from the lighting and noise of the project, and by acting as a barrier to keep domestic animals out of the wetlands. In addition, the Applicant increased the amount of property to be preserved as mitigation by adding 2.97 acres of wetlands and 1.2 acres of uplands to the mitigation plan to mitigate for any remaining secondary impacts. Accordingly, the first part of the secondary impacts test in Section 12.2.7(a) is satisfied. As to Section 12.2.7(b), because there is no evidence that any aquatic or wetland-dependent listed animal species use uplands for existing nesting or denning adjacent to the project, the second part of the test has been met. No adverse secondary impacts will occur under the third part of the test in Section 12.2.7(c) because the proposed project will not cause impacts to significant historical or archaeological resources. Finally, adverse secondary impacts as proscribed by Section 12.2.7(d) will not occur because no evidence was presented that there would be additional phases or expansion of the proposed system or that there are any onsite or offsite activities that are closely or causally linked to the proposed system. Therefore, the proposed project satisfies Paragraph (f) of the Rule. Paragraph (g) of the Rule requires that an applicant provide reasonable assurance that a project will not adversely impact the maintenance of surface or ground water levels or surface water flows established in Chapter 40C-8. Minimum (but not maximum) surface water levels have been established for the Lake pursuant to Chapter 40C-8 for the basin in which the project is located. The project will not cause a decrease of water to, or cause a new withdrawal of water from, the Lake. Therefore, the project satisfies this requirement. Finally, Petitioners have acknowledged in their Proposed Recommended Order that the Applicant has given reasonable assurance that the requirements of Paragraphs (h), (i), (j), and (k) have been met. The parties have also stipulated that the receiving water (Lake Howell) meets all Class III water quality standards. Therefore, the project satisfies the requirements of Subsection 40C-4.301(2). Rule 40C-4.302 - Public Interest Test Under Rule 40C-4.302(1)(a)1.-7., an applicant must provide reasonable assurance that the parts of its surface water management system located in, on, or over wetlands are not contrary to the public interest. Similar requirements are found in Section 12.2.3. The Applicant has provided reasonable assurance that the parts of the project that are located in, on, or over wetlands (mainly the detention pond and fill) are not contrary to the public interest, because the evidence showed that all seven of the public interest factors to be balanced are neutral. Because the proposed permanent mitigation will offset the project’s adverse impacts to wetlands, no adverse effects to the conservation of fish and wildlife due to the project’s permanent nature will occur. The evidence also showed that best management practices and erosion control measures will ensure that the project will not result in harmful erosion or shoaling. Further, it was demonstrated that the project will not adversely affect the flow of water, navigation, significant historical or archaeological resources, recreational or fishing values, marine productivity, or the public health, safety, welfare or property of others. Finally, the evidence showed that the project’s design, including permanent mitigation, will maintain the current condition and relative value of functions performed by parts of the wetland proposed to be impacted. Therefore, the project meets the public interest criteria found in Rule 40C-4.302(1)(a). Rule 40C-4.302(1)(b) - Cumulative Impacts Rule 40C-4.302(1)(b) and Section 12.2.8 require that an applicant demonstrate that its project will not cause unacceptable cumulative impacts upon wetlands and other surface waters within the same drainage basin as the regulated activity for which the permit is being sought. Under this requirement, if an applicant proposes to mitigate the adverse impacts to wetlands within the same drainage basin as the impacts, and if the mitigation fully offsets these impacts, the District will consider the regulated activity to have no unacceptable cumulative impacts upon wetlands and other surface waters. The Applicant has chosen to mitigate for the impacts to 0.99 acres of wetlands by preserving 17.8 acres of wetlands and 1.2 acres of uplands on-site. Since this mitigation will occur in the same drainage basin as the impacts and the mitigation fully offsets those impacts, the Applicant satisfies the requirements of the Rule. Rule 40C-4.302 - Other Requirements The parties have stipulated that the requirements of Paragraphs (c) and (d) of Rule 40C-4.302(1) do not apply. There is no evidence that the Applicant has violated any District rules or that it has been the subject of prior disciplinary action. Therefore, the requirements of Subsection (2) of the Rule have been met. Miscellaneous Matters County Pond Site The Seminole County pond site located on the east side of Lake Ann Lane and across the street from the project is not a jurisdictional wetland and does not have any wetland indicators. It is classified as an upland cut surface water. The Applicant is not proposing to impact any wetlands at the pond site, and the site is not part of the proposed mitigation plan for the project. The permit in issue here is not dependent on the pond site, and nothing in the application ties the project with that site. Indeed, the transfer of density rights from the County property is not relevant to the District permitting criteria. Review of Application When the decision to issue the permit was made, the District had received all necessary information from the Applicant to make a determination that the project met the District's permitting criteria. While certain information may have been omitted from the original application, these items were either immaterial or were not essential to the permitting decision. The application complies with all District permitting criteria. Contrary to Petitioners' contention, the Applicant does not have to be the contract purchaser for property in order to submit an application for that property. Rather, the District may review a permit application upon receipt of information that the applicant has received authorization from the current owners of the property to apply for a permit. In this case, the Applicant has the permission of the current owners (the Harold Kasik Living Trust).

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order granting the requested permit as described above. DONE AND ENTERED this 29th day of March, 2002, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of March, 2002. COPIES FURNISHED: Kirby B. Green, III, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Shirley B. Haynes 2764 Lake Howell Road Winter Park, Florida 32792-5725 Egerton K. van den Berg 1245 Howell Point Winter Park, Florida 32792-5706 Charles A. Lobdell, III, Esquire St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Meredith A. Harper, Esquire Shutts & Bowen Post Office Box 4956 Orlando, Florida 32802-4956

Florida Laws (3) 120.569120.57373.414