The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.
The Issue The issue in this case is whether Respondent properly rejected the bid of Petitioner.
Findings Of Fact Respondent issued on February 28, 1990, an invitation to bid concerning the installation of bleachers at a high school ("ITB"). The ITB was duly advertised. Among the bidders was Interkal, Inc., which is a manufacturer of bleachers. The Interkal bid, which was timely submitted, was executed by its president. The Interkal bid contained a bid bond naming Interkal as principal and a certification from the secretary of Interkal reflecting a corporate resolution authorizing the execution of all bid documents on behalf of Interkal by its corporate officers. The Interkal bid disclosed two subcontractors. The supplier was shown as Interkal, and the erector was shown as Petitioner. Petitioner is the authorized factory representative for Interkal in Florida. As such, Petitioner solicits business and installs and removes bleachers on behalf of Interkal. As compensation, Petitioner receives commissions for such work from Interkal. However, the shareholder and chief executive officer of Petitioner is not a shareholder or officer of Interkal. In addition, Petitioner is not authorized to execute bid documents on behalf of Interkal. Petitioner is no more than a Subcontrator of Interkal. The bidder in this case was Interkal, not Petitioner, even though Petitioner handled much of the paperwork or its manufacturer. When an unrelated bidder was awarded the contract, Petitioner filed a formal written protest in its name. Interkal has not participated as a party in the subject proceeding.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that Respondent enter a Final Order dismissing the petition of Diversified Design Enterprises. ENTERED this 22nd day of May, 1990, in Tallahassee, Florida. ROBERT D. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of May, 1990. COPIES FURNISHED: Ned N. Julian Stenstrom, McIntosh, et al. P.O. Box 1330 Sanford, FL 32772-1330 William Merkel, President Diversified Design Enterprises 321 N.E. Second Avenue Delray Beach, FL 33444 Robert W. Hughes, Superintendent Seminole County School Board 1211 Mellonville Avenue Sanford, FL 32771
Findings Of Fact On or about December 29, 1981, the College solicited sealed bids for construction of alterations and additions to the Technical and Gymnasium Buildings located on its campus in Madison, Florida. In response, seven general contractors submitted bids. (P-1, P-2, P-3.) Bids were publicly opened on February 9, 1982. Griffin Construction, with a bid of $536,575, was the apparent low bidder; the second lowest bidder was Long Contractors, with a bid of $539,512. (Testimony of Griffin, Sims, Rutherford; P-3, P-4, P-5.) After the low bid was identified, Tom McClanahan, representing Long Contractors, asked that the subcontractor list accompanying the low bid be opened. Griffin Construction's subcontractor list was then opened. McClanahan asked if the license and charter numbers of the subcontractors were listed. 2/ Upon learning that these numbers were not included on Griffin Construction's subcontractor list, McClanahan protested. (Testimony of Sims, Rutherford, Griffin.) At its February 15, 1982, meeting, the College District Board of Trustees ("Board") rejected the low bid of Griffin Construction on the sole ground that the omission of subcontractor license and charter numbers constituted a failure to comply with the conditions of the bid documents. 3/ The Board then voted to award the contract to Long Contractors, the second lowest bidder, on the ground that it was the lowest bid conforming to the bid documents. In so doing, the Board followed the College president's recommendation--a recommendation based on his belief that the non-complying bid must be rejected, that it did not involve a matter of Board discretion. (Testimony of Sims, Rutherford, Griffin; Stipulation of Parties; P-41.) The bid specifications contain instructions to bidders requiring "each Bidder . . . [to] submit with his proposal a list of the subcontractors who will perform the work . . . as indicated by the `List of Subcontractors' form." (P-1, P-2.) The instructions further provide: The applicable subcontractor license registration or certification number must be noted on the bid opposite his name, and in the event that the subcontractor is a corporation, his State Corporate Charter number shall also be noted. If the subcontractor is an out of state firm, their Charter number with the Secretary of State to do business in the State of Florida should also be noted. The "Listing of Subcontractors" form provided with the specifications contains column headings for the names and addresses of the subcontractors but does not contain a separate heading for the requested license or corporate charter numbers. 4/ The form states that the subcontractor list "is an integral part of the bid." (P-1, P-2.) The bid instructions further require bidders to evaluate and determine the qualifications of their listed subcontractors. The bidder shall have determined to his own complete satisfaction that a listed subcontractor has been successfully engaged in this particular type of business for a reasonable length of time, has successfully completed installations comparable to that which is required by this agreement and is qualified both technically and financially to perform that pertinent phase of the work for which he is listed. (P-1, P-2.) The bid documents expressly reserve to the College the right "to reject any or all bids, and to waive informalities." (P-1 P-2.) No bidder correctly listed the required license and corporate charter numbers on its "Listing of Subcontractors" form. Griffin Construction. Griffin failed to include any license or corporate charter numbers. However, by subsequent letters dated February 9 and February 18, 1982, and at hearing, it supplied the required subcontractor license and charter numbers. Long Contractors. Long listed for its roofing subcontractor a sheet metal registration number, not the required roofing license number. [A sheet metal registration does not qualify a contractor for roofing work. See, 489.105, 489.113, Fla. Stat. (1981).] For its electrical subcontractor, Long omitted the prefix, "ER" from the listed number. For its plumbing subcontractor, Long listed a mechanical registration number instead of the required plumbing certification or registration number. [A mechanical registration does not qualify a contractor to perform plumbing work. See, 489.105, 489.113, supra.] Of the four areas requiring state licenses--roofing, heating and air conditioning, electrical, and plumbing--Long listed correctly only the registration number for its heating and air conditioning subcontractor. Long incorrectly listed No. FO6962 as the corporate number of Gandy Enterprises, its painting subcontractor. This is the number of a related corporation, Industrial Coatings, Inc. Remaining Bidders. Of the five other general contractors submitting bids, two-- Richard Walker Construction Company and GRC Contracting, Inc.--omitted all subcontractor license and charter numbers. The other three bidders failed to completely list all the required numbers. (Testimony of Rutherford; P-11, P-12, P-13, P-14, P-15, P-16, P-17, P-34, P-37, R-1, R-5.) The project architect testified that the submittal of incorrect or incomplete subcontractor license and charter numbers was a deficiency which a bidder should be allowed to cure after bid opening. But the failure to submit any required "number" was a deficiency which, in his opinion, could not be similarly corrected. He failed, however, to supply a reasonable basis for drawing such a distinction. Therefore, his opinion on this question is given little weight. 5/ (Testimony of Rutherford.) Subcontractor license and charter numbers are readily obtainable and can be verified by contacting the pertinent state agency--the Florida Department of Professional Regulation, Construction Industry Licensing Board, or the Florida Department of State. (Testimony of Griffin, Rutherford; P-32, P-33, P- 34, P-35, P-36, P-37.) The project architect, William Rutherford, routinely requires the listing of subcontractor license and charter numbers on bids for public construction projects. The main purpose it serves is that it would enable him to identify the listed contractor, since sometimes subcontractors have similar business names. Although if he was uncertain about the qualifications of a subcontractor, he would ordinarily question the general contractor. (Testimony of Rutherford.) Although Mr. Rutherford has customarily required the listing of subcontractor "numbers" on public projects, he has never made any use of those numbers in the past. (Testimony of Rutherford.) The general contractor who is awarded the contract is responsible to Mr. Rutherford and the College for construction of the project in accordance with the bid specifications. If, after bid opening, a listed subcontractor is unable to perform, Mr. Rutherford would ordinarily arrange for substitution of a new subcontractor acceptable to the general contractor and owner. (Testimony of Rutherford.) Griffin Construction's failure to list the license and charter numbers of its listed subcontractors, and its subsequent curing of that failure, did not affect the amount of its bid 6/ by giving it an advantage or benefit not enjoyed by other bidders. The bid omission did not allow Griffin Construction the opportunity to change any material element of its bid after bid opening. The inclusion or exclusion of subcontractor "numbers" at bid opening does not affect the ability of a contractors to obtain the required bond, the quality of bidding general contractors, the quality of listed subcontractors, the quality of work performed, or any material feature of the competitive bidding process. (Testimony of Griffin, Rutherford.)
Recommendation Based on the foregoing, it is RECOMMENDED: That the construction contract in question be awarded to Vick Griffin Construction Company, the lowest responsible bidder. DONE AND RECOMMENDED this 29th day of April, 1982, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1982.
The Issue The issue for consideration herein is whether the Respondent's proposed award on BID No. HSMV - 90022010 to Dunn Construction Company, Inc., should be upheld.
Findings Of Fact At all times pertinent to the issues herein, the Department was the state agency responsible for the solicitation of bids for and award of contracts for the construction of state buildings in Florida. Both Greenhut and Dunn are qualified contractors who are certified to bid on state construction contracts in general and this procurement in particular. In December, 1991, the Department issued an advertisement for bids for the project in issue herein, the construction of the Kirkman Complex Addition Data Center in Tallahassee, Florida. According to the Advertisement for Bids, all bids "must be submitted in full accordance with the requirements of the Drawings, Specifications, Bidding Conditions and Contractual Conditions, which may be examined and obtained ..." from the Department's designated architect/engineer, Clemons, Rutherford and Associates, Inc. in Tallahassee. Section B-21 of the request for proposals (invitation to bid) reads, in pertinent part: The recommendation for contract award will be for the bidder qualified in accordance with Section B-2 and submitting the lowest bid provided his bid is responsible and it is in the best interest of the Owner to accept it. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the owner. Bids received on this project were originally scheduled to be opened and read aloud on January 15, 1992 with the tabulation and Bid Award Recommendation to be posted the following days at the location where the bids were opened. The proposal as originally issued called for the submittal of a Base Bid with four Alternates, 1a, 1b, 2, and 3. Alternate 1a was a deduct for merely extending the existing Johnson Controls System to incorporate the new work instead of providing a totally new and independent control system. Alternate 1b called for adding furniture and landscaping for certain of the rooms shown on the drawings; Alternate 2 called for adding a "shelled" fourth floor as described in the proposal; and Alternate 3, as originally issued, called for: Add a complete fourth floor as indicated in drawings including the finished interior partitions with full HVAC, Plumbing and Electrical Service. Include furniture and landscaping for rooms 414 and 419. (Includes items in Alternate No. 2) As a result of questions received from prospective bidders at the pre-bid conference which indicated some confusion as to the meaning and intent of the Department regarding Alternate No. 3, by letter to all prospective bidders, dated January 8, 1992 the Department's architect indicated: Alternate #3 shall be the fourth floor complete, as shown on drawings, which includes items in Alternate #2. Addendum #1 to the request for bids, dated January 10, 1992, clarified Item 1-3.6), PROPOSAL FORM, of the PROJECT MANUAL to ADD to "Alternate #3", "(Include items in Alternate #2)". Item #2-1 of Addendum #2, dated January 16, 1992, deleted the sentence changed by Item #1- 3.6, and revised the sentence to read as follows: This includes any items required in addition to Alternate #2 to complete the remainder of the work for the Fourth Floor. Information contained at the beginning of each Addendum calls the bidders' attention to the change and indicates that failure to incorporate it may result in disqualification. The due date for bids was extended at the instance of the Department. Both Petitioner and Intervenor submitted bids for this project as did several other concerns on January 23, 1992. Greenhut's base bid was $4,139,000 with a deduct of $63,600 for Alternate 1a, and additions for Alternates 1b, 2, and 3 of $69,500, $239,000, and $209,000 respectively. Greenhut's total bid, therefore, through Alternate 3, was $4,592,900. Dunn's base bid was $4,079,000 with a zero deduct for Alternate 1a, and additions for Alternates 1b through 3 of $67,000, and $428,000. Dunn's total bid, therefore, was $4,574,000 for a difference of $18,900. Greenhut's bid was submitted on a form which provided for the base bid, the deduct for 1a, and the additions for 1b. 2 and 3 with the figure for 3 being those costs in addition to those identified in Dunn's bid was submitted on a prior form which provided for a base bid, a 1a deduction if any, (there was none), and additions for 1b, 2, and 3 with the figure for 3 including the figure listed for 2. An initial review of Dunn's bid form, then, showed a base bid of $4,079,000, no 1a deduction, a 1b addition of $67,000, a 2 addition of $311,000, and a 3 addition of $428,000. This letter figure included the $311,000 figure for Alternate 2, which should have been deducted from the bid during tabulation. When the bids were opened on January 23, 1992 by Mr. Everline, each figure on each bid was read off and listed on the bid tabulation form in the appropriate area. No attention was given at that time to the appropriateness or correctness of the figures listed on each bid form, nor was any attention paid to any other technical requirement of the procurement. This was merely a transfer of figures from the bid form to the tabulation form, and when this was done, Mr. Everline announced to all in attendance, including many contractor representatives, that the "apparent low bidder" was Greenhut. In arriving at that conclusion, Mr. Everline added all of Dunn's figures together without deducting the $311,000 listed for Alternate 2, a figure which was included in the $428,000 figure listed for Alternate 3. This resulted in an incorrectly large total bid for Dunn. Sometime later that day, a representative of Dunn contacted Mr. Everline to indicate that Dunn had inadvertently bid on the wrong form which precipitated its misleading presentation. Mr. Everline properly declined to discuss the matter and referred the Dunn representative to the Department's legal counsel. Sometime thereafter, when the bids had been tabulated and reviewed for responsiveness and legal qualification of bidders, Mr. Everline suggested to representatives of DHSMV that in order to forestall a protest, only so much of the project as extended through Alternate 2 be awarded. DHSMV officials, however, had sufficient funds available for the entire project, including some additional funds, if necessary, for cabling, and insisted they wanted the entire project awarded. The Department's legal counsel, upon review of the situation, concluded that the Dunn's actual bid intent was clear to include the amount listed for Alternate 2 within that listed for Alternate 3, and not to consider the two as additives to each other. It further concluded that Dunn's use of the improper form on which to submit its bid was immaterial and afforded it no improper competitive edge over other bidders. Therefore, it was concluded that Dunn was the low responsive bidder and, on February 4, 1992, the Department issued a Notice of Award to Dunn. Thereafter, Greenhut filed its Petition For Hearing taken as a protest to the award. Both the Department and Dunn agreed that Greenhut had standing to protest the award and that the protest was timely filed. It is so found.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of General Services enter a Final Order in this case dismissing the protest of Greenhut Construction Company, Inc., in regard to the proposed award of contact in bid number HSMV - 90022010 to Dunn Construction Company, Inc. RECOMMENDED in Tallahassee, Florida this 21st day of April, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-1297 BID The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of fact submitted by the parties to this case. FOR THE PETITIONER: 1. - 6. Accepted and incorporated herein. 7. - 9. Accepted. Accepted. & 12. Accepted and incorporated herein. Accepted. Accepted. & 16. Accepted and incorporated herein. Accepted and incorporated herein. & 19. Accepted and incorporated herein. Accepted. & 22. Accepted and incorporated herein. Argument and not Finding of Fact except for 1st sentence which is accepted. & 25. Accepted and incorporated herein. FOR THE RESPONDENT: 1. - 3. Accepted. 4. - 6. Accepted and incorporated herein. 7. & 8. Accepted. 9. - 12. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Accepted and incorporated herein. & 17. Accepted and incorporated herein. Irrelevant but accepted as true. Accepted. Accepted and incorporated herein. Accepted. Accepted. Irrelevant but accepted as true. Accepted. Accepted and incorporated herein. Irrelevant. Accepted and incorporated herein. Accepted. FOR THE INTERVENOR: Accepted. - 5. Accepted and incorporated herein. Accepted and incorporated herein. & 8. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. - 15. Accepted. 16. - 19. Accepted. 20. & 21. Accepted. Accepted and incorporated herein. & 24. Accepted. COPIES FURNISHED: Robert A. Emmanuel, Esquire 30 South Spring Street Post Office Drawer 1271 Pensacola, Florida 32596 Sylvan Strickland, Esquire Suite 309, Knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950 Harry R. Detwiler, Jr., Esquire 315 S. Calhoun Street, Suite 600 Tallahassee, Florida 32301 Ronald W. Thomas Executive Director Department of General Services Suite 307, Knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950 Susan Kirkland General Counsel Department of General Services Suite 309, knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950
The Issue The first issue to be determined is whether the BOARD can reject all bids, with or without cause. The second issue is to determine if the BOARD is required to have cause, was there a sufficient basis for the rejection of all bids in Bid NO. 3996?
Findings Of Fact On December 14, 1987, the BOARD sent invitations to bid to a list of approved vendors in Bid NO. 3996. The purpose of the invitation was to obtain the lowest responsible bid on a purchase of one hundred and fifty typewriters. The bids were to be submitted prior to January 11, 1988 at 2:00 P.M.. They were opened by the BOARD on the same day. OFFICE did not receive an invitation to bid despite its request to be placed on the approved vendor's list in November of 1987. When OFFICE learned of the outstanding invitation to bid, its representative, Mr. Richard Foss, went to the BOARD's Purchasing Department and requested a bid package. The bid documents given to OFFICE mistakenly gave January 14, 1988 at 2:00 P.M. as the deadline for the bid submission. Because of the later date given by the BOARD to OFFICE, the company's bid was received after the opening of the bids. When the results of the bidding were made known at the public bid opening, NAPLES bid was the lowest received. On January 14, 1988, after 10:42 A.M., it was discovered by the BOARD that OFFICE's bid price was lower than the price submitted by NAPLES. At this time, NAPLES bid had not yet been accepted by the BOARD, and no formal announcement had been made awarding the contract to NAPLES. During the BOARD's Purchasing Department's bid analysis, a request was made to reject all bids in Bid NO. 3996. The reason given by Purchasing for the request for rejection was that the specifications were being revised. The bids were rejected on the same date. The written reason sent to the vendors on January 14, 1988 for the bid rejection was that one vendor had been given an incorrect opening date. Attached to the written notice to the vendors was a new bid invitation for Bid NO. 4013. The BOARD explained its mistake was unfair to the one vendor. A new bid opening date was given of February 1, 1988. On January 14, 1988, in addition to the required bid documents, OFFICE submitted a letter which listed additional offerings or incentives that OFFICE would give the BOARD if OFFICE was awarded the contract. These additional purchasing incentives were: wall charts and teacher/student manuals for each typing classroom in the county. OFFICE also informed the BOARD that one of the BOARD's own service personnel was already trained in the servicing of Swintec typewriters. The bid submitted by OFFICE did not meet either the weight or the print wheel specifications as set forth in Bid NO. 3996. The specifications as written in Bid NO. 3996 were not written to eliminate all other typewriters but the Brothers 511-11. Weight specifications required were below the Brother's minimum weight, and at least two other manufacturers provide protected drop-in cassette print wheels in electronic typewriters. The Invitation to Bid contained specific provisions which encouraged the bidding of typewriters other than the Brother 511-11, and set up procedures under which other typewriters, which substantially meet the specifications, could be reviewed on their merits. NAPLES was the lowest responsible bidder for the electronic typewriter contract in the prior school year. The BOARD had rejected all bids at that time because of the decision to consider a different brand of typewriter once bids were opened. A notice of protest was filed by NAPLES, and the BOARD agreed to honor NAPLES bid and award the company the contract. The BOARD revised its bid specifications from last year prior to its solicitations for bids in Bid NO. 3996. The protected drop-in cassette print wheel and the weight requirements were two new technical specifications. During the hearing, the BOARD was unable to determine whether the weight factor or the protected drop-in cassette print wheel requirement will continue to be included in future revisions of the specifications.
Recommendation Based on the foregoing, it is RECOMMENDED: That the BOARD reject the bid submitted by OFFICE as it was nonconforming and sought an advantage not enjoyed by the other bidders. Reinstate the bids which were rejected in Bid NO. 3996, consider the bids, and make an award of the contract to NAPLES. DONE and ENTERED this 30th day of March, 1988, in Tallahassee, Florida. VERONICA D. DONNELLY Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of March, 1988. COPIES FURNISHED: Stephen Emens, President Naples Business Equipment and Systems, Inc. 859 4th Avenue South Naples, Florida 33940 Harry A. Blair, Esquire 2138-40 Hoople Street Ft. Myers, Florida 33901 Richard Foss, Typewriter Sales Manager 8A-Del Prado Boulevard Cape Coral, Florida 33904 Karl Engel, Superintendent Lee County Public Schools The School Board of Lee County 2055 Central Avenue Fort Myers, Florida 33901
Findings Of Fact Prior to June, 1988, HRS determined that it needed 23,871 square feet of office space to house some of its social services for indigents in Northern Escambia County. Since HRS desired more than 2,000 square feet of office space, it was required to bid lease number 590:1987 competitively. To that end, Respondent prepared an Invitation to Bid and a bid submittal package. The package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: client safety public access, ingress and egress availability of public transportation. The above areas were important to HRS since the agency would render indigent services to approximately 1000 people a month, many of whom are handicapped or lack good mobility due to age or infirmity. The majority of Respondent's clients are served within a 10 day period during each month. A great deal of pressure is placed on the surrounding area due to the in flux of people. Additionally, many of Respondent's clients utilize public transportation since they do not own or have access to personal vehicles. Because of servicing so many people the above factors received a great deal of weight under HRS's consideration of the property it desired to lease and occupy. All of the above areas were covered by Respondent's weighted bid evaluation criteria. Additionally, in order to submit a responsive bid, a prospective lessor was required to meet one of the following qualifications at the time the bid was submitted: (a) be the owner of record of the facility and parking areas; (b) be the lessee of the space being proposed and present with the bid a copy of the lease with documentation of authorization to sublease the facility and parking areas; (c) submit documentation of an option to purchase the facility and/or parking areas; or (d) submit documentation of an option to lease the facility with authorization to, in turn, sublease. The District Administrator of HRS, Chelene Schembera, is ultimately responsible for bidding, selection and leasing of all HRS facilities within District I, including Escambia County, Florida. In order to accomplish this task Ms. Schembera appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to her the committee's choice of the lowest and best bid. Ms. Schembera's purpose in establishing the bid evaluation committee was to secure input from a cross section of people who had a variety of backgrounds and knowledge that would be material in evaluating the office space, in light of the uses for which it was intended and the relative public worth of the work space. Ms. Schembera appointed individuals who were familiar with the type of work to be done in the proposed space, as well as persons familiar with the bid process. On July 21, 1988, HRS received five bids on the lease. Intervenors submitted the apparent low bid which Northside consisted of one building located at the Brentwood Shopping Center in Pensacola, Florida. At the time that the Intervenors submitted their bid, they included documentation which showed that they had a contract to purchase the subject facility; they have since closed on that transaction. This bid package did not include the four acres adjacent to the Brentwood Shopping Center property and no contract to purchase or other documentation was submitted as to the four acre parcel of property. Petitioner submitted the apparent second lowest bid which consisted of one building located at Fairfield Plaza in Pensacola, Florida. Petitioner's interest in Fairfield Plaza is that of a lessee under a Master Lease with rights to sublet the property. All appropriate documentation was submitted with the bid. This property was the subject of a semi-friendly foreclosure action at the time that the Petitioner's bid was submitted. Petitioner was still in possession and control of the property. Both Petitioner's and Intervenors' property were within the mandatory geographical area designated in the bid package. Both bids were responsive under the minimum bid specifications and bidder qualifications. The other three bids which were submitted by HRS are not in contention The committee members personally inspected the sites offered by the Petitioner and the Intervenors. While at the Intervenors' site, the committee's concern over the property's minimal parking (as compared to Fairfield) and limited safe public access, ingress and egress were raised. The only access to Intervenor's property was from a very busy multi-lane highway. Certain turns onto and off the property were extremely dangerous. In order to make its bid package more acceptable, Intervenors' representative orally amended the bid package to include the southerly four acres contiguous to the Brentwood property. The Inclusion of the southerly four acres would adequately increase Intervenors' parking. The amendment would also create additional and safer public ingress and egress since the four acres abutted on Murray Lane which intersects Highway 29. This amendment substantially worked to Intervenors' advantage and was a material change to the previously submitted bid. The improper amendment cannot be considered here. Following the on-site inspections, the committee members met and rated the properties submitted by Petitioner and Intervenors according to a Bid Synopsis evaluation sheet which they had been previously provided. The committee members' review of the Intervenors' property included the improper bid amendment. Even with the improper amendment, the unanimous recommendation of the evaluation committee was to award the lease to the Petitioner and Fairfield Plaza. The evaluation committee based its decision on the scores attributed to each property on the Bid Synopsis sheet by the individual committee members. The committee utilized all the weighted bid criteria. However, two factors were of primary importance. One was its determination that the property offered by the Intervenors presented greater problems for ingress and egress due to the congested nature the area. The other consideration was that service to Fairfield Plaza from public transportation was both more frequent and direct. The property offered by the Intervenors had less public transportation service. The stops were less frequent and a significant number of clients would be required to transfer buses to reach Brentwood when utilizing such public transportation. All bus passengers would be required to walk from the bus stop close to Brentwood and attempt at their peril to cross a very busy, dangerous and congested highway. The reasons given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the Bid synopsis score sheets. The scoring was done by each member after discussion of the two buildings and without influence from the other committee members. In essence, the committee felt that Petitioner's property was the better property for the money. Importantly, every committee member came to the conclusion that Petitioner's property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a piece of property. On these facts, the individual scoring methods used by the individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. The District Administrator initially adopted the committee's recommendation and reported that recommendation to King Davis, the Director of General Services for HRS. The Director of General Services later informed the District Administrator that he and his staff were concerned with the fact that the recommendation was to award the lease to the second lowest bidder. The staff's review considered the improper amendment as part of the Intervenors' bid. Over a ten year period the Petitioner's rental cost was $62,381.00 more than the Intervenors'. In addition, the estimated energy consumption for the first year for the Petitioner's property was approximately $4800 more than for Intervenors. King Davis and his staff did not believe that the justifications cited in the recommendation letter would be considered crucial enough to override awarding the lease to the lowest bidder, should the agency get involved in a bid protest over the award. He and his staff did not disagree that the reasons assigned by the committee and Ms. Schembera were legitimate considerations. Their ultimate concern was that the reasons given by the committee and Ms. Schembera would not be given as great a weight by a Division of Administrative Hearings' hearing officer; and therefore, fail to withstand a potential bid challenge. But the conclusion that the lack of ingress and egress and public transportation could not outweigh the cost differences assumed that Intervenors' bid included the four acres. Without the four acres, the problems with ingress and egress, congestion and public transportation become even more important and can outweigh minor price differences in rent and energy. This is especially true when one considers the impact that the influx of at least 1000 people would have on an already congested and unsafe area. Put simply, the conclusion that the above factors can and do outweigh price and cost considerations in these facts is not an arbitrary and capricious decision, even though others may disagree with that decision. Instead of reconvening the committee after receiving the recommendation from King Davis and discussing the same with him, the District Administrator made the determination that the lease should be awarded to the Intervenors. The District Administrator, acquiesced in Mr. Davis' assessment that HRS could not succeed in a bid challenge. She did not like his advice. In fact, even at the hearing Ms. Schembera still believed Petitioner's property was the lowest and best for HRS purposes. However, through circular reasoning she also concluded that Intervenors' property was the lowest and best bid because she chose it. The agency's ability to succeed in a bid challenge which may or may not happen is not covered by any of the weighted bid evaluation criteria contained in the bid package and is not an appropriate reason to prefer one bid over another. The foregoing is particularly true when the reason given (surviving a bid protest) is based on the occurrence of a future event which may not occur. To reject a bid for a reason outside the bid criteria and one based on an unknowable future event is an arbitrary and capricious act on the part of Respondent. A court-appointed receiver was ordered to take control of the property belonging to the Petitioner on September 28, 1988, after the bid award was announced. Petitioner still retains its right of redemption of the property, and such an interest is sufficient to confer standing on Petitioner to maintain this action. Moreover, the evidence was clear that Petitioner had both the ability and wherewithal to perform the lease should it receive the bid award. Perfected ownership or control is not required. With Petitioner's apparent ability to perform, the fact of the foreclosure action and the receiver should not work against the Petitioner in this bid protest.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Department of Health and Rehabilitative Services enter a final order awarding lease number 590:1987 to Eccelston Properties, Ltd., as the lowest and best bidder. DONE and ORDERED this 10th day of January, 1989, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of January, 1989.
The Issue Whether the bid submitted by VSM of Florida, Inc., under cover of the bid blank issued to VSM, Inc. for the construction on State Project 16070-3511 (the Project), with the Florida Department of Transportation (Department), was the lowest responsive bid. Whether the Department acted arbitrarily, illegally, dishonestly or fraudulently in rejecting the bid submitted by VSM of Florida, Inc. under cover of the bid blank issued to VSM, Inc. for the construction of the Project based on the Department's determination that VSM of Florida, Inc. was not a prequalified contractor. Whether VSM, Inc., has standing to bring this bid protest by and on behalf of its operating subsidiary, VSM of Florida, Inc.
Findings Of Fact Upon consideration of all of the evidence, the following relevant findings of fact are made: Bids submitted on the Project were opened on May 27, 1992 and posted on June 18, 1992. The bid submitted by VSM of Florida, Inc. under cover of the bid blank issued by the Department to VSM, Inc., a prequalified contractor, was the apparent low bid on the Project in the amount of $1,565,565.00. The bid submitted by Leware under cover of the bid blank issued by the Department to Leware, a prequalified contractor, was the apparent second low bid on the Project in the amount of $1,600,000.00. All contractors who seek to bid on Department projects in excess of $250,000.00 must be prequalified by the Department in order to bid on such projects. The Project was in excess of $250,000.00 thereby requiring all bidders to be prequalified contractors. The Department's Contract Administration Office (CAO) is responsible for prequalifying contractors to bid on Department projects in excess of $250,000.00, for issuing bid packages for such projects, and for processing bids for award of a contract. The Department will not issue a bid blank for a project in excess of $250,000.00 unless a request for a bid blank is received from a prequalified contractor. Upon a request being made, the Department first determines that the contractor making the request is prequalified and has the capacity to bid on the project, then the Department prints or stamps the name of the prequalified contractor on the front page (cover sheet) of the bid blank and mails the bid package to the prequalified contractor. Contractors do not have to be prequalified to bid on projects of less than $250,000.00 but the Department's Equal Employment Opportunity (EEO) requirements would be applicable to projects of less than $250,000.00 as well as those in excess of $250,000.00. Contractors do not have to be prequalified to work as subcontractors on a Department project. The Department does not approve subcontractors on Department projects but does review and approve the use of subcontractors on Department projects to ensure that subcontractors do not perform in excess of 49% of the work on the project in violation of Standard Specification No. 8 in the Department's contract. Review of the subcontractors being used on a project is conducted by the Department's District offices and the CAO is not made aware of which contractors are being used as subcontractors an a project. There is no specific language in the application for prequalification that requires a separate application be submitted for each contracting firm seeking prequalification. However, a copy of the Department's rule included in the application package does require that a separate application must be submitted for each contracting firm seeking prequalification. The purpose of the information sought in Question 8 (Question 6 in 1989) of the application concerning the affiliates of the parent company is to: (a) determine if any of the affiliates have been disbarred by other agencies or convicted of contract crimes which would disqualify them or; (b) alert the Department that an affiliate is applying for prequalification independent of the parent company so that the Department can properly audit the financial statements of each applicant. It is not intended to allow or provide for a joint application. The application must be accompanied by an audited financial statement and an equipment list. First-time applicants must also provide resumes and letter of recommendation supporting the applicant's representation that it is qualified and capable of performing the type of work for which it is seeking qualification. The CAO reviews the application for completeness and checks various data bases to determine if the applicant and its affiliates have adverse reports from other contracting agencies. The Department's Internal Audit Section reviews the financial information provided with the application for purposes of developing the Current Ratio and Net Worth Factors for use in calculating the applicant's Maximum Capacity Factor. The Internal Audit Section also reviews the information on corporate subsidiaries provided in response to "Question 8" (Question 6 in 1989) on the application. The Department's Construction Office reviews the equipment and experience information provided with the application to develop an applicant's Ability Factor for use in calculating the applicant's Maximum Capacity Factor. The Internal Audit Section and the Construction Office report their conclusions to the CAO, which issues the Certificate of Prequalification (Certification) to the applicant. Where the Opinion Letter of the applicant's Certified Public Accountant, which must be included with the application, states that the financial statement was audited in accordance with General Accepted Accounting Principles, the Department can rely on the Opinion Letter and the financial statements submitted with the application, unless there is a reasonable basis for the Department to question the financial statements. Where the Opinion Letter identifies the entity and subsidiaries, if any, whose financial condition is reflected in the financial statement, it is the Department's practice and policy to issue the Certification in name of the entity whose financial condition is reflected in the financial statement as indicated by the Opinion Letter. Where the Opinion Letter indicates that the financial condition of both the parent company and subsidiaries are reflected in the financial statement, then the Department will issue the Certification in the name of the parent company and the generic term "subsidiaries" or "subsidiary". Neither the parent company nor the subsidiary would be qualified separately. Under the above circumstances, the Department would accept a bid submitted by the parent company without the subsidiary even though the bid blank had been issued in the name of the parent company and "subsidiary" or "subsidiaries". For example, a Certification was issued by the Department to "Balfour Beatty Construction, Inc. and subsidiary", the bid blank was issued in the same name but the bid was submitted by and awarded to Balfour Beatty Construction, Inc. There was at least one other instance where the Department followed a similar procedure. The Department's justification for this practice is that the parent company has control over its subsidiaries and could submit a bid on their behalf and enter into a contract with the Department that would bind the subsidiaries. Whereas, with the converse, the subsidiary or subsidiaries are normally without authority to submit a bid on behalf of the parent company or enter into a contract with the Department on behalf of the parent company. However, where a prequalified parent company gives proper written authorization to a subsidiary to submit a bid on its behalf and such authorization is attached to bid, then the Department would not consider such bid submitted by the subsidiary as irregular. Where a parent company relies on the assets and experience of its majority-owned subsidiaries in its application for prequalification to which it has access to, and control over, and the Opinion Letter indicates the parent company to be the entity whose financial condition is reflected in the financial statement, then the Department would certify the parent company in its name alone and allow the parent company to bid on Department projects in excess of $250,000.00. Furthermore, the Department would allow the parent company's subsidiaries to perform all of the work on the project for the parent company notwithstanding Standard Specification No. 8 limiting the percentage of work which the subcontractors are allowed to perform on a Department project to 49%. The Department does not consider subsidiaries performing work for a parent corporation on a Department project as subcontractors within the meaning of Standard Specification No. 8 and thus, a parent company could bid on a Department project in its own name and rely solely on its subsidiaries to perform 100% of the work on the project without violating Standard Specification No. 8. For example, VSM, Inc. could bid on a Department project and, if awarded the bid, could rely solely on VSM of Florida, Inc. to perform 100% of the work on the project. It was conceded by the Department that VSM of Florida, Inc. has the expertise, experience and equipment to perform all of the work bid for on the Project. Where the applicant's name on the face of the application does not exactly correspond with the name of the entity whose financial condition is reflected in the financial statement, then the Department will issue the Certification in the name of the entity whose financial condition is reflected in the financial statement as indicated in the Opinion Letter. VSM, Inc. is a Florida corporation that was incorporated in 1988. In 1988 VSM, Inc. formed two subsidiary corporations, VSM of Florida, Inc. and VSM of Virginia, Inc. The parent corporation, VSM, Inc., owns 80% of the stock in both VSM of Florida, Inc. and VSM of Virginia, Inc. Van Monroe is the sole stockholder, sole director and president of VSM, Inc. Van Monroe is also the sole director and president of VSM of Florida, Inc. The remaining 20% stock of VSM of Florida, Inc. is owned by Gregory Monroe, brother of Van Monroe. Gregory Monroe is also vice president of VSM of Florida, Inc. These corporations (VSM, Inc. and VSM of Florida, Inc.) are separate entities with each having a separate Federal Identification Number. Beginning in 1989, VSM, Inc. applied for Certification with the Department to qualify to bid on projects in excess of $250,000.00. In the application form (Question 6), the applicant is requested to: "List the following for all affiliated companies: (a) Name and Address; (b) States Qualified ; and (c) Explain in detail your connection with this company and whether or not this company is qualifying with FDOT. In response to that question, VSM, Inc. answered in pertinent part as follows: (a) VSM of Florida, Inc., P. O. Box 5761, Jacksonville, FL 32247 (58-2916127); (b) Florida and; (c) VSM, Inc. - 80% Stockholder, Gregory B. Monroe - 20% Stockholder (We would qualify VSM of Florida, Inc. as a subsidiary of VSM, Inc.). The Department issued the Certification on April 21, 1989 in the name of VSM, Inc. Each of the applications for renewal of the Certification issued on April 21, 1989 submitted on March 26, 1990, March 26, 1991 and March 30, 1992 requested basically the same information in Question 8, as had Question 6 in the original application, and the answers were basically the same as in the original application. The renewal applications submitted on March 26, 1990 and March 30, 1992 have both VSM, Inc. and VSM of Florida listed as applicants. The Department subsequently lined out VSM of Florida, Inc. on each of these renewal applications and issued the Certification to VSM, Inc. The reason being, that each contracting firm seeking Certification must file a separate application, and the Opinion Letter indicated that the entity whose financial condition was reflected in the financial statement was VSM, Inc. A Certification was issued to VSM, Inc. on April 30, 1990, April 10, 1991 and April 16, 1992, respectively in response to the above renewal applications for Certification. The Certification dated April 16, 1992 expanded the classes of work to be performed under the certificate to include Bascule bridge repair (rehabilitation) work. In each of the above years, Van Monroe, the president of both VSM, Inc. and VSM of Florida, Inc., consciously chose not to seek Certification for VSM of Florida, Inc. independently of VSM, Inc. because VSM, Inc. and its subsidiaries operate as an integrated operation and could not be separated. Beginning in 1990 and each year thereafter, when VSM, Inc. applied for renewal of its Certification with the Department, it included a consolidated financial statement which contained the financial condition of its two subsidiaries, VSM of Florida, Inc. and VSM of Virginia, Inc. The Department chose not to issue the Certification in the name of "VSM, Inc. and subsidiaries" for these years because the Department concluded that the Opinion Letter indicated that the only entity whose financial condition was reflected in the financial statement was VSM, Inc. Although the Department conceded that the Certification could possibly have been issued to "VSM, Inc. and subsidiaries", the Department contended that this would not have changed the result of the bid since under either situation, VSM of Florida, Inc. had not submitted written authorization from VSM, Inc. authorizing VSM of Florida, Inc. to submit a bid on behalf of VSM, Inc. Since 1989, both VSM, Inc. and VSM of Florida, Inc., after requesting and receiving permission from the Department, have used the same vendor (prequalification) identification number. Additionally, the names VSM, Inc. and VSM of Florida, Inc. have been used interchangeably on documents submitted to and received from the Department. The current Certificate of Capacity, required by the Department of all prequalified contractors, was issued in the name of VSM of Florida, Inc. On February 26, 1992 under cover of the bid blank issued to VSM, Inc. by the Department, VSM of Florida, submitted a bid on a Department project in Polk County, Job No. 16630-3601. Because this bid was third lowest bid, no objection or declaration of irregularity to this bid format was made by the Department. On May 27, 1992 under cover of the bid blank issued to VSM, Inc. by the Department, VSM of Florida, Inc. submitted a bid on a Department project in Gadsden County. The Department notified VSM, Inc. by form letter dated June 17, 1992 that the bid proposal had been taken apart and not been stapled back in the same order as when issued and that such errors or omissions could result in a future bid proposal being declared irregular. One of the items (Item 5) on this form letter states "the bidder's name is not as issued per their prequalification application on the front sheet (Bid Blank)". Item 5 was not checked or noted as a deficiency in the bid on the Gadsden County project along with the other noted problem because the name (VSM, Inc.) on the cover sheet had not been altered - it was the same as issued on the Certification. The Gadsden County project bids were posted on June 18, 1992 under the name "VSM,Inc." as irregular but with no reason stated for the irregularity and there is nothing in the minutes of the Department's Bid Review Committees indicating the reason for the irregularity. Again, the bid submitted by VSM of Florida, Inc. under cover of the bid blank issued to VSM, Inc. was not the low bid on the Gadsden County project. On May 27, 1992 VSM of Florida, Inc., under cover of a bid blank issued to VSM, Inc. by the Department submitted a bid on another Department project in Polk County, Job No. 16070-3501, the apparent low bid on the project and the bid in dispute here. The name of VSM, Inc. under which the bid blank was issued by the Department was not altered on the bid submitted by VSM of Florida, Inc. The bid as submitted by VSM of Florida, Inc. was signed by V. S. Monroe and G. B. Monroe as president and secretary, respectively of VSM of Florida, Inc. Although the bid did not contained written authorization from VSM, Inc. authorizing VSM of Florida, Inc. to submit the bid on behalf of VSM, Inc., there is sufficient evidence in the record to show that at the time of the bid submittal VSM, Inc. had knowledge of, consented to and authorized the bid submittal by VSM of Florida, Inc. Also, at the time of the bid submittal, VSM, Inc. and VSM of Florida, Inc. were under the impression (rightfully or wrongfully) that VSM, Inc. and VSM of Florida, Inc. had been previously prequalified jointly by the Department. By letter dated May 29, 1992, the Department advised VSM, Inc. that it needed to file a Disadvantaged Business Enterprise (DBE) affirmative action plan with the Department in order for its bid of May 27, 1992 to be considered responsive. The DBE plan was furnished by VSM of Florida, Inc. and approved by the Department. The Department also requested that VSM, Inc. submit a current capacity rating status so that the Department could determine if the current capacity of VSM, Inc. was such that it was still qualified to perform the work required by the Project. The current capacity rating status was filed by VSM of Florida, Inc. on June 3, 1992. On June 11, 1992, the Department's Technical Review Committee (TRC) recommended that the bid executed and submitted by VSM of Florida, Inc. under cover of the bid blank issued to VSM, Inc. be declared irregular based on the TRC's determination that VSM of Florida, Inc. was not a prequalified contractor. On June 16, 1992, the Department's Contract Awards Committee (CAC) unanimously adopted the recommendation of the TRC and declared the bid submitted under cover of the bid blank issued to VSM, Inc. to be irregular. The CAC voted to post an intent to award the bid on the Project to Leware. The Department rejected the bid submitted by VSM of Florida, Inc. under cover of the bid blank issued to VSM, Inc. on the basis that VSM of Florida, Inc. was not a prequalified contractor. The bid was rejected by the Department without any review of the Department's prequalification file of VSM, Inc., or without any review as to whether the irregularity could be cured by VSM, Inc. ratifying the action of VSM of Florida, Inc. by supplying the Department with written authorization for VSM of Florida, Inc. to submit the bid on behalf of VSM, Inc. There was no evidence that curing this irregularity would provide the Petitioner with such a competitive advantage that it would restrict or stifle competition or that curing this irregularity would violate any rule or statute. The intent to award the Project to Leware was posted on June 18, 1992. VSM, Inc., by and on behalf of its operating subsidiary, VSM of Florida, Inc., filed a timely initial protest to the intent fo award on June 23, 1992 and a timely formal protest on July 1, 1992.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, accordingly RECOMMENDED: That the Department enter a Final Order awarding the contract for the construction of the Project to the Petitioner upon VSM, Inc. curing the technical deficiency in the bid by submitting to the Department authorization for VSM of Florida, Inc. to have submitted the bid on the Project on behalf of VSM, Inc. DONE and ORDERED this 12th day of November, 1992, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of November, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NUMBER 92-4859BID The following constitutes my rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Proposed findings of fact 1 - 4, 6 and 8 - 11 are adopted in substance as modified in the Recommended Order. Proposed findings of fact 5 and 7 are adopted in substance as modified in the Recommended Order, but see Findings of Fact 41 relating to reliance. Proposed Findings of Fact Submitted by the Respondent Proposed findings of fact 1 - 42 and 44 are adopted in substance as modified in the Recommended Order. Proposed finding of fact 43 is rejected as not being a finding of fact but more of an argument as to the weight to be given certain evidence. Rulings on Proposed Findings of Fact Submitted by the Intervenor, Leware 1. Proposed findings of fact 1 - 35 are adopted in substance as modified in the Recommended Order. COPIES FURNISHED: Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0458 Thornton J. Williams, Esquire General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0458 Allen P. Clark, Esquire CAVEN, CLARK, RAY and TUCKER 3306 Independent Square Jacksonville, FL 32202 George M. Meros, Jr., Esquire 106 College Avenue Tallahassee, FL 32301 Carolyn Holifield, Esquire Paul Sexton, Esquire Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0458 Mary M. Piccard, Esquire CUMMINGS LAWRENCE & VESIMA 1004 DeSoto Park Drive Tallahassee, FL 32302
The Issue This case concerns a challenge to the validity of Rules 13A-1.001(12), 13A- 1.002(1)(b) and 13A-1.002(3) , Florida Administrative Code, pursuant to Section 120.56, Florida Statutes.
Findings Of Fact In the fall of 1988, the State of Florida, Department of Transportation (DOT) put out a Request for Proposals (RFP) as RFP-DOT-88-0l. Through this RFP the agency sought to acquire a new barrier and ticket toll collection system which would automate the toll collection operations and retrieval of audit data, having in mind increased reliability and performance. The project is principally one which envisions the purchase of commodities. It has an associated service component. Section 287.062(1)(e), Florida Statutes together with Section 287.073(3), Florida Statutes, established the basic authority for the award of RFP-DOT-88-01. The agency received responses in March, 1989, from three companies. The offerors were Petitioner and Intervenor and one other concern. The other company was AGS Informations, Inc. (AGS). Following evaluation DOT determined on May 18, 1989 to reject the Intervenor's proposal as nonresponsive. This rejection was followed by the Intervenor's notice of protest on Nay 25, 1989. A formal written protest was made on June 6, 1989. On July 31, 1989, Intervenor filed a notice of voluntarily dismissal of the formal written protest. This was addressed by the DOT final order of August 2, 1989 which dismissed the formal written protest. On November 21, 1989, DOT posted its intent to award a contract to Petitioner. This statement of intent to award was met by a notice of protest filed by Intervenor on November 27, 1989, followed by a formal written protest on December 6, 1989. The case was sent to the Division of Administrative Hearings for consideration and through response to a motion to dismiss the Hearing Officer in that case, DOAH Case NO. 89-6926B1D, entered a recommended order of dismissal. On January 22, 1990 DOT entered a final order dismissing Intervenor's petition and stating its intent to award the contract to Petitioner. An amendment to the January 22, 1990 order was made on February 21, 1990 reminding all concerned that the contract award was subject to review and approval by the Governor and Cabinet sitting as the State of Florida, Department of General Services to decide the propriety of the subject purchase which was an information technology resources purchase under Section 287.073, Florida Statutes. On February 21, 1990, DOT sent notice to the three offerors that it was rejecting all proposals submitted. As described in the notice of agency decision, DOT was operating on the basis that a further review of the proposals revealed that the proposals by AGS and Intervenor were nonresponsive. It went on to say that to have competitive offerors there must be two or more offers submitted by responsive and qualified offerors. In this instance DOT felt that it did not have two acceptable proposals and did not have a competitive offer. Because the commodities sought were available from more than one source, it had decided to withdraw its notice of intent to award which was contingent upon the approval of the Governor and Cabinet. On February 27, 1990, Petitioner gave a notice of protest of the DOT decision to reject all bids. This was followed by a formal written protest on March 9, 1990. Although the decision to reject all proposals was not opposed by Intervenor, the motion by the Intervenor to intervene in DOAH Case No. 90- 1583BID was granted allowing limited participation in support of the DOT decision to reject all proposals. That outcome tended to create the opportunity for Intervenor to participate in any re-advertisement for proposals. As revealed in the final hearing in DOAH Case No. 90-1583BID, DOT utilizes Chapter 13A, Florida Administrative Code, in the procurement process. Intervenor participated in the final hearing in DOAH Case NO. 90- 1583BID. The DOT decision to reject all proposals in which reliance upon the rules under challenge are perceived to support that decision has an adverse impact on Petitioner. By that arrangement Petitioner loses the opportunity for the contract. Additionally, it is placed in a disadvantaged position in that the particulars of its method of responding to the RFP have been revealed and are now known to the competitors who might be expected to utilize that information in a setting where a re-advertisement takes place. Under the circumstances, Petitioner filed its challenge to the existing rule on March 28, 1990. Intervenor sought the opportunity to intervene in this case on April 4, 1990, and that opportunity was granted on April 6, 1990. Intervenor intends to participate in any re-advertisements of the RFP. In his testimony at hearing William Monroe, Director of the Division of Purchasing for Respondent, established that in governmental purchasing the terms "offers" and "proposals" are synonymous. This opinion is accepted. Mr. Monroe also established that Respondent believed that it was implementing Section 287.012(15), Florida Statutes, when promulgating Rule 13A- 1.001(12), Florida Administrative Code. Through the promulgation of Rules 13A- 1.002(1)(b), and 13A-1.002(3), Florida Administrative Code, Respondent believed that it was implementing Section 287.062, Florida Statutes. Respondent interprets Section 287.062, Florida Statutes, to require an agency making a commodity purchase to use competitive sealed proposals in instances where invitations to bid are not used. Mr. Monroe in speaking for Respondent indicated that this interpretation gained support from the language set out in Section 287.001, Florida Statutes. According to Mr. Monroe the circumstance in which less than two responsive and qualified offerors respond to an RFP is one in which the procuring agency must reject all proposals or seek the approval from Respondent to negotiate with the one responsive offeror or where no responsive offerors were received to negotiate with someone whom the agency has chosen. Likewise, a sole source purchase negotiation must be approved by Respondent. Mr. Monroe's testimony, in speaking for Respondent, indicates that Respondent interprets the terminology within Section 287.062(2), Florida Statutes, "no competitive" to modify the words "bids" and "proposals." Thus, it is incumbent upon an agency to receive authority to negotiate in those instances where it receives less than two proposals submitted by responsive and qualified offerors who are responding to a RFP in acquiring commodities.
The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.
Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.
Findings Of Fact Upon consideration of the oral and documentary evidence addressed at the hearing, the following relevant findings of fact are made: The request for sealed bids for the construction of the Project was advertised on October 9, 16 and 23, 1991. There were six addenda to the original bid documents which added, deleted or modified provisions of the original bidding requirements, contract requirements, administrative requirements and technical specifications. The original bid documents plus the six addenda will be referred to herein as the "bid documents". The bid documents required that all bids be in full accord with the contract documents. Sealed bids for the Project were opened on October 30, 1991. Wright submitted the lowest lump sum bid for the Project, with Sovran submitting the second lowest lump sum bid and Kellogg submitting the third lowest lump sum bid. At the time of the bid opening, the bid documents listed only four casework manufacturers that were approved to furnish casework for the Project. Empire Custom Cabinets, Inc. (Empire) was not listed as one of the four approved casework manufacturers in the bid documents. The bid documents did not require the bidder to list the casework manufacturer it intended to obtain the casework from, but only that the bidder name the casework subcontractor. The only work item in the bid documents which requires identifying the name of the manufacturer on the subcontractor's list is the metal roof system. Because Empire's bid on the casework was extremely low compared to other bids received by Wright on the casework, Wright called Empire prior to submitting its bid to confirm that Empire's bid was submitted per plans and specifications. Although Wright did not specifically inquire of Empire at this time as to which manufacturer Empire was obtaining the casework from for the Project, Empire did advise Wright that Empire's bid on the casework was according to plans and specifications. Additionally, Empire did not divulge or advise Wright at this time that the bid was based on Empire manufacturing the casework for the Project. Based on this representation from Empire, Wright listed Empire as its casework subcontractor, and calculated its lump sum bid for the Project using Empire's bid. Although Wright listed Empire as its casework subcontractor in its bid, this did not create an irregularity in Wright's bid since Wright's bid was per plans and specification without exception or exclusion. This would require Wright to furnish casework for the Project manufactured by one of the four approved casework manufacturers listed in the bid documents regardless of which subcontractor Wright listed as the subcontractor for casework. By letter dated November 1, 1991, the Board's architect for the Project requested Wright to have Empire submit written certification by one of the four approved casework manufacturers that its casework was being furnished to Empire for the project. By letter dated November 4, 1991, Empire advised Wright that Empire's bid on the casework for the Project was based on casework to be manufactured by Empire. On the same day, Wright furnished the architect for the Project a copy of Empire's letter of November 4, 1991. In response to a request by the Board, Wright, by letter dated November 7, 1991, advised the Board that Wright would furnish casework manufactured by one of the four approved manufacturers listed in the bid documents for the Project. By letter dated December 3, 1991, Empire advised Wright that Empire would need to withdraw its bid if Empire was required to use casework manufactured by one of the four approved casework manufacturers listed in the bid documents. On that same day, Wright furnished the Board a copy of Empire's letter and requested that the Board allow Wright to remove and replace Empire with Steven Ward and Associates, Inc. (Ward), as the casework subcontractor since Ward would be able to furnish and install casework manufactured by LSI Corporation of America, Inc., one of the four approved casework manufacturers. No Action has been taken on that request. The bid documents provide for a subcontractor to be removed and replaced from the list of subcontractors after the bid is opened if there is a showing of good cause and written approval by the Board and the Project architect is obtained. Although Empire's bid on the casework for the Project submitted to Wright was based on Empire manufacturing the casework, there is competent substantial evidence in the record to establish facts to show that at the time Wright submitted its bid on the Project it had reasonable grounds to believe that Empire's bid on the casework was based on Empire furnishing and installing casework manufactured by one of the four approved casework manufacturers. After determining that Empire could not perform under its bid, Wright obtained a bid from Ward for furnishing and installing the casework for the Project which was less than Ward's original bid submitted to Wright before the bid opening. However, this bid was substantially more than Empire's bid, and if Wright is allowed to substitute Ward for Empire, Wright will have to absorb the additional costs since the bids were lump sum bids. Wright is neither attempting to furnish casework from a manufacturer that is not approved, nor is Wright requesting an increase in the lump sum bid price. The advertisement for Sealed Bids for the Project required that all bidders be prequalified by the Board prior to the bid date. Sovran and one other bidder were not prequalified by the Board prior to the bid date in accordance with Advertisement for Sealed Bids for the Project. Sovran received the bid documents for the Project approximately one month before the bid date but did not file a Notice of Protest of the prequalification requirement contained in the Advertisement for Sealed Bids for the Project. Sovran holds a certificate as a general contractor licensed in the State of Florida in accordance with Chapter 489, Florida Statutes. As a certified general contractor Sovran, pursuant to Section 489.125, Florida Statutes, was authorized to bid on the Project notwithstanding the Board's prequalification requirement. This was explained by the Board's representative at the bid opening. The bid documents required that a subcontractor list be submitted by all bidders, and when submitted with the bid becomes an integral part of the bid. The purpose of the subcontractor list was to prevent bid shopping, and to allow the Board an opportunity to review the subcontractors to determine if any subcontractor on the list had performed unsatisfactorily on previous Board projects. Neither the statutes relating to competitive bidding nor the bid documents prohibit the listing of the general contractor together with a subcontractor on a subcontractor list. The subcontractor list submitted by Sovran indicated "Sovran Constr/Naples" as the name of the subcontractor for the masonry work and "Sovran/Naples" as the name of the subcontractor for the poured-in-place concrete work. "Naples" is Naples Concrete and Masonry Work, Inc. The bid received by Sovran from Naples was for both labor and materials for the poured-in-place concrete and masonry work. Sovran neither requested nor did Naples furnish Sovran a bid to provide labor only for the poured-in-place concrete and masonry work. There was no agreement between Sovran and Naples whereby Sovran would supply the materials and Naples would furnish the labor for the poured-in-place concrete and masonry work. Sovran did request and receive bids from other companies for furnishing materials only for the poured-in-place concrete and masonry work. Sovran listed itself, the general contractor, along with Naples on the subcontractor list for the purpose of supplying the materials for the poured-in- place concrete and masonry work. Sovran's main reason for supplying the materials was that Naples was not bondable. Without a payment bond from Naples, Sovran would be without protection and could be forced into paying double for the materials in the event Naples failed to pay the material suppliers. Although the Superintendent of the Lee County Schools has recommended to the Board that the Board accept Wright's bid for the Project, the Board has not voted on that recommendation. The fact that Wright used Empire's bid to calculate its lump sum bid in no way excuses Wright for the requirement set out in the bid documents that casework used for the Project (when the time comes) be manufactured by one of the four approved casework manufacturers. Wright gains no economic advantage in this regard since the lump sum bid price remains the same. The advertisement for Sealed Bids on the Project provides that the Board reserves the right to waive any and all irregularities of any bid received.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, accordingly RECOMMENDED: That the Board enter a Final Order dismissing the instant bid protest and awarding to Wright the contract for the construction of Elementary School "C", Job No. 91063. DONE and ORDERED this 13th day of February, 1992, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13 day of February, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NUMBER 91-7597B1D The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 3(1,2 and 3 , respectively); 4 - 5(6); 6(4); 7 - 9(5); 12(10); 13(11); 15 - 16(12); 17(13); 18 - 19(16); 20(29); 21(18); 23(19); 24 - 25(20); 26(22); 27(23); 28(22); 29 - 30(29); 32 - 33(25); and 34(26). Proposed finding of fact 10 is rejected as not being supported by competent substantial evidence in the record in that Wright's bid was as per plans and specifications without exceptions or exclusions which included the use of casework manufactured by one of the approved casework manufacturers. Proposed finding of fact 11 is rejected as not being supported by competent, substantial evidence in the record in that the Board knew of Empire's bid being based on nonconforming materials prior to issuing its Notice of Intent. However, the only information the Board had in reference to Wright's bid before issuing its Notice of Intent was that Wright had bid as per plans and specifications and would be installing casework manufactured by one of the approved manufacturers. The only question was whether Empire could furnish casework manufactured by one of the approved manufacturers. Proposed finding of fact 14 is neither material nor relevant. How the Board's architect interpreted Wright's bid is neither material nor relevant to this proceeding. Proposed finding of fact 22 is unnecessary to the conclusion reached in the Recommended Order. Proposed finding of fact 31 is more in the way of an argument than a finding of fact. Proposed findings of fact 35 and 36 are covered in the Preliminary Statement. The timeliness of Kellogg's protest is not an issue and therefore, a finding that it was timely is unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent While not specifically adopting proposed finding of fact 1, where material or relevant or necessary to this proceeding, and supported by competent, substantial evidence in the record the stipulated facts have been adopted. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2(4,5); 3(9); 4 - 5(7); 7 - 8(8); 10(16); 11(14); 12(31); 13(21); and 15(23). Proposed finding of fact 6 is more in the way of an argument than a finding of fact. Proposed finding of fact 9 and 14 are neither material nor relevant. Rulings on Proposed Findings of Fact Submitted by the Intervenor See ruling on Respondent's proposed finding of fact Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2 - 3(21); 4(24); 5 - 6(21); 13(23); 14(24,28); 15(22); 16 - 17(23,24); and 18(28). Proposed findings of fact 7 through 12 are neither material nor relevant to this proceeding. COPIES FURNISHED: David E. Gurley, Esquire Norton, Gurley & Darnell, P.A. 1819 Main Street, Suite 610 Sarasota, FL 34236 Marianne Kantor, Esquire The School Board of Lee County 2055 Central Avenue Fort Myers, FL 33901 James M. Talley, Esquire Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, P.A. Post Office Box 712 Orlando, FL 32802 Karl Engel Superintendent Lee County School Board 2055 Central Avenue Ft. Myers, FL 33901 Honorable Betty Castor Commissioner of Education The Capitol Tallahassee, FL 32399-0400