ALL SEASONS LANDSCAPE CONTRACTORS, INC. (E-7578) vs DEPARTMENT OF TRANSPORTATION, 96-003668BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 06, 1996 Number: 96-003668BID Latest Update: Nov. 27, 1996

Findings Of Fact Invitation to Bid (ITB) DOT Contract Number 7578 involves the mowing of various state roads in Citrus County, Florida. Citrus County is in District Seven of DOT. The ITB requires mowing, edging, sweeping and litter removal along state roads in Citrus County. The Petitioner, All Seasons is the current contractor performing the mowing services which are the subject of this protest. However, the ITB called for expansion of those services. The mowing contract had to be relet because All Seasons, opted not to renew its current contract because it felt that it was not making enough of a profit. The budget amount for the Contract Number 7578 protest was $180,000. The budget amount is the amount of money DOT has preapproved to spend for the contract. It is not the estimated amount DOT projects a contractor can perform the mowing contract for. The estimated amount is secret, but is generally close to the budgeted amount. Four bids were submitted for the mowing contract. The four bids were: Imperial Cabinets $ 70,201.05 Horticultural Industries $ 90,845.58 All Seasons $171,233.95 Mark Dunning Industries $181,119.61 In this instance, there was a large discrepancy among the bids on contract E-7578. The two lowest bidders were Imperial Cabinets and Horticultural Industries and were well below he budgeted amount. These two low bids were closer in proximity as to dollar amounts to each other and All Seasons and MDI's bids were closer in proximity to each other. The technical review committee (TRC) analyzed the bids and discussed whether or not the two lowest bidders were able to perform the contract. The TRC was concerned about whether the lowest bidder could perform the work required in the ITB at the price it bid. The TRC asked for information on the two lowest bidders from other districts. It did not receive any useful information. DOT did not inquire of the two low bidders. 1/ The TRC also consulted with DOT staff on the lowest bidder's prices. The staff thought the prices were low but could not state that the contract could not be performed the amounts which were bid. However, the TRC recommended rejection of all the bids to the awards committee. The TRC's recommendation was based on the speculation that the low bidders did not understand the scope of the mowing contract and that lack of understanding resulted in the bid prices of the two lowest bidders. However, there was nothing unique or confusing contained within the specifications of the ITB which would lead to the conclusion that a reasonable person could not understand. There is no way, just by looking at the bid proposal, to tell whether or not either firm could perform the contract at the prices. Additionally, there was no way to determine from the face of either firms bid if they did or did not understand the contract. In short, there was no factual basis for the TRC to find the low bids non-responsive and to recommend rejection of all the bids. The awards committee followed the recommendation and rejected all the bids. The awards committee utilized the same speculation the TRC had used its decision is as faulty. In this case, Petitioner relied on the same "evidence" as DOT regarding the inability of the two low bidders to perform the contract in order to demonstrate that the two low bidders were non-responsive. The evidence simply does not support a finding of non-responsiveness. Petitioner being the third place bidder has no substantive interest in this proceeding since it could not be awarded the mowing contract. Therefore, the bid protest should be dismissed.

Recommendation Based upon the findings of fact and the conclusions of law, it is, RECOMMENDED: That the contractors protest bid for Contract Number E-7578 be dismissed. DONE and ENTERED this 27th day of November, 1996, in Tallahassee, Leon County, Florida. DIANE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 27th day of November, 1996.

Florida Laws (2) 120.57287.057
# 1
ALL SEASONS LANDSCAPE CONTRACTORS, INC. (E-7578) vs DEPARTMENT OF TRANSPORTATION, 96-003667BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 07, 1996 Number: 96-003667BID Latest Update: Nov. 27, 1996

The Issue Whether All Seasons Landscape Contractors, Inc., should be awarded Department of Transportation Contract Number 7584 as the lowest and best bid.

Findings Of Fact Invitation to Bid (ITB) for DOT Contract Number E- 7584, involves the mechanical sweeping of state roadways within District Seven of DOT. District Seven is headquartered in Tampa, Florida. The budget amount for the sweeping project was $194,500.00. There were three bids submitted for the work contemplated by this contract. The bidders and amounts are: All Seasons Landscape $155,320.10 Mark Dunning Industries $187,719.68 Sweeping Corporation $191,864.03 All bidders, submitted bids that were under the budget amount. Petitioner's bid was the lowest bid submitted. The contract specifications for this project provide in pertinent part: M110-31-6 EQUIPMENT The mechanical sweeper shall have a capacity of at least three (3) cubic yards and shall be equipped with one or more brooms to loosen dirt and click it up into the sweeper. The swept material is then gathered onto the elevators for transport to the self contained storage hoppers for eventual rejection at selected disposal locations. A mechanic unit equipped with self elevation and self unloading hoppers for direct discharge into the trucks is also acceptable. The mechanical sweeper shall be equipped with the required safety devices as listed under Section M110-31 of the Special Provisions. The following sweepers are not considered mechanical sweepers for this specific contract. Vacuum Sweepers The vacuum sweeper uses brooms to loosen the dirt in the road and a vacuum to carry the dirt into the collection and storage chamber or container. Vacuum sweepers do not require mechanical elevators to pick up and load into the hoppers. Therefore, it DOES NOT meet the instead specified requirements. Regenerative Sweepers Regenerative sweepers that use forced air of a broom to loosen dirt on the road and employ the vacuum principle to collect the dust loosened by the blowing air and broom. This sweeper DOES NOT meet the requirements. The Contractor must have proof of ownership, or a signed lease for the duration of the contract for equipment suitable for meeting the requirements of this contract. A list of equipment to be used must be enclosed with the Contractor's bid. Where new equipment was purchased, the Contractor shall provide a signed quotation from an equipment dealer with a guaranteed delivery date in order to ensure that the work can begin on time. A sufficient supply of back-up equipment must be readily available by the Contractor by either lease or purchase to ensure timely and continuous fulfillment of this contract. In the event that an accident occurs involving the Contractor's equipment and another vehicle, other than the Contractor's, while the equipment is being used to accomplish authorized work on this contract, no relief in responsibility for work performance shall be granted to the Contractor. The above specification was specifically drafted by DOT to ensure a certain type of sweeping equipment be used by the contractor. DOT had problems with the equipment used under other sweeping contracts. The specifications for the sweeping contract required an equipment list to be submitted with the bid. The list was not required for other equipment. The requirement of the list was not confusing and apparent upon reading the specification. The Petitioner submitted a bid without including an equipment list. Intervenor submitted an equipment list. The third place bidder for the project also did not submit an equipment list with its bid. However, the fact that two out of three bidders failed to submit an equipment list does not lead to the conclusion that the specifications were not clear or confusing. After reviewing the bids, DOT determined that Petitioner's bid was non-responsive for failing to include an equipment list. The equipment list submitted by the Intervenor with its bid listed two pieces of equipment. DOT could not tell from this submitted list whether or not the equipment so listed met the specifications for the project. DOT procured from MDI an equipment brochure from the contractor as supplemental information to the submitted equipment list. This equipment brochure was received by DOT. The brochure demonstrated the equipment met the specification. The brochure did not materially alter the bid. DOT did not attempt to verify with the Petitioner what type of equipment it was currently using on DOT projects nor did DOT attempt to verify what type of equipment the Petitioner had available to use on this project. DOT could not allow the late submission of an equipment list since such a procedure would materially alter the bids after they were opened.

Recommendation Based upon the foregoing findings of fact and the conclusions of law, it is, RECOMMENDED: That the protest of ITB E-7584 be dismissed. DONE and ENTERED this 27th day of November, 1996, in Tallahassee, Leon County, Florida. 3060 9675 Hearings 1996. COPIES FURNISHED: _ DIANE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399- (904) 488-9675 SUNCOM 278- Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative this 27th day of November, Andrea Smart, Esquire Department of Transportation 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Brant L. Hargrove, Esquire 1026 East Park Avenue Tallahassee, Florida 32301 Thomas J. Cassidy, III, Esquire 303 Magnolia Avenue Panama City, Florida 32401 John Radey, Esquire Radey, Hinkle, Thomas, et al. 101 North Monroe Street Tallahassee, Florida 32301 Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 Thornton J. Williams, Esquire Department of Transportation 562 Haydon Burns Building Tallahassee, Florida 32399-0450

Florida Laws (3) 120.57287.057320.10
# 2
THE URBAN GROUP vs DEPARTMENT OF TRANSPORTATION, 94-005967BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 25, 1994 Number: 94-005967BID Latest Update: Feb. 14, 1995

Findings Of Fact The Department issued an invitation to bid (ITB) and solicited bids for district-wide miscellaneous property management maintenance services pursuant to ITB-DOT-94-95-4004. Kemp Services, Inc. (Kemp), submitted the lowest bid for the subject ITB. Petitioner, Urban Group, Inc., submitted the second lowest bid for the subject ITB. Section 1.1 of the ITB provided: Invitation The State of Florida Department of Transport- ation requests written bids from qualified firms to MAINTAIN RIGHT-OF-WAY STRUCTURES AND VACANT LOTS BY PROVIDING CLEAN-UP SERVICES, LAWN SERVICES, LANDSCAPE SERVICES, SECURING OF BUILDINGS, AND OTHER MISCELLANEOUS HANDYMAN AND SKILLED LABOR SERVICES. ALSO PROVIDE SERVICES FOR SIGN REMOVAL FOR STRUCTURES ILLEGALLY ON THE DEPARTMENT'S RIGHT-OF-WAY OR ILLEGALLY ON PRIVATE PROPERTY IN THE FOLLOWING FIVE COUNTY AREA: BROWARD, MARTIN, PALM BEACH, ST. LUCIE AND INDIAN RIVER COUNTIES. For the purpose of this document, the term "bidder" means the prime Consultant acting for itself and those individuals, partnerships, firms, or corporations comprising the bidder's team by joint venture or subcontract. The term "bid package" means the complete response of the bidder to the Invitation To Bid, including properly completed forms and supporting documentation. [Emphasis in text.] The services were to be provided on an as-needed basis for the term of the agreement, two years. Section 1.7.1 of the ITB provided: Qualifications 1.7.1 Bidders must meet the following minimum qualifications: BIDDERS MUST HAVE AT LEAST TWO YEARS EXPERIENCE PROVIDING AT LEAST TWO (2) OF THE SIX SERVICES OUTLINED IN THE SCOPE OF SERVICES IN EXHIBIT "A". BIDDERS MUST HAVE BEEN IN CONTINUOUS BUSINESS FOR THE PAST TWO (2) YEARS AND COMPLETE FORM "F" WITH THE INFORMATION REQUESTED REGARDING WORK EXPERIENCE AND REFERENCES. ALL REFERENCES WILL BE CHECKED. FAILURE TO PROVIDE FORM "F" AND THE WORK EXPERIENCE REQUESTED WILL CONSTITUTE A NON- RESPONSIVE BID. [Emphasis in text.] Section 1.7.4 of the ITB provided: Qualifications of Key Personnel Those individuals who will be directly involved in the project must have demonstrated experience in the areas delineated in the scope of work. Individuals whose qualifications are presented will be committed to the project for its duration unless otherwise accepted by the Department's Contract Manager. Where State of Florida registration or certification is deemed appropriate, a copy of the registration or certificate should be included in the bid package. Section 1.7.5 of the ITB provided: Authorizations and Licenses The Consultant must be authorized to do business in the State of Florida. Such authorization and/or licenses should be obtained by the bid due date and time, but in any case, will be required prior to award of the contract. For corporate authorization, contact: Florida Department of State Division of Corporations The Capitol Building Tallahassee, Florida 32399 (904)487-6052 Other than the provisions above, no other licensure or authorization to do business was required by the ITB. Section 1.8.2 of the ITB provided: Responsiveness of Bids All bids must be in writing. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid. Bids found to be non-responsive shall not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons, including, but not limited to, failure to utilize or complete prescribed forms, conditional bids, incomplete bids, indefinite or ambiguous bids, improper undated or unsealed signatures (where applicable). Section 1.8.4 of the ITB provided: Other Conditions Other conditions which may cause rejection of bids include evidence of collusion among bidders, obvious lack of experience or expertise to perform the required work, or failure to perform or meet financial obligations on previous contracts, or in the event an individual, firm, partnership, or corporation is on the United States Comptroller General's List of Ineligible Contractors for Federally Financed or Assisted Projects. Bids will be rejected if not delivered or received on or before the date and time specified as the due date for submission. Section 1.8.5 of the ITB provided: Waivers The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregular- ities are defined as those that will not have an adverse effect on the Department's interest and will not affect the price of the Bids by giving a bidder an advantage or benefit not enjoyed by other bidders. Section 1.18.1 of the ITB provided: Award of the Contract The Department intends to award a contract to the responsible and responsive bidder who bids the lowest cost as identified in Form "C", Bid Blank, attached hereto and made a part hereof. The ITB did not specify a minimum number of employees, vehicles or hours of service for a bidder to be deemed responsible or responsive. At all times material to this case, Kemp has been in continuous business for the past two (2) years, and completed form "F" with the information requested regarding work experience and references. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. At all times material to this case, Kemp had at least two years experience providing at least two (2) of the six services outlined in the scope of services. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. While Mr. Gentile was authorized to check with all references listed by Kemp, the failure to do so does not discount the information obtained from the sources that were checked. Kemp had an appropriate occupational license to perform work in the tricounty area, but did not have occupational licenses with the City of Hollywood or Broward County. At all times material to this case, Kemp maintained a warehouse to secure the equipment to be used such as lawnmowers, trimmers, and cleaning supplies/equipment. After the bid protest was filed, the Department verified that Kemp had used the warehouse as it claimed. No evidence to the contrary was presented. The mailing address Kemp listed on the first page of its bid response was 8637 S. Sutton Drive, Miramar, Florida. Mr. Faluade resides at that address. He listed that address for mail purposes. The business address for Kemp listed on the bid response was 6200 Johnson Street, Miramar, Florida. This address is a store-front facility with limited office equipment and furniture. Kemp maintains an office at this location but stores its equipment elsewhere as noted above. Kemp was the lowest responsive, responsible bid for ITB-DOT-94-95- 4004.

Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department of Transportation enter a final order dismissing Petitioner's challenge to the award of ITB-DOT-94-95-4004 to Kemp Services, Inc. DONE AND RECOMMENDED this 14th day of February, 1995, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of February, 1995. APPENDIX TO RECOMMENDED ORDER, CASE NO. 94-5967 Rulings on the proposed findings of fact submitted by the Petitioner: Paragraphs 1 through 4, 6, and 8 are accepted. With regard to paragraphs 5, 7, and 16 noting that the additional emphasis is not in the text and that the citations are incomplete (and perhaps misleading), they are accepted. Paragraph 9 is rejected as contrary to the weight of credible evidence. Paragraph 10 is rejected as contrary to the weight of credible evidence. Paragraph 11 is rejected as incomplete, and therefore, misleading. Corporate documents may have been filed on that date, however, the weight of the credible evidence established that Kemp had been in business the requisite amount of time. Paragraph 12 is rejected as incomplete, and therefore, misleading. The business conducted by the Kemp personnel continued regardless of the business entity structure that was used. Paragraph 13 is rejected as contrary to the weight of credible evidence. Paragraph 14 is rejected as contrary to the weight of credible evidence or irrelevant. Paragraph 15 is rejected as contrary to the weight of credible evidence. Paragraph 16 is rejected as contrary to the weight of credible evidence. Moreover, no credible evidence was presented to establish that Kemp did not provide services as described in the ITB or that it was not in business the requisite time. Paragraph 17 is rejected as incomplete, and therefore, misleading. The mailing address listed by Kemp was a residential address. Paragraph 18 is rejected as irrelevant. Paragraph 19 is rejected as contrary to the weight of credible evidence. Paragraph 20 is rejected as irrelevant. Kemp probably does not have a Leon County occupational license either. It did have an appropriate occupational license at all times material to this case. Rulings on the proposed findings of fact submitted by the Respondent: 1. Paragraphs 1 through 29 are accepted. COPIES FURNISHED: Thomas H. Duffy Assistant General Counsel Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Mitchell B. Polay Mark H. Klein 750 S.E. Third Avenue Suite 205 Fort Lauderdale, Florida 33316 Thornton J. Williams General Counsel Department of Transportation 562 Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450

# 3
EXPLOSIVES AND DIVING SERVICES, INC. vs. DEPARTMENT OF TRANSPORTATION, 84-003792 (1984)
Division of Administrative Hearings, Florida Number: 84-003792 Latest Update: Feb. 27, 1985

Findings Of Fact At some time prior to August 2, 1984, DOT issued bid blanks for a mini- contract for State Project No: 76020-3515, for work consisting of cleaning and guniting a concrete box culvert located on State Road 19, in Putnam County, Florida, approximately one mile south of the Cross Florida Barge Canal. The bid package, signed by C. A. Benedict, District Engineer, for the DOT, specifically reserved the right to reject any and all bids. The bid package broke the work down into three item numbers. The first was mobilization and called for one pricing unit. The second item called for maintenance of traffic at the work site and called for one pricing unit as well. The third area called for restoration of spalled areas (gunite) and called for approximately 437 cubic feet to be priced. In this regard, the plans furnished with the bid package and the bid package itself, in at least three separate locations, called for the bid as to the last item to be priced and paid for on a unit price basis. Petitioner submitted the lowest bid of seven bidders. It was determined to be faulty, however, in that though it properly priced the first two items, it failed to submit a unit price for the third item per unit, submitting instead a total price for the third item based on the entire cubic footage. Petitioner's bid indicated 437 cubic feet priced at a total of $17,832.00. Simple arithmetic permits a division which results in a unit price for each of the 437 cubic feet of $40,805. This last unit price, however, is not reflected on the bid submitted by Petitioner. Petitioner's bid is the only bid of the seven submitted which did not contain a unit price for each of the units in the third item. EDS has been in business since 1980. It performed one previous contract for DOT and is familiar with DOT's rules regarding bidding. It had ample opportunity to examine the plans and the bid blank before submitting its bid and admits that the unit price, though required, was omitted. Petitioner contends, however, that the omission is not a material variance and can be waived by Respondent. Respondent contends, on the other hand, that the failure to list the unit price in the third item is material. This determination is based on the fact that since the bid package calls for payment on a unit basis, the odd one- half cent per unit does not permit even money payment and requires rounding off. Even with this being true, the maximum difference would be one- half cent to be rounded off either upwards or downwards. At some point after opening, at least one of the unsuccessful bidders found out that Petitioner's bid failed to technically conform to the terms of the bid blank and at this point the second lowest bidder, Vann's Sandblasting, whose bid was $4,000.00 higher than that of Petitioner, and who had done several contracts for Respondent in the past, indicated that if petitioner's bid were not rejected, he would file a protest. The one-half cent variance, itself, is not material. Considering all factors, however, the failure to state the unit price may, under certain circumstances, be.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is, therefore: RECOMMENDED THAT Petitioner, EXPLOSIVE AND DIVING SERVICES, INC., be awarded the contract for State project No 76020-3515. RECOMMENDED this 27th day of February, 1985, at Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 FILED with the Clerk of the Division of Administrative Hearings this 27th day of February, 1985. COPIES FURNISHED: Gail S. Wood, President Explosive and Diving Services, Inc. Post Office Box 200 Clarksville, Florida 32430 Larry D. Scott, Esquire Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301 Paul Pappas, Secretary Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301

Florida Laws (1) 120.57
# 4
A2 M2 R CONSTRUCTION, INC. vs COLLIER COUNTY SCHOOL BOARD, 91-003828BID (1991)
Division of Administrative Hearings, Florida Filed:Naples, Florida Jun. 24, 1991 Number: 91-003828BID Latest Update: Aug. 05, 1991

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: On May 10, 1991, respondent, School Board of Collier County (Board), issued a written invitation to various contractors inviting them to submit proposals for certain construction work to be performed on Naples Park Elementary School in Collier County, Florida. The invitation in question is more specifically identified as Bid No. 120-5/91 Site Development/Naples Park Elementary School. The bidders were advised that their bids must be submitted no later than 2:00 p.m. on June 4, 1991. Bids were timely filed by five contracting firms, including petitioner, A2M2R Construction, Inc. (AMR), and Haas Construction, Inc. (Haas). On June 4, 1991, various school personnel, including Dallas Disney, Board architect, Vicki McKinney, Board assistant director of purchasing, and Pat Humphrey, a Board secretary, and the Board's engineering consultant, Glen Bridges, met for the purpose of opening the sealed bids. They agreed that the five bids would be opened in alphabetical order. This meant that AMR's bid was opened first while Haas' bid was opened fourth. Bridges was assigned the task of opening the bids and reading the dollar amount of each bid. In the case of AMR, it proposed a base bid in the amount of $174,815. When Bridges opened Haas' bid, he said words to the effect that he could not clearly make out the amount of the base bid. This was because the original number had been changed by Haas prior to the submission of its bid, and it could not be clearly read. Accordingly, Bridges handed the proposal to McKinney, who read the number as $146,500. She then handed the bid document to Disney who also concluded the bid was in that amount. At that point, the president of Haas, who was present at the bid opening, was asked if the amount was indeed $146,500. When he confirmed that it was, he was asked to place his initials next to the base bid number. He did so even though paragraph (6)(a) of the Bid Instructions provides that "(a)ny erasures or other corrections in the proposal must be explained or noted over the signature of bidders". According to AMR, this provision required that Haas initial the amount before it sealed and filed its bid. This interpretation of the Bid Instructions was confirmed by Board personnel. Thus, AMR contends that by Haas initialing its bid amount after the bids were opened, Haas violated the Bid Instructions and should have its bid proposal rejected. As it turned out, the bid amount submitted by Haas was the lowest dollar bid on the project, and the Board has proposed to award the contract to Haas. According to the Board's assistant superintendent for business affairs, Robert Wilson, who has supervised hundreds of bid lettings over the last several years, the circumstances in this case were "unusual" in that Haas initialed the bid amount after the bid documents were opened. However, Wilson considered this to be a minor irregularity which, by the terms of the Bid Instructions, could be waived by the Board. Further, he did not find such action to give Haas an undue advantage in the bidding process or place AMR and other bidders at a disadvantage. This was not contradicted. On the bid form used by the bidders, there is a line left blank before the space where the numerical amount of the bid is inserted. AMR contends that the purpose of this space was to be used by a bidder to spell out in words the amount of its bid, and because Haas did not spell out in words the dollar amount of its bid, the proposal should be rejected. However, there is no requirement in the Bid Instructions that the dollar amount be spelled out in words nor was there a school policy imposing such a requirement. Therefore, as to this contention, no irregularity in the bidding process occurred.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered by respondent awarding the contract in question to Haas Construction, Inc. DONE and ENTERED this 19th day of July, 1991, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of July, 1991. APPENDIX TO RECOMMENDED ORDER Respondent: 1-2. Adopted in finding of fact 3. Adopted in finding of fact 2. Adopted in finding of fact 4. 5-7. Adopted in finding of fact 3. Rejected as being unnecessary. Adopted in finding of fact 3. Adopted in finding of fact 4. Adopted in finding of fact 3. COPIES FURNISHED: Mr. James R. Powell, Jr. P. O. Box 150340 Cape Coral, FL 33915 Thomas W. Franchino, Esquire 700 Eleventh Street, South Suite 203 Naples, FL 33940-6777 Dr. Thomas L. Richey, Superintendent Collier County School Board 3710 Estey Avenue Naples, FL 33942

Florida Laws (1) 120.57
# 5
M AND J CONSTRUCTION COMPANY vs DEPARTMENT OF TRANSPORTATION, 94-006917BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Dec. 13, 1994 Number: 94-006917BID Latest Update: Jan. 25, 1995

Findings Of Fact Petitioner, M & J Construction Company of Pinellas County, Inc. (M & J) is a contractor prequalified to bid on FDOT construction projects in excess of $250,000. Mayo Contracting, Inc. (Mayo) is a contractor prequalified to bid on FDOT construction projects in excess of $250,000. Bid solicitation notices for state project no. 75280-3416 were mailed out to prospective bidders, including M & J, on August 26, 1994; and bid packages were mailed to firms requesting them on September 26, 1994. M & J received a bid package. On September 28, 1994, bids were submitted for a bridge repair contract in Orange County. Mayo submitted the lowest bid for the contract in the amount of $426,860.75 which was $54,060.05 lower than the second low bidder. M & J submitted the third lowest bid for the contract in the amount of $499,103.40. (Exhibit 5) The bid documents included the following notice which is printed in two different places in the bid package; once in double spaced bold capital letters, and once in standard size font. UNLESS OTHERWISE NOTIFIED IN WRITING, RETURN RECEIPT, THE SUMMARY OF BIDS FOR THIS PROJECT WILL BE POSTED WITH THE CLERK OF AGENCY PROCEED- INGS, FLORIDA DEPARTMENT OF TRANSPORTATION, 605 SUWANEE STREET, ROOM 562, TALLAHASSEE, FLORIDA 32399-0458, ON OCTOBER 20, 1994 OR NOVEMBER 7, 1994. BY CALLING THE CLERK OF AGENCY PROCEEDINGS, FLORIDA DEPARTMENT OF TRANSPORTATION, (904) 488-6212, DURING EACH POSTING PERIOD, INFORMATION CONCERNING THE POSTED PROJECTS CAN BE OBTAINED. INTERESTED PARTIES THAT HAVE A COMPUTER AND A MODEM CAN ACCESS INFORMATION FROM THE CONTRACTS ADMINISTRATION ELECTRONIC BULLETIN BOARD CONCERNING PROJECTS WHICH WERE POSTED WITH THE CLERK OF AGENCY PROCEEDINGS DURING EACH POSTING PERIOD BY DIALING (904) 922-4158 OR 922-4159. POSTING WILL PROVIDE NOTICE OF THE DEPARTMENT'S INTENT TO AWARD A CONTRACT OR TO REJECT ALL BIDS. THE DEPARTMENT'S NOTICE OF INTENT REGARDING THIS PROJECT WILL BE POSTED ON ONLY ONE OF THE ALTERNATE POSTING DATES. BIDDERS ARE SOLELY RESPONSIBLE FOR TIMELY MONITORING OR OTHERWISE VERIFYING ON WHICH OF THE SPECIFIED ALTERNATE POSTING DATES THE POSTING OF AWARD OR REJECTION OF ALL BIDS ACTUALLY OCCURS. (Exhibits 1 and 2). This notice is included in all FDOT bid packages. M & J has been bidding for FDOT contracts for seven years and submits approximately 40 bids to FDOT per year. M & J admits it did not heed the notices in the bid documents advising bidders that (1) the posting dates identified in the bid documents would not be changed unless written notice was provided, and (2) that the bidders are solely responsible for monitoring the posting dates. Mr. Boutzoukas and Mr. Leone said they were aware that the bid documents contained information regarding posting but they did not made any special note of the time frames nor did they double check after Mr. Leone's conversation with an FDOT employee. The day after the bid was submitted, M & J personnel became concerned about some alleged irregularities in the bid specifications or the bidding process. Mr. Leone called the FDOT contract office to find out the posting date. He is not certain of the identity of the person with whom he spoke, but he believes that it was Michael Schafenacher because of his "distinct, eloquent voice". The FDOT staff person, according to Mr. Leone, told him the posting was November 17 or December 5, 1994. This information was in conflict with the printed information in the bid package described in paragraph 5, above. No one at M & J bothered to look at the dates in the bid package, either before or after the telephone call to FDOT. Instead, Mr. Leone put the November 17/December 5 dates on the office chalkboard and continued with his investigation of the alleged irregularities, as directed by Mr. Boutzoukas. On October 20, 1994, consistent with the requirements of Section 120.53, F.S. and as provided in the notices in the bid packages, FDOT posted the notice of intent to award the contract to Mayo. On or about November 4, 1994, during the course of collecting data on the project, Mr. Boutzoukas realized that posting must have already occurred. He told Mr. Leone to call FDOT again and they then learned that the posting had occurred on October 20. Michael Schafenacher has worked in the FDOT contracts administration office for nine years. He maintains the critical dates chart for various projects and is involved in the pre- and post-bidding process. He and at least four or five other staff respond to numerous telephone inquiries each day regarding dates and the posting process. He remembers the early November call from M & J but nothing sooner, and he does not believe that he would have given erroneous dates from the critical dates chart. The chart reflects the same dates for the project as stated in the bid packages. FDOT keeps track of its contracts by the "letting" date, that is, the month in which bids are opened for a particular project. The project at issue, No. 75280-3416, was in the September letting. Mr. Schafenacker keeps his critical dates chart taped to his desk for easy reference. With or without the letting date, Mr. Schafenacher can quickly and easily find dates in response to telephone inquiries. If Mr. Schafenacher had given the wrong dates and had been told that the dates were inconsistent with the bidding documents, he would have investigated further to resolve the discrepancy. FDOT did not change the dates for the award of the project at issue; if it had, M & J and the other bidders would have received written notice. When there was no timely protest after the October 20 letting, FDOT awarded the contract to Mayo on or about October 26, 1994. As soon as it found out on November 4th that the bid was let, M & J filed its notice of protest by FAX on November 4, 1994. It did not follow up this notice with a formal protest, but rather filed a document called "Request for Opportunity to Protest More than Ten Days after the Post of the Intent to Award Bid, on or about November 30, 1994, after discussions with FDOT's legal staff. At no time did M & J file a protest bond. M & J's reliance on erroneous verbal information by an unidentified FDOT employee was unreasonable since M & J had the proper information readily in hand and ignored it. M & J waived its right to protest the bid award when it failed to timely file notice of the protest, a proper protest bond or a formal protest.

Recommendation Based on the foregoing, it is hereby RECOMMENDED: That the Florida Department of Transportation enter its final order denying the bid protest of M & J. DONE AND ENTERED this 24th day of January, 1995, in Tallahassee, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of January, 1995. APPENDIX The following constitute specific rulings on the findings of fact proposed by the parties. Petitioner's Proposed Findings M & J filed a memorandum and a four paragraph order. The findings proposed in that order are rejected as unsupported by the weight of evidence. However, the finding proposed in paragraph 3 is adopted to the extent that it establishes that M & J filed a notice as soon as it learned from FDOT that the bid was let on October 20. Respondent's Proposed Findings 1. Adopted in paragraph 3. 2.-4. Adopted in paragraph 5. Adopted in paragraph 3. Adopted in paragraph 5. Rejected as unnecessary. 8. Adopted in paragraph 1. 9. Adopted in paragraph 6. 10.-11. Rejected as unnecessary. 12.-13. Adopted in substance in paragraph 6. 14. Adopted in paragraph 3. 15.-16. Adopted in substance in paragraph 7. 17. Adopted in paragraph 11. 18.-20. Adopted in paragraph 12. 21. Adopted in paragraph 11. 22. Rejected as unnecessary. 23. Adopted in paragraph 12. 24. Adopted in paragraph 13. 25. Adopted in substance in paragraph 16. 26.-27. Adopted in paragraph 14. 28.-29. Adopted in paragraph 15. 30. Adopted in paragraph 14. 31. Adopted in paragraph 15. 32. Adopted in paragraph 16. Intervenor's Proposed Findings 1.-7. Adopted in paragraphs 1-6. Adopted in paragraph 7. Adopted in paragraph 9. Adopted in paragraph 14. 11.-12. Adopted in paragraph 15. COPIES FURNISHED: Michael E. Boutzoukas, Esquire Post Office Box 2731 Dunedin, Florida 34697-2731 Thomas H. Duffy, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Mary M. Piccard, Esquire Post Office Box 589 1004 DeSoto Park Drive Tallahassee, Florida 32302-0589 Ben G. Watts, Secretary ATTN: Deidre Grubbs Department of Transportation Haydon Burns Building, MS 58 605 Suwanee Street Tallahassee, Florida 32399-0450 Thornton J. Williams, General Counsel Department of Transportation 562 Haydon Burns Building Tallahassee, Florida 32399-0450

Florida Laws (3) 120.53120.57120.68 Florida Administrative Code (1) 14-25.024
# 6
ROSIEK CONSTRUCTION CO., INC. vs DEPARTMENT OF TRANSPORTATION, 04-002059BID (2004)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Jun. 09, 2004 Number: 04-002059BID Latest Update: Sep. 14, 2005

The Issue On May 12, 2004, did Respondent, Department of Transportation (DOT), act illegally, arbitrarily, dishonestly, or fraudulently when it cancelled the posting and noticed its intent to reject the bid of Rosiek Construction Co., Inc. (Rosiek), in relation to financial project Nos. 256903-1-52-01 and 256903-1-56-01, Pinellas Bayway Bridge Replacement, SR 682 (the Project)? § 120.57(3)(f), Fla. Stat. (2004).

Findings Of Fact The subject of this protest is financial project Nos. 256903-1-52-01 and 256903-1-56-01, Pinellas Bayway Bridge Replacement. Respondent and 12 other pre-qualified bidders received copies of the bid solicitation notice, plans and specifications for the Project at issue. Rosiek submitted a responsive bid for the Pinellas Bayway Bridge Replacement on April 28, 2004. There were no other bidders. Rosiek is pre-qualified to bid and receive the contract for the Project and therefore is a responsible bidder. On May 12, 2004, DOT posted its notice of intent to reject all bids. Rosiek timely filed this bid protest on May 14, 2004, with DOT, along with the statutorily required bid protest bond. DOT's 2004 Standard Specifications for Road and Bridge Construction is applicable to this project. FACTS BASED UPON ROSIEK'S ADMISSIONS DOT had advertised its bid solicitation notice for Financial Project Nos. 256903-1-52-01 and 256903-1-56-01, Pinellas Bayway Bridge Replacement on or about March 4, 2004. Rosiek received the copy of the Bid Solicitation Notice for the Project. Rosiek did not file a specifications challenge with respect to the referenced Project. DOT advertised the amount of $37,087,000.00 as its budgeted amount for the Project. Rosiek submitted a total bid of $50,470,378.12 for the Project (total bid A+B). ADDITIONAL FACTS Juanita Moore is a manager of the DOT Contracts Administration Office. She served as a member of the Technical Review Committee and the Awards Committee in relation to the Project. When the Technical Review Committee is confronted with a bid, such as the Rosiek bid, which is from a single bidder, something is missing from the bid or for certain differentials in price between the bid received and the official cost estimate, the Technical Review Committee considers these to be "problem jobs." In connection with terminology, Ms. Moore explained that the budget figure, referred to in the Bid Solicitation Notice for the Project as a Proposal Budget Estimate, is derived from an earlier estimate in the process and in turn an official cost estimate was established for the Project. The official cost estimate is also referred to simply as the estimate. The official cost estimate has not been disclosed as has been explained in the Preliminary Statement to the Recommended Order. The official cost estimate here is broken down into component items within the Project pertaining to cost for Mobilization, Concrete Class IV, Concrete Class V, etc. After the Technical Review Committee considered the Rosiek bid, the bid was passed on to the Awards Committee where it was decided to reject the bid. According to Ms. Moore the bid was rejected as too high when compared to the official cost estimate. The reference to a bid being too high relates to a bid which is more than 10 percent in excess of the official cost estimate. The budget figure and the official cost estimate are not necessarily the same in a given instance. The fact that it was the only bid was also a factor considered in the rejection. As Ms. Moore explained, at the time the Rosiek bid was rejected, it was principally because it was too high in relation to the official cost estimate. Given the posture in this case, the rejection as the only bid will form the basis for resolving this dispute, absent DOT's willingness to divulge the amount of the official cost estimate or how it was established. DOT does not have an established policy for rejecting bids based upon the fact that only a single bidder responded to the solicitation. In her experience, Ms. Moore does not remember DOT rejecting a bid solely on the ground that there was only one bidder. The minutes of the Awards Committee meeting held on May 12, 2004, detail the response by that committee to the Rosiek bid. In the copy of that document provided for this proceeding, DOT's official cost estimate is redacted. The percentage differential between the official cost estimate and the Rosiek bid is likewise redacted. The item number 0101-1 for Mobilization reflects Rosiek's bid of $4,900,000.00 compared to the official cost estimate which is redacted. Similarly, Item No. 0400-4-4, Concrete Class IV refers to the contractor bid price of $800.00 per cubic yard compared with the official cost estimate which is redacted. There are other comparisons between several additional categories or items in which the contractors bid price is reflected but the official cost estimate in comparison is redacted. The minutes go on to describe how the review being made by the Awards Committee led to the conclusion that the official cost estimate could be adjusted, placing the bid received by Rosiek a certain percentage above the estimate on a 10 percent criteria job but the differential between the adjusted official cost estimate and the Rosiek bid is not revealed as a percentage because of redaction. The DOT district where the project would be located is District 7, the Tampa office. The minutes of the Awards Committee meeting indicate that the district and the Technical Review Committee recommended to the Awards Committee that it reject the Rosiek bid and re-advertise. That was the decision made by the Awards Committee on May 12, 2004, to re-let in June. Nothing in the minutes prepared by the Awards Committee refers to the significance of Rosiek as the only bidder and any concern which the Awards Committee had about that fact. On May 12, 2004, when DOT provided a Cancellation of Posting and a Notice of Intent to Reject to Rosiek, it did not state the rationale for that decision. It merely indicated to Rosiek that it was DOT's intent to reject all bids on the project and advised Rosiek of its opportunity to contest that decision. On May 5, 2004, Kenneth A. Hartmann, P.E., the District 7 Secretary, prepared the District Response to Post- Bid Evaluation of Bids in Excess of Approved Award Criteria. The document is presented in question-and-answer form. In response to the question numbered 4 within the document, related to the prospect of critical safety deficiencies in the existing system being corrected by the construction of a new bridge, Mr. Hartmann responded with the answer "No." In relation to question numbered 2, excluding normal inflation, the question was asked whether re-advertising the project would likely result in a higher bid. Mr. Hartman answered "No." In response to question numbered 16, related to his recommendation as the district secretary, for action that should be taken by the Awards Committee he stated "This project should be rejected and re-advertised for a June 2004 1st [sic]. Considering that the project is medium to large and was competing against two other large bridge projects on the same day it is understandable that the contractor's bid was higher than our estimate." In response to question numbered 15 concerning the work load level of the contracting industry in the locality where the project would be constructed, Mr. Hartmann referred to "a high level of work load." At hearing Donald Skelton, P.E., the District 7 Secretary testified in support of the rejection of the Rosiek bid. In the past he had served as Director of Transportation Development with DOT, a position that made him responsible for preparation of the design plans and contract packages that are bid. He had involvement with this Project pertaining to the preparation of design plans and getting the Project to contract letting. He reviewed the Rosiek bid. In discussions related to the Rosiek bid during the post-bid evaluation period, there was a concern over a lack of competition and the differential between, what Mr. Skelton refers to, as the budget amount and the bid amount by Rosiek. Mr. Skelton was mindful of potential safety issues that might warrant the prospect of trying to find additional money to fund the Project, if it was necessary to replace the existing bridge for safety reasons. If the bridge were structurally deficient or in bad shape, that would need to be addressed, versus the additional time necessary to potentially rebid the project. No safety issues of that sort were found by Mr. Skelton. Mr. Skelton explained that the fact that there was single bidder made it difficult, if not impossible, to make a comparison between that bid and what the true market value of the bridge construction would be. Mr. Skelton expressed the hope by the DOT, that there would be more than one bidder in the future to truly get an impression of the degree of competition and whether the competition would result in a realistic price for the public. He recognized that there is no guarantee that DOT is going to get a lower bid if the project is re-bid. Mr. Skelton indicated that when you have multiple bids you can compare what the economic system would support in relation to the affordability of the project. That comparison is of similarity in prices among the competitors trying to win the job, with the belief that bidders put their best effort forward to prevail in the competition. A single bid does not give any indication of market factors, in his view. Michael Rosiek is the vice-president for Rosiek. In his testimony, he expressed a concern that if the project was re-let for bid, Rosiek's competitive position would not be good, in that the other contractors would have read the Rosiek bid that was made in the first letting, informing the competitors of the Rosiek price to its detriment. Further, Mr. Rosiek expressed a concern that in a re-letting the company would be bidding "against ourselves." Louis Wenick, P.E., has a business consulting service. The nature of the business is consulting work relating to the construction industry. A considerable part of the business involves DOT projects. In his work Mr. Wenick is involved with scheduling, cost analysis, and entitlement analysis in DOT projects. He is familiar with DOT's specifications, policies, and procedures. Mr. Wenick is a registered engineer in Florida and a certified general contractor in Florida. Mr. Wenick obtained information from DOT concerning its history in receiving sole bids for a project and the instances in which the sole bidder was awarded the contract. Mr. Wenick looked at procedures followed by DOT in awarding contracts. Mr. Wenick looked at the DOT experience in re- letting bids to determine if a company was a low bidder in the first letting when bids were rejected, and what percentage of the time that low bidder would succeed in being awarded the contract upon a re-letting. Mr. Wenick prepared certain charts intended to depict the DOT response in the areas examined by the witness. Rosiek's Exhibit numbered 3 is referred to as Problem Jobs for the April 28, 2004, letting, with two posting dates of May 20, 2004, and June 7, 2004, respectively. The chart depicts the proposal I.D. number (bid), the project number and the type of problem identified in reviewing bid responses and a brief statement of the Technical Committee's comments and the Awards Committee's disposition in those projects depicted. Nothing more is described in the chart. In no case set forth in the chart was the type of problem described in any detail or, limited to an experience with a single bidder, as opposed to perceived problems in relation to the bid that was too high, as well as having a single bidder or to the problem of having a bid that was too high alone. Seven projects were awarded. Two were not. The rejections were based upon the bids being too high. One of the projects initially awarded was later rejected due to the unavailability of local funding to support the project. Mr. Wenick prepared a chart, Rosiek's Exhibit numbered 4. This reflects the DOT award results for sole or single bidders from the period July 1999 through April 2005. The columns in the chart show the numeric count of sole bids, at certain letting dates, with the contracts numbers, the name of the low bidder, and the disposition of the bids. The numeric count of sole bids is a running tally over the period. This reflects 52 sole bids of which eight were rejected, making the percentage accepted 84.62 percent. Again the nature of the projects is not shown in the chart, and this chart does not indicate the basis for rejection. Rosiek's Exhibit numbered 5 is another chart prepared by Mr. Wenick. It reflects instances in which projects were re-let for bid in the period July 1999 to April 2005. The letting dates are reflected. The project numbers, the low bidders names, if known, and the amount quoted is set out. The re-let date if the project was re-let is reflected. The low quote on re-bid and the low bidder's name on re-bid are reflected, as is the percentage difference between the low quote in the first letting and the low quote in the re- letting. Where data is established in all columns in the chart, 18 of the projects are shown to have been re-bid out of 24 projects that were bid initially. Within that group, five bidders who bid in the initial letting were awarded the contract in the re-letting, while 13 low bidders in the first letting were disappointed in the re-letting. This equates to 27.78 percent success rate by the low bidder in the initial letting when re-bidding in the re-letting. Having considered the exhibits prepared by Mr. Wenick, the information is insufficient to discern the reason for DOT's past policies and practices and to compare them to the present case for consistencies in the application of those policies and practices when rejecting bids. Additionally, the reason for the choices in any single project described in the charts cannot be appropriately understood from the charts and compared to the experience here. On the topic of the success rate for contractors who provided the low bid in the original letting and the low bid in the re-letting, it is so general an analysis, that it cannot be relied upon to determine the real significance for contractors who provided the low bid in the original letting, only to be disappointed in the re-letting when the contractor did not receive the contract.

Recommendation Upon consideration, it is RECOMMENDED: That a final order be entered dismissing the Rosiek Amended Formal Written Protest challenging the DOT decision to reject its bid. DONE AND ENTERED this 17th day of August, 2005, in Tallahassee, Leon County, Florida. S ___________________________________ CHARLES C. ADAMS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of August, 2005.

Florida Laws (6) 120.569120.57120.68337.11337.168339.135
# 7
CSA MARINE SERVICES, INC. vs. DEPARTMENT OF TRANSPORTATION, 87-001161BID (1987)
Division of Administrative Hearings, Florida Number: 87-001161BID Latest Update: Apr. 22, 1987

Findings Of Fact On December 24, 1986, respondent, Department of Transportation (DOT), gave notice to qualified and interested contracting firms that it was accepting bids from firms interested in providing construction and maintenance services on State Job No. 08150-3412. Such bids were due on or before January 21, 1987. The job description read as follows: At State Bridge Nos. 080025 and 000026 over the Withlacoochee River North of Tampa. Work consists of Furnish and Install Integral Pile Jackets (port. cement grout filled); Remove and Replace Sections of Bridge Deck; Floating Turbidity Barrier; and Incidental Items. Length 0.066 Mile. (B.I. 1144013) Stated in plainer language, the project called for repairs to two bridges on I-75 which span the Withlacoochee River southwest of Ocala in Hernando County. The bidders were also provided with a copy of the specifications and bid form dated November 4, 1986 regarding the contract. In response to this offer, petitioner, CSA Marine Services, Inc. (CSAMS), a contractor with offices at 759 Parkway Street, Jupiter, Florida, filed a bid proposal by the established deadline. Its bid totalled $123,347.59. Also filing a bid proposal was Seig and Ambachtsheer, Inc. (SAI), a contractor in Orange City, Florida. Its bid price was $137,209.50. The bid form itself was prepared by DOT and merely required the contractor to fill in the blanks where appropriate. The first two columns were labeled "item number" and "approximate quantities" and were already completed by DOT. For those items having a quantity of only one, the words "lump sum were written in the second column. Where quantities exceeded one, they were expressed in such terms as linear feet, cubic yards and pounds together with the approximate numerical quantities. The third column was labeled "item description and unit or lump price (written in words)." The fourth column read "unit price (in figures)" and required the bidder to indicate the unit price of each line item in figures. The fifth or final column was labeled "amounts" and required the bidder to reflect the lump sum price of each line item in figures. Columns three through five were filled in by CSAMS where necessary. The total price of the bid was to be listed on a bid blank which was attached to the bid form. On its face, the third column on the form offered petitioner the option of either using a unit or lump sum price. In addition, section 2-5.1 of the Standard Specifications for Road and Bridge Construction, 1986 Edition, which governs the awarding of contracts and has been incorporated as a part of the bid documents, provides as follows: Proposals shall be submitted on the form described in 2-2. Unit or lump sum prices for all bid items shall be shown in words and figures, and all extensions shall be carried out. Notwithstanding the form and instructions, according to a DOT representative, a lump sum price may be used only when the quantity in column two is one item. If more than one item is reflected in column two, then DOT expects a contractor to use the unit price. However, there is no written rule, instruction or provision in the specifications that sets forth this requirement. CSAMS properly opted to use lump sum price under column three on at least two line items even though the quantities exceeded one. Of particular interest was line item 8400-3-4 which, according to column two, required 20.800 cubic yards of concrete for a "superstructure." Relying upon the optional language on the form, petitioner wrote the words seven thousand, one hundred, fifty five dollars and 00/100 cents" in column three (which was a lump sum price), and a unit price of $344.00 in column four. It then used the figure of $7,155 in the final column of that item, which is the approximate sum of $344 times the quantity (20.800). Because of the volume of bid lettings each month, DOT uses a computer to total the numbers in each line item for each bid. If the amount in column five does not agree with the figures in columns three and four, the computer flags the item, and a manual review of the line item is made. While reviewing line item 8400-3-4 of petitioner's bid form, the computer found the numbers did not agree. More specifically, when 20.800 in column two was multiplied times $344.00 in column four, it equalled $7,155.20 and not $7,155.00 as reflected in column five of petitioner's bid form. This twenty-cent disagreement arose because petitioner had rounded off the unit price from $343.99038 to $344.00 in column four. The disagreement prompted a manual review of petitioner's bid form and a recalculation of the line item. On January 30, 1987 DOT bureau chief J. Ted Barefield prepared a letter to CSAMS styled "Notice of Switch in Apparent Low Bidder" indicating in part: Due to mathematical error(s) on the bid of CSA Marine Services, Inc. and Continental Shelf Associates, Inc., the apparent low bidder, whose bid amount was $123,347.59 is now $265,016.59. Therefore, the apparent low bidder is Seig & Ambachtsheer, Inc. The change in amount was the result of DOT increasing the unit price in column four from $344 to $7,155 (to agree with column three) and multiplying the quantity (20.800) times the sum specified in words in column three ($7,155) to arrive at a total in column five of $148,824. This caused an increase of $141,669 over the original bid price. In making the above change, DOT relied on Section 3-1 of the 1986 Edition of the Standard Specifications for Road and Bridge Construction. Section 3-1 provides in relevant part as follows: In the event of any discrepancy in the three entries for the price for any item, the unit price as shown in words shall govern unless the extension and the unit price shown in figures are in agreement with each other, in which case they shall govern over the unit price shown in words. (Emphasis added) Here, because of the twenty-cent discrepancy in the entries for line item 8400-3-4, DOT used the "unit price as shown in words" in column three to recalculate the item since the extension ($7,155.00) and the unit price shown in figures ($344.00)" did not agree. In doing so, DOT did not first evaluate the price written in words to see if it was a lump sum or unit price. After receiving the above letter, CSAMS and DOT representatives met in early February 1987 to discuss the CSAMS proposal. It was represented to CSAMS that it should have used a unit price in words in column three rather than a lump sum price. Petitioner was also provided with a copy of a letter previously sent to it on September 6, 1985 by DOT which noted the following irregularity on a bid: "Unit prices as written in words and figures do not agree (Item 8457- 70)." However, the letter did not contain explicit advice as to DOT's unwritten policy. On February 5, 1987 Barefield wrote a second letter to CSAMS indicating that there were several discrepancies in its bid proposal. These included: (a) the name on the cover sheet (CSAMS and Continental Shelf Associates, Inc.) did not agree with the name (CSAMS) in other parts of the bid, (b) unit prices as written in words and figures did not agree, (c) an incomplete affidavit was filed, and (d) an incorrect MBE Certification and incomplete Utilization Sheets were submitted. The latter two errors were related to the discrepancy in the names. However, the letter stated that "no further action is requested by you at this time," and that the letter was to serve as a reminder that in the future the irregularities could cause petitioner's bid to be rejected. Petitioner's bid was accepted as being appropriate but with the substantially higher bid price of $265,016.59. The error made by CSAMS is a common one. Indeed, it was stated the same mistake is made by contractors on "several bids during each letting." Even so, DOT has not considered providing some special instruction or rule to clarify this matter.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that petitioner be awarded the contract on State Job No. 08150- 3412. DONE AND ORDERED this 22nd day of April, 1987, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of April, 1987.

Florida Laws (5) 120.53120.57120.68155.2035.22
# 8
BUTLER CONSTRUCTION COMPANY vs DEPARTMENT OF CORRECTIONS, 93-003971BID (1993)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 22, 1993 Number: 93-003971BID Latest Update: Sep. 15, 1993

Findings Of Fact Based upon the evidence adduced at hearing, and the record as a whole, the following Findings of Fact are made: In March of 1993, the Department issued an Advertisement for Bids (hereinafter referred to as the "Advertisement") through which it solicited the submission of bids on a construction project (Department Project No. NV-30A, which is hereinafter referred to as the "Project") involving the expansion of the water treatment facility at the Martin Correctional Institution. The Advertisement, along with the other bid documents issued in conjunction with the Advertisement, including, but not limited to, the Instructions to Bidders (hereinafter referred to as the "Instructions") and the Proposal Form, were compiled in a two-volume Specifications Manual (hereinafter referred to as the "Manual") that was made available for public inspection. Section B of the Manual's first volume contained the Instructions. Section B-2 2.A.(11) thereof provided that "Section 01420 as contained in the Technical Specifications must be submitted and the qualifications listed therein must be satisfactory to the Owner and the Engineer. " "Section 01420 as contained in the Technical Specifications" was a "Bidder's Qualification Form, Reverse Osmosis Treatment System Component" (hereinafter referred to as the "R.O. Form"), on which the bidder was to provide "R.O. [Reverse Osmosis] System Supplier" information. The R.O. Form repeated the directive that the bidder was to "[r]eturn [the] [c]ompleted [R.O.] Form [w]ith [its] proposal." Section B-14 of the Instructions addressed the subject of "preparation and submission of bids" and provided, in pertinent part, as follows: Each Bidder shall copy the proposal form on his own letterhead, indicate his bid prices thereon in proper spaces, for the Base Bid and for alternates on which he bids. . . . Proposals containing . . . . items not called for or irregularities of any kind may be rejected by the Owner. Section B-16 of the Instructions addressed the subject of "disqualification of bidders" and provided, in pertinent part, as follows: More than one bid from an individual, firm, partnership, corporation or association under the same or different names will not be considered. Reasonable grounds for believing that a Bidder is interested in more than one proposal for the same work will cause the rejection of all proposals in which such Bidders are believed to be interested. The subject of "contract award" was addressed in Section B-21 of the Instructions, which provided, in pertinent part, as follows: . . . The recommendation for contract award will be for the bidder qualified in accordance with Section B-2 and submitting the lowest bid provided his bid is responsible and it is in the best interest of the Owner to accept it. The qualified bidder submitting the lowest bid will be that bidder who has submitted the lowest price for the base bid, or the base bid plus additive alternates or less deductive alternates, taken in the numerical order listed in the bid documents in an amount to be determined by the Owner. The Order of the alternates may be accepted by the Owner in any sequence so long as such acceptance does not alter the designation of the low bidder. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the Owner. Section C of Volume I of the Manual contained the Proposal Form that all bidders were required to use to indicate their bid prices. The following statement appeared at the bottom of the second page of the Proposal Form: There is enclosed: A certified check, cashier's check, treasurer's check, bank draft or Bid Bond in the amount of not less than five (5) percent of the Base Bid payable to the Department of Corrections, as a guarantee. An executed Trench Excavation Safety Certification, Section F-13. An executed Experience Questionnaire and Contractor's Financial Statement and Public Entity Criminal Conviction Form, Section L. An executed Bidder's Qualifications Form (Reverse Osmosis), Technical Specification Section 01420. While one completed R.O. Form had to accompany each bid, there was no provision in any of the bid documents issued by the Department requiring a bidder to submit only one such completed form and no more. Petitioner, McMahan and R.J. Sullivan Corporation (hereinafter referred to as "Sullivan") were among the contractors that timely submitted bids in response to the Advertisement. McMahan's and Sullivan's bids were each accompanied by more than one completed R.O. Form. Petitioner, on the other hand, provided the Department with only one completed R.O. Form along with its bid. Of the bids submitted, McMahan's was the lowest, Sullivan's was the second lowest and Petitioner's was the third lowest. McMahan's base bid price was $857,000.00. Petitioner's was $905,000.00. McMahan's total price, including the nine additive alternates accepted by the Department, was $948,000.00. Petitioner's was $1,032,600.00, $84,600.00 more than McMahan's. By letter dated July 1, 1993, the Department advised McMahan of its intent "to award the contract [for Department Project No. NV-30A] to [McMahan] as the lowest responsive bidder." On July 9, 1993, Petitioner filed a formal written protest of the preliminary determination to award the contract to McMahan alleging that McMahan was not a responsive bidder inasmuch as McMahan "submitted Reverse Osmosis ("R.O.") Qualifications Forms for more tha[n] one vendor." According to Petitioner, "[t]his [was] not in conformance with the Bid Documents and gave [McMahan] an unfair advantage."

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Corrections enter a final order finding Petitioner's bid protest to be without merit and awarding McMahan, as the lowest responsive and qualified bidder, the contract for Department Project No. NV-30A. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 2nd day of September, 1993. STUART M. LERNER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of September, 1993.

Florida Administrative Code (3) 60D-5.00260D-5.00760D-5.0071
# 9
POWER SWEEPING SERVICE, INC. vs DEPARTMENT OF TRANSPORTATION, 91-007592BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Nov. 26, 1991 Number: 91-007592BID Latest Update: May 01, 1992

Findings Of Fact By Joint Prehearing Stipulation filed at the time of hearing, the parties agree that bids for contract No. E-4450, the contract in issue here, were opened by the Respondent in Fort Lauderdale on October 11, 1991. Bids were received from five bidders including the Petitioner, Power, and the low bidder, Certified. Based on its evaluation of the bids submitted, on October 18, 1991, Respondent posted an intent to award the contract to Power Sweeping Services, Inc., Petitioner herein. However, thereafter, on October 22, 1991, the Department received a formal protest from the low bidder, Certified, challenging the intent to award. After review of the substance of Certified's protest, Respondent notified all bidders that it would be reposting its intent to award on November 5, 1991, and on that date, did repost, indicating an intent to award the contract in question to Certified, the low bidder. Thereafter, on November 14, 1991, Petitioner timely filed its formal protest, having filed its initial intent to protest on November 6, 1991. The bid blank, which was issued to all prospective bidders at the pre- bid conference held in this matter for a contract to involve mechanical sweeping on Interstate Highway 595 from its eastern terminus to Southwest 136th Avenue, including interchange ramps at I-95, I-595, and State Road 84, contained as a part thereof a notice to contractors which, at page 1 of 4, (page 1 of the 36 page bid package), contained a notation that for contracts of $150,000.00 or less, the bidder would be required to submit, as proof of ability to acquire a performance and payments bond: a notarized letter from a bonding company, bank or other financial institution stating they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: a bid guarantee of five percent (5%); or a copy of the contractor's certificate of qualification issued by the Department. This note specifically states that "failure to provide the following required evidence of bonding", as indicated above, with the bid proposal would result in rejection of the contractor's bid. Petitioner submitted a notarized "letter of commitment to issue bond" dated October 8, 1991, by Burton Harris, attorney in fact and resident agent for American Bonding Company. Certified submitted with its bid an un-notarized letter from Mark A. Latini, bond manager with Bonina - McCutchen - Bradshaw Insurance to the effect that "Amwest Surety Insurance Company is the surety for the above referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should CPM be low and awarded the referenced contract." Five bidders submitted bids. Certified was the low bidder with a bid price of $61,474.85. Florida Sweeping, Incorporated was second low bidder with a bid of $67,388.16, but that bid was rejected because an addendum was not noted. Petitioner was third lowest bidder with a bid of $72,290.65. Because Certified's bid as initially submitted did not contain the required notarized letter from the bonding company, its bid was initially rejected. Thereafter, however, Certified's president, Mr. Hanousek, who prepared Certified's bid, and who attended the pre-bid meeting, called the Department's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. As a result, he submitted a notice of protest and a subsequent protest to the denial of Certified's bid. A hearing on Certified's protest was not held. When Joseph Yesbeck, the District's director of planning and programs, who was at the time serving as acting district secretary in the absence of the appointed secretary, was contacted by Mr. Hanousek. He reviewed the file and met with Ms. Martin, the District's contract administrator for construction and maintenance contracts and the contracting staff to see what was happening. At that point Ms. Martin explained why Certified's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. When the District secretary came back, Mr. Yesbeck briefed him and recommended that based on the information he had received from the District and Department attorneys, the failure to submit the notarized letter should be considered a non-material deviation and the Certified bid be determined the low responsive bidder. The reasons for this were that the absence of the notary did not really give any competitive advantage to Certified and that ordinarily defects of this nature are routinely allowed to be cured. When the District secretary, on the basis of the information provided by Mr. Yesbeck, decided to repost the contract, Mr. Yesbeck prepared a joint letter of reposting which removed Certified's disqualification and left it as the low bidder. None of the other rejected bidders, including Florida Sweeping and bidder Number 5, which was rejected because its bond proposal was not of a proper character, were advised that they could come in and correct the defects with their bond letters. According to Ms. Martin, the notice to contractors requiring a notarized letter from a bonding company as an alternative to the requirement to post a 5% bid guarantee was designed to promote participation in state contracting by small business and minority business enterprise applicants, so that the bidder does not actually have to post the bond in question. The notarization requirement was put in by the Department but neither Ms. Martin nor any other witness testifying on behalf of the Department was able to indicate why the bond certification had to be notarized. Historically, when the Department has gotten a bid without a notarized bond letter it has been rejected, and in Ms. Martin's experience, she has never known of a protest based on such a denial since she began working with contracts in July, 1988. When she reviews the bids, she reviews the bonding letter for its content as well as seeing whether it is notarized. Here, her reason for initially rejecting certified's bid was solely that the bond commitment letter was not notarized. The decision to reject was not hers alone, however, since she also checked with the District General Counsel who initially advised her that Certified's bond commitment letter was no good. Apparently, counsel changed his position upon discussion of the matter with Mr. Yesbeck and the Department's General Counsel since, according to Mr. Yesbeck, both counsel recommended subsequently that the absence of the notarization not be a disqualification. Further, according to Ms. Martin the requirement for the notarization has been utilized by District 4 since 1987 with all bids requiring it notwithstanding Mr. Hanousek's testimony that he has never seen the requirement before in any of the 6 successful contract's he has had with the Department before. In that regard, however, he admits this is the only contract he has had with District 4. Ms. Martin does not know if the notarization requirement is used in other Districts and no evidence as presented by any party to clarify that issue.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law it is, therefore: RECOMMENDED that a Final Order be entered setting aside the determination that Certified Property Maintenance's bid on Contract No. E4450, Job No. 869069108 was the low responsive bid. RECOMMENDED in Tallahassee, Florida this 28th day of January, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of January, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 91-7592BID The following constitute my ruling on all Proposed Findings of Fact pursuant to Section 120.59(2), Florida Statutes submitted by the parties hereto. FOR THE PETITIONER: None submitted. FOR THE RESPONDENT: 1. & 2. Accepted and incorporated herein. Accepted and incorporated herein except for the finding that Certified's bid complied in every respect except the notarization. The assurance by the bonding company was not unqualified but conditioned upon Certified being awarded the contract. Accepted and incorporated herein. & 6. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Accepted and incorporated herein except for last sentence regarding which see 3., supra. Accepted and incorporated herein. FOR THE INTERVENOR: None submitted. COPIES FURNISHED: Bruce M. Cease, Esquire 2720 West Flagler Street Miami, Florida 33135 Susan P. Stephens, Esquire Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0458 Ray Hanousek President Certified Property Maintenance 3203 Robbins Road Pompano Beach, Florida 33062 Ben G. Watts Secretary Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458 Thornton J. Williams General Counsel Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458

Florida Laws (3) 120.53120.57337.11