POSEIDON MINES, INC. vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-002092 (1975)
Division of Administrative Hearings, Florida Number: 75-002092 Latest Update: Mar. 21, 1977

The Issue Whether a consumptive use permit for the quantities of water requested in the application should be granted.

Findings Of Fact Application 7500137 seeks an average daily withdrawal of 2.4 million gallons of water with maximum daily withdrawal not more than 2.88 million gallons from an existing well in order to process phosphate and reclaim land. This is an existing use for mining operations located southwest of Lakeland, Florida, on land consisting of 1531 acres. Notice was published in a newspaper of general circulation, to wit: The Lakeland Ledger, on November 11 & 18, 1975, pursuant to Section 373.146, Florida Statutes. The application and affidavit of publication were admitted into evidence without objection as Composite Exhibit 1, together with correspondence from James R. Brown, Vice President, Dagus Engineers, Inc., dated November 19, 1975 to the Southwest Florida Water Management District. No objections were received by the Water Management District as to the application. Mr. George Szell, hydrologist of the Water Management District testified that the application met the conditions for a consumptive use permit as set forth in Chapter 16J-2.11, Florida Administrative Code, except that the quantity of water requested to be withdrawn is 41.06 per cent over the maximum average daily withdrawal permitted under the water crop theory as set forth in Section 16J-2.11(3), F.A.C. However, the Water Management District witness recommended waiver of that provision since the mining operations will be concluded in several years and thereafter the water table and hydrologic conditions will return to normal. The Water District staff recommended approval of the application with the condition that a meter be installed on the well and that the applicant be required to take monthly readings thereof and submit quarterly reports of the readings to the District. The applicant's representative agreed to these conditions at the hearing.

Recommendation It is recommended that Application No. 7500137 submitted by Poseidon Mines, Inc., for a consumptive water use permit be granted on the condition that a meter be installed on the applicant's well and that monthly readings be taken and submitted quarterly by the applicant to the Southwest Florida Water Management District. It is further recommended that the Board of Governors of the Southwest Florida Water Management District, pursuant to Rule 16J-2.11(5), for good cause, grant an exception to the provisions of Rule 16J-2.11(3), as being consistent with the public interest. DONE and ENTERED this 19th day of January, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: J.T. Ahern, Staff Attorney Southwest Florida Water Management District P.O. Box 457 Brooksville, Florida 33512 Poseidon Mines, Inc. P.O. Box 5172 Bartow, Florida

Florida Laws (1) 373.146
# 1
LAKE WORTH DRAINAGE DISTRICT vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-001741 (1983)
Division of Administrative Hearings, Florida Number: 83-001741 Latest Update: May 02, 1984

Findings Of Fact Lake Worth Drainage District requested a variance from the provisions of Rule 17-3.121(13) , Florida Administrative Code, related to dissolved oxygen parameters which would be involved in the installation of a canal known as the S-9 Canal to be located in Palm Beach County, Florida. That request was met by the Department of Environmental Regulation's Statement of Intent to Deny, leading to a request for formal hearing filed by Petitioner with the Department on May 26, 1983. On June 1, 1983, the Department requested the Division of Administrative Hearings to conduct a formal hearing in that matter. The variance request became D.O.A.H. Case No. 83-1741. Contemporaneous with the variance request that was pending before the Department of Environmental Regulation, was petitioner's request for necessary construction permits to install the S-9 Canal. Again, the Petitioner was informed of the agency's intent to deny that permit request. As a consequence, Petitioner requested a formal hearing to question the Department's policy decision. That request for formal hearing was made on June 23, 1983. Effective July 1, 1983, the Department asked the Division of Administrative Hearings to conduct a formal hearing related to that permit request. The case related to the dredge and fill permit is D.O.A.H. Case No. 63-2132. WITNESSES AND EXHIBITS In the final hearing, petitioner presented the testimony of Richard Wheeliahn, Assistant Manager for Lake Worth Drainage District; John Adams, General Counsel for Lake Worth Drainage District; Mike Slaton, supervisory biologist with the United States Corp. of Engineers; William Winters, Lake Worth Drainage District's in-house engineer; Rebecca Serra, South Florida Water Management District's Water Management Engineer, who was accepted as an expert in water management engineering; Raleigh Griffis, Agricultural Agent with the United States Department of Agriculture, accepted as an expert in the agricultural practices found within the area of the proposed S-9 Canal; William E. Hill, Consulting Engineer for Petitioner, who was accepted as an expert in civil engineering and drainage design; and Robert D. Blackburn, consultant to Lake Worth Drainage District, accepted as an expert in freshwater ecology to include water quality and biology. Respondent called as witnesses Dan Garlick, Environmental Specialist for the Department of Environmental Regulation, accepted as expert in dredge and fill matters; Keith McCarron, Environmental Specialist for the Southeast Branch of the Department of Environmental Regulation, accepted as an expert in dredge and fill matters and Helen Setchfield, Technical Assistant to the Department's Director of the Division of Environmental Permitting. In addition, Richard L. Miller, Rebecca Butts, Francis T. Kuschell, Donald King and Dan alley were public witnesses in favor of the proposed project. Rosa Druando and Sherry Cummings were public witnesses opposed to the project. Petitioner offered 45 exhibits which have been received. Respondent introduced two exhibits which were admitted. The public offered two composite exhibits which were admitted. SPECIFIC FACTS Lake Worth Drainage District is a governmental entity created by the Florida Legislature. The District's function is that of the control of water supply and elevation related to lands within its jurisdiction. Those areas in dispute in the present case are within that jurisdictional ambit. In this instance, Lake Worth Drainage District has proposed the construction of a drainage facility involving dredging and filling of approximately 45,000 cubic yards of material. In particular, Petitioner seeks necessary permits from Respondent to construct a canal known as the S-9 Canal, whose purpose would be to transport the flow of water from an agricultural operation north of the canal site. Petitioner's Exhibit No. 1 depicts the area in question with the north- south orange tape representing an unnamed drainage ditch or canal and the blue tape showing the proposed S-9 connecting it to the east-west orange tape line which is L23W. The primary type of water expected in the canal is stormwater; however, surface and groundwater will also be in the canal system at times. The agricultural operation is capable of discharging at a rate which would utilize 145 CFS of the potential capacity of the canal system contemplated for construction which ultimate capacity is 170 CFS. The proposed canal by its connection of the existing agricultural drainage ditch or canal and L23W, becomes part of a water transport system flowing to the Atlantic Ocean through the South Florida Water Management District and Lake Worth Drainage District canal network. The principal benefit of the construction of S-9 would be to create a uniform connection of water discharge from the agricultural operation into L23W. Secondarily, it would relieve periodic flooding of a residential area west of the unnamed drainage ditch and northwest of the proposed S-9 Canal. It is not designed to receive direct water input from that residential area. Only the agricultural operation has been granted permits to discharge into the unnamed canal through two pumping stations to the east of that canal and as a result of the present permit request through S-9 and thus to L23W. Those persons living in the residential area west of the unnamed canal have not sought necessary permitting for discharge into the proposed S-9 System. Moreover, even if permits were granted to the residents, the S-9 system would only allow the addition of 25 CPS over and above the 145 which the agricultural operation has preempted. The 25 CPS would not satisfactorily address high water problems found in the residential area. A more particular description of the limited value of the project's benefit to the homeowners is that it protects against occasional flooding which occurs when the farm operation discharges into the unnamed canal, causing water incursion in the southeast corner of the residential area to the west of the unnamed canal. If the S-9 Canal is constructed, it will be built within an 80 foot right-of-way held by petitioner. The canal as depicted in petitioner's Exhibit 35 admitted into evidence is 40-45 feet wide, approximately 5-8 feet deep and is configured in a u-shape transversing an area of 7,730 feet. The applicants in this present proposal have added a vegetated iittoral zone on one side of the canal and it covers approximately 20 percent or 1.9 acres of the canal surface. This zone affords a limited amount of treatment of the water in the system. In this regard, approximately 30 percent of the nutrients found within the water flowing in the system would be expected to be taken up or absorbed in the vegetational zone, except in the months of August and September, when optimum retention time within the system will not be afforded to allow the littoral zone to uptake 30 percent of contaminants in the water. A 21 foot maintenance berm would be constructed on the east side of the canal and bleeder pipes would be installed to control water elevations in the adjacent wetlands. The 170 CFS volume mentioned before is the design capacity of the proposed system. At that volume, the flow velocity is less than 2.6 feet per second, a velocity at which the canal's structural integrity would be expected to continue, i.e., erosion will not occur. The 145 CFS expected from the agricultural operation pursuant to permits for discharge issued by the South Florida Water Management District would promote a flow velocity of approximately 2 feet per second. This farm activity is known as the DuBois farm. (Its permit from the South Florida Water Management District allowing the 145 CFS to be discharged into the unnamed drainage ditch or canal is not contingent upon the construction of S-9.) The configuration of the S-9 Canal has been brought about principally to advantage the Petitioner in obtaining a construction permit from the United States Corps of Engineers. The Corps had an interest in protecting that corridor of land over which it has jurisdiction which is adjacent to the S-9 Canal and is described as a wetland area. A consequence of this choice of design for S-9 is the typical 72 to 80 hour travel time of water introduced into the system providing some settling of pollutants and some assimilation of pollutants within the littoral zone of the canal discussed before. 10..Necessary permits have been obtained from South Florida Water Management District and the United States Corps of Engineers to allow the construction of the proposed project. The configuration of this project takes into account the special concerns of those two agencies. In this sequence of collateral permitting, South Florida Water Management District has been responsible for an examination of stormwater quality considerations in deciding to grant a permit to Petitioner. With the construction of S-9 and connection of the unnamed canal to S- 9 and thus to L23W, all the waters within that conveyance system become Class III waters of the state in keeping with Chapter 403, Florida Statutes and its associated rules of the Florida Administrative Code. In effect, this is a dredge and fill activity under the Respondent's jurisdiction found in Rule 17- 4.20, Florida Statutes. As such, it becomes a stationary installation which can reasonably be expected to be a source of water pollution of waters of the state by discharge of pollutants into waters of the state as envisioned by Section 403.087, Florida Statutes. During the construction phase of the canal, water quality degradation can be controlled related to turbidity, transparency and other criteria. Upon connection of the S-9 Canal to L23W and the utilization of that system, problems will be experienced with dissolved oxygen levels and to a lesser extent, nutrients and total coliform. Oils and greases problems are possible though not probable. No other water quality impacts are expected after connection. In expectation of the difficulty in achieving compliance with Respondent's water quality standards related to dissolved oxygen, the Petitioner has sought a variance under Section 403.021, Florida Statutes. This request is necessary because the dissolved oxygen levels in the proposed S-9 Canal, the unnamed canal or drainage ditch and L23W are not expected to uniformly exceed 5 mg/1. See Rule 17-3.121(13), Florida Administrative Code. The problem with dissolved oxygen in the unnamed canal and L23W and expected in the S-9 canal is not an enigma. This condition is prevalent in the South Florida area to include Palm Beach County, the site of the project. The water in the canals and drainage ditches in the region is frequently in violation of the standards related to dissolved oxygen, given the elevations of the land, climatic conditions, type of plant life, water temperature and constituents of the water. The addition of S-9 to the system would neither improve nor significantly degrade the quality of water related to the dissolved oxygen values for Class III waters, of which this proposed system is constituted. This finding acknowledges the fact that dissolved oxygen values in the unnamed canal are superior to L23W. Nonetheless, upon completion of S-9 and connection to the two other canals, no significant positive improvements of dissolved oxygen will be realized. Moreover, considering the fact that the installation of the S-9 Canal will stop the flooding on the southeast corner of the residential area west of the unnamed drainage ditch or canal, an increased volume of water flowing into L23W at any given moment can be expected, compared to the present outfall primarily along the Florida Power and Light system road into L23W. This has significance related to the dissolved oxygen standard to the extent of an increased volume of water in which substandard dissolved oxygen levels are found being introduced into L23W. It is more significant related to nutrients and bacteriological quality of the water, in particular fecal coliform. While there is no reason to believe that the quality of cleansing of water involved in sheet flow into L23W related to nutrients and coliforms is remarkably better at present, given the sparse vegetation along the power-line road which leads to L23W, than would be the case with S-9 with littoral zone, the increased volume of cater being introduced at the connection of S-9 and L23W during times of peak discharge, can be expected to present greater quantities of nutrients and coliform. In essence, the treatment afforded by the littoral zone and the transport in the S-9 Canal, contrasted with the treatment afforded during the transport of waters by sheet flow along the relatively barren stretch of land adjacent to the power-line road is found to be comparable, and the differences relate only to volume of discharge. This difficulty with nutrients and coliform count has been confirmed by tests made in the unnamed canal showing excessive levels of nitrogen, phosphorus and coliform and the water treatment features of the S-9 Canal will not entirely remove these materials. Although the farming practices of the DuBois operation tend to alleviate some nutrient loading in the unnamed canal, the test results established that those practices do not entirely eliminate the introduction of those nutrient materials into the canal. Consequently, some problems related to the effects of nutrient loading on populations of flora and fauna in the proposed system can be expected. In the context of the variance request, alternatives to the construction of the S-9 Canal are here considered. The alternative to leave the circumstance as it now exists carries with it the risk of periodic flooding of the southeast corner of the residential property west of the unnamed canal. That area and the balance of the residential acreage are subject to flooding without regard for the agricultural operation to the east. To deal with the difficulty related to the elevated water table, rainfall events and the flooding due to farm operation, some persons who reside in that residential tract have employed their own pump systems and ditches and retention areas to combat problems related to the geography of their property. In addition, the property is protected to some extent from outside influences by the existence of a dike and associated ditch, which limit some off-property incursion of water and assists to an extent in the transport of water away from their property. Moreover, the DuBois farm operation recently has placed a barrier at the end of the unnamed canal which directs water south along the Florida Power and Light road into L23W. In addition, the farm management has held down the pump speed during a rain event to protect the residential area. Nonetheless, at times the dike in the southeast corner adjacent to the residential property has breached in heavy rain events. As an alternative, the installation of S-9 would be only partially effective in alleviating the adverse conditions in the residential area west of the unnamed canal. It principally helps the DuBois farm operation. The relief afforded the residents would be the cessation of flooding caused by the operation of the farm pumps to the east as they breach the area in the southeast corner of the residential property, the future possibility of introducing as much as 25 CFS into the S-9 System subject to appropriate permits and the more tenuous possibility that the farm operation and the residential area could share the remaining 145 CPS capacity in the proposed system. The latter point isn't tenable from an examination of testimony at hearing. First, because the farmer wishes to conserve fertilizer and to maintain the moisture gradient and he does this by pumping off stormwater in a rainfall event, which events are most prevalent during his agricultural season. Secondly, the residential area is most in need of relief when the farmer is. Finally, the question of necessary permits to share capacity is unclear. Other alternatives related to a more comprehensive protection of the residential area by diking, a direct connection canal system to L23W from the unnamed canal, or dispersed sheet flow through the wetland area adjacent to the proposed S-9 Canal are not viable either for reason of design infirmity or impediments from other permitting agencies or inadequate property rights. Therefore, the viable choices are to either leave the property as it now stands or grant a permit to allow the construction of S-9. Between the remaining choices, no particular advantage is gained by the construction of this project. Dissolved oxygen problems in L23W, the receiving body of water, will not improve with the S-9 construction in a significant way and given the increased volume of discharge into L23W promoted by this construction are made worse. Nothing in the construction is so compelling to cause the exercise of the Respondent's discretion in favor of the grant of a variance related to dissolved oxygen values. 16..In examining the variance request by affording deference to Petitioner's regulatory responsibility, the need of the Lake Worth Drainage District to provide relief to those residents who are paying for drainage services is conceded. To that end, the proposed project does provide a certain amount of relief but it does not have as its primary emphasis purported assistance to those residents. As often stated, its principal benefit is to the DuBois farm operation. Left unresolved is the major source of suffering which is the lay of the land, a source which has prevailed from the beginning of the utilization of that property on the part of the residents. Plainly stated, much of the residential area was from the beginning and continues to be under water. The removal of the farm flooding and the future possibility of introducing a small increment of discharge into the S-9 system from the residential area subject to necessary permitting does not modify the characterization of this project as being one primarily for the farmer and to a much lesser extent for the residents. On this occasion, Petitioner's choice to fulfill its change is not persuasive enough to create special permission to violate the dissolved oxygen standard. In summary, a variance from the dissolved oxygen standard for Class III waters is not indicated. On the question of the permit application, in addition to failing to give reasonable assurances related to dissolved oxygen, the applicant has failed to satisfactorily address the problems with nutrients and coliforms. Other water quality standards have been satisfactorily addressed. Again, most of the water that will be introduced into the proposed system shall be stormwater; however, there will be other water components in the system constituted of surface water an groundwater, which also carry nutrients arid bacteriological deposits. Surface and groundwater are involved, given the level of elevations in the area, the depths of the unnamed canal, S-9 Canal and L23W and the fact that the DuBois farm operation can extract waters from the E-l Canal to the east of the farm properties as well as discharge water into that canal. It will not always be possible to distinguish whether the water in the proposed system is stormwater, groundwater or surface water. Consequently, South Florida Water Management's permitting related to stormwater is not definitive.

Florida Laws (4) 120.57403.021403.087403.201
# 2
HENRY C. ROSS vs CITY OF TARPON SPRINGS AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 10-010214 (2010)
Division of Administrative Hearings, Florida Filed:Tarpon Springs, Florida Nov. 12, 2010 Number: 10-010214 Latest Update: Jul. 15, 2011

The Issue Whether Petitioner Ross has standing to challenge the issuance of the WUP? Whether the District should approve the Application and enter a final order that issues the WUP?

Findings Of Fact The Parties Petitioner Ross Petitioner Ross is a resident of Pinellas County, (referred to by him at hearing as "the most urbanized county in the State of Florida"). Besides residing there, Petitioner Ross operates a farm on his property in the County. The City's experts reasonably projected and mapped a 0.5 foot drawdown contour surrounding the well field that is the subject of this proceeding. The contour defines "the cone of depression" associated with the well field. See Tr. 136. Mr. Ross' property is outside the cone of depression, to its south and west. The overall groundwater gradient in the area of the well field is from the east to the west. The water pumped from the well field does not pull water from the west because the pumping withdrawal will not reduce the potentiometric surface gradient enough to reverse the current gradient. Mr. Ross' property and the well on his property are "way outside," tr. 138, the well field and the 0.5 drawdown contour surrounding the well field. Based on the amount of drawdown reasonably projected by the well field, the effect on Mr. Ross' property could not be measured because it would be so slight. If the water in his well were to rise after the WUP is implemented, it would be impossible to tell whether the water rose "because the pump's turned off or because it rained the day before." Tr. 163. The District The District is the administrative agency charged with the responsibility to conserve, protect, manage, and control the water resources within its geographic boundaries. The District administers and enforces chapter 373, and the rules promulgated pursuant thereto. Among those rules are those that relate to the consumptive use of water found in chapter 40D-2. The City The City of Tarpon Springs is the applicant for the WUP that is the subject of this proceeding. The City's application seeks to modify an existing permit. The Existing Permit The City has an existing Water Use Permit (the "Existing Permit") from the District. Originally granted in 1976, it allows for withdrawal of fresh groundwater for public supply. The Existing Permit was last renewed in October of 2005 for a ten-year period. It expires in October of 2015. Under the Existing Permit, the withdrawal capacity is 1.38 million gallons per day annual average and allows for seven production wells. The Application and its Modification The City submitted the Application in July, 2008. The Application at that time was for 25 wells in a brackish water well field for a proposed brackish groundwater reverse osmosis plant that the City plans to build. The City's intent originally was to apply for a permit separate from the Existing Permit.1/ In September of 2009, however, the City requested that the Application be considered a modification of the Existing Permit. In honoring the request, the District changed the number assigned to the Application to "20000742.010."2/ The Application was also modified with regard to the number of production wells in the brackish well field. The number was reduced from 25 to 22, "due to land acquisition efforts indicating that the maximum number of wells . . . required for the project would be 22." Tr. 54. The Application contains an introduction that summarized the City's water supply system and its water supply plans, a completed Individual Water Use Permit Application form, a completed Public Supply Supplemental form, and an Impact Analysis Report (the "Report"). The Report states that the ground-water flow model "MODFLOW"3/ was used to perform the impact analysis. Assessment of average annual and peak month withdrawal impacts in the Upper Floridan and surficial aquifers used the SWFWMD District Wide Regulation Model Version 2 ("DWRM2"). One of the enhancements the DWRM2 offers over earlier model versions is "integrated focused telescopic mesh refinement (FTMR) which allows the model grid user to refine the model grid spacing to focus on specific areas within the District."4/ The Report included the FTMR model grid, total drawdown scenarios in the Upper Floridan Aquifer and the surficial aquifer, and a peak month drawdown scenario. The Application also included a summary of the regional hydro-geology, a summary of the City's wastewater system, a description of the City's potable water supply, an historical operating protocol and a proposed well field management plan for the City's new brackish water well field, a service area and well field location aerial, a table showing the general hydrostratigraphy in northern Pinellas County, a summary of seasonal fluctuations which addressed the conditions for issuance of a permit as set forth in rule 40D-2.381, a summary of the City's reclaimed water system, well location maps, wetland maps, Water Use Permit maps and schedules, the City's well field protection ordinance, maps pertaining to the proposed service areas, a water conservation letter, and water conservation information. The 22 new production wells in the brackish water well field will provide enough water once treated at the proposed reverse osmosis membrane treatment plant to enable the City to supply the anticipated potable water demand for all of the City's customers through the year 2015. Installation of the additional production wells will increase the annual average quantity of groundwater pumpage to 4,200,000 gallons per day ("gpd") and the peak month quantity to 6,300,000 gpd. Review of the Application by the District led to four requests by the District for additional information. The City responded to each. The responses included a well construction and aquifer testing program report, a Water Quality/Water Level Well Impact Mitigation Plan, a Water Quality Action Plan, a revised Water Quality/Water Level Well Impact Mitigation Plan, a revised Water Quality Action Plan and a second revision of the Water Quality Action Plan, a second Water Quality/Water Level Well Impact Mitigation Plan, a proposed Environmental Monitoring Plan, a third revised Water Quality Action Plan, a third revised Water Quality/Water Level Well Impact Mitigation plan, and the final Environmental Monitoring Plan. Draft Water Use Permit On October 8, 2010, the District gave notice of its intent to issue a permit that would modify the City's Existing Permit for public supply use. Attached to the notice is a Draft WUP. The modification includes the development of a brackish water well field with 22 additional production wells to allow the City to self-supply the anticipated potable water demand in 2015 for a customer base of approximately 34,259 persons. The annual average quantity authorized by the WUP is 4,200,000 gpd and the permitted peak month quantity increases to 6,300,000 gpd.5/ Special conditions of the Draft WUP require the City to maintain meters on existing and proposed withdrawal points; record and report monthly meter readings; confirm meter accuracy every five years; monitor and report the water quality and aquifer water levels; maintain an adjusted per capita rate of 150 gpd or less; conduct and report water audits; submit annual reports of residential water use, reclaimed water supplied, per capita water use rates, and well field operations; investigate withdrawal-related well complaints; conduct a well field inventory prior to the activation of the proposed production wells; comply with the environmental monitoring plan; set water quality concentration limits prior to the activation of the proposed production wells; and submit an Annual Water Quality Report and an annual Well Field Report. Criteria in Rule for Issuance of WUPs The District utilizes rule 40D-2.381 (the "Rule") in its review of water use permit applications. The Rule opens with the following: In order to obtain a Water Use Permit, an Applicant must demonstrate that the water use is reasonable and beneficial, is consistent with the public interest, and will not interfere with any existing legal use of water . . . Rule 40D-2.381(1), Tab 1 of the Binder Containing the Matters Officially Recognized, pp. 7-8. The Rule requires that the applicant make the required demonstrations through the provision of "reasonable assurances, on both an individual and a cumulative basis that the water use," id., will meet 14 conditions listed in subsections (a) through (n).6/ Condition (a) Condition (a) requires that the City demonstrate that the water use is necessary to fulfill a certain reasonable demand. To meet this condition, the City provided a population estimate through the end of the permit term and also provided a per capita rate that the City had used in the last five years. Calculations set forth in a table prepared at the request of the City show the population projections and projected water demands over a period from 2008 through 2030. These calculations provide reasonable assurances that the proposed water use meets Condition (a). Condition (b) Condition (b) requires that the City must demonstrate that the water use will not cause quantity or quality changes that adversely affect the water resources, including both surface water and groundwater. The City provided a groundwater model showing the anticipated groundwater drawdowns within the Upper Floridan and surficial aquifers. The City also completed a study on the wells within the sections of the actual proposed well field. Based upon the modeling, the drawdowns are not large enough to cause any impacts to quantity or quality of the water in the area. The City has a Water Quality/Water Level Well Impact Mitigation Plan, should there be any complaints of impact, to correct any problems after implementation of the WUP. The well field is designed with 22 supply wells. All 22 wells need not be operated at the same time to meet the water demand. Wells beyond those needed by demand have been designed into the well field so that there can be rotational capacity. Pumping at lower rates from among the 22 wells on a rotational basis is a management tool for protecting the resource and minimizing the effects of the withdrawals. The City's monitoring program provides for the collection of water levels from a large number of wells either on a monthly or quarterly basis to assess water level fluctuations in the Upper Floridan and surficial aquifers. The City also has numerous wells that will sample for chloride sulfates, total dissolved solids (TDS) and other water quality constituents on a monthly and quarterly basis to ensure that the conditions of issuance continue to be met. The City will submit groundwater pumping data on a monthly basis from all the production wells so that the District can determine that the City is indeed adhering to the quantities reflected in the WUP. Groundwater in the Upper Floridan Aquifer flows in a westward direction towards the Gulf of Mexico. The location of the proposed wells is in an urban land use area near the Gulf Coast. The wells will capture brackish groundwater that would otherwise flow westward into the Gulf. Brackish groundwater from the City's service area is the lowest quality water available for public supply in the area. The City plans to construct a reverse osmosis facility to utilize available brackish groundwater. The brackish groundwater pumped from the well field is an alternative supply source. Isolated from the regional system, it will be used for public supply in the service area. The high number of low-capacity wells will provide rotational ability for the City to manage the quantity and quality of the water resource in the area of the well field. Maximum drawdown within the well field area due to the average annual withdrawal is approximately 3 feet, with an additional 1.5 feet during peak month withdrawal. This amount of drawdown is not likely to impact other wells in the area. Condition (c) Condition (c) requires the City to demonstrate that water use will comply with the provisions of 4.2 of the WUP Basis of Review, incorporated by reference in rule 40D-2.091, regarding adverse impacts to wetlands, lakes, streams, estuaries, fish and wildlife or other natural resources. The Anclote River and associated wetlands are tidally influenced and will not be adversely impacted by the proposed withdrawal. Other wetlands in the well field area examined by a District biologist identified several isolated wetlands of concern. Isolated wetlands are generally more sensitive to withdrawal of groundwater than wetlands connected to larger basins. Initially, the City's proposed drawdowns were deemed to be unacceptable to the District because of the impact to the isolated wetlands of concern. As a first step, the City reduced the quantities of water to be withdrawn. Subsequently, an extensive Wetland Monitoring Plan was developed that included a mitigation plan if adverse impacts did occur to wetlands. Storm-water runoff will be the primary factor controlling the functions of the wetland areas. Mitigation measures, should any adverse impact become too great, include reduction of well field pumping, augmentation with well water, potable water and other feasible sources, and the purchase of mitigation credits. Condition (d) Condition (d) requires the City to demonstrate that the water use will not interfere with a reservation of water as set forth in rule 40D-2.302. The groundwater modeling that the City provided the District indicates that there are no adverse impacts to the minimum flows and levels ("MFLs") in the Anclote River or the water level at the Tarpon Road Deep Well. There are, therefore, no impacts to reservations of water. Condition (e) Condition (e) requires the City to demonstrate that the water use will comply with the provisions of 4.3 of the WUP Basis of Review,7/ regarding MFLs. The closest MFL site is the Upper Floridan Aquifer monitoring well called Tarpon Road Deep, located approximately 2.4 miles southeast of the well field. The impact analysis model results show that at the annual average withdrawal rate of 4.20 million gallons per day ("mgd") approximately 0.1 feet of drawdown at this MFL site is currently projected to occur, assuming static pumping conditions in all other regional groundwater withdrawals. This amount of drawdown will not cause the water level at the Tarpon Road Deep Well to fall below its minimum level. The District is in the process of setting an MFL for the Anclote River. Based on the operation of the new well field and the City's continued operation of their freshwater discharge to the Anclote River from their reclaimed water facility, there will be no impact to the Anclote River. Condition (f) Condition (f) requires the City to demonstrate that the water use will utilize the lowest water quality the City has the ability to use, provided that its use does not interfere with the recovery of a water body to its established MFL and it is not a source that is either currently or projected to be adversely impacted. The City is using brackish water, the lowest water quality available to be used for public supply. The City will be treating it at a reverse osmosis water treatment plant. Water of this quality is not available for others to use without special treatment. Based upon the modeling provided by the City, there are no anticipated impacts to MFLs or any other water body resources. Condition (g) Condition (g) requires the City to demonstrate that the water use will comply with section 4.5 of the WUP Basis of Review,8/ regarding saline intrusion. Groundwater in the Upper Floridan Aquifer in the area of the well field is brackish. The well field's design allowing well rotation minimizes changes in water quality during operation. The amount of drawdown and the fact that water levels will remain above sea level suggests that saline water intrusion will not occur. The reported potentiometric surface in the area of the well is approximately five feet NGVD while the land surface is roughly five feet higher at approximately ten feet NGVD. The City's monitoring and mitigation programs will address adverse impacts from saline intrusion should they occur. Condition (h) Condition (h) requires the City to demonstrate that the water use will not cause the pollution of the aquifer. Soil and groundwater contamination is documented at the Stauffer Management Company site located approximately 3,000 feet west of the well field. The drawdown from the well field is calculated to be about one foot at the Stauffer site. That level of drawdown will not induce migration of contaminants because the upward head differential from the Upper Floridan Aquifer to the surficial aquifer will be altered and the Stauffer site is down gradient of the well field. Testimony from Mr. Wiley established that the aquifers should not be contaminated by the City's withdrawals despite the presence of the Stauffer site: [T]here is a known source of contamination approximately 3,000 feet from the new well field to the west, Stauffer Chemical Company. With the small amount of drawdown that's caused in the Upper Floridan aquifer and the surficial aquifer, there's no potential for the withdrawals to cause pollution of the aquifer. Tr. 254-55. Mr. Wiley's opinion was reached primarily based on the use of the groundwater flow model to determine the drawdown at the Stauffer site and through review of groundwater levels in the Floridan and the surficial aquifers. The United States Environmental Protection Agency (the "EPA") is in charge of managing the contamination at the Stauffer site. A remediation plan has been developed based, in part, on EPA records. The remediation plan includes the construction of a barrier wall in the subsurface around the contaminated area to prevent contaminated groundwater from migrating. The City's groundwater monitoring wells will detect movement of contaminants toward the well field. The monitoring of the wells and the mitigation plan will assist in preventing pollution of the aquifers. Condition (i) Condition (i) requires the City to demonstrate that the water use will not adversely affect offsite land uses existing at the time of the application. Primary existing land uses within the City's service area are residential, commercial, and light industrial. The proposed withdrawal will not adversely impact these land uses as shown in Figure 10 of the City Exhibit 1. Five sink holes are known to exist in the general area around the well field. The closest is approximately 1,000 feet from a proposed well location. Maximum drawdown at the distance is approximately 2 feet. This amount of drawdown does not significantly increase the potential for sinkhole activity. Condition (j) Condition (j) requires that the City demonstrate the water use will not adversely impact an existing legal withdrawal. The Pasco County Utilities' wells located to the north of the well field are listed on the WUP as plugged. Wells owned by Crest Ridge Utility Corp. are located within 0.5 to 0.8 miles of the well field. Drawdown at these wells, due to the average annual withdrawal, is approximately one foot, with an additional 0.4 feet during peak month withdrawal. This amount of drawdown will not create a water level impact at these wells. Maximum drawdown at domestic wells in the area due to the average annual withdrawal is approximately three feet, with an additional 1.5 feet during peak month withdrawal. This amount of drawdown is not likely to impact other wells in the area. The City's mitigation plan addresses any adverse impact that might occur from the City's withdrawal. Condition (k) Condition (k) requires the City to demonstrate that the water use will incorporate water conservation measures. The existing per capita use rate for the City's service area is 110 gpd. Its position well below the district goal of 150 gpd per person demonstrates that the City's water conservation measures are effective. The City uses an inclined block rate structure which encourages water conservation. It also encourages water conservation through a reclaimed water system that encourages conservation of public water supply. It currently uses a little over one million gallons per day of reclaimed water. The City also conserves water through a leak protection program, a water loss audit program, adherence to the District's watering restrictions and provision of a low-flow toilet rebate program through the County, a landscape code, and the provision of educational materials to users. Condition (l) Condition (l) requires the City to demonstrate that the water use will incorporate the use of alternative water supplies to the greatest extent possible. The City has an extensive reclaimed water program. It provides reclaimed water for its golf course, for residential irrigation, for public parks and recreation, and for public schools. The City expanded its reclaimed water storage system recently by doubling the amount of reclaimed water that it is able to store for redistribution. Condition (m) Condition (m) requires the City to demonstrate that the water use will not cause water to go to waste. The City performs an unaccounted-for water audit of its system as required by a special condition of its existing WUP. The unaccounted-for water use is approximately 4 percent, well below the District guidelines. Furthermore, the City's per capita use rate of 110 gpd is well within the District's goal of 150 gpd per person. The City also has an extensive reclaimed water system which offsets potable water supply and prohibits wasted drinking water as an irrigation source. Condition (n) Condition (n) requires that the City demonstrate that the water use will not otherwise be harmful to the water resources within the District. Facts found above support a conclusion that the City has provided reasonable assurances that it meets this condition. In addition, the water that is pumped locally by the City will offset the need for ground water that would have otherwise been obtained from elsewhere in the region. Notices The District published its Notice of Proposed Agency Action in the Tampa Tribune on October 22, 2010. The District published its Notice of Proposed Agency Action in the St. Petersburg Times on October 24, 2010.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Southwest Florida Water Management District enter a Final Order determining that Petitioner Ross lacks standing and that his Petition, therefore, be dismissed. Should it be determined in a Final Order that Petitioner Ross has standing, it is recommended that the Southwest Florida Water Management District enter a Final Order that issues Water Use Permit No. 20000742.010 to the City of Tarpon Springs. DONE AND ENTERED this 14th day of April, 2011, in Tallahassee, Leon County, Florida. S DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of April, 2011.

Florida Laws (5) 120.52120.569120.57373.019403.412
# 3
FLORIDA INSTITUTE FOR SALTWATER HERITAGE, INC. vs LAND TRUST NO. 97-12 AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 14-005135 (2014)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Oct. 30, 2014 Number: 14-005135 Latest Update: Apr. 10, 2017

The Issue The issue to be determined is whether Respondent Land Trust #97-12 (“Land Trust”) is entitled to an Environmental Resource Permit (“ERP”) for its proposed project on Perico Island in Bradenton, Florida.

Findings Of Fact The Parties Petitioner Joseph McClash is a resident of Bradenton, Florida, who uses the waters in the vicinity of the project for fishing, crabbing, boating, and wildlife observation. Petitioner Manasota-88, Inc., is an active Florida nonprofit corporation for more than 20 years. Manasota-88 has approximately 530 members, most of whom (approximately 300) reside in Manatee County. The mission and goal of Manasota-88 includes the protection of the natural resources of Manatee County, including Anna Maria Sound and Perico Island. Petitioner FISH is an active Florida nonprofit corporation in existence since 1991. FISH owns real property in unincorporated Cortez in Manatee County and maintains a Manatee County mailing address. FISH has more than 190 members and more than 150 of them own property or reside in Manatee County. The mission and goal of FISH includes protection of the natural resources of Manatee County, including Anna Maria Sound and Perico Island. Intervenor Suncoast Waterkeeper, Inc., is an active Florida nonprofit corporation in existence since 2012. The mission of Suncoast Waterkeeper is “to protect and restore the Suncoast’s waterways through enforcement, fieldwork, advocacy, and environmental education for the benefit of the communities that rely upon coastal resources.” Suncoast Waterkeeper provided the names and addresses of 25 members residing in Manatee County. A substantial number of the members of Suncoast Waterkeeper use the area and waters near the proposed activity for nature-based activities, including nature observation, fishing, kayaking, wading, and boating along the natural shorelines of Anna Maria Sound and Perico Island. Intervenor Sierra Club, Inc., is a national organization that is a California corporation registered as a foreign nonprofit corporation in Florida. Sierra Club has been permitted to conduct business in Florida since 1982. The mission of Sierra Club includes protection of the natural resources of Manatee County, which include Anna Maria Sound and Perico Island. Sierra Club provided the names and addresses of 26 members who live in Manatee County. A substantial number of the members of Sierra Club use the area and waters near the proposed project for nature-based activities, including observing native flora and fauna, fishing, kayaking, wading, and boating along the natural shorelines of Anna Maria Sound and Perico Island. Respondent Land Trust is the applicant for the challenged ERP and owns the property on which the proposed project would be constructed. Respondent District is an independent special district of the State of Florida created, granted powers, and assigned duties under chapter 373, Florida Statutes, including the regulation of activities in surface waters. The proposed project is within the boundaries of the District. The Project Site The project site is 3.46 acres of a 40.36-acre parcel owned by Land Trust. The parcel includes uplands, wetlands, and submerged lands, on or seaward of Perico Island, next to Anna Maria Sound, which is part of Lower Tampa Bay. Anna Maria Sound is an Outstanding Florida Water. The project site is adjacent to a large multi-family residential development called Harbour Isles, which is currently under construction. Access to the Land Trust property is gained through this development. The Land Trust parcel contains approximately seven acres of high quality mangroves along the shoreline of Anna Maria Sound. They are mostly black and red mangroves, with some white mangroves. The mangroves on the project site amount to a total of 1.9 acres. Mangroves have high biological productivity and are important to estuarine food webs. Mangroves provide nesting, roosting, foraging, and nursery functions for many species of wildlife. Mangroves also provide a buffer from storm surge and help to stabilize shorelines. Wildlife species found on the project site include ibises, pelicans, egrets, spoonbills, mangrove cuckoos, bay scallops, fiddler crabs, mangrove tree crabs, horseshoe crabs, marsh rabbits, raccoons, mangrove bees, and a variety of fish. No endangered species have been observed on the project site, but mangroves are used by a number of listed species. The Proposed Project The proposed project is to construct a retaining wall, place fill behind the wall to create buildable lots for four single-family homes, construct an access driveway, and install a stormwater management facility. The stormwater management facility is a “Stormtech” system, which is an underground system usually used in situations where there is insufficient area to accommodate a stormwater pond. Riprap would be placed on the waterward side of the retaining wall. The retaining wall would be more than 35 feet landward of the mean high water line in most areas. Petitioners contend the proposed retaining wall is a vertical seawall, which is not allowed in an estuary pursuant to section 373.414(5). “Vertical seawall” is defined in section 2.0(a)(111), Volume I, of the Environmental Resource Permit Applicant’s Handbook (“Applicants Handbook”) as a seawall which is steeper than 75 degrees to the horizontal. It further states, “A seawall with sloping riprap covering the waterward face to the mean high water line shall not be considered a vertical seawall.” The retaining wall is vertical, but it would have riprap covering its waterward face and installed at a slope of 70 degrees. The retaining wall is not a vertical seawall under the District’s definition. Stormwater Management Stormwater in excess of the Stormtech system’s design capacity would discharge into Anna Maria Sound. Because Anna Maria Sound is an Outstanding Florida Water, District design criteria require that an additional 50 percent of treatment volume be provided. The Stormtech system meets the District’s design criteria for managing water quality and water quantity. Projects which meet the District’s design criteria are presumed to provide reasonable assurance of compliance with state water quality standards. Petitioners’ evidence was not sufficient to rebut this presumption. Petitioners contend the District waiver of water quality certification for the proposed project means that Land Trust was not required to meet water quality standards. However, that was a misunderstanding of the certification process. All state water quality criteria are applicable. Petitioners contend water quality monitoring should be imposed for this project. However, section 4.7 of the Applicant’s Handbook, Volume II, provides that if the applicant meets the District’s design criteria, water quality monitoring is not required. Petitioners failed to prove the proposed stormwater management system cannot be constructed, operated, or maintained in compliance with applicable criteria. Wetland Impacts In order to create buildable lots, 1.05 acres of the 1.9 acres of mangroves on the project site would be removed and replaced with fill. A swath of mangroves approximately 40 feet wide would remain waterward of the retaining wall. The proposed direct and secondary impacts to the functions provided by wetlands were evaluated using the Uniform Mitigation Assessment Method (“UMAM”) as required by Florida Administrative Code Chapter 62-345. UMAM is used to quantify the loss of functions performed by wetlands considering: current condition, hydrologic connection, uniqueness, location, fish and wildlife utilization, time lag, and mitigation risk. The District determined the filling of 1.05 acres of wetlands would result in a functional loss of 0.81 units and the secondary impacts resulting from installation of the retaining wall would result in a loss of 0.09 units for a total functional loss of 0.9 units. Petitioners contend the functional loss would be greater. Petitioners contend the wetland delineation performed by Land Trust and confirmed by the District did not extend as far landward as the hydric soils and, therefore, the total acreage of affected wetlands would be greater. However, Petitioners did not produce a wetland delineation for the project site, and their evidence was not sufficient to rebut Land Trust's prima facie evidence on this issue. Petitioners’ experts believe the secondary impacts caused by the proposed project would be greater than calculated, including fragmentation of the shoreline mangrove system, damage to the roots of mangroves near the retaining wall, and scouring effects caused by wave action associated with the retaining wall. Respondents assert that the analysis by Petitioners’ expert Jacqueline Cook relied on federal methodology and that “the science used in her analysis is not contained in the state or district rule criteria.” Reliance on science is always appropriate. However, Ms. Cook’s use of a federal impact assessment methodology creates doubt about whether her scoring is consistent with UMAM. Despite the unreliability of Ms. Cook’s UMAM score, it is found that Respondents’ UMAM score under-calculated secondary impacts due to scour and other effects of changed water movement that would be caused by the retaining wall. It was not explained how the loss of storm buffering and erosion prevention functions of wetlands are accounted for in the UMAM score. Elimination or Reduction of Impacts Section 10.2.1 of the Applicant’s Handbook, Volume I, states that in reviewing a project the District is to consider practicable design modifications to eliminate or reduce impacts to wetland functions. Section 10.2.1.1 explains: The term “modification” shall not be construed as including the alternative of not implementing the activity in some form, nor shall it be construed as requiring a project that is significantly different in type or function. A proposed modification that is not technically capable of being completed, is not economically viable, or that adversely affects public safety through the endangerment of lives or property is not considered “practicable.” A proposed modification need not remove all economic value of the property in order to be considered not “practicable.” Conversely, a modification need not provide the highest and best use of the property to be “practicable.” In determining whether a proposed modification is practicable, consideration shall also be given to cost of the modification compared to the environmental benefit it achieves. Land Trust originally proposed constructing a surface water retention pond. The Stormtech stormwater management system would cause less wetland impact than a retention pond. Land Trust contends the use of a retaining wall reduces wetland impacts because, otherwise, more mangroves would have to be removed to account for the slope of the waterward side of the fill area. However, this proposition assumes the appropriateness of the size of the fill area. Land Trust also contends wetland impacts are reduced by using the adjacent development to access the proposed project site, rather than creating a new road. However, the evidence did not establish that Land Trust had a practicable and preferred alternative for access. Unlike the Stormtech system, the retaining wall and access driveway were not shown to be project modifications. The proposed project would cause fewer impacts to wetlands if the fill area was reduced in size, which was not shown to be impracticable. Reducing the size of the fill area would not cause the project to be significantly different in type or function. Land Trust did not demonstrate that it implemented reasonable design modifications to eliminate or reduce impacts to wetland functions. Mitigation Land Trust proposes to purchase credits from the Tampa Bay Mitigation Bank, which is 17 miles north of the proposed project site. The Tampa Bay Mitigation Bank is in the Tampa Bay Drainage Basin. The project site is in the South Coastal Drainage Basin. Pursuant to section 10.2.8 of the Applicant’s Handbook, Volume I, if an applicant mitigates adverse impacts within the same drainage basin, the agency will consider the regulated activity to have no unacceptable cumulative impacts upon wetlands and other surface waters. However, if the applicant proposes to mitigate impacts in another drainage basin, factors such as “connectivity of waters, hydrology, habitat range of affected species, and water quality” will be considered to determine whether the impacts are fully offset. The parties disputed whether there was connectivity between the waters near the project site and the waters at the Tampa Bay Mitigation Bank. The more persuasive evidence shows there is connectivity. There was also a dispute about the habitat range of affected species. The evidence establishes that the species found in the mangroves at the project site are also found at the mitigation bank. However, local fish and wildlife, and local biological productivity would be diminished by the proposed project. This diminution affects Petitioners’ substantial interests. The loss or reduction of storm buffering and erosion prevention functions performed by the mangroves at Perico Island cannot be mitigated for at the Tampa Bay Mitigation Bank. Cumulative impacts are unacceptable when the proposed activity, considered in conjunction with past, present, and future activities would result in a violation of state water quality standards, or significant adverse impacts to functions of wetlands or other surface waters. See § 10.2.8.1, Applicant’s Handbook, Vol. I. Section 10.2.8(b) provides that, in considering the cumulative impacts associated with a project, the District is to consider other activities which reasonably may be expected to be located within wetlands or other surface waters in the same drainage basin, based upon the local government’s comprehensive plan. Land Trust did not make a prima facie showing on this point. Land Trust could propose a similar project on another part of its property on Perico Island. Anyone owning property in the area which is designated for residential use under the City of Bradenton’s comprehensive plan and bounded by wetlands could apply to enlarge the buildable portion of the property by removing the wetlands and filling behind a retaining wall. When considering future wetland impacts in the basin which are likely to result from similar future activities, the cumulative impacts of the proposed project would result in significant adverse impacts to wetland functions in the area. Public Interest For projects located in, on, or over wetlands or other surface waters, an applicant must provide reasonable assurance that the project will not be contrary to the public interest, or if such activities significantly degrade or are within an Outstanding Florida Water, are clearly in the public interest, as determined by balancing the criteria set forth in rule 62- 330.302(1)(a), and as set forth in sections 10.2.3 through of the Applicant’s Handbook. Rule 62-330.302, which is identical to section 373.414, Florida Statutes, lists the following seven public interest balancing factors to be considered: Whether the activities will adversely affect the public health, safety, or welfare or the property of others; Whether the activities will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activities will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activities will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activities will be of a temporary or permanent nature; Whether the activities will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S.; and The current condition and relative value of functions being performed by areas affected by the proposed regulated activity. The Parties stipulated that the proposed project would not have an adverse impact on public health, navigation, historical resources, archeological resources, or social costs. Land Trust proposes to give $5,000 to the City of Palmetto for an informational kiosk at the City of Palmetto’s public boat ramp. A District employee testified that this contribution made the project clearly in the public interest. Reasonable assurances were not provided that the proposed project is clearly in the public interest because of the adverse cumulative effects on the conservation of fish and wildlife, fishing and recreational values, and marine productivity of Anna Maria Sound, an Outstanding Florida Water.

Recommendation Based on the Findings of Fact and Conclusions of Law set forth above, it is RECOMMENDED that the Southwest Florida Water Management District issue a final order that denies the Environmental Resource Permit. DONE AND ENTERED this 25th day of June, 2015, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 2015. COPIES FURNISHED: Christian Thomas Van Hise, Esquire Abel Band, Chartered Post Office Box 49948 Sarasota, Florida 34230-6948 (eServed) Martha A. Moore, Esquire Southwest Florida Water Management District 7601 Highway 301 North Tampa, Florida 33637 (eServed) Douglas P. Manson, Esquire MansonBolves, P.A. 1101 West Swann Avenue Tampa, Florida 33606 (eServed) Joseph McClash 711 89th Street Northwest Bradenton, Florida 34209 (eServed) Ralf G. Brookes, Esquire Ralf Brookes Attorney 1217 East Cape Coral Parkway, Suite 107 Cape Coral, Florida 33904 (eServed) Justin Bloom, Esquire Post Office Box 1028 Sarasota, Florida 34230 (eServed) Robert Beltram, P.E., Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899

Florida Laws (7) 120.52120.569120.57120.68267.061373.414403.412
# 4
BRUCE LAHEY vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 03-000333 (2003)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Jan. 29, 2003 Number: 03-000333 Latest Update: May 07, 2003

The Issue The issue is whether the Southwest Florida Water Management District's (District's) proposed construction of a temporary floating weed barrier across the mouth of the canal exiting to the southwest side of Lake Hancock in Polk County, Florida, is exempt from regulatory review under Section 373.406(6), Florida Statutes.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background This proceeding involves a request by the District for authorization to construct a temporary floating weed barrier across the mouth of the canal exiting the southwest side of the Lake in Polk County, Florida (County). After reviewing the request, and based on its determination that the project would "have only minimal or insignificant individual or cumulative adverse impacts on the water resources of the State," on September 27, 2002, the Department concluded that the project qualified for an exemption from regulatory review under Section 373.406(6), Florida Statutes. The Department also authorized the District to use state-owned submerged lands, if applicable, for the construction of the project, and it found that the project was in compliance with the SPGP program and thus required no further permitting from the United States Army Corps of Engineers (Corps of Engineers). Even if the Department had not considered the project to be exempt, it concluded that it had sufficient information and assurances from the District to grant a Noticed General Environmental Resource Permit (ERP) authorizing the requested activity. On December 2, 2002, Petitioner, Bruce Lahey, who has resided and owned property on the southwest side of the Lake for 15 years and regularly uses the Lake for fishing and recreational purposes, filed a Petition for Administrative Hearing (Petition) challenging the proposed agency action. In his Petition, as later clarified and narrowed in the parties' Joint Pre-Hearing Stipulation, Mr. Lahey contends that a weed barrier is no longer necessary since there has not been a weed problem in the Lake since late 2002; that the placement of a weed barrier will make access to and from the Lake more difficult and create a safety hazard; and that in the event a problem arises again, the more desirable options for removing the weeds are "a 'cookie-cutter,' mechanical harvester, or the spraying of [the] tussocks," rather than erecting a barrier. Finally, Mr. Lahey contends that as a matter of law, Section 369.20, Florida Statutes, bars the construction of a barrier. He has not challenged the Department's authorization for the District to use state-owned submerged lands or its determination that the project complies with the SPGP program, and therefore those aspects of the proposed agency action are not in issue. Respondents do not dispute that Mr. Lahey has standing to bring this action. The Lake and Control Structure The Lake is an approximately 4,500-acre Class III waterbody located east of Highway 98 and Highland City, southeast of Lakeland, and just northeast of the City of Bartow (Bartow). It receives drainage from a significant portion of the County, including three streams and runoff from a surrounding 131-square mile watershed. Waters discharge from the Lake to Saddle Creek (the canal), which exits at the southwest end of the Lake and runs in a southerly direction for around a mile and a half until it merges with the Peace Creek, where the two then become the Peace River. At the confluence of the canal and Peace Creek, the waters flow through a broad, flat floodplain. Water moves slowly through this area, which can affect the ability of the Lake to discharge, especially during flood conditions. Like the Lake and canal, the Peace Creek also has a significant contributing basin. The canal contains a District-owned and operated water control structure known as Water Control Structure P-11 (the control structure) consisting of two twenty-foot radial arm gates that are raised when necessary to manage the water levels on the Lake and prevent the flooding of lakefront property. The control structure is approximately 3,000 feet or so south of the Lake and is the only control structure regulating water levels for the Lake. The gates are designed to discharge at a flow level of 1,100 cubic feet per second (cfs). The invert elevation of the control structure is 91.7 feet and the crest elevation is 98.7 feet. Flows from the Lake will exceed 1,100 cfs when the water levels are higher than the crest elevation of the structure. At this point, water flows over the structure’s weirs and flood control is no longer provided. The maximum desirable water elevation level for the Lake is 98.5 feet above mean sea level (msl). Typically, the District begins to operate, or open, the control structure when the Lake's water elevation reaches 98.25 feet msl. A water level of 99.0 feet msl is considered minimum flood level (or high guidance level). The low management water elevation (low guidance level) is 96.0 feet msl. These established water levels have been maintained at the Lake since approximately 1981. The District seeks to hold the water level of the Lake close to the maximum desirable level, and typically tries to hold the water level at 98.25 feet msl, which is slightly below the maximum desirable level of 98.5 feet msl, to allow storage of water and some response time. The control structure is intended primarily to be a water conservation structure that regulates the Lake's water levels to benefit the water resources, to include the Lake and the Peace River. In managing the Lake's levels, the District balances conservation of the water resource and public safety/flooding concerns. The Lake's water level elevations are monitored through the District’s Supervisory Control and Data Acquisition System (SCADA), which measures the water level and transmits hourly data to the District offices via satellite. SCADA monitors are located immediately upstream and downstream of the control structure. Since the tussock blockage events in the summer and fall of 2002, described more fully below, the District has installed an additional SCADA monitor on the north end of the Lake so that water levels in the Lake and canal can be compared. The Lake does not have direct public access or a public boat ramp and is not easily accessible. In addition, in the canal, there is only one unimproved location upstream from the control structure where boats can be placed in the water and gain access to the Lake. That portion of the canal which lies between the Lake and the control structure has not always been open to boat access. In the 1980’s, a floating weed barrier extended across the canal approximately 1,000 feet upstream from the current control structure, which blocked the canal and boat access. This floating weed barrier was installed primarily to address problems with water hyacinths that would float down the canal and interfere with the control structure. This floating barrier gave way sometime in the 1990’s. An earlier control structure also used to exist in this area, which blocked canal access. Navigation of the canal is limited due to the existence of the control structure and a number of other blockages further downstream, including a low bridge where old Highway 17 crosses the canal. Thus, boats coming from the Lake cannot navigate down the canal any further than the control structure, or slightly more than one-half mile, without taking the boat out of the water. Between 1999 and 2001, the District experienced one of the most severe droughts on record. During this time, the Lake went dry except for some isolated pools of water. Because of these conditions, a significant amount of wetland or aquatic vegetation began to grow on the exposed bottom of the Lake. The Lake historically did not support much plant growth, due to its eutrophic condition, poor water quality, and gelatinous mucky lake bottom. The types of vegetation currently existing in the Lake include cattails, pickerelweed, duck potato, and primrose willow. Following the return of summer rains and El Nino conditions in 2002, the Lake rebounded to within normal water levels. Because of the return of water in the Lake, the buoyant pressure of the water combined with the flaccid nature of the mucky lake bottom caused significant portions of vegetation to become uprooted, which formed an extensive amount of tussocks. Tussocks are floating mats of uprooted aquatic vegetation. They contain plant and organic material accumulated around the plant roots, can range from a few feet across to one hundred feet across or larger, and can reach a height of more than four feet. Once tussocks form, they move about the Lake by wind and water currents. The amount of vegetation currently existing in the Lake exceeds historic levels. At the present time, the District estimates that approximately 2,000 acres of the Lake are covered with tussocks, and that due to the flaccid nature of the lake bottom, the tussocks are susceptible to becoming uprooted through fluctuating water levels, wind, and wave action. Therefore, there is a strong potential that much of the currently rooted vegetation will form tussocks. Tussocks first impacted the District’s ability to operate the control structure in July 2002. During this event, the canal became partially filled with tussocks. Because the blockage occurred during the rainy and hurricane seasons, the District undertook efforts to clear the canal of tussocks. District staff used mechanical equipment commonly called a cookie cutter to break up the tussocks and flush them downstream through the control structure. During this tussock event, the Lake's water levels rose briefly above the maximum desirable level of 98.5 feet msl and then fell back to within normal elevations. In late August 2002, approximately three weeks after the first tussock blockage event, a number of homeowners on the Lake, including Petitioner's wife, contacted District staff to advise that the water level of the Lake was rising and flooding their yards. A rise in water levels did not register on the District’s water level monitoring SCADA system. Visual observation of the Lake did reveal, however, that there was a significant difference between the water levels being experienced on the Lake and the water levels reported at the control structure via the SCADA system. During this tussock event, masses of tussocks had completely filled the 3,000-foot length of the canal all the way to the control structure and were jamming against the control structure gates. Tussocks had also formed a vegetation dam approximately 900 to 1,400 feet north of the control structure where they compacted and became lodged on the bottom of the canal, significantly impeding the flow of water. During this event, flows out of the Lake were significantly diminished to a fraction of what they should have been. The tussock dam caused the Lake's level to rise above the minimum flood elevation of 99.0 feet and flood Petitioner's yard. There was an approximately one to one and one-half foot difference in the water levels in the Lake and in the canal. In response to this disparity, the District installed a third water level elevation monitor at the northern end of the Lake, so that it can monitor any differences in water elevations between the Lake and the canal and be alerted in the event that a blockage occurs in the canal. To eliminate the tussock blockage and restore flow through the control structure, the District had to employ mechanical means to break up and remove the tussocks. At the control structure, a trac-hoe was initially used in an attempt to force tussocks through the control structure, as tussocks would not flow through the structure unassisted. A cookie cutter was also employed, but it became sucked into the control structure and was damaged and had to be removed with a crane and repaired. The cookie cutter proved ineffectual in addressing the tussock blockage problem. If the canal were to again become clogged with tussocks, any resulting blockage of flow from the Lake would cause water levels to rise, which would endanger public safety and welfare. Prior to the tussock blockages experienced in the summer and fall of 2002, problems with tussocks had never been experienced at the Lake. The magnitude of the tussock formation on the Lake is unique and has not been experienced elsewhere in the District. In 2002, the Department expended over $46,000.00 in contracting for mechanical equipment and for spraying herbicide on tussocks to respond to the tussock buildup on the Lake. Since their formation after the summer of 2002, tussocks have blocked Petitioner's access to his dock on several occasions, thereby preventing him from being able to take his boat out into the Lake or to return to the dock once out on the Lake. The potential for similar blockages to occur remains, regardless of whether a floating weed barrier is erected as proposed. The direction of the winds is a major factor in determining where and how many tussocks will stack up in front of anyone’s property along the Lake. Access to the canal could become blocked with tussocks at any time, depending upon how the wind blows. Breaking up tussock blockages and flushing tussocks through the control structure does not eliminate water resource problems for the District. Tussocks that are pushed through the control structure cause downstream problems requiring the District to expend resources to push the tussocks through and under low downstream bridges crossing the canal, as well as break up tussock blockages that form in downstream waters. In January 2003, tussocks again accumulated at the control structure in such volume as to require assistance in flushing through the control structure. As a result of the large volume of tussocks pushed through the control structure, a tussock blockage occurred at a downstream bridge crossing, for which the District had to use mechanical equipment to restore flow. During March 2003, tussocks flushed through the control structure created a jam downstream on the Peace River. The tussocks were jammed up in a bend in the river and were blocking navigational access to the river. An El Nino weather cycle is currently being experienced. Water levels, including the Lake's water level, are already at their maximum and the ground is saturated. Localized flooding events have occurred. A very active summer rainy season is anticipated, which will mean significant flood control operations for the District. As the summer season approaches, the District must keep the control structure open and operational, which requires that the canal be kept open and flowing. A floating weed barrier at the entrance to the canal would keep tussocks from clogging the canal and prevent problems affecting operation of the control structure, downstream tussock blockages, and possible flooding. The Project To address the problem of tussocks entering the canal and causing blockages or possible flooding, on September 11, 2002, the District applied to the Department for a Noticed General ERP under Rule 62-341.475(1)(a), Florida Administrative Code, to authorize the construction of a floating weed barrier at the entrance to the canal. On September 27, 2002, the Department issued its notice of intent to authorize the requested activity. The proposed barrier will be constructed in two sections arranged at approximately 90-degree angles to each other, with a twenty-foot opening between the sections to allow boat access to the canal. A schematic drawing of the barriers is found in District Exhibit 5 received in evidence. As originally proposed, the barrier would consist of a total of sixteen nine-inch diameter pilings driven twenty-one feet apart, with twenty-foot sections of floating foam-filled polyvinyl chloride pipe (pvc) connected to the pilings. Pilings will be marked with reflective tape and five of the pilings will have three-foot diamond-shaped reflective danger signs reading "DANGER PILE/FLOAT BARRIER" placed on their upstream and downstream sides. The pilings are twenty-five feet in length and will extend above the Lake's water level approximately twelve to fourteen feet. Since the District's submittal of the application and the Department's authorization notice, the District has located commercially manufactured floating booms, called "Tuffbooms," that, if authorized, will be installed in lieu of the foam-filled pvc pipes. Use of these booms reduces the number of pilings needed from sixteen to eight, and their bright orange color is more visible than pvc piping. All other aspects of the proposed activity remain the same. The change in material to be used in the construction of the proposed floating barrier does not present any water quality issues, nor does it affect the Department's determination that the proposed activity will have minimal or insignificant adverse impacts on the water resources. The staggered layout of the proposed floating weed barrier is intended to keep tussocks in the Lake, where they can remain subject to the winds, while providing boat access to the canal in such a manner that is more difficult for tussocks to enter the canal. The Department's Exemption Process The Department's Tampa District Office routinely approves around 800 projects each year under various exemptions authorized by statute or rule. One type of exemption is found in Section 373.406(6), Florida Statutes, referred to as the de minimus exemption, which allows the Department to exempt from regulation those activities that are determined will have only minimal or insignificant individual or cumulative adverse impacts on the water resources of the District. The Department is authorized to make this determination on a case-by-case basis. In determining whether an activity qualifies for a de minimus exemption from permitting, the Department looks for parallels to other specific statutory or rule exemptions and analyzes the proposed activity similarly in terms of its scope, construction methods, potential to create water quality impacts or impediments to navigation, and other factors, because these recognized exemptions are also deemed to have minimal or insignificant impacts to the water resources. There is no specific exemption for a floating weed barrier as proposed by the District, but the Department considers this type of project to be similar in scope and potential impacts to other specific activities that have been determined to have minimal or insignificant adverse impacts to the water resources, such as docks and other piling-supported structures, navigational aids, and buoy systems. In assessing whether a project is appropriate for the de minimus exemption, the Department also looks to the criteria for Noticed General ERPs for guidance in determining whether a proposed project will have minimal or insignificant adverse individual or cumulative impacts upon the water resources. Under Section 373.406(5), Florida Statutes, the Department may by rule establish general permits for activities that have, either singularly or cumulatively, minimal environmental impact. Chapter 62-341, Florida Administrative Code, sets forth the Noticed General ERPs established by the Department. Department Rule 62-341.475(1)(a), Florida Administrative Code (as does District Rule 40D-400.475(1)(a), Florida Administrative Code), allows noticed general permits for piling supported structures of less than 1,000 square feet over wetlands or other surface waters, which are not designated Outstanding Florida Waters. To qualify for a noticed general permit for such activity, an applicant must provide reasonable assurance that the proposed structure: Does not significantly impede navigation and does not entail the construction of a structure for the launching or mooring of a boat when navigational access to the structure does not currently exist; Does not cause a violation of state water quality standards; Does not impede the conveyance of a stream, river or other watercourse in a manner that would increase off-site flooding; Does not adversely impact aquatic or wetland dependent listed species; Does not cause the drainage of wetlands; and Is not located in, on or over a coral community, macro-marine algae or submerged grassbed community. Will the Project Impact Water Resources? The District’s proposed floating weed barrier will involve less than 7.1 square feet of impact to the water resources, which is significantly less impact in square footage to the water resources than is allowed by Rule 62- 341.475(1)(a), Florida Administrative Code, or occurs with other specified exempt projects. Best management practices will be used in the erection of the pilings and in the construction of the barriers. Pilings will be jetted into the lake bottom without need for any dredging or lake bottom removal. Installation of a floating weed barrier will not result in any significant detriment to existing conditions in the Lake or the canal. Installation of the proposed floating weed barrier will benefit the public interest and the water resources by allowing unimpeded operation of the control structure without risk of tussocks causing blockages and flooding. Installation of the proposed floating weed barrier will not have significant adverse impacts on fishing, boating, or recreational use of the Lake or canal. A blockage of the canal entrance by tussocks, or a tussock jam anywhere on the Lake, could occur under present conditions, and similar blockages have already occurred. The potential for tussocks to block the opening between the sections of the floating weed barrier is considered remote and of temporary duration, due to the potential for shifting winds. The District’s proposed floating weed barrier is a reasonable means of addressing the continuing potential for tussocks to interfere with operation of the control structure. Use of mechanical equipment such as a cookie cutter or harvester would not be an effective or economical means of addressing tussock blockages in the canal or preventing their occurrence and possible interference with operation of the control structure. Pushing tussocks through the control structure would not be an effective means of addressing the potential for tussocks to cause blockages and possible flooding. Merely pushing the material through the control structure moves the potential blockage problem downstream and does not alleviate the potential for tussocks to cause adverse impacts to the water resources of the District. Spraying tussocks with herbicides would not be an effective means of addressing tussock blockages due to the fact that, once treated, tussocks can take weeks to die and fall to the lake bottom. Floating tussocks are and will continue to be treated with herbicide sprays when found in the Lake to reduce the amount of tussocks. However, once tussocks enter the canal, spraying serves little benefit in preventing tussocks from causing blockages or other problems. Tussocks originate in the Lake and not in the canal. Tussocks in the Lake have had and likely will continue to have an impact on boating and recreational use of the Lake and canal, as evidenced by tussock blockages to Petitioner's dock. By confining the tussocks to the Lake, the potential for tussocks to impact boating and recreational use of the Lake will remain the same as current conditions, but the potential for tussocks to affect operation of the control structure and contribute to Lake flooding will be eliminated. Petitioner contends that the proposed floating weed barrier will impede navigation, either by itself or as a result of tussocks piling up in front of the barrier. The proposed barrier will be marked and visible through reflective tape and signage. The barrier does not create a navigational hazard and is not a significant impediment to access to the canal. Constructed in two sections, the barrier provides an opening that allows boat access to the canal. As noted above, the likelihood of tussocks piling up at the barrier and blocking the opening between the barrier sections is considered remote and temporary. Based upon the information provided by the District, the proposed floating weed barrier will not significantly impede navigation; will not cause a violation of state water quality standards; will not impede the conveyance of a stream, river, or other water course in a manner that would increase off-site flooding; will not adversely impact aquatic or wetland dependent listed species; and will not cause the drainage of wetlands. There is no evidence that the proposed activity is located in, on, or over a coral community, macro-marine algae, or submerged grassbed community or that it entails the construction of a structure for the launching or mooring of a boat for which navigational access does not currently exist. The proposed activity would have only minimal or insignificant individual or cumulative adverse impacts on the water resources of the District. As an activity that has minimal or insignificant adverse impacts on the water resources of the District, either individually or cumulatively, the District’s project qualifies for an exemption pursuant to Section 373.406(6), Florida Statutes, as well as a Noticed General ERP under Rule 62- 341.475(1)(a), Florida Administrative Code. The Department's exemption determination authorized the District’s floating weed barrier for one year, presumably so that the effectiveness of the barriers can be evaluated during that period of time. If they are effective, an extension or renewal of the authorization will be sought. If the tussocks problem becomes less acute, or the barriers do not achieve the desired purpose, they will be taken down. In contrast, Noticed General ERPs authorize a particular activity for five years. Other Contentions by Petitioner Petitioner has also contended that the proposed activity may violate a condition of the District's Corps of Engineers general permit by interfering with general navigation. As found earlier, however, the more credible evidence indicates otherwise. Moreover, it is presumed that this issue was considered by the Corps of Engineers prior to its approval of the project. In any event, that matter should be raised with the Corps of Engineers, and not with the Department. Finally, Mr. Lahey contends that since at least late 2002, the Lake has been free of a tussocks problem and therefore barriers are no longer needed. As noted above, however, blockages have occurred at the control structure and in the Peace River as recently as January and March 2003, and such blockages were the direct result of tussocks which originated in the Lake. Given the likelihood of a very active summer rainy season, it is essential that the canal be kept open so that the District can properly manage and control the water resources.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection issue a final order determining that the Southwest Florida Water Management District's proposed project qualifies for an exemption under Section 373.406(6), Florida Statutes; that authorization to use state-owned lands be given; and that the project is in compliance with the State Programmatic General Permit program. DONE AND ENTERED this _____ day of May, 2003, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this _____ day of May, 2003. COPIES FURNISHED: Kathy C. Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Bruce Lahey 5280 Waterwood Drive Bartow, Florida 33830-9766 Martha A. Moore, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899 Doreen Jane Irwin, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

Florida Laws (4) 120.569120.57369.20373.406
# 5
CITY OF SUNRISE vs INDIAN TRACE COMMUNITY DEVELOPMENT DISTRICT AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 91-006036 (1991)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 23, 1991 Number: 91-006036 Latest Update: Dec. 13, 1991
Florida Laws (4) 120.57373.019373.219373.223 Florida Administrative Code (1) 40E-2.301
# 6
DUNES GOLF AND COUNTRY CLUB vs. SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 78-000756 (1978)
Division of Administrative Hearings, Florida Number: 78-000756 Latest Update: Sep. 21, 1978

Findings Of Fact The Dunes Golf and Country Club, Sanibel, is a partnership owned by John K. Kontinos and William R. Frizzell. They operate a nine hole golf course consisting of 65 acres of the eastern portion of Sanibel Island. The golf course is open to the public and, during the winter season, some 150 to 175 persons utilize the facility daily, but in the period May--November, it is utilized by only about 15 or 20 persons per day. The golf course is presently irrigated by water obtained from the lower Hawthorn and Suwannee aquifers through a well that is approximately 737 feet deep. On the days that water is pumped from the well, the pumping duration is from 8 to 12 hours per day, but the monthly hours during which pumping occurs averages approximately 155 hours per month. There is another existing well in another portion of the applicant's property which extends 896 feet into the Suwannee aquifer. The well presently in use (well number 1) has 546 feet of casing and the well that is not in use (well number 2) has 700 feet of casing. (Testimony of Kontinos, Exhibits 2, 4) On December 15, 1977, the Dunes Golf and Country Club submitted an application to the South Florida Water Management District for a consumptive use permit to withdraw 320 acre feet of groundwater per year to irrigate an area of approximately 109 acres. The intent of the application was to obtain a sufficient quantity of water to irrigate the golf course which the applicant intends to enlarge to consist of 18 holes. The additional 9 holes would cover some 44 acres and well number 2 is intended to be activated to provide additional water for this purpose. (Testimony of Kontinos, Keiling, Exhibits 1- 2) The South Florida Water Management District issued the required public notice of the application on March 30, 1978, and objections to the application were received by that agency from the City Council of Sanibel, the Island Water Association, Inc., and George R. Campbell. Public notice of hearing on the application was duly published on March 30, 1978. (Exhibits 5-7) The staff of the South Florida Water Management District reviewed the application and recommended continuation of the applicant's existing use from the lower Hawthorn Formation and use of additional irrigation water from the Suwannee aquifer in the total amount of 320 acre feet annually. It also recommended that the issuance of a permit should be conditioned in various respects to include semiannual submission of water quality data and pumpage records for each well, installation and maintenance of well controls, and repair or replacement of well casings, valves or controls that leak or become inoperative. The staff further recommended that maximum monthly withdrawals from the lower Hawthorn Formation be limited to 7.5 million gallons and 7.6 million gallons from the Suwannee Formation. At the hearing however, the South Florida Water Management District representative changed these recommendations to 8.9 MO and 6.1 MG respectively. Additionally, the initial recommendation of 320 acre feet annual withdrawal was reduced to 200 acre feet. This amount is considerably less that the average of 600 acre feet used on other comparably sized golf courses. Further the staff representative recommended at the hearing that a further condition be attached to the issuance of the permit; i.e., Condition 15, which requires the permittee to submit analyses of total dissolved concentrations in water samples from each well within 30 days of permit issuance and, if such concentration exceeds 4,000 MG/L, logging procedures as to the affected well will be required with necessary safeguards to be employed to eliminate any interaquifer leakage. (Testimony of Gleason, Exhibit 4) The objections of the City of Sanibel and the Island Water Association, Inc. involved concerns that further withdrawals from the lower Hawthorn aquifer will affect the availability of water which is treated by the water association for general island use. In addition, there is concern about possible contamination of the lower Hawthorn aquifer from interaquifer leakage. The Water Association is a member-owned cooperative that is not under the jurisdiction of the municipality. It is concerned about the draw down in the water table which will be occasioned by additional withdrawals by the applicant. It therefore believes that pumping tests should be conducted prior to the issuance of a permit to provide information concerning the capacity and safe yield of the wells. Although an Association expert testified that the proposed Dunes' withdrawal would create a cone of depression that would extend into and influence the existing Water Association wells, the evidence shows such influence to be minimal due to the fact that the Dunes wells are almost three miles away from the nearest Association well. Further, due to the limited time that the Dunes wells are pumped each day, the aquifer recovers to a certain extent during other hours. Although concerns are felt by the Water Association that water quality will be affected because of leakage from the Suwannee aquifer to the lower Hawthorn aquifer due to possible corrosion of steel casings in the Dunes wells, no evidence was presented that such casings are in fact defective and will contribute to degradation of water quality because of additional withdrawals. The additional special condition placed upon the issuance of a permit by the South Florida Water Management District will require correction of any such leakage that is discovered in the future. Previous studies show that the lower Hawthorn aquifer is separated from the Suwannee aquifer by the Tampa Limestone Formation which would slow down any entry of poorer quality water into the Hawthorn aquifer. It is found that the lesser amounts of water recommended by the South Florida Water Management District at the hearing will further reduce the likelihood of water quality degradation or draw down in other Island wells. (Testimony of Butler, Holland, Nuzman, Gleason, Exhibits 6, 8-13) Ecological concerns were expressed at the hearing by a public witness as to the wastefulness of irrigating golf coup Yes and the requirement for fertilizer in sandy soil which causes leaching of nutrients after heavy water use. (Testimony of Webb)

Recommendation That a permit be issued to the applicant authorizing the consumptive use of the quantity of water recommended by the South Florida Water Management District staff, subject to the recommended conditions thereto. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: John H. Wheeler Post Office Box V West Palm Beach, Florida 33402 James D. Decker, Esquire Post Office Box 200 Ft. Myers, Florida 33902

Florida Laws (2) 373.019373.223
# 7
FLORIDA AUDUBON SOCIETY, FLORIDA KEYS AUDUBON SOCIETY, AND UPPER KEYS CITIZENS ASSOCIATION vs WILLIAM R. CULLEN AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-003779 (1989)
Division of Administrative Hearings, Florida Filed:Key Largo, Florida Jul. 14, 1989 Number: 89-003779 Latest Update: Aug. 22, 1990

The Issue The central issue in this case is whether the Department of Environmental Regulation (Department) should grant a dredge and fill permit which has been requested by the Respondent, William R. Cullen (Applicant). That proposed permit has been opposed by the Petitioners (who will be referred to collectively as Petitioners for convenience sake).

Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received, the following findings of fact are made: The Department is the state agency authorized to issue permits pursuant to Chapter 403, Florida Statutes. The Respondent, William R. Cullen, filed an application for a dredge and fill permit to construct a slip marina on June 4, 1985. The original request was subsequently amended to seek approval for a forty-two slip commercial marina. The project site for the Applicant's marina is located at Key Largo, Monroe County, Florida. The site is within Buttonwood Sound, Florida Bay. The property is owned by Mr. Cullen and his family. All of the proposed improvements will be constructed on submerged lands or uplands owned or controlled by the Cullen family. The project site is located within a commercial area of Key Largo and contains frontage on both the water, Buttonwood Sound, and the highway, U.S. Highway 1. The project site has a basin which was created by the excavation of materials used for road construction from the shoreline and the installation of an L-shaped rock jetty which runs roughly perpendicular and then parallel to the shoreline. This jetty was installed during the late 1960s. The water depths within the basin range from 3 feet to approximately 14 feet. The water within the basin is subject to the same tidal considerations as the waters within Buttonwood Sound. There is no interruption of the flow of water in and out of the basin from those waters of the Sound. The water within this basin is within an Outstanding Florida Water as defined in Rule 17-3.041, Florida Administrative Code. The Applicant's plan calls for the excavation of appproximately 30,170 square feet of upland area and the dredging of the existing basin for approximately 18,460 dredged square feet. During the construction phases, the Applicant proposes to install turbidity curtains to limit the adverse effects expected during that time. The improvements are intended to be a permanent alteration to the basin design and will permanently modify the marine life habitat within that basin. The Applicant proposes to remove portions of the existing jetty to allow additional water to flow through the basin unimpeded by the jetty walls. The removal of the jetty walls will expedite the dilution and flushing of potential pollutants from the basin on a tidal frequency. That flushing is purported to assure that the water quality within the basin will not be diminished. However, such pollutants will be flushed into Buttonwood Sound. Stormwater accumulating on the upland project is to flow toward a lower upland area and should not to be dumped into the basin. The proposed marina is to have fueling facilities and the Applicant has agreed to design that system to limit inadvertent spillage. Further, as a condition of the permit, the Applicant has agreed to abide by the Department of Natural Resources' spill contingency plan requirements. The proposed marina is designed to provide portable sewage pumpout facilities for each slip. A permanent pumpout facilities will also be available. The Applicant seeks to attract boats in the range of 30 to 50 feet in length at this facility. While there are a number of other marinas in other areas of Key Largo which might accomodate that size boat, the marinas in the immediate vicinity of this project site are designed for smaller craft. The area within the basin consists of unvegetated bottom, submerged rip-rap, sea grasses, and hardbottom/algae communities--the predominant classifications being the latter two. The deeper hardbottom areas are to be filled and portions of the sea grasses will be dredged in order to configure the proposed docks. Additionally, other sea grass areas will be shaded, and thereby disturbed, by the construction of the docks. There are no historical or archaeological features relevant to the proposed site. The area has not been designated as a critical manatee area, however, manatees do frequent the project vicinity and have been observed feeding immediately adjacent to the basin. The permit proposed for this project requires a water quality monitoring plan. In addition to sampling for coliform, diesel by-products, oils, greases, detergents, oxygen, copper, lead and zinc, the plan requires sampling for aluminum, cadmium, and chromium. The monitoring stations are to be located both within the basin (2 stations) and outside the basin (2 stations). Liveaboards or others continuously docked at the marina will create additional shading which will disrupt and adversely affect the sea grass system. In order to provide access to the marina, the Applicant intends to dredge a channel in an area containing sea grass which is undisputedly within the Outstanding Florida Waters. The Department deemed the subject application was complete on February 23, 1988. The Department did not apply the Keys Rule found in Rule 17-312.400, Florida Administrative Code, to this project. The Department also did not apply the Mitigation Rule found in Rule 17-312.300, Florida Administrative Code, to this project. Michael Dentzau has personally reviewed and processed 250-300 dredge and fill permits during his tenure with the Department. Of those projects he has reviewed, he has not recommended that dense sea grass beds of the type located within this project site be dredged in order to construct a commercial marina. Phillip Edwards was responsible for executing the Intent to Issue in this case. In determining that this project had provided reasonable assurances that water quality standards will not be violated, Mr. Edwards weighed the public interests criteria set forth in Section 403.918, Florida Statutes. Because he received letters purportedly from elected officials, Mr. Edwards presumed that the project was in the public interest. That assumption of fact has not been established by this record. According to Mr. Edwards, the adverse effects expected by this project could be adequately addressed by the permit conditions when weighed against the public interest in favor of the project. Since Mr. Edwards' assumptions as to the public interest in this project have not been established, his conclusion regarding the weight that interest should receive can be given little consideration. The project as proposed by the Applicant will not adversely affect navigation or cause harmful erosion or shoaling. The project as proposed by the Applicant will adversely affect fishing or marine productivity within the basin since it will permanently alter the basin biologically by destroying sea grass. The increased boat traffic within the Sound will also detract from the present recreational uses enjoyed by area residents. According to Mr. Edwards, it is very unusual for the Department to issue a permit when sea grasses will be adversely affected. In the 17 years in which he has reviewed permits, only two occasions merited approval when the destruction of sea grasses to the extent in this case would result. Neither of those cases were factually similar to the case at issue. In those cases, however, elected officials advised Mr. Edwards, as he presumed they had here, that there was a public need for the permit. Increased boat traffic will result in increased manatee mortality due to collisions. In order to assure water quality will not be degraded within a marina, the project should have a short flushing time comparable to healthy natural embayments. In this case, the flushing proposed by the Applicant is dependent, in part, on winds which may be inconsistent or relatively minimal during the summer months.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Department of Environmental Regulation enter a final order denying the permit requested by the Applicant. DONE and ENTERED this 22nd day of August, 1990, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings 1230 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 1990. APPENDIX TO CASE NOS. 89-3779 et seq. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY PETITIONERS: The first three sentences of paragraph 1 are accepted; the remainder is rejected as argument or irrelevant. Paragraph 2 is accepted. Paragraph 3 is accepted. With regard to paragraph 4, it is accepted that the Department deemed the application complete on February 23, 1988; otherwise, the paragraph is rejected as argument. With regard to paragraph 5, it is accepted that the habitat within the basin is the same as the habitat throughout Florida Bay and that the basin is not "enclosed" hydrologically; otherwise, the paragraph is rejected as argument or comment. Paragraphs 6, 7, 8, 9, 10, 11, and 12 are rejected as argument, conclusions of law, or comment. The paragraphs do not recite facts pertinent to this case. Paragraphs 13, 14, and the first two sentences of paragraph 15 are accepted. The remainder of paragraph IS is rejected as argument. The first two sentences of paragraph 16 are accepted. The remainder of the paragraph is rejected as comment or argument. Paragraph 17 is accepted. Paragraph 18 is rejected as argument. To the extent that paragraph 19 accurately describes Van de Kreeke's assessment of the report it is accepted; otherwise rejected as irrelevant, comment, argument, recitation of testimony or unsupported by the record. The report upon which comment is directed was not offered in this cause to prove its truth/accuracy. Paragraphs 20 through 22 are rejected as comment, argument, recitation of testimony or unsupported by the record-- see comment to paragraph 19 above. Paragraphs 23 through 26 are accepted. Paragraphs 27 and 28 are rejected as argument, comment, or contrary to the weight of the evidence. Paragraphs 29 and 30 are accepted. Paragraph 31 is rejected as argument or contrary to the weight of the evidence. Paragraphs 32 and 33 are accepted. Paragraph 34 is rejected as hearsay, irrelevant, or argument. Paragraph 35 is rejected as comment or argument. Paragraph 36 is accepted. Paragraphs 37 through 40 are rejected as argument or contrary to the weight of the evidence. Paragraphs 41 through 43 are accepted. Paragraph 44 is rejected as contrary to the record. Paragraph 45 is rejected as argument. Paragraph 46 is rejected as argument or contrary to the weight of the evidence. Paragraph 47 is accepted but is comment. Paragraphs 48 and 49 are accepted. Paragraph 50 is rejected as repetitive. Paragraph 51 is rejected as argument or conclusions of law. The first three sentences of paragraph 52 are accepted. The remainder of the paragraph is rejected as argument. The first sentence and that portion of the second sentence of paragraph 53 that ends with the word "authenticity" is accepted. The remainder of the paragraph is rejected as argument or conclusions of law. Paragraphs 54 and 55 are accepted. Paragraph 56 is rejected as irrelevant or hearsay. Paragraph 57 is rejected as hearsay. Paragraph 58 is rejected as argument, comment, or irrelevant. Paragraphs 59 through 66 are accepted. Paragraph 67 is rejected as contrary to the weight of the evidence. Paragraph 68 is rejected as contrary to the weight of the evidence. Paragraphs 69 and 70 are accepted. Paragraph 71 is rejected as repetitive. Paragraph 72 is rejected as argument. The first sentence of paragraph 73 is accepted; the remainder is rejected as contrary to the weight of the evidence. Paragraph 74 is accepted. Paragraphs 75 through 77 are rejected as contrary to the weight of the evidence. Paragraphs 78 and 79 are accepted. Paragraph 80 is rejected as repetitive. With the inclusion of the words "and hardbottom and algae" paragraph 81 is accepted. Paragraph 82 is accepted. Paragraph 83 is accepted. Paragraph 84 is rejected as contrary to the weight of the evidence. 5l. Paragraphs 85 through 89 are accepted. With the substitution of the word "not" for the word "ever" in the last sentence of paragraph 90, it is accepted. Paragraphs 91 through 94 are accepted. Paragraph 95 is rejected as not supported by the record or contrary to the weight of the evidence. Paragraphs 96 through 100 are accepted. Paragraph 101 is rejected as repetitive. Paragraphs 102 through 106 are rejected as argument, comment, or irrelevant. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY THE DEPARTMENT: Paragraph 1 is accepted. Paragraph 2 is rejected as contrary to the weight of the credible evidence. The waters within the basin are of the same origin as they were prior to the creation of the jetty; no artificial body of water was created. With regard to paragraph 3 it is accepted that the jetty was constructed in the late 1960s. Paragraph 4 is accepted. With regard to paragraph 5 it is accepted that that is the applicants proposal no conclusion as to the likelihood of that is reached. Paragraph 5 is accepted. Paragraph 6 is accepted. Inevitably, however, spills will occur and must be considered as an adverse affect of the project. Paragraph 7 is accepted. Paragraph 8 is rejected as unsupported by competent evidence or contrary to the weight of the evidence presented. Paragraph 9 is rejected as contrary to the weight of the evidence. Paragraph 10 is accepted. Paragraph 11 is accepted but is inadequate to offset the adverse affects to manatees. Paragraph 12 is accepted but is inadequate to limit the adverse affects to sea grass. Paragraph 13 is rejected as contrary to the weight of the evidence. Paragraph 14 is rejected as contrary to the weight of the evidence. Paragraph 15 is accepted. Paragraph 16 is accepted. Paragraphs 17 and 18 are accepted. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY THE APPLICANT: Paragraphs 1 through the first sentence of paragraph 6 are accepted. The second sentence of paragraph 6 is rejected as contrary to the weight of the evidence. Paragraphs 7 through Il are accepted. Paragraph 12 is rejected as irrelevant. Paragraphs 13 through the first sentence of paragraph 17 are accepted. The remainder of paragraph 17 is rejected as contrary to the weight of the evidence. Paragraph 18 is accepted. Paragraph 19 is rejected as unsupported by the record or contrary to the weight of the evidence. Paragraph 20 is accepted. Paragraphs 21 through 26 are rejected as contrary to the weight of the evidence. Paragraph 27 is rejected as contrary to the weight of the evidence or unsupported by competent evidence. The first sentence of paragraph 28 is accepted, the remainder rejected as speculative, comment, or unsupported by the record. The first sentence of paragraph 29 is accepted, the remainder rejected as contrary to the weight of the evidence. Paragraph 30 is accepted. Paragraph 31 is rejected as contrary to the weight of the evidence. Paragraph 32 is rejected as contrary to the weight of the evidence. Paragraph 33 is accepted but is irrelevant. Paragraph 34 is rejected as contrary to the weight of the evidence. Paragraph 35 is accepted; however, sea grasses not disturbed by dredging will still suffer adverse affects from shading and silting. Paragraph 36 is accepted but see comment to paragraph 35 above. Paragraph 37 is accepted. Paragraph 38 is accepted. Paragraph 39 is accepted but is irrelevant. Paragraph 40 is accepted. Paragraph 41 is accepted. Paragraph 42 is accepted. Paragraph 43 is rejected as irrelevant. Paragraph 44 is rejected as contrary to the weight of the evidence. Paragraph 45 is accepted but it should be noted that is not the extent of the proposal. Paragraph 46 is rejected as contrary to the weight of the evidence. Paragraph 47 is accepted. Paragraph 48 is rejected as contrary to the weight of the evidence. Paragraph 49 is rejected as contrary to the weight of the evidence. COPIES FURNISHED: Pamela Presnell Garvin Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Charles Lee Florida Audubon Society 1101 Audubon Way Maitland, Florida 32751 Robert Routa P.O. Box 6506 Tallahassee, Florida 32314-6506 Linda McMullen McFARLAIN, STERNSTEIN, WILEY & CASSEDY, P.A. 600 First Florida Bank Building Tallahassee, Florida 32301 Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 =================================================================

Florida Laws (2) 120.68267.061
# 8
LAKE PADGETT ESTATES vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-000308 (1975)
Division of Administrative Hearings, Florida Number: 75-000308 Latest Update: Jun. 18, 1992

The Issue Whether a consumptive-use permit for the quantities of water applied for should be granted.

Findings Of Fact Applicant, by Application No. 7500025, applied for a consumptive-use permit for an average daily withdrawal of 138,000 gallons of water from one (1) well penetrating the Florida Acquifer. This is an existing use. Exhibits were entered without objection, as follows: Original application with attachments, marked "Exhibit 1". Proof of Publication, marked "Exhibit 2". There were no written objections. The witness for permittee, George Szell, Hydrologist, was questioned at length by the staff attorney on issues to be resolved under Chapter 373, Florida Statutes, and the Rules and Regulations promulgated thereunder by the Southwest Florida Water Management District, and particularly Rule 16J-2.11, Conditions for a Consumptive-Use Permit. A typed transcript of the testimony has been examined and made a part of the record for this hearing. The witness for the Board, Mr. Szell, objected to the granting of the permit on the grounds that the water crop was exceeded by 3.24 percent. Upon request of the Hearing Officer, the parties agreed to consider their differences and file a joint stipulation enumerating conditions upon which the parties agree. A joint stipulation signed by both parties was filed with the Division is marked "Supplement to the Record" and made a part of this recommended order. Mr. Szell recommended that the permit be granted consistent with the conditions in six (6) above.

# 9
MANASOTA-88, INC. vs LAND TRUST NO. 97-12 AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 14-005038 (2014)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Oct. 23, 2014 Number: 14-005038 Latest Update: Apr. 10, 2017

The Issue The issue to be determined is whether Respondent Land Trust #97-12 (“Land Trust”) is entitled to an Environmental Resource Permit (“ERP”) for its proposed project on Perico Island in Bradenton, Florida.

Findings Of Fact The Parties Petitioner Joseph McClash is a resident of Bradenton, Florida, who uses the waters in the vicinity of the project for fishing, crabbing, boating, and wildlife observation. Petitioner Manasota-88, Inc., is an active Florida nonprofit corporation for more than 20 years. Manasota-88 has approximately 530 members, most of whom (approximately 300) reside in Manatee County. The mission and goal of Manasota-88 includes the protection of the natural resources of Manatee County, including Anna Maria Sound and Perico Island. Petitioner FISH is an active Florida nonprofit corporation in existence since 1991. FISH owns real property in unincorporated Cortez in Manatee County and maintains a Manatee County mailing address. FISH has more than 190 members and more than 150 of them own property or reside in Manatee County. The mission and goal of FISH includes protection of the natural resources of Manatee County, including Anna Maria Sound and Perico Island. Intervenor Suncoast Waterkeeper, Inc., is an active Florida nonprofit corporation in existence since 2012. The mission of Suncoast Waterkeeper is “to protect and restore the Suncoast’s waterways through enforcement, fieldwork, advocacy, and environmental education for the benefit of the communities that rely upon coastal resources.” Suncoast Waterkeeper provided the names and addresses of 25 members residing in Manatee County. A substantial number of the members of Suncoast Waterkeeper use the area and waters near the proposed activity for nature-based activities, including nature observation, fishing, kayaking, wading, and boating along the natural shorelines of Anna Maria Sound and Perico Island. Intervenor Sierra Club, Inc., is a national organization that is a California corporation registered as a foreign nonprofit corporation in Florida. Sierra Club has been permitted to conduct business in Florida since 1982. The mission of Sierra Club includes protection of the natural resources of Manatee County, which include Anna Maria Sound and Perico Island. Sierra Club provided the names and addresses of 26 members who live in Manatee County. A substantial number of the members of Sierra Club use the area and waters near the proposed project for nature-based activities, including observing native flora and fauna, fishing, kayaking, wading, and boating along the natural shorelines of Anna Maria Sound and Perico Island. Respondent Land Trust is the applicant for the challenged ERP and owns the property on which the proposed project would be constructed. Respondent District is an independent special district of the State of Florida created, granted powers, and assigned duties under chapter 373, Florida Statutes, including the regulation of activities in surface waters. The proposed project is within the boundaries of the District. The Project Site The project site is 3.46 acres of a 40.36-acre parcel owned by Land Trust. The parcel includes uplands, wetlands, and submerged lands, on or seaward of Perico Island, next to Anna Maria Sound, which is part of Lower Tampa Bay. Anna Maria Sound is an Outstanding Florida Water. The project site is adjacent to a large multi-family residential development called Harbour Isles, which is currently under construction. Access to the Land Trust property is gained through this development. The Land Trust parcel contains approximately seven acres of high quality mangroves along the shoreline of Anna Maria Sound. They are mostly black and red mangroves, with some white mangroves. The mangroves on the project site amount to a total of 1.9 acres. Mangroves have high biological productivity and are important to estuarine food webs. Mangroves provide nesting, roosting, foraging, and nursery functions for many species of wildlife. Mangroves also provide a buffer from storm surge and help to stabilize shorelines. Wildlife species found on the project site include ibises, pelicans, egrets, spoonbills, mangrove cuckoos, bay scallops, fiddler crabs, mangrove tree crabs, horseshoe crabs, marsh rabbits, raccoons, mangrove bees, and a variety of fish. No endangered species have been observed on the project site, but mangroves are used by a number of listed species. The Proposed Project The proposed project is to construct a retaining wall, place fill behind the wall to create buildable lots for four single-family homes, construct an access driveway, and install a stormwater management facility. The stormwater management facility is a “Stormtech” system, which is an underground system usually used in situations where there is insufficient area to accommodate a stormwater pond. Riprap would be placed on the waterward side of the retaining wall. The retaining wall would be more than 35 feet landward of the mean high water line in most areas. Petitioners contend the proposed retaining wall is a vertical seawall, which is not allowed in an estuary pursuant to section 373.414(5). “Vertical seawall” is defined in section 2.0(a)(111), Volume I, of the Environmental Resource Permit Applicant’s Handbook (“Applicants Handbook”) as a seawall which is steeper than 75 degrees to the horizontal. It further states, “A seawall with sloping riprap covering the waterward face to the mean high water line shall not be considered a vertical seawall.” The retaining wall is vertical, but it would have riprap covering its waterward face and installed at a slope of 70 degrees. The retaining wall is not a vertical seawall under the District’s definition. Stormwater Management Stormwater in excess of the Stormtech system’s design capacity would discharge into Anna Maria Sound. Because Anna Maria Sound is an Outstanding Florida Water, District design criteria require that an additional 50 percent of treatment volume be provided. The Stormtech system meets the District’s design criteria for managing water quality and water quantity. Projects which meet the District’s design criteria are presumed to provide reasonable assurance of compliance with state water quality standards. Petitioners’ evidence was not sufficient to rebut this presumption. Petitioners contend the District waiver of water quality certification for the proposed project means that Land Trust was not required to meet water quality standards. However, that was a misunderstanding of the certification process. All state water quality criteria are applicable. Petitioners contend water quality monitoring should be imposed for this project. However, section 4.7 of the Applicant’s Handbook, Volume II, provides that if the applicant meets the District’s design criteria, water quality monitoring is not required. Petitioners failed to prove the proposed stormwater management system cannot be constructed, operated, or maintained in compliance with applicable criteria. Wetland Impacts In order to create buildable lots, 1.05 acres of the 1.9 acres of mangroves on the project site would be removed and replaced with fill. A swath of mangroves approximately 40 feet wide would remain waterward of the retaining wall. The proposed direct and secondary impacts to the functions provided by wetlands were evaluated using the Uniform Mitigation Assessment Method (“UMAM”) as required by Florida Administrative Code Chapter 62-345. UMAM is used to quantify the loss of functions performed by wetlands considering: current condition, hydrologic connection, uniqueness, location, fish and wildlife utilization, time lag, and mitigation risk. The District determined the filling of 1.05 acres of wetlands would result in a functional loss of 0.81 units and the secondary impacts resulting from installation of the retaining wall would result in a loss of 0.09 units for a total functional loss of 0.9 units. Petitioners contend the functional loss would be greater. Petitioners contend the wetland delineation performed by Land Trust and confirmed by the District did not extend as far landward as the hydric soils and, therefore, the total acreage of affected wetlands would be greater. However, Petitioners did not produce a wetland delineation for the project site, and their evidence was not sufficient to rebut Land Trust's prima facie evidence on this issue. Petitioners’ experts believe the secondary impacts caused by the proposed project would be greater than calculated, including fragmentation of the shoreline mangrove system, damage to the roots of mangroves near the retaining wall, and scouring effects caused by wave action associated with the retaining wall. Respondents assert that the analysis by Petitioners’ expert Jacqueline Cook relied on federal methodology and that “the science used in her analysis is not contained in the state or district rule criteria.” Reliance on science is always appropriate. However, Ms. Cook’s use of a federal impact assessment methodology creates doubt about whether her scoring is consistent with UMAM. Despite the unreliability of Ms. Cook’s UMAM score, it is found that Respondents’ UMAM score under-calculated secondary impacts due to scour and other effects of changed water movement that would be caused by the retaining wall. It was not explained how the loss of storm buffering and erosion prevention functions of wetlands are accounted for in the UMAM score. Elimination or Reduction of Impacts Section 10.2.1 of the Applicant’s Handbook, Volume I, states that in reviewing a project the District is to consider practicable design modifications to eliminate or reduce impacts to wetland functions. Section 10.2.1.1 explains: The term “modification” shall not be construed as including the alternative of not implementing the activity in some form, nor shall it be construed as requiring a project that is significantly different in type or function. A proposed modification that is not technically capable of being completed, is not economically viable, or that adversely affects public safety through the endangerment of lives or property is not considered “practicable.” A proposed modification need not remove all economic value of the property in order to be considered not “practicable.” Conversely, a modification need not provide the highest and best use of the property to be “practicable.” In determining whether a proposed modification is practicable, consideration shall also be given to cost of the modification compared to the environmental benefit it achieves. Land Trust originally proposed constructing a surface water retention pond. The Stormtech stormwater management system would cause less wetland impact than a retention pond. Land Trust contends the use of a retaining wall reduces wetland impacts because, otherwise, more mangroves would have to be removed to account for the slope of the waterward side of the fill area. However, this proposition assumes the appropriateness of the size of the fill area. Land Trust also contends wetland impacts are reduced by using the adjacent development to access the proposed project site, rather than creating a new road. However, the evidence did not establish that Land Trust had a practicable and preferred alternative for access. Unlike the Stormtech system, the retaining wall and access driveway were not shown to be project modifications. The proposed project would cause fewer impacts to wetlands if the fill area was reduced in size, which was not shown to be impracticable. Reducing the size of the fill area would not cause the project to be significantly different in type or function. Land Trust did not demonstrate that it implemented reasonable design modifications to eliminate or reduce impacts to wetland functions. Mitigation Land Trust proposes to purchase credits from the Tampa Bay Mitigation Bank, which is 17 miles north of the proposed project site. The Tampa Bay Mitigation Bank is in the Tampa Bay Drainage Basin. The project site is in the South Coastal Drainage Basin. Pursuant to section 10.2.8 of the Applicant’s Handbook, Volume I, if an applicant mitigates adverse impacts within the same drainage basin, the agency will consider the regulated activity to have no unacceptable cumulative impacts upon wetlands and other surface waters. However, if the applicant proposes to mitigate impacts in another drainage basin, factors such as “connectivity of waters, hydrology, habitat range of affected species, and water quality” will be considered to determine whether the impacts are fully offset. The parties disputed whether there was connectivity between the waters near the project site and the waters at the Tampa Bay Mitigation Bank. The more persuasive evidence shows there is connectivity. There was also a dispute about the habitat range of affected species. The evidence establishes that the species found in the mangroves at the project site are also found at the mitigation bank. However, local fish and wildlife, and local biological productivity would be diminished by the proposed project. This diminution affects Petitioners’ substantial interests. The loss or reduction of storm buffering and erosion prevention functions performed by the mangroves at Perico Island cannot be mitigated for at the Tampa Bay Mitigation Bank. Cumulative impacts are unacceptable when the proposed activity, considered in conjunction with past, present, and future activities would result in a violation of state water quality standards, or significant adverse impacts to functions of wetlands or other surface waters. See § 10.2.8.1, Applicant’s Handbook, Vol. I. Section 10.2.8(b) provides that, in considering the cumulative impacts associated with a project, the District is to consider other activities which reasonably may be expected to be located within wetlands or other surface waters in the same drainage basin, based upon the local government’s comprehensive plan. Land Trust did not make a prima facie showing on this point. Land Trust could propose a similar project on another part of its property on Perico Island. Anyone owning property in the area which is designated for residential use under the City of Bradenton’s comprehensive plan and bounded by wetlands could apply to enlarge the buildable portion of the property by removing the wetlands and filling behind a retaining wall. When considering future wetland impacts in the basin which are likely to result from similar future activities, the cumulative impacts of the proposed project would result in significant adverse impacts to wetland functions in the area. Public Interest For projects located in, on, or over wetlands or other surface waters, an applicant must provide reasonable assurance that the project will not be contrary to the public interest, or if such activities significantly degrade or are within an Outstanding Florida Water, are clearly in the public interest, as determined by balancing the criteria set forth in rule 62- 330.302(1)(a), and as set forth in sections 10.2.3 through of the Applicant’s Handbook. Rule 62-330.302, which is identical to section 373.414, Florida Statutes, lists the following seven public interest balancing factors to be considered: Whether the activities will adversely affect the public health, safety, or welfare or the property of others; Whether the activities will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activities will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activities will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activities will be of a temporary or permanent nature; Whether the activities will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S.; and The current condition and relative value of functions being performed by areas affected by the proposed regulated activity. The Parties stipulated that the proposed project would not have an adverse impact on public health, navigation, historical resources, archeological resources, or social costs. Land Trust proposes to give $5,000 to the City of Palmetto for an informational kiosk at the City of Palmetto’s public boat ramp. A District employee testified that this contribution made the project clearly in the public interest. Reasonable assurances were not provided that the proposed project is clearly in the public interest because of the adverse cumulative effects on the conservation of fish and wildlife, fishing and recreational values, and marine productivity of Anna Maria Sound, an Outstanding Florida Water.

Recommendation Based on the Findings of Fact and Conclusions of Law set forth above, it is RECOMMENDED that the Southwest Florida Water Management District issue a final order that denies the Environmental Resource Permit. DONE AND ENTERED this 25th day of June, 2015, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 2015. COPIES FURNISHED: Christian Thomas Van Hise, Esquire Abel Band, Chartered Post Office Box 49948 Sarasota, Florida 34230-6948 (eServed) Martha A. Moore, Esquire Southwest Florida Water Management District 7601 Highway 301 North Tampa, Florida 33637 (eServed) Douglas P. Manson, Esquire MansonBolves, P.A. 1101 West Swann Avenue Tampa, Florida 33606 (eServed) Joseph McClash 711 89th Street Northwest Bradenton, Florida 34209 (eServed) Ralf G. Brookes, Esquire Ralf Brookes Attorney 1217 East Cape Coral Parkway, Suite 107 Cape Coral, Florida 33904 (eServed) Justin Bloom, Esquire Post Office Box 1028 Sarasota, Florida 34230 (eServed) Robert Beltram, P.E., Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899

Florida Laws (7) 120.52120.569120.57120.68267.061373.414403.412