Findings Of Fact The College realized that it needed a new telecommunication system about three years ago, when it began to renovate some of its buildings. On June 8, 1992, the College issued an Invitation To Bid, No. 3656, to eight vendors to replace its fifteen-year-old AT&T Dimension Private Branch Exchange (PBX) System and install a voice and data communications network among the College's four campuses. The bids were to be opened at 2:30 p.m. on July 29, 1992. The College believed replacement of the existing PBX system would result in lower operating costs, permit the system to serve more functions and permit the system to expand as the College's needs grew. Two vendors, NEC and AT & T, submitted bids. The College already has gone through two prior bids for the new PBX system, which did not result in contracts with any of the bidders. AT&T had submitted a bid in response to each of those attempts to let a contract for replacement of the College's communications system. The process of developing the bid specifications was initiated by the College's Vice President for Business Affairs, Dr. Clinton Hamilton, who asked those who would be using the communications system (the Registrar, the Learning Resources Department, the Provost, and others) to explain their needs so they could be incorporated in the new system. He also asked College employees familiar with information systems and telecommunication systems to help draft the bid documents to incorporate the functions the users desired. The College received assistance from a committee made up of representatives of the State's Department of General Services, Division of Communications; the State Department of Education; Miami Dade Community College; Nova University; and the School Board of Broward County. These groups reviewed the proposed bid specifications before each of the College's three attempts to let a contract and advised the College on them. The College made a careful effort to craft its specifications to ensure it would purchase the most appropriate communications system for its needs. The College currently has separate and independent voice and data communications systems. For data, each of the College's locations (South campus, Central campus, North campus and the College's administrative center in Fort Lauderdale) use more than one data circuit (AT&T Exhibit 5; Bid page D-1). For example, the eight controllers at the South campus are connected to the Fort Lauderdale Center by a pair of data circuits. The 15 controllers at the Central campus are linked to the Fort Lauderdale Center by four data circuits. If the controllers associated with one data circuit should go down for some reason, those connected to the other data circuits at campus will continue to operate, and the campus will only suffer "partial paralysis." The bid at issue seeks a single "voice and data T-1 network" to link each of the campuses to Fort Lauderdale Center in a unified system, which eliminates the need for separate voice and data systems. The new system is designed so that controllers at each campus will communicate with the mainframe computer at Fort Lauderdale Center through T-1 trunk lines, the same lines connecting the voice telephone system at each campus. Each campus will have its own PBX system, and the T-1 lines will allow users at each campus to place telephone calls to extensions at all campuses internally, i.e., without leaving the College's own network. They can also use the local Southern Bell network to place calls if all internal lines are in use, just as the Southern Bell network is used to place calls to numbers outside the College's campuses. Connection of the voice system (the PBX equipment) and data terminals at each of the College's three campuses to the Fort Lauderdale Center requires the use of multiplexors, devices which improve efficiency in networks by concentrating and combining signals and switching them over connecting links (i.e., the T-1 circuits) to other locations or devices. The bid solicitation document requires a multiplexor known as a "40- Series" multiplexor at each campus to perform the concentrating and combining role. The bid solicitation document also specifies a single multiplexor of a more complex type, a "45-Series" multiplexor, at the Fort Lauderdale Center. This multiplexor performs the switching function to redirect signals from one location to another. The bid solicitation document instructs bidders to supply a Comsphere 6800 Network Management System, which is a type of software to operate the hardware components. Comsphere is manufactured by a wholly owned subsidiary of AT & T, known as "AT&T Paradyne." This software manages the entire network, and allows remote troubleshooting of any problems on the network, Comsphere's system can automatically dial out to the AT&T Paradyne Center in Largo, Florida, so that a technician can investigate and often solve problems without the need to send anyone to a campus to perform maintenance. On July 7, 1992, the College held a bidders conference to explain the bid documents and their requirements, in order to insure that the bids the College received would be accurate and complete. During that conference, the vendors were told: (1) any price corrections must be initialed or the bid would be disqualified; (2) all pages of the bid documents which contain signature lines had to be signed; (3) bidders could not modify the general conditions or special conditions of the bid documents; and (4) any questions about the specifications would be answered only by written addendum. The same instructions can be found in text of the bid solicitation document (AT&T Exhibit 4). The College issued Addendum One to its bid documents on July 9, 1992, Addendum Two on July 14, 1992, and Addendum Three July 22, 1992. Addendum Two is the source of the dispute here. As is the College's practice, all bids were opened publicly after the hour for the receipt of bids had passed on July 29, 1992. Each bid submission had two parts. The first was a bid summary sheet containing a required format for the vendor's price. The second part of the submissions were bound volumes explaining how the vendor would satisfy each of the specific requirements in the bid specifications. During the bid opening, a College employee opened the sealed envelopes containing the vendor's bid summary sheet, and read aloud the prices found on each bidder's summary sheet. Page 13, paragraph 19.6 of the Bid Specifications told bidders that the bid summary sheets must recite the total bid price for the entire system, which had to include any upgrades to the standard features of the vendor's equipment so that the equipment provided would meet the College's specifications. When the bids were opened, representatives of AT & T, AT&T Paradyne, and NEC were present. As the bid summary sheets were opened and the prices announced, no one from AT&T objected to the prices read out or contended there was an error in AT&T'S pricing. The College's Director of Purchasing, Janet Rickenbacker, and the senior buyer handling the acquisition, Susan Kuzenka, then reviewed the extensive responses to the specifications submitted by the two bidders. They determined that NEC was the low responsive bidder. The amount AT&T bid based on the bid summary sheet found in its sealed bid was $1,558,836.57, NEC's bid was $1,549,895.15. 1/ After the bid opening, Mr. Zinn of AT&T had two conversations with Ms. Kuzenka about the AT&T bid. These conversations focused on the conflict in the entry for system maintenance on the bid summary sheet for AT&T which had been opened and read aloud on July 22, 1992, and the backup data for the system maintenance figure found in a section of AT&T'S bid response documents. On the bid summary page, AT&T had listed its "four-year maintenance totals M[onday] through F[riday] 8 a.m. through 5 p.m." as $755,536.16. But on page 53 of its bound bid response, AT&T listed the "total maintenance" cost as $530,204.00. This lesser figure is consistent with other maintenance price information found on page 61 of the AT&T bound bid documents, which set out total monthly maintenance costs for Monday through Friday maintenance from 8:00 a.m. to 5:00 p.m. for all four college locations as $11,045.92 per month. If this monthly figure is multiplied by the maintenance term (48 months) the sum is the $530,204.00 shown on page 53. During his first conversation, however, Mr. Zinn told Ms. Kuzenka that the higher figure of $755,536.16 was correct, because AT&T had neglected to add in the maintenance for the AT&T Paradyne multiplexor in the entries in the bound bid documents at pages 53 and 61. During a second conversation, Mr. Zinn reversed his position and indicated that he had added the maintenance for the multiplexor twice, which resulted in an erroneously high figure of $755,536.16 on the bid summary sheet, and that the $530,204 figure on page 53 was correct. One week after the bid opening, on August 5, 1992, AT&T sent a fax letter to Ms. Kuzenka, which confirmed Mr. Zinn's second conversation, and stated that the correct maintenance price was the $530,204.00 found on page 53 of the AT&T bid, rather than the $755,536.16 figure found on its bid summary sheet. Ms. Kuzenka had not asked anyone from AT&T to submit this price change to its bid, and it was not accepted by the College, under its standard policy that price changes will not be accepted once a sealed bid has been received and opened. The College has consistently adhered to this practice through the entire term of Ms. Kuzenka's employment. While a lower maintenance price can be found in one portion of the voluminous response of AT&T to the Bid Specifications, the figure on the bid summary sheet controls. See the "Special Instructions" found at page 5 of the bid solicitation documents (AT&T Exhibit 4). A bidder should not be permitted to look for ambiguities in the supporting documentation to contradict clear entries of price components found on its bid summary sheet. Use of the bid summary sheet permits the College to rely on a specific portion of the bid submission, which will be comparable from bidder to bidder, and to avoid wading through voluminous and perhaps internally inconsistent submissions to try to determine exactly what the bidder's price is. The "Special Instructions" state: "Bidder must use bid pages provided by the College and submit bid in the order issued; failure to do so will result in rejection of your bid" (AT&T'S Exhibit 4). Over and above the maintenance price differential, the College staff found the submission by AT&T to be materially non-responsive to the Invitation to Bid. Ms. Kuzenka found five problems with the AT&T submission, which led her to conclude that the response submitted by AT&T failed to meet the bid specifications: (1) AT&T qualified or modified the terms and conditions of the specifications; (2) price corrections were not initialed by AT & T; (3) the maintenance contract was partially assigned to another vendor; (4) the bid was not signed by AT&T on all pages which have required signature lines; and (5) AT&T failed to provide a qualification statement. Modification of terms and conditions The College's bid document stated in paragraph 54.1 that the terms and conditions of the bid and purchase order constitute the contract and "no other terms and conditions apply" (Tr. 157). The maintenance agreement, titled "Product Agreement," which is appended to the AT&T Service Offerings and Support Plan is a standard AT&T form (College Exhibit 6). It contains a provision in paragraph 20G., which states "THIS AGREEMENT SHALL BE CONSTRUED IN ACCORDANCE WITH AND GOVERNED BY THE LOCAL LAWS OF THE STATE OF NEW JERSEY" (emphasis in original). The general conditions of the bid required that the contract be governed by Florida law (Tr. 152). AT&T argues that the standard product agreement it attached to its bid response had not been signed by a representative of AT & T, and that the College had the right to accept or reject the terms of the Service Offerings and Support Plans and the attachments to it. This is true, but the inclusion in its bid response of the New Jersey choice of law provision certainly creates an ambiguity over the applicable law, if AT&T'S bid were accepted. This ambiguity would be completely avoided had it not been proposed by AT & T, in contravention of the bid's general conditions. Paragraph 2 of the Product Agreement states "Terms and conditions on any non-AT&T order form shall not apply." Fairly read, AT&T was attempting to have its duties under its standard Product Agreement governed by the laws of New Jersey, not the laws of Florida. As a matter of sovereignty, Florida agencies do not subject themselves to foreign law. The College acted within its legitimate range of discretion when it rejected the choice of law provision as inconsistent with its bid documents. The same problem is caused by similar language in paragraph 12F of the AT&T Service Agreement (College Exhibit 5). The AT&T Product Agreement also has an integration clause, Paragraph 20H, stating that it constitutes the entire agreement of the parties, and supersedes any other oral or written agreements. This provision also attempts to modify the terms and conditions of the bid specifications to give the terms of AT &T's Service Offerings and Support Plan priority over the specifications. The College was entitled to reject this as inconsistent with the bid specifications. The same problem is presented by similar language in paragraph 12G of the AT&T Service Agreement (College Exhibit 5). The Service Offerings and Support Plan also contained a provision allowing AT&T to assign the agreement, which violates the anti-assignment provisions of paragraph 56.1 of the bid specifications. AT&T'S bid response stated that the College would be required to pay the cost for installing any additional cable. The bid specifications required vendors to inspect existing facilities at the College during a pre-bid walk- through, so that bidders could determine whatever cabling would be needed, and incorporate all necessary cable in their bid price. AT&T'S attempt to make the College liable for any cabling over and above that estimated by AT&T when submitting its bid is inconsistent with the bid specifications. The AT&T submission includeds a statement that the College was obligated to pay for the cost of a site survey to be performed by the project manager before the execution of the contract. Yet a site survey had already been performed, and the bidder's price was to have been inclusive of a total system, with no additional cost to the College for items such as surveys. Finally, the AT&T Service Offerings and Support Plan required the College to provide, at the College's expense, a secured and protected area for storage of tools and equipment near the equipment room, which was not part of the bid specifications. At the walk-through, AT&T should have determined whatever its security needs were and included those costs in its bid price. In essence, AT&T submitted preprinted forms without tailoring them to the carefully crafted requirements of the College's bid specifications. It cannot now disavow the contents of its forms which violate or fail to conform to these specifications. The time to review the company's standard forms was before they were submitted in its bid response, not afterward. Price correction There is a price correction on page 48 of the AT&T bid which is not initialed. The bid specifications require that "all corrections, manual or written or white-out must be initialed by the person signing the bid" (Bid Specifications, page 63, paragraph C). This was not done. The specifications stated "Failure to initial price corrections will result in the rejection of your bid" (AT&T Exhibit 4, page 5, numbered paragraph 2). Assignment provisions There was also confusion in the AT&T bid arising from the attachment of two proposed maintenance agreements, one from AT&T itself, another from AT&T Paradyne. The two maintenance contracts are not identical. 2/ College personnel believed that one contract was for part of the equipment, while the other contract was for another block of equipment. The College had been concerned about the difficulty in having to deal with different companies; it had drawn its specifications so that the bidder would be the single entity responsible to the College for maintenance. The submission of a proposed maintenance contract from an entity other than the bidder was inconsistent with the bid specifications. Signature Not all pages with signature lines had been signed by AT&T'S representative. These included page D1, which had a bearing on the equipment allowance being provided for the existing system traded in by the College. While AT&T regards these failures as trivial, the College went to pains to require bidders to sign pages with signature lines. Page 5 of the Bid Specifications stated: "Failure to sign all pages with a signature line will result in the rejection of your bid" (AT&T Exhibit 4, page 5, numbered paragraph 3). It is not arbitrary for the College to insist that these requirements be followed or to enforce the penalty stated in the specifications. Qualifications statement The special conditions for the bid required that vendors submit a qualifications statement listing similar work done for others (Tr. 168; Bid Specifications Section 25.1 at page 25). The College intended to consult those listed to determine whether they were satisfied with the equipment the vendor installed and the service it provided. AT&T did not provide that list, but rather provided an annual report which contains no customer references. This was not responsive to the bid. The College had experience with AT&T'S fifteen- year-old Dimension system, but not with the new equipment AT&T bid. The failure to submit the qualifications statement deprived the College of the opportunity to check with entities which had purchased the equipment AT&T had bid, something it had been careful to require of bidders. Deciding how to treat these inadequacies is a matter of discretion. Staff recommended rejection of the AT&T bid for genuine instances of noncompliance with specific requirements of the bid specifications the College had carefully crafted. This action cannot be characterized as arbitrary. The College's decision The College's purchasing department recommended to Dr. Hamilton that the bid be awarded to NEC as the low responsive bidder. A bid tabulation was posted on August 7, 1992, awarding the contract to NEC and rejecting AT&T'S bid. The protest AT&T filed a Notice of Protest, and later a Formal Written Protest on August 18, 1992, which dealt with a number of technical aspects, but did not claim that NEC's rival submission failed to conform to the bid specifications. Dr. Hamilton advised the College's president that, to be fair to both bidders, an outside consultant should be retained to evaluate the issues raised by AT&T in its Formal Written Protest. This was done, and the College retained Technology Associates for $8,600 to report to the College on the issues raised by AT & T. Technology Associates found that AT&T did not meet the emergency 911 requirements outlined in the College's bid documents. Southern Bell requires that when 911 calls are made from the College, the telephone system be capable of identifying to the police dispatcher which campus, which room and which extension number originated the emergency 911 call. The consultant also found that NEC's system met this requirement. AT&T did not attempt to refute this determination at the final hearing. The consultant found that AT&T'S proposed system was "over designed," in that it included elements not required by the bid documents. AT&T argues that Addendum Two, issued on July 14, 1992, 14 days before the bid opening, was so ambiguous with respect to necessary redundancy that the two bidders were bidding on fundamentally different systems, so that the matter should be bid for a fourth time. The portion of the addendum at issue states: The College requires two additional T-1 lines; not one as previously stated, to be added to diagram D-2 to ensure redundancy. A T-1 line is to connect North Campus with Central Campus and an additional T-1 line is to connect Central Campus with South Campus. (Tr. 85) Addendum Two explains that these lines are required to "ensure the ability to redirect calls if required, enabling the system to be fully redundant" (Tr. 86- 87, emphasis added). The addendum directed only the addition of two T-1 lines. This can be done, as NEC proposed, by connecting additional T-1 lines, one from the PBX at the North Campus to the PBX at the Central Campus and the other from the PBX at the Central Campus to the PBX at the South Campus. AT&T chose to feed each of the PBX installations at the North Campus, Central Campus and South Campus first into its own additional 45-Series multiplexor (the complex multiplexor, see Finding 10 above) so that a 45-Series multiplexor will handle T-1 connections from North Campus to a 45-Series multiplexor at Fort Lauderdale center, and to a 45-Series multiplexor at Central Campus. The PBX at Central Campus, because it has its own 45-Series multiplexor, then can be connected by T-1 lines to the 45- Series multiplexors at North Campus, South Campus and Fort Lauderdale Center. The PBX at South Campus, through its 45-Series multiplexor, then can connect to the 45-Series multiplexors at Central Campus and Fort Lauderdale Center (this configuration is shown on the final page of AT&T Exhibit 5). This is a more complex way to provide the T-1 connections between North and Central Campus and Central and South Campus than the addendum required, and uses four 45-Series multiplexors rather then one. AT&T argues its more complex solution was necessary so that both voice and data systems would be redundant, thus meeting the requirement in the addendum that the system be "fully redundant." The problem with the approach taken by AT&T is that it fails to follow the language of Addendum Two. There is no reference to alternative routing or redundancy for data, the redundancy is required to redirect calls, i.e., PBX or voice components. See the final quotation in Finding 40, above. Redundancy for data transmissions, something the AT&T solution provides, was not required. AT&T'S solution is overdesigned. This is not a pivotal issue, however, because for the reasons stated in the foregoing findings, the submission by AT&T was properly rejected by College staff as non-responsive to the terms of the Invitation to Bid. NEC is the low responsive bidder. Software certification AT&T argues in pages 16 through 20 of its proposed recommended order that the bid of NEC fails to conform to the requirements of the Invitation to Bid. AT&T had not raised the issue of whether the bid of NEC was responsive in its Formal Written Protest, and the attempt to do so at the beginning of the final hearing was rejected. As a result, this is not an issue which should have been addressed in the proposed recommended order. Nonetheless, it may be easily disposed of. The bid documents require that each bidder provide the College with a certification that the bidder: [O]wns, leases or controls the software it offers in response to this bid. If the bidder does not own the software, their certificate must include the source from which the software shall be obtained, and that the bidder has a right to sell or lease this software (Bid Specifications at 26, AT&T Exhibit 4.) The bidder also must certify that it is "eligible to maintain and support the software." (Id.) In its certification, NEC stated: NEC is the manufacturer of the NEAX2400 IMS that has been proposed to Broward Community College. As the manufacturer, we developed all software utilized on the NEAX2400. NEC owns all the rights to the software and has over 600 software engineers in Dallas dedicated to maintain and support the software. (AT&T Exhibit 4, final page) AT&T objects that this certification goes only to NEC's hardware, and does not constitute a certification that NEC has the rights to convey to the College the software necessary to operate the Comsphere 6800 Network Management System, which is a product of AT&T Paradyne. When reviewing the submissions of both bidders, the College staff found that their software certifications were equivalent. Both companies certified that they had the right to sell the software to operate the system each offered to the College. The College is entitled to rely on the certification given to it by NEC. If NEC is wrong, and does not have the right to provide the necessary software because AT&T or AT&T Paradyne will refuse to permit it to use that software, NEC may be liable in damages for failure to meet its contractual obligations to the College. NEC did not offer at the hearing evidence on why it believes it is entitled to use the software for the Comsphere 6800 Network Management System, because AT&T's attempt to raise this issue had been rejected when AT&T's motion to amend its Formal Written Protest of August 18, 1992 was denied.
Recommendation It is RECOMMENDED that a final order be entered by the Board of Trustees of Broward Community College awarding Bid No. 3656, the rebid of the College-wide PBX system, to NEC for a bid price of $1,549,895.15. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 9th day of March 1993. WILLIAM R. DORSEY, JR. Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of March 1993.
The Issue This case considers whether Petitioner's response to Invitation to Bid, No. 94-014, as revised, issued by the Respondent, is responsive to the terms of the Invitation to Bid. If Petitioner is found responsive, then the question is raised whether Petitioner has offered the lowest and best response to the invitation to bid.
Findings Of Fact On May 26, 1994, Respondent provided a memorandum to prospective vendors concerning Bid No. 94-014, as revised. This memorandum informed the prospective vendors that the new bid due date was June 6, 1994. The memorandum attached the bid instructions. Under general conditions to the invitation to bid the prospective vendors were reminded in Paragraph 7 that the Respondent could ". . . reject any or all bids or waive any minor irregularity or technicality in bids received." Under the heading "Special Provisions" prospective vendors were informed that "The charge per 1,000 for individual items under Exhibit A shall be the rates for the contract with the successful bidder." The prospective bidders were instructed as follows: REQUIRED ITEMS TO BE SUBMITTED WITH BID: The bidder must complete all required items below and submit as part of the bid package. Any bid in which these items are not used or in which these items are improperly executed, may be considered non-responsive and the bid may be subject to rejection. Among the items to be submitted with the bid was Exhibit A. The bidders were informed about the process of EVALUATION/AWARD. There it was stated: Bids will be evaluated and awarded on an all or none basis to one bidder. Award will be based on the total costs of four (4) theoretical jobs (See Exhibit B-Bid Total) requiring varying services and on the bidder's qualifications to best serve the Department's needs. The prospective bidders were then reminded a second time that: "THE DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION RESERVES THE RIGHT TO REJECT ANY AND ALL BIDS AND TO WAIVE ANY MINOR IRREGULARITIES IN BIDS RECEIVED." Within Exhibit A to the bid document was a category referred to as "Tabbing", calling for the charge per 1,000 for that service. Within Exhibit B under the fourth theoretical job was a requirement to quote the subtotal cost for 200,000 newsletter preparations to include "Tabbing." Three vendors submitted responses to the invitation to bid. Those responses were opened on June 6, 1994. The vendors who responded were Petitioner, Educational Clearinghouse, Inc. and Mail Masters of Tallahassee, Inc. In the subtotal for costs for 200,000 newsletter preparations, in activity four, concerning theoretical jobs, found within Petitioner's Exhibit B to the response to the invitation to bid, Petitioner made a mistake. It misplaced the decimal point and described the subtotal cost for 200,000 newsletter preparations as $73.80 instead of $7,380.00. Respondent characterized this as a typographical error or nominal mistake. In fact, this error constituted a minor irregularity which did not preclude the ability to understand Petitioner's response so that it might be compared to the responses by the competition. Petitioner made a second error. This error occurred when Petitioner failed to indicate the amount that it would charge per 1,000 for "Tabbing" within Exhibit A. Respondent did not consider this to be a minor irregularity and rejected Petitioner's bid as non-responsive for the failure to include a quotation for the charge per 1,000 for "Tabbing." This resulted in the intent to award the contract to Educational Clearinghouse, Inc. whose bid total for the four theoretical jobs under Exhibit B was $9,137.25 compared to Petitioner's bid total of $8,374.62. In preparing Exhibit B, activity four, Petitioner included a theoretical charge for "Tabbing" in the amount of $8.00 per 1,000. Petitioner contends that the $8.00 per 1,000 found within that entry may be correlated with the missing information concerning "Tabbing" in Exhibit A to its response to the invitation to bid. In the instructions to the vendors, Respondent has informed the vendors that the charge per thousand for individual items identified in Exhibit A constitutes the rate that the Respondent would expect to pay under a contract with the successful bidder. By contrast, the function of the information provided in Exhibit B is for purposes of awarding the contract based upon total costs of the four theoretical jobs and on the basis of the vendor's qualifications to best serve the Respondent's needs. Although not stated in the invitation to bid it can be inferred that similar references within Exhibits A and B, such as the reference to "Tabbing", calls for a comparable price to be set forth for the item in both Exhibit A and Exhibit B. Otherwise vendors would have the opportunity to quote low prices in completing Exhibit B as a means to win the cost comparison with their competitors for purposes of the award and then have the opportunity to charge higher costs per 1,000 as reflected in Exhibit A when establishing the charges for the contract with the Respondent following the competition contemplated in the comparison of the theoretical bid total under Exhibit B. Therefore, it would be reasonable for the Respondent to expect that the Petitioner would charge $8.00 per 1,000 for "Tabbing" under a contract between the Petitioner and Respondent based upon information that was set forth in the response to Exhibit B, activity four, "Tabbing." In summary, Petitioner's oversight in leaving out reference to the tabbing charge in Exhibit A does not affect the comparison of bid responses as contemplated by the instructions to the vendors, a function performed by comparing the respective Exhibits B. Otherwise, Respondent may gain the necessary understanding of Petitioner's charge per 1,000 for "Tabbing" as contemplated in instructions concerning Exhibit A as a means for entering into the contract. This understanding is achieved by transposing the $8.00 per 1,000 "Tabbing" quotation in Exhibit B to the "Tabbing" charge within Exhibit A as $8.00 per 1,000. With this adjustment, Modern Mailers, Inc. is the lowest responsive bidder and best able to serve Respondent's needs pertaining to Invitation to Bid No. 94-014, as revised.
Recommendation Based upon the findings of fact and the conclusions of law reached, it is, RECOMMENDED: That a final order be entered which finds that Petitioner is a "qualified" and "responsible" bidder who is the lowest and best responsive bidder to Invitation to Bid, No. 94-014, as revised and is entitled to the award of the contract contemplated by that invitation to bid. DONE and ENTERED this 8th day of September, 1994, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of September, 1994. APPENDIX The following discussion is given concerning the proposed findings of fact of the Parties: Petitioner's Facts: Paragraph 1 is subordinate to facts found. Paragraph 2 is not necessary to the resolution of the dispute. Paragraphs 3 through 5 are subordinate to facts found. Paragraphs 6 and 7 are rejected to the extent that they are intended to establish an excuse for the Petitioner not providing information related to the cost for tabbing called for in Exhibit A in the invitation to bid. Paragraph 8 is subordinate to facts found. Paragraphs 9 through 12 are not necessary to the resolution of the dispute. Paragraph 13 is subordinate to facts found. Paragraph 14 is rejected to the extent that it suggests that Petitioner may amend its response to the invitation to bid to specifically set forth the amount attributable to the tabbing charges per 1,000 in Exhibit A. Nonetheless one may infer that the cost per 1,000 for tabbing is the same as is set forth in Exhibit B. Paragraphs 15 through 17 are subordinate to facts found. Paragraph 18 constitutes legal argument. Respondent's Facts: Paragraph 1 is subordinate to facts found. Paragraph 2 is contrary to facts found Paragraph 3 is rejected in fact and law. Paragraph 4 is rejected in the suggestion that the Petitioner does not have the ability to perform the contract. COPIES FURNISHED: Daniel W. Dobbins, Esquire Callahan & Dobbins 433 North Magnolia Drive Tallahassee, FL 32308 Vytas J. Urba, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Jack McRay, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 George Stuart, Secretary Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Informational Copies: Ronald W. Brooks, Esquire Brooks and LeBoeuf, P.A. 863 East Park Avenue Tallahassee, FL 32301 Joan Reeves, Vice President Educational Clearinghouse Post Office Box 3951 Tallahassee, FL 32315
The Issue Whether Respondent has acted acted fraudulently, arbitrarily, capriciously, illegally, or dishonestly with regard to the intended award of ITB 93/94-040- LOT/P.
Findings Of Fact By correspondence filed July 18, 1994, this bid protest was referred to the Division of Administrative Hearings from the Department of Lottery for the conduct of formal proceedings pursuant to Section 120.53(5), Florida Statutes. The formal bid protest document consists solely of a single page letter signed by Petitioner's president, C. Whitside-Curry, basically stating that the letter is to serve as Petitioner's formal written protest to Respondent's "Notice of Award - Notice of Non-Responsiveness - ITB 93/94-040-LOT/P - Invitation To Bid for Painting the Interior of the Lottery Central Building. Final hearing in the matter was scheduled for August 2, 1994, in compliance with requirements of Section 120.53(5)(e), Florida Statutes, that bid protests be set for hearing within 15 days absent stipulation of the parties waiving that statutory time frame. By motion filed July 29, 1994, counsel for Petitioner sought a continuance of the final hearing for a period of one week. Counsel had just been retained by Petitioner. As reflected in Petitioner's motion, counsel's request for a one week delay was acceptable to counsel for Respondent, provided that: the 30 day time frame governing issuance of recommended orders in bid challenge cases was not waived. that deposition of a principal of Petitioner, C. Whitside-Curry, be held on August 3, 1994 at 11:30 a.m. and that certain documents also be produced. A telephone hearing on Petitioner's continuance motion was held on August 1, 1994, to clarify the hearing officer's understanding that a one week continuance of the final hearing would not subtract a period of one week from the 30 day time frame following the final hearing within which to prepare a recommended order in the case. Thereafter the motion was granted and final hearing rescheduled, as agreed in the telephone conference, for August 9, 1994, one week after the initial hearing date. By notice filed on August 3, 1994 (transmitted to Petitioner's counsel by facsimile transmission on July 29, 1994), Respondent documented the agreed upon deposition of C. Whitside-Curry and documents to be produced. By motion filed on August 3, 1994, subsequent to Respondent's notice, Petitioner's counsel sought a further continuance of the final hearing and noticed the unavailability of Petitioner's principal, C. Whitside-Curry, for the scheduled deposition on August 3 or the final hearing scheduled for August 9, 1994. By motion filed on August 3, 1994, subsequent to Petitioner's second motion for continuance, Respondent moved for imposition of sanctions, including the dismissal of the bid protest on the basis that Petitioner had not complied with conditions agreed to by the parties as a part of the one week continuance, i.e., C. Whitside-Curry did not appear for deposition and documents were not produced. The motion further related that Respondent's notice of the deposition and request to produce documents (filed on August 3, 1994) had been transmitted, as noted above, to Petitioner's counsel by facsimile transmission on July 29, 1994. In the course of telephone conference with the parties on August 8, 1994, Petitioner's counsel agreed to payment of costs related to court reporter expense incurred by Respondent at the deposition where Petitioner's principal failed to appear. Respondent's counsel refused to consent to further continuance of the final hearing and Petitioner's request for a second continuance was denied. At final hearing, consideration was given to an Petitioner's Amended Second Motion For Continuance. The motion differed from previous motions to the extent that an attached copy of a letter dated April 21, 1994, appeared to indicate that a mediation meeting in another legal proceeding required the Petitioners' presence in Tampa, Florida, on the afternoon of August 9, 1994. No direct admissible evidence of Petitioner's inability to attend the hearing was presented. Upon denial of the amended motion for continuance, counsel for Petitioner announced that he could not go forward.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the formal bid protest filed in response to Respondent's intent to award ITB 93/94-040-LOT/P, be DISMISSED. DONE AND ENTERED this 10th day of August, 1994, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 1994. COPIES FURNISHED: Curley R. Doltie, Esquire 1103 Hays Street P.O. Box 1325 Tallahassee, Florida 32302 Louisa Warren, Esquire Department of Lottery 250 Marriot Drive Capitol Complex Tallahassee, Florida 32399-4011 Marcia Mann Secretary Department of Lottery Capitol Complex Tallahassee, Florida 32399-4002 Ken Hart General Counsel Department of Lottery Capitol Complex Tallahassee, Florida 32399-4011 NOTICE OF RIGHT TO SUBMIT EXCEPTIONS All parties have the right to submit written exceptions to this recommended order. All agencies allow each party at least 10 days in which to submit written exceptions. Some agencies allow a larger period within which to submit written exceptions. You should consult with the agency that will issue the final order in this case concerning their rules on the deadline for filing exceptions to this recommended order. Any exceptions to this recommended order should be filed with the agency that will issue the final order in this case. ================================================================= DISTRICT COURT OPINION ================================================================= IN THE DISTRICT COURT OF APPEAL FIRST DISTRICT, STATE OF FLORIDA J C & C ASSOCIATES, INC., NOT FINAL UNTIL TIME EXPIRES TO FILE MOTION FOR REHEARING AND Petitioner, DISPOSITION THEREOF IF FILED vs. CASE NO. 94-3185 DOAH CASE NO. 94-3955BID DEPARTMENT OF LOTTERY, Respondent. / Opinion filed January 22, 1996. An Appeal from Order of the Department of Lottery. Curley R. Doltie, Tallahassee, for Appellant. Louisa H. Warren of Department of the Lottery, Tallahassee, for Appellee. PER CURIAM. AFFIRMED. ALLEN and KAHN, JJ., and SMITH, SENIOR JUDGE, CONCUR. MANDATE From DISTRICT COURT OF APPEAL OF FLORIDA FIRST DISTRICT To the Honorable Don W. Davis, Hearing Officer Division of Administrative Hearings WHEREAS, in that certain cause filed in this Court styled: J C & C ASSOCIATES, INC., Petitioner, vs. CASE NO. 94-3185 DOAH CASE NO. 94-3955BID DEPARTMENT OF LOTTERY, Respondent. The attached opinion was rendered on January 22, 1996. YOU ARE HEREBY COMMANDED that further proceedings be had in accordance with said opinion, the rules of this Court and the laws of the State of Florida. WITNESS the Honorable E. Earle Zehmer Chief Judge of the District Court of Appeal of Florida, First District and the Seal of said court at Tallahassee, the Capitol, on this 11th day of March, 1996. (SEAL) Jon S. Wheeler Clerk, District Court of Appeal of Florida, First District
The Issue Whether the Department’s action to reject all bids submitted in response to DOT-RFP-20-5003-DAA, relating to asbestos abatement, demolition, and removal services, is illegal, arbitrary, dishonest, or fraudulent.
Findings Of Fact Stipulated Facts (verbatim) The Department is an agency of the State of Florida tasked with procuring the services for Districtwide Asbestos Abatement and Demolition and Removal Services for Right of Way property under the Department’s supervision by law. The Department published a bid solicitation for DOT-RFP-20-5003- DAA, seeking bids to provide District Five Asbestos Abatement and Demolition and Removal Services for FDOT. The RFP included specifications, qualification requirements, instructions on what would be required of responders, a bid price proposal sheet, and the award criteria. Cross Construction and Cross Environmental submitted bids in response to the RFP. Cross Construction’s and Cross Environmental’s bids were evaluated by the Department. There is no debate, challenge, or disagreement raised in the Petitions with regard to the Technical Scores submitted by the responding firms to the RFP, only disagreement on three pay items. On June 15, 2020, the Department’s Selection Committee reviewed and discussed the information presented as to the Technical and Pricing scores of the Responding firms, asked for an additional bid item analysis, and indicated that it would reconvene at a future date for a decision. On June 22, 2020, the Selection Committee reviewed, discussed, and confirmed the recommendation presented by the results of the Technical Review Committee scorings and the Project Manager’s Bid Price analysis and selected Cross Construction and Cross Environmental as Intended Awardees. The Selection committee also found that Johnson’s Excavation and Services Inc., [Johnson] and Simpson Environmental LLC [Simpson] were deemed non-responsive due to irregular, and unbalanced pay items prices. On August 24, 2020, the Department’s Selection Committee decided to cancel the Procurement with the intent to readvertise with adjustments to the Scope and Pricing Structure and decided to reject all proposals. Additional Findings of Fact The “three pay items” referenced in paragraph six of the stipulated facts are the items that ultimately caused the Department to reject all bids in the instant dispute. The three pay items are collectively referred to as mobilization pay items. The RFP directs that bids are to contain two parts. Part I is the technical proposal, and Part II is the price proposal. Section 30.3 of the RFP provides that proposers “shall complete the Bid Price Proposal Form No. 2 and submit [the form] as part of the Price Proposal Package … [and that] [t]he Procurement Office and/or the Project Manager/TRC will review and evaluate the price proposals and prepare a summary of its price evaluation.” Five bidders submitted proposals in response to the RFP. One bidder did not advance beyond the initial review phase because its technical proposal did not meet minimum bid standards. The remaining bidders were CCS, CES, Simpson, and Johnson. Price proposals submitted by each of the remaining bidders were evaluated by the Department. Section 3 of the RFP provides a general outline of the process associated with awarding the contract. The steps are: “Pre-Proposal Conference; Public Opening (Technical Proposals); Price Proposal Opening & Intended Award Meeting; and, Selection Committee Meeting Summarizing Evaluations and Determining Anticipated Award.” The agenda for the “Price Proposal Opening & Intended Award Meeting,” as established by the RFP, provides as follows: Opening remarks of approx. 2 minutes by Department Procurement Office personnel. Public input period – To allow a reasonable amount of time for public input related to the RFP solicitation. At conclusion of public period, the Technical evaluation scores will be summarized. Announce the firms that did not achieve the minimum technical score. Announce the firms that achieved the minimum technical score and their price(s) as price proposals are opened. Calculate price scores and add to technical scores to arrive at total scores. Announce Proposer with highest Total Score as Intended Award. Announce time and date the decision will be posted on the Vendor Bid System (VBS). Adjourn. Section 30.4 b. of the RFP provides that a proposer can be awarded a maximum of 30 points for its price proposal. This section also provides that “[p]rice evaluation is the process of examining a prospective price without evaluation of the separate cost elements and proposed profit of the potential provider.” On June 15, 2020, the selection review committee met publicly for the purpose of opening price proposals and announcing an intended award. Price proposals were opened, and the eligible bidders received the following price scores: CCS - 11.09; CES - 13.22; Johnson - 19.76; and Simpson - 30. In terms of total score, which combined both the technical and price scores, Simpson received a score of 113.00, which was the highest score, followed by CES (107.55), CCS (103.76), and Johnson (101.76). After opening and considering the price proposals of the respective bidders, the selection committee did not announce an intended award at the meeting on June 15, 2020, but instead requested that the project manager “do further analysis on the pay items for any potential imbalance.” The project manager, through a staff member, performed the additional analysis and determined that Johnson and Simpson submitted “irregular, unbalanced pay items” which resulted in their respective bids being deemed non- responsive and thus not eligible for award. The “irregular, unbalanced pay items” are the three mobilization pay items at issue in the instant matter, and are identified on the bid price proposal sheet as items AB200, AB201, and AB202. Simpson bid $400 for item AB200, $100 for item AB201, and $50 for item AB202. Johnson bid $250 for item AB200, $250 for item AB201, and $100 for item AB202. CCS bid $1 for item AB200, $1 for item AB201, and $1 for item AB202. CES bid $1 for item AB200, 75 cents for item AB201, and 50 cents for item AB202. The Department, in evaluating the bidders’ mobilization pay items, considered costs associated with abatement two structures, a 1,500 and 2,250 square feet structure respectively. For the 1,500-square-foot structure, CCS’ AB200 mobilization costs totaled $1,500. For the 2,250-square-foot structure, CCS’ AB201 mobilization costs totaled $2,250. For the 1,500-square-foot structure, CES’ AB200 mobilization costs totaled $1,500. For the 2,250-square-foot structure, CES’ AB201 mobilization costs totaled $1,687.50. For the 1,500-square-foot structure, Johnson’s AB200 mobilization costs totaled $375,000. For the 2,250-square-foot structure, Johnson’s AB201 mobilization costs totaled $562,500. For the 1,500-square-foot structure, Simpson’s AB200 mobilization costs totaled $600,000. For the 2,250-square-foot structure, Simpson’s AB201 mobilization costs totaled $225,000. On June 22, 2020, the selection committee reconvened and announced CCS and CES as intended awardees of the contract. The Department also announced at this meeting that Johnson and Simpson were “deemed non- responsive due to irregular, unbalanced pay item prices.” On June 24, 2020, Simpson filed a Notice of Protest wherein the company informed the Department of its intent to formally protest the intended award of contracts to CCS and CES. On or about July 6, 2020, Simpson filed with the Department its “formal written petition of protest.” Although Simpson’s formal protest is dated July 6, 2020, CCS and CES contend that Simpson’s protest was actually filed on July 7, 2020, thereby making the protest untimely by a day. The Department did not refer Simpson’s formal protest to DOAH for final hearing, but instead considered the issues presented by Simpson in its protest and then attempted to negotiate a resolution with Simpson, CCS, and CES. Those efforts were unsuccessful. The question of the timeliness of the formal bid protest filed by Simpson is not before the undersigned. Nevertheless, the undisputed facts as to Simpson’s protest, as demonstrated by the record herein, are as follows. On June 24, 2020, Simpson filed notice of its intent to protest the RFP. On June 29, 2020, CCS received notice that a bid protest was filed with respect to the RFP. On July 1, 2020, CES filed a public records request “for public records related to the bid protest made to the” RFP. On or about July 6, 2020, Simpson filed its formal written protest with respect to the RFP, and although the evidence is not clear as to the date, it is undisputed that the Department received affidavits from Simpson explaining the factual circumstances surrounding the filing of the company’s formal written protest. On July 15, 2020, the Department notified CCS and CES that “in response to the Formal Written Protest filed by Simpson Environmental Services, the Department will hold a settlement conference” on Friday, July 17, 2020. On July 21, 2020, Simpson, CES, and CCS notified the Department that they “reached an agreed upon settlement proposal.” On August 11, 2020, the Department, after considering the settlement proposal for several weeks, notified Simpson, CES, and CCS that the Department would discuss the RFP at a public meeting to be held on August 24, 2020. As previously noted, it was during the meeting on August 24, 2020, when the Department announced that all proposals received in response to RFP were rejected. CES, on or about July 1, 2020, submitted to the Department a public records request wherein the company sought a copy of documents related to Simpson’s protest. In response to the request, the Department provided CES a copy of the formal written protest filed by Simpson. It is undisputed that the initial copy provided to CES by the Department did not show either the date or time of receipt of the document filed by Simpson. At some point after the settlement conference, the Department provided to CES a date and time stamped copy of Simpson’s formal written protest. There was no evidence presented explaining the circumstances or the process which resulted in the Department providing different copies of Simpson’s formal written protest to CES, and the remaining evidence does not provide a sufficient foundation to reasonably infer that the Department acted with nefarious motives when providing different versions of the documents to CES. Simpson’s formal protest contains the following statement with respect to the price proposal that the company submitted in response to the RFP: Petitioner’s individual bid price items were based in fact, were reasonable and were in conformity with standard industry rates for similar asbestos abatement and demolition and removal projects. Petitioner’s bid price items were also patently similar to bid price items that Petitioner has previously submitted in response to past FDOT proposal requests that ultimately resulted in the corresponding contracts having been awarded to Petitioner. Indeed, Petitioner has a longstanding relationship with the FDOT as Petitioner has previously contracted with FDOT as a vendor performing asbestos abatement services on numerous projects over the course of the past eight years. Petitioner’s price items for bid proposals have remained consistent for each of its past projects with FDOT. Petitioner’s price items for the instant bid proposal did not differ or vary in any material aspect from those proposed by Petitioner for previous projects that FDOT has deemed reasonable. Michelle Sloan works for the Department as a district procurement manager, and was assigned to manage the instant RFP. Ms. Sloan testified that because Simpson protested the Department’s intended decision to award the contracts to CCS and CES, and specifically referenced in its protest “that their bid for mobilization was in conformance with industry standards, as well as previous bids submitted to the agency that were deemed responsive,” she conducted additional review of the Simpson and Johnson bids. Ms. Sloan testified that after reviewing the RFP, the price sheets related thereto, Simpson’s protest, and the additional analysis of the pay items conducted following the June 15, 2020, selection committee meeting, she concluded that material ambiguities existed in the RFP’s mobilization pay items and recommended to the district secretary that the Department “reject all [bids] and re-advertise with a revised pricing sheet and instructions.” On August 24, 2020, the selection committee, following public notice, accepted Ms. Sloan’s recommendation, rejected all proposals, and canceled the procurement with the “intent to re-advertise with adjustments to the Scope and Pricing structure.” A review of the credible evidence demonstrates a rational basis for the conclusions reached by Ms. Sloan and members of the selection committee. Exhibit C of the RFP is titled “Price Proposal/Detailed and Contractual Price Sheet.” The first page of this document provides a general description of the asbestos removal and abatement pay items. The general pay items are as follows: AB100 Fees [as] determined from the Department of Environmental Protection based upon regulated material. AB200 One-time fee necessary to mobilize for full isolation, per parcel, when abatement with isolation is required. AB300 Fees to be charged by square feet for preparation [of] structure before abatement can commence. AB400 Fees to be charged by square feet, to abate asbestos from various surfacing material such as ceiling, walls, beams, plaster, sheetrock and fireproofing using conventional containment methods. AB500 Fees to be charged either by square foot, linear foot or fittings to abate asbestos from various mechanical systems such as boilers, stacks ducts, fittings, pipes, flutes and flanges. AB600 Fees to be charged either by square foot, linear foot or fittings to abate asbestos from various mechanical systems such as boilers, stacks, ducts, pipe, fittings and jackets which involve the use of a Glove bag. AB700 Fees to be charged by square foot, to abate asbestos from various roofing materials such as cement roof shingles, flashing, rolled roof, felts, wood shingles and mobile home coating. AB800 Fees to be charged by square foot or piece to abate asbestos from various materials such as floor tile, mastic adhesive, sheet vinyl, carpet, wood sub- floor, concrete sub-floor, vibrator dampers, wallboard, metal ductwork and sinks with insulation and heat shields (light fixture). AB900 Fees to be charge[d] by landfill for asbestos disposal. The bid price proposal sheet, which is form number 2 of the RFP, provides a listing of specific pay items related to the general “AB ---” items listed in Exhibit C to the RFP. Below is an example of some of the specific pay items listed on the bid price proposal sheet: [See table on next page] Item Number Description (A) Estimat ed Quantit y Unit (B) Unit Pric e Total Bid Amount (A x B) ASBESTOS REMOVAL ABATEMENT AB200 Mobilization for structures less than 2,000 Sq. FT. 1 SQ. FT. AB201 Mobilization for structures [from] 2001 – 5000 Sq. FT. 1 SQ. FT. AB202 Mobilization for structures over 5001 Sq. FT. 1 SQ. FT. AB300 Mask and Seal 1 SQ. FT. AB401 Remove ACM plaster/lathe including all surface materials 1 SQ. FT. AB501 Remove insulation from fittings 1 LF. AB603 Remove insulation from boilers, stacks or ducts piping 1 LF. AB703 Remove roofing cement 1 SQ. FT. AB810 Remove carpet and mastic adhesive 1 SQ. FT. AB820 Remove sinks with insulation 1 SQ. FT. AB901 Non-Friable 1 SQ. FT. General pay item category AB200, as described on Exhibit C, does not reference a “unit of measurement,” but instead notes that items within this category are to be determined on a “one-time – per parcel” basis. When the AB200 general pay item category is compared to the specific pay items for this category enumerated on the bid price proposal sheet (i.e., AB200, AB201, and AB202), it is evident that the unit of measurement “square feet” is listed as the basis for calculating the bid amount for this item when no such unit of measurement is stated for this item on Exhibit C. Comparatively, general pay item categories AB300 through AB800 each expressly references a specific unit of measurement (i.e., square foot, linear foot, or by the “piece”), and these units of measurement carry over to and are consistently reflected on the bid price proposal sheet for the specific pay items enumerated therein. By inserting a unit of measurement (i.e., square feet) in the mobilization pay items listed on the bid price proposal sheet, when the general description on Exhibit C instructs that they are “one-time, per parcel” pay items, the Department created a material ambiguity in the bidding process.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby Recommended that the Department of Transportation issue a final order in Case Nos. 20-4214 and 20-4216 finding that the rejection of all proposals in response to Request for Proposal RFP-DOT-20-5003-DAA was not illegal, arbitrary, dishonest, or fraudulent, and dismissing the two petitions. DONE AND ENTERED this 14th day of December, 2020, in Tallahassee, Leon County, Florida. S LINZIE F. BOGAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of December, 2020. COPIES FURNISHED: Douglas Dell Dolan, Esquire Florida Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0458 (eServed) Richard E. Shine, Esquire Florida Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399 (eServed) Brian A. Leung, Esquire Holcomb & Leung, P.A. 3203 West Cypress Street Tampa, Florida 33607 (eServed) Diane E. H. Watson, Esquire Cross Environmental Services, Inc. Post Office Box 1299 Crystal Springs, Florida 33524-1299 (eServed) Kevin J. Tibault, P.E., Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street, MS 57 Tallahassee, Florida 32399-0450 (eServed) Sean Gellis, General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0450 Andrea Shulthiess, Clerk of Agency Proceedings Department of Transportation Haydon Burns Building 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0450 (eServed)
Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made: In January of 1994, FDOT issued an Invitation to Bid ("ITB") for contracts FE2494Z1 and FE2494Z2 to provide storm shutters for the FDOT facilities in Zones 1 and 2 of the Florida Turnpike. The ITB was entitled "Storm Shutters, Removable, Manufacture, Furnish and Install." Prospective bidders for the contracts were provided with a packet which included General Conditions, Special Conditions, Specifications and General Special Provisions. The General Conditions set forth the procedures for submitting and opening the bids. The Specifications called for custom-sized removable storm shutters and detailed the materials and installation procedures that were required. The bid package contained the following pertinent language in the Special Conditions, Section 1.0, entitled "Description", and in the Specifications, Section 1.0, entitled "Scope of Work": Work under this contract consists of providing all labor, materials, equipment, tools and incidentals necessary to manufacture, furnish and install galvanized steel storm panels and accessories for all of Zone 1 & Zone 2 buildings and locations as identified in the building listing listings document, see Exhibit "A" Zone 1 & Exhibit "A" Zone 2. The bid package contained the following pertinent language in Special Conditions Section 8.1, entitled "Required Documents": Bidders are required to complete and return the State of Florida "Invitation to Bid" form as well as the bid sheet(s). These forms must be signed by a representative who is authorized to contractually bind the bidder. All bid sheets and the "Invitation to Bid" form must be executed and submitted in a sealed envelope. At a mandatory pre-bid conference on February 17, 1994, the Department's representatives were available to answer questions regarding the bid package. During the pre-bid conference, John Vecchio of the Department orally advised the prospective bidders that they should return the whole bid package, including the specifications, when they submitted their bid. No written amendment to this effect was issued. The bids were opened on March 3, 1994 in Fort Lauderdale. Bids were received for each contract from at least three bidders, including Accurate and Hurst. The apparent low bidder for both contracts was Broward Hurricane Panel Co. ("Broward"). Prior to the bids being posted on March 28, 1994, Broward's bid was determined to be nonresponsive and Broward was therefore disqualified. After Broward was disqualified, Accurate was the apparent low qualified bidder for Zone 2 and Hurst was the apparent low qualified bidder for Zone 1. Hurst's bid for the contract for Zone 2 was $85,000. Its bid for the Contract for Zone 1 was $36,000. Accurate's bids for the contracts were $84,854.82 and $36,287.16, respectively. Hurst was awarded the contract for Zone 1 and that decision has not been challenged. At the same time the Department announced the award of the Contract for Zone 1 to Hurst, the Department announced its intent to award the contract for Zone 2 to Accurate. Hurst timely filed a notice of protest and a formal written protest of the proposed award of the contract for Zone 2 to Accurate. Initially, FDOT raised as a defense that Hurst had not posted a protest bond as required by Section 287.042(2)(c), Florida Statutes. At the hearing in this matter, FDOT conceded that Hurst had subsequently posted a protest bond which had been accepted by FDOT. Hurst contends that Accurate's bid should have been deemed nonresponsive because Accurate does not have the ability to "manufacture" the specified product in its own facility. The 2 inch corrugated shutter required by the ITB has to be shaped on a special type of machine that rolls, presses and forms the metal. Hurst owns and maintains at its Opa-Locka facility a rolling mill capable of forming the panels to the bid specifications. Accurate is in the business of supplying the types of products sought by the ITB in this case. However, Accurate does not own the kind of machine necessary to shape the metal. The evidence established that for many years, Accurate has had a continuing business relationship with a local subcontractor, Shutter Express, that rolls, presses and forms raw material supplied by Accurate in accordance with Accurate's specifications. Shutter Express has the capability of fabricating shutters with a 2 inch corrugation in accordance with the ITB. Accurate is equipped to attach the headers and sills, drill the necessary holes, complete the assembly and install the final product. The ITB in this case did not preclude subcontracting any or all of the work specified. While the description of the work in the ITB includes the term "manufacture", this reference should not be read to mean that only those companies that were able to fabricate the entire product at their own facility could properly respond to the ITB. There is no logical justification for such a narrow interpretation. Only a few companies have the ability to completely fabricate the shutters on their own property. At the prebid conference, there was discussion amongst the prospective bidders about subcontracting the fabrication work and the FDOT representatives did not raise any objections to such an arrangement. It was widely understood by the parties present at the pre-bid conference that the Department was not interpreting the ITB in the restrictive manner now urged by Hurst. Such a reading of the ITB would have precluded from the bidding process a number of companies such as Accurate that routinely supply and install shutters. Hurst also contends that the bid proposal submitted by Accurate should be deemed nonresponsive because Accurate failed to include the entire ITB with its proposal in accordance with the oral instructions at the pre-bid conference. Hurst's proposals included the entire ITB. As discussed below, Accurate's proposal did not include the entire ITB. FDOT determined that all essential pages were included in Accurate's response and the evidence did not establish that this conclusion was arbitrary, capricious or fraudulent. Paragraph 6 of the General Conditions of the ITB provided: ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and affect and are inapplicable to the bid. As noted above, at the prebid conference held on February 17, 1994, an FDOT employee told all prospective bidders to return the entire bid package when making their submittals. This request that the entire bid package be returned was simply meant as a protection for the bidder to ensure that all the necessary documents referenced in Section 8.1 of the Specifications were submitted. Other than those documents referenced in Section 8.1 of the Specifications, FDOT had no interest in having the remaining portion of the ITB submitted with a proposal. Accurate's submittal contained every document required by Section 8.1 of the Specifications. Accurate's proposal did not contain pages 3 through 12, 14, 15 and 17 through 20 of the ITB, but did include pages 1 and 2, 13, 16, 21 and 22 along with a signed Form PUR 7068 and a signed acknowledgment of Addendum In other words, the submittal contained a signed and completed Bidder Acknowledgment, completed Bid Price Forms for Zones 1 and 2, a signed copy of Addendum #1, a completed copy of the Ordering Instructions, and a signed, but not notarized, statement regarding public entity crimes. 1/ In addition to the "REQUIRED DOCUMENTS," set forth in Section 8.1 of the Specifications and quoted in Findings of Fact 6 above, the ITB included Section 8.2, "PUBLIC ENTITY CRIMES STATEMENT" which provides: Any person submitting a bid or proposal in response to this invitation should execute the enclosed form PUR 7068, SWORN STATEMENT UNDER SECTION 287.133(A), FLORIDA STATUTES, ON PUBLIC ENTITY CRIMES, including proper check(s) provided, and submit it with the bid/proposal or within 72 hours of the bid opening. Page 7 of the ITB provided in pertinent part: 10.0 BID PREFERENCE IDENTICAL TIE BIDS - Preference shall be given to businesses with drug-free workplace programs. Whenever two or more bids which are equal with respect to price, quality and service are received by the State or by any political subdivision for the procurement of commodities or contractual services, a bid received from a business that certifies that it had implemented a drug-free workplace program shall be given preference in the award process. . . . Accurate's proposal did not include a certification that it was a drug-free workplace in accordance with this provision. However, such a certification is only used by the Department as a tie-breaker. In other words, in the event of identical bids, any firm with a drug-free workplace would get preference. Since there were no tied bids in this case, certification was totally irrelevant. When the bids were opened, Mary Bailey, the contracts administrator for the Department, noticed that Accurate's submittal was thinner than the others and asked Accurate's representative, Richard Johnson, about the remaining pages. Mr. Johnson replied that the other pages were in his truck and offered to retrieve them. Ms. Bailey told him there was no need to do so. Section 10 of the General Conditions in the bid package provides as follows: As the best interest of the State may require, the right is reserved...to reject any and all bids or waive any minor irregularity or technicality in bids received... It does not appear that Accurate has obtained any competitive advantage as a result of its failure to include the entire ITB with its bid proposals. Even if the oral instructions at the pre-bid conference are deemed to have modified the ITB so that the entire bid package should have been submitted, Accurate's failure to include the entire ITB with its response should be considered a minor technicality, pursuant to Section 10 of the General Conditions cited above, that can and should be waived in evaluating the responsiveness of the bid. Similarly, the failure to have the Form PUR 7068 notarized may have rendered Accurate's bid proposals incomplete, but not necessarily nonresponsive. This oversight can be easily corrected without giving Accurate a competitive advantage.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered finding the bid submitted by Accurate to be responsive and dismissing the challenge filed by Hurst. DONE and ENTERED this 24th day of June 1994, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June 1994.
The Issue Whether Respondent should sustain Petitioner's challenge to the preliminary determination to reject Petitioner's bid as not responsive to Respondent's Invitation to Bid No. SB 91C-284V and to award the contract to another bidder that submitted a higher bid?
Findings Of Fact Based on the record evidence, the following Findings of Fact are made: On March 12, 1991, Respondent issued Invitation to Bid No. SB 91C-284V (hereinafter referred to as the "ITB") through which Respondent solicited the submission of bids to supply Respondent with prestressed concrete poles for a one year period beginning May 16, 1991. The ITB was a multi-page document with various component parts. Bidders were instructed on the first page of the ITB to complete and "RETURN ONE COPY OF ALL BID SHEETS AND THIS [BIDDER ACKNOWLEDGMENT] FORM." They were advised elsewhere on the first page of the ITB that "[o]ne copy of all bid documents that ha[d] page numbers, and this executed Invitation to Bid [Bidder Acknowledgment] [F]orm [had to] be returned for the Bid to be considered." The advisement concerning the requirement that all numbered pages had to be returned for a bid to be considered was repeated at the bottom of each numbered page of the ITB. Directly beneath the Bidder Acknowledgment Form on the first page of the ITB was the following provision: This Invitation to Bid, General Conditions, Instructions to Bidders, Special Conditions, Specifications, Addenda and/or any other pertinent document form a part of this proposal and by reference are made a part thereof. The ITB further provided, among other things, that "[i]n the best interest of [Respondent], [Respondent] reserve[d] the right to reject any and all bids and to waive any irregularity in bids received." Petitioner and South Eastern Prestressed Concrete, Inc. (South Eastern) submitted the only bids in response to the ITB. In accordance with the ITB'S instructions, Petitioner completed and returned to Respondent the Bid Summary Sheet, on which it indicated its price offer. It also completed and executed the Bidder Acknowledgment Form and returned it, along with the entire first page of the ITB, to Respondent. Petitioner, however, failed to return, as part of its bid submittal, all of the numbered pages of the ITB. Omitted from Petitioner's submittal were numbered pages 3 and 4. These missing pages contained paragraphs A. through N. of the ITB's Special Conditions, which covered the following subjects: A. Scope; B. Delivery; C. Award; D. Term of Contract; E. Brand Name; F. Catalog Cuts; G. Estimated Quantities; H. Bid Exempt; I. Bidders Responsibility; J. Corrections; K. Joint Bidding, Cooperative Purchasing Agreement; L. Withdrawal; 1/ M. Minority Certification Application; and N. Public Entity Crimes. There was nothing on numbered pages 3 and 4 of the ITB that the bidder needed to fill out or sign. While paragraphs M. and N. of the ITB's Special Conditions did make reference to certain forms that the bidder had to complete and submit to Respondent, these forms did not appear on either numbered page 3 or numbered page 4. They were separate documents. Petitioner completed these forms and submitted them to Respondent pursuant to the requirements of the Special Conditions. Petitioner did not propose in its bid submittal any contract terms or conditions that were at variance with those set forth in paragraphs A. through N. of the ITB's Special Conditions. Petitioner did not intend to signify, by failing to return numbered pages 3 and 4, any unwillingness on its part to adhere to contract terms and conditions set forth on those pages. Of the two bids submitted in response to the ITB, Petitioner's was the lowest. A preliminary determination, though, was made to reject Petitioner's bid because Petitioner had not returned numbered pages 3 and 4 of the ITB and to award the contract to South Eastern as the lowest responsive bidder. It is this preliminary determination that is the subject of the instant bid protest filed by Petitioner.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Palm Beach County School Board enter a final order sustaining the instant bid protest and awarding to Petitioner the contract advertised in Invitation to Bid No. SB 91C-284V. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 24th day of June, 1991. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June, 1991.
Findings Of Fact Sometime before January, 1989, The Department of Health and Rehabilitative Services (HRS) requested and received approval from the Department of General Services (DGS) for additional office space to provide for social services in Haines City, Florida. HRS was authorized to procure, through competitive bidding, a lease of 9041 square feet of existing office space, plus or minus 3%. Public notice that HRS was seeking competitive bids was given by advertisement in four central Florida newspapers. HRS had prepared a document entitled Invitation to Bid for Existing Facilities (ITB), which set forth in detail all of HRS' requirements. The purpose of the ITB was to inform all potential bidders of the minimum requirements for submitting a responsive bid, and the specific criteria by which the bids would be evaluated. The evaluation factors and their relative weights were stated in the ITB: Evaluation Criteria The successful bid will be that one determined to be the lowest and best. All bids will be evaluated on the award factors enumerated below: Associated Fiscal Costs Rental rates for basic term of lease. Evaluated using present value methodology by application of the present value discount rate of % (Weighting: 30) Rental rates for optional renewal of terms of lease. Rates proposed are within projected budgeting restraints of the department. (Weighting: 5) Associated moving costs i.e. furniture, equipment, telephone systems, etc. (Weighting: 0) Location Proximity of offered space in central or preferred area of map boundaries. (Weighting: 10) Frequency and availability of satisfactory public transportation within proximity of the offered space. (Weighting: 5) The effect of environmental factors, including the physical characteristics of the building and the area surrounding it, on the efficient and economical conduct of the departmental operations planned for the requested space. (Weighting: 20) Facility Susceptibility of the design of the space offered to efficient layout and good utilization. (Weighting: 20) Provision of the aggregate square footage in a single building. Proposals will be considered, but fewer points given, which offer the aggregate square footage in not more than two locations provided the facilities are immediately adjacent to or within 15 yards of each other. (Weighting: 10) TOTAL POSSIBLE 100% The bid package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: rental rates environmental factors efficient space layout The above areas were important to HRS since the agency would render indigent services to several hundred people every month. The majority of Respondent's clients are served within a 10 day period each month. A great deal of pressure is placed on the surrounding area due to the influx of people. Because of servicing so many people, factors two and three received a great deal of weight under HRS's consideration of the property it desired to lease and occupy. All of the above areas were covered by Respondent's weighted bid evaluation criteria. Sealed bids were submitted by Intervenor, Unirealty Services, Inc. (bid A), and Petitioners, Messrs. Matthews and Walker (bid B). The bids were opened February 20, 1989, and Mr. Michael T. Akridge, former Facilities Services Manager, District VI HRS, determined both bids were responsive. At the time the Intervenors submitted their bid, they included documentation which showed that they had an option contract to purchase the subject facility, and an authorization from the optionees (two principals of Intervenors) for Unirealty to act as their agent. Both Petitioner's and Intervenor's property were within the mandatory geographical area designated in the bid package. Both bids were responsive under the minimum bid specifications and bidder qualifications. The District Administrator appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to him the committee's choice of lowest and best bid. The purpose in establishing the bid evaluation committee was to secure input from a cross section of people who had a variety of backgrounds and knowledge that would be material in evaluating the office space, in light of the uses for which it was intended and the relative public worth of the work space. Six individuals who were familiar with the type of work to be done in the proposed space, as well as persons familiar with the bid process were appointed to the Committee. The bid evaluation committee determined that the bid of Unirealty was the "lowest and best." The bid evaluation committee consisted of six representatives of the Department who visited each bidders' site and questioned the bidders' representatives. Each of the committee members worked with or supervised HRS programs that were to be located in the leased space. The solicitation for bids provided each bidder, among other things, with the bid evaluation criteria, a 100 point scale, which the committee used to evaluate the bids. Each committee member's evaluation scores were averaged and totaled to score Petitioners at 90.8, and Unirealty at 83.9. Each committee member gave a higher score to Unirealty. The three major bid evaluation criteria were FISCAL COSTS, LOCATION and FACILITY. Under the FISCAL COST criterion were three sub-categories: Rental Rates, Renewal Rates, and Moving Costs. For Rental Rates, Petitioners received 30 points out of 30 possible, and Unirealty got 23.1. For Renewal Rates, Petitioners got 5 out of 5 possible points, and Unirealty received 3.7 points. No points were awarded for Moving Costs. The evaluation committee did not assess points for Rental or Renewal Rates. These were scored by Michael T. Akridge, bid manager, based on a present value analysis of bidders' proposed rates. Mr. Akridge did not give the Committee the points for Rental and Renewal Rates until after they had completed their evaluations of the LOCATION and FACILITY criteria. The LOCATION criterion also had three sub-categories: Central Area-- 10 points--with both bidders receiving 9.3; Public Transportation--5 points-- which both bidders received; and, Environmental Factors--20 points--out of which Petitioners received 12.8 points and Unirealty 20 points. The Environmental Factors sub-category included building physical characteristics and surrounding area and their effect on the efficient and economical conduct of Department operations. Unirealty received a higher score than Petitioner because the committee believed its building had a better appearance, and was in better shape. The area surrounding the building was more open, while Petitioners' building was in a less desirable neighborhood with a bar or liquor store and bus station nearby which could create problems for clients because of transients. It had far more window space which creates a better work environment, and allows staff to be watchful of clients and their children outside, and the windows would be tinted. The windows at Petitioner's site were limited and no more could be added. Unirealty had more adjacent parking spaces, with handicapped parking closer to the building, and part of it was fenced which provided added protection to clients and staff. Petitioners' site had adjacent businesses whose patrons were using some of the parking spaces which the committee felt could create a problem. The Unirealty building could have an outside food stamp issuance facility which would be far more accessible to clients and to make the lobbies less crowded. It had an existing alarm system. It did not have side streets adjacent to the building, thus there would be less traffic congestion and therefore safer for clients; and, it had outside gathering areas where clients could go to smoke. Of the three sub-categories under FACILITY, Petitioners received 11.8 points out of 20 for Layout/Utilization and Unirealty received 19.7 points; for Single Building, both bidders received 10 points out of 10 possible. For the Layout/Utilization sub-category Unirealty received more points because its building configuration was more flexible and conducive to design of interior space, with less maze effect. The members of the committee each testified that it was important that the Unirealty building had no support poles to get in the way as they did in Petitioners' building. The support poles in Petitioner's building created a safety problem for clients and inhibited the location of desks and corridors. At Unirealty's site each worker could have a window, and mechanical and service areas could be put in the center of the building, with a playroom for clients' children. It provided a better restroom location near the front of Petitioner's building and lobby areas, and clients would not have to wander through work areas to get to the restrooms. Unirealty's building provided better control of clients' movements and thus better security. Members of the committee also upgraded the Unirealty building because its pitched roof was less likely to leak and its air conditioning was zoned thus providing better air quality and temperature control. At Unirealty there was better ingress and egress, and entry ways could be added. This could not be done at Petitioners' site. The Unirealty building could have different entrances for each HRS program, with separate lobbies for each program with less client congestion and better control. During the Committee members inspection of the sites they were told of an existing security alarm system already in place at the Unirealty site and were told that system would remain in place. When asked, the Petitioner's representative was unsure if his client would install a similar system at their site. A security system for the entire building was not included in the bid specifications, and it was improper for the committee to give Unirealty extra points for this unsolicited item. The proposed lease agreement calls for 9041 square feet of office space and a minimum of 66 parking spaces. Unirealty offered 72 parking spaces and Petitioner offered 75. The committee awarded more evaluation points to the Unirealty site based on future expansion capability of the building and the existing additional on-site parking spaces which were visible at the site at the time of inspection. The committee erroneously believed that the extra square footage of building space and extra parking spaces would necessarily be available to HRS if and when it might expand its offices. Future expansion was not in the bid specifications and it was clearly erroneous for them to have included this factor in their bid evaluation. The evaluation committee included the improper bid considerations in their evaluation of the Unirealty property. The two improper factors cannot be considered here. The unanimous recommendation of the evaluation committee was clearly to award the lease to the Intervenor. The evaluation committee based its decision on the scores attributed to each property on the Bid Synopsis sheet by the individual committee members. The committee utilized all the weighted bid criteria. However, two factors were of primary importance. One was its determination that the property offered by the Petitioners presented greater problems for design and flexibility due to the rectangular configuration of the building. The other consideration was that the physical characteristics of the Unirealty site and the surrounding area were considered far superior to the Petitioner's site. A close review of each evaluation sheet and the testimony of each committee member at the hearing shows that the improper factors were not so heavily weighted as to invalidate the committee recommendation. The reasons given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the Bid synopsis score sheets. The scoring was done by each member after inspection of the two buildings and without influence from the other committee members. In essence, the committee felt that Intervenor's property was the better property for the money. Importantly, every committee member came to the conclusion that Intervenor's property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a piece of property. On these facts, the individual scoring methods used by individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. Over an eight year period the Petitioner's rental cost was significantly lower than the Intervenor's. However, it is clear the legitimate considerations of the committee were crucial enough to override awarding the lease to the lowest bidder. The conclusion that the above factors can and do outweigh price and cost considerations in these facts is not an arbitrary and capricious decision, even though others may disagree with that decision. After the committee recommendation was scored and tabulated, Mr. Akridge requested the committee chair, Ms. Gail Newell, to prepare a draft letter of the proposed bid award. This was done in collaboration with the other committee members. Mr. Michael T. Akridge then prepared the bid award letter for the signature of the Administrative Services Director based on the draft letter. In it the two improper considerations were mentioned. The authority to award the lease to Unirealty was approved on March 8, 1989, by King W. Davis, Director of General Services for HRS based on the bid award letter, dated February 26, 1989.
Recommendation Based on the foregoing, the Hearing Officer recommends that the Secretary of the Department of Health and Rehabilitative Services enter a final order awarding lease number 590:2057 to Unirealty Services, Inc., as the lowest and best bidder. DONE and ENTERED this 21st day of July, 1989, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of July, 1989. APPENDIX Petitioner's Proposed Findings of Fact: The facts contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 12, 15, 23, 26, 27, 28, 30, 34, 38, 39 (in part), 40, 41, 42, 45, 46, 47, 48, 49, 50, 51, 53, 64, 65, 67, 69, 70, 71, 76, 77, 81, 83 (in part) are adopted in substance in so far as material. Paragraphs 14, 16, 17, 18, 21, 22, 24, 25, 29, 33, 36, 37, 73, 74, 80 are rejected as conclusions of law. Paragraphs 13, 19, 20, 44, 54, 59, 60, 61, 63, 68, 72, 75, 778, 82, are rejected as not supported by the evidence. Paragraphs 31, 32, 35, 43, 52, 55, 56, 57, 58, 62, 66 are rejected assubordinate or immaterial. Respondent's Proposed Findings of Fact: The facts contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17 are adopted in substance in so far as they are material. Intervenor's Proposed Findings of Fact: The facts contained in paragraphs 1-17 are adopted in substance in so far as they are material. COPIES FURNISHED: Edward D. Matthews, Jr. 2405 Hideaway Court Tallahassee, Florida 32303 Gregory L. Coler Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Jack Emory Farley, Esquire HRS District VI Legal Counsel 4000 West Buffalo Avenue, Room 500 Tampa, Florida 33614 Neal A. Sivyer, Esquire Paul J. Ullom, Esquire Shackleford, Farrior, Stallings and Evans, P. A. 501 East Kennedy Boulevard Suite 1400 Tampa, Florida 33601 Sam Power, Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building One, Suite 407 Tallahassee, FL 32399-0700 John Miller, Esquire Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building One, Suite 407 Tallahassee, FL 32399-0700
The Issue Whether, in issuing the Revised Recommendation/Tabulation for contracts for Items 1 and 3 for Invitation to Bid No. 15- 048E, Multifunctional Devices, Cost-Per-Copy, Respondent acted contrary to one or more governing statutes, rules, policies, or procurement specifications, or any combination thereof; and if so, for each such instance, whether the misstep was clearly erroneous, arbitrary or capricious, or contrary to competition.
Findings Of Fact On June 3, 2014, SBBC issued ITB No. 15-048E (the ITB) entitled "Multifunctional Devices, Cost-Per-Copy" for the provision and maintenance of copying devices during the contract term. The listed Submittal Requirements were: Manufacturer's Authorization Special Condition 8; Descriptive Literature Special Condition 6; and Material Safety Data Sheets Special Condition 16. A Bidder's Preference Statement was not identified as a Submittal Requirement. Section 4, Paragraph 2, of the ITB was entitled "TERM" and notified bidders that SBBC sought through the award of this bid to "establish a contract for the period beginning from the date of award and continuing through June 30, 2017." The Bid Summary Sheet found at Section 5 of the ITB requested bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months and for 36 months. Page 1 of the ITB contained a certification to be executed by each bidder's authorized representative which stated in pertinent part as follows: Bidder agrees to be bound to any and all specifications, terms and conditions contained in the ITB, and any released Addenda and understand that the following are requirements of this ITB and failure to comply will result in disqualification of bid submitted. All bidders submitted a signed bidder certification. Section 3, Paragraph 1(a), of the General Conditions of the ITB provided as follows: SEALED BID REQUIREMENTS: The "Bidder Acknowledgment Section" must be completed, signed and returned with the bid. The Bid Summary Sheet pages on which the Bidder actually submits a bid, and any pages, upon which information is required to be inserted, must be completed and submitted with the bid. The School Board of Broward County (SBBC) reserves the right to reject any bid that fails to comply with these submittal requirements. BIDDER'S RESPONSIBILITY: It is the responsibility of the Bidder to be certain that all numbered pages of the bid and all attachments thereto are received and all Addendum released are received prior to submitting a bid without regard to how a copy of this ITB was obtained. All bids are subject to the conditions specified herein on the attached bid documents and on any Addenda issued thereto. Section 3, Paragraph 6, of the General Conditions of the ITB provided as follows: AWARDS: In the best interest of SBBC, the Board reserves the right to: 1) withdraw this bid at any time prior to the time and date specified for the bid opening; 2) to reject any or all bids received when there are sound documented business reasons that serve the best interest of SBBC; 3) to accept any item or group of items unless qualified by Bidder; and 4) to acquire additional quantities at prices quoted on this ITB unless additional quantities are not acceptable, in which case, the bid sheets must be noted "BID IS FOR SPECIFIED QUANTITY ONLY." On June 18, 2014, SBBC issued Addendum Number 1 for the ITB which replaced a number of pages within the bidding documents and contained responses to questions posed by prospective bidders. Addendum Number 1 included Question No. 6 in which Xerox inquired whether SBBC "would . . . consider a change to the contract term of the contract to 48 or 60-month term?" SBBC responded through Addendum Number 1 that it had amended the bid "to include additional pricing for 48 or 60-months term[s]," and SBBC continued to request proposals for a 36-month contract term. Addendum Number 1 revised Section 4, Paragraph 2, of the Special Conditions of the ITB to state as follows: TERM: The award of this bid shall establish a contract for the period beginning from the date of award and continuing through an award for a term of 36, 48 or 60 months. Bids will not be considered for a shorter period of time. All prices quoted must be firm throughout the contract period. Items will be ordered on an as needed basis. Addendum Number 1 included an Appendix A–Summary Cost Sheet which required bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months, 36 months, 48 months, and 60 months. On June 20, 2014, SBBC issued Addendum Number 2 for the ITB. The first page of Addendum Number 2 advised prospective bidders, "This Addendum amends the above referenced bid in the following particulars only: 1. DELETE: Appendix A–Cost Summary Sheet INSERT: Revised Appendix A–Cost Summary Sheet." The first page of Addendum Number 2 further cautioned bidders that "[i]t is important to include the REVISED page when submitting your response." Addendum Number 2 went on to provide a Revised- Appendix A-Summary Cost Sheet which stated "A Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months" and included a cost summary sheet for each of those three options. The ITB and addenda numbers 1 and 2 were released by SBBC via Onvia DemandStar, with email notices thereof to prospective vendors who subscribed to its bid notification service. Toshiba downloaded the ITB, Addendum Number 1, and at least the first page of Addendum Number 2 from DemandStar prior to the submission of its bid to SBBC. Again, the first page of Addendum Number 2 cautioned bidders that Appendix A–Summary Cost Sheet had been deleted and replaced and that it was "important to include the REVISED page when submitting your response." No bid specifications protest was filed by any person or entity concerning the ITB or addenda numbers 1 or 2. On July 3, 2014, SBBC opened bids timely submitted in response to the ITB by: Toshiba; ImageNet; Innovative; Lexmark International, Inc.; and Ricoh. Konica had also presented a bid to SBBC in the bid opening room prior to the opening of bids but after the announced time for submittal of bids. The Konica bid was delivered to SBBC but was not opened at the time of the bid opening. Toshiba, the incumbent, was the only bidder that violated the pricing requirements of the ITB. The bid submitted by Toshiba utilized the version of Appendix A-Summary Cost Sheet that was released under Addendum Number 1 and only offered cost- per-copy pricing for the 60-month term option. Toshiba's bid did not submit the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, nor did it contain any bids offering cost per copy pricing to SBBC for the 36 or 48-month term options. Although Toshiba's bid was not rejected as non-responsive for failing to bid on the 36 and 48-month term options and for failing to utilize and complete the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, SBBC's staff later concluded in hindsight that it should have been rejected for such non-compliance. Toshiba's bid included a "Pricing" note immediately prior to its Appendix A–Summary Cost Sheet that stated: [Toshiba] is proposing a 60 month CPC as a response to the [ITB]. Based on the fact the [ITB] has no minimum, cancellation for convenience, ability to upgrade and downgrade with no penalty, it is in the best interest of our organization to bid a term of 60 months. This term allows us to provide the most aggressive price to the [SBBC] and maintain the excellent service and support level in place. SBBC's staff recommended that an award be made under the ITB for pricing offered for a 36-month contract term for Items 1, 2, and 3 for a contract period of August 6, 2014, through September 30, 2017. On July 10, 2014, SBBC posted its initial ITB Recommendation/Tabulation which did not consider the Konica bid. The initial posted Recommendation/Tabulation notified bidders of SBBC's intended award of contracts for Items 1 and 2 to ImageNet as the primary awardee and to Innovative as the alternate awardee for a contract period of August 6, 2014, through September 30, 2017, and recommended the award of contracts for Item 3 to Ricoh as primary awardee and to ImageNet as alternate awardee for a contract period of August 6, 2014, through September 30, 2017. Timely bid protests and bid protest bonds were filed by Konica and by Toshiba concerning SBBC's initial Recommendation/Tabulation of July 10, 2014. SBBC's Bid Protest Committee conducted a meeting with the protestors on August 26, 2014, and determined that Konica's bid had been timely submitted and directed SBBC's Procurement and Warehousing Services Department (the Department) to evaluate Konica's bid for responsiveness. It also directed the Department to revise its recommendation on the ITB to reject Toshiba's bid for Item 2 as the device offered by Toshiba for that item did not meet the ITB's specifications which called for a single device capable of performing 95 copies per minute (cpm) and Toshiba instead offered two devices that performed at 85 cpm. After reviewing Konica's bid for responsiveness, SBBC posted a Revised Recommendation/Tabulation for the ITB on August 29, 2014, which (a) recommended award of Item 1 to ImageNet for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to Innovative as the alternate awardee; (b) recommended award of Item 3 to Ricoh for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to ImageNet as the alternate awardee; and (c) recommended the rejection of Toshiba's bid for Item 2 for its failure to meet the specifications for that Item. On September 4, 2014, Toshiba timely filed its notice of intent to protest the August 29, 2014, posted Revised Recommendation/Tabulation. On September 15, 2014, Toshiba timely filed its Amended Formal Petition Protesting Proposed Revised Recommendation/Tabulation. SBBC's Bid Protest Committee conducted a meeting with Toshiba on November 5, 2014, pursuant to section 120.57(3), SBBC Purchasing Policy 3320, and the ITB, and rejected Toshiba's bid protest. On November 10, 2014, Toshiba timely requested that SBBC forward its bid protest to DOAH for a formal hearing. Toshiba has presented a number of arguments in these proceedings seeking to avoid the circumstances Toshiba created for itself when it failed to comply with Addendum Number 2 and violated the ITB's pricing requirements and the ITB's requirement as to the term of the contract to be awarded, when Toshiba only submitted a single bid and restricted the contract term for which it would be considered to 60 months. First, Toshiba attempts to divest SBBC of its express authority to select proposals for any contract duration for which it solicited bids other than for a month term. Second, Toshiba argues that SBBC was somehow obligated to specify within the bid specifications those business considerations that would inform SBBC's selection of the duration of the contract term to be awarded under the ITB. Third, Toshiba argues that ImageNet was non-responsive regarding the ITB's specifications concerning manufacturer's certifications. Toshiba also argues that all bidders, including itself, were non- responsive with regard to the ITB's specifications regarding bidding preference laws. None of the arguments presented by Toshiba in opposition to SBBC's intended award of Items 1 and 3 are persuasive. The Selection of the 36-Month Term SBBC's recommended award for a 36-month contract period from October 7, 2014, through November 30, 2017, is consistent with the terms and conditions of the ITB and its addenda. At the very start of this competitive solicitation, SBBC informed bidders through Section 4, Paragraph 2, of the ITB and the Bid Summary Sheet at Section 5 of the ITB that it was seeking a contract through June 30, 2017-–i.e., a 36-month contract. SBBC also made it clear in its response to Question No. 6 of Addendum Number 1 that "[t]he contract will be for a full 36 months." Although SBBC revised the bid specifications through Addendum Number 1 to allow bidders to submit "additional pricing for 48 and 60 months term[s]," "to allow the School District to consider a 48 and/or 60 months term contract," and revised Section 4, Paragraph 2, of the ITB to provide for "an award for a term of 36, 48 or 60 months," it was clear under the ITB that SBBC contemplated that a 36-month contract could serve its needs. Addendum Number 2 further revised the bid specifications by providing the Revised–Appendix A–Summary Cost Sheet which informed bidders that "a Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months." SBBC intended to review the additional pricing offered for 48 and 60- month contract terms to determine whether those particular options were a better business decision for SBBC. Several factors were considered by SBBC in selecting the contract duration for the award under the ITB. The selection of the shorter 36-month contract term was consistent with the expressed terms of the ITB and addenda and the expressed preference of SBBC's governing board to refrain from entering into long-term contracts and enabled SBBC to be flexible in finding solutions to its copying needs and to take advantage of changes that may arise in technology; avoided problems the school district was currently experiencing with a long-term cost-per- copy contract which ranged from equipment performance issues to the long-term placement of technology in schools; and enabled the school district to conduct research to determine whether future implementation of a managed print solution would provide the school district with additional cost savings or financial benefits in contrast to the cost-per-copy services being procured through the ITB. Clearly, this selection was neither arbitrary nor capricious. SBBC's elected governing board has made it known by its actions taken at public meetings that it disfavors long-term contracts for the procurement of goods and services and has gone so far as to reduce the term of contracts from the dais. SBBC's staff determined that the pricing offered to SBBC for a 60-month contract term was not significant enough to recommend a contract longer than the 36-month term SBBC had been requesting since the release of the ITB. Any cost advantages offered by Toshiba's bids for Items 1, 2, and 3 were reduced by $525,000 per year due to the disqualification of its bid for Item 2, which failed to meet the ITB's specifications. Consideration of Managed Print Services Xerox Corporation informed SBBC that a managed print services (MPS) program could save millions of dollars per year and later submitted a no bid response to SBBC regarding the ITB because SBBC was not implementing a MPS program under the ITB. SBBC had also received proposals from vendors in October 2013 concerning a MPS program and concluded that there existed a potential annual savings of millions of dollars if such a program could be implemented. All of which were additional reasonable, rational reasons for SBBC to remain consistent with its decision to award the contracts for a term of 36 months and not something longer. The ITB contains standard terms and conditions which enable SBBC to terminate an awarded contract regardless of reason and with or without cause upon 30 days written notice to the other party. Toshiba wants SBBC to rescue Toshiba from its failure to submit required bids for 36-month and 48-month periods by forcing SBBC to award a contract obligating the agency for a longer duration under the ITB than desired by the agency and then have SBBC terminate the 60-month contract award for convenience after 36 months. SBBC includes termination for convenience provisions within its contracts for goods and services due to section 1011.14, Florida Statutes, which restricts the ability of district school boards to obligate public funds for a period beyond one year. The inclusion of the standard termination for convenience clauses in its ITBs enables SBBC to enter into contracts exceeding one year which affords the school district opportunities to obtain continuity of service and price advantages that would not be available under shorter contracts. While SBBC has the ability under the ITB to terminate contracts for convenience upon 30 days' notice, it rarely does so. SBBC has never exercised its right to terminate its two prior contracts for the services sought under this ITB. Any such termination requires action by SBBC's governing board during a public meeting. SBBC's staff would not engage in the sham of recommending a contract to its governing board for a contract term longer than the period for which it intends to procure services from a vendor. SBBC's procurement staff believes that using the termination for convenience clause in the manner Toshiba recommends can have an adverse effect upon the school district's ability to encourage bidders to participate in its competitive solicitations or to offer it their best pricing. Questions 1 and 59 of Addendum Number 1 of the ITB provide evidence of concern within the bidding marketplace that SBBC might exercise its termination for convenience clauses with regard to the services being procured under the ITB and support the perception of SBBC's that it should avoid a reputation for exercising such termination authority. Toshiba argues that SBBC somehow materially misled bidders through the ITB by stating in response to Question No. 3 concerning MPS of Addendum Number 1 that: The School District is not planning to implement a Managed Print Services at this time. The School District would like to receive Additional information regarding other districts that have implemented a Managed Print Services. There are no evaluation points associated with this ITB. SBBC's responses to Question No. 3 of Addendum Number 1 were accurate and did not mislead bidders. Toshiba is the only bidder to claim to have been misled. Section 6, Paragraph 10, of the ITB requested bidders provide SBBC with information about how the awardee could transition SBBC to a MPS model from the cost-per-copy model being offered under its bid. While SBBC requested such information from vendors within the bidding marketplace, there is no evidence that any bidder's provision or omission of such information within its bid submission was considered in the selection of the recommended awardees. In fact, ImageNet was recommended for award even though it did not provide this ancillary information about transition to a MPS delivery model. Rather, the recommended awardees for a 36-month contract term for Items 1 and 3 were determined solely on the basis of cost submitted for those items by the bidders, all in accordance with the ITB. A MPS program was a possible initiative being considered by SBBC's former Chief Information Officer prior to his departure from SBBC in February 2014, at which time the school district's current cost-per-copy contract was nearing its expiration. Although SBBC still had an interest in the possibility of a MPS program, it was not going in that direction at the time it needed to release a bid for copying services to replace its current expiring contract. Toshiba contends that SBBC was somehow required to disclose to bidders whether the potential future implementation of a MPS program might impact the contract award period that SBBC might choose under the ITB. A myriad of business considerations may inform an agency in selecting the length of its contracts for goods and services, and there is no law or rule that requires an agency to specify those factors within an ITB. Responsiveness of the Bidders Toshiba has attempted to argue that ImageNet, the recommended awardee for Item 1 and the alternate awardee for Item 3, was somehow non-responsive under the ITB and ineligible for award. In support of this argument, Toshiba has referenced Section 4, Paragraph 8, of the Special Conditions of the ITB which state as follows: MANUFACTURER'S CERTIFICATION: Bidder must submit with their ITB a notarized letter from manufacturer certifying that bidder is authorized to sell, service and warrant the multifunctional devices offered within this ITB. Failure of the bidder to provide this letter with their submitted bid or upon request shall result in disqualification of entire bid. If the bidder is the manufacturer, then bidder should state that their company is the manufacturer of the equipment provided in this bid (the letter does not need to be notarized). A bid is only disqualified under Section 4, Paragraph 8, of the ITB if (1) a notarized manufacturer's letter is omitted from the bid; and (2) the bidder fails to comply with a subsequent request from SBBC to provide the letter. No bidder, including Toshiba and ImageNet, included a notarized letter from a manufacturer with its bid. SBBC did not request any of the bidders to submit a notarized manufacturer's letter at any time after the submission of bids. As a result, none of the bids, including that of ImageNet, was non-responsive for a failure to satisfy Paragraph 8 of Section 4 of the ITB. Toshiba has also argued that all bids should be rejected due to Section 3, Paragraph 1(d), of the General Conditions of the ITB which concerns bidders' preference laws and states as follows: d) BIDDING PREFERENCE LAWS: ALL BIDDERS MUST COMPLETE AND SUBMIT THE LEGAL OPINION OF BIDDER'S PREFERENCE FORM IN ORDER TO BE CONSIDERED [sic] FOR AWARD. The State of Florida provides a Bidder's preference for Florida vendors for the purchase of personal property. The local preference is five (5) percent. Bidders outside the State of Florida must have an Attorney, licensed to practice law in the out-of-state jurisdiction, as required by Florida Statute 287.084(2), execute the "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form and must submit this form with the submitted bid. Such opinion should permit SBBC's reliance on such attorney's opinion for purposes of complying with Florida Statute 287.084. Florida Bidders must also complete its portion of the form. Failure to submit and execute this form, with the bid, shall result in bid being considered "non-responsive" and bid rejected. No bidder, including Toshiba, included an "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form with its bid. Each bidder's omission of that form was for good reason. Section 3, Paragraph 1(d), of the General Conditions of the ITB is a boilerplate provision within SBBC's standard bidding documents that is included pursuant to section 297.084(2), Florida Statutes, for any competitive solicitations in which personal property is to be purchased by SBBC. In instances in which it solicits bids to purchase personal property, SBBC includes a "Bidder's Preference Statement" form and includes that form among the checked "Submittal Requirements" listed in Section 2, Page 1, of the ITB. This ITB did not include a "Bidders Preference Statement" form among the bidding documents or list it as one of the required submittals. The state law and the boilerplate provision at Section 3, Paragraph 1(d), of the General Conditions of the ITB are only applicable to competitive solicitations for the purchase of personal property and do not extend to competitive solicitations for the purchase of services. As Section 4, Paragraph 12, of the Special Conditions of the ITB makes it clear that the multi-functional devices to be provided by the awardee under the ITB will "remain the property of the vendor," the standard bidder's preference provision contained within the ITB is plainly inapplicable to this procurement.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a final order that adopts the Findings of Fact and Conclusions of Law contained herein, dismisses the protest filed by Toshiba Business Solutions (USA), Inc., and upholds the awards of contracts under the procurement for a 36-month term from October 7, 2014, through November 30, 2017, to ImageNet Consulting of Miami, Inc., as the primary awardee for Item 1 and to Innovative Software Solution, Inc., as the alternate awardee for Item 1, and to Ricoh USA, Inc., as the primary awardee for Item 3 and to ImageNet Consulting of Miami, Inc., as the alternate awardee for Item 3. DONE AND ENTERED this 15th day of June, 2015, in Tallahassee, Leon County, Florida. S MARY LI CREASY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of June, 2015. COPIES FURNISHED: Robert Paul Vignola, Esquire Office of the General Counsel Eleventh Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) William G. Salim, Jr., Esquire Moskowitz, Mandell, Salim and Simowitz, P.A. 800 Corporate Drive, Suite 500 Fort Lauderdale, Florida 33334 (eServed) Eric J. Rayman, Esquire Genovese, Joblove and Battista, P.A. PNC Center, Suite 1110 200 East Broward Boulevard Fort Lauderdale, Florida 33301 (eServed) Albert E. Dotson, Esquire Wendy Francois, Esquire Bilzin, Sumberg, Baena, Price and Axelrod, LLP 1450 Brickell Avenue, Suite 2300 Miami, Florida 33131 (eServed) Matthew Mears, General Counsel Department of Education Turlington Building, Suite 1244 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed) Robert W. Runcie, Superintendent Broward County School Board Tenth Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) Pam Stewart Commissioner of Education Department of Education Turlington Building, Suite 1514 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed)
Findings Of Fact On or about June 3, 1987, DOT advertised that it would receive bids on State Project No. 97870-334, etc. in Dade, Broward and Palm Beach Counties to improve portions of the Florida Turnpike. On June 24, 1987, bids were received by DOT from Gilbert, State Paving and Archer Western Contractors. The apparent low bidder at bid opening on June 24, 1987, was Gilbert and State Paving was apparent second low bidder. DOT was informally advised by John Beck, an attorney representing State Paving, that Gilbert's bid was believed to be unbalanced and the appropriate officials referred the issue to the DOT Bureau of Estimates to look into the low bid to see if it was unbalanced to the detriment of the State. Review of the Gilbert bid began with an internal analysis of the bid prices in comparison to the DOT Estimate of the Work. All bid prices above or below a certain percent of the engineer's estimate of costs were prepared in a computer printout and those items were checked by the consultants on the project. Basically, the major items in the project, which comprises some 400 bid items, were broken down to 10 groupings and the bids for each item in these groups was prepared for the three bidders and tabulated in Exhibit 2. The DOT Technical Committee reviewed the bids and concluded there was no unbalancing in Gilbert's bid which was detrimental to the State. This recommendation was approved by the Awards Committee which had also been furnished the information in Exhibit 2 by the consulting engineer for the project. Based upon this information, the Awards Committee concluded that the awards should go to Gilbert as no unbalancing detrimental to the State was found. Specification made a part of all DOT bid proposals provide that DOT may reject an unbalanced bid. As a matter of policy, DOT only rejects unbalanced bids deemed contrary to the interests of the State. Bids may be unbalanced in numerous ways. One significant method is known as front loading where the bidder submits a high bid for the work to be done at the beginning of the project such as clearing and grubbing and low bids for the work done later in the project. If successful in getting the award, this bidder would have excess profits on the clearing and grubbing which could draw interest while the less profitable later work was being done. Another variant is to study the plans and specifications to see if the quantities listed in the bid proposal are accurately reflected in the plans and specifications. If not, those items for which the bid proposal shows more than the plans and specifications reasonably required can be bid low, and for those items by which the bid proposal shows less than actually will be required can be bid high. Since the contractor is paid by the units used, those excess units at a higher price would result in more profit for the contractor yet allow him to submit an overall lower bid. For example, if the bid proposal contains two similar items for which the request for proposal estimates 100 each will be required, and the bidder concludes that only 50 will be required at Site A and 150 at Site B, he submits a low bid for Site A and a high bid for Site B. If the fair price for these units is $10 each, and the bidder bids $5 per unit for Site A or $500, and $15 for Site B or $1500, the total bid price is $2000, but if the bidder only installs 50 at Site A he would be paid $250 and install $150 at Site B for which he would be paid $2250. His total compensation would be $2500. In competitively bid contracts, such as the instant project, contractors modify their prices by taking a calculated risk that certain items bid on will not need to be accomplished and submit a nominal bid of $1 or 1 cent for such an item. By definition, such a bid is unbalanced, but if the item so bid has to be provided, the contractor has to provide this service at the bid price. The only evidence submitted by Petitioner tending to show Gilbert's bid was unbalanced to the detriment of the State was testimony, objected to and sustained, that the plans and specifications showed more of certain units would be needed than the estimated quantities on the bid proposal, which constituted the basis for the bids submitted. Such evidence constitutes a challenge to the bid specifications and is untimely. Gilbert's witness who prepared the bid submitted by Gilbert adequately explained the basis for bids submitted by Gilbert on the challenged items. The document entitled "This is Not an Addendum," clearly states on its face that "an addendum may follow containing the following information." No bids are solicited thereby and for no item contained thereon is the State obligated to contract. This document was provided all bidders before bids were open and no unfair advantage to anyone or detriment to the State was shown. In a project containing some 400 bid items, many modifications of the contract during construction is required to cover unforeseen circumstances that arise. While it would be better to get competitive bids on every bit of work done on this project, in this imperfect world unforeseen items will appear. The document complained of attempts to alert the bidders to some anticipated work not foreseen when the bid proposal was prepared, but it is not a part of the bid solicitation.