Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
MORRIS HARVEY AND IRENE HARVEY vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003869 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003869 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57
# 1
MICHAEL L. PEMBERTON, ET AL. vs. TRIANGLE CONSTRUCTION ROAD BUILDING, INC., 85-000621 (1985)
Division of Administrative Hearings, Florida Number: 85-000621 Latest Update: Jul. 03, 1985

Findings Of Fact On January 23, 1985, following the filing of the and its on-site inspection, DER issued its notice of intent to grant the air construction permit, pursuant to Chapter 403, Florida Statutes (F.S.), and Chapters 17-2 and 17-4, Florida Administrative Code (F.A.C.). The notice stated that the proposed equipment, with a cyclone primary dust collector followed by a Dustex Baghouse Model DW-14-28W dust collector, was adequate to insure compliance with DER particulate emission standards. The ambient air standards for sulfur dioxide emissions by the plant were to be controlled by the use of low sulfur fuel oil (maximum 0.5 percent sulfur). Subsequent to the issuance of the notice of intent, DER received a Petition for Administrative Hearing regarding the issuance of the permit. The petition alleged, inter alia, that the plant would emit particulates and gases in contravention of Chapter 17-2, F.A.C., and that stormwater run-off from the plant would be contaminated with oil, scum and debris. The petition further asserted that this run-off would cause water pollution in contravention of Chapters 17-3 and 17-25, F.A.C., and would introduce pollution into Dry Branch and Bayou George, a Class I Water. The permit application covers only the proposed batch plant site and the immediately adjacent property consisting of 2.15 acres. The location of the building would be at the northern end of the parcel, approximately 0.10 miles from both Star Avenue and U.S. Highway 231. There is no residential use of property immediately adjacent to the project site. However, Petitioners all reside in the immediate area, and will be affected to some extent by this facility. Dust from construction activity has already been experienced. In this regard, it must be recognized that the area has no zoning restrictions and is therefore subject to industrial uses such as that proposed here. The Applicant owns several acres of property surrounding the location of the proposed batch plant. The permit application at issue covers only the request to construct the facility on a 2.15 acre portion of the larger parcel. Anticipated environmental problems caused by activity not on the immediate parcel are not related to this permit application and thus are not germane to a determination whether the permit should be issued or denied. Further, the construction permit will only allow the applicant to build the proposed air pollution source. Before such a source can actually be operated, a separate operation permit application must be made, and testing for compliance with standards by the facility must be satisfactorily completed. Petitioners demonstrated that the individuals who own Triangle Construction Company, Inc. were previously employed by Gulf Asphalt Company, which was occasionally out of compliance with state air emission standards. Petitioners asserted that these individuals would likely fail to operate the proposed facility in compliance with DER standards. Although these individuals did have managerial responsibility at Gulf Asphalt, final decisions concerning financial expenditures for repairs and maintenance were made by the owner of the plant, rather than the Applicant's owners. It was also established that the Gulf Asphalt Plant continued to have emission problems after such individuals left as employees. Petitioners contend the Applicant's unrelated dredging activities in an adjacent borrow pit area caused turbidity in Dry Branch Creek, and characterized the Applicant as a habitual violator who could not be expected to comply with state pollution control regulations in the operation of the proposed facility. Testimony revealed that the Applicant constructed a culvert in Dry Branch, which flows through a borrow pit area and did some other incidental dredging in areas within the landward extent of waters of the state. However, when the Applicant became aware that activities in the proposed borrow pit area were potentially in violation of DER rules, it ceased activities and applied for the appropriate permits. An asphalt concrete batch plant is a relatively simple operation in which sand and aggregate are dried, then mixed with hot liquid asphalt and loaded directly into trucks. It is the drying process which emits the particulates which the cyclone and the baghouse are designed to control. Baghouse operations are similar to those of a vacuum cleaner. Particulate-laden air from the drying process is vented into the baghouse, where it is filtered through a number of cloth bags. The bags trap the particulates, and pass the filtered air through the bag cloth and out of the building. When enough air has been filtered to cause a build-up of trapped particulates, a portion of the baghouse is taken off cycle and reverse air is blown through the bags. The reverse air causes the trapped particulates to fall into a hopper where they are removed for disposal. The baghouse was designed to function efficiently in conjunction with a plant producing up to 120 tons per hour of asphalt concrete. Applicants's plant will produce only 80-85 tons of asphalt concrete per hour due to the limited size of the dryer. The estimated air to cloth ratio in the amended permit application is 6:1, which will result in emissions substantially lower than DER standards. Air to cloth ratio is not a specific standard or requirement, but is a figure which is used by engineers to determine projected emissions which may reasonably be anticipated from facilities which use an air pollution control mechanism. A projected air to cloth ratio of 6:1 for this baghouse may be reasonably expected to yield emissions of approximately 0.014 micrograms per dry cubic foot, which is approximately one-third of the DER standard of 0.04 mg. per dry cubic foot. The equipment to be installed is used and in need of minor repairs. The testimony established that necessary repairs will be accomplished prior to plant activation, and that operations will not be adversely affected when such repairs are complete.

Recommendation Based on the foregoing, it is RECOMMENDED that the Department of Environmental Regulation issue a final order granting Triangle Construction Company an air construction permit. DONE and ENTERED this 21st day of June, 1985, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of June, 1985. COPIES FURNISHED: Lynn C. Higby, Esquire BRYANT, HIGBY & WILLIAMS, P.A. Post Office Box 124 Panama City, Florida 32402 E. Gary Early, Esquire and Clare E. Gray, Esquire Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32301 Richard Smoak, Esquire SALE, BROWN & SMOAK Post Office Box 1579 Panama City, Florida 32402 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blairstone Road Tallahassee, Florida 32301

USC (1) 40 CFR 60.90 Florida Laws (2) 120.57403.087
# 2
ELMORE FUTSCHER AND MARTHA FUTSCHER vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003867 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003867 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57
# 3
FLORIDA POWER CORPORATION vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 96-005344 (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Nov. 13, 1996 Number: 96-005344 Latest Update: Jan. 13, 1999

The Issue The issue in this case is whether Petitioner should be issued an air construction permit authorizing its Crystal River steam generating plant Units 1 and 2 to co-fire a five to seven percent blend of petroleum coke with coal.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background Petitioner, Florida Power Corporation (FPC), is an investor-owned public utility engaged in the sale of electricity to approximately 1.2 million customers. Among others, it operates the Crystal River Power Plant consisting of five electric-generating units in Citrus County, Florida. Units 1, 2, 4, and 5 are coal-fired, while Unit 3 is a nuclear unit. Respondent, Department of Environmental Regulation (DEP), is a state agency charged with the statutory responsibility of regulating the construction and operation of business enterprises in a manner to prevent air pollution in excess of specified limits. Among other things, DEP issues air construction permits for a limited period of time to undertake and evaluate initial operations of a business enterprise; long- term approval subsequently is available under an air operation permit. As a part of this process, and pursuant to federal law, DEP engages in a Prevention of Significant Deterioration (PSD) review to determine if non-exempt alterations to major facilities result in net emission increases greater than specified amounts. Under certain conditions, however, the use of alternative fuels or raw materials are exempted from PSD review. Intervenor, Legal Environmental Assistance Foundation, Inc. (LEAF), is a non-profit Alabama corporation licensed to do business in the State of Florida. It is a public interest advocacy organization whose corporate purposes include securing environmental and health benefits from clean air and water. Intervenor, Sierra Club, Inc. (Sierra Club), is a public interest advocacy organization incorporated in California and doing business in Florida. Its corporate purposes include securing the environmental and health benefits of clean air and water. On December 26, 1995, FPC filed an application with DEP for an air construction permit authorizing it to burn a blend of petroleum coke and coal in its existing coal-fired Units 1 and 2 at the Crystal River Power Plant in Citrus County, Florida. In the application, FPC did not address PSD review since it believed it qualified for an exemption from PSD permitting under Rule 62- 212.400(2)(c)4., Florida Administrative Code. That rule exempts from PSD review the [u]se of an alternative fuel or raw material which the facility was capable of accommodating before January 6, 1975, unless such change would be prohibited under any federally enforceable permit condition which was established after January 6, 1975. After reviewing the application, DEP issued an Intent to Deny on June 25, 1996. In that document, DEP stated that [a]ccording to information in Department files, both Units 1 and 2 operated on liquid fuel prior to January 6, 1975. Very substantial modifications of the boilers and pollution control equipment were implemented thereafter by [FPC] to convert the units to coal-firing mode. Therefore the project does not qualify for the exemption from PSD review claimed by the company. Contending that it was entitled to an exemption from PSD review and therefore a permit, FPC filed a Petition for Administrative Hearing on October 4, 1996. In its Petition, FPC generally alleged that petroleum coke is a product with characteristics very similar to coal; Units 1 and 2 were capable of accommodating coal and petroleum coke as of January 6, 1975; and contrary to the statements in the Intent to Deny, any boiler modifications and pollution control improvements to those units were minor and not substantial. The Permitting Program The PSD program is based on similar PSD requirements found in the federal Clean Air Act of 1970, as amended (the Act). The permitting program is a federally required element of DEP's State Implementation Plan (SIP) under Section 110 of the Act. DEP has fulfilled the requirement of administering the federal PSD program by obtaining approval from the Environmental Protection Agency (EPA) of state PSD regulations that meet the requirements of federal law. The requirements of the SIP are found in Chapters 62-204, 62-210, 62-212, 62-296, and 62-297, Florida Administrative Code. Chapter 62-212 contains the preconstruction review requirements for proposed new facilities and modifications to existing facilities. Rule 62-212.400, Florida Administrative Code, establishes the general preconstruction review requirements and specific requirements for emission units subject to PSD review. The provisions of the rule generally apply to the construction or modification of a major stationary source located in an area in which the state ambient air quality standards are being met. Paragraph (2)(c) of the rule identifies certain exemptions from those requirements. More specifically, subparagraph (2)(c)4. provides that a modification that occurs for the following reason shall not be subject to the requirements of the rule: 4. Use of an alternative fuel or raw material which the facility was capable of accommodating before January 6, 1975, unless such change would be prohibited under any federally enforceable permit condition which was established after January 6, 1975. The rule essentially tracks verbatim the EPA regulation found at 40 CFR 52.21(b)(2)(iii)(e)1. Therefore, in order to qualify for an exemption from PSD review, FPC must use "an alternative fuel . . . which [Units and 2 were] capable of accommodating before January 6, 1975." In addition, FPC must show that "such change would [not] be prohibited under any federally enforceable permit condition which was established after January 6, 1975." Contrary to assertions by Respondent and Intervenors, in making this showing, there is no implied or explicit requirement in the rule that FPC demonstrate that it had a subjective intent to utilize petroleum coke prior to January 6, 1975. The Application and DEP's Response In its application, FPC proposes to co-fire a five percent (plus or minus two percent) blend of petroleum coke with coal, by weight. It does not propose to make any physical changes to Units 1 and 2 to utilize petroleum coke. Also, it does not request an increase in any permitted air emission rates for the units because it can meet its current limits while burning the proposed blend rate of petroleum coke with coal. The application included extensive fuel analysis and air emissions data obtained from a DEP-authorized petroleum coke trial burn conducted from March 8 until April 4, 1995. Although it is not proposing to make physical changes to the plant, FPC applied for the air construction permit in deference to DEP's interpretation that such a permit is required when a permittee utilizes an alternative fuel. After completing his initial review, the DEP supervisor of the New Source Review program acknowledged in a memorandum to his supervisor that FPC was "entitled to a permit" but suggested that FPC be asked to "change their minds." Before the permit was issued, however, DEP changed its mind and issued an Intent to Deny on the ground that prior to January 6, 1975, Units 1 and 2 were not capable of accommodating coal or a blend of petroleum coke with coal. The Units Unit 1 has a generating capacity of 400 MW and commenced operation as a coal-fired plant in October 1966. It fired coal until March 1970, fuel oil until October 1978, and then again fired coal from June 1979 to the present. Unit 2 has a generating capacity of 500 MW and commenced operations as a coal-fired plant in November 1969. It fired coal until September 1971, fired fuel oil from December 1971 until October 1976, and then again fired coal from December 1976 to the present. Original equipment installed during the initial construction of Units 1 and 2 included the following: the barge unloader, which removes coal from barges that deliver coal from New Orleans; the stacker/reclaimer, which stacks the coal into piles and then reclaims the coal by directing it from the coal piles to conveyors that deliver it to the units; the crusher house, which has two crushers that crush the coal on the way to units down to nuggets no larger than three-quarters of an inch in diameter; the silos, which store the crushed coal; the feeders, located below the silos, which regulate the flow of coal from the silos to the pulverizers; the pulverizers, which grind the coal in preparation for combustion and then direct the pulverized coal to the burners, which are located on the corners of each unit's boiler; and the boilers, where the fuel is combusted, imparting heat to water contained in the waterwalls and thereby producing steam for electrical generation. The foregoing equipment was reflected in the plant's construction specifications and remains in operation, on site, at the plant. Components and parts of this equipment have been maintained, replaced, and repaired periodically. The original operations manual for the barge unloader, stacker/reclaimer, crushers, and conveyor systems are still kept and utilized on site. The primary fuel utilized in Units 1 and 2 is coal, although these units also co-fire from one to five percent number fuel oil and used oil. The combustion of fuel in Units 1 and 2 results in air emissions. As a result of changing regulatory requirements, there have been substantial improvements to the units' air pollution control capabilities since original construction. Existing Air Permits Unit 1 currently operates under Air Operation Permit Number A009-169341. Unit 2 operates under Air Operation Permit Number A-009-191820. Both permits were amended by DEP on October 8, 1996. Although each air operation permit contains an expiration date that has been surpassed, the permits remain in effect under DEP's regulations during the pendency of the agency's review of FPC's applications for air operation permits under the new Title V program found in Chapter 62-213, Florida Administrative Code. The air operation permits governing Units 1 and 2 contain mass emission rate limitations of 0.1 pounds/million (mm) British thermal units (Btu) or particulate matter (PM), and 2.1 pounds/mmBtu for sulfur dioxide. These mass emission rate limitations restrict the amount of each pollutant (measured in pounds) that is to be released into the atmosphere per million Btu of heat energy by burning fuel. The PM limitation is applicable to Units 1 and 2 under state regulations originally promulgated in 1972. The sulfur dioxide limitation was established in 1978 as a result of a PSD air quality analysis performed in conjunction with the permitting of Units 4 and 5. Prior to 1978, sulfur dioxide limits promulgated early in 1975 imposed a limit of 6.17 pounds/mmBtu on coal-fired operations at Units 1 and 2. Because Units 1 and 2 were subjected to a PSD air quality impact analysis along with Units 4 and 5, the units' sulfur dioxide emission limits were reduced from 6.17 to 2.1 pounds/mmBtu. The 2.1 pounds/mmBtu sulfur dioxide emission limitation applicable to Units 1 and 2 was set with the intention of assuring no adverse air quality impacts. The sulfur dioxide impacts associated with Units 1, 2, 4, and 5, after collectively being subjected to PSD air quality review, were much lower than the sulfur dioxide impacts previously associated with only Units 1 and 2. Is Petroleum Coke an Alternative Fuel? Petroleum coke is a by-product of the oil refining process and is produced by many major oil companies. The oil refineries refine the light ends and liquid products of oil to produce gasoline and kerosene, resulting in a solid material that resembles and has the fuel characteristics of coal. Both historically and presently, it has been common- place for electric utilities to rely on petroleum coke as fuel. For example, during the period 1969 through 1974, regular shipments of petroleum coke were sent to various electric utility companies throughout the United States to be co-fired with coal. In addition, DEP has issued permits for Tampa Electric Company to co-fire petroleum coke with coal. In 1987 and again in 1990, the EPA promulgated air- emission regulations which specifically define "coal" as including "petroleum coke." DEP has incorporated these regulations by reference at Rule 62-204.800(7)(b) 3. and 4., Florida Administrative Code. Given these considerations, it is found that petroleum coke constitutes an alternative fuel within the meaning of Rule 62-212.400(4)(c)4., Florida Administrative Code. Were the Units Capable of Accommodating the Fuel? Petroleum coke and coal are operationally equivalent. Petroleum coke can be handled, stored, and burned with the existing coal handling equipment at Units 1 and 2. The barge unloader, stacker/reclaimer, storage areas, conveyors, silos, crusher house, pulverizers, and burners, all installed prior to 1975, can handle petroleum coke. The equipment comprising Units 1 and 2 does not require any modification in order to burn a blend of petroleum coke with coal. Also, there will be no net impact on steam generator design or operation, and there will be no decline in performance or adverse impacts to the boilers. FPC could have co-fired petroleum coke with coal historically without making physical alterations or derating the units. Similarly, petroleum coke can be fired in Units 1 and 2 now without alterations or derating. These findings are further supported by Petitioner's Exhibits 35 and 36, which are reference books published in 1948 and 1967 by the manufacturer of the equipment installed at Units 1 and 2. They confirm that prior to 1975, petroleum coke was suitable for the manufacturer's boilers and pulverizers. Unrebutted testimony demonstrated that Units 1 and 2 could have co-fired petroleum coke with oil during the oil-firing period. Even when Units 1 and 2 fired oil instead of coal for a period of time in the 1970s, the coal-handling equipment remained in existence on-site and available for use, and both units remained readily convertible to their original, coal-firing modes. Because the plant remained capable of accommodating coal, it also remained capable of accommodating petroleum coke. In light of the foregoing, it is found that co-firing petroleum coke with coal at Units 1 and 2 could have been accomplished prior to January 6, 1975. Are there Post-January 6, 1975, Prohibitions? There is no evidence to support a finding that a federally enforceable permit condition was establshed after January 6, 1975, that prohibits co-firing petroleum coke with coal. I. Miscellaneous By letters dated February 14 and June 2, 1997, the EPA Region IV office replied to inquiries from DEP regarding the instant application. The conclusions reached in those letters, however, were based on a misapprehension of the facts in this case. Therefore, the undersigned has not credited these letters. To prove up its standing, LEAF introduced into evidence a copy of its articles of incorporation and a brochure describing the organization. In addition, it asserted that the air quality for its members would be "at risk" if Units 1 and 2 did not meet PSD standards and air emissions were "increased." Intervenor Sierra Club proffered that a substantial number of members "live, work, or recreate in the vicinity of the Crystal River Units 1 and 2, and in the area subject to the air emissions by those units," and that those members "would be substantially affected by the proposed exemption."

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting the application of Florida Power Corporation and issuing the requested air construction permit. DONE AND ORDERED this 23rd day of September, 1997, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1560 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of September, 1997. COPIES FURNISHED: Kathy Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 James S. Alves, Esquire Post Office Box 6526 Tallahassee, Florida 32314-6526 W. Douglas Beason, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Gail Kamaras, Esquire 1115 North Gadsden Street Tallahassee, Florida 32303-6327 Jaime Austrich, Esquire Post Office Box 1029 Lake City, Florida 32056-1029 F. Perry Odom, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

USC (1) 40 CFR 52.21(b)(2)(iii)(e)1 Florida Laws (1) 120.569 Florida Administrative Code (2) 62-204.80062-212.400
# 4
ELMORE FUTSCHER AND MARTHA FUTSCHER vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003839 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003839 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57
# 5
LEE HIESTAND vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003860 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003860 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57
# 6
DOROTHY HAZZARD vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003826 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003826 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57
# 7
PATRICIA D'HONDT vs CONSTRUCTION BURNING, INC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 95-004817 (1995)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Oct. 02, 1995 Number: 95-004817 Latest Update: Jul. 08, 1996

Findings Of Fact On June 8, 1995, Respondent Construction Burning, Inc. (Applicant) filed an application with Respondent Department of Environmental Protection (DEP) for the construction of a McPherson Systems, Inc. Model M40B Air Curtain Incinerator with a Model M16ACD Blower (Model 40). The application states that Applicant would use the Model 40 air curtain incinerator (ACI) "to combust and destroy landscape debris such as leaves, limbs, trunks, tree clippings, brush, pallets and clean wood that [Applicant] accepts from outside landscaping contractors." An ACI encloses a fire with four walls. The operator adds combustible material to the fire from an open top. The air curtain is an air stream generated by blowers directed over the fire. The air curtain helps the fire maintain the high temperatures required for effective combustion. The air curtain also creates a barrier to trap materials in the incinerator until more completely burned. In these ways, the ACI reduces emissions from the incinerator Petitioner proposes in the application the construction of a refractory walled burning pit 40 feet long, 12 feet wide, and 15 feet deep with blowers above and beneath the fire. The blower beneath the fire would help maintain high temperatures in the fire. The Model 40 ACI that is the subject of the application adds three ten-foot upper chamber walls, which assist in maintaining the integrity of the air curtain above the fire. The Model 40 ACI also features a fine-meshed cage to trap particulates and ash. The application states that the Model 40 ACI would reach temperatures from 2000 to 2500 degrees Fahrenheit and would have a maximum incineration rate of 25 tons per hour of clean landclearing or landscaping debris, producing 1000 pounds per hour of sanitary ash. The application requests a permit to operate the Model 40 ACI 9.5 hours daily, five days a week. The application assures that, in terms of visible emissions, the Model 40 ACI would generate only 5 percent opacity, except for 35 percent opacity in the 30-minute startup period. On August 31, 1995, DEP issued its Intent to Issue. The permit notes that this is the second ACI at the site. Specific Condition 4 prohibits the facility from storing more combustible material than can be burned in 30 days during normal operating hours. If either unit becomes inoperative, Specific Condition 4 requires that the facility stop accepting material after it reaches 6000 tons onsite, until the onsite material is reduced to less than 5600 tons. Specific Condition 9 requires that Applicant discontinue use of the Model 40 ACI anytime that it is performing inadequately due to overloading, neglect, or other reasons. Specific Condition 12 sets the maximum burning rate at 50,000 tons per hour. Specific Conditions 13 and 14 address visible emissions. Specific Condition 13 prohibits no more than five percent opacity outside of startup, except that opacity up to 20 percent is allowed for not more than three minutes in any one hour. Specific Condition 14 allows opacity of up to 35 percent averaged over a six-minute period during startup, which is the first 30 minutes of operation. Specific Condition 15 limits the materials to be burned in the Model 40 ACI to "wood wastes consisting of trees, logs, large brush, stumps relatively free of soil, unbagged leaves and yard trash, tree surgeon debris, and clean dry lumber such as pallets." At the hearing, DEP produced an undated draft permit for the Model 40 ACI. The only change from the August 31, 1995, permit is that the draft permit requires Applicant to remove the existing ACI from the facility. Applicant has been operating a McPherson Model 30 ACI at the same location as that proposed for the Model 40 ACI. Formerly zoned heavy industrial, the location, which is 16351 Old Highway 41 in Ft. Myers, is presently zoned for the operation of an ACI, and the facility is surrounded by industrial uses. Applicant has been operating the Model 30 ACI at the present location since December 1992 under a permit dated February 15, 1993. The permit for the Model 30 ACI, which expires February 15, 1998, contains similar Specific Conditions as those under contained in the new permit, except that the old permit does not limit the amount of material that can be stored onsite. The Model 30 ACI is different from the Model 40 ACI. The Model 30 ACI is an older, smaller model with a capacity of 20 tons per hour. Lacking the three-walled upper chamber, the Model 30 ACI cannot maintain the integrity of the air curtain as well as can the Model 40 ACI. The Model 30 ACI has a larger- meshed screen than the Model 40 ACI, so larger particulates and ash can escape the incinerator. Compared to the Model 40 ACI, the Model 30 ACI is manufactured with less durable components, which are more vulnerable to damage from the hot steam produced from the combustion of exceptionally moist vegetation, such as Brazilian Pepper and melaleuca. Also, Applicant's Model 30 ACI either lacks a below-fire blower or its below-fire blower is broken, so as to impede effective combustion. Applicant's Model 30 ACI is in dilapidated condition, leaving it both unsafe and ineffective. The operating history of Applicant's Model 30 ACI has been uneven. Applicant's Model 30 ACI has never failed a Class III inspection, which is a 90- minute inspection conducted annually. Applicant's Model 30 ACI has failed one of five Class II inspections, which are 30-minute visible-emissions inspections. Applicant's Model 30 ACI has passed most of about 17 Class I inspections, but its failures have resulted in two consent orders, including one in which DEP fined Applicant $2000. On April 4, 1994, a defective wall in Applicant's Model 30 ACI allowed hot embers to escape and ignite a large fire on the grounds of the facility. The fire required many hours of firefighting before it could be extinguished. However, Applicant has since adopted a firefighting plan and installed sprinklers on the grounds. The proposed limitation of onsite vegetative debris would further reduce the risk of fires escaping from the Model 40 ACI. DEP produced some, but not all, field investigation reports for Applicant's facility. On June 9, 1994, DEP inspectors visited the site after receiving complaints of heavy smoke in the area. After an investigation, they prohibited Applicant from accepting new material for three weeks, presumably so Applicant would be under less pressure to burn vegetative material that had not dried sufficiently to burn efficiently and without visible emissions. On July 5, 1994, a DEP inspector visited the site after receiving a complaint and found brown and white smoke of 15-30 percent opacity emanating from the Model 30 ACI, largely due to excessive moisture in the vegetative material being added to the incinerator. A week later, at mid-day, a DEP inspector visited the site and saw white smoke of 30-50 percent opacity for one minute, followed eventually by five percent opacity. On August 24, 1994, a DEP inspector noticed brown smoke emanating from the Model 30 ACI at about 4:00 pm. The opacity was 10-25 percent. Applicant had allowed a log to protrude through the air curtain, which allowed smoke to escape from the incinerator. On November 17, 1994, two DEP inspectors visited the site and noted brown smoke emanating from the Model 30 ACI with 10-25 percent opacity. Applicant's representative explained that the walls of the Model 30 ACI were damaged and allowed the smoke to escape from the incinerator. The representative assured the DEP inspectors that a replacement wall was onsite and maintenance was soon to be undertaken. DEP conducted T-screen modeling to determine whether particulate emissions from the Model 40 ACI would be below the ambient air quality standards within one-half mile of the facility. DEP determined that, under the worst-case situation, proper operation of the Model 40 ACI would not have an adverse impact within one-half mile of the facility. Applicant has not, at all times, operated the Model 30 ACI in a safe and effective manner, especially with respect to the moisture content of loads added to the ACI. Hot steam emerging from excessively moist loads has damaged the walls of the Model 30 ACI and shortened its useful life. The damage to the walls has in turn impaired the ability of the Model 30 ACI to burn safely and efficiently the vegetative material added to the unit, leading to one serious fire and many violations of DEP's standards for visible emissions. Petitioner presented evidence of visible smoke and smoky odors entering her home and the homes of other residents living in the vicinity of Applicant's facility. Some of these incidents are attributable to Applicant, and some are not. The Model 40 ACI would improve the conditions of which Petitioner complains. The new ACI would be a marked improvement over the old ACI, as long as Applicant properly operates the Model 40 ACI and DEP routinely monitors Applicant's operations and enforces the permit conditions and other provisions of law. Under the circumstances, including Applicant's recent operating history, Applicant has provided the necessary reasonable assurance for the issuance of a new permit authorizing the construction and operation of the Model 40 ACI described in the August 31, 1995, proposed permit, as modified by the undated draft permit, together with the proposed general and special conditions. However, the finding of reasonable assurance is predicated on a new provision in the proposed permit limiting the term of the new permit to the termination date of the original permit for the Model 30 ACI, which is February 15, 1998. Given Applicant's recent operating history, Applicant has not provided the necessary reasonable assurance for an operating permit with a longer term than the term remaining under the old permit. If Applicant demonstrates that it can safely and effectively operate the Model 40 ACI between now and February 15, 1998, it can obtain a five-year permit at that time.

Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order issuing a permit to Construction Burning, Inc. to replace the existing McPherson Model 30 ACI with a Model 40 ACI, pursuant to the Intent to Issue dated August 31, 1995, as modified by the undated draft permit requiring the elimination of the Model 30 ACI, and operate the Model 40 ACI through February 15, 1998, in accordance with all permit conditions and other provisions of law. ENTERED on May 22, 1996, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings on May 22, 1996. APPENDIX Rulings on Petitioner's Proposed Findings 1: rejected as not finding of fact. 2: rejected as unsupported by the appropriate weight of the evidence. 3-5: rejected as recitation of evidence. 6: rejected as recitation of evidence. However, the failure of the DEP witness to bring with him the file of Applicant is inexplicable. 7: adopted or adopted in substance. 8 (first two sentences): rejected as irrelevant. 8 (remainder): adopted or adopted in substance, to the extent of a limit on the term of the new permit. 9: rejected as not finding of fact. 10: rejected as recitation of evidence. 11: rejected as unsupported by the appropriate weight of the evidence and relevance. Rulings on Applicant's Proposed Findings 1-3: adopted or adopted in substance. 4: rejected as not finding of fact. 5: adopted or adopted in substance except as to the date on which operation started. Applicant's president testified that Applicant began operations in 1992. 6-7: adopted or adopted in substance. 8 (first sentence): rejected as unsupported by the appropriate weight of the evidence. 8 (remainder): adopted or adopted in substance, except for finding as to when Applicant learned of damage to the Model 30 ACI. 9: rejected as subordinate. 10-14: adopted or adopted in substance. 15-16: rejected as recitation of evidence. 17: rejected as unsupported by the appropriate weight of the evidence. 18: rejected as subordinate. 19: rejected as recitation of evidence. 20: rejected as unsupported by the appropriate weight of the evidence. However, this remedy is available by law to DEP, regardless of the provisions of the permit. 21-22: adopted or adopted in substance. 23: rejected as recitation of evidence. 24-25 (first sentence): adopted or adopted in substance. 25 (remainder): rejected as recitation of evidence. 26: adopted or adopted in substance. 27-30: rejected as recitation of evidence. 31: rejected as legal argument. Rulings on DEP's Proposed Findings 1-24: adopted or adopted in substance. 25: rejected as recitation of evidence. 26-27: adopted or adopted in substance. 28: rejected as unsupported by the appropriate weight of the evidence, unless the term of the new permit is limited to the remaining term of the old permit. 29: rejected as legal argument. 30-59: rejected as subordinate, except to the extent incorporated in the recommended order. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Kenneth Plante, General Counsel Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Patricia d'Hondt 6288 Briarwood Terrace Ft. Myers, Florida 33912 Connie D. Harvey Akerman, Senterfitt & Eidson, P.A. 100 South Ashley Street, Suite 1500 Tampa, Florida 33602-5311 Stephen K. Tilbrook Assistant General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-2400

Florida Laws (2) 120.57403.087 Florida Administrative Code (2) 62-296.40162-4.070
# 8
HAZEL AYERS vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003832 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003832 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57
# 9
SUN PIERCE vs S.M.G., INC. AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-003873 (2002)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 19, 2002 Number: 02-003873 Latest Update: Jun. 03, 2003

The Issue The issue presented is whether Respondent, S.M.G., Inc. (SMG), has provided reasonable assurance that its existing air curtain incinerator will be operated in accordance with applicable statutory and rule provisions.

Findings Of Fact The Parties The Department is the state agency responsible for receiving applications for, and the issuance of, permits for the construction and operation of air curtain incinerators in the State of Florida. SMG is a contracting company, with residential, trucking, agricultural, and commercial driver's license divisions. SMG is the applicant for a permit to operate an air curtain incinerator. Petitioners reside in Citrus County, Florida, in the vicinity of the constructed and operational air curtain incinerator. For the most part, Petitioners reside northeast, east, or southeast of the site. The Petitioners demonstrated their standing in this proceeding. SMG's Construction Permit On May 23, 2001, SMG submitted an application for an air construction permit to the Department's Southwest District Office. The application sought authorization to construct an air curtain incinerator "[o]n the east or west side of 6844 N. Citrus Avenue, Crystal River," Citrus County, Florida. 1 The general purpose of pursuing this permit was to burn wood waste. On July 9, 2001, the Department issued SMG a Notice of Intent to Issue the Proposed Air Construction Permit (Permit No. 0170360-001-AC). A copy of the Notice of Intent was published in the Citrus Times in Citrus County on July 19, 2001. On August 6, 2001, the Department issued SMG an air construction permit for the proposed air curtain incinerator. The construction permit authorized the construction of a McPherson Systems, Inc. - Model M30E air curtain destructor (incinerator) with under fire air at a natural non-Title V facility. Pursuant to the terms of the construction permit, in November 2001, SMG constructed an air curtain incinerator on approximately 500 acres of land on the east side of State Route 495 north of Crystal River in Citrus County, Florida, on property owned by the Gerrits family. See Endnote 1. Pursuant to the construction permit, SMG installed a McPherson Systems, Inc. - Model M30E air curtain incinerator with under fire air, a refractory lined burning pit, three upper chamber refractory lined walls (ten feet high), and a stainless steel spark arrester screen. The manifold blower and under fire air fans are powered by an electric engine. The manufacture designs and specifications for the McPherson model were submitted with the application for the air construction permit and admitted in evidence. Construction of a portable air curtain incinerator with a blower/fan system powered by a diesel-fired engine was contemplated by the air construction permit. Although cheaper, SMG instead chose to install the McPherson model that would produce the cleanest burn, i.e., one with fewer emissions, that was operated by electricity. The McPherson model used by SMG is recognized as an efficient, reliable model of air curtain incinerator. The diesel-fired blower/fan/engine system contemplated by the construction permit is considered exempt from permitting. An engine operated by electricity has no emissions and therefore does not require an air permit from the Department. The Department could not require a permit for the blower/fan system alone. The operating permit supercedes the construction permit, except as amended. Testing after Construction of the Incinerator On November 23, 2001, SMG began operating the air curtain incinerator. Pursuant to Special Condition 22 of the air construction permit, an initial visible emissions (VE) (opacity test) compliance test was performed on November 23, 2001, by Bernard A. Ball, Jr., an environmental engineer with Southern Environmental Services, Inc. The results of the initial VE compliance test were within the opacity limits contained in the construction permit. Specific Condition 19 of the construction permit requires SMG to maintain daily operating logs of the air curtain incinerator's daily operations. In order to obtain an air operating permit, a permit applicant is required to demonstrate compliance with the Department's rules and with the conditions of the construction permit. The Department requires an applicant for an operating permit to submit copies of recent daily operating records for the facility and copies of the emissions test required by the construction permit. These operating records are submitted in order for the Department to determine whether the applicant is complying with the applicable emissions standards and that the applicant is, in fact, maintaining the required operating logs as required by the construction permit. In order for SMG to obtain the operating permit for the incinerator, Specific Condition 28 of the construction permit required SMG to file an application for an air operating permit with the Department within 45 days of testing and required the application to include a copy of the VE test report and copies of at least two recent weeks of daily operating logs. On March 14, 2002, a second VE test was conducted by Mr. Ball, which also indicated that emissions were within the construction permit's opacity limits. On April 1, 2002, SMG submitted its application for the air operation permit to the Department. The application was signed by Sean Gerrits, and contained copies of the VE test reports for the November 2001 and March 2002 tests, as well as three and one-half months of daily operating logs, certificates showing that the incinerator operators were trained, and photographs of the incinerator in operation. SMG submitted the documentation required under the construction permit. On April 19, 2002, Robert E. Soich, Jr., air compliance inspector for the Department's Southwest District Office, performed an unannounced inspection and conducted a VE test in response to a complaint by Mr. Leonard Kaplan (a Petitioner), complaining of odors present. Excessive visible emissions were observed by Mr. Soich on April 19, 2002. The incinerator did not pass the VE test because of the improper alignment of the blade angle on the manifold of the blower system and because of green leaves and inadequate drying of the materials to be burned in the incinerator. Mr. Soich also observed, in part, that "materials need to be prepared better for burning." As a result of this unannounced inspection and the negative VE test, the Department requested SMG to provide an explanation of the VE test results and of the type of changes SMG planned to implement to correct the problem. On learning of the problem, SMG shut down the incinerator and called a McPherson mechanical contractor to come out and adjust the blade angle. Southern Environmental Services conducted another VE test to ensure the problem had been corrected. On April 22, 2002, a VE test was conducted by Southern Environmental Services on-site which showed compliance with the construction permit. On April 30, 2002, SMG advised the Department that adjustments were made to the baffles to correct the angles. SMG provided the Department with the April 22, 2002, VE test results. SMG also implemented better operational procedures. On May 30, 2002, with Mr. Soich present, SMG, by Byron E. Nelson, performed another VE test. The test results showed compliance with the opacity limits in the construction permit and the results were submitted to the Department.2 Mr. Nelson, an environmental engineer with Southern Environmental Sciences, testified that he has been involved in preparing approximately two dozen applications for air curtain incinerators and has conducted probably "thousands" of visible emissions tests. Mr. Nelson is certified by the State of Florida to conduct VE tests. He has seen "two or three dozen" air curtain incinerators in operation and has conducted VE tests on about 20 of them. Based on his experience, Mr. Nelson testified that SMG employed the same practices and controls to control odor, smoke, and fugitive emissions as other such incinerators he is familiar with. He testified that the amount of smoke and odors from the SMG incinerator is similar to that emitted from other air curtain incinerators, and that the fugitive emissions from the SMG incinerator were probably less than others he is familiar with. Based on his experience, Mr. Nelson opined that SMG has taken reasonable measures to minimize odor, smoke and dust/particulates from the operation of the incinerator. Mr. Nelson likewise opined that the SMG incinerator is well run, perhaps better run than other incinerators. (Mr. Nelson had been on the SMG site twice when the incinerator was operating and burning wood products.) Based on his experience, Mr. Nelson opined that SMG meets the requirements necessary to obtain an air operating permit from the Department and has demonstrated that it has complied with the conditions of its construction permit. Mr. Soich is the air compliance inspector for the Department's Southwest District Office. He testified that he has inspected the operations of other air curtain incinerators over the last 15 years. Mr. Soich testified that SMG is one of the "better operators" of air curtain incinerators he is familiar with. (Mr. Soich visited the SMG site approximately nine times from March 13, 2002, to October 15, 2002.) Mr. McDonald is the Air Permitting Engineer for the Southwest District Office of the Department. He is responsible for reviewing all applications for air curtain incinerators in the Southwest District and has reviewed applications for between 25 and 30 incinerators. Mr. McDonald reviewed the SMG permit applications. Based on the latest VE test results, copies of the records attached to the operating permit application, and his experience, Mr. McDonald, for the Department, determined that SMG had demonstrated compliance with the conditions of the construction permit and recommended issuance of the operating permit for the incinerator. He maintained the same position at hearing. SMG provided assurance that the DeRosa Fire Department would respond in the event of a fire at the incinerator. On June 19, 2002, the Department issued the proposed air operating permit. Operation of the Air Curtain Incinerator Emissions from the incinerator are controlled by a curtain of forced air at a very high static pressure over and around the burning pit. The air curtain traps smoke and small particles and recirculates them to enhance combustion and reduce smoke. The underfire air introduces air underneath the air curtain to ensure complete combustion and minimize opacity at start-up. The refractory-tiled ceramic concrete burn pit provides a safe combustion chamber, and the refractory panels keep excess heat from escaping. The upper chamber refractory panels, which surround three sides of the burn pit, allow more retention time in the burner to better control opacity and sparks. The stainless screen spark arrestor also controls sparks and debris from leaving the burner. The operating permit application proposed the use of an air curtain blower along with a manifold to provide forced air to the burning pit. According to the manufacturer specifications, the blower can force air into the pit at velocities of between 100 and 120 mph. This ensures that the flames in the burn pit receive enough oxygen to combust completely. The air circulates inside the burn pit to ensure a complete burn, which reduces smoke and odor. The combustion temperature for the burning pit ranges from approximately 1,800 to 2,500 degrees Fahrenheit. The operating permit allows a maximum charging rate of ten tons per hour on a daily average basis and 31,200 tons per any consecutive 12 month period. The incinerator has been operating below the maximum charging rate. The operating permit limits the hours of operation (charging) to 3,120 hours per year, i.e., ten hours/day, six days/week, 52 weeks/year. According to various SMG operating and maintenance logs, the incinerator has been operated below this limit. The operating permit, in accordance with Rule 62- 296.401(7), Florida Administrative Code, allows the burning of only wood waste, yard waste, and clean lumber, and prohibits the burning/incineration of materials such as sawdust, paper, trash, tires, garbage, rubber material, plastics, liquid wastes, Bunker C residual oil, roofing materials, tar, asphalt, railroad cross ties, or other creosoted lumber, chemically treated or painted wood, and other similar materials. Biological waste shall not be burned in the incinerator. During its operation, the incinerator only burned wood and yard waste, and Mr. Gerrits testified that the waste materials are inspected before being burned in order to ensure that no prohibited materials are burned. If any non-authorized materials are observed, they are removed before the waste is burned. See Finding of Fact 24. The operating permit allows visible emissions during start-up periods (not to exceed the first 30 minutes of operation) of an opacity up to 35 percent, averaged over a six- minute period, as provided for in Rule 62-296.401(7)(a)-(b), Florida Administrative Code. The McPherson model is designed to meet the requirements of the above-referenced rule, and the VE tests run during start-up periods (except one performed by Mr. Soich on April 19, 2002) demonstrated compliance with this requirement. Id. The operating permit limits visible emissions outside of start-up periods (the first 30 minutes of daily operation) to no more that five percent opacity, with visible emissions of up to ten percent opacity allowed up to three minutes in any one hour as provided for in Rule 62-296.401(7)(a), Florida Administrative Code, and 40 Code of Federal Regulations Part 60, Subpart CCCC, adopted and incorporated by reference in Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Rule 62- 296.401(7)(a) permits up to 20 percent opacity. The ten percent rate is required by the new federal standard. See SMG Exhibit 13, page 3 of 9.) The opacity limits in the operating permit are more stringent than those contained in the construction permit, which allows visible emissions of up to 20 percent opacity up to three minutes in any one-hour period. (By definition, a "visible emission" is "[a]n emission greater than 5 percent opacity or 1/4 Ringelmann measured by standard methods." Rule 62-296.200(278), Florida Administrative Code.) The VE test results submitted by SMG demonstrate compliance with the opacity limits in the operating permit and with the opacity limits in the construction permit for the days tested. See Findings of Fact 18, 22, 27, and 29. The operating permit requires that the incinerator must be attended at all times while materials are being burned and that public access to the incinerator must be restricted. A certified operator is in attendance whenever the incinerator is operated, i.e., when something is burning in the incinerator. A fence has been constructed around the property. The operating permit prohibits starting the incinerator before sunrise and requires that all charging of the incinerator be completely stopped before sunset as required by Rule 62- 296.401(7)(h), Florida Administrative Code. Mr. Gerrits testified that the incinerator is never started before sunrise and is typically started after 8:00 a.m. Mr. Gerrits testified that the incinerator is never charged after sunset and that charging typically stops at 4:00 or 5:00 p.m. See Endnote 4. These practices are consistent with the Operations and Maintenance Guide for the incinerator. The operating permit limits the height of the ash in the burning pit to one-third of the depth of the pit or to a point where the ash begins to impede combustion, whichever occurs first as provided in Rule 62-296.401(7)(m), Florida Administrative Code. The one-third depth line is marked on the outside of the incinerator. Mr. Gerrits testified that ash is regularly removed from the burning pit every third day to keep the ash level low, which helps ensure better combustion and reduces smoke. The operating permit provides that material shall not be loaded into the incinerator in such a way that it will protrude above the air curtain. Testimony established that the SMG incinerator is properly loaded. The operating permit requires that all operators of the incinerator be trained in the proper operation and maintenance of the incinerator and that an operations and maintenance guide be maintained at the facility at all times. All of the operators of the SMG incinerator have taken a four-hour training course to learn how to operate the incinerator in accordance with Department regulations and good operating practices, and certificates attesting to that training were submitted with the application for the operating permit. An Operations and Maintenance Guide was submitted with the application for the construction permit. The operating permit requires the maintenance of a daily operating log. The daily operating log must be maintained at the facility for at least five years and must be available for inspection by the Department upon request. SMG currently maintains a daily operating log that meets the requirements of the construction permit. SMG submits those daily logs to the Department on a monthly basis after the Department requested that SMG do so. The log includes a date and site location, daily operating hours, total charges, total material charged in tons, average hourly charging rate, any maintenance performed, fuel usage in gallons, and the operator's signature. The logs of record contain this information and have been initialed by SMG's operator for each day when the incinerator has been operated. SMG operators responsible for preparing the logs have no incentive to indicate the incinerator is not operating on days or during hours when it is running, as a deliberate misstatement on the operating logs could result in enforcement action by the Department and being fired by SMG. The operating permit requires that all reasonable precautions be undertaken to prevent and control the generation of unconfined emissions of particulate matter in accordance with Rule 62-296.320(4)(c), Florida Administrative Code. SMG takes reasonable precautions to prevent and control the generation of unconfined emissions of particulate matter, including paving the road that leads to the incinerator to reduce dust, wetting the ashes removed from the burn pit, wetting the ash piles and ramp that addresses the incinerator, approaching the incinerator at a slow rate, and placing a charge into the incinerator slowly and carefully. SMG voluntarily added a sprinkler system on all four corners of the burning pit that was not contemplated by the construction permit. The Department witness Mr. McDonald testified that this provided an additional method to control unconfined emissions. Although the construction permit and proposed permit do not contain conditions prohibiting the burning of green wood or wet wood waste, SMG takes precautions at the request of Mr. Soich to ensure that the wood is properly dried before being burned. See Finding of Fact 24. This helps to reduce smoke and emissions from the incinerator. (Moisture is the primary factor that inhibits burning and causes smoke and potentially odor.) As part of the routine practice in handling the wood waste before it is burned, trucks bringing wood waste to the incinerator are instructed to dump it into a pile. SMG operators then use a loader to flatten out the pile and remove dirt, prohibited materials, and harvestable pieces of wood. Harvestable pieces of wood and dirt are removed to separate staging areas. The remaining wood waste is separated into long windrows, with the oldest row closest to the incinerator. The windrows are flipped or rolled over in the direction of the incinerator, allowing the waste to dry. The waste in the row closest to the incinerator is burned, and subsequent windrows are rolled over in its place. Ash is generally removed from the burn pit every third day; it is wetted on removal to reduce dust, and the ash piles adjacent to the incinerator are also kept wetted by the sprinkler system. The ash is eventually mixed with the dirt in a composter for use as Class-A unrestricted compost. The SMG operator in charge on a particular day decides whether the incinerator will operate that day, in accordance with standard operational practices. The operator checks the weather forecast. If it is raining or if there are high winds (over 20 miles per hour), the incinerator will not be operated that day, and SMG typically waits four days after a rain to begin operating the incinerator again. These procedures are not contained in any permit conditions. The purpose of not operating during or immediately after a rain and taking steps to ensure the wood is dry is to reduce smoke; wet wood smokes more. Rainy weather can also affect odor. The purpose of not operating during windy conditions is to reduce the possibility of fire on SMG's property, but wind can also affect odor and visible emissions. On days when the incinerator is not operating, SMG conducts yard maintenance, maintains the waste windrows, and runs the composter. The composter is a source of noise and is located adjacent to the incinerator and is run when the incinerator is shut down. To ensure that the visible emission limitations are not exceeded and objectionable odors3 not generated, the operating permit requires that the incinerator's fan shall continue to operate after the last charge of the day until all combustion (presence of any flame or smoke) has ceased. Generally, the incinerator keeps burning an hour to an hour and one-half. Mr. Gerrits testified that the fan is kept running until the flames and smoke die out and that a certified operator is present until the fan is switched off. The operating permit requires that the testing of visible emissions must be conducted within 90-100 percent of the maximum allowable charging rate of 10 tons/hour and shall be conducted when the highest emissions can reasonable be expected to occur.4 Testing of the SMG incinerator was conducted at within 90-100 percent of the maximum allowable charging rate of 10 tons per hour, and the May 30, 2002, test results indicated that the incinerator was operating within the opacity limits of its permit even when operating at close to maximum capacity. Evidence established that the May 30, 2002, VE test complied with the specific conditions of both the construction and operating permit. See Finding of Fact 29. The test method for visible emissions required by both the construction permit and the operating permit is EPA Method 9, adopted and incorporated by reference at Rule 62- 204.800(8)(b)74, Florida Administrative Code. (Method 22 is not required pursuant to Department rules for compliance testing of an air curtain incinerator.) Testimony established that Method 9 was the method used for the VE tests conducted on the SMG incinerator. As required by both the construction and operating permits, the incinerator is located in excess of 300 feet from any pre-existing occupied building located off site as required by Rule 62-296.401(7)(j), Florida Administrative Code. The closest residences, that of Mr. Gerrits' father and his tenant, are approximately 1,500 feet away. Petitioners' Challenge For the most part, Petitioners reside northeast, east, or southeast of the incinerator. One Petitioner resides approximately three-tenths of a mile southeast of the incinerator; others reside at greater distances, up to approximately a mile and one-half away from the incinerator. Each of the Petitioners who testified have resided in this area for many years, pre-dating the operation of the incinerator. The Petitioners who testified were credible and well- intentioned. Each of these Petitioners maintained daily logs covering several months when the incinerator was authorized to operate. Some kept logs for several months, while others kept logs for several days. They noted their observations and perceptions in the logs. Admittedly, Petitioners are not experts in the detection of odors or noise levels. Nevertheless, they recorded their own experiences as to what they saw, heard, and/or smelled, believing that the odors and noise came from the incinerator. Some recorded that they smelled the strong odor of smoke, an "acrid smell," a "pungent smell," for example; "it makes your eyes burn and throat burn" said another during the hearing. One witness described the experience as being a prisoner in his house. Another does not go outside when the smell is bad. Generally, the level of odor varied with the weather conditions, i.e., a stronger odor was noticed on foggy and wet days or nights and when the wind blows from the west, which Petitioners contend is the prevailing wind. Some witnesses only smelled the odor during the night and not during the day, and not all of the time. Some complained about the odor and noise, or one and not the other. Some believed the noise coming from the incinerator was a major problem. At least two witnesses who live approximately three-tenths of a mile and 3,500 feet, respectively, from the incinerator site, described the noise as being like a jet airplane. One witness shuts her windows to keep out the noise. (SMG also operates a "wood chipper" or "composter" on site which is loud. Mr. Gerrits stated that he did not think the sound was the same as made by the incinerator fan. He also stated that "[i]t doesn't exceed the noise decibels. It doesn't exceed background noise levels at [their] property line.") Petitioners documented their concerns which are described, in part, above, and also documented their complaints to the Department and local government. It appears that each of the logs prepared by the Petitioners (who kept logs) were given to Petitioner Martha Futscher, who summarized and compiled a hand-written master list of the complaints. Then, Mr. Harvey inputted this data on the master list (spread sheet) of complaints, which appears as Petitioners' Exhibit F1. The master list contains recorded observations from May 2002 through January 2003. The master list contains a representation of when the incinerator started and stopped for various days and when it was operational or not, and this information was derived, according to Mr. Harvey, from the logs maintained by SMG. The master list also provides tons per hour of waste burned on particular days, the observer's initials, and the approximate distance each observer lived from the incinerator, and the comments, with time of observation or perception noted. There are discrepancies between the master list and the actual logs maintained by SMG as to when the incinerator was operational. There also appears to be several differences in observations between the Petitioners' master list and other evidence which indicates when Mr. Soich inspected the incinerator and determined that the incinerator was operating satisfactorily. Compare Petitioners' Exhibit 2 with Petitioners' Exhibit F1. For example, the master list records an observation from May 30, 2002, when the incinerator was operating, when there was noise and smoke noted at 8:00 a.m., and flames at the incinerator and odor at 5:30 p.m. Conversely, Mr. Soich was on-site on May 30, 2002, and observed the scheduled VE test. No problems were noted with the operation on this date by Mr. Soich. Mr. Soich also noted that "wood waste was properly dry and free of debris." The VE test on May 30, 2002, was performed from 10:29 a.m. to 11:59 a.m. and showed compliance with opacity limits. The master list indicates that black smoke was observed (no time given) on May 7, 2002, when the incinerator was operational, yet Mr. Soich inspected the incinerator on that day and there is a notation in the record that the incinerator was operating between 0-5 percent visible emissions. (Mr. Soich opined that it should be very rare to smell objectionable odors if the visible emissions run at a 5 percent level.) For October 15, 2002, there is a notation in the master list that a Petitioner commented that the incinerator was running during the day ("AM/PM Running") and that there was a strong smell at approximately 7:05 p.m. A strong smell at the person's house was also noted at approximately 9:30 p.m. on that day. However, Mr. Soich performed an annual inspection of the incinerator on October 15, 2002, and there is a notation on the master list, Petitioners' Exhibit 2, that the incinerator was not operating due to recent rain. As one Petitioner testified, her point was that the inspectors are not there when she hears the noise, sees smoke, and smells the odor. Mr. Soich confirmed that he does not inspect the facility in the evening. Petitioners also provided, as evidence in support of their position, six videotapes of the incinerator for September 19, October 3, October 23, November 25 (2 tapes), 2002, and January 10, 2003. (Mr. Harvey took the videotapes from the same location, across the street and west of the incinerator.) Each tape, except for September 19, 2002, showed smoke emanating from the operational incinerator. On September 19, 2002, the incinerator was not running according to the SMG log. There was a malfunction which was reported to the Department. The SMG log indicates that the pit was cleaned out, site cleared and rows moved. There is also a notation in the SMG log for this date that there was a power failure/malfunction at the incinerator at 9:00 a.m., and that the power was out. According to Mr. Gerrits, the malfunction caused smoke. (One Petitioner observed smoke from ashes on September 19, 2002.) While the Petitioners proved that there was smoke emanating from the operation of the incinerator on the days which were videotaped, with the exception of September 19, 2002, this did not necessarily prove that the emissions exceeded the requirements of the Department rules or that there was an objectionable odor emanating therefrom. Mr. Stoich observed the videotapes played during the hearing. In particular, with respect to the January 10, 2003, videotape, Petitioners' Exhibit 12, Mr. Stoich stated that a level of opacity cannot be determined from photographs and videotapes. He also noted that there was "a lot of white smoke," an atypical situation according to him, emanating from the incinerator and that he, as a compliance inspector, would have investigated further and performed an inspection, including a VE test, to determine if there was a violation, had he seen this smoke. However, he stated that without actually seeing the operation, he could not determine whether a violation had occurred. There was persuasive evidence that compliance with the opacity limits of a permit can only be determined through VE tests conducted using the Department-approved EPA Method 9. The VE test takes into account wind, the angle of the plume, the position of the sun, and other factors, and must use appropriate averaging to ensure that the test is valid. A smoke plume can look quite dense at the wrong angle or if the light is reflecting off the plume in a certain way, when in fact it is in compliance with Department rules. The VE tests for the incinerator have, with one exception, see Finding of Fact 24, demonstrated compliance with the opacity limits in the construction permit. As noted herein, upon receipt of notice that one VE test failed, SMG implemented corrective actions, and two VE tests conducted after the time showed the incinerator was operating in compliance with the opacity limits of the permit. See Findings of Fact 27 and 29. The Department relies on its compliance inspectors, such as Mr. Soich, to make a determination of whether an air emission source is causing an objectionable odor. There does not appear to be an approved Department method for measuring odors from incinerators. (Mr. Nelson stated that odors are difficult to test and that "odor is done collecting samples." No samples were taken or analyzed.) On the other hand, Mr. Soich testified that, based on his years of experience, he has developed certain methods for determining whether a facility is emitting an objectionable odor under the rules. If he receives an odor complaint, which he has in this case, he goes to the site and checks the prevailing winds. He also travels around the facility to determine the source of the odor. An odor can be deemed objectionable if it is very strong and overpowering, such that he cannot stay on- site and breathe in the odors. An odor can also be deemed objectionable if, after being on-site for some extended period of time, he begins to develop symptoms such as runny eyes, a scratchy throat, or a headache as a result of the smell. Finally, he may bring along another Department employee to determine whether the other individual finds the odor objectionable. Enforcement actions can be taken if objectionable odors are detected. Mr. Soich testified that he has inspected the incinerator at least nine times in the past year and never detected an objectionable odor. On some of the visits, the incinerator was not operational. On rebuttal, several residents of the area testified that they had not experienced objectionable odors from the incinerator. David Stevens, the Chief of the DeRosa County Fire Department, testified that an open land-clearing burn emits black smoke, more so than he observed from the incinerator. This fire department only had to respond to false alarms at the incinerator. Mr. Stevens personally inspected the operation of the incinerator and thought it was a very safe operation. Randy Morgan, a wildlife firefighter and certified burner with the Division of Forestry with over 16 years of experience in fire control, testified that approximately 50,000 acres of the state land burns occurred in Citrus County last year. These land burns can be a significant source of smoke and odor. In addition, approximately 50 open burn authorizations are issued each day. He also testified that controlled burns of approximately 15 fires of approximately 50 to 2,000 acres a day occurred in 2002 in proximity of the SMG incinerator which is a source of smoke and odor. The state also conducts open burns of some kind approximately ten months out of the year. Other witnesses testified that, given the rural nature of the community, open burning of trash, wood, and leaves occurs on a regular basis. Ultimate Findings of Fact Credible evidence established that SMG meets or exceeds the requirements in the construction permit to reduce smoke, dust, and odor, and these requirements are carried over to the operating permit. Credible evidence established that SMG employs the same, if not better, practices and permit conditions to control smoke, dust, and odor as other air curtain incinerators in the state. Credible evidence established that the SMG incinerator is operated in accordance with its construction permit. Credible evidence established that the SMG incinerator can be expected to be operated in accordance with its operating permit. Credible evidence established that the SMG incinerator is operated in accordance with Department rules. In light of the foregoing, SMG has demonstrated reasonable assurance that its air curtain incinerator has been operated in compliance with the construction permit and that the incinerator can continue to be operated in accordance with the conditions of the operating permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting SMG's application and issuing Permit No. 0170360-002-AO, as amended, and subject to all conditions, including but not limited to the Specific Conditions set forth in the Department's Notice of Intent to Issue, for the operation of an air curtain incinerator in Citrus County, Florida. It is further recommended that Petitioners' challenge to the amendment to the operating permit be dismissed. See Preliminary Statement. DONE AND ENTERED this 21st day of April, 2003, in Tallahassee, Leon County, Florida.5 CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2003.

Florida Laws (2) 120.569120.57