HIGHLANDS LAKES ESTATES HOMEOWNERS' ASSOCIATION vs REPUBLIC SERVICES OF FLORIDA, L.P., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 09-006754 (2009)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Dec. 15, 2009 Number: 09-006754 Latest Update: Nov. 30, 2010

The Issue The issue is whether Respondent Department of Environmental Protection (DEP) may issue to Respondent Republic Services of Florida, L.P. (Republic), permits to construct and operate a Class III landfill, pursuant to Permit Numbers 266830-003-SC/01 and 266830-004-SO/01, as modified as set forth below.

Findings Of Fact Background On June 30, 2009, Republic filed with DEP an application for a permit to construct and operate a Class I landfill (Application). In response to DEP's request for additional information dated July 30, 2009 (RAI), Republic filed a response dated September 14, 2009 (RRAI), upon receipt of which, DEP deemed the Application to be complete. References to the Application typically include the Application, RRAI, and other materials, such as reports, plans, and drawings, that are part of the Application, as well as three subsequent modifications, which are detailed below. Republic revised several reports, plans, and drawings in the RRAI; references to these items, such as the Engineering Report and Operation Plan, are to the versions contained in the RRAI. On November 13, 2009, DEP filed its intent to issue construction permit #266830- 003-SC/01 (Construction Permit) and intent to issue operation permit #266830-004-SO/01 (Operation Permit; collectively, the Permit). Republic Services, Inc. and its affiliates constitute the second largest waste-management operator group in the United States. Their market capitalization is just over $11 billion. The capitalization of the affiliate formed to operate the subject landfill is doubtlessly less than $11 billion, as the record does not suggest that any significant part of the overall capitalization of Republic Services, Inc., and its affiliates would be at risk in the operation of the proposed landfill. Republic presently owns and operates a Class III landfill in the City of Bartow, Polk County, known as the Cedar Trail Landfill. The oldest part of this landfill is an unlined Class III landfill of 52.5 acres in the center of the property owned by Republic. Immediately west of this unlined landfill is a 30.7-acre lined Class III landfill, which comprises cells 1-4. The Cedar Trail Landfill is located at 2500 West State Road 60, about three miles west northwest of the intersection of State Road 60 and State Road 98, which marks the center of Bartow. The landfill is immediately west of E.F. Griffin Road. Petitioners Frost live on E.F. Griffin Road, about one mile north of the Cedar Trail Landfill. Petitioner Highland Lakes Estates Homeowner's Association serves a residential subdivision known as Highland Lakes Estates. Highland Lakes Estates occupies a notch at the southeast corner of Republic's property. Aerial photographs reveal the changing land use of the land on which Cedar Trail Landfill is situated. Fifty years ago, the land was vacant with indications of agricultural uses. At the site of the proposed landfill were mostly citrus groves on the west side and some rangeland or vacant land on the east side. Ten years later, a large area immediately northeast of the subject land reveals the effects of strip mining for phosphate. Three years later, in 1971, the mined area had greatly expanded to encompass all or nearly all of the subject site and much of the surrounding area, including the western half of what would become Highland Lakes Estates. By 1980, the pits had been refilled and active mining had ceased, and the streets had been constructed for what is now known as Highland Lakes Estates. By 1993, about three dozen homes had been built in this residential, large-lot subdivision. 9. The Cedar Trail Landfill was constructed in the early 1990s as an unlined construction and demolition debris landfill. Now designated an approved landfill for Class III waste, this facility accepts such waste as is defined by Florida Administrative Code Rule 62-701.200(14) (2010), which includes construction and demolition debris, yard trash, processed tires, asbestos, carpet, paper, glass, furniture (but not white goods), plastic, and other materials not expected to produce leachate that presents a risk to the public health or environment. A zoning/land use map reveals that the land for which the proposed landfill is proposed is designated "sewage/borrow pits/spray fields." Highland Lakes Estates occupies land that is designated single-family residential with a density of one dwelling unit on up to 2.49 acres. The Cedar Trail Landfill has been the subject of three recent environmental resource permits (ERPs). Appendix R to the Application is an individual ERP issued in April 2009, and Appendix R to the RRAI is a conceptual ERP issued in March 2005. The April 2009 ERP mentions that the entire stormwater project was conceptually approved by an ERP issued on September 10, 2008, but this ERP is not part of the record. In any event, these ERPs approve the construction of a comprehensive stormwater or surface water management system for the entire Republic property. In particular, the April 2009 ERP permits the construction of a borrow pit at the southeast corner of the Republic property and a modification of the perimeter ditch/wet retention system. The April 2009 ERP states that the permitted stormwater management system will provide total onsite retention for runoff from the 100-year, 24-hour storm. The April 2009 ERP requires 2.8 acres of compensation for 2.8 acres of encroachment in the 100-year floodplain. Specific Condition 14 prohibits excavation of the borrow pits to a clay confining layer or limestone bedrock layer. Specific Condition 20 prohibits the mixing of leachate with stormwater and provides that, if leachate enters stormwater, the stormwater becomes leachate. Presumably reflecting this permitting activity, Application Drawing 4, as revised in the RRAI, is the site plan, including the unlined Class III landfill, the four-cell lined Class III landfill immediately to the west of the unlined landfill, and the eight cells proposed to accept Class I waste. These eight cells are immediately south of the four cells of the lined Class III landfill. The two northernmost of these eight cells abut, on their east boundary, the unlined Class III landfill. The remaining six cells abut, on their east boundary, an 800-foot wide borrow pit, which lies between these cells and Highland Lakes Estates. Immediately north of Highland Lake Estates is a second borrow pit, and west of this borrow pit is the unlined Class III landfill. The other major feature on the site plan is a third borrow pit running, from west to east, along the north border of the lined Class III cells, the unlined Class III landfill, and the second borrow pit. Bearing no signs of ambitious reclamation activity, the backfilled mining cuts host large water storage areas and, as described in the application for the March 2005 ERP, wetlands of "very poor quality." The backfilled soils are best described as complex surficial soils, consisting mostly of fine sands with varying amounts of organics, silts, and clays. Geotechnical investigations of the Cedar Trail Landfill suggest that mining depths, although variable, probably averaged 40 feet. Petitioners and Intervenor are substantially affected by the Permit and the construction and operation of the proposed landfill, which will stand nearly 200 feet above grade and will be the focus of substantial activity six days per week during its years of operation. Like Petitioners, Intervenor owns land in the immediate vicinity of the Cedar Trail Landfill, which is in the jurisdiction of Intervenor, and Intervenor's various municipal operations are much affected by whether the proposed Class I landfill is permitted. Among other things, Intervenor has agreed to accept untreated leachate from the proposed landfill. Petitioners Frost built their home in 1980 or 1981. During the hours of operation of the existing landfill, Petitioners Frost constantly hear the beeping noise of heavy- duty equipment, presumably a safety device when the equipment is moved. Over a dozen lots in Highland Lakes Estates abut the property line of the Cedar Trail Landfill, and the closest residence is about 1000 feet from the nearest proposed Class I cell. At present, the existing landfill subjects the Highland Lakes Estates to constant noise during operating hours and a coating of dust inside their homes. Several residents of Highland Lakes Estates testified. Hard-working people, some of whom are now retired, these residents decided to purchase homes in Highland Lakes Estates because it was a sunny, healthy place to live. Over time, most of these residents, by varying degrees, have come to accept the fact of the Class III operations at Cedar Trail Landfill, but they object to the substantial intensification of land use that will result from a regional Class I landfill. One resident testified that she finds in her pool dirt that has escaped from the existing landfill, and she has become concerned about her grandchildren coming over to swim. Another resident testified that he only began closing his windows five or six years ago when the noise levels at the existing landfill increased; he eventually had to install a window air- conditioner. The same resident testified that the green herons and snowy egrets that he used to see around his house have not returned for five years, and his wife, who has health problems, including respiratory distress, would suffer from the expanded landfill operations. Application, RRAI, and Permit, Including Modifications The Permit incorporates the Application, including the RRAI, Engineering Report, Operation Plan, and drawings. Thus, all of the documents are part of the Permit. In the Application, Republic proposes to convert cells 5-8, which are not yet constructed, from a Class III to a Class I landfill and add four new cells adjacent to the unused cells. The unfilled portion of Cells 1-4 would continue to receive only Class III waste. Pursuant to Florida Administrative Code Rule 62-701.200(13) (2010), Class I waste is all solid waste, other than hazardous waste, that is not otherwise prohibited by rule. The Application states that the proposed landfill will serve communities within 100 miles. The service area of this regional landfill will thus extend in central Florida from Marion to Osceola counties, along the Gulf Coast from Pasco to Lee counties, and along the Atlantic Coast from Volusia to Martin counties. As stated in the Application, this service area is populated by 9.7 million persons, who would daily account for 3000 tons of waste at the Cedar Trail Landfill. Initially, according to the Engineering Report, the proposed landfill will receive 1600 tons per day of Class I waste, but, once the existing Class III cells are filled, the proposed landfill will receive 1600 tons per day of Class I waste plus the 1400 tons per day of the Class III waste that is currently going into the existing landfill. As revised by the RRAI, the life expectancy of the proposed landfill is seven years. The Application states that Republic will employ an attendant, a trained operator, and 3-5 spotters at the landfill. The Application reports that the landfill would operate Monday through Saturday from 7:00 a.m. to 6:00 p.m. and that the working face would be covered daily. The Application reports that Republic would install seven new detection wells and use 17 existing wells for monitoring groundwater and would use two existing staff gauges for monitoring surface water, evidently at a single location, as discussed in the next paragraph. 23. Application Appendix V is the Water Monitoring Plan. Appendix V states that surface water will be monitored every time that the stormwater pond for the leachate storage area discharges offsite, but not more frequently than weekly. Application Drawing 4, as revised in the RRAI, shows that the sole surface water monitoring location is close to the leachate storage tanks, which are described below. 23. Appendix V also requires leachate monitoring, "at least annually," for five field parameters--specific conductivity, pH, dissolved oxygen, colors, and sheens; eight laboratory parameters--including chloride, mercury, and total dissolved solids; and the parameters listed in 40 CFS Part 258, Appendix II, which includes a comprehensive list of volatile organic compounds; persistent organic pollutants, including 2,3,7,8-TCDD (a major dioxin) and Dibenzofuran; and metals, including lead and chromium. Fourteen days prior to all sampling events, Republic is required to notify DEP, so that it may obtain split samples for its own analysis. Republic is required to report the results of the groundwater monitoring quarterly and to analyze the groundwater data in a technical report filed with DEP every two years. Appendix V also requires monitoring for odors and combustible gases, mostly methane. Republic will monitor combustible gas quarterly at various ambient locations, such as the office buildings and to monitor combustible gas quarterly in the soil down to the seasonal high water table. The purpose of this monitoring is to determine combustible gas concentrations and, if they exceed 25%, take "all necessary steps to ensure protection of human health." Some confusion in the Application arises as to the issue of whether the Cedar Trails Landfill will be subject to, or voluntarily implement, the more elaborate provisions applicable to a landfill covered under Title V of the federal Clean Air Act, as amended in 1990. Regulated emissions for a new source might include particulate matter, sulphur dioxide, nitrogen oxides, volatile organic compounds (VOCs), and specified hazardous air pollutants. Appendix V states that the landfill will become a Title V landfill once permitted to receive Class I waste, and, at that time, it will be subject to a "more comprehensive system of landfill gas collection and monitoring." Appendix V assures that these items "will be addressed in separate documentation from this monitoring plan"--and, apparently, separate from the present record. By contrast, the Operation Plan concedes only that, based on the nature of Class I waste and the design capacity of the proposed landfill, Cedar Trail Landfill "may" become a Title V facility. The Operation Plan states: "If the regulatory thresholds at [Cedar Trail Landfill] are met [under Title V] requiring an active gas collection and control system (GCCS), [Cedar Trail Landfill] will submit as required the GCCS design plans for approval and install an active gas extraction system within the regulatory timeframes specified by Title 40, Code of Federal Regulations, Part 60, Subpart WWW." More specific provisions in the Operation Plan identify best management practices to prevent objectionable odors. Four practices are identified, including an "active gas collection and extraction system." On the DEP form application, which is a cover sheet to the more elaborate application materials, Republic checked boxes indicating that the landfill would use active gas controls with gas flaring and gas recovery, which is probably what is meant by an "active gas collection and extraction system." The Application provides that the landfill liner would be double composite; the leachate collections system would consist of collection pipes, geonets, and a sand layer; the leachate would be stored in tanks; some of the leachate would be recirculated as spray on the working face; and the remainder of the leachate would be stored onsite and periodically transferred to a wastewater treatment center for treatment. The Engineering Report states that the waste disposal footprint will not be located where geological formations or other subsurface features will not provide support for the waste. The Engineering Report identifies appendices addressing the slope-stability analysis and foundation analysis and relies on a March 12, 1997, report by Ardaman & Associates, Inc. (Ardaman Report), January 23, 2004, report by Golder Associates, Inc. (Golder Report), and June 26, 2009, report by Hanecki Consulting Engineers, Inc. (Hanecki Report). These items are discussed in greater detail below in connection with the sinkhole issue. The Engineering Report assures that the waste disposal footprint will not be within 500 feet of an existing or approved potable water well, nor will it be within 1000 feet of an existing or approved potable water well serving a community water supply. The Engineering Report adds that the minimum horizontal distance between waste deposits and the property line is 100 feet. The Engineering Report assures that the landfill footprint will not be in a dewatered pit, as the installation elevations are at least 2-3 feet higher than the seasonal high water table. The Engineering Report acknowledges that a small part of the eastern end of the four southernmost cells lies within the 100-year floodplain, as depicted by the Flood Insurance Rate Map effective December 29, 2000, and as shown in Application Appendix A, Drawing 1. Claiming that the relevant map was not revised in 2000, the Engineering Report asserts that the last update to the FIRM map was in 1975, and the depicted floodplain was filled during the mine reclamation process. The Engineering Report notes that the floodplain concerns were addressed in the April 2009 ERP. 34. The Engineering Report discloses two enforcement actions against Republic at the Cedar Trail Landfill. In a letter dated October 19, 2001, DEP warned Republic about noncompliant items at the site, and, in a notice of noncompliance dated January 30, 2006, DEP warned Republic not to use a new cell prior to construction certification of the cell's stormwater system. Both matters were reportedly resolved, and Republic has not been the subject of other enforcement actions for the Cedar Trails Landfill. At DEP's urging, the RRAI elaborates on enforcement actions against Republic or, evidently, Republic affiliates at a variety of Florida facilities, not just landfills. The additional information reveals that DEP imposed a fine of $61,300 for the October 2001 violations, which included disposing of unacceptable waste, storing an excessive number of tires and exceeding groundwater standards without notifying DEP, and a fine of $1000 for the January 2006 notice of noncompliance. The other enforcement actions against Republic or affiliates concerning landfills involved consent orders about the Nine Mile Road Landfill (Seaboard Waste): in February 2003, DEP imposed a fine of $13,000 in settlement of charges that employees were not removing all unacceptable waste from the site and, in November 2005, DEP imposed a $285 fine for a failure to submit required stormwater monitoring reports. There were many other enforcement actions, generally resulting in modest fines, but they involved hauling facilities, transfer stations, and materials recovery facilities, not landfills. The Engineering Report states that the proposed landfill is within six miles of, but greater than 10,000 feet from, the Bartow Municipal Airport. Airport safety is addressed in more detail below. The Engineering Report describes in detail the double composite liner system, which uses materials whose physical, chemical, and mechanical properties prevent failure due to contact with Class I waste and leachate, climactic conditions, installation stress, and other applied stresses and hydraulic pressures. The Engineering Report performs no contingency sinkhole analysis. The report does not suggest that the liner system could withstand the stresses and pressures resulting from any size sinkhole, so the necessary inference is that the liner will fail if any sinkhole forms directly beneath it. The Engineering Report states that waste placement will remain within the lined containment berm. The Engineering Report describes in detail the double composite liner system for use at the proposed landfill. The primary liner system and secondary liner system each comprises three layers with the top layer consisting of a composite drainage net, the middle layer consisting of a high-density polyethylene geomembrane with a minimum average thickness of 60 ml, and the bottom layer consisting of a geosynthetic clay liner with a maximum hydraulic conductivity of 5 x 10-9 cm/second. The Engineering Report describes in detail the leachate collection and removal system, which, sitting atop the primary liner, includes a 24-inch thick sand drainage layer with a minimum hydraulic conductivity of 1 x 10-3 cm/second, a composite drainage net, and a single perforated 8-inch diameter lateral pipe in each cell. The collection lateral pipes will gravity drain to the east to a header pipe that gravity drains to the primary leachate collection pump stations--one station for the four converted cells and one station for the four new cells. A smaller leachate collection and removal system will handle the leachate that penetrates to the leak detection layer by routing it to a secondary leachate collection pump station. Based on calculations derived from the HELP groundwater model, the leachate collection and removal system is designed to prevent leachate head from exceeding the thickness of the composite drainage net (about 1 cm) over the secondary geomembrane and from exceeding one foot over the primary geomembrane. According to the Engineering Report, flow meters will be installed at each of the pump stations to allow daily readings of the amount of leachate being pumped. At one foot of head over the primary liner, the Engineering Report expects just over three gallons per day collected at each secondary leachate collection pump station--significantly less than the leakage rate typical of a double liner system without a geosynthetic clay liner beneath the primary liner. However, the Engineering Report provides a standard action leakage rate of 100 gallons/acre/day, meaning that Republic is required to report to DEP liner leakage only when this leakage rate is attained. The pump stations will transmit the leachate to one of two above-ground, 150,000-gallon storage tanks. From these tanks, most of the leachate will be transported to an offsite location for treatment. However, up to 12,000 gallons per day of the untreated leachate will be recirculated to be sprayed on the working faces of the landfill. This is to control dust and possibly to assist with the degradation of the waste. The Engineering Report states that the Cedar Trail Landfill implements a facility-wide water quality monitoring plan. Upon completion of the pump stations for the eight cells that are the subject of the Application, Republic will expand its leachate sampling program to include annual sampling of the leachate collected in the primary and secondary leachate collection pump stations. The groundwater monitoring wells would be installed as closely as possible to the outer edge of the roadway that, with a stormwater ditch, will run the perimeter of the proposed Class I landfill. In the revised Engineering Report contained in the RRAI, Republic proposes a surface water discharge point in the stormwater pond located near the leachate storage tanks. The Engineering Report adds that Republic will continue to comply with the following prohibitions: No waste will be knowingly burned on site; Hazardous waste will not knowingly be accepted; PCB contaminated waste will not knowingly be accepted; Untreated biomedical waste will not knowingly be accepted. Please note that treated biomedical waste may be accepted at [Cedar Trail Landfill]'s Class I Landfill provided that the waste containers are marked "Treated Biomedical Waste.;" No waste disposal at the proposed Class I Landfill will occur within 3,000 feet of a Class I surface water body; [Cedar Trails Landfill] will not knowingly accept liquid waste within containers, excluding leachate and gas condensate derived from solid waste disposal operations. [Cedar Trails Landfill] will comply with the requirements of Rule 62- 701.300(10), FAC regarding the handling of liquid wastes; Neither oily waste nor commingled oily waste will knowingly be accepted; and Lead-acid batteries, used oil, white goods, and whole-waste tires will not knowingly be disposed of in the Class I waste disposal system. The Joint Stipulation to Permit Modification, identified above, adds four items to this list of operational prohibitions: i. Garbage will not be knowingly accepted; Household Waste, except waste from residential sources generated as Class III waste, will not be knowingly accepted; Animal carcasses will not be knowingly accepted; and Aluminum dross will not be knowingly accepted. Capitalized terms are generally defined in the Florida Administrative Code. Florida Administrative Code Rule 62-701.200(39) defines "Garbage" as " all kitchen and table food waste, and animal or vegetative waste that is attendant with or results from the storage, preparation, cooking, or handling of food materials." Application Appendix H is the Operation Plan, which also identifies the types of wastes to be permitted at the proposed landfill. Section 3(b) of the Operation Plan authorizes the proposed landfill to accept: Commercial waste Ash residue Incinerator by-pass waste Construction and demolition debris, including from a residence Treated biomedical waste Agricultural waste Industrial waste Yard trash, including from a residence Sewage sludge Industrial sludge Water/air treatment sludges Waste tires De minimis amounts of non-hazardous waste from incidental residential sources Section 5 of the Operation Plan provides, in relevant part: [Cedar Trail Landfill] will accept waste included in any of the waste categories identified under Section 3(b) of this Operation Plan[, but] will . . . NOT knowingly accept any hazardous waste, untreated biomedical waste, liquid waste (including paint), explosive waste, toxic waste, or radioactive waste for disposal at the [Cedar Trail Landfill.] Unacceptable types of refuse are listed below and will not be knowingly accepted for disposal. --Hazardous waste --Explosive waste --Radioactive waste --Drums that have not been opened and Emptied --Refrigerators, freezers, air Conditioners (white goods) --Any toxic or hazardous materials, i.e. batteries, solvents, oil, etc. --Automobiles or parts that contain fuel, lubricants, or coolants --Untreated Biomedical waste The original Application prohibited the acceptance of septic tank pumpage, but the application form accompanying the original Application indicated that the proposed landfill would accept industrial sludge and domestic sludge. After modification by the RRAI, the prohibition against accepting septic tank pumpage was deleted, and the Operating Plan added, among acceptable wastes, sewage sludge, industrial sludge, and water- and air-treatment sludge. Florida Administrative Code Rule 62-701.200(101) (2001) defines "sludge" to include solid waste pollution control residual from an industrial or domestic wastewater treatment plant, water supply treatment plant, air pollution control facility, septic tank, grease trap, portable toilet, or other source generating a waste with similar characteristics. Florida Administrative Code 62-701.200(64) (2001) defines "liquid waste" as any waste with free liquids, according to the "Paint Filler Liquids Test." As modified by the Joint Stipulation to Permit Modification, Section 5 of the Operation Plan was amended to add the following items to unacceptable types of refuse that will not be knowingly accepted for disposal: --Garbage --Household Waste, except waste from residential sources generated as Class III waste --Animal carcasses --Aluminum dross At the hearing, Republic and DEP agreed to an additional condition to the Operation Plan that unacceptable waste would include Garbage contained in commercial, industrial or agricultural waste. According to the Operation Plan, the initial waste screening occurs at the gate house where the attendant interviews the driver and inspects the incoming waste load. If the attendant sees more than a negligible amount of unauthorized wastes, he will reject the load and will contact the hauler to identify the source of the waste. Additionally, Republic will notify DEP if anyone tries to dispose of hazardous waste at the proposed landfill. As modified by the Joint Stipulation to Permit Modification, the Operation Plan was amended to provide a new paragraph between the paragraph addressing the initial waste screening at the gate house and, as discussed below, the second screening at the working face. The new paragraph provides: Any malodorous waste will be covered with mulch and/or additional soil or other approved cover materials to control odors promptly, within one (1) hour from the time of unloading, except in the event of exigent circumstances, such as extreme weather. Cedar Trail Landfill will promptly cover any sludge deposited on the landfill working face within one (1) hour from the time of the unloading, except in the event of exigent circumstances, such as extreme weather. At the hearing, Republic and DEP agreed to an additional condition to the Operation Plan, which would prohibit Republic from accepting malodorous waste or sludge that, due to exigent circumstances, it would not be able to cover within one hour from the time of unloading. If the load passes the initial waste screening, it will proceed to the working face of the landfill, according to the Operation Plan. At least one spotter will be stationed at the working face at all times that the landfill receives waste. Her job will be to detect unauthorized wastes. Republic is to assure that it has a sufficient number of spotters to find and remove unauthorized waste prior to compaction. The Operation Plan allows the spotter to work from ground level or the cab of a compactor. If the operator of a piece of heavy equipment is trained as a spotter, she may also serve as a spotter. During periods of higher waste traffic, the equipment operator will, according to the Operation Plan, "likely" need the assistance of another operator or spotter to screen the higher waste volumes. When finding unauthorized wastes in manageable volumes, the spotter or operator will remove these wastes by hand and place them into nearby containers for removal to an appropriate facility. The third waste screen occurs as the equipment operator spreads the waste, pursuant to the Operation Plan. The equipment operator is required to place any unacceptable observed wastes into containers, which will be located "within the lined area." These wastes will also be removed to an appropriate facility. In the RAI, DEP questioned the proximity of the containers to the working face, as the lined area consists of 72 acres, but, in the RRAI, Republic ignored the comment, restating only that the containers would not be located outside the lined area. The Operation Plan specifies a filling sequence. Republic will assure that the first layer of waste placed above the liner in each cell will be a minimum of four feet in compacted thickness and will be free of rigid objects that could damage the liner or leachate collection and removal system. Republic will maintain the working face to minimize the amount of exposed waste and initial cover necessary at the end of each day. The filling sequence will proceed until the permitted final grade elevations have been reached, less three feet for the final cover. The Operation Plan states that the initial cover at the Class I landfill will consist of a six-inch layer of soil that is transferred from onsite borrow pits or offsite sources. This soil will be compacted and placed on top of the waste by the end of each work day. At Republic's option, subject to DEP's approval, it may use a spray-on or tarpaulin cover, instead of a soil cover. The Operation Plan requires Republic to apply at least one foot of intermediate cover within seven days of cell completion, if additional waste will not be deposited within 180 days of cell completion. Republic may remove all or part of this intermediate cover before placing additional waste or the final cover. Through the placement of initial, daily, and intermediate cover, Republic will minimize the occurrence of moisture infiltration, fires, odors, blowing litter, and animals and other disease vectors. 59. The Operation Plan requires Republic to control litter primarily by daily waste compaction and cover. However, at least daily, if needed, employees will collect litter along the entrance and access roads and around the working face. Complaints about litter must be logged. In addition to the inspections detailed above, the Operation Plan establishes a random load-checking program to detect unauthorized wastes. Each week, Republic employees will examine at least three random loads of solid waste by requiring drivers to discharge their loads at a designated location within the landfill where the employees may undertake a detailed inspection. All random inspections will be logged. Notwithstanding the daily limit of 12,000 gallons per day, the Operation Plan prohibits Republic from spraying leachate during rain events. To apply the recirculated leachate, the lead operator will drive the leachate tanker truck on the working face, so that it can spray leachate over waste as it is being compacted, but after it has been screened by spotters. The spraying will be done to avoid causing leachate to pond atop the waste and will not be done within 50 feet of an outside slope. No restrictions apply to wind conditions. The Operation Plan states that, if the annual sampling of leachate water quality at the two pump stations reveals a contaminant in excess of the permissible limits listed in 40 CFR Part 261.24, Republic will start monthly sampling and notify DEP in writing. Also, the Cedar Trail Landfill will maintain a recording rain gauge. The Operation Plan requires Republic employees to conduct daily surveys for objectionable odors and take immediate corrective action, if odors are found at the property line. As modified by the Joint Stipulation to Permit Modification, this portion of the Operation Plan was amended to add two odor- remediation actions and another form of odor inspection. The two additional actions to prevent odors are to 1) provide additional cover using mulch, additional soil, or other approved cover material and 2) use odor masking or neutralizing agents. The new inspection provision states: Internal inspection will be performed on a weekly basis by a properly trained odor ranger or equivalently trained person. Such individual will tour the facility, property boundary, and the subdivision of Highland Lakes Estates . . . to identify any odors leaving the Landfill's property boundaries. The results of each weekly inspection will be document, and any odors identified will be mitigated. Another new provision from the Joint Stipulation for Permit Modification applies to the handling of sludge. As amended, the Operation Plan states: When accepting sludge from a new source or distributor, [Republic] will obtain information regarding the characteristics and constituents of the sludge, including a description of the industrial process or circumstances that resulted in the generation of the sludge. Upon delivery of the sludge, [Republic] will mix lime, sodium hydroxide, or any other suitable agents to eliminate objectionable odors as required during disposal of the sludge before the material is covered. Furthermore, [Republic] will obtain advance notice from contributors prior to delivery of any sludge and shall promptly cover any sludge unloaded on the landfill working face within one (1) hour from the time of unloading, except in the event of exigent circumstances, such as severe weather. [Republic] shall use its best efforts to avoid accepting or disposing of sludge on Saturdays, Sundays, or public holidays. Additionally, with respect to sludge received from wastewater treatment facilities only, such sludge shall not exceed the lesser of (1) twenty percent (20%) of the total volume of waste disposed in the landfill on an average monthly basis, determined annually on the prior calendar year, or (2) two-hundred (200) tons per day, averaged over the prior 12-month calendar year. Republic is required to monitor combustible gases quarterly and transmit the results to DEP, according to the Operation Plan. If Republic detects methane above the limits specified in Florida Administrative Code Rule 62-701.530 (2010), Republic must submit a gas remediation plan to DEP within seven days. The Operating Plan indicates that the separation of the waste from the groundwater prevents the saturation of the waste and, thus, the generation of odor. Sloping and compacting will promote stormwater runoff, again to discourage the generation of odor. The Construction Permit authorizes construction of the proposed landfill in accordance with the "rules[,] . . . reports, plans and other information" submitted by Republic "(unless otherwise specified)." This parenthetical reference provides that the provisions of the Construction Permit control over any contrary provisions in the other documents that are part of the Permit due to incorporation by reference. In addition to the original Application, RRAI, and drawings, the Construction Permit also incorporates Florida Administrative Code Chapter 62-701 (2001). The Construction Permit states that Republic may not violate the prohibitions set forth in Florida Administrative Code Rule 62-701.300, which is discussed in the Conclusions of Law. Construction Permit Specific Condition A.9.a requires notification to DEP of the discovery of limestone during excavation or discovery. Specific Condition A.9.b requires notification to DEP of any surface depressions or other indications of sinkhole activity onsite or within 500 feet of the site. Specific Condition A.9.c prohibits open burning. Construction Permit Specific Condition C.1.b prohibits the discharge of leachate, during construction or operation, to soils, surface water, or groundwater outside the liner and leachate management system. Specific Condition C.4 prohibits the acceptance of hazardous waste and does not condition this prohibition on Republic's knowledge that the waste is a hazardous waste. Specific Condition C.5 requires Republic to "control . . . odors and fugitive particulates (dust)" and "minimize the creation of nuisance conditions on adjoining property." "Nuisance conditions" include "complaints confirmed by [DEP] personnel upon site inspection." Specific Condition C.5 orders Republic to "take immediate corrective action to abate the nuisance" and to "control disease vectors so as to protect the public health and welfare." Construction Permit Specific Condition C.6.b requires immediate notice to DEP of any sinkholes or other subsurface instability. Specific Condition C.8 requires Republic to manage leachate in accordance with the Operating Permit and Florida Administrative Code Rule 62-700.500(8). The Operating Permit incorporates the same materials that are incorporated into the Construction Permit, again "(unless otherwise specified)." Like the Construction Permit, the Operating Permit incorporates Florida Administrative Code Chapter 62-701 (2001) and requires immediate notice to DEP in the event of a sinkhole or subsurface instability. The Operating Permit specifies that the action leakage rate is 100 gallons per acre per day and the leachate recirculation rate is 12,000 gallons per day. As modified by the Joint Stipulation to Permit Modification, Operating Permit Specific Condition A.1.b states: This Facility is not authorized to accept Garbage; untreated Biomedical Waste; animal carcasses; liquids and non-liquid PCB containing materials or wastes with a PCB concentration greater than or equal to 50 parts per million; Liquid Waste; and aluminum dross. Additionally, this facility is not authorized to accept Household Waste, except waste from residential sources generated as Class III waste. Class III waste means yard trash, construction and demolition debris, processed tires, asbestos, carpet, cardboard, paper, glass, plastic, furniture other than appliances, or other materials approved by [DEP] that are not expected to produce leachate which are a threat to public health or the environment as defined in Rule 62-701.200(14), F.A.C. Based on this authorization to allow certain wastes as described above from residential sources, and since the landfill design, including liner and leachate collection systems, meets the requirements of Chapter 62-701, F.A.C., for Class I landfills, the facility will be entitled to [the] household hazardous waste exemption pursuant to 40 C.F.R. 261.4(b)(1). Specific Condition A.9.c prohibits open burning. Operating Permit Specific Condition C.1.b prohibits the discharge of leachate to soils, surface water, or groundwater outside the liner. Specific Condition C.1.c prohibits the discharge of "residual contaminants," such as gasoline, oil, paint, antifreeze, and polychlorinated biphenyls (PCBs), onto the ground or into surface water or groundwater. Operating Permit Specific Condition C.1.k(1) provides that authorized waste types are those listed in Section 3(b) of the Operations Plan, and unacceptable wastes shall be removed from the site as described in Sections 3(a) and 7. As modified by the Joint Stipulation to Permit Modification, Operating Permit Specific Condition C.1.k(1) provides: "Waste types authorized for management at this site are those listed in Section 3(b) of the Operations [sic] Plan. Unacceptable wastes are those listed in Section 5 [of the Operation Plan] " Operating Permit Specific Condition C.1.k(2) requires the use of a sufficient number of spotters to remove unacceptable wastes, but allows Republic to direct its equipment operators to serve as spotters from the equipment. This condition allows DEP to require that spotters work from the ground, if DEP determines that spotting from equipment is not effective. Specific Condition C.1.k(3) requires Republic to remove unacceptable wastes immediately and not to unload additional wastes in the immediate vicinity until placing unacceptable wastes in the designated waste containers" "near the working face" and within the lined landfill area. Operating Permit Specific Condition C.1.l(2) requires Republic to inspect on each operating day the property boundary for objectionable odors and, if any are detected, abate them in accordance with Specific Condition C.5. Specific Condition C.5.a requires Republic to control odors, disease vectors (insects and rodents), and fugitive particles (dust and smoke) to protect the public health and welfare. Control is defined as "minimiz[ing]" the creation of nuisance conditions on adjoining property. Odors confirmed by DEP personnel are a nuisance condition, and Republic must take immediate corrective action to "abate" the nuisance. Specific Condition C.5.b provides that, if odor control measures do not "sufficiently abate" objectionable odors within 30 days, Republic will submit an odor remediation plan to DEP for approval. Operating Permit Specific Condition C.8.e requires monthly reports to DEP of leachate quantities. Specific Condition C.8.h(1) prohibits recirculation of leachate at rates that result in seepage that may discharge outside the lined area. Leachate may not be sprayed when the application area is saturated or during a rainfall event. There is no prohibition against spraying during windy conditions. Operating Permit Specific Condition E details the extensive water quality monitoring requirements. However, Specific Condition E.9.b requires only annual testing of the five field parameters, eight laboratory parameters, and the comprehensive list of Appendix II parameters set forth in 40 CFR Part 258, all of which are identified below. Specific Condition E.9.c provides that, if a contaminant listed in 40 CFR 261.24 exceeds the level listed therein, Republic will notify DEP and take monthly leachate samples until no exceedances are detected for three consecutive months. Operating Permit Specific Condition F.1.a states: "This solid waste permit will meet the statutory requirement to obtain an air construction permit before . . . constructing a source of air pollution, except for those landfills that are subject to the prevention of significant deterioration (PSD) requirements of Chapter 62-212, F.A.C." Such facilities are required to obtain an air construction permit from the Bureau of Air Regulations prior to construction. Specific Condition F.1.b requires Republic to comply with Title V of 40 CFR 60, Subparts WWW and CC. This section notes that Title V permit applications must be submitted to the District Air Program Administrator or County Air Program Administrator responsible for the landfill. Aviation Safety Landfills attract birds in search of food. Flying birds may interfere with aviation safety. Thus, landfills are typically not located in close proximity to airfields to minimize the risk that flying birds will interfere with airborne aircraft approaching or departing from an airport. The nearest airport to the Cedar Trail Landfill is the Bartow Municipal Airport, which is operated by the Bartow Aviation Development Authority. This airport is over five miles from the footprint of the active landfill and 4.6 miles from the boundary of the proposed site. Republic provided notice of the Application to all airports within six miles of the proposed landfill, the Federal Aviation Administration, and the Florida Department of Transportation. None of these entities objected to the proposed landfill. When Republic gave the Bartow Aviation Development Authority notice of an earlier application, which sought a permit for a landfill that would accept garbage, the authority objected to the proposal due to concerns posed by birds to aviation safety. When asked about the Application, the authority's executive director testified that she still has concerns about the proposed landfill, but she did not specify the nature of her concerns or her analysis. As explained in the Conclusions of Law, these are the only facts required for a determination of whether Republic has provided reasonable assurance of aviation safety. The record provides no basis for finding that Republic has failed to provide reasonable assurance of aviation safety. Neither the FAA nor the Bartow Aviation Development Authority has objected to the proposed landfill. The executive director's unspecified concerns do not override the absence of a formal objection from these agencies. Petitioners assign too much weight to the earlier objection submitted by the authority. The composition of the authority may have changed or some authority members may have decided they were wrong in their earlier analysis. This earlier objection does not outweigh the absence of objection to the present proposal from any of the aviation agencies and the absence of any evidence of the expected nature or extent of bird usage of the proposed landfill and the extent to which these birds would interfere with existing and expected flight paths of aircraft using the Bartow Municipal Airport. Public Health Petitioners' expert witness on public-health issues, Dr. David Carpenter, is a medical doctor with a long, prestigious history of public service, including with the Department of Defense, the National Institutes of Mental Health, the United States Public Health Service, and the New York Department of Health, where he served as director from 1980-85. At that time, Dr. Carpenter started the School of Public Health at the University of Albany. Republic's expert witness on public-health issues, Dr. Christopher Teaf, is an expert in the evaluation of environmental contamination, waste management, and toxicology, but not a medical doctor. Dr. Teaf is a professor at Florida State University and owns a small consulting firm. The major part of Dr. Carpenter's career has been devoted to research. For the past ten years, he has focused more on human health, especially human disease from exposure to environmental contaminants. Dr. Carpenter has considerable experience with the adverse effects of landfills on human health, but his experience has been mostly with older landfills, where containment measures were few and offsite releases were many. Clearly, Dr. Carpenter's experience does not extend to the role of landfill design, construction, and operation in the transmission of human disease. Thus, Dr. Carpenter is qualified to opine on the effects of pollutants that may escape landfills, but not on the relationship of landfill design, construction, and operation on the probability that a landfill will transmit pollutants. For the most part, Dr. Carpenter did not attempt to address matters outside of his expertise. However, Dr. Carpenter testified that the risk of disease or injury increased in relationship to the proximity of the person to the landfill. This testimony can only be credited if one assumes that the landfills are identical in terms of design, construction, and operation and in terms of the environmental conditions of the landfill site. In other words, in real-world applications, it is impossible to credit this element of Dr. Carpenter's testimony, especially to the extent of his implicit suggestion that public health is unreasonably endangered by the construction of a landfill, in compliance with all rules, that satisfies all of the separation criteria and design criteria set forth in the rules, as discussed below. By contrast, Dr. Teaf focused on the details of the proposed landfill. Applying his knowledge of toxicology, Dr. Teaf determined that the proposed landfill adequately protects public health. In making this determination, Dr. Teaf analyzed the effects of various design and operational characteristics of the proposed landfill, including the double liner system, the leachate collection and management system, the selection of appropriate waste types, the procedures for the evaluation and covering of sludges, the prohibition against municipal garbage, the restrictions on household items, the monitoring of groundwater and surface water, the stormwater management system, and the plans to control dust and odors. Dr. Carpenter's testimony and the literature that he sponsored suggested important links between older landfills and a wide range of human disease. But the recurring problem with Dr. Carpenter's testimony and the research articles that he sponsored was the inability to link this information to the proposed landfill. All of the landfills studied in his research articles were older, and most of them appeared to have been designed, constructed, and operated under far more relaxed regulatory regimes than exist today. Nothing in Dr. Carpenter's testimony or sponsored literature attempted to delineate the design or operational characteristics of these landfills, such as whether they were double- or even single-lined, served by leachate circulation and recovery systems, limited as to materials that they could accept, or required to install stormwater management and water monitoring systems. 93. Analysis of the risk to public health posed by the proposed landfill requires consideration of the various means of transmission of the pollutants received by the landfill: water, land, and air. Of these, water requires little analysis, on this record. Even Dr. Carpenter conceded that the proposed landfill does not appear to pose a threat to groundwater. The double liner, leachate collection and recovery system, and groundwater monitoring plan support the finding that groundwater transmission of pollutants from the proposed landfill is unlikely. Transmission by surface water is also unlikely. Compared to groundwater monitoring, surface water monitoring is limited. For instance, there is only a single monitoring site. Also, as noted above, the stormwater pond for the leachate storage area is expected to discharge stormwater offsite during excessive storm events, at which time surface water samples will be taken. However, a comprehensive surface water management system is in place at the landfill and will prevent offsite discharges in all but a few excessive rain events. Transmission by land is also unlikely. The Application contains engineering analysis of the proposed stability of the side slopes and a determination that they will be stable. The discussion of sinkholes, below, does not affect this finding. Treating dust as transmission by air, the only other means by which pollutants may transmit by land is by animals, such as insects, rodents, and birds. An important factor limiting the activity of animals in spreading pollutants offsite is the fact that the proposed landfill will not receive garbage. Although putrescible waste may be received within other categories of waste, the prohibition against receiving garbage will greatly reduce the amount of potential food sources for animals and thus the utilization rate of the proposed landfill by these animals. A further reduction in animal utilization will be achieved through the daily and intermediate cover requirements. Thus, transmission of pollutants by animals is also unlikely. Transmission by air takes several forms. Pollutants may be transmitted as or on dust, with water in the form of aerosol, or as gas. In terms of how transmission by air is addressed by the Permit, this means of transmission potentially represents a greater threat than transmission by water or land for four reasons. First, the explicit focus of the Permit, as to gas, is to avoid explosive concentrations of methane and objectionable odors, but not the transmission of other pollutants by air. Second, the effect of the Permit is to prohibit the release of pollutants into the groundwater or offsite surface water and to prohibit the release of pollutant-bearing land offsite, but no such flat prohibition applies to the offsite release of pollutants by air. Third, the leachate recirculation system provides a good opportunity for the release of certain pollutants into the air by aerosol or evaporation, but similar releases to offsite land, surface water, or groundwater are prohibited. Fourth, scientific understanding of the effects of exposure, especially by inhalation, to pollutants, especially in the form of organic compounds, is continuing to develop: with the use of chemicals increasing three fold in the 50 years preceding 1995 and approximately 80,000 chemicals in use in 2002, only a few hundreds of these chemicals have been subjected to long- or short-term study, resulting in the discovery that about 10% of the chemicals in use in 2002 were carcinogens. Transmission by dust appears to be limited by the frequent covering and spraying of the working faces. Although nearby residents complain of dust in their homes, the practices of the less-regulated Class III landfill cannot be extrapolated to the proposed Class I landfill. Thus, the prospect of dust transmission of chemicals contained in the fill received by the proposed landfill appears also to be slight. The use of untreated leachate as the spray medium to control the dust itself raises two risks, however. First, spraying leachate will release chemicals in aerosol. The potential range of aerosol is great, especially as the landfill ascends toward its design height of 190 feet. However, the risk of transmission by aerosol is reduced to insubstantial levels by adding a Permit condition that prohibits spraying during windy conditions. Second, depositing leachate on the landfill face will release chemicals through evaporation. The point of spraying the landfill face is to control dust between the addition of the waste materials to the pile and the application of the cover. Between these two events, dry conditions will sometimes intervene and may cause the evaporation of certain, but not all, pollutants. The leachate acquires pollutants as it percolates down the waste column and into the leachate collection system. As Dr. Teaf noted, the leachate becomes more concentrated as it recirculates, but, otherwise, this record is largely silent as to the likely composition of the recirculated leachate. However, for landfills accepting sludge, higher levels of mercury may be present in the leachate. As reported by the Florida Center for Solid and Hazardous Waste Management at the University of Florida, in a report issued March 2007, and titled, "Design and Operational Issues Related to Co-Disposal of Sludges and Biosolids and Class I Landfills--Phase III," one study found that the concentration of mercury in the leachate of landfills that receive sludge is almost three times greater than the concentration of mercury in the leachate of landfills that do not accept sludge. The same study reported that total dissolved solids and chlorides were present at greater concentrations at the landfills that did not accept sludge and that other parameters--unidentified in the cited article--were not significantly different between the two types of landfills. Republic proposes to recirculate substantial volumes of leachate--sufficient, for instance, to raise the moisture content of the fill from 25 percent to 28.9 percent. The Permit allows the proposed landfill to operate six days per week, for a total of 312 days annually. The Operation Plan prohibits the application of leachate during rain, but the number of days annually during which rain extends for the entire day is few, probably no more than a dozen. These numbers suggest that Republic may apply as much as 3.6 million gallons annually of untreated leachate to the landfill face. The 12,000 gallon-per-day limit and restrictions on head in the leachate collection and removal system effectively limit the quantities of leachate that may be recirculated, but the sole provision addressing leachate water quality is the annual monitoring event described above. Given the time required to analyze the many parameters included in the EPA regulation, for most of the year between tests, Republic will be applying over three million gallons of leachate whose pollutant concentrations will be completely unknown. Some assurances emerge, though, when considering air transmission of pollutants by class. In general, on this record, as to transmission by gas, there appears to be an inverse relationship between a compound's volatility, which is a measure of its ability to enter the air, and a compound's persistence. VOCs are one of the most dangerous classes of pollutants to public health and include such carcinogens as benzene, tolulene, xylene and, the most dangerous of all VOCs, vinyl chloride, which is released upon the degradation of such common substances as plastics, carpets, and upholstery. Biogas, which is generated by the anerobic decomposition of organic compounds in a landfill, contains mostly methane and carbon dioxide, but also significant levels of VOCs. When inhaled, the primary results of exposure to VOC are respiratory irritation and allergenic effects. Volatility is measured by vapor pressure, which is a measure of a chemical's ability to get into the air. As their name suggests, VOCs enter the air easily. They are also capable of traveling great distances due to their light molecule. However, VOCs are easily destroyed by sunlight and diluted by wind. Other organic compounds common to landfills are only semi-VOCs, such as PCBs. Although less volatile, these chemicals, too, are hazardous to public health--in the case of PCBs, in any amount. Due to this fact and their persistence in the environment, the United States has prohibited the manufacture of PCBs for over 30 years. However, not only are PCBs considerably less likely to enter the air than VOCs, they also travel shorter distances than VOCs due to a heavier molecule. Dr. Carpenter opined that there is little evidence that PCBs are an issue in the proposed landfill. Another class of organic compound, 1000 times less volatile than even PCBs, is phthalates, which are used in the production of plastics. Phthalates pose significant threats to public health, especially reproductive health. However, the exceptionally low volatility of this compound renders transmission by evaporation highly unlikely. Much of the regulatory framework imposed on landfill design, construction, and operation arises out of concerns for the control of human pathogens, which are infection-causing organisms, such as bacteria, viruses, protozoa, and parasitic worms. One of the great advances in human longevity in the United States occurred in the early 1900s--not with the development of antibiotics or improved medical care--but with the implementation of basic sanitation control and the removal of pathogens from the drinking water. For the proposed landfill, sludge will be the primary source of pathogens. Sludge is nutrient-rich organic matter, which will be received at the proposed landfill without any treatment except possibly dewatering. Even with the acceptance of sludge, the proposed landfill presents little risk for the transmission of pathogens. Pathogens communicate disease only when a person is exposed to an effective dose and are better transmitted by direct contact or animal than air. Bacterial pathogens are themselves killed by wind, as well as sunlight, temperature, and humidity differentials, so the preferred means of air transmission would be aerosol versus gas. The record permits no findings as to the persistence of pathogenic viruses, protozoa, and parasitic worms. However, as noted above in connection with the land transmission of pathogens, the immediate application of lime and cover to the sludge will tend to prevent the release of effective doses of pathogens by air, as well. The last major class of pollutant that could be transmitted by air is heavy metals, such as mercury or lead. Although these metals produce a wide range of neurological diseases and generally interfere with cognition and behavior, Dr. Carpenter admitted that heavy metals were not as much of a concern as VOCs, presumably due to their resistance to vaporization. Even though transmission by air is not as tightly controlled as transmission by water or land, for the four reasons noted above, there is little risk of transmission by air--i.e., dust, aerosol, or gas--when the specific properties of likely pollutants are considered. In all but five respects, then, Republic has provided reasonable assurance that public health will not be endangered by pollutants released from the landfill by water, land, or air. First, to provide reasonable assurance concerning public health, the Permit needs a condition that prohibits spraying leachate during windy conditions, which DEP may define as it reasonably sees fit. As noted in the Conclusions of Law, this is a requirement in the rules and, due to its importance, should be restated explicitly in the Permit, which restates numerous other rule requirements. Second, to provide reasonable assurance concerning public health, the Permit needs more frequent monitoring of leachate water quality, at least at the frequency, as noted in the Conclusions of Law, set forth in the rules. Large volumes of untreated leachate will be recirculated through the landfill. Even if aerosol transmission is controlled, transmission by evaporation of some pollutants, although not the heavy metals, is possible. Also, pollutants are concentrated in recirculated leachate and thus the consequences of transmission into groundwater or surface water, however unlikely, become greater. At the same time, the action leakage rate is generous--to Republic, not the groundwater. At 100 gallons per acre per day, Republic is not required to report to DEP possible liner leakage until about 7300 gallons per day are lost to the surficial aquifer. Suitable for the detection of catastrophic failures associated with most sinkholes, this action leakage rate is too high to trigger action for small liner leaks. If Republic is to be allowed this much leakage into the groundwater, it must identify the leachate's constituents and their concentrations at least semi-annually. Third, to provide reasonable assurance concerning public health, the Application must extend the right of split testing to all of the parties in these cases, if DEP fails to exercise its right to take a split sample. The spraying of untreated leachate and generous limit applied to liner leakage before reporting and remedial action are required underscore the importance to public health of independent leachate testing. There is no reason to allow budgetary constraints or administrative oversight to preclude Petitioners and Intervenor, who are uniquely situated to suffer from the escape of excessive pollutants in the leachate, from providing, at their expense, this independent leachate testing. Fourth, to provide reasonable assurance concerning public health, the Permit needs to restate accurately the language of the rules concerning the extent of knowledge required of Republic, if it is to be liable for the acceptance of certain prohibited wastes. Fifth, to provide reasonable assurance concerning public health, the Permit needs to be modified to ensure that at least one spotter, whose sole responsibility is spotting, will be assigned to each working face while the landfill is receiving waste. Sinkholes The sinkhole issue arises in the geotechnical analysis of the sufficiency of the foundation to support the considerable loads of a landfill and also in the stability of the side slopes of the landfill. This analysis starts with consideration of the geology of the area, of which Republic's property is a part, and, among other things, the potential for sinkhole formation in the area. The Cedar Trail Landfill lies within the Bartow Embayment and along the eastern slope of the Lakeland Ridge of the Central Lake District Physiographic Province. This embayment is a large erosional basin partially backfilled with phosphatic sand and clayey sand of the Bone Valley Member. At this location, the top of the Floridan Aquifer is formed by Suwannee Limestone, which consists of white to tan, soft to hard, granular, porous, very fossiliferous limestone with interbedded dolomite. This rock unit is 110-140 feet thick. Atop the Suwannee Limestone sits the Hawthorne Group, which comprises the Arcadia Formation, at the base of which is the Nocatee Member, which is a relatively impermeable sand and clay unit. Atop the Nocatee Member is the Tampa Member, which consists of hard, dense, sandy, locally phosphatic, fossiliferous limestone. The top of this member, which is the top of the Arcadia Formation, is locally referred to as the "bedrock complex," which marks the lower limit of phosphate mining. Atop the Arcadia Formation, still within the Hawthorne Group, sits the Peace River Formation, which consists of phosphatic clayey sand and clayey sand. The lower portion of the Peace River Formation is a relatively impermeable, undifferentiated clayey unit locally known as "bedclay." The Bone Valley Member of the Peace River Formation is mined for phosphate and is locally known as "matrix." Atop of the Peace River Formation are undifferentiated surficial soils, typically consisting of silty sand, clayey sand, and some hardpan and organic soils. These materials are locally known as "overburden." Phosphate mining is prevalent in the area, including, as noted above, much or all of the Cedar Trail Landfill site. Strip mining for phosphate normally removes the entire surficial aquifer, just into the bedclay. Mined areas are then backfilled with overburden spoil soils, clay, waste clay, and sand tailings. After backfilling, the soil strata bear little resemblance to premining strata. Sinkholes are prevalent in the general area surrounding the Cedar Trail Landfill. A sinkhole is a surface depression varying in depth from a few feet up to several hundreds of feet and in area from several square feet to several acres. Sinkholes are typically funnel-shaped and open broadly upward. Sinkholes form when weakly acidic groundwater creates cavities in the calcium carbonate within limestone. Soils above these cavities erode into the cavities. In the area that includes the Cedar Trail Landfill, cover-collapse and cover- subsidence sinkholes predominate among sinkhole types. A cover-collapse sinkhole, which is typically steep- sided and rocky, forms when cohesive soils over a limestone cavity can no longer bridge the cavity under the weight of overlying soil and rock. At this point, the cohesive soils suddenly collapse into the cavity. These are more common in the part of the state in which the Cedar Trail Landfill is located. A cover-subsidence sinkhole occurs due to the gradual lowering of the rock surface as solutioning occurs in the subsurface rocks. This type of sinkhole develops as subsurface soluble rock is dissolved and overlying soils subside into the resulting shallow surface depressions. Regardless of the type of sinkhole, borings into sinkholes will reveal zones of very loose soil sediments that have washed downward into the cavernous voids within the bedrock. This very loose soil zone is called a raveling zone, which starts at the limestone layer, as the overlying soils begin to collapse into the solution features within the limestone. As the loosening works its way upward toward the surface, it eventually results in the subsidence of the ground surface and formation of a sinkhole. Considerable sinkhole activity has taken place in the immediate vicinity of Republic's property. Most visibly, a sinkhole formed in 2006 in 285-acre Scott Lake, 4.5 miles northwest of the landfill. This sinkhole drained the entire lake and destroyed several structures. The Florida Geological Service sinkhole database, which consists of anecdotal reports of sinkhole activity, some of which are unverified, includes 49 sinkholes within five miles of the proposed landfill. Two documented sinkholes have occurred within .17 mile of the landfill--one of which is reported to be 125 feet in diameter and 80 feet deep. Based upon the information contained in the preceding paragraph, Clint Kromhout, a professional geologist with the Florida Geological Survey, opined on August 23, 2009, that the potential for sinkhole formation "within the proposed site and surrounding area" is "low to moderate." Mr. Kromhout does not provide a definition of "low," but part of his opinion is shared by the Golder Report, which agrees that the sinkhole potential on the proposed site is "low." The potential for sinkhole formation in the general area surrounding the proposed landfill, as distinguished from the site itself, is at least moderate. In their Proposed Recommended Order, Republic and Intervenor necessarily concede: "All parties acknowledge that the proposed landfill site is in a general region that has a relatively high frequency of sinkholes as compared with the rest of the state of Florida." It is misleading to characterize the area surrounding the proposed landfill as of low potential for the formation of sinkholes, unless there is another category, like "nonexistent." But characterizing the sinkhole potential of the surrounding area as moderate is not determinative of the likelihood of sinkholes at the landfill's footprint, nor is a site-specific geotechnical investigation mooted by such a characterization. Rather, characterizing the sinkhole potential of the surrounding area as moderate dictates the intensity and scope of the ensuing geotechnical investigation, if the investigation is to provide reasonable assurance of the structural integrity of the proposed landfill. Acknowledging moderate potential for sinkhole formation in the surrounding area, Republic has appropriately relied on three geotechnical reports, including three sets of boring data. The final of these reports, the Hanecki Report, is based on the collection and analysis of boring data, as well as a review of the data and analysis contained in the two earlier geotechnical reports, the Ardaman Report and Golder Report. The boring data reveal that the proposed landfill site features four units. Nearest the surface is Unit 1, which is brown to dark brown, medium- to fine-grained sand with minor amounts of clayey silt. Unit 1 is 0-10 feet thick. Next down is Unit 2, which is tan to gray, medium- to fine-grained sand with increasing silty clay or clayey silt. Unit 2 is 5-10 feet thick and generally marks the upper limit of fine-grained, granular soils (i.e., clayed sands and silty sands). Unit 3 is orange brown to yellow brown, gray and tan silty clay to clayey silt or fine sand and silty clay. Unit 3 is 5-15 feet thick. Unit 4 is gray and tan clayey silt or silty clay with minor amounts of fine sand. This material is very stiff or very dense, and most borings terminated in this unit. The few borings that penetrated this unit suggest that it may consist of dolomitic sandy clays and silts and dolomitic limestone to depths greater than 100 feet below grade. Units 3 and 4 generally mark the upper limits of low permeability/low compressibility soils. The Hanecki investigation comprised two main steps. First, Hanecki retained a subconsultant to perform electrical resistivity imaging (ERI) along 100-foot-wide transects run across the site. Any anomalies revealed by the ERIs were to be followed by standard penetration test (SPT) borings, which permit soil testing at predetermined intervals, as well as a measure of the compressibility of the soils. Compressibility is measured during the soil-testing intervals, during which the drill bit is replaced by a soil sampler. The driller records the number of blows required for a 140-pound hammer falling 30 inches to produce 12 inches of penetration. The value is expressed in N-values, where N represents the number of such blows. Looser soils produce lower N values. Another important piece of information obtained during SPT boring is the partial or total loss of circulation fluid during drilling. While the drill is penetrating soil, a slurry circulates through the borehole to prevent the collapse of the sides of the hole. This slurry is recycled during drilling, but, if the drill encounters a void, all or part of the circulation fluid is lost. The ERI survey revealed no real anomalies because of a narrow range of resistance values. However, taking relatively small differences in resistivity as an anomalies, Hanecki identified 14 features of interest. At each of these locations, Hanecki performed an SPT boring. Because the ERI transects were unable to span the two onsite ponds, Hanecki added two locations for SPT borings adjacent to each side of each pond, for a total of four additional SPT borings. At the request of DEP, Hanecki added a nineteenth SPT boring at Golder site G-11, which had revealed low N-values during Golder's borings. Hanecki extended the borings into "refusal" quality soil, which was defined as soils requiring more than 50 blows of the 140-pound hammer to achieve six inches or less of penetration. All of Hanecki's SPT borings encountered very hard limestone. Among the most significant findings of Hanecki's borings, only one boring, G-11, experienced any circulation fluid loss, and this was estimated at 50 percent. However, it is more likely that this partial circulation fluid loss is due to loosely deposited sands than a void that might be indicative of conditions suitable for sinkhole formation. Not all circulation losses indicate voids that that will result in sinkhole formation. Also significant among Hanecki's findings is a clayey soil, or bedclay, at every SPT boring, which severely limits hydraulic recharge to the limestone. By impeding vertical migration of surface and shallow subsurface water to the limestone layer, this bedclay "greatly inhibits limestone erosion." This bedclay also supports the looser soils above the bedclay and thus prevents raveling, without which sinkholes cannot form. Two borings--G-11 and F3-1--lacked a layer of Unit 3 or 4 soil above the limestone, but Hanecki concluded that the Unit 2 layers above the limestone at these locations contained sufficient clay or clayey sand to serve the same functions of impeding the downward movement of groundwater and preventing the downward movement of loose soils. This conclusion appears reasonable because Unit 2 is the uppermost reach of the finer- grained materials, of which clays and silts are examples when compared to sands. There is obviously some variability in the distribution of finer- and coarser-grained materials within each occurrence of Unit 2 soils. Hanecki's findings indicated intervals of loose soils, sometimes at depth, which typically would suggest raveling zones. At the proposed location, though, these findings do not support raveling due to the underlying bedclay layer and the history of mining, which probably introduced looser soils typically found closer to the surface through the entire 40-foot depth of the mine cut. Based on these findings, the Hanecki Report concludes that, regardless of at least moderate potential for sinkhole potential in the area, the footprint of the proposed landfill has an acceptably low risk of sinkhole development to permit development of the proposed landfill. This is a reasonable conclusion because it is supported by the data collected by Hanecki and his reasoned analysis of these data. Hanecki's conclusion is also supported by the data and analysis contained in the Golder Report and Ardaman Report, which are based on an additional 84 SPT borings, post- reclamation. Only about 12 percent of these SPT borings reached the limestone, and they cover all of Republic's property, not merely the footprint of the proposed landfill. Even so, these borings confirm two important findings of the Hanecki Report. First, they produced data indicative of an extensive bedclay layer intact on Republic's property. Second, the Ardaman and Golder borings reveal only two or three instances of partial circulation loss that, like the sole occurrence of partial circulation loss in the Hanecki borings, are located on Republic's property, but outside the footprint of the proposed landfill. Republic has provided reasonable assurance that the site will provide an adequate foundation for the proposed landfill and sinkholes are unlikely to undermine the structural integrity of the proposed landfill.

Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order granting the Construction Permit and Operation Permit, but only if the Operation Permit is modified by the addition of the five items identified in paragraphs 172, 174, 175, 181, and 187. DONE AND ENTERED this 8th day of October, 2010, in Tallahassee, Leon County, Florida. S ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of October, 2010. COPIES FURNISHED: Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Tom Beason, General Counsel Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Mimi A. Drew, Secretary Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Ronald L. Clark, Esquire Clark, Campbell & Mawhinney, P.A. 500 South Florida Avenue, Suite 800 Lakeland, Florida 33801-5271 William D. Preston, Esquire William D. Preston, P.A. 4832-A Kerry Forest Parkway Tallahassee, Florida 32309-2272 Jennings Kemp Brinson, Esquire Clark, Campbell & Mawhinney, P.A. 500 South Florida Avenue, Suite 800 Lakeland, Florida 33801 Sean R. Parker, Esquire Boswell & Dunlap, LLP 245 North Central Avenue Bartow, Florida 33830-4620 Ralph A. DeMeo, Esquire Hopping, Green, & Sams, P.A. 119 South Monroe Street, Suite 300 Tallahassee, Florida 32301 Stanley M. Warden, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Station 35 Tallahassee, Florida 32399-3000 Paula L. Cobb, Esquire Hopping Green & Sams, P.A. Post Office Box 6526 Tallahassee, Florida 32314 John W. Frost, Esquire Frost Sessums Van den Boom & Smith, P.A. Post Office Box 2188 Bartow, Florida 33831 John Stanley Fus Highland Lakes Estates HOA 2190 Boardman Road Bartow, Florida 33830

CFR (4) 40 CFR 25840 CFR 261.2440 CFR 261.4(b)(1)40 CFR 60 Florida Laws (4) 120.569120.57403.703403.707
# 1
TOWN OF DAVIE vs. BROWARD COUNTY AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-001239 (1983)
Division of Administrative Hearings, Florida Number: 83-001239 Latest Update: Oct. 21, 1983

The Issue The ultimate issue to be resolved in this proceeding is whether the Department of Environmental Regulation should issue a permit to Broward County authorizing construction of the proposed Cell 14 extension of the Broward County landfill located in the Town of Davie, Florida. Broward County and the Department of Environmental Regulation contend that Broward County has provided reasonable assurance that the proposed facility will meet the requirements of the Department's rules and regulations and not cause pollution in contravention of the Department's standards. The Town of Davie contends that the proposed facility will not meet the Department's requirements and will result in pollution in contravention of the Department's standards.

Findings Of Fact Broward County presently operates a landfill known as the Davie Landfill on a tract of land comprising 200 acres within the Town of Davie, Broward County, Florida. The existing sanitary landfill includes 13 cells which cover approximately 20 acres on the northeastern portion of the site. The landfill had an original design elevation of50 feet. The Department of Environmental Regulation, in a separate permitting proceeding, has authorized an increase to the height of the existing landfill to 90 feet. The permit authorizing increasing the height of the existing landfill has been challenged by the Town of Davie and is the subject of a separate proceeding before the Division of Administrative Hearings. The site which includes the landfill also has a sludge lagoon and trash landfill located in close proximity to the sanitary landfill. The sludge lagoon was used until sometime in 1981 for disposal of septic tank clean-out, sludges, grease trap waste, and wastewater treatments. The trash landfill was designed primarily for disposal of yard trash. The existing landfill has vertical side slopes of 3.5 to l. In other words, the height of the landfill increases along sides by i foot for every 3.5 feet traveled horizontally. Through this application, Broward County is seeking approval to expand its sanitary landfill by adding a proposed Cell 14. Cell 14 would constitute a Class I landfill since it will receive in excess of 20 tons of solid waste per day. The proposed Cell 14 would be constructed along the existing western face of Cells 1 through 13. It would ultimately be constructed to a height of 90 feet and would be capped with an impervious substance. The western side slope of the proposed cell would also be 3.5 to 1. Cell 14 would cover approximately 11 acres, bringing the total size of the sanitary landfill to just over 30 acres. With Cell 14, the sanitary landfill would continue to operate until approximately 1986. Containing leachate and preventing it from entering surface or ground waters is a most important consideration in determining whether to permit sanitary landfills. Leachate is water that has passed through refuse and been contaminated by the refuse. If significant amounts of leachate from Cell 14 enters into surface and ground waters, violations of the Department's water quality standards would be likely. Several features have been designed into Cell 14 to prevent introduction of leachate into surface and ground waters. The base of the cell would have a high density polyethylene liner to prevent percolation of Leachate that collects at the bottom of the cell into groundwater. A leachate collection system consisting of pipes and manholes has been devised. As leachate collects at the base of the cell, it will be dumped into tank trucks and carried to nearby wastewater disposal plants where it will be treated. A stormwater collection system has been designed so that initial stormwater runoff will be pumped to the leachate collection system and tested. If significant pollutants are contained in the stormwater runoff, it can continue to be pumped into the leachate collection system and ultimately removed to off-site treatment plants. If there are not significant pollutants in the runoff, runoff will be collected in a swale system and ultimately percolate into groundwater. Water that leaves the site in this manner is not likely to cause violations of Department of Environmental Regulation standards either in surface or ground waters. Numerous technological advances have occurred since Cells 1 through 13 of the Davie Landfill were designed and constructed. These cells have a designed-in leachate collection system. The system presently functions adequately, except that the liners under the earlier cells appear to be breaking down. It is apparent that the liner under Cells 1 through 4 has deteriorated to the extent that all leachate from these cells is not collected in the leachate collection system, but enters the groundwater below the landfill. Leachate from a landfill of this sort and magnitude that enters groundwater is likely to cause pollution in violation of the Department's standards. Leachate is presently entering the groundwater from Cells 1 through 4. The nature of the liner under the remaining original cells is not known. It is thought to be made of asphalt. Many forms of asphalt, obviously including the kind that was used to line Cells 1 through 4, are not capable of containing Leachate for an extended period of time. If the liner breaks down, the leachate collection system under all of the original cells will no longer function, and leachate will enter the groundwater, causing violations of Department of Environmental Regulation standards. There will not be an impervious liner between the existing cells of the Davie Landfill and the proposed Cell 14. It has been estimated that the cost of such a liner would be prohibitive. There will be limerock placed between the existing cells and the proposed cell; however, limerock is permeable. Some Leachate from Cell 14 will seep into the existing cells. Some of the leachate from the proposed Cell 14 that enters the existing Cells 1 through 4 will find its way into groundwater under the landfill. Leachate that enters the remaining cells will also find its way into groundwater if the liner under these cells breaks down as the liner under Cells 1 through 4 has broken down. If Leachate from the proposed Cell 14 enters groundwater under the site of the landfill, it is likely to cause pollution in violation of Department of Environmental Regulation standards. Groundwater in the area of the Davie Landfill flows generally from the northwest to the southeast. Some of the groundwater from the site of the sanitary landfill is likely to find its way into a canal which is located just to the south of the site. this is the C-11 Canal. If leachate from the proposed Cell 14 enters groundwater under the site of the landfill, it is likely to ultimately cause violations of Department of Environmental Regulation standards in the C-11 Canal. Except for the fact that the liners under the existing cells of the sanitary landfill are subject to deterioration, the leachate collection system can function appropriately. The leachate collection system for the proposed Cell 14 can also function without allowing introduction of leachate into surface and ground waters. The leachate collection systems utilize pipes that are presently buried under the existing landfill and will be further buried by the construction of Cell 14. The pipes that are presently being used, and are proposed to be used, are designed to withstand pressure greater than would be imposed on them. Furthermore, they are being placed in such a manner (surrounded by rock and utilizing ball joints) as to reduce the pressure imposed upon them. It is possible that one of the pipes could break and that leachate could thus escape from the Leachate collection system. This possibility is not a likely one, however, given the design parameters of the pipes and the nature of their installation. The fact that the leachate collection system for existing cells of the Davie Landfill would be buried under the proposed Cell 14 does not raise a significant danger that the system will break down. Again, the design parameters of the pipes and the nature of their installation render breakage unlikely. The sludge pit that is located just to the southwest of the sanitary landfill and the trash landfill that is located just to the south of the sanitary landfill offer potentially severe threats to the integrity of ground and surface waters on and off of the site. The sludge pit is a hazardous waste site. The trash landfill is not designed to prevent substances placed on the landfill from percolating into groundwater. It does not appear that construction of the proposed Cell 14 addition to the sanitary landfill would increase the risk of pollution that the sludge pit and trash landfill present. It does not appear that construction of the proposed Cell 14 would cause significant additional surface or ground water flows that would increase the risk of material from the sludge pit or the trash landfill from entering surface or ground waters. The applicant has failed to provide reasonable assurance that its proposed addition to the Davie Landfill will not result in violations of Department of Environmental Regulation standards contained in Chapters 17-3, 17- 4, and 17-7, Florida Administrative Code. While the proposed cell has been designed with appropriate liners and with an appropriate leachate collection system, its location abutting an existing landfill which does not have an adequate liner preventing percolation of leachate into groundwater increases the risk of that occurring. It appears that the only means of preventing or reducing that risk is either to close off the existing cells, or to place a liner between the existing cells and any addition in order to prevent flows of Leachate from new landfill activities into the existing cells.

Florida Laws (1) 120.57
# 2
DAVID AND LISA CIMINI, MIRIAM RESTO, TIM MCCORMACK, JOHN MAPP, AND JIM TAYLOR vs LAKE ENVIRONMENTAL RESOURCES, LLC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 06-002005 (2006)
Division of Administrative Hearings, Florida Filed:Tavares, Florida Jun. 07, 2006 Number: 06-002005 Latest Update: Dec. 15, 2006

The Issue The issue is whether a permit should be issued to Respondent, Lake Environmental Resources, LLC (LER), authorizing the construction and operation of a construction and demolition debris disposal facility in unincorporated Lake County, Florida.

Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: The Parties LER, whose mailing address is Post Office Box 2872, Windermere, Florida, is a limited liability company authorized to do business in the State. LER's principals are Linwood Brannon and Richard Bazinet, both of whom have had at least ten years' experience in the operation and construction of demolition debris disposal facilities. The Department is an agency of the State that is authorized under Chapter 403, Florida Statutes (2005)2, to evaluate applications and issue permits for construction and demolition debris disposal and recycling facilities. The permit in issue here was processed, reviewed, and approved for issuance by the Department's Central District Office in Orlando, Florida. Petitioners Miriam Resto and Jim Taylor did not appear at the final hearing or otherwise present any evidence as to where they resided or how their substantial interests would be determined by the issuance of a permit. Petitioner Timothy L. McCormack resides at 11321 Valley View Road, Howey-in-the-Hills, Florida. Mr. McCormack's home is "a little over a mile" north-northwest of the proposed facility. His concern with the proposed facility is generally over contamination from the landfill, and not contamination occurring at the property. Petitioner John A. Mapp, Jr., resides at 21307 County Road 561, Clermont, Florida, which is approximately one-half mile from the proposed facility. Mr. Mapp's home is upgradient from the facility and consequently he has no "individual concerns" as to how the proposed facility would affect his home. He is concerned, however, with potential groundwater contamination from the facility. Petitioners David and Lisa Cimini did not testify at the final hearing or otherwise present any evidence as to where they resided or how their substantial interests would be determined by this proceeding. According to the Partial Pre- Hearing Stipulation filed by Respondents, however, they reside at 21423 County Road 455, Clermont, Florida, which is near the proposed facility. Background On July 26, 2005, LER filed an application with the Department for a permit authorizing it to construct and operate a facility for construction and demolition debris disposal and recycling in an unincorporated area of the County. A lengthy definition of construction and demolition debris is found in Florida Administrative Code Rule 62-701.200(27), which reads as follows: discarded materials generally considered to be not water soluble and non-hazardous in nature, including but not limited to steel, glass, brick, concrete, asphalt material, pipe gypsum wallboard, and lumber, from the construction or destruction of a structure as part of a construction or demolition project or from the renovation of a structure, including such debris from construction of structures at a site remote from the construction or demolition project site. The term includes rocks, soils, tree remains, trees, and other vegetative matter which normally results from land clearing or land development operations for a construction project; clean cardboard, paper, plastic, wood, and metal scraps from a construction project; effective January 1, 1997, except as provided in Section 403.707(12)(j), F.S., unpainted, non-treated wood scraps from the facilities manufacturing materials used for construction of structures or their components and unpainted, non-treated wood pallets provided the wood scraps and pallets are separated from other solid waste where generated and the generator of such wood scraps or pallets implements reasonable practices of the generating industry to minimize the commingling of wood scraps or pallets with other solid waste; and de minimus amounts of other non-hazardous wastes that are generated at construction and demolition projects, provided such amounts are consistent with best management practices of the construction and demolition industries. Mixing of construction and demolition debris with other types of solid waste will cause it to be classified as other than construction and demolition debris. The facility will be located on a 44.33-acre site one- half mile west of State Road 561, off County Road 455, in an unincorporated part of Lake County. Based on this description, it appears that the facility will be located east of Howey-in- the Hills, west of Tavares, and approximately half-way between Astatula and where State Road 561 crosses the Florida Turnpike to the southwest. The site presently has an active sand mine (borrow pit) that covers an area of approximately twenty-two acres. The facility intends to recycle metal, concrete, asphalt, wood chips, and PVC (polyvinyl chloride) and will serve areas in Lake County and nearby communities. In response to LER's initial application, the Central District Office submitted a Request for Additional Information dated August 22, 2005, asking for additional well and site information, operations plan details, and financial assurance clarification. On October 20, 200, LER submitted its Response to Request for Additional Information. While the application was being processed, Mr. Cimini advised the Department that two additional wells surrounded the property, including one that had recently been installed on property owned by Mr. Gary Sprauer that lies within five hundred feet of the limits of waste disposal of the facility. On November 18, 2005, the Department submitted an additional Request for Additional Information, in which it brought up the fact that Mr. Cimini had advised the Department of the existence of these wells. On November 28, 2005, LER submitted its Response to Request for Additional Information, in which it stated that only one well, which belonged to a Mr. Sprauer, had been drilled within five hundred feet of the proposed facility; that there was no electricity to the well; that the nearest residence was approximately seven hundred feet away; and that the well was not approved or being used as a potable water well. Therefore, LER asserted that the Department should not treat the Sprauer well as a potable water well subject to the five-hundred-foot setback from potable water wells for landfills established in Florida Administrative Code Rule 62-701.300(2)(b). LER's submittal provided additional information on the geology and operational aspects of its proposed facility. On December 6, 2005, LER submitted additional information in response to items discussed at a meeting held between the Department and LER on December 2, 2005. The submittal contained further information about potential drinking water wells around the proposed facility, and LER reasserted that the Sprauer well should not be treated by the Department as a potable drinking water well. Based upon its own investigation, however, the Department concluded that the Sprauer well "was a bona fide drinking water well for domestic supply." On January 6, 2006, Mr. Bradner, a Department solid and hazardous waste program manager who was assisting in the processing and review of the application, wrote a memorandum to the file confirming that the Department considered the application complete as of December 6, 2005. On February 10, 2006, LER provided additional hydrologic and operational information in order to try to convince the Department not to apply the five-hundred-foot setback to the Sprauer well. This information showed that the Sprauer well would be upgradient from the proposed facility. The Department allows waste to be placed within five hundred feet of an existing potable water well based upon site-specific conditions as demonstrated by an applicant. See Fla. Admin. Code R. 62-701.300(2)(b). On March 27, 2006, in response to the Department's comments on its submittal of this additional information, LER submitted further hydrologic and modeling information to support its contention that groundwater flowed away from the well belonging to Mr. Sprauer. On April 27, 2006, LER provided the Department with further refinement of its groundwater model to demonstrate that there would be no impact to the Sprauer well. On May 4, 2006, the Central District Office issued notice of its intent to approve the application and issue a permit to LER. Of significance here is the fact that the Department did not require LER to install a liner and leachate collection system. This was consistent with the terms of Florida Administrative Code Rule 62-701.730(4)(a), which does not require a liner unless the Department demonstrates that the facility is "reasonably expected to result in violations of ground water standards and criteria." On May 17, 2006, Petitioners filed their Petition challenging the issuance of the permit. As grounds, Petitioners alleged that there is a substantial risk that the surrounding groundwater will be contaminated by leachates from the facility, and that the Department should accordingly require LER to (a) install a liner and associated leachate recovery system in their facility and (b) post a surety bond necessary to maintain the system in good working order and to fund a toxic cleanup should it become necessary. The Proposed Project Among other things, the application included an engineering report, an operations plan, a geotechnical evaluation of the stability of the site, a hydrological investigation, a stormwater management plan, a reclamation and closure plan, and financial assurance documentation. These elements are required by Florida Administrative Code Rule 62- 701.730, which governs this type of application. The proposed facility is to be located on a 44.33-acre parcel in a rural area that has been the site of a sand and clay borrow pit. The pit has been mined for the last thirty years, has been permitted by Lake County as a mine since 1986, and before being used as a mine was the site of an orange grove. As explained by Mr. Golden, the proposed facility's project manager, the site is "high and dry" and "a good site for a landfill." The water table is at least one hundred feet below the ground surface. There is a confining layer of clays and sandy clays approximately one hundred fifty feet below the ground surface at the site of the proposed facility, and the layer has very low hydrologic conductivity, that is, 1,000 to 10,000 times less permeable than the surface sands. The Floridan Aquifer is approximately two hundred feet below ground surface. The horizontal velocity of the groundwater at the site is approximately two feet per year, and the vertical velocity about 1.3 inches per year. As a result, the groundwater monitoring system at the proposed facility would detect any contamination that might be emitted. In addition, approximately twenty feet of dry soils underlying the landfill would absorb whatever comes out of the landfill to begin with, just like a septic tank. The confining layer would be approximately one hundred to one hundred twenty feet below the landfill base and would be anywhere from twenty to forty feet deep. As a result, it is highly unlikely that any potential contaminants that hypothetically might be emitted from the facility would ever reach the Floridan Aquifer. The Proposed Permit On May 4, 2006, the Central District Office issued its intent to issue the permit. Attached to that intent to issue was a Draft Permit. The Draft Permit restricts disposal of solid waste exclusively to construction and demolition debris (as defined in the rule cited above) and requires LER to comply with an Operations Plan developed by LER. Among other things, the Operations Plan provides for operators trained in spotting and turning away unacceptable waste and other screening procedures to ensure nondisposal of unacceptable waste. The Operations Plan exceeds minimum Department rule requirements. The Operations Plan prohibits disposal of CCA (chromated copper arsenate) pressure treated wood and has a special screening procedure to ensure that these wood products do not come into the facility. The Draft Permit requires LER to install a system of groundwater monitoring wells that surround the property at both shallow and deep depths to detect any potential contaminants coming off of the site. Thus, LER will be required to monitor the surficial aquifer, the Floridan Aquifer, and adjacent wells to ensure protection of area groundwater. The wells will act as a form of early warning indicator so that corrective action can be undertaken in the event the wells show a potential threat to drinking water beyond the property boundary of the proposed facility. The Draft Permit requires two wells to be installed immediately to the north of the Sprauer well, even though it is upgradient from the site. To be conservative and prudent, the Department is requiring that the number of wells that LER must install be substantially greater than the minimum required under Department rules. Based upon the hydrologic evaluation and the proposed permit conditions, Mr. Golden concluded that LER has provided reasonable assurance that the proposed facility will not discharge pollutants in contravention of Department standards or rules. Mr. Bradner agreed with this conclusion and likewise concluded that LER had provided reasonable assurance that the proposed facility will comply with all of the required statutes and rules. The weight of the evidence supports these conclusions. The weight of the evidence also supports Mr. Golden's conclusion that based upon the hydrologic evaluation and the proposed permit conditions, the proposed facility will not be a source of contamination for wells within or greater than five hundred feet of the proposed facility. In the same vein, Mr. Bradner determined that the Sprauer well was the only existing potable drinking water well within five hundred feet. Both experts concluded that the Sprauer well would not be adversely impacted based upon the Department's review of the groundwater modeling data provided to it by LER. Finally, the weight of the evidence supports Mr. Golden's conclusion that, based upon the hydrologic evaluation and the proposed permit conditions, the Department should not require LER to install a landfill liner at the proposed facility. Mr. Bradner agreed with that conclusion. Petitioners' Objections In their Petition, Petitioners have raised the following objections to the issuance of a permit: That because the proposed facility would have no liner, the local environment and drinking water supplies would not be adequately protected from contamination; That the application significantly underestimates the amount of recharge to local aquifers; That the application ignores or underestimates the ecological fragility of the area; and That the location of the Sprauer well should require a reconfiguration of the footprint of the proposed facility. As relief, the Petition asks that the Department require a liner and associated leachate recovery system and adequate financial assurance to ensure proper operation and cleanup if necessary. During opening argument, Petitioners raised one more issue not previously raised in their Petition — - the potential cumulative impacts of the proposed facility in conjunction with two other landfills in the area. This allegation was not timely raised, however, and has been disregarded. The positions taken by Petitioners (other than cumulative impacts) appear to be interrelated, that is, the Department should require a liner because the area is ecologically fragile and recharge is greater than calculated by LER. In support of their position, Petitioners first presented the testimony of Mr. McCormack, who is engaged in the commercial nursery and landscaping business. Mr. McCormack identified the presence of CCA treated wood as his main concern from a contamination standpoint. His concern is that a possible spread of leachate will result from mingling the wood with rainwater or groundwater and that the surrounding groundwater (which ultimately flows into Double Run Springs, the Harris Chain of Lakes, and the Floridan Aquifer) would be adversely impacted. Mr. McCormack estimated that the edge of the Double Run Springs system was approximately 2,500 feet, or around one- half mile, from the site. He expressed the opinion that it was physically impossible to remove such wood prior to its being landfilled. Mr. McCormack conceded, however, that he was not an expert on landfill management or hydrology and had no personal experience with the operation of a landfill. There is specific language in LER's Operations Plan prohibiting the disposal of CCA treated wood and requiring best management practices to enforce the prohibition against the disposal of CCA treated wood. This requirement is mandatory, and not voluntary, and provides reasonable assurance that CCA treated wood would not be a potential source of contamination. The testimony of expert witnesses Bradner and Golden, who expressed this view, is accepted as being more credible on this issue. Petitioners also presented the testimony of Mr. Mapp, who critiqued the hydrological investigation performed by LER by asserting that the recharge to the Floridan Aquifer is four or five times the amount stated in the application. He also opined that LER's evapotranspiration rates were understated.3 Mr. Mapp is a systems analyst for Lockheed Martin Missiles and has a master's degree in business and an undergraduate degree in physics. While highly educated, Mr. Mapp has no prior experience in any kind of hydrologic, geologic, chemical, or similar types of analyses, or any analyses of the rate of transport of chemicals in the environment. The knowledge and opinions rendered in this case by Mr. Mapp were obtained through personal research after the permit application was filed. Mr. Mapp opined that LER's recharge calculations constitute a "significant discrepancy." He acknowledged, however, that his estimate of the true speed of downward flow of water at the site of the proposed facility was "just off the cuff" and did not factor in the effects of applying cover to, and the filling and capping of, the landfill. He did not know how fast particular contaminants may migrate through the groundwater or what volume of waste might be necessary to cause a violation of groundwater quality standards. He also could not give a specific calculation of where a contaminant might be located after a set period of years. Unlike the other experts in this case, the witness had not calculated Floridan Aquifer recharge rates or otherwise used Darcy's Law.4 Even if the permit application underestimated the recharge rate, the thickness of the confining layer below the base of the proposed facility, which was conservatively estimated, would cause groundwater to flow horizontally, not vertically, once the confining layer is reached. As explained by Mr. Golden, LER did not rely exclusively on the recharge calculations that Mr. Mapp relied upon in determining recharge rates. Separate information regarding the permeability of the confining layer provides additional support for the recharge calculations. Mr. Mapp also opined that LER's evapotranspiration rate calculations were underestimated, based upon his review of a study of a deforested site elsewhere in the Lake Wales Ridge. He assumed the evapotranspiration rate in that study (for a site located fifteen miles away) would be applicable to the site of the proposed facility, and he then assumed that the evapotranspiration rate identified in the permit application for the proposed facility would be applicable only to the properties adjacent to the proposed facility. There is, however, no scientific basis for drawing an analogy between the borrow pit that is the location of the proposed facility and the deforested site with different geological characteristics about which Mr. Mapp read in the study he relied upon for his conclusions. Furthermore, LER undertook site-specific analyses of the permeability of the soils underlying the site of the proposed facility, whereas Mr. Mapp's calculations were based upon assumptions drawn from a study of a site fifteen miles away. The testimony of Mr. Golden is found to be credible and persuasive on this issue. Finally, there was no evidence concerning Petitioners' contention that LER should post a surety bond necessary to maintain the system in good working order and to fund a toxic cleanup should it become necessary. Therefore, no modification to the permit in this respect is required.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting the application of Lake Environmental Resources, LLC, for a permit authorizing the construction and operation of a construction and demolition debris disposal and recycling facility in unincorporated lake County. DONE AND ENTERED this 8th day of November, 2006, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of November, 2006.

Florida Laws (3) 120.569120.57403.707
# 3
WRB ENTERPRISES, INC. vs ANGELO`S AGGREGATE MATERIALS, LTD., D/B/A ANGELO`S RECYCLED MATERIALS AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 09-001545 (2009)
Division of Administrative Hearings, Florida Filed:Temple Terrace, Florida Mar. 23, 2009 Number: 09-001545 Latest Update: Sep. 16, 2013

The Issue The issue to be determined in this proceeding is whether Angelo's Aggregate Materials, LTD ("Angelo's") is entitled to permits from the Department of Environmental Protection ("Department") to construct and operate a Class I landfill in Pasco County.

Findings Of Fact The Parties The Department is the state agency with the power and duty under chapter 403, Florida Statutes, to review and take action on applications for permits to construct and operate solid waste management facilities, including landfills. Angelo's is a Florida limited partnership authorized to conduct business under the name Angelo's Recycled Materials. Angelo's filed the permit applications which are the subject of this proceeding. Angelo's owns the property on which the proposed landfill would be constructed and operated. Crystal Springs Preserve is a Florida corporation that owns approximately 525 acres in Pasco County, Florida on which is located Crystal Springs, a second magnitude spring that flows into the Hillsborough River. The property is about 10 miles south of Angelo's proposed landfill site. Crystal Springs Preserve's primary business activities are selling spring water for bottling for human consumption and operating an environmental education center that focuses on Crystal Springs and the Hillsborough River. Crystal Springs Preserve hosts approximately 50,000 visitors annually at the environmental education center. Crystal Springs Preserve holds a water use permit which authorizes it to withdraw up to 756,893 gallons of water per day (annual average) from Crystal Springs for production of bottled water. The water is transported about three miles to a water bottling facility operated by Nestlé. Nestlé is a private corporation engaged in the business of bottling and selling spring water. Nestlé purchases spring water from Crystal Springs Preserve. Nestlé's "Zephyrhills Spring Water" brand is composed of approximately 90 percent Crystal Springs water and 10 percent Madison Blue Spring water. The only water treatment applied by Nestlé is filtering the water to remove gross contaminants and passing the water through ultraviolet light or ozone to kill any potential bacteria before bottling. Nestlé has established "norms" for its spring water and would not be able to use the water from Crystal Springs if its chemical composition varied significantly from the norms. WRB is a Florida corporation that owns 1,866 acres in Pasco County known as Boarshead Ranch. Boarshead Ranch is adjacent to the east and south of Angelo’s property and is approximately 3,000 feet from the proposed landfill at its closest point. Boarshead Ranch is currently being used for agricultural, recreational, residential, and conservation purposes, including wildlife management. Nearly all of Boarshead Ranch is subject to a conservation easement held by the Southwest Florida Water Management District (SWFWMD). The conservation easement allows WRB to continue agricultural operations. Numerous agricultural water wells are located on Boarshead Ranch. WRB holds a water use permit which authorizes the withdrawal of 820,000 gallons per day (gpd) (annual average) for a number of uses, including production of agricultural products, animal drinking water, and personal use. The City of Zephyrhills is located in Pasco County and is a municipal corporation. Zephyrhills' water service area encompasses Zephyrhills and portions of Pasco County. Zephyrhills owns, operates, and maintains a water distribution and transmission system of pipes, pump stations, and storage tanks within the City and its service area. Zephyrhills holds a water use permit which authorizes nine potable water supply wells with a combined withdrawal of 2.9 million gallons per day ("mgd") (annual average). Zephyrhills has two new production wells located about two miles southeast of the proposed landfill. The City of Tampa owns and operates the David L. Tippin Water Treatment Plant, the Hillsborough River dam, and the City of Tampa reservoir on the Hillsborough River. Flows from Crystal Springs make up a substantial amount of the water in the Hillsborough River, especially during drought conditions when the spring flow accounts for about 50 percent of the flow. The City of Tampa holds a water use permit which authorizes the withdrawal 82 mgd (annual average). The City of Tampa owns, operates, and maintains a water distribution and transmission system of pipes, pump stations, and storage tanks within the City and its service area. Carl Roth, Marvin Hall, and Louis Potenziano own property in Pasco County near the proposed landfill site. Roth's property is 3.5 miles west of the proposed landfill site; Hall's property is located approximately one mile southwest of the site; and Potenziano's property is 1.6 miles to the south/southeast of the site. Roth, Hall, and Potenziano have water wells on their properties. The record does not establish that John Floyd owns property in the area. Floyd and Associates, Inc., owns about 55 acres in the area and holds a water use permit authorizing the withdrawal of water for agricultural uses. The Stipulated Agreement On March 1, 2010, Angelo's filed with DOAH a "Stipulated Agreement" signed by all parties. The Stipulated Agreement states in relevant part: Angelo's shall provide a final design, revised complete permit application and site investigation (referred to jointly as "Revised Submittal") to DEP with copies to all Parties and DEP shall make a completeness determination prior to this proceeding being set for a new final hearing date. * * * Angelo's shall not revise its permit application or supporting information beyond the Revised Submittal prior to or during the final hearing except in response to issues raised by DEP. It appears that the Aligned Parties did not remember the Stipulated Agreement until the commencement of the final hearing. They did not object before then to any of the evidence which Angelo's had prepared or intended to prepare for hearing on the basis that it violated the terms of the Stipulated Agreement. At the commencement of the hearing, Nestlé argued that the Stipulated Agreement barred Angelo's from revising its application or presenting new support for its project at the final hearing. The Stipulated Agreement is unusual and the necessity for Angelo's to make any concessions to the Aligned Parties in order to obtain their agreement to an abeyance was not explained. Allowing an applicant time to amend a permit application is usually good cause for an abeyance. The Stipulated Agreement allowed Angelo's to continue to respond to issues raised by the Department. Angelo's contends that all of the evidence it presented at the final hearing qualifies as a response to issues raised by the Department. The Proposed Landfill Angelo's applied to construct and operate a Class I landfill with associated buildings and leachate holding tanks. Application No. 22913-001-SC/01 corresponds to the construction permit application and Application No. 22913-001-SO/01 corresponds to the operation permit application. A Class I landfill is a landfill authorized to receive Class I waste, which is solid waste from households and businesses. Class I waste does not include hazardous waste, yard waste, or construction and demolition debris. See Fla. Admin. Code R. 62-701.200(13) and (14). The proposed landfill would be approximately 30 acres in size. It is part of a 1,020-acre parcel owned by Angelo's that is west of County Road 35 and south of Enterprise Road in Pasco County. The site is currently leased for cattle grazing and hay and sod production. There are also spray fields, orange groves, and a pond on the 1,020-acre parcel. Angelo's would construct the landfill by first clearing the 30-acre site. It would then excavate and fill to create the design subgrade or floor of the landfill with slopes required for the liner system. The subgrade would be compacted with a vibratory roller. After the subgrade compaction, the grouting plan would be implemented. The grouting plan calls for grouting 39 subsurface locations on the site that have voids, loose soils, or other unstable characteristics. A liner system would be installed after the grouting is completed and the subgrade is finished. From the bottom upward, the liner system would begin with a 12-inch layer of clay, over which a reinforcement geotextile would be installed, followed by another 12-inch layer of clay. This reinforcement geotextile is in addition to the double liner system required by Department rule. Its purpose is to maintain the integrity of the liner system in the event that a sinkhole occurs beneath the landfill. Installed above the reinforcement geotextile and clay layer would be a 60-millimeter high-density polyethylene ("HDPE") geomembrane, followed by a HDPE drainage net. These last two components comprise the secondary leachate collection system. Above the HDPE drainage net would be the primary leachate collection system, consisting of another 60-millimeter HDPE geomembrane and HDPE drainage net, followed by a geotextile, then a 12-inch sand layer for drainage, and an additional 12-inch sand layer for protection against puncture of the HDPE liner. A 48-inch layer of selected waste, free of items that could puncture the liner, would be the first waste placed over the primary leachate collection system. "Leachate" is "liquid that has passed through or merged from solid waste and may contain soluble, suspended, or miscible materials." See Fla. Admin. Code R. 62-701.200(66). Leachate would be collected through a system of perforated pipes that empty into a sloping trench with a leachate collection pipe. The leachate collection pipe would run down the center of the landfill to the lowest point where a pump would send the collected leachate through a force main 0.25 miles to storage tanks. Five above-ground storage tanks would be installed on a concrete pad with capacity to store 90,000 gallons of leachate. The stored leachate would be periodically transported to an offsite location, such as a wastewater treatment facility, for disposal. Sinkholes and Karst The terms "sinkhole" and "sinkhole activity" are not defined by Department rule, but the statutory definitions in chapter 627, a chapter dealing with insurance coverage for homes and other buildings, are generally consistent with the scientific meanings of these terms. The term "sinkhole" is defined in section 627.706(2)(h) as: a landform created by subsidence of soil, sediment, or rock as underlying strata are dissolved by groundwater. A sinkhole forms by collapse into subterranean voids created by dissolution of limestone or dolostone or by subsidence as these strata are dissolved. The term "sinkhole activity" is defined in section 627.706(2)(i) as: settlement or systematic weakening of the earth supporting the covered building only if the settlement or systematic weakening results from contemporaneous movement or raveling of soils, sediments, or rock materials into subterranean voids created by the effect of water on a limestone or similar rock formation. Sinkholes occur throughout Florida. There have been many reported and confirmed sinkholes in Pasco County. The more common type of sinkhole that has occurred on the Brooksville Ridge is a "cover subsidence" sinkhole, which is caused by voids in the limestone and the downward movement--"raveling"--of overlying soils into the cavity. Eventually, the loss of soils in the raveling zone will propagate upward until the soils at the ground surface also move downward and a depression is formed at the surface. Cover subsidence sinkholes develop slowly and are usually small, less than ten feet in diameter. Less common are "cover collapse" sinkholes, which can form in a matter of days or hours as the result of the collapse of the "roof" of a dissolved cavity in the limestone. These sinkholes are usually large and deep. The occurrence of a sinkhole does not always mean that areas near the sinkhole are unstable. However, the occurrence of a sinkhole is reasonable cause for concern about the stability of nearby areas and a reasonable basis for the Department to require thorough geologic investigations. "Karst" refers to limestone that is undergoing dissolution and it is common in Florida. A sinkhole forms in karst. "Epikarst" is limestone that was weathered while exposed above sea level millions of years ago before being submerged again. It is generally softer and more permeable than unweathered limestone. "Paleokarst" refers to karst that is very old in geologic time. Paleosinks are old sinkhole features in the paleokarst. A paleosink may no longer be unstable because it has been filled in for thousands or millions of years. A "lineament," or a "photolineament," is a relatively straight line seen in the topography or aerial photographs of the ground surface in an area. It might be defined by soil color, sloughs, ponds, wetlands, or other land features that follow a linear path. Lineaments are sometimes, but not always, associated with subsurface fractures in the bedrock where one would expect to also find active karst, sinkholes, and relatively rapid groundwater flow. Even where there is no lineament, there can be fractures in limestone that, when extensive enough, will allow for "fractured," "preferential," or "conduit flow" of groundwater. Fractured flow can occur in a small area or may go on for miles. Springs in Florida are usually associated with fractured flow or conduit flow that allows groundwater to move through the aquifer a long distance relatively rapidly, in weeks rather than decades. Geotechnical Investigation The Department's rules require subsurface conditions to be explored and described, including soil stratigraphy, soft ground, lineaments, and unstable areas, but the rules do not require the application of any particular geologic testing technique. An applicant's testing program is primarily a function of the professional judgment of the applicant’s geologist in cooperation with Department staff. The amount of geological testing done by Angelo's during its initial testing was similar to what was done for recent landfill applications. Angelo's conducted additional testing to respond to Department concerns and to prepare for the final hearing in this case, making the total amount of testing at Angelo's proposed site more extensive than is usual for a proposed landfill. The geologic investigation conducted by Angelo's experts to determine subsurface features, including any sinkholes, employed several technologies. Split Spoon Penetrometer Test (SPT) or SPT borings were drilled with a drill rig that advances a split spoon sampler into the ground with a 140 pound hammer. The hammer is dropped 30 inches and the number of blows required to drive the sampler each successive 12 inches is referred to as the "N" value and indicates soil strength and density. The higher the N value, the denser the soil. When the material is so dense the drill rod cannot (essentially) be hammered deeper, the N value is shown as "R," which stands for "refusal." SPT Bore logs also note any observed "weight of hammer," "weight of rod," or "loss of circulation." These terms describe areas where the drilling encounters very soft material or voids. Weight of rod, for example, means the weight of the drilling rod, by itself, with no hammer blow, was enough to cause the rod to fall deeper through the soil or rock. Cone Penetrometer Test ("CPT") borings were also conducted. CPT borings are relatively shallow, performed with a hand-held rod and special tip that the operator pushes into the ground. The CPT equipment continuously measures and records tip resistance and sleeve resistance as the rod moves downward through soils. It is helpful in some applications, but is less precise in determining soil type, strength, and compressibility than SPT borings and cannot be used to explore deep zones. Ground penetrating radar ("GPR") studies were used. GPR equipment transmits pulses of radio frequency waves into the ground. The manner in which the radio waves are reflected indicates the types of soil and rock encountered. It can also detect cavities and other features that would suggest karst activity. When the GPR identifies geologic features of interest, they can be further investigated with SPT borings. Another investigative tool used by Angelo's was Multiple Electrode Resistivity ("MER"). MER uses a grid of wires and electrodes and the equipment interprets the resistivity of electrical signals transmitted through the subsurface. MER data can be displayed in a two dimensional or three dimensional format, depending on the software program that is used to process the data. Like GPR, MER is useful for indentifying geologic features of interest that can be further explored with SPT borings. However, GPR generally has good resolution only near the ground surface, while MER has good resolution to a depth of 100 feet. The Regional Geology The proposed site is in a geologic transition zone on the eastern flank of a regional, geological feature known as the Brooksville Ridge. It is a transition zone for both the Suwannee Limestone and Hawthorn Group. The Brooksville Ridge was formed when it was part of the coastline. In its geologic past, the Brooksville Ridge experienced sea level changes, weathering, erosion of sediments, and beach reworking. The general layering of geologic features on the Brooksville Ridge, from the top down, begins with topsoil and a layer of sand. Under the sand layer is the Hawthorn Group, an older geologic layer consisting of a heterogeneous mix of limestone, clays, and sands which generally range in depth from slightly under 60 feet to 80 feet or more. It was formed by river and wind erosion, flushing, and re-deposition in a beach dune environment. Below the Hawthorn Group is the Suwannee Limestone Formation, which is present throughout eastern Pasco County. The upper surface of the Suwannee Limestone Formation is undulating, due to a gradual chemical weathering of its upper surface, representing a "paleokarst environment." Underlying the Suwannee Limestone Formation is the Ocala Limestone Formation. It extends throughout most of Florida. It is composed of nearly pure limestone and is considered the Floridan Aquifer. It extends across the site’s subsurface. Angelo's used the Florida Geologic Survey's data base to determine there are six sinkholes within five miles of the proposed landfill. A seventh sinkhole, not in the data base, is the 15- foot sinkhole at the Angelo's Enterprise Road Facility landfill, a Class III landfill (yard waste and construction and demolition debris) about a mile northwest of the proposed site. Angelo's contends that the sinkhole at its Class III landfill was "induced" during construction of the facility by the diversion of stormwater runoff to an area where overburden had been removed. The average diameter of the seven sinkholes is 11.9 feet. The Geology of the Proposed Site Rule 62-701.410(2)(c) requires a geotechnical site investigation and report, which shall: Explore and describe subsurface conditions including soil stratigraphy and ground water table conditions; Explore and address the presence of muck, previously filled areas, soft ground, lineaments, and sinkholes; Evaluate and address fault areas, seismic impact zones, and unstable areas as described in 40 C.F.R. 258.13, 258.14 and 258.15; Include estimates of the average and maximum high ground water table across the site; and Include a foundation analysis to determine the ability of the foundation to support the loads and stresses imposed by the landfill. It may include geotechnical measures necessary to modify the foundation to accommodate the imposed loads and stresses. The foundation shall be analyzed for short-term, end of construction, and long-term stability and settlement conditions. Considering the existing or proposed subgrade conditions and the landfill geometry, analysis shall include: Foundation bearing capacity; Subgrade settlements, both total and differential; and Subgrade slope stability. Angelo's conducted a geotechnical site investigation, but it was not adequate, as discussed below and in sections I. and J. The proposed landfill site is geologically complex, having features that are discontinuous horizontally and vertically. The site has karst features or areas where the limestone has dissolved. There is a clay layer in some areas, but it is not continuous and its depth and thickness vary. There are deposits of hard and soft sands at various depths. There are pinnacles of limestone surrounded by softer materials. Photographs from a quarry called the Vulcan Mine, located on the western flank of the Brooksville Ridge, show exposed features in the top 20 to 30 feet of the Suwannee Limestone in the region. The features at the Vulcan Mine are roughly similar to features at the Angelo's site. There are a number of shallow depressions on the surface of the ground on the Angelo's site. The origin and significance of these depressions was a matter of dispute. The Aligned Parties believe they represent sinkhole activity, but the evidence presented did not rise to the level of proof. However, Angelo's did not prove they were unassociated with geotechnical issues that could affect the proposed landfill. Angelo's offered no reasonable explanation for the depressions. Determining the exact cause of the depressions may not be possible even with more extensive investigation, but it was Angelo's responsibility as the permit applicant, pursuant to rule 62-701.410(2)(c), to make a greater effort to account for them. Angelo's initial permit application identified two intersecting lineaments on Angelo's property, based on aligned lowlands, enclosed valleys, and ponds. Angelo's contends the lineaments do not reflect an unstable subsurface or fractured limestone. The Aligned Parties contend that the lineaments are regional features and reflect fractures in the bedrock. They also contend that the onsite pond, which is located along the lineament, is an old sinkhole. The Aligned Parties did not prove the proposed landfill site is above an area of fractured bedrock, but the evidence presented by Angelo's was incomplete and insufficient to show there are no fractures. The limestone on the site was not adequately investigated for voids and fractures. Angelo's did not refute the possibility that the lineaments reflect a significant subsurface feature that could affect both site stability and groundwater movement. The Regional and Local Hydrogeology Rule 62-701.410(1) requires a hydrogeological investigation and site report, which shall: Define the landfill site geology and hydrology and its relationship to the local and regional hydrogeologic patterns including: Direction and rate of ground water and surface water flow, including seasonal variations; Background quality of ground water and surface water; Any on site hydraulic connections between aquifers; For all confining layers, semi-confining layers, and all aquifers below the landfill site that may be affected by the landfill, the porosity or effective porosity, horizontal and vertical permeabilities, and the depth to and lithology of the layers and aquifers; and Topography, soil types and characteristics, and surface water drainage systems of the site and surrounding the site. Include an inventory of all the public and private water wells within a one-mile radius of the proposed landfill site. The inventory shall include, where available: The approximate elevation of the top of the well casing and the depth of each well; The name of the owner, the age and usage of each well, and the estimated daily pumpage; and The stratigraphic unit screened, well construction technique, and static water levels of each well. Identify and locate any existing contaminated areas on the landfill site. Include a map showing the locations of all potable wells within 500 feet of the waste storage and disposal areas to demonstrate compliance with paragraph 62- 701.300(2)(b), F.A.C. Angelo's conducted a hydrogeological investigation, but it was not adequate, as discussed below. Angelo's and the Aligned Parties disputed the hydrogeological characteristics of the proposed landfill site and region. The principal disputes related to the direction and velocity of groundwater flow. Angelo's contends that groundwater flows from the landfill site to the west, making the proposed landfill site part of the Withlacoochee River groundwater basin. The Aligned Parties contend that groundwater flows south toward Crystal Springs and, therefore, the site is within the "springshed" of Crystal Springs. A United States Geological Survey map of the Crystal Springs springshed shows Angelo's proposed landfill site within the springshed. A springshed study done for SWFWMD also indicates the site is within the Crystal Springs springshed, but the District has not always been consistent in its statements about the groundwater basin boundaries in this area. A water chemistry analysis of the groundwater in the area of Angelo's proposed landfill indicates that the site is an area of higher recharge and within the Crystal Springs springshed. The springshed boundary can shift, depending on rainfall. Angelo's hydrogeological evidence was not sufficient to refute the reasonable possibility that the proposed landfill site is within the Crystal Springs springshed. Therefore, the Department's determination whether Angelo's has provided reasonable assurances must account for the threat of contamination to Crystal Springs and the other public and private water supply sources to the south. There are no creeks or streams and only a few lakes in the area between Crystal Springs and the Angelo's site. The absence of surface runoff features indicates it is an area of high recharge to the groundwater. Crystal Springs is in an area of conduit flow. The hydrologic investigation conducted by Angelo's was not thorough enough to characterize surficial aquifer flow and flow between aquifers. The preponderance of the evidence shows more groundwater recharge to the Floridan Aquifer in the area than estimated by Angelo's. Angelo's hydrogeological investigation was inadequate to refute the possibility of fractured flow or rapid groundwater movement at the proposed landfill site. Angelo's contends there is a continuous clay confining layer that would prevent contamination from moving into deep zones, but the preponderance of the evidence shows discontinuity in the clay and large variations in thickness and depth. The landfill's impermeable liner will impede water movement downward from the landfill, but groundwater will still recharge from outside the landfill to carry any contaminants deeper. If fractured flow or conduit flow extends south from the proposed landfill site, any leachate released into the groundwater beneath the landfill could travel rapidly toward the water supply sources of the City of Zephyrhills, Crystal Springs, Nestlé, and the City of Tampa. Whether the Proposed Landfill is in an Unstable Area Rule 62-701.200(2)(a) prohibits the storage or disposal of solid waste "[i]n an area where geological formations or other subsurface features will not provide support for the solid waste." However, the Department has adopted by reference a federal regulation, 40 C.F.R. 258.15, which allows a landfill to be constructed in a geologically unstable area if the permit applicant can demonstrate that engineering measures are incorporated into the design to ensure that the integrity of the landfill’s structural components "will not be disrupted." The parties presented evidence on many disputed issues of fact at the final hearing, but most of the case involved two ultimate questions: whether the proposed landfill site is unstable and, if so, whether Angelo's has proposed measures that would eliminate the unstable conditions and make the site suitable for a landfill. as: An "unstable area" is defined in 40 C.F.R. § 258.15 A location that is susceptible to natural or human-induced events or forces capable of impairing the integrity of some or all of the landfill structural components responsible for preventing releases from a landfill. Unstable areas can include poor foundation conditions, areas susceptible to mass movements, and Karst terrains. There is overwhelming evidence that the proposed landfill site is an unstable area. A considerable amount of evidence presented by Angelo's supports this finding. For example, Angelo's experts agreed there are loose soils, evidence of raveling, and sinkhole activity. These conditions make the site susceptible to natural or human-induced events or forces capable of impairing the integrity of some or all of the landfill structural components responsible for preventing releases from the proposed landfill. The Department's landfill permitting staff requested a sinkhole risk assessment from the Florida Geologic Survey ("FGS"). The State Geologist and Director of the FGS, Dr. Jonathan Arthur, believes the potential for sinkhole formation at the proposed site is moderately high to high. That potential is consistent with the characterization of the area as unstable. Whether the Proposed Engineering Measures Are Adequate Because the site is unstable, Angelo’s must demonstrate that engineering measures have been incorporated into the landfill's design to ensure that the integrity of its structural components will not be disrupted. See 40 C.F.R. § 258.15(a). The engineering measures proposed by Angelo's are discussed below. Because it was found that Angelo's hydrogeological and geotechnical investigations were not sufficient to characterize all potentially unstable features of the subsurface, it was not demonstrated that the proposed engineering measures would overcome the instability and make the site suitable for a landfill. Roller Compaction Angelo's would use roller compaction on the graded floor of the landfill to compact the soils to a depth of about five feet and eliminate any voids within that depth. The Aligned Parties did not contradict Angelo's evidence that its proposed roller compaction will be done in a manner exceeding what the Department usually requires as far as roller force and the number of roller "passes." However, roller compaction will not affect deep voids. Liner System In order to ensure that the landfill’s liner system components will not be disrupted in the event of a sinkhole, Angelo’s proposes to include the reinforcement geotextile discussed above. The Department previously approved the use of geotextile reinforcement, combined with grouting, to demonstrate site stability for the Hernando County Northwest Landfill, which had a comparable risk of sinkhole formation according to the Department. The reinforcement geotextile can span a 15-foot diameter sinkhole without failure. As found above, the average diameter of the seven sinkholes within five miles of the proposed landfill is 11.9 feet. Angelo's proved that the proposed liner system meets all applicable criteria, except the requirement of rule 62- 701.400(3)(a) that the liner be installed upon a geologically stable base. Grouting Plan Angelo's grouting plan would be implemented to fill voids and stabilize areas of loose or weak material. The grouting plan was first designed to grout all locations where there was a Weight of Hammer, Weight of Rod, Loss of Circulation, or loose sands, as indicated by a low blow count. Angelo's revised the grout plan to include several more areas of concern identified later, for a total of 39 locations. Each grout location would have seven grout points, one in the center and six others equally-spaced on a ten-foot radius from the center. If more than ten cubic yards of grout is needed, additional grout points further outward would be injected until the void or loose soils are filled or stabilized. Although Angelo's proposes to grout every boring of concern, that still ties the integrity of the grouting plan to the thoroughness of the borings. The geologic evidence indicates that there are unstable areas which the grouting plan does not address. The Aligned Parties' MER analysis was persuasive in identifying potential areas of instability that were omitted from Angelo's investigation and from its grouting plan. There are other unstable areas existing on the site that should be grouted or otherwise engineered to provide support for the landfill. The grouting plan does not provide reasonable assurance that the integrity of the structural components of the landfill will not be disturbed. Other Issues Raised by the Aligned Parties The Aligned Parties raise a number of other issues, some of which begin with the assumption that the site is unstable and a large sinkhole would form at the landfill. This sometimes mixes issues inappropriately. It has been found that Angelo's did not provide reasonable assurance that the site will support the proposed landfill, but other project elements must be reviewed on their own merits where possible, assuming the site was engineered for stability. Leachate Collection System There is a single leachate collection trench in the center of the two landfill cells, which makes the landfill operate much like a single cell. The two halves of the cell slope toward the center, so that leachate will drain to the leachate collection trench, and the entire landfill slopes to the west, so that the trench will drain to a sump from which the leachate is pumped to storage tanks. At full capacity, the landfill will generate about 40,000 gallons of leachate per day. Careful cutting and grading of the earth is necessary to create the slopes that are essential to the proper functioning of the project’s leachate collection system. Settlement analyses are necessary to assure that the slopes are maintained. Rule 62-701.410(2)(e) requires a foundation analysis which must include a study of "subgrade settlements, both total and differential." "Total settlement" refers to the overall settlement of a landfill after construction and the loading of solid waste. "Differential settlement" compares settlement at two different points. Angelo's did not meet its burden to provide reasonable assurance on this point. The settlement analysis conducted by Angelo's was amended two or three times during the course of the final hearing to account for computational errors and other issues raised by the Aligned Parties. The analysis never came completely into focus. The final analysis was not signed and sealed by a professional engineer. The settlement analysis is dependent on the geologic analysis, which is inadequate. Without adequate settlement and geologic analyses, it cannot be determined that leachate collection would meet applicable criteria. Storage Tanks The Aligned Parties contend that the leachate storage tanks cannot be supported by the site. Because it was found that Angelo's geologic investigation was not adequate to identify all unstable areas, it is also found that Angelo's failed to provide reasonable assurance that the site would support the leachate storage tanks. In all other respects, the Aligned Parties failed to refute Angelo's demonstration that the storage tanks would meet applicable criteria. Groundwater Monitoring Plan The Aligned Parties contend that there is an insufficient number of monitor wells proposed by Angelo's to detect a leak from the landfill and the wells are too shallow. Because it was found that Angelo's did not adequately characterize the geology and hydrology of the proposed landfill site, the monitoring plan does not provide reasonable assurance of compliance with applicable criteria. Cell Design The Aligned Parties contend that the "mega-cell" design proposed by Angelo's provides less flexibility to respond to and isolate landfill problems than other landfill designs with smaller cells, and the mega-cell design could generate more leakage. No evidence was presented to show whether Angelo's design was one that had been approved or rejected in the past by the Department. Although it is not the best landfill design, the Aligned Parties did not show that the proposed design violates any permitting criteria. Operation and Closure The evidence presented by the Aligned Parties in support of their issues regarding the operation of the proposed landfill, such as noise, odor, and traffic, was not sufficient to refute Angelo's evidence of compliance with applicable criteria, with one exception: Angelo's has not provided an adequate contingency plan to show how it would respond to a sinkhole or other incident that required the landfill to be shut down and repaired. Assuming the site was engineered to support the landfill, there is nothing about the Closure Plan that the Aligned Parties showed does not meet applicable criteria.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection deny Angelo's Permit Application Nos. 22913-001-SC/01 and 22913- 002-SO/01. DONE AND ENTERED this 28th day of June, 2013, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of June, 2013. COPIES FURNISHED: Carl Roth, Qualified Representative 8031 Island Drive Port Richey, Florida 34668-6220 Christopher M. Kise, Esquire Foley and Lardner, LLP 106 East College Avenue, Suite 900 Tallahassee, Florida 32301-7732 Wayne E. Flowers, Esquire Lewis, Longman and Walker, P.A. Suite 150 245 Riverside Avenue Jacksonville, Florida 32202-4931 Janice M. McLean, Esquire City of Tampa 7th Floor 315 East Kennedy Boulevard Tampa, Florida 33602-5211 Joseph A. Poblick, Esquire City of Zephyrhills 5335 8th Street Zephyrhills, Florida 33542-4312 Doug Manson, Esquire William Bilenky, Esquire Brian A. Bolves, Esquire Manson Bolves, P.A. 1101 West Swann Avenue Tampa, Florida 33606-2637 Jacob D. Varn, Esquire Linda Loomis Shelley, Esquire Karen A. Brodeen, Esquire Fowler, White, Boggs, P.A. 101 North Monroe Street, Suite 1090 Tallahassee, Florida 32302-1547 David Smolker, Esquire Smolker, Bartlett, Schlosser, Loeb and Hinds, P.A. Suite 200 500 East Kennedy Boulevard Tampa, Florida 33602-4936 Stanley Warden, Esquire Christopher Dale McGuire, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 William D. Preston, Esquire William D. Preston, P.A. 4832-A Kerry Forest Parkway Tallahassee, Florida 32309-2272 Herschel T. Vinyard, Jr., Secretary Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Matthew Z. Leopold, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Lea Crandall, Agency Clerk Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

# 4
H. A. BRAY AND BRAY LANDFILL vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 77-001225 (1977)
Division of Administrative Hearings, Florida Number: 77-001225 Latest Update: Jun. 12, 1978

Findings Of Fact Bray is the owner of and lives on property located at 5550 Pine Hills Road, Orlando, Florida. He operates a solid waste disposal site on this property. By application dated June 6, 1977, and revised June 13, 1977, Bray applied to DER for an Operation Permit for a Solid Waste Resource Recovery and Management Facility pursuant to Chapter 17-7, Florida Administrative Code. At that time, Bray held a Temporary Operating Permit which had been issued on February 4, 1976. In Bray's application materials, which included the application dated June 6, 1977 and revised June 13, 1977, and letters from Bray to DER dated June 8, 1977, and June 30, 1977, Bray proposed an alternate procedure pursuant to Rule 17-7.05(3) (q) for operation of his landfill which procedure would permit Bray to cover, spread and compact the fill material in a manner different from that specifically set forth in Rule 17-7.05, Florida Administrative Code. DER did not consider Bray's request for an alternate procedure, but responded by letter stating that Bray must apply for a variance pursuant to Rule 17-1.25, Florida Administrative Code, and recommended denial of Bray's application for a permit for the following reasons: No provisions were made for daily cover. Refuse was not spread in two (2) foot layers. No intermediate cover was applied within one week of cell completion. No cover materials were stockpiled. During the testimony presented, DER acknowledged that the fourth reason given for denial of the permits-no cover materials were stockpiled-is not a requirement of the Rules and is not a valid reason for denial of a Permit Application. This Hearing Examiner agrees and finds that Chapter 17-7, Florida Administrative Code only requires that the site have an adequate quantity of acceptable earth cover available. See Rule 17-7.05(1) (c)3, Florida Administrative Code. Bray presented adequate testimony demonstrating that sufficient acceptable cover material was available at his site. Bray conceded at the hearing that it was still his intention to operate the landfill site without daily cover, intermediate cover and compaction as required by DER. Bray's principal contention is that compaction and daily cover are not necessary for a landfill which accepts only non-putrescible waste. Bray urges that the attenuation of leachate, prevention of fires, prevention of settling and ponding of water which provide breeding grounds for mosquitoes and other vectors and reducing the area of land needed to dispose of solid waste are justifications for the requirements of compaction and daily cover of solid waste which may not be present at non-putrescible landfills. Bray concludes that the absence of these problems at his landfill obviates the necessity for the application of the provisions of the rule requiring daily and intermediate cover and compaction. However, Bray has not met his burden of establishing that non- putrescible waste does not require compaction and daily cover. There are multiple reasons for the requirement of compaction and daily cover of solid waste. When solid-waste is spread to approximately a 2-foot thickness and then compacted to a 1-foot thickness, followed by the daily application of a cover of 6 inches of compacted earth, a layering effect is created which helps attenuate, if not prevent, the formation of leachate from both putrescibles and non-putrescibles which may be contained in the waste. Leachate is a liquid that has percolated through solid waste, usually originating as rain, which contains dissolved or suspended material that may contaminate ground water supply. Leachate occurs in landfills that accept putrescible material as well as landfills that accept only non-putrescibles. Compaction and daily cover consequently slow, if not prevent, the contamination of ground water supplies. The formation of leachate containing various chemicals which would have adverse affects on the human body is expected when water percolates through strictly non-putrescible waste Commonly discarded non-putrescibles such as metals, plastics, ashes, rocks and dirt from an industrial site, miscellaneous organics, heavy metal solutions and sludges, organic solvents and oils, caustic and acid solutions, inorganic chemical solutions and sludges, pesticides and fungicide wastes, paint and ink wastes, asphalt roofing and paving material, explosive waste and radioactive waste are probable sources of leachate contamination. The process of leachate formation from non-putrescibles involve the physical and chemical reaction of compounds in the non-putrescibles with the water percolating through them. The contamination of ground water supplies by leachate from either a putrescible or non-putrescible site constitutes a threat to the health, safety and welfare of the public as many of the contaminates are toxic and have adverse affects on the human body. In particular, leachate from non-putrescibles may contain toxic metal solutions, carcinogenic pesticides and other organic compounds as well as toxic inorganic compounds. Another reason for compacting and daily cover is the prevention of fires. Exposed, non-putrescible wastes can ignite and result in serious dump fires. Daily cover, if applied, serves as a fire break and eliminates the fire hazard created by exposed combustible non-putrescible wastes. Furthermore, compaction and daily cover prevent settling and ponding which would contribute to both downward flow' of water through the solid waste and the creation of breeding grounds for mosquitoes and other vectors. Compaction and daily cover contribute to the general aesthetics of the site and reduce the area of land needed to dispose of solid waste Bray has attempted to show that his method of operation effectively screens putrescible wastes from the site and otherwise adequately protects the public health, safety and welfare. However, the evidence which belies the assertion, shows that putrescibles have, in fact, been dumped at Bray Landfill. Coliform readings obtained in samples from monitoring wells at the Bray property can reasonably be attributed to putrescible matter on site. Birds have been observed feeding on site and these would not be feeding on non-putrescible wastes. The policing techniques are largely ineffectual. The site contains unopened trash bags with undisclosed contents as well as observed putrescible garbage. Trucks enter the site and dump their loads without inspection. Two major dump fires have occurred at the Bray Landfill during the past four years.

# 5
FLORIDA AUDUBON SOCIETY, TROPICAL AUDUBON SOCIETY vs. CITY OF NORTH MIAMI, MUNISPORT, INC., AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-000316 (1978)
Division of Administrative Hearings, Florida Number: 78-000316 Latest Update: May 31, 1979

The Issue Whether permit application SWO 13-5152, should be granted under Chapter 403, Florida Statutes. This case involves the application of Respondents City of North Miami and Munisport, Inc. to Respondent Department of Environmental Regulation (DER) for an operating permit under the provisions of Chapter 403, Florida Statutes, and Chapter 17-7, Florida Administrative Code, to operate a sanitary landfill located in North Miami, Florida. DER granted provisional approval of the application by the issuance of a Notice of Intent to issue the permit on January 27, 1978. Petitioners filed the instant petition of February 13, 1978, challenging the issuance of the proposed permit. Final hearing herein was originally scheduled for April 7, 1978, but at the instance of the parties was continued and reset to commence on October 18, 1978. During the course of the final hearing, 29 witnesses presented testimony, including six public witnesses. (List of public witnesses - Hearing Officer's Exhibit 3) A total of 35 exhibits were admitted in evidence. Three exhibits (Exhibits 5, 13 and 15) were rejected by the Hearing Officer.

Findings Of Fact By application dated November 14, 1977, Respondent City of North Miami, Florida, as owner, and Respondent Munisport, Inc. as the "responsible operating authority" requested Respondent DER to issue a permit to operate a solid waste resource recovery and management facility consisting of 345.90 acres located at 14301 Biscayne Boulevard, North Miami, Florida. The site, known as the North Miami Recreation Development, had been operating as a sanitary landfill under temporary operating permits (TOP) issued by the DER on May 8, 1975 and September 21, 1976. The 1976 TOP provided for an expiration date of July 1, 1977, and contained various conditions designed to give the permittees a reasonable period of time to conform to the DER regulations relative to sanitary landfills. These included standard requirements such as the rendering of reports on the operation of the facility and prohibiting the deposit of raw and infectious waste, or hazardous waste that had not been rendered safe and sanitary prior to delivery. Additionally, the permit conditions required the facility to be so operated that it would cause minimum adverse effects on the environment, such as objectionable odors, contaminated storm water runoff, or leachates causing degradation of surface of ground waters. Further, the permit provided for a three-month review program after its issuance to consider the feasibility of dumping solid waste in 63 acres of submerged land subject to previous filling with clean fill and/or construction debris, filling of land above mean high water with garbage either above clean fill or above trenches filled with wood and construction debris and covered with clean fill, and a six-week period of weekly water quality monitoring at agreed to sites for analysis by both permittees and the Dade County Environmental Resources Management (DERM). The permit further prohibited the placement of refuse waterward of the mean high water line or in trenches cut below the natural ground water table. (Exhibits 1, 4). By letter of January 27, 1978, DER gave notice to the applicant of its intent to issue the requested operation permit for the solid waste disposal facility and stated therein the following reasons for its determination: The solid waste disposal site is in the public interest. The Department feels that the site will not substantially affect the water quality or interfere with the area's wildlife. The applications and plans for this facility have been evaluated and found to be in conformance with Chapter 403, F.S., Chapter 17-4, FAC, and Chapter 17-7, FAC. The letter stated standard conditions to which the permit would be subject, including special conditions that had been noted in the 1976 TOP. It also prescribed specific conditions that no solid wastes could be placed within 30 feet of any existing or future lake area, no dumping below water at any time nor in any dewatered excavations, and that a quarterly water quality monitoring program at monitoring wells No. 4 through 12 be sampled for specified substances. Proposed Condition 16 stated as follows: Solid waste shall be deposited in locations consistent with those approved in the Army Corps of Engineers' dredge and fill permit #75B-0869. No solid waste shall be deposited in the areas commonly known as the wetlands and transitional zones of said wetlands, as shown on the attached map. Subject to the Corps approval of proposed modifications to permit #75B-0869, a revised DER solid waste permit will be issued consistent with the approved modifications. A sketch of the landfill site purporting to designate the landfill deposal area, wetlands and transitional zone, and mean high water line was attached. (Exhibit 3) The Petitioners consist of the Florida Audubon Society, which has some 2,000 members residing in Dade County, Tropical Audubon Society, which is affiliated with Florida Audubon Society; Keystone Point Homeowners Association, Inc., comprised of approximately 425 owners of mostly waterfront or canal homes in North Miami within a mile of the landfill site; Thomas Pafford, North Miami, Florida, who uses the waters of Biscayne Bay and nearby wetlands for recreational purposes; and Maureen B. Harwitz, who resides within a half mile of the landfill site and uses Biscayne Bay and the mangrove preserve adjacent to the landfill site for recreational purposes. Members of the above-named organizational groups use the waters surrounding the landfill site for recreational purposes and are concerned that the waters and fish and animal life therein will be adversely affected if the operation permit is granted. (Testimony of Lee, Brown, Pafford, Lippelman, Harwitz) Munisport has been operating the North Miami landfill under a lease with the City of North Miami since approximately 1974. The ultimate aim is to convert the area into a recreational complex consisting of golf courses, club house, and other sports facilities. The site was used as an unregulated dump for many years prior to initiation of the Munisport operation. The site has been the subject of previously issued state and Corps of Engineer dredge and fill permits which are not the subject of this proceeding. The landfill site occupies an area generally between Northwest 135th Street on the south and Northwest 151st Street on the north. It lies between Biscayne Boulevard on the west, and state mangrove preserves and land of Florida International University on the east. It is less than a mile to Biscayne Bay on the east side of the landfill. The nearest point of entry is in the southeast area where Arch Creek empties into the Bay. At this time, Munisport has filled approximately 210 acres at the site with ten feet or more of fill material. A final cover has been completed over about 70 acres of this land and a golf course is presently being constructed. Pursuant to the dredge and fill permits, five lakes approximately 35 feet deep are nearly completed and some six or seven more are to be dug in the future pursuant to those permits. These lakes are separated from the solid waste by a 30 foot wide dike of clean fill. Although some cover material has been trucked to the site, about 1.6 million cubic yards of fill from the excavated lakes have been or will be utilized in cover operations for the landfill. The solid waste layer averages 15 feet in depth and lies about two feet above the ground water table. About 230 acres lie within the upland fill area above the mean high water line which is not within the area of jurisdiction of the Army Corps of Engineers. The mean high water line has been established by appropriate procedures under Chapter 177, F.S., and the surveying procedures were approved by the Department of Natural Resources on April 6, 1978. Although not stated in the Notice of Intent to issue the requested permit, DER intends to restrict the life of any permit to the time when the Metropolitan Dade County Resources Recovery Facility commences operation in approximately two years. The applicants and Dade County also have a memorandum of understanding to this effect. (Testimony of Stotts, Checca, Exhibits 1, 2, 35, 36, Hearing Officer's Exhibit 1) Munisport receives solid waste from a variety of firms, institutions, and surrounding municipalities. Its procedures are for vehicles to enter and exit the site from an access road leading to Biscayne Boulevard. A sign is located along the road indicating the operating hours, fee schedule, waste restrictions and other pertinent information. A large portion of the site is virtually inaccessible due to dense mangroves and mosquito control canals and ditches. At the check-in gate, a cursory inspection of vehicle loads is made by Munisport personnel who check the contents for quantity. Each load is directed to a designated place at the site where Munisport employees spread and compact the waste. At this stage, they are instructed to look for any unauthorized materials, such as hazardous and infectious waste. If such wasted is found, the offending party is required to remove it from the site. compactors and bulldozers push the solid waste to the face of the landfill and spread it out to facilitate compaction. During the hours of 6:00 P.M. to 6:00 A.M., a watchman is on duty at the site to accommodate customers. If less than four or five truckloads arrive during the night hours, the material is not processed. If a larger quantity is involved, a Munisport employee moves and covers the material prior to the following workday. Due to the high ground water tabled, the area method is used for filling the site. This is a procedure by which refuse cells are constructed in lifts not to exceed ten feet in vertical height. They are composed of cells which constitute a one-day quantity of refuse. Six inches minimum cover of clean fill is applied daily, and a one foot intermediate cover is applied within a year after compaction. The cells are compacted in two-foot layers and, upon completion of a particular area, a minimum of two feet of final cover is applied. A dike constructed of compacted limerock borders the east side of the site and basically constitutes the present mean high water line. It is designed to protect the adjoining 129 acres of mangrove preserve and Biscayne Bay from any adverse water quality which might occur from runoff of degraded waters from the landfill site in the event of contamination. (Testimony of Haddad, Checca, Exhibit 1, 9) The shallow soil underlying the landfill at depths ranging to almost ten feet consists of a combination of organic matter and debris from prior dump use, muck, and sand. Soil borings taken at the site show that limestone or calcareous rock known as Miami oolite is about eight feet below the soil layer. At this depth is found the Biscayne aquifer that carries the unconfined ground water in the area. The aquifer is approximately 160 feet deep under the site and constitutes the major source of water supply in Dade County. The gradient of the water table for the landfill site runs in a southeasterly direction toward Biscayne Bay. Approximately 75% of the surface soil layer consists of organic muck, whereas in approximately 25% of the area, which was previously filled in the southern and westerly portions before commencement of the Munisport operation, the soil is primarily of a sandy type. (Testimony of Checca, Pitt, Exhibit 1) Leachate is produced in sanitary landfills by precipitation that percolates down through decomposing refuse cells and picks up polluting substances created from the decaying solid waste. It can form a "plume" or "bubble" that takes the course of least resistance in flowing laterally or vertically through a landfill site. The strength and concentration of the leachate is dependent upon various factors including the composition, compaction, and the age of decomposing refuse, and the amount of water being introduced into the area. As it passes slowly through the soil beneath the solid waste material, the unsaturated soils act as filters and permit ion exchange which reduces the quantity of contaminants. Dilution takes place where leachate comes in contact with ground water and leachate movement occurs gradually through the ground water aquifer in its direction of the flow. The presence and movement of leachate normally can be detected by analysis of ground water samples taken at various places throughout the landfill site. (Testimony of Checca, Pitt, Coker, Exhibit 1) Commencing in 1975, a monitoring program was instituted at the sanitary landfill to determine its effects on the ground water regime. A number of monitoring wells at various depths were constructed at different sites at the landfill, and samples were withdrawn and evaluated periodically to determine the types and degrees of pollution being generated by the landfill. Background samples were also obtained from wells off the site to establish the general character of water quality in the area and to compare these samples with those obtained from the site. Additionally, "grab" samples were taken of water from the bay and nearby canals and wetlands. Locations of the background and sampling wells were established by the applicants in conjunction with the DER and the Environmental Protection Agency. To determine the amount of leachate that probably would be generated at the site, the "water balance method" of computing the estimated time required to produce leachate, as well as the quantity that probably would be generated upon completion of the landfill, was made by representatives of the EPA in 1975 utilizing specific climatological and surface conditions at the site. This study indicated that percolation of surface water would increase during the operation of the landfill and before final soil and vegetative cover were in place, and that leachate would occur in about a year in larger quantities than would be produced by a completed landfill. Tests conducted during the ensuing three-year period of both surface and ground water through the monitoring program have failed to produce evidence that water quality is not within acceptable parameters or that water quality in the area surrounding the landfill site has been degraded. No significant differences in the concentrations of various ground water constituents were found between samples obtained at the disposal site and those collected in the adjacent mangrove forest or background areas. Neither was any evidence of contamination from leachate found in samples of surface water collected in the vicinity of the landfill or in nearby natural areas. (Testimony of Checca, Pitt, Linett, Perez, Exhibit 1, Exhibit 33) Three basic factors have undoubtedly accomplished reduction in the amount of leachate generated at the landfill. These are (a) attenuation and filtration of pollutants by unsaturated soils between and beneath the refuse cells, (b) biological assimilation by organisms living within the refuse cells and underlying soils, and (c) dilution upon contact with the ground water. A hydrogeologic study shows that the uppermost 14 feet of the aquifer immediately below the landfill represents only 0.2% of the total discharges with a ground water velocity of less than 0.1 foot per day. This part of the aquifer therefore provides considerable detention time for the water that percolates through the landfill. The strata, as well as the overlying organic marine soils, provide the absorption and assimilation that removes pollutants from the water. After water percolates through this layer, it reaches the highly permeable Miami oolite that carries about 43% of the ground water flow. The effects of soil absorption, filtration through the upper 14 feet of the aquifer, and dilution within the aquifer have demonstrably been sufficient to assimilate the water that percolates through the landfill. It is estimated that the time of travel of ground water from the landfill site to the closest discharge point in Biscayne Bay is approximately 68 years. Although the attenuation capability of the organic muck soil underlying the greater part of the landfill is high, the older area of the site in the southwestern portion which had been filled before the Munisport operation commenced, has no muck and consists primarily of sand with a higher rate of permeability. (Testimony of Checca, Pitt, Teas, Exhibits 1, 33) The fact that the organic muck material under the landfill is not uniform throughout the site, plus the fact that there have been various breaches in the permeable oolite layer below the soil, will, in the opinion of some experts, eventually lead to the generation and movement of a leachate plume into such breaches and ultimately to Biscayne Bay. These breaches consist of the deep lakes at the site, the Arch Creek Canal to the south of the site and a dredged excavation at the exit of that body of water into the bay some 3,600 feet distant from the landfill. Additionally, these experts postulate that the dike located on the eastern border of the site will not prevent leachate from moving into the surrounding mangrove area. It is therefore estimated that in the above ways, large amounts of leachate would enter the bay and adjacent wetlands within a period of five to ten years. (Testimony of Coker, Hudson, Pasley, Browder, Exhibits 12, 14, 29, 30) Although water monitoring at various levels in and at probable discharge points near the site have not found degradation of water quality, the applicants propose to address any future leachate problems in a variety of ways. These include continuous periodic testing of water quality and monitoring wells, excavation of a canal on the upland side of the site to intercept leachate and treatment of any contaminated water therein or by pumping the water to an interior lake for treatment. Based on the particular type of any degradation, chlorination and precipitators would be utilized. Long-range problems will be further reduced by the ultimate construction of the golf courses and placement of final soil and vegetative cover to reduce percolation of surface water. This will be aggravated to an undetermined degree, however, by periodic irrigation of the golf courses. (Testimony of Checca, Pitt, Kelman, Exhibits 1,33) During the early years of the Munisport operation, a number of violations of the conditions of the temporary operating permit occurred, but for the most part these were caused either through simple negligence of landfill personnel, breakdown of equipment, or introduction of unauthorized materials to the site by Munisport customers. In these situations, Munisport usually took prompt and effective action to prevent recurrence and to remedy the problem. For example, on one occasion in 1977, some 12 drums containing residue of a chemical substance deemed to constitute "hazardous waste" was brought into the site by persons unknown and was found leaking into the ground. A number of violations and warning notices were issued to Munisport by the Dade County Department of Environmental Resources Management (DERM), primarily in 1976, involving the placement of tree cuttings and wood scraps into excavations containing water at the south end of the site. These occurred, however, during a period when Munisport was engaging in tests to determine the suitability of such operations in conjunction with DER. Additionally, in 1976 and 1977, Munisport was advised of violations in the placement of garbage in exposed water, uncovered garbage, and delivery of garbage after hours. Munisport has had a continuing problem over the years with the unauthorized delivery of hospital wastes from various customers to the landfill in spite of letters written to hospital facilities and delivery firms cautioning them concerning the prohibition against the introduction of such material to the landfill. DERM personnel concede, however, that the operation has been continuously improved and that it is well-conducted in comparison with other landfills in the country. However, they believe that lakes should not exist in landfills and that the North Miami landfill is too close to the wetlands. (Testimony of Morrissey, Karafel, Sobrino, Haddad, Checca, Exhibits 6-11, 17, 18, 20-24, 27, supplemented by testimony of Pafford and Exhibit 16) In a letter of January 17, 1977, DERM expressed concerns about the Munisport operation to DER. One of these concerns was that leachate would migrate to proposed golf course lakes and the resulting pollution would produce poor water quality. Although 1976 testing of then existing lakes at the site reflected unusually high amounts of fecal coliform, subsequent tests in late 1978 showed very little, but tests again in January, 1979, showed that several lakes were again somewhat high in coliform. Coliform is not considered to be a strong parameter in assessing the presence of leachate and amounts vary considerably from day to day in lake areas. Additionally, great numbers of birds are normally present on the landfill site during operations and contribute in raising coliform readings to some extent. Dade County has a current policy that does not permit lakes to be excavated on landfills operated by the county. (Testimony of Checca, Morrissey, Sobrino, Karafel, Kosakowski, Linett, Newman, Kelman, Perez, Exhibits 17, 19, 20, 24, 25, 31, 32, 37, 38)

Recommendation That a permit be issued to the City of North Miami, Florida and Munisport, Inc. to operate the solid waste disposal facility as described and under the conditions stated in the letter of the Department of Environmental Regulation, dated January 27, 1978, wherein it gave notice of its intent to issue the said permit. DONE and ENTERED, this 13th day of April, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: David Gluckman, Esquire 5305 Isabelle Drive Ken VanAssenderp, Esquire Tallahassee, Florida Smith, Young and Blue, P.A. Post Office Box 1833 Josepy D. Fleming, Esquire 620 Ingraham Building Marvin Sadur and 25 Southeast Second Avenue Richard J. Potash, Esquires Miami, Florida 33131 2000 L Street NW - Suite 612 Washington, D.C. 20036 Silvia Alderman, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (3) 403.703403.707403.708
# 6
IN RE: HILLSBOROUGH COUNTY RESOURCE RECOVERY FACILITY EXPANSION POWER PLANT SITING APPLICATION NO. PA 83-19A vs *, 05-004347EPP (2005)
Division of Administrative Hearings, Florida Filed:Brandon, Florida Nov. 28, 2005 Number: 05-004347EPP Latest Update: Aug. 02, 2006

The Issue The issue to be determined in this case is whether a site certification should be issued to Hillsborough County for the construction and operation of a fourth municipal waste combustor unit (“Unit No. 4”) at Hillsborough County’s Resource Recovery Facility, in accordance with the provisions of the Florida Electrical Power Plant Siting Act.

Findings Of Fact The Applicant The Applicant, Hillsborough County, is a political subdivision of the State of Florida. The County owns the existing Facility and will own the proposed Project. The Facility was designed, built, and is operated by a private company pursuant to a long-term contract with the County. It is anticipated that a private company will design, construct, and operate the Project for the County. Hillsborough County’s Existing Solid Waste System The County has adopted a solid waste Comprehensive Master Plan (the “Master Plan”) in conjunction with the Cities of Tampa, Temple Terrace, and Plant City. The Master Plan provides for state-of-the-art technology and innovative approaches to recycling, waste reduction, and waste disposal. In accordance with the Master Plan, the County has developed: (a) an aggressive recycling program that significantly reduces the quantity of materials requiring disposal; (b) a resource recovery facility for waste reduction and energy recovery from those materials that are not recycled; and (c) a landfill for the disposal of ash and by-pass waste (i.e., materials that are not recycled or processed in the Facility). Hillsborough County and the three cities have used a cooperative, regional approach to solid waste management issues, while providing environmentally protective, cost-efficient programs for local residents. Despite the County’s comprehensive recycling program, the amount of solid waste generated in the County has increased each year since the Facility began operation, primarily due to population growth. The amount of solid waste generated in the County now significantly exceeds the Facility’s design capacity. Consequently, large quantities of solid waste currently are being diverted from the Facility to the County landfill. In 2005, the Board of County Commissioners decided to expand the Facility, consistent with the County’s long-standing Master Plan, rather than dispose of ever-increasing amounts of solid waste in a landfill. The Board’s decision was based on a thorough evaluation of the County’s solid waste disposal options. For these reasons, on November 21, 2005, the County filed an application with DEP for the construction and operation of Unit No. 4. The Site The Facility is located next to Falkenburg Road in an unincorporated area in the County. The Facility is southeast of the City of Tampa, west of Interstate 75 (“I-75"), and north of the Crosstown Expressway and State Road 60. The Facility was built on a 50.4-acre site (“Site”), which is in the southern portion of a 353-acre tract of land owned by Hillsborough County. The Surrounding Area The Facility is surrounded by a variety of governmental and industrial land uses. The Facility is bounded: on the south by the County’s Falkenburg Road Wastewater Treatment Plant and a railroad track that is owned by the CSX railroad company; on the west by a 230 kilovolt transmission line corridor and easement owned by Tampa Electric Company (“TECO”); on the north by vacant improved pasture land, the Falkenburg Road Jail, the Hillsborough County Department of Animal Services, and the Hillsborough County Sheriff’s Office (District 2); and on the east by Falkenburg Road and vacant land. The Facility is compatible with the adjacent and surrounding land uses. The nearest residential area is approximately 1 mile away from the Facility. It is located on the opposite (east) side of I-75. Zoning and Land Use In 1984, the Siting Board determined that the Site and Facility were consistent and in compliance with the applicable land use plans and zoning ordinances. The Siting Board’s determination was based on the County’s plans for the construction and operation of four MWC units at the Facility. The Site is currently zoned “Planned Development”, and is designated “Public/Quasi-Public” under the County’s comprehensive land use plan, specifically to allow the Facility and the Project to be built and operated on the Site. The Existing Facility The Facility currently has three MWC units. Each MWC unit has a nominal design capacity of 400 tons per day (“tpd”) of municipal solid waste (440 tpd when burning a reference fuel with a higher heating value of 4500 British thermal units (“Btu”) per pound). The three MWC units are located inside a fully enclosed building, which also contains the air pollution control systems for the MWC units, the “tipping floor,” the refuse storage pit, and a turbine generator. The Facility also includes an ash management building, cooling tower, stack, stormwater management ponds, water treatment system, transformer yard, electrical transmission lines, and ancillary equipment and facilities. Municipal solid waste (e.g., household and commercial garbage) is delivered to the Site in trucks, which drive inside the refuse storage building to the tipping floor, where the trucks dump the MSW into the refuse storage pit. Two overhead cranes mix the waste in the refuse storage pit and then load the waste into the charging hoppers that feed the three MWC units. The combustion of the municipal solid waste produces heat, which is used to produce steam. The steam is used in a turbine generator to produce approximately 29.5 megawatts (“MW”) of electricity. The Project The Project involves the construction and operation of a fourth MWC unit at the Facility. The new unit will be substantially the same as the three existing MWC units, but larger. The new unit will be designed to process approximately 600 tpd of municipal solid waste (660 tpd @ 5000 Btu/lb). A new turbine generator also will be installed, which will increase the Facility’s electrical generating capacity by approximately 18 MW, thus increasing the Facility’s total net generating capacity to approximately 47 MW. In addition, the Facility’s cooling tower will be expanded, the refuse and ash management buildings will be expanded, two lime silos and a carbon silo will be installed, a new settling basin will be installed, and other related improvements will be made. Construction of Unit No. 4 The Facility was designed and built to accommodate the addition of a fourth MWC unit, thus making the construction of Unit No. 4 relatively simple, without disrupting large areas of the Site. Unit No. 4 will be located adjacent to the three existing MWC units. The construction of the other Facility improvements also will occur adjacent to the existing components of the Facility. Only about 0.3 acres of the Site will be converted from open space to a building or similar use. Construction of Unit No. 4 will occur in previously disturbed upland areas on the Site that are already used for industrial operations. Construction of Unit No. 4 will not affect any wetlands or environmentally sensitive areas. No new electrical transmission lines will need to be built to accommodate the additional electrical power generated by Unit No. 4. No new pipelines or other linear facilities will need to be built for the Project. The construction of Unit No. 4 will not expand the Facility beyond the boundaries of the Site that was certified by the Siting Board in 1984. Operation of Unit No. 4 The basic operation of the Facility will not change when Unit No. 4 becomes operational. Municipal solid waste will be processed at the Facility in the same way it is currently processed. The Facility has operated since 1987 and has an excellent track record for compliance with all applicable regulations, including regulations concerning noise, dust, and odors. All of the activities involving solid waste and ash occur inside enclosed buildings. The tipping floor and refuse storage pit are maintained under negative air pressure, thus ensuring that dust and odors are controlled within the building. Since the operations at the Facility will remain the same after Unit No. 4 becomes operational, no problems are anticipated in the future due to noise, dust, or odors. The Facility’s basic water supply and management system will remain the same after Unit No. 4 becomes operational. Treated wastewater from the County’s co-located Falkenburg Road Wastewater Treatment Plant (“WWTP”) will be provided via an existing pipeline to satisfy the Facility’s need for cooling water. Potable water will be provided to the Facility via an existing pipeline from the City of Tampa’s water supply plant. The Facility does not use groundwater or surface water for any of its operations. The Facility will not discharge any industrial or domestic wastewater to any surface water or groundwater. Most of the Facility’s wastewater will be recycled and reused in the Facility. Any excess wastewater will be discharged to the Falkenburg Road WWTP. Stormwater runoff from the Project will be collected and treated in the existing system of swales and ponds on the Site. The County will modify two existing outfall weirs to provide improved treatment of stormwater and to ensure compliance with water quality standards. A traffic analysis was performed to evaluate the potential traffic impacts associated with the operation of the Facility, after the Project is completed. The analysis demonstrated the Facility will not have any significant impacts on the surrounding roadway network, even when Unit No. 4 is operational. Air Quality Regulations The County must comply with federal and state New Source Performance Standards (“NSPS”) and Best Available Control Technology (“BACT”) requirements, both of which impose strict limits on the Facility’s airborne emissions. The County also must comply with Ambient Air Quality Standards (“AAQS”) and Prevention of Significant Deterioration (“PSD”) standards, which establish criteria for the protection of ambient air quality. Best Available Control Technology BACT is a pollutant-specific emission limit that provides the maximum degree of emission reduction, after taking into account the energy, environmental, and economic impacts and other costs. As part of the BACT determination, all available and feasible pollution control technologies being used worldwide are evaluated. The Department performed a BACT determination for the Project. As part of its BACT analyses, DEP determined that (a) a flue gas recirculation system and a selective non-catalytic reduction system (“SNCR”) will control NOx; (b) a spray dryer with lime injection will control MWC acid gas; (c) an activated carbon injection system (“ACI”) will control MWC organic compounds; (d) a fabric filter baghouse will control particulate matter and MWC metals; and (e) proper facility design and operating methods will control other pollutants. These air pollution control technologies (except flue gas recirculation) and methods are currently used in the three existing MWC units and they have performed extremely well. Unit No. 4 will have better, more modern, and more sophisticated versions of these air pollution control systems, plus a flue gas recirculation system. In its analysis of the Project, DEP determined the emission limits for the Project that represent BACT. All of the emission limits determined by DEP for Unit No. 4 are as low as or lower than the emission limits established in 2006 by the U.S. Environmental Protection Agency (“EPA”) in the NSPS (40 CFR 60, Subpart Eb) for new MWC units. The NSPS are based on the use of Maximum Achievable Control Technology (“MACT”). Unit No. 4 will be subject to the lowest NOx emission limits imposed on any MWC unit in the United States. The Facility will use an array of continuous emissions monitors to help ensure that the Facility is continuously in compliance with the DEP’s emission limits. Indeed, Unit No. 4 will be the first MWC unit in the United States to be equipped with a continuous emissions monitor for mercury. Protection of Ambient Air Quality The EPA has adopted “primary” and “secondary” National Ambient Air Quality Standards ("NAAQS"). The primary NAAQS were promulgated to protect the health of the general public, including the most susceptible groups (e.g., children, the elderly, and those with respiratory ailments), with an adequate margin of safety. The secondary NAAQS were promulgated to protect the public welfare, including vegetation, soils, visibility, and other factors, from any known or anticipated adverse effects associated with the presence of pollutants in the ambient air. Florida has adopted EPA’s primary and secondary NAAQS, and has adopted some Florida AAQS (“FAAQS”) that are more stringent than EPA’s NAAQS. The County analyzed the Project’s potential impacts on ambient air quality, using conservative assumptions that were intended to over-estimate the Project’s impacts by a wide margin. These analyses demonstrate that the maximum impacts from Unit No. 4 will be less than one percent of the amount allowed by the ambient air quality standards. The maximum impact from the Facility (i.e., all four units) will be less than 2.5 percent of the amount allowed by the FAAQS and NAAQS. For these reasons, the emissions from Unit No. 4 and the Facility are not expected to cause adverse impacts on human health or the environment. The maximum impacts of Unit No. 4 and the Facility, when operating under worst case conditions, will be immeasurably small and will be indistinguishable from ambient background conditions. Human Health and Ecological Risk Assessments The County performed a human health and ecological impact assessment of the risks associated with the Facility’s airborne emissions. The County’s risk assessment evaluated the impacts of the entire Facility, with all four MWC units in operation. The risk assessment was designed to over-estimate the potential impacts of the Facility. The County’s risk assessment was conducted in compliance with current EPA guidance. The risk assessment considered hypothetical human receptors (e.g., infants, children, and adults) that were engaged in different types of behavior (e.g., a typical resident; a beef farmer; a subsistence fisherman) and were exposed through multiple pathways (e.g., inhalation; ingestion of soil; ingestion of local produce, beef, and/or fish) to chronic long term impacts from the Facility. The risk assessment also considered the Facility’s potential impacts on sensitive environmental receptors, including aquatic life (benthic dwelling aquatic organisms), wood storks, and river otters. The County’s risk assessment demonstrates that the potential risks associated with the Facility’s emissions will not exceed, and in most cases will be much less than, the risks that are deemed acceptable by the EPA and DEP for the protection of human health and the environment. The County’s assessment is consistent with the findings in environmental monitoring studies, epidemiological studies, and risk assessments that have been performed for other modern waste-to-energy ("WTE") facilities in the United States. The County’s findings also are consistent with the determinations made by the EPA, which has concluded that WTE facilities equipped with modern pollution control systems are a “clean, reliable, renewable source of energy.” The evidence presented by the County in this case demonstrates that the Facility is not likely to have any adverse effect on human health or the environment, even when all four MWC units are operational, if the Facility is built and operated in compliance with the Conditions of Certification. Potential Impacts on Water Quality The Facility’s emissions of nitrogen oxides (i.e., NOx) will not cause or contribute to violations of any water quality standards in any surface waterbody. Environmental Benefits of the Project The addition of Unit No. 4 will provide significant environmental benefits to the County. Unit No. 4 will reduce the volume of processible solid waste by approximately 90 percent. By reducing the volume of processible waste, Unit No. 4 and the Facility will greatly extend the useful life of the County’s landfill, thus postponing the need to build a new landfill. The Facility also will convert putrescible waste into a relatively inert ash, which poses less threat to groundwater resources. The Project will also provide environmental benefits to the State of Florida. For example, the Facility will produce electricity from discarded materials. In this manner, Unit No. 4 will reduce the need to use fossil fuels to generate electricity at traditional power plants. Unit No. 4 will eliminate the need to use approximately 4 million barrels of oil and thus will save approximately $200 million in oil purchases over the next 20 years. Socioeconomic Benefits of the Project The local economy and labor market will benefit from approximately $100 million that the County will spend to construct the Project. A significant amount of construction supplies, goods, and services are anticipated to be purchased from local businesses. The Project will provide jobs for construction workers. The daily workforce is expected to average between 25 and 75 people over a period of approximately 21 months. The addition of Unit No. 4 will also provide approximately 8 new permanent jobs at the Facility. WTE Criteria in Section 403.7061 Section 403.7061, Florida Statutes, establishes several criteria that must be satisfied before an existing waste-to-energy facility may be expanded. The County has provided reasonable assurance that the Project will satisfy all of the standards and criteria in Section 403.7061, Florida Statutes. Among other things, the County has demonstrated that the County’s waste reduction rate has consistently exceeded the State’s 30 percent recycling goal. Consistency With Land Use Plans and Zoning Ordinances As required by Section 403.508(2), Florida Statutes, the County demonstrated that the Site is consistent and in compliance with the Hillsborough County comprehensive land use plan and Hillsborough County’s applicable zoning ordinances. Compliance with Environmental Standards The Department has concluded and the evidence demonstrates that the County has provided reasonable assurance the Project will comply with all of the nonprocedural land use and environmental statutes, rules, policies, and requirements that apply to the Project, including but not limited to those requirements governing the Project’s impacts on air quality, water consumption, stormwater, and wetlands. The County has used all reasonable and available methods to minimize the impacts associated with the construction and operation of the Facility. The location, construction, and operation of the Project will have minimal adverse effects on human health, the environment, the ecology of the State’s lands and wildlife, and the ecology of the State’s waters and aquatic life. The Project will not unduly conflict with any of the goals or other provisions of any applicable local, regional, or state comprehensive plan. The Conditions of Certification establish operational safeguards for the Project that are technically sufficient for the protection of the public health and welfare, with a wide margin of safety. Agency Positions Concerning Certification of the Project On May 4, 2006, the PSC issued a report concluding that the Project was exempt from the PSC’s need determination process, pursuant to Section 377.709(6), Florida Statutes. The DEP, DOT, and SWFWMD recommend certification of the Project, subject to the Conditions of Certification. The other agencies involved in this proceeding did not object to the certification of the Project. The County has accepted, and has provided reasonable assurance that it will comply with, the Conditions of Certification. Public Notice of the Certification Hearing On December 19, 2005, the County published a “Notice of Filing of Application for Electrical Power Plant Site Certification” in the Tampa Tribune, which is a newspaper of general circulation published in Hillsborough County, Florida. On May 25, 2006, the County published notice of the Certification Hearing in the Tampa Tribune. On December 23 and December 30, 2005, the Department electronically published “Notice of Filing of Application for Power Plant Certification.” On May 26, 2006, the Department electronically published notice of the Certification Hearing. The public notices for the Certification Hearing satisfy the informational and other requirements set forth in Section 403.5115, Florida Statutes, and Florida Administrative Code Rules 62-17.280 and 62-17.281(4).

Conclusions For Petitioner Hillsborough County (the “County”) David S. Dee, Esquire Young van Assenderp, P.A. 225 South Adams Street, Suite 200 Tallahassee, Florida 32301-1720 For the Florida Department of Environmental Protection (“Department” or “DEP”) Scott A. Goorland, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, M.S. 35 Tallahassee, Florida 32399-300

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that the Governor and Cabinet, sitting as the Siting Board, enter a Final Order granting a site certification for the construction and operation of Unit No. 4 at the Hillsborough County Resource Recovery Facility, in accordance with the Conditions of Certification contained in DEP Exhibit 2. DONE AND ENTERED this 2nd day of August, 2006, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of August, 2006.

CFR (1) 40 CFR 60 Florida Laws (10) 120.569377.709403.501403.502403.507403.508403.5115403.517403.519403.7061
# 7
KENNETH C. WILLIAMS, JOSEPH KAISER, ET AL. vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 76-001250 (1976)
Division of Administrative Hearings, Florida Number: 76-001250 Latest Update: Jun. 08, 1977

Findings Of Fact Respondent, Textron Petroleum Products Company, Inc., has applied for a construction permit to construct a sanitary landfill in Sections 3 and 10, Township 1 North, Range 2 East, Leon County, Florida. The proposed site consists of ninety (90) acres and is approximately 2,000 feet from U.S Highway 90 at Its closest point to that highway. The application is in proper form and contains all information required by the Department of Environmental Regulation. towns and areas to be served by the application are the City," of Tallahassee and Leon County. The facility is designed to serve a population of 135,000 people. Although evidence was presented for the purpose of showing that the City of Tallahassee and Leon County, as governmental entities, do not intend to use the proposed sanitary landfill as an "official" landfill site for those governmental bodies, this evidence did not establish that the area to be served and the population to be served by the proposed sanitary landfill is other than that stated above. The applicant, Textron Petroleum Products Company, Inc. does not have a franchise from any county, municipality or other governmental agency with regard to solid waste resource recovery and management responsibilities. The applicant, Textron Petroleum Products Company, Inc., had not, at the time of hearing, posted a performance bond or other approved security with the agency within whose jurisdiction the proposed site is located. The "owner" as that term is used in Section 17-4.21(1)(d), F.A.C., is the applicant, Textron Petroleum Products Company, Inc. The unrebutted evidence presented,at hearing established that the applicant has a net worth of $1 million and is financially responsible. The evidence presented did not establish any violation of the State Resource Recovery And Management Program set out in Part II, Chatper 17-7, F.A.C. There is a public supply well located in the Homestead Ridge area. This system serves 38 or more customers at an averave rate of about 200,000 gallons per month. The well is located more than 2,700 feet from the site boundary of the proposed sanitary landfill. As found by the Northwest Florida Water Management District, even if the consumption of that well system were increased to 2.16 million gallons of water per month, the drawdown at a radius of 2,000 feet would be 0.13 feet. Therefore, it was concluded that the cone of influence of the public water supply does not extend under the proposed sanitary landfill site. As a condition for issuance of a construction permit the Department of Environmental Regulation proposes the requirement of a monitoring system of wells which would include a deep well located between the proposed site and the Homestead Ridge public supply, the purpose of which would be to detect the potential intrusion of leachate or other contaminants into the public water supply from the sanitary landfill. It is improbable that the proposed sanitary landfill will produce any significant quantity of leachate. However, the application proposes that if monitoring indicates that lechate control is needed, a well point system will be installed in the completed cells and underground pipe drains installed in the new cells. It further provides that, dependent upon the quantities involved, the leachate.will be transported to the City of Tallahassee Sewage Treatment Facilities for disposal or it will be treated on-site by transporting the leachate to the settling pond which will at that time be equipped with suitable aeration and chlorination equipment for treatment of the leachate. The proposed design of the sanitary landfill provides that all final discharge from the sedimentatlon pond will conform to the water quality standards set out in Chapter 17-3, F.A.C, even though this may require the constrjction of treatment equipment by the applicant. The application, at pages 12 and 14,.provides for the equipment to be used on-site in the operation of the proposed sanitary landfill as well as for the method of providing adequate site supervision. No evidence was presented showing these provisions to be other than adequate. The evidence presented did not establish that the utilization of U.S. Highway 90 by vehicles transporting waste to the proposed sanitary landfill would create any unusual 0rincreased traffic and safety hazard. The application, at page 3, proposed the installation of electronic signalization equipment to alleviate any hazard which might be created by traffic using the proposed site. No evidence was presented showing this proposal to be inadequate. According to a letter to Mr. James Barrineau, Leon County Department of Pollution Control, from Mr. Mark Stamps, Assistant Zoning Director, Tallahassee Leon County Planning Department, the proposed site is currently zoned Agricultural 2. The letter further states that an Agricultural 2 zoning allows a sanitary landfill as a permitted use. A small portion of the proposed sanitary landfill site is open to public view from,U.S. Highway 90 which is a major thoroughfare. It was estimated by a witness that the distance to the proposed site from that section of U.s. Highway 90 from which the site was open to public view was one (1) mile. An examination of the plot plan of.the proposed site contained in the application shows that at the closest point, the site boundary is approximately 2,000 feet from U.5 Highway 90. The site is screened from public view from most places on Highway 90 by the existing topography and ground cover.

Florida Laws (4) 403.702403.706403.7147.04
# 8
SON-MAR SOUTH SANITATION, INC. vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 94-005488BID (1994)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Oct. 05, 1994 Number: 94-005488BID Latest Update: Jul. 05, 1995

Findings Of Fact On November 16, 1988, Industrial Waste Service, Inc. (IWS), obtained approval to provide garbage and trash collection services to the City of Pembroke Pines (City) when the City passed and adopted Resolution No. 1876 approving the assignment of the contract for such services between the City and Citywide Sanitation Company, Inc. (Citywide), to IWS. Citywide's contract was to expire June 30, 1993. On November 6, 1991, the city amended Chapter 112 of its Code and passed and adopted a solid waste franchise ordinance, called the "City Solid Waste Franchise Ordinance," Ordinance No. 975, effective November 6, 1991. The Ordinance provides in pertinent part: Sec. 112.39 FRANCHISE REQUIRED TO OPERATE; RESTRICTIONS ON OPERATING IN THE CITY; AWARD OF FRANCHISE It shall be unlawful to commence or engage in the business of collecting and disposing of solid waste originating in the city without a franchise issued by the franchising authority in accordance with the provisions of this subchapter. It shall be unlawful for any hauler operating in the city to dispose of solid waste collected in the city at any location other than to the Resource Recovery System transfer station or facilities designated in the plan of operation under the Solid Waste Disposal Agreement, as defined in section 94.22 of the code, the City's Flow Control Ordinance. (Underscore and strike through omitted) On February 13, 1992, the City and IWS entered into a "Solid Waste Collection & Disposal Agreement" (Agreement). The Agreement provides in pertinent part: 2. DEFINITIONS Contract Collection Area shall include all of the City of Pembroke Pines, Florida, as the boundaries of said City shall exist at all times during the life of this Contract. * * * 4. TERM & EFFECTIVE DATE The term of this Contract shall be for a five (5) year period beginning February 1. 1992 and termi- nating January 31, 1997. This Agreement shall become effective upon execution by the parties hereto. On April 1, 1992, the Agreement was amended, "First Amendment to Solid Waste Collection & Disposal," which provides in pertinent part. DEFINITIONS * * * Commercial Service shall mean the collection and disposal of Garbage, trash, Solid Waste and Processable Waste for all Business, Commercial, Industrial, hospital, school, governmental and quasi-governmental establishments, including the collection and disposal of Construction and Demolition Debris. * * * Processable Waste shall mean that portion of Waste Stream that is capable of being processed in the Corporation's resource recovery and compost facility, including but not limited to materials which are recyclable and all acceptable Waste other than Non- Processable Waste (as defined herein). * * * Solid Waste shall mean all waste accumulations consisting of garbage, residential/household trash, commercial/business trash and construction and demolition debris, including but limited to all materials which are recyclable. * * * CONTRACTOR'S RIGHTS (D) The City further grants to Contractor the exclusive right to service all Residential Curbside, Apartment, Condominium, Business, Industrial, and Commercial establishments that are certified for occupancy after February 1, 1992, provided, however, a certificate of occupancy issued as a result of remodeling with no change in ownership shall not require the owner to change service to the Contractor except for the Solid Waste (i.e. Construction Demolition and Debris) created thereby. * * * The City grants to the Contractor the exclusive right to provide Solid Waste collection and disposal services to any Residential Apartment, Business, Commercial or Industrial establishments for the following customers as of February 1, 1992: For CONTRACTORS's existing customers; and For customers that have a change in ownership after the City's approval of the Agreement; and For customers which received Solid Waste collection and disposal services in the City prior to the City's approval of the Agreement and whose contract for such services expires and is not renewed with the same provider in the future. (Underscore and strike through omitted) On November 4, 1992, the City passed and adopted an ordinance, Ordinance No. 1016, amending Chapter 94 of its Code providing for a new subchapter entitled "Garbage Collection" and providing new sections. The Ordinance provides in pertinent part: Sec. 94-10 Agreement with Private Collector. The City acting by and through its City Commission, and in accordance with the provisions of Section 112.37 through 112.41 of the Code, approved a Solid Waste Collection & Disposal Franchise Agreement dated January 15, 1992, as amended by the First Amendment dated April 1, 1992 ("Agreement") between the City and Industrial Waste Service Inc. ("Collector"). All providers of Solid Waste collection and disposal services other than Collector who provide such services within the City boundaries shall be referred to herein as "Haulers". All terms not otherwise defined in this Subchapter shall have the meaning ascribed thereto in the Agreement. The Agreement is specifically made a part hereof as Appendix A, and a copy of same will be maintained at the City Clerk's Office at City Hall. Pursuant to the Agreement the City has granted the Collector the following rights and obligations to provide Solid Waste collection and disposal services: * * * The exclusive right and obligation to provide solid waste collection and disposal services within the City boundaries, present and future, for all Residential Curbside, and all Apartment, Condominium, Business, Industrial and Commercial establishments that are certified for occupancy after February 1, 1992, and govern- mental establishments to the extent permitted by law, provided, however, that a certificate of occupancy issued as a result of remodeling with no change in ownership of the property shall not require the Customer to change to Collector except for construction/remodeling demolition and debris created thereby; and The exclusive right and obligation to provide solid waste collection and disposal services within the City boundaries for all construction or remodeling demolition and debris within the City; and As of February 1, 1992, the exclusive right and obligation to provide solid waste collection and disposal services within the City boundaries for; [sic] Collector's existing Customers; Customers/property owners in the City that have a change in ownership; and customers/property owners whose contract for solid waste collection and disposal services expires and is not renewed with the same provider. Sec. 94.14 Certain Acts Prohibited. * * * (C) It shall be a violation of this subchapter for any person, firm, corporation or other entity, other than Collector to collect and/or dispose of Solid Waste originating in the City except to the extent the same is specifically permitted by the terms of this subchapter. (Underscore and strike through omitted) By letter dated June 10, 1992, IWS notified South Florida State Hospital that it (IWS) was the exclusive contractor for solid waste collection and disposal. South Florida State Hospital (Hospital) is a state mental health treatment facility operated and administered by the Division of Health and Rehabilitative Services (HRS) pursuant to Chapter 394, Florida Statutes. The Hospital is located on state property and is situated within the city limits of the City of Pembroke Pines (City), Broward County, Florida. In December 1993, HRS published an Invitation To Bid (ITB) on Bid # 595-591 for waste disposal services at the Hospital. Browning Ferris Industries, IWS, and Southern Sanitation Service submitted bids. On December 8, 1993, a pre-bid conference was held which included an opportunity for questions and answers. At this conference, HRS pointed out, among other things, that the City had an exclusive contract with IWS for waste disposal services but it (HRS) was also obligated by Florida Statutes to ensure the bidding remained competitive and that all waste collected from the Hospital had to be deposited at land fill sights designated by the City. In or around January 1994, HRS notified the bidders of Bid # 595-591 that, due to the bid document being flawed, a contract would not be awarded. All the bidders filed protests but none raised the City's exclusive contract with IWS as an issue. Ultimately, the contract was awarded to IWS but for only a six-month period. In April 1994, HRS published another ITB on Bid # 595-594 for waste disposal services at the Hospital. In the section entitled "SECTION A. INTRODUCTION," the ITB provides in pertinent part: STATEMENT OF NEED [T]he department requires the services of a qualified waste disposal company to provide waste disposal services to maintain sanitary conditions essential to the health, safety and well being of residents and staff living and working at the hospital. STATEMENT OF PURPOSE Pursuant to Florida Statutes, Chapter 287, this Invitation to Bid is being issued by the State of Florida, Department of Health and Rehabilitative Services, South Florida State Hospital, to obtain the services of a suitably qualified provider to enter into a contract for the removal and disposal of garbage from the hospital campus, and related services; in keeping with hospital requirements and the waste flow control ordinance of the City of Pembroke Pines. In the section "SECTION B. ITB SPECIFICATIONS: MINIMUM DEPARTMENTAL REQUIREMENTS," the ITB provides in pertinent part: PROGRAMMATIC REQUIREMENTS Method of Service Delivery 13) The provider will dispose of waste collected from the hospital at disposal site(s) specified by the City of Pembroke Pines, in keeping with the city's waste flow control ordinance. * * * Other Special Requirements * * * 2) Bidders Eligibility Requirements The successful bidder, in order to contract with the department to provide the services requested by this Invitation to Bid, must have all licenses and/or permits in accordance with city and county ordinances, rules, regulations, and provisions. All licenses and/or permits must be obtained at provider's expense. All costs for tests and inspections shall be paid for by the provider. GENERAL INFORMATION * * * Acceptance of Bids [T]he department reserves the right to reject any or all bids or waive minor irregularities when to do so would be in the best interest of the State of Florida. Minor irregularities are those which will not have a significant adverse effect on overall competition, cost or performance. In the section entitled "SECTION E. BID EVALUATION CRITERIA AND BID TABULATION," the ITB provides in pertinent part: 1) Evaluation Committee An evaluation committee of at lest three (3) members will be established to select the lowest responsive and qualified bidder. * * * 3) Evaluation of Bids Following the bid opening, the committee will review bid packages, beginning with the lowest cost bid, for compliance with the ITB requirements. A Fatal Items Checklist (Appendix IX) will be used to evaluate all bid packages. All items on the checklist MUST be met in order for the proposal to be considered. Receipt of a "No" response for any item will result in automatic rejection of the bid. All references will be checked. Only bidders with a good record of satisfactory performance will be considered. The contract will be awarded to the lowest responsive and qualified bidder who meets all the criteria specified in this ITB. The section entitled "General Conditions" of the ITB Contractual Services Bidder Acknowledgment form provides in pertinent part: 7. AWARDS: As the best interest of the State may require, the right is reserved to make award(s) by individual service, group of services, all or none, or a combination thereof; to reject any and all bids or waive any minor irregularity or technicality in bids received. Bidders are cautioned to make no assumptions unless their bid has been evaluated as being responsive. In response to the ITB, HRS received bids from Browning Ferris Industries which had previously bid on Bid # 595-591, Coastal Carting, Ltd., IWS which had also previously bid on Bid #595-591, Son Mar South Sanitation, Inc. (SON MAR), and Southern Sanitation Service which had also previously bid on Bid # 595-591. SON MAR was the apparent lowest bidder with a bid of $72,200.48 for the first year, $79,420.52 for the second year, and $87.362.57 for the third year, totalling $238.983.57, and IWS was the apparent second lowest bidder with a bid of $106,739.84 for the first year, $112,734.46 for the second year, and $121,971.12 for the third year, totalling $341,445.42. Subsequently, IWS' bid was recalculated due to HRS discovering a calculation error by IWS. The recalculation was performed without a reconvening of the Evaluation Committee and resulted in IWS' bid being $113,579.84 for the first year, $119,814.46 for the second year, and $129,291.12 for the third year, totalling $362,685.42. The Evaluation Committee reviewed all the bids and evaluated them using, among other things, the Fatal Items Checklist. If one item in the checklist were not satisfied, a bid would be disqualified. Pertinent to this case, both SON MAR and IWS satisfied the Checklist and all other evaluation criteria used by the Committee. On May 12, 1994, the Bid Tabulation sheet was posted. HRS indicated its intent to award Bid # 595-594 contract to SON MAR as the apparent lowest and responsive bidder. At that time, HRS was aware that SON MAR had no licenses or permits issued by the City. The Evaluation Committee considered the absence of a license or permit as not material to awarding the bid 1/ and were aware that an awardee obtaining a license or permit would involve a simple process of the awardee completing an application for and paying a fee to the City. By letter dated May 20, 1994, HRS requested that the City advise it of any permits and/or licenses required by the City for an awardee to provide waste removal services to the Hospital. HRS did not receive a written response to its letter. Instead, the City orally advised HRS that it (the City) would issue SON MAR a special permit which would be issued upon SON MAR making application for an occupational license and paying a franchise fee. SON MAR was agreeable to complying with the City's terms and conditions. SON MAR dispatched one of its representatives to the City to obtain an application for the license. However, the City refused to provide SON MAR an application. By letter dated June 13, 1994, IWS filed its formal bid protest of Bid # 595-594 with HRS alleging, among other things, that SON MAR did not have a license from the City to provide waste removal services because it (IWS) had the exclusive waste removal contract with the City, that, without a license, SON MAR could not comply with the bid eligibility requirements and that, therefore, the bid should be awarded to it (IWS). On or about June 28, 1994, SON MAR notified the City that its refusal to issue it (SON MAR) an occupational license was unconstitutional per a U.S. Supreme Court case and requested immediate issuance of the license. SON MAR forwarded HRS a copy of this notification and request. By letter dated June 30, 1994, the City notified SON MAR that it would not issue it (SON MAR) a permit to provide waste removal services in the City, as such an action would violate the exclusive franchise agreement that it (the City) had with IWS. On or about June 30, 1994, HRS was aware that the City would not permit SON MAR to provide waste removal services in the City as it received a copy of the City's letter to SON MAR. On July 14, 1995, HRS and IWS settled the protest filed by IWS, without involving SON MAR in the negotiations. The terms of the settlement, which were communicated to SON MAR on July 15, 1995, were that IWS would dismiss its protest if, within ten days, 2/ SON MAR obtained a license/permit from the City, produced the license to HRS and otherwise remain qualified for the award and that, if SON MAR was unable to obtain a license from the City, HRS would declare SON MAR unqualified and declare IWS the lowest responsive and qualified bidder and award the bid to IWS. SON MAR was unable to obtain a license from the City. Moreover, the City refused to provide SON MAR with an application, remaining consistent with its letter of June 30, 1994, to SON MAR. As SON MAR was unable to obtain a license within the prescribed ten- day period, by letter dated July 29, 1994, HRS notified all bidders to Bid # 595-594 that it was declaring SON MAR unqualified and of its intent to award the bid to IWS, as the next lowest and qualified bidder. Further, HRS notified the bidders that the bids of IWS and another bidder were recalculated to correct a calculation error, which would not affect the order of the bids. By letter dated August 9, 1994, SON MAR notified HRS of its intent to file a formal protest. On or about August 24, 1994, SON MAR filed its formal protest. At no time material hereto, has SON MAR pursued any civil action to challenge the validity of the exclusive contract between the City and IWS or the constitutionality of the City's Ordinance.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Health and Rehabilitative Services enter a final order awarding Bid # 595-594 to Industrial Waste Service, Inc. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 28th day of March 1995. ERROL H. POWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March 1995

Florida Laws (7) 112.41120.53120.57120.68284.30287.012287.057
# 9
HIGHLANDS LAKES ESTATES HOMEOWNERS' ASSOCIATION, JOHN W. FROST, II, AND TERRY P. FROST vs REPUBLIC SERVICES OF FLORIDA, L.P., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 09-006750 (2009)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Dec. 15, 2009 Number: 09-006750 Latest Update: Nov. 30, 2010

The Issue The issue is whether Respondent Department of Environmental Protection (DEP) may issue to Respondent Republic Services of Florida, L.P. (Republic), permits to construct and operate a Class III landfill, pursuant to Permit Numbers 266830-003-SC/01 and 266830-004-SO/01, as modified as set forth below.

Findings Of Fact Background On June 30, 2009, Republic filed with DEP an application for a permit to construct and operate a Class I landfill (Application). In response to DEP's request for additional information dated July 30, 2009 (RAI), Republic filed a response dated September 14, 2009 (RRAI), upon receipt of which, DEP deemed the Application to be complete. References to the Application typically include the Application, RRAI, and other materials, such as reports, plans, and drawings, that are part of the Application, as well as three subsequent modifications, which are detailed below. Republic revised several reports, plans, and drawings in the RRAI; references to these items, such as the Engineering Report and Operation Plan, are to the versions contained in the RRAI. On November 13, 2009, DEP filed its intent to issue construction permit #266830- 003-SC/01 (Construction Permit) and intent to issue operation permit #266830-004-SO/01 (Operation Permit; collectively, the Permit). Republic Services, Inc. and its affiliates constitute the second largest waste-management operator group in the United States. Their market capitalization is just over $11 billion. The capitalization of the affiliate formed to operate the subject landfill is doubtlessly less than $11 billion, as the record does not suggest that any significant part of the overall capitalization of Republic Services, Inc., and its affiliates would be at risk in the operation of the proposed landfill. Republic presently owns and operates a Class III landfill in the City of Bartow, Polk County, known as the Cedar Trail Landfill. The oldest part of this landfill is an unlined Class III landfill of 52.5 acres in the center of the property owned by Republic. Immediately west of this unlined landfill is a 30.7-acre lined Class III landfill, which comprises cells 1-4. The Cedar Trail Landfill is located at 2500 West State Road 60, about three miles west northwest of the intersection of State Road 60 and State Road 98, which marks the center of Bartow. The landfill is immediately west of E.F. Griffin Road. Petitioners Frost live on E.F. Griffin Road, about one mile north of the Cedar Trail Landfill. Petitioner Highland Lakes Estates Homeowner's Association serves a residential subdivision known as Highland Lakes Estates. Highland Lakes Estates occupies a notch at the southeast corner of Republic's property. Aerial photographs reveal the changing land use of the land on which Cedar Trail Landfill is situated. Fifty years ago, the land was vacant with indications of agricultural uses. At the site of the proposed landfill were mostly citrus groves on the west side and some rangeland or vacant land on the east side. Ten years later, a large area immediately northeast of the subject land reveals the effects of strip mining for phosphate. Three years later, in 1971, the mined area had greatly expanded to encompass all or nearly all of the subject site and much of the surrounding area, including the western half of what would become Highland Lakes Estates. By 1980, the pits had been refilled and active mining had ceased, and the streets had been constructed for what is now known as Highland Lakes Estates. By 1993, about three dozen homes had been built in this residential, large-lot subdivision. 9. The Cedar Trail Landfill was constructed in the early 1990s as an unlined construction and demolition debris landfill. Now designated an approved landfill for Class III waste, this facility accepts such waste as is defined by Florida Administrative Code Rule 62-701.200(14) (2010), which includes construction and demolition debris, yard trash, processed tires, asbestos, carpet, paper, glass, furniture (but not white goods), plastic, and other materials not expected to produce leachate that presents a risk to the public health or environment. A zoning/land use map reveals that the land for which the proposed landfill is proposed is designated "sewage/borrow pits/spray fields." Highland Lakes Estates occupies land that is designated single-family residential with a density of one dwelling unit on up to 2.49 acres. The Cedar Trail Landfill has been the subject of three recent environmental resource permits (ERPs). Appendix R to the Application is an individual ERP issued in April 2009, and Appendix R to the RRAI is a conceptual ERP issued in March 2005. The April 2009 ERP mentions that the entire stormwater project was conceptually approved by an ERP issued on September 10, 2008, but this ERP is not part of the record. In any event, these ERPs approve the construction of a comprehensive stormwater or surface water management system for the entire Republic property. In particular, the April 2009 ERP permits the construction of a borrow pit at the southeast corner of the Republic property and a modification of the perimeter ditch/wet retention system. The April 2009 ERP states that the permitted stormwater management system will provide total onsite retention for runoff from the 100-year, 24-hour storm. The April 2009 ERP requires 2.8 acres of compensation for 2.8 acres of encroachment in the 100-year floodplain. Specific Condition 14 prohibits excavation of the borrow pits to a clay confining layer or limestone bedrock layer. Specific Condition 20 prohibits the mixing of leachate with stormwater and provides that, if leachate enters stormwater, the stormwater becomes leachate. Presumably reflecting this permitting activity, Application Drawing 4, as revised in the RRAI, is the site plan, including the unlined Class III landfill, the four-cell lined Class III landfill immediately to the west of the unlined landfill, and the eight cells proposed to accept Class I waste. These eight cells are immediately south of the four cells of the lined Class III landfill. The two northernmost of these eight cells abut, on their east boundary, the unlined Class III landfill. The remaining six cells abut, on their east boundary, an 800-foot wide borrow pit, which lies between these cells and Highland Lakes Estates. Immediately north of Highland Lake Estates is a second borrow pit, and west of this borrow pit is the unlined Class III landfill. The other major feature on the site plan is a third borrow pit running, from west to east, along the north border of the lined Class III cells, the unlined Class III landfill, and the second borrow pit. Bearing no signs of ambitious reclamation activity, the backfilled mining cuts host large water storage areas and, as described in the application for the March 2005 ERP, wetlands of "very poor quality." The backfilled soils are best described as complex surficial soils, consisting mostly of fine sands with varying amounts of organics, silts, and clays. Geotechnical investigations of the Cedar Trail Landfill suggest that mining depths, although variable, probably averaged 40 feet. Petitioners and Intervenor are substantially affected by the Permit and the construction and operation of the proposed landfill, which will stand nearly 200 feet above grade and will be the focus of substantial activity six days per week during its years of operation. Like Petitioners, Intervenor owns land in the immediate vicinity of the Cedar Trail Landfill, which is in the jurisdiction of Intervenor, and Intervenor's various municipal operations are much affected by whether the proposed Class I landfill is permitted. Among other things, Intervenor has agreed to accept untreated leachate from the proposed landfill. Petitioners Frost built their home in 1980 or 1981. During the hours of operation of the existing landfill, Petitioners Frost constantly hear the beeping noise of heavy- duty equipment, presumably a safety device when the equipment is moved. Over a dozen lots in Highland Lakes Estates abut the property line of the Cedar Trail Landfill, and the closest residence is about 1000 feet from the nearest proposed Class I cell. At present, the existing landfill subjects the Highland Lakes Estates to constant noise during operating hours and a coating of dust inside their homes. Several residents of Highland Lakes Estates testified. Hard-working people, some of whom are now retired, these residents decided to purchase homes in Highland Lakes Estates because it was a sunny, healthy place to live. Over time, most of these residents, by varying degrees, have come to accept the fact of the Class III operations at Cedar Trail Landfill, but they object to the substantial intensification of land use that will result from a regional Class I landfill. One resident testified that she finds in her pool dirt that has escaped from the existing landfill, and she has become concerned about her grandchildren coming over to swim. Another resident testified that he only began closing his windows five or six years ago when the noise levels at the existing landfill increased; he eventually had to install a window air- conditioner. The same resident testified that the green herons and snowy egrets that he used to see around his house have not returned for five years, and his wife, who has health problems, including respiratory distress, would suffer from the expanded landfill operations. Application, RRAI, and Permit, Including Modifications The Permit incorporates the Application, including the RRAI, Engineering Report, Operation Plan, and drawings. Thus, all of the documents are part of the Permit. In the Application, Republic proposes to convert cells 5-8, which are not yet constructed, from a Class III to a Class I landfill and add four new cells adjacent to the unused cells. The unfilled portion of Cells 1-4 would continue to receive only Class III waste. Pursuant to Florida Administrative Code Rule 62-701.200(13) (2010), Class I waste is all solid waste, other than hazardous waste, that is not otherwise prohibited by rule. The Application states that the proposed landfill will serve communities within 100 miles. The service area of this regional landfill will thus extend in central Florida from Marion to Osceola counties, along the Gulf Coast from Pasco to Lee counties, and along the Atlantic Coast from Volusia to Martin counties. As stated in the Application, this service area is populated by 9.7 million persons, who would daily account for 3000 tons of waste at the Cedar Trail Landfill. Initially, according to the Engineering Report, the proposed landfill will receive 1600 tons per day of Class I waste, but, once the existing Class III cells are filled, the proposed landfill will receive 1600 tons per day of Class I waste plus the 1400 tons per day of the Class III waste that is currently going into the existing landfill. As revised by the RRAI, the life expectancy of the proposed landfill is seven years. The Application states that Republic will employ an attendant, a trained operator, and 3-5 spotters at the landfill. The Application reports that the landfill would operate Monday through Saturday from 7:00 a.m. to 6:00 p.m. and that the working face would be covered daily. The Application reports that Republic would install seven new detection wells and use 17 existing wells for monitoring groundwater and would use two existing staff gauges for monitoring surface water, evidently at a single location, as discussed in the next paragraph. 23. Application Appendix V is the Water Monitoring Plan. Appendix V states that surface water will be monitored every time that the stormwater pond for the leachate storage area discharges offsite, but not more frequently than weekly. Application Drawing 4, as revised in the RRAI, shows that the sole surface water monitoring location is close to the leachate storage tanks, which are described below. 23. Appendix V also requires leachate monitoring, "at least annually," for five field parameters--specific conductivity, pH, dissolved oxygen, colors, and sheens; eight laboratory parameters--including chloride, mercury, and total dissolved solids; and the parameters listed in 40 CFS Part 258, Appendix II, which includes a comprehensive list of volatile organic compounds; persistent organic pollutants, including 2,3,7,8-TCDD (a major dioxin) and Dibenzofuran; and metals, including lead and chromium. Fourteen days prior to all sampling events, Republic is required to notify DEP, so that it may obtain split samples for its own analysis. Republic is required to report the results of the groundwater monitoring quarterly and to analyze the groundwater data in a technical report filed with DEP every two years. Appendix V also requires monitoring for odors and combustible gases, mostly methane. Republic will monitor combustible gas quarterly at various ambient locations, such as the office buildings and to monitor combustible gas quarterly in the soil down to the seasonal high water table. The purpose of this monitoring is to determine combustible gas concentrations and, if they exceed 25%, take "all necessary steps to ensure protection of human health." Some confusion in the Application arises as to the issue of whether the Cedar Trails Landfill will be subject to, or voluntarily implement, the more elaborate provisions applicable to a landfill covered under Title V of the federal Clean Air Act, as amended in 1990. Regulated emissions for a new source might include particulate matter, sulphur dioxide, nitrogen oxides, volatile organic compounds (VOCs), and specified hazardous air pollutants. Appendix V states that the landfill will become a Title V landfill once permitted to receive Class I waste, and, at that time, it will be subject to a "more comprehensive system of landfill gas collection and monitoring." Appendix V assures that these items "will be addressed in separate documentation from this monitoring plan"--and, apparently, separate from the present record. By contrast, the Operation Plan concedes only that, based on the nature of Class I waste and the design capacity of the proposed landfill, Cedar Trail Landfill "may" become a Title V facility. The Operation Plan states: "If the regulatory thresholds at [Cedar Trail Landfill] are met [under Title V] requiring an active gas collection and control system (GCCS), [Cedar Trail Landfill] will submit as required the GCCS design plans for approval and install an active gas extraction system within the regulatory timeframes specified by Title 40, Code of Federal Regulations, Part 60, Subpart WWW." More specific provisions in the Operation Plan identify best management practices to prevent objectionable odors. Four practices are identified, including an "active gas collection and extraction system." On the DEP form application, which is a cover sheet to the more elaborate application materials, Republic checked boxes indicating that the landfill would use active gas controls with gas flaring and gas recovery, which is probably what is meant by an "active gas collection and extraction system." The Application provides that the landfill liner would be double composite; the leachate collections system would consist of collection pipes, geonets, and a sand layer; the leachate would be stored in tanks; some of the leachate would be recirculated as spray on the working face; and the remainder of the leachate would be stored onsite and periodically transferred to a wastewater treatment center for treatment. The Engineering Report states that the waste disposal footprint will not be located where geological formations or other subsurface features will not provide support for the waste. The Engineering Report identifies appendices addressing the slope-stability analysis and foundation analysis and relies on a March 12, 1997, report by Ardaman & Associates, Inc. (Ardaman Report), January 23, 2004, report by Golder Associates, Inc. (Golder Report), and June 26, 2009, report by Hanecki Consulting Engineers, Inc. (Hanecki Report). These items are discussed in greater detail below in connection with the sinkhole issue. The Engineering Report assures that the waste disposal footprint will not be within 500 feet of an existing or approved potable water well, nor will it be within 1000 feet of an existing or approved potable water well serving a community water supply. The Engineering Report adds that the minimum horizontal distance between waste deposits and the property line is 100 feet. The Engineering Report assures that the landfill footprint will not be in a dewatered pit, as the installation elevations are at least 2-3 feet higher than the seasonal high water table. The Engineering Report acknowledges that a small part of the eastern end of the four southernmost cells lies within the 100-year floodplain, as depicted by the Flood Insurance Rate Map effective December 29, 2000, and as shown in Application Appendix A, Drawing 1. Claiming that the relevant map was not revised in 2000, the Engineering Report asserts that the last update to the FIRM map was in 1975, and the depicted floodplain was filled during the mine reclamation process. The Engineering Report notes that the floodplain concerns were addressed in the April 2009 ERP. 34. The Engineering Report discloses two enforcement actions against Republic at the Cedar Trail Landfill. In a letter dated October 19, 2001, DEP warned Republic about noncompliant items at the site, and, in a notice of noncompliance dated January 30, 2006, DEP warned Republic not to use a new cell prior to construction certification of the cell's stormwater system. Both matters were reportedly resolved, and Republic has not been the subject of other enforcement actions for the Cedar Trails Landfill. At DEP's urging, the RRAI elaborates on enforcement actions against Republic or, evidently, Republic affiliates at a variety of Florida facilities, not just landfills. The additional information reveals that DEP imposed a fine of $61,300 for the October 2001 violations, which included disposing of unacceptable waste, storing an excessive number of tires and exceeding groundwater standards without notifying DEP, and a fine of $1000 for the January 2006 notice of noncompliance. The other enforcement actions against Republic or affiliates concerning landfills involved consent orders about the Nine Mile Road Landfill (Seaboard Waste): in February 2003, DEP imposed a fine of $13,000 in settlement of charges that employees were not removing all unacceptable waste from the site and, in November 2005, DEP imposed a $285 fine for a failure to submit required stormwater monitoring reports. There were many other enforcement actions, generally resulting in modest fines, but they involved hauling facilities, transfer stations, and materials recovery facilities, not landfills. The Engineering Report states that the proposed landfill is within six miles of, but greater than 10,000 feet from, the Bartow Municipal Airport. Airport safety is addressed in more detail below. The Engineering Report describes in detail the double composite liner system, which uses materials whose physical, chemical, and mechanical properties prevent failure due to contact with Class I waste and leachate, climactic conditions, installation stress, and other applied stresses and hydraulic pressures. The Engineering Report performs no contingency sinkhole analysis. The report does not suggest that the liner system could withstand the stresses and pressures resulting from any size sinkhole, so the necessary inference is that the liner will fail if any sinkhole forms directly beneath it. The Engineering Report states that waste placement will remain within the lined containment berm. The Engineering Report describes in detail the double composite liner system for use at the proposed landfill. The primary liner system and secondary liner system each comprises three layers with the top layer consisting of a composite drainage net, the middle layer consisting of a high-density polyethylene geomembrane with a minimum average thickness of 60 ml, and the bottom layer consisting of a geosynthetic clay liner with a maximum hydraulic conductivity of 5 x 10-9 cm/second. The Engineering Report describes in detail the leachate collection and removal system, which, sitting atop the primary liner, includes a 24-inch thick sand drainage layer with a minimum hydraulic conductivity of 1 x 10-3 cm/second, a composite drainage net, and a single perforated 8-inch diameter lateral pipe in each cell. The collection lateral pipes will gravity drain to the east to a header pipe that gravity drains to the primary leachate collection pump stations--one station for the four converted cells and one station for the four new cells. A smaller leachate collection and removal system will handle the leachate that penetrates to the leak detection layer by routing it to a secondary leachate collection pump station. Based on calculations derived from the HELP groundwater model, the leachate collection and removal system is designed to prevent leachate head from exceeding the thickness of the composite drainage net (about 1 cm) over the secondary geomembrane and from exceeding one foot over the primary geomembrane. According to the Engineering Report, flow meters will be installed at each of the pump stations to allow daily readings of the amount of leachate being pumped. At one foot of head over the primary liner, the Engineering Report expects just over three gallons per day collected at each secondary leachate collection pump station--significantly less than the leakage rate typical of a double liner system without a geosynthetic clay liner beneath the primary liner. However, the Engineering Report provides a standard action leakage rate of 100 gallons/acre/day, meaning that Republic is required to report to DEP liner leakage only when this leakage rate is attained. The pump stations will transmit the leachate to one of two above-ground, 150,000-gallon storage tanks. From these tanks, most of the leachate will be transported to an offsite location for treatment. However, up to 12,000 gallons per day of the untreated leachate will be recirculated to be sprayed on the working faces of the landfill. This is to control dust and possibly to assist with the degradation of the waste. The Engineering Report states that the Cedar Trail Landfill implements a facility-wide water quality monitoring plan. Upon completion of the pump stations for the eight cells that are the subject of the Application, Republic will expand its leachate sampling program to include annual sampling of the leachate collected in the primary and secondary leachate collection pump stations. The groundwater monitoring wells would be installed as closely as possible to the outer edge of the roadway that, with a stormwater ditch, will run the perimeter of the proposed Class I landfill. In the revised Engineering Report contained in the RRAI, Republic proposes a surface water discharge point in the stormwater pond located near the leachate storage tanks. The Engineering Report adds that Republic will continue to comply with the following prohibitions: No waste will be knowingly burned on site; Hazardous waste will not knowingly be accepted; PCB contaminated waste will not knowingly be accepted; Untreated biomedical waste will not knowingly be accepted. Please note that treated biomedical waste may be accepted at [Cedar Trail Landfill]'s Class I Landfill provided that the waste containers are marked "Treated Biomedical Waste.;" No waste disposal at the proposed Class I Landfill will occur within 3,000 feet of a Class I surface water body; [Cedar Trails Landfill] will not knowingly accept liquid waste within containers, excluding leachate and gas condensate derived from solid waste disposal operations. [Cedar Trails Landfill] will comply with the requirements of Rule 62- 701.300(10), FAC regarding the handling of liquid wastes; Neither oily waste nor commingled oily waste will knowingly be accepted; and Lead-acid batteries, used oil, white goods, and whole-waste tires will not knowingly be disposed of in the Class I waste disposal system. The Joint Stipulation to Permit Modification, identified above, adds four items to this list of operational prohibitions: i. Garbage will not be knowingly accepted; Household Waste, except waste from residential sources generated as Class III waste, will not be knowingly accepted; Animal carcasses will not be knowingly accepted; and Aluminum dross will not be knowingly accepted. Capitalized terms are generally defined in the Florida Administrative Code. Florida Administrative Code Rule 62-701.200(39) defines "Garbage" as " all kitchen and table food waste, and animal or vegetative waste that is attendant with or results from the storage, preparation, cooking, or handling of food materials." Application Appendix H is the Operation Plan, which also identifies the types of wastes to be permitted at the proposed landfill. Section 3(b) of the Operation Plan authorizes the proposed landfill to accept: Commercial waste Ash residue Incinerator by-pass waste Construction and demolition debris, including from a residence Treated biomedical waste Agricultural waste Industrial waste Yard trash, including from a residence Sewage sludge Industrial sludge Water/air treatment sludges Waste tires De minimis amounts of non-hazardous waste from incidental residential sources Section 5 of the Operation Plan provides, in relevant part: [Cedar Trail Landfill] will accept waste included in any of the waste categories identified under Section 3(b) of this Operation Plan[, but] will . . . NOT knowingly accept any hazardous waste, untreated biomedical waste, liquid waste (including paint), explosive waste, toxic waste, or radioactive waste for disposal at the [Cedar Trail Landfill.] Unacceptable types of refuse are listed below and will not be knowingly accepted for disposal. --Hazardous waste --Explosive waste --Radioactive waste --Drums that have not been opened and Emptied --Refrigerators, freezers, air Conditioners (white goods) --Any toxic or hazardous materials, i.e. batteries, solvents, oil, etc. --Automobiles or parts that contain fuel, lubricants, or coolants --Untreated Biomedical waste The original Application prohibited the acceptance of septic tank pumpage, but the application form accompanying the original Application indicated that the proposed landfill would accept industrial sludge and domestic sludge. After modification by the RRAI, the prohibition against accepting septic tank pumpage was deleted, and the Operating Plan added, among acceptable wastes, sewage sludge, industrial sludge, and water- and air-treatment sludge. Florida Administrative Code Rule 62-701.200(101) (2001) defines "sludge" to include solid waste pollution control residual from an industrial or domestic wastewater treatment plant, water supply treatment plant, air pollution control facility, septic tank, grease trap, portable toilet, or other source generating a waste with similar characteristics. Florida Administrative Code 62-701.200(64) (2001) defines "liquid waste" as any waste with free liquids, according to the "Paint Filler Liquids Test." As modified by the Joint Stipulation to Permit Modification, Section 5 of the Operation Plan was amended to add the following items to unacceptable types of refuse that will not be knowingly accepted for disposal: --Garbage --Household Waste, except waste from residential sources generated as Class III waste --Animal carcasses --Aluminum dross At the hearing, Republic and DEP agreed to an additional condition to the Operation Plan that unacceptable waste would include Garbage contained in commercial, industrial or agricultural waste. According to the Operation Plan, the initial waste screening occurs at the gate house where the attendant interviews the driver and inspects the incoming waste load. If the attendant sees more than a negligible amount of unauthorized wastes, he will reject the load and will contact the hauler to identify the source of the waste. Additionally, Republic will notify DEP if anyone tries to dispose of hazardous waste at the proposed landfill. As modified by the Joint Stipulation to Permit Modification, the Operation Plan was amended to provide a new paragraph between the paragraph addressing the initial waste screening at the gate house and, as discussed below, the second screening at the working face. The new paragraph provides: Any malodorous waste will be covered with mulch and/or additional soil or other approved cover materials to control odors promptly, within one (1) hour from the time of unloading, except in the event of exigent circumstances, such as extreme weather. Cedar Trail Landfill will promptly cover any sludge deposited on the landfill working face within one (1) hour from the time of the unloading, except in the event of exigent circumstances, such as extreme weather. At the hearing, Republic and DEP agreed to an additional condition to the Operation Plan, which would prohibit Republic from accepting malodorous waste or sludge that, due to exigent circumstances, it would not be able to cover within one hour from the time of unloading. If the load passes the initial waste screening, it will proceed to the working face of the landfill, according to the Operation Plan. At least one spotter will be stationed at the working face at all times that the landfill receives waste. Her job will be to detect unauthorized wastes. Republic is to assure that it has a sufficient number of spotters to find and remove unauthorized waste prior to compaction. The Operation Plan allows the spotter to work from ground level or the cab of a compactor. If the operator of a piece of heavy equipment is trained as a spotter, she may also serve as a spotter. During periods of higher waste traffic, the equipment operator will, according to the Operation Plan, "likely" need the assistance of another operator or spotter to screen the higher waste volumes. When finding unauthorized wastes in manageable volumes, the spotter or operator will remove these wastes by hand and place them into nearby containers for removal to an appropriate facility. The third waste screen occurs as the equipment operator spreads the waste, pursuant to the Operation Plan. The equipment operator is required to place any unacceptable observed wastes into containers, which will be located "within the lined area." These wastes will also be removed to an appropriate facility. In the RAI, DEP questioned the proximity of the containers to the working face, as the lined area consists of 72 acres, but, in the RRAI, Republic ignored the comment, restating only that the containers would not be located outside the lined area. The Operation Plan specifies a filling sequence. Republic will assure that the first layer of waste placed above the liner in each cell will be a minimum of four feet in compacted thickness and will be free of rigid objects that could damage the liner or leachate collection and removal system. Republic will maintain the working face to minimize the amount of exposed waste and initial cover necessary at the end of each day. The filling sequence will proceed until the permitted final grade elevations have been reached, less three feet for the final cover. The Operation Plan states that the initial cover at the Class I landfill will consist of a six-inch layer of soil that is transferred from onsite borrow pits or offsite sources. This soil will be compacted and placed on top of the waste by the end of each work day. At Republic's option, subject to DEP's approval, it may use a spray-on or tarpaulin cover, instead of a soil cover. The Operation Plan requires Republic to apply at least one foot of intermediate cover within seven days of cell completion, if additional waste will not be deposited within 180 days of cell completion. Republic may remove all or part of this intermediate cover before placing additional waste or the final cover. Through the placement of initial, daily, and intermediate cover, Republic will minimize the occurrence of moisture infiltration, fires, odors, blowing litter, and animals and other disease vectors. 59. The Operation Plan requires Republic to control litter primarily by daily waste compaction and cover. However, at least daily, if needed, employees will collect litter along the entrance and access roads and around the working face. Complaints about litter must be logged. In addition to the inspections detailed above, the Operation Plan establishes a random load-checking program to detect unauthorized wastes. Each week, Republic employees will examine at least three random loads of solid waste by requiring drivers to discharge their loads at a designated location within the landfill where the employees may undertake a detailed inspection. All random inspections will be logged. Notwithstanding the daily limit of 12,000 gallons per day, the Operation Plan prohibits Republic from spraying leachate during rain events. To apply the recirculated leachate, the lead operator will drive the leachate tanker truck on the working face, so that it can spray leachate over waste as it is being compacted, but after it has been screened by spotters. The spraying will be done to avoid causing leachate to pond atop the waste and will not be done within 50 feet of an outside slope. No restrictions apply to wind conditions. The Operation Plan states that, if the annual sampling of leachate water quality at the two pump stations reveals a contaminant in excess of the permissible limits listed in 40 CFR Part 261.24, Republic will start monthly sampling and notify DEP in writing. Also, the Cedar Trail Landfill will maintain a recording rain gauge. The Operation Plan requires Republic employees to conduct daily surveys for objectionable odors and take immediate corrective action, if odors are found at the property line. As modified by the Joint Stipulation to Permit Modification, this portion of the Operation Plan was amended to add two odor- remediation actions and another form of odor inspection. The two additional actions to prevent odors are to 1) provide additional cover using mulch, additional soil, or other approved cover material and 2) use odor masking or neutralizing agents. The new inspection provision states: Internal inspection will be performed on a weekly basis by a properly trained odor ranger or equivalently trained person. Such individual will tour the facility, property boundary, and the subdivision of Highland Lakes Estates . . . to identify any odors leaving the Landfill's property boundaries. The results of each weekly inspection will be document, and any odors identified will be mitigated. Another new provision from the Joint Stipulation for Permit Modification applies to the handling of sludge. As amended, the Operation Plan states: When accepting sludge from a new source or distributor, [Republic] will obtain information regarding the characteristics and constituents of the sludge, including a description of the industrial process or circumstances that resulted in the generation of the sludge. Upon delivery of the sludge, [Republic] will mix lime, sodium hydroxide, or any other suitable agents to eliminate objectionable odors as required during disposal of the sludge before the material is covered. Furthermore, [Republic] will obtain advance notice from contributors prior to delivery of any sludge and shall promptly cover any sludge unloaded on the landfill working face within one (1) hour from the time of unloading, except in the event of exigent circumstances, such as severe weather. [Republic] shall use its best efforts to avoid accepting or disposing of sludge on Saturdays, Sundays, or public holidays. Additionally, with respect to sludge received from wastewater treatment facilities only, such sludge shall not exceed the lesser of (1) twenty percent (20%) of the total volume of waste disposed in the landfill on an average monthly basis, determined annually on the prior calendar year, or (2) two-hundred (200) tons per day, averaged over the prior 12-month calendar year. Republic is required to monitor combustible gases quarterly and transmit the results to DEP, according to the Operation Plan. If Republic detects methane above the limits specified in Florida Administrative Code Rule 62-701.530 (2010), Republic must submit a gas remediation plan to DEP within seven days. The Operating Plan indicates that the separation of the waste from the groundwater prevents the saturation of the waste and, thus, the generation of odor. Sloping and compacting will promote stormwater runoff, again to discourage the generation of odor. The Construction Permit authorizes construction of the proposed landfill in accordance with the "rules[,] . . . reports, plans and other information" submitted by Republic "(unless otherwise specified)." This parenthetical reference provides that the provisions of the Construction Permit control over any contrary provisions in the other documents that are part of the Permit due to incorporation by reference. In addition to the original Application, RRAI, and drawings, the Construction Permit also incorporates Florida Administrative Code Chapter 62-701 (2001). The Construction Permit states that Republic may not violate the prohibitions set forth in Florida Administrative Code Rule 62-701.300, which is discussed in the Conclusions of Law. Construction Permit Specific Condition A.9.a requires notification to DEP of the discovery of limestone during excavation or discovery. Specific Condition A.9.b requires notification to DEP of any surface depressions or other indications of sinkhole activity onsite or within 500 feet of the site. Specific Condition A.9.c prohibits open burning. Construction Permit Specific Condition C.1.b prohibits the discharge of leachate, during construction or operation, to soils, surface water, or groundwater outside the liner and leachate management system. Specific Condition C.4 prohibits the acceptance of hazardous waste and does not condition this prohibition on Republic's knowledge that the waste is a hazardous waste. Specific Condition C.5 requires Republic to "control . . . odors and fugitive particulates (dust)" and "minimize the creation of nuisance conditions on adjoining property." "Nuisance conditions" include "complaints confirmed by [DEP] personnel upon site inspection." Specific Condition C.5 orders Republic to "take immediate corrective action to abate the nuisance" and to "control disease vectors so as to protect the public health and welfare." Construction Permit Specific Condition C.6.b requires immediate notice to DEP of any sinkholes or other subsurface instability. Specific Condition C.8 requires Republic to manage leachate in accordance with the Operating Permit and Florida Administrative Code Rule 62-700.500(8). The Operating Permit incorporates the same materials that are incorporated into the Construction Permit, again "(unless otherwise specified)." Like the Construction Permit, the Operating Permit incorporates Florida Administrative Code Chapter 62-701 (2001) and requires immediate notice to DEP in the event of a sinkhole or subsurface instability. The Operating Permit specifies that the action leakage rate is 100 gallons per acre per day and the leachate recirculation rate is 12,000 gallons per day. As modified by the Joint Stipulation to Permit Modification, Operating Permit Specific Condition A.1.b states: This Facility is not authorized to accept Garbage; untreated Biomedical Waste; animal carcasses; liquids and non-liquid PCB containing materials or wastes with a PCB concentration greater than or equal to 50 parts per million; Liquid Waste; and aluminum dross. Additionally, this facility is not authorized to accept Household Waste, except waste from residential sources generated as Class III waste. Class III waste means yard trash, construction and demolition debris, processed tires, asbestos, carpet, cardboard, paper, glass, plastic, furniture other than appliances, or other materials approved by [DEP] that are not expected to produce leachate which are a threat to public health or the environment as defined in Rule 62-701.200(14), F.A.C. Based on this authorization to allow certain wastes as described above from residential sources, and since the landfill design, including liner and leachate collection systems, meets the requirements of Chapter 62-701, F.A.C., for Class I landfills, the facility will be entitled to [the] household hazardous waste exemption pursuant to 40 C.F.R. 261.4(b)(1). Specific Condition A.9.c prohibits open burning. Operating Permit Specific Condition C.1.b prohibits the discharge of leachate to soils, surface water, or groundwater outside the liner. Specific Condition C.1.c prohibits the discharge of "residual contaminants," such as gasoline, oil, paint, antifreeze, and polychlorinated biphenyls (PCBs), onto the ground or into surface water or groundwater. Operating Permit Specific Condition C.1.k(1) provides that authorized waste types are those listed in Section 3(b) of the Operations Plan, and unacceptable wastes shall be removed from the site as described in Sections 3(a) and 7. As modified by the Joint Stipulation to Permit Modification, Operating Permit Specific Condition C.1.k(1) provides: "Waste types authorized for management at this site are those listed in Section 3(b) of the Operations [sic] Plan. Unacceptable wastes are those listed in Section 5 [of the Operation Plan] " Operating Permit Specific Condition C.1.k(2) requires the use of a sufficient number of spotters to remove unacceptable wastes, but allows Republic to direct its equipment operators to serve as spotters from the equipment. This condition allows DEP to require that spotters work from the ground, if DEP determines that spotting from equipment is not effective. Specific Condition C.1.k(3) requires Republic to remove unacceptable wastes immediately and not to unload additional wastes in the immediate vicinity until placing unacceptable wastes in the designated waste containers" "near the working face" and within the lined landfill area. Operating Permit Specific Condition C.1.l(2) requires Republic to inspect on each operating day the property boundary for objectionable odors and, if any are detected, abate them in accordance with Specific Condition C.5. Specific Condition C.5.a requires Republic to control odors, disease vectors (insects and rodents), and fugitive particles (dust and smoke) to protect the public health and welfare. Control is defined as "minimiz[ing]" the creation of nuisance conditions on adjoining property. Odors confirmed by DEP personnel are a nuisance condition, and Republic must take immediate corrective action to "abate" the nuisance. Specific Condition C.5.b provides that, if odor control measures do not "sufficiently abate" objectionable odors within 30 days, Republic will submit an odor remediation plan to DEP for approval. Operating Permit Specific Condition C.8.e requires monthly reports to DEP of leachate quantities. Specific Condition C.8.h(1) prohibits recirculation of leachate at rates that result in seepage that may discharge outside the lined area. Leachate may not be sprayed when the application area is saturated or during a rainfall event. There is no prohibition against spraying during windy conditions. Operating Permit Specific Condition E details the extensive water quality monitoring requirements. However, Specific Condition E.9.b requires only annual testing of the five field parameters, eight laboratory parameters, and the comprehensive list of Appendix II parameters set forth in 40 CFR Part 258, all of which are identified below. Specific Condition E.9.c provides that, if a contaminant listed in 40 CFR 261.24 exceeds the level listed therein, Republic will notify DEP and take monthly leachate samples until no exceedances are detected for three consecutive months. Operating Permit Specific Condition F.1.a states: "This solid waste permit will meet the statutory requirement to obtain an air construction permit before . . . constructing a source of air pollution, except for those landfills that are subject to the prevention of significant deterioration (PSD) requirements of Chapter 62-212, F.A.C." Such facilities are required to obtain an air construction permit from the Bureau of Air Regulations prior to construction. Specific Condition F.1.b requires Republic to comply with Title V of 40 CFR 60, Subparts WWW and CC. This section notes that Title V permit applications must be submitted to the District Air Program Administrator or County Air Program Administrator responsible for the landfill. Aviation Safety Landfills attract birds in search of food. Flying birds may interfere with aviation safety. Thus, landfills are typically not located in close proximity to airfields to minimize the risk that flying birds will interfere with airborne aircraft approaching or departing from an airport. The nearest airport to the Cedar Trail Landfill is the Bartow Municipal Airport, which is operated by the Bartow Aviation Development Authority. This airport is over five miles from the footprint of the active landfill and 4.6 miles from the boundary of the proposed site. Republic provided notice of the Application to all airports within six miles of the proposed landfill, the Federal Aviation Administration, and the Florida Department of Transportation. None of these entities objected to the proposed landfill. When Republic gave the Bartow Aviation Development Authority notice of an earlier application, which sought a permit for a landfill that would accept garbage, the authority objected to the proposal due to concerns posed by birds to aviation safety. When asked about the Application, the authority's executive director testified that she still has concerns about the proposed landfill, but she did not specify the nature of her concerns or her analysis. As explained in the Conclusions of Law, these are the only facts required for a determination of whether Republic has provided reasonable assurance of aviation safety. The record provides no basis for finding that Republic has failed to provide reasonable assurance of aviation safety. Neither the FAA nor the Bartow Aviation Development Authority has objected to the proposed landfill. The executive director's unspecified concerns do not override the absence of a formal objection from these agencies. Petitioners assign too much weight to the earlier objection submitted by the authority. The composition of the authority may have changed or some authority members may have decided they were wrong in their earlier analysis. This earlier objection does not outweigh the absence of objection to the present proposal from any of the aviation agencies and the absence of any evidence of the expected nature or extent of bird usage of the proposed landfill and the extent to which these birds would interfere with existing and expected flight paths of aircraft using the Bartow Municipal Airport. Public Health Petitioners' expert witness on public-health issues, Dr. David Carpenter, is a medical doctor with a long, prestigious history of public service, including with the Department of Defense, the National Institutes of Mental Health, the United States Public Health Service, and the New York Department of Health, where he served as director from 1980-85. At that time, Dr. Carpenter started the School of Public Health at the University of Albany. Republic's expert witness on public-health issues, Dr. Christopher Teaf, is an expert in the evaluation of environmental contamination, waste management, and toxicology, but not a medical doctor. Dr. Teaf is a professor at Florida State University and owns a small consulting firm. The major part of Dr. Carpenter's career has been devoted to research. For the past ten years, he has focused more on human health, especially human disease from exposure to environmental contaminants. Dr. Carpenter has considerable experience with the adverse effects of landfills on human health, but his experience has been mostly with older landfills, where containment measures were few and offsite releases were many. Clearly, Dr. Carpenter's experience does not extend to the role of landfill design, construction, and operation in the transmission of human disease. Thus, Dr. Carpenter is qualified to opine on the effects of pollutants that may escape landfills, but not on the relationship of landfill design, construction, and operation on the probability that a landfill will transmit pollutants. For the most part, Dr. Carpenter did not attempt to address matters outside of his expertise. However, Dr. Carpenter testified that the risk of disease or injury increased in relationship to the proximity of the person to the landfill. This testimony can only be credited if one assumes that the landfills are identical in terms of design, construction, and operation and in terms of the environmental conditions of the landfill site. In other words, in real-world applications, it is impossible to credit this element of Dr. Carpenter's testimony, especially to the extent of his implicit suggestion that public health is unreasonably endangered by the construction of a landfill, in compliance with all rules, that satisfies all of the separation criteria and design criteria set forth in the rules, as discussed below. By contrast, Dr. Teaf focused on the details of the proposed landfill. Applying his knowledge of toxicology, Dr. Teaf determined that the proposed landfill adequately protects public health. In making this determination, Dr. Teaf analyzed the effects of various design and operational characteristics of the proposed landfill, including the double liner system, the leachate collection and management system, the selection of appropriate waste types, the procedures for the evaluation and covering of sludges, the prohibition against municipal garbage, the restrictions on household items, the monitoring of groundwater and surface water, the stormwater management system, and the plans to control dust and odors. Dr. Carpenter's testimony and the literature that he sponsored suggested important links between older landfills and a wide range of human disease. But the recurring problem with Dr. Carpenter's testimony and the research articles that he sponsored was the inability to link this information to the proposed landfill. All of the landfills studied in his research articles were older, and most of them appeared to have been designed, constructed, and operated under far more relaxed regulatory regimes than exist today. Nothing in Dr. Carpenter's testimony or sponsored literature attempted to delineate the design or operational characteristics of these landfills, such as whether they were double- or even single-lined, served by leachate circulation and recovery systems, limited as to materials that they could accept, or required to install stormwater management and water monitoring systems. 93. Analysis of the risk to public health posed by the proposed landfill requires consideration of the various means of transmission of the pollutants received by the landfill: water, land, and air. Of these, water requires little analysis, on this record. Even Dr. Carpenter conceded that the proposed landfill does not appear to pose a threat to groundwater. The double liner, leachate collection and recovery system, and groundwater monitoring plan support the finding that groundwater transmission of pollutants from the proposed landfill is unlikely. Transmission by surface water is also unlikely. Compared to groundwater monitoring, surface water monitoring is limited. For instance, there is only a single monitoring site. Also, as noted above, the stormwater pond for the leachate storage area is expected to discharge stormwater offsite during excessive storm events, at which time surface water samples will be taken. However, a comprehensive surface water management system is in place at the landfill and will prevent offsite discharges in all but a few excessive rain events. Transmission by land is also unlikely. The Application contains engineering analysis of the proposed stability of the side slopes and a determination that they will be stable. The discussion of sinkholes, below, does not affect this finding. Treating dust as transmission by air, the only other means by which pollutants may transmit by land is by animals, such as insects, rodents, and birds. An important factor limiting the activity of animals in spreading pollutants offsite is the fact that the proposed landfill will not receive garbage. Although putrescible waste may be received within other categories of waste, the prohibition against receiving garbage will greatly reduce the amount of potential food sources for animals and thus the utilization rate of the proposed landfill by these animals. A further reduction in animal utilization will be achieved through the daily and intermediate cover requirements. Thus, transmission of pollutants by animals is also unlikely. Transmission by air takes several forms. Pollutants may be transmitted as or on dust, with water in the form of aerosol, or as gas. In terms of how transmission by air is addressed by the Permit, this means of transmission potentially represents a greater threat than transmission by water or land for four reasons. First, the explicit focus of the Permit, as to gas, is to avoid explosive concentrations of methane and objectionable odors, but not the transmission of other pollutants by air. Second, the effect of the Permit is to prohibit the release of pollutants into the groundwater or offsite surface water and to prohibit the release of pollutant-bearing land offsite, but no such flat prohibition applies to the offsite release of pollutants by air. Third, the leachate recirculation system provides a good opportunity for the release of certain pollutants into the air by aerosol or evaporation, but similar releases to offsite land, surface water, or groundwater are prohibited. Fourth, scientific understanding of the effects of exposure, especially by inhalation, to pollutants, especially in the form of organic compounds, is continuing to develop: with the use of chemicals increasing three fold in the 50 years preceding 1995 and approximately 80,000 chemicals in use in 2002, only a few hundreds of these chemicals have been subjected to long- or short-term study, resulting in the discovery that about 10% of the chemicals in use in 2002 were carcinogens. Transmission by dust appears to be limited by the frequent covering and spraying of the working faces. Although nearby residents complain of dust in their homes, the practices of the less-regulated Class III landfill cannot be extrapolated to the proposed Class I landfill. Thus, the prospect of dust transmission of chemicals contained in the fill received by the proposed landfill appears also to be slight. The use of untreated leachate as the spray medium to control the dust itself raises two risks, however. First, spraying leachate will release chemicals in aerosol. The potential range of aerosol is great, especially as the landfill ascends toward its design height of 190 feet. However, the risk of transmission by aerosol is reduced to insubstantial levels by adding a Permit condition that prohibits spraying during windy conditions. Second, depositing leachate on the landfill face will release chemicals through evaporation. The point of spraying the landfill face is to control dust between the addition of the waste materials to the pile and the application of the cover. Between these two events, dry conditions will sometimes intervene and may cause the evaporation of certain, but not all, pollutants. The leachate acquires pollutants as it percolates down the waste column and into the leachate collection system. As Dr. Teaf noted, the leachate becomes more concentrated as it recirculates, but, otherwise, this record is largely silent as to the likely composition of the recirculated leachate. However, for landfills accepting sludge, higher levels of mercury may be present in the leachate. As reported by the Florida Center for Solid and Hazardous Waste Management at the University of Florida, in a report issued March 2007, and titled, "Design and Operational Issues Related to Co-Disposal of Sludges and Biosolids and Class I Landfills--Phase III," one study found that the concentration of mercury in the leachate of landfills that receive sludge is almost three times greater than the concentration of mercury in the leachate of landfills that do not accept sludge. The same study reported that total dissolved solids and chlorides were present at greater concentrations at the landfills that did not accept sludge and that other parameters--unidentified in the cited article--were not significantly different between the two types of landfills. Republic proposes to recirculate substantial volumes of leachate--sufficient, for instance, to raise the moisture content of the fill from 25 percent to 28.9 percent. The Permit allows the proposed landfill to operate six days per week, for a total of 312 days annually. The Operation Plan prohibits the application of leachate during rain, but the number of days annually during which rain extends for the entire day is few, probably no more than a dozen. These numbers suggest that Republic may apply as much as 3.6 million gallons annually of untreated leachate to the landfill face. The 12,000 gallon-per-day limit and restrictions on head in the leachate collection and removal system effectively limit the quantities of leachate that may be recirculated, but the sole provision addressing leachate water quality is the annual monitoring event described above. Given the time required to analyze the many parameters included in the EPA regulation, for most of the year between tests, Republic will be applying over three million gallons of leachate whose pollutant concentrations will be completely unknown. Some assurances emerge, though, when considering air transmission of pollutants by class. In general, on this record, as to transmission by gas, there appears to be an inverse relationship between a compound's volatility, which is a measure of its ability to enter the air, and a compound's persistence. VOCs are one of the most dangerous classes of pollutants to public health and include such carcinogens as benzene, tolulene, xylene and, the most dangerous of all VOCs, vinyl chloride, which is released upon the degradation of such common substances as plastics, carpets, and upholstery. Biogas, which is generated by the anerobic decomposition of organic compounds in a landfill, contains mostly methane and carbon dioxide, but also significant levels of VOCs. When inhaled, the primary results of exposure to VOC are respiratory irritation and allergenic effects. Volatility is measured by vapor pressure, which is a measure of a chemical's ability to get into the air. As their name suggests, VOCs enter the air easily. They are also capable of traveling great distances due to their light molecule. However, VOCs are easily destroyed by sunlight and diluted by wind. Other organic compounds common to landfills are only semi-VOCs, such as PCBs. Although less volatile, these chemicals, too, are hazardous to public health--in the case of PCBs, in any amount. Due to this fact and their persistence in the environment, the United States has prohibited the manufacture of PCBs for over 30 years. However, not only are PCBs considerably less likely to enter the air than VOCs, they also travel shorter distances than VOCs due to a heavier molecule. Dr. Carpenter opined that there is little evidence that PCBs are an issue in the proposed landfill. Another class of organic compound, 1000 times less volatile than even PCBs, is phthalates, which are used in the production of plastics. Phthalates pose significant threats to public health, especially reproductive health. However, the exceptionally low volatility of this compound renders transmission by evaporation highly unlikely. Much of the regulatory framework imposed on landfill design, construction, and operation arises out of concerns for the control of human pathogens, which are infection-causing organisms, such as bacteria, viruses, protozoa, and parasitic worms. One of the great advances in human longevity in the United States occurred in the early 1900s--not with the development of antibiotics or improved medical care--but with the implementation of basic sanitation control and the removal of pathogens from the drinking water. For the proposed landfill, sludge will be the primary source of pathogens. Sludge is nutrient-rich organic matter, which will be received at the proposed landfill without any treatment except possibly dewatering. Even with the acceptance of sludge, the proposed landfill presents little risk for the transmission of pathogens. Pathogens communicate disease only when a person is exposed to an effective dose and are better transmitted by direct contact or animal than air. Bacterial pathogens are themselves killed by wind, as well as sunlight, temperature, and humidity differentials, so the preferred means of air transmission would be aerosol versus gas. The record permits no findings as to the persistence of pathogenic viruses, protozoa, and parasitic worms. However, as noted above in connection with the land transmission of pathogens, the immediate application of lime and cover to the sludge will tend to prevent the release of effective doses of pathogens by air, as well. The last major class of pollutant that could be transmitted by air is heavy metals, such as mercury or lead. Although these metals produce a wide range of neurological diseases and generally interfere with cognition and behavior, Dr. Carpenter admitted that heavy metals were not as much of a concern as VOCs, presumably due to their resistance to vaporization. Even though transmission by air is not as tightly controlled as transmission by water or land, for the four reasons noted above, there is little risk of transmission by air--i.e., dust, aerosol, or gas--when the specific properties of likely pollutants are considered. In all but five respects, then, Republic has provided reasonable assurance that public health will not be endangered by pollutants released from the landfill by water, land, or air. First, to provide reasonable assurance concerning public health, the Permit needs a condition that prohibits spraying leachate during windy conditions, which DEP may define as it reasonably sees fit. As noted in the Conclusions of Law, this is a requirement in the rules and, due to its importance, should be restated explicitly in the Permit, which restates numerous other rule requirements. Second, to provide reasonable assurance concerning public health, the Permit needs more frequent monitoring of leachate water quality, at least at the frequency, as noted in the Conclusions of Law, set forth in the rules. Large volumes of untreated leachate will be recirculated through the landfill. Even if aerosol transmission is controlled, transmission by evaporation of some pollutants, although not the heavy metals, is possible. Also, pollutants are concentrated in recirculated leachate and thus the consequences of transmission into groundwater or surface water, however unlikely, become greater. At the same time, the action leakage rate is generous--to Republic, not the groundwater. At 100 gallons per acre per day, Republic is not required to report to DEP possible liner leakage until about 7300 gallons per day are lost to the surficial aquifer. Suitable for the detection of catastrophic failures associated with most sinkholes, this action leakage rate is too high to trigger action for small liner leaks. If Republic is to be allowed this much leakage into the groundwater, it must identify the leachate's constituents and their concentrations at least semi-annually. Third, to provide reasonable assurance concerning public health, the Application must extend the right of split testing to all of the parties in these cases, if DEP fails to exercise its right to take a split sample. The spraying of untreated leachate and generous limit applied to liner leakage before reporting and remedial action are required underscore the importance to public health of independent leachate testing. There is no reason to allow budgetary constraints or administrative oversight to preclude Petitioners and Intervenor, who are uniquely situated to suffer from the escape of excessive pollutants in the leachate, from providing, at their expense, this independent leachate testing. Fourth, to provide reasonable assurance concerning public health, the Permit needs to restate accurately the language of the rules concerning the extent of knowledge required of Republic, if it is to be liable for the acceptance of certain prohibited wastes. Fifth, to provide reasonable assurance concerning public health, the Permit needs to be modified to ensure that at least one spotter, whose sole responsibility is spotting, will be assigned to each working face while the landfill is receiving waste. Sinkholes The sinkhole issue arises in the geotechnical analysis of the sufficiency of the foundation to support the considerable loads of a landfill and also in the stability of the side slopes of the landfill. This analysis starts with consideration of the geology of the area, of which Republic's property is a part, and, among other things, the potential for sinkhole formation in the area. The Cedar Trail Landfill lies within the Bartow Embayment and along the eastern slope of the Lakeland Ridge of the Central Lake District Physiographic Province. This embayment is a large erosional basin partially backfilled with phosphatic sand and clayey sand of the Bone Valley Member. At this location, the top of the Floridan Aquifer is formed by Suwannee Limestone, which consists of white to tan, soft to hard, granular, porous, very fossiliferous limestone with interbedded dolomite. This rock unit is 110-140 feet thick. Atop the Suwannee Limestone sits the Hawthorne Group, which comprises the Arcadia Formation, at the base of which is the Nocatee Member, which is a relatively impermeable sand and clay unit. Atop the Nocatee Member is the Tampa Member, which consists of hard, dense, sandy, locally phosphatic, fossiliferous limestone. The top of this member, which is the top of the Arcadia Formation, is locally referred to as the "bedrock complex," which marks the lower limit of phosphate mining. Atop the Arcadia Formation, still within the Hawthorne Group, sits the Peace River Formation, which consists of phosphatic clayey sand and clayey sand. The lower portion of the Peace River Formation is a relatively impermeable, undifferentiated clayey unit locally known as "bedclay." The Bone Valley Member of the Peace River Formation is mined for phosphate and is locally known as "matrix." Atop of the Peace River Formation are undifferentiated surficial soils, typically consisting of silty sand, clayey sand, and some hardpan and organic soils. These materials are locally known as "overburden." Phosphate mining is prevalent in the area, including, as noted above, much or all of the Cedar Trail Landfill site. Strip mining for phosphate normally removes the entire surficial aquifer, just into the bedclay. Mined areas are then backfilled with overburden spoil soils, clay, waste clay, and sand tailings. After backfilling, the soil strata bear little resemblance to premining strata. Sinkholes are prevalent in the general area surrounding the Cedar Trail Landfill. A sinkhole is a surface depression varying in depth from a few feet up to several hundreds of feet and in area from several square feet to several acres. Sinkholes are typically funnel-shaped and open broadly upward. Sinkholes form when weakly acidic groundwater creates cavities in the calcium carbonate within limestone. Soils above these cavities erode into the cavities. In the area that includes the Cedar Trail Landfill, cover-collapse and cover- subsidence sinkholes predominate among sinkhole types. A cover-collapse sinkhole, which is typically steep- sided and rocky, forms when cohesive soils over a limestone cavity can no longer bridge the cavity under the weight of overlying soil and rock. At this point, the cohesive soils suddenly collapse into the cavity. These are more common in the part of the state in which the Cedar Trail Landfill is located. A cover-subsidence sinkhole occurs due to the gradual lowering of the rock surface as solutioning occurs in the subsurface rocks. This type of sinkhole develops as subsurface soluble rock is dissolved and overlying soils subside into the resulting shallow surface depressions. Regardless of the type of sinkhole, borings into sinkholes will reveal zones of very loose soil sediments that have washed downward into the cavernous voids within the bedrock. This very loose soil zone is called a raveling zone, which starts at the limestone layer, as the overlying soils begin to collapse into the solution features within the limestone. As the loosening works its way upward toward the surface, it eventually results in the subsidence of the ground surface and formation of a sinkhole. Considerable sinkhole activity has taken place in the immediate vicinity of Republic's property. Most visibly, a sinkhole formed in 2006 in 285-acre Scott Lake, 4.5 miles northwest of the landfill. This sinkhole drained the entire lake and destroyed several structures. The Florida Geological Service sinkhole database, which consists of anecdotal reports of sinkhole activity, some of which are unverified, includes 49 sinkholes within five miles of the proposed landfill. Two documented sinkholes have occurred within .17 mile of the landfill--one of which is reported to be 125 feet in diameter and 80 feet deep. Based upon the information contained in the preceding paragraph, Clint Kromhout, a professional geologist with the Florida Geological Survey, opined on August 23, 2009, that the potential for sinkhole formation "within the proposed site and surrounding area" is "low to moderate." Mr. Kromhout does not provide a definition of "low," but part of his opinion is shared by the Golder Report, which agrees that the sinkhole potential on the proposed site is "low." The potential for sinkhole formation in the general area surrounding the proposed landfill, as distinguished from the site itself, is at least moderate. In their Proposed Recommended Order, Republic and Intervenor necessarily concede: "All parties acknowledge that the proposed landfill site is in a general region that has a relatively high frequency of sinkholes as compared with the rest of the state of Florida." It is misleading to characterize the area surrounding the proposed landfill as of low potential for the formation of sinkholes, unless there is another category, like "nonexistent." But characterizing the sinkhole potential of the surrounding area as moderate is not determinative of the likelihood of sinkholes at the landfill's footprint, nor is a site-specific geotechnical investigation mooted by such a characterization. Rather, characterizing the sinkhole potential of the surrounding area as moderate dictates the intensity and scope of the ensuing geotechnical investigation, if the investigation is to provide reasonable assurance of the structural integrity of the proposed landfill. Acknowledging moderate potential for sinkhole formation in the surrounding area, Republic has appropriately relied on three geotechnical reports, including three sets of boring data. The final of these reports, the Hanecki Report, is based on the collection and analysis of boring data, as well as a review of the data and analysis contained in the two earlier geotechnical reports, the Ardaman Report and Golder Report. The boring data reveal that the proposed landfill site features four units. Nearest the surface is Unit 1, which is brown to dark brown, medium- to fine-grained sand with minor amounts of clayey silt. Unit 1 is 0-10 feet thick. Next down is Unit 2, which is tan to gray, medium- to fine-grained sand with increasing silty clay or clayey silt. Unit 2 is 5-10 feet thick and generally marks the upper limit of fine-grained, granular soils (i.e., clayed sands and silty sands). Unit 3 is orange brown to yellow brown, gray and tan silty clay to clayey silt or fine sand and silty clay. Unit 3 is 5-15 feet thick. Unit 4 is gray and tan clayey silt or silty clay with minor amounts of fine sand. This material is very stiff or very dense, and most borings terminated in this unit. The few borings that penetrated this unit suggest that it may consist of dolomitic sandy clays and silts and dolomitic limestone to depths greater than 100 feet below grade. Units 3 and 4 generally mark the upper limits of low permeability/low compressibility soils. The Hanecki investigation comprised two main steps. First, Hanecki retained a subconsultant to perform electrical resistivity imaging (ERI) along 100-foot-wide transects run across the site. Any anomalies revealed by the ERIs were to be followed by standard penetration test (SPT) borings, which permit soil testing at predetermined intervals, as well as a measure of the compressibility of the soils. Compressibility is measured during the soil-testing intervals, during which the drill bit is replaced by a soil sampler. The driller records the number of blows required for a 140-pound hammer falling 30 inches to produce 12 inches of penetration. The value is expressed in N-values, where N represents the number of such blows. Looser soils produce lower N values. Another important piece of information obtained during SPT boring is the partial or total loss of circulation fluid during drilling. While the drill is penetrating soil, a slurry circulates through the borehole to prevent the collapse of the sides of the hole. This slurry is recycled during drilling, but, if the drill encounters a void, all or part of the circulation fluid is lost. The ERI survey revealed no real anomalies because of a narrow range of resistance values. However, taking relatively small differences in resistivity as an anomalies, Hanecki identified 14 features of interest. At each of these locations, Hanecki performed an SPT boring. Because the ERI transects were unable to span the two onsite ponds, Hanecki added two locations for SPT borings adjacent to each side of each pond, for a total of four additional SPT borings. At the request of DEP, Hanecki added a nineteenth SPT boring at Golder site G-11, which had revealed low N-values during Golder's borings. Hanecki extended the borings into "refusal" quality soil, which was defined as soils requiring more than 50 blows of the 140-pound hammer to achieve six inches or less of penetration. All of Hanecki's SPT borings encountered very hard limestone. Among the most significant findings of Hanecki's borings, only one boring, G-11, experienced any circulation fluid loss, and this was estimated at 50 percent. However, it is more likely that this partial circulation fluid loss is due to loosely deposited sands than a void that might be indicative of conditions suitable for sinkhole formation. Not all circulation losses indicate voids that that will result in sinkhole formation. Also significant among Hanecki's findings is a clayey soil, or bedclay, at every SPT boring, which severely limits hydraulic recharge to the limestone. By impeding vertical migration of surface and shallow subsurface water to the limestone layer, this bedclay "greatly inhibits limestone erosion." This bedclay also supports the looser soils above the bedclay and thus prevents raveling, without which sinkholes cannot form. Two borings--G-11 and F3-1--lacked a layer of Unit 3 or 4 soil above the limestone, but Hanecki concluded that the Unit 2 layers above the limestone at these locations contained sufficient clay or clayey sand to serve the same functions of impeding the downward movement of groundwater and preventing the downward movement of loose soils. This conclusion appears reasonable because Unit 2 is the uppermost reach of the finer- grained materials, of which clays and silts are examples when compared to sands. There is obviously some variability in the distribution of finer- and coarser-grained materials within each occurrence of Unit 2 soils. Hanecki's findings indicated intervals of loose soils, sometimes at depth, which typically would suggest raveling zones. At the proposed location, though, these findings do not support raveling due to the underlying bedclay layer and the history of mining, which probably introduced looser soils typically found closer to the surface through the entire 40-foot depth of the mine cut. Based on these findings, the Hanecki Report concludes that, regardless of at least moderate potential for sinkhole potential in the area, the footprint of the proposed landfill has an acceptably low risk of sinkhole development to permit development of the proposed landfill. This is a reasonable conclusion because it is supported by the data collected by Hanecki and his reasoned analysis of these data. Hanecki's conclusion is also supported by the data and analysis contained in the Golder Report and Ardaman Report, which are based on an additional 84 SPT borings, post- reclamation. Only about 12 percent of these SPT borings reached the limestone, and they cover all of Republic's property, not merely the footprint of the proposed landfill. Even so, these borings confirm two important findings of the Hanecki Report. First, they produced data indicative of an extensive bedclay layer intact on Republic's property. Second, the Ardaman and Golder borings reveal only two or three instances of partial circulation loss that, like the sole occurrence of partial circulation loss in the Hanecki borings, are located on Republic's property, but outside the footprint of the proposed landfill. Republic has provided reasonable assurance that the site will provide an adequate foundation for the proposed landfill and sinkholes are unlikely to undermine the structural integrity of the proposed landfill.

Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order granting the Construction Permit and Operation Permit, but only if the Operation Permit is modified by the addition of the five items identified in paragraphs 172, 174, 175, 181, and 187. DONE AND ENTERED this 8th day of October, 2010, in Tallahassee, Leon County, Florida. S ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of October, 2010. COPIES FURNISHED: Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Tom Beason, General Counsel Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Mimi A. Drew, Secretary Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Ronald L. Clark, Esquire Clark, Campbell & Mawhinney, P.A. 500 South Florida Avenue, Suite 800 Lakeland, Florida 33801-5271 William D. Preston, Esquire William D. Preston, P.A. 4832-A Kerry Forest Parkway Tallahassee, Florida 32309-2272 Jennings Kemp Brinson, Esquire Clark, Campbell & Mawhinney, P.A. 500 South Florida Avenue, Suite 800 Lakeland, Florida 33801 Sean R. Parker, Esquire Boswell & Dunlap, LLP 245 North Central Avenue Bartow, Florida 33830-4620 Ralph A. DeMeo, Esquire Hopping, Green, & Sams, P.A. 119 South Monroe Street, Suite 300 Tallahassee, Florida 32301 Stanley M. Warden, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Station 35 Tallahassee, Florida 32399-3000 Paula L. Cobb, Esquire Hopping Green & Sams, P.A. Post Office Box 6526 Tallahassee, Florida 32314 John W. Frost, Esquire Frost Sessums Van den Boom & Smith, P.A. Post Office Box 2188 Bartow, Florida 33831 John Stanley Fus Highland Lakes Estates HOA 2190 Boardman Road Bartow, Florida 33830

CFR (4) 40 CFR 25840 CFR 261.2440 CFR 261.4(b)(1)40 CFR 60 Florida Laws (4) 120.569120.57403.703403.707